Introduction To MS Project 2007 Professional 10 Project Information One would be able to get MS-Project to schedule from a specified project end date 2- 4 Must St ar t on 10/8/2009 Constr ai n should be removed to do this It is advisable to introduce all project constrains at the very end of your planning session. Task : Remove the constrain for 2-4 and specify project end date as 12/01/2009 and schedule from Project Finish Date. What is the project Start Date now Use the undo button to get it back to schedule from the Project start date.  ©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  7

Transcript of MS Project (4)

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 1/12

Introduction To MS Project 2007 Professional

10 Project Information

One would be able to get MS-Project to schedule from a specified project end date

2-4 Must Start on 10/8/2009 Constrain should be removed to do this

It is advisable to introduce all project constrains at the very end of your planning session.

Task : Remove the constrain for 2-4 and specify project end date as 12/01/2009 and schedule from Project Finish Date.

What is the project Start Date now

Use the undo button to get it back to schedule from the Project start date.

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  7

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 2/12

Introduction To MS Project 2007 Professional

11 Assigning Resources to ActivitiesCheck : TOOLS / OPTIONS / GENERAL

Define Rate Works on Working Hours Max Units

Peter 100 T/S 8-5

Harry 100 T/S 8-5

Martin 100 T/S 8-5

Bob 200 T/S 8-5

Chris 100 t/s 8-5

cat 5 network wire 5000 per 100m

sk-lab 40 T/S 8-5 400%unsk-lab 20 T/S 8-5 800%

12 Fields to Insert to Resource work sheet

Type Material , Work, Cost

Material Label Units

Cost

Booking Type Committed , Proposed

Max Units

Base Calendar

Accrue at : Prorated / Start / End

Available From

Available To

Can you delete them ?

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  8

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 3/12

Introduction To MS Project 2007 Professional

13 Material

Cost

Material Label

Max Units

             Fie

ld     Desc

riptions

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  9

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 4/12

Introduction To MS Project 2007 Professional

14 Booking Types

Accrue at

Base Calendar

             Fie

ld     Desc

riptions

. Custom

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  10

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 5/12

Introduction To MS Project 2007 Professional

15 Assign 1-2 Peter1-4 Chris

2-4 Peter 200 m of cat 5

  2-3 Bob 200 m of cat 5

3-5 Bob

2-5 Harry 300 m of cat 5

4-5 Peter

5-7 Peter

7-9 Peter

5-6 Sk Lab 100%6-9 Harry

5-8 Martin

8-9 Martin

What is the project duration ?

When it is going to finish ?

What is the Project Cost?

16 1-2 Peter Add  One More Skilled Lab to 1-2

1-4 chris

2-4 Martin 200 m of cat 5 How to Answer ? What does it mean ?2-3 Bob 200 m of cat 5 Very Critical to get this right ….!

3-5 Bob

2-5 Harry 300 m of cat 5

4-5 Peter5-7 Peter

7-9 Peter

5-6 Harry

6-9 Harry

5-8 Bob

8-9 Bob

Increase work . Keep the duration

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  11

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 6/12

Introduction To MS Project 2007 Professional

17

18

Option 1 Option 2 Option 3

Introduce

constrain As

Late AsPossible to

Phase 1 and

Phase 2

Activities

Do you see

any change in

project

duration ?

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  12

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 7/12

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 8/12

Introduction To MS Project 2007 Professional

20 Making Changes to the project : Change -- ONE

Chris is unavailable and replace him with Bobby

Rate Works on Working Hours Instructions

Bobby 200 T and W only 8-5

Needs to define additional calendar for Bobby

Assign to 1-4

What has happened to the Critical Path now ?

What is the project duration ?

When it is going to finish ?

Project Cost

21 Tracking - Saving Baseline : What does it mean ?

Ready to Implement / Construct

End of Month / Quarter

Major Change

Next Phase

Project Assumption Contract is signed and construction is starting

Save your Baseline Baseline :Original Scope

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  14

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 9/12

Introduction To MS Project 2007 Professional

22 Tracking Method : Percentage of work done

23 Project Status Date Report Following Percentages

1-2 100

What does the project status date mean ? 1-4 30

2-4 0

2-3 0

Set the Date to 10/15/2009 3-5 0

2-5 0

4-5 05-7 0

7-9 0

5-6 0

6-9 0

5-8 0

8-9 0

View / Tool Bars / Tracking

Report that first 2 progress meetings

has been done too

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  15

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 10/12

Introduction To MS Project 2007 Professional

24 More options to report progress

Remember to have your tracking table and also move the cursor to the activity you want to update

Try out the options : Would be faster than

doing it one at a time

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  16

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 11/12

Introduction To MS Project 2007 Professional

25 Getting progress lines

Experiment with the

progress lines using

10/15/2009 project

status date

Try Line Styles tab too

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  17

8/8/2019 MS Project (4)

http://slidepdf.com/reader/full/ms-project-4 12/12

Introduction To MS Project 2007 Professional

26 Setting Baselines : Manipulation of baselines / others start finish dates : What if sessions

Discuss the use of this option

Helps in managing baselines

and interim plans

 

©  Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page  :  18