KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 1 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
1
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR PIPING
AND STRUCTURES
(Doc. No.: MS- 1306-BP-01)
SHAYBAH INCREASE GAS HANDLING CAPACITY PROJECT
Package # 4
04
03
02
01
00 04th
Jun,2013 For Approval Karrena
Arabia
Rev Date Description Prepared by Checked by
QC
Approved by
Samsung (SEA)
Approved by
ARAMCO
Client : SAMSUNG ENGINEERING, SAUDI ARABIA
Plant : SHAYBAH INCREASE GAS HANDLING PROJECT
Owner : SAUDI ARAMCO OIL COMPANY
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 2 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
2
Table of Contents
1. SCOPE
2. REFERENCES
3. RESPONSIBILITIES
4. TOUCH-UP PROCEDURE
5. QUALITY CONTROL PROCEDURE
6. PAINTING SUMMARY REPORTS
7. MANAGEMENTS OF HSE
8. JOB SAFETY ANALYSIS
ATTACHMENTS
- 1. SATIP-H-100-01 Paint Application of Liquid Coating Systems (Industrial Facilities)
- 2. Material Receiving Checklist (SAIC-H-2024, SAIC-H-2025, SAIC-H-2026)
- 3. Installation Phase Checklist (SAIC-H-2032, SAIC-H-2033)
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 3 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
3
1. SCOPE
This plan is compiled for TOUCH-UP work of the carbon steel, LTCS, alloy A/G piping, Stainless
steel A/G piping and structural steel including pipe support etc, both in the site and in the lay
down workshop area.
The plan is to meet the safety requirements of SHAYBAH PACKAGE-4 PROJECT.
This plan covers the minimum mandatory requirements for the surface preparation, painting
application and the requirements for inspection and testing.
2. REFERENCES
SAEP-316 Engineering Requirement
SAES-H-100 Coating materials and Application requirements for industrial facilities
SAES-H-001 Coating selection and Application requirements for industrial plants and
equipments
SAES-H-002 Internal and external coatings for steel pipelines and piping
SAES-H-101 Approved protective coating system for industrial plants and equipment
SAES-H-101V Approved Saudi Aramco data sheets - Paints and Coatings
SAES-H-204 General specification and application procedures of Heat-Shrink sleeves to
coated pipe
SAES-H-102 Safety requirements for coating applications
SAES-B-067 Safety identification and safety colours
09-SAMSS-060 Packaging requirements for coatings
GI-0006.021 Safety requirements for abrasive blasting
3. RESPONSIBILITIES
3.1 Painting Crew Supervisor
Supervisor shall be responsible for supervising the painting and coating works, the qulaity of work
and the safety of all the crew. He shall check and record the weather condition, the surface
preparation, wet film thickness(WFT) and dry film thickness(DFT). Every day prior to start the
work, the painting supervisor shall check the equipments.
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 4 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
4
3.2 Painting Inspector
The painting inspector is responsible for the quality of the painting. The painting inspector shall be responsible to issue daily base all QC reports in accordance to QCP requirements. He shall be in charge to ensure timely issue of RFI’s.
3.3 Foreman for Touch-Up
He is responsible for the safety of the crew and make sure that the working environment is in
good condition. In working progress, he should supervise the work. When finding any problems,
he should immediately inform supervisor.
3.4 Safety Inspector
He is responsible for all the painting staffs. Every day the safety personal should hold a safety
meeting. Before working, he should check the PPE, equipment and tools to make sure they all in
good condition and tell everyone the risk they may meet.
3.5 Blaster and Painter
Every staff must wear suitable PPE before starting the work. All the blasters and painters should
work as to the requirements of SAUDI ARAMCO standards. The blaster and painter should be
qualified as per the requirement of SAEP-316.
4. TOUCH UP PROCEDURE
4.1 Surface preparation requirements
Clean the defective or damaged area by power brush. Grind to a rough metal surface using
atleast on 80 grit disc sander. Feather edge the coating atleast 25mm to 50mm beyond bare
metal. Remove the dust and debris prior to touch-up.
Consider that the power brush will be used only if the damaged area is less than 0.1m2. For
areas greater than 0.1m2, use blast cleaning to obtain the metal surface pretreatment originally
specifie.
Feather edge the coating atleast 50mm beyond the bare metal. Solvent cleaning (SSPC SP1),
Hand tool cleaning (SSPC SP2) etc., will be apply rely on the condition and situation raises.
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 5 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
5
4.2 Paints schedule for touch-up and Paint details
TABLE 4.2.1
Items
Final color / RAL
Original
Coating Sys.
Paint Sys. for
Touch-up
Remarks
For CS, LTCS
& Alloy A/G
Piping
(uninsulated)
Up to 80ºC Aluminium APCS – 4 APCS – 4
Up to 120ºC As per Manufacture APCS – 26 APCS – 26
Up to 150ºC As per Manufacture APCS – 1B APCS – 1B
151 - 400ºC As per Manufacture APCS – 11A APCS – 11A
For CS, LTCS
& Alloy A/G
Piping
(insulated)
Up to 90ºC As per Manufacture APCS – 2A APCS – 2A
Up to 120ºC As per Manufacture APCS – 2C APCS – 2C
-10 to 150ºC As per Manufacture APCS – 2I APCS – 2I
Up to 177ºC As per Manufacture APCS – 5A APCS – 5A
For SS A/G
Piping
(uninsulated &
insulated)
-
As per Manufacture
APCS – 11C
APCS – 11C
For structural
steel including
pipe support
- Traffic Grey / 7042
APCS – 11C
APCS – 11C
TABLE 4.2.2
Paint System
Type of
Coat
Manufacturer
Product name
Generic Code
APCS - 1B
Primer International Intergard 291 Epoxy primer – Polyamide cured
Intermediate International Intergard 410 Polyamide cured epoxy Intermd.
Top Coat International Intergard 410 Polyamide cured epoxy Intermd.
APCS - 4
Primer International Interprime 409 Zinc Phosphate Alkyd primer
Intermediate International Interprime 409 Zinc Phosphate Alkyd primer
Top Coat International Intertherm 891 Aluminium Topcoat
APCS – 11A
Primer International Interzinc 22 Inorganic zinc Primer: Solvent based
Top Coat International Intertherm 50 Heat-Resistant silicone topcoat
APCS – 11C
Primer International Intertherm 751 CSA Hi-Temp resistant
Top Coat International Intertherm 751 CSA Hi-Temp resistant
APCS - 26 Top Coat International Interseal 738 Epoxy Mastic coat – Self priming
APCS – 2A
Primer International Interline 399 Phenolic Epoxy
Intermediate International Interline 399 Phenolic Epoxy
Top Coat International Interline 399 Phenolic Epoxy
APCS – 2I Primer Belzona Belzona 1391S Epoxy-Phenol Novolac coating
APCS – 5A Primer Jotun Pengard Express Polymide Epoxy
APCS – 2C Primer Jotun Tankgard Storage
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 6 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
6
4.3 General Requirements
The repair coating shall be compatible with the existing coating. No coating shall be applied when
steel surface temperatures are less than 3°C above dew point, and when the relative humidity is
more than 85% so as to avoid the risk of condensation during painting.
Complicated areas like Welds, nuts, bolts and supports etc., can be painted by Stripe coating
using proper brush.
4.4 Paint application method
Touch up shall be use brush, roller and as well as airless sprayer. Touch works shall flow the
manufacturer’s data sheet requirement.
4.5 Painting inspection
The final appearance of the surface painting film should be well-proportioned and free from
flowing and dropping. Finished painting should have a uniform appearance.
Areas showing painting defects such as runs, sags, drips, embedded foreign matter, blisters,
cracks, visible holidays and low DFT areas should be marked for repairs.
After paint cured and totally dried, the dry film thickness shall be measured with a magnetic or
ultrasonic probe such as “DIGITAL ELCOMETER” etc., as of SSPC PA-2.
5. QUALITY CONTROL PROCEDURE
5.1 Dry film thickness inspection
After every layer of painting dried and cured, the dry film thickness (DFT) should be checked and
must meet the required thickness as per the SSPC PA2.
5.2 Inspection facilities list:
Clemtex tape with Dial gauge
Digital dew point meter
WFT film thickness measurements – Comb gauge
DFT film thickness measurements – Electronic gauge
Surface temperature gauge
Torch Light
DFT gauges must be calibrate prior to measure the painted surface.
5.3 Inspection Report and record
SATIP SHALL BE FOLLOWED FOR TOUCH UP INSPECTION AND RECORD.
SATIP-H-100-01 Paint Application of Liquid Coating Systems (Industrial Facilities).
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 7 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
7
.
6. PAINTING SUMMARY REPORTS
After the painting inspection, summary reports should be filled in as per the approved form of
Saudi Aramco Inspection Checklist (SAIC).
Reference
SATIP-H-100-01 Paint application of Liquid Coating Systems (Industrial Facilities)
SAIC-H-2032 Inspection of Repair/Touch-up of Coatings
7. MANAGEMENTS OF HSE
7.1 General Instructions
Appropriate work permit shall be taken before start of work as applicable. All safety rules must
be followed by all the people. A designed safety inspector is always at the painting application
area. Every day the safety meeting shall be held. The appropriate PPE should be worn. Pay
more attention to Fire and explosion prevention. Health hazards should be analyzed before
starting the work. Materials Safety Data Sheets for all paintings, solvents, cleaners and
equipments in use shall be readily available on-site. Solvents shall not be used by personal for
washing up. Electrically driven power tools shall be properly grounded to prevent work.
7.2 Environmental Issues
Storage of paints
Paints and thinners shall be stored in well-ventilated buildings at storage temperatures as
recommended in the Manufacturer's data sheet. Paints materials used at construction sites must
be covered with appropriate canvas, tarpaulins, or equivalent for a temporary storage period not
to exceed 14 days.
Each paint container shall be clearly marked in accordance with 09-SAMSS-060. Paints shall not
be used from a container showing a sign of leakage. Paints which have exceeded the shelf life
given in the Saudi Aramco Data Sheet (see definition in SAES-H-101) shall be set aside and
must not be used unless written authorization to the contrary is given by the CSD.
All materials for coating shall, until usage, remain in the Air conditioned containers, marked with
supplier's name, brand, batch number and expiry date. Storage conditions shall comply with paint
supplier's data sheet recommendations.
Collection and Disposal of Used Paint Tins – All the paint tins shall be collected in a designed
and signposted area for temporary storage. MSDS shall be always attached in the storage
container.
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 8 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
8
8. JOB SAFETY ANALYSIS
Step
No.
Description of
Task step
Potential Accidents or Hazards Control Measures / Safe Job Procedures
1
2
Surface cleaning
Touch up works
2.1 Occupational Health problem to
inhalation of paint fumes
2.2 Fire / Environmental hazard,
spills, disposal.
2.3 Trips / Slips / Fails
2.4 Inadequate storage / disposal of
paint and empty container.
2.5 Non-availability of eye wash kit
2.6 Eye injury
2.7 Hand injury
2.8 Working at high platform
2.1.1 TBT to b conducted on the hazards and
risk to health by paint materials MSDS
attached.
2.1.2 Suitable respiratory protection mask to
be used and correct maintenance of PPE’s.
2.1.3 Use chemical rubber hand gloves.
2.2.1 Paint will be stored in ventilated and cool
place.
2.2.2 Fire extinguisher shall be kept as
required in the required area.
2.3.1 Use proper access work platform.
2.3.2 Use adequate rope to lift / lower the paint
containers / brush while working in the height.
2.3.3 Maintian area clean and tidy at all times.
2.4.1 Make sure that the paint can put a firm
place to avoid falling down. In case any paint
spillage, it will be cleaned immediately.
2.4.2 Left out paint will be kept in separate
container and disposed as regularly as Waste
Management System.
2.5.1 Emergency eye wash kit shall be placed
in the painting area.
2.6.1 All area nearby will be masked prior to
spray.
2.7.1 All tools / equipment shall be inspected
and colour coded.
2.8.1 Safety glasses shall be worn at all time,
especially during the paint spray and mixing.
MANDATORY / OR
RECOMMENDED
PERSONAL PROTECTIVE EQUIPMENT
(Tick Appropriate PPE)
√ . Hard Hat.
√ . Safety Glasses, Goggles,
Face Shield.
√ . Safety shoes.
√ . Coveralls – Long sleeve
Nomex.
√ . Air Supplied Blasting Hood.
√ . Hearing protection.
√ . Hand gloves (Cotton,
Leather, Rubber and others).
. Full body Harness &
Lifeline.
√ . Respiratory Protective
Equipment.
. H2S Gas Alert Clip.
. SCBA on stand-by.
. Hard Hat.
COMMENTS:
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 9 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
9
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR PIPING
AND STRUCTURES
(Doc. No.: MS- 1306-BP-01)
Attachment – 1
SATIP-H-100-01
Paint Application of Liquid Coating System
(Industrial Facilities)
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 10 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
10
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR PIPING
AND STRUCTURES
(Doc. No.: MS- 1306-BP-01)
Attachment – 2
Material Receiving Checklist
SAIC-H-2024 Receiving Inspection of Paint & Abrasive Materials
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 11 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
11
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR PIPING
AND STRUCTURES
(Doc. No.: MS- 1306-BP-01)
Attachment – 2
Material Receiving Checklist
SAIC-H-2025 Storage, Handling and Preservation of Paint and
Abrasive Materials
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 12 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
12
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR PIPING
AND STRUCTURES
(Doc. No.: MS- 1306-BP-01)
Attachment – 2
Material Receiving Checklist
SAIC-H-2026 Coating Equipment Inspection
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 13 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
13
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR PIPING
AND STRUCTURES
(Doc. No.: MS- 1306-BP-01)
Attachment – 3
Installation Phase Checklist
SAIC-H-2032 Repair and /or Touch-up of Coatings
KARRENA
SAMSUNG engineering
SAUDI ARAMCO INGC SHAYBAH
PACKAGE # 4 PROJECT
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR
PIPING AND STRUCTURES
AGREEMENT NO SSA-SHAYBAH#4-PPS-001
OUR REF. NO P/SA/SAMSUNG-13/46
DOC. NO. MS-1306-BP-01
FORM NO. FM-PAINT-001
REVISION NO. 00
PAGE 14 of 14
P.O. Box 2147, Saihat 31972 – Kingdom of Saudi Arabia
Tel. + 966 3 839 2429 / 839 2196 / 8319 1577 Fax +966 3 839 2238
www.karrenagulf.com , [email protected]
14
METHOD STATEMENT OF
PAINT TOUCH-UP WORKS FOR PIPING
AND STRUCTURES
(Doc. No.: MS- 1306-BP-01)
Attachment – 3
Installation Phase Checklist
SAIC-H-2033 Application of Safety Colour Coding & Stencilling
of Equipment / Piping Identification