Eglinton-Scarborough Crosstown (ESC) Light Rail Transit
December 12, 2012 – Public Meeting
Environmental Assessment and
Mobility Hub Update:
Mount Dennis Area
![Page 2: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/2.jpg)
2
Objectives
• Provide overview of ongoing studies for Eglinton Scarborough
Crosstown
• Environmental Assessment Update (West)
• Review updates to concept design for LRT facilities
• Get public input on the updated concept, potential impacts and
mitigations
• Mobility Hub Study
• Place new transit in context of wider neighbourhood
• Present existing conditions and opportunities
• Get public input on opportunities and design directions
![Page 3: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/3.jpg)
3
was created in 2006 for the
purpose of providing residents and
businesses in the Greater Toronto
and Hamilton Area (GTHA) a
transportation system that is
modern, efficient and integrated.
![Page 4: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/4.jpg)
4
Metrolinx LRT Projects in Toronto
![Page 5: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/5.jpg)
5
Eglinton-Scarborough Crosstown
• Project $4.9 B (2010$), funded by the Province of Ontario
• 19 kilometres east-west LRT from Kennedy to Mt. Dennis,
including 10 kilometres of tunnel
• New Transit Connections to Yonge, University-Spadina
Subway, Scarborough RT and GO Stouffville
• Up to 26 stations
![Page 6: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/6.jpg)
6
Project Schedule
• Delivered using Public Private Partnership and
Alternative Financing + Procurement (AFP)
![Page 7: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/7.jpg)
7
Project Schedule
![Page 8: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/8.jpg)
8
What is a Mobility Hub?
51 mobility hubs identified in The Big Move
Mobility hubs are major transit station areas within the GTHA
that are particularly significant given the level of transit service
planned for them and the development potential around them.
![Page 9: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/9.jpg)
9 Mount Dennis is a hub in the growing regional transit system
Terminal station of
Phase 1 of the new
Eglinton Crosstown
LRT line
![Page 10: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/10.jpg)
10 Mount Dennis is a hub in the growing regional transit system
Future GO Transit
connection
![Page 11: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/11.jpg)
11 Mount Dennis is a hub in the growing regional transit system
New and existing
bus routes
connecting through
Mount Dennis
![Page 12: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/12.jpg)
12
Mt. Dennis Mobility Hub Study Objectives
• A fully integrated transit station to
facilitate transfers between rail and bus
services, and the surrounding area
• Re-purposing the Kodak building
• Improvements to the public realm
including streetscaping
• Enhanced pedestrian/cyclist connectivity
• Potential uses of lands adjacent to
Metrolinx property for transit oriented
development
• Phasing of implementation of the mobility
hub components
![Page 13: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/13.jpg)
13
How will the Mobility Hub Study be
Implemented?
• Metrolinx will:
• Incorporate recommendations into the concepts for LRT
facilities and stations
• Work with the City of Toronto to support zoning updates
to reflect study recommendations
• Work with the City of Toronto to prioritize infrastructure
and public realm improvements recommended
![Page 14: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/14.jpg)
14 DRAFT
What are the key elements of the new public transit?
![Page 15: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/15.jpg)
15 DRAFT
A new LRT station with two entrances
![Page 16: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/16.jpg)
16 DRAFT
A new transit overpass over Black Creek Drive
![Page 17: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/17.jpg)
17 DRAFT
A new bus facility
![Page 18: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/18.jpg)
18
A maintenance and storage facility (MSF)
![Page 19: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/19.jpg)
19
Future GO Transit connection
![Page 20: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/20.jpg)
20
A passenger pick-up
and drop-off area
![Page 21: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/21.jpg)
21 DRAFT
The Mobility Hub Study is focusing on five areas
![Page 22: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/22.jpg)
22
4. Eglinton Ave and
Black Creek Dr Triangle
1. Kodak Lands
5. Black Creek Business Area
![Page 23: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/23.jpg)
23
• Former Kodak land
• Site of Kodak Building No. 9
• Large contaminated site to the east of the rail corridor
• Station area includes Keelesdale Drive
1 Kodak Lands
![Page 24: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/24.jpg)
24
1 What is it today?
Kodak Lands
•Vacant
• Isolated from Mount
Dennis by the rail
corridor
![Page 25: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/25.jpg)
25
What is it today?
Kodak Lands
•Contaminated from
former industrial uses
1
![Page 26: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/26.jpg)
26
What is it today?
Kodak Lands
•Separated from
Eglinton by significant
grade changes
•Site of Kodak
Building No. 9
1
![Page 27: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/27.jpg)
27
What is it today?
Kodak Lands
•Site of Kodak
Building No. 9
1
![Page 28: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/28.jpg)
28
What are the opportunities?
Maintenance and
storage facility (MSF)
New station with two
entrances
Bus
facility
Potential new street or
pedestrian link
Realigned retaining wall
Expanded park land
Kodak Lands
Future GO Rail platforms
Passenger pick-up and
drop-off
1
![Page 29: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/29.jpg)
29
4 Mount Dennis Station What are the opportunities?
Re-purposing the Kodak
Building as the station
![Page 30: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/30.jpg)
30
4 Mount Dennis Station What are the opportunities?
Connecting from the station
down to Eglinton Avenue
![Page 31: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/31.jpg)
31
4 Mount Dennis Station What are the opportunities?
Setting back the retaining wall and
creating a new green wall and more
generous sidewalk
![Page 32: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/32.jpg)
32
4 Mount Dennis Station What are the opportunities?
Incorporating artwork to enliven the
street
![Page 33: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/33.jpg)
33
4 Mount Dennis Station What are the opportunities?
A more animated structure that
celebrates the activity of the station
![Page 34: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/34.jpg)
34
4 Mount Dennis Station What are the opportunities?
A more animated structure that
celebrates the activity of the station
![Page 35: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/35.jpg)
35
Key Plan 4 Mount Dennis Station
What are the opportunities? Creating a light and airy LRT
overpass
![Page 36: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/36.jpg)
36
4 Mount Dennis Station What are the opportunities?
Designing the overpass as an
interesting feature with
opportunities for public art
![Page 37: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/37.jpg)
37
4 Mount Dennis Station What are the opportunities?
Extending the parks west of
Black Creek
![Page 38: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/38.jpg)
38
4 Mount Dennis Station What are the opportunities?
Preserving for a new complete
street to Industry Street and Black
Creek drive…
![Page 39: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/39.jpg)
39
4 Mount Dennis Station What are the opportunities?
… or possibly a pedestrian and
cycling only connection
![Page 40: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/40.jpg)
40
• Primary east-west link through the neighbourhood
• Location of the future station
• Designated an “Avenue” in the Official Plan
• Connects the major parks at Black Creek and Humber
• Important cycling connection
Eglinton Corridor 2
![Page 41: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/41.jpg)
41
Key Plan
Eglinton Corridor What is it today?
• Fast moving street
• Lacking sidewalks in
locations
•No cycling facilities
2
![Page 42: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/42.jpg)
42
Key Plan
Eglinton Corridor What is it today?
•Busy street
•Major intersections
are unfriendly to
pedestrians
2
![Page 43: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/43.jpg)
43
Key Plan
Eglinton Corridor What is it today?
•Narrow sidewalks
•Poor pedestrian
environment
•No active (retail or
residential) uses
• Limited streetscaping
and no street trees
between Weston
Road and Black
Creek
2
![Page 44: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/44.jpg)
44
Key Plan
Eglinton Corridor What is it today?
•Six lanes of car traffic
•No active (retail or
residential) uses
• Limited streetscaping
and no street trees
between Weston
Road and Black
Creek
2
![Page 45: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/45.jpg)
45
Key Plan
Eglinton Corridor What is it today?
• Large intersection
with long crossing
distances
•Extension of
Keelesdale park’s
green edge
•New community
centre
2
![Page 46: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/46.jpg)
46
Eglinton Corridor What are the opportunities?
Cycling connections
Streetscape improvements
Enhanced pedestrian crossings
Widening the public realm
New green connections
Future York
Community Centre
2
![Page 47: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/47.jpg)
47
1 Enhancing pedestrian crossings Eglinton Corridor What are the opportunities?
![Page 48: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/48.jpg)
48
1 Creating a 4-lane street to provide a more
generous pedestrian environment
Eglinton Corridor What are the opportunities?
![Page 49: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/49.jpg)
49
1 Extending the Eglinton multi-use path east of
Weston Road to link the Humber River Trail
with the Community Centre and Beyond
Eglinton Corridor What are the opportunities?
![Page 50: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/50.jpg)
50
1 Adding new street trees, furniture and
pedestrian lighting
Eglinton Corridor What are the opportunities?
![Page 51: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/51.jpg)
51
1 Extending the park-like setting Eglinton Corridor What are the opportunities?
![Page 52: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/52.jpg)
52
• Neighbourhood main street
• Primary north-south route through the neighbourhood
• Designated an “Avenue” in the Official Plan
• Location of many of the community uses (churches, social services)
Weston Road 3
![Page 53: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/53.jpg)
53
Weston Road What is it today?
•Smaller sites and a
fine grain of low-rise
buildings
3
![Page 54: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/54.jpg)
54
Weston Road What is it today?
•Narrow sidewalks
• Inconsistent
streetscaping
•On-street parking
•Vacant storefronts
3
![Page 55: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/55.jpg)
55
Weston Road What is it today?
•Storefronts being
converted into new
residential
3
![Page 56: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/56.jpg)
56
Weston Road What is it today?
•New station entrance
3
![Page 57: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/57.jpg)
57
Weston Road What are the opportunities?
Streetscape improvements
Enhanced pedestrian crossings Possible future development sites
Entrance to the future station
3
![Page 58: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/58.jpg)
58
Developing a new station plaza at Eglinton
and Weston Road
![Page 59: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/59.jpg)
59
Landscaping the plaza to add some green
relief to Weston Road and extend the park
like setting along Eglinton
![Page 60: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/60.jpg)
60
Locating smaller retail and community uses
adjacent to the station plaza
![Page 61: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/61.jpg)
61
Filling vacant stores and refreshing the retail
presence
![Page 62: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/62.jpg)
62
Encouraging a range of redevelopment
opportunities
![Page 63: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/63.jpg)
63
Encouraging a range of redevelopment
opportunities
![Page 64: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/64.jpg)
64
Preserving for active uses at street level
![Page 65: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/65.jpg)
65
• Large retail site
• Partially owned by the City of Toronto
• Primary neighbourhood food store
• Faces onto an “Avenue” and has permissions for increased density
• Adjacent to future community centre
• One of the largest potential areas for redevelopment along Eglinton
Eglinton Ave and Black Creek Dr Triangle 4
![Page 66: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/66.jpg)
66
•Existing grocery store
• Large areas of
surface parking
What is it today?
Eglinton Ave and Black Creek Dr Triangle 4
![Page 67: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/67.jpg)
67
•Photography Drive is
the only road
connection to the
station
What is it today?
Eglinton Ave and Black Creek Dr Triangle 4
![Page 68: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/68.jpg)
68
•High profile site
• The only big site
suitable for large-
scale development
•City owned parcel
What is it today?
Eglinton Ave and Black Creek Dr Triangle 4
![Page 69: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/69.jpg)
69
• Large unfriendly
pedestrian crossing
• Faces the new
community centre
What is it today?
Eglinton Ave and Black Creek Dr Triangle 4
![Page 70: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/70.jpg)
70
Key Plan
What are the opportunities?
Eglinton Ave and Black Creek Dr Triangle
New station with two
entrances
Potential
development
site
Future York
Community
Centre
Street and public realm
enhancements
4
![Page 71: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/71.jpg)
71
Key Plan
5 No Frills What are the opportunities?
Providing a greater mix of
uses integrated vertically
![Page 72: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/72.jpg)
72
Key Plan
Relating to the new York
Community Centre
![Page 73: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/73.jpg)
73
Key Plan
Orienting buildings to face the
park and community centre
![Page 74: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/74.jpg)
74
• Primary employment zone within the Mount Dennis Community
• Healthy employment area
• Contains a range of businesses from small office to larger warehouse
Black Creek Business Area 5
![Page 75: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/75.jpg)
75
• Industrial area in
transition to service
retail
• Few employee
services (restaurants,
etc.)
What is it today?
Black Creek Business Area 5
![Page 76: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/76.jpg)
76
•Predominantly car-
oriented
• Few/insufficient
sidewalks
What is it today?
Black Creek Business Area 5
![Page 77: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/77.jpg)
77
•Poor waiting areas for
transit users
What is it today?
Black Creek Business Area 5
![Page 78: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/78.jpg)
78
•Poor connections to
the surrounding
neighbourhood make
it feel isolated from its
surroundings
What is it today?
Black Creek Business Area 5
![Page 79: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/79.jpg)
79
Key Plan
What are the opportunities?
Streetscape improvements
Enhanced pedestrian
and cycling connections
New and enhanced
building frontage
Potential new link to transit
Black Creek Business Area 5
![Page 80: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/80.jpg)
80
Key Plan
Locating new buildings and uses along the
street edge
![Page 81: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/81.jpg)
81
Key Plan
Supporting employees with a greater mix of
uses
![Page 82: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/82.jpg)
82
Key Plan
Improving the pedestrian and cycling
environment
![Page 83: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/83.jpg)
83
The Big Picture
![Page 84: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/84.jpg)
84
Designing the MSF to contribute to
the image of industry street and
support the creation of new
neighbourhood connections
The Big Picture
![Page 85: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/85.jpg)
85
Transforming Eglinton into a new
“green” street that extends the
Humber trail network east to the
new community centre and beyond.
The Big Picture
![Page 86: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/86.jpg)
86
Encouraging the revitalization of
Weston Road as the Principle
community and retail spine centred
upon a new station and green plaza
space
The Big Picture
![Page 87: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/87.jpg)
87
Encouraging new mixed-use
development on the No Frills Site
that relates positively to Keeledale
Park and the Station.
The Big Picture
![Page 88: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/88.jpg)
88
Enhancing the image of the Black
Creek Business Area and improving
access for pedestrians, cyclists and
transit users
The Big Picture
![Page 89: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/89.jpg)
89
The Big Picture A hub in the regional cycling network
![Page 90: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/90.jpg)
90
The Big Picture A key connection in the regional green network
![Page 91: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/91.jpg)
91
The Big Picture
Designing the MSF to contribute to
the image of industry street and
support the creation of new
neighbourhood connections
Transforming Eglinton into a new
“green” street that extends the
Humber trail network east to the
new community centre and beyond.
Encouraging the revitalization of
Weston Road as the Principle
community and retail spine centred
upon a new station and green plaza
space
Encouraging new mixed-use
development on the No Frills Site
that relates positively to Keeledale
Park and the Station.
Enhancing the image of the Black
Creek Business Area and improving
access for pedestrians, cyclists and
transit users
![Page 92: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/92.jpg)
92
Next Steps
December 18th – 6:30pm
• Economic Development Workshop
Early 2013
• Community Liaison Group Meeting
• Mobility Hub Concepts Presented at Public Meeting
• Station Design Concept Public Meeting
Spring 2013
• Finalize Mobility Hub Study
Ongoing:
• Metrolinx will:
• Incorporate recommendations into the concepts for LRT facilities and stations
• Work with the City of Toronto to support zoning updates to reflect study recommendations
• Work with the City of Toronto to prioritize infrastructure and public realm improvements
recommended
![Page 93: Mount Dennis Mobility Hub Study](https://reader034.fdocuments.net/reader034/viewer/2022052307/55698c1dd8b42a673a8b49d6/html5/thumbnails/93.jpg)
93
Thank you!