Monthly Progress Report March-17 (P04B)
ODISHA WORKS DEPARTMENT
Page 1 of 35
CHAPTER 1. EXECUTIVE SUMMARY ...................................................................................... 3
1.1 PROJECT BACKGROUND .............................................................................................. 3 1.2 THE PROJECT ................................................................................................................ 3 1.3 CONTRACT MANAGEMENT FRAME WORK .................................................................. 4 1.4 PROJECT DETAILS ......................................................................................................... 5 1.5 SALIENT FEATURES ...................................................................................................... 5 1.6 MILESTONES .................................................................................................................. 6
CHAPTER 2. PHYSICAL PERFORMANCE AND PROGRAMME OF WORK ............................ 7
2.1 ROAD WORK ................................................................................................................... 7 2.2 PROGRESS OF CD WORKS AND STRUCTURE ......................................................... 10 2.3 SECTION WISE ACHIEVEMENT ................................................................................... 11 2.4 ROUTINE MAINTENANCE ............................................................................................ 19 2.5 PROGRAMME OF WORK.............................................................................................. 19 2.6 FORECAST FOR NEXT MONTH ................................................................................... 20 2.7 STATUS OF EXTENSION OF TIME .............................................................................. 21
CHAPTER 3. FINANCIAL PERFORMANCE ............................................................................ 22
3.1 FINACIAL PROGRESS .................................................................................................. 22 3.2 MONTH WISE FINANCIALPROGRESS......................................................................... 22 3.3 MOBILIZATION ADVANCE ............................................................................................ 23 3.4 STATEMENT OF IPC ..................................................................................................... 24
CHAPTER 4. STATUS OF RISK .............................................................................................. 25
4.1 HANDING OVER OF SECTION ..................................................................................... 25 4.2 STATUS OF UTILITY SHIFTING.................................................................................... 25 4.3 ANY OTHER ISSUE ....................................................................................................... 25 4.4 RISK INVOLVED ............................................................................................................ 25
CHAPTER 5. ENVIRONMENTAL MONITORING AND SAFETY ............................................. 26
5.1 ENVIRONMENT MANAGEMENT PLAN ........................................................................ 26 5.2 ROAD SAFETY .............................................................................................................. 27
CHAPTER 6. VARIATION AND CHANGES ............................................................................. 28
6.1 SUMMARY OF CHANGE ORDER ................................................................................. 28
CHAPTER 7. QUALITY CONTROL AND QUALITY ASSURANCE ........................................ 30
7.1 TESTS CONDUCTED .................................................................................................... 30
CHAPTER 8. MOBILISATION .................................................................................................. 31
8.1 CONSULTANT’S TEAM ................................................................................................. 31 8.2 CONTRACTOR’S TEAM ................................................................................................ 31 8.3 STATUS OF PLANT AND EQUIPMENT OF CONTRACTOR ......................................... 32
Monthly Progress Report March-17 (P04B)
ODISHA WORKS DEPARTMENT
Page 2 of 35
CHAPTER 9. VISITS AND MEETINGS .................................................................................... 33
CHAPTER 10. IMPORTANT CORRESPONDENCE DURING THE MONTH .............................. 34
10.1 SUBMISSIONS AND APPROVALS ................................................................................ 34 10.2 CORRESPONDENCES ................................................................................................. 34
CHAPTER 11. WEATHER DURING THE MONTH ..................................................................... 35
LIST OF APENDICES
Appendix 1– Strip Chart of Highways
Appendix 2– Strip Chart of Bridges& Box culverts
Appendix 3 – Strip Chart of Structures (HPC)
Appendix 4– List of GFC Drawings Issued
Appendix 5– S curve
Appendix 6– Correspondence
Page 3 of 35
Chapter 1. Executive Summary
1.1 PROJECT BACKGROUND
The Odisha Works Department (OWD) has a medium to long-term comprehensive programme to rehabilitate, upgrade and expand the road network throughout the state to improve accessibility, connectivity and enhance the overall development. It is the pre-eminent state level road authority in Odisha which deals with issues relating to Feasibility Study and preparation of Detailed Project Report including the Route Selection, even for relatively low volume roads.
The Government of Odisha has secured a loan from International Bank for Reconstruction and Development (The World Bank) towards the cost of Widening and Strengthening of existing Jagatpur- Chandbali Road Project (106 km).
Jagatpur-Chandbali Road Project is part of 825 km of roads under Phase-I which aims at promoting trade and regional integration between districts by improving transport communication. The project road Jagatpur-Chandbali is a part of the Phase-I road development, which was built several years ago with two lane configuration and currently serves moderate level of traffic. The project involves widening of the existing road which has an average carriageway width of 5.5 m to 6.8 m and 1.5m. Earthen shoulder on both sides, to a 7.0 m carriageway and 2.5m shoulders on both sides in flat and rolling sections. The expected outcome of the project include reduced transportation time of goods and better connectivity between districts along with improved safety standards; reduced transit time for import and export goods via port
The Jagatpur-Chandbali road was divided into two Packages for the purpose of improvement.1st package from Jagatpur to Duhuria and 2nd package from Duhuria to Chandbali. After termination of the Contract of 1st package, it is divided into two packages, viz., Jagatpur to Nischintakoli (P04A1) and Nischintakoli to Duhuria (P04A2). 3rd package is from Duhuria to Chandbali (P04B)
1.2 THE PROJECT
The Duhuria – Chandbali (SH9A) section km 49/00 to km 99/00 and (SH9) km 45/00 to km 51/500 which is a part of Jagatpur - Kendrapada – Chandbali - Bhadrak 152 km project corridor. The road section Duhuria – Chandabali starts from at Chainage km 49/00 and ends at Duhuria. Jagatpur is industrial area in Cuttack district, Kendrapada is districts’ headquarter of Kendrapara district. There are in total 14 numbers of major and minor bridges in Duhuria – Chandbali section. Along the project road there are in total 167 existing culverts and 36 reptile passes between Duhuria – Chandbali section. About 21% of the road length passes through built up area.
The total length of the project road is 56.500 Km. the road passes completely through plain terrain. Major stretch of the road is located in the District of Kendrapara. This stretch passes through major human settlements at Kendrapara.
Monthly Progress Report March-17 (P04B)
ODISHA WORKS DEPARTMENT
Page 4 of 35
The location map of the project road is shown below in Figure 1-1;
Figure 1-1: Location Map
1.3 CONTRACT MANAGEMENT FRAME WORK
1.3.1 Employer
Mr. Om Prakash Patel, Chief Engineer, DPI & Roads, Odisha On behalf of Works Department, Government of Odisha
1.3.2 Employer’s Representative
Mr. B C Dash, Employer’s representative-cum-Superintending Engineer, Cuttack, R&B Circle.
1.3.3 Engineer
Mr. Dinakar Mondal, Resident Engineer Lea Associates South Asia Pvt. Ltd B1/E-27, Mohan Co Operative Industrial Estate Mathura Road, New Delhi-110 044 Site Office-Near NH-5A Underpass, Duhuria, P.O.-Pandiri, District – Kendrapara, Odisha, Pin – 754211 Email: [email protected]
1.3.4 Contractor
M/S. DPJ-NKC(JV), HO: Plot No-63, Phase –IV,UdyogVihar,Gurgaon-122016(Harayana) Project Manager – Mr. Virendra Pal Singh Site Office –Plot No.-28-35, Vill: Pohala, Dist-Kendrapara, Pin-754211, Odisha
Monthly Progress Report March-17 (P04B)
ODISHA WORKS DEPARTMENT
Page 5 of 35
1.4 PROJECT DETAILS
Contract Value Rs.170,42,73,538
Period of Construction :– 27 months
Date of Commencement of Work :– 04th December 2013
Scheduled Date of Completion :- 03rd March 2016
Revised Date of Completion:- 07th July.2018
Progress Achieved till this month :- 30.51%
1.5 SALIENT FEATURES
1.5.1 Highways
Total Length of Project Corridor (MDR + SH 09) – 56.50km MDR 50.00km SH 09 6.50km
Type of Carriageway Flexible 44.750km Rigid 11.750 km
Roadway Width 12 m Carriageway Width 10 m (Revised from 7 m) Bus Bays and Bus Shelter 38 Nos Toll Plaza Nil Junctions 119 Nos
1.5.2 Structures
Minor Bridges 08 Nos Rehabilitation & Widening Bridges 06 Nos Cattle Underpass 07 Nos Box Culverts 06 Nos Hume Pipe Culvert s 166 Nos
1.5.3 Crust Details
Flexible Pavement Sub-Grade 500 mm
GSB 200 mm WMM 250 mm DBM 50mm BC 40 mm
Rigid Pavement Sub-grade 500 mm
GSB 150 mm DLC 150 mm PQC 300 mm
Monthly Progress Report March-17 (P04B)
ODISHA WORKS DEPARTMENT
Page 6 of 35
1.6 MILESTONES
The project corridor has been divided into four sections for completion of work. Details of Sections are furnished below.
Section-I: Total Length 16.100 Km
From Km 58+600 To Km 62+800 & From Km 63+600 to Km 65+400, From Km 66+200 to Km 67+500,From Km 73+000 to Km 74+000, From Km 75+000 to Km 77+600, & From Km 78+100 to Km 83+300.
Section-II : Total Length 11.800 Km
From Km 55+000 to Km 58+600, From Km 62+800 to Km 63+600, From Km 65+400 to Km 66+200, From Km 86+300 to Km 91+000, From Km 91+600 to Km 93+500.
Section-III(Revised) :Total Length 16.000 Km
From Km 49+000 to Km 55+000, From Km 74+000 to Km 75+000, From Km 77+600 to Km 78+100, From Km 83+300 to Km 86+300.From km 93+500 to km 99+000.
Section-IV(Revised) :Total Length 12.600 Km
From Km 67+500 to Km 73+000, From Km 91+000 to Km 91+600,From Km 45+000 to Km 51+500 of SH-9A.
All the above sections have been rescheduled as follows
Section Name Length of Section Stretch of the Section
Section-I 16.1 km Between Duhuria to Pattamundai i.e.
Km.49.000 to Km.69.000
Section-II 11.8 km Anywhere in project corridor
Section-III 15.5 km Anywhere in project corridor
Section-IV 13.1 km Anywhere in project corridor
Page 7 of 35
Chapter 2. Physical Performance and Programme of Work 2.1 ROAD WORK
2.1.1 Linear Progress – Total Length- 56.50 km
Project Length - 56.5 Km, Flexible - 44.75 km , Rigid- 11.75 Km
Sl. No. Description of Item Side
Total Length in Km
Length completed /in Progress in Lane Km. Length Completed Over full
Width (Km)
Completed upto
previous Month
Completed during the
Month Total
Completed In progress Cumulative
length (completed + in progress)
Balance length to be taken
up A B C D E F G=E+F H I=G+H J=D-I K
1 Embankment /Excavation
LHS 56.500 17.153 1.710 18.863 10.530 29.393 27.107 10.050
RHS 56.500 15.740 3.160 18.900 10.720 29.620 26.880
2 Subgrade LHS 56.500 17.083 1.410 18.493 1.147 19.640 36.860
8.910 RHS 56.500 11.490 2.690 14.180 0.380 14.560 41.940
3 GSB LHS 56.500 14.150 0.870 15.020 15.020 41.480
8.910 RHS 56.500 10.370 2.715 13.085 13.085 43.415
4 WMM LHS 44.750 9.345 0.610 9.955 9.955 34.795
6.110 RHS 44.750 6.368 2.831 9.199 9.199 35.551
5 DBM LHS 44.750 9.295 0.620 9.915 9.915 34.835
5.910 RHS 44.750 6.358 2.724 9.082 9.082 35.668
6 BC LHS 44.750 44.750
RHS 44.750 44.750
7 DLC LHS 11.750 4.154 0.280 4.434 4.434 7.316
2.050 RHS 11.750 3.134 0.623 3.757 3.757 7.993
8 PQC LHS 11.750 3.810 0.255 4.065 4.065 7.685
2.050 RHS 11.750 3.088 0.610 3.698 3.698 8.052
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 8 of 35
2.1.2 Progress in Quantities
Pie chart showing the weight age of major items of construction is shown in Figure 2-1;
Figure 2-1: Weight age of Major Construction Items
Site Clearance0%Earthwork
18%
GSB8%
WMM8%
DBM9%
BC8%
DLC3%
PQC11%
Culverts7%
Major/Minor Bridges7%
Road Safety & Amenities6%
Protective Work11%
Repair 2%
EMM2%
Dayworks0%
Other21%
Project Details
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 9 of 35
Progress in Quantities
Sl. No.
Description
Unit
BOQ Qty
Total Quantity Executed as per BOQ
Remark Executed Quantity up to
previous Month
Executed Quantity During
this month Total Quantity
executed Balance Quantity
1 Emb. in Soil Cum 194689 63643 4142 67785 126904
2 Emb.in Sand Cum 433394 306438 25685 332123 101271
3 Subgrade Cum 385595 84646 11326 95972 289623
4 GSB Cum 128267 31193 5020 36213 92054
5 WMM Cum 91126 21031 4393 25424 65702
6 DBM Cum 18056 3900 789 4689 13367
7 BC Cum 14008 0 0 14008
8 DLC Cum 17083 6397 1125 7522 9561
9 PQC Cum 34165 11970 2276 14246 19919
10 PCC M15 Cum 13851 4107 195 4302 9549 11 PCC M 20 Cum 13220 667 614 1281 11939 12 PCC M 25 Cum 643 0 18 18 625 13 PCC M 30 Cum 938 0 0 938 14 PCC M 35 Cum 5036 592 282 874 4162 15 Saucer Drain LM 21000 3507 10 3517 17483
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 10 of 35
2.2 PROGRESS OF CD WORKS AND STRUCTURE
Sl. No. Structure Type
Total Nos. to
be Executed
Side
Completed & In Progress Number
Completed over full
width.(No)
Complete upto
Previous Month
Complete During Month
Complete up to date
IN progress
Cumulative Number
(completed + in progress)
Balance Number to be
taken up
A B C D E F G=E+F H I=G+H J=C-I K
1 Minor Bridge 8 LHS 1 1 5 6 2
1 8 RHS 1 1 5 6 2
2 Rehabilitation & Widening
6 LHS 6
6 RHS 6
3 Box Culvert/Cattle underpass
14 LHS 6 0 6 0 6 8 6
14 RHS 6 0 6 0 6 8
4 HP Culvert 166 LHS 95 2 97 5 102 64
82 166 RHS 87 6 93 6 99 67
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 11 of 35
2.3 SECTION WISE ACHIEVEMENT
A) Road Works MS-I – 16.100 Km.(Flexible-16.1 Km ) ( Km. 58.600 to Km. 62.800, 63.600 to 65.400, 66.200 to 67.500, 73.000 to 74.000, 75.000 to 77.600 & 78.100
to 83.300)
Sl. No. Description of Item Side
Total Length in Km
Length completed /in Progress in Lane Km. Length Completed Over full
Width (Km)
Completed upto
previous Month
Completed during the
Month Total
Completed In progress Cumulative
length (completed + in progress)
Balance length to be taken
up A B C D E F G=E+F H I=G+H J=D-I K
1 Embankment /Excavation
LHS 16.100 7.390 0.720 8.110 6.100 14.210 1.890 4.520
RHS 16.100 8.210 0.930 9.140 6.570 15.710 0.390
2 Subgrade LHS 16.100 7.390 0.720 8.110 0.440 8.550 7.550
4.520 RHS 16.100 5.990 0.930 6.920 6.920 9.180
3 GSB LHS 16.100 6.270 0.280 6.550 6.550 9.550
4.520 RHS 16.100 5.430 0.930 6.360 6.360 9.740
4 WMM LHS 16.100 5.760 0.280 6.040 6.040 10.060
4.520 RHS 16.100 5.000 1.170 6.170 6.170 9.930
5 DBM LHS 16.100 5.740 0.280 6.020 6.020 10.080
4.520 RHS 16.100 4.990 0.860 5.850 5.850 10.250
6 BC LHS 16.100 16.100
RHS 16.100 16.100
7 DLC LHS
RHS
8 PQC LHS
RHS
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 12 of 35
MS-II – 11.800 Km (Flexible-9.8 Km & Rigid -2.350 Km ) (Km. 55.000 to Km. 58.000, 62.800 to 63.600, 65.400 to 66.2000, 86.300 to 91.000 & 91.600 to 93.500)
Sl. No. Description of Item Side
Total Length in Km
Length completed /in Progress in Lane Km. Length Completed Over full
Width (Km)
Completed upto
previous Month
Completed during the
Month Total
Completed In progress Cumulative
length (completed + in progress)
Balance length to be taken
up A B C D E F G=E+F H I=G+H J=D-I K
1 Embankment /Excavation
LHS 11.800 5.293 0.180 5.473 3.280 8.753 3.047 3.590
RHS 11.800 5.520 1.090 6.610 2.050 8.660 3.140
2 Subgrade LHS 11.800 5.293 5.293 0.647 5.940 5.860
3.590 RHS 11.800 3.560 1.090 4.650 0.380 5.030 6.770
3 GSB LHS 11.800 5.293 5.883 5.883 5.917
3.590 RHS 11.800 3.560 1.115 4.030 4.030 7.770
4 WMM LHS 9.450 1.925 1.925 1.925 7.525
1.390 RHS 9.450 1.091 1.141 2.232 2.232 7.218
5 DBM LHS 9.450 1.925 1.925 1.925 7.525
1.190 RHS 9.450 1.091 1.364 2.455 2.455 6.995
6 BC LHS 9.450 9.450
RHS 9.450 9.450
7 DLC LHS 2.350 2.120 2.120 2.120 0.230
2.050 RHS 2.350 2.059 0.053 2.112 2.112 0.238
8 PQC LHS 2.350 2.117 2.117 2.117 0.233
2.050 RHS 2.350 2.053 0.050 2.103 2.103 0.247
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 13 of 35
MS-III – 16.00 km (Flexible -9.75 Km & Rigid -6.25 Km) (Km 49.000 to Km 55.000, Km 74.000 to Km 75.000,Km 77.600 to Km 78.100,Km 83.300 to Km 86.300,km 93.500 to km 99.000)
Sl. No. Description of Item Side
Total Length in Km
Length completed /in Progress in Lane Km. Length Completed Over full
Width (Km)
Completed upto
previous Month
Completed during the
Month Total
Completed In progress Cumulative
length (completed + in progress)
Balance length to
be taken up
A B C D E F G=E+F H I=G+H J=D-I K
1 Embankment /Excavation
LHS 16.000 3.240 0.590 3.830 0.950 4.780 11.220 1.940
RHS 16.000 2.010 0.470 2.480 1.900 4.380 11.620
2 Subgrade LHS 16.000 3.220 0.590 3.810 0.060 3.870 12.130
0.800 RHS 16.000 1.940 0.470 2.410 2.410 13.590
3 GSB LHS 16.000 1.407 0.590 1.997 1.997 14.003
0.800 RHS 16.000 1.380 0.470 1.850 1.850 14.150
4 WMM LHS 9.750 0.480 0.330 0.810 0.810 8.940
0.200 RHS 9.750 0.277 0.220 0.497 0.497 9.253
5 DBM LHS 9.750 0.470 0.340 0.810 0.810 8.940
0.200 RHS 9.750 0.277 0.200 0.477 0.477 9.273
6 BC LHS 9.750 9.750
RHS 9.750 9.750
7 DLC LHS 6.250 2.034 0.280 2.314 2.314 3.936
RHS 6.250 1.075 0.570 1.645 1.645 4.605
8 PQC LHS 6.250 1.693 0.255 1.948 1.948 4.302
RHS 6.250 1.035 0.560 1.595 1.595 4.655
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 14 of 35
MS-IV – 12.600 Km (Flexible -9.4 Km & Rigid 3.2 km) (Km 67.500 to Km 73.000,Km 91.000 to Km 91.600,Km 45.000 to Km 51.500 of SH-9A,)
Sl. No. Description of Item Side
Total Length in Km
Length completed /in Progress in Lane Km. Length Completed Over full
Width
Completed upto
previous Month
Completed during the
Month Total
Completed In progress Cumulative
length (completed + in progress)
Balance length to
be taken up
A B C D E F G=E+F H I=G+H J=D-I K
1 Embankment /Excavation
LHS 12.600 1.230 0.220 1.450 0.200 1.650 10.950
RHS 12.600 0.670 0.670 0.200 0.870 11.730
2 Subgrade LHS 12.600 1.180 0.100 1.280 1.280 11.320
RHS 12.600 0.200 0.200 0.200 12.400
3 GSB LHS 12.600 1.180 1.180 1.180 11.420
RHS 12.600 0.200 0.200 0.200 12.400
4 WMM LHS 9.400 1.180 1.180 1.180 8.220
RHS 9.400 0.300 0.300 0.300 9.100
5 DBM LHS 9.400 1.160 1.160 1.160 8.240
RHS 9.400 0.300 0.300 0.300 9.100
6 BC LHS 9.400 9.400
RHS 9.400 9.400
7 DLC LHS 3.200 3.200
RHS 3.200 3.200
8 PQC LHS 3.200 3.200
RHS 3.200 3.200
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 15 of 35
GSB laying at Ch. 49+600 to 49+800 (RHS) DBM laying at Ch. 54+500 to 55+090 (LHS)
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 16 of 35
MS-I – 16.100 Km.(Flexible-16.1 Km ) ( Km. 58.600 to Km. 62.800, 63.600 to 65.400, 66.200 to 67.500, 73.000 to 74.000, 75.000 to 77.600 & 78.100 to 83.300)
Sl. No. Structure Type
Total Nos. to
be Executed
Side
Completed & In Progress Number Completed
over full width.(No)
Complete upto Previous
Month
Complete During Month
Complete up to date
IN progress
Cumulative Number
(completed + in progress)
Balance Number to be
taken up A B C D E F G=E+F H I=G+H J=C-I K
1 Minor Bridge 3 LHS 1 1 2 3 0 1 3 RHS 1 1 2 3 0
2 Rehabilitation & Widening 1 LHS 1 1 RHS 1
3 Box Culvert/Cattle underpass
2 LHS 2 2 2 0 2 2 RHS 2 2 2 0
4 HP Culvert 61 LHS 46 47 3 50 11 42 61 RHS 45 6 51 1 52 9
MS-II – 11.800 Km (Flexible-9.8 Km & Rigid -2.350 Km ) (Km. 55.000 to Km. 58.000, 62.800 to 63.600, 65.400 to 66.2000, 86.300 to 91.000 & 91.600 to 93.500)
Sl. No. Structure Type
Total Nos. to
be Execute
d
Side
Completed & In Progress Number
Completed over full
width.(No)
Complete up to Previous
Month
Complete During Month
Complete up to date
IN progress
Cumulative Number
(completed + in progress)
Balance Number to be
taken up
A B C D E F G=E+F H I=G+H J=C-I K
1 Minor Bridge 1 LHS 1 1 RHS 1
2 Rehabilitation & Widening 1 LHS 1 1 RHS 1
3 Box Culvert/Cattle underpass
4 LHS 3 0 3 0 3 1 3 4 RHS 3 0 3 0 3 1
4 HP Culvert 36 LHS 20 0 20 20 16 16 36 RHS 16 0 16 3 19 17
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 17 of 35
MS-III – 16.00 km (Flexible -9.75 Km & Rigid -6.25 Km) (Km 49.000 to Km 55.000, Km 74.000 to Km 75.000,Km 77.600 to Km 78.100,Km 83.300 to Km 86.300,km 93.500 to km 99.000)
Sl. No. Structure Type
Total Nos. to
be Executed
Side
Completed & In Progress Number
Completed over full
width.(No)
Complete up to
Previous Month
Complete During Month
Complete up to date
IN progress
Cumulative Number
(completed + in progress)
Balance Number to be
taken up
A B C D E F G=E+F H I=G+H J=C-I K
1 Minor Bridge LHS RHS
2 Rehabilitation & Widening 2 LHS 2 2 RHS 2
3 Box Culvert/Cattle underpass
5 LHS 1 0 1 0 1 4 1 5 RHS 1 0 1 0 1 4
4 HP Culvert 37 LHS 14 1 15 0 15 22 14 37 RHS 14 0 14 1 15 22
MS-IV – 12.600 Km (Flexible -9.4 Km & Rigid 3.2 km) (Km 67.500 to Km 73.000,Km 91.000 to Km 91.600,Km 45.000 to Km 51.500 of SH-9A,)
Sl. No. Structure Type
Total Nos. to
be Executed
Side
Completed & In Progress Number
Completed over full
width.(No)
Complete up to
Previous Month
Complete During Month
Complete up to date
IN progress
Cumulative Number
(completed + in progress)
Balance Number to be
taken up
A B C D E F G=E+F H I=G+H J=C-I K
1 Minor Bridge 4 LHS 3 3 1 4 RHS 3 3 1
2 Rehabilitation & Widening 2 LHS 2 2 RHS 2
3 Box Culvert/Cattle underpass
3 LHS 3 3 RHS 3
4 HP Culvert 32 LHS 15 0 15 2 17 15 10 32 RHS 12 0 12 1 13 19
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 18 of 35
Minor Bridge Raft concreting at Ch. 69+727 Pipe laying Ch.64+162 (LHS)
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 19 of 35
2.4 ROUTINE MAINTENANCE
As per Contract, the Contractor is required to maintain the portion of road which has been handed over to him. The balance portion is to be maintained by OWD divisions till it is handed over to the Contractor. At the time of handing over, the condition of road was very bad. Hence the contractor executed routine maintenance works for which payment was made. The Contractor is doing pothole repair works as per requirement assessed jointly as payable item.
2.5 PROGRAMME OF WORK
Contractor has submitted baseline work program though e-mail dated 14.04.14 for completion by 3rd March 2016, the same was approved by Engineer. The contractor has not submitted the revised programme for completion so far.
A chart showing the time elapsed is given bellowing
Figure 2-2.
Figure 2-2:
Total Duration of the Project (Construction Phase) - 820 Days (27 Months) and provisional EOT for 9months.
Monthly Progress Report March -2017 (P04B)
ODISHA WORKS
DEPARTMENT
Page 20 of 35
2.6 FORECAST FOR NEXT MONTH
The Contractor has submitted work programme for the month of April-17.
FORECAST for April -17
Sl. No. Description Unit
Quantity remaining
to be executed by end of March -17
Length planned to
be executed during (half
width) April -17 (Mtr/No)
Quantity planned to
be executed
during April -17
Approximate cost of
work April -17 (Rs)
Remarks
1 Embankment in Soil Cum 126904 NA 22194 0.53
2 Embankment in Sand Cum 101271 NA 21585 0.75
3 Subgrade Cum 289623 NA 29003 0.69
4 GSB Cum 92054 NA 13548 1.46
5 WMM Cum 65702 NA 9858 1.37
6 DBM Cum 13367 NA 1787 1.41
30.51%
69.49%
Work Done Amount V/S Balance Amount Work Done Amount Balance Amount
Monthly Progress Report March -2017 (P04B)
ODISHA WORKS
DEPARTMENT
Page 21 of 35
7 BC Cum 14008 NA 0
8 DLC Cum 9561 NA 1472 0.41
9 PQC Cum 19919 NA 2959 1.61
10 Misc work of Highway Lakh NA 2.20
11 Structures Work Lakh NA 2.92
Total amount of work programme for April-17 13.39 Cr.
2.7 STATUS OF EXTENSION OF TIME
Considering the ground conditions and on request of the Contractor, extension of time for all the four rescheduled sections has been granted as mentioned below after obtaining the approval from the Employer.
Sl. No. Section Extended Date of Completion
1 Section-I (Rescheduled Section) 03rd May 2017
2 Section-II (Rescheduled Section) 31st October 2017
3 Section-III (Rescheduled Section) 23rd May 2018
4 Section-IV (Rescheduled Section) 07th July 2018
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 22 of 35
Chapter 3. Financial Performance
3.1 FINACIAL PROGRESS
Financial Progress achieved up to the end of this month is furnished below
1. Contract Price :170.43 Cr 2. Value of work done up to March 2017 a. Gross amount : 52.94cr. b. Amount excluding price adjustment : 52.00cr. 3. Mobilisation Advance : 8.52 cr. 4. Secured Advance : 4.40 cr. 5. Percentage of Progress (2b/1)*100 : 30.51%
3.2 MONTH WISE FINANCIALPROGRESS
Month wise financial progress on work proper excluding price adjustment and advances is furnished in given below.
Month
Base target Achieved Rema
rks Amount (Rs Cr.)
Cumulative Amount (Rs Cr.)
Percentage
Cumulative Percentage
Amount (Rs Cr.)
Cumulative Amount (Rs Cr.)
% achieved
Cumulative %
achieved
Jan-14 0 0 0.00% 0 0.19 0.18 0.11% 0.11% Feb-14 0.23 0.23 0.13% 0.13% 0.06 0.24 0.04% 0.15% Mar-14 1.38 1.61 0.81% 0.94% 0.48 0.72 0.28% 0.43% Apr-14 3.48 5.09 2.04% 2.99% 0.24 0.97 0.14% 0.57% May-14 4.99 10.08 2.93% 5.91% 0.39 1.36 0.23% 0.80% Jun-14 5.41 15.49 3.17% 9.09% 0.10 1.46 0.06% 0.86% Jul-14 4.24 19.73 2.49% 11.58% 0.00 1.46 0.00% 0.86% Aug-14 3.95 23.68 2.32% 13.90% 0.00 1.46 0.00% 0.86% Sep-14 3.73 27.41 2.19% 16.08% 0.00 1.46 0.00% 0.86% Oct-14 5.72 33.13 3.36% 19.44% 1.07 2.53 0.63% 1.49% Nov-14 5.38 38.51 3.16% 22.60% 0.64 3.17 0.38% 1.86% Dec-14 5.4 43.91 3.17% 25.77% 0.66 3.83 0.39% 2.25% Jan-15 8.19 52.1 4.81% 30.57% 0.79 4.62 0.46% 2.71% Feb-15 7.5 59.6 4.40% 34.97% 0.72 5.34 0.42% 3.14% Mar-15 11.63 71.23 6.82% 41.80% 0.66 6.00 0.39% 3.53% Apr-15 12.08 83.31 7.09% 48.89% 1.03 7.03 0.60% 4.13% May-15 14.48 97.79 8.50% 57.38% 1.12 8.15 0.66% 4.79%
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS
DEPARTMENT
2
Jun-15 13.12 110.91 7.70% 65.08% 0.73 8.88 0.43% 5.21% Jul-15 7.31 118.22 4.29% 69.37% 0.37 9.25 0.22% 5.43% Aug-15 6.32 124.54 3.71% 73.08% 0.25 9.49 0.14% 5.57% Sep-15 4.28 128.82 2.51% 75.59% 0.49 9.98 0.29% 5.86% Oct-15 11.31 140.13 6.64% 82.23% 0.23 10.21 0.13% 5.99% Nov-15 12.65 152.78 7.42% 89.65% 0.37 10.57 0.21% 6.21% Dec-15 11.77 164.55 6.91% 96.56% 0.75 11.32 0.44% 6.65% Jan-16 5.67 170.22 3.33% 99.88% 1.32 12.64 0.78% 7.42% Feb-16 0.20 170.42 0.12% 100.00% 1.29 13.94 0.76% 8.18% Mar-16 2.93 16.86 1.72% 9.90% Apr-16 3.14 20.00 1.84% 11.74%
May-16 4.93 24.93 2.89% 14.63%
Jun-16 2.68 27.62 1.57% 16.21%
Jul-16 0.38 27.99 0.22% 16.43%
Aug-16 0.36 28.35 0.21% 16.64%
Sept-16
0.93 29.29 0.55% 17.19%
Oct-16 0.91 30.19 0.53% 17.72%
Nov-16 1.56 31.75 0.92% 18.64%
Dec-16 4.42 36.17 2.59% 21.23%
Jan-17 4.73 40.90 2.78% 24.01%
Feb-17 4.93 45.83 2.89% 26.90%
Mar-17 6.16 52.00 3.61% 30.51%
3.3 MOBILIZATION ADVANCE
Net Amount Paid Cumulative Amount Paid Remarks
Mobilisation advance 8,52,13,677 8,52,13,677
8,52,13,677
Total : 8,52,13,677
Amount of Advance recovered up to this month Nil
Balance amount to be recovered : 8,52,13,677
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS
DEPARTMENT
2
3.4 STATEMENT OF IPC
IPC No. Month
Gross Amount of IPC (Rs. Crore) Recoveri
es Net
Amount Paid
Cumulative of Net Amount
Paid
Cumulative Gross
Amount Of IPC
Value of BOQ
Item Variation
Price Adjustme
nt
Secured
Advance
Gross amou
nt
IPC - 01 Feb - 14 0.00 0.00 0.00 8.52 8.52 0.17 8.35 8.35 8.52 IPC - 02 Mar - 14 0.74 0.00 0.00 0.00 0.74 0.14 0.60 8.95 9.26 IPC - 03 Apr - 14 0.46 0.00 0.00 0.00 0.46 0.09 0.37 9.33 9.72 IPC - 04 May, Jun - 14 0.29 0.00 0.00 0.00 0.29 0.05 0.24 9.56 10.01 IPC - 05 Oct - 14 0.90 0.00 0.00 0.00 0.90 0.15 0.75 10.31 10.91 IPC - 06 Nov-14 0.62 0.00 0.00 0.82 1.44 0.14 1.31 11.62 12.36 IPC - 07 Dec-14 0.52 0.00 0.00 0.00 0.52 0.10 0.42 12.04 12.88 IPC - 08 Jan-15 0.63 0.00 0.12 0.00 0.75 0.16 0.59 12.63 13.62 IPC - 09 Feb-15 0.68 0.00 0.00 0.07 0.75 0.31 0.44 13.07 14.38 IPC - 10 Mar-15 0.44 0.00 0.01 0.30 0.75 0.13 0.62 13.69 15.13 IPC - 11 Apr-15 1.56 0.00 0.00 0.18 1.74 0.64 1.10 14.79 16.87 IPC - 12 May-15 0.65 0.00 0.00 1.12 1.77 0.34 1.43 16.22 18.64 IPC - 13 June-15 0.79 0.00 0.05 0.07 0.92 0.28 0.64 16.85 19.56 IPC - 14 14 Jul 15 to 18 Sep 15 0.96 0.00 0.00 0.17 1.13 0.36 0.77 17.62 20.68 IPC - 15 19 Sep 15 to 31 Oct 15 0.39 0.00 0.00 0.54 0.92 0.12 0.80 18.42 21.61 IPC - 16 Nov 15 0.37 0.00 0.00 1.06 1.43 0.13 1.30 19.72 23.04 IPC - 17 Dec 15 0.75 0.00 0.00 0.16 0.91 0.33 0.58 20.30 23.95 IPC - 18 Jan 16 1.19 0.00 0.00 0.00 1.19 0.25 0.94 21.24 25.14 IPC - 19 Feb 16 1.27 0.00 0.00 0.07 1.35 0.37 0.97 22.22 26.48 IPC - 20 Mar 16 2.21 1.54 0.00 0.99 4.74 1.21 3.53 25.74 31.22 IPC - 21 1 Apr to 13 Apr 16 1.00 0.04 0.00 0.61 1.65 0.36 1.29 27.03 32.87 IPC - 22 14 Apr to 30 Apr 16 1.88 0.23 0.00 0.43 2.54 0.82 1.72 28.76 35.41 IPC - 23 May 16 4.82 0.21 0.00 0.84 5.86 1.87 3.99 32.75 41.27 IPC - 24 Jun 16 1.86 0.82 0.00 0.53 3.22 1.08 2.14 34.90 44.49 IPC - 25 July 16 to Sep 16 1.46 0.00 (0.22) 0.18 1.42 0.38 1.04 35.93 45.91 IPC - 26 Oct 16 0.50 0.43 0.00 0.12 1.06 0.26 0.80 36.74 46.97 IPC - 27 Nov 16 1.34 0.22 0.00 0.23 1.79 0.46 1.34 38.07 48.77 IPC - 28 Dec 16 3.75 0.57 (0.53) 0.66 4.45 1.21 3.25 41.32 53.22 IPC - 29 Dec 16 suppl 0.00 0.00 0.62 0.00 0.62 0.09 0.53 41.85 53.84 IPC - 30 Jan-17 4.71 0.02 0.00 0.86 5.59 1.53 4.06 45.92 59.43 IPC - 31 Feb-17 4.66 0.28 0.95 5.88 1.86 4.02 49.94 65.31 IPC - 32 Mar-17 6.08 0.14 0.93 7.10 1.33 5.77 55.71 65.86
Total 47.79 4.50 0.94 12.92 65.86 10.14 55.71
Page 25 of 35
Chapter 4. Status of Risk 4.1 HANDING OVER OF SECTION
Handing over status of Sections is mentioned below
Section Name
Scheduled date of Handing Over
Actual date of handing over Encumbrances if any Remarks
Section I 4-Dec-2013 29-Sep-2013
Section II 4-Apr-2014 22-Aug-2014
Section III 4-Aug-2014 11-May-2016 Tree-05,R&R-17,EP1,RWSS-10
Section IV 4-Dec-2014 11-May-2016(Part -6.1Km)
Tree-63,R&R-79,EP-148,RWSS-24
6.5 km yet to Hand Over.
4.2 STATUS OF UTILITY SHIFTING
Section Name Encumbrances Number existing till
last month (Feb-17) Number removed during this month
( March-17) Balance remaining for
removal
Section I
Electric Pole - - - R&R - - - Telephone pole - - - Tree cutting - - -
Section II
Electric Pole - - - RWSS - - - Tree - - - R&R - - - Land - - -
Section III
Tree 10 5 5 R&R 24 7 17 EP 2 1 1 TP RWSS 14 4 10
Section IV
Tree 76 13 63 R&R 102 23 79 EP 151 3 148 TP RWSS 26 2 24
4.3 ANY OTHER ISSUE
The progress of work is very slow, it is required to be expedited in order to complete all the sections and whole work by 7th July 2018 upto which EOT has been granted.
4.4 RISK INVOLVED
There is apprehension of delay in completion of the work if Contractor does not plan and mobilise adequate men, material and machineries accordingly for execution as per programme.
Page 26 of 35
Chapter 5. Environmental Monitoring and Safety
5.1 ENVIRONMENT MANAGEMENT PLAN Sl. No.
Environmental Issue / Aspect Management Measures
1 Tree Cutting Tree cutting done by other agency.
2 Joint Field Verification Site visit is done time to time.
3 Location and Installation of Crushers, Hot Mix Plants and Batching Plants
Contractor obtained CTE/ CTO for BMP/HMP/WMM plants. CTO is valid up to 31.03.2018. -Contractor obtained CTE/CTO for Crusher. CTO is valid up to 31.03.2020.
4 Construction Camp(s) – Selection, Design and Layout
After approval, constructed office/laboratory/store/ guest house/workshop.
5 Construction Vehicles, Equipment and Machinery Obtained PUC certificates for vehicles.
6 Identification, Operation and Rehabilitation of Borrow Areas
Nilakanthpur and Kuwarpur, Baro borrow areas for subgrade are in operation Embankment cover soil at Barunadih, Tanar and Kantia borrow areas are in operation
7 Identification, Operation and Rehabilitation of Stone Quarry
Anjira (Dharamsala) stone quarry is in operation. Lease granted for 5 yrs. on 15.02.2016.
8 Identification, and Operation of Sand Quarry
Embankment sand quarries at Kuwanrpur, Chaudakulat, Nimpura, Sasan, Kharaswata and Patrapur are in operation.
9 Arrangement for Construction Water Contractor excavated bore well at camp for water consumption.
10 Clearing and Grubbing Action is being taken as per EMP.
11 Stripping, Stacking and Preservation of Top Soil
Top soil from Clearing & grubbing is stored at roadside, stocked soil is used for slope filling.
12 Labour Camp Management All basic amenities provided in camp, proper sanitation, housekeeping & cleaning is on-going process.
13 Transportation of Construction Materials and Haul Road Management
Covered vehicles are used for material transportation and haul road is maintained time to time.
14 Worksite Safety Management Safety arrangement as sign boards, barricading, sand bags are provided at different construction sites.
15 Accessibility No obstructions reported during this month.
16 Disruption to Other Users of Water Such obstructions have not been reported.
17 Labour Requirements Labourers engaged are local.
18 Pollution Management No discharge in water body, obtained PUC certificate. Pollution monitoring is yet to be done.
19 Drainage and Flood Control Not observed any blockage of cross drainage
20 Slope Protection and Control of Soil Erosion Slope protection is being done for avoidance of soil erosion.
21 Waste Management Scarified materials are used in haul road management.
22 Chance Found Archaeological Property No archaeological property found.
23 Demobilisation and Decommissioning No activity during this month
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 27 of 35
5.2 ROAD SAFETY
At different construction sites safety arrangement as signages, barricading, sand bags, delineators, and caution tapes has been provided for safe passage of commuters. Made diversion with barricading and sign boards at culvert opening. Water sprinkling is being done for dust suppression.
Ch. 51+300, 51+600
Ch.69+280, 69+327
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 28 of 35
Chapter 6. Variation and Changes 6.1 SUMMARY OF CHANGE ORDER
Change Order
No. Description of Change
Item Increase in cost (Rs Cr)
Revised contract Price (Rs
Cr)
Percentage of increase/ decrease on
contract price
Cumulative % of
increase/ decrease of
contract price
Remarks
1
Carrying and Confirmatory bores up to required depth at locations of bridges as directed by the Engineer complete in all respects, conducting all the tests required as directed by the Engineer and as per Technical Specification Section 2400 and interpretation of the bore data and presentation of the results and as per the direction of the Engineer.
0.39 0.39 0.23% 0.23%
Submitted to
Employer for
approval
2
Four-lane road divided carriageway in Kendrapara town area with rigid pavement from Km 49+000 to Km 53+200.
3.62 4.01 2.12% 2.35% --do--
3 Addition of Underpass at Km 70+401 and profile correction in Km 70+080 to 70+700
0.61 4.62 0.36% 2.71% --do--
4
Providing rigid pavement in place of flexible pavement at Km 58+000 to 58+050 and 91+400 to 91+600.
0.25 4.87 0.15% 2.86% --do--
5 Addition/deletion of HP Culverts 0.11 4.98 0.06% 2.92% --do--
6
Widening of culverts envisaged in Contract is proposed as new construction
0.05 5.04 0.03% 2.95% --do--
7 HPC at 69+731 is proposed as Box culvert 0.18 5.22 0.11% 3.06% --do--
8 Temporary diversion with GSB 11.11 16.33 6.52% 9.58% --do--
9 Pothole repair for maintenance 1.10 17.44 0.65% 10.23% --do--
10 RCC grade M 35 in superstructure 0.12 17.56 0.07% 10.30% --do--
11 Embankment construction with soil having CBR not less than 5%
-0.01 17.55 0.00% 10.30% --do--
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 29 of 35
12
Revision of pavement width from 7m to 10m for providing 2-lane carriageway with paved shoulder
25.60 43.15 15.02% 25.32% --do--
13
To provide four spans of 10m box cell in place of pile foundation and deck slab with girder for the minor bridge (4 x 10m span) over canal near Pattamundai.1m thick sand cushion is provided below the raft for ground improvement
-0.39 42.77 -0.23% 25.09% --do--
14
1. Deletion of HPC at Km 50+850 (1 x 1.0), HPC at 51+240 (1 x 1.0) & HPC at Km 55+080 (1 x 1.0) - 3nos. 2. New construction of HPC at Km 50+350 (5 x 1.2) in place of widening 3. Change in dimension Box culvert at Km 86+434 (from 1 x 3 x 3 to 1 x 6 x 4) 4. Box culvert at Km 86+050 (1 x 6 x 3) changed to HPC (1 x 1.2)
-0.03 42.74 -0.02% 25.07% --do--
15
Ground improvement below the raft of Box culverts, Box minor bridges and Underpasses by providing 2m to 3m thick sand filling to improve bearing capacity as per requirement. 300mm thick sand blanket is also proposed under the headwalls of the HP culverts.
0.52 43.26 0.31% 25.38% --do--
16
1) Encasement of Hume pipes with PCC M 15. 2) Provision of nominal reinforcement mat on top of head walls of pipe culverts.
0.09 43.35 0.05% 25.44% --do--
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 30 of 35
Chapter 7. Quality Control and Quality Assurance
7.1 TESTS CONDUCTED
Following tests both at site and at Laboratory have been conducted during the month to ensure Quality control and Quality Assurance.
Sl. No.
Description of Tests conducted
Number of Tests conducted
No. of Test Failed Remedial measure adopted
1 Embankment control Tests 274(FDD Test) 3 Retested after compaction
2 Tests in Sub grade 305(FDD Test) 1 Retested after compaction
3 Tests in GSB 98 1 Retested after compaction
4 Tests in WMM 76 0
5 Tests in DBM 58 0
6 Tests in BC
7 Coarse aggregate for Structures (Gradation) 30 0
8 Fine aggregate for Structures (Gradation) 30 0
9 Cement 5 0
10 Cube Compression Tests (28 days) 81 0
Page 31 of 35
Chapter 8. Mobilisation 8.1 CONSULTANT’S TEAM
The staff mobilization is being done in consultation with Employer as per the project requirement. The following table depicts the staff mobilization history as on date.
Sl. No Designation Name Joining
Date/Period Remarks
1 Resident Engineer Mr. Dinakar Mondal 05.06.2015 2 Highway Engineer Mr. Amit Kumar Mohapatra 21.12.2015 3 Quantity Surveyor Mr. A.R. Sudarshana 01.03.2015 4 Bridge Engineer Mr. B. Mallikarjuna Rao 05.06.2015
5 Senior Surveyor (For Both PKG-P04A & P04B) Mr. Dilip Kumar De 21.12.2015
6 Material Engineer- cum- Quality Monitor Mr. Niranjan Kumar 20.10.2016 7 Bridge Design Engineer (Intermittent) Mr. Dhruvjyoti Ghatak 03.01.2014
8 Environment Expert (For Both PKG-P04A & P04B) Mr. Mukesh Srivastava 14.02.2014
9 CADD Engineer Mr. Hamanta Paul 24.02.2016 10 Asst. Highway Engineer Mr. Suresh Chandra Nayak 26.08.2015 11 Asst. Highway Engineer Mr. Umesh Chandra Chaurasia 01.03.2016 12 Asst. Highway Engineer Mr. Mrutyunjaya Biswal 29.11.2016 13 Asst. Bridge Engineer Mr. Abhay Kumar Dubey 01.11.2016 14 Asst. Bridge Engineer Mr. Rajesh Patel 10.12.2013 15 Asst. Quantity Surveyor Mr. Suman Paul 22.01.2014 16 Asst. Material-cum-Quality Engineer Mr. Bijay Kumar Nayak 01.02.2015 17 Asst. Material-cum-Quality Engineer Mr. Anurag Satapathi 17.10.2016 18 Technician (Field/Lab/Plant) Mr. Nalinikanta Mallik 03.01.2014 19 Technician (Field/Lab/Plant) Mr. Ranjit Kumar Nayak 06.12.2016 20 Asst. Surveyor Mr. Malaya Kumar Swain 01.12.2015 21 Asst. Surveyor Mr. Ujjwal Rout 29.11.2016 22 Junior Road Safety Expert Mr. Parwej Alam 17.12.2015 23 Office Manager-cum-Accountant Mr. Rajesh Kumar 08.03.2015 24 Computer Operator-cum-Office Assistant Mr. Sumant Kumar Sahoo 01.04.2014 25 Office Attendant /Watch man Mr. Manoranjan Sahoo 17.12.2013 26 Office Attendant /Watch man Mr. Gourahari Das 21.03.2014 27 Office Attendant /Watch man Mr. Akhay Mallick 01.04.2014
8.2 CONTRACTOR’S TEAM The Contractor’s Key Mobilisation status is as follows:
Sl. No Position Name Date of Joining Remarks 1 Project Manager Mr. VP Singh 17-01-2016 CV not submitted 2 Highway Engineer Mr. Chandra Ban Singh 06-05-2015 CV not approved 3 Bridge Engineer TBN 4 Material Engineer Mr. B. Kastshuri Raju 09.10.2016 CV not submitted 5 Equipment Maintenance Engineer Mr. Mir Md Faridadin 16.05.2016 CV not submitted 6 Quantity Surveyor Mr. Ganesh Pandian 27.09.2016 CV not submitted 7 Environment & Safety Manager TBN
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 32 of 35
8.3 STATUS OF PLANT AND EQUIPMENT OF CONTRACTOR
Sl. No. Description of Equipment / Plant
Min. No. to be Mobilized as per Contract
No. Mobilized
1 Mechanical Bitumen Sensor Paver100 TPH 1 1
2 Motor Grader(200 cum/Hr) 2 4
3 Hydraulic Excavator 2 20 (Includes stone quarry and crusher 7 nos)
4 Vibratory Roller (Tandem-8T) (100 cum/Hr) 3 2
5 Pneumatic Tyre Roller(25 cum/Hr) 1 1
6 Transit Mixer(6 cum/Hr) 5 11
7 Front end Loader 3 2
8 Dozer (150 cum/Hr) 1 1
9 Tipper (of different capacities) 35 57(Includes stone quarry, crusher & aggt. transportation 20nos)
10 Bitumen sprayer(1750 sqm/hr) 1 1
11 Earth Compactor ( 8-10 ton) 3 6
12 Water tanker (12 KL) 5 4
13 Mechanical Paver (100 TPH) 1 1
14 Concrete Pump ( 20 cum/Hr) 2 1
15 Concrete Fixed Form Paver (100 TPH) 1 0
Plants
16 Hot Mix Plant (Batch Mix only)( 100 TPH) 1 1
17 Concrete Batch-mix Plant (30 cum/Hr ) 1 1
18 Cone Crushing Unit ( 200 TPH) 1 1
19 WMM Plant (100 TPH) 1 1
The following survey equipment is available at site;
Sl. No. Name of the equipment Quantity (Nos.)
1 Total station 1
2 Auto level 4
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 33 of 35
Chapter 9. Visits and Meetings No VIP visits during the month.
Page 34 of 35
Chapter 10. Important Correspondence during the Month
10.1 SUBMISSIONS AND APPROVALS
Submission the interim payment certificate of IPC 31 vide letter LASA/RE-2/73466/2017/743 dated 07-March-2017.
10.2 CORRESPONDENCES
Contractor
Incoming from the Contractor: 19 nos.
Outgoing to the Contractor: 16 nos.
Employer
Incoming from OWD: 5 nos.
Outgoing to OWD: 17 nos.
The list of important correspondences made during the month is furnished as Annexure-6.
Monthly Progress Report March- 2017 (P04B)
ODISHA WORKS DEPARTMENT
Page 35 of 35
Chapter 11. Weather during the Month
Sl. No Date Minimum Temp °C
Maximum Temp °C
Min Humidity
Max Humidity
Rain Fall (mm) Remarks
1 1-Mar-17 22.8 37.9 34 75 Nil
2 2-Mar-17 23.1 32.2 36 77 Nil
3 3-Mar-17 22.9 33.1 35 74 Nil
4 4-Mar-17 22.4 32.9 37 78 Nil
5 5-Mar-17 23.5 33.3 34 77 Nil
6 6-Mar-17 23.3 33.1 36 78 Nil
7 7-Mar-17 23.1 32.4 38 80 137.0mm
8 8-Mar-17 22.7 31.9 37 82 82.0mm
9 9-Mar-17 22.2 32.2 36 81 Nil
10 10-Mar-17 22.8 31.7 38 79 Nil
11 11-Mar-17 22.5 31.9 37 80 73.0mm
12 12-Mar-17 23.2 32.3 36 78 30.0mm
13 13-Mar-17 NOT RECORDED
14 14-Mar-17 22.8 32.0 37 77 Nil
15 15-Mar-17 23.4 32.3 35 78 Nil
16 16-Mar-17 24.1 33.7 37 79 Nil
17 17-Mar-17 23.7 32.6 36 76 Nil
18 18-Mar-17 24.4 32.9 37 80 Nil
19 19-Mar-17 23.5 32.5 36 78 0.3mm
20 20-Mar-17 24.2 33.1 35 77 12.0mm
21 21-Mar-17 24.0 33.4 37 79 Nil
22 22-Mar-17 24.5 33.7 36 77 Nil
23 23-Mar-17 24.7 34.5 37 76 Nil
24 24-Mar-17 24.6 34.8 36 77 Nil
25 25-Mar-17 25.0 35.2 36 79 Nil
26 26-Mar-17 24.8 34.4 34 78 Nil
27 27-Mar-17 24.4 34.6 35 76 Nil
28 28-Mar-17 23.7 35.1 38 78 Nil
29 29-Mar-17 23.9 35.4 37 77 Nil
30 30-Mar-17 24.2 35.6 35 76 Nil
31 31-Mar-17 24.4 35.2 37 80 Nil