PETROBEL SETH ONSHORE DEVELOPMENT 4187-440
EGYPT MONTHLY PROGRESS REPORT NO.2 Rev. 0
4187-440 SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT NO.2
AS OF 30 APRIL 2011
• v I I I
0 18/05/2011 ISSUED FOR IMPLEMENTATION If/' /-,1'.- ....r-REV DATE REVISIONS v BY I CH'D APPR
PTB
Egypt
Contents
•Enpp:l.SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
PAGE 1 OF5
4187-440
Rev. (0
18-MAY-2011
I. Project Description
2. Parties Involved and Relevant Scope
3. Schednle Milestones
4. Major Activities Completed
5. Major Activities in Progress
6. Major Activities To Be Started During Next Reporting Period
7. Area of concern
7.1. Progress summary Sheets With Relevant S-Curves
7.2. Progress Control Sheets
7.3. Updated Schedule
7.4. Critical and Near Critical Activities
7.5. One Month Look Ahead Report
7. 6. Procurement Status.
7.7. Equipment and material status report
7.8. Alert report
PTB
Egypt
1.0 Project Description:
SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
PAGE20F5
4187-440
Rev. (0)
18-MAY-20II
The Temsah Pliocene Gas Gathering Network is in operation to collect the gas production from several Pliocenefields located in the Temsah area.Actually the only Denise A and Tuna productions are gathered by the new sealine, and in the following months alsoDenise B and Seth Fields.
The whole new production is transported to the onshore El Gamil plant via a new 32" export pipeline.Denise A reservoir production (Pliocene "heavier" gas) is separated on TNW2 platform. The gas phase is conveyedto El Gamil plant through the new 32" trunk-line.
Tuna and Denise B productions will be collected into a common subsea PLEM and conveyed via a new 24" sealineto the Denise A SSIV; Seth production will be routed via 16" sealines to the Tuna PLEM, Km 10.5 approximately.
During the EI Gamil Upgrading Project Phase (I)a dedicated Slug Catcher for the Denise A Production has beenforeseen and installed.
With Seth Onshore Development Project, the installation of a new slug catcher operating in parallel with theexisting Denise Slug Catcher has been foreseen.
2.0 Parties Involved and Relevant Scope:
PTB: Owner
ENPPI: Contractor shall perfonn basic, detailed engineering and procurement services.
3.0 Schedule Milestones:
Milestone
Project Coming Into Force
Complete Engineering Services
Complete Procurement Services
Planned
22-DEC-1O
22-SEP-11
20-JAN-12
Actual
22-DEC-IO
Expected
22-SEP-ll
20-JAN-12
4.0Major Activities Completed During the Current Reporting Period:4.1. Engineering
Basic engineering review completion
-/ Process• Hazardous Area Classification Schedule IFD• HSE philosophy IFD• Detection And Alarm Layout Drawings IFD• Fire Fighting Layout Drawings IFD
PTB
Egypt
•E:n.pp.l.SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
if Piping• Under Ground Composite Drawing IFD• Under Ground Piping Standard Details IFD• piping specification classes IFD• Standard Piping Support Details IFD
if Electrical• Earthing Layout IFD• Hazardous Area Classification Layout IFD
if Civil• Standard Drawings IFA
PAGE30F5
4187-440
Rev. (0
18-MAY-201I
4.2. Procurement
• Piping Bulk Bidding
5.0Major Activities in Progress During the Current Reporting Period:
5.1. Engineering
if Process• Fire Fighting System Technical Evaluation• Detection and Alarm system Technical Evaluation
5.2. Procurement• Piping bulk Bidding
6.0Major Activities To Be Started / Completed During Next Reporting Period:
6.1. Engineering
if Process• Cause and effect IFD• Process cause and effect matrix IFD• Fire and gas cause and effect IFD• Fire and gas cable routing drawings IFD• Fire protection system TER
if Piping• Piping Bulk TER
PTB
Egypt
•Enpp1SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
.{ Instrumentation• Field Instrument Cable Routing IFD• Junction Box Interconnections IFD• Field Instrument Layouts IFD• Loop Diagrams IFD• Instrument Index IFD• Instrument Cable Schedule IFD• Instrument Hook Up And Supporting Drawings IFD• I/O list IFD• Instrument Bulk Material MRQ's• Instrument Cable Trays MRQ's
.{ Electrical• Electrical Bulk MTO
.{ Civil
• Standard Drawings IFC• Miscellaneous pipe support Foundation Drawings IFA
PAGE 4 OF 5
4187-440
Rev. (0
18-MAY-2011
6.2. Procurement
• Instrument Bulk Material Bidding• Electrical Bulk Bidding• Piping bulk Bidding
PTB
Egypt
•Enppa.SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
7.ATTACHMENTS
PAGE50F5
4187-440
Rev. (0
18-MAY-2011
II
rI
PTB
Egypt
•E:n.pp.l.SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
7.l.Progress summary Sheets With Relevant S-Curves
4187-440
Rev. (0
18-MAY-2011
Summary Report
Overall
Project No.: 4187-440
SETH ONSHORE PROJECTAs Of: 30-Apr-11
Item Description Relative Planned Actual DuringWeight % % %
"Engineering 76.55% 39.98 27.26 10.26
, ": : : :
";;:c-;;r~m:n~ - - - - - - - - - - - - - - - r- --;:::---~-- -275""; - - - t - - - ~.;; - - - -i - - - -:.; - --
~ ~ ~ L ~ _
Total
Monday, May 16. 2011
100.00%
Page 1 of 1
35.66 25.25 8.86
Layout No.1
Data'Nes Systems, Release 2.21
EDpptProject No.: 4187.440
SETH ONSHORE PROJECT
Overall
Progress Curve
As Of: 30·Apr-11
100
90 lp'a~ned % =
IActual %=
80 : ....
70
60~IIIIII
" 50~
Cl0~
0..40
30
20
10
35.66 I25.25 I
:
;
•
;.
;
.; . - -: • •
0
..." ..." ...... ...... ...... ...... ...... ...... ... ...... ...... ...... ...... ...... ...'l- ...'l- ...'l-",' c: ')"C-<$ ",' ~~/ .: ~..« ~ ,,'" ",<$ G.;P" " .J: c: ":J'lJ.<$
",' ~~.~o Qe ~e.,.q
)'" )'" .,. 0" ~o Qe ~e
Time I Date
---"'-_.--- ..._.-- ..
Actual - - • Planned
--------- ._-- ._--------- ...•---_...:
Layout NO.1
Dala'Nes Systems, Release 2.21
Summary ReportEllppl
Overall
Enaineerina
Project No.: 4187-440
SETH ONSHORE PROJECTAsOf: 30-Apr-11
Item Description Relative Planned Actual DuringWeight % % %
...----------------------,...----------.-----------....,.-------------.---------· ....i Process : 17.92% : 45.98 ; 34.09 ; 12.38: ::::· ....~--------------------~--------~--------~--------~---------i Piping i 42.73% i 31.76 i 30.25 i 7.03
~--------------------~--------~--------~--------~----- ----i Instrumentation i 12.40% i 38.27 i 5.19 i 5.19
~--------------------~--------~--------~--------~----- ----i Electrical i 5.51% i 73.33 i 40.00 1 40.00L L L L j -- __· ....i Pressure Vessels i 4.90% i 65.00 i 65.00 i 0.00
~--------------------~--------~--------~--------~----- ----i Civil i 16.54% i 37.50 i 13.24 i 13.24L ~ ~ L ~ _
Total
Tuesday, May 17, 2011
100.00%
Page 1 of 2
39.98 27.26 10.26
Layout No.1
Data'Nes Systems, Release 2.21
100
90
80
70
60
"~~ 50~
'"£40
30
20
10
(Planned % =
IActual % =
39.98 l27.26 I
.•••,,
•.:
Project No.: 4187-440
SETH ONSHORE PROJECT
Proffesional Services
Engineering
•:..':
,"" .... ,
Progress Curve
o-l--~~=------i--~-~----:--~-~-~-:------i-------i----i-----i---i---1Nov-10 Dec-10 Jan-11 Feb·11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12
Time I Date
Actual - - • Planned
Layout No.1
Data'Nes Systems, Release 2.21
Summary Report
Overall
Procurement
Project No.: 4187-440
SETH ONSHORE PROJECTAs Of: 30-Apr-11
Item Description Relative Planned Actual DuringWeight % % %
'i Purchasing 42.00% 42.86 38.57 8.57~ ~ ~ i ~ ----
i Expediting ! 34.00% ! 10.44 i 7.35 i 2.06
~--------------------~--------~--------~--------~----- ----i Inspection ! 24.00% ! 0.00 ! 0.00 ! 0.00L L L l J _
Total
Tuesday, May 17, 2011
100.00%
Page 20f2
21.55 18.70 4.30
Layout No.1
Data'Nes Systems, Release 2.21
EnpplProject No,: 4187.440
SETH ONSHORE PROJECTProgress Curve
Proffesional Services As Of 30-Apr~11
Procurement
'... . -;
, :,,
--,, ,
••
,•
• • o!l
,:,.'
21,551
18,70 I
':
Iplanned % =
IActual % =
100
90
80
70
60..00
50~Cle0-
40
30
20
10
Feb·12 Mar-12Jan-12o.c-11Nov~11Ocl·11Aug-11 Sep-11Jut-11Apr-11 May-11 Jun-11Mar-11Feb-11o.c-10
.. ,- ......,;-"--~o.jo....:.=--T..c.'-----;---;--~'---;_--;_--;_--.;_--.;_--..;_--..;_--.;..--.;..--..;..--_:_--_/Nov~10
• • • Planned
Time I Date
Actual I,,__, ' " ,, , ", J
Layout No, 1
Data'Nes Systems, Release 2.21
Enppl 4187·470 PTB, SETH ONSHORE PROJECT
DELAY ANALYSIS
AS OF 30-Apr·11
Process CaUse and effect matrixfire & gas I/O IIsl
11.89 1.54Halardous area c1asslflcotion s~hedule
24-Mar-ll 26·May-l1Firefightlng system layout drawing
Detection and alarm layout draWing
1.51 0.52Pplping Valves Vendor prints review
27-Feb·ll 20-May-ll
Instrument Index
I/o listInstrument Hook Up And Supporting Drawings
33.0& 3.59 Field Instrumenllayouts 30·Mar-1l 26-M"y-U
Field Instrument Cable Routing
Instrument Bulk MRQ
Instrument Cable T,a s MRQ
33.33 1.66Electrical Bulk MTO
24·Mar-ll 24-May-ll
24.26 3.10Civil standard drawings IFe
24-M.r-ll i6-Apr·nMisc. Steel supports found"tion plan & details IFD
Instrument I Fire & gas cables RFQ The delay of MRQ's issuanceElectrical bulk material RFQ
4.29 0.47I....trument Bulk RFQ 13·Apr-ll 26-May-llInstrument I Fire & gas Cable Trays RFQ
In progress
3.09 0.24Piping Valves start fabrication
17·Feb·ll 18·May·ll
PTB
Egypt
•Enpp1SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
7.2.Progress Control Sheets
4187-440
Rev. (0
18-MAY-2011
~
I
I
Project No.: 4187·440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%
0.00%
0.00%
0.00%
20.00%
60.00%
60.00%
0.00%
0.00%
60.00%
60.00%
4.27%
4.27%
4.27%
4.27%
4.27%
20
20
20
40
40
4.27% 60.00% 20.00%
20•• « ••••
40.... - _.40
4.27% 60.00% 60.00%
20. ... - - -40
_ ... _.-40
27-Jul-11
16-Aug-11
22-May-11 20. - - .... - .. - ....2S-May-11 40. .31-Jul-11 40
11-Aug-11..... - ..17-Aug-11. .. "" ...02-Sep-11
11-Apr-11." .
08-Apr-11•• _ ••• _ ••• T •• _
:13-Mar-11
:13-Nov-11
:28-Nov-11
cause and effect
81art
Start
Start
Start :ZO-Feb-11 29-Mar-11· . "De~i~~ T ••••• 'i24~Feb-;; . ~ . « • « •••
............. ., .Construction : 27-Jul-11
Start :03-Apr-11 . 25-Apr-11.......... - -' "0"·············« .Design : 07-Apr-11 , 19-May-11
· .. Co'n~lr'ucti~~ . - . -!24~Au~~11' . " 23-Au"g:11 .
· - - - - - " - ..
• •• ~e.si~~ ••••••Finish
Start
Design :17-Mar-11 , 18-Apr-11· . - - - , ',' - - - - -Finish :17-Aug-11
_ ••• _ •• r " •••• _ • •••
Design !OS-Dec-11.............., .Finish :21-Dec-11
Process cause and effect matrix
Fire and
Hazardous area classification schedule
Fire & gas 110 list
Pre-commissioning procedure
Commissioning procedure
Design ,20-Nov-11 02-Aug-11 40
" ••• Fi~is"h' •• :~~Jo6~De~-;1' • " •• :,~~:~8-AUi~~':_:_~.~ 40'~ _
HSE philosophy specification
20
40
40
29.91% I 42.86% 22.86%
Drawin s
Fire fighting system layout drawing
Start : 13-Mar-11" ',' " .. " ..
Design :17-Mar-11.............. , .••• ~o.n~tr.u:ti?~ • _ ~ .:!7:~u~-~~ •
20
40
40
3.42% 60.00% 60.00%
* Weights ofActivities are calculated relative to (Process)
Tuesday, May 17, 2011 Page 1 of 19
Layout NO.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
Milestone I Dates I Milestone I * Relative Planned I Actual
I Planned Actual Expected I Value Weight Progress% Progress%
Overall
••••••••• ~ • « • ',' • • • • •• • •••• «««.« ••••••
0.00%60.00%4.27%
20
12-May-11
18-May-11....... .01-Sep-11
4.27% 60.00% 0.00%
16.May-11 20.... _. .......19-May-11 40. . «_. - . .. ... .08-Sep-11 40... .. _.
4.27% 60.00% 60.00%
:27-Mar-11Start
Design :31-Mar-11« •••••••••••• ",' ••• « " •••••••
:04-Sep-11
Start :03-Apr-11" ••••• - • - •••• ',' ••••• «
Design : 07-Apr-11
-.. C;n~t;ucti~~ ... '!11~Se~-11' .
Start ,'OS-Mar-lt 13-Apr-11••• - ••••••• - • ',' •••••••• « ••• - -
Design !to-Mar-tt , 20-Apr-11••••••••••••••, •••• -'. c - ••••••
Construction :10-Aug-11
Detection and alarm layout drawing
Fire fighting, safety equipment and safety signs
Start :20-Mar-11 15-May-11 20~ . , - - . - ',' ;- .
Design !24-Mar-11 ; . 26-May-11, 40~ •• a C;n~t;ucti~~ ••• ·i24~Au;.;1· a , ••••••• " y 23-Aug:11 » : : ~ • 40· ••
20.51% I 60.00% I 22.50%
Start
Construction
i27-Jan-11
: 20-Jul-11
10-Mar-11
19-Jul-11
20
40
10
30
20
40
40
... Weights of Activities are calculated relative to (Process)
Tuesday, May 17, 2011 Page 2 of 19
Layout NO.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
Milestone i Dates I Milestone III--'p"":-.-nn-e-d""'---A7"c:-t:-U-.:-,---:E:-x-p-e-ct:-e""'d-lI Value I'" Relative I Planned I Actual
Weight Progress% Progress%
Design 17-Feb--11 17~Mar-11 40. . . . . . . . . . . . . . . . . . . .. . .Construction 20-Jul-11 19-Jul-11 40
34.09%
4.27%
2010-Mar-1127-Jan-11Start
Total Process
"" Weights of Activities are calculated relative to (Process)
Tuesday, May 17, 2011 Page 3 of 19
Layout No.1
Dala'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
Dates Milestone I* Relative I Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%
Overall
DesIgn :03-Mar-11 , 20-Apr-11 . ,40," ~ •• - ••••••••• ',' •••••• " ••••••• " •••••••• " ••••••• i
Finish ,'24-Aug-11 23~Aug-11 40~~~~~~~.._-~ ..._....~_......__......__..._..._._........-"-.....~....~-"-.- ......~~~.~~~~~~""'''''''-'--_._~~.~~-~~---------------- --_._._------_._-_.
0.00%
0.00%
60.00%
0.00%
0.00%
60.00%
2.87%
2.87%
2.87%
30
20
20
40
40
3.58% 60.00% 60.00%
20· .... ~ .40
• " " " « ~ ~
40
3.58% 60.00% 60.00%
20"«.« •••
40· - - - - - -
40
38.18%
ZQ-Jul-11
08-Sep-11
31-Mar-11
10-Mar-11
15-Mar-11
21-Jul-11
:27-feb-11
:20-Feb-11
:03-Mar-11
Table
Start
Start 28-Jul-11
Finish 27-Jul-11
Start
Finish
Start
Start
••••••••• « •••••••••• " •••••••
· " " .. . ~ .
Design :24-Feb-11 28-Mar-11• •• Co<n;t:Udi~~ « 4 • '!28~AU;-11' •." « « « « ••••,. 25-Au·9:11"
Start : 03-Apr-11 31-Mar-11
• - - De~i;~«' ~ ~ ~ ~ ·!Oi-Ap~-11· -:- - 07=A~;-1·1·• •• _ ••• ~ _ • ~ •••,' ••• _ •• ~ ••• v • __
• « « ~~n~t~u:ti?~ ••• ':~1.-~e~;~ _ « •• " ••• <
• •• < " • < , •• « •• '," •••••• , • « « •••••••••••• ~
Specification for ins. Of UlG system.
~ ~ ••••••••••• '," < , « ••• < ••••••• ", ••••••••
Specification for field test of U/G system.
Piping Material Classes specification
Tie-In List
•••••••••• - - - - -.' - - - ••• ~ •••••• « .:. - • - •• - - , - - ••• - • ;
4.30% 60.00% 60.00%
Start :20-Feb-11 15--Mar~11 20· . · -,' .. ,
Design :03-Mar-11 20-Mar-11 40. . . - · '," .. .. .. - . ..Construction :03-Aug-11 02-Aug-11 40
4.30% 60.00% 60.00%
Start :27-Feb-11 15-Mar-11 20.. · . . . ,_~~si~~ : 10-Mar-11 20-Mar-11 40.. -,' y y - -« . . ... . .
Construction :10-Aug-11 09--Aug-11 40
Underground composite drawing 5.02% 60.00% 60.00%
* Weights of Activities are calculated relative to (Piping)
Tuesday, May 17, 2011 Page4of19
Layout NO.1
Data'Nes Systems, Release 2.21
Project No.: 4187·440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
MilestoneDates Milestone 'It Relative Planned Actual
Planned Actual Expected Value Weight Progress% Progress%
Start :19-5ep-11 18-Sep-11 20, ••• co'n~t;ucti~n' .•. ·i25~Se~11· • ~ .• - •••••:. 22-S~~11' C 80 .. :.......................~~_4~~_"__~_~'_ "-"_""_ _<..~~ ___"__~__?_~ ~L_~~~_~~~_~_ _"'"--~-'- ~.~ ~__~ ~"_"_.~._.__"_._
Hydrostatic test loops.
60.00%60.00%3.58%
20
40
4.30% 60.00% 60.00%
20...... .40...... .40
4.30% 0.00% 0.00%
3.58% 0.00% 0.00%
20...... .80
3.58% 0.00% 0.00%
20.......80
32.97% 39.13% 39.13%
02-0ct-11 40
details
Start : 05-Apr-11 08-Apr-11• •• De~i;~ •.•• " • 'i 09-Ap~-:;1' • :. '14:A~;-1"1' •..• - " •••· . ~ " ',' " . ~ - .
Construction :06·Sep-.11 03-Sep-11
Start :14-Apr-11 31-Mar-11• • ~ De~i~; •••••• '::;O~Ap;-11' • " • 21:A~:-1-1'
• - • co'n~t;ucti~~ - - . -i 03-0ct~:; 1" • , ••••.••
Underground piping standard details
Standard
Start : 02-0ct-11 29-Sep-11• - • Co'n~t;u~i~n' ••• -i os-octo:; 1" • " .•••••••• 'OS-Oct-; l' .
Special piping support
Standard steel structure list
OverallEngineering
Commodities
3.58% 15.00% 15.00%
15.... .. .30... ...1S.. . . ...10. .. - ...30
7.89% 65.00% 55.00%
19-May-11....... .09-Jun-11
22-Mar-11:17-Mar-11
:04-Aug-11VPR finish
MRO
Piping Bulk
Ppiping Valves
;. ~ , ~~~ .VPR start :26-Jun-11 26-Jun-11
~~~~ -: " : .
1. Evaluation :19-May-11."." -MRp······· ·i09-J·u~-11···-····"·
1S
40
16-May-11 10... "" ..... " ....13-Dec-11 35
MRQ : 04-Jan-11 04-Jan-11= I :" .. --r. E~alu~ti'o~ ••• 'io2~Feb-;1' - ~ • 08~F~b.1·1·~J ~ ... VPR's~art' •• - • -:;7~Feb-;1' • ~ •••••••
mml •... VPR'fi~i;h' •••• '!05-0ct-11" • " •••••••
11.. -!._1_1_.4_7.;.%_,_.I.I_4_9_._38_'_Y'_.l.-4_2_.5_O_%_,_
* Weights of Activities are calculated relative to (Piping)
Tuesday, May 17,2011 Page 5 of 19
Layout No.1
Data'Nes Systems, Release 2_21
Project No.: 4187·440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%
Overall
0.00%
0.00%
80,00%
0.00%
0.00%
100.00%
100.00% 100.00%
3.58%
3.58%
3.58%
0.00%
20
27-Sep-11 20
OS-Oct-11 80
27-Dec-11
, ,--".-"-'--'~'.~""""~~--""~.""""'''---<''-''---''-''''''''''''"------
....... -.' " :
:27-Feb-11
Start 2B.Sep-11.... ".""" .Finish 09-0ct-11
Piping bulk final MTO
Start :03-Mar~11 15-Mar-11 20 ,
L_:~_~ FI~I;h - .. ~_:~~M~'r-11'-~_~_~~~M~i~~_~:~:_: ~~~_: ~~~~_~~~_~ ~~_._._.._._. _
Start
Finish
Piping valves final MTO 0.00% 0.00% 0.00%
Finish 19-Jul-11........, --29-Jun-11
oo
10.75% 66.67% 60.00%
GA~
8.60% 0.00% 0.00%
28-Aug-11»»»««« - -.- ••• _.«»
10-Aug-11.». - - - - -,_ •••••••
19-5ep-.11
9.68% 0.00% 0.00%
28-Aug-11 20•••• »» » .. • • - • » ~
28-Jul-11 0- _ ..... .. • • M • « ......19-5ep-.11 80
18.28% , 0.00% 0.00%
10.75% 0.00% 0.00%
20-Jul-11
: 20-Jul-11Start
Start
Piping GA drawing area
Existing piping GA drawing area
~ ••• « « » » » » • « •• ',' ••••• »
. Design : 28-Jul-11~ • - ••••• - - « « « « -, •••••••
Construction :20-Sep-11
~""---"~'.'»'---'--
I ~. ~ .~e.si~~ •• « • « •• ~~-~u~-~1••~I Construction 20-Sep-11
1lI1d==~~~~~==~~'='='===~::::==;==:=:=~~iii[ti~----------------------------------"'-----"'----"'----ffJii/SO's
€Ij!j-F~;='==;===:='=================:::::::==;:=;=~::::=:::::::===='"ili~i2ill Piping isometrics
~IIBh " ~::;r~cti;~ ----:~:~~:;~{ ~ ~ - -~~~;:f~~ ~ ~ ~ ~ .~~ ..i;;lIIF====~='===~~~~~='=====r~::==F~==;=:===5. 10.75% 0.00% 0.00%1lI1------------------------------J-------J------..I,-------., Weights of Activities are calculated relative to (Piping)
Tuesday, May 17, 2011 Page 6 of 19
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%
Overall
I
b
* Weights of Activities are calculated relative to (Piping)
Tuesday, May 17, 2011 Page 7 of 19
Layout NO.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of: 30-Apr-11
Dates I Milestone I * Relative Planned ActualMilestonePlanned Actual Expected I Value Weight Progress% Progress%
0.00%
60.00%
20.00%
60.00%
60.00%
: 60.00%
7.41%
3.70%
3.70%
3.70%
3.70%
20
20
40
40
20
20
40
40
18-May-11••• z •••
24-May-11
16-Aug-11
15-May-11
18-May-11. .26-Jul-11
16-May-11
. - _. "-19-M~Y~1;'
...... ',' 23-Au"9:11 .
20-Feb-11
:27-Feb-11
:24-Aug-11
i 10-Mar-11
Start
Start
Finish
Start
Start
· .. ~e.si~~ .•••.•. ~4.-~e~~ 1..Finish 27-JuJ-11
. - - .· .. ~e.sj~~ :?3:'~a:-~1..
Finish !03:AU~-~1
Start . _ . __ ..!~7.-~a!-~1..
· __ ~e.si~~ .... __ .!~3:~a!-~1. _
Instrument Index
Design :16-Mar-11.......... - - - -, - . - ....
Loose Instrument data sheets
Instrument Cable Schedule
Sand probes data sheets
Start :24-Mar-11 , 10-Apr-11 20~'-'--'.' .. "-'.""-'-'--"'" " - .. ,
Design :30-Mar-11 . 14-Apr-11 , ,40,, " •••••••• __ • " ", _ " ••••• ~ •••• __ • _, T ••••••• ~ ••••• _ • ,
_J.---,--_,,---,-.?~~~~~~~:~P-11....>.-.~-"-"-'-...~~._~~"---"---,,_,,_~.~,,-.-<-., .__..._ .._. .__. _
* Weights of Activities are calculated relative to (Instrumentation)
Tuesday, May 17, 2011 Page 8 of 19
layout NO.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
Dates Milestone '" Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%
Overall
Junction Box Interconnections
~ ••••• « ••••••• ',' ••••••
Design :23-Mar-11;. .. - ",' .
Construction :23:-AU~-11
Start :17-Mar-11 25-May-11• •• « ••••••••••••
26-May-11
22-Aug-11
20
40
40
4.94% 60.00% 0.00%
23.46% 60.00% 0.00%
Commodities
0.00%
5.19%
20.00%
19.75%
17.28%
40
20
10
40
20
10
30
1B-Jul-11
19-May-11. .26-Jun-11
: 14-Jul-11
cables
VPR s1art
VPR finish.. _. - -' _ " .., .
MRQ : 07-Apr-11...... - . - - - - - " - - - - - ..T. Evaluation :29-May-11............. ',' .
Instrument I Fire &
Instrument Bulk
Total Instrumentation
'" Weights of Activities are calculated relative to (Instrumentation)
Tuesday, May 17, 2011 Page 9 of 19
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
I Dates Milestone * Relative Planned ActualMilestoneI Planned Actual Expected Value Weight Progress% Progress%
Overall
" ••••••••••••• ',"'"«"
0.00%
60.00%
60.00%
60.00%
60.00%
60.00%
60.00%
60.00%
100.00%
22.22%
22.22%
22.22%
33.33%
20
20
20
40
40
40
40
40
40
16-Aug-11
09-Aug-11
28-Apr-11.......
13-Apr-11.......17-Apr-11.... - --
14-Apr-11.... - - - -.- - - - - - --. ~S:A?~-1.1 .
23-Aug-11
20-Mar-11
:13-Mar-11Start
Start
... ~~si~~ ••••... ~0:~a!-!1..Construction 10-Aug-11
. . . l?e.si~~ __ .. __ . ~4:~a!-~ i. _
Construction .•• ~4-Aug-11
Electrical grounding layout
Hazardous area classification layout
Electrical Lighting MRQ
.... I?e.si~~ _ !~7:~a:-!1..Construction :17-Aug-11- - - .....
Start
Finish
20-Mar-11
24-Mar-11..• "" •• ~: ~ ~~-~~Y:1~ .
24-May-11
20
80
33.33% , 100.00% 0.00%
Total Electrical 40.00%
., Weights of Activities are calculated relative to (Electrical)
Tuesday, May 17, 2011 Page 10 of 19
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of :30·Apr·11
Dates IMilestone I I.. Relative I Planned ActualMilestonePlanned Actual Expected 1 Value Weight Progress% Progress%
Overall
Total Pressure Vessels
MRO
T. Evaluation
VPR start
VPR finish
04-Jan-11
02-Feb-11
20-Mar-11
28-Jun-11
04-Jan-11
13-Feb-11
28-Mar-11
21-Jul-11
15
40
10
35
100.00% 65.00% 65.00%
65.00%
65.00%
.. Weights of Activities are calculated relative to (Pressure Vessels)
Tuesday, May 17, 2011 Page 11 of 19
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of :30-Apr-11
Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%
17.11%
10
40
50
10
30
40
50
70
10
5040
02-Jun-11
15·Jun·11
24·May·11
1.85% 50.00% 50.00%
" :O:Ap~-~1 . 10. .......17-Apr-11 40.......
50
1.85% 50.00% 50.00%
. ~O:Ap~-~1» .' .... « " ••
17-Apr~11.« ••••••.•••••. «
· ~0:Ap~.~1.
· :7:Ap~.~1.
• ~3:A'p~-1.1.
14-Apr-11
:17-Mar-11Construction
• « • ~t~rt• ••.••.•. 9~-~p~-!1••
... 9,:Si~~ ... « ••• !~-~P~-!1••Finish 13-May-11
Shim and grouting Specification
Concrete Specification
Start !20-Feb-11. --De~i;~ '!24~Feb-l1- •............. ',' .
Overall
Engineering
Start : 06-Apr-11...... - ",'" "" ...Design : 18-Apr-11
- •••• » •••••• - " - - - • - • »
Fi~is_h _ •• _ ••••:~3-May-11 . :~-~aY-11
hqyF='::'=~~=c=~~==~===!==~====:=:::o:;===c:::~==::~=
.
..r.~.,.; structural st••1fabrication Sp.cification 1.85% 50.00% 50.00%
-;:;\ Start : 06-Apr-11 , 1D-Apr-11 10_.» •• »» •• _. - - -,- - _. - -» •••••••• -.- - _. - - - - -';III Design : 18-Apr-11 ! 17-Apr-11: 40II .. -Fi~is-h - .... _. >j3~Ma~'11' - -' - T' •• _.- ;8-M~Y~1;' . - - 50 -';gl="S=ite::=p"r."p"'a"'ra=t:Oio"n"',"'e=a=rt:Oh"W"O"'rk:;=;&""ba"'ckfi"":~IiI"S"P"""'C:Cifi"'lc"a'"ti"'on""'=:=:====:=:""====::=±o=======1"."8"5'''~===;5::0:=.0:=0:=%;;=="5::0:=.0:'0"'::~=1mi-..,~.:.~.~.J. 1°" ~ ••• ~t~rt_ _ • _ » _ • » • ~O:A?~-1.1_ • _ •• , __ • " .•••. ~ ~
§it « « ~ £?~si~~ • • • • • • ~7:Ap~-1.1 . .... ~ .. « « « " « •• ~o•• _
11=""==:"",F=;n";~'h==:=:====:.=:=."",,,,,,,,,,~,,,,,,,,,,::=,,,,,,,,,,=,,,,8=.,,M,,a,,,Y'=',,,,,,,,,,,,,,,,,,,,,,,,5,,0=='========7':0=:':='==:=:::=:'=:==0=::=:'",,="linE Concrete paving Specification 1.85% 50.00% 50.00%:s2&""lW
,[g~~..~.c.•: 10___ ~. ~,~t~rt••••••••• :?6"-~P~-!1•• ~. ~O:Ap~-1.1••:.. YTY«.«,. ••••••• ;~:g Design : 18-Apr-11 , 17-Apr-11 , 40
r.i.F.-~,=±' "·"·",·~F=·;"~",i;,,h=:~:~.·~~:.,,·.=·,,,,,:,,·~j 1",3~:M,,'a~~~'-~"='"'='=='"'~',,,,,' "'",'",,,'".~.'='8-",'=M",a~'y=:,=;",'~'"',,,'=' "5",0'",,,',,'±=========:=::'::===='0=:0:7===':':':C:==::::::t -- ~ ...............-"---'-~-"-----"-"-"-..;,-"- ........_,~_.......:.._."- ----~-II Soil & foundation investigation Specification 2.78% 50.00% 50.00%
II
r.:.t.,:.··~...;" : : : ~::~~~ : : : : : : : ~~:~:;:;:: :£::: Finish. :~3-May-11 18--May-11
1l=='=Ex==:is"'t=in=g"p=/~RO=V"''''ri~fi''ca''ti~'o=n-2r''''p'''o'''rt±=±====:=:'''''-2==±::=="""""=====±=======~2~3~.~15~'~l\===~0~.0~0~%C===0:'.=0~0~%,:=,=
;1 ~::'h- ·:~~1~;~;; .f~1 35.19% I 17.11%11l------------------....-------------..I.----...l----..I.----!;D~r.~..s~~~~~:~:~:~1g=.=n".=ra"l=n=ot:='='========================="3:=.7='0"%;;===;1=00='.:::0"0':=~==::60='.:::0=0'?~=IZi§i!l1§jaej@ill.'i_I
* Weights of Activities are calculated relative to (Civil)
Tuesday, May 17, 2011 Page 12 of 19
Layout NO.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440SETH ONSHORE PROJECT
Issuance Status ReportAs Of :30-Apr-11
Dates Milestone I * Relative I Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%
Drawings
Anchor bolts standard details 2.76%
standard details
60.00%100.00%2.78%
2.78%
50
10
40
50
10
4024-May-11
24-MaY-11
03-Apr-11...... .« ~4:A?~-~1 •
03-Apr-11 ,.... - - - ., .14-Apr-11....... '," .
:17-Mar-11
Construction
Construction
Start :20-Feb-11••••••••••• « •• , •••••••
Design :24-Feb-11• • • • • • • • • • • • • ',' ••••• «
Start ;20-Feb-11". - _ -' ., .Design :24-Feb-11
••••••••••• " •• , - « •••••
Start :20-Feb-11
~ ~ ~ ~e:Si~~ : : : : : : :!~4:~e~-~1~ ~Construction :17-Mar-11
Misc. Steel supports foundation plan & details 8.33% 60.00% 0.00%
0.00%
0.00%0.00%
9.26%
11.11%
10
50
40
05-Jun-11: 19-Jan-11
Valves foundation plan & details
Start :12-MaY-11 19-May-11, 10 ,~'"'_ ••••• "*'*:_""'H~""'.' •••••• • ••••.
91 ~ ~e.si9~ ••••.• •:~o:~ay-}~ ", ;. ~:-~~Y:1~ ~ : ~ ~ • :0.••.;1_-... Con:tr~~~~ ..".,"-,,-1~~~~~,,~.->--"-'C-,-~~:~~~-, __~~~4~~~: __~ .__. ~ ._
§ New slug catcher foundation plan & details 12.96% : 60.00%ii!E
4QWf
1m Starttil .--De'si~~ ••• ~ • - -i;6-J-a~-11" •• T •• « - -, - 23-M~y~1; •II .« ••••••••••• -i18~Au~-;1·· ••..•• ««. 09-Au9:11 .
·§fjfF==;;;;=====":~=='==="'===~==='=======c===~o=====o====~ steel details 11.11% 60.00%"Wi
I , St~rt ' !"Ap~.~,.. , :~"~~Y:'~ 10 .ill Design ,: 26-Apr-1l , . 26-May-11. 50
1I1==',=='"'"'=c"o,,'n,,;t,,;"=ct=i~=n,,",,',,'='=',,,!2,,'0,,:,,se,,;""",""'"',,'=',,,,,""',,'='=',,,,'"··"·='=9,,·.A,,·U,,·g,,:,=',,,,,·"',,',,'='=4,,'0,,',,'='''''=====r======r=====r=====II 55.56% 56.67% 13.00%1I:... ...l_;.;,~.;,;,_..l....;.:......;;.....l .....,;,;,;.;.;;.,_
=MTO~--I Civil MTO
iliili~ Start :OS-May-11 , 19-May-11 20
~I '_.: ~ ~i~jS~: :: .. :: >o~~ar-}~·'····:::::: ~~-~~y~1;· r··· 80"
;~l:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::~:::9.:2:6:%:::~1::0:.0:0:'/.:'::~::0:.0:0:'/.:.::* Weights of Activities are calculated relative to (Civil)
Tuesday, May 17, 2011 Page 13 of 19
Layout No.1
Dala'Nes Systems, Release 2.21
Project No.: 4187·440
SETH ONSHORE PROJECTIssuance Status Report
As Of :30-Apr-11
Dates Milestone , * Relative I Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%
Overall
• Weights of Activities are calculated relative to (Civil)
Tuesday, May 17, 2011 Page 14 of 19
Layout NO.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
Dates I Milestone I* Relative Planned I ActualMilestonePlanned Actual Expected t Value Weight Progress% Progress%
OverallProcurement
RFQ 11-Apr-11.....................Rec.Bids OZ·May-11
•••••••••••••••••• « ••III
Fire detection
C. Evaluation
F.OA
Piping Bulk
13-Jun-11
20-Jun-11
9.52% 10.00% 40.00%
24-Feb-11 10. - - -23-Mar-11 30
. - "fi fi •
10-Jul-11- - - - - - -
17-Jul-11
9.52% 40.00% 40.00%
RFQ 24-Mar-11 10
0.00%
40.00% 40.00%
10.00% 0.00%
40.00%
100.00% 100.00%9.52%
9.52%
9.52%
16.67%
11.90%
30
30
30
10
30
30
30
10
30
30
30
10
02-Jun-11
09-Jun-11
02-Jun-11
30
10_ " -:
, ,.... - - - -,- - - - _ ... ,'
03-Jan-11
20-Jan-11
10-Mar-11
15-Mar-11
05-Jan-11
18-Jan-11
02-Jun-11 30
28-May·11 30..... _. .. - - . . .. _ .... - .04-Jun-11 30
- .... - " , - - ... ~ .11-Apr-11 18-Apr-11... - .. - " ..... ~ -
17-Feb-11
OS-Feb-11
22-Dec-10
19-Jun-11
:22-Dec-10
:OS-Feb-11
:28-Mar-11
F.GA
C. Evaluation
Rec.Bids
C. Evaluation
F.OA
RFQ
Rec.Bids
F.OA
Rec.Bids
RFQ
Catcher
RFQ
· - . - - - " - - -
• •• » " , " •• " • " " -, •••• - •• ~ " •••• " "
RFQ 11-Apr-11 02-Jun-11 10• •• - • - - - •••• ~ •••• - • - - - •• " •• , •• < - - - -
Rec.Bids 29-May-11 30· - ... , .. - - - - ~ " ... " ~ - ..... ".. . ... - - -c. Evaluation 12-Jun~11 10-Jul-11 30
RFQ !04-Apr-11 24-Feb-11· .. - " . - ... , " , ., - ... " .. ~ - . - . " " .Rec.Bids : 07-Apr-11 28-Mar-11........... ". ",." "C Evaluation :17-May-11, 10-Jun-11
· ~ ~ F.O.A." .... 4 ••!;5-J·u~-11· • ~ • " ••••••,' ·15-ju~-;1 •
· . ~ .. - . - - - ... " .... - ...- - - - - - ..
· - " ~ ... - . ~ .. - " - - - - ~ . ~
Rec.Bids : 18-Apr-11- .. - ... " - - .. - -, .... - . -C. Evaluation :OS-May-11
~ - .. - - . ',' .. " - - -· . "~''?~ __ . __:~2~~ar-}: .
Instrument I Fire & gas cables
Fire protection system
., Weights of Activities are calculated relative to (Purchasing)
Tuesday, May 17, 2011 Page 15 of 19
layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
MilestoneDates Milestone ,., Relative Planned Actual
Planned Actual Expected Value Weight Progress% Progress%
Overall
0.00%
38.57%
10.00%
11.90%
11.90%
10
30
30
24-Jul-11
17-Jul-11
19-Jul-11
25-MaYc11« • « « « .« - - - « « « • «
07-Jun-11
19-Jun-11
12-Jun-11C. Evaluation
F.G.A.
RFQ 11-Apr-11 26--Jun-11 10« ••••• « •• ««.« •• « ••••••••• ««« «««««. _ ••• ««« ••
Rec.Bids 01-MaY-11 05-Jun-11 30« « ••••• _ ••••••• « ••• " « •• « •• « A A ••• « « « «
Instrument Bulk
Instrument I Fire & gas Cable Trays
Total Purchasing
RFQ : 13-Apr-11" « « •• « « - « « •• « « ".' ••• - - -I Rec.Bids :03-May-11
~~I «-« - C.·E~u~t;o~ - « - "i 14-jU~-11- -
ill=",'=·=·=·~,:~.o"·."A,,.·=·=·=·=·=·==·.:·i";='~,;,J·U,,;=-;~,'==',='"'='=-='='=='='='2=6='J=~='-=;'='=-,,,='='='=3=0='='='~====r=======T=======;=======II ... --.. -- ... ... 100.00% 42.86% 38.57%
"Weights ofActivities are calculated relative to (Purchasing)
Tuesday, May 17, 2011 Page 16 of 19
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of :30-Apr-11
Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%
30
20
10
12-Feb-12
24-Dec~11 20
17-Jul-l1
09-Jun-l1 10
26-Jun-11 10. .04-Aug-11 20
16-Nov-l1 20
26-Dec-11 30
18-Jul-!1
03-Jan-12 20
12-feb-12 30
17-Mar-l1 10
2a-Mar-It 10.21-Jul-l1 20
.14-0ct-l1 20
23-Dec-l1 30
16-Jan-12
16-Jan-12
Start
VPR finish
VPR start
Fab. Start
SID.Award
Fab. Finish
S/D.Award
VPR start
VPR finish
.... - .. ~ ' .Fab. Finish
....... , -16-Jan-12
17·Jul-l1 10
17-Jul-l1 10
28-Jul-1! 20
03-Jan-12 20
12-Feb-12 30
." Weights of Activities are calculated relative to (Expediting)
Tuesday, May 17, 2011 Page 17 of 19
Layout NO.1
Dala'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of : 30-Apr-11
Dates IMilestone I * Relative I Planned ActualMilestonePlanned Actual Expected! Value Weight Progress% Progress%
Overall
Procurement
0.00%
0.00%
7.35%
7.35%
0.00%
0.00%
1 10.44%
10.29%
10.29%
10.29%
100.00%
10
10
10
10
10
30
05-Jun-11
05-Jun-11
05-Jun-11
01-Nov-11
• ••••••• " ••••• « • ,
18-MaY-11, 10 ,
· 22-Ju~-·11· "- .. 20' - . ;
22-Sep-11: 20 ,• •• " " •• - ,. ••••••• i
· ~ .· ~ :
· _ ,.""."."
18-Apr-11.......
24-Apr-11.......
........: ~ :01-Nov-11 20'
:06-Mar-11
:17-Feb-11
:09-0c1-11
Fab. Start
VPR start
VPR finish
•••••••• x» •• _ •••••••••
Start :17-Feb-11~ ••••••••••••• ",' ••••• 4
....... - - , - - ~ . ',' .. - ...
Electrical bulk material
Start :12-May-11,. - .. ',' .
Fab. Start :12-May-11••••• ». _." -, ..•,.••.•• ",~ •• ~~R"s!a~ y k )~2:~ay-.1~.
S/O.Award :30-Aug-11
~ •• « Fab"Finish • - • " ": 09-0ct-11- -....... " " .. " .. ',' .
Total Expediting
VPR finish "14-Apr-11 ,"-. -SjO.A~rd .. - . '!06~AU~-11- • ~ ..... _. . "14-0d-11- ~ ... 20' . ,
I~~~~~a~!~n~~~~~i~-~i~~~~_~~~_~~~~ ~_~_;;1~:_~~~_L_~ _
* Weights of Activities are calculated relative to (Expediting)
Tuesday, May 17, 2011 Page 18 of 19
layout NO.1
Data'Nes Systems, Release 2_21
Project No.: 4187-440
SETH ONSHORE PROJECTIssuance Status Report
As Of :30-Apr-11
Dates Milestone * Relative Planned ActualMilestonePlanned Actual Expected Value Weight Progress% Progress%
OverallProcurement
Fire detection system 8.33% 0.00% 0.00%
NFl OS-Feb-12 40« ••••••••• « •• . ....... •• « v««.RFS 12-Feb-12 60
Bulk 8.33% 0.00% 0.00%
NFl !19-Dec-11 , 19-Dec-11, 40
.. « .... RFS' « • « ~ ~~J.~~~~~_~~_~:~~~_~_:_~_~2i~~:~~~_~_~.~~?~~: ._" _
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
16.67%
12.50%
12.50%
NFl
NFl
RFS
NFl_ •• ««. _ v.«« __
RFS
Slug Catcher
Instrument I Fire & gas cables
Fire protection system
0.00%
40
60
25-0cl-11 40
16-Dec-11
01-Nov-11 60
21-Nov-11
: 08-0ct-11NFl
Total Inspection
!!11=;;;::;~RF~Sc====d~~~=====~~~±=~====~==;;o:~==;=~===;;o:===;~ Piping valves 8.33% 0.00% 0.00%1'=!6W
III~til ~ .. -RFS' -- T - -« - -j15-o~-;1" ~ ... «« •• -:- 23-6~c~1; - ~«- - 60' -«:PiF~~'''-~,,-=,·-=-=·,,-:==·::;.-=~=-'''--,,~'C--,,·-'''=-=·=·-=-'-=--'~~"-=.-=.,-=,.= .•=-.=.-=",-='=,'".=.•,,-..-,,..-=.-='=.=-..~=-="".-='-=."-=.=..,"-="-=.--=--=-,,-.,,--=.-=--=-'~-.~~=-~-==-~"'~~--~--~-,,-'=-'::c_:=-~-c;-=-=c-~--,,-~--=-~-=-~--=c=",,-:=="""" Electrical bulk material 8.33% 0.00% 0.00%•==illtH NFl : 02-0ct-11 ,II "" ¥ RFS···· ~. a - ·'09-0ct-11"·'·· y v •••
IFC±I"n"st:=ru=m~e"n:=t;:;B=U;;.lk====~~~~<±====""======'====='=======':1"2".5"0:::%""==0"."0"0:::%""==:00".0"0:::.."',=I,-II ~ ... ~~I .••• _ • * _ .: ~O.-?~-~1_ • " ...• ~ •• • .1~-~~V-.1~. • •• ~Oy •.
iii RFS : 17-0ct·11
¥,§Fo\:'='===:7:==:=;;'7==!:::~~=~=========='====='=====;==';;;:;;;:::f===;::;;;:::f==::'::::::""=;§Ii Instrument I Fire & gas Cable Trays 12.50% 0.00% 0.00%
n$WiII ~ . " . ~~I ........•: ~2..C?C:-~1. . ~ ... y ••• _: ••1~-~~V~1~ _ .'. ~o.. _
IIF=,==R=F=s==-=.=-=-=-=-=.,=:~~9.=-O=.ct=:='='.=-<±'=.=_=.=.=.=.=.=.=.=2=3-=N=~=V'=.'='=.====6=0=""'=====;=1~O~O~.O~O~,~y,,==r=O~.O~O~'''y,,==;=O~.~O~O~'I.~,=
* Weights ofActivities are calculated relative to (Inspection)
Tuesday, May 17, 2011 Page 190f19
layout No.1
Data'Nes Systems, Release 2.21
PTB
Egypt
•E:n.PP1SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
7.3. Updated Schedule
4187-440
Rev. (0
18-MAY-2011
4187.440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30·Apr-11Enppl
Slug Catcher Data Sheets
Evaluation (Slug Catcher)
VPR (Slug Catcher)
30
70 20-Mar-11
04-Jan-11
02-Feb-11
28-Jun-11
Page 1 of10
... Actual Work
1_00:';'/";;>:1 Remaining Work
I!iBIIIIIIIl Critical Remaining Work:
• • Milestone
Summary Start Date: 22..Dec-10Finish Date : 26·Feb~12Data Date: 30·Ap....11
Print Date: 16-May-11
Date18-May-11 Rav.O
By: Haytham A.Rahman
Revision CheckedA.Fathy
ApprovedM. Abushanab
'~~-"'-'---
Page 2 of 104187-440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11
HSE philosophy IFD 18 06 M Mar-11 03-Apr-11 A
cause and effect 5 20-Feb-11 31-MarM 11 A 02M MayM 11
Fire 5 03-Apr-11 09-May-11
cause and effect IFC 5 21-Jul-11 27R JulM 11
Com missioning 20M Nov-11 28M JulM 11 03-Aug-11
-Aug-11 10-Aug-11
Hazardous Area Classification IFF 17-Aug-11 11-Aug-11 17-Aug-11
Enppl
Page 3 of 10
01-Aug-11
15-May-1128-Mar-11 A
18-Feb-11 A 24-Feb-11 A24-Mar-11
10-May-11Technical
4187.440, PETROBELSETH ONSHORE DEVELOPMENT PRO~ECTUPDATED SCHEDULE AS OF 30-Apr-11
Fighting System MRQ
Fire Fighting System VPRA1590
A1990
DETECTION AND GAS SYSTEM
10 06 M Mar·11 10M Mar-11
5
A2200 0 20-Mar-11 24-Mar-11 02-May-11 02-May-11
A2240 5 27-Mar-11 31-Mar-11 02-May-11 08-May-11
A2260 Junction Box Interconnecting Wiring Diagram IFD 5 03-Apr-11 07-Apr-11 09-May-11 15-May-11
A1560 P&ID's IFC 20-Jul-11 07-Jul-11 20-Jul-11
A2230 And Alarm Layout DraVllings IFe 10-Aug-11 04-Aug-11
A1570 Fire Fighting Drawings IFe 11-Aug-11
24-Aug-11 18-Aug-1.1 24-Aug-11
A2250 5 25-Aug-11
A2270 5 05-Sep-11 11-Sep-11 11-Sep-11
Enppl
Enppl4187-440, PETROBEL
SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11
5
Page 4 of 10
A3180
20 23-Mar-11 A
03-Aug-ll
A3200
A1630
A3290
Under Ground Piping Standard Details IFD
Under Ground Composite Drawing IFe (Header)
l4-Apr-1l
03-Aug-11
6 ll-Aug-ll 04-Aug-ll
25 04-Aug-l ep-ll 04-Aug-ll
5 05-Sep-ll ll-Sep-ll 05-Sep-ll
ll-Sep-ll
24-Feb-ll
A2330 piping specification IFD 03-Mar-11
A3220 Under Ground Specification
Page 5 of 10
16-May-1130-Mar-11
16-Mar-11
,J'7~"~;:,:i-------- i2;;3':_'Mi~a;r:_;1-11 --I n09Q'-'M,ia~;Y;:-:'1 11 -I-,;;:"i~;;:;
IFe
4187-440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11
Cable Routing IFD
Line Designation Tables JFC
Standard Steel Structure Support List IFC
piping specification dasses IFe
Loop Diagrams
A2360
A2340
A2380
A3230
A3260
A3250
A2450
A2400
Enppl
Enpp l 4187.440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30.Apr-11
Page 6 of 10
A2410
A2440
A2460
Instrument Hook Up And Supporting DrawingsIFD
Aug-11
11-Aug-11
17-Aug-11
24-Aug-11
17-Aug-11
23-Aug-11
--CO"~,:: ------- 'Instrument Index IFD
A2490
A2510
A1970
A2500
Instrument Cable Schedule IFD
Instrument Index [Fe
Drawings
".".. ~.,~,~-~~"~"0 20 R Feb M 11 24~FebM11 02w MaYM 11
5 27-Feb-11 03R MarM 11 02-May-11 08-May-11
5 17~Mar~11 23-Mar~11 09-May-11 15-MaY-11
5 21-Jul-11 27-Jul-11 21-Jul-11
03-Aug-11 03-Aug-11
18-Aug-11
Enppl4187-440, PETROBEL
SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11Page 7 of 10
A2850 Instrument Cable Trays MRQ's
Instrument Cable Trays VPR
AZ860
AZ870
Instrument Trays Evaluation
16-May-1 31-0CI-11
30R Mar-11 16-May 16-May-11
31-May-11 9-Jun-11 06-Ju~11
8-Aug-11 31-0cl-11
A2570 HazardousArea Classification Layout IFD 0 20-Mar-11 28-Apr-l1 A
0 06-Mar-11 10-Mar-11 02-May-11
5 20·Mar-11 24-Mar-11 02-May-11 08-May-11
5 04-Aug-11 10-Aug-11 04-Aug-11 10-Aug-11
w··,'nnnnnmm",_•• ,
IFe 11-Aug-11 11-Aug-11 17-Aug-11
AZ580 Layout [Fe 18-Aug-11 24-Aug-11 18-Aug-11 24-Aug-11
A3310 24-Aug-l1 18-Aug-11
AZ050 30-Apr-11
Page 8 of 10
24-Feb-11 A02-May·1120 1Z·Apr·11
4187-440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Ap....11
support Foundation Drawings
Drawings
Drawings
Bidding
Slug catcher Foundation Drawings IFe
Valves Foundation Drawings JFCAZ6S0
A1790
A2730
A1750
A17S0
AZ670
A1740
Enppl
•.•.... :A;;'l"S:OOOO .. !F~i;;i~,;ti~~lu:Pt:o" 'R"F"S····· ....•........... , ~;~f;,;., ;~:;; ................• ;Z'O"-';D~'e"c'-·'1"1··········· i ··'Z·'Z-'M'·a"'y'- ;1;1 i ;1 'S-;D'e'c'-';1';1 i
Enppl
A1860
A1870
A1880
A3280
4187-440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11
Page 9 of 10
4187.440, PETROBELSETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr·11
II:
Page 10 of 10
03~Nov-11
23-May-11
09-0cl-11
12-May-11
12-May-11
15 19·Apr-11
21
Electrical Bulk Commercial Evaluation Upto POIssuance By PTS
Electrical Bulk Fabrication Upto RFSA1960
A1950
A1940
Enppt
PTB
Egypt
•E:n.PP1SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
7A.Critical and Near CriticalActivities
4187-440
Rev. (0
18-MAY-2011
Commercial Evaluation Upto PO Issuance ByPTS
E.nppl4187-440, PETROBEL
SETH ONSHORE DEVELOPMENT PROJECT CRITICAL ACTIVITIES AS OF 30·Apr-11Page 1 of 2
.... Actual Work
!.;",,+ x,',;, ! Remaining Work
_ Critical Remaining Work
• • Milestone
Summary Start Date: 22·Dec-10Finish Date: 26-Feb-12Data Date: 30-Apr..11
Print Date: 16-May-11
Date
1S·May-11 Rev.O
By: Haytham A.Rahman
Revision Checked
A.Fathy
Approved
M. Abushanab
Enppl4187.440, PETROBEL
SETH ONSHORE DEVELOPMENT PROJECT CRITICAL ACTIVITIES AS OF 30·Apr·11Page 2 of 2
PTB
Egypt
SETII ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
7. S. One Month Look Ahead Report
4187-440
Rev. (0
18-MAY-2011
Project No.: 4187-440
SETH ONSHORE PROJECTLookahead Report
As Of: 30-Apr-11
Forecast Date: 28-May~11
Dates Milestone " Relative Planned ActualMilestone Value Weight Progress% Progress%Planned Expected
Overall
.. - ',' ',' .
Process cause and effect matrix
0.00%
0.00%
0.00%
0.00%
20.00%
20.00%
60.00%
60.00%
60.00%
20.00%
: 60.00%
: 60.00%
4.27%
4.27%
4.27%
4.27%
4.27%
11.11%
40
40
20
19-May-11
18-May-11
12-May-11
07-Apr-11
27-Mar-11
31-Mar-11
Design
Design
Start
Design
1. Evaluation
Fire and gas cause and effect
Fire & gas 110 list
Fire and gas cable routing drawings
Fire and gas cable wiring diagram
Start 08-Apr-11 22-May-11 20
r - - - D';Sig~ - - - - ~ -,' . ;2-AP~-11- -: - 25-M~Y=11- . - . -40 - - -
Fire fighting, safety equipment and safety signs
Start 20-Mar-11 15-May-11 20- - . - _. ." - - . - - - - .Design 24-Mar-11 26-May-11 40
Start 03·Apr-11 16-May-11 20... ~ De~ig~ ..... ',' . Oi-Ap·r.11· -i- "19-M~Y:1; - ... '40' ..
"Weights of Activities are calculated relative to (Process)
Tuesday, May 17, 2011 Page 1 ofS
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTLookahead Report
As Of: 30-Apr-11
Forecast Date: 28-May-11
Dates Milestone * Relative Planned Actual IMilestone Value Weight Progress% Progress%Planned Expected
Overall
Bulk
T. Evaluation
Ppiping Valves
VPR start 27-Feb-11 16-May-11 10
7.89% 65.00% 55.00%
II
II
r
* Weights of Activities are calculated relative to (Piping)
Tuesday, May 17, 2011 Page 2 of 8
layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTLookahead Report
As Of: 30-Apr-11
Forecast Date: 28-May-11
Dates IMilestone * Relative II Planned ActualMilestone
Expected! Value Weight Progress% Progress%Planned
Instrument Cable Schedule 0.00%
0.00%
60.00%
60.00%3.70%
7.41%
3.70%
22-MaY-11 4003-Mar-11
data sheets
Start
Design
Design
Start
Design
Instrument Index
Instrument Hook Up And Supporting Drawings 9.88% 60.00% 0.00%
Start 06-Mar-11 22-May-11 20
~ .. ·6e"Si9~··'· H <, ·10·-M~r-l1· .:. 25~M~Y~11 H'" "40' --
Field Instrument Layouts
Start 06-Mar-11 19-May-11 20
... 6;Si9~···'· .:. '10'-M~r-;1' .:. 26~M~Y~1;···· "40"-
Field Instrument Cable Routing
Star! 10-Mar-11 : 18-May~11
t ••• 6e"sig~ - ... > ":' • ;6·-Ma~r-;1· ·i· 24.M~y~1; •
Junction Box Interconnections
4.94%
3.70%
60.00%
60.00%
0.00%
0.00%
Start 17-Mar·11
Design 23-Mar·11
20
2030·Mar-11 24-May-11. - _ ' ..
l~c~o~m~m~O~d~1~'t~ie~S~====::;======================:=:3:::::===:=:3:::::===::=::='='======II Instrument! Fire & gas cables 19.75% 20.00% 0.00%
ilif@mill MRQ 07-Apr·11 19·May-11
IF=':oln"s"'tru=m"e=n':t"BC'U"lk"'===~"'========"":==:==~==="'='======:=C;=;';;;='='=7~';;;='='=::;==;:';;;='='======;
iiliili M~~~~:~"--:~~~ 24-May-11 x.'-,,-_,-~~~~_.__~,_,_. , ~ ,_. _IF=':oln"sO'tru=m"e"n':t7t"'F;'ir:'e';&C'9ecaC'S=;:cC'a"bC'le"T;:ra=ys==============='=======:="1:;7".2"8"0/<7,=0=';;2"0".0"0"0/<7,=::;==;:0".0"0"%;=::;======:
1illti MRQ'B3E- •••••• _ •
* Weights of Activities are calculated relative to (Instrumentation)
Tuesday, May 17, 2011 Page 3 of 8
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTLookahead Report
As Of: 30~Apr~11
Forecast Date: 28~May~11
Dates Milestone * Relative Planned ActualMilestone Value Weight Progress% Progress%Planned Expected
Overall
Electrical Lighting MRQ
Start
Finish
2Q...Mar~11 2Q...May~11
.. i4-M;r~;1" "i' 24-M~Y:1; .20
80
33.33% 100.00% 0.00%
* Weights of Activities are calculated relative to (Electrical)
Tuesday, May 17, 2011 Page 4 of 8
layout NO.1
Data'Nes Systems, Release 2.21
Project No.: 4187·440
SETH ONSHORE PROJECTLookahead Report
As Of: 30-Apr-11
Forecast Date: 28-May-11
I DatesMilestone I * Relative Planned Actual
Milestone Value Weight Progress% Progress%Planned Expected
50.00%
50.00%
0.00%
50.00%
50.00%
50.00%
60.00%
60.00%
: 50.00%
50.00%
50.00%
50.00%
50.00%
50.00%
50.00%
60.00%
100.00%
100.00%
1.85%
1.85%
1.85%
1.85%
2.78%
1.85%
2.76%
2.78%
8.33%
50
50
40
40
40
18-May-11
18-May-11
24-May-11
24-May-11
13-MaY-11
13-MaY-11
17-Mar-11
17-Mar-11
notes
Finish
Finish
Construction
Finish
Finish
Construction
Construction
Construction
Shim and grouting Specification
Structural steel fabrication Specification
Site preparation, earth work & backfill Specification
Concrete paving Specification
Soil & foundation investigation Specification
Anchor bolts standard details
Paving standard details
Standard connections details
Misc. Steel supports foundation plan & details
Start 20-Mar-11 18-May-11 10- ••• De'sig~ . - ••••.. 24.M~r-;1· r 25-M~Y:1;' .•• ·50' ..
~~~_".....>.--L-"---"-~,,:,,,,--,--~ ~"-""""-"-'- .. .~. . _
Start
Valves foundation plan & details
12-May-11 19-May-11 10~ - - -De·si~~ -' _ •••: •• 2o:.Ma~-;1- - 25-M~Y:1;· .:. - -50-"
11.11% 0.00% 0.00%rf
I* Weights of Activities are calculated relative to (Civil)
Tuesday, May 17, 2011 Page 5 of 8
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTLookahead Report
As Of: 30-Apr-11
Forecast Date: 28-May~11
Dates Milestone I * Relative Planned ActualMilestone
Planned Value Weight Progress% Progress%Expected
Overall
Engineering
Drawings
New slug catcher foundation plan & details 12.96% 60.00% 0.00%
Design 26-Jan-11 23-May-11 50
Misc. Steel supports steel details 11.11% 60.00% 0.00%
Start
Design
Start
Finish
18-Apr-11 18-May-11 10• __ •••• a ••••• _ • •• _ " ••
26-Apr-11 26-May-11 50
05-May-11 19-May-11 20••••• T T _ •••••••• __
1Q..MaY-11 26-May-11 80
;0 Weights of Activities are calculated relative to (Civil)
Tuesday, May 17, 2011 Page 6 of 8
Layout No.1
Data'Nes Systems. Release 2.21
Project No.: 4187·440
SETH ONSHORE PROJECTLookahead Report
As Of : 30~Apr-11
Forecast Date: 28-May-11
Dates Milestone * Relative Planned ActualMilestone Value Weight Progress% Progress%Planned Expected
Electrical bulk material
Instrument I Fire & gas Cable Trays
RFQ 13.Apr-11
9.52%
11.90%
25-May-11 10
40.00%
10.00%
0.00%
0.00%
* Weights ofActivities are calculated relative to (Purchasing)
Tuesday, May 17,2011 Page 7 of 8
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTLookahead Report
As Of: 30-Apr-11
Forecast Date: 28-May-11
Dates Milestone ,., Relative Planned ActualMilestone
Planned Value Weight Progress% Progress'%Expected
OverallProcurement
Commodities
Valves
VPR start 06-Mar-11 10
10.29% 50.00%
• Weights of Activities are calculated relative to (Expediting)
Tuesday, May 17, 2011 Page 8 of8
Layout NO.1
Data'Nes Systems, Release 2.21
PTB
Egypt
•Enpp.J.SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
7.6.Procurement Status.
4187-440
Rev. (0
18-MAY-2011
As of: 18 Mav 2011
PROCUREMENT DIVISIONFOREIGN PURCHASING SECTIONPTB, SETH OFFSHORE DEVELOPMENT PROJECTPROJECT NO.: 4187-440
No. of Bid due date No. ofRevised
Serial Technical Technical commercialCommodity invited and its bidders F.O.ADATE
no.bidders extensions quoted
opening date report date bid duedate
AWARDED TO1 SLUG CATCHER I lOll 112010 1 1111112010 14/02/2011 21102/2011 PTJ
IN 17/03/2011
LCM
2 MANUAL VALVES 8 20112/2010 8 21/12/2010 10/2/2011 17/021201105B Awarded toLVF05C Awarded to
3FIRE & GAS
1 6/3/2011 1 23/03/2011DETECTION
6/3/2011
FIRE FIGHTINGEXT TILL
4 9 14/03/2011 5 28/03/2011SYSTEM
EXT TILL24/03/2011
5/4/20115 PIPING BULK 13 EXT TILL 12 17/04/2011
12/04/2011
PTB, SETH ONSHORE DEVELOPMENT PROJECTProject no.: 4187-440R.F.Q 4187-440Commodity: SLUG CATCHER SETH - 03R.F.Q issuance date: 02/11/2010
TechnicalTechnical
TechnicalRevised
Serial Supplier name Country Bid due dateBidder Technical clarification
clarificationclarification Technical
commercial bid Remarksresponse opening date issuance
due dateactual reply report date
due datedate date
AWARDED IN
I PTJ EGYPT 11/10/20106/1/2011 16/01/2011 16/01/2011
14/02/2011 21102/201117/03/2011 WITH
26/01/2011 01/02/2011 06/02/2011 DELIVERY 9.5 - 11MONTHS F.O.T
PTB, SETH ONSHORE DEVELOPMENT PROJECTProject no.: 4187-440R.F.Q no. 4187-440-SETH - 05Commodity: MANUAL VALVESR.F.Q issuance date: 01112/2010
Bidder TechnicalTechnical Technical Technical
Technical reportRevised
Serial Supplier name Country Bid due date clarification clarification due clarification commercial Remarksresponse opening date
issuance date date actual reply datedate
bid due date
1THARWA
EGYPT Q 9/1/2011 12/1/2011 FOROSABREDA AWARDED TO
13/01/2011 16101/2011 23/01/2011LCMIN
2 TLPR ITALY Q26101/2011 29/01/2011 06102/2011
20104/2011 WITHDELIVERY 18-
3 TRP-PERAR ITALY Q 9/112011 12/1/201 I 23/01/201126wksEXW
FOROSBAWARDED TO
4 DAFRAM ITALY Q 13/01/2011 16101/2011 19/01/2011 LVFIN
1211/2011 1610112011 26101/2011 20/04/2011 WITH5 LVF ITALY 20/12/2010 Q 21/12/2010 26101/2011 29/0112011 07/02/2011 10/212011 17/02/2011 DELIVERY 24-
26wks FOB6 DRV U.S.A Q 1211/2011 16101/2011 FOROSC
AWARDED TO
LCM ITALY Q11/1/2011 15/0112011 16101/2011 QUALIVALIN7
20101/2011 23/0112011 23/01/2011 20/04/2011 WITHDELIVERY 24-
26 EX-
8 QUALIVAL EGYPT Q 6/1/2011 101112011 101112011 FACTORY IN10th of Ramadan
city, Egypt
PTB, SETH ONSHORE DEVELOPMENT PROJECTProject No.: 4187-440SPEC NO.: 00192700 - BMSF - 13205Commodity: SETH - 21 /PIPING BULK MATERIALSR F Q Issuance Date' 22/03/2011
TechnicalTechnical Technical Technical
TechnicalRevised
Serial Supplier name Country Bid due date Bidder responseopening date
clarification clarification due clarificationreport date
commercial Remarksissuance date date actual reply date opening date
1AR
ITALY Quoted 2/5/2011 5/5/2011 3/5/2011TECHNOLOGY
2 HPF UK Quoted 2/5/2011 5/5/2011 10/5/2011
3 FAD ITALY Quoted 2/5/2011 5/5/2011 10/5/2011
4 DYLAN Quoted2/5/2011 5/5/2011 3/5/2011
NL8/5/2011 9/5/2011 9/5/2011
5 CHEROP1PING ITALY Quoted 2/5/2011 5/5/2011 4/5/2011
6 IPS ITALY Quoted 2/5/2011 5/5/2011 8/5/201105/04/2011
7 IGAMM ITALYEXT TILL
Quoted 2/5/2011 5/5/2011 4/5/201112/04/2011 17/04/2011EXT. TILL
Quoted8 TLPR ITALY 14/04/2011 2/5/2011 5/5/2011 5/5/2011
9 EJSW EGYPT Quoted 2/5/2011 5/512011 8/5/2011
10 TUXOR ITALY Regret
11 MINTA EGYPT Quoted 2/5/2011 5/5/2011 9/5/2011
12 FERRARI ITALY Quoted 2/5/2011 5/5/2011 5/5/2011
13 STEEL TRADE ITALY Quoted 2/5/2011 5/5/2011 4/5/2011
PTB, SETH ONSHORE DEVELOPMENT PROJECTProject No.: 4187·440SPEC NO.: 00192700·BISF·24204Commodity: FIRE & GAS DETECTION / SETH· 27R.F.Q Issuance Date: 24/0212011
Bidder TechnicalTechnical Technical Technical
TechnicalRevised
Serial Supplier name Country Bid due date clarification clarification due clarification commercial Remarksresponse opening date
issuance date date actual reply datereport date
opening date
1 FORESENG ITALY 06/03/2011 Q 23/03/20113/4/2011 6/4/2011
11/4/2011ll/5/2011 12/5/2011
PTB, SETH ONSHORE DEVELOPMENT PROJECTProject No.: 4187-440
SPEC NO.:00192700-BMSF-13206Commodity: FIRE FIGHTING SYSTEM SETH - 28R F Q Issuance Date' 24/02/2011..
TechnicalTechnical Technical Technical
TechnicalRevised
Serial Supplier name Country Bid dne date Bidder responseopening date
clarification clarification due clarificationreport date
commercial Remarksissuance date date actual reply date opening date
1 SAFCO ITALY REGRET
2 DETRONICS UAE REGRET
3 EUSEBI ITALY Q5/4/2011 9/4/20 II
10/4/201110/5/2011 12/5/2011
06/03/20114 FORESENG ITALY EXTENDED REGRET 10/5/2011 12/5/2011
TILL
5GENERAL
U.S.A 14/03/2011 REGRET 28/03/2011MONITORS
EXTENDED
6 SILVANI ITALY TILL Q5/4/2011 9/4/20 II
11/4/201124/03/2011 10/5/2011 12/5/2011
7 SANCO ITALY Q5/4/2011 9/4/2011
10/4/201110/5/2011 10/5/2011
8 MINTA EGYPT Q5/4/2011 9/4/20 II
12/4/201 I10/5/201 I 10/5/2011
9 FAS ITALY Q 5/4/2011 9/4/2011 10/4/2011
PTB
Egypt
•E:n.pp.J.SETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
7. 7.Equipment and material status report
4187-440
Rev. (0
18-MAY-2011
I
PROJE.CT COMMITME.NTS STATISTICAL OVERVIEW
STATISTII
COMMITMENTS COUNT:
A.
B.C.
D.
TOTAL NO. OF ISSUED COMMITMENTS:
F.D.C ISSUED.
P.Oo'S ISSUED.
P.Oo'S COMPLETED/RELEASED FOR SHIPMENT
P.Oo'S FOR SERVICES.
P.Oo'S FABRICATION IN PROGRESS.
=
=
4
4
o
oo
4
Enpp!~'i~....r,,1bo~Uw..,••;nu
SETH DEVElOPMENT PROJECT RA5!EL.BAR CONCESSION
SlUG CATCHERPAcKAG,
,ETHOSA
MANUAL VALVES
FROM 9.S MONTH TO11 MONTHS
lB-26WEEKS ,PLUS ONt l~-~6 WEEKS,PLUS ONEEX·WORKS/ITAlV WEEK FO~ AUGUST WEEHORAUGUST
SHUTDOWN SHUTDOWN
'"
REPORT NO. 1
AS Of 28/4/2011
FDA WAS ISSUEOTO PTJ ON 17/3 fOR THE SUPPLY OF ONE SLUGCATCHER PACKAGES, COMPLETE WITllTHE INST~UMENTS, VALVES,INTERCONNECTING PiPiNG SKID AND lOCAL CONTROL PANEl.KOM WAS CONDUCTED ON 4/4/l0U.PTJ suaCONTRACTED I.M.S.• Indu,lric MCe<'ni'he ON ~3/3 S'''doliatoS.p,A.FORTHE OESIGN,SUPPLYOF lOOSE MATERIALS AND MECHANICALGARANTEE FOR THE SLUG CATCHER WITH INTE~PIPING SKID AND LDOSEINSTRUEMENTS AND VALVES ON SSHIPMENTS fROM 21/7 fOR FLANGES,PI PIES AND flnlNGS TILL 20/2/1.012 fOR All VALVES AND CONTROLPANEl.,ENGINEERING DOCUMENTS STARETDTD B, RECEIVED FROM 29/3 ANQ20/4 FoRTHE; VESSElCAlCUAtTlON, PFo, QUAtlT'I PLAN. VDeF.OATASHEET.PROCUREMENT SU~ORDERING IS SCH,OUlEO FROM l/4 Tlll29/4IWAITING FO~ CONFIRMIITIONIFAe~leATION IS EXPECTED fROM 14/9 Fo~ NOULE wonKS TILL1/l/l0U.
FoA WAS ISlum TO SUPPLIER ON 1.0/4/2011 FOR lllTEMS OF MANUALVALVES ITOTAllB VALVE).DRAWINGS APPROVAL IS 10 DAYSE·MAIL WAS SENT TO SUPPlIfR ON ~8/4 TO SUBMIT THEACKNOWLEDGMENT AND ,NGINEE;RING DOCUMENTS AND ORDERSCHEDULE
20-4-2011I
LVF/ITALV
fDA WA5ISSUED TOSUPPUER ON :!OI~/2011 FOR U ITEMS OF MANUALVALVES ITOTAL 36 VAlVEI.
SETH 058 FOB ITALY24·l6 WEEKS FROM 24-l6 WEI'K5 FROM
" "'" '" ,-MAil WAS SENT TO SUPPlIER ON 28/4 TO SUBMIT THEMANUAL VALVES
ACKNOWLEDGMENT AND ENGINEERING DOCUMENTS AND ORDERSCHeDULE
20·4-2011 QUAUVAl/,GYPT
FOA WAS ISSUED TOSU~PtlER ON 20/4/Z011 FORS ITEMS OF MANUALVAlVES{TOTAL ,VALVE)
sF;THOSCE~·WORKS jlOTH Of 24·1.6 WEEKS fROM 24·26 WEEKS fROM
" " "RAMADAN £(;YPT '" '" E'MAll WAS SENTlO SUPPLIER ON 28/4 TO SUBMITrHEMANUAL VAlVES
ACKNOWLEDGMENT AND ENGINEERING DOCUMENTS AND ORD,RSCHEDULE.
PTB
Egypt
•EnppaSETH ONSHORE DEVELOPMENT
MONTHLY PROGRESS REPORT No.2
7. 8.Alert report
4187-440
Rev. (0
18-MAY-2011
IrI
r
Project No.: 4187-440
SETH ONSHORE PROJECTAlert I Delay Report
As Of : 30-Apr-11
Dates IMilestone J * Relative I i Planned. 1 Actual WeightedMilestone
Expected! Value Weight Progress% Progress% DelayPlanned
Anchor bolts standard details
24-May-11 40-"--...--........--'---"-~-"---"---"---"-------------_._----_._-------------_._----
1.48%
1.11%
60.00%
60.00%
100.00%
100.00%2.78%
40
3.70%
24-May-1117-Mar-11Construction
Construction
Structural general notes
Paving standard details 2.78% 100.00% 60.00% 1.11%
Standard connections details 2.78% 100.00% 60.00% 1.11%
Start 20-Mar-11 19..May-11 10.. ~ . - . . . . . .. . ~. . .Design 24-Mar-11 25-May-11 50
New slug catcher foundation plan & details 7.78%
5.00%
0.00%
0.00%
0.00% : 6.67%
60.00%
60.00%
60.00%
8.33%
12.96%
11.11%
10OS-Jun-11
17-Mar-11Construction
Start
Misc. steel supports foundation plan & details
Misc. steel supports steel details
Start 18~Apr-11 18-May-11 10- - - - - ••••••••••••••• - • < ••••••••• " " ••••
Design 26-Apr-11 26-May-11 50
* Weights of Activities are calculated relative to (Civil)
Tuesday, May 17, 2011 Page 5 of7
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTAlert I Delay Report
As Of : 30-Apr-11
I Dates IMilestone I * Relative Planned I J Actual WeightedMilestone
Planned Expected I Value Weight Progress% Progress% Delay
RFQ 28-Mar-11 OZ-Jun-11 10" - .......... - - - - - . - . ~ ~ ..... - - - - - ......
Ree.Bids 18-Apr-11 02-Jun-11 30
Instrument Bulk 11.90% 10.00% 0.00% 1.19%
RFQ 11-Apr-11 26-Jun-11 10
Instrument I Fire & gas Cable Trays 11.90% 10.00% 0.00% 1.19%
RFQ 13-Apr-11 25-May-11 10..
Instrument I Fire & gas cables
RFQ
Electrical bulk material
11-Apr-11 02-Jun-11 10
9.52%
9.52%
10.00%
40.00%
0.00%
0.00%
0.95%
3.81%
• Weights of Activities are calculated relative to (Purchasing)
Tuesday, May 17, 2011 Page6of7
layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTAlert I Delay Report
As Of : 30·Apr·11
Dates Milestone * Relative IPlanned Actual WeightedMilestone Value Weight Progress% Progress% DelayPlanned Expected
OverallProcurement
VPR start
VPR finish
06-Mar-11
14-Apr-11
18-May-11
22-Jun-11
10
20
10.29% 50.00% 20.00% 3.09%
!
I
.. Weights of Activities are calculated relative to (Expediting)
Tuesday, May 17, 2011 Page 7 of 7
Layout No.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTAlert I Delay Report
As Of : 30-Apr-11
Dates Milestone I I '" Relative Planned Actual WeightedMilestone Value Weight Progress% Progress% DelayPlanned Expected
Start 08-Apr-11 ,22-May-11 20"_. De~ig~ ••••• ', •• 1i-Ap'r-11- -,- 25-M~Y~1;··· A "40""
Process cause and effect matrix 1.71%
2.56%
2.56%
0.00%
20.00%: 1.71 %60.00%
60.00% : 20.00%
60.00%
60.00% 0.00%
4.27%
4.27%
4.27%
40
20
4.27%
12-May-11
07-Apr-11
27-Mar-11
24-Feb-11 16-MaY-11 40---"--"----"_"-".'-.....L......."'-....._ ......-"-,~'~_"--'-"-,"--'-"......:.....................
1/0 list
Design
Design
Start
Fire and gas cause and effect
Fire &
Fire and gas cable routing drawings
Fire and gas cable wiring diagram 4.27% 60.00% 0.00% 2_56%
Fire fighting, safety equipment and safety signs
•••• :t~rt". " " ••••: •• ?~-~P!-~1••i. ;~~~Y:1~.Design '07-Apr-11 ' 19-May-11
0.00% : 2.56%60.00%4.27%
15-May-11 20.. "". - - _ .26-May-11 40
20-Mar-11
24-Mar-11
Start
Design
* Weights of Activities are calculated relative to (Process)
Tuesday, May 17, 2011 Page 1 of7
Layout NO.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTAlert I Delay Report
As Of : 30-Apr-11
Dates Milestone * Relative Planned Actual WeightedMilestone Value Weight Progress% Progress% DelayPlanned Expected
OverallEngineering
Ppiping Valves
VPR start 27-Feb-11 16-May-11 10
7.89% 65.00% 55.00% 0.79%
* Weights of Activities are calculated relative to {Piping)
Tuesday, May 17, 2011 Page 2 of?
layout NO.1
Data'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTAlert I Delay Report
As Of : 30-Apr-11
Dates Milestone * Relative Planned Actual WeightedMilestone Value Weight Progress% Progress% DelayPlanned Expected
4.44%
2.96%0.00%
0.00%
60.00%
60.00%
4.94%
7.41%Instrument Index
Instrument Cable Schedule 3.70%
Start
3.70% 60.00% 20.00% 1.48%
Design 03-Mar-11 22·May·11 40..
Instrument Hook Up And Supporting Drawings 9.88% 60.00% 0.00% 5.93%
Field Instrument Layouts
Start . 06~Mar·11 i 22-May-11 20
" " - - De~i~~ .. » H • H;' • 10·.Ma"r-11" "i' i5-M~Y=1; .... "40 - - "
Start ,06-Mar-11 ! 19-May-11 20
r " - - 6e~i~~ ... H • ":' • 10·-M';r-11" r 26-M~Y=1; .... "40 - . "
Start ,20-Feb-11 15-May·11: 20
~~~~:~?~~~~~~£Feb.;1» ":' ;8-0~Y:1~ ~ :i :_~:~~~~_:__~~__~~.__."~._". _
Field Instrument Cable Routing 3.70% 60.00% 0.00% 2.22%
•••••• _. _ •• - - - _.". - - - .,_ ••••••• A,A A •••••
Design 23-Mar-11 : 26-May-11 40
Junction Box Interconnections 2.96%0.00%60.00%4.94%
2025-May-1117-Mar-11Start
Start
Design
30-Mar-11MRQ
~l",c;o~m;m;;;O;d;i;ti~e~s=.=::;:===;:=;:===================::::==::::;===========:::== =::====:::==~:::::;;=.=:::;;Ifi Instru:::tI Fire & gas ca:~_:P'_11 19.May-11 20 19.75% 20.00% 0.00% 3.95%
I F"I"n"'struO=m""e"n"t=B"'U:'lk=:="'=:-=~:=·~""=··"""'=:=:=""'=~"~"·~""C:C=:=""=c.=-=-="",,~~~=--~~~=-~~=:~1=7-=;.~2':'8"':'%:'-==-=-="':2"':'0-=.O:'0':%7==~~'--~0=.0='-;;-=""l\==~-==3-=.~4':'6"':'~l\""~-=;·
$1! F""="",M"R=Q"""'=:""'""",7'""",~~,,,""=~=--3,,0=.M,,="',,-~,,,'...~,,,,,2=4-,,,M,,a=y,,-""="==",2"0",,,.~,,,,.~=_=_==~=_=_=-=-=-=__=:_::,:7'=.-=-=-=_=-=-7'._""'_7'~_=.~-'--=-=O-""'~~=-=7~"7,,"=-=;= Instrument! Fire & gas Cable Trays 17.28% 20.00%: 0.00% 3.46%
~=mm
* Weights ofActivities are calculated relative to (Instrumentation)
Tuesday, May 17, 2011 Page30f7
layout NO.1
Dala'Nes Systems, Release 2.21
Project No.: 4187-440
SETH ONSHORE PROJECTAlert I Delay Report
As Of : 30-Apr-11
Dates Milestone I * Relative II Planned DI Actual IWeightedMilestone Value Weight Progress% Progress% DelayPlanned Expected
Overall
Electrical Lighting MRQ
Start
Finish
20-Mar-11 2o-May-11 20.. "." .24-May-11 80
33.33% 100.00% 0.00% 33.33%
* Weights of Activities are calculated relative to (Electrical)