Contributing Crash Factors, Countermeasure Selection, and Evaluation
Multi-objective Evaluation in Countermeasure Selection at Two-Way ...
-
Upload
nguyendung -
Category
Documents
-
view
219 -
download
2
Transcript of Multi-objective Evaluation in Countermeasure Selection at Two-Way ...
1
Multi-objective Evaluation in Countermeasure Selection at Two-Way Stop
Controlled Intersections Considering Traffic Operation, Safety and Environment
By
Zhao Yang, Ph.D., Assistant Professor
National Key Laboratory of Air Traffic Flow Management
College of Civil Aviation, Nanjing University of Aeronautics and Astronautics
Jiangjun Road No. 29, Nanjing 211106, China
Tel: +86-13605152958
Email: [email protected]
Yuanyuan Zhang, Ph.D. (corresponding author)
Safe Transportation Research & Education Center
Institute of Transportation Studies, UC Berkeley
2614 Dwight Way, Mail Code #7374
Berkeley, CA 94720-7374
Tel: 315 706 6231
Email: [email protected]
Renwei Zhu, Graduate Research Assistant
China Academy of Urban Planning & Design, Shanghai 200335, China
Tel: +86-13915998295
Email: [email protected]
and
Yin Zhang, Ph.D., Assistant Professor
College of Civil Aviation, Nanjing University of Aeronautics and Astronautics
Jiangjun Road No. 29, Nanjing 211106, China
Tel: +86-13584092095
Email: [email protected]
Total number of words = 5244+ 250*9=7494
January 8-12, 2017
Paper submitted to the 96th Annual Meeting of the Transportation Research Board
2
Multi-objective Evaluation in Countermeasure Selection at Two-Way Stop Controlled 1
Intersections Considering Traffic Operation, Safety and Environment 2 3
by Zhao Yang, Yuanyuan Zhang, Renwei Zhu and Yin Zhang 4
5
ABSTRACT: 6
This study aims to develop a procedure to conduct multi-objective evaluation in traffic countermeasure 7
(CM) selection process at two-way stop-controlled (TWSC) intersections. To illustrate the procedure, 8
the economic benefits of three vehicle safety related CMs were calculated considering not only the 9
safety impacts but also the operational and environmental impacts. First, for each countermeasure, 10
VISSIM simulation models were developed to obtain the average delay, vehicle emission and fuel 11
consumption for the intersection both before and after the treatment. The traffic operational impacts 12
were calculated as the change in delay costs. The environmental impacts were calculated as the change 13
in vehicle emission and fuel consumption costs. Next, the safety impacts were calculated as the crash 14
reduction benefits for different CMs using safety performance functions (SPFs) and crash modification 15
factors (CMFs). Finally, the life cycle cost (LCC) method was used to combine the different 16
components in the total benefit. The Monte Carlo (MC) simulation method was used to conduct 17
uncertainty analysis by using random sampling from probability descriptions of uncertain input 18
variables to generate a probabilistic description of results. The findings showed first, that the 19
operational and environmental impacts accounted for a large proportion of the total impacts, which can 20
significantly affect the selection of CMs. Second, the rankings of the CMs differ depending on whether 21
the safety impacts alone are considered, or whether the safety, operational and environmental impacts 22
are considered together. The study illustrates the detailed process of evaluating projects considering 23
multiple objectives. This process offers policy and decision makers a solid and practical reference of 24
how to conduct multi-objective evaluation. The findings also explain how different objectives can 25
countervail with each other in improving motorist safety at TWSC intersections. 26
27
KEYWORDS: Traffic operation; safety; environment; countermeasure; multi-objective 28 29
30
3
INTRODUCTION 31 32
In transportation project decision making process, decision makers need to select the most competing 33
project from a set of alternatives. To realize a fully integrated and sustainable transportation system, 34
decision makers need information about the impacts of alternatives on multiple aspects of the 35
transportation system, the environment, and society. The “Transportation Strategic Plan 2012-2016” set 36
up the goals to provide safe, efficient, convenient, and sustainable transportation choices (1). This 37
requires project analysts to consider the multi-objective implications in designing and providing 38
transportation choices and services (2-4), particularly for those projects having countervailing effects 39
on different objectives (i.e., an operational enhancement that speeds up traffic flow may have negative 40
effects on traffic safety (5)). 41
42
Mobility, safety and environment are three important components in multi-objective evaluation for 43
both state and regional plans. Accommodating one objective without negatively affecting other 44
objectives is important when selecting traffic improvements. Therefore, to achieve the multi-objective 45
planning goal, it is necessary to examine the trade-offs among different objectives in order to make the 46
most informed choices among potential CMs. 47
48
In recent years, a few studies have investigated the trade-off impacts among different objectives for a 49
specific project. For example, Sharma et al. examined the impact of signal countdown timer on safety 50
and efficiency of signalized intersections by comparing the queue-discharge characteristics and 51
red-light violations in the presence and absence of timers. Results showed that the information 52
provided at the start of green (end of red) enhances efficiency while increasing incidence of red-light 53
violations (6). Stevanovic et al. examined the trade-off between efficiency and safety in the 54
development of signal timing plans to improve traffic safety. The results indicated that with the 55
increase in cycle length, the total number of conflicts was reduced while the delay was increased (7). 56
Mendonca evaluated the trade-offs between noise pollution and traffic safety of traffic-noise abatement 57
approaches. Results revealed that low noise pavements combined with all-electric and hybrid vehicles 58
might pose a severe threat to the safety of vulnerable road users (8). 59
60
Although some research has been conducted to examine the trade-off impacts among different 61
objectives for a specific project, most of them only provided the separate impact of the project for each 62
objective, without combining them together. But to prioritize the potential treatments, impacts on 63
different objectives need to be combined into one uniformed value to evaluate the multi-objective 64
effects of specific projects (2-4, 9) and to compare potential options. The “User and Non-User Benefit 65
Analysis for Highways” manual (5) presents the concept of combining multiple objectives by 66
converting them into monetary values. However, to date, there are few applications to streamline the 67
entire process of quantifying multiple objectives of a project, and combining them together to evaluate 68
the composite impacts for a specific project. 69
70
To this end, this study presents an analytic approach to select best option of traffic improvements by 71
taking into account multiple impacts of operation, safety and environment on motorists. To achieve this 72
goal, the paper illustrated the procedure through the case of incorporating different objectives into the 73
process of evaluating CMs at TWSC intersections. First, the impacts of different CMs on the traffic 74
operation, traffic safety and environment were quantified. Then, the combined impact for each CM 75
incorporating different objectives was calculated. Finally, the selected CMs were ranked considering 76
4
different objectives under various traffic scenarios. The framework implemented in the study illustrates 77
the solid process of prioritizing the alternative projects considering multi-objective impacts. The 78
framework can also be expanded to integrate additional objectives. 79
80
SAFETY-RELATED COUNTERMEASURES AT TWSC INTERSECTIONS 81 82
Two-way stop-controlled intersection is a common type of intersections in the United States. In a 83
TWSC intersection, vehicles from the two minor approaches to the intersection are required to stop and 84
all the other approaches are uncontrolled. Stopped vehicles on the minor roads are required to wait until 85
there is a sufficient gap in traffic before proceeding. Forcing vehicle to have a full stop is beneficial for 86
safety, but it causes the delay and emission raise on minor roads. In this way, operation, environment, 87
and safety could countervail with each other. A few traffic treatments are proposed to reduce stops and 88
improve traffic operation at TWSC intersections, i.e. conversion from a TWSC intersection into a 89
yield-controlled (YC) intersection. On the other hand, as part of an effort to reduce crashes at 90
intersections, some safety treatments are commonly implemented at TWSC intersections, such as 91
conversion from a TWSC intersection into an all-way stop controlled (AWSC) intersection or a 92
roundabout. These treatments are illustrated as follows: 93
94
CM 1: conversion from a TWSC intersection into a yield-controlled intersection (TWSC-YC). 95
Yield control is an intermediate form of control between normal right-of-way under no sign control and 96
stop sign control. Vehicles arriving at the minor approaches of the intersection do not have to stop 97
before proceeding if there is no traffic on major roads. Prior research has indicated that there could be 98
large savings in fuel consumption, vehicle operating costs, motorists delay, and vehicle emissions if 99
yield control were substituted for stop control at appropriate locations (10). 100
101
CM 2: conversion from a TWSC intersection into an all-way stop-controlled intersection 102
(TWSC-AWSC). An all-way stop-controlled intersection, also referred to as a four-way stop-controlled 103
intersection, is an intersection at which all vehicles are required to stop before proceeding through the 104
intersection. Vehicles generally have the right-of-way to proceed through the intersection in the order 105
that they arrived. This CM is implemented due to the perceived safety benefits, relative low cost, and 106
ease of implementation at the original TWSC intersections with safety problems (11). 107
108
CM 3: conversion from a TWSC intersection into a modern roundabout. A roundabout is a type of 109
circular intersection or junction in which road traffic flows almost continuously in one direction around a 110
central island. A great benefit of roundabouts is that they eliminate perpendicular/T-bone crashes (12). 111
112
DATA COLLECTION 113 114
To calibrate and validate the VISSIM simulation models, data were collected at six TWSC intersections 115
in the state of California. The following criteria were applied in the site selection process: 116
The major street had bidirectional six lanes with a non-traversable median. The minor street had 117
bidirectional two lanes with undivided medians; 118
There were few pedestrians crossing streets; 119
There were limited numbers of bicyclists; 120
Lane widths should be at least 9 feet; 121
The approach grade was level; and 122
5
The selected sites should be 250 feet away from upstream traffic signals. 123
124
The selected sites are given in Table 1. A video camera was set up in the field for recording traffic data. 125
The video cameras were inconspicuously mounted to avoid altering motorist behaviors. Field data 126
collection was conducted during weekday peak periods under fine weather conditions. In total, the 127
research team recorded 24 hours of traffic data in the field. 128
129
The recorded video tapes were later reviewed in the laboratory for obtaining traffic data. For each 130
movement, two reference lines were marked in the video as the location where the motorists generally 131
started to decelerate and the location where the motorists accomplished the acceleration to normal 132
speed (Figure 1). The following pieces of information were collected: (1) the vehicle volume and traffic 133
composition for each movement; (2) the exact time at which the rear wheel of a vehicle crossed 134
reference line A and B. With the recoded data, the travel time for each vehicle from A to B could be 135
obtained. 136
137
METHODOLOGY 138 139
To estimate the impacts of different CMs, the operational, safety and environmental components of the 140
total effects that arise from each CM were calculated. The original TWSC intersection is treated as the 141
base condition. VISSIM simulation models were used to evaluate the operational and environmental 142
impacts with different treatments. The operational impact is calculated as the change in total delay 143
costs for all the vehicles at the treated intersection observed in the calculation time compared with 144
those for the base condition. Similarly, the environmental impact with each treatment is calculated as 145
the change in vehicle emission costs and fuel consumption costs at the intersection compared with 146
those for the base condition. For safety performance, the Highway safety manual (HSM) provides 147
analytical tools and techniques to predict the average crash frequency at TWSC intersections (13). 148
Crash modification factors can be used to estimate cash reduction due to each treatment. 149
150
As the safety, operational and environmental elements of project impacts are quantified in different 151
units of measurements (i.e., delay is measured in seconds, traffic safety is measured as the number and 152
severity of crashes, vehicle emission is measured in grams per unit of time, and fuel consumption is 153
measured in gallon per unit of time), they are converted to a common unit of measurement so that they 154
can be compared with each other. The impacts are spread over future years and the net impacts in each 155
year are discounted to a present value. The User and Non-User Benefit Analysis for Highways (Red 156
Book) presents a method for converting benefit components with various units into monetary values 157
and aggregating the annual benefits/costs across years (5). 158
159
Because the operational impacts and environmental impacts are obtained from the simulation tool by 160
hour, the estimated costs are extrapolated to daily then to annual data. To account for the traffic volume 161
fluctuation during a day, the default hourly traffic distribution provided by FHWA is used in this study, 162
as shown in Table 2 (14). It is assumed that the distribution is consistent through the whole week. The 163
estimated hourly delay savings were aggregated through a day, and then through a year. 164
165
Operational Impacts 166 To obtain the impacts on delay and vehicle emission with the installation of different treatments, 167
VISSIM simulation model was developed for the selected TWSC intersections. The VISSIM 168
6
simulation models were calibrated using the traffic and geometric data measured at the selected site. 169
Travel time for different movements was used to validate the model. To take into account the stochastic 170
nature of simulation results, the VISSIM simulation models were run for multiple times with different 171
random number seeds and each run lasted for one hour period. The mean absolute percent error (MAPE) 172
was used to measure the differences between the field measured and the simulated travel time. The 173
MAPE value can be estimated as: 174
1
1i i
f s
i
f
l
i
t tMAPE
l t
(1) 175
where 176
MAPE = mean absolute percent error between the field measured and the simulated travel time; 177
l= number of movements; 178
tif = the field measured average travel time for movement i which is estimated by using the delay model 179
(sec); 180
tis = the simulated travel time for movement i (sec). 181
182
The calibrated VISSIM simulation model yielded a MAPE value of 8.69% for the average travel time 183
at the selected intersection, indicating that the calibrated simulation model provides reasonable 184
estimates. With the calibrated VISSIM simulation models for TWSC intersections, some similar 185
simulation models were established by changing the traffic control methods for the base condition, 186
including YC intersections, AWSC intersections and roundabouts, as shown in Figure 2. 187
188
The simulation model for each treated intersection was established based on the VISSIM simulation 189
model for the base condition. A node was created in VISSIM so that data could be collected in this area. 190
The outputs of the VISSIM simulation model include average delay (sec), emissions CO (g), emissions 191
NOx (g), emissions VOC (g), and fuel consumption (gal). 192
193
The delay reduction benefit associated with each CM is estimated as the additional value of total delay 194
for the treated intersection over the total delay for the base condition, which is shown as follows: 195
, , ,Ti h B h Ci hB VOT T T (2) 196
24
, ,
1
365Ti yearly Ti h
h
B B
(3) 197
where 198
BTi, h = delay reduction benefits during hour h with CM i (i=1, 2, 3) ($); 199
VOT = the value of time for motorists ($/person hours); 200
TCi,h = total delay during hour h with CM i (h); 201
TB,h = total vehicle delay during hour h for the base condition (h); 202
BTi, yearly = the annual delay reduction benefits for CM i compared with that of the base condition ($). 203
204 It should be noted that in the simulation models, the selected intersection has moderate traffic volume 205
(around 400 vehicles per hour per lane during peak hours), so that we assume that the traffic shift from 206
the intersection to other paths is minor. 207
208
Environmental Impacts 209 Similarly, the environmental impact was calculated as the change in vehicle emission and fuel 210
consumption costs, which are shown as follows: 211
7
, , , , ,+Ei h j Bj h Cij h F B h Ci h
j
B C E E C F F (4) 212
24
, ,
1
365Ei yearly Ei h
h
B B
(5) 213
where 214
BEi, h = the environmental impact during hour h for CM i ($); 215
BEi, yearly = the annual environmental impact for CM i ($); 216
Cj = cost for emission j ($/U.S. ton); 217
ECij,h = total amount of emission j during hour h for CM i (U.S. ton); 218
EBj,h = total amount of emission j during hour h for the base condition (U.S. ton); 219
CF= fuel price ($/gallon); 220
FCi,h = total fuel consumption during hour h for CM i (gallon); 221
FB,h = total fuel consumption during hour h for the base condition (gallon). 222
223
Safety Impacts 224 To estimate the safety impact of each treatment, the change in number of crashes due to the CM was 225
calculated. Safety performance function (SPF) was used to estimate the predicted average crash 226
frequency for a specific site type using a regression model developed from data for a number of similar 227
sites. HSM provides a series of SPFs to estimate the average crash frequency of a TWSC intersection 228
with specified base conditions based on average daily traffic volumes of major and minor roads (5). 229
The predicted average crash frequency includes multiple-vehicle crashes and single-vehicle crashes. 230
Crash modification factors (CMF) are then used to adjust the SPF estimates of predicted average crash 231
frequencies to determine the effects of individual geometric design and traffic control treatments. The 232
equations are shown as follows (5): 233
exp( ln( ) ln( ))k k minbkmv kmajN AADT AADa b c T (6) 234
exp( ' ' ln( ) ' ln( ))minbksv majk k kN AADT AADa b c T (7) 235
SPFk bkmv bksvN N N (8) 236
ikbik SPFkN N CMF (9) 237
, ( )k SPFk bikSi yearly
k
C N NB (10) 238
where 239
k = crash severity (T= all, F = fatal/injury, O= property damage only); 240
Nbksv = predicted average number of single-vehicle collisions for base conditions; 241
Nbkmv = predicted average number of multiple-vehicle collisions for base conditions; 242
AADTmaj = average daily traffic volume (veh/day) for major road (both directions of travel combined); 243
AADTmin = average daily traffic volume (veh/day) for minor road (both directions of travel combined); 244
Nspfk = predicted total average crash frequency for crash type k for base conditions (excluding 245
vehicle-pedestrian and vehicle-bicycle collisions); 246
Nbik = predicted crash frequency for CM i for crash type k (excluding vehicle-pedestrian and 247
vehicle-bicycle collisions); 248
CMFik = crash modification factors for CM i for crash type k, as shown in Table 3 (15); 249
ak, bk, ck, a’k, b’k, c’k = regression coefficients for crash type k, as shown in Table 4 (13); 250
BSi, yearly = the annual safety impact for CM i ($); 251
Ck = crash cost estimates for crash type k, as shown in Table 4 (5). 252
8
253
Life-Cycle Cost Analysis 254 To compare the overall performance of different treatments, the operational, safety and environmental 255
impacts are quantified using monetized expressions in order to establish a common unit. The life-cycle 256
cost analysis (LCC) is used to evaluate the overall long term economic efficiency for investment 257
alternatives (5, 16). The net present value (NPV) for each CM is calculated by combing all costs and 258
benefits or returns associated with a transportation project into a single present value over the life cycle. 259
A positive NPV indicates that the project is economically efficient. The procedure to estimate the NPV 260
of each treatment is illustrated as follows: 261
262
Step 1: Identify the evaluating objectives and performance measurements. In our case, the objectives 263
include traffic operation, traffic safety and environment impacts. 264
265
Step 2: Estimate the change in annual crash costs, delay costs, vehicle emission and fuel consumption 266
costs using equations (2) to (10). 267
268
Step 3: Convert the annual crash costs, delay costs, vehicle emission and fuel consumption costs into a 269
present value. The factor to convert a series of uniform future values to a single present value (P/A, m, 270
n) is calculated as follows: 271
(1 ) 1
( / , , )(1 )
n
n
mP A m n
m m
(11) 272
, , ( / , , )NPV Ti Ti yearlyB B P A m n (12) 273
, , ( / , , )NPV Si Si yearlyB B P A m n (13) 274
, , ( / , , )NPV Ei Ei yearlyB B P A m n (14) 275
where 276
m= discount rate; 277
n= year in service life of the countermeasure; 278
BNPV,Ti = the NPV of the operational impact for CM i ($); 279
BNPV,Si = the NPV of the safety impact for CM i ($); 280
BNPV, Ei= the NPV of the environmental impact for CM i ($); 281
282
Step 4: Calculate the NPV of each CM, which is the sum of the present value of the operational, safety 283
and environmental impacts over the implementation costs. 284
, , , ,+ +NPVi NPV Ti NPV Si NPV Ei NPV IiB B B B B (15) 285
where 286
BNPVi = the NPV of overall impact for CM i ($); 287
BNPV,Ii = the NPV of implementation costs for CM i ($). 288
289
The procedure to conduct the multi-objective evaluation is summarized in Figure 3. 290
291
To account for the variability of the input data in the LCC analysis, the MC method was used to 292
conduct uncertainty analysis by using random sampling from probability descriptions of uncertain input 293
variables to generate a probabilistic description of results. With the uncertainty analysis results, the 294
decision maker knows not only the full range of possible values, but also the relative probability of any 295
9
particular outcome actually occurring. An example of the values or distributions of input variables is 296
shown in Table 5. 297
298
RESULTS 299
300
Sensitivity Analysis 301 Traffic volume is one of the crucial parameters that may affect the impact of different objectives. The 302
tradeoff between those objectives depends on traffic volume from both major and minor roads. So this 303
study evaluates the combined impacts of each treatment under different traffic volume scenarios. With 304
the established VISSIM simulation models, sensitivity analysis can be conducted to identify the effects 305
of traffic volume on travel time, vehicle emission and fuel consumption with each treatment. 306
307
As mentioned in HSM, the SPFs are applicable to the intersection with AADT of the major road 308
ranging from 0 to 46,800 veh/d and AADT of the minor road ranging from 0 to 5,900 veh/d. 309
Meanwhile, as shown in Table 1, the critical volume for selected CMFs ranges from 680 veh/d to 310
15,400 veh/d for both the major and minor roads. Therefore, in the sensitivity analysis, the AADT of 311
the major road ranges from 680 veh/d to 15,400 veh/d, and the AADT of the minor road ranges from 312
680 veh/d to 5,900 veh/d. Field observation showed that the percentage of left-turn and right-turn 313
traffic from the major road and minor road of the selected site are around 20%. The NPV for each CM 314
was calculated under different traffic volume conditions with the same traffic composition. 315
316
Figure 4 illustrates the comparison of annual delay cost, emission cost and fuel consumption cost 317
before and after the treatment. As shown in Figure 4, the annual delay cost can be up to 1 million 318
dollars per year under the selected traffic volume condition. The annual emission cost can reach 60,000 319
dollars per year. And for annual fuel consumption cost the number can increase to 800,000 dollars per 320
year. So for each countermeasure, the annual delay cost always accounts for the largest proportion 321
(over 60%) of the total annual cost, followed by the annual fuel consumption cost (over 30%) and 322
annual emission cost (less than 10%). 323
324
Generally, the annual delay cost, emission cost and fuel consumption cost increase with the raise in 325
AADT on both the major roads and the minor roads, and the increase becomes more sensitive as traffic 326
volumes get higher. As shown in Figure 4, the slopes are gentle when the volumes are low, and become 327
steeper as traffic volumes increase. The slope in Figure 4 (a) turns to be the steepest, indicating that the 328
annual delay cost is the most sensitive to the volume changes. 329
330
Along with the conversion from the base condition to different CMs, the cost changes in different ways. 331
Using CM2 (convert TWSC to AWSC) always costs more for each objective at each volume condition. 332
As compared with the base condition (TWSC), all the three types of costs become higher with the 333
implementation of CM 2 for most traffic volume scenarios. In Figure 4, as the AADT from the major 334
street or minor street changes, the grey layer of CM2 are all above the black layer of base condition. 335
The greatest increase of annual cost by conversion from base condition to CM2 increase occurs with 336
the largest AADT from the major road and the lowest AADT from the minor road. This is reasonable 337
because when major road traffic volume is far more than the minor road, stopping vehicles on major 338
roads results in much more costs. On the contrary, changing from the base condition to CM1 and CM3 339
reduces the costs for every objective. The greatest cost reduction occurs with the greatest AADT from 340
the major road and the minor road. As shown in Figure 4, the red layer of CM1 and blue layer of CM3 341
10
are all below the black layer of base condition. This is reasonable because yielding and roundabout do 342
not need to fully stop vehicles so that the delay and costs from breaking are reduced. In addition, the 343
red layer and blue layer are very close to each other with changing the vehicle volume on major and 344
minor roads. The only difference is when the volumes become very high. It means the costs between 345
CM1 and CM3 are similar until the major and minor roads become very busy. In this scenario, CM1 346
costs more than CM3. 347
348
Ranking of the Selected CMs 349 To combine the different components to obtain the total benefits of each countermeasure, MC method 350
was used to estimate the NPVs before and after the treatment. The range and distribution of NPV can 351
be estimated for each traffic volume condition. Figure 5 illustrates the distribution of NPVs when 352
AADT of major road is 7,100 veh/d and AADT of the minor road is 5,650 veh/d as an example. For 353
each CM, the distribution of NPV incorporating the operational, safety and environmental impacts is 354
compared with the NPV incorporating the safety impact only. As shown in Figure 5, the mean NPV is 355
the highest for CM 2 (TWSC-AWSC), followed by CM 3 (TWSC-Roundabout) and CM 1 (TWSC-YC) 356
when considering the safety impact only. However, when traffic efficiency and environmental impacts 357
are incorporated, the mean NPV for CM 3 (TWSC-Roundabout) is the highest, followed by CM1 358
(TWSC-YC) and CM 2 (TWSC-AWSC). The results indicate that as a countermeasure to improve 359
motorist safety at a TWSC intersection, CM 2 (TWSC-AWSC) tends to be the most effective. However, 360
when considering the external impacts, this countermeasure greatly increases the total delay and stops 361
for motorists, and thus causes negative impacts to traffic flow and the environment. 362
363
CONCLUSION 364 365
This study presents a procedure for evaluating traffic treatments considering multiple objectives. The 366
treatments are safety related countermeasures at TWSC intersections. The multiple objectives 367
considered are traffic efficiency, traffic safety and environmental impacts. The change in total delay, 368
vehicle emission and fuel consumption for each CM is obtained using VISSIM simulation tools. The 369
safety benefits are quantified using a method from HSM based on SPF and CRF. To combine the 370
different objectives, the NPV of each selected CM is calculated, including the change in delay costs, 371
crash costs, vehicle emission costs and fuel consumption costs. On the basis of the estimated results 372
and analysis, the following conclusions can be made: 373
374
AADT of the major and minor roads may influence the external impacts of different treatments. 375
For each CM, the delay costs, vehicle emission costs and fuel consumption costs increase with the 376
increase in major and minor road AADT. The external costs are increased for CM2 (TWSC-AWSC) 377
while decreased for CM1 (TWSC-YC) and CM3 (TWSC-Roundabout). 378
379
For each CM, trade-offs may exist among different objectives. CM1 improves traffic operation and 380
reduces vehicle emissions but may result in some safety problems. CM2 improves traffic safety while 381
increasing vehicle delay and emissions. CM3 improves traffic operation, traffic safety and reduces 382
vehicle emissions under most traffic volume scenarios. When combining all the impacts together, the 383
mean NPV is positive for CM3, negative for CM2, and around zero for CM1 when AADT of the major 384
street equals 7,100 veh/d and AADT of the minor street equals 5,650 veh/d. 385
386
11
Combining multiple objectives in the evaluation could result in reprioritization of traffic 387
improvement projects. This study illustrates the common evaluation for treatments by ranking potential 388
CMs based only on the consideration of the safety impacts. However, by incorporating the external 389
impacts, the prioritization of the selected CMs may change. This is because the total delay, vehicle 390
emission and fuel consumption savings benefits comprise a large proportion of the estimated NPVs, 391
which when added into the total benefits can change the dominant trending of the benefits patterns. 392
393
DISCUSSION 394 395
Although there are specific resources to provide quantification of the impacts of each objective, 396
combining them into the practice of evaluation results in greater challenges than expected. This study 397
summarizes these challenges for other researchers: 398
399
The present documentation provides a series of equations and default parameter values that can be 400
directly applied in conducting traffic efficiency and safety analyses. However, when applying these to 401
other research, data from local studies should be used to calibrate the parameters of the equations. 402
When selecting data from different studies, the best value of each parameter should be chosen. If 403
research to evaluate the operational or safety impacts is unavailable, it is necessary to establish 404
estimation models or simulation techniques. 405
406
The results of this study rely on the values obtained from existing studies, including CMF, VOT, 407
crash cost and emission cost estimates. These estimates may vary over time. For example, the emission 408
cost may change given the penetration of vehicles equipped with new technology. Thus, the values 409
should be updated as new research results become available. 410
411
One of the limitations of this study is that the effects of a treatment are likely to have an impact on 412
traffic flow. The traffic volume and traffic conditions may change after the treatment implemented. In 413
this paper, the selected intersection has moderate traffic volume in simulation models, so that this 414
impact was ignored in the evaluation. However, if the intersection is a key point in the roadway 415
network, the change in traffic flow should be considered. Not only the single location but also the 416
larger area network should be evaluated. The authors recommend that the future research can be 417
expanded by considering this issue. 418
419
Another limitation of this study is that only the impacts of different CMs for motorists are 420
considered is this study. The impacts for other roadway users are not incorporated. When considering 421
multiple objectives, it is necessary to simultaneously consider multiple road users. Among the 422
objectives, those that might have countervailing impacts under different traffic conditions or among 423
different roadway users should be investigated more thoroughly. 424
425
ACKNOWLEDGMENTS 426 427
This research was sponsored by the National Natural Science Foundation of China (Grant No. 428
51608268), the Natural Science Foundation of Jiangsu Province (BK20150747) and the Fundamental 429
Research Funds for the Central Universities (NJ20160016). 430
431
12
REFERENCES 432
433 [1]. U.S. Department of Transportation (2014). Transportation for a new generation, strategic plan for 434
fiscal years 2012-2016. Washington, D.C. [Accessed April 18, 2015]. 435
[2]. Hickman, R., Saxena, S., Banister, D., Ashiru, O. (2012) Examining transport futures with 436
scenario analysis and MCA. Transport Res A-Pol, 46, 560-575. 437
[3]. Sælensminde, K. (2004) Cost-benefit analyses of walking and cycling track networks taking into 438
account insecurity, health effects and external costs of motorized traffic. Transport Res A-Pol, 38, 439
593-606. 440
[4]. Sohn, K. (2011) Multi-objective optimization of a road diet network design. Transport Res A-Pol, 441
45, 499-511. 442
[5]. American Association of State Highway Transportation Officials (AASHTO). (2010a) User and 443
Non-User Benefit Analysis for Highways. Washington, D.C. 444
[6]. Sharma,A., Vanajakshi, L., Girish, V., Harshitha, M. (2012) Impact of Signal Timing 445
Information on Safety and Efficiency of Signalized Intersections. Journal of Transportation 446
Engineering, 138(4), pp.467-478. 447
[7]. Stevanovic, A., Stevanovic, J., Kergaye, C. (2013) Optimization of traffic signal timings based on 448
surrogate measures of safety. Transportation Research Part C, pp. 159-178. 449
[8]. Mendonc C., Freitas, E., Ferreirac, J., Raimundoc, I., Santosa, J. (2013) Noise abatement and 450
traffic safety: The trade-off of quieter engines and pavements on vehicle detection. Accident 451
Analysis and Prevention, 11-17. 452
[9]. Metropolitan Transportation Commission (MTC). Transportation 2035 Plan for the San 453
Francisco Bay Area, 2009. http://www.mtc.ca.gov/planning/2035_plan/. [Accessed October 30, 454
2015]. 455
[10]. Transportation Research Board (TRB). (1989) NCHRP 320: Guidelines for Converting Stop to 456
Yield Control at Intersections. National Research Council, Washington, D.C. 457
[11]. Carrie L. Simpson & Joseph E. Hummer (2010) Evaluation of the Conversion from Two-Way 458
Stop Sign Control to All-Way Stop Sign Control at 53 Locations in North Carolina, Journal of 459
Transportation Safety & Security, 2:3, 239-260. 460
[12]. Federal Highway Administration (FHWA). Roundabouts: An Information Guide, 461
FHWA-RD-00-67, Exhibit 5.2, pp 106, Washington, DC, June 2000. 462
(www.tfhrc.gov/safety/00068.htm). 463
[13]. American Association of State Highway Transportation Officials (AASHTO). (2010b) Highway 464
Safety Manual. Washington, D.C. 465
[14]. Walls III, J. and Smith, M. R. (1998) Life-Cycle Cost Analysis in Pavement Design. Report No. 466
FHWA-SA-98-079. 467
[15]. Crash Modification Factors Clearing House. http://www.cmfclearinghouse.org. [Accessed 468
October 30, 2015]. 469
[16]. Caltrans. Life-Cycle Benefit-Cost Analysis Economic Parameters 2012. 470
http://www.dot.ca.gov/hq/tpp/offices/eab/benefit_cost/LCBCA-economic_parameters.html. 471
[Accessed June 30, 2016]. 472
473
13
Nomenclature 474
475 List of symbols and abbreviations 476
477
CM countermeasure 478
TWSC two-way stop-controlled 479
YC yield-controlled 480
AWSC all-way stop controlled 481
SPF safety performance function 482
CMF crash modification factor 483
LCC life cycle cost 484
MC Monte Carlo 485
MAPE mean absolute percent error 486
NPV net present value 487
HSM Highway safety manual 488
AADT average annual daily traffic 489
L number of movements 490
tif the field measured average travel time for movement i which is estimated by using the 491
delay model (sec) 492
tis the simulated travel time for movement i (sec) 493
BTi, h delay reduction benefits during hour h with CM i (i=1, 2, 3) ($) 494
VOT the value of time for motorists ($/person hours) 495
TCi,h total delay during hour h with CM i (h) 496
TB,h total vehicle delay during hour h for the base condition (h) 497
BTi, yearly the annual delay reduction benefits for CM i compared with that of the base condition 498
($) 499
BEi, h the environmental impact during hour h for CM i ($) 500
BEi, yearly the annual environmental impact for CM i ($) 501
Cj cost for emission j ($/U.S. ton) 502
ECij,h total amount of emission j during hour h for CM i (U.S. ton) 503
EBj,h total amount of emission j during hour h for the base condition (U.S. ton) 504
CF fuel price ($/gallon) 505
FCi,h total fuel consumption during hour h for CM i (gallon) 506
FB,h total fuel consumption during hour h for the base condition (gallon) 507
k crash severity (T= all, F = fatal/injury, O= property damage only) 508
Nbksv predicted average number of single-vehicle collisions for base conditions 509
Nbkmv predicted average number of multiple-vehicle collisions for base conditions 510
AADTmaj average daily traffic volume (veh/day) for major road (both directions of travel 511
combined) 512
AADTmin average daily traffic volume (veh/day) for minor road (both directions of travel 513
combined) 514
ak, bk, ck regression coefficients for multiple-vehicle collisions 515
a’k, b’k, c’k regression coefficients for single-vehicle collisions 516
Nspfk predicted total average crash frequency for crash type k for base conditions (excluding 517
vehicle-pedestrian and vehicle-bicycle collisions) 518
14
Nbik predicted crash frequency for CM i for crash type k (excluding vehicle-pedestrian and 519
vehicle-bicycle collisions) 520
CMFik crash modification factors for CM i for crash type k 521
BSi, yearly the annual safety impact for CM i ($) 522
Ck crash cost estimates for crash type k 523
m discount rate 524
n year in service life of the countermeasure 525
BNPV,Ti the NPV of the operational impact for CM i ($) 526
BNPV,Si the NPV of the safety impact for CM i ($) 527
BNPV, Ei the NPV of the environmental impact for CM i ($) 528
BNPVi the NPV of overall impact for CM i ($) 529
BNPV,Ii the NPV of implementation costs for CM i ($) 530
531
532
15
533
List of Figures 534 535
Figure 1 An example of the selected TWSC intersection 536
537
Figure 2 VISSIM simulation models 538
539
Figure 3 The procedure to conduct multi-objective evaluation 540
541
Figure 4 Cost comparison before and after the treatment 542
543
Figure 5 Distribution of NPVs (AADTmaj=7,100veh/d, AADTmin=5,650veh/d): (a) considering 544
multiple objectives and (b) considering the safety impacts only 545
546
547
List of Tables 548 549
Table 1 Selected sites for field data collection 550
551
Table 2 Default hourly traffic distribution 552
553
Table 3 Crash modification factors for selected CMs 554
555
Table 4 Regression coefficients 556
557
Table 5 Probability distribution of input values 558
559
16
560 Figure 1. An example of the selected TWSC intersection 561
562
17
563 Figure 2. VISSIM simulation models 564
565
18
Identify evaluating objectives
- Traffic Operation
- Traffic safety
- Environment
Identify evaluating objectives
- Traffic Operation
- Traffic safety
- Environment
Safety impactSafety impact
Prioritize the alternativesPrioritize the alternatives
Environmental impactEnvironmental impact
Calculate the NPV of each CMCalculate the NPV of each CM
, ( )k SPFk bikSi yearly
k
C N NB
24
, ,
1
365Ei yearly Ei h
h
B B
SPFk bkmv bksvN N N
ikbik SPFkN N CMF
exp( ln( ) ln( ))k k minbkmv kmajN AADT AADa b c T
exp( ' ' ln( ) ' ln( ))minbksv majk k kN AADT AADa b c T
Operational impactOperational impact Safety impactSafety impact Environmental impactEnvironmental impact
, , ( / , , )NPV Ti Ti yearlyB B P A m n , , ( / , , )NPV Si Si yearlyB B P A m n
, , ( / , , )NPV Ei Ei yearlyB B P A m n
Convert to a present valueConvert to a present value
(1 ) 1( / , , )
(1 )
n
n
mP A m n
m m
, , , ,+ +NPVi NPV Ti NPV Si NPV Ei NPV IiB B B B B
Operational impactOperational impact
24
, ,
1
365Ti yearly Ti h
h
B B
, , ,Ti h B h Ci hB VOT T T
, , ,
, ,+
Ei h j Bj h Cij h
j
F B h Ci h
B C E E
C F F
566 Figure 3. The procedure to conduct multi-objective evaluation 567
568
19
569 Figure 4. Cost comparison before and after the treatment 570
571
20
572 Figure 5. Distribution of NPVs (AADTmaj=7,100veh/d, AADTmin=5,650veh/d): (a) considering 573
multiple objectives and (b) considering the safety impacts only 574 575
576
21
Table 1. Selected sites for field data collection 577
Sites City Type Wa (ft)
1 San Pablo Ave & Harrison St Berkeley, California TWSC 12
2 San Pablo Ave & Hearst Ave Berkeley, California TWSC 12
3 San Pablo Ave & Jones St Berkeley, California TWSC 12
4 San Pablo Ave & Camelia St Berkeley, California TWSC 12
5 Shattuck Ave & Virginia St Berkeley, California TWSC 10
6 Shattuck Ave & Berkeley Way Berkeley, California TWSC 10 aWidth of median nose. 578
579
22
580
TABLE 2. Default hourly traffic distribution 581
Hour % ADTa Hour % ADT Hour % ADT Hour % ADT
0-1 1.2 6-7 5.1 12-13 5.6 18-19 5.9
1-2 0.8 7-8 7.8 13-14 5.7 19-20 3.9
2-3 0.7 8-9 6.3 14-15 5.9 20-21 3.3
3-4 0.5 9-10 5.2 15-16 6.5 21-22 2.8
4-5 0.7 10-11 4.7 16-17 7.9 22-23 2.3
5-6 1.7 11-12 5.3 17-18 8.5 23-24 1.7 a Average daily traffic 582
583
584
23
Table 3. Crash modification factors for selected CMs 585
Countermeasures
CMF
Crash
Type
Crash
Severity
Major Road
Traffic
Volume
(veh/d)
Minor Road
Traffic
Volume
(veh/d)
Mean Std.
Error
CM 1 TWSC-YC 2.27 1.26 All All Not Specified Not Specified
CM 2 TWSC-AWSC 0.319 0.022 All All Not Specified Not Specified
CM 3 TWSC-
Roundabout
0.71 0.11 All All
680-15,400 680-15,400 0.19 0.09 All
Serious
Injury,
Minor
Injury
586
587
24
Table 4. Regression coefficients 588
Crash Type Crash Severity Intercept AADTmaj AADTmin
Multiple-Vehicle Crashes
ak bk ck
T -8.90 0.82 0.25
F -11.13 0.93 0.28
O -8.74 0.77 0.23
Single-Vehicle Crashes
a'k b'k c'k
T -5.33 0.33 0.12
F NbFsv= 0.28×NbTsv
O -7.04 0.36 0.25
589
590
25
Table 5 . Probability distribution of input values 591
Parameters
Types of
Probability
Distribution
Values
Average fuel price ($/Gallon) (16) Constant 3.714
VOT ($/person hours)( 16) Constant 12.50
Crash cost estimates
($)
(13)
Fatality (K) Constant 4,008,900
Disabling injury (A) Constant 216,000
Evident injury (B) Constant 79,000
Fatal/Injury (K/A/B) Constant 158,200
Possible injury (C) Constant 44,900
PDO (O) Constant 7,400
Emission cost
estimates ($)
(16)
Carbon Monoxide
(CO) Constant 75
Nitrogen Oxide
(NOx) Constant 17,300
Volatile Organic
Compounds (VOC) Constant 1,210
Implementation cost ($)
(11, 12)
Uniform
(min, max)
CM 1 Uniform (4,430,
5,000)
CM 2 Uniform (4,430,
5,000)
CM 3 Uniform(194,00
0, 500,000)
Annual mantaintance fees ($) Constant
CM 1 200
CM 2 200
CM 3 1,000
Interest rate
Triang (min,
most likely,
max)
Triang (0.03,0.04,0.05)
CMF Normal (avg,
std) See Table 3
592