![Page 1: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/1.jpg)
Monthly Progress Update
Monthly Progress Update
October 2017
![Page 2: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/2.jpg)
Monthly Progress Update 2
Cricket Valley Energy Center Highlights
Community Benefits Package
Generation Station Construction Progress
Transmission Line Construction Progress
Questions/Closing
Today’s Topics
![Page 3: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/3.jpg)
Monthly Progress Update
• Fully-permitted combined cycle natural gas-fired energy center• Previously abandoned, industrial-zoned site• 193 acres off Route 22, Dover, New York• 79 acres of wetlands will remain undisturbed• No fracking at this facility—CVE is a consumer, not a producer, of natural gas
• Now under construction • Compact design reuses existing industrial footprint• Air cooling technology will reduce water use by 98%+• No process water will be discharged into Swamp River
• Scheduled for completion first quarter 2020
3
Cricket Valley Energy Center Overview
![Page 4: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/4.jpg)
Monthly Progress Update
• Limited site access
• Required safety training
• Security procedures
• Safety procedures and compliance
4
Steps for Safety
![Page 5: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/5.jpg)
Monthly Progress Update
• $3 million during construction phase
• Over $150 million through 2049
5
Contributing to Dover’s Tax Base
![Page 6: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/6.jpg)
Monthly Progress Update 6
• Well and filtration system at Thomas J. Boyce Park
• New Salt Shed and Pole Barn
• J.H. Ketcham Memorial Park improvements
• Mini-excavator, 10-wheel truck, and other equipment
• Joint Project/School District Scholarship program
• Athletic field lighting and sound system at Dover High School
• Annual contribution to Dover Educational Enrichment Program
• Annual contribution to Board of Education Discretionary Fund
• Air Quality Monitoring Station
• Pleasant Valley Little League Ball Field
Advancing Community Benefits in Dover & Pleasant Valley
Total Benefit Commitment: $2,432,235
![Page 7: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/7.jpg)
Monthly Progress Update 7
Construction ProgressCricket Valley Energy Center
![Page 8: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/8.jpg)
Monthly Progress Update 8
• Established electrical service for construction power
• Site Grading Continues
• Blasting• Completed switchyard area• Continue with pond 1 area
• Continued installation of underground utilities
• Started ACC foundations
Construction Progress
![Page 9: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/9.jpg)
Monthly Progress Update 9
• Started Route 22 road improvements
• Started laydown yard grading
• Erected fence around laydown yard
• Started construction fence around project site
• Started erection of craft tent at main site
• Foundation complete• Structural erection started
Construction Progress
![Page 10: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/10.jpg)
Monthly Progress Update 10
• Continue civil excavation work
• Continue blasting activities
• Continue with Site Entrance Improvements
• Continue underground piping and electrical installation
• Continue earthwork at Laydown Yard
• Continue formwork and rebar installation for Heat Recovery Steam Generator foundation Unit 1.
4 Week Look Ahead
![Page 11: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/11.jpg)
Monthly Progress Update 11
Photos
HRSG Modules - Harp stacking Heat Recovery Steam Generator Drum
![Page 12: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/12.jpg)
Monthly Progress Update 12
Photos
Generator - Stator Generator Rotor Forging
![Page 13: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/13.jpg)
Monthly Progress Update 13
Photos
Intermediate Pressure Steam Turbine Rotor Forging
Low Pressure Steam Turbine Rotor Forging
![Page 14: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/14.jpg)
Monthly Progress Update 14
• 250 craft workers currently onsite
• 8 active 1st and 2nd subcontractors are onsite today.
• C.B. Strain & Sons– Poughkeepsie, NY
• E-J/Perreca Electric – Newburgh, NY
• Tectonic Engineering & Surveying –Newburgh, NY
• Dutchess County Constructors – Dover Plains, NY
• O&G Industries. – Torrington, CT
• Baystate Blasting, Inc. – Ludlow, MA
• Empire Layout – Somers, NY
• Bay Crane – Long Island City, NY
Jobs for 1,100
![Page 15: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/15.jpg)
Monthly Progress Update 15
Construction ProgressTransmission Upgrade
![Page 16: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/16.jpg)
Monthly Progress Update 16
Conducted Danger Tree Survey
Commenced ROW and access road clearing
Commenced tree clearing
Transmission Line Progress Update
ROW and tree clearing near PV Substation
![Page 17: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/17.jpg)
Monthly Progress Update 17
• Continue Survey for future construction activities
• Continue improvements to access roads
• Continue tree clearing
ROW and tree clearing
4 Week Look Ahead – Transmission Upgrade
![Page 18: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/18.jpg)
Monthly Progress Update 18
• TEC Survey – Beacon, New York ROW Survey and Laydown Yards
• Crux – Foundation Design
• Real Time Engineering – Structure Design
• Supreme – Initial tree clearing and access road improvements
Active Sub-Contractors – Transmission Upgrade
ROW and tree clearing
![Page 19: Monthly Progress Update Progress Update 6 • Well and filtration system at Thomas J. Boyce Park • New Salt Shed and Pole Barn • J.H. Ketcham Memorial Park improvements • Mini-excavator,](https://reader031.fdocuments.net/reader031/viewer/2022022501/5aa8b6307f8b9a86188bd87f/html5/thumbnails/19.jpg)
Monthly Progress Update 19
• More Information?• Scott Curry, Project Manager• [email protected]
Next Up