Montrin Richview GP Inc. Stormwater Management Report€¦ · Montrin Richview GP Inc.
Transcript of Montrin Richview GP Inc. Stormwater Management Report€¦ · Montrin Richview GP Inc.
Montrin Richview GP Inc.
Stormwater Management Report
Richview Square
4620 Eglinton Avenue West and 250 Wincott Drive
MARCH 18, 2019
WSP Canada Inc.
Stormwater Management Report
Richview Square
4620 Eglinton Avenue West and 250 Wincott Drive
Montrin Richview GP Inc.
Rezoning Application
Project No.: 15M-00048-03
Date: March 2019
WSP
100 Commerce Valley Drive West
Thornhill, ON, Canada L3T 0A1
Tel.: +1 905 882-1100
Fax: +1 905 882-0055
wsp.com
Q u a l i t y M a n a g e m e n t
ISSUE/REVISION FIRST ISSUE REVISION 1 REVISION 2 REVISION 3
Remarks Rezoning
Application
Rezoning
Application
Date 2018/04/24 2019/03/18
Prepared by Jennifer Chan Samer Elhallak,
EIT
Signature
Checked by Bhavika Patel Sarah Piasetzki,
P.Eng.
Signature
Project number 15M-00048-03 15M-00048-03
Stormwater Management Report Project No. 15M-00048-03 Montrin Richview GP Inc.
WSP March 2019
Page v
P r o d u c t i o n T e a m CLIENT
Montrin Richview GP Inc.
WSP
Designer Samer Elhallak, EIT
Reviewer Sarah Piasetzki, P.Eng.
Stormwater Management Report Project No. 15M-00048-03 Montrin Richview GP Inc.
WSP March 2019
Page vii
TABLE OF CONTENTS
1 Introduction .............................................................. 1
1.1 Scope ................................................................................. 1
1.1 Site Location ...................................................................... 1
1.2 Stormwater Management Plan Objectives ......................... 1
1.3 Design Criteria ................................................................... 1
2 Pre-Development Conditions .................................. 4
2.1 General .............................................................................. 4
2.2 Rainfall Information ............................................................ 4
2.3 Allowable Flow Rates ......................................................... 5
3 Post-Development Conditions ................................ 8
3.1 General .............................................................................. 8
3.2 Water Balance .................................................................. 11
3.3 Water Quality Control ....................................................... 12
3.4 Erosion Control ................................................................ 12
3.5 Water Quantity Control ..................................................... 13
3.6 Hydrogeology and Groundwater Characterization ........... 15
4 Conclusions ............................................................ 16
WSP March 2019 Page viii
Stormwater Management Report Project No. 15M-00048-03
Montrin Richview GP Inc.
Tables
TABLE 1: RAINFALL PARAMETERS ............................ 4
TABLE 2: AREA BREAKDOWN BY CATCHMENT ................................................. 5
TABLE 3: PRE-DEVELOPMENT PEAK FLOW RATE CALCULATIONS – CATCHMENT 101 .......................................... 6
TABLE 4: PRE-DEVELOPMENT PEAK FLOW RATE CALCULATIONS – CATCHMENT 102 .......................................... 6
TABLE 5: PROPOSED CONDITIONS AREA BREAKDOWN – CATCHMENT 201 .............. 8
TABLE 6: PROPOSED CONDITIONS AREA BREAKDOWN – CATCHMENT 202 .............. 9
TABLE 7: WATER BALANCE – CATCHMENT 201 ............................................................... 11
TABLE 8: WATER BALANCE – CATCHMENT 202 ............................................................... 12
TABLE 9: SUMMARY OF MODELLING RESULTS – CATCHMENT 201 ................... 14
TABLE 10: SUMMARY OF MODELLING RESULTS – CATCHMENT 202 ................... 14
Figures
FIGURE 1: SITE LOCATION ............................................ 3 FIGURE 2: EXISTING CONDITIONS ............................... 7
FIGURE 3: PROPOSED CONDITIONS ......................... 10
Appendices
A STORMWATER MANAGEMENT CALCULATIONS
B HYDROLOGIC MODEL OUTPUT (HYDROCAD)
C WATER QUALITY UNIT DETAILS
Stormwater Management Report Project No. 15M-00048-03 Montrin Richview GP Inc.
WSP March 2019
Page 1
1 Introduction
1.1 Scope
WSP has been retained by Montrin Richview GP Inc. to prepare a Stormwater Management
(SWM) Report to support the zoning by-law amendment application for the proposed
development at 4620 Eglinton Avenue West and 250 Wincott Drive, in The City of Toronto.
This SWM report examines the potential water balance, water quality, and water quantity
impacts of the proposed development and summarizes how each will be addressed in
accordance with the City of Toronto’s Wet Weather Flow Management Guidelines (WWFMG).
1.1 Site Location
The site is located on the northwest corner of Eglinton Avenue West and Wincott Drive. The
location of the proposed re-development is illustrated in Figure 1.
1.2 Stormwater Management Plan Objectives
The objectives of the stormwater management plan are as follows:
— Determine site specific stormwater management requirements to ensure that the proposals
are in conformance with the City of Toronto WWFMG document;
— Evaluate various stormwater management practices that meet the requirements of the City
and recommend a preferred strategy; and
— Prepare a stormwater management report documenting the strategy along with the
technical information necessary for the justification and preliminary sizing of the proposed
stormwater management facilities.
1.3 Design Criteria
The City of Toronto issued the WWFMG document in November 2006 to provide direction on
the management of rainfall and runoff inside the City’s jurisdiction. A summary of the
stormwater management criteria applicable to this project follows:
WSP March 2019 Page 2
Stormwater Management Report Project No. 15M-00048-03
Montrin Richview GP Inc.
— Water Balance – The WWFMG requires a site to ‘retain stormwater on-site, to the extent
practicable, to achieve the same level of annual volume of overland runoff allowable from
the development site under pre-development conditions’. According to the guidelines, if the
allowable annual runoff volume from the development site under post-development
conditions is less than the pre-development conditions, then the maximum allowable
annual runoff is 50% of the total average annual rainfall depth. Typically, the minimum on-
site runoff retention will require the site to retain all runoff from a 5 mm storm event through
infiltration, evapotranspiration or rainwater re-use.
— Water Quality – Under the WWFMG, the site is required to target a long-term removal of
80% of total suspended solids (TSS) on an annual loading basis.
— Erosion Control –As indicated in WWFMG, ‘For small infill/redevelopment sites < 2 ha,
erosion control in the form of stormwater detention is normally not required, provided the
on-site minimum runoff retention from a small design rainfall event (typically 5 mm) is
achieved under the Water Balance Criteria.’ The developable area of the site is slightly
greater than 2 ha. However, the proposed site will be delineated into two catchments that
are both less than 2 ha and each will have its own stormwater management strategy.
During construction, appropriate erosion and sediment controls will be implemented.
— Water Quantity Control and Discharge to Municipal Infrastructure – Runoff from the 2-
year to 100-year design storms must not exceed the allowable release rate as stated in the
WWFMG. The allowable release rate to the municipal storm sewer system from the
development site is the 2-year pre-development flow rate based on a runoff coefficient of
0.50 or the capacity of the receiving sewer.
SITELOCATION
FIG
UR
E 1
.d
wg
- S
ite
L
oca
tio
n J:\1
44
1 P
ro
je
cts b
y Jo
b N
um
be
r\2
01
8\1
5M
-0
00
48
-0
3-S
W1
R
ich
vie
w S
qu
are
- U
pd
ate
\4
. C
AD
\F
IG
UR
ES
\ M
ar 1
2, 2
01
9 - 1
2:5
1p
mF
IG
UR
E 1
.d
wg
- S
ite
L
oca
tio
n J:\1
44
1 P
ro
je
cts b
y Jo
b N
um
be
r\2
01
8\1
5M
-0
00
48
-0
3-S
W1
R
ich
vie
w S
qu
are
- U
pd
ate
\4
. C
AD
\F
IG
UR
ES
\ M
ar 1
2, 2
01
9 - 1
2:5
1p
m
@2018 Google - Map data @2018 Tele Atlas3000 100 200 400m
WSP March 2019 Page 4
Stormwater Management Report Project No. 15M-00048-03
Montrin Richview GP Inc.
2 Pre-Development Conditions
2.1 General
The 3.04 ha site is currently partially developed, hosting a few buildings, surface parking and
vacant lands. For the purposes of the stormwater management strategy, only the planned
development area of 2.26 ha (to be re-developed as Richview Square) will be taken into
consideration, and will be referred to as the site. The existing runoff coefficient of the site is
estimated at 0.60, as the site is comprised of pervious grassed areas, impervious roof and
impervious paving. The existing site has a drainage split, draining to Widdicombe Hill on the
northwest side and Wincott Drive on the east side, delineated as catchments 101 and 102
respectively. The site currently does not receive external drainage from adjacent areas. The
existing condition of the site is shown in Figure 2.
2.2 Rainfall Information
The rainfall intensity for the site was calculated using the following equation: 𝐼 = 𝐴𝑇𝐶
Where;
I = rainfall intensity in mm/hour
T = time of concentration in hours
A and C = constant parameters (see below)
The parameters (A, C) recommended for use by the City of Toronto (per Section 3.1 of the Wet
Weather Flow Management Guidelines) are summarized in Table 1.
Table 1: Rainfall Parameters
Return Period
(Years) 2 5 10 25 50 100
A 21.8 32.0 38.7 45.2 53.5 59.7
C -0.78 -0.79 -0.80 -0.80 -0.80 -0.80
Source: City of Toronto Wet Weather Flow Management Guidelines (November, 2006)
An initial time of concentration, TC, of 10 minutes (or 0.167 hours) is recommended in the
WWFMG document.
Stormwater Management Report Project No. 15M-00048-03 Montrin Richview GP Inc.
WSP March 2019
Page 5
2.3 Allowable Flow Rates
The site is located within a suburban area and drains to the municipal storm sewers. As noted
in Section 1.4, relevant policies from the WWFMG require the discharge rate from this site to
be controlled to the allowable rate for discharge to municipal sewers. The pre-development
Catchments 101 and 102 were delineated based on existing topographic features and storm
service connections. Table 2 provides an area breakdown by catchment. The post-
development catchment area breakdowns will be discussed further in later sections.
Table 2: Area Breakdown by Catchment
Catchment Area (ha) Runoff Coefficient
Pre-Development
101 0.27 0.90
102 1.99 0.60
Total 2.26 0.64
Post-Development
201 0.40 0.78
202 1.86 0.62
Total 2.26 0.65
According to the WWFMG, Section 2.2.3.8, the target release rate to the municipal storm
sewer system is based on the 2-year pre-development flow rate calculated with a maximum
runoff coefficient value of 0.50 as required by the City of Toronto WWFMG. This results in
target release rates of 33.1 L/s and 243.9 L/s for Catchments 101 and 102, respectively. The
calculated peak flow rates for the site under pre-development conditions are summarized
below in Tables 3 and 4. Detailed calculations are contained within Appendix A.
WSP March 2019 Page 6
Stormwater Management Report Project No. 15M-00048-03
Montrin Richview GP Inc.
Table 3: Pre-Development Peak Flow Rate Calculations – Catchment 101
Return Period
(Years)
Rainfall Intensity, I
(mm/Hour)
Existing Peak Flow
Rate, Q*
(L/s)
WWFMG Allowable
Release Rate, Qa**
(L/s)
2 88.2 59.6
33.1
5 131.8 89.0
10 162.3 109.6
25 189.5 128.0
50 224.3 151.5
100 250.3 169.1
*C=0.90, area of 0.27 ha and time of concentration of 10 minutes
**C=0.50, area of 0.27 ha and time of concentration of 10 minutes
Table 4: Pre-Development Peak Flow Rate Calculations – Catchment 102
Return Period
(Years)
Rainfall Intensity, I
(mm/Hour)
Existing Peak Flow
Rate, Q*
(L/s)
WWFMG Allowable
Release Rate, Qa**
(L/s)
2 88.2 292.7
243.9
5 131.8 437.5
10 162.3 538.6
25 189.5 629.1
50 224.3 744.6
100 250.3 830.9
*C=0.60, area of 1.99 ha and time of concentration of 10 minutes
**C=0.50, area of 1.99 ha and time of concentration of 10 minutes
HE
DG
E
HE
DG
E
GR
AS
S
AR
EA
ROW OF CONIFEROUS TREES
(23 TREES, DIA=0.10, EACH)
SHRUBS
SHRUB
E
D
G
E
O
F
T
R
E
E
S
E
D
G
E
O
F
T
R
E
E
S
GR
AS
S A
RE
A
GR
AS
S A
RE
A
GRASS
AREA
GR
AS
S A
RE
A
CHAIN LINK FENCE
SIGN
CU
RB
C
UT
AS
PH
ALT
E
DG
E
CU
RB
SIGN
S
I
G
N
SIGN
LS
CO
NC
RE
TE
S
ID
EW
ALK
MH
CB
BOL
BOL
BUILDING
CURB
CH
AIN
LIN
K F
EN
CE
LS
LS
SP
SIG
N
SIGN
ASPHALT EDGE
SIGN
ASPHALT EDGE
CURB
H
CU
RB
BU
IL
DIN
G
CB
CB
MH
LS
LS
LS
LS
LS
LS
SIGN
SIGN
SIGN
SIGN
SIGN
SIGN
BUILDING
GR
AT
E
SP
MH
SIGNSIGN
SIGN
GUIDE RAIL
BU
ILD
IN
G
SIGN
CB
CB
C/L OF ROAD
C/L OF ROAD
C/L O
F R
OA
D
SIG
N
SIGN
CURB
ASPHALT EDGE
ASPHALT EDGE
CURB
ASPHALT EDGE
CURB
CU
RB
AS
PH
ALT
E
DG
E
AS
PH
ALT
E
DG
E
AS
PH
ALT
E
DG
E
AS
PH
ALT
E
DG
E
CU
RB
BOL
BOL BOL
CU
RB
C
UT
CU
RB
AS
PH
ALT
E
DG
E
CU
RB
CONCRETE
WALKWAY
CONCRETE
WALKWAY
CURB
ASPHALT EDGE
G METER
SP
BOL
G METER
WK
OVERHANG
LS
CB
CB
MH
MH
MH
MH
CURB
ASPHALT EDGE
PARKING CURB
HANDRAIL
CU
RB
AS
PH
ALT
E
DG
E
CO
NC
RE
TE
WA
LK
WA
Y
BOLBOL
G METER
GK
SO
LID
P
AIN
T LIN
E
SOLID PAINT LINESOLID PAINT LINE
SOLID PAINT LINE
SOLID PAINT LINE
BU
ILD
IN
G O
VE
RH
AN
G
L
S
B
O
A
R
D
F
E
N
C
E
C
H
A
I
N
L
I
N
K
F
E
N
C
E
CB
CB
CB
MH
MH
BOARD FENCE
CHAIN LINK FENCE
LS
BOTTOM OF SLOPE
SIGN
SIGN
OVERHANG
OV
ER
HA
NG
HANDRAIL
WV
BSP
SIGN
LS
SIGN
SIGN
ASPHALT EDGE
CURB
AS
PH
ALT
E
DG
E
CU
RB
AS
PH
ALT
E
DG
E
CU
RB
AS
PH
ALT
E
DG
E
CU
RB
G METER
GK
GK
WK WK
HANDRAIL
SIGN
CB
C/L OF SURFACE
CU
RB
C
UT
AS
PH
ALT
E
DG
E
CU
RB
CU
RB
CB
BOL
BOL
BOL
BOL
PARKING
CURB
BSP
G METER
H
MH
MH
CB
CB
CU
RB
AS
PH
ALT
E
DG
E
CU
RB
C
UT
CB
CU
RB
C
UT
CU
RB
CU
RB
AS
PH
ALT
E
DG
E
GK
SIGN
C/L O
F R
OA
D
CONCRETE
AREA
G METER
GUIDE RAIL
WK
MH
MH
SIGN
SIGN
C
U
R
B
C
U
T
CURB CUT
ELECTRICAL
BOX
LS
CB
S
P
E
E
DB
U
M
P
MH
SIGN
SIGN
A
S
P
H
A
L
T
E
D
G
E
CB
A
S
P
H
A
L
T
E
D
G
E
C
U
R
B
LS
BOL
G METER
WK
WK
GUIDE RAIL
SIGN
MH
BACK OF CURB
CURB
ASPHALT
EDGE
CONCRETE AREA
C
U
R
B
C
U
T
LS
CU
RB
C
UT
C
U
R
B
CU
RB
AS
PH
ALT
E
DG
E
CU
RB
C
UT
SIGNS
C
U
R
B
VENT
OVERHANG
RETAINING WALL
HANDRAIL
STEPS
HANDRAIL
ASPHALT EDGE
AS
PH
ALT
E
DG
E
SIGN
CURB CUT
C
U
R
B
WK
WK
GUIDE RAIL
AS
PH
ALT
E
DG
E
CU
RB
ASPHALT EDGE
1-STOREY
BRICK BUILDING
1-STOREY
BRICK BUILDING
1-STOREY
BRICK BUILDING
1-STOREY
BRICK BUILDING
COLUMNS
COLUMNS
BUILDING
OVERHANG
BUILDING
OVERHANG
1-STOREY
BRICK BUILDING
" BEER STORE "
MH
LS
CO
NC
RE
TE
SID
EW
ALK
C
U
R
B
C
U
T
OV
ER
HE
AD
E
LE
CT
RIC
CONCRETE WALKWAY
P
A
R
K
IN
G
C
U
R
BS
METAL GUARDS
PARKING
CURBS
CO
NC
RE
TE
AR
EA
CO
NC
RE
TE
SID
EW
ALK
GUIDE
RAIL
METAL STAIRS (4)
CONCRETE
AREA
B
O
A
R
D
F
E
N
C
E
C
H
A
I
N
L
I
N
K
F
E
N
C
E
LS
CH
AIN
LIN
K F
EN
CE
CONC.
STEP
CO
NC
RE
TE
S
ID
EW
ALK
CH
AIN
LIN
K F
EN
CE
A
S
P
H
A
L
T
C
O
N
C
R
E
T
E
S
I
D
E
W
A
L
K
A
S
P
H
A
L
T
E
D
G
E
C
U
R
B
PARKING
CURBS
SIGN
LS
S
P
E
E
D
B
U
M
P
HW
CO
NC
RE
TE
S
ID
EW
ALK
RE
TA
IN
IN
G W
ALLS
CO
NC
RE
TE
W
ALK
WA
Y
CONCRETE WALKWAY
RE
TA
IN
IN
G W
ALL
CO
NC
RE
TE
W
ALK
WA
Y
BOL
BOL
BOL
CB
C
U
R
B
C
U
T
CU
RB
C
UT
CU
RB
C
UT
CU
RB
C
UT
CU
RB
C
UT
CB
CB
STM MH
SAN MH
STM MH
CB
CB
C
U
R
B
C
U
T
CB
CB
C
U
R
B
C
U
R
B
CURB
C
U
R
B
C
U
T
C
U
R
B
C
U
T
CU
RB
C
UT
CU
RB
C
UT
CU
RB
C
UT
C
U
R
B
AS
PH
ALT
E
DG
E
C
O
N
C
R
E
T
E
W
A
L
K
LS
MH
C
U
R
B
C
U
T
C
U
R
B
C
U
T
C
U
R
B
C
U
T
C
U
R
B
C
U
T
CB
PARKING
CURBS
CURB
CUT
PARKING
CURBS
HANDRAIL
BOL
C
O
N
C
R
E
T
E
W
A
L
K
C
O
N
C
R
E
T
E
W
A
L
K
C
O
N
C
R
E
T
E
W
A
L
K
C
U
R
B
E
D
G
E
O
F
A
S
P
H
A
L
T
R
O
A
D
E
D
G
E
O
F
A
S
P
H
A
L
T
R
O
A
D
C
U
R
B
A
S
P
H
A
L
T
E
D
G
E
A
S
P
H
A
L
T
E
D
G
E
CB
MH
MH
MH
CH
AIN
LIN
K F
EN
CE
PA
VIN
G
ST
ON
ES
PA
VIN
G
ST
ON
ES
TELEPHONE
BOOTH
PA
VIN
G
ST
ON
ES
MH
MH
LS
WV
WV
LS
LS
MH
MH
HW
LS
SIGN
GARBAGE
BIN
HP
GM
TL
TL
HW
TL
TSC
HW
TL
SIGN HP
LS
LS
C/L OF DITCH
HP
HP
HP
LS
LS
SAN MH
CU
RB
C
UT
CU
RB
C
UT
C
U
R
B
C
U
T
C
U
R
B
C
U
T
CB
CB
CB
CO
NC
RE
TE
A
RE
A
C
U
R
B
C
U
T
MH
C/L OF ROAD
C
/L
O
F
R
O
A
D
C/L O
F R
OA
D
C/L O
F R
OA
D
CU
RB
CU
RB
AS
PH
ALT
E
DG
E
AS
PH
ALT
E
DG
E
CU
RB
CU
RB
AS
PH
ALT
E
DG
E
AS
PH
ALT
E
DG
E
C
U
R
B
C
U
T
C
U
R
B
C
U
T
C
U
R
B
C
U
T
C
U
R
B
C
U
T
C
U
R
B
C
U
T
SIGN
ASPHALT WALK
EDGE OF A
SPHALT
ASPHALT
ASPHALT
ASPHALT WALK
EDGE OF ASPHALT
ED
GE
O
F A
SP
HA
LT
R
OA
D
ED
GE
O
F A
SP
HA
LT
R
OA
D
ED
GE
O
F A
SP
HA
LT
R
OA
D
CO
NC
W
ALK
CONC WALK
CONC W
ALK
C
B
CB
CB
CB
CO
NC
W
ALK
C/L O
F R
OA
D
CURB & GUTTER
CURB & GUTTER
CU
RB
GU
TT
ER
GU
TT
ER
CU
RB
MH
CONCRETE PAD
A
S
P
H
A
L
T
E
D
G
E
C
U
R
B
C
U
T
C
U
R
B
C
U
T
C
/
L
O
F
R
O
A
D
BICYCLE
STANDS
WV
H
WV
H
WV WV
ASPHALT EDGE
PAINT LINE PAINT LINE
TRAFFIC LINE
TRAFFIC LINE
TRAFFIC LINE
TRAFFIC LINE
TRAFFIC LINE
TRAFFIC LINE
TRAFFIC LINE
TRAFFIC LINE
TRAFFIC LINE
TRAFFIC LINE
ASPHALT EDGE
ASPHALT EDGE
CO
NC
RE
TE
W
ALK
AS
PH
ALT
E
DG
E
AS
PH
ALT
E
DG
E
LS
TL
HP
LS
HW
SIGN
LS
HP
TO
P O
F S
LO
PE
BO
TT
OM
O
F S
LO
PE
C
U
R
B
A
S
P
H
A
L
T
E
D
G
E
A
S
P
H
A
L
T
E
D
G
E
C
U
R
B
CU
RB
AS
PH
ALT
E
DG
E
AS
PH
ALT
E
DG
E
CU
RB
BOARD
FENC
E
1
5
9
1
5
8
1
6
0
1
6
0
BE
ME
RS
YD
E P
AR
K
WK
EGLINTON AVENUE WEST
WATERFORD DRIVE
WIN
CO
TT
D
RIV
E
W
I
D
D
I
C
O
M
B
E
H
I
L
L
102
1.99
0.90
101
0.27
0.90
FIGURE 2.dwg - Existing Conditions \\thfiler1.mmm.ca\ENVDATA$\1441 Projects by Job Number\2018\15M-00048-03-SW1 Richview Square - Update\4. CAD\FIGURES\ Mar 12, 2019 - 12:52pmFIGURE 2.dwg - Existing Conditions \\thfiler1.mmm.ca\ENVDATA$\1441 Projects by Job Number\2018\15M-00048-03-SW1 Richview Square - Update\4. CAD\FIGURES\ Mar 12, 2019 - 12:52pm
0 10 3020 40 50m
LEGEND
SITE BOUNDARY
SUB-CATCHMENT BOUNDARY
101
0.27
0.90
SUB-CATCHMENT ID.
DRAIANGE AREA (ha)
RUNOFF COEFFICIENT
OVERLAND FLOW DIRECTION
WSP March 2019 Page 8
Stormwater Management Report Project No. 15M-00048-03
Montrin Richview GP Inc.
3 Post-Development Conditions
3.1 General
The proposed development consists of the construction of 3 new residential and commercial
mixed-use buildings. The proposed Building A will be 20 storeys, Building B will be 19 storeys,
and both Buildings C and E will be 12 storeys. Buildings B, C, and E will be connected. A
common underground parking structure will be shared by each of the buildings, with the
parking structure underlying almost the entire development footprint. Vehicular access to the
site will be provided via Wincott Drive, Eglinton Avenue West and Widdicombe Hill. The
loading areas and ramp to the basement parking will be entirely covered by the canopy of the
building above.
The site will have two separate stormwater control cisterns and as such, the proposed
development will be divided into two catchments – 201 and 202. Note that due to site grading
and layout, these catchments are slightly different than the existing catchments. Catchment
201, which includes Building A, will have a total area of 0.40 ha, while Catchment 202 will
control an area of 1.86 ha which will include Buildings B, C, and E. In accordance with the
Toronto Municipal Code, a green roof area of 368 m2 for Building A (located on the twentieth
storey) and a combined area of 5,070 m² for Buildings B, C and E (located on the third, twelfth,
thirteenth, and nineteenth storeys) shall be provided. An area breakdown for the new site
layout is provided below in Tables 5 and 6. Please refer to Figure 3 for details of the post-
development condition land-uses and stormwater catchments.
Table 5: Proposed Conditions Area Breakdown – Catchment 201
Land-Use Area (m2) % Coverage Runoff Coefficient, C
Pervious At-Grade 482 11.9 0.25
Impervious At-Grade 2,237 55.3 0.90
Impervious Roof 959 23.7 0.90
Green Roof 368 9.1 0.45
Total Site Area 4,047 100 0.78
Stormwater Management Report Project No. 15M-00048-03 Montrin Richview GP Inc.
WSP March 2019
Page 9
Table 6: Proposed Conditions Area Breakdown – Catchment 202
Land-Use Area (m2) % Coverage Runoff Coefficient, C
Pervious At-Grade 4,496 24.1 0.25
Impervious At-Grade 7,012 37.6 0.90
Impervious Roof 2,069 11.1 0.90
Green Roof 5,070 27.2 0.45
Total Site Area 18,646 100 0.62
PROPERTY LINE
PR
OP
ER
TY
LIN
E
PROPERTY LINE
PR
OP
ER
TY
LIN
E
PROPERTY LINE
PR
OP
ER
TY
LIN
EP
RO
PE
RT
Y LIN
E
PR
OP
ER
TY
LIN
E
PROPERTY LINE
PR
OP
ER
TY
LIN
E
PROPERTY LINE
P
R
O
P
E
R
T
Y
L
I
N
E
PR
OP
ER
TY
LIN
E
1
A421
APPROXIMATE LOCATION OF
PROPOSED SWM TANK
APPROXIMATE
LOCATION OF
PROPOSED SWM TANK
201
0.40
0.78
202
1.86
0.62
FIGURE 3.dwg - Proposed Conditions J:\1441 Projects by Job Number\2018\15M-00048-03-SW1 Richview Square - Update\4. CAD\FIGURES\ Mar 12, 2019 - 12:53pmFIGURE 3.dwg - Proposed Conditions J:\1441 Projects by Job Number\2018\15M-00048-03-SW1 Richview Square - Update\4. CAD\FIGURES\ Mar 12, 2019 - 12:53pm
0 10 3020 40 50m
LEGEND
SITE BOUNDARY
SUB-CATCHMENT BOUNDARY
201
0.40
0.76
SUB-CATCHMENT ID.
DRAIANGE AREA (ha)
RUNOFF COEFFICIENT
GREEN ROOF AREA
ROOF AREA
AT-GRADE SOFT LANDSCAPING
Stormwater Management Report Project No. 15M-00048-03 Montrin Richview GP Inc.
WSP March 2019
Page 11
3.2 Water Balance
As noted in Section 1.4, the WWFMG state that the proponent should target the retention of 5
mm of stormwater runoff from all surfaces, in order to ensure 50% of the total average annual
rainfall volume is retained on site.
For both Catchments 201 and 202, the primary mechanism to capture rainwater will be a
stormwater cistern with a dedicated sump volume for re-use purposes. Discharge from all roof
and at-grade areas will be directed to the underground cisterns. Allowing for an initial abstraction
of 1 mm for all impervious surfaces and 5 mm for all pervious surfaces results in a water balance
volume of 12.8 m3 and 36.3 m3 for Catchment 201 and 202, respectively.
The re-use methods for the captured stormwater are still being assessed in conjunction with the
mechanical design of the building’s water supply systems. Proposed re-use options include
flushing of toilets in the interior amenity areas on the ground floor level, irrigation of the green
roof and landscaped areas as well as any additional non-potable demand in the communal
building areas. It is believed that sufficient opportunities exist within the development to re-use
the full volume of retained stormwater within the required drawdown time. The mechanical
design of the rainwater re-use pump systems from the cistern will ensure that the cistern is empty
prior to switching to the City’s water supply. A summary of the water balance provision on site is
provided below in Tables 7 and 8.
Table 7: Water Balance – Catchment 201
Surface Type Area
(m2)
5 mm
Volume
(m3)
Initial
Abstraction
(m)
Volume
Abstracted
(m3)
Water
Balance
(m3)
Pervious At-Grade 482 2.41 0.005 2.41 0.00
Impervious At-Grade 2,237 11.19 0.001 2.24 8.95
Impervious Roof 959 4.80 0.001 0.96 3.84
Green Roof 368 1.84 0.005 1.84 0.00
Total Site Area 4,047 20.23 - 7.45 12.79
WSP March 2019 Page 12
Stormwater Management Report Project No. 15M-00048-03
Montrin Richview GP Inc.
Table 8: Water Balance – Catchment 202
Surface Type Area
(m2)
5 mm
Volume
(m3)
Initial
Abstraction
(m)
Volume
Abstracted
(m3)
Water
Balance
(m3)
Pervious At-Grade 4,496 22.48 0.005 22.48 0.00
Impervious At-Grade 7,012 35.06 0.001 7.01 28.05
Impervious Roof 2,069 10.35 0.001 2.07 8.28
Green Roof 5,070 25.35 0.005 25.35 0.00
Total Site Area 18,646 93.23 - 56.91 36.32
3.3 Water Quality Control
The water quality criteria in the WWFMG is long-term removal of 80% TSS on an annual
loading basis. A media filtration unit for each catchment is proposed to treat runoff from the at-
grade areas. The roof is considered clean for the purposes of the water quality and does not
require treatment.
The proposed unit for Catchment 201 is a JF4-1-1 (or approved equivalent) while the proposed
unit for Catchment 202 is a JF6-5-1 (or approved equivalent). These units will provide each
catchment with TSS removal for the full inflow areas and will be installed upstream of the
cisterns in an offline configuration which includes bypass manholes. Flows in excess of the
treatment rate will flow directly to the stormwater cisterns.
Please note that the media filtration unit calculations are for preliminary analysis only. It will be
the Contractor’s responsibility to ensure that the selected units meet water quality
requirements per this stormwater management plan. Detailed sizing reports generated by the
manufacturer are included within Appendix C.
3.4 Erosion Control
As mentioned in Section 1.4, this development is an overall small footprint development.
According to the WWFMG, ‘For small infill/redevelopment sites <2 ha, erosion control in the
form of stormwater detention is normally not required, provided the on-site minimum runoff
retention from a small design rainfall event (typically 5 mm) is achieved under the Water
Balance Criteria.’
Stormwater Management Report Project No. 15M-00048-03 Montrin Richview GP Inc.
WSP March 2019
Page 13
The site area for each of the catchments (0.40 ha for Catchment 201 and 1.86 ha for
Catchment 202) is below the 2.0 ha guideline, and the 5 mm water balance requirement has
been addressed – therefore additional measures for erosion control are not recommended.
3.5 Water Quantity Control
The target release rate to the municipal sewer system from the site for Catchments 201 and
202 is 33.1 L/s and 243.9 L/s, respectively. This is equivalent to the peak runoff rate under pre-
development conditions during a 2 year design storm event using a runoff coefficient of 0.50
for both catchments.
A HydroCAD model of the project was constructed and utilized to determine the required
storage volume in the stormwater cistern, and to calculate the discharge rates achieved by the
proposed flow controls under all storm events. The Modified Rational Method (an inherent
subroutine of the HydroCAD software) has been used for the modelling exercise.
An emergency overflow will be provided at the top of the cistern, with discharge to street level
and the adjacent right of way. This will prevent flow backing up into the building pipework if the
primary outlet is blocked, or if a storm event in excess of the 100-year return period occurs.
For Catchment 201, the cistern was designed to provide a storage volume of 160 m3, with a
base area of 80 m². The primary gravity outlet is set 0.20 m above the internal base, to provide
a sufficient re-use volume to satisfy the water balance. A 100 mm diameter orifice plate is
proposed as the primary outlet – this provides sufficient flow restriction to control release rates
to within the target rate set by the WWFMG.
For Catchment 202, the cistern was designed to provide a storage volume of 400 m3, with a
base area of 200 m² and the primary gravity outlet set 0.20 m above the internal base. Based
on the tank dimensions this will provide sufficient volume to satisfy the water balance. A 250
mm diameter orifice tube is proposed as the primary outlet – this provides sufficient flow
restriction to control release rates to within the target rate set by the WWFMG.
A summary of the modelling results is provided below in Tables 9 and 10. HydroCAD
modelling output is provided in Appendix B.
WSP March 2019 Page 14
Stormwater Management Report Project No. 15M-00048-03
Montrin Richview GP Inc.
Table 9: Summary of Modelling Results – Catchment 201
Return Period
(Years)
Modelled Post-
Development Peak
Flow Rate (L/s)
Target
Release Rate
(L/s)
Utilized
Cistern
Storage (m3)
Peak Water
Elevation in
Cistern (m)
Time of
Peak
(min)
2 13.8
33.1
55.1 0.689 27
5 17.7 77.5 0.969 30
10 20.0 93.3 1.167 30
25 22.0 108.6 1.358 33
50 24.3 128.7 1.608 36
100 26.0 143.9 1.799 39
Table 10: Summary of Modelling Results – Catchment 202
Return Period
(Years)
Modelled Post-
Development Peak
Flow Rate (L/s)
Target
Release Rate
(L/s)
Utilized
Cistern
Storage (m3)
Peak Water
Elevation in
Cistern (m)
Time of
Peak
(min)
2 98.3
243.9
128.9 0.644 13
5 133.2 182.3 0.911 15
10 154.6 222.9 1.115 15
25 172.7 262.1 1.310 16
50 194.5 315.1 1.576 18
100 210.0 356.4 1.782 19
The modelling results demonstrate that the post-development peak flow rates for all events up
to the 100-year storm are lower than the target release rate established in accordance with the
WWFMG. The maximum required storage volume to control the 100-year post-development
runoff is 143.9 m3 and 356.4 m3 for the cisterns in Catchment 201 and 202 respectively. Note
that the total utilized storage volumes include the sump volume designated for re-use.
As all flow rates are controlled by the project cistern, the rainfall intensity and storm duration
resulting in the maximum utilized storage produces the largest flows. This has been iteratively
determined at td = 39 and td = 19 minutes (for the 100-year event) for Catchment 201 and 202
respectively.
Stormwater Management Report Project No. 15M-00048-03 Montrin Richview GP Inc.
WSP March 2019
Page 15
3.6 Hydrogeology and Groundwater Characterization
A hydrogeological investigation was conducted in March 2019 by Brown Associates Limited in
order to assess the groundwater conditions and soil characteristics of the development, and
test for the presence of groundwater contamination.
Groundwater was found to enter the site; it does not meet the City of Toronto’s Sewer By-Law
requirements for discharge to the sanitary sewer but is proposed to be treated and discharged
to the sanitary sewer. The groundwater sample, collected on February 16, 2018, exceeds the
sanitary sewer standards for total suspended solids only.
As groundwater is not currently proposed to be released through the stormwater system, it will
not impact the SWM design. The hydrogeological investigation report will be submitted
separately from this report.
WSP March 2019 Page 16
Stormwater Management Report Project No. 15M-00048-03
Montrin Richview GP Inc.
4 Conclusions A stormwater management plan has been prepared to support the rezoning application for the
proposed redevelopment of 4620 Eglinton Avenue West and 250 Wincott Drive in the City of
Toronto. The key points are summarized below.
WATER BALANCE
The site is required to retain 5 mm of runoff from each rainfall event for re-use on site to meet
the WWFMG requirements. Water balance strategies will be addressed through provision of
green roof surfaces and sump volume (equivalent to the post-development 5 mm runoff
volume) at the base of the proposed cisterns for both Catchments 201 and 202. Re-use
methods for the captured stormwater are still being assessed in conjunction with the
mechanical design of the buildings’ water supply systems.
WATER QUANTITY
Runoff from the area within Catchment 201 will be directed to a 160 m3 stormwater cistern and
runoff from Catchment 202 will be directed to a 400 m3 stormwater cistern. Post-development
flows have been controlled to below 33.1 L/s for Catchment 201 and 243.9 L/s for Catchment
202 in compliance with the target release rate to the municipal storm sewer system.
WATER QUALITY
The target of 80% TSS removal can be achieved through the use of approved stand-alone
media filtration units. Jellyflish Filter models JF4-1-1, and JF6-5-1 from Imbrium have been
sized to treat at grade areas in Catchment 201 and 202 respectively.
GROUNDWATER
The groundwater on site is not proposed to be released through the stormwater system;
therefore, it will not impact the SWM design.
The report has demonstrated that the proposed stormwater management strategy will address
stormwater management related impacts from this project in adherence with City of Toronto’s
Wet Weather Flow Management Guidelines.
Respectfully submitted,
WSP
APPENDIX
A STORMWATER
MANAGEMENT
CALCULATIONS
By: Date: 3/8/2019 Page:
Checked: Checked: 3/8/2019 1
Calculation of existing runoff rate is undertaken using the Rational Method: Q = 2.78 CIA
Where: Q = Peak flow rate (litres/second)
C = Runoff coefficient
I = Rainfall intensity (mm/hour)
A = Catchment area (hectares)
Project Area, A 0.27 hectares
Runoff Coef, C 0.90
Where: A and C = Parameters defined in WWFMG section 3.1.
I = Rainfall intensity (mm/hour)
T = Time of concentration (hours)
2 5 10 25 50 100
21.8 32.0 38.7 45.2 53.5 59.7
-0.78 -0.79 -0.80 -0.80 -0.80 -0.80
10 10 10 10 10 10
0.167 0.167 0.167 0.167 0.167 0.167
88.2 131.8 162.3 189.5 224.3 250.3
59.6 89.0 109.6 128.0 151.5 169.1
0.060 0.089 0.110 0.128 0.152 0.169
** Note recommended minimum value for time of concentration for small sites (<2.0ha) is 10 minutes.
Satellite
Stormwater Management
CalculationsProject: Richview Square No.: 15M-00048-03
Existing Offsite Discharge Rate
Catchment 101
SE
SP
I (mm/hr)
Q (litres/sec)
Q (m3/sec)
Return Period (Years)
A
C
T (mins) **
T (hrs)
CATI =
By: Date: 3/8/2019 Page:
Checked: Checked: 3/8/2019 2
Calculation of existing runoff rate is undertaken using the Rational Method: Q = 2.78 CIA
Where: Q = Peak flow rate (litres/second)
C = Runoff coefficient
I = Rainfall intensity (mm/hour)
A = Catchment area (hectares)
Project Area, A 1.99 hectares
Runoff Coef, C 0.60
Where: A and C = Parameters defined in WWFMG section 3.1.
I = Rainfall intensity (mm/hour)
T = Time of concentration (hours)
2 5 10 25 50 100
21.8 32.0 38.7 45.2 53.5 59.7
-0.78 -0.79 -0.80 -0.80 -0.80 -0.80
10 10 10 10 10 10
0.167 0.167 0.167 0.167 0.167 0.167
88.2 131.8 162.3 189.5 224.3 250.3
292.7 437.5 538.6 629.1 744.6 830.9
0.293 0.437 0.539 0.629 0.745 0.831
** Note recommended minimum value for time of concentration for small sites (<2.0ha) is 10 minutes.
Satellite
Stormwater Management
CalculationsProject: Richview Square No.: 15M-00048-03
Existing Offsite Discharge Rate
Catchment 102
SE
SP
I (mm/hr)
Q (litres/sec)
Q (m3/sec)
Return Period (Years)
A
C
T (mins) **
T (hrs)
CATI =
By: Date: 3/8/2019 Page:
Checked: Checked: 3/8/2019 3
Calculation of existing runoff rate is undertaken using the Rational Method: Q = 2.78 CIA
Where: Q = Peak flow rate (litres/second)
C = Runoff coefficient
I = Rainfall intensity (mm/hour)
A = Catchment area (hectares)
Project Area, A 0.27 hectares
Runoff Coef, C* 0.50
Where: A and C = Parameters defined in WWFMG section 3.1.
I = Rainfall intensity (mm/hour)
T = Time of concentration (hours)
2 5 10 25 50 100
21.8 32.0 38.7 45.2 53.5 59.7
-0.78 -0.79 -0.80 -0.80 -0.80 -0.80
10 10 10 10 10 10
0.167 0.167 0.167 0.167 0.167 0.167
88.2 131.8 162.3 189.5 224.3 250.3
33.1 49.5 60.9 71.1 84.2 93.9
0.033 0.049 0.061 0.071 0.084 0.094
** Note recommended minimum value for time of concentration for small sites (<2.0ha) is 10 minutes.
Allowable release rate to municipal storm sewer system is therefore 33.1 litres/second.
(As per City of Toronto WWFMG section 2.2.3.7)
Satellite
15M-00048-03No.:Richview Square
SP
SE
A
Allowable Offsite Discharge Rate
Catchment 101
Return Period (Years)
* Note - actual site runoff coefficient is approximately 0.90, however City of Toronto WWFMG states maximum runoff
coefficient to be used in calculation of pre-development peak flow is 0.50 (section 2.2.3.8).
Project:Stormwater Management
Calculations
Q (m3/sec)
Q (litres/sec)
I (mm/hr)
T (hrs)
T (mins) **
C
CATI =
By: Date: 3/8/2019 Page:
Checked: Checked: 3/8/2019 4
Calculation of existing runoff rate is undertaken using the Rational Method: Q = 2.78 CIA
Where: Q = Peak flow rate (litres/second)
C = Runoff coefficient
I = Rainfall intensity (mm/hour)
A = Catchment area (hectares)
Project Area, A 1.99 hectares
Runoff Coef, C* 0.50
Where: A and C = Parameters defined in WWFMG section 3.1.
I = Rainfall intensity (mm/hour)
T = Time of concentration (hours)
2 5 10 25 50 100
21.8 32.0 38.7 45.2 53.5 59.7
-0.78 -0.79 -0.80 -0.80 -0.80 -0.80
10 10 10 10 10 10
0.167 0.167 0.167 0.167 0.167 0.167
88.2 131.8 162.3 189.5 224.3 250.3
243.9 364.6 448.8 524.2 620.5 692.4
0.244 0.365 0.449 0.524 0.621 0.692
** Note recommended minimum value for time of concentration for small sites (<2.0ha) is 10 minutes.
Allowable release rate to municipal storm sewer system is therefore 243.9 litres/second.
(As per City of Toronto WWFMG section 2.2.3.7)
Satellite
I (mm/hr)
Q (litres/sec)
Q (m3/sec)
* Note - actual site runoff coefficient is approximately 0.60, however City of Toronto WWFMG states maximum runoff
coefficient to be used in calculation of pre-development peak flow is 0.50 (section 2.2.3.8).
Return Period (Years)
A
C
T (mins) **
T (hrs)
Stormwater Management
CalculationsProject: Richview Square No.: 15M-00048-03
Allowable Offsite Discharge Rate
Catchment 102
SE
SP
CATI =
By: Date: 3/8/2019 Page:
Checked: Checked: 3/8/2019 5
The City of Toronto Wet Weather Flow Management Guidelines (WWFMG) require a site "to retain water on-site to the extent practicable,
- Section 2.2.1.1 (a)
The current area measurements and land use types for the site are as follows:
Land Use Area (m2) Runoff C Impervious CN % Coverage
Pervious At-Grade 482 0.25 0% 74 11.9
Impervious At-Grade 2,237 0.90 100% 98 55.3
Impervious Roof 959 0.90 100% 98 23.7
Green Roof 368 0.45 0% 81 9.1
Total Site Area: 4,047 0.78 79% 94 100.0
Pervious 482 2.41 0.005 2.41 0.00
Impervious At-Grade 2,237 11.19 0.001 2.24 8.95
Roof 959 4.80 0.001 0.96 3.84
Green Roof 368 1.84 0.005 1.84 0.00
Total Site Area: 4,047 20.23 - 7.45 12.79
producing any runoff.
weights).
It is assumed that the remaining hard surfaces on the site can abstract 1 mm of rainfall, and that all soft landscaped areas
can absorb 5 mm
Therefore, volume of runoff during a 5 mm storm event: 12.79 m3
For the purposes of the water balance calculation it is assumed that green roofs can accept 10 mm of rainfall without
Water
Balance
(m3)
IA
(m)
SE
SP
In this case, the minimum on-site runoff retention will require the site to retain all runoff from 5 mm storm event through evapotranspiration
infiltration, or rainwater reuse. WWFMG Section 2.2.1.1 (d).
to achieve the same level of annual volume of overland runoff allowable from the development site under pre-development conditions”.
Abstractions and Water Balance
Catchment 201
This is supported by EPA analysis of green roof manufacturer data sheets (dry unit weights versus saturated unit
No.:Project: 15M-00048-03Richview SquareStormwater Management
Calculations
Surface TypeArea
(m2)
Volume
Abstracted
(m3)
5 mm
Volume
(m3)
By: Date: 3/8/2019 Page:
Checked: Checked: 3/8/2019 6
The City of Toronto Wet Weather Flow Management Guidelines (WWFMG) require a site "to retain water on-site to the extent practicable,
- Section 2.2.1.1 (a)
The current area measurements and land use types for the site are as follows:
Land Use Area (m2) Runoff C Impervious CN % Coverage
Pervious At-Grade 4,496 0.25 0% 74 24.1
Impervious At-Grade 7,012 0.90 100% 98 37.6
Impervious Roof 2,069 0.90 100% 98 11.1
Green Roof 5,070 0.45 0% 81 27.2
Total Site Area: 18,646 0.62 49% 88 100
Pervious 4,496 22.48 0.005 22.48 0.00
Impervious At-Grade 7,012 35.06 0.001 7.01 28.05
Roof 2,069 10.35 0.001 2.07 8.28
Green Roof 5,070 25.35 0.005 25.35 0.00
Total Site Area: 18,646 93.23 - 56.91 36.32
producing any runoff.
weights).
It is assumed that the remaining hard surfaces on the site can abstract 1 mm of rainfall, and that all soft landscaped areas
can absorb 5 mm
Therefore, volume of runoff during a 5 mm storm event: 36.32 m3
For the purposes of the water balance calculation it is assumed that green roofs can accept 10 mm of rainfall without
This is supported by EPA analysis of green roof manufacturer data sheets (dry unit weights versus saturated unit
to achieve the same level of annual volume of overland runoff allowable from the development site under pre-development conditions”.
In this case, the minimum on-site runoff retention will require the site to retain all runoff from 5 mm storm event through evapotranspiration
infiltration, or rainwater reuse. WWFMG Section 2.2.1.1 (d).
Surface TypeArea
(m2)
IA
(m)
Volume
Abstracted
(m3)
5 mm
Volume
(m3)
Water
Balance
(m3)
Stormwater Management
CalculationsProject: Richview Square No.: 15M-00048-03
Abstractions and Water Balance
Catchment 202
SE
SP
APPENDIX
B HYDROLOGIC
MODEL OUTPUT
(HydroCAD)
Catchment 201 (A)
3
Impervious Roof
4
Pervious Landscaping
7S
Green Roof
8S
At-Grade Impervious
5
SWM Tank (33.1L/s)
6P
Green Roof
Routing Diagram for Richview SquarePrepared by WSP Canada Inc., Printed 3/8/2019
HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Subcat Reach Pond Link
Richview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 2HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Area Listing (selected nodes)
Area
(sq-meters)
C Description
(subcatchment-numbers)
368.0 1.00 Green Roof (7S)
959.0 0.90 Impervious Roof (3)
2,237.0 0.90 Paved Areas (8S)
482.0 0.25 Pervious Area (4)
4,046.0 0.83 TOTAL AREA
Richview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 3HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Soil Listing (selected nodes)
Area
(sq-meters)
Soil
Group
Subcatchment
Numbers
0.0 HSG A
0.0 HSG B
0.0 HSG C
0.0 HSG D
4,046.0 Other 3, 4, 7S, 8S
4,046.0 TOTAL AREA
Richview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 4HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Ground Covers (selected nodes)
HSG-A
(sq-meters)
HSG-B
(sq-meters)
HSG-C
(sq-meters)
HSG-D
(sq-meters)
Other
(sq-meters)
Total
(sq-meters)
Ground
Cover
Subcatchment
Numbers
0.0 0.0 0.0 0.0 368.0 368.0 Green Roof
0.0 0.0 0.0 0.0 959.0 959.0 Impervious
Roof
0.0 0.0 0.0 0.0 2,237.0 2,237.0 Paved Areas
0.0 0.0 0.0 0.0 482.0 482.0 Pervious
Area
0.0 0.0 0.0 0.0 4,046.0 4,046.0 TOTAL
AREA
Toronto 2-Year Duration=39 min, Inten=30.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 5HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=959.0 m² 0.00% Impervious Runoff Depth=18 mmSubcatchment 3: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0073 m³/s 17.1 m³
Runoff Area=482.0 m² 0.00% Impervious Runoff Depth=5 mmSubcatchment 4: Pervious Landscaping Tc=10.0 min C=0.25 Runoff=0.0010 m³/s 2.4 m³
Runoff Area=368.0 m² 100.00% Impervious Runoff Depth=20 mmSubcatchment 7S: Green Roof Tc=10.0 min C=1.00 Runoff=0.0031 m³/s 7.3 m³
Runoff Area=2,237.0 m² 0.00% Impervious Runoff Depth=18 mmSubcatchment 8S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.0171 m³/s 39.9 m³
Peak Elev=0.678 m Storage=54.2 m³ Inflow=0.0273 m³/s 65.9 m³Pond 5: SWM Tank (33.1L/s) Outflow=0.0137 m³/s 65.5 m³
Peak Elev=100.011 m Storage=4.8 m³ Inflow=0.0031 m³/s 7.3 m³Pond 6P: Green Roof Outflow=0.0020 m³/s 6.5 m³
Total Runoff Area = 4,046.0 m² Runoff Volume = 66.7 m³ Average Runoff Depth = 16 mm90.90% Pervious = 3,678.0 m² 9.10% Impervious = 368.0 m²
Toronto 2-Year Duration=39 min, Inten=30.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 6HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 3: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0073 m³/s @ 0.17 hrs, Volume= 17.1 m³, Depth= 18 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=39 min, Inten=30.5 mm/hr
Area (m²) C Description
959.0 0.90 Impervious Roof
959.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 3: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.008
0.007
0.007
0.006
0.006
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Toronto 2-Year
Duration=39 min,
Inten=30.5 mm/hr
Runoff Area=959.0 m²
Runoff Volume=17.1 m³
Runoff Depth=18 mm
Tc=10.0 min
C=0.90
0.0073 m³/s
Toronto 2-Year Duration=39 min, Inten=30.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 7HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 4: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0010 m³/s @ 0.17 hrs, Volume= 2.4 m³, Depth= 5 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=39 min, Inten=30.5 mm/hr
Area (m²) C Description
482.0 0.25 Pervious Area
482.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 4: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0
0
0
Toronto 2-Year
Duration=39 min,
Inten=30.5 mm/hr
Runoff Area=482.0 m²
Runoff Volume=2.4 m³
Runoff Depth=5 mm
Tc=10.0 min
C=0.25
0.0010 m³/s
Toronto 2-Year Duration=39 min, Inten=30.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 8HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 7S: Green Roof
Runoff = 0.0031 m³/s @ 0.17 hrs, Volume= 7.3 m³, Depth= 20 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=39 min, Inten=30.5 mm/hr
Area (m²) C Description
368.0 1.00 Green Roof
368.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 7S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.003
0.003
0.003
0.003
0.003
0.002
0.002
0.002
0.002
0.002
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0
Toronto 2-Year
Duration=39 min,
Inten=30.5 mm/hr
Runoff Area=368.0 m²
Runoff Volume=7.3 m³
Runoff Depth=20 mm
Tc=10.0 min
C=1.00
0.0031 m³/s
Toronto 2-Year Duration=39 min, Inten=30.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 9HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 8S: At-Grade Impervious
Runoff = 0.0171 m³/s @ 0.17 hrs, Volume= 39.9 m³, Depth= 18 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=39 min, Inten=30.5 mm/hr
Area (m²) C Description
2,237.0 0.90 Paved Areas
2,237.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 8S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.019
0.018
0.017
0.016
0.015
0.014
0.013
0.012
0.011
0.01
0.009
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Toronto 2-Year
Duration=39 min,
Inten=30.5 mm/hr
Runoff Area=2,237.0 m²
Runoff Volume=39.9 m³
Runoff Depth=18 mm
Tc=10.0 min
C=0.90
0.0171 m³/s
Toronto 2-Year Duration=39 min, Inten=30.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 10HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 5: SWM Tank (33.1L/s)
Inflow Area = 4,046.0 m², 9.10% Impervious, Inflow Depth > 16 mm for 2-Year eventInflow = 0.0273 m³/s @ 0.65 hrs, Volume= 65.9 m³Outflow = 0.0137 m³/s @ 0.74 hrs, Volume= 65.5 m³, Atten= 50%, Lag= 5.4 minPrimary = 0.0137 m³/s @ 0.74 hrs, Volume= 65.5 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 80.0 m² Storage= 16.0 m³Peak Elev= 0.678 m @ 0.74 hrs Surf.Area= 80.0 m² Storage= 54.2 m³ (38.2 m³ above start)
Plug-Flow detention time= 60.6 min calculated for 49.5 m³ (75% of inflow)Center-of-Mass det. time= 38.5 min ( 67.6 - 29.1 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 160.0 m³ 1.00 mW x 80.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 100 mm Vert. Orifice/Grate C= 0.600
Primary OutFlow Max=0.0137 m³/s @ 0.74 hrs HW=0.678 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0137 m³/s @ 1.74 m/s)
Pond 5: SWM Tank (33.1L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Inflow Area=4,046.0 m²
Peak Elev=0.678 m
Storage=54.2 m³
0.0273 m³/s
0.0137 m³/s
Toronto 2-Year Duration=39 min, Inten=30.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 11HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 6P: Green Roof
Inflow Area = 368.0 m²,100.00% Impervious, Inflow Depth = 20 mm for 2-Year eventInflow = 0.0031 m³/s @ 0.17 hrs, Volume= 7.3 m³Outflow = 0.0020 m³/s @ 0.71 hrs, Volume= 6.5 m³, Atten= 36%, Lag= 32.4 minPrimary = 0.0020 m³/s @ 0.71 hrs, Volume= 6.5 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.011 m @ 0.71 hrs Surf.Area= 736.0 m² Storage= 4.8 m³
Plug-Flow detention time= 48.7 min calculated for 6.4 m³ (88% of inflow)Center-of-Mass det. time= 46.8 min ( 71.3 - 24.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 0.7 m³ 1.00 mW x 368.00 mL x 0.01 mH Green Roof Media Storage3.7 m³ Overall x 20.0% Voids
#2 100.000 m 29.4 m³ 1.00 mW x 368.00 mL x 0.08 mH Green Roof
30.2 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 3.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0020 m³/s @ 0.71 hrs HW=100.011 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0020 m³/s @ 0.19 m/s)
Pond 6P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.003
0.003
0.003
0.003
0.003
0.002
0.002
0.002
0.002
0.002
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0
Inflow Area=368.0 m²
Peak Elev=100.011 m
Storage=4.8 m³
0.0031 m³/s
0.0020 m³/s
Toronto 5-Year Duration=39 min, Inten=45.0 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 12HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=959.0 m² 0.00% Impervious Runoff Depth=26 mmSubcatchment 3: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0108 m³/s 25.2 m³
Runoff Area=482.0 m² 0.00% Impervious Runoff Depth=7 mmSubcatchment 4: Pervious Landscaping Tc=10.0 min C=0.25 Runoff=0.0015 m³/s 3.5 m³
Runoff Area=368.0 m² 100.00% Impervious Runoff Depth=29 mmSubcatchment 7S: Green Roof Tc=10.0 min C=1.00 Runoff=0.0046 m³/s 10.8 m³
Runoff Area=2,237.0 m² 0.00% Impervious Runoff Depth=26 mmSubcatchment 8S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.0252 m³/s 58.9 m³
Peak Elev=0.962 m Storage=77.0 m³ Inflow=0.0406 m³/s 97.5 m³Pond 5: SWM Tank (33.1L/s) Outflow=0.0176 m³/s 97.1 m³
Peak Elev=100.016 m Storage=6.5 m³ Inflow=0.0046 m³/s 10.8 m³Pond 6P: Green Roof Outflow=0.0033 m³/s 9.9 m³
Total Runoff Area = 4,046.0 m² Runoff Volume = 98.4 m³ Average Runoff Depth = 24 mm90.90% Pervious = 3,678.0 m² 9.10% Impervious = 368.0 m²
Toronto 5-Year Duration=39 min, Inten=45.0 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 13HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 3: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0108 m³/s @ 0.17 hrs, Volume= 25.2 m³, Depth= 26 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=39 min, Inten=45.0 mm/hr
Area (m²) C Description
959.0 0.90 Impervious Roof
959.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 3: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.012
0.011
0.011
0.01
0.01
0.009
0.009
0.008
0.008
0.007
0.007
0.006
0.006
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Toronto 5-Year
Duration=39 min,
Inten=45.0 mm/hr
Runoff Area=959.0 m²
Runoff Volume=25.2 m³
Runoff Depth=26 mm
Tc=10.0 min
C=0.90
0.0108 m³/s
Toronto 5-Year Duration=39 min, Inten=45.0 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 14HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 4: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0015 m³/s @ 0.17 hrs, Volume= 3.5 m³, Depth= 7 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=39 min, Inten=45.0 mm/hr
Area (m²) C Description
482.0 0.25 Pervious Area
482.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 4: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.002
0.002
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Toronto 5-Year
Duration=39 min,
Inten=45.0 mm/hr
Runoff Area=482.0 m²
Runoff Volume=3.5 m³
Runoff Depth=7 mm
Tc=10.0 min
C=0.25
0.0015 m³/s
Toronto 5-Year Duration=39 min, Inten=45.0 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 15HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 7S: Green Roof
Runoff = 0.0046 m³/s @ 0.17 hrs, Volume= 10.8 m³, Depth= 29 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=39 min, Inten=45.0 mm/hr
Area (m²) C Description
368.0 1.00 Green Roof
368.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 7S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.005
0.005
0.005
0.004
0.004
0.004
0.004
0.004
0.003
0.003
0.003
0.003
0.003
0.002
0.002
0.002
0.002
0.002
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0
Toronto 5-Year
Duration=39 min,
Inten=45.0 mm/hr
Runoff Area=368.0 m²
Runoff Volume=10.8 m³
Runoff Depth=29 mm
Tc=10.0 min
C=1.00
0.0046 m³/s
Toronto 5-Year Duration=39 min, Inten=45.0 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 16HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 8S: At-Grade Impervious
Runoff = 0.0252 m³/s @ 0.17 hrs, Volume= 58.9 m³, Depth= 26 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=39 min, Inten=45.0 mm/hr
Area (m²) C Description
2,237.0 0.90 Paved Areas
2,237.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 8S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 5-Year
Duration=39 min,
Inten=45.0 mm/hr
Runoff Area=2,237.0 m²
Runoff Volume=58.9 m³
Runoff Depth=26 mm
Tc=10.0 min
C=0.90
0.0252 m³/s
Toronto 5-Year Duration=39 min, Inten=45.0 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 17HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 5: SWM Tank (33.1L/s)
Inflow Area = 4,046.0 m², 9.10% Impervious, Inflow Depth > 24 mm for 5-Year eventInflow = 0.0406 m³/s @ 0.65 hrs, Volume= 97.5 m³Outflow = 0.0176 m³/s @ 0.75 hrs, Volume= 97.1 m³, Atten= 57%, Lag= 6.1 minPrimary = 0.0176 m³/s @ 0.75 hrs, Volume= 97.1 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 80.0 m² Storage= 16.0 m³Peak Elev= 0.962 m @ 0.75 hrs Surf.Area= 80.0 m² Storage= 77.0 m³ (61.0 m³ above start)
Plug-Flow detention time= 60.8 min calculated for 81.1 m³ (83% of inflow)Center-of-Mass det. time= 44.6 min ( 73.1 - 28.6 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 160.0 m³ 1.00 mW x 80.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 100 mm Vert. Orifice/Grate C= 0.600
Primary OutFlow Max=0.0176 m³/s @ 0.75 hrs HW=0.962 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0176 m³/s @ 2.24 m/s)
Pond 5: SWM Tank (33.1L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.044
0.042
0.04
0.038
0.036
0.034
0.032
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Inflow Area=4,046.0 m²
Peak Elev=0.962 m
Storage=77.0 m³
0.0406 m³/s
0.0176 m³/s
Toronto 5-Year Duration=39 min, Inten=45.0 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 18HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 6P: Green Roof
Inflow Area = 368.0 m²,100.00% Impervious, Inflow Depth = 29 mm for 5-Year eventInflow = 0.0046 m³/s @ 0.17 hrs, Volume= 10.8 m³Outflow = 0.0033 m³/s @ 0.70 hrs, Volume= 9.9 m³, Atten= 28%, Lag= 31.6 minPrimary = 0.0033 m³/s @ 0.70 hrs, Volume= 9.9 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.016 m @ 0.70 hrs Surf.Area= 736.0 m² Storage= 6.5 m³
Plug-Flow detention time= 41.5 min calculated for 9.9 m³ (92% of inflow)Center-of-Mass det. time= 39.8 min ( 64.3 - 24.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 0.7 m³ 1.00 mW x 368.00 mL x 0.01 mH Green Roof Media Storage3.7 m³ Overall x 20.0% Voids
#2 100.000 m 29.4 m³ 1.00 mW x 368.00 mL x 0.08 mH Green Roof
30.2 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 3.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0033 m³/s @ 0.70 hrs HW=100.016 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0033 m³/s @ 0.23 m/s)
Pond 6P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0
Inflow Area=368.0 m²
Peak Elev=100.016 m
Storage=6.5 m³
0.0046 m³/s
0.0033 m³/s
Toronto 10-Year Duration=39 min, Inten=54.6 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 19HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=959.0 m² 0.00% Impervious Runoff Depth=32 mmSubcatchment 3: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0131 m³/s 30.6 m³
Runoff Area=482.0 m² 0.00% Impervious Runoff Depth=9 mmSubcatchment 4: Pervious Landscaping Tc=10.0 min C=0.25 Runoff=0.0018 m³/s 4.3 m³
Runoff Area=368.0 m² 100.00% Impervious Runoff Depth=36 mmSubcatchment 7S: Green Roof Tc=10.0 min C=1.00 Runoff=0.0056 m³/s 13.1 m³
Runoff Area=2,237.0 m² 0.00% Impervious Runoff Depth=32 mmSubcatchment 8S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.0305 m³/s 71.5 m³
Peak Elev=1.161 m Storage=92.8 m³ Inflow=0.0496 m³/s 118.6 m³Pond 5: SWM Tank (33.1L/s) Outflow=0.0199 m³/s 118.1 m³
Peak Elev=100.018 m Storage=7.5 m³ Inflow=0.0056 m³/s 13.1 m³Pond 6P: Green Roof Outflow=0.0042 m³/s 12.2 m³
Total Runoff Area = 4,046.0 m² Runoff Volume = 119.5 m³ Average Runoff Depth = 30 mm90.90% Pervious = 3,678.0 m² 9.10% Impervious = 368.0 m²
Toronto 10-Year Duration=39 min, Inten=54.6 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 20HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 3: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0131 m³/s @ 0.17 hrs, Volume= 30.6 m³, Depth= 32 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=39 min, Inten=54.6 mm/hr
Area (m²) C Description
959.0 0.90 Impervious Roof
959.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 3: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.014
0.013
0.012
0.011
0.01
0.009
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Toronto 10-Year
Duration=39 min,
Inten=54.6 mm/hr
Runoff Area=959.0 m²
Runoff Volume=30.6 m³
Runoff Depth=32 mm
Tc=10.0 min
C=0.90
0.0131 m³/s
Toronto 10-Year Duration=39 min, Inten=54.6 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 21HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 4: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0018 m³/s @ 0.17 hrs, Volume= 4.3 m³, Depth= 9 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=39 min, Inten=54.6 mm/hr
Area (m²) C Description
482.0 0.25 Pervious Area
482.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 4: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.002
0.002
0.002
0.002
0.002
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Toronto 10-Year
Duration=39 min,
Inten=54.6 mm/hr
Runoff Area=482.0 m²
Runoff Volume=4.3 m³
Runoff Depth=9 mm
Tc=10.0 min
C=0.25
0.0018 m³/s
Toronto 10-Year Duration=39 min, Inten=54.6 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 22HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 7S: Green Roof
Runoff = 0.0056 m³/s @ 0.17 hrs, Volume= 13.1 m³, Depth= 36 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=39 min, Inten=54.6 mm/hr
Area (m²) C Description
368.0 1.00 Green Roof
368.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 7S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.006
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Toronto 10-Year
Duration=39 min,
Inten=54.6 mm/hr
Runoff Area=368.0 m²
Runoff Volume=13.1 m³
Runoff Depth=36 mm
Tc=10.0 min
C=1.00
0.0056 m³/s
Toronto 10-Year Duration=39 min, Inten=54.6 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 23HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 8S: At-Grade Impervious
Runoff = 0.0305 m³/s @ 0.17 hrs, Volume= 71.5 m³, Depth= 32 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=39 min, Inten=54.6 mm/hr
Area (m²) C Description
2,237.0 0.90 Paved Areas
2,237.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 8S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.034
0.032
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 10-Year
Duration=39 min,
Inten=54.6 mm/hr
Runoff Area=2,237.0 m²
Runoff Volume=71.5 m³
Runoff Depth=32 mm
Tc=10.0 min
C=0.90
0.0305 m³/s
Toronto 10-Year Duration=39 min, Inten=54.6 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 24HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 5: SWM Tank (33.1L/s)
Inflow Area = 4,046.0 m², 9.10% Impervious, Inflow Depth > 29 mm for 10-Year eventInflow = 0.0496 m³/s @ 0.65 hrs, Volume= 118.6 m³Outflow = 0.0199 m³/s @ 0.76 hrs, Volume= 118.1 m³, Atten= 60%, Lag= 6.5 minPrimary = 0.0199 m³/s @ 0.76 hrs, Volume= 118.1 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 80.0 m² Storage= 16.0 m³Peak Elev= 1.161 m @ 0.76 hrs Surf.Area= 80.0 m² Storage= 92.8 m³ (76.8 m³ above start)
Plug-Flow detention time= 62.2 min calculated for 102.0 m³ (86% of inflow)Center-of-Mass det. time= 48.6 min ( 76.8 - 28.3 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 160.0 m³ 1.00 mW x 80.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 100 mm Vert. Orifice/Grate C= 0.600
Primary OutFlow Max=0.0199 m³/s @ 0.76 hrs HW=1.161 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0199 m³/s @ 2.54 m/s)
Pond 5: SWM Tank (33.1L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=4,046.0 m²
Peak Elev=1.161 m
Storage=92.8 m³
0.0496 m³/s
0.0199 m³/s
Toronto 10-Year Duration=39 min, Inten=54.6 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 25HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 6P: Green Roof
Inflow Area = 368.0 m²,100.00% Impervious, Inflow Depth = 36 mm for 10-Year eventInflow = 0.0056 m³/s @ 0.17 hrs, Volume= 13.1 m³Outflow = 0.0042 m³/s @ 0.69 hrs, Volume= 12.2 m³, Atten= 25%, Lag= 31.3 minPrimary = 0.0042 m³/s @ 0.69 hrs, Volume= 12.2 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.018 m @ 0.69 hrs Surf.Area= 736.0 m² Storage= 7.5 m³
Plug-Flow detention time= 37.7 min calculated for 12.2 m³ (93% of inflow)Center-of-Mass det. time= 36.8 min ( 61.3 - 24.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 0.7 m³ 1.00 mW x 368.00 mL x 0.01 mH Green Roof Media Storage3.7 m³ Overall x 20.0% Voids
#2 100.000 m 29.4 m³ 1.00 mW x 368.00 mL x 0.08 mH Green Roof
30.2 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 3.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0042 m³/s @ 0.69 hrs HW=100.018 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0042 m³/s @ 0.24 m/s)
Pond 6P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.006
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Inflow Area=368.0 m²
Peak Elev=100.018 m
Storage=7.5 m³
0.0056 m³/s
0.0042 m³/s
Toronto 25-Year Duration=39 min, Inten=63.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 26HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=959.0 m² 0.00% Impervious Runoff Depth=37 mmSubcatchment 3: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0153 m³/s 35.8 m³
Runoff Area=482.0 m² 0.00% Impervious Runoff Depth=10 mmSubcatchment 4: Pervious Landscaping Tc=10.0 min C=0.25 Runoff=0.0021 m³/s 5.0 m³
Runoff Area=368.0 m² 100.00% Impervious Runoff Depth=41 mmSubcatchment 7S: Green Roof Tc=10.0 min C=1.00 Runoff=0.0065 m³/s 15.3 m³
Runoff Area=2,237.0 m² 0.00% Impervious Runoff Depth=37 mmSubcatchment 8S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.0357 m³/s 83.5 m³
Peak Elev=1.354 m Storage=108.4 m³ Inflow=0.0581 m³/s 138.7 m³Pond 5: SWM Tank (33.1L/s) Outflow=0.0219 m³/s 138.2 m³
Peak Elev=100.021 m Storage=8.4 m³ Inflow=0.0065 m³/s 15.3 m³Pond 6P: Green Roof Outflow=0.0051 m³/s 14.4 m³
Total Runoff Area = 4,046.0 m² Runoff Volume = 139.5 m³ Average Runoff Depth = 34 mm90.90% Pervious = 3,678.0 m² 9.10% Impervious = 368.0 m²
Toronto 25-Year Duration=39 min, Inten=63.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 27HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 3: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0153 m³/s @ 0.17 hrs, Volume= 35.8 m³, Depth= 37 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=39 min, Inten=63.8 mm/hr
Area (m²) C Description
959.0 0.90 Impervious Roof
959.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 3: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.017
0.016
0.015
0.014
0.013
0.012
0.011
0.01
0.009
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Toronto 25-Year
Duration=39 min,
Inten=63.8 mm/hr
Runoff Area=959.0 m²
Runoff Volume=35.8 m³
Runoff Depth=37 mm
Tc=10.0 min
C=0.90
0.0153 m³/s
Toronto 25-Year Duration=39 min, Inten=63.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 28HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 4: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0021 m³/s @ 0.17 hrs, Volume= 5.0 m³, Depth= 10 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=39 min, Inten=63.8 mm/hr
Area (m²) C Description
482.0 0.25 Pervious Area
482.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 4: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Toronto 25-Year
Duration=39 min,
Inten=63.8 mm/hr
Runoff Area=482.0 m²
Runoff Volume=5.0 m³
Runoff Depth=10 mm
Tc=10.0 min
C=0.25
0.0021 m³/s
Toronto 25-Year Duration=39 min, Inten=63.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 29HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 7S: Green Roof
Runoff = 0.0065 m³/s @ 0.17 hrs, Volume= 15.3 m³, Depth= 41 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=39 min, Inten=63.8 mm/hr
Area (m²) C Description
368.0 1.00 Green Roof
368.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 7S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.007
0.007
0.006
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Toronto 25-Year
Duration=39 min,
Inten=63.8 mm/hr
Runoff Area=368.0 m²
Runoff Volume=15.3 m³
Runoff Depth=41 mm
Tc=10.0 min
C=1.00
0.0065 m³/s
Toronto 25-Year Duration=39 min, Inten=63.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 30HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 8S: At-Grade Impervious
Runoff = 0.0357 m³/s @ 0.17 hrs, Volume= 83.5 m³, Depth= 37 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=39 min, Inten=63.8 mm/hr
Area (m²) C Description
2,237.0 0.90 Paved Areas
2,237.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 8S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.038
0.036
0.034
0.032
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 25-Year
Duration=39 min,
Inten=63.8 mm/hr
Runoff Area=2,237.0 m²
Runoff Volume=83.5 m³
Runoff Depth=37 mm
Tc=10.0 min
C=0.90
0.0357 m³/s
Toronto 25-Year Duration=39 min, Inten=63.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 31HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 5: SWM Tank (33.1L/s)
Inflow Area = 4,046.0 m², 9.10% Impervious, Inflow Depth > 34 mm for 25-Year eventInflow = 0.0581 m³/s @ 0.65 hrs, Volume= 138.7 m³Outflow = 0.0219 m³/s @ 0.76 hrs, Volume= 138.2 m³, Atten= 62%, Lag= 6.8 minPrimary = 0.0219 m³/s @ 0.76 hrs, Volume= 138.2 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 80.0 m² Storage= 16.0 m³Peak Elev= 1.354 m @ 0.76 hrs Surf.Area= 80.0 m² Storage= 108.4 m³ (92.4 m³ above start)
Plug-Flow detention time= 64.8 min calculated for 122.2 m³ (88% of inflow)Center-of-Mass det. time= 52.2 min ( 80.3 - 28.1 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 160.0 m³ 1.00 mW x 80.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 100 mm Vert. Orifice/Grate C= 0.600
Primary OutFlow Max=0.0219 m³/s @ 0.76 hrs HW=1.354 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0219 m³/s @ 2.79 m/s)
Pond 5: SWM Tank (33.1L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=4,046.0 m²
Peak Elev=1.354 m
Storage=108.4 m³
0.0581 m³/s
0.0219 m³/s
Toronto 25-Year Duration=39 min, Inten=63.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 32HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 6P: Green Roof
Inflow Area = 368.0 m²,100.00% Impervious, Inflow Depth = 41 mm for 25-Year eventInflow = 0.0065 m³/s @ 0.17 hrs, Volume= 15.3 m³Outflow = 0.0051 m³/s @ 0.69 hrs, Volume= 14.4 m³, Atten= 22%, Lag= 31.0 minPrimary = 0.0051 m³/s @ 0.69 hrs, Volume= 14.4 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.021 m @ 0.69 hrs Surf.Area= 736.0 m² Storage= 8.4 m³
Plug-Flow detention time= 35.3 min calculated for 14.4 m³ (94% of inflow)Center-of-Mass det. time= 34.5 min ( 59.0 - 24.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 0.7 m³ 1.00 mW x 368.00 mL x 0.01 mH Green Roof Media Storage3.7 m³ Overall x 20.0% Voids
#2 100.000 m 29.4 m³ 1.00 mW x 368.00 mL x 0.08 mH Green Roof
30.2 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 3.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0051 m³/s @ 0.69 hrs HW=100.021 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0051 m³/s @ 0.26 m/s)
Pond 6P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.007
0.007
0.006
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Inflow Area=368.0 m²
Peak Elev=100.021 m
Storage=8.4 m³
0.0065 m³/s
0.0051 m³/s
Toronto 50-Year Duration=39 min, Inten=75.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 33HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=959.0 m² 0.00% Impervious Runoff Depth=44 mmSubcatchment 3: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0181 m³/s 42.4 m³
Runoff Area=482.0 m² 0.00% Impervious Runoff Depth=12 mmSubcatchment 4: Pervious Landscaping Tc=10.0 min C=0.25 Runoff=0.0025 m³/s 5.9 m³
Runoff Area=368.0 m² 100.00% Impervious Runoff Depth=49 mmSubcatchment 7S: Green Roof Tc=10.0 min C=1.00 Runoff=0.0077 m³/s 18.1 m³
Runoff Area=2,237.0 m² 0.00% Impervious Runoff Depth=44 mmSubcatchment 8S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.0422 m³/s 98.8 m³
Peak Elev=1.607 m Storage=128.6 m³ Inflow=0.0690 m³/s 164.3 m³Pond 5: SWM Tank (33.1L/s) Outflow=0.0243 m³/s 163.7 m³
Peak Elev=100.024 m Storage=9.5 m³ Inflow=0.0077 m³/s 18.1 m³Pond 6P: Green Roof Outflow=0.0062 m³/s 17.2 m³
Total Runoff Area = 4,046.0 m² Runoff Volume = 165.2 m³ Average Runoff Depth = 41 mm90.90% Pervious = 3,678.0 m² 9.10% Impervious = 368.0 m²
Toronto 50-Year Duration=39 min, Inten=75.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 34HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 3: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0181 m³/s @ 0.17 hrs, Volume= 42.4 m³, Depth= 44 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=39 min, Inten=75.5 mm/hr
Area (m²) C Description
959.0 0.90 Impervious Roof
959.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 3: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.02
0.019
0.018
0.017
0.016
0.015
0.014
0.013
0.012
0.011
0.01
0.009
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Toronto 50-Year
Duration=39 min,
Inten=75.5 mm/hr
Runoff Area=959.0 m²
Runoff Volume=42.4 m³
Runoff Depth=44 mm
Tc=10.0 min
C=0.90
0.0181 m³/s
Toronto 50-Year Duration=39 min, Inten=75.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 35HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 4: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0025 m³/s @ 0.17 hrs, Volume= 5.9 m³, Depth= 12 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=39 min, Inten=75.5 mm/hr
Area (m²) C Description
482.0 0.25 Pervious Area
482.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 4: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.003
0.003
0.002
0.002
0.002
0.002
0.002
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0
Toronto 50-Year
Duration=39 min,
Inten=75.5 mm/hr
Runoff Area=482.0 m²
Runoff Volume=5.9 m³
Runoff Depth=12 mm
Tc=10.0 min
C=0.25
0.0025 m³/s
Toronto 50-Year Duration=39 min, Inten=75.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 36HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 7S: Green Roof
Runoff = 0.0077 m³/s @ 0.17 hrs, Volume= 18.1 m³, Depth= 49 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=39 min, Inten=75.5 mm/hr
Area (m²) C Description
368.0 1.00 Green Roof
368.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 7S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.009
0.008
0.007
0.007
0.006
0.006
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Toronto 50-Year
Duration=39 min,
Inten=75.5 mm/hr
Runoff Area=368.0 m²
Runoff Volume=18.1 m³
Runoff Depth=49 mm
Tc=10.0 min
C=1.00
0.0077 m³/s
Toronto 50-Year Duration=39 min, Inten=75.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 37HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 8S: At-Grade Impervious
Runoff = 0.0422 m³/s @ 0.17 hrs, Volume= 98.8 m³, Depth= 44 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=39 min, Inten=75.5 mm/hr
Area (m²) C Description
2,237.0 0.90 Paved Areas
2,237.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 8S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.046
0.044
0.042
0.04
0.038
0.036
0.034
0.032
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 50-Year
Duration=39 min,
Inten=75.5 mm/hr
Runoff Area=2,237.0 m²
Runoff Volume=98.8 m³
Runoff Depth=44 mm
Tc=10.0 min
C=0.90
0.0422 m³/s
Toronto 50-Year Duration=39 min, Inten=75.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 38HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 5: SWM Tank (33.1L/s)
Inflow Area = 4,046.0 m², 9.10% Impervious, Inflow Depth > 41 mm for 50-Year eventInflow = 0.0690 m³/s @ 0.65 hrs, Volume= 164.3 m³Outflow = 0.0243 m³/s @ 0.77 hrs, Volume= 163.7 m³, Atten= 65%, Lag= 7.0 minPrimary = 0.0243 m³/s @ 0.77 hrs, Volume= 163.7 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 80.0 m² Storage= 16.0 m³Peak Elev= 1.607 m @ 0.77 hrs Surf.Area= 80.0 m² Storage= 128.6 m³ (112.6 m³ above start)
Plug-Flow detention time= 67.4 min calculated for 147.5 m³ (90% of inflow)Center-of-Mass det. time= 56.6 min ( 84.5 - 27.9 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 160.0 m³ 1.00 mW x 80.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 100 mm Vert. Orifice/Grate C= 0.600
Primary OutFlow Max=0.0243 m³/s @ 0.77 hrs HW=1.607 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0243 m³/s @ 3.10 m/s)
Pond 5: SWM Tank (33.1L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.075
0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=4,046.0 m²
Peak Elev=1.607 m
Storage=128.6 m³
0.0690 m³/s
0.0243 m³/s
Toronto 50-Year Duration=39 min, Inten=75.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 39HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 6P: Green Roof
Inflow Area = 368.0 m²,100.00% Impervious, Inflow Depth = 49 mm for 50-Year eventInflow = 0.0077 m³/s @ 0.17 hrs, Volume= 18.1 m³Outflow = 0.0062 m³/s @ 0.68 hrs, Volume= 17.2 m³, Atten= 20%, Lag= 30.8 minPrimary = 0.0062 m³/s @ 0.68 hrs, Volume= 17.2 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.024 m @ 0.68 hrs Surf.Area= 736.0 m² Storage= 9.5 m³
Plug-Flow detention time= 32.8 min calculated for 17.2 m³ (95% of inflow)Center-of-Mass det. time= 32.2 min ( 56.7 - 24.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 0.7 m³ 1.00 mW x 368.00 mL x 0.01 mH Green Roof Media Storage3.7 m³ Overall x 20.0% Voids
#2 100.000 m 29.4 m³ 1.00 mW x 368.00 mL x 0.08 mH Green Roof
30.2 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 3.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0062 m³/s @ 0.68 hrs HW=100.024 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0062 m³/s @ 0.28 m/s)
Pond 6P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.009
0.008
0.007
0.007
0.006
0.006
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Inflow Area=368.0 m²
Peak Elev=100.024 m
Storage=9.5 m³
0.0077 m³/s
0.0062 m³/s
Toronto 100-Year Duration=39 min, Inten=84.3 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 40HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=959.0 m² 0.00% Impervious Runoff Depth=49 mmSubcatchment 3: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0202 m³/s 47.3 m³
Runoff Area=482.0 m² 0.00% Impervious Runoff Depth=14 mmSubcatchment 4: Pervious Landscaping Tc=10.0 min C=0.25 Runoff=0.0028 m³/s 6.6 m³
Runoff Area=368.0 m² 100.00% Impervious Runoff Depth=55 mmSubcatchment 7S: Green Roof Tc=10.0 min C=1.00 Runoff=0.0086 m³/s 20.2 m³
Runoff Area=2,237.0 m² 0.00% Impervious Runoff Depth=49 mmSubcatchment 8S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.0471 m³/s 110.3 m³
Peak Elev=1.799 m Storage=143.9 m³ Inflow=0.0771 m³/s 183.4 m³Pond 5: SWM Tank (33.1L/s) Outflow=0.0260 m³/s 182.8 m³
Peak Elev=100.026 m Storage=10.2 m³ Inflow=0.0086 m³/s 20.2 m³Pond 6P: Green Roof Outflow=0.0071 m³/s 19.3 m³
Total Runoff Area = 4,046.0 m² Runoff Volume = 184.3 m³ Average Runoff Depth = 46 mm90.90% Pervious = 3,678.0 m² 9.10% Impervious = 368.0 m²
Toronto 100-Year Duration=39 min, Inten=84.3 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 41HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 3: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0202 m³/s @ 0.17 hrs, Volume= 47.3 m³, Depth= 49 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=39 min, Inten=84.3 mm/hr
Area (m²) C Description
959.0 0.90 Impervious Roof
959.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 3: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.022
0.021
0.02
0.019
0.018
0.017
0.016
0.015
0.014
0.013
0.012
0.011
0.01
0.009
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Toronto 100-Year
Duration=39 min,
Inten=84.3 mm/hr
Runoff Area=959.0 m²
Runoff Volume=47.3 m³
Runoff Depth=49 mm
Tc=10.0 min
C=0.90
0.0202 m³/s
Toronto 100-Year Duration=39 min, Inten=84.3 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 42HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 4: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0028 m³/s @ 0.17 hrs, Volume= 6.6 m³, Depth= 14 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=39 min, Inten=84.3 mm/hr
Area (m²) C Description
482.0 0.25 Pervious Area
482.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 4: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.003
0.003
0.003
0.002
0.002
0.002
0.002
0.002
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0
Toronto 100-Year
Duration=39 min,
Inten=84.3 mm/hr
Runoff Area=482.0 m²
Runoff Volume=6.6 m³
Runoff Depth=14 mm
Tc=10.0 min
C=0.25
0.0028 m³/s
Toronto 100-Year Duration=39 min, Inten=84.3 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 43HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 7S: Green Roof
Runoff = 0.0086 m³/s @ 0.17 hrs, Volume= 20.2 m³, Depth= 55 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=39 min, Inten=84.3 mm/hr
Area (m²) C Description
368.0 1.00 Green Roof
368.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 7S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.009
0.009
0.008
0.008
0.007
0.007
0.006
0.006
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Toronto 100-Year
Duration=39 min,
Inten=84.3 mm/hr
Runoff Area=368.0 m²
Runoff Volume=20.2 m³
Runoff Depth=55 mm
Tc=10.0 min
C=1.00
0.0086 m³/s
Toronto 100-Year Duration=39 min, Inten=84.3 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 44HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 8S: At-Grade Impervious
Runoff = 0.0471 m³/s @ 0.17 hrs, Volume= 110.3 m³, Depth= 49 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=39 min, Inten=84.3 mm/hr
Area (m²) C Description
2,237.0 0.90 Paved Areas
2,237.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 8S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.052
0.05
0.048
0.046
0.044
0.042
0.040.038
0.036
0.034
0.032
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.0140.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 100-Year
Duration=39 min,
Inten=84.3 mm/hr
Runoff Area=2,237.0 m²
Runoff Volume=110.3 m³
Runoff Depth=49 mm
Tc=10.0 min
C=0.90
0.0471 m³/s
Toronto 100-Year Duration=39 min, Inten=84.3 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 45HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 5: SWM Tank (33.1L/s)
Inflow Area = 4,046.0 m², 9.10% Impervious, Inflow Depth > 45 mm for 100-Year eventInflow = 0.0771 m³/s @ 0.65 hrs, Volume= 183.4 m³Outflow = 0.0260 m³/s @ 0.77 hrs, Volume= 182.8 m³, Atten= 66%, Lag= 7.2 minPrimary = 0.0260 m³/s @ 0.77 hrs, Volume= 182.8 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 80.0 m² Storage= 16.0 m³Peak Elev= 1.799 m @ 0.77 hrs Surf.Area= 80.0 m² Storage= 143.9 m³ (127.9 m³ above start)
Plug-Flow detention time= 69.8 min calculated for 166.5 m³ (91% of inflow)Center-of-Mass det. time= 59.7 min ( 87.5 - 27.7 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 160.0 m³ 1.00 mW x 80.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 100 mm Vert. Orifice/Grate C= 0.600
Primary OutFlow Max=0.0260 m³/s @ 0.77 hrs HW=1.799 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0260 m³/s @ 3.31 m/s)
Pond 5: SWM Tank (33.1L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.085
0.08
0.075
0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=4,046.0 m²
Peak Elev=1.799 m
Storage=143.9 m³
0.0771 m³/s
0.0260 m³/s
Toronto 100-Year Duration=39 min, Inten=84.3 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 46HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 6P: Green Roof
Inflow Area = 368.0 m²,100.00% Impervious, Inflow Depth = 55 mm for 100-Year eventInflow = 0.0086 m³/s @ 0.17 hrs, Volume= 20.2 m³Outflow = 0.0071 m³/s @ 0.68 hrs, Volume= 19.3 m³, Atten= 18%, Lag= 30.6 minPrimary = 0.0071 m³/s @ 0.68 hrs, Volume= 19.3 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.026 m @ 0.68 hrs Surf.Area= 736.0 m² Storage= 10.2 m³
Plug-Flow detention time= 31.7 min calculated for 19.3 m³ (96% of inflow)Center-of-Mass det. time= 30.8 min ( 55.3 - 24.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 0.7 m³ 1.00 mW x 368.00 mL x 0.01 mH Green Roof Media Storage3.7 m³ Overall x 20.0% Voids
#2 100.000 m 29.4 m³ 1.00 mW x 368.00 mL x 0.08 mH Green Roof
30.2 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 3.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0071 m³/s @ 0.68 hrs HW=100.026 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0071 m³/s @ 0.29 m/s)
Pond 6P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.009
0.009
0.008
0.008
0.007
0.007
0.006
0.006
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Inflow Area=368.0 m²
Peak Elev=100.026 m
Storage=10.2 m³
0.0086 m³/s
0.0071 m³/s
Catchment 202 (BC)
36S
Impervious Roof
37S
Pervious Landscaping
38S
Green Roof
39S
At-Grade Impervious
40P
SWM Tank (243.9L/s)
41P
Green Roof
Routing Diagram for Richview SquarePrepared by WSP Canada Inc., Printed 3/8/2019
HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Subcat Reach Pond Link
Richview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 2HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Area Listing (selected nodes)
Area
(sq-meters)
C Description
(subcatchment-numbers)
7,012.0 0.90 (39S)
5,070.0 1.00 Green Roof (38S)
2,069.0 0.90 Impervious Roof (36S)
4,496.0 0.25 Pervious Area (37S)
18,647.0 0.77 TOTAL AREA
Richview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 3HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Soil Listing (selected nodes)
Area
(sq-meters)
Soil
Group
Subcatchment
Numbers
0.0 HSG A
0.0 HSG B
0.0 HSG C
0.0 HSG D
18,647.0 Other 36S, 37S, 38S, 39S
18,647.0 TOTAL AREA
Richview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 4HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Ground Covers (selected nodes)
HSG-A
(sq-meters)
HSG-B
(sq-meters)
HSG-C
(sq-meters)
HSG-D
(sq-meters)
Other
(sq-meters)
Total
(sq-meters)
Ground
Cover
Subcatchment
Numbers
0.0 0.0 0.0 0.0 7,012.0 7,012.0
0.0 0.0 0.0 0.0 5,070.0 5,070.0 Green Roof
0.0 0.0 0.0 0.0 2,069.0 2,069.0 Impervious
Roof
0.0 0.0 0.0 0.0 4,496.0 4,496.0 Pervious
Area
0.0 0.0 0.0 0.0 18,647.0 18,647.0 TOTAL
AREA
Toronto 2-Year Duration=19 min, Inten=53.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 5HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=2,069.0 m² 0.00% Impervious Runoff Depth=15 mmSubcatchment 36S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0276 m³/s 31.5 m³
Runoff Area=4,496.0 m² 0.00% Impervious Runoff Depth=4 mmSubcatchment 37S: Pervious Landscaping Tc=10.0 min C=0.25 Runoff=0.0167 m³/s 19.0 m³
Runoff Area=5,070.0 m² 100.00% Impervious Runoff Depth=17 mmSubcatchment 38S: Green Roof Tc=10.0 min C=1.00 Runoff=0.0753 m³/s 85.8 m³
Runoff Area=7,012.0 m² 0.00% Impervious Runoff Depth=15 mmSubcatchment 39S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.0937 m³/s 106.8 m³
Peak Elev=0.636 m Storage=127.2 m³ Inflow=0.1554 m³/s 231.1 m³Pond 40P: SWM Tank (243.9L/s) Outflow=0.0970 m³/s 228.5 m³
Peak Elev=100.012 m Storage=68.8 m³ Inflow=0.0753 m³/s 85.8 m³Pond 41P: Green Roof Outflow=0.0247 m³/s 73.8 m³
Total Runoff Area = 18,647.0 m² Runoff Volume = 243.1 m³ Average Runoff Depth = 13 mm72.81% Pervious = 13,577.0 m² 27.19% Impervious = 5,070.0 m²
Toronto 2-Year Duration=19 min, Inten=53.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 6HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 36S: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0276 m³/s @ 0.17 hrs, Volume= 31.5 m³, Depth= 15 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=19 min, Inten=53.5 mm/hr
Area (m²) C Description
2,069.0 0.90 Impervious Roof
2,069.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 36S: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 2-Year
Duration=19 min,
Inten=53.5 mm/hr
Runoff Area=2,069.0 m²
Runoff Volume=31.5 m³
Runoff Depth=15 mm
Tc=10.0 min
C=0.90
0.0276 m³/s
Toronto 2-Year Duration=19 min, Inten=53.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 7HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 37S: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0167 m³/s @ 0.17 hrs, Volume= 19.0 m³, Depth= 4 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=19 min, Inten=53.5 mm/hr
Area (m²) C Description
4,496.0 0.25 Pervious Area
4,496.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 37S: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.018
0.017
0.016
0.015
0.014
0.013
0.012
0.011
0.01
0.009
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Toronto 2-Year
Duration=19 min,
Inten=53.5 mm/hr
Runoff Area=4,496.0 m²
Runoff Volume=19.0 m³
Runoff Depth=4 mm
Tc=10.0 min
C=0.25
0.0167 m³/s
Toronto 2-Year Duration=19 min, Inten=53.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 8HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 38S: Green Roof
Runoff = 0.0753 m³/s @ 0.17 hrs, Volume= 85.8 m³, Depth= 17 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=19 min, Inten=53.5 mm/hr
Area (m²) C Description
5,070.0 1.00 Green Roof
5,070.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 38S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.08
0.075
0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 2-Year
Duration=19 min,
Inten=53.5 mm/hr
Runoff Area=5,070.0 m²
Runoff Volume=85.8 m³
Runoff Depth=17 mm
Tc=10.0 min
C=1.00
0.0753 m³/s
Toronto 2-Year Duration=19 min, Inten=53.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 9HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 39S: At-Grade Impervious
Runoff = 0.0937 m³/s @ 0.17 hrs, Volume= 106.8 m³, Depth= 15 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=19 min, Inten=53.5 mm/hr
Area (m²) C Description
7,012.0 0.90
7,012.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 39S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.1
0.095
0.09
0.085
0.08
0.075
0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 2-Year
Duration=19 min,
Inten=53.5 mm/hr
Runoff Area=7,012.0 m²
Runoff Volume=106.8 m³
Runoff Depth=15 mm
Tc=10.0 min
C=0.90
0.0937 m³/s
Toronto 2-Year Duration=19 min, Inten=53.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 10HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 40P: SWM Tank (243.9L/s)
Inflow Area = 18,647.0 m², 27.19% Impervious, Inflow Depth > 12 mm for 2-Year eventInflow = 0.1554 m³/s @ 0.31 hrs, Volume= 231.1 m³Outflow = 0.0970 m³/s @ 0.40 hrs, Volume= 228.5 m³, Atten= 38%, Lag= 5.2 minPrimary = 0.0970 m³/s @ 0.40 hrs, Volume= 228.5 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 200.0 m² Storage= 40.0 m³Peak Elev= 0.636 m @ 0.40 hrs Surf.Area= 200.0 m² Storage= 127.2 m³ (87.2 m³ above start)
Plug-Flow detention time= 39.6 min calculated for 188.5 m³ (82% of inflow)Center-of-Mass det. time= 17.2 min ( 48.7 - 31.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 400.0 m³ 1.00 mW x 200.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 250 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0970 m³/s @ 0.40 hrs HW=0.636 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0970 m³/s @ 1.98 m/s)
Pond 40P: SWM Tank (243.9L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.17
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=18,647.0 m²
Peak Elev=0.636 m
Storage=127.2 m³
0.1554 m³/s
0.0970 m³/s
Toronto 2-Year Duration=19 min, Inten=53.5 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 11HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 41P: Green Roof
Inflow Area = 5,070.0 m²,100.00% Impervious, Inflow Depth = 17 mm for 2-Year eventInflow = 0.0753 m³/s @ 0.17 hrs, Volume= 85.8 m³Outflow = 0.0247 m³/s @ 0.43 hrs, Volume= 73.8 m³, Atten= 67%, Lag= 15.5 minPrimary = 0.0247 m³/s @ 0.43 hrs, Volume= 73.8 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.012 m @ 0.43 hrs Surf.Area= 10,140.0 m² Storage= 68.8 m³
Plug-Flow detention time= 54.4 min calculated for 73.7 m³ (86% of inflow)Center-of-Mass det. time= 53.3 min ( 67.8 - 14.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 10.1 m³ 1.00 mW x 5,070.00 mL x 0.01 mH Green Roof Media Storage50.7 m³ Overall x 20.0% Voids
#2 100.000 m 405.6 m³ 1.00 mW x 5,070.00 mL x 0.08 mH Green Roof
415.7 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 35.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0247 m³/s @ 0.43 hrs HW=100.012 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0247 m³/s @ 0.19 m/s)
Pond 41P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.08
0.075
0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=5,070.0 m²
Peak Elev=100.012 m
Storage=68.8 m³
0.0753 m³/s
0.0247 m³/s
Toronto 5-Year Duration=19 min, Inten=79.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 12HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=2,069.0 m² 0.00% Impervious Runoff Depth=23 mmSubcatchment 36S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0411 m³/s 46.8 m³
Runoff Area=4,496.0 m² 0.00% Impervious Runoff Depth=6 mmSubcatchment 37S: Pervious Landscaping Tc=10.0 min C=0.25 Runoff=0.0248 m³/s 28.2 m³
Runoff Area=5,070.0 m² 100.00% Impervious Runoff Depth=25 mmSubcatchment 38S: Green Roof Tc=10.0 min C=1.00 Runoff=0.1118 m³/s 127.4 m³
Runoff Area=7,012.0 m² 0.00% Impervious Runoff Depth=23 mmSubcatchment 39S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.1391 m³/s 158.6 m³
Peak Elev=0.904 m Storage=180.9 m³ Inflow=0.2377 m³/s 348.8 m³Pond 40P: SWM Tank (243.9L/s) Outflow=0.1324 m³/s 346.1 m³
Peak Elev=100.017 m Storage=96.3 m³ Inflow=0.1118 m³/s 127.4 m³Pond 41P: Green Roof Outflow=0.0440 m³/s 115.2 m³
Total Runoff Area = 18,647.0 m² Runoff Volume = 361.0 m³ Average Runoff Depth = 19 mm72.81% Pervious = 13,577.0 m² 27.19% Impervious = 5,070.0 m²
Toronto 5-Year Duration=19 min, Inten=79.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 13HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 36S: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0411 m³/s @ 0.17 hrs, Volume= 46.8 m³, Depth= 23 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=19 min, Inten=79.4 mm/hr
Area (m²) C Description
2,069.0 0.90 Impervious Roof
2,069.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 36S: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.044
0.042
0.04
0.038
0.036
0.034
0.032
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 5-Year
Duration=19 min,
Inten=79.4 mm/hr
Runoff Area=2,069.0 m²
Runoff Volume=46.8 m³
Runoff Depth=23 mm
Tc=10.0 min
C=0.90
0.0411 m³/s
Toronto 5-Year Duration=19 min, Inten=79.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 14HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 37S: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0248 m³/s @ 0.17 hrs, Volume= 28.2 m³, Depth= 6 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=19 min, Inten=79.4 mm/hr
Area (m²) C Description
4,496.0 0.25 Pervious Area
4,496.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 37S: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 5-Year
Duration=19 min,
Inten=79.4 mm/hr
Runoff Area=4,496.0 m²
Runoff Volume=28.2 m³
Runoff Depth=6 mm
Tc=10.0 min
C=0.25
0.0248 m³/s
Toronto 5-Year Duration=19 min, Inten=79.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 15HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 38S: Green Roof
Runoff = 0.1118 m³/s @ 0.17 hrs, Volume= 127.4 m³, Depth= 25 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=19 min, Inten=79.4 mm/hr
Area (m²) C Description
5,070.0 1.00 Green Roof
5,070.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 38S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.125
0.12
0.115
0.11
0.105
0.1
0.095
0.09
0.085
0.08
0.075
0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 5-Year
Duration=19 min,
Inten=79.4 mm/hr
Runoff Area=5,070.0 m²
Runoff Volume=127.4 m³
Runoff Depth=25 mm
Tc=10.0 min
C=1.00
0.1118 m³/s
Toronto 5-Year Duration=19 min, Inten=79.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 16HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 39S: At-Grade Impervious
Runoff = 0.1391 m³/s @ 0.17 hrs, Volume= 158.6 m³, Depth= 23 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=19 min, Inten=79.4 mm/hr
Area (m²) C Description
7,012.0 0.90
7,012.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 39S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 5-Year
Duration=19 min,
Inten=79.4 mm/hr
Runoff Area=7,012.0 m²
Runoff Volume=158.6 m³
Runoff Depth=23 mm
Tc=10.0 min
C=0.90
0.1391 m³/s
Toronto 5-Year Duration=19 min, Inten=79.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 17HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 40P: SWM Tank (243.9L/s)
Inflow Area = 18,647.0 m², 27.19% Impervious, Inflow Depth > 19 mm for 5-Year eventInflow = 0.2377 m³/s @ 0.31 hrs, Volume= 348.8 m³Outflow = 0.1324 m³/s @ 0.41 hrs, Volume= 346.1 m³, Atten= 44%, Lag= 6.1 minPrimary = 0.1324 m³/s @ 0.41 hrs, Volume= 346.1 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 200.0 m² Storage= 40.0 m³Peak Elev= 0.904 m @ 0.41 hrs Surf.Area= 200.0 m² Storage= 180.9 m³ (140.9 m³ above start)
Plug-Flow detention time= 32.8 min calculated for 306.1 m³ (88% of inflow)Center-of-Mass det. time= 17.0 min ( 46.5 - 29.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 400.0 m³ 1.00 mW x 200.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 250 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.1324 m³/s @ 0.41 hrs HW=0.904 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.1324 m³/s @ 2.70 m/s)
Pond 40P: SWM Tank (243.9L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.26
0.24
0.22
0.2
0.18
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
Inflow Area=18,647.0 m²
Peak Elev=0.904 m
Storage=180.9 m³
0.2377 m³/s
0.1324 m³/s
Toronto 5-Year Duration=19 min, Inten=79.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 18HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 41P: Green Roof
Inflow Area = 5,070.0 m²,100.00% Impervious, Inflow Depth = 25 mm for 5-Year eventInflow = 0.1118 m³/s @ 0.17 hrs, Volume= 127.4 m³Outflow = 0.0440 m³/s @ 0.42 hrs, Volume= 115.2 m³, Atten= 61%, Lag= 14.9 minPrimary = 0.0440 m³/s @ 0.42 hrs, Volume= 115.2 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.017 m @ 0.42 hrs Surf.Area= 10,140.0 m² Storage= 96.3 m³
Plug-Flow detention time= 46.5 min calculated for 115.2 m³ (90% of inflow)Center-of-Mass det. time= 45.3 min ( 59.8 - 14.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 10.1 m³ 1.00 mW x 5,070.00 mL x 0.01 mH Green Roof Media Storage50.7 m³ Overall x 20.0% Voids
#2 100.000 m 405.6 m³ 1.00 mW x 5,070.00 mL x 0.08 mH Green Roof
415.7 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 35.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0440 m³/s @ 0.42 hrs HW=100.017 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0440 m³/s @ 0.24 m/s)
Pond 41P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.125
0.12
0.115
0.11
0.105
0.1
0.095
0.09
0.085
0.08
0.075
0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=5,070.0 m²
Peak Elev=100.017 m
Storage=96.3 m³
0.1118 m³/s
0.0440 m³/s
Toronto 10-Year Duration=19 min, Inten=97.1 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 19HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=2,069.0 m² 0.00% Impervious Runoff Depth=28 mmSubcatchment 36S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0502 m³/s 57.2 m³
Runoff Area=4,496.0 m² 0.00% Impervious Runoff Depth=8 mmSubcatchment 37S: Pervious Landscaping Tc=10.0 min C=0.25 Runoff=0.0303 m³/s 34.6 m³
Runoff Area=5,070.0 m² 100.00% Impervious Runoff Depth=31 mmSubcatchment 38S: Green Roof Tc=10.0 min C=1.00 Runoff=0.1368 m³/s 155.9 m³
Runoff Area=7,012.0 m² 0.00% Impervious Runoff Depth=28 mmSubcatchment 39S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.1702 m³/s 194.0 m³
Peak Elev=1.108 m Storage=221.7 m³ Inflow=0.2953 m³/s 429.4 m³Pond 40P: SWM Tank (243.9L/s) Outflow=0.1540 m³/s 426.5 m³
Peak Elev=100.020 m Storage=114.1 m³ Inflow=0.1368 m³/s 155.9 m³Pond 41P: Green Roof Outflow=0.0583 m³/s 143.6 m³
Total Runoff Area = 18,647.0 m² Runoff Volume = 441.7 m³ Average Runoff Depth = 24 mm72.81% Pervious = 13,577.0 m² 27.19% Impervious = 5,070.0 m²
Toronto 10-Year Duration=19 min, Inten=97.1 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 20HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 36S: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0502 m³/s @ 0.17 hrs, Volume= 57.2 m³, Depth= 28 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=19 min, Inten=97.1 mm/hr
Area (m²) C Description
2,069.0 0.90 Impervious Roof
2,069.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 36S: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 10-Year
Duration=19 min,
Inten=97.1 mm/hr
Runoff Area=2,069.0 m²
Runoff Volume=57.2 m³
Runoff Depth=28 mm
Tc=10.0 min
C=0.90
0.0502 m³/s
Toronto 10-Year Duration=19 min, Inten=97.1 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 21HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 37S: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0303 m³/s @ 0.17 hrs, Volume= 34.6 m³, Depth= 8 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=19 min, Inten=97.1 mm/hr
Area (m²) C Description
4,496.0 0.25 Pervious Area
4,496.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 37S: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.032
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 10-Year
Duration=19 min,
Inten=97.1 mm/hr
Runoff Area=4,496.0 m²
Runoff Volume=34.6 m³
Runoff Depth=8 mm
Tc=10.0 min
C=0.25
0.0303 m³/s
Toronto 10-Year Duration=19 min, Inten=97.1 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 22HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 38S: Green Roof
Runoff = 0.1368 m³/s @ 0.17 hrs, Volume= 155.9 m³, Depth= 31 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=19 min, Inten=97.1 mm/hr
Area (m²) C Description
5,070.0 1.00 Green Roof
5,070.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 38S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 10-Year
Duration=19 min,
Inten=97.1 mm/hr
Runoff Area=5,070.0 m²
Runoff Volume=155.9 m³
Runoff Depth=31 mm
Tc=10.0 min
C=1.00
0.1368 m³/s
Toronto 10-Year Duration=19 min, Inten=97.1 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 23HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 39S: At-Grade Impervious
Runoff = 0.1702 m³/s @ 0.17 hrs, Volume= 194.0 m³, Depth= 28 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=19 min, Inten=97.1 mm/hr
Area (m²) C Description
7,012.0 0.90
7,012.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 39S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.19
0.18
0.17
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 10-Year
Duration=19 min,
Inten=97.1 mm/hr
Runoff Area=7,012.0 m²
Runoff Volume=194.0 m³
Runoff Depth=28 mm
Tc=10.0 min
C=0.90
0.1702 m³/s
Toronto 10-Year Duration=19 min, Inten=97.1 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 24HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 40P: SWM Tank (243.9L/s)
Inflow Area = 18,647.0 m², 27.19% Impervious, Inflow Depth > 23 mm for 10-Year eventInflow = 0.2953 m³/s @ 0.31 hrs, Volume= 429.4 m³Outflow = 0.1540 m³/s @ 0.42 hrs, Volume= 426.5 m³, Atten= 48%, Lag= 6.6 minPrimary = 0.1540 m³/s @ 0.42 hrs, Volume= 426.5 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 200.0 m² Storage= 40.0 m³Peak Elev= 1.108 m @ 0.42 hrs Surf.Area= 200.0 m² Storage= 221.7 m³ (181.7 m³ above start)
Plug-Flow detention time= 30.8 min calculated for 386.5 m³ (90% of inflow)Center-of-Mass det. time= 17.6 min ( 46.1 - 28.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 400.0 m³ 1.00 mW x 200.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 250 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.1540 m³/s @ 0.42 hrs HW=1.108 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.1540 m³/s @ 3.14 m/s)
Pond 40P: SWM Tank (243.9L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.32
0.3
0.28
0.26
0.24
0.22
0.2
0.18
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
Inflow Area=18,647.0 m²
Peak Elev=1.108 m
Storage=221.7 m³
0.2953 m³/s
0.1540 m³/s
Toronto 10-Year Duration=19 min, Inten=97.1 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 25HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 41P: Green Roof
Inflow Area = 5,070.0 m²,100.00% Impervious, Inflow Depth = 31 mm for 10-Year eventInflow = 0.1368 m³/s @ 0.17 hrs, Volume= 155.9 m³Outflow = 0.0583 m³/s @ 0.41 hrs, Volume= 143.6 m³, Atten= 57%, Lag= 14.5 minPrimary = 0.0583 m³/s @ 0.41 hrs, Volume= 143.6 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.020 m @ 0.41 hrs Surf.Area= 10,140.0 m² Storage= 114.1 m³
Plug-Flow detention time= 42.2 min calculated for 143.3 m³ (92% of inflow)Center-of-Mass det. time= 41.8 min ( 56.3 - 14.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 10.1 m³ 1.00 mW x 5,070.00 mL x 0.01 mH Green Roof Media Storage50.7 m³ Overall x 20.0% Voids
#2 100.000 m 405.6 m³ 1.00 mW x 5,070.00 mL x 0.08 mH Green Roof
415.7 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 35.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0583 m³/s @ 0.41 hrs HW=100.020 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0583 m³/s @ 0.26 m/s)
Pond 41P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=5,070.0 m²
Peak Elev=100.020 m
Storage=114.1 m³
0.1368 m³/s
0.0583 m³/s
Toronto 25-Year Duration=19 min, Inten=113.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 26HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=2,069.0 m² 0.00% Impervious Runoff Depth=32 mmSubcatchment 36S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0587 m³/s 66.9 m³
Runoff Area=4,496.0 m² 0.00% Impervious Runoff Depth=9 mmSubcatchment 37S: Pervious Landscaping Tc=10.0 min C=0.25 Runoff=0.0354 m³/s 40.4 m³
Runoff Area=5,070.0 m² 100.00% Impervious Runoff Depth=36 mmSubcatchment 38S: Green Roof Tc=10.0 min C=1.00 Runoff=0.1597 m³/s 182.0 m³
Runoff Area=7,012.0 m² 0.00% Impervious Runoff Depth=32 mmSubcatchment 39S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.1988 m³/s 226.6 m³
Peak Elev=1.307 m Storage=261.5 m³ Inflow=0.3491 m³/s 503.5 m³Pond 40P: SWM Tank (243.9L/s) Outflow=0.1724 m³/s 500.6 m³
Peak Elev=100.024 m Storage=129.9 m³ Inflow=0.1597 m³/s 182.0 m³Pond 41P: Green Roof Outflow=0.0721 m³/s 169.7 m³
Total Runoff Area = 18,647.0 m² Runoff Volume = 515.9 m³ Average Runoff Depth = 28 mm72.81% Pervious = 13,577.0 m² 27.19% Impervious = 5,070.0 m²
Toronto 25-Year Duration=19 min, Inten=113.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 27HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 36S: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0587 m³/s @ 0.17 hrs, Volume= 66.9 m³, Depth= 32 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=19 min, Inten=113.4 mm/hr
Area (m²) C Description
2,069.0 0.90 Impervious Roof
2,069.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 36S: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 25-Year
Duration=19 min,
Inten=113.4 mm/hr
Runoff Area=2,069.0 m²
Runoff Volume=66.9 m³
Runoff Depth=32 mm
Tc=10.0 min
C=0.90
0.0587 m³/s
Toronto 25-Year Duration=19 min, Inten=113.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 28HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 37S: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0354 m³/s @ 0.17 hrs, Volume= 40.4 m³, Depth= 9 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=19 min, Inten=113.4 mm/hr
Area (m²) C Description
4,496.0 0.25 Pervious Area
4,496.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 37S: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.038
0.036
0.034
0.032
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 25-Year
Duration=19 min,
Inten=113.4 mm/hr
Runoff Area=4,496.0 m²
Runoff Volume=40.4 m³
Runoff Depth=9 mm
Tc=10.0 min
C=0.25
0.0354 m³/s
Toronto 25-Year Duration=19 min, Inten=113.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 29HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 38S: Green Roof
Runoff = 0.1597 m³/s @ 0.17 hrs, Volume= 182.0 m³, Depth= 36 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=19 min, Inten=113.4 mm/hr
Area (m²) C Description
5,070.0 1.00 Green Roof
5,070.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 38S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.17
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 25-Year
Duration=19 min,
Inten=113.4 mm/hr
Runoff Area=5,070.0 m²
Runoff Volume=182.0 m³
Runoff Depth=36 mm
Tc=10.0 min
C=1.00
0.1597 m³/s
Toronto 25-Year Duration=19 min, Inten=113.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 30HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 39S: At-Grade Impervious
Runoff = 0.1988 m³/s @ 0.17 hrs, Volume= 226.6 m³, Depth= 32 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=19 min, Inten=113.4 mm/hr
Area (m²) C Description
7,012.0 0.90
7,012.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 39S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.22
0.21
0.2
0.19
0.18
0.17
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 25-Year
Duration=19 min,
Inten=113.4 mm/hr
Runoff Area=7,012.0 m²
Runoff Volume=226.6 m³
Runoff Depth=32 mm
Tc=10.0 min
C=0.90
0.1988 m³/s
Toronto 25-Year Duration=19 min, Inten=113.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 31HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 40P: SWM Tank (243.9L/s)
Inflow Area = 18,647.0 m², 27.19% Impervious, Inflow Depth > 27 mm for 25-Year eventInflow = 0.3491 m³/s @ 0.31 hrs, Volume= 503.5 m³Outflow = 0.1724 m³/s @ 0.43 hrs, Volume= 500.6 m³, Atten= 51%, Lag= 6.9 minPrimary = 0.1724 m³/s @ 0.43 hrs, Volume= 500.6 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 200.0 m² Storage= 40.0 m³Peak Elev= 1.307 m @ 0.43 hrs Surf.Area= 200.0 m² Storage= 261.5 m³ (221.5 m³ above start)
Plug-Flow detention time= 29.9 min calculated for 460.6 m³ (91% of inflow)Center-of-Mass det. time= 18.3 min ( 46.0 - 27.7 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 400.0 m³ 1.00 mW x 200.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 250 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.1724 m³/s @ 0.43 hrs HW=1.307 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.1724 m³/s @ 3.51 m/s)
Pond 40P: SWM Tank (243.9L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.38
0.36
0.34
0.32
0.3
0.28
0.26
0.24
0.22
0.2
0.18
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
Inflow Area=18,647.0 m²
Peak Elev=1.307 m
Storage=261.5 m³
0.3491 m³/s
0.1724 m³/s
Toronto 25-Year Duration=19 min, Inten=113.4 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 32HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 41P: Green Roof
Inflow Area = 5,070.0 m²,100.00% Impervious, Inflow Depth = 36 mm for 25-Year eventInflow = 0.1597 m³/s @ 0.17 hrs, Volume= 182.0 m³Outflow = 0.0721 m³/s @ 0.41 hrs, Volume= 169.7 m³, Atten= 55%, Lag= 14.3 minPrimary = 0.0721 m³/s @ 0.41 hrs, Volume= 169.7 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.024 m @ 0.41 hrs Surf.Area= 10,140.0 m² Storage= 129.9 m³
Plug-Flow detention time= 40.0 min calculated for 169.7 m³ (93% of inflow)Center-of-Mass det. time= 39.2 min ( 53.7 - 14.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 10.1 m³ 1.00 mW x 5,070.00 mL x 0.01 mH Green Roof Media Storage50.7 m³ Overall x 20.0% Voids
#2 100.000 m 405.6 m³ 1.00 mW x 5,070.00 mL x 0.08 mH Green Roof
415.7 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 35.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0721 m³/s @ 0.41 hrs HW=100.024 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0721 m³/s @ 0.28 m/s)
Pond 41P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.17
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=5,070.0 m²
Peak Elev=100.024 m
Storage=129.9 m³
0.1597 m³/s
0.0721 m³/s
Toronto 50-Year Duration=19 min, Inten=134.2 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 33HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=2,069.0 m² 0.00% Impervious Runoff Depth=38 mmSubcatchment 36S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0694 m³/s 79.1 m³
Runoff Area=4,496.0 m² 0.00% Impervious Runoff Depth=11 mmSubcatchment 37S: Pervious Tc=10.0 min C=0.25 Runoff=0.0419 m³/s 47.8 m³
Runoff Area=5,070.0 m² 100.00% Impervious Runoff Depth=42 mmSubcatchment 38S: Green Roof Tc=10.0 min C=1.00 Runoff=0.1891 m³/s 215.5 m³
Runoff Area=7,012.0 m² 0.00% Impervious Runoff Depth=38 mmSubcatchment 39S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.2353 m³/s 268.2 m³
Peak Elev=1.575 m Storage=314.9 m³ Inflow=0.4186 m³/s 598.2 m³Pond 40P: SWM Tank (243.9L/s) Outflow=0.1944 m³/s 595.2 m³
Peak Elev=100.027 m Storage=149.5 m³ Inflow=0.1891 m³/s 215.5 m³Pond 41P: Green Roof Outflow=0.0905 m³/s 203.1 m³
Total Runoff Area = 18,647.0 m² Runoff Volume = 610.6 m³ Average Runoff Depth = 33 mm72.81% Pervious = 13,577.0 m² 27.19% Impervious = 5,070.0 m²
Toronto 50-Year Duration=19 min, Inten=134.2 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 34HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 36S: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0694 m³/s @ 0.17 hrs, Volume= 79.1 m³, Depth= 38 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=19 min, Inten=134.2 mm/hr
Area (m²) C Description
2,069.0 0.90 Impervious Roof
2,069.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 36S: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.075
0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 50-Year
Duration=19 min,
Inten=134.2 mm/hr
Runoff Area=2,069.0 m²
Runoff Volume=79.1 m³
Runoff Depth=38 mm
Tc=10.0 min
C=0.90
0.0694 m³/s
Toronto 50-Year Duration=19 min, Inten=134.2 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 35HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 37S: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0419 m³/s @ 0.17 hrs, Volume= 47.8 m³, Depth= 11 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=19 min, Inten=134.2 mm/hr
Area (m²) C Description
4,496.0 0.25 Pervious Area
4,496.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 37S: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.046
0.044
0.042
0.04
0.038
0.036
0.034
0.032
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 50-Year
Duration=19 min,
Inten=134.2 mm/hr
Runoff Area=4,496.0 m²
Runoff Volume=47.8 m³
Runoff Depth=11 mm
Tc=10.0 min
C=0.25
0.0419 m³/s
Toronto 50-Year Duration=19 min, Inten=134.2 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 36HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 38S: Green Roof
Runoff = 0.1891 m³/s @ 0.17 hrs, Volume= 215.5 m³, Depth= 42 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=19 min, Inten=134.2 mm/hr
Area (m²) C Description
5,070.0 1.00 Green Roof
5,070.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 38S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.21
0.2
0.19
0.18
0.17
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 50-Year
Duration=19 min,
Inten=134.2 mm/hr
Runoff Area=5,070.0 m²
Runoff Volume=215.5 m³
Runoff Depth=42 mm
Tc=10.0 min
C=1.00
0.1891 m³/s
Toronto 50-Year Duration=19 min, Inten=134.2 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 37HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 39S: At-Grade Impervious
Runoff = 0.2353 m³/s @ 0.17 hrs, Volume= 268.2 m³, Depth= 38 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=19 min, Inten=134.2 mm/hr
Area (m²) C Description
7,012.0 0.90
7,012.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 39S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.26
0.250.24
0.23
0.22
0.21
0.2
0.19
0.18
0.17
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.090.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 50-Year
Duration=19 min,
Inten=134.2 mm/hr
Runoff Area=7,012.0 m²
Runoff Volume=268.2 m³
Runoff Depth=38 mm
Tc=10.0 min
C=0.90
0.2353 m³/s
Toronto 50-Year Duration=19 min, Inten=134.2 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 38HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 40P: SWM Tank (243.9L/s)
Inflow Area = 18,647.0 m², 27.19% Impervious, Inflow Depth > 32 mm for 50-Year eventInflow = 0.4186 m³/s @ 0.31 hrs, Volume= 598.2 m³Outflow = 0.1944 m³/s @ 0.43 hrs, Volume= 595.2 m³, Atten= 54%, Lag= 7.3 minPrimary = 0.1944 m³/s @ 0.43 hrs, Volume= 595.2 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 200.0 m² Storage= 40.0 m³Peak Elev= 1.575 m @ 0.43 hrs Surf.Area= 200.0 m² Storage= 314.9 m³ (274.9 m³ above start)
Plug-Flow detention time= 29.4 min calculated for 555.2 m³ (93% of inflow)Center-of-Mass det. time= 19.4 min ( 46.3 - 26.9 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 400.0 m³ 1.00 mW x 200.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 250 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.1944 m³/s @ 0.43 hrs HW=1.574 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.1944 m³/s @ 3.96 m/s)
Pond 40P: SWM Tank (243.9L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.46
0.44
0.42
0.4
0.38
0.36
0.34
0.32
0.3
0.28
0.26
0.24
0.22
0.2
0.18
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
Inflow Area=18,647.0 m²
Peak Elev=1.575 m
Storage=314.9 m³
0.4186 m³/s
0.1944 m³/s
Toronto 50-Year Duration=19 min, Inten=134.2 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 39HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 41P: Green Roof
Inflow Area = 5,070.0 m²,100.00% Impervious, Inflow Depth = 42 mm for 50-Year eventInflow = 0.1891 m³/s @ 0.17 hrs, Volume= 215.5 m³Outflow = 0.0905 m³/s @ 0.40 hrs, Volume= 203.1 m³, Atten= 52%, Lag= 14.0 minPrimary = 0.0905 m³/s @ 0.40 hrs, Volume= 203.1 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.027 m @ 0.40 hrs Surf.Area= 10,140.0 m² Storage= 149.5 m³
Plug-Flow detention time= 36.8 min calculated for 202.7 m³ (94% of inflow)Center-of-Mass det. time= 36.6 min ( 51.1 - 14.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 10.1 m³ 1.00 mW x 5,070.00 mL x 0.01 mH Green Roof Media Storage50.7 m³ Overall x 20.0% Voids
#2 100.000 m 405.6 m³ 1.00 mW x 5,070.00 mL x 0.08 mH Green Roof
415.7 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 35.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.0905 m³/s @ 0.40 hrs HW=100.027 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.0905 m³/s @ 0.30 m/s)
Pond 41P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.21
0.2
0.19
0.18
0.17
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=5,070.0 m²
Peak Elev=100.027 m
Storage=149.5 m³
0.1891 m³/s
0.0905 m³/s
Toronto 100-Year Duration=19 min, Inten=149.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 40HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Time span=0.00-6.00 hrs, dt=0.01 hrs, 601 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=2,069.0 m² 0.00% Impervious Runoff Depth=43 mmSubcatchment 36S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0775 m³/s 88.3 m³
Runoff Area=4,496.0 m² 0.00% Impervious Runoff Depth=12 mmSubcatchment 37S: Pervious Tc=10.0 min C=0.25 Runoff=0.0468 m³/s 53.3 m³
Runoff Area=5,070.0 m² 100.00% Impervious Runoff Depth=47 mmSubcatchment 38S: Green Roof Tc=10.0 min C=1.00 Runoff=0.2110 m³/s 240.4 m³
Runoff Area=7,012.0 m² 0.00% Impervious Runoff Depth=43 mmSubcatchment 39S: At-Grade Impervious Tc=10.0 min C=0.90 Runoff=0.2626 m³/s 299.3 m³
Peak Elev=1.782 m Storage=356.4 m³ Inflow=0.4711 m³/s 668.9 m³Pond 40P: SWM Tank (243.9L/s) Outflow=0.2100 m³/s 665.9 m³
Peak Elev=100.030 m Storage=163.7 m³ Inflow=0.2110 m³/s 240.4 m³Pond 41P: Green Roof Outflow=0.1047 m³/s 228.0 m³
Total Runoff Area = 18,647.0 m² Runoff Volume = 681.3 m³ Average Runoff Depth = 37 mm72.81% Pervious = 13,577.0 m² 27.19% Impervious = 5,070.0 m²
Toronto 100-Year Duration=19 min, Inten=149.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 41HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 36S: Impervious Roof
Collection from various impervious roof areas
Runoff = 0.0775 m³/s @ 0.17 hrs, Volume= 88.3 m³, Depth= 43 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=19 min, Inten=149.8 mm/hr
Area (m²) C Description
2,069.0 0.90 Impervious Roof
2,069.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 36S: Impervious Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.085
0.08
0.075
0.07
0.065
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 100-Year
Duration=19 min,
Inten=149.8 mm/hr
Runoff Area=2,069.0 m²
Runoff Volume=88.3 m³
Runoff Depth=43 mm
Tc=10.0 min
C=0.90
0.0775 m³/s
Toronto 100-Year Duration=19 min, Inten=149.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 42HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 37S: Pervious Landscaping
Remaining landscaped areas to be defined (pavestone, grass, ect)
Runoff = 0.0468 m³/s @ 0.17 hrs, Volume= 53.3 m³, Depth= 12 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=19 min, Inten=149.8 mm/hr
Area (m²) C Description
4,496.0 0.25 Pervious Area
4,496.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 37S: Pervious Landscaping
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.052
0.05
0.048
0.046
0.044
0.042
0.04
0.038
0.036
0.034
0.032
0.03
0.028
0.026
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 100-Year
Duration=19 min,
Inten=149.8 mm/hr
Runoff Area=4,496.0 m²
Runoff Volume=53.3 m³
Runoff Depth=12 mm
Tc=10.0 min
C=0.25
0.0468 m³/s
Toronto 100-Year Duration=19 min, Inten=149.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 43HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 38S: Green Roof
Runoff = 0.2110 m³/s @ 0.17 hrs, Volume= 240.4 m³, Depth= 47 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=19 min, Inten=149.8 mm/hr
Area (m²) C Description
5,070.0 1.00 Green Roof
5,070.0 100.00% Impervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 38S: Green Roof
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.23
0.22
0.21
0.2
0.19
0.18
0.17
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 100-Year
Duration=19 min,
Inten=149.8 mm/hr
Runoff Area=5,070.0 m²
Runoff Volume=240.4 m³
Runoff Depth=47 mm
Tc=10.0 min
C=1.00
0.2110 m³/s
Toronto 100-Year Duration=19 min, Inten=149.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 44HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Subcatchment 39S: At-Grade Impervious
Runoff = 0.2626 m³/s @ 0.17 hrs, Volume= 299.3 m³, Depth= 43 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=19 min, Inten=149.8 mm/hr
Area (m²) C Description
7,012.0 0.90
7,012.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry, Direct Entry
Subcatchment 39S: At-Grade Impervious
Runoff
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.28
0.26
0.24
0.22
0.2
0.18
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
Toronto 100-Year
Duration=19 min,
Inten=149.8 mm/hr
Runoff Area=7,012.0 m²
Runoff Volume=299.3 m³
Runoff Depth=43 mm
Tc=10.0 min
C=0.90
0.2626 m³/s
Toronto 100-Year Duration=19 min, Inten=149.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 45HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 40P: SWM Tank (243.9L/s)
Inflow Area = 18,647.0 m², 27.19% Impervious, Inflow Depth > 36 mm for 100-Year eventInflow = 0.4711 m³/s @ 0.31 hrs, Volume= 668.9 m³Outflow = 0.2100 m³/s @ 0.44 hrs, Volume= 665.9 m³, Atten= 55%, Lag= 7.6 minPrimary = 0.2100 m³/s @ 0.44 hrs, Volume= 665.9 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrs / 3Starting Elev= 0.200 m Surf.Area= 200.0 m² Storage= 40.0 m³Peak Elev= 1.782 m @ 0.44 hrs Surf.Area= 200.0 m² Storage= 356.4 m³ (316.4 m³ above start)
Plug-Flow detention time= 28.9 min calculated for 624.9 m³ (93% of inflow)Center-of-Mass det. time= 20.2 min ( 46.7 - 26.4 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 400.0 m³ 1.00 mW x 200.00 mL x 2.00 mH Cistern + Orifice
Device Routing Invert Outlet Devices
#1 Primary 0.200 m 250 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.2099 m³/s @ 0.44 hrs HW=1.782 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.2099 m³/s @ 4.28 m/s)
Pond 40P: SWM Tank (243.9L/s)
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
Inflow Area=18,647.0 m²
Peak Elev=1.782 m
Storage=356.4 m³
0.4711 m³/s
0.2100 m³/s
Toronto 100-Year Duration=19 min, Inten=149.8 mm/hrRichview Square Printed 3/8/2019Prepared by WSP Canada Inc.
Page 46HydroCAD® 10.00-21 s/n 05585 © 2018 HydroCAD Software Solutions LLC
Summary for Pond 41P: Green Roof
Inflow Area = 5,070.0 m²,100.00% Impervious, Inflow Depth = 47 mm for 100-Year eventInflow = 0.2110 m³/s @ 0.17 hrs, Volume= 240.4 m³Outflow = 0.1047 m³/s @ 0.40 hrs, Volume= 228.0 m³, Atten= 50%, Lag= 13.8 minPrimary = 0.1047 m³/s @ 0.40 hrs, Volume= 228.0 m³
Routing by Stor-Ind method, Time Span= 0.00-6.00 hrs, dt= 0.01 hrsPeak Elev= 100.030 m @ 0.40 hrs Surf.Area= 10,140.0 m² Storage= 163.7 m³
Plug-Flow detention time= 35.6 min calculated for 228.0 m³ (95% of inflow)Center-of-Mass det. time= 35.0 min ( 49.5 - 14.5 )
Volume Invert Avail.Storage Storage Description
#1 99.990 m 10.1 m³ 1.00 mW x 5,070.00 mL x 0.01 mH Green Roof Media Storage50.7 m³ Overall x 20.0% Voids
#2 100.000 m 405.6 m³ 1.00 mW x 5,070.00 mL x 0.08 mH Green Roof
415.7 m³ Total Available Storage
Device Routing Invert Outlet Devices
#1 Primary 100.000 m 100 mm Horiz. Orifice/Grate X 35.00 C= 0.800 Limited to weir flow at low heads
Primary OutFlow Max=0.1047 m³/s @ 0.40 hrs HW=100.030 m (Free Discharge)1=Orifice/Grate (Weir Controls 0.1047 m³/s @ 0.31 m/s)
Pond 41P: Green Roof
InflowPrimary
Hydrograph
Time (hours)6543210
Flo
w
(m³/
s)
0.23
0.22
0.21
0.2
0.19
0.18
0.17
0.16
0.15
0.14
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=5,070.0 m²
Peak Elev=100.030 m
Storage=163.7 m³
0.2110 m³/s
0.1047 m³/s
APPENDIX
C WATER QUALITY UNIT DETAILS
JF4-1-1 1 1 1.2 7.6 85
1
STANDARD OFFLINE
Thank you for the opportunity to present this information to you and your client.
CDN/Int'l: 1 (800) 565-4801 | US: 1 (888) 279-8826 www.ImbriumSystems.com
Regular scheduled inspections and maintenance is necessary to assure proper functioning of the
Jellyfish Filter. The maintenance interval is designed to be a minimum of 12 months, but this will
vary depending on site loading conditions and upstream pretreatment measures. Quarterly
inspections and inspections after all storms beyond the 5-year event are recommended until enough
historical performance data has been logged to comfortably initiate an alternative inspection interval.
Maintenance
Please see www.ImbriumSystems.com for more information.
Jellyfish Filter System RecommendationThe Jellyfish Filter model JF4-1-1 is recommended to meet the water quality objective by treating a
flow of 7.6 L/s, which meets or exceeds 90% of the average annual rainfall runoff volume based on
18 years of TORONTO CENTRAL rainfall data for this site. This model has a sediment capacity of
85 kg, which meets or exceeds the estimated average annual sediment load.
Sediment
Capacity (kg)
Treatment
Flow Rate
(L/s)
The Jellyfish Filter System
Jellyfish
Model
Jellyfish Filter Sizing Report
This report provides information for the sizing and specification of the Jellyfish Filter. When
designed properly in accordance to the guidelines detailed in the Jellyfish Filter Technical Manual,
the Jellyfish Filter will exceed the performance and longevity of conventional horizontal bed and
granular media filters.
Please see www.ImbriumSystems.com for more information.
Project Information
Location
Monday, March 04, 2019
Richview Square - Catchment 201
Date
Project Name
Jellyfish Filter Design Overview
15M-00048-03
Toronto
Project Number
Number of
High-Flo
Cartridges
Number of
Draindown
Cartridges
Manhole
Diameter
(m)
The patented Jellyfish Filter is an engineered stormwater quality treatment technology featuring
unique membrane filtration in a compact stand-alone treatment system that removes a high level
and wide variety of stormwater pollutants. Exceptional pollutant removal is achieved at high
treatment flow rates with minimal head loss and low maintenance costs. Each lightweight Jellyfish
Filter cartridge contains an extraordinarily large amount of membrane surface area, resulting in
superior flow capacity and pollutant removal capacity.
90% Total Copper, 81% Total Lead, 70% Total Zinc
Free oil, Floatable trash and debris
l
l
l
2
Jellyfish Filter Treatment Functions
The ability to capture fine particles as indicated by an effluent d50 median of 3 microns
for all monitotred storm events, and a median effluent turbidity of 5 NTUs;
A median Total Phosphorus removal of 59%, and a median Total Nitrogen removal of
51%.
Pre-treatment and Membrane Filtration
A median TSS removal efficiency of 89%, and a median SSC removal of 99%;
CDN/Int'l: 1 (800) 565-4801 | US: 1 (888) 279-8826
Field Proven Peformance
Performance
The Jellyfish filter has been field-tested on an urban site with 25 TARP qualifying rain events and
field monitored according to the TARP field test protocol, demonstrating:
Particulate-bound pollutants such as nutrients, toxic metals, hydrocarbons and bacteria
Jellyfish efficiently captures a high level of Stormwater pollutants, including:
www.ImbriumSystems.com
59% TP removal & 51% TN removal89% of the total suspended solids (TSS) load, including particles less than 5 microns
Name:
State:
ID:
Record:
Co-ords:
JF4-1-1 1 1 1.2 2313 0.34 379 7.6 85
JF4-2-1 2 1 1.2 2313 0.34 379 12.6 142
JF6-3-1 3 1 1.8 5205 0.79 848 17.7 199
JF6-4-1 4 1 1.8 5205 0.79 848 22.7 256
JF6-5-1 5 1 1.8 5205 0.79 848 27.8 313
JF6-6-1 6 1 1.8 5205 0.79 848 28.6 370
JF8-6-2 6 2 2.4 9252 1.42 1469 35.3 398
JF8-7-2 7 2 2.4 9252 1.42 1469 40.4 455
JF8-8-2 8 2 2.4 9252 1.42 1469 45.4 512
JF8-9-2 9 2 2.4 9252 1.42 1469 50.5 569
JF8-10-2 10 2 2.4 9252 1.42 1469 50.5 626
JF10-11-3 11 3 3.0 14456 2.21 2302 63.1 711
JF10-12-3 12 3 3.0 14456 2.21 2302 68.2 768
JF10-12-4 12 4 3.0 14456 2.21 2302 70.7 796
JF10-13-4 13 4 3.0 14456 2.21 2302 75.7 853
JF10-14-4 14 4 3.0 14456 2.21 2302 78.9 910
JF10-15-4 15 4 3.0 14456 2.21 2302 78.9 967
JF10-16-4 16 4 3.0 14456 2.21 2302 78.9 1024
JF10-17-4 17 4 3.0 14456 2.21 2302 78.9 1081
JF10-18-4 18 4 3.0 14456 2.21 2302 78.9 1138
JF10-19-4 19 4 3.0 14456 2.21 2302 78.9 1195
JF12-20-5 20 5 3.6 20820 3.2 2771 113.6 1280
JF12-21-5 21 5 3.6 20820 3.2 2771 113.7 1337
JF12-22-5 22 5 3.6 20820 3.2 2771 113.7 1394
JF12-23-5 23 5 3.6 20820 3.2 2771 113.7 1451
JF12-24-5 24 5 3.6 20820 3.2 2771 113.7 1508
JF12-25-5 25 5 3.6 20820 3.2 2771 113.7 1565
JF12-26-5 26 5 3.6 20820 3.2 2771 113.7 1622
JF12-27-5 27 5 3.6 20820 3.2 2771 113.7 1679
3
Project Name: Richview Square - Catchment 201
Number of
High-Flo
Cartridges
Jellyfish
Model
Treatment
Flow Rate
(L/s)
Sediment
Capacity
(kg)
www.ImbriumSystems.comCDN/Int'l: 1 (800) 565-4801 | US: 1 (888) 279-8826
Recommendation
Design System Requirements
Number of
Draindown
Cartridges
Manhole
Diameter
(m)
Wet Vol
Below Deck
(L)
Sump
Storage
(m³)
Oil
Capacity
(L)
Treating 90% of the average annual runoff volume,
1395 m³, with a suspended sediment concentration of
60 mg/L.
7.3 L/s
45°30'N, 90°30'W
Phone #:
WSP Canada Group Ltd.
Sediment
Loading
100
1982 to 1999
Pretreatment Credit:
n/aPeak Release Rate:
n/a
90% of the Average Annual Runoff based on 18 years
of TORONTO CENTRAL rainfall data:
Flow
Loading
84 kg
Company:
Contact:
Notes
Total Area:
Runoff Coefficient:
Upstream Detention
0.27 ha
Project Number:
Location:
15M-00048-03
The Jellyfish Filter model JF4-1-1 is recommended to meet the water quality objective by treating a
flow of 7.6 L/s, which meets or exceeds 90% of the average annual rainfall runoff volume based on
18 years of TORONTO CENTRAL rainfall data for this site. This model has a sediment capacity of
85 kg, which meets or exceeds the estimated average annual sediment load.
Project Information Rainfall
Samer Elhallak
Designer Information
Drainage Area
0.8
TORONTO CENTRALMonday, March 04, 2019
Toronto
ON
Date:
Jellyfish Filter Design Notesl
Jellyfish Filter Typical Layout
l
l
l
l
l
l
l
l
4
3.6 40º 300 450
www.ImbriumSystems.comCDN/Int'l: 1 (800) 565-4801 | US: 1 (888) 279-8826
The Jellyfish Filter can be built at all depths of cover generally associated with conventional
stormwater conveyance systems. For sites that require minimal depth of cover for the stormwater
infrastructure, the Jellyfish Filter can be applied in a shallow application using a hatch cover. The
general minimum depth of cover is 36 inches (915 mm) from top of the underslab to outlet invert.
If driving head caclulations account for water elevation during submerged conditions the Jellyfish
Filter will function effectively under submerged condtions.
Jellyfish Filter systems may incorporate grated inlets depending on system configuration.
For sites with water quality treatment flow rates or mass loadings that exceed the design flow rate of
the largest standard Jellyfish Filter manhole models, systems can be designed that hydraulically
connect multiple Jellyfish Filters in series or alternatively Jellyfish Vault units can be designed.
2.4 52º 250 300
3.0 48º 300 450
1.2 62º 150 200
1.8 59º 200 250
Typically the Jellyfish Filter is designed in an offline configuration, as all stormwater filter systems
will perform for a longer duration between required maintenance services when designed and
applied in off-line configurations. Depending on the design parameters, an optional internal bypass
may be incorporated into the Jellyfish Filter, however note the inspection and maintenance
frequency should be expected to increase above that of an off-line system. Speak to your local
representative for more information.
Typically, 18 inches (457 mm) of driving head is designed into the system, calculated as the
difference in elevation between the top of the diversion structure weir and the invert of the Jellyfish
Filter outlet pipe. Alternative driving head values can be designed as 12 to 24 inches (305 to
610mm) depending on specific site requirements, requiring additional sizing and design assistance.
Typically, the Jellyfish Filter is designed with the inlet pipe configured 6 inches (150 mm) above the
outlet invert elevation. However, depending on site parameters this can vary to an optional
configuration of the inlet pipe entering the unit below the outlet invert elevation. The Jellyfish Filter can accommodate multiple inlet pipes within certain restrictions.
Model Diameter (m)Minimum Angle
Inlet / Outlet Pipes
Minimum Inlet Pipe
Diameter (mm)
Minimum Outlet Pipe
Diameter (mm)
While the optional inlet below deck configuration offers 0 to 360 degree flexibility between the inlet
and outlet pipe, typical systems conform to the following:
JF6-5-1 5 1 1.8 27.8 313
1
STANDARD OFFLINE
Thank you for the opportunity to present this information to you and your client.
CDN/Int'l: 1 (800) 565-4801 | US: 1 (888) 279-8826 www.ImbriumSystems.com
Regular scheduled inspections and maintenance is necessary to assure proper functioning of the
Jellyfish Filter. The maintenance interval is designed to be a minimum of 12 months, but this will
vary depending on site loading conditions and upstream pretreatment measures. Quarterly
inspections and inspections after all storms beyond the 5-year event are recommended until enough
historical performance data has been logged to comfortably initiate an alternative inspection interval.
Maintenance
Please see www.ImbriumSystems.com for more information.
Jellyfish Filter System RecommendationThe Jellyfish Filter model JF6-5-1 is recommended to meet the water quality objective by treating a
flow of 27.8 L/s, which meets or exceeds 90% of the average annual rainfall runoff volume based on
18 years of TORONTO CENTRAL rainfall data for this site. This model has a sediment capacity of
313 kg, which meets or exceeds the estimated average annual sediment load.
Sediment
Capacity (kg)
Treatment
Flow Rate
(L/s)
The Jellyfish Filter System
Jellyfish
Model
Jellyfish Filter Sizing Report
This report provides information for the sizing and specification of the Jellyfish Filter. When
designed properly in accordance to the guidelines detailed in the Jellyfish Filter Technical Manual,
the Jellyfish Filter will exceed the performance and longevity of conventional horizontal bed and
granular media filters.
Please see www.ImbriumSystems.com for more information.
Project Information
Location
Monday, March 04, 2019
Richview Square - Catchment 202
Date
Project Name
Jellyfish Filter Design Overview
15M-00048-03
Toronto
Project Number
Number of
High-Flo
Cartridges
Number of
Draindown
Cartridges
Manhole
Diameter
(m)
The patented Jellyfish Filter is an engineered stormwater quality treatment technology featuring
unique membrane filtration in a compact stand-alone treatment system that removes a high level
and wide variety of stormwater pollutants. Exceptional pollutant removal is achieved at high
treatment flow rates with minimal head loss and low maintenance costs. Each lightweight Jellyfish
Filter cartridge contains an extraordinarily large amount of membrane surface area, resulting in
superior flow capacity and pollutant removal capacity.
90% Total Copper, 81% Total Lead, 70% Total Zinc
Free oil, Floatable trash and debris
l
l
l
2
Jellyfish Filter Treatment Functions
The ability to capture fine particles as indicated by an effluent d50 median of 3 microns
for all monitotred storm events, and a median effluent turbidity of 5 NTUs;
A median Total Phosphorus removal of 59%, and a median Total Nitrogen removal of
51%.
Pre-treatment and Membrane Filtration
A median TSS removal efficiency of 89%, and a median SSC removal of 99%;
CDN/Int'l: 1 (800) 565-4801 | US: 1 (888) 279-8826
Field Proven Peformance
Performance
The Jellyfish filter has been field-tested on an urban site with 25 TARP qualifying rain events and
field monitored according to the TARP field test protocol, demonstrating:
Particulate-bound pollutants such as nutrients, toxic metals, hydrocarbons and bacteria
Jellyfish efficiently captures a high level of Stormwater pollutants, including:
www.ImbriumSystems.com
59% TP removal & 51% TN removal89% of the total suspended solids (TSS) load, including particles less than 5 microns
Name:
State:
ID:
Record:
Co-ords:
JF4-1-1 1 1 1.2 2313 0.34 379 7.6 85
JF4-2-1 2 1 1.2 2313 0.34 379 12.6 142
JF6-3-1 3 1 1.8 5205 0.79 848 17.7 199
JF6-4-1 4 1 1.8 5205 0.79 848 22.7 256
JF6-5-1 5 1 1.8 5205 0.79 848 27.8 313
JF6-6-1 6 1 1.8 5205 0.79 848 28.6 370
JF8-6-2 6 2 2.4 9252 1.42 1469 35.3 398
JF8-7-2 7 2 2.4 9252 1.42 1469 40.4 455
JF8-8-2 8 2 2.4 9252 1.42 1469 45.4 512
JF8-9-2 9 2 2.4 9252 1.42 1469 50.5 569
JF8-10-2 10 2 2.4 9252 1.42 1469 50.5 626
JF10-11-3 11 3 3.0 14456 2.21 2302 63.1 711
JF10-12-3 12 3 3.0 14456 2.21 2302 68.2 768
JF10-12-4 12 4 3.0 14456 2.21 2302 70.7 796
JF10-13-4 13 4 3.0 14456 2.21 2302 75.7 853
JF10-14-4 14 4 3.0 14456 2.21 2302 78.9 910
JF10-15-4 15 4 3.0 14456 2.21 2302 78.9 967
JF10-16-4 16 4 3.0 14456 2.21 2302 78.9 1024
JF10-17-4 17 4 3.0 14456 2.21 2302 78.9 1081
JF10-18-4 18 4 3.0 14456 2.21 2302 78.9 1138
JF10-19-4 19 4 3.0 14456 2.21 2302 78.9 1195
JF12-20-5 20 5 3.6 20820 3.2 2771 113.6 1280
JF12-21-5 21 5 3.6 20820 3.2 2771 113.7 1337
JF12-22-5 22 5 3.6 20820 3.2 2771 113.7 1394
JF12-23-5 23 5 3.6 20820 3.2 2771 113.7 1451
JF12-24-5 24 5 3.6 20820 3.2 2771 113.7 1508
JF12-25-5 25 5 3.6 20820 3.2 2771 113.7 1565
JF12-26-5 26 5 3.6 20820 3.2 2771 113.7 1622
JF12-27-5 27 5 3.6 20820 3.2 2771 113.7 1679
3
Project Name: Richview Square - Catchment 202
Number of
High-Flo
Cartridges
Jellyfish
Model
Treatment
Flow Rate
(L/s)
Sediment
Capacity
(kg)
www.ImbriumSystems.comCDN/Int'l: 1 (800) 565-4801 | US: 1 (888) 279-8826
Recommendation
Design System Requirements
Number of
Draindown
Cartridges
Manhole
Diameter
(m)
Wet Vol
Below Deck
(L)
Sump
Storage
(m³)
Oil
Capacity
(L)
Treating 90% of the average annual runoff volume,
5017 m³, with a suspended sediment concentration of
60 mg/L.
23.1 L/s
45°30'N, 90°30'W
Phone #:
WSP Canada Group Ltd.
Sediment
Loading
100
1982 to 1999
Pretreatment Credit:
n/aPeak Release Rate:
n/a
90% of the Average Annual Runoff based on 18 years
of TORONTO CENTRAL rainfall data:
Flow
Loading
301 kg
Company:
Contact:
Notes
Total Area:
Runoff Coefficient:
Upstream Detention
1.15 ha
Project Number:
Location:
15M-00048-03
The Jellyfish Filter model JF6-5-1 is recommended to meet the water quality objective by treating a
flow of 27.8 L/s, which meets or exceeds 90% of the average annual rainfall runoff volume based on
18 years of TORONTO CENTRAL rainfall data for this site. This model has a sediment capacity of
313 kg, which meets or exceeds the estimated average annual sediment load.
Project Information Rainfall
Samer Elhallak
Designer Information
Drainage Area
0.71
TORONTO CENTRALMonday, March 04, 2019
Toronto
ON
Date:
Jellyfish Filter Design Notesl
Jellyfish Filter Typical Layout
l
l
l
l
l
l
l
l
4
3.6 40º 300 450
www.ImbriumSystems.comCDN/Int'l: 1 (800) 565-4801 | US: 1 (888) 279-8826
The Jellyfish Filter can be built at all depths of cover generally associated with conventional
stormwater conveyance systems. For sites that require minimal depth of cover for the stormwater
infrastructure, the Jellyfish Filter can be applied in a shallow application using a hatch cover. The
general minimum depth of cover is 36 inches (915 mm) from top of the underslab to outlet invert.
If driving head caclulations account for water elevation during submerged conditions the Jellyfish
Filter will function effectively under submerged condtions.
Jellyfish Filter systems may incorporate grated inlets depending on system configuration.
For sites with water quality treatment flow rates or mass loadings that exceed the design flow rate of
the largest standard Jellyfish Filter manhole models, systems can be designed that hydraulically
connect multiple Jellyfish Filters in series or alternatively Jellyfish Vault units can be designed.
2.4 52º 250 300
3.0 48º 300 450
1.2 62º 150 200
1.8 59º 200 250
Typically the Jellyfish Filter is designed in an offline configuration, as all stormwater filter systems
will perform for a longer duration between required maintenance services when designed and
applied in off-line configurations. Depending on the design parameters, an optional internal bypass
may be incorporated into the Jellyfish Filter, however note the inspection and maintenance
frequency should be expected to increase above that of an off-line system. Speak to your local
representative for more information.
Typically, 18 inches (457 mm) of driving head is designed into the system, calculated as the
difference in elevation between the top of the diversion structure weir and the invert of the Jellyfish
Filter outlet pipe. Alternative driving head values can be designed as 12 to 24 inches (305 to
610mm) depending on specific site requirements, requiring additional sizing and design assistance.
Typically, the Jellyfish Filter is designed with the inlet pipe configured 6 inches (150 mm) above the
outlet invert elevation. However, depending on site parameters this can vary to an optional
configuration of the inlet pipe entering the unit below the outlet invert elevation. The Jellyfish Filter can accommodate multiple inlet pipes within certain restrictions.
Model Diameter (m)Minimum Angle
Inlet / Outlet Pipes
Minimum Inlet Pipe
Diameter (mm)
Minimum Outlet Pipe
Diameter (mm)
While the optional inlet below deck configuration offers 0 to 360 degree flexibility between the inlet
and outlet pipe, typical systems conform to the following: