Page 1 of 1 PETROBEL SETH ONSHORE DEVELOPMENT 4187-440 EGYPT MONTHLY PROGRESS REPORT NO.2 Rev. 0 4187-440 SETH ONSHORE DEVELOPMENT MONTHLY PROGRESS REPORT NO.2 AS OF 30 APRIL 2011 v I I I 0 18/05/2011 ISSUED FOR IMPLEMENTATION If/' /-,1'.- .... r- REV DATE REVISIONS v BY I CH'D APPR

Transcript of Monthly Progress Report No 2 (As of Apr 30 2011).pdf

Page 1 of 1

PETROBEL SETH ONSHORE DEVELOPMENT 4187-440

EGYPT MONTHLY PROGRESS REPORT NO.2 Rev. 0

4187-440 SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT NO.2

AS OF 30 APRIL 2011

• v I I I

0 18/05/2011 ISSUED FOR IMPLEMENTATION If/' /-,1'.- ....r-REV DATE REVISIONS v BY I CH'D APPR

PTB

Egypt

Contents

•Enpp:l.SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

PAGE 1 OF5

4187-440

Rev. (0

18-MAY-2011

I. Project Description

2. Parties Involved and Relevant Scope

3. Schednle Milestones

4. Major Activities Completed

5. Major Activities in Progress

6. Major Activities To Be Started During Next Reporting Period

7. Area of concern

7.1. Progress summary Sheets With Relevant S-Curves

7.2. Progress Control Sheets

7.3. Updated Schedule

7.4. Critical and Near Critical Activities

7.5. One Month Look Ahead Report

7. 6. Procurement Status.

7.7. Equipment and material status report

7.8. Alert report

PTB

Egypt

1.0 Project Description:

SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

PAGE20F5

4187-440

Rev. (0)

18-MAY-20II

The Temsah Pliocene Gas Gathering Network is in operation to collect the gas production from several Pliocenefields located in the Temsah area.Actually the only Denise A and Tuna productions are gathered by the new sealine, and in the following months alsoDenise B and Seth Fields.

The whole new production is transported to the onshore El Gamil plant via a new 32" export pipeline.Denise A reservoir production (Pliocene "heavier" gas) is separated on TNW2 platform. The gas phase is conveyedto El Gamil plant through the new 32" trunk-line.

Tuna and Denise B productions will be collected into a common subsea PLEM and conveyed via a new 24" sealineto the Denise A SSIV; Seth production will be routed via 16" sealines to the Tuna PLEM, Km 10.5 approximately.

During the EI Gamil Upgrading Project Phase (I)a dedicated Slug Catcher for the Denise A Production has beenforeseen and installed.

With Seth Onshore Development Project, the installation of a new slug catcher operating in parallel with theexisting Denise Slug Catcher has been foreseen.

2.0 Parties Involved and Relevant Scope:

PTB: Owner

ENPPI: Contractor shall perfonn basic, detailed engineering and procurement services.

3.0 Schedule Milestones:

Milestone

Project Coming Into Force

Complete Engineering Services

Complete Procurement Services

Planned

22-DEC-1O

22-SEP-11

20-JAN-12

Actual

22-DEC-IO

Expected

22-SEP-ll

20-JAN-12

4.0Major Activities Completed During the Current Reporting Period:4.1. Engineering

Basic engineering review completion

-/ Process• Hazardous Area Classification Schedule IFD• HSE philosophy IFD• Detection And Alarm Layout Drawings IFD• Fire Fighting Layout Drawings IFD

PTB

Egypt

•E:n.pp.l.SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

if Piping• Under Ground Composite Drawing IFD• Under Ground Piping Standard Details IFD• piping specification classes IFD• Standard Piping Support Details IFD

if Electrical• Earthing Layout IFD• Hazardous Area Classification Layout IFD

if Civil• Standard Drawings IFA

PAGE30F5

4187-440

Rev. (0

18-MAY-201I

4.2. Procurement

• Piping Bulk Bidding

5.0Major Activities in Progress During the Current Reporting Period:

5.1. Engineering

if Process• Fire Fighting System Technical Evaluation• Detection and Alarm system Technical Evaluation

5.2. Procurement• Piping bulk Bidding

6.0Major Activities To Be Started / Completed During Next Reporting Period:

6.1. Engineering

if Process• Cause and effect IFD• Process cause and effect matrix IFD• Fire and gas cause and effect IFD• Fire and gas cable routing drawings IFD• Fire protection system TER

if Piping• Piping Bulk TER

PTB

Egypt

•Enpp1SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

.{ Instrumentation• Field Instrument Cable Routing IFD• Junction Box Interconnections IFD• Field Instrument Layouts IFD• Loop Diagrams IFD• Instrument Index IFD• Instrument Cable Schedule IFD• Instrument Hook Up And Supporting Drawings IFD• I/O list IFD• Instrument Bulk Material MRQ's• Instrument Cable Trays MRQ's

.{ Electrical• Electrical Bulk MTO

.{ Civil

• Standard Drawings IFC• Miscellaneous pipe support Foundation Drawings IFA

PAGE 4 OF 5

4187-440

Rev. (0

18-MAY-2011

6.2. Procurement

• Instrument Bulk Material Bidding• Electrical Bulk Bidding• Piping bulk Bidding

PTB

Egypt

•Enppa.SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

7.ATTACHMENTS

PAGE50F5

4187-440

Rev. (0

18-MAY-2011

II

rI

PTB

Egypt

•E:n.pp.l.SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

7.l.Progress summary Sheets With Relevant S-Curves

4187-440

Rev. (0

18-MAY-2011

Summary Report

Overall

Project No.: 4187-440

SETH ONSHORE PROJECTAs Of: 30-Apr-11

Item Description Relative Planned Actual DuringWeight % % %

"Engineering 76.55% 39.98 27.26 10.26

, ": : : :

";;:c-;;r~m:n~ - - - - - - - - - - - - - - - r- --;:::---~-- -275""; - - - t - - - ~.;; - - - -i - - - -:.; - --

~ ~ ~ L ~ _

Total

Monday, May 16. 2011

100.00%

Page 1 of 1

35.66 25.25 8.86

Layout No.1

Data'Nes Systems, Release 2.21

EDpptProject No.: 4187.440

SETH ONSHORE PROJECT

Overall

Progress Curve

As Of: 30·Apr-11

100

90 lp'a~ned % =

IActual %=

80 : ....

70

60~IIIIII

" 50~

Cl0~

0..40

30

20

10

35.66 I25.25 I

:

;

;.

;

.; . - -: • •

0

..." ..." ...... ...... ...... ...... ...... ...... ... ...... ...... ...... ...... ...... ...'l- ...'l- ...'l-",' c: ')"C-<$ ",' ~~/ .: ~..« ~ ,,'" ",<$ G.;P" " .J: c: ":J'lJ.<$

",' ~~.~o Qe ~e.,.q

)'" )'" .,. 0" ~o Qe ~e

Time I Date

---"'-_.--- ..._.-- ..

Actual - - • Planned

--------- ._-- ._--------- ...•---_...:

Layout NO.1

Dala'Nes Systems, Release 2.21

Summary ReportEllppl

Overall

Enaineerina

Project No.: 4187-440

SETH ONSHORE PROJECTAsOf: 30-Apr-11

Item Description Relative Planned Actual DuringWeight % % %

...----------------------,...----------.-----------....,.-------------.---------· ....i Process : 17.92% : 45.98 ; 34.09 ; 12.38: ::::· ....~--------------------~--------~--------~--------~---------i Piping i 42.73% i 31.76 i 30.25 i 7.03

~--------------------~--------~--------~--------~----- ----i Instrumentation i 12.40% i 38.27 i 5.19 i 5.19

~--------------------~--------~--------~--------~----- ----i Electrical i 5.51% i 73.33 i 40.00 1 40.00L L L L j -- __· ....i Pressure Vessels i 4.90% i 65.00 i 65.00 i 0.00

~--------------------~--------~--------~--------~----- ----i Civil i 16.54% i 37.50 i 13.24 i 13.24L ~ ~ L ~ _

Total

Tuesday, May 17, 2011

100.00%

Page 1 of 2

39.98 27.26 10.26

Layout No.1

Data'Nes Systems, Release 2.21

100

90

80

70

60

"~~ 50~

'"£40

30

20

10

(Planned % =

IActual % =

39.98 l27.26 I

.•••,,

•.:

Project No.: 4187-440

SETH ONSHORE PROJECT

Proffesional Services

Engineering

•:..':

,"" .... ,

Progress Curve

o-l--~~=------i--~-~----:--~-~-~-:------i-------i----i-----i---i---1Nov-10 Dec-10 Jan-11 Feb·11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

Time I Date

Actual - - • Planned

Layout No.1

Data'Nes Systems, Release 2.21

Summary Report

Overall

Procurement

Project No.: 4187-440

SETH ONSHORE PROJECTAs Of: 30-Apr-11

Item Description Relative Planned Actual DuringWeight % % %

'i Purchasing 42.00% 42.86 38.57 8.57~ ~ ~ i ~ ----

i Expediting ! 34.00% ! 10.44 i 7.35 i 2.06

~--------------------~--------~--------~--------~----- ----i Inspection ! 24.00% ! 0.00 ! 0.00 ! 0.00L L L l J _

Total

Tuesday, May 17, 2011

100.00%

Page 20f2

21.55 18.70 4.30

Layout No.1

Data'Nes Systems, Release 2.21

EnpplProject No,: 4187.440

SETH ONSHORE PROJECTProgress Curve

Proffesional Services As Of 30-Apr~11

Procurement

'... . -;

, :,,

--,, ,

••

,•

• • o!l

,:,.'

21,551

18,70 I

':

Iplanned % =

IActual % =

100

90

80

70

60..00

50~Cle0-

40

30

20

10

Feb·12 Mar-12Jan-12o.c-11Nov~11Ocl·11Aug-11 Sep-11Jut-11Apr-11 May-11 Jun-11Mar-11Feb-11o.c-10

.. ,- ......,;-"--~o.jo....:.=--T..c.'-----;---;--~'---;_--;_--;_--.;_--.;_--..;_--..;_--.;..--.;..--..;..--_:_--_/Nov~10

• • • Planned

Time I Date

Actual I,,__, ' " ,, , ", J

Layout No, 1

Data'Nes Systems, Release 2.21

Enppl 4187·470 PTB, SETH ONSHORE PROJECT

DELAY ANALYSIS

AS OF 30-Apr·11

Process CaUse and effect matrixfire & gas I/O IIsl

11.89 1.54Halardous area c1asslflcotion s~hedule

24-Mar-ll 26·May-l1Firefightlng system layout drawing

Detection and alarm layout draWing

1.51 0.52Pplping Valves Vendor prints review

27-Feb·ll 20-May-ll

Instrument Index

I/o listInstrument Hook Up And Supporting Drawings

33.0& 3.59 Field Instrumenllayouts 30·Mar-1l 26-M"y-U

Field Instrument Cable Routing

Instrument Bulk MRQ

Instrument Cable T,a s MRQ

33.33 1.66Electrical Bulk MTO

24·Mar-ll 24-May-ll

24.26 3.10Civil standard drawings IFe

24-M.r-ll i6-Apr·nMisc. Steel supports found"tion plan & details IFD

Instrument I Fire & gas cables RFQ The delay of MRQ's issuanceElectrical bulk material RFQ

4.29 0.47I....trument Bulk RFQ 13·Apr-ll 26-May-llInstrument I Fire & gas Cable Trays RFQ

In progress

3.09 0.24Piping Valves start fabrication

17·Feb·ll 18·May·ll

PTB

Egypt

•Enpp1SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

7.2.Progress Control Sheets

4187-440

Rev. (0

18-MAY-2011

~

I

I

Project No.: 4187·440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%

0.00%

0.00%

0.00%

20.00%

60.00%

60.00%

0.00%

0.00%

60.00%

60.00%

4.27%

4.27%

4.27%

4.27%

4.27%

20

20

20

40

40

4.27% 60.00% 20.00%

20•• « ••••

40.... - _.40

4.27% 60.00% 60.00%

20. ... - - -40

_ ... _.-40

27-Jul-11

16-Aug-11

22-May-11 20. - - .... - .. - ....2S-May-11 40. .31-Jul-11 40

11-Aug-11..... - ..17-Aug-11. .. "" ...02-Sep-11

11-Apr-11." .

08-Apr-11•• _ ••• _ ••• T •• _

:13-Mar-11

:13-Nov-11

:28-Nov-11

cause and effect

81art

Start

Start

Start :ZO-Feb-11 29-Mar-11· . "De~i~~ T ••••• 'i24~Feb-;; . ~ . « • « •••

............. ., .Construction : 27-Jul-11

Start :03-Apr-11 . 25-Apr-11.......... - -' "0"·············« .Design : 07-Apr-11 , 19-May-11

· .. Co'n~lr'ucti~~ . - . -!24~Au~~11' . " 23-Au"g:11 .

· - - - - - " - ..

• •• ~e.si~~ ••••••Finish

Start

Design :17-Mar-11 , 18-Apr-11· . - - - , ',' - - - - -Finish :17-Aug-11

_ ••• _ •• r " •••• _ • •••

Design !OS-Dec-11.............., .Finish :21-Dec-11

Process cause and effect matrix

Fire and

Hazardous area classification schedule

Fire & gas 110 list

Pre-commissioning procedure

Commissioning procedure

Design ,20-Nov-11 02-Aug-11 40

" ••• Fi~is"h' •• :~~Jo6~De~-;1' • " •• :,~~:~8-AUi~~':_:_~.~ 40'~ _

HSE philosophy specification

20

40

40

29.91% I 42.86% 22.86%

Drawin s

Fire fighting system layout drawing

Start : 13-Mar-11" ',' " .. " ..

Design :17-Mar-11.............. , .••• ~o.n~tr.u:ti?~ • _ ~ .:!7:~u~-~~ •

20

40

40

3.42% 60.00% 60.00%

* Weights ofActivities are calculated relative to (Process)

Tuesday, May 17, 2011 Page 1 of 19

Layout NO.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

Milestone I Dates I Milestone I * Relative Planned I Actual

I Planned Actual Expected I Value Weight Progress% Progress%

Overall

••••••••• ~ • « • ',' • • • • •• • •••• «««.« ••••••

0.00%60.00%4.27%

20

12-May-11

18-May-11....... .01-Sep-11

4.27% 60.00% 0.00%

16.May-11 20.... _. .......19-May-11 40. . «_. - . .. ... .08-Sep-11 40... .. _.

4.27% 60.00% 60.00%

:27-Mar-11Start

Design :31-Mar-11« •••••••••••• ",' ••• « " •••••••

:04-Sep-11

Start :03-Apr-11" ••••• - • - •••• ',' ••••• «

Design : 07-Apr-11

-.. C;n~t;ucti~~ ... '!11~Se~-11' .

Start ,'OS-Mar-lt 13-Apr-11••• - ••••••• - • ',' •••••••• « ••• - -

Design !to-Mar-tt , 20-Apr-11••••••••••••••, •••• -'. c - ••••••

Construction :10-Aug-11

Detection and alarm layout drawing

Fire fighting, safety equipment and safety signs

Start :20-Mar-11 15-May-11 20~ . , - - . - ',' ;- .

Design !24-Mar-11 ; . 26-May-11, 40~ •• a C;n~t;ucti~~ ••• ·i24~Au;.;1· a , ••••••• " y 23-Aug:11 » : : ~ • 40· ••

20.51% I 60.00% I 22.50%

Start

Construction

i27-Jan-11

: 20-Jul-11

10-Mar-11

19-Jul-11

20

40

10

30

20

40

40

... Weights of Activities are calculated relative to (Process)

Tuesday, May 17, 2011 Page 2 of 19

Layout NO.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

Milestone i Dates I Milestone III--'p"":-.-nn-e-d""'---A7"c:-t:-U-.:-,---:E:-x-p-e-ct:-e""'d-lI Value I'" Relative I Planned I Actual

Weight Progress% Progress%

Design 17-Feb--11 17~Mar-11 40. . . . . . . . . . . . . . . . . . . .. . .Construction 20-Jul-11 19-Jul-11 40

34.09%

4.27%

2010-Mar-1127-Jan-11Start

Total Process

"" Weights of Activities are calculated relative to (Process)

Tuesday, May 17, 2011 Page 3 of 19

Layout No.1

Dala'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

Dates Milestone I* Relative I Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%

Overall

DesIgn :03-Mar-11 , 20-Apr-11 . ,40," ~ •• - ••••••••• ',' •••••• " ••••••• " •••••••• " ••••••• i

Finish ,'24-Aug-11 23~Aug-11 40~~~~~~~.._-~ ..._....~_......__......__..._..._._........-"-.....~....~-"-.- ......~~~.~~~~~~""'''''''-'--_._~~.~~-~~---------------- --_._._------_._-_.

0.00%

0.00%

60.00%

0.00%

0.00%

60.00%

2.87%

2.87%

2.87%

30

20

20

40

40

3.58% 60.00% 60.00%

20· .... ~ .40

• " " " « ~ ~

40

3.58% 60.00% 60.00%

20"«.« •••

40· - - - - - -

40

38.18%

ZQ-Jul-11

08-Sep-11

31-Mar-11

10-Mar-11

15-Mar-11

21-Jul-11

:27-feb-11

:20-Feb-11

:03-Mar-11

Table

Start

Start 28-Jul-11

Finish 27-Jul-11

Start

Finish

Start

Start

••••••••• « •••••••••• " •••••••

· " " .. . ~ .

Design :24-Feb-11 28-Mar-11• •• Co<n;t:Udi~~ « 4 • '!28~AU;-11' •." « « « « ••••,. 25-Au·9:11"

Start : 03-Apr-11 31-Mar-11

• - - De~i;~«' ~ ~ ~ ~ ·!Oi-Ap~-11· -:- - 07=A~;-1·1·• •• _ ••• ~ _ • ~ •••,' ••• _ •• ~ ••• v • __

• « « ~~n~t~u:ti?~ ••• ':~1.-~e~;~ _ « •• " ••• <

• •• < " • < , •• « •• '," •••••• , • « « •••••••••••• ~

Specification for ins. Of UlG system.

~ ~ ••••••••••• '," < , « ••• < ••••••• ", ••••••••

Specification for field test of U/G system.

Piping Material Classes specification

Tie-In List

•••••••••• - - - - -.' - - - ••• ~ •••••• « .:. - • - •• - - , - - ••• - • ;

4.30% 60.00% 60.00%

Start :20-Feb-11 15--Mar~11 20· . · -,' .. ,

Design :03-Mar-11 20-Mar-11 40. . . - · '," .. .. .. - . ..Construction :03-Aug-11 02-Aug-11 40

4.30% 60.00% 60.00%

Start :27-Feb-11 15-Mar-11 20.. · . . . ,_~~si~~ : 10-Mar-11 20-Mar-11 40.. -,' y y - -« . . ... . .

Construction :10-Aug-11 09--Aug-11 40

Underground composite drawing 5.02% 60.00% 60.00%

* Weights of Activities are calculated relative to (Piping)

Tuesday, May 17, 2011 Page4of19

Layout NO.1

Data'Nes Systems, Release 2.21

Project No.: 4187·440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

MilestoneDates Milestone 'It Relative Planned Actual

Planned Actual Expected Value Weight Progress% Progress%

Start :19-5ep-11 18-Sep-11 20, ••• co'n~t;ucti~n' .•. ·i25~Se~11· • ~ .• - •••••:. 22-S~~11' C 80 .. :.......................~~_4~~_"__~_~'_ "-"_""_ _<..~~ ___"__~__?_~ ~L_~~~_~~~_~_ _"'"--~-'- ~.~ ~__~ ~"_"_.~._.__"_._

Hydrostatic test loops.

60.00%60.00%3.58%

20

40

4.30% 60.00% 60.00%

20...... .40...... .40

4.30% 0.00% 0.00%

3.58% 0.00% 0.00%

20...... .80

3.58% 0.00% 0.00%

20.......80

32.97% 39.13% 39.13%

02-0ct-11 40

details

Start : 05-Apr-11 08-Apr-11• •• De~i;~ •.•• " • 'i 09-Ap~-:;1' • :. '14:A~;-1"1' •..• - " •••· . ~ " ',' " . ~ - .

Construction :06·Sep-.11 03-Sep-11

Start :14-Apr-11 31-Mar-11• • ~ De~i~; •••••• '::;O~Ap;-11' • " • 21:A~:-1-1'

• - • co'n~t;ucti~~ - - . -i 03-0ct~:; 1" • , ••••.••

Underground piping standard details

Standard

Start : 02-0ct-11 29-Sep-11• - • Co'n~t;u~i~n' ••• -i os-octo:; 1" • " .•••••••• 'OS-Oct-; l' .

Special piping support

Standard steel structure list

OverallEngineering

Commodities

3.58% 15.00% 15.00%

15.... .. .30... ...1S.. . . ...10. .. - ...30

7.89% 65.00% 55.00%

19-May-11....... .09-Jun-11

22-Mar-11:17-Mar-11

:04-Aug-11VPR finish

MRO

Piping Bulk

Ppiping Valves

;. ~ , ~~~ .VPR start :26-Jun-11 26-Jun-11

~~~~ -: " : .

1. Evaluation :19-May-11."." -MRp······· ·i09-J·u~-11···-····"·

1S

40

16-May-11 10... "" ..... " ....13-Dec-11 35

MRQ : 04-Jan-11 04-Jan-11= I :" .. --r. E~alu~ti'o~ ••• 'io2~Feb-;1' - ~ • 08~F~b.1·1·~J ~ ... VPR's~art' •• - • -:;7~Feb-;1' • ~ •••••••

mml •... VPR'fi~i;h' •••• '!05-0ct-11" • " •••••••

11.. -!._1_1_.4_7.;.%_,_.I.I_4_9_._38_'_Y'_.l.-4_2_.5_O_%_,_

* Weights of Activities are calculated relative to (Piping)

Tuesday, May 17,2011 Page 5 of 19

Layout No.1

Data'Nes Systems, Release 2_21

Project No.: 4187·440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%

Overall

0.00%

0.00%

80,00%

0.00%

0.00%

100.00%

100.00% 100.00%

3.58%

3.58%

3.58%

0.00%

20

27-Sep-11 20

OS-Oct-11 80

27-Dec-11

, ,--".-"-'--'~'.~""""~~--""~.""""'''---<''-''---''-''''''''''''"------

....... -.' " :

:27-Feb-11

Start 2B.Sep-11.... ".""" .Finish 09-0ct-11

Piping bulk final MTO

Start :03-Mar~11 15-Mar-11 20 ,

L_:~_~ FI~I;h - .. ~_:~~M~'r-11'-~_~_~~~M~i~~_~:~:_: ~~~_: ~~~~_~~~_~ ~~_._._.._._. _

Start

Finish

Piping valves final MTO 0.00% 0.00% 0.00%

Finish 19-Jul-11........, --29-Jun-11

oo

10.75% 66.67% 60.00%

GA~

8.60% 0.00% 0.00%

28-Aug-11»»»««« - -.- ••• _.«»

10-Aug-11.». - - - - -,_ •••••••

19-5ep-.11

9.68% 0.00% 0.00%

28-Aug-11 20•••• »» » .. • • - • » ~

28-Jul-11 0- _ ..... .. • • M • « ......19-5ep-.11 80

18.28% , 0.00% 0.00%

10.75% 0.00% 0.00%

20-Jul-11

: 20-Jul-11Start

Start

Piping GA drawing area

Existing piping GA drawing area

~ ••• « « » » » » • « •• ',' ••••• »

. Design : 28-Jul-11~ • - ••••• - - « « « « -, •••••••

Construction :20-Sep-11

~""---"~'.'»'---'--

I ~. ~ .~e.si~~ •• « • « •• ~~-~u~-~1••~I Construction 20-Sep-11

1lI1d==~~~~~==~~'='='===~::::==;==:=:=~~iii[ti~----------------------------------"'-----"'----"'----ffJii/SO's

€Ij!j-F~;='==;===:='=================:::::::==;:=;=~::::=:::::::===='"ili~i2ill Piping isometrics

~IIBh " ~::;r~cti;~ ----:~:~~:;~{ ~ ~ - -~~~;:f~~ ~ ~ ~ ~ .~~ ..i;;lIIF====~='===~~~~~='=====r~::==F~==;=:===5. 10.75% 0.00% 0.00%1lI1------------------------------J-------J------..I,-------., Weights of Activities are calculated relative to (Piping)

Tuesday, May 17, 2011 Page 6 of 19

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%

Overall

I

b

* Weights of Activities are calculated relative to (Piping)

Tuesday, May 17, 2011 Page 7 of 19

Layout NO.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of: 30-Apr-11

Dates I Milestone I * Relative Planned ActualMilestonePlanned Actual Expected I Value Weight Progress% Progress%

0.00%

60.00%

20.00%

60.00%

60.00%

: 60.00%

7.41%

3.70%

3.70%

3.70%

3.70%

20

20

40

40

20

20

40

40

18-May-11••• z •••

24-May-11

16-Aug-11

15-May-11

18-May-11. .26-Jul-11

16-May-11

. - _. "-19-M~Y~1;'

...... ',' 23-Au"9:11 .

20-Feb-11

:27-Feb-11

:24-Aug-11

i 10-Mar-11

Start

Start

Finish

Start

Start

· .. ~e.si~~ .•••.•. ~4.-~e~~ 1..Finish 27-JuJ-11

. - - .· .. ~e.sj~~ :?3:'~a:-~1..

Finish !03:AU~-~1

Start . _ . __ ..!~7.-~a!-~1..

· __ ~e.si~~ .... __ .!~3:~a!-~1. _

Instrument Index

Design :16-Mar-11.......... - - - -, - . - ....

Loose Instrument data sheets

Instrument Cable Schedule

Sand probes data sheets

Start :24-Mar-11 , 10-Apr-11 20~'-'--'.' .. "-'.""-'-'--"'" " - .. ,

Design :30-Mar-11 . 14-Apr-11 , ,40,, " •••••••• __ • " ", _ " ••••• ~ •••• __ • _, T ••••••• ~ ••••• _ • ,

_J.---,--_,,---,-.?~~~~~~~:~P-11....>.-.~-"-"-'-...~~._~~"---"---,,_,,_~.~,,-.-<-., .__..._ .._. .__. _

* Weights of Activities are calculated relative to (Instrumentation)

Tuesday, May 17, 2011 Page 8 of 19

layout NO.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

Dates Milestone '" Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%

Overall

Junction Box Interconnections

~ ••••• « ••••••• ',' ••••••

Design :23-Mar-11;. .. - ",' .

Construction :23:-AU~-11

Start :17-Mar-11 25-May-11• •• « ••••••••••••

26-May-11

22-Aug-11

20

40

40

4.94% 60.00% 0.00%

23.46% 60.00% 0.00%

Commodities

0.00%

5.19%

20.00%

19.75%

17.28%

40

20

10

40

20

10

30

1B-Jul-11

19-May-11. .26-Jun-11

: 14-Jul-11

cables

VPR s1art

VPR finish.. _. - -' _ " .., .

MRQ : 07-Apr-11...... - . - - - - - " - - - - - ..T. Evaluation :29-May-11............. ',' .

Instrument I Fire &

Instrument Bulk

Total Instrumentation

'" Weights of Activities are calculated relative to (Instrumentation)

Tuesday, May 17, 2011 Page 9 of 19

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

I Dates Milestone * Relative Planned ActualMilestoneI Planned Actual Expected Value Weight Progress% Progress%

Overall

" ••••••••••••• ',"'"«"

0.00%

60.00%

60.00%

60.00%

60.00%

60.00%

60.00%

60.00%

100.00%

22.22%

22.22%

22.22%

33.33%

20

20

20

40

40

40

40

40

40

16-Aug-11

09-Aug-11

28-Apr-11.......

13-Apr-11.......17-Apr-11.... - --

14-Apr-11.... - - - -.- - - - - - --. ~S:A?~-1.1 .

23-Aug-11

20-Mar-11

:13-Mar-11Start

Start

... ~~si~~ ••••... ~0:~a!-!1..Construction 10-Aug-11

. . . l?e.si~~ __ .. __ . ~4:~a!-~ i. _

Construction .•• ~4-Aug-11

Electrical grounding layout

Hazardous area classification layout

Electrical Lighting MRQ

.... I?e.si~~ _ !~7:~a:-!1..Construction :17-Aug-11- - - .....

Start

Finish

20-Mar-11

24-Mar-11..• "" •• ~: ~ ~~-~~Y:1~ .

24-May-11

20

80

33.33% , 100.00% 0.00%

Total Electrical 40.00%

., Weights of Activities are calculated relative to (Electrical)

Tuesday, May 17, 2011 Page 10 of 19

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of :30·Apr·11

Dates IMilestone I I.. Relative I Planned ActualMilestonePlanned Actual Expected 1 Value Weight Progress% Progress%

Overall

Total Pressure Vessels

MRO

T. Evaluation

VPR start

VPR finish

04-Jan-11

02-Feb-11

20-Mar-11

28-Jun-11

04-Jan-11

13-Feb-11

28-Mar-11

21-Jul-11

15

40

10

35

100.00% 65.00% 65.00%

65.00%

65.00%

.. Weights of Activities are calculated relative to (Pressure Vessels)

Tuesday, May 17, 2011 Page 11 of 19

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of :30-Apr-11

Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%

17.11%

10

40

50

10

30

40

50

70

10

5040

02-Jun-11

15·Jun·11

24·May·11

1.85% 50.00% 50.00%

" :O:Ap~-~1 . 10. .......17-Apr-11 40.......

50

1.85% 50.00% 50.00%

. ~O:Ap~-~1» .' .... « " ••

17-Apr~11.« ••••••.•••••. «

· ~0:Ap~.~1.

· :7:Ap~.~1.

• ~3:A'p~-1.1.

14-Apr-11

:17-Mar-11Construction

• « • ~t~rt• ••.••.•. 9~-~p~-!1••

... 9,:Si~~ ... « ••• !~-~P~-!1••Finish 13-May-11

Shim and grouting Specification

Concrete Specification

Start !20-Feb-11. --De~i;~ '!24~Feb-l1- •............. ',' .

Overall

Engineering

Start : 06-Apr-11...... - ",'" "" ...Design : 18-Apr-11

- •••• » •••••• - " - - - • - • »

Fi~is_h _ •• _ ••••:~3-May-11 . :~-~aY-11

hqyF='::'=~~=c=~~==~===!==~====:=:::o:;===c:::~==::~=

.

..r.~.,.; structural st••1fabrication Sp.cification 1.85% 50.00% 50.00%

-;:;\ Start : 06-Apr-11 , 1D-Apr-11 10_.» •• »» •• _. - - -,- - _. - -» •••••••• -.- - _. - - - - -';III Design : 18-Apr-11 ! 17-Apr-11: 40II .. -Fi~is-h - .... _. >j3~Ma~'11' - -' - T' •• _.- ;8-M~Y~1;' . - - 50 -';gl="S=ite::=p"r."p"'a"'ra=t:Oio"n"',"'e=a=rt:Oh"W"O"'rk:;=;&""ba"'ckfi"":~IiI"S"P"""'C:Cifi"'lc"a'"ti"'on""'=:=:====:=:""====::=±o=======1"."8"5'''~===;5::0:=.0:=0:=%;;=="5::0:=.0:'0"'::~=1mi-..,~.:.~.~.J. 1°" ~ ••• ~t~rt_ _ • _ » _ • » • ~O:A?~-1.1_ • _ •• , __ • " .•••. ~ ~

§it « « ~ £?~si~~ • • • • • • ~7:Ap~-1.1 . .... ~ .. « « « " « •• ~o•• _

11=""==:"",F=;n";~'h==:=:====:.=:=."",,,,,,,,,,~,,,,,,,,,,::=,,,,,,,,,,=,,,,8=.,,M,,a,,,Y'=',,,,,,,,,,,,,,,,,,,,,,,,5,,0=='========7':0=:':='==:=:::=:'=:==0=::=:'",,="linE Concrete paving Specification 1.85% 50.00% 50.00%:s2&""lW

,[g~~..~.c.•: 10___ ~. ~,~t~rt••••••••• :?6"-~P~-!1•• ~. ~O:Ap~-1.1••:.. YTY«.«,. ••••••• ;~:g Design : 18-Apr-11 , 17-Apr-11 , 40

r.i.F.-~,=±' "·"·",·~F=·;"~",i;,,h=:~:~.·~~:.,,·.=·,,,,,:,,·~j 1",3~:M,,'a~~~'-~"='"'='=='"'~',,,,,' "'",'",,,'".~.'='8-",'=M",a~'y=:,=;",'~'"',,,'=' "5",0'",,,',,'±=========:=::'::===='0=:0:7===':':':C:==::::::t -- ~ ...............-"---'-~-"-----"-"-"-..;,-"- ........_,~_.......:.._."- ----~-II Soil & foundation investigation Specification 2.78% 50.00% 50.00%

II

r.:.t.,:.··~...;" : : : ~::~~~ : : : : : : : ~~:~:;:;:: :£::: Finish. :~3-May-11 18--May-11

1l=='=Ex==:is"'t=in=g"p=/~RO=V"''''ri~fi''ca''ti~'o=n-2r''''p'''o'''rt±=±====:=:'''''-2==±::=="""""=====±=======~2~3~.~15~'~l\===~0~.0~0~%C===0:'.=0~0~%,:=,=

;1 ~::'h- ·:~~1~;~;; .f~1 35.19% I 17.11%11l------------------....-------------..I.----...l----..I.----!;D~r.~..s~~~~~:~:~:~1g=.=n".=ra"l=n=ot:='='========================="3:=.7='0"%;;===;1=00='.:::0"0':=~==::60='.:::0=0'?~=IZi§i!l1§jaej@ill.'i_I

* Weights of Activities are calculated relative to (Civil)

Tuesday, May 17, 2011 Page 12 of 19

Layout NO.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440SETH ONSHORE PROJECT

Issuance Status ReportAs Of :30-Apr-11

Dates Milestone I * Relative I Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%

Drawings

Anchor bolts standard details 2.76%

standard details

60.00%100.00%2.78%

2.78%

50

10

40

50

10

4024-May-11

24-MaY-11

03-Apr-11...... .« ~4:A?~-~1 •

03-Apr-11 ,.... - - - ., .14-Apr-11....... '," .

:17-Mar-11

Construction

Construction

Start :20-Feb-11••••••••••• « •• , •••••••

Design :24-Feb-11• • • • • • • • • • • • • ',' ••••• «

Start ;20-Feb-11". - _ -' ., .Design :24-Feb-11

••••••••••• " •• , - « •••••

Start :20-Feb-11

~ ~ ~ ~e:Si~~ : : : : : : :!~4:~e~-~1~ ~Construction :17-Mar-11

Misc. Steel supports foundation plan & details 8.33% 60.00% 0.00%

0.00%

0.00%0.00%

9.26%

11.11%

10

50

40

05-Jun-11: 19-Jan-11

Valves foundation plan & details

Start :12-MaY-11 19-May-11, 10 ,~'"'_ ••••• "*'*:_""'H~""'.' •••••• • ••••.

91 ~ ~e.si9~ ••••.• •:~o:~ay-}~ ", ;. ~:-~~Y:1~ ~ : ~ ~ • :0.••.;1_-... Con:tr~~~~ ..".,"-,,-1~~~~~,,~.->--"-'C-,-~~:~~~-, __~~~4~~~: __~ .__. ~ ._

§ New slug catcher foundation plan & details 12.96% : 60.00%ii!E

4QWf

1m Starttil .--De'si~~ ••• ~ • - -i;6-J-a~-11" •• T •• « - -, - 23-M~y~1; •II .« ••••••••••• -i18~Au~-;1·· ••..•• ««. 09-Au9:11 .

·§fjfF==;;;;=====":~=='==="'===~==='=======c===~o=====o====~ steel details 11.11% 60.00%"Wi

I , St~rt ' !"Ap~.~,.. , :~"~~Y:'~ 10 .ill Design ,: 26-Apr-1l , . 26-May-11. 50

1I1==',=='"'"'=c"o,,'n,,;t,,;"=ct=i~=n,,",,',,'='=',,,!2,,'0,,:,,se,,;""",""'"',,'=',,,,,""',,'='=',,,,'"··"·='=9,,·.A,,·U,,·g,,:,=',,,,,·"',,',,'='=4,,'0,,',,'='''''=====r======r=====r=====II 55.56% 56.67% 13.00%1I:... ...l_;.;,~.;,;,_..l....;.:......;;.....l .....,;,;,;.;.;;.,_

=MTO~--I Civil MTO

iliili~ Start :OS-May-11 , 19-May-11 20

~I '_.: ~ ~i~jS~: :: .. :: >o~~ar-}~·'····:::::: ~~-~~y~1;· r··· 80"

;~l:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::~:::9.:2:6:%:::~1::0:.0:0:'/.:'::~::0:.0:0:'/.:.::* Weights of Activities are calculated relative to (Civil)

Tuesday, May 17, 2011 Page 13 of 19

Layout No.1

Dala'Nes Systems, Release 2.21

Project No.: 4187·440

SETH ONSHORE PROJECTIssuance Status Report

As Of :30-Apr-11

Dates Milestone , * Relative I Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%

Overall

• Weights of Activities are calculated relative to (Civil)

Tuesday, May 17, 2011 Page 14 of 19

Layout NO.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

Dates I Milestone I* Relative Planned I ActualMilestonePlanned Actual Expected t Value Weight Progress% Progress%

OverallProcurement

RFQ 11-Apr-11.....................Rec.Bids OZ·May-11

•••••••••••••••••• « ••III

Fire detection

C. Evaluation

F.OA

Piping Bulk

13-Jun-11

20-Jun-11

9.52% 10.00% 40.00%

24-Feb-11 10. - - -23-Mar-11 30

. - "fi fi •

10-Jul-11- - - - - - -

17-Jul-11

9.52% 40.00% 40.00%

RFQ 24-Mar-11 10

0.00%

40.00% 40.00%

10.00% 0.00%

40.00%

100.00% 100.00%9.52%

9.52%

9.52%

16.67%

11.90%

30

30

30

10

30

30

30

10

30

30

30

10

02-Jun-11

09-Jun-11

02-Jun-11

30

10_ " -:

, ,.... - - - -,- - - - _ ... ,'

03-Jan-11

20-Jan-11

10-Mar-11

15-Mar-11

05-Jan-11

18-Jan-11

02-Jun-11 30

28-May·11 30..... _. .. - - . . .. _ .... - .04-Jun-11 30

- .... - " , - - ... ~ .11-Apr-11 18-Apr-11... - .. - " ..... ~ -

17-Feb-11

OS-Feb-11

22-Dec-10

19-Jun-11

:22-Dec-10

:OS-Feb-11

:28-Mar-11

F.GA

C. Evaluation

Rec.Bids

C. Evaluation

F.OA

RFQ

Rec.Bids

F.OA

Rec.Bids

RFQ

Catcher

RFQ

· - . - - - " - - -

• •• » " , " •• " • " " -, •••• - •• ~ " •••• " "

RFQ 11-Apr-11 02-Jun-11 10• •• - • - - - •••• ~ •••• - • - - - •• " •• , •• < - - - -

Rec.Bids 29-May-11 30· - ... , .. - - - - ~ " ... " ~ - ..... ".. . ... - - -c. Evaluation 12-Jun~11 10-Jul-11 30

RFQ !04-Apr-11 24-Feb-11· .. - " . - ... , " , ., - ... " .. ~ - . - . " " .Rec.Bids : 07-Apr-11 28-Mar-11........... ". ",." "C Evaluation :17-May-11, 10-Jun-11

· ~ ~ F.O.A." .... 4 ••!;5-J·u~-11· • ~ • " ••••••,' ·15-ju~-;1 •

· . ~ .. - . - - - ... " .... - ...- - - - - - ..

· - " ~ ... - . ~ .. - " - - - - ~ . ~

Rec.Bids : 18-Apr-11- .. - ... " - - .. - -, .... - . -C. Evaluation :OS-May-11

~ - .. - - . ',' .. " - - -· . "~''?~ __ . __:~2~~ar-}: .

Instrument I Fire & gas cables

Fire protection system

., Weights of Activities are calculated relative to (Purchasing)

Tuesday, May 17, 2011 Page 15 of 19

layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

MilestoneDates Milestone ,., Relative Planned Actual

Planned Actual Expected Value Weight Progress% Progress%

Overall

0.00%

38.57%

10.00%

11.90%

11.90%

10

30

30

24-Jul-11

17-Jul-11

19-Jul-11

25-MaYc11« • « « « .« - - - « « « • «

07-Jun-11

19-Jun-11

12-Jun-11C. Evaluation

F.G.A.

RFQ 11-Apr-11 26--Jun-11 10« ••••• « •• ««.« •• « ••••••••• ««« «««««. _ ••• ««« ••

Rec.Bids 01-MaY-11 05-Jun-11 30« « ••••• _ ••••••• « ••• " « •• « •• « A A ••• « « « «

Instrument Bulk

Instrument I Fire & gas Cable Trays

Total Purchasing

RFQ : 13-Apr-11" « « •• « « - « « •• « « ".' ••• - - -I Rec.Bids :03-May-11

~~I «-« - C.·E~u~t;o~ - « - "i 14-jU~-11- -

ill=",'=·=·=·~,:~.o"·."A,,.·=·=·=·=·=·==·.:·i";='~,;,J·U,,;=-;~,'==',='"'='=-='='=='='='2=6='J=~='-=;'='=-,,,='='='=3=0='='='~====r=======T=======;=======II ... --.. -- ... ... 100.00% 42.86% 38.57%

"Weights ofActivities are calculated relative to (Purchasing)

Tuesday, May 17, 2011 Page 16 of 19

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of :30-Apr-11

Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%

30

20

10

12-Feb-12

24-Dec~11 20

17-Jul-l1

09-Jun-l1 10

26-Jun-11 10. .04-Aug-11 20

16-Nov-l1 20

26-Dec-11 30

18-Jul-!1

03-Jan-12 20

12-feb-12 30

17-Mar-l1 10

2a-Mar-It 10.21-Jul-l1 20

.14-0ct-l1 20

23-Dec-l1 30

16-Jan-12

16-Jan-12

Start

VPR finish

VPR start

Fab. Start

SID.Award

Fab. Finish

S/D.Award

VPR start

VPR finish

.... - .. ~ ' .Fab. Finish

....... , -16-Jan-12

17·Jul-l1 10

17-Jul-l1 10

28-Jul-1! 20

03-Jan-12 20

12-Feb-12 30

." Weights of Activities are calculated relative to (Expediting)

Tuesday, May 17, 2011 Page 17 of 19

Layout NO.1

Dala'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of : 30-Apr-11

Dates IMilestone I * Relative I Planned ActualMilestonePlanned Actual Expected! Value Weight Progress% Progress%

Overall

Procurement

0.00%

0.00%

7.35%

7.35%

0.00%

0.00%

1 10.44%

10.29%

10.29%

10.29%

100.00%

10

10

10

10

10

30

05-Jun-11

05-Jun-11

05-Jun-11

01-Nov-11

• ••••••• " ••••• « • ,

18-MaY-11, 10 ,

· 22-Ju~-·11· "- .. 20' - . ;

22-Sep-11: 20 ,• •• " " •• - ,. ••••••• i

· ~ .· ~ :

· _ ,.""."."

18-Apr-11.......

24-Apr-11.......

........: ~ :01-Nov-11 20'

:06-Mar-11

:17-Feb-11

:09-0c1-11

Fab. Start

VPR start

VPR finish

•••••••• x» •• _ •••••••••

Start :17-Feb-11~ ••••••••••••• ",' ••••• 4

....... - - , - - ~ . ',' .. - ...

Electrical bulk material

Start :12-May-11,. - .. ',' .

Fab. Start :12-May-11••••• ». _." -, ..•,.••.•• ",~ •• ~~R"s!a~ y k )~2:~ay-.1~.

S/O.Award :30-Aug-11

~ •• « Fab"Finish • - • " ": 09-0ct-11- -....... " " .. " .. ',' .

Total Expediting

VPR finish "14-Apr-11 ,"-. -SjO.A~rd .. - . '!06~AU~-11- • ~ ..... _. . "14-0d-11- ~ ... 20' . ,

I~~~~~a~!~n~~~~~i~-~i~~~~_~~~_~~~~ ~_~_;;1~:_~~~_L_~ _

* Weights of Activities are calculated relative to (Expediting)

Tuesday, May 17, 2011 Page 18 of 19

layout NO.1

Data'Nes Systems, Release 2_21

Project No.: 4187-440

SETH ONSHORE PROJECTIssuance Status Report

As Of :30-Apr-11

Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%

OverallProcurement

Fire detection system 8.33% 0.00% 0.00%

NFl OS-Feb-12 40« ••••••••• « •• . ....... •• « v««.RFS 12-Feb-12 60

Bulk 8.33% 0.00% 0.00%

NFl !19-Dec-11 , 19-Dec-11, 40

.. « .... RFS' « • « ~ ~~J.~~~~~_~~_~:~~~_~_:_~_~2i~~:~~~_~_~.~~?~~: ._" _

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

16.67%

12.50%

12.50%

NFl

NFl

RFS

NFl_ •• ««. _ v.«« __

RFS

Slug Catcher

Instrument I Fire & gas cables

Fire protection system

0.00%

40

60

25-0cl-11 40

16-Dec-11

01-Nov-11 60

21-Nov-11

: 08-0ct-11NFl

Total Inspection

!!11=;;;::;~RF~Sc====d~~~=====~~~±=~====~==;;o:~==;=~===;;o:===;~ Piping valves 8.33% 0.00% 0.00%1'=!6W

III~til ~ .. -RFS' -- T - -« - -j15-o~-;1" ~ ... «« •• -:- 23-6~c~1; - ~«- - 60' -«:PiF~~'''-~,,-=,·-=-=·,,-:==·::;.-=~=-'''--,,~'C--,,·-'''=-=·=·-=-'-=--'~~"-=.-=.,-=,.= .•=-.=.-=",-='=,'".=.•,,-..-,,..-=.-='=.=-..~=-="".-='-=."-=.=..,"-="-=.--=--=-,,-.,,--=.-=--=-'~-.~~=-~-==-~"'~~--~--~-,,-'=-'::c_:=-~-c;-=-=c-~--,,-~--=-~-=-~--=c=",,-:=="""" Electrical bulk material 8.33% 0.00% 0.00%•==illtH NFl : 02-0ct-11 ,II "" ¥ RFS···· ~. a - ·'09-0ct-11"·'·· y v •••

IFC±I"n"st:=ru=m~e"n:=t;:;B=U;;.lk====~~~~<±====""======'====='=======':1"2".5"0:::%""==0"."0"0:::%""==:00".0"0:::.."',=I,-II ~ ... ~~I .••• _ • * _ .: ~O.-?~-~1_ • " ...• ~ •• • .1~-~~V-.1~. • •• ~Oy •.

iii RFS : 17-0ct·11

¥,§Fo\:'='===:7:==:=;;'7==!:::~~=~=========='====='=====;==';;;:;;;:::f===;::;;;:::f==::'::::::""=;§Ii Instrument I Fire & gas Cable Trays 12.50% 0.00% 0.00%

n$WiII ~ . " . ~~I ........•: ~2..C?C:-~1. . ~ ... y ••• _: ••1~-~~V~1~ _ .'. ~o.. _

IIF=,==R=F=s==-=.=-=-=-=-=.,=:~~9.=-O=.ct=:='='.=-<±'=.=_=.=.=.=.=.=.=.=2=3-=N=~=V'=.'='=.====6=0=""'=====;=1~O~O~.O~O~,~y,,==r=O~.O~O~'''y,,==;=O~.~O~O~'I.~,=

* Weights ofActivities are calculated relative to (Inspection)

Tuesday, May 17, 2011 Page 190f19

layout No.1

Data'Nes Systems, Release 2.21

PTB

Egypt

•E:n.PP1SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

7.3. Updated Schedule

4187-440

Rev. (0

18-MAY-2011

4187.440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30·Apr-11Enppl

Slug Catcher Data Sheets

Evaluation (Slug Catcher)

VPR (Slug Catcher)

30

70 20-Mar-11

04-Jan-11

02-Feb-11

28-Jun-11

Page 1 of10

... Actual Work

1_00:';'/";;>:1 Remaining Work

I!iBIIIIIIIl Critical Remaining Work:

• • Milestone

Summary Start Date: 22..Dec-10Finish Date : 26·Feb~12Data Date: 30·Ap....11

Print Date: 16-May-11

Date18-May-11 Rav.O

By: Haytham A.Rahman

Revision CheckedA.Fathy

ApprovedM. Abushanab

'~~-"'-'---

Page 2 of 104187-440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

HSE philosophy IFD 18 06 M Mar-11 03-Apr-11 A

cause and effect 5 20-Feb-11 31-MarM 11 A 02M MayM 11

Fire 5 03-Apr-11 09-May-11

cause and effect IFC 5 21-Jul-11 27R JulM 11

Com missioning 20M Nov-11 28M JulM 11 03-Aug-11

-Aug-11 10-Aug-11

Hazardous Area Classification IFF 17-Aug-11 11-Aug-11 17-Aug-11

Enppl

mohamed
Line
mohamed
Line
mohamed
Line
mohamed
Line

Page 3 of 10

01-Aug-11

15-May-1128-Mar-11 A

18-Feb-11 A 24-Feb-11 A24-Mar-11

10-May-11Technical

4187.440, PETROBELSETH ONSHORE DEVELOPMENT PRO~ECTUPDATED SCHEDULE AS OF 30-Apr-11

Fighting System MRQ

Fire Fighting System VPRA1590

A1990

DETECTION AND GAS SYSTEM

10 06 M Mar·11 10M Mar-11

5

A2200 0 20-Mar-11 24-Mar-11 02-May-11 02-May-11

A2240 5 27-Mar-11 31-Mar-11 02-May-11 08-May-11

A2260 Junction Box Interconnecting Wiring Diagram IFD 5 03-Apr-11 07-Apr-11 09-May-11 15-May-11

A1560 P&ID's IFC 20-Jul-11 07-Jul-11 20-Jul-11

A2230 And Alarm Layout DraVllings IFe 10-Aug-11 04-Aug-11

A1570 Fire Fighting Drawings IFe 11-Aug-11

24-Aug-11 18-Aug-1.1 24-Aug-11

A2250 5 25-Aug-11

A2270 5 05-Sep-11 11-Sep-11 11-Sep-11

Enppl

Enppl4187-440, PETROBEL

SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

5

Page 4 of 10

A3180

20 23-Mar-11 A

03-Aug-ll

A3200

A1630

A3290

Under Ground Piping Standard Details IFD

Under Ground Composite Drawing IFe (Header)

l4-Apr-1l

03-Aug-11

6 ll-Aug-ll 04-Aug-ll

25 04-Aug-l ep-ll 04-Aug-ll

5 05-Sep-ll ll-Sep-ll 05-Sep-ll

ll-Sep-ll

24-Feb-ll

A2330 piping specification IFD 03-Mar-11

A3220 Under Ground Specification

Page 5 of 10

16-May-1130-Mar-11

16-Mar-11

,J'7~"~;:,:i-------- i2;;3':_'Mi~a;r:_;1-11 --I n09Q'-'M,ia~;Y;:-:'1 11 -I-,;;:"i~;;:;

IFe

4187-440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

Cable Routing IFD

Line Designation Tables JFC

Standard Steel Structure Support List IFC

piping specification dasses IFe

Loop Diagrams

A2360

A2340

A2380

A3230

A3260

A3250

A2450

A2400

Enppl

Enpp l 4187.440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30.Apr-11

Page 6 of 10

A2410

A2440

A2460

Instrument Hook Up And Supporting DrawingsIFD

Aug-11

11-Aug-11

17-Aug-11

24-Aug-11

17-Aug-11

23-Aug-11

--CO"~,:: ------- 'Instrument Index IFD

A2490

A2510

A1970

A2500

Instrument Cable Schedule IFD

Instrument Index [Fe

Drawings

".".. ~.,~,~-~~"~"0 20 R Feb M 11 24~FebM11 02w MaYM 11

5 27-Feb-11 03R MarM 11 02-May-11 08-May-11

5 17~Mar~11 23-Mar~11 09-May-11 15-MaY-11

5 21-Jul-11 27-Jul-11 21-Jul-11

03-Aug-11 03-Aug-11

18-Aug-11

Enppl4187-440, PETROBEL

SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11Page 7 of 10

A2850 Instrument Cable Trays MRQ's

Instrument Cable Trays VPR

AZ860

AZ870

Instrument Trays Evaluation

16-May-1 31-0CI-11

30R Mar-11 16-May 16-May-11

31-May-11 9-Jun-11 06-Ju~11

8-Aug-11 31-0cl-11

A2570 HazardousArea Classification Layout IFD 0 20-Mar-11 28-Apr-l1 A

0 06-Mar-11 10-Mar-11 02-May-11

5 20·Mar-11 24-Mar-11 02-May-11 08-May-11

5 04-Aug-11 10-Aug-11 04-Aug-11 10-Aug-11

w··,'nnnnnmm",_•• ,

IFe 11-Aug-11 11-Aug-11 17-Aug-11

AZ580 Layout [Fe 18-Aug-11 24-Aug-11 18-Aug-11 24-Aug-11

A3310 24-Aug-l1 18-Aug-11

AZ050 30-Apr-11

Page 8 of 10

24-Feb-11 A02-May·1120 1Z·Apr·11

4187-440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Ap....11

support Foundation Drawings

Drawings

Drawings

Bidding

Slug catcher Foundation Drawings IFe

Valves Foundation Drawings JFCAZ6S0

A1790

A2730

A1750

A17S0

AZ670

A1740

Enppl

•.•.... :A;;'l"S:OOOO .. !F~i;;i~,;ti~~lu:Pt:o" 'R"F"S····· ....•........... , ~;~f;,;., ;~:;; ................• ;Z'O"-';D~'e"c'-·'1"1··········· i ··'Z·'Z-'M'·a"'y'- ;1;1 i ;1 'S-;D'e'c'-';1';1 i

Enppl

A1860

A1870

A1880

A3280

4187-440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

Page 9 of 10

4187.440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr·11

II:

Page 10 of 10

03~Nov-11

23-May-11

09-0cl-11

12-May-11

12-May-11

15 19·Apr-11

21

Electrical Bulk Commercial Evaluation Upto POIssuance By PTS

Electrical Bulk Fabrication Upto RFSA1960

A1950

A1940

Enppt

PTB

Egypt

•E:n.PP1SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

7A.Critical and Near CriticalActivities

4187-440

Rev. (0

18-MAY-2011

Commercial Evaluation Upto PO Issuance ByPTS

E.nppl4187-440, PETROBEL

SETH ONSHORE DEVELOPMENT PROJECT CRITICAL ACTIVITIES AS OF 30·Apr-11Page 1 of 2

.... Actual Work

!.;",,+ x,',;, ! Remaining Work

_ Critical Remaining Work

• • Milestone

Summary Start Date: 22·Dec-10Finish Date: 26-Feb-12Data Date: 30-Apr..11

Print Date: 16-May-11

Date

1S·May-11 Rev.O

By: Haytham A.Rahman

Revision Checked

A.Fathy

Approved

M. Abushanab

Enppl4187.440, PETROBEL

SETH ONSHORE DEVELOPMENT PROJECT CRITICAL ACTIVITIES AS OF 30·Apr·11Page 2 of 2

PTB

Egypt

SETII ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

7. S. One Month Look Ahead Report

4187-440

Rev. (0

18-MAY-2011

Project No.: 4187-440

SETH ONSHORE PROJECTLookahead Report

As Of: 30-Apr-11

Forecast Date: 28-May~11

Dates Milestone " Relative Planned ActualMilestone Value Weight Progress% Progress%Planned Expected

Overall

.. - ',' ',' .

Process cause and effect matrix

0.00%

0.00%

0.00%

0.00%

20.00%

20.00%

60.00%

60.00%

60.00%

20.00%

: 60.00%

: 60.00%

4.27%

4.27%

4.27%

4.27%

4.27%

11.11%

40

40

20

19-May-11

18-May-11

12-May-11

07-Apr-11

27-Mar-11

31-Mar-11

Design

Design

Start

Design

1. Evaluation

Fire and gas cause and effect

Fire & gas 110 list

Fire and gas cable routing drawings

Fire and gas cable wiring diagram

Start 08-Apr-11 22-May-11 20

r - - - D';Sig~ - - - - ~ -,' . ;2-AP~-11- -: - 25-M~Y=11- . - . -40 - - -

Fire fighting, safety equipment and safety signs

Start 20-Mar-11 15-May-11 20- - . - _. ." - - . - - - - .Design 24-Mar-11 26-May-11 40

Start 03·Apr-11 16-May-11 20... ~ De~ig~ ..... ',' . Oi-Ap·r.11· -i- "19-M~Y:1; - ... '40' ..

"Weights of Activities are calculated relative to (Process)

Tuesday, May 17, 2011 Page 1 ofS

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTLookahead Report

As Of: 30-Apr-11

Forecast Date: 28-May-11

Dates Milestone * Relative Planned Actual IMilestone Value Weight Progress% Progress%Planned Expected

Overall

Bulk

T. Evaluation

Ppiping Valves

VPR start 27-Feb-11 16-May-11 10

7.89% 65.00% 55.00%

II

II

r

* Weights of Activities are calculated relative to (Piping)

Tuesday, May 17, 2011 Page 2 of 8

layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTLookahead Report

As Of: 30-Apr-11

Forecast Date: 28-May-11

Dates IMilestone * Relative II Planned ActualMilestone

Expected! Value Weight Progress% Progress%Planned

Instrument Cable Schedule 0.00%

0.00%

60.00%

60.00%3.70%

7.41%

3.70%

22-MaY-11 4003-Mar-11

data sheets

Start

Design

Design

Start

Design

Instrument Index

Instrument Hook Up And Supporting Drawings 9.88% 60.00% 0.00%

Start 06-Mar-11 22-May-11 20

~ .. ·6e"Si9~··'· H <, ·10·-M~r-l1· .:. 25~M~Y~11 H'" "40' --

Field Instrument Layouts

Start 06-Mar-11 19-May-11 20

... 6;Si9~···'· .:. '10'-M~r-;1' .:. 26~M~Y~1;···· "40"-

Field Instrument Cable Routing

Star! 10-Mar-11 : 18-May~11

t ••• 6e"sig~ - ... > ":' • ;6·-Ma~r-;1· ·i· 24.M~y~1; •

Junction Box Interconnections

4.94%

3.70%

60.00%

60.00%

0.00%

0.00%

Start 17-Mar·11

Design 23-Mar·11

20

2030·Mar-11 24-May-11. - _ ' ..

l~c~o~m~m~O~d~1~'t~ie~S~====::;======================:=:3:::::===:=:3:::::===::=::='='======II Instrument! Fire & gas cables 19.75% 20.00% 0.00%

ilif@mill MRQ 07-Apr·11 19·May-11

IF=':oln"s"'tru=m"e=n':t"BC'U"lk"'===~"'========"":==:==~==="'='======:=C;=;';;;='='=7~';;;='='=::;==;:';;;='='======;

iiliili M~~~~:~"--:~~~ 24-May-11 x.'-,,-_,-~~~~_.__~,_,_. , ~ ,_. _IF=':oln"sO'tru=m"e"n':t7t"'F;'ir:'e';&C'9ecaC'S=;:cC'a"bC'le"T;:ra=ys==============='=======:="1:;7".2"8"0/<7,=0=';;2"0".0"0"0/<7,=::;==;:0".0"0"%;=::;======:

1illti MRQ'B3E- •••••• _ •

* Weights of Activities are calculated relative to (Instrumentation)

Tuesday, May 17, 2011 Page 3 of 8

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTLookahead Report

As Of: 30~Apr~11

Forecast Date: 28~May~11

Dates Milestone * Relative Planned ActualMilestone Value Weight Progress% Progress%Planned Expected

Overall

Electrical Lighting MRQ

Start

Finish

2Q...Mar~11 2Q...May~11

.. i4-M;r~;1" "i' 24-M~Y:1; .20

80

33.33% 100.00% 0.00%

* Weights of Activities are calculated relative to (Electrical)

Tuesday, May 17, 2011 Page 4 of 8

layout NO.1

Data'Nes Systems, Release 2.21

Project No.: 4187·440

SETH ONSHORE PROJECTLookahead Report

As Of: 30-Apr-11

Forecast Date: 28-May-11

I DatesMilestone I * Relative Planned Actual

Milestone Value Weight Progress% Progress%Planned Expected

50.00%

50.00%

0.00%

50.00%

50.00%

50.00%

60.00%

60.00%

: 50.00%

50.00%

50.00%

50.00%

50.00%

50.00%

50.00%

60.00%

100.00%

100.00%

1.85%

1.85%

1.85%

1.85%

2.78%

1.85%

2.76%

2.78%

8.33%

50

50

40

40

40

18-May-11

18-May-11

24-May-11

24-May-11

13-MaY-11

13-MaY-11

17-Mar-11

17-Mar-11

notes

Finish

Finish

Construction

Finish

Finish

Construction

Construction

Construction

Shim and grouting Specification

Structural steel fabrication Specification

Site preparation, earth work & backfill Specification

Concrete paving Specification

Soil & foundation investigation Specification

Anchor bolts standard details

Paving standard details

Standard connections details

Misc. Steel supports foundation plan & details

Start 20-Mar-11 18-May-11 10- ••• De'sig~ . - ••••.. 24.M~r-;1· r 25-M~Y:1;' .•• ·50' ..

~~~_".....>.--L-"---"-~,,:,,,,--,--~ ~"-""""-"-'- .. .~. . _

Start

Valves foundation plan & details

12-May-11 19-May-11 10~ - - -De·si~~ -' _ •••: •• 2o:.Ma~-;1- - 25-M~Y:1;· .:. - -50-"

11.11% 0.00% 0.00%rf

I* Weights of Activities are calculated relative to (Civil)

Tuesday, May 17, 2011 Page 5 of 8

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTLookahead Report

As Of: 30-Apr-11

Forecast Date: 28-May~11

Dates Milestone I * Relative Planned ActualMilestone

Planned Value Weight Progress% Progress%Expected

Overall

Engineering

Drawings

New slug catcher foundation plan & details 12.96% 60.00% 0.00%

Design 26-Jan-11 23-May-11 50

Misc. Steel supports steel details 11.11% 60.00% 0.00%

Start

Design

Start

Finish

18-Apr-11 18-May-11 10• __ •••• a ••••• _ • •• _ " ••

26-Apr-11 26-May-11 50

05-May-11 19-May-11 20••••• T T _ •••••••• __

1Q..MaY-11 26-May-11 80

;0 Weights of Activities are calculated relative to (Civil)

Tuesday, May 17, 2011 Page 6 of 8

Layout No.1

Data'Nes Systems. Release 2.21

Project No.: 4187·440

SETH ONSHORE PROJECTLookahead Report

As Of : 30~Apr-11

Forecast Date: 28-May-11

Dates Milestone * Relative Planned ActualMilestone Value Weight Progress% Progress%Planned Expected

Electrical bulk material

Instrument I Fire & gas Cable Trays

RFQ 13.Apr-11

9.52%

11.90%

25-May-11 10

40.00%

10.00%

0.00%

0.00%

* Weights ofActivities are calculated relative to (Purchasing)

Tuesday, May 17,2011 Page 7 of 8

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTLookahead Report

As Of: 30-Apr-11

Forecast Date: 28-May-11

Dates Milestone ,., Relative Planned ActualMilestone

Planned Value Weight Progress% Progress'%Expected

OverallProcurement

Commodities

Valves

VPR start 06-Mar-11 10

10.29% 50.00%

• Weights of Activities are calculated relative to (Expediting)

Tuesday, May 17, 2011 Page 8 of8

Layout NO.1

Data'Nes Systems, Release 2.21

PTB

Egypt

•Enpp.J.SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

7.6.Procurement Status.

4187-440

Rev. (0

18-MAY-2011

As of: 18 Mav 2011

PROCUREMENT DIVISIONFOREIGN PURCHASING SECTIONPTB, SETH OFFSHORE DEVELOPMENT PROJECTPROJECT NO.: 4187-440

No. of Bid due date No. ofRevised

Serial Technical Technical commercialCommodity invited and its bidders F.O.ADATE

no.bidders extensions quoted

opening date report date bid duedate

AWARDED TO1 SLUG CATCHER I lOll 112010 1 1111112010 14/02/2011 21102/2011 PTJ

IN 17/03/2011

LCM

2 MANUAL VALVES 8 20112/2010 8 21/12/2010 10/2/2011 17/021201105B Awarded toLVF05C Awarded to

3FIRE & GAS

1 6/3/2011 1 23/03/2011DETECTION

6/3/2011

FIRE FIGHTINGEXT TILL

4 9 14/03/2011 5 28/03/2011SYSTEM

EXT TILL24/03/2011

5/4/20115 PIPING BULK 13 EXT TILL 12 17/04/2011

12/04/2011

PTB, SETH ONSHORE DEVELOPMENT PROJECTProject no.: 4187-440R.F.Q 4187-440Commodity: SLUG CATCHER SETH - 03R.F.Q issuance date: 02/11/2010

TechnicalTechnical

TechnicalRevised

Serial Supplier name Country Bid due dateBidder Technical clarification

clarificationclarification Technical

commercial bid Remarksresponse opening date issuance

due dateactual reply report date

due datedate date

AWARDED IN

I PTJ EGYPT 11/10/20106/1/2011 16/01/2011 16/01/2011

14/02/2011 21102/201117/03/2011 WITH

26/01/2011 01/02/2011 06/02/2011 DELIVERY 9.5 - 11MONTHS F.O.T

PTB, SETH ONSHORE DEVELOPMENT PROJECTProject no.: 4187-440R.F.Q no. 4187-440-SETH - 05Commodity: MANUAL VALVESR.F.Q issuance date: 01112/2010

Bidder TechnicalTechnical Technical Technical

Technical reportRevised

Serial Supplier name Country Bid due date clarification clarification due clarification commercial Remarksresponse opening date

issuance date date actual reply datedate

bid due date

1THARWA

EGYPT Q 9/1/2011 12/1/2011 FOROSABREDA AWARDED TO

13/01/2011 16101/2011 23/01/2011LCMIN

2 TLPR ITALY Q26101/2011 29/01/2011 06102/2011

20104/2011 WITHDELIVERY 18-

3 TRP-PERAR ITALY Q 9/112011 12/1/201 I 23/01/201126wksEXW

FOROSBAWARDED TO

4 DAFRAM ITALY Q 13/01/2011 16101/2011 19/01/2011 LVFIN

1211/2011 1610112011 26101/2011 20/04/2011 WITH5 LVF ITALY 20/12/2010 Q 21/12/2010 26101/2011 29/0112011 07/02/2011 10/212011 17/02/2011 DELIVERY 24-

26wks FOB6 DRV U.S.A Q 1211/2011 16101/2011 FOROSC

AWARDED TO

LCM ITALY Q11/1/2011 15/0112011 16101/2011 QUALIVALIN7

20101/2011 23/0112011 23/01/2011 20/04/2011 WITHDELIVERY 24-

26 EX-

8 QUALIVAL EGYPT Q 6/1/2011 101112011 101112011 FACTORY IN10th of Ramadan

city, Egypt

PTB, SETH ONSHORE DEVELOPMENT PROJECTProject No.: 4187-440SPEC NO.: 00192700 - BMSF - 13205Commodity: SETH - 21 /PIPING BULK MATERIALSR F Q Issuance Date' 22/03/2011

TechnicalTechnical Technical Technical

TechnicalRevised

Serial Supplier name Country Bid due date Bidder responseopening date

clarification clarification due clarificationreport date

commercial Remarksissuance date date actual reply date opening date

1AR

ITALY Quoted 2/5/2011 5/5/2011 3/5/2011TECHNOLOGY

2 HPF UK Quoted 2/5/2011 5/5/2011 10/5/2011

3 FAD ITALY Quoted 2/5/2011 5/5/2011 10/5/2011

4 DYLAN Quoted2/5/2011 5/5/2011 3/5/2011

NL8/5/2011 9/5/2011 9/5/2011

5 CHEROP1PING ITALY Quoted 2/5/2011 5/5/2011 4/5/2011

6 IPS ITALY Quoted 2/5/2011 5/5/2011 8/5/201105/04/2011

7 IGAMM ITALYEXT TILL

Quoted 2/5/2011 5/5/2011 4/5/201112/04/2011 17/04/2011EXT. TILL

Quoted8 TLPR ITALY 14/04/2011 2/5/2011 5/5/2011 5/5/2011

9 EJSW EGYPT Quoted 2/5/2011 5/512011 8/5/2011

10 TUXOR ITALY Regret

11 MINTA EGYPT Quoted 2/5/2011 5/5/2011 9/5/2011

12 FERRARI ITALY Quoted 2/5/2011 5/5/2011 5/5/2011

13 STEEL TRADE ITALY Quoted 2/5/2011 5/5/2011 4/5/2011

PTB, SETH ONSHORE DEVELOPMENT PROJECTProject No.: 4187·440SPEC NO.: 00192700·BISF·24204Commodity: FIRE & GAS DETECTION / SETH· 27R.F.Q Issuance Date: 24/0212011

Bidder TechnicalTechnical Technical Technical

TechnicalRevised

Serial Supplier name Country Bid due date clarification clarification due clarification commercial Remarksresponse opening date

issuance date date actual reply datereport date

opening date

1 FORESENG ITALY 06/03/2011 Q 23/03/20113/4/2011 6/4/2011

11/4/2011ll/5/2011 12/5/2011

PTB, SETH ONSHORE DEVELOPMENT PROJECTProject No.: 4187-440

SPEC NO.:00192700-BMSF-13206Commodity: FIRE FIGHTING SYSTEM SETH - 28R F Q Issuance Date' 24/02/2011..

TechnicalTechnical Technical Technical

TechnicalRevised

Serial Supplier name Country Bid dne date Bidder responseopening date

clarification clarification due clarificationreport date

commercial Remarksissuance date date actual reply date opening date

1 SAFCO ITALY REGRET

2 DETRONICS UAE REGRET

3 EUSEBI ITALY Q5/4/2011 9/4/20 II

10/4/201110/5/2011 12/5/2011

06/03/20114 FORESENG ITALY EXTENDED REGRET 10/5/2011 12/5/2011

TILL

5GENERAL

U.S.A 14/03/2011 REGRET 28/03/2011MONITORS

EXTENDED

6 SILVANI ITALY TILL Q5/4/2011 9/4/20 II

11/4/201124/03/2011 10/5/2011 12/5/2011

7 SANCO ITALY Q5/4/2011 9/4/2011

10/4/201110/5/2011 10/5/2011

8 MINTA EGYPT Q5/4/2011 9/4/20 II

12/4/201 I10/5/201 I 10/5/2011

9 FAS ITALY Q 5/4/2011 9/4/2011 10/4/2011

PTB

Egypt

•E:n.pp.J.SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

7. 7.Equipment and material status report

4187-440

Rev. (0

18-MAY-2011

I

PROJE.CT COMMITME.NTS STATISTICAL OVERVIEW

STATISTII

COMMITMENTS COUNT:

A.

B.C.

D.

TOTAL NO. OF ISSUED COMMITMENTS:

F.D.C ISSUED.

P.Oo'S ISSUED.

P.Oo'S COMPLETED/RELEASED FOR SHIPMENT

P.Oo'S FOR SERVICES.

P.Oo'S FABRICATION IN PROGRESS.

=

=

4

4

o

oo

4

,Ii

, r, .

- ...

I;

-<

... ---- ..-,

i; I

,,

•1---.- -

• I-' ..,~ I

'"i--'-.

I"

"...~

"

"

" I. . .,

Enpp!~'i~....r,,1bo~Uw..,••;nu

SETH DEVElOPMENT PROJECT RA5!EL.BAR CONCESSION

SlUG CATCHERPAcKAG,

,ETHOSA

MANUAL VALVES

FROM 9.S MONTH TO11 MONTHS

lB-26WEEKS ,PLUS ONt l~-~6 WEEKS,PLUS ONEEX·WORKS/ITAlV WEEK FO~ AUGUST WEEHORAUGUST

SHUTDOWN SHUTDOWN

'"

REPORT NO. 1

AS Of 28/4/2011

FDA WAS ISSUEOTO PTJ ON 17/3 fOR THE SUPPLY OF ONE SLUGCATCHER PACKAGES, COMPLETE WITllTHE INST~UMENTS, VALVES,INTERCONNECTING PiPiNG SKID AND lOCAL CONTROL PANEl.KOM WAS CONDUCTED ON 4/4/l0U.PTJ suaCONTRACTED I.M.S.• Indu,lric MCe<'ni'he ON ~3/3 S'''doliatoS.p,A.FORTHE OESIGN,SUPPLYOF lOOSE MATERIALS AND MECHANICALGARANTEE FOR THE SLUG CATCHER WITH INTE~PIPING SKID AND LDOSEINSTRUEMENTS AND VALVES ON SSHIPMENTS fROM 21/7 fOR FLANGES,PI PIES AND flnlNGS TILL 20/2/1.012 fOR All VALVES AND CONTROLPANEl.,ENGINEERING DOCUMENTS STARETDTD B, RECEIVED FROM 29/3 ANQ20/4 FoRTHE; VESSElCAlCUAtTlON, PFo, QUAtlT'I PLAN. VDeF.OATASHEET.PROCUREMENT SU~ORDERING IS SCH,OUlEO FROM l/4 Tlll29/4IWAITING FO~ CONFIRMIITIONIFAe~leATION IS EXPECTED fROM 14/9 Fo~ NOULE wonKS TILL1/l/l0U.

FoA WAS ISlum TO SUPPLIER ON 1.0/4/2011 FOR lllTEMS OF MANUALVALVES ITOTAllB VALVE).DRAWINGS APPROVAL IS 10 DAYSE·MAIL WAS SENT TO SUPPlIfR ON ~8/4 TO SUBMIT THEACKNOWLEDGMENT AND ,NGINEE;RING DOCUMENTS AND ORDERSCHEDULE

20-4-2011I

LVF/ITALV

fDA WA5ISSUED TOSUPPUER ON :!OI~/2011 FOR U ITEMS OF MANUALVALVES ITOTAL 36 VAlVEI.

SETH 058 FOB ITALY24·l6 WEEKS FROM 24-l6 WEI'K5 FROM

" "'" '" ,-MAil WAS SENT TO SUPPlIER ON 28/4 TO SUBMIT THEMANUAL VALVES

ACKNOWLEDGMENT AND ENGINEERING DOCUMENTS AND ORDERSCHeDULE

20·4-2011 QUAUVAl/,GYPT

FOA WAS ISSUED TOSU~PtlER ON 20/4/Z011 FORS ITEMS OF MANUALVAlVES{TOTAL ,VALVE)

sF;THOSCE~·WORKS jlOTH Of 24·1.6 WEEKS fROM 24·26 WEEKS fROM

" " "RAMADAN £(;YPT '" '" E'MAll WAS SENTlO SUPPLIER ON 28/4 TO SUBMITrHEMANUAL VAlVES

ACKNOWLEDGMENT AND ENGINEERING DOCUMENTS AND ORD,RSCHEDULE.

PTB

Egypt

•EnppaSETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT No.2

7. 8.Alert report

4187-440

Rev. (0

18-MAY-2011

IrI

r

Project No.: 4187-440

SETH ONSHORE PROJECTAlert I Delay Report

As Of : 30-Apr-11

Dates IMilestone J * Relative I i Planned. 1 Actual WeightedMilestone

Expected! Value Weight Progress% Progress% DelayPlanned

Anchor bolts standard details

24-May-11 40-"--...--........--'---"-~-"---"---"---"-------------_._----_._-------------_._----

1.48%

1.11%

60.00%

60.00%

100.00%

100.00%2.78%

40

3.70%

24-May-1117-Mar-11Construction

Construction

Structural general notes

Paving standard details 2.78% 100.00% 60.00% 1.11%

Standard connections details 2.78% 100.00% 60.00% 1.11%

Start 20-Mar-11 19..May-11 10.. ~ . - . . . . . .. . ~. . .Design 24-Mar-11 25-May-11 50

New slug catcher foundation plan & details 7.78%

5.00%

0.00%

0.00%

0.00% : 6.67%

60.00%

60.00%

60.00%

8.33%

12.96%

11.11%

10OS-Jun-11

17-Mar-11Construction

Start

Misc. steel supports foundation plan & details

Misc. steel supports steel details

Start 18~Apr-11 18-May-11 10- - - - - ••••••••••••••• - • < ••••••••• " " ••••

Design 26-Apr-11 26-May-11 50

* Weights of Activities are calculated relative to (Civil)

Tuesday, May 17, 2011 Page 5 of7

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTAlert I Delay Report

As Of : 30-Apr-11

I Dates IMilestone I * Relative Planned I J Actual WeightedMilestone

Planned Expected I Value Weight Progress% Progress% Delay

RFQ 28-Mar-11 OZ-Jun-11 10" - .......... - - - - - . - . ~ ~ ..... - - - - - ......

Ree.Bids 18-Apr-11 02-Jun-11 30

Instrument Bulk 11.90% 10.00% 0.00% 1.19%

RFQ 11-Apr-11 26-Jun-11 10

Instrument I Fire & gas Cable Trays 11.90% 10.00% 0.00% 1.19%

RFQ 13-Apr-11 25-May-11 10..

Instrument I Fire & gas cables

RFQ

Electrical bulk material

11-Apr-11 02-Jun-11 10

9.52%

9.52%

10.00%

40.00%

0.00%

0.00%

0.95%

3.81%

• Weights of Activities are calculated relative to (Purchasing)

Tuesday, May 17, 2011 Page6of7

layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTAlert I Delay Report

As Of : 30·Apr·11

Dates Milestone * Relative IPlanned Actual WeightedMilestone Value Weight Progress% Progress% DelayPlanned Expected

OverallProcurement

VPR start

VPR finish

06-Mar-11

14-Apr-11

18-May-11

22-Jun-11

10

20

10.29% 50.00% 20.00% 3.09%

!

I

.. Weights of Activities are calculated relative to (Expediting)

Tuesday, May 17, 2011 Page 7 of 7

Layout No.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTAlert I Delay Report

As Of : 30-Apr-11

Dates Milestone I I '" Relative Planned Actual WeightedMilestone Value Weight Progress% Progress% DelayPlanned Expected

Start 08-Apr-11 ,22-May-11 20"_. De~ig~ ••••• ', •• 1i-Ap'r-11- -,- 25-M~Y~1;··· A "40""

Process cause and effect matrix 1.71%

2.56%

2.56%

0.00%

20.00%: 1.71 %60.00%

60.00% : 20.00%

60.00%

60.00% 0.00%

4.27%

4.27%

4.27%

40

20

4.27%

12-May-11

07-Apr-11

27-Mar-11

24-Feb-11 16-MaY-11 40---"--"----"_"-".'-.....L......."'-....._ ......-"-,~'~_"--'-"-,"--'-"......:.....................

1/0 list

Design

Design

Start

Fire and gas cause and effect

Fire &

Fire and gas cable routing drawings

Fire and gas cable wiring diagram 4.27% 60.00% 0.00% 2_56%

Fire fighting, safety equipment and safety signs

•••• :t~rt". " " ••••: •• ?~-~P!-~1••i. ;~~~Y:1~.Design '07-Apr-11 ' 19-May-11

0.00% : 2.56%60.00%4.27%

15-May-11 20.. "". - - _ .26-May-11 40

20-Mar-11

24-Mar-11

Start

Design

* Weights of Activities are calculated relative to (Process)

Tuesday, May 17, 2011 Page 1 of7

Layout NO.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTAlert I Delay Report

As Of : 30-Apr-11

Dates Milestone * Relative Planned Actual WeightedMilestone Value Weight Progress% Progress% DelayPlanned Expected

OverallEngineering

Ppiping Valves

VPR start 27-Feb-11 16-May-11 10

7.89% 65.00% 55.00% 0.79%

* Weights of Activities are calculated relative to {Piping)

Tuesday, May 17, 2011 Page 2 of?

layout NO.1

Data'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTAlert I Delay Report

As Of : 30-Apr-11

Dates Milestone * Relative Planned Actual WeightedMilestone Value Weight Progress% Progress% DelayPlanned Expected

4.44%

2.96%0.00%

0.00%

60.00%

60.00%

4.94%

7.41%Instrument Index

Instrument Cable Schedule 3.70%

Start

3.70% 60.00% 20.00% 1.48%

Design 03-Mar-11 22·May·11 40..

Instrument Hook Up And Supporting Drawings 9.88% 60.00% 0.00% 5.93%

Field Instrument Layouts

Start . 06~Mar·11 i 22-May-11 20

" " - - De~i~~ .. » H • H;' • 10·.Ma"r-11" "i' i5-M~Y=1; .... "40 - - "

Start ,06-Mar-11 ! 19-May-11 20

r " - - 6e~i~~ ... H • ":' • 10·-M';r-11" r 26-M~Y=1; .... "40 - . "

Start ,20-Feb-11 15-May·11: 20

~~~~:~?~~~~~~£Feb.;1» ":' ;8-0~Y:1~ ~ :i :_~:~~~~_:__~~__~~.__."~._". _

Field Instrument Cable Routing 3.70% 60.00% 0.00% 2.22%

•••••• _. _ •• - - - _.". - - - .,_ ••••••• A,A A •••••

Design 23-Mar-11 : 26-May-11 40

Junction Box Interconnections 2.96%0.00%60.00%4.94%

2025-May-1117-Mar-11Start

Start

Design

30-Mar-11MRQ

~l",c;o~m;m;;;O;d;i;ti~e~s=.=::;:===;:=;:===================::::==::::;===========:::== =::====:::==~:::::;;=.=:::;;Ifi Instru:::tI Fire & gas ca:~_:P'_11 19.May-11 20 19.75% 20.00% 0.00% 3.95%

I F"I"n"'struO=m""e"n"t=B"'U:'lk=:="'=:-=~:=·~""=··"""'=:=:=""'=~"~"·~""C:C=:=""=c.=-=-="",,~~~=--~~~=-~~=:~1=7-=;.~2':'8"':'%:'-==-=-="':2"':'0-=.O:'0':%7==~~'--~0=.0='-;;-=""l\==~-==3-=.~4':'6"':'~l\""~-=;·

$1! F""="",M"R=Q"""'=:""'""",7'""",~~,,,""=~=--3,,0=.M,,="',,-~,,,'...~,,,,,2=4-,,,M,,a=y,,-""="==",2"0",,,.~,,,,.~=_=_==~=_=_=-=-=-=__=:_::,:7'=.-=-=-=_=-=-7'._""'_7'~_=.~-'--=-=O-""'~~=-=7~"7,,"=-=;= Instrument! Fire & gas Cable Trays 17.28% 20.00%: 0.00% 3.46%

~=mm

* Weights ofActivities are calculated relative to (Instrumentation)

Tuesday, May 17, 2011 Page30f7

layout NO.1

Dala'Nes Systems, Release 2.21

Project No.: 4187-440

SETH ONSHORE PROJECTAlert I Delay Report

As Of : 30-Apr-11

Dates Milestone I * Relative II Planned DI Actual IWeightedMilestone Value Weight Progress% Progress% DelayPlanned Expected

Overall

Electrical Lighting MRQ

Start

Finish

20-Mar-11 2o-May-11 20.. "." .24-May-11 80

33.33% 100.00% 0.00% 33.33%

* Weights of Activities are calculated relative to (Electrical)

Tuesday, May 17, 2011 Page 4 of?