Evaluation& R ecommendation Start: Mon 1/18/16 ID: 3 Finish: Fri 1/22/16 Dur: 5 days Res: Associate02, Associate03 DevelopProjectCharter Start: Mon 1/25/16 ID: 4 Finish: Fri 2/5/16 Dur: 10 days Res: Associate01, PM01 Planning St art : 1/1/8 4 ID: 9 Fin ish :1/1/8 4 D ur: 1 2 5d ays C om p: 0% Software St art : 1/1/8 4 ID: 10 Fin ish :1/1/8 4 Dur:55d ays C om p: 0% Hardware St art : 1/1/8 4 ID: 15 Fin ish :1/1/8 4 Dur:34d ays C om p: 0% Consultant St art : 1/1/8 4 ID: 19 Fin ish :1/1/8 4 Dur:36d ays C om p: 0% Implementation St art : 1/1/8 4 ID: 26 Fin ish :1/1/8 4 Dur:38 d ays? C om p: 0% Documentation St art : 1/1/8 4 ID: 27 Fin ish :1/1/8 4 Dur:10 d ays C om p: 0% Configuration St art : 1/1/8 4 ID: 30 Fin ish :1/1/8 4 Dur:10 d ays C om p: 0% Development St art : 1/1/8 4 ID: 33 Fin ish :1/1/8 4 Dur:18 d ays? C om p: 0% DevelopBusinessCase Start: Fri 1/1/16 ID: 2 Finish: Fri 1/15/16 Dur: 11 days Res: Associate01, Associate02 Project Set-up St art : 1/1/8 4 ID: 1 Fin ish :1/1/8 4 Dur:53d ays C om p: 0% Page 1

Transcript of MS Project Network ERP02 12-08-2016 (1)

Page 1: MS Project Network ERP02 12-08-2016 (1)

Evaluation& R ecom m endation

Start: Mon 1/18/16 ID: 3

Finish: Fri 1/22/16 Dur: 5 days

Res: Associate02, Associate03

DevelopP rojectCharter

Start: Mon 1/25/16 ID: 4

Finish: Fri 2/5/16 Dur: 10 days

Res: Associate01, PM01

Planning

Start: 1/1/8 4 ID: 9

Fin ish :1/1/8 4 Dur:125d ays

C om p:0%

Software

Start: 1/1/8 4 ID: 10

Fin ish :1/1/8 4 Dur:55d ays

C om p:0%

Hardware

Start: 1/1/8 4 ID: 15

Fin ish :1/1/8 4 Dur:34d ays

C om p:0%

Consultant

Start: 1/1/8 4 ID: 19

Fin ish :1/1/8 4 Dur:36d ays

C om p:0%

Implementation

Start: 1/1/8 4 ID: 26

Fin ish :1/1/8 4 Dur:38 d ays?

C om p:0%

Documentation

Start: 1/1/8 4 ID: 27

Fin ish :1/1/8 4 Dur:10 d ays

C om p:0%

Configuration

Start: 1/1/8 4 ID: 30

Fin ish :1/1/8 4 Dur:10 d ays

C om p:0%

Development

Start: 1/1/8 4 ID: 33

Fin ish :1/1/8 4 Dur:1 8 d ays?

C om p:0%

DevelopBusinessCase

Start: Fri 1/1/16 ID: 2

Finish: Fri 1/15/16 Dur: 11 days

Res: Associate01, Associate02

Project Set-up

Start: 1/1/8 4 ID: 1

Fin ish :1/1/8 4 Dur:53d ays

C om p:0%

Page 1

Page 2: MS Project Network ERP02 12-08-2016 (1)

Deployment

Start: 1/1/8 4 ID: 39

Fin ish :1/1/8 4 Dur:8 4d ays?

C om p:0%

Data Integration

Start: 1/1/8 4 ID: 40

Fin ish :1/1/8 4 Dur:1 7 d ays

C om p:0%

Training

Start: 1/1/8 4 ID: 44

Fin ish :1/1/8 4 Dur:15d ays

C om p:0%

Testing

Start: 1/1/8 4 ID: 48

Fin ish :1/1/8 4 Dur:1 8 d ays

C om p:0%

Go Live

Start: 1/1/8 4 ID: 52

Fin ish :1/1/8 4 Dur:1 7 d ays

C om p:0%

Finalize

Start: 1/1/8 4 ID: 56

Fin ish :1/1/8 4 Dur:1 7 d ays?

C om p:0%

Page 2

Page 3: MS Project Network ERP02 12-08-2016 (1)

T ollgateR eview R 01

Start: Mon 2/29/16 ID: 7

Finish: Tue 3/15/16 Dur: 12 days

Res: Senior Exec01, Associate01, PM01

DevelopR FP

Start: Wed 3/16/16 ID: 11

Finish: Tue 4/5/16 Dur: 15 days

Res: Consult01

P rojectS chedule

Start: Mon 2/15/16 ID: 6

Finish: Fri 2/26/16 Dur: 10 days

Res: PM02, Associate03, Consult01, PM01

GetM anagem entS upport

Start: Mon 2/8/16 ID: 5

Finish: Fri 2/12/16 Dur: 5 days

Res: Senior Exec01

Page 3

Page 4: MS Project Network ERP02 12-08-2016 (1)

Page 4

Page 5: MS Project Network ERP02 12-08-2016 (1)

R eview S ystem s

Start: Wed 4/6/16 ID: 12

Finish: Tue 4/19/16 Dur: 10 days

Res: Consult01

S electER P S ystem

Start: Wed 4/20/16 ID: 13

Finish: Tue 5/3/16 Dur: 10 days

Res: Associate02, PM01, Consult01, Senior Exec03

R eceiveS oftw are

Start: Wed 5/4/16 ID: 14

Finish: Tue 5/31/16 Dur: 20 days

Res: Consult01, Consult02, Consult03

U pgradeHardw are

Start: Wed 6/1/16 ID: 16

Finish: Thu 6/16/16 Dur: 12 days

Res: Consult01

Page 5

Page 6: MS Project Network ERP02 12-08-2016 (1)

Page 6

Page 7: MS Project Network ERP02 12-08-2016 (1)

S etupP rojectO ffice

Start: Fri 6/17/16 ID: 17

Finish: Mon 7/4/16 Dur: 12 days

Res: PM02

O perations& M aintenance

Start: Tue 7/5/16 ID: 18

Finish: Mon 7/18/16Dur: 10 days

Res: Consult03

DevelopR FP

Start: Tue 7/19/16 ID: 20

Finish: Wed 7/27/16Dur: 7 days

Res: Associate02, PM03

R eview P roposals

Start: Thu 7/28/16 ID: 21

Finish: Wed 8/10/16Dur: 10 days

Res: Associate01, PM01, Senior Exec01

Page 7

Page 8: MS Project Network ERP02 12-08-2016 (1)

Page 8

Page 9: MS Project Network ERP02 12-08-2016 (1)

S electConsultant

Start: Thu 8/11/16 ID: 22

Finish: Wed 8/17/16Dur: 5 days

Res: Associate02, PM01, Senior Exec01

S ignContract

Start: Thu 8/18/16 ID: 23

Finish: Wed 8/24/16Dur: 5 days

Res: PM02, Senior Exec01

T ollgateR eview R 02

Start: Thu 8/25/16 ID: 24

Finish: Tue 9/6/16 Dur: 9 days

Res: Senior Exec01, Senior Exec02, Senior Exec03

Docum entP rocesses

Start: Wed 9/7/16 ID: 28

Finish: Tue 9/13/16 Dur: 5 days

Res: Consult01, Consult02

Page 9

Page 10: MS Project Network ERP02 12-08-2016 (1)

Page 10

Page 11: MS Project Network ERP02 12-08-2016 (1)

P repareEnd-U serDocum ents

Start: Wed 9/14/16 ID: 29

Finish: Tue 9/20/16 Dur: 5 days

Res: Consult01, Consult02

ConfigureS ystem s

Start: Wed 9/21/16 ID: 31

Finish: Tue 9/27/16 Dur: 5 days

Res: Consult02, Consult03

P repareP rototypes

Start: Wed 9/28/16 ID: 32

Finish: Tue 10/4/16 Dur: 5 days

Res: Consult02, Consult03

Verify R equirem ents

Start: Wed 10/5/16 ID: 34

Finish: Tue 10/11/16Dur: 5 days

Res: Consult03

Page 11

Page 12: MS Project Network ERP02 12-08-2016 (1)

Page 12

Page 13: MS Project Network ERP02 12-08-2016 (1)

P repareDesign

Start: Wed 10/12/16ID: 35

Finish: Tue 10/18/16Dur: 5 days

Res: Consult02

BuildP rototype

Start: Wed 10/19/16ID: 36

Finish: Thu 10/27/16Dur: 7 days

Res: Consult03

T ollgateR eview R 03

Start: Fri 10/28/16 ID: 37

Finish: Fri 10/28/16 Dur: 1 day?

Res: Senior Exec01, Senior Exec02, Senior Exec03, Associate01, Consult01

Page 13

Page 14: MS Project Network ERP02 12-08-2016 (1)

Determ ineDataR equirem ents

Start: Mon 10/31/16ID: 41

Finish: Tue 11/8/16 Dur: 7 days

Res: Associate01, Consult01

Page 14

Page 15: MS Project Network ERP02 12-08-2016 (1)

Page 15

Page 16: MS Project Network ERP02 12-08-2016 (1)

P repareData

Start: Wed 11/9/16 ID: 42

Finish: Tue 11/15/16Dur: 5 days

Res: Associate03, Consult02

U ploadData

Start: Wed 11/16/16ID: 43

Finish: Tue 11/22/16Dur: 5 days

Res: Consult02, Consult03

ConductL evelIT raining

Start: Wed 11/23/16ID: 45

Finish: Tue 11/29/16Dur: 5 days

Res: Consult01, Consult02

ConductL evelIIT raining

Start: Wed 11/30/16ID: 46

Finish: Tue 12/6/16 Dur: 5 days

Res: Consult02, Consult03

Page 16

Page 17: MS Project Network ERP02 12-08-2016 (1)

Page 17

Page 18: MS Project Network ERP02 12-08-2016 (1)

ConductEnd-U serT raining

Start: Wed 12/7/16 ID: 47

Finish: Tue 12/13/16Dur: 5 days

Res: Consult01, Consult03

P erform U nitT ests

Start: Wed 12/14/16ID: 49

Finish: Tue 12/20/16Dur: 5 days

Res: Consult01

P erform IntegrationT ests

Start: Wed 12/21/16ID: 50

Finish: Tue 12/27/16Dur: 5 days

Res: Consult02

P erform S tressT ests

Start: Wed 12/28/16ID: 51

Finish: Fri 1/6/17 Dur: 8 days

Res: Consult03

Page 18

Page 19: MS Project Network ERP02 12-08-2016 (1)

Page 19

Page 20: MS Project Network ERP02 12-08-2016 (1)

T roubleshooting

Start: Mon 1/9/17 ID: 53

Finish: Tue 1/17/17 Dur: 7 days

Res: Consult01, Consult02, Consult03

Dam ageControls

Start: Wed 1/18/17 ID: 54

Finish: Tue 1/24/17 Dur: 5 days

Res: Consult01, Consult02, Consult03

U serR eview s

Start: Wed 1/25/17 ID: 55

Finish: Tue 1/31/17 Dur: 5 days

Res: Consult01, Consult02, Consult03

S etupS upportP lan

Start: Wed 2/1/17 ID: 57

Finish: Tue 2/7/17 Dur: 5 days

Res: Associate03, Consult01, PM01, Senior Exec03

Page 20

Page 21: MS Project Network ERP02 12-08-2016 (1)

Page 21

Page 22: MS Project Network ERP02 12-08-2016 (1)

U pgradeHelpdesk

Start: Wed 2/8/17 ID: 58

Finish: Tue 2/14/17 Dur: 5 days

Res: Consult01, Consult02

CloseP roject

Start: Wed 2/15/17 ID: 59

Finish: Tue 2/21/17 Dur: 5 days

Res: PM01, PM02, PM03

T ollgateR eview R 04

Start: Wed 2/22/17 ID: 60

Finish: Wed 2/22/17Dur: 1 day?

Res: Senior Exec01, Senior Exec02, Senior Exec03

T ollgateR eview R 05

Start: Thu 2/23/17 ID: 62

Finish: Thu 2/23/17 Dur: 1 day?

Res: Senior Exec01, Senior Exec02, Senior Exec03, Associate01, Associate02, Associate03, Consult01, PM01, PM02, PM03

Page 22

Page 23: MS Project Network ERP02 12-08-2016 (1)

Critical

Noncritical

Critical Milestone

Milestone

Critical Summary

Summary

Critical Inserted

Inserted

Critical Marked

Marked

Critical External

External

Project Summary

Highlighted Critical

Highlighted Noncritical

Page 23

Project: Project1.mppDate: Wed 12/7/16