Mohawk View Water Treatment Plant - Filter Failurenysawwa.org/docs/pdfs/5B-When Water Filters...
Transcript of Mohawk View Water Treatment Plant - Filter Failurenysawwa.org/docs/pdfs/5B-When Water Filters...
Outline The Mohawk View Water Treatment Plant & 2005
Expansion
What Happened?
2010 Failure and Subsequent Failures
Investigation of the Failure
Remediation & Repair
What We Learned
Q&A
Today
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Plant Expansion to 31.5 MGD - Rebuilt Filters 1 - 6 - New Filters 7 - 10
Timeline
The Mohawk View Water Treatment Plant EXPANSION
Capacity: 31.5 MGD
2005: Completed $24 Million Expansion
• 4 New Dual Media Filters
• 6 Existing Filters Rebuilt
• All Filters Had Under Drain Systems and Utilized Filter Media Support Caps
Today
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Plant Expansion to 31.5 MGD - Rebuilt Filters 1 - 6 - New Filters 7 - 10
All appears fine...making water
Grout Repairs in Filters 7 & 8 - Manufacturer
Representative instructs operators on repair techniques
- Repairs went well
Timeline
Today
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Plant Expansion to 31.5 MGD - Rebuilt Filters 1 - 6 - New Filters 7 - 10
All appears fine...making water
Grout Repairs in Filters 7 & 8 - Manufacturer
Representative instructs operators on repair techniques
- Repairs went well
Media loss observed in Filter 4 - Underdrain uplift noted - Manufacturer notified
Timeline
Today
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Plant Expansion to 31.5 MGD - Rebuilt Filters 1 - 6 - New Filters 7 - 10
All appears fine...making water
Grout Repairs in Filters 7 & 8 - Manufacturer
Representative instructs operators on repair techniques
- Repairs went well
Media loss observed in Filter 4 - Underdrain uplift noted - Manufacturer notified
May 2011 – Media removed from Filter 4
June 2011 – Manufacturer site visit & inspection of failure
July, 2011 – Manufacturer’s report - Rebuild Filter 4 with new
underdrains - Town decides to have an
independent review of the failure
Timeline
Manufacturer’s Initial Inspection
• A split media support cap was found at the back end of the filter
• No noticeable leaks
were found where the media support cap attaches to the underdrain blocks
Manufacturer’s Inspection Conclusions
• Leaks along orifice plate allowed media to enter underdrain
• Not much media inside laterals away from failure point
• Media support caps hydraulically tested – pressure drop in “normal range”
• Media under caps only where cap was split
• L-rod installed improperly … no epoxy, easily pulled out of the tank floor
Manufacturer’s Recommendations
REBUILD FILTER
• Remove all underdrains and base grout
• Backwash and flush all media from filter #4 flume and piping
• Remove and clean & reinstall the orifice plate
• Install new underdrain
• Test new system and re-install media
Today
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Plant Expansion to 31.5 MGD - Rebuilt Filters 1 - 6 - New Filters 7 - 10
All appears fine...making water
Grout Repairs in Filters 7 & 8 - Manufacturer
Representative instructs operators on repair techniques
- Repairs went well
Media loss observed in Filter 4 - Underdrain uplift noted - Manufacturer notified
May 2011 – Media removed from Filter 4
June 2011 – Manufacturer site visit & inspection of failure
July, 2011 – Manufacturer’s report - Rebuild Filter 4 with new
underdrains - Town decides to have an
independent review of the failure
B&L begins investigation of filter failure
Timeline
Filter Investigation
Determine the Cause of Filter 4 Failure
Assess Potential for Other Filters to Fail
Filter Investigation
Backwash Observations:
Continued air release during
High Rate Wash
Significant Boils along
Gullet wall
Filter Investigation
Air vent during water wash
Air must vent through underdrains
Air line installed low
Filter Investigation Here is what happens when media builds up under media support caps. Filters 1 & 5 Shut Down
Today
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Plant Expansion to 31.5 MGD - Rebuilt Filters 1 - 6 - New Filters 7 - 10
All appears fine...making water
Grout Repairs in Filters 7 & 8 - Manufacturer
Representative instructs operators on repair techniques
- Repairs went well
Media loss observed in Filter 4 - Underdrain uplift noted - Manufacturer notified
May 2011 – Media removed from Filter 4
June 2011 – Manufacturer site visit & inspection of failure
July, 2011 – Manufacturer’s report - Rebuild Filter 4 with new
underdrains - Town decides to have an
independent review of the failure
B&L begins investigation of filter failure
Media loss observed at Filters 1 & 5 Filters 1 & 5 shut down
Timeline
B&L Filter Investigation Conclusions Low air vent from flume results in boils and loss
of media during backwash
Media leakage around orifice plate resulted in
Media buildup under support caps
Excessive backwash cycle pressure
CATISTROPHIC FAILURE OF Filter 4 UNDERDRAIN STRUCTURE
Repair Filters 4, 1 & 5 as “Emergency”
Today
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Plant Expansion to 31.5 MGD - Rebuilt Filters 1 - 6 - New Filters 7 - 10
All appears fine...making water
Grout Repairs in Filters 7 & 8 - Manufacturer
Representative instructs operators on repair techniques
- Repairs went well
Media loss observed in Filter 4 - Underdrain uplift noted - Manufacturer notified
May 2011 – Media removed from Filter 4
June 2011 – Manufacturer site visit & inspection of failure
July, 2011 – Manufacturer’s report - Rebuild Filter 4 with new
underdrains - Town decides to have an
independent review of the failure
B&L begins investigation of filter failure
Media loss observed at Filters 1 & 5 Filters 1 & 5 shut down
Emergency declared - Filters 1, 4 & 5 Fast-track rehab
initiated - Filters 2, 3 & 6 rehab also initiated
Timeline
Today
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Plant Expansion to 31.5 MGD - Rebuilt Filters 1 - 6 - New Filters 7 - 10
All appears fine...making water
Grout Repairs in Filters 7 & 8 - Manufacturer
Representative instructs operators on repair techniques
- Repairs went well
Media loss observed in Filter 4 - Underdrain uplift noted - Manufacturer notified
May 2011 – Media removed from Filter 4
June 2011 – Manufacturer site visit & inspection of failure
July, 2011 – Manufacturer’s report - Rebuild Filter 4 with new
underdrains - Town decides to have an
independent review of the failure
B&L begins investigation of filter failure
Media loss observed at Filters 1 & 5 Filters 1 & 5 shut down
Emergency declared - Filters 1, 4 & 5 Fast-track rehab
initiated - Filters 2, 3 & 6 rehab also initiates
Filter 5 back on line 6/21/13
Filter 4 back on line 6/26/13
Filter 1 back on line 8/12/13
Timeline
Filters 2, 3, & 6 non-emergency rehab complete
What Was Learned ‘Institutional Knowledge’ Has Left The Building
retirement of key workers
Do Not Underestimate Apparently Small Problems
track down problems to their root cause
relentless attitude is needed when problems arise
Get Others Involved Early
Design Engineers
Manufacturers