1 Welcome to Worley Parsons Project Management Process (WPMP) Training Module 9 – Managing Project Procurement

description

training

Transcript of Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    1/77

    1

    Welcome to Worley Parsons Project Management

    Process (WPMP) Training

    Module 9Managing Project Procurement

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    2/77

    2

    Managing Project Procurement

    Introduction

    Overview of Procurement

    Responsibilities for Procurement

    Commencing the Procurement Process \Procurement Planning

    SmartPlant Materials

    Procurement Reports

    Procurement Initiation

    Procurement Execution

    Procurement Close-out

    About this training session

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    3/77

    3

    Learning Objectives

    On completion of this module, you will be able to:

    Identify and understand the procurement methodologies and tools

    available to Project Managers for the management of EPCM

    projects

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    4/77

    4

    Learning Outcomes

    Early involvement of the Procurement function in project planning

    is essential

    The projects procurement strategy and procurement plan must

    align with the overall project strategy

    Clear definition of the objectives of the Procurement Process is

    critical for the project team

    On completion of this module, you will be able to demonstrate an

    understanding that:

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    5/77

    5

    Procurement is an integral part of the WorleyParsons growth

    strategy

    Procurement shall support the company to compete more

    successfully as a leading provider of professional servicesworldwide

    Procurement in WorleyParsons

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    6/77

    6

    Overview of Procurement

    Procurement is the process by which materials, equipment andthird-party services are acquired for projects

    Key procurement interfaces include:

    Project Management Engineering

    HSE

    Quality

    Cost Estimation

    Project Controls

    Construction Management

    Legal & Risk

    What is procurement?

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    7/777

    Overview of Procurement

    At the best possible total cost of ownership

    In the right quantity and quality

    At the right time

    In the right place

    For the direct benefit of the customer

    What does procurement involve?

    the acquisition of materials, equipment or third-party services:

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    8/778

    Procurement and Capex

    The Capital Expenditure (Capex) of a Project can be split into a

    few elements:

    Engineering and designapprox. 10% of Capex

    Procurement: Materials and equipmentapprox. 30 to 45% of Capex

    Contractsapprox. 30 to 45% of Capex

    Balance is owners costs, insurance, land purchases etc

    The above is indicative only and dependent on the type and

    location of a project. However, on average the Capex element

    managed by procurement ranges between 60% and 90% of the

    overall project value

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    9/779

    Overview of Procurement

    Procurement is the bridge between Engineering (design) and

    Construction (execution)

    What is the role of procurement in a project?

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    10/7710

    Overview of Procurement

    Materials Management

    Purchasing, Expediting, Materials Control, Coordination ofInspection (liaising with Quality), Traffic/Logistics, Warehousing/

    Inventory Control etc

    Legal agreement used is a Purchase Order

    Contracts

    Acquisition and management of third-party services

    Legal agreement used is a Contract

    Both Purchase Orders and Contracts are written and binding legal

    agreements between relevant parties to supply either goods or

    services against agreed conditions

    Procurement is divided into 2 functions

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    11/7711

    Procurement Executive Directive

    To minimise risk exposure, procurement services are usually

    provided for and on behalf of Customers, in the Customers name

    or on Customer paper this is the companys preferred position

    However, this does not preclude provision of procurement servicesin WorleyParsons name or on WorleyParsons paper requires

    CEO to proceed in any event where additional supplier-related

    risks and liabilities are assumed (eg warranty obligations, delivery

    commitments, product liability, etc)

    In most instances, procurement services are provided on behalf of

    the Customer, requiring active interaction with the Customer and

    their various approvals to proceed

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    12/7712

    EMS Workflows and Procedures 1/2

    Contracts services cover the provision of third-party services such as

    construction labor, inspection services, painting and sand blasting

    The provision of contract services is governed by the Contracts

    Workflow in EMS containing a number of procedures, guidelines,

    forms and templates

    Preferred Terminology:

    ITT = Invitation to Tender

    Contract = legal agreement for the provision of services

    Contracts

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    13/7713

    EMS Workflows and Procedures 2/2

    Materials Management includes the purchasing of goods and

    equipment, subsequent expediting, inspection and receipt.

    The provision of Materials Management services is governed by the

    Materials Workflow in EMS containing a number of procedures,

    guidelines, forms and templates

    Materials Management activities are managed and tracked through

    SmartPlant Materials, WorleyParsons Materials Management system

    which starts from creation of the requisition through to final material

    reconciliation on site

    Preferred Terminology:

    RFQ = Request for Quotation

    Purchase Order (PO) = legal agreement for the supply of goods

    Materials Management

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    14/7714

    Overview of Procurement

    WorleyParsons procurement process

    Pre-award Activities* Materials Management

    * ContractsObtain quotations

    Select the preferred suppliers

    Project Procurement PlanDetermine procurement

    requirements

    Procurement InitiationIdentify potential

    suppliers

    Post-award ActivitiesManage the supplier

    Administer POs and contractsManage POs/ contract variation

    Expediting / Inspection

    Materials Field AdministrationActivities

    Field PurchasingTransport/ Logistics

    Receipt on siteWarehousing

    Close-out ActivitiesConclude the engagement of the

    suppliersRecord the performance against

    each order & contract

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    15/77

    15

    Responsibilities for Procurement

    As Project Manager, you are responsible for the overall

    management of procurement activities associated with the project

    You are not responsible for the execution of procurement activities

    That is the responsibility of your Project Procurement Manager

    To fulfill your responsibilities, you should work closely with the

    Procurement Manager

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    16/77

    16

    Responsibilities for Procurement

    Procurement specialists in each region

    Detailed procurement procedures, guidelines and associated

    documentation

    Deployment of SmartPlant Materials as the company-wide materials

    control system to record, track and report on procurement activity

    Global supplier database for materials, equipment and services

    Global Sourcing initiatives

    Supply arrangements with key suppliers

    WorleyParsons procurement capability

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    17/77

    17

    Procurement staff managing the Materials Management andContracts activities usually:

    Work either from a core Procurement group in a key companylocation or

    Form a part of a dedicated project procurement team

    Procurement activities on the project are usually led by anexperienced Project Procurement Manager

    Where warehousing staff are required for specific customers orprojects, they are usually located on site

    Inspection may involve in-house or third-party inspectors, dependingon the location of the inspection activities

    Procurement resourcing

    Responsibilities for Procurement

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    18/77

    18

    Procurement Process

    Establish exactly what the customer requirements are andwhatWorleyParsons has committedto do

    Establish your procurement team and set out their responsibilities

    Procurement to participate in the Project Risk Assessment and ensure thatrisk mitigation is included in the Procurement Plan to be developed

    Procurement to incorporate appropriate flow-down conditions from the Primecontract (the agreement between Customer and WorleyParsons) in theProject Conditions to ensure compliance and alignment (e.g. includingcustomers confidentiality requirements, alignment of warranty periods etc.)

    Procurement to develop the project procurement procedures, based on EMSbut incorporating as appropriate Customers requirements (e.g. approvalinterfaces)

    Arrange to have the project set up on SmartPlant Materials

    Ensure WBS is established

    Commencing the procurement process for a project

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    19/77

    19

    Procurement Planning

    Planning is at the crux of all project activities

    Procurement is no exception

    The aim of procurement planning is to:

    Know what needs to be procured, when, where and how

    Identify critical long lead items and services

    Establish order and consistency in the way the procurementactivities are performed

    Understand the risks involved in the project environment andidentify mitigating actions

    The Project Procurement Plan is part of the Project ExecutionPlan

    Planning

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    20/77

    20

    Procurement & Risk Management

    Procurement is an integral part of risk management on the project

    Develop appropriate procurement/ contracts/ materials managementstrategies, identifying the various risks (market, forex, local content

    requirements, taxation and importation issues, logistics complexities,

    etc. to be managed) Use EMS procurement procedures to the largest extent, however,

    recognize Customer requirements in the project specific procedure.

    Ensure that the project specific procurement procedures areapproved by the customer and shared with the project procurement

    team Develop the procurement schedule early, in line with the overall

    project schedule, resulting in correct priorities to achieve the

    Required on Site Dates

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    21/77

    21

    Procurement Planning

    What you need to plan for

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    22/77

    22

    Procurement Planning

    When planning occurs

    Identify Evaluate Define Execute Operate1 2 3 4

    Procurement Strategy

    Procurement Plan

    Materials Management Plan, if required

    Purchasing and Contracts Initiation

    Materials Management Plan, if required

    Contracts Plan, if required

    Materials Field Administration

    Contracts Plan, if required

    Materials Management and Contracts Close-out

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    23/77

    23

    Procurement Planning

    Project Procurement Strategy (PPS) is the:

    Process for identifying and documenting the procurement

    opportunities applicable to the project First step in developing the Project Procurement Plan

    Typically, the PPS is first developed during the scoping stages of a

    project

    Sometimes the customer provides the initial procurement strategy for

    further development in the Project Procurement Plan

    Project Procurement Strategy

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    24/77

    24

    Procurement Planning

    Purchasing activities can involve long lead times

    Certain materials and equipment may be particularly critical to a

    projects success

    Purchasing activities usually involve multiple countries (infrastructureand logistics, local legislation etc.)

    Market and technology developments can impact on the success of a

    project and therefore need to be monitored on an ongoing basis

    During the development of the PPS, the following factors need to be

    considered:

    Project Procurement Strategy

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    25/77

    25

    Procurement Planning

    The PPS is a hierarchical matrix covering the entire work scope of a

    project, broken down into separate work packages

    Only the major critical items are separately identified as work packages

    These packages are created and identified according to:

    Unique technical and commercial attributes of the work activities

    they comprise Methods by which they are to be executed

    Project Procurement Strategy

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    26/77

    26

    Procurement Planning

    Example of a PPS matrix

    Components

    Physical

    Discipline

    SpecialEquipment Item A

    SpecialEquipment Item B

    Balance of Plant Civil Works

    ProjectManagement

    Project Management Services ContractorReimbursable Costs withIncentives Fee$ 70m total

    Design Design Contract

    Lump Sum

    $10m Facilities E & P Contract

    Reimbursable Costs with Fixed Fee$30m totalProcurement

    SpecialistSupplier ALumpSum PurchaseOrder$200mtotal

    SpecialistSupplier BLump SumPurchase Order$100m total

    FabricationConstruction ContractReimbursable Cost and EquipmentRates with Incentives Fee - $100M

    total

    Materials Control

    Construction /Erection Services

    Installation Contract

    Lump Sum

    $10m

    Quality InspectionSpecialist Quality ContractAll-inrates$10m

    Part of Project Management Services

    Commissioning /Start-up

    Assistance

    Part of Supplier APurchase Order

    Part of Supplier BPurchase Order

    Contract N/A

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    27/77

    27

    Procurement Planning

    The structure of the PPSdepends on the:

    Scope of work

    Nature and complexity of the project

    Requirements of the customer

    The PPS assists in:

    Administrative and commercial planning

    Cost/schedule control functions of a project

    Project Procurement Strategy

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    28/77

    28

    Procurement Planning

    Allows a concise, high-level overview of how procurement activities

    relate to the execution strategy of the project

    Illustrates alternative ways of executing the project procurement

    activities

    Identifies where:

    Consolidation (or further break-down) of work scopes can work tothe projects advantage

    Gaps may occur in hand-offs during execution

    A Procurement Strategyis a deliverable that can be provided for

    projects in Identify and Evaluate phase

    Benefits of a PPS

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    29/77

    29

    Procurement Planning

    When planning occurs

    Identify Evaluate Define Execute Operate1 2 3 4

    Procurement Strategy

    Procurement Plan

    Materials Management Plan, if required

    Purchasing and Contracts Initiation

    Materials Management Plan, if required

    Contracts Plan, if required

    Materials Field Administration

    Contracts Plan, if required

    Materials Management and Contracts Close-out

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    30/77

    30

    Procurement Planning

    Projects in Identifyand Evaluatephases:

    While you might not be able to fully identify these requirements, youshould be able to identify them in broad scope

    Concentrate on Procurement Strategy approach

    Projects inDefinephase:

    The procurement needs of the project should be sufficiently identified tosupport the Customers overall project schedule

    Full fledged procurement plan can be developed

    Projects inExecutephase:

    The procurement needs are clearly identified and a procurement planshall be developed to achieve the timely delivery of the project

    Full fledged procurement plan must be developed

    Planning in the various WMPM project phases

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    31/77

    31

    Procurement Planning

    Documents the basis for obtaining and managing materials,equipment and third-party services required for project execution

    Addresses relevant aspects of both materials management andcontracts for the project

    Maps out the various anticipated risks and constraints and identifiedmitigating actions

    Identifies critical supplies (see also Procurement Strategy) andoutlines general strategy

    Ensures that the procurement activities align with the overall projectschedule

    Project Procurement Plan

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    32/77

    32

    Procurement Planning

    The Project Procurement Plan:

    Must clearly define the deliverables of the procurement process

    Needs to be fit for its purpose

    Project Procurement Plan

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    33/77

    33

    Procurement Planning

    The Project Procurement Plan

    may also include details about

    the targeting of procurement

    efforts

    The Project Procurement

    Manager will consider the

    assessment in the strategy

    development

    Criticality-Value Assessment

    Project Procurement Plan

    Bottleneck, e.g. specialalloy steel grade

    Ensure continuity

    Develop alternativesRevise specifications

    Critical, e.g. turbinecompressor

    Form closer relationships

    Direct negotiations

    Routine, e.g. pipingbulk blanket orders

    Simplify procurementprocess

    Automate

    Rationalise supplier base

    Leverage, e.g. customersstandard agreement

    Maximise commercialadvantage

    Competitive tender

    Standardisation

    Criticality

    Low

    Low High

    Value Potential

    High

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    34/77

    34

    Procurement Planning

    Project Procurement Plan

    Where the complexity and / or size of the project warrant it, the Project

    Procurement Plan may be further developed in separate plans:

    A detailed Project Materials Management Plan

    Separate detailed Project Contracts Plan for major contractpackages

    Separate detailed Procurement Plans for key procurementpackages

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    35/77

    35

    Procurement Planning

    The various elements of the Procurement Plan are further defined in the

    Materials Management Plan, including:

    Specific strategies for buying materials and equipment

    Associated activities for managing the expediting, traffic/logistics etc

    The materials control and reporting systems

    Prioritization of procurement activities and associated engineering

    deliverables in line with the ROS (Required on Site dates) as definedin the project schedule

    Materials Management planning

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    36/77

    36

    Procurement Planning

    Level of procurement effort based on cost, schedule, criticality, and

    other relevant factors

    POs/activities already executed and/or underway prior to

    engagement of WorleyParsons

    Transition of early purchase agreements from the customer

    Material control systems

    Quality management, verification and inspection, which includes an

    outline of inspection to be undertaken

    Site materials management plans

    Materials Management planning (contd)

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    37/77

    37

    Procurement Planning

    Subsets of the Material Management Plan

    Engineered equipment planning

    Bulk materials planning

    Prefabrication planning and modularization

    Materials Management planning

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    38/77

    38

    Procurement Planning

    The primary objective is to ensure that items are acquired and

    released in time to meet the overall project schedule

    The dates on which items are required on site to meet construction

    needs drive the engineering and procurement planning and activityfor engineered equipment

    A major equipment list for the project needs to be developed early

    Engineered equipment planning

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    39/77

    39

    Procurement Planning

    Planning for bulk materials can be more complex than planning for

    engineered equipment

    Bulk materials control starts with an examination of the project

    schedule to assess:

    What bulk materials are required over time

    Critical required on site (ROS) dates

    Bulk material planning

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    40/77

    40

    Procurement Planning

    Procurement planning:

    Is usually very complex for extensive prefabrication

    modularization often involving multiple sites

    An extensive prefabrication program demands an early procurement

    planning effort that addresses the interfaces between vendors,

    fabricators and site construction

    Prefabrication planning and modularization

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    41/77

    41

    Procurement Planning

    The Contracts Plan can be:

    Subset of the Project Procurement Plan or

    Separate planscomplex projects

    The main focus of project contracts planning is the selection the bestcontractor under the best available terms and conditions

    Needs to:

    Analyze the options and the marketplace for the requiredservices

    Define the number, type, scope, timing, interfaces, compensationbasis, etc of major contracts to be developed for the project from

    early planning through start-up

    Contracts planning

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    42/77

    42

    Procurement Planning

    For Projects in the Definephase the Project Contracts Plan needs to

    document:

    Critical contracting issues (e.g. labour resource constraints,market constraints) for the major contracts

    How will the impact be managed and the risk mitigated?

    What is the schedule to meet timely completion of the Project?

    Contracts Planning in Define Phase

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    43/77

    43

    Procurement Planning

    For Projects in the Executephase, the Project Contracts Plan

    review the constraints and identify mitigation measures similar to

    the Define phase projects but not just for major contracts.

    All anticipated contracts are identified.

    If the project is a continuation of a Define phase project, theContracts Plan developed for the Define phase will be

    reviewed and updated by the Project Procurement Manager to

    reflect project progress and significant new developments

    A list of matters that typically need to be considered are listed onpage 32 of the participants manual

    Contracts Planning in Execute Phase

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    44/77

    44

    Procurement Planning

    The customer must approve the Project Procurement Plan as part of

    the Project Execution Plan

    Approving the Project Procurement Plan

    S

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    45/77

    45

    SmartPlant Materials

    WorleyParsons uses a suite of project management systems to

    record, track, control and report on projects

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    46/77

    46

    SmartPlant Materials

    SmartPlant Materials is used to:

    Identify

    Record

    Track

    materials and equipment required and purchased for a project

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    47/77

    47

    SmartPlant Materials

    SmartPlant Materials has four integrated modules, which are described on

    page 36 of the workbook

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    48/77

    48

    SmartPlant Materials

    Maintains the Material Stock Code catalogue

    Generates bulk requisitions via interface to design systems (e.g.PDS)

    Generates equipment and services requisitions

    Preparation of RFQs

    Supports bid evaluations

    Creates and, if required, amends POs

    Facilitates expediting

    Facilitates Traffic/Logistics

    Facilitates stores management

    Can undertake invoice reconciliation via Invoice Matching Interface

    module

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    49/77

    49

    SmartPlant Materials

    SmartPlant Materials imports bills of materials from 2-D/3-D engineering

    design software and other sources

    SmartPlant Materials supports better material planning on site and materialreconciliation through the ability to track imported bills of materials fromRequisition to Material Issue

    Materials are identified as being in any of the following phases:

    Requisition

    RFQ

    Purchasing

    Expediting

    Shipping

    Warehouse receipt

    Storage

    Material Issue

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    50/77

    50

    SmartPlant Materials

    SmartPlant Materials was designed as a system for controlling

    materials and equipment, not for administering contracts

    SmartPlant Materials can, however, be used to record basic

    information about contracts

    Using SmartPlant Materials for recording and tracking contracts

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    51/77

    51

    SmartPlant Materials

    Each individual project needs to be set up in SmartPlant Materials so

    that its procurement activities can be recorded, monitored and

    reported

    SmartPlant Materials should be set up as soon as the ProjectProcurement Plan or Materials Management Plan has been approved

    You are responsible for ensuring that SmartPlant Materials is set up

    properly

    You work with the project Procurement Manager to identify and

    obtain the information for the set up

    Setting up SmartPlant Materials for a project

    SmartPlant Materials Training

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    52/77

    52

    SmartPlant MaterialsTraining

    When you need to start using SmartPlant Materials, you will receive

    specific training on how to use it

    Contact the Business Systems Group to arrange the training

    Training in SmartPlant Materials

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    53/77

    53

    Procurement Reports

    Procurement activities are monitored and reviewed regularly

    SmartPlant Materials generates a range of reports which you use to

    monitor progress and identify actions to be taken to address issues

    Two particularly important reports for the management ofprocurement activities are the:

    Procurement Status Report

    Procurement Expediting Report

    Procurement reports

    P I i i i

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    54/77

    54

    Procurement Initiation

    The Project Procurement Manager is responsible for completing the activities

    that enable purchasing and contracts to be initiated

    The initiation activities should be completed during the early stages of the

    project

    The initiation activities are:

    Purchasing initiation

    Contracts initiation and formulation

    Part of the initiation activities is the development of the Project terms andconditions for purchase orders and contracts.

    These may be provided by the Customer as we will typically be acting ontheir behalf.

    The conditions shall be checked for alignment with the Prime contract.

    Overview of procurement initiation

    P t I iti ti

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    55/77

    55

    Purchasing initiation involves setting up the project base for the

    Purchasing documentation and databases

    The main activities are:

    Identifying PO provisions (including standard Terms andConditions)

    Preparing standard documentation, including Instructions toBidders, master Request for Quotation, master purchase order

    document

    Carrying out vendor pre-qualification

    Establishing a project vendor list

    Overview of purchasing initiation (Materials Management)

    Procurement Initiation

    P t I iti ti

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    56/77

    56

    Contract initiation and formulation involves:

    Setting up the project base for contracts documentation(including standard Terms and Conditions)

    Establishing the contracts system for the project

    The main activities are:

    Establishing the contract types, sites conditions, HSE etc

    Preparing common enquiry requirements and special contractprovisions

    Carrying out contractor pre-qualifications

    Establishing the contractor list

    Overview of Contracts initiation and formulation

    Procurement Initiation

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    57/77

    57

    Procurement Execution

    All procurement execution activities are undertaken by the Project

    Procurement Manager and the Procurement team

    You are responsible for ensuring that the procurement activities are

    executed in accordance with the Project Procurement Plan

    You and your Project Procurement Manager need to hold regular

    meetings to:

    Review the status of procurement activities

    Identify issues early and determine the action required tominimize any adverse impact

    Overview of procurement execution

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    58/77

    58

    Procurement Execution

    The purpose of the Purchasing Pre-award Process is to award the POs under

    which the projects materials and equipment are obtained

    The pre-award process ensures that all bidders are treated fairly and

    equitable, that the confidentiality of the information is maintained and that the

    recommendation to award is in accordance with the agreed evaluation criteria

    Agreed evaluation criteria may be as simple as Technically acceptable,lowest cost or more complex Total Cost of Ownership (TCO). Consider

    that TCO often requires Customer input as well.

    Competitive bidding is indicated. However, if single source is considered

    for purchase orders, justification must be provided. This may includeproprietary technology or customers standardisation preference.

    Project Purchasing pre-award activities occur predominantly during the

    Execution phase

    For long-lead items some activities may occur in the Define phase

    Materials Management executionpurchasing pre-award process

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    59/77

    59

    Procurement Execution

    Preparing enquiry packages, including special terms andrequirements (for example, supplier data, support, spares)

    Issuing the enquiry packages and managing bid preparation andreceipt process

    Managing all communications with bidders during bidding andevaluation

    Evaluating the bids

    Preparing recommendations for award, conducting post-bidnegotiation and facilitating final issue

    Entering all data related to the purchases into SmartPlant Materials

    Materials Management executionpurchasing pre-award process

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    60/77

    60

    Procurement Execution

    Maintains the required level of confidentiality of information

    Ensures that engineering deliverables are aligned to support timelyprocurement activities

    Maintains the interfaces between Engineering, Quality andConstruction

    Involves the Project Procurement Manager in the regular teamprogress meetings

    Undertakes and completes procurement activities in accordance withthe Project Procurement Plan

    Materials Management executionpurchasing pre-award process

    As Project Manager, you will need to ensure that the procurement

    team:

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    61/77

    61

    Procurement Execution

    Purchase Order documents are to be prepared by Engineering and

    Procurement on receipt of the approved Award Recommendation

    Kick-off meetings are arranged as required

    Post-award activities are initiated by the project procurement team

    Once internal and other approvals have been obtained to place a

    contract or a PO theProcurement Manager is the only person with

    the authority to confirm the commitment for the contract or PO with

    the supplier on behalf of WorleyParsons and/or our customers

    Materials Management executionpurchasing award process

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    62/77

    62

    Procurement Execution

    Confirm that the cost of the awarded POs is within theproject budget

    Provide relevant information to the projects Cost ControlsManager

    Materials Management executionpurchasing award process

    You are responsible for ensuring that the award process is

    properly undertaken

    You need to:

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    63/77

    63

    Procurement Execution

    This process covers award of a PO through to receipt at site andfinancial close-out

    The purpose of the Purchasing Post-award Process is to:

    Administer the POs to obtain the projects materials and

    equipment on schedule and in accordance with specifications Provide cost and schedule information to Project Services

    Identify PO issues for Risk Management activities

    Liaise with Inspection to ensure compliance to specifications

    The Purchasing Post-award Process covers the technical andcommercial activities in the manufacture and delivery of materials andequipment

    Ensure all meetings and vendor contact are coordinated byProcurement.

    Materials Management executionpurchasing post-award process

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    64/77

    64

    Procurement Execution

    The main activities in the Purchasing Post-award Process are:

    Expediting (including Supplier documentation)

    Inspection coordination

    Traffic/Logistics

    Receiving on site, warehousing and preservation

    Change/Claim administration

    Invoice payment

    Materials Management executionpurchasing post-award process

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    65/77

    65

    Procurement Execution

    Effective procurement performance requires:

    Use of SmartPlant Materials

    Monitoring the vendors engineering and manufacturing processes

    Meeting documentation obligations

    Measuring and assuring conformance to the technical specification

    Administering delivery of the materials and equipment

    Managing any changes to the PO technical and commercial

    provisions

    Managing any claims by the vendor for additional payment or

    schedule time

    Materials Management executionpurchasing post-award process

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    66/77

    66

    Procurement Execution

    The Construction Manager involves the ProjectProcurement Manager in construction progress reviewmeeting

    Materials Management executionpurchasing post-award process

    As Project Manager you are responsible for ensuring that:

    For most items, weekly status meetings are sufficient

    For critical items, daily review meetings between the Constructionand Procurement Managers may be required

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    67/77

    67

    Procurement Execution

    The Materials Field Administration Process governs the day-to-day

    procurement activities on site

    The actual administration is the responsibility of your Project

    Procurement Manager

    Materials Field Administration may include site administration,

    purchasing and contracting

    Materials Management executionpurchasingmaterials field

    administration process

    You are responsible for ensuring that the requirements for

    materials field administration are included in the Project

    Procurement Plan

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    68/77

    68

    Procurement Execution

    The purpose of the Contracts Pre-award Process is the contracting of

    third-party services

    Project Contracts pre-award activities predominantly occur during the

    Execution phase

    For early contracts, some activities may occur in the Define phase

    The deliverables of the Contracts Pre-award Process are:

    Bidders lists

    Enquiry packages

    Approved recommendations for award Contract documents

    Cost and schedule information provided to Project Services and

    contracts issues input into Risk Management activities

    Contracts executioncontract pre-award process

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    69/77

    69

    Procurement Execution

    Contractor selection

    A thorough prequalification process will normally be executed for majorcontracts, e.g. fabrication contracts. This will involve multiple disciplines toprepare the questionnaire for the relevant work scope, typically including

    construction, engineering, quality, HSE as well as project controls andprocurement.

    Competitive, sealed bids are indicated for major contracts

    If single source is considered for service contracts, justification must beprovided. This may include proprietary technology (e.g. software) orcustomers preference.

    Once internal and other approvals have been obtained to place a contract ora PO theProcurement Manager is the only person with the authority toconfirm the commitment for the contract or PO with the supplier on behalf ofWorleyParsons and/or our customers

    Contracts executioncontract award process

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    70/77

    70

    Procurement Execution

    The Contracts Post-award Process covers the technical andcommercial activities

    The main activities are:

    Awarding contracts

    Administering and monitoring the contractors

    Managing any changes to the contract

    Managing any claims

    Processing any payments and back charges, reconcilingquantities and finalizing all contract obligations

    Providing cost and schedule information to Project Services

    Identifying any contracts issues for Risk Management activities

    Contracts executioncontracts post-award process

    Procurement Execution

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    71/77

    71

    Procurement Execution

    PO and contract variation must be processed in accordance with the

    Management of Project Change Process

    You and the Procurement Manager must sign-off any variances

    before they can take effect

    Purchase order and contracts variation

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    72/77

    72

    The scenario for the case study is on page 55 of your workbooks

    Discussion topics:

    What would you say are the key procurement issues on the project?

    What can be done to remedy the situation?

    Case studygroup discussion

    Procurement Close-out

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    73/77

    73

    Procurement Close-out

    The Procurement team completes the procurement close-out tasks

    You are responsible for ensuring that the Project Procurement

    Manager and the procurement team do this

    Responsibilities for procurement close-out

    Procurement Close-out

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    74/77

    74

    Procurement Close out

    Project Materials Management close-out activities generally occurlate in the Execution phase

    Close-out must follow the requirements for finalization of supply as

    set out in the Project Procurement Plan

    The main objectives of materials close-out are:

    Materials reconciliation

    Surplus management

    Final inspection (this is a Quality activity)

    Receipt Final Vendor Documentation

    Claims resolution

    Closing out of all PDs

    Materials Management close-out

    Procurement Close-out

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    75/77

    75

    Procurement Close out

    Close-out must follow the requirements for finalization of supply asset out in the Project Procurement Plan

    The main objectives of contracts close-out are:

    Provision of acceptance certificates

    Confirmation of warranties

    Handover of documentation

    Final inspections (Quality activity)

    Claims resolution and payment reconciliation

    Demobilization of the site by WorleyParsons and the contractor does

    not necessarily indicate final close-out of the project

    Contracts close-out

    Summary and Feedback

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    76/77

    76

    Summary and Feedback

    Review learning objectives and outcomes

    Summary

    Overview of Procurement

    Responsibilities for Procurement

    Commencing the Procurement Process \Procurement Planning

    SmartPlant Materials

    Procurement Reports

    Procurement Initiation

    Procurement Execution

    Procurement Close-out

    Questions

    Evaluation

  • 5/22/2018 Module 9 - Managing Project Procurement - PowerPoint Presentation Rev 2

    77/77

    Module 9 Managing Project Procurement

    Thank you for your participation