MS Project Network ERP02 12-08-2016 (1)
Transcript of MS Project Network ERP02 12-08-2016 (1)
Evaluation& R ecom m endation
Start: Mon 1/18/16 ID: 3
Finish: Fri 1/22/16 Dur: 5 days
Res: Associate02, Associate03
DevelopP rojectCharter
Start: Mon 1/25/16 ID: 4
Finish: Fri 2/5/16 Dur: 10 days
Res: Associate01, PM01
Planning
Start: 1/1/8 4 ID: 9
Fin ish :1/1/8 4 Dur:125d ays
C om p:0%
Software
Start: 1/1/8 4 ID: 10
Fin ish :1/1/8 4 Dur:55d ays
C om p:0%
Hardware
Start: 1/1/8 4 ID: 15
Fin ish :1/1/8 4 Dur:34d ays
C om p:0%
Consultant
Start: 1/1/8 4 ID: 19
Fin ish :1/1/8 4 Dur:36d ays
C om p:0%
Implementation
Start: 1/1/8 4 ID: 26
Fin ish :1/1/8 4 Dur:38 d ays?
C om p:0%
Documentation
Start: 1/1/8 4 ID: 27
Fin ish :1/1/8 4 Dur:10 d ays
C om p:0%
Configuration
Start: 1/1/8 4 ID: 30
Fin ish :1/1/8 4 Dur:10 d ays
C om p:0%
Development
Start: 1/1/8 4 ID: 33
Fin ish :1/1/8 4 Dur:1 8 d ays?
C om p:0%
DevelopBusinessCase
Start: Fri 1/1/16 ID: 2
Finish: Fri 1/15/16 Dur: 11 days
Res: Associate01, Associate02
Project Set-up
Start: 1/1/8 4 ID: 1
Fin ish :1/1/8 4 Dur:53d ays
C om p:0%
Page 1
Deployment
Start: 1/1/8 4 ID: 39
Fin ish :1/1/8 4 Dur:8 4d ays?
C om p:0%
Data Integration
Start: 1/1/8 4 ID: 40
Fin ish :1/1/8 4 Dur:1 7 d ays
C om p:0%
Training
Start: 1/1/8 4 ID: 44
Fin ish :1/1/8 4 Dur:15d ays
C om p:0%
Testing
Start: 1/1/8 4 ID: 48
Fin ish :1/1/8 4 Dur:1 8 d ays
C om p:0%
Go Live
Start: 1/1/8 4 ID: 52
Fin ish :1/1/8 4 Dur:1 7 d ays
C om p:0%
Finalize
Start: 1/1/8 4 ID: 56
Fin ish :1/1/8 4 Dur:1 7 d ays?
C om p:0%
Page 2
T ollgateR eview R 01
Start: Mon 2/29/16 ID: 7
Finish: Tue 3/15/16 Dur: 12 days
Res: Senior Exec01, Associate01, PM01
DevelopR FP
Start: Wed 3/16/16 ID: 11
Finish: Tue 4/5/16 Dur: 15 days
Res: Consult01
P rojectS chedule
Start: Mon 2/15/16 ID: 6
Finish: Fri 2/26/16 Dur: 10 days
Res: PM02, Associate03, Consult01, PM01
GetM anagem entS upport
Start: Mon 2/8/16 ID: 5
Finish: Fri 2/12/16 Dur: 5 days
Res: Senior Exec01
Page 3
Page 4
R eview S ystem s
Start: Wed 4/6/16 ID: 12
Finish: Tue 4/19/16 Dur: 10 days
Res: Consult01
S electER P S ystem
Start: Wed 4/20/16 ID: 13
Finish: Tue 5/3/16 Dur: 10 days
Res: Associate02, PM01, Consult01, Senior Exec03
R eceiveS oftw are
Start: Wed 5/4/16 ID: 14
Finish: Tue 5/31/16 Dur: 20 days
Res: Consult01, Consult02, Consult03
U pgradeHardw are
Start: Wed 6/1/16 ID: 16
Finish: Thu 6/16/16 Dur: 12 days
Res: Consult01
Page 5
Page 6
S etupP rojectO ffice
Start: Fri 6/17/16 ID: 17
Finish: Mon 7/4/16 Dur: 12 days
Res: PM02
O perations& M aintenance
Start: Tue 7/5/16 ID: 18
Finish: Mon 7/18/16Dur: 10 days
Res: Consult03
DevelopR FP
Start: Tue 7/19/16 ID: 20
Finish: Wed 7/27/16Dur: 7 days
Res: Associate02, PM03
R eview P roposals
Start: Thu 7/28/16 ID: 21
Finish: Wed 8/10/16Dur: 10 days
Res: Associate01, PM01, Senior Exec01
Page 7
Page 8
S electConsultant
Start: Thu 8/11/16 ID: 22
Finish: Wed 8/17/16Dur: 5 days
Res: Associate02, PM01, Senior Exec01
S ignContract
Start: Thu 8/18/16 ID: 23
Finish: Wed 8/24/16Dur: 5 days
Res: PM02, Senior Exec01
T ollgateR eview R 02
Start: Thu 8/25/16 ID: 24
Finish: Tue 9/6/16 Dur: 9 days
Res: Senior Exec01, Senior Exec02, Senior Exec03
Docum entP rocesses
Start: Wed 9/7/16 ID: 28
Finish: Tue 9/13/16 Dur: 5 days
Res: Consult01, Consult02
Page 9
Page 10
P repareEnd-U serDocum ents
Start: Wed 9/14/16 ID: 29
Finish: Tue 9/20/16 Dur: 5 days
Res: Consult01, Consult02
ConfigureS ystem s
Start: Wed 9/21/16 ID: 31
Finish: Tue 9/27/16 Dur: 5 days
Res: Consult02, Consult03
P repareP rototypes
Start: Wed 9/28/16 ID: 32
Finish: Tue 10/4/16 Dur: 5 days
Res: Consult02, Consult03
Verify R equirem ents
Start: Wed 10/5/16 ID: 34
Finish: Tue 10/11/16Dur: 5 days
Res: Consult03
Page 11
Page 12
P repareDesign
Start: Wed 10/12/16ID: 35
Finish: Tue 10/18/16Dur: 5 days
Res: Consult02
BuildP rototype
Start: Wed 10/19/16ID: 36
Finish: Thu 10/27/16Dur: 7 days
Res: Consult03
T ollgateR eview R 03
Start: Fri 10/28/16 ID: 37
Finish: Fri 10/28/16 Dur: 1 day?
Res: Senior Exec01, Senior Exec02, Senior Exec03, Associate01, Consult01
Page 13
Determ ineDataR equirem ents
Start: Mon 10/31/16ID: 41
Finish: Tue 11/8/16 Dur: 7 days
Res: Associate01, Consult01
Page 14
Page 15
P repareData
Start: Wed 11/9/16 ID: 42
Finish: Tue 11/15/16Dur: 5 days
Res: Associate03, Consult02
U ploadData
Start: Wed 11/16/16ID: 43
Finish: Tue 11/22/16Dur: 5 days
Res: Consult02, Consult03
ConductL evelIT raining
Start: Wed 11/23/16ID: 45
Finish: Tue 11/29/16Dur: 5 days
Res: Consult01, Consult02
ConductL evelIIT raining
Start: Wed 11/30/16ID: 46
Finish: Tue 12/6/16 Dur: 5 days
Res: Consult02, Consult03
Page 16
Page 17
ConductEnd-U serT raining
Start: Wed 12/7/16 ID: 47
Finish: Tue 12/13/16Dur: 5 days
Res: Consult01, Consult03
P erform U nitT ests
Start: Wed 12/14/16ID: 49
Finish: Tue 12/20/16Dur: 5 days
Res: Consult01
P erform IntegrationT ests
Start: Wed 12/21/16ID: 50
Finish: Tue 12/27/16Dur: 5 days
Res: Consult02
P erform S tressT ests
Start: Wed 12/28/16ID: 51
Finish: Fri 1/6/17 Dur: 8 days
Res: Consult03
Page 18
Page 19
T roubleshooting
Start: Mon 1/9/17 ID: 53
Finish: Tue 1/17/17 Dur: 7 days
Res: Consult01, Consult02, Consult03
Dam ageControls
Start: Wed 1/18/17 ID: 54
Finish: Tue 1/24/17 Dur: 5 days
Res: Consult01, Consult02, Consult03
U serR eview s
Start: Wed 1/25/17 ID: 55
Finish: Tue 1/31/17 Dur: 5 days
Res: Consult01, Consult02, Consult03
S etupS upportP lan
Start: Wed 2/1/17 ID: 57
Finish: Tue 2/7/17 Dur: 5 days
Res: Associate03, Consult01, PM01, Senior Exec03
Page 20
Page 21
U pgradeHelpdesk
Start: Wed 2/8/17 ID: 58
Finish: Tue 2/14/17 Dur: 5 days
Res: Consult01, Consult02
CloseP roject
Start: Wed 2/15/17 ID: 59
Finish: Tue 2/21/17 Dur: 5 days
Res: PM01, PM02, PM03
T ollgateR eview R 04
Start: Wed 2/22/17 ID: 60
Finish: Wed 2/22/17Dur: 1 day?
Res: Senior Exec01, Senior Exec02, Senior Exec03
T ollgateR eview R 05
Start: Thu 2/23/17 ID: 62
Finish: Thu 2/23/17 Dur: 1 day?
Res: Senior Exec01, Senior Exec02, Senior Exec03, Associate01, Associate02, Associate03, Consult01, PM01, PM02, PM03
Page 22
Critical
Noncritical
Critical Milestone
Milestone
Critical Summary
Summary
Critical Inserted
Inserted
Critical Marked
Marked
Critical External
External
Project Summary
Highlighted Critical
Highlighted Noncritical
Page 23
Project: Project1.mppDate: Wed 12/7/16