MoUD Center of Excellence: PPP initiatives in Water & Sanitation Analysis of City Corporate Plan:...

40
MoUD Center of Excellence: PPP initiatives in Water & Sanitation Analysis of City Corporate Plan: PPP-ability Criterion Matrix

Transcript of MoUD Center of Excellence: PPP initiatives in Water & Sanitation Analysis of City Corporate Plan:...

MoUD Center of Excellence: PPP initiatives in Water & SanitationAnalysis of City Corporate Plan:

PPP-ability Criterion Matrix

Page 2

Pallavaram

Financial Ability of ULB

The revenue surplus in FY2003-04 was Rs 452 Lakhs

End User Paying Capacity

Industrial cluster can augment capacity

Demand Supply Gap

Water supply – Only 30% have of property have serviced connections,

Sewage Disposal – There is no proper UGDS

Solid Waste Management

Orientation towards PPP

Partial privatization in the SWM collection stage

Collection efficiency - water charges @ 72%.

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

Annuity

Recycling Waste Water for Industrial Use

Annuity/User Payment

With high presence of Ind. Clusters and a high requirement for water, there are substantially high chances of implementing a PPP project in the ‘wastewater to water’ sector in Pallavaram.

Legend: High; Medium; Low

Page 3

Trichy

Financial Ability of ULB

The overall surplus in FY2005 was Rs 4,008 Lakhs

End User Paying Capacity

Industrial cluster can augment capacity

Demand Supply Gap

Water supply – Only 50% of assessed properties have water connections.

Sewage Disposal – About 50,000 new connections required.

Orientation towards PPP

Partial privatization in the SWM collection stage

Water meters for household water connections

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

User Payment

Recycling Waste Water for Industrial Use

User Payment

With the presence of an Ind. Cluster and a high requirement for water, there are substantially high chances of implementing a PPP project in the ‘wastewater to water’ sector.

Legend: High; Medium; Low

Page 4

Ambattur

Financial Ability of ULB

There is a good total revenue which is increasing.

End User Paying Capacity

Industrial cluster can augment capacity

Demand Supply Gap

Water supply – Only 35% of the roads is covered with distribution network.

Sewage Disposal – No UGD system in 16 wards.

Orientation towards PPP

Partial privatization in the SWM collection stage

Water Distribution

Annuity

Sanitation Annuity/BOT

Solid Waste Management

BOT

Recycling Waste Water for Industrial Use

BOT

With high presence of Ind. Clusters and a high requirement for water, there are substantially high chances of implementing a PPP project in the ‘wastewater to water’ sector.

Legend: High; Medium; Low

Page 5

Ramanathapuram

Financial Ability of ULB

The revenue income has been rising at 14.71% per annum

End User Paying Capacity

Level of affluence of public is high owing to the increase in the wholesale and retail trade.

Demand Supply Gap

Water supply- Current supply = 2.26MLD; Demand (in 2006) = 6 MLD

Sewage Disposal- No UGDS

SWM- No Compost yard

Orientation towards PPP

No PPP initiative in the past and no user based charges levied on

water consumption.

Water Distribution

Annuity

Sanitation Annuity/BOT

Solid Waste Management

BOT

Recycling Waste Water for Industrial Use

BOT

With high level of affluence of the public and a high requirement in all sectors of Water & sanitation, there is a fairly high chance of implementing an annuity / BOT model of PPP in Ramanathapuram.

Legend: High; Medium; Low

Page 6

Kovilpatti

Financial Ability of ULB

The capital account has mostly witnessed a deficit over the years.

End User Paying Capacity

Textile and Match are the major industries in the town, providing employment to 85% of the workforce.

Demand Supply Gap

Water supply- HSC @35% of assessed prop.

Sewage Disposal- No UGDS

SWM- No compost yard.

Orientation towards PPP

Water meters for household water connections

Water Distribution

Sanitation BOT

Solid Waste Management

BOT

Recycling Waste Water for Industrial Use

BOT

With relatively high capacity of end users to pay, and substantially high demand in all sectors of water & sanitation, it may be possible to implement a BOT model of PPP in Kovilpatti.

Legend: High; Medium; Low

Page 7

Avadi

Financial Ability of ULB

There is a healthy revenue and a fair operating surplus.

End User Paying Capacity

22 SSI in the municipality. Trading and manufacturing of small scale and industrial goods provides the main economic activities.

Demand Supply Gap

Water supply- There are no house connections.

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

No PPP initiative in the past and no user based charges levied on

water consumption.

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

Annuity

Recycling Waste Water for Industrial Use

With reasonably high end user capacity, and substantially high demand in all sectors of water & sanitation, it may be possible to implement a BOT model of PPP in Avadi.

Legend: High; Medium; Low

Page 8

Mettupalayam

Financial Ability of ULB

There is no surplus in the ULB funds.

End User Paying Capacity

There are very small industrial developments in the town and only 37% of the population is employed.

Demand Supply Gap

Water supply – 15%Leakage in the dist. System.

Sewage Disposal – No UGD

SWM – Only 26% collection of solid waste.

Orientation towards PPP

Waste collection in 5 wards is privatized;

Collection efficiency ranges b/w 70-95%

Water Distribution

Sanitation

Solid Waste Management

Recycling Waste Water for Industrial Use

With low financial ability of the ULB and low end user’s paying capacity, there is very less scope of implementing a PPP model.

Legend: High; Medium; Low

Page 9

Tiruppur

Financial Ability of ULB

Though the Revenue expenditure has shown an increase over the last few years, ULB has maintained a fair surplus of funds.

End User Paying Capacity

More than 85% of the workforce is employed in Tertiary sector; 3350 industries located in the town.

Demand Supply Gap

Sewage Disposal – No UGD

Orientation towards PPP

The composting plant has been set up on BOT basis

Water Distribution

Sanitation BOT

Solid Waste Management

Recycling Waste Water for Industrial Use

With a high end users paying capacity and a high need for a good sewage disposal system, it would be feasible to undertake a BOT based PPP project in Tiruppur.

Legend: High; Medium; Low

Page 10

Tambaram

Financial Ability of ULB

ULB has an operating surplus and the revenues are increasing over time

End User Paying Capacity

High house working sector with good income

Demand Supply Gap

Water Supply- Current supply: 25LPCD

Sewage Disposal – No UGD

SWM- No compost yard.

Orientation towards PPP

Waste collection is privatized in some of

the wards;

Water Distribution

Annuity

Sanitation Annuity/BOT

Solid Waste Management

Annuity/BOT

Recycling Waste Water for Industrial Use

With a reasonable financial ability of the ULB and medium end user capacity, it might be feasible to implement a combination of Annuity/BOT model for a project in the water & sanitation sector.

Legend: High; Medium; Low

Page 11

Tiruvottriyur

Financial Ability of ULB

ULB is experiencing a decrease in the revenues and still maintaining a surplus.

End User Paying Capacity

There are leading industrial units in the town, including

1000 small scale industries.

Demand Supply Gap

Water Supply- Storage capacity is 26% of supply.

Sewage Disposal – Partial UGD system exists.

Orientation towards PPP

Waste collection is privatized in some of the wards

Water Distribution

Sanitation BOT

Solid Waste Management

Recycling Waste Water for Industrial Use

BOT

With a high presence of industrial cluster, and a high demand supply gap for water, it might be feasible to execute a BOT model of PPP project for the recycling of Waste water for Industrial use.

Legend: High; Medium; Low

Page 12

Nagarcoil

Financial Ability of ULB

Despite a robust own revenue source, the ULB relies significantly on the State grants for its revenue expenses,

End User Paying Capacity

Demand Supply Gap

Water supply - Storage capacity is 25% of daily supply

Sewage Disposal- No UGD

SWM- No Compost yard.

Orientation towards PPP

Waste collection is privatized in all wards

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

Annuity

Recycling Waste Water for Industrial Use

With a high financial ability of the ULB and a high demand supply gap, it would be feasible to execute an Annuity based PPP model in a UGD system or enhancing the storage capacity for water supply to the town..

Legend: High; Medium; Low

Page 13

Alandur

Financial Ability of ULB

Though there is a surplus in the ULB, there is an outstanding net liability.

End User Paying Capacity

Majority of the population is involved in Tertiary sector of economic activities.

Demand Supply Gap

Water supply – HSC is only 44% of assessed properties.

SWM- No compost yard.

Orientation towards PPP

Waste collection is privatized in most of

the wards

Sewerage system is privatized

Water Distribution

Annuity/BOT

Sanitation

Solid Waste Management

Annuity/BOT

Recycling Waste Water for Industrial Use

With a reasonable financial ability of ULB, the end user paying capacity, and the existing exposure to PPP in SWM, the water supply system may be enhanced on the BOT model of PPP.

Legend: High; Medium; Low

Page 14

Mayiladuthurai

Financial Ability of ULB

There has been a 10% growth in the operating surplus over the years.

End User Paying Capacity

Demand Supply Gap

Water supply – HCS cover 37% of the assessed properties.

Sewage Disposal – No UGD

SWM – Insufficient area for composting

Orientation towards PPP

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

Annuity

Recycling Waste Water for Industrial Use

With a reasonable financial ability of ULB, and a high demand in the water supply and sewage disposal, it might be feasible to execute an Annuity model of PPP project.

Legend: High; Medium; Low

Page 15

Thanjavur

Financial Ability of ULB

End User Paying Capacity

Demand Supply Gap

Water supply – HSC cover 56% of properties; Storage capacity is 55% of daily supply

SWM – Need for excess compost yard.

Orientation towards PPP

Water Distribution

Sanitation

Solid Waste Management

Legend: High; Medium; Low

Owing to the non existence of financial aid, it might be difficult to execute a PPP project

Page 16

Kumbakonam

Financial Ability of ULB

End User Paying Capacity

Demand Supply Gap

Water supply – HSC covers 50% of assessed properties.

Sewage Disposal – No UGD

SWM – Need for compost yard.

Orientation towards PPP

Water Distribution

Sanitation

Solid Waste Management

Legend: High; Medium; Low

Owing to the non existence of financial aid, it might be difficult to execute a PPP project

Page 17

Conoor

Financial Ability of ULB

End User Paying Capacity

Demand Supply Gap

Water supply – HCS cover 65% of the assessed properties.

Sewage Disposal – No UGD

SWM – Inadequate composting facilities

Orientation towards PPP

Water Distribution

Sanitation

Solid Waste Management

Legend: High; Medium; Low

Owing to the non existence of financial aid, it might be difficult to execute a PPP project

Page 18

Kathivakkam

Financial Ability of ULB

.

End User Paying Capacity

Demand Supply Gap

Water supply – Capacity gap; insufficient storage; absence of connections.

Sewage Disposal- No UGD

Orientation towards PPP

Water Distribution

Sanitation

Solid Waste Management

Legend: High; Medium; Low

Owing to the non existence of financial aid, it might be difficult to execute a PPP project

Page 19

Kancheepuram

Financial Ability of ULB

There has been a surplus registered over the years.

End User Paying Capacity

The town is a center for wholesale and retail trade for textiles, building material, and food grains

Demand Supply Gap

Water supply – Transmission losses account for about 18%.

Sewage Disposal- Effluent discharge lines for the mills need to be laid.

Orientation towards PPP

Water Distribution

Annuity

Sanitation Annuity/BOT

Solid Waste Management

Annuity/BOT

Recycling Waste Water for Industrial Use

Legend: High; Medium; Low

With a reasonable financial ability of ULB, end user paying capacity, and a high demand in the water supply and sewage disposal, it might be feasible to execute an Annuity/ BOT model of PPP project

Page 20

Virudhachalam

Financial Ability of ULB

The revenue surplus has slightly dipped over the years

End User Paying Capacity

Predominant industry include the Ceramic industry; The population is mainly involved in secondary & tertiary sector activities.

Demand Supply Gap

Sewage Disposal – No UGD

SWM – No composting

Orientation towards PPP

Water Distribution

Sanitation Annuity/BOT

Solid Waste Management

Annuity/BOT

Legend: High; Medium; Low

With a reasonable financial ability of ULB, end user paying capacity, and a high demand in the sewage disposal and SWM, it might be feasible to execute an Annuity/ BOT model of PPP project

Page 21

Tiruvarur

Financial Ability of ULB

The overall surplus of the ULB has increased from over the years.

End User Paying Capacity

About 85% of the population is involved in tertiary sector of activities

Demand Supply Gap

Water supply – HSC covers 23% of assessed properties

Sewage Disposal – No UGD

SWM – No composting

Orientation towards PPP

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

Annuity

Legend: High; Medium; Low

With a reasonable financial ability of ULB, end user paying capacity, and a high demand in the water supply, sewage disposal and SWM, it might be feasible to execute an Annuity model of PPP project

Page 22

Tiruvallur

Financial Ability of ULB

There has been a constant rise in the surplus of the ULB.

End User Paying Capacity

There are Petrochemical factories, refineries and handloom industries in the town. Further, most of the population is employed in these industries.

Demand Supply Gap

Water supply – HSC cover 35% of assessed properties

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Waste collection is privatized in 11 wards

97% are metered water connection

Water Distribution

Annuity

Sanitation Annuity/BOT

Solid Waste Management

Annuity/BOT

Recycling Waste Water for Industrial Use

BOT

Legend: High; Medium; Low

With high presence of Ind. Clusters and a high requirement for water, there are substantially high chances of implementing a BOT model PPP project in the ‘waste to water’ sector.

Page 23

Chidambaram

Financial Ability of ULB

End User Paying Capacity

About 88% of the working population is in Tertiary sector.

Demand Supply Gap

Water supply – Current supply: 76 LPCD

Sewage Disposal – HSC cover 35% of properties.

SWM – No compost yard

Orientation towards PPP

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

Annuity

Legend: High; Medium; Low

With level of affluence of the end users and a high demand in the Sewage disposal, it might be feasible to execute an Annuity/ BOT model PPP project .

Page 24

Hosur

Financial Ability of ULB

There has been a steady increase in the overall surplus

End User Paying Capacity

There are Steel & Engineering industries in the town; Further 94% of the population is employed in the tertiary sector.

Demand Supply Gap

Water supply – HSC cover 48% of the properties.

Sewage Disposal – No UGD.

SWM – No compost yard

Orientation towards PPP

Water Distribution

Annuity

Sanitation Annuity/BOT

Solid Waste Management

Annuity/BOT

Recycling Waste Water for Industrial Use

BOT

Legend: High; Medium; Low

With the presence of an Ind. Cluster and a high requirement for water, there are substantially high chances of implementing a PPP project in the ‘waste to water’ sector.

Page 25

Rajapalayam

Financial Ability of ULB

End User Paying Capacity

82 large & medium industries – textiles, processing factories; 85% of the working population is in Tertiary sector.

Demand Supply Gap

Water supply – Current supply: 59LPCD.

Sewage Disposal – No UGD.

Orientation towards PPP

Waste collection is privatized in 29 wards

Water Distribution

Annuity

Sanitation Annuity/BOT

Solid Waste Management

Recycling Waste Water for Industrial Use

BOT

Legend: High; Medium; Low

With the presence of an Ind. Cluster and a high requirement for water, there are substantially high chances of implementing a PPP project in the ‘waste to water’ sector.

Page 26

Cuddalore

Financial Ability of ULB

There has been a steady revenue surplus in the ULB

End User Paying Capacity

SIPCOT industrial estate houses 30 industries – around which the economy revolves.

Demand Supply Gap

Water supply – Water supplied to 39% of assessed properties.

Sewage Disposal – No UGD.

Orientation towards PPP

Waste collection is privatized in some

wards

Water connections are metered.

Water Distribution

Annuity

Sanitation Annuity/BOT

Solid Waste Management

Recycling Waste Water for Industrial Use

BOT

Legend: High; Medium; Low

With the presence of an Ind. Cluster and a high requirement for water, there are substantially high chances of implementing a PPP project in the ‘wastewater to water’ sector.

Page 27

Bodinayakanur

Financial Ability of ULB

End User Paying Capacity

Demand Supply Gap

Water supply – Current supply: 75LPCD

Sewage Disposal – No UGD

SWM – No compost yard.

Orientation towards PPP

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

Legend: High; Medium; Low

With a medium financial ability of the ULB and a large gap in the Sewage disposal, an annuity model of PPP project would be a feasible option.

Page 28

Karaikudi

Financial Ability of ULB

End User Paying Capacity

There are man small scale industries in the town

Demand Supply Gap

Water supply – Current Capacity demand ratio = 0.15; Reqd. 0.33

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Waste collection is privatized in some wards

All HSC are metered

Water Distribution

Sanitation

Solid Waste Management

Legend: High; Medium; Low

With a medium end user paying capacity and a high gap in the sewage disposal, a BOT model in PPP might be a reasonable option.

Page 29

Dharmapuri

Financial Ability of ULB

There has been a steady overall surplus in the ULB

End User Paying Capacity

Demand Supply Gap

Water supply – HSC cover only 38% of total assessed properties.

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

Annuity

Legend: High; Medium; Low

With a medium financial ability of the ULB and a high demand in the water supply and sewage disposal, Annuity model of PPP might be a feasible option.

Page 30

Mettur

Financial Ability of ULB

There has been a steady overall surplus in the ULB

End User Paying Capacity

There are major Hydro power plants and chemical industries in the town. Industrial cluster can augment capacity.

Demand Supply Gap

Water supply – HSC cover only 48% of total assessed properties.

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Water Distribution

Annuity

Sanitation BOT

Solid Waste Management

BOT

Recycling Waste Water for Industrial Use

BOT

Legend: High; Medium; Low

With a medium financial ability of the ULB coupled with a high presence of industrial cluster, the demand supply gap in the sewage disposal and SWM can be filled by a BOT model. Further, the industrial water requirement can be met by use of ‘wastewater to water’ technologies.

Page 31

Udhagamandalam

Financial Ability of ULB

There has been a steady surplus in the Revenue Income

End User Paying Capacity

There are small industries in the town, that serve employment to a majority of the population

Demand Supply Gap

Water supply – Storage capacity is 33% of supply; HSC covers 47% of assessed properties.

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

Annuity

Legend: High; Medium; Low

With a medium financial ability of the ULB coupled with a reasonable end user paying capacity, and a high demand supply gap, it might be feasible to implement an annuity/BOT model of PPP project in the water supply and sewage disposal project.

Page 32

Chengalpattu

Financial Ability of ULB

There has been a steady surplus in the Revenue Income

End User Paying Capacity

Bulk of the population is engaged in tertiary sector.

Demand Supply Gap

Water supply – Current supply: 42LPCD.

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Water Distribution

Annuity

Sanitation Annuity

Solid Waste Management

Annuity

Legend: High; Medium; Low

With a medium financial ability of the ULB coupled with a reasonable end user paying capacity, and a high demand supply gap, it might be feasible to implement an annuity/BOT model of PPP project in the water supply and sewage disposal project.

Page 33

Palani

Financial Ability of ULB

There has been a steady surplus in the Revenue Income

End User Paying Capacity

Bulk of the working population is engaged in tertiary sector.

Demand Supply Gap

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Water Distribution

Sanitation Annuity/BOT

Solid Waste Management

Annuity/BOT

Legend: High; Medium; Low

With a medium financial ability of the ULB coupled with a reasonable end user paying capacity, and a high demand supply gap, it might be feasible to implement an annuity/BOT model of PPP project in the sewage disposal and SWM project.

Page 34

Pattukottai

Financial Ability of ULB

There has been a steady surplus in the Revenue Income

End User Paying Capacity

Coir and Agriculture based commercial activities is the main economic basis of the town.

Demand Supply Gap

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Water Distribution

Sanitation Annuity/BOT

Solid Waste Management

Annuity/BOT

Legend: High; Medium; Low

With a medium financial ability of the ULB coupled with a reasonable end user paying capacity, and a high demand supply gap in sewage disposal, it might be feasible to implement an annuity/BOT model of PPP project in the sewage disposal and SWM project.

Page 35

Krishnagiri

Financial Ability of ULB

End User Paying Capacity

Demand Supply Gap

Water Supply – Currently 45% of the demand is fulfilled.

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Water Distribution

Sanitation

Solid Waste Management

Legend: High; Medium; Low

Owing to the non existence of financial aid, it might be difficult to execute a PPP project

Page 36

Cumbum

Financial Ability of ULB

End User Paying Capacity

Demand Supply Gap

Water Supply – Current supply:60LPCD

Sewage Disposal – No UGD

SWM – Insufficient compost yard

Orientation towards PPP

Collection efficiencies are very high.

Water Distribution

Sanitation

Solid Waste Management

Legend: High; Medium; Low

Owing to the non existence of financial aid, it might be difficult to execute a PPP project

Page 37

Bhavani

Financial Ability of ULB

End User Paying Capacity

There are small scale textile industries within the town.

Demand Supply Gap

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Waste collection is privatized in some wards

Water Distribution

Sanitation BOT

Solid Waste Management

BOT

Legend: High; Medium; Low

With reasonable end user paying capacity among industries, it might be feasible to implement a BOT model in PPP for the Sewage disposal/SWM.

Page 38

Sathyamangalam

Financial Ability of ULB

End User Paying Capacity

Demand Supply Gap

Water supply – HSC covers 50%

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

All house connections are metered.

Water Distribution

Sanitation

Solid Waste Management

Legend: High; Medium; Low

Owing to the non existence of financial aid, it might be difficult to execute a PPP project

Page 39

Thuraiyur

Financial Ability of ULB

End User Paying Capacity

About 76% of the working population is involved in the tertiary sector of economic activities.

Demand Supply Gap

Water supply – HSC covers 20%

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Collection efficiency is very high.

Water Distribution

Sanitation BOT

Solid Waste Management

BOT

Legend: High; Medium; Low

With a reasonable end user paying capacity and a high demand supply gap , it might be feasible to execute a BOT model PPP project in the sector.

Page 40

Attur

Financial Ability of ULB

End User Paying Capacity

Demand Supply Gap

Water supply – Current supply:75LPCD

Sewage Disposal – No UGD

SWM – No compost yard

Orientation towards PPP

Waste collection has been privatised in some wards

Collection efficiency is very high.

Water Distribution

Sanitation

Solid Waste Management

Legend: High; Medium; Low

Owing to the non existence of financial aid, it might be difficult to execute a PPP project