Monthly Progress Brief – February 2015 Page 1
PUBLIC WORKS DEPARTMENT GOVERNMENT OF KERALA
KERALA STATE TRANSPORT PROJECT - II (UNDER WORLD BANK ASSISTANCE – Loan No. 5284)
MONTHLY PROGRESS BRIEF FEBRUARY 2015
Project Management Team Kerala State Transport Project T.C.11/339, JAGAD Building Keston Road, Nanthancode, Kawdiar P.O. Thiruvananthapuram - 695003
Monthly Progress Brief – February 2015 Page 2
PUBLIC WORKS DEPARTMENT
GOVERNMENT OF KERALA
KERALA STATE TRANSPORT PROJECT - II (UNDER WORLD BANK ASSISTANCE – Loan No. 5284)
MONTHLY PROGRESS BRIEF FEBRUARY 2015
Project Management Team Kerala State Transport Project T.C.11/339, JAGAD Building Keston Road, Nanthancode, Kawdiar P.O., Thiruvananthapuram - 695003
Monthly Progress Brief – February 2015 Page 3
Table of Contents
1.1 Project Development Objectives ...................................................................... 5 1.2 Outline Project Data: ..................................................................................................... 5 1.3 Overall Implementation: ................................................................................. 9 1.4 Project Components .............................................................................................................. 9 2.1 Project Description ............................................................................................................. 10 2.2 Road Upgrading Under Item Rate Contract:- ................................................. 10 2.3 Sub Component A1 (US$322 mn) .................................................................. 10 2.4 Supervision Consultancy ............................................................................... 11 2.5 Sub Component A2 (US$ 91 mn) ................................................................... 11 2.6 Component B – Road Safety Management (US$ 22 mn) ................................. 11 2.7 Component C – Institutional Strengthening (US$ 10 mn) .............................. 12 2.8 Project Cost and Disbursement ..................................................................... 13 2.9 Project location map ........................................................................................................... 14 3.0 Upgradation Works ............................................................................................................. 15 3.1 Summary of Progress (works) ........................................................................ 16 3.2 General Issues: .............................................................................................. 16 4.1 CURRENT STATUS OF WORKS .................................................................................... 18 4.2 Contract Package I ........................................................................................ 18 4.3 Contract Details ............................................................................................ 18 4.4 Progress of Works .......................................................................................... 18 4.5 Summary of progress for major items is as follows: ....................................... 18 4.6 Progress Considering the Contract price up to February 2015. ...................... 20 4.7 Physical progress Bar Chart (Quantity Wise) ................................................. 21 4.8 Utilities ......................................................................................................... 21 4.9 Potential Issues ............................................................................................. 22 4.10 Payments to the Contractor ........................................................................... 22 4.11 Compliance with Statutory Clearances .......................................................... 22 4.12 Environment Management at Work Sites ...................................................... 23 4.13 Traffic Management and Road Safety Measures ......................................... 23 5.1 Contract Package II ............................................................................................................. 24 5.2 Contract Details ............................................................................................................ 24 5.3 Progress of Works .......................................................................................... 24 5.4 Structure ....................................................................................................... 25 5.5 Work progress considering the contract price ................................................ 25 5.6 Physical Progress .......................................................................................... 26 5.7 Strip Chart ...................................................................................................................... 26 5.8 Potential Issues ............................................................................................. 27 5.9 Payments to the Contractor ........................................................................... 27 5.10 Environment Management at Work Sites ....................................................... 28 5.11 Traffic Management and Road Safety Measures ............................................. 28 6.1 Contract Package III ........................................................................................................... 29 6.2 Contract Details ............................................................................................ 29 6.3 Utilities ......................................................................................................... 30 6.4 Work Progress as end February 2015: ........................................................... 30 6.5 Schedule of culverts and drainage works ........................................................................... 32 6.6 Potential Issues ............................................................................................. 32 6.7 Physical Progress .......................................................................................... 33 6.8 Physical Progress S Curve ............................................................................. 33 6.9 Payment to Contractor .................................................................................. 34 6.10 Implementation of EMP ................................................................................. 34 6.11 Compliance with Statutory Clearances .......................................................... 34 6.12 Environment Management at Work Sites ....................................................... 34 6.13 Traffic Management and Road Safety Measures ............................................. 35
Monthly Progress Brief – February 2015 Page 4
7.1 Contract Package IVA ........................................................................................................ 35 7.2 Contract Details ............................................................................................ 36 7.3 Utilities ......................................................................................................... 36 7.4 Moblization of Resources ............................................................................... 36 7.5 Work Progress .................................................................................................................... 36 7.6 Physical Progress (Quantity wise): ..................................................................................... 37 7.7 Potential Issues ................................................................................................................... 37 7.8 Schedule of culverts and drainage works ........................................................................... 37 7.9 Implementation of EMP: ................................................................................ 38 7.10 Payment ........................................................................................................ 38 8.1 Contract Package IV ........................................................................................................... 38 8.2 Contract details: ............................................................................................ 38 8.3 Pre-Construction Activities: ........................................................................... 39 8.3.1 Utilities ......................................................................................................... 39 8.4 Mobilization of Resources .......................................................................................... 39 8.4.1 Plant and machinery ..................................................................................... 39 8.5 Work Progress ................................................................................................................ 39 8.6 Physical Progress .......................................................................................... 40 8.7 Schedule of culverts and drainage works ............................................................. 41 8.8 Implementation of EMP .............................................................................................. 41 8.9 Payments ......................................................................................................................... 42 9.1 Contract Package V ............................................................................................................ 42 9.2 Contract details: ............................................................................................ 42 9.3 Utilities ......................................................................................................... 43 9.4 Plant & Machinery ......................................................................................... 43 9.5 Work Progress ............................................................................................... 43 9.6 Schedule of culverts and drainage works ........................................................................... 44 9.7 Key issues: .................................................................................................... 45 9.8 Payment to the contractor ............................................................................. 45 9.9 Implementation of EMP .............................................................................................. 45 9.10 Compliance with Statutory Clearances ....................................................................... 45 9.11 Traffic Management and Road Safety Measures ......................................... 46 10.1 Contract Package VI .................................................................................................... 46 10.1 Contract details: ........................................................................................................... 47 10.2 Financial Progress: ........................................................................................ 47 10.3 Work Progress: ....................................................................................................... 47 10.1 Work Progress: ....................................................................................................... 48 10.2 Physical Progress .......................................................................................... 48 10.3 Environment Management Plan & Mitigation: ............................................ 49 10.4 Environment Management at Ancillary facilities ............................................ 49 10.5 Payment to contractor ................................................................................... 50 11.1 Contract Package VII .................................................................................................. 50 12.1 Contract Package VIII ................................................................................................. 50 13.1 Proactive actions taken by employer: .......................................................................... 50 14.1 Road Safety Component – Current Status ................................................................... 50 15.1 Institutional Strengthening Components – Current Status .......................................... 51 16.1 Payment to the consultants as on end February 2014: ................................................ 52 17.1 Overlay to 150 km KSTP-I Roads .............................................................................. 52 18.1 Meetings, Site visits & Inspection ............................................................................... 52 19.1 Land Acquisition Status .............................................................................................. 53 20.1 Status on Critical Actions ............................................................................................ 54 21.1 List of Annexure: ......................................................................................................... 56
Monthly Progress Brief – February 2015 Page 5
Kerala State Transport Project-II Government of Kerala has decided to take up Phase-II upgradation component of KSTP
as a standalone project, the KSTP-II. The project envisages the upgradation of 363 km
of SH and MDR, Road Safety Management and Institutional Strengthening of PWD. The
total Project cost is 445 million USD out of which 216 million USD is loan assistance
from World Bank. The project loan agreement was signed on June 19, 2013 at the DEA
Office, New Delhi. The loan effectiveness date is September 6, 2013. The project
implementation period is five years, upto 30 November 2018.
1.1 Project Development Objectives The Project Development objective is to improve condition, traffic flow and road safety
with a focus on vulnerable road user on Kerala State Core road networks comprising of
363 Km of state highways. The main beneficiaries of the Project will be the users living
along the Project corridors mainly the travelling public, agricultural and industrial
producers, consumers and local community. The main benefit is in the form of reduced
transport bottlenecks, lower passenger freight transport costs, reduced travel time and
improved road safety in terms of reducing severe crashes and injury. The roads
identified for improvement passes through about 87 villages covering eight districts.
1.2 Outline Project Data: The upgrading works for six roads are included in t he KSTP-II. The major items of
works included are improvement to gradient, widening and strengthening the roads
including minor realignments wherever essential, reconstruction of narrow bridges and
culverts and improvements to drainage system. A Bypass also is proposed at Thiruvalla.
The carriageway proposed are generally 2 lane with 1.50 mt. slow lanes on either side
with hard shoulders and drains for a total width of 12 meters. The ROW is generally 15
Meters. The specification for civil works are as per MORTH & IRC standards.
The land acquisition for the project roads are almost completed except in the
Perimbilavu- Pattambi- Perinthalmanna Road.
Monthly Progress Brief – February 2015 Page 6
1.2.0.1 Kasargod Kanhangad Road – SH 57 Length - 27.76 km.Covers Kasargod, Pallikkara, manikoth and Kanhad areas and
Tourist destinations at Bakel Fort and Ezhimala come under this stretch.
1.2.0.2 Pilathara Pappinissery Road Length - 20.90 km. Covers Pilathara, Cheruthayam, Kunnupuram and
Pappinissery.
1.2.0.3 Thalassery - Valavupara Road – SH 30 Length 53.12 km. It is a part of SH 30 Thalasserry – Coorg Road and passes
through Koothuparambu, Mattannor, and Irutty.
1.2.0.4 Chengannur - Ettumanoor – Muvattupuzha – SH1
Chengannur Ettumanoor Muvattupuzha stretch of SH-1, MC (Main Central) Road, one
of the most important and oldest roads in Kerala passing through Thiruvalla,
Changanasserry, Kottayam, Ettumannor, Kuravilangad, Kuttathukulam.
Total length covered is 88 kms.
Road portion from Thiruvananthapuram (Venjaramoodu) to Chengannur was taken up
under Phase I. Bypass at Thiruvalla also forms part of this stretch. The road passes
through the plantation areas and provides access to the tourist centres Kumarakom and
Thekkady.13 bridges will be constructed in this stretch.
The improvement for this road portion is proposed in three construction packages,
Chengannor- Ettumannor(41 km), Ettumanoor-Muvattupuzha (47km) and Thiruvalla
Bypass (2.4km). Reconstruction of three Major Bridges and Nine Minor Bridges are
included in this stretches.
Monthly Progress Brief – February 2015 Page 7
1.2.0.5 Punaloor - Ponkunnam – Thodupuzha – SH 8
Punaloor Ponkunnam Thodupuzha stretch of SH 8 is included in this package.
Total road length is 132 kms.
Major areas covered are Punaloor, Pathanapuram, Manimala, Pala and Thodupuzha.
Five Bridges will be constructed in this stretch. The road passes through Kollam-
Pathanamthitta, Kottayam and Idukki districts. The portion from Punalur-Ponkunnam
is proposed under PPP (modified annuity) arrangement.
1.2.0.6 Perumbilavu - Pattambi – Perinthalmanna – SH 39
Perumbilavu- Pattambi-Perinthalmanna Road Link of SH 39 is included in the package
(Starts at Kuttinad Jn). The growth centre connected is Pattambi town
Length: 41 kms. The road passes through Thrissur, Palakkad and Malappuram
Districts.
Basic Information
Project ID Lending Instrument
EA Category Team Leader
P130339 Specific A - Full Arnab Bandyopadhyay
Monthly Progress Brief – February 2015 Page 8
Investment Loan
Assessment
Project Implementation Start Date Project Implementation End Date
30 July2013 30 July2018
Expected Effectiveness Date Expected Closing Date
30 July 2013 30 November 2018
Joint IFC
No
Sector Manager Sector Director Country Director Regional Vice President
Karla Gonzalez John Henry Stein Onno Ruhl Isabel M. Guerrero
Borrower: Government of India Responsible Agency: Kerala State Transport Project Contact: Mr. APM Mohammed Haneesh,
IAS Title: Secretary PWD
Telephone No.: +91-471-2327803
Email: [email protected]
Contact: K.P. Prabhakaan Title: Project Director Telephone No.:+91-471-2318946 Email: [email protected]
For Loans/Credits/Others
Total Project Cost (US$M):
445.00
Total Bank Financing (US$M):
216.00
Financing Source Amount(US$M) Borrower 229.00 International Bank for Reconstruction and Development
216.00
Total 445.00
Expected Disbursements (in USD Million) Fiscal Year FY14 FY15 FY16 FY17 FY18 Annual 22 43 65 54 32
Cumulative 22 65 130 184 216
Monthly Progress Brief – February 2015 Page 9
1.2.0.7 The Finance plus agenda of KSTP – II
1. Upgrading Punalur – Ponkunnam Road under PPP(Annuity)
2. Development of Model Safe Corridor Kazhakuttam – Adoor Section (80 km)
3. Development of Oxbow land (left out lands)
4. Construction of Head Quarters Building for PWD / KSTP under green
building concept
1.3 Overall Implementation:
Project Staffing: KSTP is managed by a Project Director, in the Rank of a senior level Chief
Engineer assisted by one Chief Engineer, a Superintending Engineer and other engineers
and officers. The Technical Wing headed by the Chief Engineer is responsible for
activities related to engineering, environment, social and contract management. Further,
the legal contract management cell is headed by a legal professional. KSTP has qualified
and experienced Social and Environmental Experts and a Project Management Advisor.
The Finance Wing headed by a Finance Controller (deputed from the Secretariat) has a
qualified Finance Manager with support staff. On the field, the KSTP has Two
Superintending Engineers, Five Divisions located at Kottarakkara, Muvattupuzha,
Kuttippuram, Kannur, Ponkunnam each headed by an Executive Engineer to monitor
project progress.
Project co-ordination: Govt. of Kerala has established two committees to monitor, coordinate,
and expedite project activities. The Project Steering Committee chaired by the Chief Secretary, has
its main functions to review and approval of recommendations regarding acceptance of
tenders and taking the final decisions on all matters concerning procurement and
monitoring of project activities. The members of the committee are Additional Chief
Secretary (Finance), Secretaries to Government, PWD, Law Department, Revenue, Chief
Engineer, R&B, Project Director, KSTP, Chief Engineer (Projects) KSTP. There is an
Evaluation Committee headed by the PWD Secretary and comprising the Project
Director, KSTP and Chief Engineer (Projects), to make recommendations on any issues
on procurement as may require approval of the Steering Committee.
1.4 Project Components
1.4.0.1 Road Upgrading Works:
This component will include upgrading 363 kms of strategically important State
Highways to complete network connectivity in the state with the objective of reducing
travel time between key socio-economic centers.
Monthly Progress Brief – February 2015 Page 10
1.4.0.2 Road Safety Management:
This component will support the strengthening of the road safety management systems
in Kerala with the objective of arresting the increase of crash fatalities in the state. This
component will finance various initiatives building on the work already undertaken
during the first project including a safe corridor demonstration project, implementation of
local level programs utilizing the challenge fund and advisory support for road safety
activities. The road section improved under KSTP-I from Kazhakuttom - Venjaramoodu-
Adoor is proposed to be developed as Safe Corridor Demonstration Project (80 km)
1.4.0.3 Institutional Strengthening:
The objective of this component is to improve the sustainability of Kerala’s state road
network with respect to its functional adequacy, financial viability and capacity of key
state road sector institutions to deliver road infrastructure and services that are
responsive to road user needs. The major initiatives include Modernization of Road
Sector. The development and Management of a Strategic Road Network is proposed
under the Road Sector Modernization Program.
2.1 Project Description
2.2 Road Upgrading Under Item Rate Contract:-
This component will include upgrading of 240 km of State Highways through FIDIC base input contracts and conventional item rate contracts as noted below.
1. Pilathara - Pappinissery Road – 20.90 km
2. Kasaragod – Kanhangad Road – 27.76 km
3. Thalassery – Valavupara Road – 53.10 km
4. Ponkunnam – Thodupuzha Road – 50.30 km
5. Chenganur – Ettumanoor Road – 41.00 km
6. Ettumanoor – Muvattupuzha Road – 47.00 km
2.2.0.1 Road upgrading under PPP (Hybrid Modified Annuity) mode:-
Punalur - Ponkunnam stretch (82 km) of Punalur – Thodupuzha Road
2.2.0.2 Road upgrading under Engineering Procurement Construction (EPC) mode :-
Perimbilavu – Pattambi- Perinthalmanna Road – 41 km
2.3 Sub Component A1 (US$322 mn) Consists of the following civil contracts:
Monthly Progress Brief – February 2015 Page 11
SI. NO.
CONTRACT PACKAGE NAME OF WORK LENGTH (KM)
1. KSTP-II/UG-1 Kasargod – Kanhangad 27.78
2. KSTP-II/UG-2 Pilathara – Pappinisery 20.90
3. KSTP-II/UG-3 Thalassery – Valavupara 54.00
4. KSTP-II/UG-4 Chengannoor - Ettumannoor 45.40
5. KSTP-II/UG-5 Ettumannoor- Muvattupuzha 40.96
6. KSTP-II/UG-4A Thiruvalla Bypass along Chengannoor -
Ettumannoor 2.3
7. KSTP-II/UG-6 Ponkunnam - Thodupuzha 50
8. KSTP-II/UG- Punalur-Ponkunnam 82
9. KSTP-II/UG-7 Perumbilavu - Perinthalmanna 41
2.4 Supervision Consultancy Under this component 2 supervision consultancies CSC1 and CSC 2, 2 Independent
engineering services, Transaction Advisory Service for PPP are included. Contract
Agreement for Consultancy for CSC 1 for 190 Km of upgradation road has been executed
with M/s Egis International in JV with Egis India Consulting Engineers Pvt. Ltd on
28.02.2013 and mobilized and in place. Egis has established rented office for Team
Leader at Thiruvananthapuram near to Client’s Office and started functioning from April
2013. Also RE offices at Kanhangad in Kasargod District for package - 1, Pazhyangadi in
Kannur District for package – II and at Uliyil near Mattannur in Kannur District for
package – III are functional.
M/s MSV International USA is the selected consultant for Construction Supervision for
the Ponkunnam – Thodupuzha stretch (50 km) CSC-2. The length of road covered is 50
km and the assignment commenced on 15 May 2014.
2.5 Sub Component A2 (US$ 91 mn) DPR for this sub component (Punalur – Ponkunnam – 82 Km under PPP) completed and
schedule prepared by the consultants. M/s L&T Ramboll, Chennai in association with
M/s Fortress has been selected for the Transaction Advisory Services and activities in
progress. The Investor Meet is proposed on March 2015 at Kochi.
2.6 Component B – Road Safety Management (US$ 22 mn) The baseline survey for the proposed safe demonstration corridor has been completed by
‘NATPAC’ and report shared with Bank. M/s VicRoads, Australia has been selected as
consultant for Road Safety Capacity Building and program management and activities in
progress.
Monthly Progress Brief – February 2015 Page 12
2.7 Component C – Institutional Strengthening (US$ 10 mn) 2.7.0.1 Consultancy Services
The following Consultancy services were procured.
1. Consultancy for Road User Perception Survey has been completed for 363 Km of
Project Road through M/s Sherwood Consultants and report shared with Bank.
2. Consultancy for Prioritization and DPR Preparation for 1000 Km of Improvement
of State roads was entrusted with M/s Egis India Consulting Engineers Pvt. Ltd
and final report submitted. DPR for 439 km roads has been completed. The
preliminary project report was submitted to Government for posing for External
Financial Assistance from the ADB and JICA.
3. Consultancy for Strategic Option Study (SOS) for 8570 Km newly declared MDR
was completed by M/s CDM Smith Associates Pvt. Ltd. Study report has been
handed over to PWD and further action to improve these roads will be taken by
them using their own funds.
4. Consultancy services for Developing Multi Model Integrated Transport Hub at 3
cities, Trivandrum, Kozhikode and Kochi was completed and report forwarded to
Government. This report was also shared with NATPAC for consideration while
preparing Comprehensive City Development Projects.
5. The EOI notification study on Strategic Road Network in Package II, III and IV has
been sent to Bank for review. Mr. Babu Jacob, Former Chief Secretary Kerala is
under consideration for the position of Client Executive Program Sponsor.
6. Rebidding for the selection of consultant for Development of Integrated
Information management System is being done. The EoI notification under review
by Bank.
7. The purchase of Project Management Software is at final stage. Agreement with
M/s Backend, Bangalore has been got installed and training to Engineering given
8. The EoI notification for selection of consultant for Community Participation and
User Engagement in Road Safety and Design has been invited. Seven EoIs are
received and short listing is being done.
Monthly Progress Brief – February 2015 Page 13
2.8 Project Cost and Disbursement
Sl No
Claim Date
EXPENDITURE in Lakh
AMOUNT CLAIMED in Lakh
DISBURSED BALANCE FUNDS AVAILABLE FOR CLAIM (MUSD) USD in
millions
TOTAL TOTAL TOTAL TOTAL
216.00
Front end fee 0.54 215.46
1 Retroactive 15.06.12 to 15.06.13 1,863.95 1,043.00
1.69 213.77
2 1st Quarter 213.77
3 2nd Quarter
01.07.13 to 30.9.13 1,355.79 764.00
1.23 212.54
4 3rd quarter 01.10.13 to 31.12.13 1,906.01 1,071.00
1.71 210.82
5 4th quarter
01.01.14 to 20.03.14 2,696.00 1,510.00
2.50 208.32
21.03.14 to 31.03.14 53.79 30.00
0.05 208.27
6 1st Quarter
01.04.14 to 18.06.14 1,826.41 1,023.00
1.70 206.57
19.06.14 to 30.06.14 14.69 8.23
0.01 206.56
7 2nd Quarter
01.07.14 to 30.09.14 1,405.61 787.00
1.27 205.29
8 3rd Quarter 30.09. 14 to 31.12.14 3,790.21 2,124.00
3.44 201.85
9. 4th Quarter 01.01.2015 to 28.02.2015 3,706.35 2,076.00 ‐ 201.85
18,618.81 10,436.23 14.15
Monthly Progress Brief – February 2015 Page 14
2.9 Project location map
Monthly Progress Brief – February 2015 Page 15
3.0 Upgradation Works Bids were invited for the Contract Packages 1 & 2 on 31.10 2012, Contract package 3 on
12.12. 2012 and Contracts awarded to the lowest evaluated Bidders after getting NOC
from Bank. The bids for package 4 & 5 were invited on 17.04.2013 and lowest evaluated
bidders selected. Bids for Package 4A invited on 02.07.2013 as per NCB norms and
Letter of Acceptance was issued on 29.10.2013 and is temporarily stopped due to a case
before the National Green Tribunal (NGT) and resumed after the verdict of NGT. Works
in Package 6 were commenced and in progress. The works in contract Package IV was
awarded to M.s Delma-Sreedhanya and contract signed.
363 Km of upgradation civil works are divided into 9 Contract packages. SI. NO.
CONTRACT PACKAGE
NAME OF WORK CONTRACTOR
1. KSTP-II/UG-1 Kasargod – Kanhangad RDS Projects, Kochi
2. KSTP-II/UG-2 Pilathara – Pappinisery RDS Projects, Kochi
3. KSTP-II/UG-3 Thalassery – Valavupara SACYR-ESSAR JV
4. KSTP-II/UG-4 Chengannoor - Ettumannoor Delma-Sreedhanya
JV
5. KSTP-II/UG-5 Ettumannoor- Muvattupuzha NAPC Ltd, Chennai
6. KSTP-II/UG-4A Thiruvalla Bypass along
(Chengannoor – Ettumannoor) EKK & Co, Kochi.
7. KSTP-II/UG-6 Ponkunnam - Thodupuzha GHV – EKK JV
8. KSTP-II/UG-7 Perumbilavu – Perinthalmanna (EPC) LA initiated
9 KSTP-II/UG-8 Punalur – Ponkunnam (PPP) TA consultancy mobilized
The works are being executed under FIDIC (5th edition) Conditions of Contract. The
work involves improvement of State Highways including geometric improvements and
realignments to standard 2 lane of 7 m carriageway, 2.5 m paved shoulders. The
Construction Works include:
Widening the existing pavement where it is less than design width;
Scarification, clearance, earthworks,
granular sub-base, wet mix macadam base course, bituminous mix surfacing,
Construction of overlays to the existing pavement, inclusive of regulating course to a designed vertical profile;
Geometric realignments at specific locations;
Construction of paved shoulders;
Construction and maintenance of diversion roads
Construction of lined and unlined longitudinal drains, covered drains and footpaths in urban areas;
Monthly Progress Brief – February 2015 Page 16
New culverts, new bridges and rehabilitation of existing bridges/culverts and protective works
Provision of road signs and markings;
Provision of traffic safety features - road furniture and other road safety appurtenances,
Routine maintenance and maintenance during Defects Notification Period.
Environmental protection measures and Social enhancement works/ landscaping works etc.
3.1 Summary of Progress (works) The following tables present the summary of progress in each contract package during the quarter under report.
Contract packages Contract value
(Rs. Crore)
Cumulative
target in
percentage up to
end of February
2015
Achieved
cumulative
percentage upto
end of the
February 2015
Balance period
(months)
KSTP/PMT/UG-I 1,33,05 32.13% 24.49% 13 (extended)
KSTP/PMT/UG-II 118.20 29.00% 17.91% 13 (extended)
KSTP/PMT/UG-III 234.99 70.30% 6.99% 13
KSTP/PMT/UG-V 171.49 9.20 3.73% 17
KSTP/PMT/
UG-IVA 31.80 47.90% 5.55% 9
KSTP/PMT/UG-VI 227.13 19.96 15.12% 21
KSTP/PMT/UG-IV 293.58 - Work in progress 30
3.1.0.1 Details of Supervision Consultancy Assignments:
Name of consultant
Contract signed
Contract Period
Commencement Date
Contract Amount (Rs.)
Work Package
CSC-1 – M/s Egis International in JV with M/s Egis India Pvt. Ltd.
28.02.2013
42 months
04.04.2013 18,36,04,600
I, II, III, IV, IVA & V (190 km)
CSC-2 – M/s MSV International USA
14.05.2014
30 months
14.05.2014 4,41,88200 VI
(50 km)
3.2 General Issues: The progress is not upto the expectation. The major factors that hindered the progress
of works were:
Monthly Progress Brief – February 2015 Page 17
1. Delay in obtaining statutory clearances for erection of plants and crushers from
the State Pollution Control Board, Mining and Geology Department and local
bodies.
2. Unprecedented unseasonal rains affected adversely all the contract Packages
work progress in the early stages
3. Resistance in identifying, erecting and operating crushers and quarry from the
local people.
4. Poor cashflow problems with the contractors.
5. Shortage of machinery, labour force in most of the contracts.
6. Frequent changes needed in key personnel in some of the contracts
7. Migrant labours working in all packages and labourers not available during
festival season for long duration.
8. Lack of planning and managerial issues in contracts I, II, III & V
issues 1 to 3 were beyond the control of the contractors, and by now, all the
clearances have been obtained and the problems are sorted out. The contractors were
instructed to speed up the works during working season to show better results.
However the contractor for Package III is still not in a position to speed up the works as
anticipated.
In view of the adverse weather conditions due to continuous rainy season upto
end November 2014, and other reasons explained above, the contractors were not able to
complete the works in milestone-1 for Packages 1,2 and 3 and this also will affect the
time schedule for milestones-II and III. It has been requested by the contractors to
extend the time limits.
The Steering Committee has recommended extension for milestones I, II & III for
Packages 1 and 2. Also the time of completion for milestone – 1 for Package-3 was
proposed to the Council of Ministers. Accordingly the Council of Ministers endorsed the
recommendations of Steering Committee. The extended time limit for Milestone-I for
Package-3 was upto 31.12.2015. However the contractor could not complete the works
in Milestone-1 with in this date. Stringent action against the contractor are being taken.
Monthly Progress Brief – February 2015 Page 18
Scope of Works Viaduct – 1 Major Bridge – 2 Minor Bridge _ 2 Widening Bridge – 2 New culverts _ 16 Widening Slab culverts – 16 Reconstruction _ 9 Foot path _ 6.7 Km Drain – 22.20 Km Solar Lights
The following sections describe Civil Works Contract packages in detail:
4.1 CURRENT STATUS OF WORKS 4.2 Contract Package I Upgradation of Road from Kasargod to Kanhangad of SH 57
4.3 Contract Details Letter of Acceptance Date 06.03.2013
Agreement Date 01.04.2013
Name of Contractor M/s RDS Projects Ltd, Kochi
Contract Price Rs.133,05,79,485/-
Notice to Commence 24.04.2013
Total Length 27.78 Km
Contract Period 24 months
Completion Date 23-04-2015 extended to
Defect Liability Period 365 days
1st Milestone Km. 0+000 – Km. 10+000 - 22nd February 2014 revised
to 22 March 2015
2nd Milestone Km. 0+000 – Km. 20+000 - 19 November 2015
3rd Milestone Km. 0+000 – Km. 27+780 - 26th March 2016
4.4 Progress of Works
4.5 Summary of progress for major items is as follows:
Milestone I II III
Length in km 10 20 27.78
Length handed over to contractor in km 10 20 27.78
Monthly Progress Brief – February 2015 Page 19
Milestone I II III
Unencumbered land available to the contractor in km 10 20 27.78
Stretch completed in all respects in km 0 0 0
FW HW
GSB completed in km 6.260 1.627
WMM completed in km 5.840 1.785
DBM completed in km 5.675 1.602
BC completed in km 0
CD completed in Nos. 14
• Viaduct at Km.3+392 – Pile Caps 8(P1, P2 P3, P4, P5, P6, A1, and A2) completed.
Pier Caps 6 (P1, P2 P3, P4, P5and p5) completed. Out of the 54 piles 54 completed.
Deck slab A1-P1, P1-P2, P4-P5 and P6-A2 completed. P2-P3 & P5-P6 Girder is in
Progress and P3-P4 Staging work yet to be started.
• RCC Retaining wall work in progress from Ch. 0+280 to 0+290, Ch. 0+310 to 0+320
and 2+850 to 3+180. Total 275m Raft completed. Work stopped due to Land Slide,
alternate proposal of Soil Nailing along the cut slopes submitted.
• Chithari at Km.18+400 – Out of the 34 piles 29 completed. Pile caps P1, P2, P3 &
A2 completed. A1 – Piling work is in Progress, P1- Substructure completed and P1-P2
Staging in Progress. P2-P3 Deck Slab Completed and P3-A2 Girder completed.
• MS- I
• Box Culverts - Km. 2+704, 11+620 and 11+870 are in Progress. Culvert &
Return walls completed for Km.1+750, Km.1+974, Km. 2+215, Km. 2+454, Km.
4+970, Km. 5+500, Km. 5+737, Km. 6+630 and Km. 8+894.
• Slab Culverts – Km. 7+015, Km. 7+463, Km. 8+093, Km. 8+679 and 9+921 are
completed and Km. 11+580 yet to be started.
• MS- II
• Box Culverts - Km. 13+834 and Km. 15+490 are in Progress and remaining 13
nos of culverts are yet to be started.
• Slab Culverts – Total 02Nos are yet to be started.
Precast drain
LHS -Km. 5+120 to 5+500, Km.6+120 to 6+210, Km. 6+232 to 6+242, Km. 6+255 to
6+450, Km. 9+810 to 9+899.5, Km. 9+920 to 9+980, Km. 10+020 to 10+110, Km.
10+150 to 10+250, km. 10+270 to 10+320 and km. 10+410 to 10+420 done.
Monthly Progress Brief – February 2015 Page 20
RHS - Km. 4+520 to 4+600, Km.4+640 to 4+670, Km. 6+120 to 6+240, Km.
8+115 to 8+300, Km. 9+800 to 9+995, Km. 10+060 to 10+140 and Km. 10+680 to
10+730 done.
• Box cell Minor Bridges
• Km. 2+600 – Excavation completed at LHS and PCC completed at RHS.
• Km. 6+510 – Box cell wall 2nd completed (03cells out of 05 cells) at LHS and RHS
retained.
SCHEDULE OF CULVERTS AND DRAINAGE WORKS
Nature of work
Total num
ber
No. dwgs app
roved
Num
ber completed
Num
ber in progress
Num
ber remaining
Total N
umbe
r
No. dwgs app
roved
Num
ber completed
Num
ber in progress
Num
ber remaining
Total num
ber
No. dwgs app
roved
Num
ber completed
Num
ber in progress
Num
ber remaining
Culverts Milestone ‐ I
(1 to 2.8Km and 3.80 to 12.0Km )
Milestone ‐ II (12 to 22Km.) Milestone ‐ III
(0 to 1.0Km, 2.80 to 3.80Km and 22 to 27.78Km.)
Widening Slab/Box Culverts
8
8
5
‐
3
2
‐
‐
‐
2
4
‐
‐
‐
4
Reconstruction Slab/Box
7
7
6
1
‐
9
2
‐
1
8
1
‐
‐
‐
1
New Box Culvert 5
5
3
2
‐
6
1
‐
1
5
3
‐
‐
‐
3
Total culverts
20 20
14
3
3
17
3
‐
2
15
8
‐
‐
‐
8
Bridges/ROB Retained**
2
‐
‐
‐
‐
2
‐
‐
‐
‐
‐
‐
‐
‐
‐
Bridges Widening ***
2
2
‐
2
‐
‐
‐
‐
‐
‐
‐
‐
‐
‐
‐
New Bridges/Viaduct*
‐
‐
‐
‐
‐
1
1
‐
1
‐
1
1
‐
1
‐
4.6 Progress Considering the Contract price up to February 2015. Up to previous Month This Month Cumulative to end of this Month
Target Achieved Target Achieved Target Achieved 23.39% 18.84% 8.73% 2.65% 32.13% 21.49%
Monthly Progress Brief – February 2015 Page 21
4.7 Physical progress Bar Chart (Quantity Wise)
4.8 Utilities Shifting of utilities such as water lines, telephone cables and associated accessories are
in progress. Relocation of electric lines/poles and cutting of trees are in progress during
this month. Electrical Poles shifted in Mile Stone I are 299nos and 259nos in Mile Stone
II shifted up to date and 558 poles and some of the accessories are received by the
Contractor. Total 413 numbers of the trees have been cut till date. Contractor shifted
558 nos. of electric poles and 16 no. of transformer till date. No delay can be accounted
on obstruction due to utility shifting and Contractor has enough work fronts.
Monthly Progress Brief – February 2015 Page 22
4.9 Potential Issues • Lack of resources at site which reflected in planning of works at site, delay in preparing
mix designs, delay in submission of working cross sections, in preparation of survey
data etc.
• Shortage of labour force and equipments
• One Crusher and HM Plant for Package I and II. Aggregate production is inadequate
• Acute shortage of aggregates have seriously hampered the progress.
• Monthly Achieved Progress as per revised work program is not improving and
progress of works is not near the targets. Instructions issued to Contractor for taking
measures to enhance the progress of works.
• Poor cash flow of contractor
4.10 Payments to the Contractor Mobilization advance, Equipment advance and Interim payment Certificate for works up
to (IPC-9) was paid to the Contractor amounting to Rs. 320031855/-. Timely payments
are released to the contractor. The Steering Committee held on 28.06.2014 lowered the
threshold limit of minimum IPC amount for Rs. 1.5 crores from Rs. 3.00 crores to
facilitate the cash flow of contractor.
4.11 Compliance with Statutory Clearances The action taken by the Contractor for complying with the statutory requirements is
summarized below.
Monthly Progress Brief – February 2015 Page 23
Type of plant Type of Approval /Licence
Date of Issue Date of Expiry
WMM Plant Consent to Establish 27-11-2013 26-11-2016 Consent to operate 17-05-2014 28-01-2017 License 21-06-2014 31-12-2014
Batching Plant Consent to Establish 27-11-2013 26-11-2016 Consent to operate 17-05-2014 28-01-2017 License 21-06-2014 31-12-2014
Labour Camps
Consent to operate Building permit 30-4-2014 License 14-03-2014
4.12 Environment Management at Work Sites
Environmental Engineer of CSC visited project site on 20th January 2015. No major
deviation noticed. Contractor was asked to develop oxbow land along the corridor
wherever enough land is available. Contractor will prepare site specific plans for
approval of the Engineer. Further direction was also given to initiate tree planting by
next monsoon from June 2015.
4.13 Traffic Management and Road Safety Measures
The Contractor has provided safety precautions such as flags, safety signboards, traffic
cones, blinkers and safety tapes at the work site. The Contractor is also required to
provide personal safety equipment to his workers such as jackets, safety shoes, face
shields, and hand gloves as appropriate to the nature of their work. The workers at
various locations were seen not using personal safety equipments. The traffic and road
safety measures adopted by the contractor have to be improved further. Road safety
aspects to be improved at construction sites.
The Contractor has provided safety precautions which was inadequate. Therefore RE has
imposed damages as per sub clause 14.6of part B specific provision for various
locations. The Contractor is also required to provide personal safety equipment to his
workers such as jackets, safety shoes, face shields, and hand gloves as appropriate to
the nature of their work.
Monthly Progress Brief – February 2015 Page 24
5.1 Contract Package II Upgradation of Road from Pilathara to Pappinissery of SH 67
5.2 Contract Details
Letter of Acceptance Date 05.03.2013
Agreement Date 01.04.2013
Name of Contractor M/s RDS Projects Ltd, Kochi
Contract Price Rs.118,29,77,833/-
Notice to Commence 23.04.2013
Total Length 20.90 Km
Contract Period 24 months
Completion Date 22nd April 2015 extended to 14 March 2016
Defect Liability Period 365 days
1st Milestone Km. 0+000 – Km. 08+000 - 22nd February 2014 Revised to 21 March 2015
2nd Milestone Km. 0+000 – Km. 14+000 - 07th November 2015
3rd Milestone Km. 0+000 – Km. 20+900 - 14th March 2016
5.3 Progress of Works
5.3.0.1 Summary of progress for major items is as follows:
Milestone I II III
Length in km 8.000 14 20.9
Length handed over to contractor in km 8.000 14 -
Scope of Works New ROB – 2 Repair of Bridge – 2 New Box culverts _ 9 Widening Slab culverts – 20 Reconstruction _ 8 Drain – 26.04 Km Foot path _ 12.6 Km Solar Lights -
Monthly Progress Brief – February 2015 Page 25
Milestone I II III
Unencumbered land available to the contractor in km 8.000 14 -
Stretch completed in all respects in km - - -
FW HW FW HW
GSB completed in km 5.900 0 0.800 1.740
WMM completed in km 5.900 0 0 1.290
DBM completed in km 5.800 0 0 1.070
BC completed in km 2.540 0.120 0 0
CD completed in Nos. 11 0
5.4 Structure • Confirmatory boring for Abutment A2, P22, P20, P18, P16, P14, A1, P1, P3, P5, P7, P9
(12Nos) completed for ROB @KM19+950 (Pappinissery).
• Confirmatory boring for A1, A2 and P4 (3Nos) of ROB@ Km. 7+420 (Thavam)
completed.
• Railway Department has approved GAD of ROB @KM 7+420(Thavam) in July-
2014.Now tree cutting permission for the trees lying in railway land has been sought
by the contractor from Railway department through KSTP division, Kannur for the
construction of diversion road works and the permission is awaited from Railway.
• Test pile casting has been done for ROB @KM7+420 and initial load test on pile is yet
to be started
• ROB at Km. 7+420 Piling Work started on 18/12/14, Piling Work 9 No’s out of 24
No’s completed. Test pile casting has been done for ROB @KM19+950 and initial load
test on pile completed.
• ROB at Km. 19+950 Piling Work 71 No’s out of 132 completed. Pile Cap for A1
Abutment is in Progress.
5.5 Work progress considering the contract price
For previous Month This Month Cumulative to end of this Month
Target Achieved Target Achieved Target Achieved 20.38% 15.78 8.62% 2.13% 29.00 17.91%
Monthly Progress Brief – February 2015 Page 26
5.6 Physical Progress
5.7 Strip Chart
0 100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
1600
1700
1800
1900
2000
2100
2200
2300
2400
2500
2600
2700
2800
2900
3000
3100
3200
3300
3400
3500
3600
3700
3800
3900
4000
4100
4200
4300
4400
4500
4600
4700
4800
4900
5000
5100
5200
5300
Miscellaneous WorksBridges Nos Culverts Nos 8 Nos 4 NosDrains and Walls 1.64Bituminous Concrete 2.66Dense Bituminous Macadam 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 4.90Wet Mix Macadam 2nd 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5.00Wet Mix Macadam 1st 1 1 5.10Granular Sub base 1 1 5.10 1KMSubgrade 1 1 5.30 3KMEW - Embankment 1 1 5.30 1KM
EW - Embankment 5.40Subgrade 5.25Granular Sub base ## 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ## 5.15Wet Mix Macadam 1st ## 5.02Wet Mix Macadam 2nd 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5.00Dense Bituminous Macadam 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 5.00Bituminous Concrete 1 1 2.54Drains and Walls 1.75Culverts Nos Bridges NosMiscellaneous Works
Legend Completed Activity
On going Work
(No./Km)
RIG
HT
SID
EL
EFT
SID
E
Chainage (Km)
Culverts & Bridges Cum. Completed
Work (No/Km)
Monthly Progress Brief – February 2015 Page 27
5400
5500
5600
5700
5800
5900
6000
6100
6200
6300
6400
6500
6600
6700
6800
6900
7000
7100
7200
7300
7400
7500
7600
7700
7800
7900
8000
8100
8200
8300
8400
8500
8600
8700
8800
8900
9000
9100
9200
9300
9400
9500
9600
9700
9800
9900
1000
010
100
1020
010
300
1040
010
500
1060
010
700
Miscellaneous WorksBridges Nos 1 NosCulverts Nos 3 No 2 NosDrains and Walls 0.25Bituminous Concrete 0.00Dense Bituminous Macadam ## ## ## ## ## ## ## ## 1 1 1 1 1 1 1.49Wet Mix Macadam 2nd 1.49Wet Mix Macadam 1st 1.93Granular Sub base 2.20Subgrade 2.20EW - Embankment 2.69
EW - Embankment 3.24Subgrade 2.70Granular Sub base 2.70Wet Mix Macadam 1st 1.97Wet Mix Macadam 2nd 1.60Dense Bituminous Macadam ## ## ## ## ## ## ## ## ## ## ## ## 1.29Bituminous Concrete 0.00Drains and Walls 0.12Culverts Nos 2 NosBridges Nos 1 NosMiscellaneous Works
Legend Completed Activity
RIG
HT
SID
E
Culverts & Bridges Cum. Completed Work
(No/Km)
On going Work
(No./Km)Chainage (Km)
LE
FT S
IDE
5.8 Potential Issues • Lack of experienced staff at site which reflected in planning of works at site, delay in
preparing Mix designs, delay in submission of working cross sections, in preparation
of survey data etc.
• The work suffered due to shortage of aggregate, cement, steel etc.,
• The approval for General Arrangement Drawing of ROB@Km7+240 (Thavam) has
been obtained from Railway. Now tree cutting permission for the trees lying in railway
land has been sought by KSTP and the permission is awaited from Railway for which
employer is liaisoning with the Railway Personals.
• RoB work slow due to non diversion of entire traffic.
• The contractor has established one quarry, crusher and HM Plant for contract I and
II. The aggregate production is not sufficient to meet the requirement of both
packages. Only one crusher for both Package I & II
• Poor cash flow of contractor.
• Equipment and shortage of labourers
• The monthly targets as per revised work program are not achieved by the contractor. Strict instructions issued to contractor to accelerate work program and achieve targets.
5.9 Payments to the Contractor Mobilization advance and Equipment advance and all IPC’s (upto IPC-7) was paid to the
Contractor amounting to Rs. 27,95,37,737/-. The Steering Committee held on
Monthly Progress Brief – February 2015 Page 28
28.06.2014 lowered the threshold limit of minimum IPC amount for Rs. 1.5 crores from
Rs. 3.00 crores to facilitate the cash flow of contractor.
5.10 Environment Management at Work Sites Site Visit conducted by Environmental Engineer of CSC on 20th & 21st January 2015 and
reviewed the measures taken by the Contractor for implementing the mitigation
measures proposed in the EMP. Instructions were given to avoid accumulation of debris
along the project site and at ROB location to remove the debris from the site periodically.
Regular sprinkling of water at active work phase are to be continued. The Environmental
management for Pappinissery ROB at Ch.19+950 to be improved. The waste
management system in the Camp are being followed properly and advised by World
Bank to replicate such systems in the other contract packages also. It is noticed that
waste material from pile drilling at Thavam ROB is directly dumped in to natural water
stream which shall be stopped immediately.
As the measures adopted by the Contractor for implementing EMP is satisfactory but
some improvement is required in ROB sites and Road. Contractor has provided
additional septic tank for labour camp at RoB sites.
5.11 Traffic Management and Road Safety Measures The contractor is required to provide safety precautions such as barricading, flags,
safety signboards and traffic cones at all work zones to ensure safety for all road users.
Personal safety equipment such as jackets, safety shoes, face shields and hand gloves
are to be provided to all workers as necessary. Instructions were given to provide
adequate safety sign boards and fencing all along the active work sites. The safety
arrangements at ROB locations are very poor and to be improved. The traffic at these
locations is to be fully diverted during construction. The deviation road to be urgently
repaired to divert traffic to close to ROB.
The safety measures adopted by the contractor were not satisfactory and due to non-
compliance, RE has imposed of damages as per sub clause 17-2 of part B specific
provision for various location Site visit conducted by the Environmental Officer of CSC
and the observations are also sent to the contractor for urgent corrective action.
Monthly Progress Brief – February 2015 Page 29
6.1 Contract Package III Upgradation of Road from Thalassery to Valavupara of SH 30
6.2 Contract Details Letter of Acceptance Date 19.03.2013
Agreement Date 06.05.2013
Name of Contractor M/s SACYR–ESSAR JV, Mumbai
Contract Price Rs.234,99,31,763/-
Notice to Commence 29.06.2013
Total Length 54.00 Km
Contract Period 30 months
Completion Date 28th December 2015
Defect Liability Period 365 days
1st Milestone Km. 1+200 – Km. 16+200 28th April 2014 Revised to 6 August 2014
2nd Milestone Km. 1+200 – Km. 36+200 - 24th February 2015
3rd Milestone Km. 1+200 – Km. 55+200 - 29th December 2015
6.2.0.1 A summary of progress for major items is as follows. Milestone I II III
Length in km 15 20 19
Length handed over to contractor in km 15 20 19
Unencumbered land available to the contractor in km
15 20 19
Stretch completed in all respects in km 0
Scope of Works Construction of Major Bridges – 3 Construction of Minor Bridge – 4 New Box culverts _ 21 Widening Slab culverts – 88 Reconstruction of Culverts _ 50 Drain – 65.30 Km Footpath _ 44Km Solar lights
Monthly Progress Brief – February 2015 Page 30
Milestone I II III
GSB completed in km 1.50
WMM completed in km 0.40
DBM completed in km 0
BC completed in km 0
CD completed in Nos. 16 (except aprons)
3 (except aprons )
6.3 Utilities Utilities such as water lines, telephone cables and associated accessories, electrical lines
and associated accessories and trees are remaining to be removed / shifted. Relocation
of electrical utilities and water supply line using materials issued by KSTP is the
responsibility of Contractor. Similarly, removal of stumps of trees cut by agencies
engaged by KSTP is also the responsibility of Contractor. KSTP/PMT has made
arrangements with BSNL and other private agencies for relocation of cables, telephone
posts and telephone pillars. Progress achieved on these activities:
• Relocation of electric poles (PSC) : 458 No
• Relocation of A poles : 267 No
• Stringing of HT line with ASCR Raccoom Conductors : : 17.85 km
• Stringing of LT line with ASCR Conductors : 17.85 km
6.4 Work Progress as end February 2015:
Activities During the month Total Remarks
Structure Works: • Major Bridge at km 2+910
i. Confirmatory Boring 3 Nos.
ii. Piling 1 No. 22 Nos. Routine pile load test yet to be completed.
iii. Pile cap 2 No. Pile cap of abutment A1 is yet to be carried out.
iv. Pier/ Abutment with
cap
2 No.
• Major Bridge at km 19+758
i. Confirmatory Boring 4 Nos. Report of pier P2 yet to be submitted.
ii. Piling 28 Nos. Routine pile load tests are yet to be completed.
v. Pile cap 1 No. 2 No. Pile cap of Abutment A1 & P2 are yet to be
Monthly Progress Brief – February 2015 Page 31
Activities During the month Total Remarks
carried out. vi. Pier/ Abutment with
cap
1 No. 2 No. P1 & A2 completed
• Minor Bridge at km 21+162 Confirmatory Boring 1 No. Foundation work yet
to be initiated. • Minor Bridge at km 29+570
i. Confirmatory Boring 2 Nos. ii. Raft Foundation
1 No
Foundation of abutment A1 completed. Abutment A2 PCC completed and reinforcement work is in progress.
iii. Pier/ Abutment with
cap
1 No Abutment A1 completed except abutment cap.
• Minor Bridge at km 35+405
i. Confirmatory Boring 2 Nos. ii. Raft Foundation 1 No. 1 No. Raft foundation for
Abutment A2 side completed on 24.01.2015
iii. Pier/ Abutment with
cap
Abutment A2 1st lift completed.
• Major Bridge at km 42+195 iv. Confirmatory Boring 1 No. Confirmatory boring
for abutment A1 completed, report yet to be submitted. Test pile casting completed on 24.01.2015at A1 side. Confirmatory boring for abutment A2 and pier locations are yet to be started.
v. Raft / Pile Foundation 1 No. 4 No. Pile A1G7, A1G6, A1G2 & A1G8 completed.
• Major Bridge at km 53+865 Confirmatory borings at abutment and pier locations are yet to be started.
• SP Tests for Culvert Locations 81 No.
• Widening of Slab Culverts 3 No 16 Nos. 2 No. in progress. • Pipe Culvert Nil
completed. 6 Nos. in progress. Concrete Pipes for culverts not procured
• Box Culvert 2 No. 3 No. 10 Nos. in progress.
Monthly Progress Brief – February 2015 Page 32
Activities During the month Total Remarks
Casting of Precast drains at base camp
2104.5m 17614.5 m
Precast drain units erected at site. 3267 m 13660 m
Casting of Precast drain cover slab at base camp
192.5 m 375 m
Gabion wall construction 1400 Cum Submission of manufacturing test certificates and rectification still pending.
Considering the overall value of work 234.99 crores, progress up to 25th January 2015 is given in table below:
Up to end of Previous month This month Cumulative to end of this month
Target Achieved Target Achieved Target Achieved
62.70% 5.91% 7.70% 1.08% 70.30% 6.99%
6.5 Schedule of culverts and drainage works
Nature of work
Ori
gina
l num
ber
No.
dw
gs a
ppro
ved
Num
ber
com
plet
ed
Num
ber
in p
rogr
ess
Num
ber
rem
aini
ng
Ori
gina
l num
ber
No.
dw
gs a
ppro
ved
Num
ber
com
plet
ed
Num
ber
in p
rogr
ess
Num
ber
rem
aini
ng
Ori
gina
l num
ber
No.
dw
gs a
ppro
ved
Num
ber
com
plet
ed
Num
ber
in p
rogr
ess
Num
ber
rem
aini
ng
Culverts
Widening Slab Culverts 24 15 14 1 9 28 8 2 26 19
Slab Culvert retained 6 6 8 8 1
New Pipe Culverts(2 Culverts converted to Pipe culverts in MS-I) 7 4 4 3 22 3 2 20 23
New Box Culvert 10 8 1 4 5 11 5 1 7 3 23
Total culverts 47 27 15 9 23 69 16 3 9 57 66
Bridges 1 1 1 4 4 3 1 2
Milestone - I Milestone - II Milestone - III
6.6 Potential Issues The following issues are very critical which may have adverse impact on the timely
completion of the Project.
• Delay in mobilization of crusher, WMM Plant, Hot Mix Plant • Acute shortage of Construction materials. • Implementation of EMP & safety management plan - Poor • Shifting of electrical and water utilities - slow
Monthly Progress Brief – February 2015 Page 33
• Identification of adequate sources for construction materials not actively following • Procurement of POT cum PTFE bearings – not initiated • Initial & routine Pile load test delayed • Submission of revised Work Programme – delayed delayed • Submission of corrected working cross sections • Procurement of applicable permits for establishing and operating HMP and WMM
plant not obtained • Acute shortage of cash flow condition of contractor • Absence of lead partner • Frequent change of contractors key personnel
6.7 Physical Progress
6.8 Physical Progress S Curve
Monthly Progress Brief – February 2015 Page 34
6.9 Payment to Contractor Mobilization advance and IPCs paid to the contractor amounting to
Rs. 21,64,43541/-. Up to IPC-4. The Steering Committee decided to lower the threshold
limit of minimum IPC amount for Rs. 1.50 crore from Rs. 3.00 crores. Timely payments
were made to the contractor.
6.10 Implementation of EMP Instead of establishing the quarry and crusher, the contractor has leased out two quarry
and crusher for the supply of raw materials required for the project. The details of these
facilities were not reported to the CSC. The contractor has established a base camp near
Chavassery where the construction camp, labour camp, and construction plant site were
established.
6.11 Compliance with Statutory Clearances The action taken by Contractor for complying with statutory requirements is summarized below:
Compliance with Statutory Requirements
Unit Status of Compliance Remarks Crusher and quarry
Three existing quarry and crusher were identified for the supply of materials required for the project.
Documents to show the details of the quarry and crushers, the agreement with them, the valid Consent to Operate obtained by them etc. were not furnished.
Hot Mix Plant Proposed inside the present camp. Consent for operate HM plant obtained f
Issue date 28.11.2014 valid till 31.10.2017
WMM Plant Consent application submitted on
Not received
Base camp and batching plant
Obtained Consent to Establish and Consent to Operate from Kerala State Pollution Control Board
Date of Issue of Consent to Operate-09.04.2014 and Valid Upto 31.03.2016
6.12 Environment Management at Work Sites The Environmental Engineer of CSC visited the project site on21st January 2015 and
reviewed the measures taken by the Contractor for implementing the mitigation
measures proposed in the EMP. Instructions were given to avoid accumulation of debris
along the project site and to remove the debris from the site periodically. Regular
sprinkling of water at active work phase and maintenance of proper records of water
sprinkling are to be carried out. The environmental management at construction sites
like Drain, Bridgework sites to be improved. It is also noted that waste from pile driving
is not disposed properly. Notices were issued.
Monthly Progress Brief – February 2015 Page 35
As the measures adopted by the Contractor for implementing EMP is not satisfactory,
Environmental Engineer recommended for imposing penalty as per contract agreement.
Resident Engineer has imposed of penalty that is 10% of the interim payment certificate
will be withheld from next IPC as per sub clause 14.6 of part B specific provision. The
stock height of the vent pipe of the DG set at HM plant to be increased and proper
geosite enclosures to be provided.
6.13 Traffic Management and Road Safety Measures The Contractor has provided safety precautions such as flags, safety signboards, traffic
cones and safety tapes at the work site. The Contractor is also required to provide
personal safety equipment to his workers such as jackets, safety shoes, face shields, and
hand gloves as appropriate to the nature of their work. The workers at various locations
were not generally using personal safety equipments. Traffic and road safety measures
adopted by the contractor have to be improved further. Procurement of sign boards,
delineators and blinkers are not provided at site. The big pot holes at construction sites
are hazards to the traffic. This has to be rectified urgently.
The safety measures adopted by the contractor were not satisfactory and due to non-
compliance, RE has imposed of damages as per sub clause 17-2 of part B specific
provision for various locations. It is noticed that road excavation was also started in
some locations without establishing WMM and HM plants. No road excavation will be
allowed before establishment of WMM and HM plant. Roads are opened for long time
for contractor but they could not start DBM, WMM works. The performance of contractor
is very poor.
7.1 Contract Package IVA Construction of Thiruvalla Bypass along Chengannoor - Ettumannoor Road (SH-1) from chainage 7+390 to 9+400
Scope of Works Major Bridges - Nil
Minor Bridge - 1 no.
Flyovers - 1 no.
Culverts - 8 nos.
Pipe Culverts - 2 nos.
Solar lights - 1380 nos.
Monthly Progress Brief – February 2015 Page 36
7.2 Contract Details Letter of Acceptance Date 29.10.2013
Agreement Date 29.11.2013
Name of Contractor M/s EKK & Co, Kochi
Contract Price Rs. 31,80,45,071/-
Notice to Commence 19.12.2013
Total Length 2.3 Km
Contract Period 24 months
Completion Date 18th December 2015
Defect Liability Period 365 days
7.3 Utilities Contractor has submitted variation item rates required for relocation of electrical utilities
from the project road in the absence of specific provision in the BOQ. Removal of stumps
of trees cut by agencies engaged by KSTP is also the responsibility of the Contractor.
7.4 Moblization of Resources
• Contractor has not established equipment like WMM Plant, HM Plant and
Crusher. The Concrete Batching plant has been established. On restarting the
work, the contractor has started to mobilize the required plants and machinery
7.5 Work Progress Date of Commencement of project is 19thDecember 2013. All Survey works and
confirmatory boring required have been completed except for the minor bridge location.
Earth Work has been started at the PVD area for the working platform.
2 Nos Box Culvert completed and 1 No in progress.
18Nos of piles cast out of 36 Nos for the Fly over at Km.1+220.
Up to previous Month This Month Cumulative to end of this Month
Target Achieved Target Achieved Target Achieved 45.00% 3.93% 2.92% 1.62% 47.90% 5.55%
Monthly Progress Brief – February 2015 Page 37
7.6 Physical Progress (Quantity wise):
7.7 Potential Issues The following issues are very critical which may have adverse impact on the timely
completion of the Project.
• Slow Progress of work due to Court Order for 9 Months.
• Delay in mobilization of Crusher, WMM Plant and Hot Mix Plant due to above.
• Shifting of Electrical and Water utilities slow
• Delay in clearances for borrow area for earth
7.8 Schedule of culverts and drainage works
Nature of work
Tot
al n
umbe
r
No.
dw
gs a
ppro
ved
Num
ber
com
plet
ed
Num
ber
in p
rogr
ess
Num
ber
rem
aini
ng
Culverts
Pipe culvert 4 4 4
New Box Culvert 6 3 1 2 3
Total culverts 10 7 1 2 7
Fly over 1 1 1
Minor bridge 1 1 1
Monthly Progress Brief – February 2015 Page 38
7.9 Implementation of EMP: The construction activities for Contract IV-A was temporarily suspended due to the
intervention of Green Tribunal Chennai. The case was disposed and contractor started
the works. Contractor has submitted a generic HSE plan and was approved. The borrow
area management plan has to be approved Contractor has established a batching plant
and the required consents have been also obtained.
Contractor has not mobilized the environmental engineer and site specific management
plans are not submitted so far.
7.10 Payment Mobilization advance has been paid to the contractor Rs. 25116746/-
8.1 Contract Package IV Upgradation of Road from Chengannoor to Ettumannoor of SH-1
8.2 Contract details: Letter of Acceptance - 21.08.2014
Agreement date - 15.09.2014
Name of contractor - M/s Delma-Sreedhanya JV
Contract amount - Rs. 293,58,17987
Notice to commence - November 25, 2014
Total length - 45-80
Contract period - 36 months
Completion date - 24.11.2017
Defect liability period - 365 days
I milestone - 10 km upto BC level 18 months from commencement date
Scope of Works (45.40 Km): Construction of Major Bridges – 3 Construction of Minor Bridge – 5 New Box culverts - 9 Widening Slab culverts – 8 Reconstruction of Culverts - 59 Foot path, Solar lights
Monthly Progress Brief – February 2015 Page 39
II milestone - 25 km upto BC level 25 months from commencement date
III milestone - 47.80 km upto BC level 36 months from commencement date
8.3 Pre-Construction Activities:
8.3.1 Utilities Utilities such as water lines, telephone cables and associated accessories, electrical lines
and associated accessories are remaining to be removed / shifted.
Relocation of Electrical lines and Waterlines are included in the Contract and the
responsibility of contractor.
8.4 Mobilization of Resources
8.4.1 Plant and machinery The Contractor has started the process of mobilizing Plant and Equipment. They have
identified their base camp at Ettumannur where Store, WMM Plants are to be set up and
another camp at Thirumoolapuram where Batching plant, Pre casting yard has
commenced production. The Chingavanam QC Lab facility construction completed. Two
nos of piling rigs have been mobilized. Other Construction Equipments are being
brought to site.
8.5 Work Progress Preparatory works & mobilization has been in progress since the handing over of site on
24th September 2014.
Survey o GPS Topo survey & TBM Fixing completed Upto Km.47+700 o Centre line marking completed.
o PCL level for design purpose completed
o OGL level 0+000 to 25+700 completed
Culverts:-
Work is in progress for 3 Nos (Km.0+271, Km.0+473 & Km.2+084)
Bridge at Km.0+740 :-
Confirmatory Boring Completed and Existing Bridge dismantled.
Piling completed (8 Nos)
Bridge at Km.4+008:-
Confirmatory Boring Completed and Initial Load Test for Test Pile at A1 completed.
Bridge at Km.5+213:-
Monthly Progress Brief – February 2015 Page 40
Confirmatory Boring Completed.
Bridge at Km.11+235:-
Confirmatory Boring Completed. Construction of culvert to divert village road is in
progress. 5 Nos of Piling Completed.
Bridge at Km.39+709:-
• Confirmatory Boring Completed for Abutment Locations and Boring at Pier
location to be initiated. Breaking of abandoned existing bridge Completed.
• Highway works, pot hole filling completed.
• RMC plant started operation on 6/1/2015.
• Precast Drain concrete cast 415 Nos (622.50 Rm.) erection at site just initiated.
• Electrical Utility shifting has been commenced.
• Material procurement for waterline relocation has been started
8.6 Physical Progress
Monthly Progress Brief – February 2015 Page 41
8.7 Schedule of culverts and drainage works
Nature of work
Tot
al n
umbe
r
No.
dw
gs a
ppro
ved
Num
ber
com
plet
ed
Num
ber
in p
rogr
ess
Num
ber
rem
aini
ng
Culverts
Pipe culvert 1 1 1
New Box Culvert 81 3 3 78
Total culverts 82 4 4 78
Minor bridge 4 3 3 1
Major Bridge 2 2
Widening Bridge 3 3
8.8 Implementation of EMP
8.8.1.1 General The Environment Management Plan (EMP) prepared for Package IV describes the
environmental issues anticipated during the execution of the project and suggests
mitigation measures to be carried out during the implementation to minimize the impact
on the environment. The EMP has been made an integral part of the construction
contract and is being implemented along with the execution of the project. The progress
of implementation of EMP during the execution of Package IV as of February 2015 is
summarized below.
Contractor has submitted the HSE plan and was also approved. Site specific
management plan have to be submitted for each facility. The contractor has mobilized
an Engineer for Environment and Safety in the month of December 2014. The
establishment of batching plant is almost completed, the required land for establishing
HM Plant, WMM Plant and labour camps. Site Specific plans to be submitted. Relocation
of tree at bridge location has been started.
Culvert and Bridge works are in progress. Contractor has taken land for HM plant at
Chingavanam and WMM plant at Vemballge and initial works started. The PCB
clearance process is in progress. Contractor has also arranged Air & Water quality
monitoring and results are awaited.
Monthly Progress Brief – February 2015 Page 42
8.9 Payments Mobilization advance amounting to Rs. 14,67,90,899/- has been paid to the Contractor
based on their application. Contractor not yet applied for Machinery Advance.
9.1 Contract Package V Upgradation of Road from Ettumannoor to Muvattupuzha of SH 1
9.2 Contract details: Letter of Acceptance Date 29.11.2013
Agreement Date 30.12.2013
Name of Contractor M/s NAPC Ltd.,
Contract Price Rs. 171.49
Notice to Commence 04.02.2014
Total Length 40.60 km
Contract Period 30 months
Completion Date 03.08.2016
Defect Liability Period 365 days
1st Milestone 10 km – BC level 02.05.2015
2nd Milestone 30 km – 30 km BC level 03.02.2016
3rd Milestone 40.960 km whole works by 03.08.2016
Scope of Works (40.96 Km): Construction of Major Bridges – 0
Construction of Minor Bridge – 4
New Box culverts - 3
Widening Slab culverts – 14
Reconstruction of Culverts - 75
Foot path, Solar Lights
Monthly Progress Brief – February 2015 Page 43
9.3 Utilities Relocation of electrical utilities and water supply line using materials issued by KSTP is
the responsibility of Contractor. KSTP/PMT has made arrangements with BSNL and
other private agencies for relocation of cables, telephone posts and telephone pillars.
KSTP has issued most of the items required for relocation of Electric and Water utilities
and relocation work is under progress.
9.4 Plant & Machinery Contractor has established a new concrete Batching Plant and obtained consent for its
operation from KSPCB and Local Bodies concerned. D&O Certificate from local authority
is still pending to obtain. Erection & commissioning of the WMM Plant is completed.
Erection of Crusher is under progress. Apart from this, 2 Nos of Weigh bridges have
been erected and commissioned. HMP has been established and commissioned. They
have mobilized most of equipment. Due to non-availability of adequate work groups and
due to severe cash crunch, their progress is far below satisfactory. There is shortage of
construction materials also to due to which progress is hampered.
9.5 Work Progress • Construction of 5 nos of Box culvert completed. Construction of 5 nos of Box
culvert completed on LHS and 3 nos Box culvert completed on RHS.
• Widening of 3 nos of Slab culverts completed.
• Source approval has been issued for use of Coarse Aggregates from 2 sources and Fine Aggregates from 2sources. Alignment soils for 18Km have been collected and Lab Tests are progressing. Mix designs for concrete grade PCC M15, PCC M 20, RCC M20, RCC M25 and RCC M30 have been approved. Job mix for GSB and WMM has been approved. Job mix for DBM has been provisionally approved.
• Work on relocation of electrical and water utilities in the first Mile Stone reach has been done.
• Widening of 3 slab culvert, Construction of 5 Box culvert completed.
• Construction of drain about 3825 m (Total precast drains cast is 9730Nos)
• Subgrade completed for 2140 m on LHS and 3880 m on RHS
• GSB for 1310 m on LHS and 2030 m on RHS completed
• WMM top layer completed for 40 m on LHS and 710 m on RHS.
• The progress of work with reference to the contract price
For previous Month This Month Cumulative to end of this Month
Target Achieved Target Achieved Target Achieved 5.80% 3.07% 3.43% 0.66% 9.20% 3.73%
A summary of progress for major items is as follows.
Monthly Progress Brief – February 2015 Page 44
Milestone I II III
Length in km 10 36.20 40.96
Length handed over to contractor in km 10 36.20 40.96
Stretch completed in all respects in km - - -
FW HW FW HW
GSB completed in km 1.750
WMM completed in km
DBM completed in km
BC completed in km
CD completed in Nos. 11 0
9.6 Schedule of culverts and drainage works
Nature of work
Ori
gina
l num
ber
No.
dw
gs a
ppro
ved
Bot
h Si
de c
ompl
eted
Ori
gina
l num
ber
No.
dw
gs a
ppro
ved
Num
ber
com
plet
ed
Num
ber
in p
rogr
ess
Num
ber
rem
aini
ng
Ori
gina
l num
ber
No.
dw
gs a
ppro
ved
Num
ber
com
plet
ed
Num
ber
in p
rogr
ess
Num
ber
rem
aini
ng
LHS RHS LHS RHS LHS RHS
Culverts
Widening Slab Culverts 3 3 1 2 8 8 6 6
Slab Culvert retained 4 5 0 2 0
Reconstruction Slab/Box 24 23 4 5 3 3 5 12 12 28 28 11 11
New Box Culvert 1 1 1 3 3 3 3
Dropped 1
New Pipe Culvert 0 0 5 5 5 5
Total culverts 33 27 5 6 5 3 5 12 12 49 0 0 0 44 27 0 0 0 25
Bridges Retained 0 0 1 1 1 1
Widening Bridges 1 1 3 3 0 0
Reconstruction Bridges 0 0 1 1 0 0
Total Bridges 1 0 0 0 1 5 0 0 0 4 1 0 0 0 0
Milestone - I Milestone - II Milestone - III
Num
ber
com
plet
ed
Num
ber
in p
rogr
ess
Num
ber
rem
aini
ng
Monthly Progress Brief – February 2015 Page 45
9.7 Key issues: The following issues are very critical which may have adverse impact on the timely
completion of the Project.
• Inordinate delay in installation of Crusher. Its commissioning and obtaining consent
for operation are pending.
• Delay in Identification and procurement of adequate construction materials.
• Delay in mobilization of adequate labour and machineries.
• Acute shortage of cash flow. Contractor’s Bank accounts are freezed due to
management issues
• Change in management of company and frequent change of key personnel of contractor
9.8 Payment to the contractor The contractor has been paid the IPC-3 Rs. 119800769/-
9.9 Implementation of EMP As part of the pre-construction activities, setting up of facilities like base camp, labour
camps, borrow area, batching plant, WMM plant, mobilization of plants and machineries
are in progress. Environment management facilities adopted at these ancillary facilities
are detailed below.
The contractor is establishing a base camp near Palakuzha where the construction
camp, pre-cast yard, workshop, batching plant, hot mix plant, WMM plant, labour camp
and stock yard are being established. The details of facilities at Palakuzha camp site are
shown below:
Sl. No Camp Identity Location
Nearest village with distance from camp
1 Base Camp for Precast yard, Field laboratory, heavy vehicle workshop, batching plant, WMM Plant, pre-cast yard and material stock yard
7.24 acres of land about 150 m from Project Road
Palakuzha
2 Base camp for Crusher 8 acres of land at 31 km of the project road and about 1.5 km from project road
Arakuzha
3 Labour camp Project road at CH 3.300 km
Vempally
9.10 Compliance with Statutory Clearances The action taken by Contractor for complying with statutory requirements is summarized below:
Unit Status of Compliance Remarks
Monthly Progress Brief – February 2015 Page 46
Quarry Planning to take on lease. Two quarries are identified which have all statutory clearances.
• Quarry-1. Owned by Sabu Varghesse.
• Quarry-1. Owned by Babu Kuriakose.
Crusher Obtained Consent to Establish from Kerala State Pollution Control Board
Date of Issue of Consent to Establish-02.05.2014 and Valid Upto 28.02.2017. No major activities at crusher site.
Hot Mix Plant
Obtained Consent to Establish from Kerala State Pollution Control Board
Date of Issue of Consent to Establish-01.04.2014 and Valid Upto 28.02.2017
Base camp and batching plant
Obtained Consent to Establish and operate from Kerala State Pollution Control Board
Date of Issue of Consent to Establish-01.04.2014 and Valid Upto 28.02.2017. Consent to operate 02.05.2014 and valid Upto 28.02.2017
WMM Plant Obtained Consent to Establish from Kerala State Pollution Control Board
Date of Issue of Consent to Establish-01.04.2014 and Valid Upto 28.02.2017
The change of management has slowed down the progress. There is no major activities at Crusher site. Contractor has to obtain consent to operate for all the plants immediately. Even though the contractor has commissioned the HM plant no bituminous works started so far. Site works were started for long stretch and kept un completed works without any top layers. The contractor has not completed the bituminous works on these stretches before monsoon the traffic along the road will be very difficult. 9.11 Traffic Management and Road Safety Measures Contractor has submitted the Health, Environmental and Safety management plan
which is under scrutiny. A site visit was conducted by the Environmental officer of CSC
on 20th Nov.2014. The observations during the visit was also forwarded to the contractor
for strict compliance and further action for submitting the management plan for
approval by CSC. Traffic safety management at site has to be improved urgently.
10.1 Contract Package VI Upgradation of Road from Ponkunnam to Thodupuzha Scope of work (46.363 km)
Minor Bridge reconstruction - 1 no.
Culvert:
Reconstruction - 109 nos.
Widening - 44nos.
New Construction - 7 nos.
Drain - 65 km
Foot Path -
Solar Street Light -
Monthly Progress Brief – February 2015 Page 47
10.2 Contract details:
10.3 Financial Progress:
Targeted in % Achieved in %
Oct-14 3.84 1.08 Nov-14 4.81 2.42 Dec-14 3.48 2.67 Jan-15 3.88 4.02 Feb-15 3.95 4.93
10.4 Work Progress:
10.4.0.1 Pavement works: Road excavation work has been commenced in a length of 1.110 km
WMM Work had been completed in chainage 2+000 to 2+210 (LHS) & 2+285 to 2+500
(LHS) during the month and prime coat over WMM surface has been completed in
chainage 2+285 to 2+500 in LHS. Bitumen prime coat had been completed in chainage
from 1+680 to 2+210 in LHS during the month.WMM Work had been completed in
chainage from 0+250 to 0+400 & 0+700 to 0+900 in RHS and top layer level checking
and Field density tests were conducted and approved. WMM Surface prepared to lay
Dense Bituminous course from 1+680 to 2+210 & 2+285 to 2+500. WMM Surface has
been completed in chainage from 0+000 to 0+230 in RHS, from 0+020 to 0+230 in RHS,
from 0+250 to 0+390 in RHS, from 0+700 to 0+900 in RHS.
Letter of Acceptance date 04.02.2014
Agreement date 05.05.2014
Name of Contractor M/s GHV-EKK (JV)
Contract price Rs. 227,13,73,548
Notice to Commence 10.06.2014
Total Length 46.363 km
Contract Period 30 months
Completion date 09.12.2016
Defect Liability Period 365 days
1st Milestone 10 km
2nd Milestone 25 km
3rd Milestone Completion of full stretch & Thodupuzha
Bypass
Monthly Progress Brief – February 2015 Page 48
DBM work completed in chainages from 1+680 to 2+210, from 2+285 to 2+500 in LHS
during the month. DBM has been laid over WMM prime coated surface in chainage from
1+965 to 2+210 in RHS. DBM has been laid over WMM prime coated surface in chainage
from 2+285 to 2+490. DBM has been laid in chainage from 0+000 to 0+230 & 0+250 to
0+670.
10.5 Work Progress: Details of progress of construction of Box Culverts and Pipe culverts are listed below:
S. No. Description
Milestone-1 Milestone - 2 Milestone – 3
Total Started Yet to be Total Started Yet to
be Total Started Yet to be
1 Pipe Culvert 6 5 1 11 9 2 13 5 8
2 Precast box Culvert 13 1 12 25 0 25 42 1 41
3 Box Culvert cast-in-situ 1 1 0 3 3 0 13 4 9
4 Box Culvert widening 1 1 0 3 0 3 13 2 11
5 Cast-in-situ New 0 0 0 2 0 2 0 0 0
5 Box Culvert retained 0 0 0 2 2 0 3 0 3
Total For each 21 8 13 46 14 32 84 12 72
Grand Total of Culverts = 151
10.6 Physical Progress
Notes: Concreting includes all grades of concrete mix required for drains and walls, bridges and culverts.
33094
31189
4408
11381
7607.12
5860
6143
691
0
6838
4348
231
291
0
0
82600
1500
8500
65000
27500
30625
75000
3500
1600
7278
1561
815
310
0
0
Excavation (cum)
Excavation (cum) in hardrock
Embankment (cum)
Subgrade (cum)
GSB (cum)
WMM (cum)
Loosening and recompacting
DBM (cum)
BC (cum)
Concreting M-15 (cum)
Concreting M-20 (cum)
Concreting M-25 (cum)
Concreting M-30 (cum)
Concreting M-35 (cum)
Concreting M-40 (cum)
Cumulative target to end of this month Cumulative Achieved to end of this month
Monthly Progress Brief – February 2015 Page 49
10.7 Environment Management Plan & Mitigation: Planning, monitoring and coordinating authorities for environment mitigation work were
in progress in the month of February 2015 as an exercise for compliance of EMP along
with up-gradation of road from Ponkunnam (KM 84+000) to Thodupuzha (130+000) and
Thodupuzha bypass of SH-08.
During the work progress the statutory compliance under environment regulations, Air
(Prevention & control pollution) act 1981 and Water (Prevention & control of pollution)
Act 1974 was emphasized. The traffic management and safety has been practiced
throughout. The labour laws were protected, also public grievances had been registered
and solutions/action plans were suggested.
10.7.0.1 6.1 Work Force Management for construction work
S. No. Category Male Female Employment Status Residential Status Regular Temporar
y Migrant Native
1 Unskilled Labourers
296 Nil Nil 296 138 158
2 Skilled Labourers
326 Nil Nil 326 165 161
3 Supervisors 38 Nil 38 Nil 26 12 4 Engineers 27 Nil 27 Nil Nil 27 5 Office staff 40 Nil 40 Nil Nil 40 6 Non Technical
Staff 190 Nil 150 40 59 131
Total 917 Nil 255 662 388 529
10.8 Environment Management at Ancillary facilities S. No. Details of
Camp/Plant Environment Management Facilities Extended
1 Construction Camp
• Oil interceptors and settling tank for disposal of liquid waste from workshop and hot mix plant had been constructed.
• Fire extinguishers are deployed in laboratory and camp. • Fencing had been extended around the office. •
2 Labour Camps • Lawn plantation and green belt plantation is done in and around these camps.
• The solid waste (kitchen and paper waste) disposal is done in compost pit. Monitoring register had been maintained for waste disposal at labour camps.
• Plastic waste and biodegradable waste is collected in separate bins for segregation. Plastic waste is supplied to a school for reuse/recycle treatment.
• Fencing has been done around the surroundings.
Monthly Progress Brief – February 2015 Page 50
10.9 Payment to contractor
Payment upto February 2015 is IPC-5 Rs. 469176943/-
11.1 Contract Package VII Upgradation of Road from Punalur to Ponkunnam
Work has to be arranged under PPP mode (Modified Annuity). DPR submitted by
M/s CDM Smith Associates is under review. The Transaction Advisory has been
selected and assignment commenced. The Transaction Advisory is M/s L&T Ramboll in
JV with M/s Fortress. The review of DPR and RFQ, RFP and Financial modal are in
progress.
12.1 Contract Package VIII
Upgradation of Road from Perumbilavu – Pattambi - Perintalmanna
Horizontal alignment finalized and boundary stone planted for land acquisition. The
original proposal was to upgrade the project under EPC mode. But due to the delay
anticipated in acquiring the land invoking the provision of the new LA Act for which
rules are being framed by the Government, it has been decided to provide a modest level
of improvement to the surface. It is also proposed to make use of the savings due to the
change in the improvement proposals for providing overlay to the KSTP-I roads.
Accordingly proposals have been submitted to the Government and to the Bank after
obtaining approval of the Steering Committee on 28th June 2014. The DPR has been
prepared.
13.1 Proactive actions taken by employer:
1. The threshold limit of minimum IPC has been lowered to Rs. 1.50 crores from Rs.
3.00 crores to facilitate cashflow of the contractors.
2. Extension time limit for completion of Milestone-I has been granted for Package I,
II and III to compensate the delay caused due to reasons beyond the control of the
contractors.
14.1 Road Safety Component – Current Status
1 Base Line Road Safety Survey for Safe Corridor Demonstration Project – Kazhakkoottam – Adoor
:: Study completed
2. Road Safety Capacity Building and program
management :: M/s Vick Roads, Australia is
identified as consultant and
Monthly Progress Brief – February 2015 Page 51
assignment commenced. The inception Report submitted and workshop to finalise the report was held 30 January 2015. The consultants strengthening for the institutions responsible for Management of Road Safety in the State is in progress. This also includes assistance in developing Safe Corridor Demonstration Projects and Local Level Road Safety Programs and Implementation.
15.1 Institutional Strengthening Components – Current Status
1 Road User Perception Survey :: Completed, report submitted 2 Prioritization and DPR preparation for 1000
km :: Work completed. Draft DPR presented. The project was processed to Govt. and passing for JICA assistance.
3 SOS for 8750 km MDR
::
Work completed and Report forwarded to Chief Engineer (R&B) for preparing DPRs of individual road packages with PWD funds.
4 Development of Multi Model (Hub) –
Prefeasibility study :: Final report received and submitted to Government. This was also shared with NATPAC
5 Appointment of client Executive Program
Sponsor and work packages
::
EOI notification for work packages 2,3 & 4 sent to Bank. Shri. Babu Jacob, Former Chief Secretary has been nominated as Client Executive Program Sponsor and approval awaited in Steering Committee
8 Integrated Information Management System
::
Only one firm M/s TRL-Experion JV was technically qualified. The Steering Committee has ordered to rebid for the assignment as their rates were high. The ToR was revised and EoI notification along with revised ToR sent to Bank.
9 Construction Head Quarters Building under
Green building concept
::
Architectural and Structural Design completed under KSTP II and proposal submitted to Government for Administrative Sanction for the construction. Now, there is proposal to construct a separate block, for the newly proposed Road Agency.
10 Community Participants and User
Engagement in Road Design and Safety :: Seven EoIs received and short listing in progress.
11 Review and updating information systems in
PWD and developing Integrated Management Information System for PWD
:: Review of existing IT systems in PWD completed.
Monthly Progress Brief – February 2015 Page 52
16.1 Payment to the consultants as on end February 2014: M/s Egis India JV - Rs. 88746310 +10969046 = 107010017
M/s MSV International - Rs. 7776688 + 961198 = 10201295
17.1 Overlay to 150 km KSTP-I Roads It has been proposed to provide overlay to 150 km of KSTP-I improved roads from the
savings anticipated from the Perumpilavu – Perintalmanna road. The Steering
Committee at its meeting held on 28 June 2014 approved the proposal and intimated to
the Bank. The DPR has been completed by the KHRI.
18.1 Meetings, Site visits & Inspection
SE and EE KSTP convened a Meeting regarding the shifting of Utilities on 06th Feb
2015 at KSTP Circle, Aluva at PWD Rest House Madai.
• SQME of CSC Visited the Site on 5th & 6th Feb 2015.
Progress Review Meeting convened at Site office of EGIS on 7th Feb 2015, RE with
CSC Staff’s and Contractor’s representative attended.
• The Project Director and Chief Engineer (Projects) of KSTP and the Team Leader
of CSC have visited the Site on 13th Feb 2015.
The Secretary, PWD convened Progress Review Meeting on 23rd Feb 2015 at
Kozhikode.
The Chief Engineer (Projects) Convened the Review Meeting at 10.30Am at PMT
Conference Hall, Trivandrum on 25th Feb 2015.
Progress Review meeting was convened at Trivandrum on 25th Feb 2015 by the
Secretary PWD at 3.30pm. KSTP Officials, Consultants, and Contractor’s
representatives attended the meeting.
SE and EE Convened the Utility Meeting on 06th Feb 2015 at KSTP Circle, Aluva at
PWD Rest House Madai.
SQME of CSC visited the site on 04th Feb 2015.
Chief Engineer of KSTP and Team Leader Visited the Site on 12th Feb 2015.
Project Director and CE of KSTP Visited the Site on 13th Feb 2015.
The Secretary of Govt. PWD convened a Meeting on 23rd Feb 2015 at Kozhikode.
Meeting at KSEB office (Kannur) Convened by Nodal Officers (Additional CE, KSEB)
on 24th Feb 2015.
Monthly Progress Brief – February 2015 Page 53
PD Convened the Review Meeting at 10.30Am at PMT Conference Hall, Trivandrum
on 25th Feb 2015.
The Hon’ble Secretary for works) convened a Review Meeting at 3.00Pm on 25th Feb
2015 at PWD Rest House Trivandrum.
Project Director, KSTP visited the site 06th February 2015.
Chief Engineer, KSTP visited the site 14th February 2015.
SE, KSTP visited the site on 21st February 2015.
During this month, Honorable Secretary for works reviewed the progress of the
works on 25th February 2015 at Thiruvananthapuram.
Secretary, PWD convened meetings on 23rd February 2015 at Calicut.
Progress review meetings at KSTP level has been conducted on 04th February 2015
and 25th February 2015 at Thiruvananthapuram.
The Chief Engineer – KSTP visited the site on 24th February 2015
Progress Review Meeting by the Project Director was conducted at
Thiruvananthapuram on 25th February 2015 by the PWD Secretary.
PWD Minister has Convened a project progress review meeting at
Thiruvananthapuram on 25thFebruary 2015.
The Chief Engineer – KSTP visited the site on 24th February 2015.
Progress Review Meeting by the Project Director was conducted at
Thiruvananthapuram on 25th Jan 2015 by the PWD Secretary.
19.1 Land Acquisition Status Sl. No. Name of Road
Total Requirement
(Ha)
Extent of pending
acquisition
Percentage of pending acquisition
LA Stage
Date of taking
Possession
1 Kasargod – Kanhangad 2.983 0 0 - -
2 Pilathara – Pappinisery 6.234 0 0 - -
3 Thalassery – Valavupara 25.32 1.032 4.08 Award
Stage 30.03.2014
4 Chengannoor - Ettumannoor 15.368 0.246 1.6 DLPC 31.03.2014
5 Ettumannoor- Muvattupuzha 17.866 0.07 0.39 DLPC 31.03.2014
6 Ponkunnam - Thodupuzha 35.733 0 0 - -
7 Perumbilavu – 13.5 13.5 100 LAO appointe 31.12.2014
Monthly Progress Brief – February 2015 Page 54
Perinthalmanna d
8 Punalur –
Ponkunnam 17.705 0.026 0.14 4(1) stage 31.06.2014
Direct purchase proposal of land was approved by the Steering Committee on 28 June 2014
20.1 Status on Critical Actions
1.
Initiate road pavement works in contract-3 and start achieving consistent monthly progress of 2.5%, failing which face stringent contractual action.
-
The contractor is reluctant to enhance progress. The WMM plant has been commissioned. However the HM Plant has not been commissioned. Stringent action against the contractor is under consideration.
2. Complete mobilization in contract-5 and start achieving consistent monthly progress of 2.5%
-
Contractor could not show 2.5% progress consistently mainly due to change in management. Hence meeting has been called for on the 9th March 2015 to review the status of work and to decide on the future course of action.
3.
Achieving at least 4 km of completed road works in contract-1 and 2 (each) and consistent monthly progress of 5%
- Some progress is achieved. However is not as envisaged due to shortage of bitumen and aggregates.
4. Roll out the new rules and resume remaining land acquisition -
This is published and a copy forwarded to World Bank (Mrs. Mridula Singh) for comments
5. Send the Feasibility Study, DPR and bid documents for contract-8 and additional 130 km roads
-
The feasibility study, DPR and bid documents are completed and under scrutiny in this office. The present proposal is to limit the Package-8 to overlay works.
6. Submit strategy for financial analysis and market sounding for PPP road
-
The viability analysis is expected from Transaction Advisor. The investor meet is proposed at Kochi on 6th March 2015.
7.
Revise TOR for Loyola college and instruct them to cover geo referencing of land acquisition and filling of gaps for locations without mark stones
- Clearance from the Steering Committee obtained and this is done.
8.
Revise TOR for Transaction Advisor to include review and updating of DPR and scope of physical design of project
-
The discrepancies in the DPR have been rectified by M/s CDM Smith, the original DPR consultant. This has been reviewed by the TA and final cost arrived at
Monthly Progress Brief – February 2015 Page 55
9. Initiate procurement for the case study for LA & R&R for Package 1 and 2
Actions taken to procure the consultancy services – EoI of two firms received. RFP prepared.
10. Issues RFQ for PPP road - This is under process and the SPN will be issued after the Investor Meet.
Component - B
11. Submit Inception Report for Road Safety -
The draft inception report is received and a workshop was held on 30, January 2015 for finalizing the same.
12.
Initiate staff recruitment in KRSA and procurement of equipment for initial preparation of demonstration corridor
- The consultant M/s VicRoads are interacting with the KRSA authorities for this purpose.
Component - C
13. Propose-3 strong candidates for Client Executive Program Sponsor and finalize appointment
- Mr. Babu Jacob, Former Chief Secretary has been identified and follow up actions are on.
14.
Issue functional analysis and commission architect to prepare options for conceptual design of Road Agency Head Quarter
- This shall be speeded up in consultation with the Client Executive Program Sponsor as he is now in place.
15. Appoint Technical and Financial Advisor for the client sponsor - Enquiries are on and experts are being
identified.
16. Complete review and validation of task inputs and man months for consultancy activities
- The TORs were already verified and man months are reviewed as advised by the Bank.
17. Issue RFP for the Sector Strategic Study Works packages -
EOI have to be invited. The work package 2 and 4 are ICB. The revised EOI notification will be submitted to Bank shortly.
18.
Finalize selection of agency for the integrated Omni Channel IT and Communication System for improved public communication and user engagement
-
Only one consultant was technically qualified and their rate was formed high. The Steering Committee had advised to rebid for the assignment clearance from Bank obtained and EoI sent to Bank.
19. Issue RFP for direct stakeholder engagement in road safety enhancement and asset preservation
- Expression of Interest from Seven firms received and short listing is being done.
General Issue
20. Maintain adequate balance in the project account to meet requirement - This is taken up with Government of
Kerala
Monthly Progress Brief – February 2015 Page 56
for next 45 days 21. Submit statutory audit report - This was forwarded to Bank
22. Start using the e-project management system for improving overall project management
- Training conducted for Engineers on the use
Current Status of Six Point Program: 1. Achieve a consistent 5%
financial progress per month from December 2014 onward for contract Package-1 and 2
:: Review of Progress of Works have been done by the Hon’ble Minister on 5th January 2015 and Secretary on 9th January 2015 to speed up the works.
2. Achieve a consistent 2.5%
financial progress per month from December 2014 onwards for Contract Package 3 and 5
:: Package-3: The contractor is reluctant to enhance progress. The WMM plant has been commissioned. However the HM Plant has not been commissioned. Stringent action against the contractor is under consideration. Package-5: Some progress is achieved. However is not as anticipated due to shortage of bitumen and aggregates. The contractor was notified to speed up the works or face stringent actions.
3. Keep the Project Account
adequately funded at all time to meet the requirement for next 45 days
:: There is no interruption to the fund flow to the project. Government have promised to release funds according to progress of work
4. Roll out the new rules for the
Right to Fair Compensation and Transparency in Land Acquisition Bill, 2013 to enable resumption of remaining land acquisition by February 2015
:: The new draft rules have been framed and published and feedbacks being analysed for finalization.
5. Engage the Client Executive
Program Sponsor, set up the client Sponsor’s office and initiate procurement of Work Packages WP1 through 4
:: Shri. Babu Jacob IAS (Retd.) former Chief Secretary, Kerala had been identified and clearance from Government awaited.
6. Pace of project
disbursements accelerate to at least three times the current level
:: Maximum efforts are being made being accelerate the pace of disbursement
21.1 List of Annexure: Annex 1 Important correspondence with the contractors and minutes of the meeting
Annex 2 Photographs
MII{UTES OF THE RD1/IEW MEETING CONI/ENED BY TIIE PROJDCTDIRDCIOR, AT TIIE CONFERENCE HALL OF PMT on O4,O2.2O15 FORTIIATASSERY -VAJ,A\iUPARA ROAD ,PIIG II1Lk' olpanrcipans h att ched separatcly
Tbe necri.e to reriew the progre$ of lhc abovc worL chaired by P.olecr Director sded at 2.30
const.uction Programme rnd Pe.fornetrc.
R6idcnl Enginee. infomed lhal the orisinal progianne was approved in Nolember 2013 and
despite tho E?eaied insrructions ksued ro rcvhc the consrruclion programd€ rs pe. thc
prcvhions in theenhdtill ddethe conhcror h6 nol cohptied wirh lhe abovc dreclions and
th€y havc subnrlr€d procrmne with MSII & MS ill dalss ertendcd. Th€n I,rojed Dnstorsodgnr the cxpltualion from rhe @nroctor. Nts SACYR -Ess JV rcprcscnralivcs replred rhat
they bove subhined &e revised prcgEnme ond thc cnd dalc is exlcndcd duc lo casrding eil{tsof the events. Then P.qet DiEctor instraoled to !€vne tne @nslrudio. prosrmmo wilhin
'be@ntFct p.riod md accoidingl, nobilize the esources.
Residem Engi.er rcporied |nal now blal6.l% finocial tdget h only achieved asai.sl Lhe
opproved prcg.smme of 62.3%- Chrel E.gineer poinGd our thar lhe EOT q6 smted upro
D*mber 31'2015 foihilesro.ewrrh d oveFll brget oI?%. Then n M nored th3t am.dinsto the nicro pro8m upto l5s April 2Ol5 submitt€d i. Deenber 2Ol4 rhe co.l.acror h6failed lo acbiov€ even lbe 35% pldned activities $ follos:
st
L*nt Phned jn Jd 2015
Achiled( Revenue in Lrkhs)
upto 29d January 2Ol5
14269 r08.85
2 Jt7.85
3 290t
11.00 10.5
L7E
6.10.75
rl
Ir!Nalso recoded mrrhcyhavcachicvc;o77v" in N.vembe.20l4,0.66%ln December20l.l
add 0.9% in Jrntrrry 2015 and agains the hger'$r by Wo.ld llank k ninim0h of2.5% pe.
Prcjel Direcror enqu;ed why rhe contrctor h Iarline continuously in ataining rargeb rhough
l9 monrhs elapsd.Sri.l.V.loseph contractor's epreseDbrive rsplicd lhat rhey have selected $e
Km 1,200 !o 2/800 lor @mplerion in milstone I snd |ner could not complele the aclivny Nplan.ed. Also i.romed rhar rhere were issues olpipo laka8e/brakage, sbining dfBSNL
cablcs elc. The. chielEneinee. replied a ler rho contmct rhe utihy shining ts pd ofrnejob
a.d lhcse issDes are frced by all lhe olh€i conlracron and lhey aE tacklre lhe ^strs and
prceedins wilh rhc works Rerdeft Enginocr inlomed rhor lhet m not workin8 r olher
sLelches Nhich w l ako add as backloes.
Al9 lne comDcror infomed fi,t ddring lhe siG vrit of(WA, Asisbnt Engi.eer they have
conndled iial lhelayi.gofKwA sedieprpe line bchven lheROwand dai. h dimcux for
repaii works in turure Md sugge{ed that this prpe 6 be laid obove subgdde l0 cd ,wry 1tun
the in.e! cdse of lbe drain- Ane. det ilcd discusions ir ws decisd lhal 6 prcpo$d by fie
contFclor the pipss 6 b€ lod below subsdde clos to lhe drain side wall footpalh ca. be
@nslruclcd ovoi the drsin using lhe covcr slab.
IiM Pllnt connisioning ,hd Mir Design Approvals
Chief Engrsr enqured abodr lhe comnBsionmg ofHM plul dd Residenl E.greer ieplied
lhar $e riM pldt is not conmisioned tet, Then the onlJaclor rcplied thar dis day rhe lrail run
6 behe done md HM pldntqillbe @dnissioned soon md lhis doy rhe c,libiaion ofnachine
is heing done On@ thh is oompleted then o.ly the lrial runs can be made ror mix design
It is Eponed that lhc lasl pne is beins @nplered nop ,nd works for 7u sirder 6lins h in
prcsres. Pmjscl Di@loi enquied about the silder launohine rnd rhe conLmclor rcprosonlarive
repli€d rhat the launchine decils wiu be nnaliz€d by O6s Febddy 2ol5 and method slatcmenl
vill b€ suhn,fted lor approvals and lannchi.e snder will uch ro sire $on. cE omme.Ied dd6e sirderlounchins prosEnnc h inordinarely dehled Md n shows contmcros incspability.
MchvambriBridge I
Reident Engineer inforncil thar now lbe slalic
€.quted abour the supeFrrucrule worLs and the
being nide ready dd will sn shin to site
Uliyil Bridge
I
loii is conplcled bow. Then Chief EnBjneer
conrFotor inlomed rttrl shurer msrerials orc
Resident Ensiner reported that the FootiDg for .{2 abuhc.t conpl€ted ed A1 abuunent workr
The conlraotor infomcd thal now 4 pil* &€ conplet d md .ow thc worts for collerdaD ha
R€siddt Engins irfomcd that as Fr DPR tne bridge is in cwe &d 6 per sile @ndition fiepid is nol pqallel to now of waEr hene tbe olignnenr will have a l3n sbin aho now sp$ wnl
be@ne le$er, Chiel En8inea enquiren wheLh.r *t ouL is node aL sile !o vqiry the .NrlicDndt ed R6iddt E gined i.Iomed thaL Lhrs
's checked at sile. chicfEnSinar di!4ted ro
proed with the.,evA€! 3liCnhd! dd advken CSC to $ue revBed dnw,ngs *irh
TlEre de iolal 162 nunber oI culwqts !o b€ @nstrucled/exFnded and Resident EnSine.
Elone! UFt olt of40 culverts in niLslon€ I only 14 nudbeE @nplet€d ad 5 culverts y€t 1o
be staned. ften Cni.f EnSnee! e.qurcd aboul the p'p€ culverl works tud ilts SACYR Ess Ivrcplied that now th.y have ordded for 82 nos ofprF.
Rsident E.gme. repoded Lhet the csB works in lhe ch 1200 to 2/800 h not yer @mpleled.
Only 930n conplet€i fo. full widlh, The @nlraclor replied thaL lh@ ws a l€ilr8e drc to DI
pipe brcakaee dlrine a stump removal nesr ChiFklGE od r.!rh m nol andcipated. The
sp€cials re4ui.€d ior rhh vork aill be available pithin teo dars dd rhe GSB qill be conpl4d.
Nts SACYR-D$,i inforncn lhaLdq havcsranedJhe WMM ind c.trld layx.ound l00m lentslh
onlyandwnhin6 days rheWMMwil becompleb,! lor Ch l/2001o2/800.
Thcn contdcror conmined rhot frcm the Ch l/200 b 2/300 uplo DBM levelwillbe complered
by l3'"Fcb2015 Then ChiefEngineerFinred out rhar rhre sn€ah uplo DBM seE pronisen nthe meering held with Minisrsron 09/0lDol5 tlat l/200 ro 2/300 uFro DBM lcv.l rvillconplete
The antractor informed LhrL Rord excavalion l'om Ch 3/000 to3/500hGsrxned on 0l/022015
mCh 1910001oCh20/000sradr.Bworks(ofdumpedmlter'al)aei.prosrcs.
It h recordcd lbal lb@ 6 .o .oad wo.ks berg edicd out i. other stEbhes Md Pojed Dnechi
infrctd @nm(ro o.bn 'odd
so'k{ in orher srckh6 olso
Resident Encine! lepon€d L5ai no cabion works q€ being cdned oul now md de conhcor
replied fi& they e€ resllnins rhc sabion works within one week.
Chiel Ensre. diE ted lhe annlotol ro alrend
Enginee. ol CSC and also sdviFd !o impove lhe
nustbe hainhined on daily L6is.
lhe comnc.ts issued by the Envircnnenral
safery $pociauy durinB nighl Wlmins si8rs
Prcject Di@toi €.qnred about the approvrl olDmwi.gs md Resident Enginee! eplied thot lbe
cF$ scrions weE approven upo Kn l2l000 md rbe orher dawi.gs .4ubnrLed by the
onlEctor will be $rulinizld end apprcved wifin one wcck. R€sident Engineer infomed lhat
the V&iation foi additDnal Electri€l ilen qill b€ subnitlcd fo! approval soon, ChietEngi.er
dnetcd lhe @nlador !o erum r.le unulilized EDE cenifi€te nsued for ste€l ond conlractor
replisd lhal the nMufadurer infomed lhd lhey have losr thc onginll cenifi@tesnd so fa! thcy
have noL ullizd the $me Then Chiei Engineer Mvisd |ne conlractor to subnn a lener frcn
lne nmuracurer in rbis resard.
ChiefEngineerenqui.cd obour lbe complahL ol Sri.P A.Mukundan Ch 2l+120 LHs for a6ess
md advisd Supcrintc.dinB Engined md Executiv€ Engineei ro onsilute a onnnGe !o
oddEss thoe 'ssu€s
.The. Reside.r E.Cinecr inlomcd lhlt rhe said l@ on were inspected
sine the house of the p€tilionq is vcry close to the bridge appr@ch and approach is in filling
4l
pedrio.er.cs be provided $ouBh dip oad rvilh ,odviscd cSC !o plocccd widr rhe ircpo$l ond advisen
It ws re€rded that agaiNr the plonned 416lobouts Equircd only 186 nunbeN m sv,ilable at
sile(shich need lo be venned by csc). Pdject Didlor enqliEd aboul rhe hain conuaclor litsSACYR ud the conlracloi relEsobrive replied that cudently only one pedon riom SACYR is
Proj*t Director dt@sed disstisladion lowdds the endE poj@r deliveabl4. Prcjecl
D'@or odvisc! M/s SACYR-B$ ry to put sincere efon @ cohplete $e prcjEcr on rine in oU
ap@15 ed oflerld all possibl€ heD. Ale diFcted the @o!@tor to ope. noE work fonts lnd
keeP all the l!!g.t dat€s for codpletion of bndges for which 6su@ce rie gNm lo Govemment
&d htioaled anEacro! rhal a srle vjsn wirl b€ held on 06/02D015.
sd/-
!i:KERALA STATE TRANSPORT PROJECT
PUBLIC WOR(s DEPARTMENT
SLb KSTP - l!-P"<la8elll-Th"las:ery-VdlalvuFra Rord - Rev'Fw meehne
vque PMr ConI-ence Hall
NAME DESICNATION SICNATURE
1.
2.
3.sab
'^ K pNLp - !.E+.r""qj
rv s4"Ph.
5. b6. sl F\ \'v P\q^.r,J \N,r
tse$ersro€+
&^si.PA te"l,A l"^ L\te tl s9tt4I ?
8_ \< K Qo-\(t"L.+tld
5u.*'l lur"c 9as tatr.l c ,ri!: I @i
t(
Kerala Public Works DepartmentKerala State Transport proiect (I6Tpl
Tel : 00-91 471-2378946
Project Management TeamT C.11/339,JAGAD Building e,mailr [email protected] Road, Nanthancode, Kowdiar.p.O wwwkeralapwd let
To
M/s SACYR - Essar JVEquinox Business park,Towet-2,Off. Bandra Kwla Complex,L.B.S. Marg, Kurla (W),Mumbai - 400 070.
Sir,
Subr KSTP II - Upgradation ofThalassery Gm l+200) to Valavupara (55+200)road of SH 30-Poor Quality of MM Executcd at Site_Direction IssuedRegarding -reg.
Ref: 1. Agnt No 208/KSTp/pMT/p /D/20t3 Dtd6/5/20j32.Letter N2.WRP/KST?3/GEN/1199 Dtd jdh Februqry 20153.Sub Clause 7.5,7.6 ofthe Conditiohs ofConhact4.Meeting Chaired by the project Director Dtd on j3/08/20j35. Meeting Chaired by the project Director Dtd on 9/12/20j 4
This has the above references. As per the report of the Resident Engineer vide letter ref(2) it isnoticed that WMM Ist layer laid between krrt 2+470 to 2+640 is defective and rcported that so
far no remedial action taken to rectiry defective works inspite of instructions issued to you. Inthe report it is specifically mentioned that wMM mix used is not plant mixed and instead it ismixed on gound and contains earth which do not conform to specification. Also WMM mixmaterials are ftom Malabar stone qusher which is lrot from approved source ano nor evenattempted to get mix design approval.
It is reminded that as per the tecbnical bid submission during the tender stage you have givenassurance ( in writing ) that a new WMM plart will be puchased in case of award of contractfiom M/s Dhruvi Road Equipment. Later you have informed that you have identified a 160 TpH$'I4M plant identified and formalities with vendor are in progress (ref 4). This has nothappened and after lapse of about 18 months now you have tied up with M/s Carmelconstuctions fot erection of WMM plant. In the meeting convened by the project Director ref(5) you have assured that N4ls SACyR-Essar JV will co-ordinate with the agency that installedthe WMM plant and ensure the quality ofthe project deliverables.
Now it is Foved that you are not even capable of delivering and laying WMM with quality and
specification requhements and the WMM being mixed without plant is not acceptabl€ in any
manner. Also there is no justification for using non approved nuterials in the work. Hence as
instructed by the Resident Etrgineer you are directed to remove the defective material from site
and as per tlre sub clause 7.5 & 7.6 rcmove total defective WMM ftom the Site and replace
Materials with good quality as per the Contract Specification and approved by the Engineer'
Defective works and bad quality materials will not be accepted.
Yours faithfi.rlly,
fcni"r ects
Copy: l. Superintending Engin€ff, Aluva for insp€ction and report2.Executive Bngineer, for follow up action atrd report3.ResideDt Engineer, Egis, Ensue no frther layers are placed without totel removal of defectiv€ material4.Tetrm L€der,Egis - For ensuring strict compliance Quality as ConFact Condition/ Specification
Cr
c
Monthly Progress Brief January 2015
Annex 2 – Photographs
UG-1
GSB Top layer from km. 4+640 to Km. 4+770 LHS Girder reinforcement in progress at Km. 3+392 P2-P3 UG-II
ROB at Km.19+950 A1 Pile Cap in Progress BC in Progress at Km.1+670 to Km.2+610-RHS
UG-III
Girder No:6 – Major Bridge at km 02+910 Shuttering work in progress of Abutment A2 at km 35+570
Monthly Progress Brief January 2015
UG-V
Culvert work at 7+339 RHS in progress GSB work at 1+200 RHS in progress UG-IVA
Box Culvert in Progress at Km.0+980 PVD Work in Progress
UG-VI
DBM COMPLETED IN RHS IN CH: 1+670 to 2+420 LHS: Lawn Plantation and Green belt plantation at Kurinji Camp
RHS: Air Monitoring and waste collection at Kurinji Camp