Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the TSG and EE Bureau. The formats for the cumulative progress (QPR) which is due in the bureau and TSG by 16 th of April, July, October and January is not received in time. The format for the report is as given below :

description

FINANCIAL STATUS (SSA) Cumulative approved outlay for Civil works till date (Rs. In lakhs) Cumulative expenditure in Civil works till date (Rs. In lakhs) Percentage Expendi ture (%) Remarks 1234 FINANCIAL STATUS (NPGEL) Cumulative approved outlay for Civil works in NPGEL till date (Rs. In lakhs) Cumulative expenditure in Civil works in NPGEL till date (Rs. In lakhs) Percentage Expendi ture (%) Remarks FINANCIAL STATUS (KGBV) Cumulative approved outlay for Civil works in KGBV till date (Rs. In lakhs) Cumulative expenditure in Civil works in KGBV till date (Rs. In lakhs) Percentage Expendi ture (%) Remarks 1 3

Transcript of Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year...

Page 1: Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the.

Monitoring of Civil Works

• Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the TSG and EE Bureau.

• The formats for the cumulative progress (QPR) which is due in the bureau and TSG by 16th of April, July, October and January is not received in time. The format for the report is as given below :

Page 2: Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the.

Quarterly Progres of civil works as on 30th June/ 30th Sep/ 31st Dec/ 31st March ___________ Year

(Physical Status)

State: _______________

S.No. ActivitiesTargets till date

(Units) Cumulative

Completed (Units)

Cumulative

In Progress

(Units) Cumulative

Remarks

1 2 3 4 5 6

1 BRCs        

2 CRCs        

3 New school buildings (Primary)        

4 New school buildings (Upper Primary)        

5 Existing schools/ building less schools (Primary)        

6 Existing schools/ building less schools (Upper Primary)        

7 Additional classrooms (Primary)        

8 Additional classrooms (Upper Primary)        

9 Toilets (Primary)        

10 Toilets(Upper Primary)        

11 Drinking water (Primary)        

12 Drinking water(Upper Primary)        

13 Other components        

  TOTAL        

Page 3: Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the.

FINANCIAL STATUS (SSA)

Cumulative approved outlay for Civil works till date (Rs. In lakhs)

Cumulative expenditure in Civil works till

date (Rs. In lakhs)

Percentage Expenditure (%)

Remarks

 

1 2 3 4

           

FINANCIAL STATUS (NPGEL)

Cumulative approved outlay for Civil works in NPGEL till date (Rs. In lakhs)

Cumulative expenditure in Civil works in

NPGEL till date (Rs. In lakhs)

Percentage Expenditure (%)

Remarks

  1   2 3 4

           

FINANCIAL STATUS (KGBV)

Cumulative approved outlay for Civil works in KGBV till date (Rs. In lakhs)

Cumulative expenditure in Civil works in

KGBV till date (Rs. In lakhs)

Percentage Expenditure (%)

Remarks

  1     3  

Page 4: Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the.

• Cumulative Progress : It means targets both physical and financial from the date of inception of SSA and up to the date of reporting as approved by PAB in AWP&B. (Targets for 2001-02, 2002-03, 2003-04, 2004-05, 2005-06 and 2006-07)

• Any revision of targets whether financial or physical will not be accounted for by the State in the report until re-appropriated by PAB.

• States are not authorized to change the targets without prior approval of PAB.

Page 5: Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the.

• Current Year Progress (MPR) : It means targets approved by PAB for the AWP&B of the current year. These will be only fresh targets without any spill over

• Any revision of targets whether financial or physical will not be accounted for by the State until re-appropriated by PAB.

• The format is as under :

Page 6: Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the.

Monthly progress of SSA Civil works approved by PAB for AWP & B 2006 - 07 (Fresh Work)

State :- Month :- Year :- (Rs. In lakhs)

Sr. No. Name of Components

Fresh approval for AWP & B

Physical (Unit)

Completed (Physical) (Unit)

In progress (Physical) (Unit)

Financial out lay approved in AWP & B for for civil works

Expenditure against Fresh approvals

1 2 3 4 5 6 7

1 BRC          

2 CRC          

3

New primary schools          

Buildingless School          

Dilapidated buildings          

4

New UP schools          

Buildingless schools          

Dilapidated building          

5

Additional classrooms (Primary)          

Additional classrooms (U.Pry)          

6Drinking water (Pri.)          

Drinking water (U.Pry)          

7Toilets (Primary)          

Toilets (U.Pry)          

TOTAL          

Page 7: Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the.

• Some of the problem being faced by TSG and Fax sent to States on 23rd October, 2006 are :

• Haryana : Report on Cumulative (QPR) has not been received along with the reports sent by you

• Meghalaya : Report on MPR & Teacher Recruitment has not been received along with the reports sent by you

• Punjab : Report on MPR & Teacher Recruitment has not been received along with the reports sent by you

• Rajasthan : Report on Teacher Recruitment has not been received along with the reports sent by you

• Tamil Nadu : Report on Teacher Recruitment has not been received along with the reports sent by you

Page 8: Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the.

• Tripura : Report on Cumulative (QPR) has not been received along with the reports sent by you

• West Bengal : Report on MPR & Teacher Recruitment has not been received along with the reports sent by you

• Andhra Pradesh, Arunachal Pradesh, Assam, Bihar, Chattisgarh, Himachal Pradesh, Karnataka, Kerala, Madhya Pradesh, Maharashtra, Manipur, Mizoram, Nagaland, Orissa, Sikkim, Uttar Pradesh, Uttranchal, Andaman Nicobar, Chandigarh, Dadra & Nagra Haveli, Daman Diu, Delhi, Lakshadweep & Pondicherry did not send their report by 23rd of October, 2006, although letter from Mr. K.R. Meena (Deputy Secretary) was addressed to them on 4th October, 2006 and even in normal course the reports were to be received by 16th of the month (October, 06).

Page 9: Monitoring of Civil Works Compiling of cumulative progress (QPR) and progress for the financial year fresh works have been a matter of concern for the.

• Other problem being faced are :• Reports are not submitted on prescribed formats.

• Financial Progress is not shown in the progress report.

• While sending cumulative progress the current year targets are not added.

• The targets are changed by the States without prior approval of PAB.

• The reports are not received on prescribed formats

• While submitting report, the same is not compared with previous report

• Minus progress has been reported by Karnataka, Orissa, Punjab, Daman Diu & Pondicherry.