MultiPower-Local December 2011
-
Upload
walter-h-rose -
Category
Documents
-
view
217 -
download
0
Transcript of MultiPower-Local December 2011
-
8/3/2019 MultiPower-Local December 2011
1/6
-
8/3/2019 MultiPower-Local December 2011
2/6
-
8/3/2019 MultiPower-Local December 2011
3/6
-
8/3/2019 MultiPower-Local December 2011
4/6MultiPower-Local
nical support, and financial assistance can
conceivably come from many directions.
The Kokhanok Project benefits from
funding through USDA and technical
expertise sharing with the Alaska Center
for Power at UAF. The local utility and
Lake and Peninsula Borough are also
making in-kind financial contributions to
the project.
Kokhanoks system integrates two refur-
bished Vestas V-17 wind turbines with
existing generators. Utilizing existing
generators and controls saves money, butit can crate its share of headaches as well.
Marsh Creek says Kokhanok should be
fully commissioned and operational
within 4 to 6 months. Things tend to take
longer than expected in rural Alaska.
Here are some of the challenges theyre
up against:
Somebody on-site needs to know how to
keep the system up and running. Local
utility operators willing to commit the
time and effort to fully understand com-
plex new technical systems is critical.Marsh Creek and Kokhanok Electric ad-
dressed this problem by signing a five
year Operations & Maintenance/Training
agreement.
For five years following commissioning
of the system, Marsh Creek will provide
two site visits annually. These site visits
will entail preventive maintenance with
hands on training for operators. In addi-
tion Marsh Creek is available 24/7 for
emergency calls and advice. Not all, but
many problems can be dealt with re-
motely, using the SCADA system.
SCADA is an acronym for supervisory
control and data acquisition and is a
computer program which monitors and
controls a facility from a distant location.
Other issues can be solved by viewing the
SCADA system and talking the local
operator through procedures.
The village of Kokhanok owns and oper-
(Continued from page 1)
ates the electric utility. The new hybrid wind
systems first responsibility is to continuously
provide high quality power to the community.
Wind is considered non-firm energy, mean-ing it does not always blow from the same
direction at the same speed, nor does it blow
when its needed for peak electric demand.
Kokhanoks demand for electricity can change
from moment to moment as well. Engineers
need to accommodate all of these scenarios..
Maximum fuel savings is achieved when the
diesel generators are turned off for extended
periods of time. One way to achieve diesels
off is to install more wind turbine capacity
than the community needs. The problem then
becomes what to do with the extra electricitythe community doesnt need.
Those of us familiar with plug-in electric heat-
ers know they use a lot of energy. Kokhanok
uses something similar, called a thermal dump
load, to soak up extra wind energy and dump
it into a boiler as needed. Heat from the boiler
goes into a domestic heat recovery loop,
which in turn is used to heat teacher housing
and the school. This way, all of the power
generated by the turbines is used. This is im-
portant to project economics.
Unalakleet, which has six wind turbines, isdealing with the problem of too much electric-
ity from the wind as well. When they first
installed their turbines, their powerhouse was-
nt ready for the extra electricity. A thermal
dump load to supplement space heating was
the answer for them as well.
The dump load by itself is not enough. Com-
plex equipment is necessary to keep voltage
and frequency within tight limits, and to avoid
damaging utility customer equipment. Equip-
ment necessary for power quality and condi-
tioning must be precisely controlled and moni-
tored.
The Alaska Energy Authoritys Energy Path-
way, which performed a detailed analysis of
every community in our region and made
short, mid, and long term recommendations
for conservation, efficiency, and renewable
energy, projects it will be 15 years before we
fully utilize the winds power here. If Marsh
Creeks success in Kokhanok is any indica-
tion, that day will come sooner, rather than
later.
Kokhanok Wind
(continued from page 1)
of Elim are in full support of this project.
They also received a letter of support from
AVEC, which provides the village power.
A number of known and suspected hot
springs are located in the rugged hills sur-
rounding Elim. Suspected means that elders
say they exist, but nobody has been there for
years.
Last summer, the Alaska Center for Energy
and Power tested innovative airborne and
remote sensing techniques at Pilgrim Hot
Springs outside of Nome. Elim and UAF
propose to use similar techniques. The
country around Elim is so rugged that even
simple reconnaissance is difficult on the
ground. It should be much easier to find
suspected springs from the air with an infra-
red camera. The countryside surrounding
Elim seems especially well suited for
UAFs airborne survey techniques.
Elim hot springs is the closest of the springs
to be surveyed to the village, but it is not the
largest or hottest in the immediate vicinity.
Clear Creek is hotter and larger, but is far-
ther away. The UAF survey would include
economic analysis of options available to
Elim.
Elim Hot Springs
Ferns growing around Elim Hot Spring
-
8/3/2019 MultiPower-Local December 2011
5/6
2nd Edition Page 5
Railbelt customers. Space heating con-
sumes 43% of energy in the average vil-
lage.
Ross Coen talked about how the availabil-
ity of energy resources has influenced
where people live in Alaska for thousands
of years. Wood for space heating is one
critical resource. Guess which Village in
(Continued from page 1)
our region exported wood for a profit during
the gold rush.
We saw how Sealaska now heats their 60,000
square foot building with wood pellets. Theysay the system is working great, and claim to
be saving lots of money. Pellets are currently
imported from Canada. Sealaska might start
making them locally if they can drum up
enough demand.
If you buy a container load of pellets, pellet
heating might be cost competitive with fuel oil
at todays prices in Nome. If they start making
pellets in Juneau, however, pellet heating
might become cheaper.
During a technical session on alternative
fuels we found out about a large coal gasifi-
cation project going on in Southeast Alaska,
and about a new biofuel diesel additive thatwill soon be manufactured in Anchorage
using feed stock shipped from the lower 48.
We ended with a bus tour of local energy
projects, including a small hydro project
nearby the conference, methane recovery at
a landfill, and grain recycling at the Alaska
Brewery.
If you are interested in energy in rural
Alaska, the Rural Energy Conference is the
place to be. They offered travel scholarships
this year. Keep your eye out, next years
conference might be closer to home.
below, is among a number of sites in the
State that might benefit from this project.
Interties are another good candidate for
HVDC. The intertie from Nome to Teller
shown on the map below wouldnt even be
considered at todays prices. Apparently
somebody thinks that HVDC might make it
cost effective.
The farther away a renewable energy re-
source like geothermal is from a commu-
nity, the more the cost of transmission line
construction becomes a factor. Todays rule
of thumb for smaller communities like
Elim is, the energy resource needs to be
located within about 15 miles to be viable.
The limit is farther with larger communities
like Nome. HVDC transmission might dou-
ble that; its a big deal. Its looking like HVDC will costs about
half as much; it only uses one wire. That
means utility poles are less expensive to
produce and install, and they can be spaced
farther apart.
Polarconsult Alaska Inc, with funding from
the Denali Commission Emerging Energy
Technology Fund, is testing HVDC trans-
mission technology near Fairbanks.
Princeton Power Systems, a subcontractor
to Polarconsult, is developing special con-
verters, needed at both ends of the wire,that are suitable for Alaska.
A Stakeholders Advisory Group headed by
Polarconsult Alaska Inc., with representa-
tion from many of the big energy players in
the State, has met three times in Anchorage
to help plan the future of this technology.
Pilgrim hot springs, shown on the map
High Voltage DC TransmissionHVDC
Polarconsult
Alaska, Inc
-
8/3/2019 MultiPower-Local December 2011
6/6