MP RAPDRP (Part-A) - mpez.co.in Folders... · What is RAPDRP ? 3 RAPDRP Roles 14 ... Increase...
Transcript of MP RAPDRP (Part-A) - mpez.co.in Folders... · What is RAPDRP ? 3 RAPDRP Roles 14 ... Increase...
MP RAPDRP (Part-A)
Index:
Topic Slide No.
What is RAPDRP ? 3
RAPDRP Roles 14
Modules of RAPDRP 16
Key Field Activities 17
Web Self Service 22
Meter Data Acquisition System 23Meter Data Acquisition System 23
Energy Audit 29
GIS 30
New Connection 39
Billing 40
Collection 42
Asset management 46
Infrastructure Setup 53
What is R-APDRP
� Power sector reforms in India have been going on for more than a decade
� Initially the focus was more on bringing about structural changes like
unbundling of SEBs and creation of independent generation, transmission
and distribution companies
� Subsequently power generation received maximum focus
� In the recent past, it was felt that power distribution was the weakest link in
the entire value chain and sector cannot achieve viability unless issues in
the power distribution sector are resolved, aiming at a sustainable
3
the power distribution sector are resolved, aiming at a sustainable
development of the sector
� With these objectives in mind, Government of India’s Ministry of Power
launched R-APDRP scheme
� This is a unique initiative in the utility industry globally
� This covers total automation of core utility business processes of the
targeted towns in an ESCOM covering millions of consumers using a
common infrastructure
� R-APDRP is GoI’s initiative with primarily objectives of
� Establishment of baseline data
� Fixation of accountability
� Reduction of AT&C losses
� Commercial viability
� Reduction of outages & interruptions
What is R-APDRP
� Reduction of outages & interruptions
� Increase consumer satisfaction through strengthening & up-gradation of
Sub-Transmission & Distribution network & adoption of Information
Technology during XI Plan
� To cover urban areas with population > 30,000 (10,000 in case of special
category states)
� To demonstrate performance improvement for availing financial benefits
� Total programme size is over Rs 50,000 Cr
� GoI grant component for Part-A : Rs.10,000 Cr (Max)
� GoI grant component for Part-B : Rs.20,000 Cr (Max)
� PFC / REC Loan for Part-B : Rs.20,000 Cr (Min)
� Part C will cover the enabling components of this programme
What is R-APDRP
5
� Part C will cover the enabling components of this programme
� GoI will provide 100% Loan for part A of the schemes including IT
applications
� GoI will provide 25% Loan for Part B of the schemes (90% for special
category states), counter part funding by PFC / REC up to 75%
� Incentive scheme for utility staff (Up to 2% of part B grant amount)
R-APDRP funding (In scope )
� Cost of hiring IT Consultants
� Project management cost
� Ring fencing cost
� System metering cost
� Sub-division / other office cost
What is R-APDRP
6
� Sub-division / other office cost
� DGPS survey cost
� Data centre cost
� Customer care centre cost
Sequence Of Activities for Utility
� Appointment of IT Consultant (from empanelled consultants with PFC)
� Preparation of DPR for Part A
� Appointment of IT Implementation Agency (from empanelled agencies )
� Implementation /Monitoring of project Part-A
� Completion of Part A & certification by TPIEA-IT
What is R-APDRP
7
� Completion of Part A & certification by TPIEA-IT
� Ring fencing of Project areas
� Establishing Base Line Data by Utility & verification by TPIEA-EA
� Preparation of DPR for Part B
� Appointment of Implementation Agency/ Monitoring of project for Part B
Expectation from Utility
� Formation of a high level steering committee to monitor the implementation of
IT project
� Formation of a dedicated core team taking nomination from each department
who are involved in business process automation including IT department
� Proper planning and administrative restructuring for migration to new IT based
business environment
� Study of business process and realigning the same to make it IT worthy with the
What is R-APDRP
8
� Study of business process and realigning the same to make it IT worthy with the
help of ITC. Utility shall help ITC to customize G2 section as per the realigned
business process of the utility
� Creation of Basic infrastructure for datacenter and customer care center viz.
building, precision air conditioning, fire fighting system, access control system,
main & standby power supply etc.
� Decision on whether to scrap or extent of use of its legacy system
� Ensuring DR Center is installed on a different seismic zone from DC
� If required utility can talk to utilities of other states for co hosting DR center
which will reduce the infrastructure and running cost of both utilities
Expectation from Utility
� Timely selection of consultants and Implementing Agencies and placement of
awards
� Ring-fencing of the project Area (Town) through metering of all import/ export
metering points and segregation of agriculture feeders
� Installation of new meters for Feeder, Distribution transformer (The new Indian
standard based on IEC 62056 open protocol, is issued by BIS).
� The detail information on protocols and memory map etc. of existing AMR
What is R-APDRP
9
� The detail information on protocols and memory map etc. of existing AMR
compatible system meters to be collected from respective meter suppliers. All
meter manufacturers who are members of IEEMA have agreed to provide the
same to utilities
� Availability of energy sales records and related data for verification of initial
Baseline Data of project area by TPIEA
� Planning for Capacity building of existing employees for working in IT based
environment
� Regularly enter & update data on APDRP’s dedicated web site maintained by
PFC
� Submission of Project area DPRs for implementation of APDRP Part-B
Components of R-APDRP
Projects under the R-APDRP program shall be taken up in Two Parts.
Part A
� Consumer Indexing, Asset Mapping
� GIS Mapping of the entire distribution network
� Automatic Meter Reading (AMR) on DT & Feeders
What is R-APDRP
10
� Automatic Meter Reading (AMR) on DT & Feeders
� Automatic Data Logging for all Distribution Transformers and Feeders
� SCADA/DMS in big towns / cities (with population > 4 lakh & energy input > 350 MU)
� Feeder Segregation / Ring Fencing
� Establishment of IT enabled customer service centres
Components of R-APDRP
Projects under the R-APDRP program shall be taken up in Two Parts.
Part B
� Renovation, modernization and strengthening of 11 kV substations, transformers
and transformer centres
� Re-conductoring of lines at 11 kV level & below
What is R-APDRP
11
� Replacement of electromagnetic meters with tamper proof electronic meters
� Load Bifurcation, Load Balancing
� HVDS (11kV)
� Installation of capacitor banks & mobile service centres etc.
� Aerial Bunched Conductors in populated areas
� Strengthening at 33kV or 66kV levels
R-APDRP funding (Out of scope)
� Land, Building (Civil, architectural, electrical & miscellaneous work) for DC,
DRC & CCC
� Air conditioning system
� Special electronic earthing for server system
� Fire fighting system
� Access control
� Main & standby power supply
What is R-APDRP
12
� Main & standby power supply
� Close Circuit TV
� Contract for outsourcing of IT related activities being taken up (AMC etc.)
� Departmental overhead expenses
� Manpower cost for managing collection centres, DC & CCC
� FMS charges allowed only remaining duration of the scheme after
successful completion of the project
R-APDRP rollout structure
What is R-APDRP
13Source: Power Finance Corporation
R-APDRP roles
Roll of various agencies
14Source: Power Finance Corporation
DISCOMs to facilitate the entire transformation process
RAPDRP In a nutshell
Business Challenges/Risks
• AT&C losses
• Visibility into processes and systems
• Operational efficiency
• Aging work force and assets
• Delay in customer services
• Manual controls leading to errors & delays
IT system:
• Minimal IT system
Current State
• Establish baseline AT&C losses to identify and rectify problem areas
• Automated business processes
• Transparency and visibility within the organization
• Improved operational efficiency and customer satisfaction
• Centralized data repositories and processing centers
• Minimum human intervention leading to elimination of errors
Future State
DISCOMsDISCOMs ITCITC
ITIAITIA
R-APDRP
15
• As-is study • Assistance in DPR and RFP
preparation• Appointment of ITIA and Programme
management Benefits • High level understanding of BESCOM
needs• Holistic approach towards the
program
ITC
ITIA
MPMKVVCL (Nodal Agency), MPPKVVCL, Indore & MPPKVVCL, Jabalpur
Phase I
IT Consulting
Phase II Phase III
IT Implementation Facility Management
• End to end implementation• Supply installation and
commissioning• Roll out
Benefits • Automated and Standardized
business processes.• Establishment of baseline data
• Manage entire IT system
Benefits • Hand holding support in resolving
technical issues• Centralized user support• Provide ESCOM time & platform to
build capabilities
MoP, PFC
Modules of RAPDRP
Other Modules
Disconnection/Dismantling
Network Analysis
MIS
Identity & Access Management
System Security Requirement
Maintenance Management
Key Field Activities
Master
ActivityActivities
GISGIS Survey for Assets
Consumer IndexingConsumer Indexing
MDASModem Installation
SIM Installation
InfrastructureInfrastructure Setup at Sub -
Division & Other offices
Application Modules
� All the modules are from the Oracle Utilities
Product Suite except :
� MDAS - Movicon
� GIS - ESRI
� Network Analysis - Mipower (PRDC)
� System Security Requirement - HP
Application Modules
Sl. No Function TCS Solution stack
1 New Connection Oracle Utilities CC&B
2 Disconnection & Dismantling Oracle Utilities CC&B
3 Metering Oracle Utilities CC&B
4 Billing Oracle Utilities CC&B
5 Collection Oracle Utilities CC&B
6 GIS - Customer Indexing and Asset ESRI Arc GIS6 GIS - Customer Indexing and Asset
Mapping + Field Survey
ESRI Arc GIS
7 GIS - Network Analysis and
Management
ESRI Arc FM and MiPower
8 Meter Data Acquisition System -
AMR Infrastructure
Voila, Finland
9 Meter Data Acquisition System –
Software
Movicon
10 Web Self Service Oracle Utilities CC&B,
WebLogic Portal
Application Modules
11 MIS
Oracle Utilities Business Intelligence,
Oracle Business Intelligence Publisher
Oracle Database
12 Asset Management Oracle Utilities CC&B
13 Maintenance Management Oracle Utilities CC&B
14 Portal Solution Oracle Web-logic Portal
15Business Intelligence/Data
Analytics
Oracle Utilities BI,
Oracle BI Publisher,
Oracle Data Integrator,15
Analytics Oracle Data Integrator,
Oracle Database
16 IT Helpdesk HP Service Manager
17Identity and Access
Management
Oracle Access Manager,
Oracle Directory Services,
Oracle Identity Manager
18Document Management
SystemOracle Universal Content Management
(part of Oracle Fusion Middleware platform)19 Workflow and BPM Tool Oracle SOA Suite20 Mail / Messaging Software Microsoft Exchange Solution
Application Modules
21 Network Service Provider TTSL/SWAN
22 Hardware (servers and storage) HP
23 Hardware (desktops) HP
24Network and communications -
hardware (routers, etc)
CISCO
25 Database Management System ORACLE
26
System Security Software HP Network Node Manager,
HP Operations Manager
Database SPI for HP Operations
Manager
HP OpenView Performance Insight
27Centralized Customer Care
Services
CISCO UCCE,
Oracle Utilities CC&B
Web Self Service
WSS will give relevant information on discoms policy, regulatory affairs, new schemes,
bill views, bill payment, bill calculator etc.The goal is to provide a high quality
experience for the customers and business associates that will provide them a user
friendly portal that will make it easy for them to communicate with the utility though
the web instead of direct phone calls or visits. This portal will also act as a source of
information for the customers regarding policies and procedures. This in turn will
improve customer satisfaction and reduce work load on the employees.
Meter Data Acquisition System
The main objective is to acquire
meter data from System and
Selected consumer meters
automatically from remote
avoiding any human
intervention, Monitor
important distribution
parameters, use meter data for
accurate billing purposes and
Objective
The system is expected to provide continuous on line
monitoring and logging of essentially, though not limited
to, the following parameters in respect of all incoming and
outgoing feeders, Distribution Transformers and consumers
on real time basis
� Voltage, Phase to Phase and Phase to Neutral
� Current on each phase
� Power factor
� Frequency
Expected benefits
23
accurate billing purposes and
generate exceptions and MIS
reports for proper planning,
monitoring, decision support
and taking corrective actions on
the business activities by the
management.
� Frequency
� Power - Active / reactive / Apparent
� Energy – Active, Reactive and Apparent
The system will provide continuous on line monitoring and
logging of above mentioned parameters & MIS report for
� System outage / downtime feeder wise
� Energy balancing at sub stations
� Daily peak loads feeder / transformer wise
� Peak Load of the Station
� Bus bar profile
� Daily Log sheets & required reports
HT
Consumers
DTs
Modems
Modems
Service
provider
Network
Data Center
Meter Data Acquisition System
LT
Consumers
MPLS
VPN
cloud
ModemsData
Acquisition
System
Substation
DCU
Meter1 Meter2 Meter3 Meter4Meter4
Modem
Meter Data Acquisition System
Modem
25
Meter Data Acquisition System
TCS
- Supply and installation of suitable Modems (GSM/GPRS/EDGE/CDMA/PSTN/LPR)
at DTs, HT and selected LT consumers and DCUs at sub-stations
- Application software for capturing, validating and analyzing the Meter data at sub-
station and data center
DISCOM
- Replacement of meters with RS 485 ports gradually, DLMS protocol wherever
Who is doing what
- Replacement of meters with RS 485 ports gradually, DLMS protocol wherever
necessary
- Sealing de-sealing of meters for modem installation
MDAS : Field Activities
Modems to be installed in all Meters at :
� Sub Stations
� Feeders
� DTRs
• Prepare & Submit the list of all metering points starting
from 11KV Feeders clearly indicating from 11KV Feeders clearly indicating
Metered/Unmetered/AMR
MDAS : Installation Process
Process :
• Provide the list of Metering Points
• Complete the Metering at all unmetered DTRs & Feeders
• TCS to start the Installation of Modems & SIM Card
• Validate the installation
• Check if it is safe & properly done
• If Installation is properly done, DISCOM to provide the sign-off• If Installation is properly done, DISCOM to provide the sign-off
• Extend necessary support to TCS Team during Modem
Installation- Shutdown’s, providing lineman etc
Activities to Verify :
� Verify that Modem is fitted properly inside the Meter box
� Verify that Modem is properly sealed after installing the SIM
� Verify that holes (for external Antenna) are properly sealed
Energy Audit
Monitor important distribution
parameters, capture hierarchical
view of energy accounting, Network
assets, intelligent analysis tools for
plugging loop holes and identifying
revenue leakage, adding into
perform network planning and
management activities, calculate /
Objective
- Automatic collection of energy flow data from
metering module
- Online graphical network diagram and network
reconfiguration
- Calculation of Bus bar and transformation losses
in the sub station
- Calculation of HT losses
- Calculation of LT losses
Expected benefits
management activities, calculate /
identify technical and commercial
losses at any point in the network.
- Calculation of LT losses
- Calculation of estimated technical and
commercial losses in the system
- Generation of report of energy accounting and
graphical analysis
- Monitor important distribution parameters, capture hierarchical view of
energy accounting, Network assets of power distribution utilities, intelligent
analysis tools for plugging loop holes and identifying revenue leakage, adding
into perform network planning and management activities, calculate / identify
technical and commercial losses at any point in the network.
The GIS system to enable users to map
the assets of the whole Discom with
all the attributes with child parent
relationship. It also provides various
activities like access interactive maps,
perform network analysis, various
Electric Utility analysis etc.
The aim of the system is to automate
Objective
- Online availability of whole network and assets
(graphical view) of DISCOM
- Unique no. Allocation to each asset
- Various details of network and connected
consumers can be accessed instantly
- Help in identifying location of the consumer
from unique pole id
- Network Management - Online Creation of new
Expected benefits
GIS based customer indexing & Asset mapping
The aim of the system is to automate
the existing processes of DISCOMs
which will help in better management
of the electricity distribution in their
respective areas. The improvement in
distribution system will further lead to
customer satisfaction and financial
benefits.
- Network Management - Online Creation of new
network, opening of exiting network, Merging of
two networks, delete network
- Online tracking of different changes in network
GIS implementation
The various states of implementation of GIS
A. Procurement of the images from ESRI
B. Capturing the part of the image and geo referencing the
same using base station and rovers stations
C. Downloading the part of the image pertaining to the area of
interest in DGPS instrumentinterest in DGPS instrument
D. Marking the various layers in the DGPS instrument
E. Uploading the image from the DGPS instrument into the
computer system for analysis
GIS Survey
The process of GIS Survey is:
1. TCS will do the survey
2. TCS will submit the data Feeder/DTR wise
3. DISCOM to acknowledge the receipt of data
4. DISCOM to validate the data and correct the errors in the data
5. If required, TCS to do re-survey and correct the required data
6. TCS to re-submit the data
7. If data is OK, DISCOM to provide the sign-off
8. Update Data after survey till Implementation
Field Activities for Assets Survey
Asset Verification :
• Verify that type of asset mentioned is correct as on field (like
Type of Pole, Type of Conductor etc.)
• Verify that count of asset is proper (No. of Conductors etc.)
• Verify that various values specific to asset are correct (KVA
rating of Transformer, Make of Transformer, etc.)
Survey of 33/11KV Line :
Submission & Validation will be Feeder Wise
Consumer Indexing :
Submission & Validation will be DTR Wise
Field Activities for Consumer Indexing
• Verify the Contact Details of the Consumer (Name, Address,
Contact No. etc.) – there shouldn't be any spelling mistake
• Verify that Meter No. and the Make of the Meter is correct.
• Verify other details like Left/Right Consumers & Phase
Perform several types of analyses on
balanced or unbalanced three-phase,
two phase and single-phase systems
that are operated in radial, looped,
meshed or mixed configurations.
Create "what-if" studies and
performing simulations to evaluate the
impact of modifications to existing
network.
Objective
- Online Creation and editing of network,
- Online Load flow and voltage drop analysis,
- Optimization studies like capacitor placement,
network reconfiguration, conductor up-gradation,
express feeder, load balancing and load allocation
etc.
- Online Creating extensive “what-if” studies.
- Fault analysis and protection coordination,
- Network design reports, cost estimates, financial
Expected benefits
GIS based Integrated Network Analysis
35
network. - Network design reports, cost estimates, financial
analysis,
- Integration with New connection module for
checking the network capability, augmentation
requirement, if any
- Can generate Single Line Diagrams (SLD) based on
GIS Surveyed Data of Electric Lines and various
equipments and it thus enables HT/ LT network
analysis of the system. The SLD depicts the
location of pole, transformer, distance between
poles and other network features.
The Commercial Database of Consumer is
to be developed by integrating Billing
Database available with Discom and the GIS
based consumer and asset data base
developed / being developed by TCS. The
system to be developed and installed shall
be capable of accepting the data which will
Objective
- Online availability of consumer data
- Online tracking of consumer details
Expected benefits
Commercial database of consumers
be capable of accepting the data which will
be made available and capable of
appending any necessary attribute etc. and
performing the entire intended task. After
the first installation, the database shall be
updated online and taken into the system
for routine functioning
The commercial data base development shall cover the following activities –
Development of master file of consumer comprising of consumer’s details including
Energy meter history, meter reading, energy consumption, assessment, payments and
other relevant data from the initial record and other relevant records to be provided byUtility.
New Connection
The system’s aim is to enhance the
convenience of the customer, when an
application for new connection is
received. It would enable the
customer to collect and submit
applications through a host of delivery
channels, allow application status
tracking etc. The system would help
reduce the time taken for the new
Objective
- Mode of application for the customer will be
� Through web
� By personal visit
- Minimized manual intervention
- Online feasibility study can be done. Estimates
can be prepared online
- Online approvals and automatic priority
settings
Expected benefits
37
reduce the time taken for the new
connection process. The system would
enable updating customer data to be
captured in the GIS based customer
indexing database in a reliable way.
The data entered at this stage would
form the basis of the customer's
record in the system. The system
would ensure, through validation and
checks, that the integrity of this data is
maintained.
settings
- Integration between New Connection and
billing
- On Line Application status tracking through
different channels
- Integration with GIS and Electrical Network
Analysis for consumer indexing
- Online of all the connection related processes
such as Temporary Connection, Load
Extension/Reduction, Name Change and Meter
Shifting, Reconnection etc.
Metering
Metering: An Effective meter
reading system would enhance
the effectiveness of the
measurement process. This
would include accurate metering
for all customers and tapping
revenue loss through the
identification and handing of
Objective
- Automatic collection of meter data where
modems are installed
- Interfacing with Spot billing devices and
MRI data for uploading such meter readings
including consumer meter readings
- Meter reading plan generation
- Monitoring meter reading plan
- Monitoring Customer exception
Expected benefits
identification and handing of
exceptions.
- Monitoring Customer exception
- Automatic Overdue alerts
An Effective meter reading system would enhance the effectiveness of
the measurement process. This would include accurate metering for all
customers and tapping revenue loss through the identification and
handing of exceptions.
TCS
- Development and implementation of Customized application software
- Data migration
- Consumer indexing
DISCOM
- Other than the meters where modems are installed, Meter reading will be the
responsibility of Discom whether it is spot billing or manual reading
Who is doing what
Metering
responsibility of Discom whether it is spot billing or manual reading
Billing
A comprehensive billing system
will ensure that the utility
efficiently bill their customers
for the services rendered. It
will support the continuous
billing to reduce the
outstanding. Will ensure the
timely and accurate billing. The
system will support the
Objective
- This system should broadly cover functions relating
to generation, printing and issue of bills to the
consumers
- Bills will be available on internet.
- SMS alerts will be given to customer regarding bills
- Bills will be generated at sub-division level
- Tracking of reasons for deviations from normal
billing, billing logic flexibility etc.
- Linking customer with appropriate tariff
Expected benefits
40
system will support the
complaints handling
functionally by providing short
turnaround times for billing
related customer queries.
- Linking customer with appropriate tariff
- Bill correction and amendments can be done online
based on the approvals provided in the system
- Flexibility of change in billing cycle
- Creation of monthly ledger
- Final Bill Reconciliation
- Monthly report generation
- Bill distribution route plan generation
- Integration and flexibility of using Spot billing
machines (Downloading, uploading of data, billing
login in m/c etc
TCS
- Development and implementation of Customized application software
- Data migration
- Consumer indexing
DISCOM
- Bill distribution and meter reading will be done by Discom
Who is doing what
Billing
Collection
The system should provide
different payment and
information channels to
customers and own staff to
improve customer
convenience for payments and
enable collections for the
energy billed, and a shorter
metering-bill billing-
Objective
- Decentralized payment processing & centralized
reconciliation
- Customer will be able to pay bills through
internet, collection center at sub-division, cash
collection kiosk located at major cities, through
third party like eMitra etc.
- System will be able to receive the payment
through Cash/ Cheque/ Bank Draft/ Credit Cards/
Debit Cards/ Internet Payment Gateway.
Expected benefits
metering-bill billing-
collections (MBC) trade Cycle
Debit Cards/ Internet Payment Gateway.
- Daily reconciliation of cash and bank
- Acceptance of part/ advance payment
- Generation of reminders/disconnection notice
- Track of cancelled receipt
- Finance & Accounting
The system should provide different payment and information channels to customers and own
staff to improve customer convenience for payments and enable collections for the energy
billed, and a shorter metering-bill billing-collections (MBC) trade cycle
TCS
- Development and implementation of Customized application software
- Data migration
DISCOM
- Third party tie-up for cash collection
Who is doing what
Collection
Customer care services
The system should
improve the customer
service by processing
and resolving customer
requests / queries /
complaints in minimum
possible time by taking
up it at appropriate
place and level.
Objective
- Single window of computerized customer care center
- Complaints will be received by Customer care and will be
processed/passed to respective officer are
� Voltage related
� Supply Failure related
� Transformer related
� Line related
� Pole related
� Services connection related
Expected benefits
44
place and level.� Services connection related
� Billing related
� Meter related
� New connection
� Disconnection / not in use
� Attribute Changes i.e. location, name, floor, load etc
- The various other services in addition to technical complaints
as mentioned above also will be extended by the customer
care center to the customer of DISCOM are
� Customer Information
� New Services Connection
� Handle Metering & Billing related and other Complaints
� Handle Service Request etc..
Customer care services
- The complaints can be lodged for the consumer belonging to any sub-division
- The Customer care centre will be linked through mobile SMS in a “closed user
group” to breakdown staff / mobile maintenance vans. Immediately upon receipt
of a no-supply complaint, an SMS will be sent by CC centre to the breakdown
staff/van for fault restoration. After restoration of the fault, the breakdown staff
will close the complaint at the CC centre.
- The Customer Care Service is integrated with the CRM, Billing and GIS applications
- The customer care executive will be able identify the fault instantly using the
Expected benefits
- The customer care executive will be able identify the fault instantly using the
above application and inform the customer accordingly
Asset Management
Accounting and maintaining
the vast fixed asset base
efficiently. The system will
have the following features:
a. Easy data migration from
legacy
b. Easy to update asset
Objective
- Life cycle analysis
- Manage various depreciation policies
- Manage the budgets for assets
- Manage extensive reporting using built-in
reporting tools and business analytics
- Manage the compliance related to
process/statutory requirements
Expected benefits
b. Easy to update asset
data as asset base grows
dynamically
c. Easy to integrate with
other applications for
accurate data exchange
e.g. GIS, Maintenance
etc.
d. Scalable for growing
requirements of utilities
Maintenance Management System
Better planning and co-
ordination of various
maintenance activities,
reduce breakdowns by
inculcating the culture of
preventive and predictive
maintenance, to maintain
maintenance history, to
review and control
Objective
Activities can be performed
- Multi-levels tracking of assets, equipments, machines,
machine parts, crews and tools.
- Detailed equipments and assets history
- Planned Maintenance Schedules
- Opportunity Maintenance
- Work order scheduling and work flow process
- Automatic alerts and email notifications to crews and
Expected benefits
review and control
maintenance costs and
providing a feedback to
management for timely
decision making.
- Automatic alerts and email notifications to crews and
managers
- Corrective Repairs & Maintenance
- Breakdown Maintenance
- Maintenance costs: Actual vs Budgeted costs tracking
- Resources allocation and crews management
- Condition Monitoring/Predictive Maintenance
- Shutdown/Turnaround Maintenance
Maintenance Management System
Benefits
- Reduce asset maintenance and operating cost
- Properly maintained machines minimizes downtime
- Production cost decreases
- Continuous improvement in commonly performed work.
- Improved equipment life
- Enhanced equipment availability and reliability
- Improved employee work efficiency
Expected benefits
- Improved employee work efficiency
- Consistent operation of machinery improves product quality
- Improve reporting and analysis capabilities.
- Comply with Health and Safety Regulations.
- Improve Business Planning and make informed decisions.
- Improve operational efficiencies.
- Increase productivity and profitability.
- Improve strategic and business planning; Analyze records, needs and
patterns.
- Identify trends and highlight potential problem
Generation of MIS Reports
� All the work being carried out by the O&M officers under this
project will be through computer system and therefore each
and each and every activity will be available in the Data Center.
� All the reports required by the Discom will be generated by the
software using DATA available at Data Center at Jaipursoftware using DATA available at Data Center at Jaipur
� There will be no body to ask information to related to MIS and
therefore no body have to provide the information.
� The O&M officers will be able to devote sufficient time for
data analysis and take the corrective measures in time.
Mail/Messaging Server(To-Be)
Section Officer
Check Availability
of material
Response
Store
CC
CC
To
Sub-Division
Officer
Executive
Engineer
Indent Approval Request
Approved
ToCC
CC
Approved
Approved
CCCC
To
Approved
ApprovedApproved5
4
3
2
1
Material Delivery
Key Benefits
•Reduced transaction time
•Quicker approval processes
•Defined standardized mailing process
Identity and Access management
� Identity management for user provisioning should have
out of the box workflow for automating approvals for
user access management, self registration and self-care
functionality for reducing the administrative load and
manual intervention.
� Sensitive customers' data must be protected in� Sensitive customers' data must be protected in
accordance with guidelines that will be agreed with the
Purchaser.
� The system shall have ability to report on roles, rights
associated with roles and users associated with roles.
System security requirement
� The system must be capable of generating log trails,
which contain details about any read / write access to
sensitive data. Details must relate activity to an
identifiable person.
� The system should be able to protect the user process� The system should be able to protect the user process
and local data from other user.
� The system should have the flexibility of encrypting the
data stored online.
Infrastructure Setup at SDOs & Other Offices
Process :
� Fix water leakages & cracks on the walls
� Complete the wiring & earthing
� Provide space to TCS to store the material
� TCS to move the Hardware to specific location� TCS to move the Hardware to specific location
� TCS Teams will visit the location and Install the
Furniture & Equipments
Infrastructure Setup at SDOs & Other Offices
List of Equipments to be installed:
� Personal Computers with UPS, Table & Chair
� Routers
� Switches
� IP Phone� IP Phone
� Bar Code reader
� DMP/Network/Inkjet/Line Matrix Printers
� UPS (2/5) KVA
� Touch Screen Kiosk
� Collection Kiosk
Thank YouThank You