Moving House: The New MTO Central Region COMPASS Traffic … ITS Canada TOC - May 28.pdf ·...

15
Moving House: The New MTO Central Region COMPASS Traffic Operations Centre Presentation to ITS Canada AGM May 26-29, 2013 May 2013 ITS Canada AGM Toronto, ON Lija Whittaker, P. Eng., Project Engineer, MTO ITS Section Anna Dybka, P. Eng., Associate, IBI Group

Transcript of Moving House: The New MTO Central Region COMPASS Traffic … ITS Canada TOC - May 28.pdf ·...

Moving House: The New MTO Central

Region COMPASS Traffic Operations Centre

Presentation to ITS Canada AGM

May 26-29, 2013

May 2013ITS Canada AGM

Toronto, ON

Lija Whittaker, P. Eng., Project Engineer, MTO ITS Section

Anna Dybka, P. Eng., Associate, IBI Group

Existing GTA TOCs

Toronto

May 2013ITS Canada AGM2

BurlingtonToronto

Why New Toronto TOC?

• Both Central Region TOCs are aging and requiring reinvestment– Downsview TOC is 23 years old

– Burlington TOC is 21 years old

• Was temporarily located in modular building

• Lease agreement for use of Joseph Brant hospital site has expired

• Opportunity to streamline operations by consolidating

• New TOC provides opportunity to expand for future

May 2013ITS Canada AGM

• New TOC provides opportunity to expand for future needs and further consolidate centres province-wide

• Coordinate and integrate emergency and special events transportation management

• Provide Unified Transportation Coordination Centre (UTCC) for PanAm Games

Arrow Road TOC Perspective – NE ViewDesign by Kasian/MSA Architects

May 2013ITS Canada AGM

Arrow Road TOC Floor Plans – Ground Floor

May 2013ITS Canada AGM

Ground Floor

Arrow Road TOC Floor Plans – Second Floor

May 2013ITS Canada AGM

Design Process for ITS

May 2013ITS Canada AGM

Design and Procurement Strategy

Outside Communications and TOC Network

Scope:

Outside Plant Communications

Reconfiguration around new physical location

Cut-over utilizing new Ethernet 10G backbone for successive

transition of network sections to support business continuity

TOC Internal Network

New design to reflect the current industry trends – Layer 3

May 2013ITS Canada AGM

New design to reflect the current industry trends – Layer 3

Core, Layer 2 Access

Modern architecture to increase network availability, buit-in

switch redundancy

Efficient connections for external Interfaces/services

Firewall

Method: Tender

Design and Procurement Strategy

IT Systems

Scope:

Workstations

Services

Relocation of voice logger and radio equipment

May 2013ITS Canada AGM

Method: Vendors of Record

Design and Procurement Strategy

Video Systems

Scope:

Video Wall – 3x8 70” cubes

New design for current and future needs

Built for easy future expansion

Video Management System

All digital solution

Efficient storage and sharing with

external subscribers

May 2013ITS Canada AGM

external subscribers

Integrated with the network

A/V Equipment

Design for access to video in key rooms

Provide in room displays throughout the facility

Method: Request for Proposal

Design and Procurement Strategy

Operator Consoles

Scope:

Sit/Stand Design

Monitor Arms

Flexible; articulated

CPU and Cable Management

Non-obstructing; flexible; accessible

Task Lighting

May 2013ITS Canada AGM

Task Lighting

Extra Storage

Binders; files

Method: Request for Proposal

Procurement Strategy

Equipment Room

Equipment Room Racks

Supplied under building tender

Coordinated with electrical and HVAC

Cable tray and conduit access

Conduit

Outside plant dual access

Utility access

May 2013ITS Canada AGM

Utility access

Internal conduits for A/V

Wiring

LAN and telephony

Cost Savings

Eliminate raised floor, aids seismic performance

Method: Included in Building Tender

Schedule

Design CompletionJuly to September 2013

AdvertiseSeptember to December 2013

Contract AwardsRFPs Fall 2013

Design CompletionJuly to September 2013

AdvertiseSeptember to December 2013

Contract AwardsRFPs Fall 2013

Work CompletionBuilding -April 30/Aug 31, 2014

Network – January to

September 2015

Video System – April to Aug,

2014

Consoles – Aug-Sept, 2014

Schedule

May 2013ITS Canada AGM

RFPs Fall 2013

Tender January 2014

VoR Procurement March 2014

March 2014

RFPs Fall 2013

Tender January 2014

VoR Procurement March 2014

March 2014

Consoles – Aug-Sept, 2014

IT – September, 2014

Integration –Oct – Dec, 2014

Trial Operations – January 2015

Initiation of Operations –

February 2015

Lessons Learned to Date

• Future-proofing – need to go back to first principles

and look and roles/responsibilities; forecast future

growth and technology trends, design for flexibility to

link/coordinate with other agencies or expand

• Coordination – planned for and undertook extensive

coordination with architect and building systems

team, and internally among various streams of design

May 2013ITS Canada AGM

team, and internally among various streams of design

• Scope Management – re-architecting of the

communications systems around the new centre vs.

rebuilding to follow the new technology and trends

• Risk Management - building new TOC allows to risk

manage continuity of operations

Thank You