Mogden Sewage Treatment Works - Thames Water...Mogden Update newsletter – general notification...
Transcript of Mogden Sewage Treatment Works - Thames Water...Mogden Update newsletter – general notification...
Thames Water
Agenda
� Review of previous minutes
� Operations and communications
� Talk: Mogden Plan 2021 and Beyond
� Mosquito survey results
� Sewage Treatment Work Upgrade Project – an update
� AOB
Thames Water
Operations update
� WAMI (Work, Asset Management and Information) has been introduced at Mogden
� The planning of work carried out by Technicians on site is now fully automated and will ensure the right person is in the right place at the right time with the right tools
� New handheld devices will record all work carried out on our assets which will allow robust future investment decisions to be made
� Enables seamless integration of Operations and Maintenance functions
Thames Water
Operational Correspondence2009 – 2012
0
10
20
30
40
50
60
70
80
90
100Ja
n-0
9
Fe
b-0
9
Ma
r-0
9
Ap
r-0
9
May-0
9
Ju
n-0
9
Jul-
09
Au
g-0
9
Se
p-0
9
Oct-
09
No
v-0
9
Dec-0
9
Ja
n-1
0
Fe
b-1
0
Ma
r-1
0
Ap
r-1
0
May-1
0
Ju
n-1
0
Jul-
10
Au
g-1
0
Se
p-1
0
Oct-
10
No
v-1
0
Dec-1
0
Ja
n-1
1
Fe
b-1
1
Ma
r-1
1
Ap
r-1
1
May-1
1
Ju
n-1
1
Jul-
11
Au
g-1
1
Se
p-1
1
Oct-
11
No
v-1
1
Dec-1
1
Ja
n-1
2
Fe
b-1
2
Ma
r-1
2
OtherMosquitoesOdour and mosquitoesOdour
Thames Water
Notifications December – Present
December 2011� Mogden Upgrade – Christmas construction activity
January 2012� Mogden Upgrade – construction update
February 2012� Mogden Update newsletter – general notification� Primary tank drain down – a precautionary notice � Mogden Upgrade – construction update� Primary tank drain down – a precautionary notice
March 2012� None
Thames Water
Communications update
� Our latest Mogden Update newsletter went out in February 2012
� A new interpretation board has been installed in the middle of the public footpath that runs through Mogden telling passers by about the sewage treatment process
2
Thames Water’s obligations
� Legal requirement to effectively drain and treat sewage
including planning for population growth
(Section 94 Water Industry Act 1991)
� Legal requirement to meet water quality discharge standards
set by the Environment Agency
(Urban Wastewater Treatment Directive)
� Regulatory requirement to maintain stable serviceability of our
assets and processes (Ofwat)
� Provide good value for money for our customers
3
History of Mogden STW
� 1930’s – A and B batteries were constructed as part of the West
Middlesex Drainage Scheme
� 28 small STWs were closed and replaced with a large trunk sewer
system draining to Mogden STW
� 1960’s – C battery was constructed
� 1999 – D battery was constructed
� 2011 E battery is being constructed, anticipated completion date in 2013
4
Drivers for expansion
Population growth
� London’s population is expected to increase over the next
10 - 20 years
� Increases in volumes of wastewater will require treatment
and storage using more or larger tanks
Water quality obligations
� Continual improvement of the River Thames through more
stringent water quality obligations
� Solutions to meet these standards often requires more or
larger tanks to increase treatment capability
5
2011 – 2021
� Current extension project is designing to a 2021 horizon
� Designed with some headroom likely to accommodate growth until 2026
� 2010 London Plan housing target of 62,300 additional units
� Predicted population increase of 149,500
6
2011 – 2021
� Current upgrade is to meet a new suspended solids and
more stringent ammonia and BOD discharge standard
� Improved quality of final effluent
� Increased capacity will reduce the frequency of storm
discharges to the River Thames
� Potential future requirements include chemical treatment
using nitrogen, phosphorus
� The EA has not yet made a decision about these therefore
there is uncertainty about future quality requirements after
2016
7
Post 2021
� Continued population growth post 2021 is difficult to forecast accurately
� GLA forecast of 6% from 2021 up to 2031
� Predicted population increase of 144,100
2021 - 2031 GLA Population Forecast
1950000
2000000
2050000
2100000
2150000
2200000
2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
population
8
Post 2021
� Uncertainty in population growth forecasts and new quality
obligations
� The water industry undertakes medium term planning in 5
year AMP cycles
� Water efficiency is forecast to increase due to more
environmentally efficient homes and water saving initiatives
– this will reduce flows
� Sustainable urban drainage and the removal of surface
water from the foul sewers – this will reduce flows
� There will still be a net increase in flow and load
(concentration of waste matter)
9
Post 2021
� Mogden will continue to be the main treatment works for all
sewage coming from the existing catchment
� Mogden will continue to meet all quality standards set by the
Environment Agency
� Some land is available for a post 2021 expansion if necessary
� Innovative solutions to increase treatment capacity - doing
more with what we have rather than building more
� Save customers money and minimise our carbon foot print
� All options will be investigated before an investment decision is
made – Best whole life cost option
� Continue to work with our neighbours and regulators on
managing and minimising odour
Thames Water
Guide to week numbers – 2012
January Weeks 1 – 5February Weeks 5 – 9March Weeks 9 – 13April Weeks 13 – 18May Weeks 18 – 22June Weeks 22 – 26July Weeks 26 – 31August Weeks 31 – 35September Weeks 35 – 39October Weeks 40 – 44November Weeks 44 – 48December Weeks 48 - 52
Thames Water
Mosquito data- Number of sites inspected
0
50
100
150
200
250
300
350
400
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Week
Nu
mb
er
of
sit
es
Average 03-07 2008 2009 2010 2011 2012
Thames Water
Mosquito data- Percentage of sites showing any activity
0
5
10
15
20
25
30
35
40
45
50
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Week
% o
f s
ite
s w
ith
an
y a
cti
vit
y
.
Average 03-07 2008 2009 2010 2011 2012
Thames Water
Mosquito data- Percentage of sites showing any adults
0
5
10
15
20
25
30
35
40
45
50
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Week
% o
f sit
es
wit
h a
cti
vit
y
.
Average 03-07 2008 2009 2010 2011 2012
Thames Water
Mosquito data- Percentage of sites with many adults
0
5
10
15
20
25
30
35
40
45
50
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Week
% o
f s
ite
s w
ith
ac
tiv
ity
.
Average 03-07 2008 2009 2010 2011 2012
Thames Water
Mosquito data- Percentage of sites with many adults (2)
0
1
2
3
4
5
6
7
8
9
10
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Week
% o
f s
ite
s w
ith
ac
tiv
ity
.
Average 03-07 2008 2009 2010 2011 2012
Thames Water
Mosquito data- Percentage of sites with larvae activity
0
5
10
15
20
25
30
35
40
45
50
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51
Week
% o
f sit
es
wit
h a
cti
vit
y
.
Average 03-07 2008 2009 2010 2011 2012
Key progress to date
� Most of the civil engineering work - such as building foundations and
tanks – is now complete.
� This means our noisiest construction activities are over.
� The focus of our work continues to be on mechanical and electrical
installation.
� We have started reducing the western embankment to its final height,
which will be carried out in phases until completion in the autumn.
Inlet works
This is where we filter the sewage to remove grit and other large items.
� The structures are complete and most of the mechanical equipment has been installed.
� We are currently installing the odour control covers, and the power supply to the new equipment.
� We will commission the new inlet works in the spring.
Primary settlement tanks
This is where solids settle to the bottom and are then removed.
� The main structures are
complete and all the
associated mechanical
equipment has been
installed.
� We are now working on
connecting the new covered
tanks to the new odour
control unit and finishing the
electrical infrastructure.
� We will start commissioning
in the spring.
Aeration lanes
This is where we encourage bacteria to eat the organic matter.
� All five new lanes are
complete.
� 1000 pre-cast panels have
been used to create the
lanes, reducing the number
of deliveries to site and
impact on local traffic.
� We are now constructing
the Intermediate Pumping
Station.
Final settlement tanks
This is where the remaining solids are removed before the effluent is returned to the River Thames.
� Eight of the ten new final tanks have been built.
� The remaining two tanks will be finished this month.
� Backfilling has started around the FSTs (see picture)
Sludge stream
This is where the remaining sludge is broken down and turned into energy.
� Five new gas compressors
and a new raw sludge
holding tank are now
operational.
� 11 of the 16 digesters
have been refurbished.
� This work will allow us to
power up to 40 per cent of
the new extension with
renewable energy.
New odour control units (OCU)
We are installing two new odour control units as part of this project:
� OCU no.11 will control the odour for the new Inlet works and primary tanks. Installation will be complete around spring 2012 when it will be fully commissioned.
� OCU no.12 will control the odour for the new sludge stream. We will soon start building this, which will be complete by the end of 2012.
The western embankment
� We’ve started removing the earth temporarily placed on the mound, meaning the embankment will be back to its original height in the autumn.
� At this point we will start planting the embankment and surrounding area with native trees, shrubs, and herb-rich grassland including wildflowers, encouraging biodiversity and improving our neighbours outlook.
Electrical infrastructure
� As part of the upgrade
we are also upgrading
the electrical
infrastructure.
� We recently took
delivery of two new 40-
tonne transformers.
� In conjunction with the
renewable energy that
we generate on site,
these will provide
enough electricity to
power the entire works.
In the community – Thames 21 clean-up
� Thames Water
and Black &
Veatch staff
volunteered with
Thames 21 in
February.
� Cleared litter and
debris from river
bed around
Isleworth Ait.
� Similar events
planned for
coming months.
Tour of upgrade works
� Dates available to tour of new works are as follows:
� Thursday 12 April
� Thursday 19 April
� Thursday 26 April
� There are two time slots available:
� 10am to 12.30pm
� 2pm to 2.30pm
� All attendees will receive a Health & Safety induction ahead of the tour
� An invitation will be sent out and joining instructions will follow
Thames Water
Proposed dates of meetings:
� Wednesday 6 June 2012
� Wednesday 5 September 2012
� Wednesday 5 December 2012
Thames Water
Need to contact us about Mogden?
Call the Mogden 24hr line (via the Thames Water
Operations Contact Centre):
0845 641 0030
To subscribe to email notifications, email us at:
Visit our website:
www.thameswater.co.uk/mogden
Write to us:
Customer FeedbackPO Box 286
SwindonSN38 2RA