CHIEF ENGINEER WRD, IRRIGATION CENTRAL ZONE
MUNIRABAD
KARNATAKA NEERAVARI NIGAM LIMITED
(A Government of Karnataka undertaking)
DETAILED PROJECT REPORT
VOLUME – I
REPORT
ESTIMATED COST – Rs. 432.55 Crores
MODERNISATION OF VIJAYANAGARA
CHANNELS IN TUNGABHADRA
PROJECT
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Contents Section 1 – Checklist
Section 2 – Salient features
Section 3 – Report
Chapter 1. Introduction ...................................................................................................................1
1.1. Vijayanagara channels ............................................................................................................1
1.2. Weir/Anicuts ..........................................................................................................................3
1.3. Location .................................................................................................................................4
1.4. Details of Canal System ........................................................................................................4
1.5. Accessibility ..........................................................................................................................6
1.6. Toposheet Mosaic of the project .........................................................................................6
1.7. Present condition ....................................................................................................................7
1.8. Deficiencies in the existing system ..........................................................................................7
1.9. Need for Modernization ...........................................................................................................8
Chapter 2. Hydrology .................................................................................................................... 10
2.1. Water availability ................................................................................................................. 11
Chapter 3. Reservoir ...................................................................................................................... 12
Chapter 4. Weir/Anicut .................................................................................................................. 12
4.1. Vijayanagara Channels ......................................................................................................... 12
4.2. Details of Channel Systems .................................................................................................. 13
Chapter 5. Land Potential ............................................................................................................. 16
5.1. Culturable Command area .................................................................................................... 16
Chapter 6. Cropping pattern and Crop Water Requirement ....................................................... 17
6.1. Details of Pre –Project / Original cropping pattern ................................................................ 17
6.2. Details of Post –Modernisation/ proposed cropping pattern .......................................... 18
6.2.1. Field application efficiency ............................................................................................ 19
6.3. Assessment of Crop Water Requirement .............................................................................. 20
6.4. Crop Water Requirement ...................................................................................................... 21
6.5. Results .................................................................................................................................. 21
6.6. Conclusions ........................................................................................................................... 22
6.6.1. Achieving required savings ........................................................................................... 22
Chapter 7. Pissiculture .................................................................................................................. 23
Chapter 8. Horticulture .................................................................................................................. 23
Chapter 9. Domestic and Industrial water supply etc. ................................................................ 23
Chapter 10. Demand Table .............................................................................................................. 24
Chapter 11. Impact of Modernisation ............................................................................................. 25
11.1. Upstream and Downstream Projects ..................................................................................... 25
Chapter 12. Interstate aspects ........................................................................................................ 25
Chapter 13. Channel system ........................................................................................................... 26
13.1. Preamble ............................................................................................................................... 26
13.2. Survey of channel system ..................................................................................................... 26
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
13.3. Site Inventory and survey of channels and structures ........................................................... 27
13.4. Review of capacity of existing channel and distribution system. ........................................... 32
13.4.1. Original design .............................................................................................................. 32
13.4.2. Present capacity ............................................................................................................ 32
13.4.3. Design of revised section (lined) ................................................................................... 32
13.5. Identification of the reaches needing improvements ............................................................. 33
13.5.1. Lining............................................................................................................................. 33
13.5.2. Strengthening and stabilization of banks ....................................................................... 34
13.6. Preparation of capacity statement ......................................................................................... 34
13.7. Need for remodeling / distribution system ............................................................................. 34
Chapter 14. Power ........................................................................................................................... 35
14.1. Power status ......................................................................................................................... 35
14.2. Modernization / upgrading proposal ...................................................................................... 35
Chapter 15. Navigation .................................................................................................................... 35
Chapter 16. Groundwater ................................................................................................................ 36
16.1. Depth of Groundwater level ................................................................................................... 36
16.2. Assessment of Groundwater potential in the command area ................................................ 37
16.3. Quality of Groundwater ......................................................................................................... 38
16.4. Assessment of possible impact on Groundwater .................................................................. 38
16.5. Conjunctive use of surface and groundwater ........................................................................ 38
Chapter 17. Drainage and land reclamation .................................................................................. 39
17.1. Review of drainage ............................................................................................................... 39
17.2. Type of reclamation ............................................................................................................... 39
17.2.1. Field drains .................................................................................................................... 39
Chapter 18. Land acquisition, Rehabilitation and Resettlement ................................................. 40
18.1. Land acquisition, Rehabilitation / Resettlement ..................................................................... 40
Chapter 19. Water management and maintenance ....................................................................... 41
Chapter 20. On farm development works ...................................................................................... 42
20.1. Command Area Development Authority ................................................................................ 42
20.1. Organization setup of On Farm Development ....................................................................... 42
20.1.1. Land leveling ................................................................................................................. 42
20.1.2. Field Irrigation Channels (FICs) .................................................................................... 42
20.1.3. Construction of field drains ............................................................................................ 43
20.1.4. Warabandi ..................................................................................................................... 43
20.1.5. Ayacut roads ................................................................................................................. 43
Chapter 21. Construction programme ........................................................................................... 44
Chapter 22. Construction organization .......................................................................................... 45
22.1. Organization setup for modernization.................................................................................... 45
Chapter 23. Environment, Ecology and Forest aspects ............................................................... 47
23.1. World Heritage Zone ............................................................................................................. 47
Chapter 24. Economic Evaluation .................................................................................................. 48
24.1. For Channels ......................................................................................................................... 48
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
24.2. For Structures ....................................................................................................................... 48
Chapter 25. Administrative and Legislative provisions................................................................ 61
25.1. Administrative set up ............................................................................................................. 61
25.2. Legal status & Policy framework ........................................................................................... 61
Chapter 26. Facilities for training the operational and maintenance personnel ........................ 62
26.1. Existing.................................................................................................................................. 62
26.2. Proposals for improvement and extension ............................................................................ 62
26.2.1. Institution framework ..................................................................................................... 62
Chapter 27. Operation and Maintenance ....................................................................................... 63
27.1. Training and Visit system ...................................................................................................... 63
Chapter 28. B C Ratio ...................................................................................................................... 64
28.1. Benefit Cost ratio ................................................................................................................... 64
28.1.1. Estimated value of produce before channel modernization ........................................... 64
28.1.2. Estimated value of produce after channel modernization .............................................. 64
Conclusion 68
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
List of Annexures
Annexure 2.1 Statement showing the year wise details of inflows, outflows (utilisation) under different canal system of Tungabhadra project. (Karnataka portion) for the period (water year) from 1990-91 to 2009-10
Annexure 2.2 Details of River releases for Vijayanagar channels and Rajolibanda Diversion Scheme
Annexure 6.1 Monthly rainfall data from year 1980 to 2009 (mm)
Annexure 6.1/1 Monthly rainfall data of Station Munirabad
Annexure 6.1/2 Monthly rainfall data of Station Kamalapura
Annexure 6.1/3 Monthly rainfall data of Station Gangavathi
Annexure 6.1/4 Monthly rainfall data of Station Kampli
Annexure 6.1/5 Monthly rainfall data of Station Sirguppa
Annexure 6.2 Average annual rainfall and monthly normal rainfall of influencing rain gauge stations (according to Theissen polygon)
Annexure 6.3 Agro-climatological data of Bellary IMD station
Annexure 6.4 Detailed calculations of Crop water requirements (Channel wise/Crop wise)
Annexure 12.1 Allocation of water (KWDT I) - Revised Master Plan – 2003
Annexure 13.1 Particulars of Canal System
Annexure 24.1 Cost Estimate (General Abstract)
Annexure 24.2 Letter from State Government for clearance of Designs
Annexure 24.3 Place of Quarries considered for different materials under Vijaynagar channels
Annexure 28.1 Benefit Cost Ratio
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
List of Figures
Fig 1.1– Top sheet mosaic of the project area ................................................................................. 7
Fig 13.1 – Survey work in progress .................................................................................................26
Fig 13.2 – Figure showing untidy channels .....................................................................................28
Fig 13.3 – Channel used as disposal point ......................................................................................28
Fig 13.4 – Channel reaches with size stone masonry lining ............................................................29
Fig 13.5 – Damage due to seepage and poor maintenance ............................................................29
Fig 13.6 – Crocodile in the reaches of Raya channel ......................................................................30
Fig 13.7 – Snake found in the initial reache of Belagodahala channel ............................................30
Fig 13.8 – Thick vegetation around the Channel .............................................................................30
Fig 13.9 – Damaged Service road ...................................................................................................31
Fig 13.10 – Poor crossing structure ................................................................................................31
Fig 13.11 – Channel flowing full ......................................................................................................31
Fig 13.12 – Service road .................................................................................................................31
Fig 13.13 –Banana plantation .........................................................................................................32
Fig 13.14 –Sugarcane plantation ....................................................................................................32
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
List of Tables
Table 1.1 – List of Channels .............................................................................................................. 2
Table 1.2 – Table showing Location details of Canal system ............................................................ 4
Table 1.3 – Table showing Hydraulic details of Canal system .......................................................... 5
Table 1.4 – Details of toposheet which cover the project area .......................................................... 6
Table 4.1 – Table showing Location details of Channel system ...................................................... 13
Table 4.2 – Table showing Hydraulic details of Channel system .................................................... 14
Table 6.1 –Existing (Pre modernization) Cropping Pattern ............................................................. 17
Table 6.2 – Proposed (Post modernization) cropping pattern ......................................................... 18
Table 6.3–Table showing the breakup of Irrigation efficiency .......................................................... 20
Table 6.4 –Demand Table ............................................................................................................... 21
Table 6.5 –Savings Achieved .......................................................................................................... 22
Table 16.1 – Table showing depth of Groundwater for Pre monsoon and Post monsoon ............... 36
Table 16.2 – Table showing Administrative wise assessment of Dynamic Groundwater resources 37
Table 16.3 – Table showing administrative assessment of unit wise categorization ....................... 37
Table 21.1 – Implementation program of Modernization of Vijayanagara channels ........................ 44
Table 22.1 – Divisions in- charge of the channels ........................................................................... 46
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Abbreviation
B.C.R Benefit Cost Ratio
CA Catchment Area
CADA Command Area Development Authority
CBL Channel Bed Level
CC Cement Concrete
CD Cross Drainage
CNS Cohesive Non Swelling
CTC Cart Track Crossing
CWC Central Water Commission
CWR Crop Water Requirement
DPR Detailed Project Report
DT Double tertiary
DTP Draft Tender Paper
EOT Electric Overhead Travelling
ETC Crop Evapo-transpiration
FIC Field Irrigation Channel
FTL Full Tank Level
GEMS Groundwater Estimation and Management system
GIR Gross Irrigation Requirement
GTS Great Trigonometric Survey
Ha Hectares
IP Inspection Path
KNNL Karnataka Neeravari Nigam Limited
MCM Million cubic meter
NIR Net Irrigation Requirement
SOR Schedule of Rates
SR Service Road
TMC Thousand Million cubic feet
WUA Waters Users Association
USDA United States Department of Agriculture
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Checklist
No. Particulars Remarks
1 Was the original project given investment clearance by Planning
Commission?
Does not arise.
2 Has the performance evaluation of the existing project been carried out? Yes
3 Have the salient features of the project as envisaged at the time of
execution of project and as present, been indicated?
Salient features as of now.
4 Have the irrigation potential of the existing project as originally envisaged,
potential created and utilized and reasons for variations been indicated?
Yes
5 Has the Culturable command area been actually assessed and compared
with that at the time of planning of the project and shortfalls/excesses, if
any, discussed?
Yes
6 Has the Hydraulic survey of channel/distribution system been carried out? Yes
7 Have the deficiencies in the existing irrigation system been identified? Yes
8 Has the need for modernization been justified? Yes
9 Have the hydrological studies been reviewed ,compared with those made
at the time of preparation of the original project if available and reasons
for variations recorded in respect of:
(i) Rainfall
(ii) Runoff
(iii) Flood
(iv) Sediment
(v) Ground water
(vi) Evaporation.
These are run of the river schemes
downstream of Tungabhadra dam
(TB dam)
10 (a) Have changes in the upstream withdrawals/diversions for
industrial use, power generation, drinking requirement and other
developments in the upper catchments to the extent which can be
collected with reasonable efforts be described?
(b) Have the changes in the power generation / consumption in
power for the lift irrigation schemes being described?
NA
NA
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
No. Particulars Remarks
11 Have the semi-detailed soil surveys been carried out for the entire
command (if not entire command then extent cornered) and soil and land
irritability classification brought out in the report? (Project to be
acceptable, semi detailed soil survey in at least 50% of command should
have been carried.)
NA
12 Is the crop water requirement determined by the modified Penman
method?
Yes
13 Have water requirements for other uses been worked out? NA
14 Has justification for the proposed cropping pattern been furnished? Yes
15 Have the cropping pattern & proper cropping calendar been devised with
a view to maximize the production and channel closure for maintenance
etc. ensured? Have these been concurred by the agriculture department?
Yes
16 Are the areas and percentage of CCA that will be irrigated during kharif,
rabi, two seasonal, hot weather and perennial been indicated and
compared with cropping pattern as existing prior to taking up the project,
originally envisaged and actually developed after completion of the
project?
Yes
17 Is the justification furnished for continuing with/or taking up perennial and
hot weather crops from the reservoir?
Existing crops have
been retained
18 Have the most suitable depths and frequencies of irrigation to be adopted,
based on the characteristics of the soil and crops been worked out?
Yes
19 Have the values of conveyance efficiency, field application efficiency and
overall water use efficiency been indicated with basis therefore?
Yes
20 Has the pattern of releases (10 daily/monthly) from the diversion/storage
headworks been worked out & compared with those envisaged originally?
Yes
21 Has the channel been redesigned to cater for peak requirement + 10
percent (20% for small reservoirs) for rush irrigation. If, not have the
alternative proposals for carrying the required discharge been discussed?
Yes
22 Whether supplementation from ground water has been considered? NA
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
No. Particulars Remarks
23 Are the supplies available sufficient to meet the requirements for ensuring
75 per cent dependability? If not, have the possibilities of augmentation of
the supplies been discussed either by increasing the storage or by
supplementing by ground water etc.? Have the revised reservoir
operation tables been furnished?
Yes
24 Has the study of ground water potential of the command area, the present
level of the ground water use and the scope of the future ground water
utilization been carried out and included in the project report?
Yes
25 Have the economics of the ground water development been studied? NA
26 Has the possible impact on ground water recharge on account of lining of
the system been kept in view in the scheme of ground water utilization?
NA
27 Has the possibility of ground water and irrigation area not commanded by
the channel system been considered?
NA
28 Has the quality of surface water and also ground water, drainage water, if
intended for irrigation use, been tested?
Yes
29 Have the requirements of the drainage in the command area been studied
and a suitable intended for irrigation use been tested?
NA
30 Have the arrangements for the following been considered and provided
for?
Execution of OFD works
(a) Training programmers for field staff and farmers – existing
position and proposals for strengthening.
(b) Participatory Irrigation Management (PIM), Water Users
Association (WUA) and turnover of the system to WUAs.
(c) Provision of extension services.
(d) Providing important inputs like seeds, fertilizers etc.
These activities are implemented by CADA
31 Have adequacy of road communication facilities and if not, the necessity
of improvements been discussed and provided for?
NA
32 Have matters about the improvement in reliability/dependability of the
annual irrigation of the existing proposed command area been discussed
in the light of modernization?
Yes
33 Have the net benefits due to the project been estimated and concurred by Yes
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
No. Particulars Remarks
the agricultural Dept.?
34 Has the concurrence of the State Finance Department been obtained for
taking up the project at the estimated cost?
Yes
35 Whether the scheme has already been started? If so, is the stage
construction indicated?
-
36 Is the scheme included in the plan? If not, what is the present position
regarding it’s inclusion in the plan?
-
37 Have the year wise requirement of funds been indicated? -
38 Is the scheme covered under State Sector or Central Sector? State Sector
39 Is the scheme covered or proposed to be covered under any foreign
assistance/aid agreement?
No
40 Are the detailed cost estimates included in the report? Yes
41 Has the benefit-cost ratio been worked out? Whether proportionate cost
of completed works included in the calculations?
Yes
42 Whether Internal Rate of Return (IRR) worked out? NA
43 Are the financial results attached? No
44 Are there any special reasons to undertake the project if it is unproductive
and whether these have been recorded in the Report?
Yes. To use water more efficiently thereby save water, modernization is proposed.
45 Are the rates of betterment levy proposed, the period of recovery and the
estimated total recovery indicated?
-
46 Are there any charges levied for irrigation facilities as distinct from water
charges?
-
47 Are the scales of water rate indicated? -
48 Have the rates of betterment levy, water charges, etc. been compared
with those obtained in other regions of the state?
NA
49 Has the concurrence of the State Revenue Department been obtained for
these rates?
Yes
50 Have the O&M aspects (both financial as well as management) been
discussed? How are the O&M cost proposed to be met?
Yes.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
No. Particulars Remarks
51 Have the programmer of construction and the expenditure involved been
furnished?
Yes
52 Has the requirement of staff been estimated and furnished with
justification?
Yes
53 Has the adequacy of the existing irrigation laws and revisions, if any,
considered necessary been discussed?
Yes
54 Have the impact of the scheme on the overall development of water
resources in the basin/state been discussed?
Yes
55 Whether views of water users about proposed works in modernization
projects been obtained and described in the Report?
Yes
56 Have environmental / ecological aspects been discussed in the Report? NA
57 Does the project involve acquisition of forest land? Has the MOE&F been
approached for clearance under Forest Conservation Act 1980?
No. NA
58 Dose the project involve any re-settlement? Whether rehabilitation of
PAFs provided for?
No. NA
59 Does the project involve rehabilitation of SC/ST population? Has the
rehabilitation package for them been cleared by Ministry of Social Justice
& Empowerment?
No
60 Have the socio economic studies (bench mark surveys) been carried out? No
61 Have the interstate aspects been examined & discussed? Yes
62 Have the list of ongoing programs of Agriculture Department in command
Area been given?
Yes
Chief Engineer KNNL, Irrigation Central Zone
Munirabad
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Salient features
1.0 Name of the Project Modernisation of Vijayanagara Channels in Tungabhadra Project
2.0 General Data
2.1 District(s) Bellary, Koppal, Raichur
2.2 Tehsil(s)/Taluk(s) Hospet, Gangavathi, Sirguppa and Raichur
2.3 River/Tributary Tungabhadra River
2.4 Location of Dam/Diversion Structures
2.5 Name of River/Basin Tungabhadra River/ Krishna
2.6 Longitude and Latitude
a) Longitude 75° 40' to 77° 35' E
b) Latitude 14° 30' to 16° 34' N
3.0 Socio-economic aspects Original Revised
3.1 District(s) Benefited Bellary, Koppal, Raichur
Bellary, Koppal, Raichur
3.2 Income
3.3 Land holdings
3.4 Population benefited
a) Total
b) Schedule cast
c) Schedule Tribe
d) Other Backward casts
4.0 Hydrological Data
4.1 Catchment area at dam site (Ha) 28,179.20 Sq. Km at Tungabhadra dam site
4.2 Rainfall (mm) Original Revised
a) Maximum annual rainfall 1540 1540
b) Minimum annual rainfall 244 244
c) Mean annual rainfall ( As per Thessien
average)
629.20 629.20
4.3 Annual runoff (M cum) Original Proposed
a) Average
-NA- b) Maximum
c) Minimum
d) 75% dependability
4.4 Design Flood -NA-
5.0 Water Utilization (TMC) Present Proposed
a) Reservation for upstream use
b) Reservation for downstream use
c) Utilisation through the project
i) Irrigation 12.05 5.80
ii) Power Generation -NA-
iii) Drinking water -NA-
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
iv) Industrial Use -NA-
v) Others (Evaporation) -NA-
d) Water saved through Modernization 6.25 TMC
6.0 Groundwater (TMC)
a) Potential 12.88 TMC
b) Present use No groundwater is utilized for Irrigation at
present
c) Proposed use after Modernisation -NA-
d) Balance for future utilization after
Modernisation
-NA-
7.0 Reservoir data (Tungabhadra Dam)
a) Storage (TMC) Existing Proposed
i) Gross storage 132.00 132.00
ii) Dead storage 2.300 2.300
iii) Live storage 116.84 116.84
iv) Annual carry over
b) Elevation (El-m) Original Proposed
i) Maximum water level (MWL) 497.74 497.74
ii) Full reservoir level (FRL) 497.74 497.74
c) Water spread area (sq.km) at
Full reservoir level 378.14 378.14
d) Water Quality Reservoir/Canal/River (Downstream)
i) Physical Good
ii) Chemical Good
iii) Bacteriological Good
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
8.0 Canal system (Irrigation) Information to be
furnished for each Main/Branch canal separately
Existing Proposed
a) Length of canal(Km)
Refer Annexure 13.1
b) Full supply level at canal head (m)
c) Full supply discharge at canal head
(m3/sec)
d) Length of complete distribution system up
to minors
e) Number of villages surveyed
f) Area (Ha)
i) Gross command area (GCA)
ii) Culturable command area (CCA
iii) Annual Irrigation (AI)
iv) Intensity of Irrigation (% of CCA)
g) Automation and SCADA Existing Proposed
i) Flow measurement and data
acquisition at all control points
No No
ii) Automatic control of gates No No
iii) Control philosophy NA NA
iv) Communication NA NA
9.0 Power -NA-
10 Cropping pattern (crop wise)-Season wise
Name of crop
season wise
Pre-Modernisation (Ha)
% of CCA
Post Modernisation (Ha)
% of CCA
Intensity of Irrigation 100% 100%
Khariff 1. Paddy 4056 (30.9 %) 2304 (14.18%) 2. Jowar 735 (5.6 %) 6326 (38.95%)
Rabi 1. Paddy 1825 (13.9 %) 1655 (10.19%) 2. Groundnut 1903 (14.50 %) 3755 (23.12%)
Perennial 1. Sugarcane 3176 (24.20 %) 1229 (7.57%) 2. Garden 1431 (10.90 %) 974 (6.0%) Total 13,125 16,243
11. Benefits (Additional, annual) Amount (Rs.)
a) Food grains 3812.67
b) Commercial crops 3216.59
c) Others -
12.0 Revenue (Rs) Existing Proposed
12.1 Revenue from water rates
a) Irrigation - -
b) Domestic water supply - -
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
c) Industrial water supply - -
d) Power - -
e) Others - -
12.2 Revenue from Irrigation cess other than water
rates
12.3 Recovery of Betterment levy -
12.4 Other sources of revenue, if any, -
13.0 Cost
13.1 Estimated cost of Modernization works
a) Irrigation 40322 Lakhs
b) Domestic water supply -
c) Industrial water supply -
d) Power -
e) Others -
13.2 Cost of completed works (Rs. Lakhs) -
13.3 Annual cost 4703.78 Lakhs
14.0 Benefit Cost Ratio 1.65
Chief Engineer KNNL, Irrigation Central Zone
Munirabad
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 1
Chapter 1. Introduction
1.1. Vijayanagara channels
The river Tungabhadra is a major tributary to Krishna River and is so called after the confluence of
two rivers Tunga and Bhadra, which rise in the Western Ghats at an altitude of about 1198 M above
mean sea level (MSL). The Tungabhadra river flows for about 531 Kms in the north-east direction in
Karnataka and Andhra Pradesh before joining Krishna river near Kurnool at an altitude of 294.10 M.
The vast drainage area of Tungabhadra river comprises of the following main tributaries (a)
Kumadvathi river (b) Dharma river (c) Varada river (d) Dodda halla (e) Murdha halla and (f) Haridhra
river.
The Vijayanagara Channel system is spread over 3 districts namely Bellary, Raichur and Koppal. The
Geographical area lies between latitude 14° 30' to 16° 34' N and Longitude 75° 40' to 77° 35' E.
Originally, Vijayanagara Channels are the run-of-the river irrigation channels and are historically
important serving the irrigation needs of the local population. They have been built during
Vijayanagara dynasty about 400 years back. In all, there are 19 Channels taking off from
Tungabhadra river of which 18 are in Karnataka and one is in Andhra Pradesh.
BELLARY
KOPPAL
RAICHUR
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 2
During Vijayanagara dynasty, 18 Channel networks were constructed in Tungabhadra basin in the
reach from Tungabhadra reservoir to Siraguppa. The list of the Channels is indicated in Table 1.1
Table 1.1 – List of Channels
A. On Right Bank of TB River B. On Left Bank of TB River
1. Raya 11. Koregal
2. Basavana 12. Hulugi
3. Bella 13. Shivapura
4. Kalaghatta 14. Anegundi
5. Turtha 15. Gangavathi Upper
6. Ramasagar 16. Gangavathi Lower
7. Kampli 17. Bichal
8. Belagodhala 18. Bennur
9. Deshnur
10. Siraguppa
Of these 18 Channels, Bennur channel is in ruins and Koregal channel command is supplied water
from Tungabhadra Left Bank Channel. In view of this, presently, Vijayanagara Channel system
comprises of 16 Channels. This modernization report deals with the 16 Channels.
The Raya and Basavanna canals were on the right bank of river Tungabhadra and were being fed
through the respective weirs located on the upstream of the present Tungabhadra dam. The
Basavanna channel was crossing the present dam alignment at Km 18 below its weir whereas Raya
Channel was crossing at about 3.5 Kms below the weir. In order to protect the irrigation in these two
channels, an irrigation sluice has been provided in the right side of Tungabhadra dam.
Two channels; Raya and Basavanna take off from TB dam. All other channels except Kalghatta and
Belgodhal take off from anicuts constructed across Tungabhadra river at various locations on
downstream of TB dam and are being partially fed by Raya and Basavanna channels.
The Raya Channel runs for about 27.74 Km and joins at 4th Km of Turtha channel. In addition, it has
a separate sluice which was constructed at 2.5 Km to fulfill the shortage of water to Bella channel.
Bella Channel runs for about 5.55 Km and joins at Ch 0.2 Km of Kalghatta channel. The Kalghatta
Channel runs for about 7.02 Km and joins Turtha Channel at Ch 0.7 Km. Turtha channel runs for
about 18.69 Km and joins Ramsagar channel at Ch 1.40 Km. Ramsagar channel runs for about 15.50
Km. It has two drainage channels joining Kampli channel. The Kampli channel runs for about 23.55
Km. It has Belgodhal channel taking off at Ch 3.20 Km and runs for a length of11.22 Kms.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 3
The discharges of each channel are considered while arriving at the channel section for the channels
Raya, Bella, Kalaghatta, Turtha, Ramsagar, Kampli and Belgodhal. The 4 Channels; Bella, Turtha,
Ramsagar and Kampli get a share from river assistance.
The Channels; Sirguppa and Deshnur on the right side and other 6 channels on the left side of
Tungabhadra River get water exclusively from river assistance, released from Tungabhadra dam.
The Index Map showing the Command area of the Scheme (16 channels) is appended in Volume V.
1.2. Weir/Anicuts
There are 12 no’s of Anicuts and the details are enclosed separately. Vijayanagara channels are
being fed from the anicuts constructed in the earlier days for providing irrigation. These anicuts were
constructed during the regime of Vijayanagar empires. They have been constructed using huge
boulders and set in Zig-Zag manner without any kind of mortar for bond. Due to this, the anicuts are
subject to leakage of water exacerbated by the displacement of boulders during high floods. Over a
period of time, the system has deteriorated and needs urgent attention and improvements. The
farmers of Vijayanagara channels are demanding improvements to anicuts.
The improvements proposed to anicuts are:
1. Providing 200 mm thick skin wall encasement to the anicut and grouting.
2. Providing anchor rods at every 1m interval on upstream and downstream of anicut for a width
of 5 m all along the length.
3. Providing concrete toe walls on both ends
4. Formation of approach roads to the anicuts wherever required from the nearest road.
The details of the channels system are tabulated below:
The Irrigation schemes comprising 17 Nos of anicuts across Tungabhadra River together known as
Vijayanagara Channels were implemented during Vijayanagara dynasty to provide irrigation facilities.
Out of these, Vallabhapur and Hoskote anicuts were submerged in the backwaters of Tungabhadra
reservoir. In order to cater to the command of Vallabhapur and Hoskote anicuts, one vent of size 1.8
m X 3.6 m is constructed in the reservoir as a permanent sluice and these commands are fed through
Raya and Basavanna channels. A total of 12.05 TMC has been allocated by the tribunal to
Vijayanagara channels with a break up of 5.71 TMC as protected utilisation and 6.35 TMC as worth
consideration.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 4
As per clause IX - E of KWDT award, 7 TMC of water from Tungabhadra reservoir is earmarked for
Raya and Basavanna channels. An allocation of 2 TMC was made by way of assistance through
other regulated discharges other than Raya and Basavanna channels from Tungabhadra reservoir.
In the 1993 master plan, an allocation of 12.05 TMC is made for the Vijayanagara channels without
channel wise breakup and river assistance.
The revised Master plan of 2003 has an allocation of 5.80 TMC for all the 16 Vijayanagara channels.
The Government of Karnataka is proposing the modernization of these Channels to improve the
channel efficiency thereby saving 6.25 TMC of water.
1.3. Location
Vijayanagara is located in Bellary District, northern Karnataka. The geographical location is at
Latitude 15°19′N and Longitude 76°28′E. It is also known as ruined capital city. The nearest town
and railway station is Hospet and the nearest canal is 13 km away by road. Hospet also lies within
the original extents of the old city.
1.4. Details of Canal System
The details of canal system considered for modernization are indicated in Table 1.2
Table 1.2 – Table showing Location details of Canal system
No Name of the
channel Name of weir &
length in Km Name of stream
Distance d/s of TB Dam in
Km Remarks
Bellary District (on right side of river)
1. Basavanna Vallabhapur Submerged in Tungabhadra
reservoir
Channel takes off directly from
Tungabhadra dam on right side
2. Raya Hosakote --do-- --do-
3. Bella Hosur-0.602 Tungabhadra 2.4 Channel utilizes
seepage from
higher level
channels
4. Kalaghatta Drainage channel Halla 8
5. Turtha Turtha 3.048 Tungabhadra 16
6. Ramsagar Ramsagar 2.042 --do-- 28.8
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 5
No Name of the
channel Name of weir &
length in Km Name of stream
Distance d/s of TB Dam in
Km Remarks
7. Kampli Kampli anicut
0.94
--do- 30.4
8. Belagodahal Drainage
channel
Halla 35.2 Channel utilizes
seepage from
higher level
channels
9. Siruguppa Siruguppa 1.95 Tungabhadra 80 Consists of 7 bits.
10. Deshnur Deshnur 0.96 ~do-- 80
Koppal District (on left side of river) 11. Koregal
Koregal Submerged in Tungabhadra
reservoir
Channel takes off directly from
Tungabhadra Left Bank Channel
12. Hulugi Hulugi - 0.518 Tungabhadra 2.4
13. Shivapura Shivapura - 0.17 do 8
14. Anegundi Sanapur - 0.518 do 16
15. Upper Gangavathi Upper
Gangavathi0.78 do 27.2
16. Lower Gangavathi Lower Gangavathi 0.45
do 30.4
Raichur district 17. Bichal Bichal - 1.192 do 137.6
Table 1.3 – Table showing Hydraulic details of Canal system
(20 years average cropped area is considered)
No. Name of the Channel Length of
Channel in Kms
Cropped area in Ha
Offtake
On right bank of TB River
1 Raya Channel 27.74 2855 Tungabhadra Dam
2 Basavanna Channel 16.50 1447 Tungabhadra Dam
3 Bella Channel 5.50 741 Hosur Anicut
4 Kalaghatta Channel 7.020 349 Drainage channel
5 Turtha Channel 18.69 1171 Turtha anicut
6 Ramasagar Channel 15.50 1024 Ramasagar Anicut
7 Kampli Channel 23.550 894 Kampli Anicut
8 Belagodahala 11.220 328 Drainage channel
9 Deshnur Channel 9.03 815 Deshnur Anicut
10 Siruguppa Channel 10.85 1344 Sirguppa Anicut
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 6
No. Name of the Channel Length of
Channel in Kms
Cropped area in Ha
Offtake
On left bank of TB River
11 Hulugi Channel 10.69 419 Hulugi anicut
12 Shivapura Channel 6.54 717 Shivapura anicut
13 Anegundi Channel 19.44 1359 Sanapur anicut
14 Gangavathi upper Channel
9.00 1363 Upper Gangavathi anicut
15 Gangavathi lower Channel
9.54 1141 Lower Gangavathi anicut
16 Bichal Channel 14.50 276 Bichal Anicut
Total 16241
The Schematic diagram of Vijayanagar channels is appended as KNNL-VNC-SD-002 vide
Volume V - Drawings
1.5. Accessibility
The project channels located at downstream of TB dam are best approached from Hospet,
Munirabad and Kamalapur on the upper reach and from Gangavathi on the lower reach.
1.6. Toposheet Mosaic of the project
The details of toposheets showing the channel network and their command area are given as below
in Table 1.4.
Table 1.4 – Details of toposheet which cover the project area
No Topo Sheet No. Scale
1. 57 A/7 1:50,000
2 57 A/8 1:50,000
3. 57 A/10 1:50,000
4 57 A/11 1:50,000
5 57 A/12 1:50,000
6 57 A/13 1:50,000
7 57 A/14 1:50,000
8 57 A/15 1:50,000
9 57 E/2 1:50,000
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 7
The mosaic of toposheets relevant to the project area is indicated in Fig 1.1
Fig 1.1– Top sheet mosaic of the project area
1.7. Present condition
Presently, the Vijayanagara channel systems comprising of the above 16 Channels are not in good
condition. The system has been in operation over the last 400 years. The reconnaissance survey has
revealed that the channels are lined with size stone masonry partly and have since lost their shape over the
years. The bed of the channels has scoured in some reaches and is silted up heavily in some reaches.
Heavy weed growth (water hyacinth) is noticed in and around the channels. Some of the structures are in
dilapidated condition which requires to be rehabilitated to make them functional.
1.8. Deficiencies in the existing system
The Vijayanagara channels were constructed during Vijayanagar dynasty i.e. about 400 years back. The
duty- delta considered for calculation of crop water requirement is not available. The duty-delta method of
calculating crop water requirements started in the 18th century. Thus, the farmers were used to the liberal
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 8
use of water for hundreds of years. With plenty of water, the crops grown were mostly rice, sugarcane etc.
Presently main channels are in bad condition and the pipe outlets are not having flow control. The
Tungabhadra project commissioned in the 50s considers the duty- delta for calculation of crop water
requirements and the channel design. However, the existing atchkat under Vijayanagar channels were
considered as part of the command under the Tungabhadra project.
Other problems encountered in the Vijayanagara channels in terms of operation and maintenance are;
a) Existing Channels have lost their section, thereby having difficulty in ensuring adequacy of flow.
b) Absence of measuring devices.
c) Inlets and outlets requiring redesign.
d) Unlined channels causing undesirable seepage, weed growth (water hyacinth)
e) Leakages in the main channels and cross drainage structures resulting in wastage of water.
1.9. Need for Modernization
The report Vol III of expert committee for preparation of master plan for river basin of Karnataka (constituted
vide G.O.No.PWD 70 NPC 85 dt.29/7/85) vide page no. 106 Para 2 mentions;
“ If this Channel system is lined and water measuring devices are provided and Warabandi system is
introduced it would be possible to manage about half the present discharge, thereby affecting the substantial
savings of about 7 TMC of scarce water resources which could be utilized for providing protective irrigation
to drought prone area in the State.”
The committee after deliberations, recommended for modernization of entire channel network of Vijayanagar
Channel system, as early as possible.
Hence, modernization of Vijayanagara Channels is proposed to save water as it was noticed that excess
water is being utilized in these channels. The Master Plan of 2003 revised the plan and made a suggestion
to modernize the existing Channel system by improvements in infrastructure to save water to an extent of
6.25 TMC which could be allocated to the Upper Bhadra project. In order to establish savings in water,
following measures are contemplated.
As the Channel systems are designed as unlined channels which are not efficient, it is proposed to redesign
the channels as lined channels to improve conveyance efficiency. The designed discharge is worked out
considering average cropped area of the last 20 years. This will facilitate reducing seepage losses thereby
improving the system efficiency and convey required discharge in the distributaries, minors and laterals
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 9
which will ensure water to the tail end of the channels thereby achieving reliability and equity in the
command area.
i. It is proposed to reconstruct the structures which are in bad condition. In addition, new structures are
proposed as per requirement of the farmers.
ii. Provision is made to install measuring devices in main channels, branch channels and minors for
improving operation.
Further, with the proposed improvements in channel infrastructure and operation, it is expected that there will
not be violation of cropping pattern by the farmers.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 10
Chapter 2. Hydrology
Extract from the further report of the Krishna Water Disputes Tribunal (KWDT)-I, the concerned paras
related to allocation of water for Raya and Basavanna Channels and Vijayanagar channels are reproduced
below
-“Raya channel and Basavanna Channel both of which take water directly from the Tungabhadra Dam on
the right side. 12.06 TMC of water (out of which 5.71 TMC is protected and 6.35 TMC is held as worth
consideration by the Tribunal) has been allocated in respect of all the Vijayanagar Channels of the state of
Karnataka including Raya and Basavanna Channels.”
“Further as per the final orders of Tribunal (KWDT-1), under the Clause IX (E), 7 TMC of water from
Tungabhadra reservoir is earmarked for Raya and Basavanna channels and an allocation of 2 TMC was
made by way of assistance through other regulated releases / discharges for Vijayanagar Channels other
than Raya and Basavanna channels in a water Year.”
As regard the provision made in KWDT-II is concerned, the order of the tribunal (KWDT-II) contained in
volume–IV of the Report (Page 800 to 811) did not mention anything on the above decision of KWDT-I.
As for as the suggestion to carry out water available studies at the off take points of these channels, it is to
report as under
The Tungabhadra Board, maintains the water account in details by bringing out Annual Report furnishing
there with the Performance of Tungabhadra Reservoir for each water year in a form of statement showing
the 10 daily inflows to Reservoir and corresponding outflows (drawals) by Karnataka state and Andhra
Pradesh and publishing it as working table for operation of Tungabhadra reservoir for the each water year.
The performance of Tungabhadra reservoir for each water year (from June to May) contains the 10 daily
inflow to the reservoir and drawals by Karnataka state and Andhra Pradesh for the different canal systems
of Tungabhadra Project.
From the above, extract of Abstract from performance of Tungabhadra reservoir is enclosed as “Statement
showing the year wise details of inflows, outflows (Utilisation) under different canal system of Tungabhadra
project (Karnataka portion) for the period (water year) from 1990-91 to 2009-2010 separately vide
Annexure 2.1
From the above Annexure 2.1, the RR (River Releases) under column 7 has been further bifurcated for
VNC (Vijayanagar Channels) and RDS (Rajolibanda Diversion Scheme) in the Annexure 2.2 enclosed
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 11
here with. Thus the actual drawals (Utilisation) from Tungabhadra reservoir for Raya, Basavanna canals
and Vijayanagar Channels have been worked out and indicated under column 7 of Annexure 2.2. It may
be seen from the column 7 that an average of 6.80 TMC being utilized in a water year for Vijayanagar
Channels system (including Raya, Basavanna canal).
From the above para’s it may be concluded that the water available for these Vijayanagar channels at the
off take points (Releases from Tungabhadra Dam) is much more than the proposed/estimated crop water
requirement of 5.80 TMC on Modernisation of Vijayanagar channels in Tungabhadra project .
2.1. Water availability
The Vijayanagar channels system consists of 16 channels with the physical area (average) of 11154 ha.
The Krishna Water Disputes Tribunal (KWDT) - 1, in its award has allocated 12.05 TMC annually as
committed utilization.
Out of the above 16 channels, two channels namely Raya and Basavanna channels gets the water through
gated sluices provided in the right side of the T B Dam.
For the remaining 14 channels, the release of water is through weirs/anicuts/runoff across them.
Government of Karnataka has carried out two performance appraisal of Tungabhadra reservoir for the
years 1976 – 77 to 2005-06. The result of appraisal shows that Vijayanagara channels get their due share
of allocated water.
Further, the return flow from main channels of Tungabhadra project and Vijayanagara channels contributes
sufficiently to the downstream section of Tungabhadra River.
Thus with the proposed utilization in Vijayanagara channels, there will be sufficient water in the river to feed
these channels.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 12
Chapter 3. Reservoir
As the report pertains to Modernisation of Vijayanagar Channels and does not involve reservoir, the above
chapter is not discussed.
Chapter 4. Weir/Anicut
There are 12 no’s of Anicuts and the details are enclosed separately. Vijayanagar channels are being fed
from the anicuts constructed in the earlier days for providing irrigation. These anicuts were constructed
during the regime of Vijayanagar empires. They have been constructed using huge boulders and set in Zig-
Zag manner without any kind of mortar for bond. Due to this, the anicuts are subject to leakage of water
exacerbated by the displacement of boulders during high floods. Over a period of time, the system has
deteriorated and needs urgent attention and improvements. The farmers of Vijayanagar channels are
demanding improvements to anicuts.
The improvements proposed to anicuts are:
5. Providing 200 mm thick skin wall encasement to the anicut and grouting.
6. Providing anchor rods at every 1m interval on upstream and downstream of anicut for a width of 5
M all along the length.
7. Providing concrete toe walls on both ends
8. Formation of approach roads to the anicuts wherever required from the nearest road.
The details of the channels system are tabulated below:
4.1. Vijayanagara Channels
The Irrigation schemes comprising 17 Nos of anicuts across Tungabhadra river together known as
Vijayanagara Channels were implemented during Vijayanagara dynasty to provide irrigation facilities. Out
of these, Vallabhapur and Hoskote anicuts were submerged in the backwaters of Tungabhadra reservoir. In
order to cater to the command of Vallabhapur and Hoskote anicuts, one vent of size 1.8 m X 3.6 m is
constructed in the reservoir as a permanent sluice and these commands are fed through Raya and
Basavanna channels. A total of 12.06 TMC has been allocated by the tribunal to Vijayanagara channels
with a break up of 5.71 TMC as protected utilisation and 6.35 TMC as worth consideration.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 13
As per clause IX - E of KWDT award, 7 TMC of water from Tungabhadra reservoir is earmarked for Raya
and Basavanna channels. An allocation of 2 TMC was made by way of assistance through other regulated
discharges other than Raya and Basavanna channels from Tungabhadra reservoir.
In the 1993 master plan, an allocation of 12.05 TMC is made for the Vijayanagara channels without
channel wise breakup and river assistance.
The revised Master plan of 2003 has an allocation of 5.80 TMC for all the 16 Vijayanagara channels.
The Government of Karnataka is proposing the modernization of these Channels to improve the channel
efficiency thereby saving 6.25 TMC of water.
4.2. Details of Channel Systems
Table 4.1 – Table showing Location details of Channel system
No Name of the
channel Name of weir &
length in Km Name of stream
Distance d/s of TB Dam in
Km Remarks
Bellary District (on right side of river)
1. Basavanna Vallabhapur Submerged in Tungabhadra
reservoir
Channel takes off directly from
Tungabhadra dam on right side
2. Raya Hosakote --do-- --do-
3. Bella Hosur-0.602 Tungabhadra 2.4 Channel utilizes
seepage from
higher level
channels
4. Kalaghatta Drainage channel Halla 8
5. Turtha Turtha 3.048 Tungabhadra 16
6. Ramsagar Ramsagar 2.042 --do-- 28.8
7. Kampli Kampli anicut
0.94
--do~ 30.4
8. Belagodahal Drainage
channel
Halla 35.2 Channel utilizes
seepage from
higher level
channels
9. Siruguppa Siruguppa 1.95 Tungabhadra 80 Consists of 7 bits.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 14
No Name of the
channel Name of weir &
length in Km Name of stream
Distance d/s of TB Dam in
Km Remarks
10. Deshnur Deshnur 0.96 ~do-- 80
Koppal District (on left side of river) 11. Koregal
Koregal Submerged in Tungabhadra
reservoir
Channel takes off directly from
Tungabhadra Left Bank Channel
12. Hulugi Hulugi - 0.518 Tungabhadra 2.4
18. Shivapura Shivapura - 0.17 do 8
19. Anegundi Sanapur - 0.518 do 16
20. Upper Gangavathi Upper
Gangavathi0.78 do 27.2
21. Lower Gangavathi Lower Gangavathi 0.45
do 30.4
Raichur district 22. Bichal Bichal - 1.192 do 137.6
Table 4.2 – Table showing Hydraulic details of Channel system
No. Name of the Channel
Length of
Channel in Kms
Cropped area in Ha
Offtake
On right bank of TB River
1 Raya Channel 27.74 2855 Tungabhadra Dam
2 Basavanna Channel 16.50 1447 Tungabhadra Dam
3 Bella Channel 5.50 741 Hosur Anicut
4 Kalaghatta Channel 7.020 349 Drainage channel
5 Turtha Channel 18.69 1171 Turtha anicut
6 Ramasagar Channel 15.50 1024 Ramasagar Anicut
7 Kampli Channel 23.550 894 Kampli Anicut
8 Belagodahala 11.220 328 Drainage channel
9 Deshnur Channel 9.03 815 Deshnur Anicut
10 Siruguppa Channel 10.85 1344 Sirguppa Anicut
On left bank of TB River
11 Hulugi Channel 10.69 419 Hulugi anicut
12 Shivapura Channel 6.54 717 Shivapura anicut
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 15
No. Name of the Channel
Length of
Channel in Kms
Cropped area in Ha
Offtake
13 Anegundi Channel 19.44 1359 Sanapur anicut
14 Gangavathi upper Channel 9.00 1363 Upper Gangavathi anicut
15 Gangavathi lower Channel 9.54 1141 Lower Gangavathi anicut
16 Bichal Channel 14.50 276 Bichal Anicut
16243 Ha
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 16
Chapter 5. Land Potential
5.1. Culturable Command area
a) Originally adopted with basis
The Vijayanagar channels are the oldest, dating back to 17th century. It is observed that the CCA and net
irrigable area are not arrived at scientifically. As such, the existing CCA is considered.
b) Basis for fixing CCA
i. The general topographical maps of Survey of India (scale 1:50,000)
ii. Survey conducted the area plotted on a scale 1:15,000 conforming availability of land
iii. Based on village maps
iv. Actual atchkat attained at present under the outlets
Over the last few centuries of cultivation and irrigation, the farmers have been growing different crops.
However, for the present proposal, the irrigated area has been arrived at taking 20 years average of actual
cultivation which works out to the physical area as 11154.00 Ha and cropped area as 16243.00 Ha
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 17
Chapter 6. Cropping pattern and Crop Water Requirement
6.1. Details of Pre –Project / Original cropping pattern
The existing cropping pattern of Vijayanagar channels are as detailed below
Table 6.1 –Existing (Pre modernization) Cropping Pattern
The physical area (CCA) of each channel of Vijayanagar channel system is as per the register maintained
by the Tungabhadra Project Authorities. The cropped area under each channel for a period of 20 years
(1990-91 to 2009-10) as per records available in the Tungabhadra project has been considered for the
studies. The minimum cropped area of each channel during the last 20 years has been considered as
cropping pattern for pre-modernization period.
Unit : Area in ha
No Name of
canal
Phy. Area
(CCA)
Khariff Rabi Bi seasonal
Total Sugar cane
Garden Paddy Jowar Paddy Groundnut
1 Basavanna 1240 311 135 66 310 281 9 1113
2 Raya 2226 501 163 446 243 1349 78 2780
3 Bella 600 67 64 10 130 381 58 710
4 Kalaghatta 237 69 68 7 98 43 6 291
5 Turtha 931 175 42 109 110 119 545 1100
6 Ramasagar 673 202 91 248 215 2 96 854
7 Kampli 620 241 38 67 0 218 109 673
8 Belagodahala 210 89 12 74 44 12 65 296
9 Sirguppa 764 316 97 201 161 180 54 1008
10 Deshnur 478 141 6 104 30 312 26 619
Total 7979 2112 717 1332 1340 2897 1046 9443
11 Hulugi 265 170 12 0 10 0 48 241
12 Shivapura 403 120 2 116 13 0 29 280
13 Anegondi 789 389 5 182 316 10 177 1078
14 Upper Gangavathi
775 666 0 134 53 43 45 941
15 Lower Gangavathi
667 590 0 49 165 51 12 867
16 Bichal 276 13 0 13 0 170 79 275
Total 3175 1949 19 493 557 274 390 3682
Total Area 11154 4061 735 1825 1896 3171 1436 13125
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 18
It may be seen from the table that against a physical area of (CCA) 11,154 ha, the minimum cropped area
of the Vijayanagar channel system works out to 13,125 ha. Thus the crop intensity of 117.67% could be
achieved in pre- modernization period.
The overall cropping pattern of Vijayanagar channel system during pre-modernization period is as below:
Season/Crop Cropped area in ha % of cropped area
Khariff
1. Paddy 4056 30.9
2. Jowar 735 5.6
Rabi
1. Paddy 1824 13.9
2. Groundnut 1903 14.5
Perennial (Bi-seasonal)
1. Sugarcane 3176 24.2
2. Garden (Banana) 1431 10.9
Total 13,125 100.00
6.2. Details of Post –Modernisation/ proposed cropping pattern
Table 6.2 – Proposed (Post modernization) cropping pattern
The physical area (CCA) of each channel of Vijayanagar channel system is as per the register maintained
by the Tungabhadra Project Authorities. The cropped area under each channel for a period of 20 years
(1990-91 to 2009-10) with slight modification has been considered for the studies. The average cropped
area of each channel during the last 20 years has been considered as cropping pattern for post-
modernization period.
No Name of canal Phy. Area
(CCA)
Khariff Rabi Bi seasonal Total
Paddy Jowar Paddy Groundnut Sugarcane Garden
1 Raya 2226 441 1285 250 429 400 50 2855
2 Basavanna 1240 100 740 20 388 170 29 1447
3 Bella 600 70 396 14 127 80 54 741
4 Kalaghatta 237 30 172 10 102 15 20 349
5 Turtha 931 110 461 75 165 100 260 1171
6 Ramasagar 673 98 440 75 276 50 85 1024
7 Kampli 620 152 301 152 125 60 104 894
8 Belagodahala 210 41 112 35 83 17 40 328
9 Sirguppa 764 165 476 202 381 90 30 1344
10 Deshnur 478 188 224 121 217 55 10 815
Total 1395 4607 954 2293 1037 682 10968
11 Hulugi 265 91 129 82 77 20 20 419
12 Shivapura 403 190 176 117 202 2 30 717
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 19
No Name of canal Phy. Area
(CCA)
Khariff Rabi Bi seasonal Total
Paddy Jowar Paddy Groundnut Sugarcane Garden
13 Anegundi 789 234 417 128 450 6 124 1359
14 Upper Gangavathi
775 217 453 195 412 56 30 1363
15 Lower Gangavathi
667 164 404 170 317 48 38 1141
16 Bichal 276 13 140 9 4 60 50 276
Total 909 1719 701 1462 192 292 5275
Total Area 11154 2304 6326 1655 3755 1229 974 16243
It may be seen from the above table that against a physical area of (CCA) 11,154 ha, the average
cropped area of the Vijayanagar channel system works out to 16,243 ha. Thus the crop intensity of
145.6% could be achieved in post- modernization period.
The overall cropping pattern of Vijayanagar channel system during post-modernization period is as below:
Season/Crop Cropped area in ha % of cropped area
Khariff
3. Paddy 2304 14.18
4. Jowar 6326 38.95
Rabi
3. Paddy 1655 10.19
4. Groundnut 3755 23.12
Perennial (Bi-seasonal)
3. Sugarcane 1229 7.57
4. Garden (Banana) 974 6.00
Total 16,243 100.00
6.2.1. Field application efficiency
The Channel network of Vijayanagara Channel system is partially lined leaving a major portion unlined.
Now, to optimize utilization of water, it is proposed to line the entire Channel system (from main Channel
to field irrigation channels). The crop water requirements are calculated using “Modified Penman Method”
considering the field application efficiency as 85 % of ponded crops and 65 % for non ponded crops and
conveyance efficiency as 75%.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 20
Table 6.3–Table showing the breakup of Irrigation efficiency
No Type of Efficiency Ponded Non ponded
Conveyance efficiency of Channel system upto out let 75% 75%
Field application efficiency 85% 65%
Overall Irrigation efficiency 0.75 x 0.85
=0.6375
0.75 x 0.65 =0.4875
Say 64 %. Say 49 %.
Water requirement for crops under the scheme is calculated as per Modified Penman’s method for the
present notified area by considering the overall irrigation efficiency of 64% for ponded crops and 49% for
non ponded crops.
6.3. Assessment of Crop Water Requirement
The crop water requirement is computed based on Modified Penman’s method. The method consists of
computing evapotranspiration of crop (ETc) using the formula;
ETc = Kc x ET0
Where Kc - Crop coefficient
ET0 - Potential evapotranspiration
The ET0 values of Bellary station are considered for calculation as notified by Indian Meteorological
Department, PPSR - 136 and is tabulated below.
No Month ET0
1. Jan 115.1
2. Feb 128.5
3. Mar 170.9
4. Apr 180.9
5. Jul 155.7
6. May 194.8
7. Jun 167.0
8. Aug 152.8
9. Sep 138.4
10. Oct 123.4
11. Nov 106.0
12. Dec 104.0
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 21
6.4. Crop Water Requirement
The main objective of Modernisation of Vijayanagar channels is to improve efficiency of the channel
system. Minimize water losses and to establish savings of water. The crop water requirement are
calculated based on modified Penman’s method considering Hydrometerological data of Bellary and
weighted average rainfall of the atchkat. The Vijayanagar channel was allocated 12.05 TMC of water as
per the actual utilisation. Now the proposed utilisation is 5.80 TMC resulting in a savings of 6.25 TMC. For
Details regarding calculation of water requirements of crops refer Annexure 6.1 to 6.4.
Table 6.4 –Demand Table
No
Nam
e o
f ca
nal
Ph
y. A
rea
(CC
A)
Khariff Rabi Bi seasonal
To
tal
Pea
k d
isch
arg
e
m3/
sec
WR
in T
MC
Pad
dy
Jow
ar
Pad
dy
Gro
un
dn
ut
Su
gar
can
e
Gar
den
1 Raya 2226 441 1285 250 429 400 50 2855 1.75 1.03
2 Basavanna 1240 100 740 20 388 170 29 1447 0.81 0.45
3 Bella 600 70 396 14 127 80 54 741 0.37 0.24
4 Kalaghatta 237 30 172 10 102 15 20 349 0.19 0.1
5 Turtha 931 110 461 75 165 100 260 1171 0.82 0.47
6 Ramasagar 673 98 440 75 276 50 85 1024 0.66 0.34
7 Kampli 620 152 301 152 125 60 104 894 0.75 0.36
8 Belagodahala 210 41 112 35 83 17 40 328 0.24 0.12
9 Sirguppa 764 165 476 202 381 90 30 1344 1.09 0.48
10 Deshnur 478 188 224 121 217 55 10 815 0.64 0.31
Total 1395 4607 954 2293 1037 682 10968 3.90
11 Hulugi 265 91 129 82 77 20 20 419 0.36 0.16
12 Shivapura 403 190 176 117 202 2 30 717 0.57 0.27
13 Anegundi 789 234 417 128 450 6 124 1359 0.96 0.48
14 Upper Gangavathi
775 217 453 195 412 56 30 1363 1.05 0.48
15 Lower Gangavathi
667 164 404 170 317 48 38 1141 0.89 0.4
16 Bichal 276 13 140 9 4 60 50 276 0.18 0.11
Total 909 1719 701 1462 192 292 5275 1.90
Total Area 11154 2304 6326 1655 3755 1229 974 16243 5.80
6.5. Results
It is seen that channel wise allocation of water was not made. An overall allocation of 12.05 TMC of water
was made in the Master plan considering the present water utilization.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 22
Table 6.5 –Savings Achieved
SI No Unit Existing Allocation
(During 1993)
Utilisation as per Penman’s Method (With lining) after
modernization
Savings achieved
1 In MCM 341.36 164.44 177.00
2 In TMC 12.05 5.80 6.25
As seen from the above table, the savings achieved after Modernisation of the Vijayanagara Channels is
6.25 TMC. (Refer Annexure 6.4 for Crop water requirement tables)
6.6. Conclusions
6.6.1. Achieving required savings
It is seen from the above table, the savings achieved after Modernisation of the Vijayanagara Channels is
6.25 TMC.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 23
Chapter 7. Pissiculture
Pissiculture is being carried out in Basavanna Channel by Tungabhadra Board (Govt. of India). Pissiculture
is not being carried out in other channels.
Chapter 8. Horticulture
The garden crop viz Banana is only grown in the command area.
Chapter 9. Domestic and Industrial water supply etc.
Domestic water supply scheme to the tune of 25 MLD is in operation supplying water to Hospet town from
Basavanna Channel. A small quantity of 3.7 MLD is being supplied to Mariyammanahalli Village.
No water from the channel systems is being used for industrial purposes.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 24
Chapter 10. Demand Table
No Name of canal Phy. Area
(CCA)
Khariff Rabi Bi seasonal Total
Peak discharge
m3/sec
WR in TMC
Paddy Jowar Paddy Groundnut Sugarcane Garden
1 Raya 2226 441 1285 250 429 400 50 2855 1.75 1.03
2 Basavanna 1240 100 740 20 388 170 29 1447 0.81 0.45
3 Bella 600 70 396 14 127 80 54 741 0.37 0.24
4 Kalaghatta 237 30 172 10 102 15 20 349 0.19 0.1
5 Turtha 931 110 461 75 165 100 260 1171 0.82 0.47
6 Ramasagar 673 98 440 75 276 50 85 1024 0.66 0.34
7 Kampli 620 152 301 152 125 60 104 894 0.75 0.36
8 Belagodahala 210 41 112 35 83 17 40 328 0.24 0.12
9 Sirguppa 764 165 476 202 381 90 30 1344 1.09 0.48
10 Deshnur 478 188 224 121 217 55 10 815 0.64 0.31
Total 1395 4607 954 2293 1037 682 10968 3.90
11 Hulugi 265 91 129 82 77 20 20 419 0.36 0.16
12 Shivapura 403 190 176 117 202 2 30 717 0.57 0.27
13 Anegundi 789 234 417 128 450 6 124 1359 0.96 0.48
14 Upper Gangavathi 775 217 453 195 412 56 30 1363 1.05 0.48
15 Lower Gangavathi 667 164 404 170 317 48 38 1141 0.89 0.4
16 Bichal 276 13 140 9 4 60 50 276 0.18 0.11
Total 909 1719 701 1462 192 292 5275 1.90
Total Area 11154 2304 6326 1655 3755 1229 974 16243 5.80
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 25
Chapter 11. Impact of Modernisation
11.1. Upstream and Downstream Projects
As the Modernisation is proposed for channel system resulting in savings of water, there will be no negative
impact on the upstream and downstream projects. In fact, the modernization has positive impact enabling
to take up Upper Bhadra Project (UBP) out of the savings in the Channels and meeting requirement of UBP
to an extent of 6.25 TMC.
Chapter 12. Interstate aspects
KWDT-1 has made enblock allocation. Scheme-wise allocation is made in 1993 Master plan and revised
Master plan of 2002.
As per the revised Master Plan of 2002, an allocation of 12.05 TMC is made for all the Vijayanagara
channels without any break-up of channel wise allocation and river assistance vide Annexure 12.1
The revised Master plan of 2003 has allocated 5.80 TMC for all the 16 Vijayanagara channels.
The Government of Karnataka is now proposing to modernize these Channels to improve the efficiency and
effectiveness of them thereby saving 6.25 TMC of water. Supply of 5.80 TMC to these channels as per crop
water requirement will be ensured.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 26
Chapter 13. Channel system
13.1. Preamble
The Vijayanagar channels are one of the oldest canal system built in India by the Vijayanagar Dynasty
which ruled the Deccan Plateau for nearly 100 – 150 years. This dynasty ruled between 15th and 16th
century AD. The said canals supposed to have been built around 15th Century (about 450-500 years
back). As such, no records on designs and other technical data of channels are available. This has
necessitated that detailed surveys had to be conducted in order to arrive at Modernization activities to be
undertaken.
13.2. Survey of channel system
All Levels are based on GTS Bench Mark, located at the top of step of Vaikuntam IB having value
500.416 m above MSL.
Fig 13.1 – Survey work in progress
Double tertiary fly leveling has been carried out from GTS bench mark using Automatic level and
Temporary benchmarks have been established enroute.
TBMs are established at every 1 Km on the existing permanent structures like buildings, Km stones,
Sheet rocks, Survey boundary stones adjacent to the channels.
A detailed strip survey along the existing channel has been carried out by taking L-sections and Cross
sections at every 30 m intervals.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 27
Cross section levels are taken at closer intervals to get the true shape of channel section in the water
prism which is required to design the channels. The levels are extended up to 15 m beyond the edge of
service road. All the planimetric features are collected for a corridor width of 30 m along the alignment
and in addition, cross sections are taken at structures.
13.3. Site Inventory and survey of channels and structures
Field reconnaissance survey along the existing channel network is carried out in order to identify the take
off point, alignment, various constraints along the existing channels, accessibility, topography, terrain, soil
formation including crops that are being cultivated.
The bigger channels are the Raya and the Basavanna channels. These channels take off from the
Tungabhadra dam and other channels take off from pick up weirs (PUWs) i.e Anicuts on Tungabhadra
river.
Anicuts have been constructed with huge boulders / cut stones dumped or set in zigzag manner. The
existing rip-rap boulders are having lot of voids which cause leakage of water and displacement of
boulders during high floods. Most of the channels take off from such PUWs across Tungabhadra river and
no head regulators or control structures exist. Actually, the Vijayanagara channels is a run-of- the river
scheme. Therefore, it is necessary to construct head regulators and measuring structures on the
channels which are absent. It is observed that the PUWs need major repairs.
Improvements to anicuts are a long felt desire of ayacutdars of Vijayanagara channels. In order to make
use of the run off from the river effectively, it is proposed to take up repairs of existing anicuts.
Irrigation under Vijayanagara channels has a long history. The anicuts and channel systems were
constructed during the regime of Vijayanagara Empire and are still in operation. With passage of time, the
system has deteriorated needing improvements which are critically needed.
A brief description of all the points observed during site visits is as follows;
The alignment of both Raya and Basavanna channels generally run through Municipal area of the
Hospet town where the urban development has taken place right up to the channel boundary and
in certain places, the channel land has also been encroached. The used water, filth including the
drainage is let into the channels at several locations and the water appears to be contaminated.
Photographs of select locations along channels showing the above observations are furnished as
below.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 28
1. The channel water being extensively used by the people residing adjacent to the channel for the
purpose of bathing, washing, cattle feeding etc. It has also been reported that some of the people
drink the water on account of which several water-bourne diseases have been reported.
Fig 13.2 – Figure showing untidy channels
2. Several inlets in the form of well-constructed pipelines, open channels etc., has been directly
linked to the channel and as such at several locations, the channel functions as either a seepage
disposal point or drainage line.
Fig 13.3 – Channel used as disposal point
3. In most of the locations, the channel has been aligned in restricted right of way due to presence
of huge rocks and boulders.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 29
4. Some of the sections of the channel have been laid using size stone masonry and concrete, but
these are all limited to the town limit.
Fig 13.4 – Channel reaches with size stone masonry lining
5. Substantial seepage has been noticed from the channel at several locations due to poor
maintenance.
Fig 13.5 – Damage due to seepage and poor maintenance
6. While reptiles such as snakes and crocodiles have been noticed in the channel water and on the
banks.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 30
Fig 13.6 – Crocodile in the reaches of Raya channel Fig 13.7 – Snake found in the initial reache of Belagodahala channel
7. Thick vegetation growth has been noticed at several locations along the channel within the water
spread area.
Fig 13.8 – Thick vegetation around the Channel
8. Most of the structures are deteriorated.
9. The entire channel network lacks proper crossing and connection. The service roads are heavily
damaged and it is difficult to carry out the inspection of the channel.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 31
Fig 13.9 – Damaged Service road Fig 13.10 – Poor crossing structure
10. Channel water happens to be the lifeline for most of the villages en-route since there is no
dedicated water supply for meeting their day to day domestic water requirement.
Fig 13.11 – Channel flowing full Fig 13.12 – Service road
11. The surface soil is generally black cotton. However, murrum, gravel and hard rock are also
encountered at select locations
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 32
Fig 13.13 –Banana plantation Fig 13.14 –Sugarcane plantation
12. Banana, sugarcane and paddy are the major crops in the command area.
13. Certain channels run in deep cut.
14. There are no proper sign boards or indicative marks, km stones, hectometer stones, chainage
stones etc. along the channel.
13.4. Review of capacity of existing channel and distribution system.
13.4.1. Original design
The Channels have been constructed during the period of Vijayanagara kingdom about 400 years ago. As
such, the channels designed and constructed are outdated in terms of water delivery service (reliability,
flexibility and equity) due to inadequate maintenance and low efficiency.
13.4.2. Present capacity
The Channel systems being unlined are utilizing 12.05 TMC for irrigating 16,241.00 Ha (both Khariff and
Rabi) of cropped area. The command area is 11,154.00 Ha.
13.4.3. Design of revised section (lined)
The Channels Raya and Basavanna take off from Tungabhadra Dam and all other channels except
Kalghatta and Belgodhal take off from anicuts. The Raya channel runs for about 27.7 Kms and joins
Turtha channel at Km 4.0. There is a separate sluice at Km 2.5 of Raya Channel to fulfill the shortage of
water to Bella channel. The Bella Channel runs for about 5.55 Kms and joins Kalghatta channel at 0.2
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 33
Km. The Kalghatta channel runs for about 7.02 Km and joins Turtha channel at K m 0.7. The Turtha
channel runs for about 18.69 Km and joins Ramasagar channel at Km 1.4. The Ramsagar channel runs
for about 15.5 km and joins Kampli channel. The Kampli channel runs for about 23.55 Kms and joins
Belgodhal channel.
The Raya channel is designed by considering its peak discharge as per Modified Penman Method plus
10% extra for rush irrigation including discharges of downstream channels like Bella, Turtha, Ramsagar
and Kampli. Likewise, the downstream channels Bella, Kalghatta, Turtha, Ramsagar and Kampli are
designed for peak discharge plus 10% for rush irrigation.
Belgodhal and Basavanna channels are also designed considering Modified Penman method plus 10%
extra for rush irrigation.
The Channels on left side of Tungabhadra river runs parallel to the Left Bank Main Channel (LBMC)
namely Hulugi, Shivpura, Anegundi, Gangavathi Upper, Gangavathi Lower, and Bichal. There are number
of direct Inlets to these Channels. The Channels are designed for peak discharge obtained from Modified
Penman Method plus 10% rush irrigation requirement.
Based on this, channel sections are designed reach wise considering the existing bed gradient with
Rugosity coefficient (n) of 0.018 for concrete lined channels. Inlets are proposed based on the site
conditions and surplussing weirs are proposed at defined nalas. Refer Annexure 13.1 for particulars of
channel system
13.5. Identification of the reaches needing improvements
A reconnaissance survey was carried out along with the officials of the department to assess the
condition of channels and structures. Looking at the poor state of the channel infrastructure,
modernization estimate is prepared incorporating dismantling and reconstruction of dilapidated structures
and providing concrete lining throughout the length of the channel to enable conveyance of water to tail
ends of the channel and to prevent seepage losses, thereby save water.
13.5.1. Lining
The channels are under operation for more than 400 years providing irrigation for two seasons. Due to the
operation of channels for two seasons in a year, it has lost its shape in several stretches due to scouring
effect and also accumulation of silt over a period. This has resulted in reduction in the velocity of water.
On account of this, it is difficult to convey water to the tail end areas during irrigation season. As a result,
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 34
standing crops at the tail end are not getting enough water. In order to mitigate this problem, water is
being allowed into the channels for saving standing crops during both seasons. Hence, it is necessary to
redesign the channel section with concrete lining. This will also help in improving the efficiency in the
channel system and achieve the desired savings in water. To have uniform quality of concrete lining and
for better compaction, mechanical paver lining is proposed where the bed width is more than 1.20 M from
practical considerations of availability of mechanical pavers. For other reaches where bed width is less
than 1.2 M, manual concrete lining is proposed. The lining has been proposed for entire length upto free
board level with concrete coping on either side for a width of 0.30 M. Since the channels are running in
black cotton soils area which is having swelling nature, CNS layer is proposed below concrete lining as
per BIS.
13.5.2. Strengthening and stabilization of banks
The works of strengthening and stabilization of banks are proposed wherever required as per site
conditions.
13.6. Preparation of capacity statement
No assessment has been made regarding the discharges in the channels as channel system is very old
and infrastructure is not in good condition.
13.7. Need for remodeling / distribution system
The distribution systems of all the channels are not in good condition. Hence, remodeling of distribution
system with concrete lining is proposed.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 35
Chapter 14. Power
14.1. Power status
No proposal for generation of electrical power is envisaged in the modernization project.
14.2. Modernization / upgrading proposal
No power generation is proposed in the 16 channels of Vijayanagara Channels and as such there will be no
impact on the existing Power generation of Tungabhadra Reservoir.
Chapter 15. Navigation
The proposal is to modernize the existing channel system and as the channels are small ones in terms of
carrying capacity, navigation is not considered in this project.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 36
Chapter 16. Groundwater
Dynamic groundwater resources of Karnataka – March 2009 is published by joint efforts put by Department
of Mines and Geology, Govt of Karnataka and Central Groundwater Board, South Western Region,
Bangalore during Dec 2010. The report mainly provides groundwater resources available in Karnataka.
The details of Groundwater resources pertaining to Vijaynagar Channels is as follows:
16.1. Depth of Groundwater level
As per assessment, the depth of Groundwater for Pre monsoon and Post monsoon is as follows:
Table 16.1 – Table showing depth of Groundwater for Pre monsoon and Post monsoon
No Assessment
Unit Command/Non
command Rainfall in
mm
Average Pre monsoon
water level (mbgl)
Average Post
monsoon water level
(mbgl)
Average fluctuation
(m)
1. 4D3A3 Command 666.7 - - -
Non Command 666.7 - - -
2. 4D3A8 Command 612.6 - - -
Non Command 612.6 5.94 3.21 2.73
3. 4D3C2 Command 682.6 - - -
Non Command 682.6 - - -
4. 4D3F2 Command 721.8 - - -
Non Command 721.8 - - -
Note:
Delineation and codification of watersheds
The delineation of watersheds has been done in 5 stages. For ex: 4D3A3 indicates 4 as water resource
region, D indicated basin code, 3 indicate catchment code, A indicates sub catchment code and 3 indicate
watershed code.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 37
16.2. Assessment of Groundwater potential in the command area
As per assessment the groundwater potential is as follows:
Table 16.2 – Table showing Administrative wise assessment of Dynamic Groundwater resources
Administrative wise assessment of Dynamic Groundwater resources in ha-m
No
Nam
e o
f D
istr
ict
Nam
e o
f T
alu
k
Co
mm
and
/No
n c
om
man
d
Rec
har
ge
fro
m r
ain
fall
du
rin
g m
on
soo
n s
easo
n
Rec
har
ge
fro
m o
ther
sou
rces
du
rin
g m
on
soo
n
seas
on
Rec
har
ge
fro
m r
ain
fall
du
rin
g N
on
- m
on
soo
n
seas
on
Rec
har
ge
fro
m o
ther
sou
rces
du
rin
g N
on
-
mo
nso
on
sea
son
To
tal A
nn
ual
GW
rech
arg
e
Pro
visi
on
fo
r n
atu
ral
dis
char
ge
Net
an
nu
al G
W
avai
lab
ility
1. Raichur Raichur Command 712 467 302 645 2126 213 1913
Non Command 3502 399 1501 759 6160 609 5552
Total 4214 866 1802 1405 8287 821 7465
2. Koppal Gangavathi Command 1453 15607 790 14336 32186 3219 28968
Non Command 1765 503 836 614 3718 244 3474
Total 3218 16110 1626 14951 35904 3463 32442
3. Bellary Sirguppa Command 2231 7729 1309 4827 16097 1610 14487
Non Command 323 791 164 695 1974 197 1776
Total 2553 8521 1473 5523 18070 1807 16263
4. Bellary Hospet Command 1520 4176 826 2412 8935 894 8042
Non Command 1408 173 787 260 2629 263 2366
Total 2929 4349 1614 2673 11564 1156 1048
As per administrative assessment of unit wise categorization is as follows:
Table 16.3 – Table showing administrative assessment of unit wise categorization
No
Nam
e o
f D
istr
ict
Nam
e o
f T
alu
k
Co
mm
and
/No
n
com
man
d
Sta
ge
of
GW
dev
elo
pm
ent
(%)
Pre Monsoon Post Monsoon C
ateg
ory
Wat
er le
vel t
ren
d
Is t
her
e a
sig
nif
ican
t d
eclin
e
Wat
er le
vel t
ren
d
Is t
her
e a
sig
nif
ican
t d
eclin
e
1. Raichur Raichur Command 50 No decline No No decline No Safe
Non Command 73 No decline No No decline No Safe
2. Koppal Gangavathi Command 11 No decline No No decline No Safe
Non Command 120 Declining Yes Declining Yes OE
3. Bellary Sirguppa Command 70 No decline No No decline No Safe
4. Bellary Hospet Command 19 No decline No No decline No Safe
Non Command 57 No decline No No decline No Safe
*OE – Over Exploited
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 38
16.3. Quality of Groundwater
The information on ground water quality with respect to Vijayanagara channels are briefed below:
As per hydro chemical data of N.H.S of May 2003 in the district E.C.values range from 730-2870 micro
mhos /cm at 25°c is recorded. Chloride is in the range of 43 to639 mg/l and floride in the range of 0.6 to 2.7
mg/l as based on the Bureau of Indian standards recommendations for drinking water the water E.C having
less than 750 micro mhos/cm at 25°C is desirable and unsuitable more than3000 micro mhos/cm at
25°C.The concentration of fluoride is distributed in the district in the range of 1.0 to1.5 mg/l up to maximum
of 2.7 mg/l. The desirable limits for drinking purposes are less than 1 ppm. The concentration beyond 1
ppm is unsuitable, noticed as pockets in Gangavathi and Kushtagi taluks.
16.4. Assessment of possible impact on Groundwater
Due to Modernisation of the existing canal system under Vijayanagara Channels, the possible impact on
Groundwater is negligible.
16.5. Conjunctive use of surface and groundwater
By adopting Conjunctive use of surface and Groundwater, the entire command of all the canals can be
irrigated with use of optimal quantity of water thereby helping to save water.
With this, the farmers can arrest further water logging menace in the command of the canals.
The conjunctive use of the ground water particularly in tail end area will also help in supplementing the
canal irrigation by which entire command area could be served with 5.80 TMC thus saving about 6.25 TMC
of water.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 39
Chapter 17. Drainage and land reclamation
17.1. Review of drainage
The drainage system is sufficient to drain the water and no water logging, soil salinity and alkalinity has
been noticed. Anyway, it is recommended to propose surface drainage, water logging and such measures.
In the command area of 11154 ha under Vijayanagara channel system, an area of 340 ha is affected by
water logging, salinity and alkalinity. The Command Area Development Authority (CADA) of Tungabhadra
project has taken up the reclamation of these water logged area. This area has been reclaimed which can
be brought under cultivation with the proposed crop intensity of 145.6%.
17.2. Type of reclamation
17.2.1. Field drains
As curative and preventive measures to water logging and salinity problems, field drains treatment is given
which drains of excess water and lowers the salt concentration in the root zone and thus helps to improve
the crop yields. The field drains has been taken up in various programs.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 40
Chapter 18. Land acquisition, Rehabilitation and Resettlement
18.1. Land acquisition, Rehabilitation / Resettlement
Since the proposal is Modernization of the existing canal system (already in practice for more than 400
years), no acquisition of lands is envisaged.
The Vijayanagar channels do not have any reservoir which leads to submersion. Hence, question of
Rehabilitation and Resettlement (R&R) does not arise.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 41
Chapter 19. Water management and maintenance
The majority of the cultivated area belongs to small land holders. This is due to the increase in number of
families over the years depending on the same piece of land which is shared among the families. The
farmers generally own bullocks to plough the farm land. But the use of tractors, power tillers and tractor-
trailers are gradually increasing in the farm work in recent years.
The responsibility of the water management has been handed over to the Water User’s Cooperative
Societies (WUCS) formed in the villages of the command area by the Tungabhadra CADA, Munirabad..
However, water Resources Department i.e. with CADA of Tungabhadra project, will be responsible for water
distribution and maintenance of the channel system.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 42
Chapter 20. On farm development works
20.1. Command Area Development Authority
The Command area of Vijayanagar channels comes under the jurisdiction of Tungabhadra Command Area
Development authority. The functions of CADA are;
Preparation of plans and programs for the development of command area.
Distribution of agricultural implements and inputs such as ploughs, seeds, pesticides etc
Conducting farm trials and demonstration of new technologies in the agricultural field
Conserving and developing soil fertility
Equitable distribution of water to the entire command
Effective utilisation of surface water
Providing financial assistance through cooperative societies, banks etc.
20.1. Organization setup of On Farm Development
On farm development works are taken up by CADA, Tungabhadra Project with the assistance of officers of
concerned departments’ viz., Water Resources Department, Agriculture Department and Co-operative
Department.
20.1.1. Land leveling
The land leveling works were initially carried out by concerned farmers with subsidy grant and technical
assistance from CADA. Now, no subsidy grant is being provided, however, technical guidance is continued
to be provided.
20.1.2. Field Irrigation Channels (FICs)
In many parts of paddy growing area, use of field-to-field irrigation or katcha field channels is in practice. In
order to ensure timely and equitable distribution of water to each field and feed the water to the tail-end
farmers in the command area, construction of pakka Field Irrigation Channels (FICs) in vulnerable stretches
have been constructed by CADA Tungabhadra Project.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 43
20.1.3. Construction of field drains
The field drains are also being executed in the command area with the Central Assistance. The field drains
to serve as drainage area is 25% of the total command area i.e. 4,060 ha. Necessary provision is made in
the estimate for construction of field drains.
20.1.4. Warabandi
To ensure equitable distribution of water to all the lands under each outlet of the command area,
Warabandi system is to be brought into practice. In this system, each farmer gets water turn by turn for a
fixed time-interval proportionate to the extent of his land. For efficient and satisfactory water management,
Wireless Communication System has been established by CADA Tungabhadra project.
20.1.5. Ayacut roads
The ayacut roads in the command area of Vijayanagara channels are very old. The new ayacut roads
wherever essential as demanded by farmers is constructed by CADA Tungabhadra project.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 44
Chapter 21. Construction programme
The construction program is planned in a phased manner to be executed without affecting the irrigation.as
shown in table below;
Table 21.1 – Implementation program of Modernization of Vijayanagara channels
Name of the Channel Phases Remarks
1. Raya Phase – I during Nov-Dec closure period
-- 2. Basavanna
3. Bella
4. Kalghatta
5. Turtha
6. Ramsagar
7. Kampli
8. Belgodhal
1. Bella Phase – II during Apr-Jun closure period
Anicut works are taken up in Phase II due to lean flow in Tungabhadra river during April to June.
Anicuts in Phase I Channels are taken up under Phase II.
2. Turtha
3. Ramasagar
4. Kampli
5. Deshnur
6. Shirguppa
7. Hulugi
8. Shivpura
9. Anegundi
10. Upper Gangavathi
11. Lower Gangavathi
12. Bichal
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 45
Chapter 22. Construction organization
22.1. Organization setup for modernization
The Vijayanagar channels come under the control of Chief Engineer, ICZ, Munirabad. The hierarchical structure of the controlling officers is as follows:
Chief Engineer Irrigation Central Zone
Munirabad
Superintending Engineer TBP Circle Munirabad
Executive Engineer No 1 T.R. Division
Munirabad
Asst. Executive Engineer Vijayanagara Channel Sub
division, Kamalapura
Asst. Executive Engineer No.1Channel Sub Division
Oddarahatti camp
Asst. Executive Engineer No.2TR Sub Division
Agalkera
Asst. Executive Engineer No.2Low level Channel Sub
Division
Sirguppa
Superintending Engineer Tungabhadra Channel
Construction Circle Yarmarus
Executive Engineer No 2Channel Division
Oddarahatti
Executive Engineer No 6Channel Division
Bellary
Executive Engineer No 5Channel . Division
Yarmarus
Asst. Executive Engineer RDS Sub Division
Gilesgur Camp
Executive Engineer QC Division Munirabad
Asst.Executive Engineer
Q.C Sub Division
Munirabad
Asst.Executive Engineer
Q.C Sub Division
Bellary
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 46
Table 22.1 shows the Engineering divisions in charge of the channels.
Table 22.1 – Divisions in- charge of the channels
No. Name of the channel Name of the division
On right bank of TB river
1 Raya channel
Executive Engineer No.1 T.R.Division, Munirabad
2 Basavanna Channel
3 Bella Channel
4 Kalghatta Channel
5 Turtha Channel
6 Ramasagar Channel
7 Kampli Channel
8 Belagodahala
9 Deshnur Channel Executive Engineer, No.6 Channel Division, Bellary 10 Siruguppa Channel
On left bank of TB river
11 Hulugi Channel
Executive Engineer, No.6 Channel Division, Oddarahatti
12 Shivapura Channel
13 Anegundi Channel
14 Gangavathi upper channel
15 Gangavathi lower channel
16 Bichal Channel Executive Engineer, No.5 channel Division Yermarus
Except in the case of Raya and Basavanna channels, where water is let out through a vent, in the case of
other channels, the water flows into channel system continuously and the maintenance is carried out by the
irrigation department.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 47
Chapter 23. Environment, Ecology and Forest aspects
Since the proposal is Modernization of the existing canal system (already in practice for more than 400
years,) there will be no effect on the Environment and Ecology of the area. No acquision is envisaged and
no forest lands are involved.
23.1. World Heritage Zone
Hampi and its surroundings are located in the buffer zone area of Hampi heritage site which is declared as
one of the world heritage center. Any activity of improvement or development are needs to be in sync with
its world heritage regulation .Turtha channel (0.00 to 8.00 Km) and Anegundi channel (0.00 to 19.44 Km )
runs in this buffer zone area and as such in order to abide by the regulations, these channels are provided
with stone pitching (above FSL) instead of cc lining as per the guidelines of the Archeological Survey of
India and also Hampi World Heritage Area Management Authority (HWHAMA).
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 48
Chapter 24. Economic Evaluation
24.1. For Channels
The estimate is prepared based on the designed section and cut-off statement of the channel. Provisions
made are as follows:
CC lining of 80 mm thickness is proposed using mechanical pavers where the channel bed is more
than 1.2 m.
Manual lining is proposed where the channel bed width is less than 1.2 m.
CNS backing is provided as the stratum met with is of B C soil as per BIS.
Provision of lugs and template walls as per standards
Improvement of service road
Improvement of inspection path.
Removal of silt.
Earthwork excavation in ordinary soil.
Constructing uncoursed rubble masonry
Tarfelt expansion joint for CC lining
Perforated GI pressure relief pipes for pressure relief arrangement
Hectometer, kilometre and boundary stones.
24.2. For Structures
Earthwork excavation in ordinary soil
M10 , 40 mm CC for foundation
M15, 40 mm CC for abutment.
M15, 20 mm CC for sub structure
M20 , 20 mm for Deck slab, kerb and wearing coat for bridges
Provision for steel reinforcement
Provision for stone pitching
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 49
An estimate for Rs.403.22 Crores is prepared for various works envisaged in the project with the following
provisions. The cost estimate is based on the latest schedule of rates of WRD, Bangalore (2013 -14). This
includes 25% extra weightage for closure period as provided in the SR. The total cost of modernization is
classified into different sub-heads shown below;
A. PRELIMINARY
A provision of Rs.174.59 lakhs is made for charges towards consultancy services viz, detailed survey,
investigation, Preparation of DPR etc and other preliminary works as required for the project.
B. LAND
No provision is made in the estimate towards land acquisition.
C. WORKS (ANICUT)
There are 11 anicuts. These anicuts are constructed using huge boulders in a Zig Zag manner. Due to
constant wear and tear during the last 400 years of existence, the boulders have been displaced and huge
leakages are noticed.
It is proposed to strengthen the anicut by providing cement concrete M 20 skin wall encasement.
The provisions made are as follows:
Providing anchor rods
Provision for curtain grouting
Providing skin wall to the entire length of anicut
Providing contraction joint
Providing concrete toe walls on both ends
Formation of approach roads to anicuts wherever required from the nearest road.
In addition, provision for coffer dam to facilitate unhindered repair works is made.
A provision of Rs. 6126.33 lakhs is made for Improvements of 11 anicuts. This involves providing anchor
rods to the bed and skin walls with CC M 20 throughout the length and width of the weir.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 50
D. REGULATORS AND MEASURING DEVICES
A provision of Rs. 2919.56 lakhs is made towards Repair/Reconstruction/new construction of head
regulators, Cross Regulators and measuring devices under main Channel and its networks. The details are
as follows:
No Name of the
Channel Name of
Structures
No of Structures
Construction Dismantling &
Reconstruction 1. Raya Head Regulator
Cross Regulator 1
Measuring Device 1
DPO 2 50 2. Basavanna Head Regulator 1
Cross Regulator 2
Measuring Device 1
DPO 42 3. Bella Head Regulator 2
Cross Regulator 1
Measuring Device 1
Distribution box 1
DPO 2 10 4. Kalghatta Head Regulator
Cross Regulator
Measuring Device 1
DPO 29 5. Turtha Head Regulator
Cross Regulator 3
Measuring Device 1
DPO 40
6. Ramsagar Head Regulator 1
Cross Regulator 2
Measuring Device 1
DPO 20 8 7. Kampli Head Regulator
Cross Regulator 1
Measuring Device 1
DPO 34 4 8. Belgodhalla Head Regulator
Cross Regulator
Measuring Device 1
DPO 21 8 9. Sirguppa Head Regulator
Cross Regulator 2 2
Measuring Device 1
DPO 2 0 10. Deshnur Head Regulator
Cross Regulator 4
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 51
No Name of the
Channel Name of
Structures
No of Structures
Construction Dismantling &
Reconstruction
Measuring Device 1
DPO 14 11. Hulugi Head Regulator
Cross Regulator
Measuring Device 1
DPO 55 12. Shivpura Head Regulator
Cross Regulator 1
Measuring Device 1
DPO 1 23 13. Anegundi Head Regulator
Cross Regulator 1
Measuring Device 1
DPO 54 14. Gangavathi
Upper Head Regulator 3
Cross Regulator 1
Measuring Device 1
DPO 26 15. Gangavathi
Lower Head Regulator 3
Cross Regulator 1 1
Measuring Device 1
DPO 29 16. B Bichal Head Regulator
Cross Regulator 1
Measuring Device 1
DPO 10
E. FALLS
A provision of Rs. 152.27 lakhs is made towards construction of channel drops for different channels and
also construction of chambers for linked channels, where the higher level channel joins the lower level
channel.
No Name of the Channel
Name of Structures
No of Structures
Construction Dismantling & Reconstruction
1. Raya Canal drop 9 2. Basavanna Canal drop 7 3. Bella Canal drop 4. Kalghatta Canal drop 1 5. Turtha Canal drop 7 6. Ramsagar Canal drop 7. Kampli Canal drop 8. Belgodhalla Canal drop
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 52
9. Sirguppa Canal drop 10. Deshnur Canal drop 11. Hulugi Canal drop 1 12. Shivpura Canal drop 1 13. Anegundi Canal drop 2 14. Gangavathi
Upper Canal drop
15. Gangavathi Lower
Canal drop 1
16. B Bichal Canal drop
F. CROSS DRAINAGE WORKS
A provision of Rs. 912.10 lakhs is made towards construction of inlets with CC M15 and under tunnels.
No Name of the Channel
Name of Structures
No of Structures
Construction
Dismantling & Reconstruction
1. Raya Inlet 2
Undertunnel 2 1 2. Basavanna Inlet 2
Undertunnel 2 2 3. Bella Inlet 4
Undertunnel 4. Kalghatta Trough 2
Undertunnel 5. Turtha Inlet
Undertunnel 6. Ramsagar Inlet 11
Undertunnel 7. Kampli Inlet 9
Trough 2 8. Belgodhalla Inlet 2
Undertunnel 9. Sirguppa Inlet
Undertunnel
Super passage 1 10. Deshnur Inlet
Undertunnel 11. Hulugi Inlet 2
Undertunnel 12. Shivpura Inlet 6
Undertunnel 1 13. Anegundi Inlet 10
Undertunnel 2 14. Gangavathi
Upper Inlet 13
Undertunnel 15. Gangavathi Inlet 3 1
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 53
Lower Undertunnel 16. B Bichal Inlet
Undertunnel
G. BRIDGES
A provision of Rs.1960.48 lakhs is made towards construction of Cart Track Crossings/ Village road
bridges with deck slab of CC M20, Foot Bridges and Sopanams.
No Name of the
Channel Name of Structures
No of Structures
Construction Dismantling &
Reconstruction 1. Raya Cart track Crossing 12 7
Major Road Bridge 1
Village road bridge 3
Foot bridges 1
Sopanams 1 2. Basavanna Cart track Crossing 7
Village road bridge 3
Foot bridges 1
Sopanams 6 3. Bella Cart track Crossing 1 4
Village road bridge 1 2
Foot bridges 1
Sopanams 1
Cattle ramp 3 4. Kalghatta Cart track Crossing 1 7
Village road bridge 2
Foot bridges 1
Sopanams 5. Turtha Cart track Crossing 7
Village road bridge
Foot bridges
Sopanams 2
Cattle ramp 1
6. Ramsagar Cart track Crossing 6 4
Village road bridge
Foot bridges
Sopanams
Cattle ramp 1 7. Kampli Cart track Crossing 20 16
Village road bridge 3 2
Foot bridges 15 5
Sopanams 3 8. Belgodhalla Cart track Crossing 12 4
Village road bridge 1
Foot bridges 1
Sopanams
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 54
No Name of the
Channel Name of Structures
No of Structures
Construction Dismantling &
Reconstruction 9. Sirguppa Cart track Crossing 2 3
Village road bridge
Retaining Wall 1
Sopanams 1 10. Deshnur Cart track Crossing 4 4
Road bridge 1
Foot bridges
Sopanams 11. Hulugi Cart track Crossing 8
Village road bridge 1
Foot bridges 1
Sopanams 12. Shivpura Cart track Crossing 2
Village road bridge 5
Foot bridges
Sopanams 13. Anegundi Cart track Crossing 2 9
Village road bridge 1
Foot bridges
Sopanams 5
Cattle ramp 3 1 14. Gangavathi
Upper Cart track Crossing 6
Village road bridge 1
Foot bridges
Sopanams 6 15. Gangavathi
Lower Cart track Crossing 4
Village road bridge
Foot bridges
Sopanams 16. B Bichal Cart track Crossing 11
Village road bridge
Foot bridges
Sopanams
H. ESCAPES
A provision of Rs.561.84 lakhs is made towards construction of Escapes, relieving weirs, and scouring
sluices with CC M15.
No Name of the
Channel Name of
Structures
No of Structures
Construction Dismantling &
Reconstruction 1. Raya Escapes 2
Relieving weirs
Scouring sluices 1 3 2. Basavanna Escapes
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 55
No Name of the
Channel Name of
Structures
No of Structures
Construction Dismantling &
Reconstruction
Relieving weirs 1
Scouring sluices 2 3. Bella Escapes
Relieving weirs 1
Scouring sluices 1 4. Kalghatta Escapes
Relieving weirs
Scouring sluices 1 5. Turtha Escapes 2
Relieving weirs 1
Scouring sluices 1
6. Ramsagar Escapes 2
Relieving weirs 1
Scouring sluices 7. Kampli Escapes
Relieving weirs
Scouring sluices 5 1 8. Belgodhalla Escapes
Relieving weirs
Scouring sluices 3 3 9. Sirguppa Escapes
Relieving weirs
Scouring sluices 1 10. Deshnur Escapes
Relieving weirs
Scouring sluices 2 11. Hulugi Escapes 1
Relieving weirs
Scouring sluices 7 12. Shivpura Escapes
Relieving weirs
Scouring sluices 1 13. Anegundi Escapes 5
Relieving weirs 2 7
Scouring sluices 14. Gangavathi
Upper Escapes 1
Relieving weirs
Scouring sluices 1 15. Gangavathi
Lower Escapes 1
Relieving weirs
Scouring sluices 1 16. B Bichal Escapes
Relieving weirs
Scouring sluices
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 56
I. NAVIGATION WORKS
No provision is made in the estimate as there is no navigation needs.
J. POWER PLANT CIVIL WORKS
No provision is made in the estimate as no power generation is involved.
K. BUILDINGS
A provision of Rs.155.00 lakhs is made in the estimate.
L. EARTHWORK, LINING AND SERVICE ROAD (MAIN CHANNEL)
A provision of Rs.20621.53 lakhs is made for 16 Nos channels of total length 215.93 Km towards
earthwork, lining and service road for main channels and its networks. CC mechanical paver lining of 80
mm thick is proposed where the bed width is greater than 1.2 m and for other reaches 75 mm thick manual
lining with M15 grade is proposed. At every 15 m interval, CC template walls are proposed. Provision of
CNS backing is made as the soil met with is of black cotton soil which is expansive in nature..
M. PLANTATION
A provision of Rs.67.95 lakhs is made for plantation on either side of the main channel at 15 m c/c. The
rate per Km works out to Rs. 31,500/-
N. TANKS AND RESERVOIRS
No provision is made in the estimate as it is not applicable to the current project.
O. MISCELLANEOUS
No provision is made in the estimate.
P. MAINTENANCE
A provision of Rs.391.41 lakhs is made towards maintenance at 1% of the cost of I – works less A,
B,O,M,P,Q and X as per CWC guidance. This covers the cost of maintenance of roads and other structures
during the period of construction.
Q. SPECIAL TOOLS AND PLANTS
A provision of Rs.40.46 lakhs is made in the estimate.
R. COMMUNICATIONS
No provision is made in the estimate.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 57
S. POWER PLANT AND ELECTRICAL MECHANICAL SYSTEM
No provision is made in the estimate.
T. WATER SUPPLY WORKS
No provision is made in the estimate.
U. DISTRIBUTARIES MINORS AND SUB-MINORS
A provision of Rs. 5454.41 lakhs is made for modernization of 64.92 Kms of distributory networks and
161 Kms of minors coming under Vijayanagara channels. Provision of CNS backing with 75 mm thick
manual CC lining of grade M15 is made in the estimate.
V. WATER COURSES
No provision is made in the estimate.
W. DRAINAGE
A provision of Rs.277.76 lakhs is made towards construction of drains as two of the channels namely
Raya and Basavanna runs in part of municipal area.
X. ENVIRONMENT AND ECOLOGY
No provision is made in the estimate.
Y. LOSSES OF STOCK
A provision of Rs.97.85 lakhs is made in the estimate at 0.25% of the cost of I – works less A, B,O,M,P,Q
and X as per CWC guidance.
Z. PROVISION FOR POWER GENERATION
No provision is made in the estimate.
TOTAL OF I - WORKS – 39913.55 LAKHS
II. ESTABLISHMENT CHARGES
No provision is made in the estimate.
III. TOOLS AND PLANTS
A provision of Rs. 9.12 lakhs is made in the estimate
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 58
IV. SUSPENSE
No provision is made in the estimate.
V. RECEIPTS AND RECOVERIES ON CAPITAL ACCOUNT
No provision is made under this sub head.
TOTAL DIRECT CHARGES
The total direct charges from the above sub head works out to Rs. 39922.67 lakhs.
INDIRECT CHARGES
A. Audit and accounts charges (1% of I –
works)
Rs 399.23 lakhs has
been made in this
sub head
B. Miscellaneous unforeseen works and
rounding of
TOTAL INDIRECT CHARGES
Total indirect charges as mentioned above Rs. 403.21 lakhs.
GRAND TOTAL = 40321.89 LAKHS
SAY 403.22 CRORES
Refer Annexure 24.1 for General Abstract
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 59
ABSTRACT COST FOR MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
Sl. No Particulars
(Rs. In Lakhs)
UNIT I Headworks (Anecuts)
UNIT II Canal Works
Total
I Direct Charges of Works
1 A - Preliminaries 174.59 174.59
2 B - Land - -
3 C - Works 6126.33 - 6126.33
4 D - Regulator 2919.56 2919.56
5 E - Falls 152.27 152.27
6 F - Cross Drainage Works 912.10 912.10
7 G - Bridges 1960.48 1960.48
8 H - Escapes 561.84 561.84
9 I - Navigation works - -
10 J - Power plants and Civil Works - -
11 K - Buildings 155.00 155.00
12
L - Earthwork
L1 - Lining 20621.53 20621.53
L2 - Service Road
13 M - Plantation 67.95 67.95
14 N - Tank and Reservoirs - -
15 O - Miscellaneous - -
16 P - Maintenance (1% of cost of I - works except A,B,M,O,Q and X)
61.26 330.15 391.41
17 Q - Special Tools and plants 40.46 40.46
18 R - Communication - -
19 S - Power plant and Electrical systems - -
20 T - Watersupply works - -
21 U - Distributories and Minors 5454.41 5454.41
22 V - Water Courses and Field Channels - -
23 W - Drainage 277.76 277.76
24 X - Environment and Ecology - -
25 Y - Loss of stocks and unforseen (0.25% of cost of I - works except A,B,M,O,Q and X)
15.32 82.54 97.85
Total of I - Works 6202.91 33710.64 39913.55
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 60
Sl. No Particulars
(Rs. In Lakhs)
UNIT I Headworks (Anecuts)
UNIT II Canal Works
Total
II Establishment charges -
III Small Tools & Plants 9.12 9.12
IV Suspens - -
V Reciepts & Recoveries on capital accounts deductions - -
Total Direct charges 6202.91 33719.76 39922.67
INDIRECT CHARGES
b)Audit and Account charges (1% of cost of I works) 62.03 337.20 399.23
Total Indirect charges 62.03 337.20 399.23
TOTAL DIRECT AND INDIRECT CHARGES 6264.94 34056.96 40321.89
Grand Total Say Rs 403.22 Crores
Chief Engineer KNNL, Irrigation Central Zone
Munirabad
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 61
Chapter 25. Administrative and Legislative provisions
25.1. Administrative set up
The present administration is under the Department of Water resources. It is oriented more towards
engineering aspects and is headed by one Chief Engineer (Irrigation Central zone). There are two circles with
four divisions and five sub-divisions to monitor the canal system. This department is responsible for
construction, maintenance of all structures within the command area and the canal system. In the past few
years, WUAS (Waters Users Association Society) named as Water Users Cooperative Society (WUCS) are
set up at the village / tank level. However, it is found that even after formation of the WUCS, there has been
low impact on the overall operation and maintenance of canal system.
Presently water demands are being done by the Water Resources Dept. /Nigam and the collection is being
done by WUCS. After registration of WUCSs, the Asst. Executive Engineer will issue the demand notice to the
WUCS and the societies will collect the charges and remit to the Govt. /Nigam as per the notification of the
Govt.
25.2. Legal status & Policy framework
The construction and O & M of the Vijayanagar channels are governed by various Government policies, which
include:
1. Karnataka Irrigation Act - 1965
2. Karnataka Community based Integrated Tank System Management Act – 2002
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 62
Chapter 26. Facilities for training the operational and maintenance personnel
26.1. Existing
No facilities for training the O& M personal have been noticed.
26.2. Proposals for improvement and extension
26.2.1. Institution framework
The water User’s Association needs to be constituted at the beginning of the implementation of the scheme
involving all the direct and indirect beneficiaries. This association shall function within the rules, regulations
and the byelaws of the society. There should be an organizing committee of the society and should contain
representative of all the sections of the beneficiaries with due representation to various sections such as
SC/ST, women, labour, backward class people etc. A proper training for management of its finance is of
utmost importance. The Programme / mechanism needs to be provided to make them aware of and be
informed to upgrade their managerial skill by way of various courses, training, discussions etc. The society
should run on a transparent basis with its finance being audited duly by the competent authority of the year.
The Government agencies should in their advisory capacity provides the society with technical inputs.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 63
Chapter 27. Operation and Maintenance
27.1. Training and Visit system
The Karnataka State Agricultural Department has taken up the training and visit system (T&V) of extensions in
the entire State of Karnataka. Under this system, the training programs have been conducted by the Assistant
Directors of Agriculture of concerned taluk, with the assistance of village extension workers and progress
would be reported to Principal Agriculture Officer. One village extension worker covers 400 farmer families.
The village extension worker will conduct regular contact programme once in fortnight. The Department will
also conduct regular workshops for every two months to educate farmers on agronomy, land protection,
introduction of new technology in the agricultural field etc.
In addition to the above, department has responsibility of proper distribution of subsidized seeds and
pesticides through agro centers and private agencies.
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 64
Chapter 28. B C Ratio
28.1. Benefit Cost ratio
The Benefit Cost Ratio (BCR) of the Modernisation of Vijayanagara channels has been prepared as per the
guidelines of Central Water Commission (CWC).
The Benefit cost ratio is worked out to 1.65
While calculating BCR, following have been considered.
28.1.1. Estimated value of produce before channel modernization
The yield of the crops, rate, and particulars of input i.e. seeds; fertilizers and pesticides and hired laborers
have been taken into account. Thus the net value of the produce is arrived at Rs. 4159.28 lakhs.
28.1.2. Estimated value of produce after channel modernization
After completion of channel Modernisation, to achieve increased production of crops, the cropping pattern
has been revised taking into consideration of water availability, soil conditions, present agricultural practice
including farmer’s attitude to grow the suggested cropping pattern.
Similarly, the yield of the crops, rate, and particulars of input i.e. seeds; fertilizers and pesticides and hired
laborers have been taken into account. The net value of the produce after Modernisation is arrived at
Rs.11899.78 lakhs. The increase in the yield of the crops after completion of Modernisation of Vijayanagara
channels, following factors contribute in the increased agricultural activities and thereby increase in the yield.
1. Seepage / wastage are minimised, thereby ensuring the supply of sufficient water to the tail end
achkat.
2. Proper and quick distribution and timely supply is assured.
The calculation of B.C. Ratio is appended in Annexure 28.1
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 65
Figures are in Rs lakhs
A Gross Receipts Before
Modernisation After
Modernisation
1 Gross value of farm produce 17355.35 25870.56
2 Dung receipts(at 30%of the fodder expenditure) 780.99 776.12
3 Total A : Gross Receipts(1+2) 18136.34 26646.68
B EXPENSES:
1 Expenditure on seeds 1048.89 688.09
2 Expenditure on manure etc. 5170.33 4305.61
3 Expenditure on hired labour(human and bullock) 3471.07 5174.11
4 Fodder expenses(as percentage of gross value of produce)
(15% ,10% of item A.1) 2603.30 2587.06
5 Depriciation on implements (2.7% of Item A.1) 468.59 698.51
6 Share and cash rent (5% 3% of Item A.1) 867.77 776.12
7 Land Revenue (2% of Item A.1) 347.11 517.41
8 Total B : Expenses (1 to 7) 13977.06 14746.89
C NET VALUE OF PRODUCE
1 Total gross receipts(Total A.3) 18136.34 26646.68
2 Minus total expenses (Total B.8) 13977.06 14746.89
3 Net value of produc © : [1-2] 4159.28 11899.78
D ANNUAL BENEFITS:
1 Net value after irrigation (C:3) 11899.78
2 Minus Net value before irrigation (C:3) 4159.28
3 Net annual benefits (D):[1-2] 7740.50
TOTAL NET ANNUAL BENEFITS (D3) 7740.50
E ANNUAL COSTS
1 Intrest on Capital @10% ( Esimated total cost of the project including cost of land development @ Rs.1000/- per Ha) (Rs 40322.00 Lakhs + 16.24 Lakhs)
4048.44
2 Depreciation of the project at 1 % of the cost of the project for 100 years life excluding cost of Land, R&R cost.(40322.00 Lakhs x 1%)
403.22
3 Annual operation and maintenance charge at Rs. 1175/ ha 190.86
4 Maintainance of the Head works at 1% its cost (Improvements to anicuts)
61.26
5 Total (E):Annual costs (1 to 4) 4703.78
BENEFITS COST RATIO = D 3 : Annual Benefits E.5: Annual cost
7740.50/4703.78 1.65
Chief Engineer KNNL, Irrigation Central Zone
Munirabad
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 66
MODERNISATION OF VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT
ESTIMATED VALUE OF PRODUCE BEFORE MODERNISATION
Crop % Area Area Ha
Produce (Qtls/Ha)
Rate per Qtl.
(Rs)
Value of produce
( Rs lakhs)
Input Seed Manure (Input) Hired Labour (Human & bullock)
Quantity Kg/Ha
Rate Rs/Kg
Amount (Rs
Lakhs)
Rate Rs/Ha
Amount (Rs Lakhs)
20% of total value of produce (Rs Lakhs)
1 2 3 4 5 6 7 8 9 10 11 12
Khariff
Paddy 30.90 4056 60 1979.00 4815.65 60.00 24 58.40 40000 1622.25 963.13
Hy. Jowar 5.60 735 20 2615.00 384.41 60.00 24 10.58 23000 169.05 76.88
Rabi
Paddy 13.90 1824 60 1979.00 2166.26 60.00 24 26.27 40000 729.75 433.25
Groundnut 14.50 1903 20 6009.00 2287.18 100.00 41 78.03 23000 437.72 457.44
Bi seasonal
Sugarcane 24.20 3176 60 2540.00 4840.61 7500.00 3 714.66 39000 1238.74 968.12
Garden (Banana) 10.90 1431 100 2000.00 2861.25 2250.00 5 160.95 68000 972.83 572.25
TOTAL 100.00 13125 17355.35 1048.89 5170.33 3471.07
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 67
MODERNISATION OF VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT
ESTIMATED VALUE OF PRODUCE AFTER MODERNISATION
Crop % Area Area Ha
Produce (Qtls/Ha)
Rate per Qtl. (Rs)
Value of produce
( Rs lakhs)
Input Seed Manure (Input) Hired Labour (Human & bullock)
Quantity Kg/Ha
Rate Rs/Kg
Amount (Rs
Lakhs)
Rate Rs/Ha
Amount (Rs Lakhs)
20% of total value of
produce (Rs Lakhs)
1 2 3 4 5 6 7 8 9 10 11 12
Khariff
Paddy 14.18 2304 75.0 1979.00 3419.71 60.00 24 33.18 30000 691.20 683.94
Hy. Jowar 38.95 6326 50.0 2615.00 8271.11 60.00 24 91.09 20000 1265.18 1654.22
Rabi
Paddy 10.19 1655 75.0 1979.00 2456.43 60.00 24 23.83 30000 496.50 491.29
Groundnut 23.12 3755 25.0 6009.00 5640.80 100.00 41 153.95 22000 826.08 1128.16
Bi seasonal
Sugarcane 7.57 1229 120.0 2540.00 3745.38 7500.00 3 276.48 36000 442.37 749.08
Garden (Banana) 6.00 974 120.0 2000.00 2337.12 2250.00 5 109.55 60000 584.28 467.42
TOTAL 100.00 16243 25870.56 688.09 4305.61 5174.11
Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project
Detailed Project Report 68
Conclusion
The Vijayanagara channels comprising of 16 channels are in existence for over 400 years. These channels
are very old and unlined. Due to lack of adequate maintenance, the channels have lost their shape and the
infrastructure is a bad state. Tail end farmers are not getting adequate water. This is resulting in inequity, low
productivity. There is dire need to modernize the channels for bringing down the over utilization in a scientific
way and for improving water delivery service (reliability, flexibility and equity). Furthermore, due to many
factors such as unlined channels, excessive seepage losses, over use of water, cropping pattern etc, the
existing channel system is utilizing excess water for irrigation. The master plan of 2003 has recommended
modernizing these channels thereby effectively bringing down the utilisation.
The report is prepared considering the above factors and proposal with estimate is prepared with the
objective to bring down the utilisation from 12.05 TMC. It is now seen that, on modernization and reworking
out crop water requirements as per Modified Penman Method, there is a savings of 6.25 TMC.
The total cost of proposed modernization is Rs. 403.22 Crores based on current WRD Bangalore SR of
2013-14 & PWD Bellary Circle SR of 2013-14 and the B.C. ratio works out to 1.65. Hence the project is
technically and financially viable. The DPR is submitted for administrative approval and technical sanction.
Chief Engineer KNNL, Irrigation Central Zone
Munirabad
UNIT I
Headworks
(Anecuts)
UNIT II
Canal
Works
Total
I
1 A - Preliminaries 174.59 174.59
2 B - Land - -
3 C - Works 6126.33 - 6126.33
4 D - Regulator 2919.56 2919.56
5 E - Falls 152.27 152.27
6 F - Cross Drainage Works 912.10 912.10
7 G - Bridges 1960.48 1960.48
8 H - Escapes 561.84 561.84
9 I - Navigation works - -
10 J - Power plants and Civil Works - -
11 K - Buildings 155.00 155.00
12 L - Earthwork
L1 - Lining 20621.53 20621.53
L2 - Service Road
13 M - Plantation 67.95 67.95
14 N - Tank and Reservoirs - -
15 O - Miscellaneous - -
16P - Maintenance (1% of cost of I - works except A,B,M,O,Q
and X)61.26 330.15 391.41
17 Q - Special Tools and plants 40.46 40.46
18 R - Communication - -
19 S - Power plant and Electrical systems - -
20 T - Watersupply works - -
21 U - Distributories and Minors 5454.41 5454.41
22 V - Water Courses and Field Channels - -
23 W - Drainage 277.76 277.76
24 X - Environment and Ecology - -
25Y - Loss of stocks and unforseen (0.25% of cost of I - works
except A,B,M,O,Q and X)15.32 82.54 97.85
Total of I - Works 6202.91 33710.64 39913.55
Direct Charges of Works
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
ABSTRACT COST FOR MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA
PROJECT
Sl. No Particulars
(Rs. In Lakhs)
UNIT I
Headworks
(Anecuts)
UNIT II
Canal
Works
Total Sl. No Particulars
(Rs. In Lakhs)
II Establishment charges -
III Small Tools & Plants 9.12 9.12
IV Suspens - -
V Reciepts & Recoveries on capital accounts deductions - -
Total Direct charges 6202.91 33719.76 39922.67
INDIRECT CHARGES
b)Audit and Account charges (1% of cost of I works) 62.03 337.20 399.23
Total Indirect charges 62.03 337.20 399.23
TOTAL DIRECT AND INDIRECT CHARGES 6264.94 34056.96 40321.89
Grand Total Say Rs 403.22 Crores
Chief Engineer KNNL, Irrigation Central Zone
Munirabad
(Rs. In Lakhs)
UNIT I
Headworks (Anecuts)
I
1 A - Preliminaries
2 B - Land
3 C - Works 6126.33
4 D - Regulator
5 E - Falls
6 F - Cross Drainage Works
7 G - Bridges
8 H - Escapes
9 I - Navigation works
10 J - Power plants and Civil Works
11 K - Buildings
12 L - Earthwork
L1 - Lining
L2 - Service Road
13 M - Plantation
14 N - Tank and Reservoirs
15 O - Miscellaneous
16 P - Maintenance (1% of cost of I - works except A,B,M,O,Q and X) 61.26
17 Q - Special Tools and plants
18 R - Communication
19 S - Power plant and Electrical systems
20 T - Watersupply works
21 U - Distributories and Minors
22 V - Water Courses and Field Channels
23 W - Drainage
24 X - Environment and Ecology
25Y - Loss of stocks and unforseen (0.25% of cost of I - works except
A,B,M,O,Q and X)15.32
Total of I - Works 6202.91
Direct Charges of Works
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
ABSTRACT COST FOR MODERNISATION OF VIJAYANAGARA CHANNELS IN
TUNGABHADRA PROJECT
Sl. No Particulars
(Rs. In Lakhs)
UNIT I
Headworks (Anecuts)
Sl. No Particulars
II Establishment charges
III Small Tools & Plants
IV Suspens
V Reciepts & Recoveries on capital accounts deductions
Total Direct charges 6202.91
INDIRECT CHARGES
b)Audit and Account charges (1% of cost of I works) 62.03
Total Indirect charges 62.03
TOTAL DIRECT AND INDIRECT CHARGES 6264.94
Sl
No.Description
Amount
Rs in Lakhs
Improvements to anicuts
1 Bella Channel 386.33
2 Turtha Channel 915.86
3 Ramasagara Channel 538.61
4 Kampli Channel 425.28
5 Deshnur Channel 561.40
6 Siruguppa Channel 248.18
7 Hulugi Channel 318.78
8 Anegundi Channel 265.38
9 Upper Gangavathi Channel 1352.52
10 Lower Gangavathi Channel 532.85
11 Bichal Channel 581.15
Total Rs 6126.33 Lakhs
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
C-WORKS
ABSTRACT
COST OF C-WORKS: Rs.6126.33 LAKHS
Sl.No Particulars Amount in Rupees Remarks
1Improvements to Hosur Anicut by provision of
skin walls3,69,39,330/-
2 Approach road to Hosur anicut 7,25,540/-
3 Coffer dam 9,68,497/-
TOTAL 3,86,33,367/-
386.33 Lakhs
2. Remodelling of Turtha Anicut
1 Improvements to Turtha Anicut 8,72,98,143/-
Details enclosed Refer
Volume-III of Annexure-1,
Page No.3
2 Construction of Coffer Dam 14,10,084/-
Details enclosed Refer
Volume-III of Annexure-1,
Page No.7
3 Construction of Approach Road 28,77,361/-
Details enclosed Refer
Volume-III of Annexure-1,
Page No.12
TOTAL 9,15,85,588/-
915.86 Lakhs
1 Improvements to Anicut 4,98,28,135/-
2 Construction of Coffer Dam 14,35,111/-
3 Construction of Approach Road 25,97,503/-
TOTAL 5,38,60,748/-
538.61 Lakhs
1 Improvements to Kampli Anicut 3,95,17,060/-
2 Construction of Coffer Dam 10,12,262/-
3 Construction of Approach Road 19,98,198/-
TOTAL 4,25,27,520/-
425.28 Lakhs
1 Improvements to Deshnur Anicut 5,47,32,203/-
2 Construction of Coffer Dam 14,07,370/-
TOTAL 5,61,39,573/-
561.40 Lakhs
1 Improvements to Siruguppa Anicut 2,41,09,418/-
2 Coffer dam 7,08,435/-
TOTAL 2,48,17,853/-
248.18 Lakhs
C-WORKS
5. Remodelling of Structures under Deshnur Channel
6. Remodelling of Structures under Siruguppa Channel
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
1. Remodelling of Structures under Bella Channel
3. Remodelling of Structures under Ramasagara Channel
4. Remodelling of Structures under Kampli Channel
Sl.No Particulars Amount in Rupees Remarks
1 Improvements to Hulugi Anicut 80,89,585/-
2 Construction of Coffer Dam 6,66,336/-
3Improvements to existing walls of the
Approach canal1,38,71,094/-
4Reconstruction of Hulugi anecut (Breached
portion) 70,24,303/-
5 Improvements to Hulugi Balancing Anicut 22,27,168/-
TOTAL 3,18,78,487/-
318.78 Lakhs
1 Improvements to Sanapur Anicut 2,55,39,606/-
2 Coffer dam 9,98,147/-
TOTAL 2,65,37,753/-
265.38 Lakhs
1 Improvements to Upper Gangavati Anicut 13,10,52,428/-
2 Construction of Coffer Dam 13,30,862/-
3 Construction of Approach Road 28,69,201/-
TOTAL 13,52,52,491/-
1352.52 Lakhs
1 Improvements to Lower Gangavathi Anicut 3,66,70,000/-
2Improvements to Lower Gangavathi Approch
Anicut1,11,49,901/-
3 Construction of side Wall to Approch Channel 37,47,075/-
4Construction of Causeway near Gangavathi
Lower anicut 10,12,653/-
5Construction of Coffer Dam for Approch
Anicut 1,17,507/-
6Construction of Coffer Dam for Gangavathi
Anicut 5,87,535/-
TOTAL 5,32,84,670/-
532.85 Lakhs
1 Improvements to Bichal Anicut 5,71,04,158/-
2 Construction of Coffer Dam 10,10,560/-
TOTAL 5,81,14,718/-
581.15 Lakhs
7. Remodelling of Structures under Hulugi Channel
8. Remodelling of Structures under Anegundi Channel
10. Remodelling of Structures under Lower Gangavathi Channel
11. Remodelling of Structures under Bichal Channel
9. Remodelling of Structures under Upper Gangavathi Channel
Amount
(Rs. In Lakhs)
UNIT I
Headworks (Anecuts)
I Direct Charges of Works
1 P - ` (1% of cost of I - works except A,B,M,O,Q and X) 61.26
Particulars
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
UNIT – I
P – MAINTENANCE
Sl. No
Amount
(Rs. In Lakhs)
UNIT I
Headworks (Anecuts)
1Y - Loss of stocks and unforseen (0.25% of cost of I - works except
A,B,M,O,Q and X)15.32
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
UNIT – I
Y – LOSS OF STOCKS AND UNFORSEEN
Sl. No Particulars
Amount
(Rs. In Lakhs)
UNIT II
Canal Works
I Direct Charges of Works
1 A - Preliminaries 174.59
2 B - Land -
3 C - Works -
4 D - Regulator 2919.56
5 E - Falls 152.27
6 F - Cross Drainage Works 912.10
7 G - Bridges 1960.48
8 H - Escapes 561.84
9 I - Navigation works -
10 J - Power plants and Civil Works -
11 K - Buildings 155.00
12 L - Earthwork
L1 - Lining 20621.53
L2 - Service Road
13 M - Plantation 67.95
14 N - Tank and Reservoirs -
15 O - Miscellaneous -
16P - Maintenance (1% of cost of I - works except A,B,M,O,Q and
X)330.15
17 Q - Special Tools and plants 40.46
18 R - Communication -
19 S - Power plant and Electrical systems -
20 T - Watersupply works -
21 U - Distributories and Minors 5454.41
22 V - Water Courses and Field Channels -
23 W - Drainage 277.76
24 X - Environment and Ecology -
25Y - Loss of stocks and unforseen (0.25% of cost of I - works
except A,B,M,O,Q and X)82.54
Total of I - Works 33710.64
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
ABSTRACT COST FOR MODERNISATION OF VIJAYANAGARA CHANNELS IN
TUNGABHADRA PROJECT
Sl. No Particulars
Amount
(Rs. In Lakhs)
UNIT II
Canal Works
Sl. No Particulars
II Establishment charges
III Small Tools & Plants 9.12
IV Suspens -
V Reciepts & Recoveries on capital accounts deductions -
Total Direct charges 33719.76
INDIRECT CHARGES
b)Audit and Account charges (1% of cost of I works) 337.20
Total Indirect charges 337.20
TOTAL DIRECT AND INDIRECT CHARGES 34056.96
Sl.
No.Description
Amount
Rs in LakhsRemarks
a
Consultancy charges for Detailed Survey, Investigation, Preparation of
designs, drawings and estimates for modernisation of Vijayanagar
Channels(Rs 74.88 Lakhs+ Tax @ 10.3 % Rs 7.71 lakhs) 82.59
Copy of
Agreement and
Shedule B
enclosed
bConsultancy charges for Preparation of Detailed Project Report as per
Central Water Commission Guidelines - 2010 19.50Quotation
enclosed
c Consultancy charges for Detailed Survey For Preparation Of Command
Area Maps, GIS Mapping For Vijayanagar Channels Command Area
72.50Quotation
enclosed
dConsultancy charges for Cost of Project Management Consultancy and
Quality Control 0.00
TOTAL 174.59
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
A -PRELIMINARIES
COST OF A-PRELIMINARIES : Rs.174.59 LAKHS
Sl.
No.Description Unit QTY
Rate
( Rs. Ps.)
Amount
( Rs. Ps.)
1 a.Concept planning
Preparation of detailed concept planning for
modernisation of vijayanagara channels including revised
hydrology,irrigation planning etc. as per guidelines of
CWC
Km 212 12000.00 25,44,000/-
2 b.Alignment / Strip survey for the main canal
Detailed survey of existing main canal km wise by taking
L section levels at 30mts interval and including alignment
plan,apex details,location of CD works. Cross sections at
30mt interval, with levels at 5mt intervl or at closer
intervals in order to describe the true shape of the
canal.Levels will be taken for a width of 15mt on either
side of main canal duly superimposing the approved
hydraulic section as per CBL and bed gradient.
3 Design and Estimates
Preparation of detailed designs, drawings, cost estimates
and DTP for modernisation main canals, branch canals
including structures as per approved concept planning for
Vijayanagara channels.
Km 212 12000.00 25,44,000/-
4 Detailed survey of distribution system (excluding FIC's)
including taking L section, and cross sections,preparation
of detailed design,drawings,cost estimates and DTP for
modernisation of distribution networks under vijayanagara
channels as per approved concept planning and to
provide irrigation facility to 16222 Ha of command area.
Km 200 12000.00 24,00,000/-
74,88,000/-
74.88 Lakhs
7,71,264/-
Rs 82.59 LakhsTotal =
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
A -PRELIMINARIES
Sub Total =
Add service tax at 10.3% as per GoI norms =
I. Detailed Survey, Investigation, Preparation of designs, drawings and estimates for modernisation of
Vijayanagar Channels
DISTRIBUTION NETWORK
Sl.
No.Description Unit QTY
Rate
( Rs. Ps.)
Amount
( Rs. Ps.)
1 Preparation of DPR in bound volumes and submitting to
MoWR/Central Water Commission for scrutiny at various
directorates
Set 15 5,000.00 75,000/-
2 Preparation of Km wise estimates of Main canal (216
Kms.) and Km wise estimates of Distributaries and minors
covering command area of 1,120 Ha (27 Kms), which is
10% of total command area, as deliberated in DPR, to
cost appraisal committee,
consisting of 216 Main canal Booklets and 27 Distributary
and Minors Booklets
Set 1 150000.00 1,50,000/-
3 Attend to the Comments & Observations of Central Water
Commission (CWC), Ministry of Water Resources
(MoWR) during Scrutiny of Detailed Project Report by
Concerned specialized directorates of CWC, CSMRS,
Central Water Board, Ministry of Agriculture (Crop
Division) & other connected departments of Govt. of India.
Attend to the Comments and Compliance/Observations
including Submission of Compliance/Clarification etc., and
finally get acceptance of Technical Advisory Committee of
MoWR/CWC.
Job 1 1400000.00 14,00,000/-
4 Submission of 10 sets of hard copies and 2 sets of soft
copies for record purpose after approval of CWC.Job 1 325000.00 3,25,000/-
19,50,000/-
19.50 Lakhs
Sub Total =
Note: Copy of quotation received from E I Technologies Pvt. Ltd. Bangalore is enclosed.
II. Preparation of Detailed Project Report as per Central Water Commission Guidelines -
Sl.
No.Description Unit QTY
Rate
( Rs. Ps.)
Amount
( Rs. Ps.)
1
Topographical survey of the Gross Command area of
Tungabhadra Project including demarcation of Main
Canal, Distributary Network, FIC network already
executed, preparation of C-planning map,
identification of realignment of canals required if any,
preparation of contours at 0.50 m interval,
mosaicking the village maps falling under the
command area and superimposing the topographical
contour/ C- planning map on th same, preparation of
Tree plan and hydraulic flow diagrams and other
data for GIS mapping, identification of reaches for
introducing Micro-Irrigation in the command area,
formation of WUC's, agriculture measures etc as
required for the scheme. Preparation of maps shall
also contain following details
Ha 11154.0 650.00 72,50,100/-
Establishing of Ground Control (GCP's) using
DGPS.
Survey number aqnd Hissa number of land
Total land under the pahani.
Land Revenue details.
Land owner's name with Extent's and Khatha
number.
The way land is acquired by the owner
Government / Public rights on the land.
Liabilities of the owners on the land.
Classification of the soil.
Number of Trees.
Source of irrigation and area irrigated.
Cultivators Details.
Utilization of land under Various categories.
Details crops grown season wise.
Details mixed crops.
Canal network as GIS layer File.
GPS Survey to be conducted to identify FIC network
upto distributory level with accuracy of + 5m.The structures to be identified as per tree plan
spatial on the ground along the canal such as DPO's Features of the Canal, Design Details of the
structures and canal to be attached to attribute data Developing database for the command area.
Land parcel wise attribute information to be attached
to the respective parcels.
The Scale of the output maps would be around
1:50000 ( + 12m accuracy) and reduced to + 5M
accuracy maps.
III. DETAILED SURVEY FOR PREPARATION OF COMMAND AREA MAPS, GIS MAPPING FOR VIJAYANAGAR
CHANNELS COMMAND AREA
Sl.
No.Description Unit QTY
Rate
( Rs. Ps.)
Amount
( Rs. Ps.)
Not only the gross command but also cultivable
command area can be authentically brought into
records by this management system.
Suffering atchkiats can be reorganized by balancing
excess and deficit water.3. Bore wells location GPS survey in the command.
4. Balancing Reservoirs/MI Tanks data with
attributes in the command.
72,50,100/-
72.50 Lakhs
Sub Total =
Note: Copy of quotation received from E I Technologies Pvt. Ltd. Bangalore is enclosed.
Sl
No.Description
Amount
Rs in Lakhs
Construction of Regulators and Measuring Device Coming
under entire Vijayanagar Channel system(16 Nos.)
1 Raya Channel 375.36
2 Basavanna Channel 259.32
3 Bella Channel 125.52
4 Kalaghatta Channel 172.92
5 Turtha Channel 244.55
6 Ramasagara Channel 216.48
7 Kampli Channel 190.26
8 Belagodhalla Channel 117.25
9 Deshnur Channel 92.85
10 Siruguppa Channel 70.40
11 Hulugi Channel 243.68
12 Shivapura Channel 116.03
13 Anegundi Channel 289.40
14 Upper Gangavathi Channel 157.06
15 Lower Gangavathi Channel 193.86
16 Bichal Channel 54.62
2919.56 Lakhs
COST OF D-REGULATORS: Rs.2919.56 LAKHS
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
D-REGULATORS
ABSTRACT
TOTAL
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1Dismantling and Reconstruction of CR with
drop0 .000 95,07,200/-
2 Construction of Measuring Device 0.8 10,32,472/-
3 Dismantling and Reconstruction of DPO 1 .298 5,37,273/-
4 Dismantling and Reconstruction of DPO 1 .416 5,37,273/-
5 Dismantling and Reconstruction of DPO 2 .398 5,37,527/-
6 Dismantling and Reconstruction of DPO 2 .497 5,37,527/-
7 Dismantling and Reconstruction of DPO 2 .646 5,37,527/-
8 Dismantling and Reconstruction of DPO 2 .792 5,37,527/-
9 Dismantling and Reconstruction of DPO 2 .871 5,37,527/-
10 Dismantling and Reconstruction of DPO 2 .964 5,37,527/-
11 Dismantling and Reconstruction of DPO 3 .198 6,40,413/-
12 Dismantling and Reconstruction of DPO 3 .274 6,40,413/-
13 Dismantling and Reconstruction of DPO 3 .426 6,40,413/-
14 Dismantling and Reconstruction of DPO 3 .875 6,40,413/-
15 Dismantling and Reconstruction of DPO 5 .572 5,33,332/-
16 Dismantling and Reconstruction of DPO 5 .665 5,33,332/-
17 Dismantling and Reconstruction of DPO 5 .750 5,33,332/-
18 Dismantling and Reconstruction of DPO 5 .857 5,33,332/-
19 Dismantling and Reconstruction of DPO 6 .385 3,93,083/-
Details enclosed Refer
Volume-III of Annexure-2,
Page No.30
20 Dismantling and Reconstruction of DPO 6 .493 3,95,899/-
21 Dismantling and Reconstruction of DPO 6 .671 3,95,899/-
22 Dismantling and Reconstruction of DPO 6 .769 3,95,899/-
23 Dismantling and Reconstruction of DPO 6 .937 3,95,899/-
24 Dismantling and Reconstruction of DPO 7 .171 4,43,536/-
25 Dismantling and Reconstruction of DPO 7 .778 4,43,536/-
26 Dismantling and Reconstruction of DPO 8 .090 3,95,029/-
27 Dismantling and Reconstruction of DPO 8 .251 3,95,029/-
28 Dismantling and Reconstruction of DPO 10 .845 5,13,007/-
29 Dismantling and Reconstruction of DPO 11 .150 5,14,612/-
30 Dismantling and Reconstruction of DPO 11 .360 5,14,612/-
31 Dismantling and Reconstruction of DPO 12 .032 5,14,459/-
32 Dismantling and Reconstruction of DPO 12 .704 5,14,459/-
33 Dismantling and Reconstruction of DPO 13 .588 5,63,709/-
34 Dismantling and Reconstruction of DPO 14 .702 5,61,170/-
35 Dismantling and Reconstruction of DPO 15 .433 5,61,440/-
36 Dismantling and Reconstruction of DPO 16 .946 5,61,705/-
37 Dismantling and Reconstruction of DPO 17 .307 5,62,974/-
1. Remodelling of Structures under Raya Channel
D- REGULATORS / DIRECT PIPE OUTLETS ( DPOs)
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
38 Dismantling and Reconstruction of DPO 17 .780 5,62,974/-
39 Dismantling and Reconstruction of DPO 18 .499 5,62,782/-
40 Dismantling and Reconstruction of DPO 18 .884 5,28,473/-
41 Dismantling and Reconstruction of DPO 19 .377 5,28,473/-
42 Dismantling and Reconstruction of DPO 19 .850 5,28,473/-
43 Dismantling and Reconstruction of DPO 20 .590 5,29,451/-
44 Construction of DPO 21 .294 5,29,112/-
45 Construction of DPO 22 .104 5,62,401/-
46 Dismantling and Reconstruction of DPO 22 .725 5,62,401/-
47 Dismantling and Reconstruction of DPO 23 .883 5,62,401/-
48 Dismantling and Reconstruction of DPO 23 .900 5,62,401/-
49 Dismantling and Reconstruction of DPO 24 .270 5,63,021/-
50 Dismantling and Reconstruction of DPO 24 .929 5,63,021/-
51 Dismantling and Reconstruction of DPO 25 .348 4,54,293/-
52 Dismantling and Reconstruction of DPO 25 .960 4,54,293/-
53 Dismantling and Reconstruction of DPO 26 .330 4,55,780/-
54 Dismantling and Reconstruction of DPO 26 .340 4,55,780/-
TOTAL 3,75,35,850/-
375.36 Lakhs
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1Dismantling and Reconstruction of Cross
Regulator0.000 29,07,145/-
2 Dismantling and Reconstruction of DPO 0.276 4,98,744/-
3 Construction of Measuring Device 0.500 3,57,464/-
4 Dismantling and Reconstruction of DPO 0.719 4,97,485/-
5Dismantling and Reconstruction Head regulator
1.343 6,68,144/-
6 Dismantling and Reconstruction of DPO 2.932 4,97,520/-
7 Dismantling and Reconstruction of DPO 3.603 4,98,515/-
8 Dismantling and Reconstruction of DPO 3.610 4,18,248/-
9Dismantling and Reconstruction of Cross
Regulator4.716
13,45,492/-
10 Dismantling and Reconstruction of DPO 5.200 5,78,782/-
11 Dismantling and Reconstruction of DPO 5.643 5,78,782/-
12 Dismantling and Reconstruction of DPO 6.800 5,78,782/-
13 Dismantling and Reconstruction of DPO 7.350 5,78,782/-
14 Dismantling and Reconstruction of DPO 8.155 5,78,782/-
15 Dismantling and Reconstruction of DPO 11.190 5,78,782/-
16 Dismantling and Reconstruction of DPO 11.486 5,78,782/-
17 Dismantling and Reconstruction of DPO 12.827 4,98,782/-
18 Dismantling and Reconstruction of DPO 13.094 4,98,782/-
19 Dismantling and Reconstruction of DPO 13.285 4,98,782/-
20 Dismantling and Reconstruction of DPO 13.289 4,98,782/-
21 Dismantling and Reconstruction of DPO 13.408 4,98,782/-
22 Dismantling and Reconstruction of DPO 13.504 4,98,782/-
23 Dismantling and Reconstruction of DPO 13.604 4,98,782/-
24 Dismantling and Reconstruction of DPO 13.710 4,98,782/-
25 Dismantling and Reconstruction of DPO 13.812 4,98,782/-
26 Dismantling and Reconstruction of DPO 13.934 4,98,782/-
27 Dismantling and Reconstruction of DPO 14.203 4,98,782/-
28 Dismantling and Reconstruction of DPO 14.169 4,98,782/-
29 Dismantling and Reconstruction of DPO 14.236 4,98,782/-
30 Dismantling and Reconstruction of DPO 14.242 4,98,782/-
31 Dismantling and Reconstruction of DPO 14.417 4,98,782/-
32 Dismantling and Reconstruction of DPO 14.435 4,98,782/-
33 Dismantling and Reconstruction of DPO 14.689 4,98,782/-
34 Dismantling and Reconstruction of DPO 14.706 4,98,782/-
35 Dismantling and Reconstruction of DPO 14.960 4,98,782/-
36 Dismantling and Reconstruction of DPO 15.145 4,28,650/-
37 Dismantling and Reconstruction of DPO 15.341 4,28,650/-
2. Remodelling of Structures under Basavanna Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
38 Dismantling and Reconstruction of DPO 15.422 4,28,650/-
39 Dismantling and Reconstruction of DPO 15.520 4,28,650/-
40 Dismantling and Reconstruction of DPO 15.658 4,28,650/-
41 Dismantling and Reconstruction of DPO 15.766 4,28,650/-
42 Dismantling and Reconstruction of DPO 15.892 4,28,650/-
43 Dismantling and Reconstruction of DPO 15.970 4,28,650/-
44 Dismantling and Reconstruction of DPO 16.044 4,28,650/-
45 Dismantling and Reconstruction of DPO 16.226 4,28,650/-
46 Dismantling and Reconstruction of DPO 16.408 4,28,650/-
TOTAL 2,59,32,247/-
259.32 Lakhs
1 Dismantling and Reconstruction of CR 0.184 23,04,475/-
2 Construction of Measuring Device 0.430 5,89,428/-
3 Dismantle and Reconstruction of DPO 0.664 4,51,383/-
4 Construction of DPO 1.180 4,53,835/-
5 Construction of DPO 1.479 4,52,468/-
6 Dismantle and reconstruction of DPO 3.002 4,56,283/-
7 Dismantle and reconstruction of DPO 3.177 4,48,211/-
8Dismantling and Reconstruction of Head
Regulator3.281 12,15,804/-
9 Dismantle and reconstruction of DPO 3.912 4,56,283/-
10 Dismantling and Reconstruction of Offtake 4.240 21,21,659/-
11 Dismantling and Reconstruction of DPO 4.652 4,57,581/-
12 Dismantle and reconstruction of DPO 4.759 4,57,581/-
13 Dismantling and Reconstruction of DPO 4.853 4,57,581/-
14 Dismantling and Reconstruction of DPO 5.100 4,59,164/-
15 Dismantle and reconstruction of DPO 5.115 4,59,151/-
16 Dismantle and reconstruction of DPO 5.121 4,59,151/-
17Dismantling and Reconstruction of
Distribution Box5.550 8,51,921/-
TOTAL 1,25,51,961/-
125.52 Lakhs
3. Remodelling of Structures under Bella Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1Dismantling and Reconstruction of Offtake
cum CTC 0.014 25,00,680/-
2 Construction of Measuring Device 0.500 4,81,822/-
3 Dismantling and Reconstruction of DPO 1.351 4,92,632/-
4 Dismantling and Reconstruction of DPO 1.474 4,92,632/-
5 Dismantling and Reconstruction of DPO 2.215 4,92,723/-
6 Dismantling and Reconstruction of DPO 2.613 4,92,723/-
7 Dismantling and Reconstruction of DPO 2.805 4,91,356/-
8 Dismantling and Reconstruction of DPO 2.850 4,92,723/-
9 Dismantle and reconstruction of DPO 3.074 4,94,010/-
10 Dismantle and reconstruction of DPO 3.178 4,94,010/-
11 Dismantle and reconstruction of DPO 3.436 4,94,010/-
12 Dismantle and reconstruction of DPO 3.727 4,88,095/-
13 Dismantle and reconstruction of DPO 3.834 4,94,010/-
14 Dismantle and reconstruction of DPO 3.923 4,94,010/-
15 Dismantling and Reconstruction of DPO 4.072 4,93,317/-
16 Dismantling and Reconstruction of DPO 4.187 4,93,317/-
17 Dismantling and Reconstruction of DPO 4.305 4,93,317/-
18 Dismantling and Reconstruction of DPO 4.437 4,93,317/-
19 Dismantling and Reconstruction of DPO 4.658 4,92,234/-
20 Dismantling and Reconstruction of DPO 4.739 4,92,234/-
21 Dismantling and Reconstruction of DPO 4.837 4,93,317/-
22 Dismantling and Reconstruction of DPO 4.843 4,92,234/-
23 Dismantle and reconstruction of DPO 5.297 4,94,803/-
24 Dismantle and reconstruction of DPO 5.341 4,94,803/-
25 Dismantle and reconstruction of DPO 5.466 4,94,803/-
26 Dismantle and reconstruction of DPO 5.554 4,94,803/-
27 Dismantling and Reconstruction of DPO 6.110 4,94,803/-
28 Dismantling and Reconstruction of DPO 6.230 4,94,803/-
29 Dismantling and Reconstruction of DPO 6.250 4,94,803/-
30 Dismantling and Reconstruction of DPO 6.358 4,94,803/-
31 Dismantling and Reconstruction of DPO 6.516 4,94,803/-
TOTAL 1,72,91,953/-
172.92 Lakhs
4. Remodelling of Structures under Kalaghatta Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1 Dismantling and Reconstruction of CR 0.926 29,70,635/-
2 Construction of Measuring Device 0.500 5,53,638/-
Details enclosed Refer
Volume-III of Annexure-4,
Page No.123
3 Dismantling and Reconstruction of DPO 2.932 4,74,394/-
4 Dismantling and Reconstruction of DPO 3.603 4,74,488/-
5 Dismantling and Reconstruction of DPO 3.610 4,13,312/-
6 Dismantling and Reconstruction of CR 4.716 13,00,838/-
7 Dismantling and Reconstruction of DPO 5.200 5,51,299/-
8 Dismantling and Reconstruction of DPO 5.643 5,55,400/-
9 Dismantling and Reconstruction of DPO 6.800 5,56,493/-
10 Dismantling and Reconstruction of DPO 7.350 5,54,486/-
11 Dismantling and Reconstruction of DPO 8.155 5,54,748/-
12 Dismantling and Reconstruction of DPO 11.190 5,57,902/-
13 Dismantling and Reconstruction of DPO 11.486 5,57,902/-
14 Dismantling and Reconstruction of DPO 12.827 4,62,419/-
15 Dismantling and Reconstruction of DPO 13.094 4,64,460/-
16 Dismantling and Reconstruction of DPO 13.285 4,64,460/-
17 Dismantling and Reconstruction of DPO 13.289 4,64,460/-
18 Dismantling and Reconstruction of DPO 13.408 4,64,460/-
19 Dismantling and Reconstruction of DPO 13.504 4,64,460/-
20 Dismantling and Reconstruction of DPO 13.604 4,64,460/-
21 Dismantling and Reconstruction of DPO 13.710 4,64,460/-
22 Dismantling and Reconstruction of DPO 13.812 4,64,460/-
23 Dismantling and Reconstruction of DPO 13.934 4,64,460/-
24 Dismantling and Reconstruction of DPO 14.203 4,66,335/-
25 Dismantling and Reconstruction of DPO 14.169 4,66,335/-
26 Dismantling and Reconstruction of DPO 14.236 4,66,335/-
27 Dismantling and Reconstruction of DPO 14.242 4,66,335/-
28 Dismantling and Reconstruction of DPO 14.417 4,66,335/-
29 Dismantling and Reconstruction of DPO 14.435 4,66,335/-
30 Dismantling and Reconstruction of DPO 14.689 4,66,335/-
31 Dismantling and Reconstruction of DPO 14.706 4,66,335/-
32 Dismantling and Reconstruction of DPO 14.960 4,66,335/-
33 Dismantling and Reconstruction of DPO 15.145 3,99,361/-
34 Dismantling and Reconstruction of DPO 15.341 3,99,361/-
35 Dismantling and Reconstruction of DPO 15.422 3,99,361/-
36 Dismantling and Reconstruction of DPO 15.520 3,99,361/-
37 Dismantling and Reconstruction of DPO 15.658 3,99,361/-
38 Dismantling and Reconstruction of DPO 15.766 3,99,361/-
39 Dismantling and Reconstruction of DPO 15.892 3,99,361/-
40 Dismantling and Reconstruction of DPO 15.970 3,99,361/-
41 Dismantling and Reconstruction of DPO 16.044 3,98,757/-
42 Dismantling and Reconstruction of DPO 16.226 3,98,757/-
43 Dismantling and Reconstruction of DPO 16.408 3,98,757/-
44 Dismantling and Reconstruction of CR 17.577 11,48,679/-
TOTAL 2,44,54,946/-
244.55 Lakhs
5. Remodelling of Structures under Turtha Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1Dismantling and Reconstruction of Cross
regulator cum escape cum VRB0.000 39,83,909/-
2 Construction of Measuring Device 0.800 2,61,908/-
3 Construction of DPO 2.886 6,45,382/-
4 Construction of DPO 2.946 6,45,382/-
5 Dismantling and Construction of DPO 3.344 6,46,749/-
6 Dismantling and Construction of DPO 6.817 6,44,828/-
7 Construction of HR 6.973 7,34,061/-
Details enclosed Refer
Volume-III of Annexure-5,
Page No.139
8 Construction of DPO 7.099 4,36,921/-
9 Dismantling and Construction of DPO 7.399 4,38,288/-
10 Dismantling and Construction of DPO 7.749 4,36,921/-
11 Construction of DPO 8.030 4,35,293/-
12 Construction of DPO 8.283 4,35,293/-
13 Construction of DPO 8.344 4,35,293/-
14 Construction of DPO 8.413 4,35,293/-
15 Construction of DPO 9.805 4,34,982/-
16 Dismantling and Construction of DPO 10.238 4,35,036/-
17 Dismantling and Construction of DPO 10.495 4,35,036/-
18 Dismantling and Construction of DPO 10.667 4,35,036/-
19 Dismantling and Construction of DPO 10.901 4,35,036/-
20 Construction of DPO 11.264 4,34,208/-
21 Construction of DPO 11.800 4,34,208/-
22 Construction of DPO 12.100 4,33,622/-
23 Construction of DPO 12.419 4,33,622/-
24 Construction of DPO 12.472 4,33,622/-
25 Construction of DPO 12.651 4,33,622/-
26 Construction of DPO 13.020 6,23,165/-
27 Construction of DPO 13.549 6,23,165/-
28 Construction of DPO 13.648 6,23,165/-
29 Construction of DPO 13.912 6,23,165/-
30 Construction of DPO 13.994 6,23,165/-
31 Construction of DPO 14.750 6,23,165/-
32Dismantling and Reconstruction of Cross
regulator cum CTC15.386 25,15,064/-
TOTAL 2,16,47,602/-
216.48 Lakhs
6. Remodelling of Structures under Ramasagara Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1Dismantling and Reconstruction of CR cum
CTC 0.000 23,64,666/-
2 Construction of Measuring Device 0.500 4,34,698/-
3 Construction of DPO 0.680 4,40,042/-
4 Construction of DPO 1.540 4,29,800/-
5 Dismantling and Reconstruction of DPO 1.628 4,31,167/-
6 Construction of DPO 1.760 4,29,800/-
7 Construction of DPO 1.866 4,29,800/-
8 Construction of DPO 1.940 4,29,800/-
9 Construction of DPO 2.050 4,46,826/-
10 Dismantling and Reconstruction of DPO 2.162 4,41,888/-
11 Construction of DPO 3.360 4,48,404/-
12 Construction of DPO 3.510 4,48,404/-
13 Construction of DPO 3.650 4,48,404/-
14 Construction of DPO 3.830 4,48,404/-
15 Construction of DPO 3.980 4,48,404/-
16 Construction of DPO 5.660 4,47,450/-
17 Construction of DPO 6.050 4,46,953/-
18 Construction of DPO 6.470 4,46,953/-
19 Construction of DPO 6.950 4,46,953/-
20 Construction of DPO 7.450 4,63,555/-
21 Construction of DPO 7.830 4,63,555/-
22 Construction of DPO 7.950 4,63,555/-
23 Dismantling and Reconstruction of DPO 8.015 4,45,869/-
24 Construction of DPO 9.240 4,39,583/-
25 Construction of DPO 9.710 4,39,583/-
26 Construction of DPO 10.050 4,44,038/-
27 Construction of DPO 10.420 4,44,038/-
28 Construction of DPO 11.650 4,43,229/-
29 Construction of DPO 12.035 3,62,021/-
30 Construction of DPO 13.650 4,43,269/-
31 Construction of DPO 14.450 3,96,457/-
32 Construction of DPO 14.960 3,96,457/-
33 Construction of DPO 15.620 4,11,172/-
34 Construction of DPO 15.630 4,11,172/-
35 Construction of DPO 16.088 3,25,184/-
36 Construction of DPO 16.330 3,25,184/-
37 Construction of DPO 20.780 3,98,977/-
38 Dismantling and Reconstruction of DPO 21.452 4,00,867/-
39 Construction of DPO 21.960 3,99,500/-
40 Construction of DPO 22.350 3,99,438/-
TOTAL 1,90,25,516/-
190.26 Lakhs
7. Remodelling of Structures under Kampli Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1 Construction of DPO 0.430 3,96,097/-
2 Construction of Measuring Device 0.500 3,49,968/-
3 Dismantle and Reconstruction of DPO 0.526 3,96,985/-
4 Construction of DPO 0.835 3,96,097/-
5 Construction of DPO 1.350 3,94,577/-
6 Construction of DPO 2.310 3,87,003/-
7 Construction of DPO 2.920 3,87,003/-
8 Construction of DPO 3.170 3,91,924/-
9 Dismantle and Reconstruction of DPO 3.309 3,93,291/-
10 Construction of DPO 3.460 3,91,924/-
11 Construction of DPO 3.610 3,91,924/-
12 Dismantle and Reconstruction of DPO 3.744 3,93,291/-
13 Dismantle and Reconstruction of DPO 3.796 3,93,291/-
14 Dismantle and Reconstruction of DPO 3.919 3,93,291/-
15 Construction of DPO 4.500 3,91,924/-
16 Construction of DPO 5.120 3,91,399/-
17 Dismantle and Reconstruction of DPO 5.257 3,92,766/-
18 Dismantle and Reconstruction of DPO 5.323 3,92,766/-
19 Construction of DPO 5.730 3,91,399/-
20 Construction of DPO 5.940 3,91,399/-
21 Construction of DPO 6.020 3,90,710/-
22 Dismantle and Reconstruction of DPO 6.141 3,92,077/-
23 Construction of DPO 6.650 3,90,710/-
24 Construction of DPO 6.950 3,90,710/-
25 Construction of DPO 7.070 3,91,435/-
26 Construction of DPO 7.450 3,91,435/-
27 Construction of DPO 8.020 3,91,634/-
28 Construction of DPO 8.550 3,91,634/-
29 Construction of DPO 8.880 3,91,634/-
30 Construction of DPO 10.850 3,94,649/-
TOTAL 1,17,24,946/-
117.25 Lakhs
8. Remodelling of Structures under Belgodhalla Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1 Construction of Measuring Device 0.51 1,69,525/-
2Dismantling and Reconstruction of Cross
Regulator 1.51
12,39,299/-
3 Dismantling and Reconstruction of DPO 1.53 3,62,709/-
4Dismantling and Reconstruction of Cross
Regulator 2.235
12,35,057/-
5 Dismantling and Reconstruction of DPO 2.76 3,82,979/-
6 Dismantling and Reconstruction of DPO 2.955 3,82,979/-
7 Dismantling and Reconstruction of DPO 3.405 3,59,858/-
8Dismantling and Reconstruction of Cross
Regulator 3.63 7,58,864/-
9Dismantling and Reconstruction of Cross
Regulator 3.75 7,58,864/-
10 Dismantling and Reconstruction of DPO 4.095 3,56,368/-
11 Dismantling and Reconstruction of DPO 4.68 3,56,368/-
12 Dismantling and Reconstruction of DPO 4.715 3,56,368/-
13 Dismantling and Reconstruction of DPO 5.12 3,55,917/-
14 Dismantling and Reconstruction of DPO 5.283 3,55,917/-
15 Dismantling and Reconstruction of DPO 5.658 3,55,917/-
16 Dismantling and Reconstruction of DPO 5.690 3,55,917/-
17 Dismantling and Reconstruction of DPO 6.455 3,57,129/-
18 Dismantling and Reconstruction of DPO 7.210 3,92,358/-
19 Dismantling and Reconstruction of DPO 7.260 3,92,358/-
TOTAL 92,84,750/-
92.85 Lakhs
1 Construction of Measuring Device 0.210 2,43,632/-
2 Construction of DPO-1 0.762 3,39,836/-
3 Construction of DPO-2 0.824 3,39,836/-
4Dismantling and Reconstruction of Cross
Regulator3.060 20,66,016/-
5 Construction of Cross Regulator 4.700 15,11,739/-
6 Construction of Cross Regulator 6.345 12,69,585/-
7Dismantling and Reconstruction of Cross
Regulator6.705 12,69,585/-
TOTAL 70,40,230/-
70.40 Lakhs
9. Remodelling of Structures under Deshnur Channel
10. Remodelling of Structures under Siruguppa Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1Dismantling and Reconstruction of Measuring
Device0.510 57,337/-
2 Dismantling and Reconstruction of DPO 1.317 4,85,397/-
3 Dismantling and Reconstruction of DPO 1.410 4,85,397/-
4 Dismantling and Reconstruction of DPO 1.805 4,85,397/-
5 Dismantling and Reconstruction of DPO 1.901 4,85,397/-
6 Dismantling and Reconstruction of DPO 1.976 4,85,397/-
7 Dismantling and Reconstruction of DPO 2.108 4,50,295/-
8 Dismantling and Reconstruction of DPO 2.320 4,50,295/-
9 Dismantling and Reconstruction of DPO 2.812 4,50,295/-
10 Dismantling and Reconstruction of DPO 3.076 4,50,767/-
11 Dismantling and Reconstruction of DPO 3.186 4,50,767/-
12 Dismantling and Reconstruction of DPO 3.350 4,50,767/-
13 Dismantling and Reconstruction of DPO 3.460 4,50,767/-
14 Dismantling and Reconstruction of DPO 3.587 4,50,767/-
15 Dismantling and Reconstruction of DPO 3.670 4,50,767/-
16 Dismantling and Reconstruction of DPO 3.798 4,50,767/-
17 Dismantling and Reconstruction of DPO 4.095 4,96,407/-
18 Dismantling and Reconstruction of DPO 4.191 4,96,407/-
19 Dismantling and Reconstruction of DPO 4.266 4,96,407/-
20 Dismantling and Reconstruction of DPO 4.480 4,96,407/-
21 Dismantling and Reconstruction of DPO 4.615 4,96,407/-
22 Dismantling and Reconstruction of DPO 4.767 4,96,407/-
23 Dismantling and Reconstruction of DPO 5.346 4,96,366/-
24 Dismantling and Reconstruction of DPO 5.674 4,96,366/-
25 Dismantling and Reconstruction of DPO 5.870 4,96,366/-
26 Dismantling and Reconstruction of DPO 5.904 4,96,366/-
27 Dismantling and Reconstruction of DPO 6.082 4,75,557/-
28 Dismantling and Reconstruction of DPO 6.176 4,75,557/-
29 Dismantling and Reconstruction of DPO 6.201 4,75,557/-
30 Dismantling and Reconstruction of DPO 6.256 4,75,557/-
31 Dismantling and Reconstruction of DPO 6.415 4,75,557/-
32 Dismantling and Reconstruction of DPO 6.600 4,75,557/-
33 Dismantling and Reconstruction of DPO 6.695 4,75,557/-
34 Dismantling and Reconstruction of DPO 7.240 3,88,573/-
35 Dismantling and Reconstruction of DPO 7.496 3,88,573/-
36 Dismantling and Reconstruction of DPO 7.595 3,88,573/-
37 Dismantling and Reconstruction of DPO 7.856 3,88,573/-
38 Dismantling and Reconstruction of DPO 7.979 3,88,573/-
39 Dismantling and Reconstruction of DPO 8.081 3,91,700/-
40 Dismantling and Reconstruction of DPO 8.299 3,98,210/-
41 Dismantling and Reconstruction of DPO 8.370 3,98,210/-
42 Dismantling and Reconstruction of DPO 8.648 3,98,210/-
11. Remodelling of Structures under Hulugi Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
43 Dismantling and Reconstruction of DPO 8.794 3,98,210/-
44 Dismantling and Reconstruction of DPO 8.828 3,98,210/-
45 Dismantling and Reconstruction of DPO 8.961 3,98,210/-
46 Dismantling and Reconstruction of DPO 9.210 3,96,794/-
47 Dismantling and Reconstruction of DPO 9.383 3,96,794/-
48 Dismantling and Reconstruction of DPO 9.496 3,96,794/-
49 Dismantling and Reconstruction of DPO 9.663 3,96,794/-
50 Dismantling and Reconstruction of DPO 9.762 3,96,794/-
51 Dismantling and Reconstruction of DPO 9.816 3,96,794/-
52 Dismantling and Reconstruction of DPO 10.009 3,95,991/-
53 Dismantling and Reconstruction of DPO 10.122 3,95,991/-
54 Dismantling and Reconstruction of DPO 10.143 3,95,991/-
55 Dismantling and Reconstruction of DPO 10.407 3,95,991/-
56 Dismantling and Reconstruction of DPO 10.584 3,95,991/-
TOTAL 2,43,67,926/-
243.68 Lakhs
1 Construction of CR/CTC 1.133 19,26,844/-
2 Construction of MD 1.200 78,899/-
3 Dismantling and Construction of DPO 1.385 407,431/-
4 Dismantling and Construction of DPO 1.778 4,07,431/-
5 Construction of DPO 1.945 4,07,431/-
6 Dismantling and Construction of DPO 2.128 4,09,258/-
7 Dismantling and Construction of DPO 2.678 4,09,258/-
8 Dismantling and Construction of DPO 2.988 4,09,258/-
9 Dismantling and Construction of DPO 3.285 4,11,738/-
10 Dismantling and Construction of DPO 3.405 4,11,738/-
11 Dismantling and Construction of DPO 3.525 4,11,738/-
12 Dismantling and Construction of DPO 3.657 4,11,738/-
13 Dismantling and Construction of DPO 3.826 4,11,738/-
14 Dismantling and Construction of DPO 3.899 4,11,738/-
15 Dismantling and Construction of DPO 3.944 4,11,738/-
16 Dismantling and Construction of DPO 4.638 4,12,126/-
17 Dismantling and Construction of DPO 4.870 4,12,126/-
18 Dismantling and Construction of DPO 5.188 4,13,922/-
19 Dismantling and Construction of DPO 5.280 4,13,922/-
20 Dismantling and Construction of DPO 5.635 3,73,196/-
21 Dismantling and Construction of DPO 5.784 3,73,196/-
22 Dismantling and Construction of DPO 6.012 3,73,400/-
23 Dismantling and Construction of DPO 6.184 3,73,400/-
24 Dismantling and Construction of DPO 6.340 3,73,400/-
25 Dismantling and Construction of DPO 6.360 3,73,400/-
26 Dismantling and Construction of DPO 6.515 3,73,400/-
TOTAL 1,16,03,462/-
116.03 Lakhs
12. Remodelling of Structures under Shivapura Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1 Construction of Measuring Device 0.500 1,99,867/-
2 Dismantling and Reconstruction of DPO-2 0.797 4,73,942/-
3 Dismantling and Reconstruction of DPO-3 1.119 5,31,979/-
4 Dismantling and Reconstruction of DPO-4 1.885 5,31,979/-
5 Dismantling and Reconstruction of DPO-6 3.075 5,06,401/-
6 Dismantling and Reconstruction of DPO-9 3.759 3,74,065/-
7 Dismantling and Reconstruction of DPO-10 4.467 3,35,281/-
8 Dismantling and Reconstruction of DPO-11 4.838 5,04,080/-
9 Dismantling and Reconstruction of DPO-12 4.995 5,04,080/-
10 Dismantling and Reconstruction of DPO-13 5.273 4,99,917/-
11 Dismantling and Reconstruction of DPO-14 5.539 4,99,917/-
12 Dismantling and Reconstruction of DPO-16 5.820 4,99,917/-
13 Dismantling and Reconstruction of DPO-17 6.839 4,99,842/-
14 Dismantling and Reconstruction of DPO-18 6.974 4,99,842/-
15 Dismantling and Reconstruction of DPO-19 7.093 4,99,540/-
16 Dismantling and Reconstruction of DPO-20 7.265 4,99,540/-
17 Dismantling and Reconstruction of DPO-22 7.948 4,27,364/-
18 Dismantling and Reconstruction of DPO-23 8.286 4,44,308/-
19 Dismantling and Reconstruction of DPO-24 8.461 4,44,308/-
20 Dismantling and Reconstruction of DPO-25 8.715 4,44,308/-
21 Dismantling and Reconstruction of DPO-26 8.808 4,44,308/-
22 Dismantling and Reconstruction of DPO-27 8.835 4,44,308/-
23 Dismantling and Reconstruction of DPO-28 8.990 4,44,308/-
24 Dismantling and Reconstruction of DPO-30 9.183 4,45,256/-
25 Dismantling and Reconstruction of DPO-31 9.400 5,01,515/-
26 Dismantling and Reconstruction of DPO-32 9.652 4,27,048/-
27 Dismantling and Reconstruction of DPO-33 9.818 4,27,048/-
28 Dismantling and Reconstruction of DPO-34 10.693 4,26,608/-
29 Dismantling and Reconstruction of DPO-36 11.008 4,26,174/-
30 Dismantling and Reconstruction of DPO-37 11.352 5,42,026/-
31 Dismantling and Reconstruction of DPO-42 12.715 5,42,059/-
32 Dismantling and Reconstruction of DPO-43 12.811 5,42,059/-
33 Dismantling and Reconstruction of DPO-44 12.916 5,42,059/-
34 Dismantling and Reconstruction of DPO-45 12.918 5,42,059/-
35 Dismantling and Reconstruction of DPO-46 13.465 5,42,099/-
36 Dismantling and Reconstruction of DPO-47 13.572 5,42,099/-
37 Dismantling and Reconstruction of DPO-50 14.415 5,56,412/-
38 Dismantling and Reconstruction of DPO-52 14.709 5,56,412/-
39 Dismantling and Reconstruction of DPO-53 14.782 5,56,412/-
40 Dismantling and Reconstruction of DPO-54 14.960 5,56,412/-
41 Dismantling and Reconstruction of DPO-57 15.046 5,37,299/-
42 Dismantling and Reconstruction of DPO-58 15.162 5,37,299/-
43 Dismantling and Reconstruction of DPO-59 15.350 5,37,299/-
13. Remodelling of Structures under Anegundi Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
44 Dismantling and Reconstruction of DPO-60 15.440 5,37,299/-
45 Dismantling and Reconstruction of DPO-61 15.668 5,37,299/-
46 Dismantling and Reconstruction of DPO-62 15.820 5,37,299/-
47 Dismantling and Reconstruction of DPO-64 16.495 5,35,595/-
48 Dismantling and Reconstruction of DPO-65 16.725 5,35,595/-
49 Dismantling and Reconstruction of DPO-66 16.785 5,35,595/-
50 Dismantling and Reconstruction of DPO-68 17.052 5,33,149/-
51 Dismantling and Reconstruction of DPO-69 17.130 5,33,149/-
52 Dismantling and Reconstruction of DPO-70 17.178 5,33,149/-
53 Dismantling and Reconstruction of DPO-72 17.245 5,33,149/-
54 Dismantling and Reconstruction of DPO-74 17.444 5,33,149/-
55 Dismantling and Reconstruction of DPO-77 18.737 5,33,149/-
56Dismantling and Reconstruction of Cross
Regulator0.000 16,83,551/-
TOTAL 2,89,40,182/-
289.40 Lakhs
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1 Dismantling and Reconstruction of CR 0.000 17,24,895/-
Details enclosed Refer
Volume-III of Annexure-3,
Page No.69
2 Dismantling and Reconstruction of Measuring
Device0.210 2,21,596/-
3 Dismantling and Reconstruction of DPO 0.280 5,23,094/-
4 Dismantling and Reconstruction of DPO 0.900 5,23,094/-
5 Dismantling and Reconstruction of DPO 1.530 5,23,675/-
6 Dismantling and Reconstruction of DPO 1.588 5,23,675/-
7 Dismantling and Reconstruction of DPO 1.827 5,23,675/-
8 Dismantling and Reconstruction of DPO 2.618 5,21,539/-
9 Dismantling and Reconstruction of DPO 2.894 5,21,539/-
10 Dismantling and Reconstruction of DPO 3.065 5,19,082/-
11 Dismantling and Reconstruction of DPO 3.723 5,19,082/-
12 Dismantling and Reconstruction of DPO 4.640 5,17,894/-
13 Dismantling and Reconstruction of DPO 5.163 4,98,697/-
14 Dismantling and Reconstruction of DPO 5.317 4,98,697/-
15 Dismantling and Reconstruction of DPO 6.090 5,16,816/-
16 Dismantling and Reconstruction of DPO 6.150 5,16,816/-
17 Dismantling and Reconstruction of DPO 6.196 6,57,847/-
18 Dismantling and Reconstruction of DPO 6.312 4,45,675/-
19 Dismantling and Reconstruction of DPO 6.450 4,45,675/-
20 Dismantling and Reconstruction of DPO 6.494 6,70,012/-
21 Dismantling and Reconstruction of DPO 7.410 8,07,872/-
22 Dismantling and Reconstruction of DPO 7.560 5,11,636/-
23 Dismantling and Reconstruction of DPO 7.670 5,10,269/-
24 Dismantling and Reconstruction of DPO 7.912 7,25,216/-
25 Dismantling and Reconstruction of DPO 8.107 4,34,474/-
26 Dismantling and Reconstruction of DPO 8.163 4,34,474/-
27 Dismantling and Reconstruction of DPO 8.295 4,34,474/-
28 Dismantling and Reconstruction of DPO 8.490 4,34,474/-
TOTAL 1,57,05,965/-
157.06 Lakhs
14. Remodelling of Structures under Upper Gangavathi Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1 Dismantling and Reconstruction of CR cum CTC0.000 19,66,237/-
2 Construction of CR with CTC 0.020 19,66,237/-
3 Dismantling and Reconstruction of DPO 0.217 4,66,739/-
4 Construction of Measuring Device 0.510 1,87,125/-
5Dismantling and Reconstruction of Head
Regulator 0.730 6,25,360/-
6 Dismantling and Reconstruction of DPO 1.405 4,48,085/-
7 Dismantling and Reconstruction of DPO 3.494 4,44,810/-
8 Dismantling and Reconstruction of DPO 3.872 4,44,810/-
9 Dismantling and Reconstruction of DPO 3.900 4,44,810/-
10 Dismantling and Reconstruction of DPO 4.144 4,47,615/-
11 Dismantling and Reconstruction of DPO 4.802 4,47,615/-
12Dismantling and Reconstruction of Head
Regulator 4.965 6,79,852/-
13 Dismantling and Reconstruction of DPO 5.045 4,48,923/-
14 Dismantling and Reconstruction of DPO 5.280 4,48,923/-
15 Dismantling and Reconstruction of DPO 5.485 4,48,923/-
16 Dismantling and Reconstruction of DPO 5.643 4,48,923/-
17 Dismantling and Reconstruction of DPO 6.060 4,49,397/-
18 Dismantling and Reconstruction of DPO 6.281 4,49,397/-
19 Dismantling and Reconstruction of DPO 6.300 4,49,397/-
20 Dismantling and Reconstruction of DPO 6.614 4,49,397/-
21 Dismantling and Reconstruction of DPO 6.715 4,49,397/-
22 Dismantling and Reconstruction of DPO 6.896 4,49,397/-
23 Dismantling and Reconstruction of DPO 7.115 4,96,355/-
24 Dismantling and Reconstruction of DPO 7.402 4,96,355/-
25 Dismantling and Reconstruction of DPO 7.421 4,96,355/-
26Dismantling and Reconstruction of Head
Regulator 7.800 4,96,355/-
27 Dismantling and Reconstruction of DPO 7.810 6,97,621/-
28 Dismantling and Reconstruction of DPO 7.860 4,96,355/-
29 Dismantling and Reconstruction of DPO 7.915 4,96,355/-
30 Dismantling and Reconstruction of DPO 8.077 4,50,364/-
31 Dismantling and Reconstruction of DPO 8.444 4,50,364/-
32 Dismantling and Reconstruction of DPO 8.465 4,50,364/-
33 Dismantling and Reconstruction of DPO 8.647 4,50,364/-
34 Dismantling and Reconstruction of DPO 8.702 4,50,364/-
35 Dismantling and Reconstruction of DPO 9.495 3,97,194/-
TOTAL 1,93,86,133/-
193.86 Lakhs
15. Remodelling of Structures under Lower Gangavathi Channel
Sl.N
oType of structure
Chainage in
Km
Amount in
RupeesRemarks
1Dismantling and Reconstruction of Cross
Regulator0.002
5,27,632/-
2 Dismantling and Reconstruction of DPO 0.225 5,14,564/-
3 Construction of Measuring Device 0.500 94,634/-
4 Dismantling and Reconstruction of DPO 1.385 4,85,154/-
5 Dismantling and Reconstruction of DPO 1.710 4,85,154/-
6 Dismantling and Reconstruction of DPO 2.910 5,16,628/-
7 Dismantling and Reconstruction of DPO 3.075 5,20,888/-
8 Dismantling and Reconstruction of DPO 3.780 5,20,888/-
9 Dismantling and Reconstruction of DPO 6.150 4,31,767/-
10 Dismantling and Reconstruction of DPO 11.295 4,54,476/-
11 Dismantling and Reconstruction of DPO 11.502 4,54,476/-
12 Dismantling and Reconstruction of DPO 12.080 4,55,917/-
TOTAL 54,62,178/-
54.62 Lakhs
16. Remodelling of Structures under Bichal Channel
Sl
No.Description
Amount
Rs in Lakhs
Construction of Falls Coming under entire Vijayanagar Channel
system(16 Nos.)
1 Raya Channel 51.94
2 Basavanna Channel 39.24
3 Kalaghatta Channel 9.22
4 Turtha Channel 38.44
5 Hulugi Channel 1.97
6 Shivapura Channel 1.78
7 Anegundi Channel 6.23
8 Lower Gangavathi Channel 3.46
152.27
COST OF E-FALLS Rs.152.27 LAKHS
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
E-FALLS
ABSTRACT
TOTAL
Sl.
NoType of structure
Chainage in
Km
Amount in
RupeesRemarks
1 Construction of Canal Drop (0.5 m ) 0.318 4,84,648/-
2 Construction of Canal Drop (1.0m ) 0.630 8,00,266/-
3 Construction of Canal Drop (1.0m ) 12.230 7,47,360/-
4 Construction of Canal Drop (0.5 m ) 16.613 4,53,271/-
5 Construction of Canal Drop (1.0m ) 18.710 8,36,934/-
6 Construction of Canal Drop (0.5 m ) 21.560 4,50,118/-
7 Construction of Canal Drop (0.5 m ) 24.574 4,50,914/-
8 Construction of Canal Drop (1.0m ) 25.085 4,85,338/-
9 Construction of Canal Drop (1.0m ) 25.800 4,85,338/-
TOTAL 51,94,188/-
51.94 Lakhs
1 Construction of Canal Drop (1.0m ) 3.800 5,89,455/-
2 Construction of Canal Drop (1.0m ) 3.890 5,89,153/-
3 Construction of Canal Drop (1.5 m ) 3.960 8,28,620/-
4 Construction of Canal Drop (1.0m ) 4.290 5,89,821/-
5 Construction of Canal Drop (1.0m ) 4.662 4,79,515/-
6 Construction of Canal Drop (1.0m ) 5.430 4,78,720/-
7 Construction of Canal Drop (0.5 m ) 6.180 3,69,122/-
TOTAL 39,24,407/-
39.24 Lakhs
1 Construction of Canal Drop (1.0m ) 6.737 9,22,013/-
TOTAL 9,22,013/-
9.22 Lakhs
1 Construction of Canal Drop (1.0m ) 3.800 5,71,885/-
2 Construction of Canal Drop (1.0m ) 3.890 5,71,885/-
3 Construction of Canal Drop (1.5 m ) 3.960 8,26,815/-
Details enclosed Refer
Volume-III of Annexure-
6, Page No.176
4 Construction of Canal Drop (1.0m ) 4.290 5,69,992/-
5 Construction of Canal Drop (1.0m ) 4.662 4,72,104/-
6 Construction of Canal Drop (1.0m ) 5.430 4,70,614/-
7 Construction of Canal Drop (0.5 m ) 6.180 3,60,570/-
TOTAL 38,43,865/-
38.44 Lakhs
4. Remodelling of Structures under Turtha Channel
1. Remodelling of Structures under Raya Channel
2. Remodelling of Structures under Basavanna Channel
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
E- FALLS
3. Remodelling of Structures under Kalaghatta Channel
Sl.
NoType of structure
Chainage in
Km
Amount in
RupeesRemarks
1 Construction of Canal Drop (0.5 m ) 8.130 1,96,537/-
TOTAL 1,96,537/-
1.97 Lakhs
Construction of Canal Drop (0.5 m ) 5.045 1,77,823/-
TOTAL 1,77,823/-
1.78 Lakhs
1 Construction of Canal Drop (0.5 m ) 3.600 2,92,087/-
2 Construction of Canal Drop (0.60 m) 11.22 3,30,790/-
TOTAL 6,22,877/-
6.23 Lakhs
1 Construction of Canal Drop (0.5 m ) 9.000 3,45,729/-
TOTAL 3,45,729/-
3.46 Lakhs
8. Remodelling of Structures under Lower Gangavathi Channel
5. Remodelling of Structures under Hulugi Channel
6. Remodelling of Structures under Shivapura Channel
7. Remodelling of Structures under Anegundi Channel
Sl
No.Description
Amount
Rs in Lakhs
Construction of Cross Drainage Works Coming under entire
Vijayanagar Channel system(16 Nos.)
1 Raya Channel 67.22
2 Basavanna Channel 72.85
3 Bella Channel 27.80
4 Kalaghatta Channel 155.77
5 Ramasagara Channel 75.41
6 Kampli Channel 166.68
7 Belagodhalla Channel 13.78
8 Siruguppa Channel 8.37
9 Hulugi Channel 10.35
10 Shivapura Channel 55.00
11 Anegundi Channel 133.70
12 Upper Gangavathi Channel 104.55
13 Lower Gangavathi Channel 20.62
912.10
COST OF F-CROSS DRAINAGE WORKS Rs.912.10 LAKHS
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
F-CROSS DRAINAGE WORKS
ABSTRACT
TOTAL
Sl.No Type of structure Chainage in
Km
Amount in
RupeesRemarks
1 Construction of Inlet 11 .917 6,36,689/-
2 Construction of Inlet 26 .355 6,30,673/-
3 Dismantling and Reconstruction of Under 0 .435 8,44,758/-
4 Construction of Under Tunnel 3 .900 19,26,216/-
5 Construction of Under Tunnel 9 .351 26,83,810/-
TOTAL 67,22,146/-
67.22 Lakhs
1 Construction of Inlet 0.610 8,05,432/-
2 Construction of Undertunnel 0.710 28,36,855/-
3 Construction of Inlet 1.298 8,05,432/-
4 Construction of Undertunnel 1.900 28,36,855/-
TOTAL 72,84,574/-
72.85 Lakhs
1 Construction of Inlet 0.295 7,05,373/-
2 Construction of inlet 1.794 6,91,678/-
3 Construction of inlet 1.844 6,91,678/-
4 Construction of inlet 1.944 6,91,678/-
TOTAL 27,80,406/-
27.80 Lakhs
1 33,25,500/-
Details enclosed Refer
Volume-III of Annexure-
7, Page No.202
2 1,22,51,241/-
TOTAL 1,55,76,741/-
155.77 Lakhs
1 Construction of Inlet 0.350 6,97,372/-
2 Construction of Inlet 0.128 6,97,372/-
3 Construction of Inlet 0.242 6,97,372/-
4 Construction of Inlet 0.300 6,97,372/-
5 Construction of Inlet 1.360 6,97,372/-
6 Construction of Inlet 1.644 6,97,372/-
7 Construction of Inlet 6.960 6,93,581/-
8 Construction of Inlet 8.335 6,91,127/-
9 Construction of Inlet 10.600 6,75,856/-
10 Construction of Inlet 10.642 6,75,856/-
11 Construction of Inlet 14.407 6,19,984/-
TOTAL 75,40,636/-
75.41 Lakhs
1. Remodelling of Structures under Raya Channel
2. Remodelling of Structures under Basavanna Channel
3. Remodelling of Structures under Bella Channel
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
F- CROSS DRAINAGE WORKS
4. Remodelling of Structures under Kalaghatta Channel
5. Remodelling of Structures under Ramasagara Channel
Construction of Trough from Ch:1900.00 m to 2000.00m
Construction of Trough from Ch:2000.00 m to 2400.00m
Sl.No Type of structure Chainage in
Km
Amount in
RupeesRemarks
1 27,05,680/-
2 78,06,298/-
3 6,78,643/-
4 6,78,643/-
5 6,94,413/-
6 6,94,413/-
7 6,89,279/-
8 6,65,007/-
9 6,85,326/-
10 6,85,326/-
11 6,85,008/-
TOTAL 1,66,68,037/-
166.68 Lakhs
1 Construction of Inlet 2.426 6,91,810/-
2 Construction of Inlet 6.975 6,86,099/-
TOTAL 13,77,909/-
13.78 Lakhs
1 Construction of Super Passage 2.950 8,36,733/-
Details enclosed Refer
Volume-III of Annexure-
8, Page No.222
TOTAL 8,36,733/-
8.37 Lakhs
1 Construction of Inlet 2.385 5,19,699/-
Details enclosed Refer
Volume-III of Annexure-
9, Page No.251
2 Construction of Inlet 8.820 5,14,826/-
TOTAL 10,34,525/-
10.35 Lakhs
1 Construction of Inlet 1.145 4,19,914/-
2 Construction of Inlet 1.462 4,19,914/-
3 Construction of Inlet 2.098 4,22,622/-
4 Construction of Inlet 2.210 4,22,622/-
5 Construction of Inlet 2.242 4,22,622/-
6 Construction of Inlet 2.542 4,22,622/-
7 Construction of Under Tunnel 6.400 29,70,161/-
TOTAL 55,00,478/-
55.00 Lakhs
Construction of Inlet Ch:5.520 Km
10. Remodelling of Structures under Shivapura Channel
6. Remodelling of Structures under Kampli Channel
Construction of Inlet Ch:10.920 Km
7. Remodelling of Structures under Belgodhalla Channel
Construction of Inlet Ch:11.120 Km
Construction of Inlet Ch:12.920 Km
Construction of Inlet Ch:11.290 Km
9. Remodelling of Structures under Hulugi Channel
8. Remodelling of Structures under Siruguppa Channel
Construction of Inlet Ch:8.550 Km
Construction of Trough from Ch:3900.00 m to 4000.00m
Construction of Trough from Ch:4000.00 m to 4400.00m
Construction of Inlet Ch:0.670 Km
Construction of Inlet Ch:0.750 Km
Construction of Inlet Ch:5.280 Km
Sl.No Type of structure Chainage in
Km
Amount in
RupeesRemarks
1 Construction of Inlet 0.408 4,59,215/-
2 Construction of Inlet 3.376 5,95,272/-
3 Construction of Inlet 5.297 8,50,833/-
4 Construction of Inlet 7.325 8,50,663/-
5 Construction of Inlet 8.600 5,07,707/-
6 Construction of Inlet 12.000 8,74,409/-
7 Construction of Inlet 12.230 8,74,409/-
8 Construction of Inlet 16.325 8,62,256/-
9 Construction of Inlet 17.600 8,57,762/-
10 Construction of Inlet 17.680 8,57,762/-
11 Construction of Under Tunnel 7.431 28,64,634/-
Details enclosed Refer
Volume-III of Annexure-
10, Page No.267
12 Construction of Under Tunnel 8.015 29,15,336/-
TOTAL 1,33,70,258/-
133.70 Lakhs
1 Construction of Inlet 0.465 8,60,895/-
2 Construction of Inlet 0.840 8,60,895/-
3 Construction of Inlet 3.230 8,50,580/-
4 Construction of Inlet 3.900 8,50,580/-
5 Construction of Inlet 4.060 8,46,797/-
6 Construction of Inlet 5.685 8,41,920/-
7 Construction of Inlet 5.900 8,41,920/-
8 Construction of Inlet 5.950 8,41,920/-
9 Construction of Inlet 6.730 7,30,678/-
10 Construction of Inlet 6.760 7,30,678/-
11 Construction of Inlet 6.860 7,30,678/-
12 Construction of Inlet 7.620 7,33,937/-
13 Construction of Inlet 7.950 7,33,937/-
TOTAL 1,04,55,413/-
104.55 Lakhs
1 Dismantling and Reconstruction of Inlet 0.883 5,19,647/-
2 Construction of Inlet 3.060 5,04,805/-
3 Construction of Inlet 5.160 5,18,911/-
4 Construction of Inlet 5.730 5,18,911/-
TOTAL 20,62,274/-
20.62 Lakhs
13. Remodelling of Structures under Lower Gangavathi Channel
11. Remodelling of Structures under Anegundi Channel
12. Remodelling of Structures under Upper Gangavathi Channel
Sl
No.Description
Amount
Rs in Lakhs
Construction of Bridges Coming under entire Vijayanagar Channel
system(16 Nos.)
1 Raya Channel 317.25
2 Basavanna Channel 119.64
3 Bella Channel 123.11
4 Kalaghatta Channel 98.61
5 Turtha Channel 66.72
6 Ramasagara Channel 114.08
7 Kampli Channel 395.33
8 Belagodhalla Channel 109.03
9 Deshnur Channel 64.35
10 Siruguppa Channel 94.00
11 Hulugi Channel 84.43
12 Shivapura Channel 73.67
13 Anegundi Channel 117.07
14 Upper Gangavathi Channel 73.80
15 Lower Gangavathi Channel 36.17
16 Bichal Channel 73.22
1960.48
COST OF G-BRIDGES Rs.1960.48 LAKHS
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
G-BRIDGES
ABSTRACT
TOTAL
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1 Construction of Foot Bridge 9 .598 3,24,891/-
2 Dismantling and Reconstruction of CTC 1 .475 19,31,861/-
3 Dismantling and Reconstruction of CTC 2 .512 19,32,723/-
4 Dismantling and Reconstruction of CTC 3 .473 15,93,293/-
5 Dismantling and Reconstruction of CTC 6 .600 10,01,765/-
6 Construction of CTC 8 .345 9,91,674/-
7 Construction of CTC 9 .148 9,91,674/-
8 Construction of CTC 9 .211 9,91,674/-
9 Construction of CTC 12 .651 13,36,101/-
10 Construction of CTC 15 .806 8,20,149/-
11 Construction of CTC 20 .805 8,23,989/-
12 Construction of CTC 22 .330 8,42,444/-
13 Dismantling and Reconstruction of CTC 22 .653 8,42,444/-
14 Construction of CTC 23 .014 8,34,085/-
15 Construction of CTC 23 .041 8,34,085/-
16 Construction of CTC 23 .633 8,34,085/-
17 Dismantling and Reconstruction of CTC 24 .652 8,42,931/-
18 Dismantling and Reconstruction of CTC 26 .346 9,73,459/-
19 Construction of CTC 27 .075 9,65,100/-
20 Construction of CTC 27 .222 9,65,100/-
21Dismantling and Reconstruction of Major
Road Bridge8 .196 25,65,133/-
Details enclosed Refer
Volume-III of Annexure-
11, Page No.303
22 Construction of Major Road Bridge 17 .990 20,16,499/-
23Dismantling and Reconstruction of Village
Road Bridge12 .145 24,85,857/-
24 Dismantling and Reconstruction Village 13 .737 19,14,112/-
25 Construction of Village Road Bridge 22 .735 19,18,093/-
26 Construction of Sopanam (washing ghat) 19 .370 1,51,510/-
TOTAL 3,17,24,731/-
317.25 Lakhs
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
G- BRIDGES
1. Remodelling of Structures under Raya Channel
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1 Dismantling and Reconstruction of Foot Bridge 0.956 4,03,844/-
2 Construction of Sopanam (Washing Ghat) 0.805 2,96,897/-
3 Construction of Sopanam (Washing Ghat) 0.914 2,96,897/-
4 Dismantling and Reconstruction of VRB 0.307 11,75,345/-
5 Dismantling and Reconstruction of VRB 0.810 11,75,345/-
6 Construction of Sopanam (Washing Ghat) 1.092 2,96,870/-
7 Dismantling and Reconstruction of VRB 1.917 11,75,345/-
8 Construction of Sopanam (Washing Ghat) 2.200 2,47,435/-
9 Construction of Sopanam (Washing Ghat) 4.180 2,78,532/-
10 Dismantling and Reconstruction of CTC 10.830 8,27,486/-
11 Dismantling and Reconstruction of CTC 11.695 7,96,585/-
12 Construction of Sopanam (Washing Ghat) 11.700 2,18,974/-
13 Dismantling and Reconstruction of CTC 11.710 7,88,218/-
14 Dismantling and Reconstruction of CTC 12.643 9,96,440/-
15 Dismantling and Reconstruction of CTC 13.799 9,96,440/-
16 Dismantling and Reconstruction of CTC 14.566 9,96,440/-
17 Dismantling and Reconstruction of CTC 14.917 9,96,440/-
TOTAL 119,63,533 / -
119.64 Lakhs
1Dismantle and Reconstruction of Sopanam
(Washing Ghat)0.184 3,06,091/-
2Dismantling and Reconstruction of Village
Road Bridge 0.484 16,23,613/-
3Dismantling and Reconstruction of Road
Bridge 1.163 24,97,559/-
4 Construction of cattle ramp 1.300 2,23,953/-
5 Construction of Foot Bridge 1.499 4,45,708/-
6 Construction of cattle ramp 3.100 2,24,870/-
7 Construction of CTC 3.500 15,85,186/-
8 Construction of cattle ramp 3.900 2,24,870/-
9 Dismantling and Reconstruction of CTC 3.930 16,34,714/-
10 Construction of cattle ramp 4.100 2,25,311/-
11 Dismantling and Reconstruction of CTC 4.181 16,37,293/-
12 Dismantling and Reconstruction of CTC 4.882 8,42,244/-
13 Dismantle and reconstruction of CTC 5.369 8,39,976/-
TOTAL 1,23,11,388/-
123.11 Lakhs
2. Remodelling of Structures under Basavanna Channel
3. Remodelling of Structures under Bella Channel
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1 Construction of Foot Bridge 0.144 4,01,147/-
Details enclosed Refer
Volume-III of Annexure-
12, Page No.336
2 Dismantling and Reconstruction of CTC 1.116 9,49,770/-
3Dismantling and Reconstruction of Village
Road Bridge1.960 10,62,338/-
4Dismantling and Reconstruction of Village
Road Bridge2.740 10,49,523/-
5 Dismantling and Reconstruction of CTC 3.359 9,54,915/-
6 Dismantling and Reconstruction of CTC 3.903 9,54,915/-
7 Dismantling and Reconstruction of CTC 5.170 9,39,924/-
8 Dismantling and Reconstruction of CTC 5.944 9,39,924/-
9 Dismantling and Reconstruction of CTC 6.563 9,39,924/-
10 Construction of CTC 6.725 8,90,396/-
11 Dismantling and Reconstruction of CTC 6.868 7,78,068/-
TOTAL 98,60,845/-
98.61 Lakhs
1 Construction of Sopanam (Washing Ghat) 4.180 2,73,293/-
Details enclosed Refer
Volume-III of Annexure-
13, Page No.358
2 Dismantling and Reconstruction of CTC 10.830 8,16,933/-
3 Dismantling and Reconstruction of CTC 11.695 7,71,813/-
Details enclosed Refer
Volume-III of Annexure-
14, Page No.370
4 Construction of Sopanam (Washing Ghat) 11.700 1,98,960/-
5 Dismantling and Reconstruction of CTC 11.710 7,58,570/-
6 Dismantling and Reconstruction of CTC 12.643 9,60,779/-
7 Dismantling and Reconstruction of CTC 13.799 9,62,788/-
8 Dismantling and Reconstruction of CTC 14.566 9,64,548/-
9 Dismantling and Reconstruction of CTC 14.917 9,64,548/-
TOTAL 66,72,232/-
66.72 Lakhs
4. Remodelling of Structures under Kalaghatta Channel
5. Remodelling of Structures under Turtha Channel
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1 Construction of CTC 2.86 14,44,890/-
2 Dismantling and Reconstruction of CTC 5.445 14,52,527/-
3 Construction of Cattle ramp 7.037 2,20,670/-
4 Dismantling and Reconstruction of CTC 7.037 10,70,143/-
5 Dismantling and Reconstruction of CTC 7.865 10,70,143/-
6 Construction of CTC 8.316 10,67,517/-
7 Dismanteling and Reconstruction of CTC 10.186 10,66,764/-
8 Construction of CTC 11.923 10,65,587/-
9 Construction of CTC 12.271 10,64,178/-
10 Construction of CTC 12.895 10,64,178/-
11 Construction of CTC 14.233 8,21,079/-
TOTAL 1,14,07,674/-
114.08 Lakhs
1 Construction of Sopanam 0.000 2,95,134/-
2 Construction of Foot Bridge 0.300 3,61,604/-
3Dismantling and Reconstruction of Foot
Bridge0.600 3,69,573/-
4 Construction of Foot Bridge 1.039 3,70,000/-
5 Construction Village Road Bridge 1.450 8,74,496/-
6 Construction Village Road Bridge 1.730 13,56,498/-
7 Dismantling and Reconstruction of CTC 1.784 9,31,940/-
8 Construction of Foot Bridge 2.330 3,62,145/-
9 Construction of Foot Bridge 2.850 3,62,145/-
10 Dismantling and Reconstruction of CTC 3.920 9,68,143/-
11 Construction of CTC 4.850 9,00,356/-
12 Dismantling and Reconstruction of CTC 5.015 9,66,781/-
13 Construction of Foot Bridge 5.150 3,26,322/-
14 Construction of Foot Bridge 5.430 3,26,322/-
15 Construction of CTC 5.580 9,26,413/-
16 Construction of Foot Bridge 5.595 3,26,322/-
17 Dismantling and Reconstruction of CTC 5.753 9,66,781/-
18Dismantling and Reconstruction of Foot
Bridge5.946 3,34,291/-
19 Construction of Foot Bridge 7.050 3,73,303/-
20Dismantling and Reconstruction of Foot
Bridge7.142 3,82,280/-
21 Construction of Foot Bridge 7.210 3,73,303/-
22 Construction of Foot Bridge 7.405 3,73,303/-
23 Construction of Sopanam (Washing Ghat) 7.665 3,02,128/-
6. Remodelling of Structures under Ramasagara Channel
7. Remodelling of Structures under Kampli Channel
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
24Dismantling and Reconstruction of Foot
Bridge7.665 3,82,280/-
25Dismantling and Reconstruction of Foot
Bridge8.010 3,07,017/-
26 Construction of CTC 9.340 9,21,669/-
27Dismantling and Reconstruction of Village
Road Bridge9.567 9,42,797/-
28 Construction of Foot Bridge 9.610 3,73,715/-
29 Construction of Sopanam (Washing Ghat) 9.670 3,01,487/-
30 Construction of Foot Bridge 9.730 3,73,715/-
31 Construction Village Road Bridge 9.940 9,02,429/-
32Dismantling and Reconstruction of Village
Road Bridge10.204 9,42,183/-
33 Construction of CTC 10.520 9,21,003/-
34 Dismantling and Reconstruction of CTC 10.852 9,61,371/-
35 Construction of CTC 12.040 9,19,554/-
36 Dismantling and Reconstruction of CTC 12.415 9,61,755/-
37 Construction of CTC 13.400 7,38,176/-
38 Dismantling and Reconstruction of CTC 13.680 9,62,160/-
39 Construction of CTC 13.840 7,38,176/-
40 Construction of Foot Bridge 14.340 3,13,853/-
41 Construction of Foot Bridge 14.520 3,13,853/-
42 Construction of CTC 14.568 6,02,050/-
43 Construction of Foot Bridge 14.580 3,13,853/-
44 Construction of Sopanam (Washing Ghat) 14.710 2,94,513/-
45 Construction of CTC 15.910 6,21,594/-
46 Dismantling and Reconstruction of CTC 16.197 6,11,093/-
47 Construction of Foot Bridge 16.520 3,14,144/-
48 Dismantling and Reconstruction of CTC 16.545 6,11,093/-
49 Construction of CTC 17.320 6,00,375/-
50 Dismantling and Reconstruction of CTC 17.627 6,12,029/-
51 Construction of CTC 17.940 6,00,375/-
52 Construction of CTC 18.130 6,00,375/-
53 Construction of CTC 18.250 6,00,375/-
54 Construction of CTC 18.380 6,00,375/-
55 Construction of CTC 18.610 6,00,375/-
56 Construction of CTC 18.920 6,00,375/-
57 Dismantling and Reconstruction of CTC 19.207 6,12,821/-
58 Dismantling and Reconstruction of CTC 20.140 6,12,821/-
59 Construction of CTC 20.140 4,84,645/-
60 Construction of CTC 20.230 4,84,645/-
61 Construction of CTC 20.690 4,84,645/-
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
62 Construction of CTC 20.830 4,84,645/-
63 Dismantling and Reconstruction of CTC 20.890 6,13,339/-
64 Dismantling and Reconstruction of CTC 21.103 6,13,892/-
65 Dismantling and Reconstruction of CTC 21.394 6,13,892/-
66 Dismantling and Reconstruction of CTC 21.607 6,13,892/-
67Dismantling and Reconstruction of Foot
Bridge22.673 3,24,446/-
TOTAL 3,95,33,453/-
395.33 Lakhs
1 Construction of Foot Bridge 0.310 2,11,119/-
2 Construction of CTC 0.610 6,10,198/-
3 Construction of CTC 0.865 6,10,198/-
4 Construction of CTC 0.940 6,10,198/-
5 Construction of CTC 1.320 6,08,656/-
6 Dismantle and Reconstruction of CTC 1.670 6,17,005/-
7 Construction of CTC 2.620 6,07,567/-
8 Construction of CTC 3.820 6,05,939/-
9 Dismantle and Reconstruction of CTC 3.966 6,14,288/-
10 Construction of Road Bridge 4.890 9,30,742/-
11 Construction of CTC 6.180 6,04,817/-
12 Dismantle and Reconstruction of CTC 6.364 6,13,166/-
13 Construction of CTC 8.050 6,05,887/-
14 Dismantle and Reconstruction of CTC 8.301 6,14,237/-
15 Construction of CTC 9.377 6,06,709/-
16 Construction of CTC 10.930 6,10,790/-
17 Construction of CTC 10.980 6,10,790/-
18 Construction of CTC 11.220 6,10,790/-
TOTAL 1,09,03,098/-
109.03 Lakhs
8. Remodelling of Structures under Belgodhalla Channel
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1 Dismantling and Reconstruction of CTC 2.753 7,57,493/-
2 Dismantling and Reconstruction of CTC 3.150 7,54,602/-
3 Construction of CTC 4.110 6,54,547/-
4 Construction of CTC 5.010 6,50,881/-
5 Construction of Road Bridge 5.110 10,37,849/-
Details enclosed Refer
Volume-III of Annexure-
15, Page No.402
6 Construction of CTC 5.310 6,50,881/-
7 Construction of CTC 5.670 6,50,881/-
8 Dismantling and Reconstruction of CTC 7.310 6,38,762/-
9 Dismantling and Reconstruction of CTC 8.010 6,39,238/-
TOTAL 64,35,134/-
64.35 Lakhs
1 Construction of CTC 3.600 9,48,469/-
2 Construction of Retaining Wall 0.000 47,92,084/-
Details enclosed Refer
Volume-III of Annexure-
16, Page No.432
3 Dismantling and Reconstruction of CTC 5.665 8,67,924/-
4 Construction of CTC 7.200 8,36,732/-
5 Dismantling and Reconstruction of CTC 7.935 8,45,081/-
6 Construction of Sopanam (Washing Ghat) 5.700 2,41,702/-
7 Dismantling and Reconstruction of CTC 5.665 8,67,924/-
TOTAL 93,99,916/-
94.00 Lakhs
1 Dismantling and Reconstruction of CTC 1.179 9,81,130/-
2 Dismantling and Reconstruction of CTC 2.040 11,91,983/-
3 Dismantling and Reconstruction of CTC 2.335 11,91,983/-
4 Dismantling and Reconstruction of Foot Bridge 2.272 4,06,978/-
5 Dismantling and Reconstruction of CTC 3.128 11,93,103/-
6Dismantling and Reconstruction of Village Road
Bridge4.000 11,53,927/-
Details enclosed Refer
Volume-III of Annexure-
17, Page No.457
7 Dismantling and Reconstruction of CTC 5.160 5,23,086/-
8 Dismantling and Reconstruction of CTC 7.158 6,04,900/-
9 Dismantling and Reconstruction of CTC 7.234 6,04,900/-
10 Dismantling and Reconstruction of CTC 8.800 5,91,040/-
TOTAL 84,43,027/-
84.43 Lakhs
9. Remodelling of Structures under Deshnur Channel
10. Remodelling of Structures under Siruguppa Channel
11. Remodelling of Structures under Hulugi Channel
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1Dismantling and Reconstruction of Village
Road Bridge 0.152 13,58,665/-
2 Dismantling and Reconstruction of CTC 1.949 6,23,080/-
3Dismantling and Reconstruction of Village
Road Bridge 3.873 11,42,156/-
4Dismantling and Reconstruction of Village
Road Bridge 4.478 11,43,793/-
5Dismantling and Reconstruction of Village
Road Bridge 5.045 11,44,836/-
6 Dismantling and Reconstruction of CTC 6.442 8,00,389/-
7Dismantling and Reconstruction of Village
Road Bridge 6.475 11,54,543/-
TOTAL 73,67,464/-
73.67 Lakhs
1Dismantling and Reconstruction of Village Road
Bridge0.489 12,84,561/-
2 Dismantling and Reconstruction of CTC 7.624 7,33,372/-
3 Dismantling and Reconstruction of CTC 9.645 7,36,764/-
4 Dismantling and Reconstruction of CTC 9.826 7,36,734/-
5 Dismantling and Reconstruction of CTC 10.320 7,33,620/-
6 Construction of CTC 11.840 7,38,060/-
7 Dismantling and Reconstruction of CTC 13.364 7,37,664/-
8 Dismantling and Reconstruction of CTC 16.115 6,86,226/-
9 Dismantling and Reconstruction of CTC 17.044 7,29,783/-
10 Dismantling and Reconstruction of CTC 17.379 7,29,783/-
11 Construction of CTC 18.176 7,29,799/-
12 Dismantling and Reconstruction of CTC 18.753 7,29,799/-
13 Construction of Sopanam (Washing Ghat) 16.745 2,18,397/-
14Dismantling and Reconstruction of CTC and
Sopanam (Washing Ghat)18.176 3,20,435/-
15Dismantling and Reconstruction of Sopanam
(Washing Ghat)18.360 3,20,435/-
16Dismantling and Reconstruction of Sopanam
(Washing Ghat)18.616 3,20,435/-
17 Construction of Sopanam (Washing Ghat) 18.738 3,20,435/-
18 Construction of Cattle Ramp 15.569 2,27,152/-
Details enclosed Refer
Volume-III of Annexure-
18, Page No.489
19Dismantling and Reconstruction of Cattle Ramp
and Sopanam16.745 2,25,272/-
20 Construction of Cattle Ramp 17.389 2,24,280/-
21 Construction of Cattle Ramp 18.738 2,24,280/-
TOTAL 1,17,07,286/-
117.07 Lakhs
13. Remodelling of Structures under Anegundi Channel
12. Remodelling of Structures under Shivapura Channel
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1 Dismantling and Reconstruction of CTC 0.250 11,27,473/-
2 Dismantling and Reconstruction of VRB 4.099 13,60,334/-
3 Construction of Sopanam (Washing Ghat) 5.370 2,04,642/-
4 Dismantling and Reconstruction of CTC 5.535 10,94,872/-
5 Construction of Sopanam (Washing Ghat) 5.970 2,04,642/-
6 Dismantling and Reconstruction of CTC 6.214 7,05,401/-
7 Construction of Sopanam (Washing Ghat) 6.250 1,67,097/-
8 Construction of Sopanam (Washing Ghat) 6.270 1,67,097/-
9 Construction of Sopanam (Washing Ghat) 6.480 1,67,097/-
10 Construction of Sopanam (Washing Ghat) 6.510 1,55,084/-
11 Dismantling and Reconstruction of CTC 6.665 7,51,945/-
12 Dismantling and Reconstruction of CTC 8.697 6,37,060/-
13 Dismantling and Reconstruction of CTC 8.782 6,37,060/-
TOTAL 73,79,803/-
73.80 Lakhs
1 Dismantling and Reconstruction of CTC 1.700 12,54,172/-
2 Dismantling and Reconstruction of CTC 2.242 8,34,481/-
3 Dismantling and Reconstruction of CTC 5.790 8,13,175/-
4 Dismantling and Reconstruction of CTC 8.325 7,14,727/-
TOTAL 36,16,556/-
36.17 Lakhs
1 Dismantling and Reconstruction of CTC 0.315 10,38,855/-
2 Dismantling and Reconstruction of CTC 1.44 10,09,001/-
3 Dismantling and Reconstruction of CTC 2.103 10,44,565/-
4 Dismantling and Reconstruction of CTC 3.89 10,05,115/-
5 Dismantling and Reconstruction of CTC 10.83 4,58,137/-
6 Dismantling and Reconstruction of CTC 12.06 4,60,479/-
7 Dismantling and Reconstruction of CTC 12.834 4,60,479/-
8 Dismantling and Reconstruction of CTC 12.942 4,60,479/-
9 Dismantling and Reconstruction of CTC 13.145 4,61,658/-
10 Dismantling and Reconstruction of CTC 13.427 4,61,658/-
11 Dismantling and Reconstruction of CTC 14.195 4,61,658/-
TOTAL 73,22,083/-
73.22 Lakhs
16. Remodelling of Structures under Bichal Channel
14. Remodelling of Structures under Upper Gangavathi Channel
15. Remodelling of Structures under Lower Gangavathi Channel
Sl
No.Description
Amount
Rs in Lakhs
Construction of Escapes coming under entire Vijayanagar Channel
system(16 Nos.)
1 Raya Channel 68.93
2 Basavanna Channel 6.96
3 Bella Channel 24.86
4 Kalaghatta Channel 7.86
5 Turtha Channel 36.32
6 Ramasagara Channel 31.07
7 Kampli Channel 33.10
8 Belagodhalla Channel 25.67
9 Deshnur Channel 12.14
10 Siruguppa Channel 6.26
11 Hulugi Channel 41.06
12 Shivapura Channel 5.65
13 Anegundi Channel 233.69
14 Upper Gangavathi Channel 10.13
15 Lower Gangavathi Channel 18.14
561.84 Lakhs
COST OF H-ESCAPES Rs.561.84 LAKHS
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
H-Escapes
ABSTRACT
TOTAL
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1 Construction of Canal Escape 11.721 9,15,092/-
2 Construction of Canal Escape 15 .616 19,30,126/-
3Dismantling and Reconstruction of
Scouring Sluice2 .169
21,43,263/-
4Dismantling and Reconstruction of
Scouring Sluice3 .440
7,46,448/-
5 Construction of Scouring Sluice 8 .332 5,72,822/-
6Dismantling and Reconstruction of
Scouring Sluice22 .347
5,85,602/-
TOTAL 68,93,353/-
68.93 Lakhs
1 Construction of Canal Escape 10.9 6,95,798/-
TOTAL 6,95,798/-
6.96 Lakhs
1Dismantle and Reconstruction of
Scouring sluice 0.447 9,30,223/-
2Dismantle and Reconstruction of
Relieving Weir0.628 15,55,720/-
TOTAL 24,85,944/-
24.86 Lakhs
1Dismantle and Reconstruction of
Scouring sluice0.893 7,85,711/-
TOTAL 7,85,711/-
7.86 Lakhs
1 Construction of Canal Escape 0.000 4,75,627/-
2 Construction of Releiving Weir 0.880 19,11,947/-
Details enclosed Refer
Volume-III of Annexure-19,
Page No.504
3Dismantle and Reconstruction of
Scouring sluice1.221 5,88,954/-
Details enclosed Refer
Volume-III of Annexure-20,
Page No.525
4 Construction of Canal Escape 10.900 6,55,475/-
Details enclosed Refer
Volume-III of Annexure-21,
Page No.572
TOTAL 36,32,003/-
36.32 Lakhs
4. Remodelling of Structures under Kalaghatta Channel
5. Remodelling of Structures under Turtha Channel
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
H- Escapes
1. Remodelling of Structures under Raya Channel
2. Remodelling of Structures under Basavanna Channel
3. Remodelling of Structures under Bella Channel
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1Dismantling and Reconstruction of
Relieving Weir 2.200 20,46,598/-
2 Construction of Canal Escape 11.310 4,95,147/-
3 Construction of Canal Escape 13.718 5,65,204/-
TOTAL 31,06,950/-
31.07 Lakhs
1 Construction of Scouring sluice 1.150 5,55,577/-
2 Construction of Scouring sluice 1.320 5,55,577/-
3 Construction of Scouring sluice 2.070 5,52,101/-
4 Construction of Scouring sluice 3.150 5,76,084/-
5Dismantle and Reconstruction of
Scouring sluice5.548 5,85,725/-
6 Construction of Scouring sluice 14.050 4,85,407/-
TOTAL 33,10,469/-
33.10 Lakhs
1 Construction of Scouring Sluice 4.32 4,30,713/-
2
Dismantle and Reconstruction of
Scouring Sluice 4.545 4,32,080/-
3 Construction of Scouring Sluice 7.33 4,30,554/-
4
Dismantle and Reconstruction of
Scouring Sluice7.567 4,22,922/-
5 Construction of Scouring Sluice 10.72 4,20,177/-
6
Dismantle And Reconstruction of
Scouring Sluice 11.001 4,30,544/-
TOTAL 25,66,990/-
25.67 Lakhs
1Dismantling and Reconstruction of
Scouring sluice0.305 5,81,783/-
2Dismantling and Reconstruction of
Scouring sluice1.41 6,32,364/-
TOTAL 12,14,146/-
12.14 Lakhs
1 Construction of Scouring Sluice 0.362 6,25,869/-
TOTAL 6,25,869/-
6.26 Lakhs
6. Remodelling of Structures under Ramasagara Channel
7. Remodelling of Structures under Kampli Channel
8. Remodelling of Structures under Belgodhalla Channel
9. Remodelling of Structures under Deshnur Channel
10. Remodelling of Structures under Siruguppa Channel
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1Dismantling and Reconstruction of
Scouring Sluice0.219 3,43,333/-
2Dismantling and Reconstruction of
Scouring Sluice0.317 3,43,333/-
3Dismantling and Reconstruction of
Scouring Sluice0.585 3,43,333/-
4Dismantling and Reconstruction of
Scouring Sluice0.990 3,43,333/-
5Dismantling and Reconstruction of
Scouring Sluice3.216 4,96,413/-
6 Construction of Canal Escape 4.277 3,46,469/-
7Dismantling and Reconstruction of
Scouring Sluice7.393 9,44,679/-
8Dismantling and Reconstruction of
Scouring Sluice7.600 9,44,679/-
TOTAL 41,05,571/-
41.06 Lakhs
1Dismantling and Reconstruction of
Scouring Sluice 3.510 5,65,088/-
TOTAL 5,65,088/-
5.65 Lakhs
11. Remodelling of Structures under Hulugi Channel
12. Remodelling of Structures under Shivapura Channel
Sl.No Type of structure Chainage in KmAmount in
RupeesRemarks
1Dismantling and Reconstruction of
Escape0.024 16,79,450/-
2Dismantling and Reconstruction of
Escape0.754 13,85,348/-
3Dismantling and Reconstruction of
Escape2.843 13,86,783/-
4Dismantling and Reconstruction of
Escape cum Releiving Weir 3.400 15,19,897/-
5Dismantling and Reconstruction of
Escape cum Releiving Weir 8.900 21,86,227/-
6Dismantling and Reconstruction of
Releiving Weir 5.799 20,40,221/-
7 Construction of Releiving Weir 9.502 18,14,722/-
8Dismantling and Reconstruction of
Releiving Weir 11.435 15,09,483/-
9Dismantling and Reconstruction of
Releiving Weir 11.725 15,09,483/-
10Dismantling and Reconstruction of
Releiving Weir 11.850 15,09,483/-
11Dismantling and Reconstruction of
Releiving Weir 14.376 16,04,293/-
12Dismantling and Reconstruction of
Releiving Weir 14.800 16,04,293/-
13Dismantling and Reconstruction of
Releiving Weir 15.760 14,91,087/-
14 Construction of Releiving Weir 18.736 21,27,983/-
TOTAL 2,33,68,753/-
233.69 Lakhs
1
Dismantling and Reconstruction of
Canal Escape7.44 10,13,446/-
TOTAL 10,13,446/-
10.13 Lakhs
1Dismantling and Reconstruction of
Scouring Sluice 0.000 7,22,015/-
2Dismantling and Reconstruction of
Escape cum CTC 3.150 10,92,022/-
TOTAL 18,14,037/-
18.14 Lakhs
14. Remodelling of Structures under Upper Gangavathi Channel
15. Remodelling of Structures under Lower Gangavathi Channel
13. Remodelling of Structures under Anegundi Channel
Sl
No.Description No.
Plinth Area
(Sq Ft)
Rate/Sq ft in
Rs
Amount
Rs in Lakhs
Non - Residential Buildings
1 Construction of office Building 1 2000 1750 35.00
Residential Buildings
2 Construction of AEE Quarters 1 1200 2000 24.00
3 Construction of 3 Nos AE Quarters 2 900 2000 36.00
4 Construction of Staff quarters (5 Nos) 5 600 2000 60.00
155.00
Note: Rates is as per SR of State PWD Circle, Bellary
All the above Residential and Non-Residential Buildings are permanent one which is exclusively
meant for operation and maintainance of Canal Network.As such item Receipts & Recoveries on
capital accounts on Buildings is Nil
Works under Head works Sub division
TOTAL
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
K - Buildings
COST OF K - Buildings = Rs.155.00 LAKHS
Sl
No.Description
Amount
Rs in Lakhs
Remodelling of Main Canal
1 Raya Channel 3423.52
2 Basavanna Channel 1291.70
3 Bella Channel 544.41
4 Kalaghatta Channel 611.03
5 Turtha Channel 1845.46
6 Ramasagara Channel 1567.33
7 Kampli Channel 1685.75
8 Belagodhalla Channel 649.03
9 Deshnur Channel 607.59
10 Siruguppa Channel 946.81
11 Hulugi Channel 887.76
12 Shivapura Channel 411.45
13 Anegundi Channel 2881.60
14 Upper Gangavathi Channel 1278.95
15 Lower Gangavathi Channel 1056.00
16 Bichal Channel 933.14
Total = 20621.53
`
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
L- Earth Work,Lining,Formation of Service Roads for Canals.
ABSTRACT
COST OF L-EARTHWORK Rs.20621.53 LAKHS
No. Particulars Cost( in Rupees) Remarks
1 Estimates for Earthwork and Lining for Km 1 1,54,79,772/-
2 Estimates for Earthwork and Lining for Km 2 1,65,66,608/-
3 Estimates for Earthwork and Lining for Km 3 1,63,38,424/-
4 Estimates for Earthwork and Lining for Km 4 1,51,66,652/-
5 Estimates for Earthwork and Lining for Km 5 1,33,64,031/-
6 Estimates for Earthwork and Lining for Km 6 1,42,44,897/-
7 Estimates for Earthwork and Lining for Km 7 1,87,09,235/-
8 Estimates for Earthwork and Lining for Km 8 1,88,10,719/-
9 Estimates for Earthwork and Lining for Km 9 1,40,69,969/-
10 Estimates for Earthwork and Lining for Km 10 1,44,98,098/-
11 Estimates for Earthwork and Lining for Km 11 1,35,55,412/-
12 Estimates for Earthwork and Lining for Km 12 1,46,70,031/-
13 Estimates for Earthwork and Lining for Km 13 1,51,18,666/-
14 Estimates for Earthwork and Lining for Km 14 1,18,34,292/-
15 Estimates for Earthwork and Lining for Km 15 1,34,65,956/-
16 Estimates for Earthwork and Lining for Km 16 1,29,47,262/-
17 Estimates for Earthwork and Lining for Km 17 94,18,686/-
18 Estimates for Earthwork and Lining for Km 18 92,48,686/-
19 Estimates for Earthwork and Lining for Km 19 1,23,88,118/-
20 Estimates for Earthwork and Lining for Km 20 94,95,459/-
21 Estimates for Earthwork and Lining for Km 21 86,86,729/-
22 Estimates for Earthwork and Lining for Km 22 97,37,809/-
23 Estimates for Earthwork and Lining for Km 23 91,87,577/-
24 Estimates for Earthwork and Lining for Km 24 84,92,699/-
25 Estimates for Earthwork and Lining for Km 25 85,99,780/-
26 Estimates for Earthwork and Lining for Km 26 86,39,236/-
27 Estimates for Earthwork and Lining for Km 27.6 1,03,25,665/-
28 Deduct Lining Cost for Structures -7,08,494
TOTAL 34,23,51,974/-
Rs 3423.52 Lakhs
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
ABSTRACT ESTIMATE FOR EARTHWORK , LINING AND FORMATION OF SERVICE ROAD UNDER
MODERNISATION OF VIJAYANAGARA CHANNELS.
L - WORKS
1. Remodelling of Raya Channel
No. Particulars Cost( in Rupees) Remarks
1 Estimates for Earthwork and Lining for Km 1 87,19,237/-
2 Estimates for Earthwork and Lining for Km 2 88,60,653/-
3 Estimates for Earthwork and Lining for Km 3 86,73,798/-
4 Estimates for Earthwork and Lining for Km 4 84,27,834/-
5 Estimates for Earthwork and Lining for Km 5 80,82,383/-
6 Estimates for Earthwork and Lining for Km 6 81,16,560/-
7 Estimates for Earthwork and Lining for Km 7 76,93,858/-
8 Estimates for Earthwork and Lining for Km 8 76,03,795/-
9 Estimates for Earthwork and Lining for Km 9 76,34,523/-
10 Estimates for Earthwork and Lining for Km 10 78,43,083/-
11 Estimates for Earthwork and Lining for Km 11 79,03,842/-
12 Estimates for Earthwork and Lining for Km 12 79,33,844/-
13 Estimates for Earthwork and Lining for Km 13 67,84,600/-
14 Estimates for Earthwork and Lining for Km 14 73,24,858/-
15 Estimates for Earthwork and Lining for Km 15 77,72,871/-
16 Estimates for Earthwork and Lining for Km 16 62,29,568/-
17 Estimates for Earthwork and Lining for Km 16.5 42,10,039/-
18 Deduct Lining Cost for Structures -6,45,143 /-
TOTAL 12,91,70,203/-
Rs 1291.70 Lakhs
1 Estimates for Earthwork and Lining for Km 1 78,02,099/-
2 Estimates for Earthwork and Lining for Km 2 1,50,54,712/-
3 Estimates for Earthwork and Lining for Km 3 9,44,495/-
4 Estimates for Earthwork and Lining for Km 4 1,56,90,483/-
5 Estimates for Earthwork and Lining for Km 5 84,57,289/-
6 Estimates for Earthwork and Lining for Km 5.5 69,91,125/-
7 Deduct Lining Cost for Structures -4,99,456/-
TOTAL 5,44,40,747/-
Rs 544.41 Lakhs
1 Estimates for Earthwork and Lining for Km 1 94,31,020/-
2 Estimates for Earthwork and Lining for Km 2 85,79,328/-
3 Estimates for Earthwork and Lining for Km 3 56,96,975/-
4 Estimates for Earthwork and Lining for Km 4 96,59,216/-
5 Estimates for Earthwork and Lining for Km 5 95,37,422/-
6 Estimates for Earthwork and Lining for Km 6 84,42,011/-
7 Estimates for Earthwork and Lining for Km 7.2 98,33,766/-
8 Deduct Lining Cost for Structures -76,475/-
TOTAL 6,11,03,262/-
Rs 611.03 Lakhs
3. Remodelling of Bella Channel
2. Remodelling of Basavanna Channel
4. Remodelling of Kalaghatta Channel
No. Particulars Cost( in Rupees) Remarks
1 Estimates for Earthwork and Lining for Km 1 1,11,74,219/-
Details enclosed Refer
Volume-III of Annexure-22,
Page No.622
2 Estimates for Earthwork and Lining for Km 2 1,13,53,337/-
3 Estimates for Earthwork and Lining for Km 3 1,10,62,435/-
4 Estimates for Earthwork and Lining for Km 4 1,08,75,507/-
5 Estimates for Earthwork and Lining for Km 5 1,02,83,157/-
6 Estimates for Earthwork and Lining for Km 6 1,07,60,852/-
7 Estimates for Earthwork and Lining for Km 7 1,06,83,952/-
8 Estimates for Earthwork and Lining for Km 8 1,00,83,626/-
9 Estimates for Earthwork and Lining for Km 9 96,94,056/-
10 Estimates for Earthwork and Lining for Km 10 99,81,898/-
11 Estimates for Earthwork and Lining for Km 11 99,75,490/-
12 Estimates for Earthwork and Lining for Km 12 1,08,08,782/-
13 Estimates for Earthwork and Lining for Km 13 90,28,363/-
14 Estimates for Earthwork and Lining for Km 14 97,63,501/-
15 Estimates for Earthwork and Lining for Km 15 1,03,43,039/-
16 Estimates for Earthwork and Lining for Km 16 81,69,862/-
17 Estimates for Earthwork and Lining for Km 17 83,46,545/-
18 Estimates for Earthwork and Lining for Km 18.692 1,27,01,816/-
19 Deduct Lining Cost for Structures -5,44,617/-
Details enclosed Refer
Volume-III of Annexure-22,
Page No.641
TOTAL 18,45,45,820/-
Rs 1845.46 Lakhs
5. Remodelling of Turtha Channel
No. Particulars Cost( in Rupees) Remarks
1 Estimates for Earthwork and Lining for Km 1 1,19,49,295/-
2 Estimates for Earthwork and Lining for Km 2 1,16,70,587/-
3 Estimates for Earthwork and Lining for Km 3 1,15,36,086/-
4 Estimates for Earthwork and Lining for Km 4 1,17,01,977/-
5 Estimates for Earthwork and Lining for Km 5 1,12,07,474/-
6 Estimates for Earthwork and Lining for Km 6 1,21,33,240/-
7 Estimates for Earthwork and Lining for Km 7 1,03,35,919/-
8 Estimates for Earthwork and Lining for Km 8 94,06,068/-
9 Estimates for Earthwork and Lining for Km 9 91,15,240/-
10 Estimates for Earthwork and Lining for Km 10 95,26,732/-
11 Estimates for Earthwork and Lining for Km 11 99,66,122/-
12 Estimates for Earthwork and Lining for Km 12 95,35,910/-
13 Estimates for Earthwork and Lining for Km 13 92,05,254/-
14 Estimates for Earthwork and Lining for Km 14 86,15,003/-
15 Estimates for Earthwork and Lining for Km 15.386 1,19,56,759/-
16 Deduct Lining Cost for Structures -11,28,609/-
TOTAL 15,67,33,055/-
Rs 1567.33 Lakhs
1 Estimates for Earthwork and Lining for Km 1 74,35,572/-
2 Estimates for Earthwork and Lining for Km 2 79,75,878/-
3 Estimates for Earthwork and Lining for Km 3 80,18,323/-
4 Estimates for Earthwork and Lining for Km 4 82,75,875/-
5 Estimates for Earthwork and Lining for Km 5 50,79,755/-
6 Estimates for Earthwork and Lining for Km 6 84,86,354/-
7 Estimates for Earthwork and Lining for Km 7 82,17,206/-
8 Estimates for Earthwork and Lining for Km 8 81,86,501/-
9 Estimates for Earthwork and Lining for Km 9 77,10,058/-
10 Estimates for Earthwork and Lining for Km 10 78,29,497/-
11 Estimates for Earthwork and Lining for Km 11 79,53,836/-
12 Estimates for Earthwork and Lining for Km 12 80,97,969/-
13 Estimates for Earthwork and Lining for Km 13 78,51,627/-
14 Estimates for Earthwork and Lining for Km 14 79,63,833/-
15 Estimates for Earthwork and Lining for Km 15 67,85,445/-
16 Estimates for Earthwork and Lining for Km 16 75,01,232/-
17 Estimates for Earthwork and Lining for Km 17 70,80,188/-
18 Estimates for Earthwork and Lining for Km 18 64,22,426/-
19 Estimates for Earthwork and Lining for Km 19 62,90,346/-
20 Estimates for Earthwork and Lining for Km 20 62,99,875/-
21 Estimates for Earthwork and Lining for Km 21 54,74,419/-
7. Remodelling of Kampli Channel
6. Remodelling of Ramasagara Channel
No. Particulars Cost( in Rupees) Remarks
22 Estimates for Earthwork and Lining for Km 22 57,57,861/-
23 Estimates for Earthwork and Lining for Km 23.55 88,17,064/-
24 Deduct Lining Cost for Structures -9,35,730
TOTAL 16,85,75,410/-
Rs 1685.75 Lakhs
1 Estimates for Earthwork and Lining for Km 1 64,05,264/-
2 Estimates for Earthwork and Lining for Km 2 62,68,616/-
3 Estimates for Earthwork and Lining for Km 3 60,51,742/-
4 Estimates for Earthwork and Lining for Km 4 59,28,189/-
5 Estimates for Earthwork and Lining for Km 5 60,33,132/-
6 Estimates for Earthwork and Lining for Km 6 49,66,926/-
7 Estimates for Earthwork and Lining for Km 7 54,43,462/-
8 Estimates for Earthwork and Lining for Km 8 57,01,197/-
9 Estimates for Earthwork and Lining for Km 9 55,82,278/-
10 Estimates for Earthwork and Lining for Km 10 56,95,595/-
11 Estimates for Earthwork and Lining for Km 11.22 69,42,525/-
12 Deduct Lining Cost for Structures -1,15,898
TOTAL 6,49,03,028/-
Rs 649.03 Lakhs
1 Estimates for Earthwork and Lining for Km 1 1,00,11,569/-
2 Estimates for Earthwork and Lining for Km 2 77,74,464/-
3 Estimates for Earthwork and Lining for Km 3 71,73,114/-
4 Estimates for Earthwork and Lining for Km 4 72,03,935/-
5 Estimates for Earthwork and Lining for Km 5 57,41,265/-
6 Estimates for Earthwork and Lining for Km 6 56,85,321/-
7 Estimates for Earthwork and Lining for Km 7 55,75,114/-
8 Estimates for Earthwork and Lining for Km 8 55,81,867/-
9 Estimates for Earthwork and Lining for Km 9 60,11,963/-
TOTAL 6,07,58,612/-
Rs 607.59 Lakhs
8. Remodelling of Belgodhalla Channel
9. Remodelling of Deshnur Channel
No. Particulars Cost( in Rupees) Remarks
1 Estimates for Earthwork and Lining for Km 1 1,01,68,647/-
2 Estimates for Earthwork and Lining for Km 2 1,02,48,901/-
3 Estimates for Earthwork and Lining for Km 3 1,12,63,291/-
4 Estimates for Earthwork and Lining for Km 4 1,16,41,685/-
5 Estimates for Earthwork and Lining for Km 5 90,66,717/-
6 Estimates for Earthwork and Lining for Km 6 98,97,942/-
7 Estimates for Earthwork and Lining for Km 7 74,73,246/-
8 Estimates for Earthwork and Lining for Km 8 73,65,085/-
9 Estimates for Earthwork and Lining for Km 9 69,35,216/-
10 Estimates for Earthwork and Lining for Km 10.85 1,07,07,399/-
11 Deduct Lining Cost for Structures -87,344/-
TOTAL 9,46,80,785/-
Rs 946.81 Lakhs
1 Earthwork of Canal including cost of lining 0 - 1 Km 87,07,620/-
2 Earthwork of Canal including cost of lining 1 - 2 Km 88,06,666/-
3 Earthwork of Canal including cost of lining 2 - 3 Km 83,64,822/-
4 Earthwork of Canal including cost of lining 3 - 4 Km 81,21,358/-
5 Earthwork of Canal including cost of lining 4 - 5 Km 94,00,829/-
6 Earthwork of Canal including cost of lining 5 - 6 Km 93,32,418/-
7 Earthwork of Canal including cost of lining 6 - 7 Km 85,13,349/-
8 Earthwork of Canal including cost of lining 7 - 8 Km 79,21,442/-
9 Earthwork of Canal including cost of lining 8 - 9 Km 76,55,035/-
10 Earthwork of Canal including cost of lining 9 - 10 Km 73,34,008/-
11 Earthwork of Canal including cost of lining 10-10.692 Km 48,10,000/-
12 Deduct Lining Cost for Structures -1,91,382/-
TOTAL 8,87,76,165/-
Rs 887.76 Lakhs
1 Estimates for Earthwork and Lining for Km 1 83,03,561/-
2 Estimates for Earthwork and Lining for Km 2 59,50,619/-
3 Estimates for Earthwork and Lining for Km 3 60,00,708/-
4 Estimates for Earthwork and Lining for Km 4 61,21,292/-
5 Estimates for Earthwork and Lining for Km 5 60,95,831/-
6 Estimates for Earthwork and Lining for Km 6 58,27,586/-
7 Estimates for Earthwork and Lining for Km 7 32,18,752/-
8 Deduct Lining Cost for Structures -3,73,665/-
TOTAL 4,11,44,683/-
Rs 411.45 Lakhs
11. Remodelling of Hulugi Channel
10. Remodelling of Siruguppa Channel
12. Remodelling of Shivapura Channel
No. Particulars Cost( in Rupees) Remarks
1 Estimates for Earthwork and Lining for Km 1 1,52,14,935/-
2 Estimates for Earthwork and Lining for Km 2 1,42,58,405/-
3 Estimates for Earthwork and Lining for Km 3 1,64,17,796/-
4 Estimates for Earthwork and Lining for Km 4 1,64,92,322/-
5 Estimates for Earthwork and Lining for Km 5 1,58,47,372/-
6 Estimates for Earthwork and Lining for Km 6 1,67,06,102/-
7 Estimates for Earthwork and Lining for Km 7 1,48,92,138/-
8 Estimates for Earthwork and Lining for Km 8 1,43,55,924/-
9 Estimates for Earthwork and Lining for Km 9 1,41,69,963/-
10 Estimates for Earthwork and Lining for Km 10 1,55,57,250/-
11 Estimates for Earthwork and Lining for Km 11 1,37,30,544/-
12 Estimates for Earthwork and Lining for Km 12 1,51,05,735/-
13 Estimates for Earthwork and Lining for Km 13 1,31,78,438/-
14 Estimates for Earthwork and Lining for Km 14 1,67,60,488/-
15 Estimates for Earthwork and Lining for Km 15 1,59,07,867/-
16 Estimates for Earthwork and Lining for Km 16 1,24,50,361/-
17 Estimates for Earthwork and Lining for Km 17 1,54,42,819/-
18 Estimates for Earthwork and Lining for Km 18 1,51,25,473/-
19 Estimates for Earthwork and Lining for Km 19.44 1,84,26,450/-
20 Deduct Lining Cost for Structures -18,79,891/-
TOTAL 28,81,60,490/-
Rs 2881.60 Lakhs
1 Estimates for Earthwork and Lining for Km 1 1,64,77,233/-
2 Estimates for Earthwork and Lining for Km 2 1,95,25,435/-
3 Estimates for Earthwork and Lining for Km 3 1,56,31,309/-
4 Estimates for Earthwork and Lining for Km 4 2,20,07,755/-
5 Estimates for Earthwork and Lining for Km 5 1,42,37,048/-
6 Estimates for Earthwork and Lining for Km 6 1,45,65,839/-
7 Estimates for Earthwork and Lining for Km 7 1,09,59,184/-
8 Estimates for Earthwork and Lining for Km 8 90,61,505/-
9 Estimates for Earthwork and Lining for Km 9.03 81,78,973/-
10 Deduct Lining Cost for Structures -27,48,883/-
TOTAL 12,78,95,398/-
Rs 1278.95 Lakhs
14. Remodelling of Upper Gangavathi Channel
13. Remodelling of Anegundi Channel
No. Particulars Cost( in Rupees) Remarks
1 Estimates for Earthwork and Lining for Km 1 1,14,08,253/-
2 Estimates for Earthwork and Lining for Km 2 1,21,78,708/-
3 Estimates for Earthwork and Lining for Km 3 1,13,38,353/-
4 Estimates for Earthwork and Lining for Km 4 1,07,31,509/-
5 Estimates for Earthwork and Lining for Km 5 1,04,71,646/-
6 Estimates for Earthwork and Lining for Km 6 1,31,71,089/-
7 Estimates for Earthwork and Lining for Km 7 1,16,71,452/-
8 Estimates for Earthwork and Lining for Km 8 1,05,89,778/-
9 Estimates for Earthwork and Lining for Km 9 76,80,550/-
10 Estimates for Earthwork and Lining for Km 9.54 68,36,513/-
11 Deduct Lining Cost for Structures -4,78,129/-
TOTAL 10,55,99,722/-
Rs 1056.00 Lakhs
1 Estimates for Earthwork and Lining for Km 1 67,83,960/-
2 Estimates for Earthwork and Lining for Km 2 69,34,425/-
3 Estimates for Earthwork and Lining for Km 3 65,28,897/-
4 Estimates for Earthwork and Lining for Km 4 68,71,047/-
5 Estimates for Earthwork and Lining for Km 5 70,96,298/-
6 Estimates for Earthwork and Lining for Km 6 85,36,597/-
7 Estimates for Earthwork and Lining for Km 7 58,54,046/-
8 Estimates for Earthwork and Lining for Km 8 59,20,989/-
9 Estimates for Earthwork and Lining for Km 9 57,36,208/-
10 Estimates for Earthwork and Lining for Km 10 59,41,438/-
11 Estimates for Earthwork and Lining for Km 11 51,05,371/-
12 Estimates for Earthwork and Lining for Km 12 61,32,141/-
13 Estimates for Earthwork and Lining for Km 13 61,76,966/-
14 Estimates for Earthwork and Lining for Km 14.52 96,95,705/-
TOTAL 9,33,14,087/-
Rs 933.14 Lakhs
15. Remodelling of Lower Gangavathi Channel
16. Remodelling of Bichal Channel
Sl No. Unit QuantityRate
(in Rs)
Amount in
Rs.
1KM
Approach Channel 0.57 31500.07 17,955/-
Raya Channel 27.74 31500.07 8,73,812/-
Basavanna Channel 16.50 31500.07 5,19,751/-
Bella Channel 5.50 31500.07 1,73,250/-
Kalaghatta Channel 7.00 31500.07 2,20,500/-
Turtha Channel 18.70 31500.07 5,89,051/-
Ramasagara Channel 15.50 31500.07 4,88,251/-
Kampli Channel 23.50 31500.07 7,40,252/-
Belagodhalla Channel 11.20 31500.07 3,52,801/-
Deshnur Channel 9.00 31500.07 2,83,501/-
Siruguppa Channel 10.80 31500.07 3,40,201/-
Hulugi Channel 10.70 31500.07 3,37,051/-
Shivapurra Channel 6.50 31500.07 2,04,750/-
Anegundi Channel 19.50 31500.07 6,14,251/-
Upper Gangavathi Channel 9.00 31500.07 2,83,501/-
Lower Gangavathi Channel 9.50 31500.07 2,99,251/-
Bichal Channel 14.50 31500.07 4,56,751/-
Total Length 215.71 67,94,880/-
Say Rs. (in Lakhs) 67.95
Providing trees along the Vijayanagar Channels
including protection, watering etc complete
COST OF M- PLANTATION Rs. 67.95 LAKHS
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
M - PLANTATION
Types of structures
NO.SSR I
NOPARTICULARS OF WORK QUANTITY RATE PER AMOUNT
1 2 3 4 5 6 7
1 129
Aligning the planting area along the
contours and marking for pits (without
stacking)28 300 1000 8.40
.
2 130
Excavation of pits of size 1mx1mx1m in
hard soil with vertically cut edges to
make uniform cube 7 heaping the
excavated soil on the lower side of the
pits(1/3rd top soil to be deposited on the
upper side 2/3rd on thelower side)1.00mx1.00mx1.00mm=250.00pits
==>250.0 Cum 134.00 90 Pit 12060.00
3 131
Refilling of pits,cutting of edge of the pit
on the lower side and refilling 75% of the
pit with the excavated soil,duly breaking
the clods & information of sucer shaped
mound on the lower sude of the pit of
size 1mx1mx1m1.00mx1.00mx1.00mm=250.00pits
==>250.0 Cum 134.00 10 pit 1340.00
4 86(f)
Loading of 8-10 ft. tall seedlings raised
in the H.D.P.E bags of size 14" x 20" into
the truck at the nursery site and
unloading nearest to the(irrespective of
the distance)
134.00 15 Each 2010.00
5 87(f)
Transportation of 14" X 20" P.B.
Seedlings in hired truck from the nursery
site to planting site.Distance from 31-
40kms.
134.00 8000.00 1000.00 1072.00
6 R.Q
Provindin 8- 10 feet along & 15 -20cms
grith plantation stakes treated with coal
tar at the bottom of the stakes up to 3
feet.
27 12 Each 324.00
ANNEXURE NO-16
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
M - PLANTATION
Length considered- 1000 m (1 Km)
No. of plants required per Km = '(1000/15) x 2 = 134 nos
NO.SSR I
NOPARTICULARS OF WORK QUANTITY RATE PER AMOUNT
1 2 3 4 5 6 7
7 132
Conveyance of tall seedlings raised in
HDPE bas of size 14" x 20" from the
dumping point to the planting site near
each pit on head load,fixing the
supporting stake firmly in the pit,planting
the tall seedling to the supporting stake
at 3 points.
134.00 10 Each 1340.00
8 M.RProcuring of Bindings wire @ 35
Plants/kg.20 40 kg 800.00
9 M.RProcuring of Bindings wire @20
grams/Plant.20 60 kg 1200.00
10 M.R Procuring of DAP wire @ 35 Plants/kg. 20 30 kg 600.00
11 133
Curring and collection of P.J. branches
loading the same into the lorry and
unloading at the planting site(8-
10branches/tall plant.)
134.000 15.00 Each 2010.00
12 134
Convenyance of P.J Branches to
individual pit,tying P.J branches around
the supporting stake properly converting
the tall plant with P.J thorny branches to
a height more than 2m and tying the P.J
branches G.I.Wire at 3 places (10 P.J
branches to be used)
134.000 6.30 Each 844.20
13 100
Apllication of lime/chemical fertiliser
around the plants about 15cm,away in a
furrow duly covering the soil(excluding
the cost of materials)
25.000 70.80 1000.00 1.77
14 135I weeding around the plants (pits) to a
radius of 60cm 134.000 1500.00 1000.00 201.00
15 137
Scraping of grass and other growth
around the tall plant to a radius of 1.00
m planted pits.(for 0.75m 3 pits only) 27.000 2500.00 1000.00 67.50
NO.SSR I
NOPARTICULARS OF WORK QUANTITY RATE PER AMOUNT
1 2 3 4 5 6 7
16 138
Saucer Bhavan to the plant with semi-
circular bound on the lower slope with
one meter distance between the ends of
two arms of the bund.
27.000 4.30 Each 116.10
17 139 Watering to the plants planted in the
pits/trench along roadside and in the city
limits at 50litres/plant.By Hiring the
private vehicle 2 times.
54.000 7.15 Each 386.10
18 Cost of poly based seedlings - - - 6500.00
19Add for miscellaneous and rounding off 619.00
Total = 31,500/-
Rs. 31,500 /-
The Rates considered for each item under M plantation ia as per as per SR of State Forest
Department
Range Forest Officer
Note: Rate of each item is as per SR of State Forest Department
Cost per Km of Plantation=
Sl
No.Description Unit Quantity
Rate
(Rs)
Amount
Rs in Lakhs
Purchasing Bollero Van for Sub-division office No. 5 8,09,136/- 40.46
40.46 Lakhs
COST OF SPECIAL TOOLS AND PLANTS Rs.40.46 LAKHS
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
Q- SPECIAL TOOLS AND PLANTS
ABSTRACT
TOTAL
Sl
No.Description Unit Qty Rate in Rs
Amount
Rs in Lakhs
Bolero Van for following sub-division
1AEE , Vijayanagar canal sub division,
KamalapurNo 1 809136 8.09
2AEE , No.1 canal sub division, Agalkera
No 1 809136 8.09
3 AEE , Vaddarahatti sub division No 1 809136 8.09
4 AEE , Siruguppa sub division No 1 809136 8.09
5 AEE , Yaramarus sub division No 1 809136 8.09TOTAL 40.46 Lakhs
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
Q- SPECIAL TOOLS AND PLANTS
Note: Rate for 1 no. of Bolero Van as per Quotation by M/S Bellary Motor Sales Pvt. Ltd., Bellary ( Copy
enclosed)
TOTAL COST OF Q- SPECIAL TOOLS AND PLANTS Rs. 40.46 LAKHS
Sl
No.Description
Amount
Rs in Lakhs
1Distributaries Network and Minors for 16 canals under Vijayanagar
Channels 5454.41 Lakhs
5454.41 Lakhs
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
U-DISTRIBUTARIES AND MINORS
TOTAL
ABSTRACT
COST OF U-WORKS Rs.5454.41 LAKHS
Executive Engineer
Details of Distributary System :
Total No. canals under Vijayanagar Channels = 16 Nos.
Total CCA of 16 Channels = 11154 ha.
Details estimate for distributary network of 10% CCA covering
No CCA in Ha
1 600
2 620
1220
1)
2)
= Rs 5,96,59,099 /-
5,96,59,099 /-
1220
Rs 3,93,75,239 /-
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
U-DISTRIBUTARIES & MINORS
Modernisation of Bella Channel
Modernisation of Kampli Channel
Particulars
TOTAL
Note: Detailed estimate for Item No 1 = Rs 2,02,83,859/- and item No 2 = 3,93,75,239/- is appended
saperately as Volume IV
Total amount for 1220 ha
=Rate per 1 ha of CCA = Rs 48,901 /ha
Total cost for distributary network of Bella canal
( 600 ha)= Rs 2,02,83,859 /-
Total cost for distributary network of Kampli canal (
620 ha)=
Executive Engineer
Details of Distributary System :
No ParticularsDistributary
Length in Km
Minor Length
in KmCCA in Ha
1 Raya Channel 1.313 44.595 2226
2 Basavanna Channel 4.36 9.286 1240
3 Bella Channel 0.9 7.951 600
4 Kalaghatta Channel 16.6 237
5 Turtha Channel 931
6 Ramasagara Channel 7.65 23.33 673
7 Kampli Channel 1.5 18.69 620
8 Belagodhalla Channel 5.63 210
9 Deshnur Channel 3.62 478
10Siruguppa Channel 3.93 764
11 Hulugi Channel 4.44 265
12 Shivapura Channel 4.05 2.4 403
13 Anegundi Channel 4.72 789
14 Upper Gangavathi Channel 11.695 5.37 775
15 Lower Gangavathi Channel 15.44 1.51 667
16 Bichal Channel 276
TOTAL 46.908 152.072 11154
= 11154 x 48,901
=
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
U-DISTRIBUTARIES & MINORS
Cost for distributary network of 16 canals under Vijayangar Channels
covering 11154 ha of CCA= Rs 48,901 /ha
Rs 54,54,40,644 /-
Total Cost = 5454.41 Lakhs
No. Particulars Cost( in Rupees) Remarks
1Estimates for Earthwork of Narsapura Branch Canal
including cost of lining 18,42,132/-
Details enclosed
Refer Volume-IV,
Page No.5
2 Earthwork and Lining of Minor-1 of Bella Canal 25,81,914/-
Details enclosed
Refer Volume-IV,
Page No.18
3 Earthwork and Lining of Minor-2 of Bella Canal 12,56,308/-
Details enclosed
Refer Volume-IV,
Page No.31
4 Earthwork and Lining of Minor-3 of Bella Canal 15,03,812/-
5 Earthwork and Lining of Minor-4 of Bella Canal 21,40,107/-
6 Earthwork and Lining of Minor-5 of Bella Canal 28,11,646/-
7 Earthwork and Lining of Minor-6 of Bella Canal 21,40,107/-
8 Earthwork and Lining of Minor-7 of Bella Canal 16,29,824/-
9Estimates for Retaining wall of Narsapura Branch
Canal 30,92,246/-
Details enclosed
Refer Volume-IV,
Page No.42
10Estimates for Drop at Ch. 0+782 Km of Narsapura
Branch Canal 3,69,562/-
Details enclosed
Refer Volume-IV,
Page No.54
11Estimates for Distribution Box at Ch. 0+900 Km (Tail
end) of Narsapura Branch Canal 7,82,021/-
Details enclosed
Refer Volume-IV,
Page No.73
12 Estimates for Silt removal for DPO - 1 24,639/-
Details enclosed
Refer Volume-IV,
Page No.89
13 Estimates for Silt removal for DPO - 2 11,982/-
Details enclosed
Refer Volume-IV,
Page No.91
14 Estimates for Silt removal for DPO - 3 14,345/-
Details enclosed
Refer Volume-IV,
Page No.93
15 Estimates for Silt removal for DPO - 4 20,420/-
16 Estimates for Silt removal for DPO - 5 26,833/-
17 Estimates for Silt removal for DPO - 6 20,420/-
18 Estimates for Silt removal for DPO - 7 15,543/-
TOTAL 2,02,83,859/-
Rs 202.84 Lakhs
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
DETAIL ESTIMATE FOR DISTRIBUTARY NETWORK OF BELLA CANAL = CCA 600 Ha
U-DISTRIBUTARIES & MINORS
No. Particulars Cost( in Rupees) Remarks
No. Particulars Cost( in Rupees) Remarks
1Estimates for Earthwork of Distributary including cost
of lining 56,27,143/-
Details enclosed
Refer Volume-IV,
Page No.121
2 Earthwork and Lining of Minor-1 of Kampli Canal 10,36,188/-
Details enclosed
Refer Volume-IV,
Page No.134
3 Earthwork and Lining of Minor-2 of Kampli Canal 7,77,477/-
Details enclosed
Refer Volume-IV,
Page No.147
4 Earthwork and Lining of Minor-3 of Kampli Canal 9,50,057/-
5 Earthwork and Lining of Minor-4 of Kampli Canal 12,94,900/-
6 Earthwork and Lining of Minor-5 of Kampli Canal 5,18,765/-
7 Earthwork and Lining of Minor-6 of Kampli Canal 7,08,529/-
8 Earthwork and Lining of Minor-7 of Kampli Canal 8,29,219/-
9 Earthwork and Lining of Minor-8 of Kampli Canal 9,50,057/-
10 Earthwork and Lining of Minor-9 of Kampli Canal 12,43,158/-
11 Earthwork and Lining of Minor-10 of Kampli Canal 10,36,188/-
12 Earthwork and Lining of Minor-11 of Kampli Canal 14,67,480/-
13 Earthwork and Lining of Minor-12 of Kampli Canal 13,46,642/-
14 Earthwork and Lining of Minor-13 of Kampli Canal 13,98,384/-
15 Earthwork and Lining of Minor-14 of Kampli Canal 15,53,611/-
16 Earthwork and Lining of Minor-15 of Kampli Canal 11,39,673/-
17 Earthwork and Lining of Minor-16 of Kampli Canal 5,18,765/-
18 Earthwork and Lining of Minor-17 of Kampli Canal 10,70,725/-
19 Earthwork and Lining of Minor-18 of Kampli Canal 11,22,467/-
20 Earthwork and Lining of Minor-19 of Kampli Canal 13,46,642/-
21 Earthwork and Lining of Minor-20 of Kampli Canal 6,73,992/-
22 Earthwork and Lining of Minor-21 of Kampli Canal 11,22,467/-
23 Earthwork and Lining of Minor-22 of Kampli Canal 9,32,704/-
24 Earthwork and Lining of Minor-23 of Kampli Canal 8,98,315/-
25 Earthwork and Lining of Minor-24 of Kampli Canal 11,05,284/-
U-DISTRIBUTARIES & MINORS
DETAIL ESTIMATE FOR DISTRIBUTARY NETWORK OF KAMPLI CANAL = CCA 620 Ha
No. Particulars Cost( in Rupees) Remarks
26 Earthwork and Lining of Minor-25 of Kampli Canal 9,84,446/-
27 Earthwork and Lining of Minor-26 Of Kampli Canal 6,73,992/-
28 Earthwork and Lining of Minor-27 of Kampli Canal 11,05,284/-
29 Earthwork and Lining of Minor-28 of Kampli Canal 4,15,281/-
30 Earthwork and Lining of Minor-29 of Kampli Canal 11,57,321/-
31 Earthwork and Lining of Minor-30 of Kampli Canal 8,46,572/-
32 Earthwork and Lining of Minor-31 of Kampli Canal 7,25,735/-
33 Earthwork and Lining of Minor-32 of Kampli Canal 9,67,240/-
34 Earthwork and Lining of Minor-33 of Kampli Canal 3,63,539/-
35 Estimates for Drop at Ch. 0+982 Km of Distributary-1 3,69,562/-
Details enclosed
Refer Volume-IV,
Page No.160
36Estimates for Distribution Box at Ch. 1+500 Km (Tail
end) of Distributary-1 7,82,021/-
Details enclosed
Refer Volume-IV,
Page No.179
37 Estimates for Silt removal for DPO - 1 10,126/-
Details enclosed
Refer Volume-IV,
Page No.195
38 Estimates for Silt removal for DPO - 2 7,594/-
Details enclosed
Refer Volume-IV,
Page No.197
39 Estimates for Silt removal for DPO - 3 9,282/-
Details enclosed
Refer Volume-IV,
Page No.199
40 Estimates for Silt removal for DPO - 4 12,657/-
Details enclosed
Refer Volume-IV,
Page No.201
41 Estimates for Silt removal for DPO - 5 5,063/-
42 Estimates for Silt removal for DPO - 6 6,919/-
43 Estimates for Silt removal for DPO - 7 8,100/-
44 Estimates for Silt removal for DPO - 8 9,282/-
45 Estimates for Silt removal for DPO - 9 12,151/-
46 Estimates for Silt removal for DPO - 10 10,126/-
47 Estimates for Silt removal for DPO - 11 14,345/-
48 Estimates for Silt removal for DPO - 12 13,163/-
49 Estimates for Silt removal for DPO - 13 13,670/-
50 Estimates for Silt removal for DPO - 14 15,188/-
51 Estimates for Silt removal for DPO - 15 11,138/-
No. Particulars Cost( in Rupees) Remarks
52 Estimates for Silt removal for DPO - 16 5,063/-
53 Estimates for Silt removal for DPO - 17 10,463/-
54 Estimates for Silt removal for DPO - 18 10,969/-
55 Estimates for Silt removal for DPO - 19 13,163/-
56 Estimates for Silt removal for DPO - 20 6,582/-
57 Estimates for Silt removal for DPO - 21 10,969/-
58 Estimates for Silt removal for DPO - 22 9,113/-
59 Estimates for Silt removal for DPO - 23 8,776/-
60 Estimates for Silt removal for DPO - 24 10,801/-
61 Estimates for Silt removal for DPO - 25 9,619/-
62 Estimates for Silt removal for DPO - 26 6,582/-
63 Estimates for Silt removal for DPO - 27 10,801/-
64 Estimates for Silt removal for DPO - 28 4,050/-
65 Estimates for Silt removal for DPO - 29 11,307/-
66 Estimates for Silt removal for DPO - 30 8,269/-
67 Estimates for Silt removal for DPO - 31 7,088/-
68 Estimates for Silt removal for DPO - 32 9,451/-
69 Estimates for Silt removal for DPO - 33 3,544/-
TOTAL A+B+C 3,93,75,239/-
Rs 393.75 Lakhs
Sl no Length in mtr Amount @ Rs 2778 per Rmtr
1 6000 1,66,65,431/-
2 4000 1,11,10,287/-
2,77,75,718/-
277.76 Lakhs
Note: Typical estimate for 100 m length drain is enclosed
Rs 2,77,757 /-
Rs 2,778 /-
Particulars
Basavanna Channel
Raya Channel
MODERNISATION OF VIJAYANAGARA CHANNELS
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
W - Drainage
Total
Say
Rate for 100 m =
Rate for 1 m length =
Drainage provided for leading out seepage water of the canal into nearest natural Drain within the
city Limits of Hospet Town
No DESCRIPTION OF WORK UNIT QUANTITY RATE AMOUNT
1 Excavation in all kinds of soil including boulders upto
0.6m diameter (0.113 cum) for foundations of canal cross
drainage and other appurtenant structures and placing
excavated stuff neatly in specified dump area or disposing
off the same as directed including cost of materials,
machinery,labour etc., complete with initial lead upto 50 m
and initial lift upto 1.50 m.
(SR Item No.WRD: 4.1, page 84 , for 2013-14)
a) Lift 0.00 m to 1.50 m cum 70.00 126.88 8,882/-
Weightage 25% 31.72 2,220/-
2 Providing and laying insitu vibrated M-10 (28 days cube
compressive strength not less than 10 N/sqmm) grade
cement concrete using 40 mm down approved, clean,
hard, graded aggregates for foundation filling including
cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling,
vibrating, finishing, curing etc., complete with initial lead
upto 50 m and depth of foundation upto 1.5 m from
surface. (Cement content :220 kg/cum with use of super
plasticiser)
(SR Item No.WRD: 4.10, page 86 , for 2013-14) cum 7.00 4812.126 33,685/-
Weightage 25% 1203.031 8,421/-
3 Providing and laying insitu vibrated M-15 (28 days cube
compressive strength not less than 15 N/sqmm) grade
cement concrete using 20 mm downsize approved, clean,
hard, graded aggregates for sub-structure works including
cost of all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with
initial lead upto 50 m and lift upto 1.5 m from surface.
(Cement content :270 kg/cum with use of super
plasticiser)
(SR Item No.WRD: 4.15, page 87 , for 2013-14) cum 21.00 5933.106 124,595/-
Weightage 25% 1483.278 31,149/-
MODERNISATION OF VIJAYNAGAR CHANNELS IN TUNGABHADRA PROJECT
ABSTRACT ESTIMATE FOR THE CONSTRUCTION OF DRAINAGE UNDER RAYA CHANNEL
No DESCRIPTION OF WORK UNIT QUANTITY RATE AMOUNT
4 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including cost of
all materials,machinery, labour,cleaning, straightening,
cutting, bending, hooking, lapping, welding wherever
required, tying with 1.25 mm dia soft annealed steel
wire,etc., complete with initial lead upto 50 m and all lifts.
(SR Item No.WRD: 4.6, page 85 , for 2013-14) kgs 824.25 66.78 55,043/-
Weightage 25% 16.70 13,762/-
Total 2,77,757/-
Say 2,77,757 /-Total 2,778/-
Rupees Two Thousand Seven Hundred Seventy Seven And Paise Fifty Seven Only
Cost for 100 m Drainage
Cost for 1 m Drainage
No DESCRIPTION OF WORK UNIT No L B D QUANTITY REMARKS
1 2 3 4 5 6 7 8 9
1 Excavation in all kinds of soil including boulders
upto 0.6m diameter (0.113 cum) for foundations of
canal cross drainage and other appurtenant
structures and placing excavated stuff neatly in
specified dump area or disposing off the same as
directed including cost of materials,
machinery,labour etc., complete with initial lead
upto 50 m and initial lift upto 1.50 m.(SR Item No.WRD: 4.1, page 84 , for 2013-14)
a) Lift 0.00 m to 1.50 m cum
U/S , D/S Head wall & Sidewall alround 1 100.00 0.70 1.00 70.00
Total 70.00
Say 70.00
2 Providing and laying insitu vibrated M-10 (28 days
cube compressive strength not less than 10
N/sqmm) grade cement concrete using 40 mm
down approved, clean, hard, graded aggregates for
foundation filling including cost of all materials,
machinery, labour, formwork, cleaning, batching,
mixing, placing in position, levelling, vibrating,
finishing, curing etc., complete with initial lead upto
50 m and depth of foundation upto 1.5 m from
surface. (Cement content :220 kg/cum with use of
super plasticiser)
(SR Item No.WRD: 4.10, page 86 , for 2013-14)
cum
1 100.00 0.70 0.10 7.00
Total 7.00
Say 7.00
MODERNISATION OF VIJAYNAGAR CHANNELS IN TUNGABHADRA PROJECT
DETAILED ESTIMATE FOR THE CONSTRUCTION OF DRAINAGE ( Qty for 100m length)
No DESCRIPTION OF WORK UNIT No L B D QUANTITY REMARKS
1 2 3 4 5 6 7 8 9
3 Providing and laying insitu vibrated M-15 (28 days
cube compressive strength not less than 15
N/sqmm) grade cement concrete using 20 mm
downsize approved, clean, hard, graded
aggregates for sub-structure works including cost of
all materials, machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in
position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and lift upto 1.5
m from surface. (Cement content :270 kg/cum with
use of super plasticiser)
(SR Item No.WRD: 4.15, page 87 , for 2013-14)
cum
Allround 1 100.00 0.10 2.10 21.00
Total 21.00
Say 21.00
4 Providing, fabricating and placing in position
reinforcement steel bars for RCC works including
cost of all materials,machinery, labour,cleaning,
straightening, cutting, bending, hooking, lapping,
welding wherever required, tying with 1.25 mm dia
soft annealed steel wire,etc., complete with initial
lead upto 50 m and all lifts.
(SR Item No.WRD: 4.6, page 85 , for 2013-14) kgs
All round 1 824.25
Total 824.25
Say 824.25
0.5/100 x 78.5 x 21
Sl
No.Description Unit Qty Rate in Rs
Amount
Rs in Lakhs
AEE , Vijayanagar canal sub division, Kamalapur
1 Levelling Instrument No 1 40000 0.4
2 Theodolite No 1 60000 0.6
3 Computer No 1 128000 1.28
AEE , No.1 canal sub division, Agalkera
1 Levelling Instrument No 1 40000 0.4
2 Theodolite No 1 60000 0.6
3 Computer No 1 128000 1.28
AEE , Vaddarahatti sub division
1 Levelling Instrument No 1 40000 0.4
2 Theodolite No 1 60000 0.6
3 Computer No 1 128000 1.28
AEE , Siruguppa sub division
1 Levelling Instrument No 1 40000 0.4
2 Theodolite No 1 60000 0.6
3 Computer No 1 128000 1.28TOTAL 9.12 Lakhs
MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT
III TOOLS AND PLANTS (Survey Instruments)
TOTAL COST OF SMALL AND PLANTS Rs. 9.12 LAKHS
Assistant Executive Engineer KNNL, Vijayanagar canal Sub Division
Kamalapura
Executive Engineer KNNL, No.1 T.R Division
Munirabad
Karnataka Neeravari Nigam Limited
20% of total value of
produce (Rs
Lakhs)
1 2 3 4 5 6 7 8 9 10 11 12
Khariff
Paddy 30.90 4056 60 1979.00 4815.65 60.00 24 58.40 40000 1622.25 963.13
Hy. Jowar 5.60 735 20 2615.00 384.41 60.00 24 10.58 23000 169.05 76.88
Rabi
Paddy 13.90 1824 60 1979.00 2166.26 60.00 24 26.27 40000 729.75 433.25
Groundnut 14.50 1903 20 6009.00 2287.18 100.00 41 78.03 23000 437.72 457.44
Bi seasonal
Sugarcane 24.20 3176 60 2540.00 4840.61 7500.00 3 714.66 39000 1238.74 968.12
Garden (Banana) 10.90 1431 100 2000.00 2861.25 2250.00 5 160.95 68000 972.83 572.25
TOTAL 100.00 13125 17355.35 1048.89 5170.33 3471.07
MODERNISATION OF VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT
ESTIMATED VALUE OF PRODUCE BEFORE MODERNISATION
Quantity
Kg/Ha
Rate
Rs/Kg
Amount
(Rs
Lakhs)
Rate
Rs/Ha
Amount
(Rs Lakhs)
Input Seed
Value of
produce
( Rs lakhs)
Manure (Input) Hired Labour
(Human & bullock)
Crop % Area Area
Ha
Produce
(Qtls/Ha)
Rate per
Qtl.
(Rs)
Benefit-Cost Ratio
Karnataka Neeravari Nigam Limited
20% of total value of
produce (Rs Lakhs)
1 2 3 4 5 6 7 8 9 10 11 12
Khariff
Paddy 14.18 2304 75.0 1979.00 3419.71 60.00 24 33.18 30000 691.20 683.94
Hy. Jowar 38.95 6326 50.0 2615.00 8271.11 60.00 24 91.09 20000 1265.18 1654.22
Rabi
Paddy 10.19 1655 75.0 1979.00 2456.43 60.00 24 23.83 30000 496.50 491.29
Groundnut 23.12 3755 25.0 6009.00 5640.80 100.00 41 153.95 22000 826.08 1128.16
Bi seasonal
Sugarcane 7.57 1229 120.0 2540.00 3745.38 7500.00 3 276.48 36000 442.37 749.08
Garden (Banana) 6.00 974 120.0 2000.00 2337.12 2250.00 5 109.55 60000 584.28 467.42
TOTAL 100.00 16243 25870.56 688.09 4305.61 5174.11
MODERNISATION OF VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT
ESTIMATED VALUE OF PRODUCE AFTER MODERNISATION
Crop % Area Area
Ha
Produce
(Qtls/Ha)
Rate per Qtl.
(Rs)
Value of
produce (
Rs lakhs)
Input Seed Manure (Input) Hired Labour (Human &
bullock)
Quantity Kg/HaRate
Rs/Kg
Amount
(Rs Lakhs)
Rate
Rs/Ha
Amount (Rs
Lakhs)
Benefit-Cost Ratio
Karnataka Neeravari Nigam Limited
A Gross ReceiptsBefore
Modernisation
After
Modernisation
1 Gross value of farm produce 17355.35 25870.56
2 Dung receipts(at 30%of the fodder expenditure) 780.99 776.12
3 Total A : Gross Receipts(1+2) 18136.34 26646.68
B EXPENSES:
1 Expenditure on seeds 1048.89 688.09
2 Expenditure on manure etc. 5170.33 4305.61
3 Expenditure on hired labour(human and bullock) 3471.07 5174.11
4 Fodder expenses(as percentage of gross value of produce)
(15% ,10% of item A.1) 2603.30 2587.06
5 Depriciation on implements (2.7% of Item A.1) 468.59 698.51
6 Share and cash rent (5% 3% of Item A.1) 867.77 776.12
7 Land Revenue (2% of Item A.1) 347.11 517.41
8 Total B : Expenses (1 to 7) 13977.06 14746.89
C NET VALUE OF PRODUCE
1 Total gross receipts(Total A.3) 18136.34 26646.68
2 Minus total expenses (Total B.8) 13977.06 14746.89
3 Net value of produc © : [1-2] 4159.28 11899.78
D ANNUAL BENEFITS:
1 Net value after irrigation (C:3) 11899.78
2 Minus Net value before irrigation (C:3) 4159.28
3 Net annual benefits (D):[1-2] 7740.50
TOTAL NET ANNUAL BENEFITS (D3) 7740.50
E ANNUAL COSTS
1
Intrest on Capital @10% ( Esimated total cost of the project
including cost of land development @ Rs.1000/- per Ha) (Rs
40322.00 Lakhs + 16.24 Lakhs)
4048.44
2Depreciation of the project at 1 % of the cost of the project for 100
years life excluding cost of Land, R&R cost.(40322.00 Lakhs x 1%)403.22
3 Annual operation and maintenance charge at Rs. 1175/ ha 190.86
4Maintainance of the Head works at 1% its cost (Improvements to
anicuts)61.26
5 Total (E):Annual costs (1 to 4) 4703.78
BENEFITS COST RATIO = D 3 : Annual Benefits 7740.50
E.5: Annual cost 4703.78
MODERNISATION OF VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT
CALCULATION OF BENEFIT COST RATIO (BCR)
AS ADOPTED BY THE TECHNICAL ADVISORY COMMITTEE
Figures are in Rs lakhs
1.65
Benefit-Cost Analysis
Rate in Rs. /ha
1 2 3 4 5 6 7 8
Khariff
Paddy 4056 60 1500 1440 40000 17650 59090
Hy. Jowar 735 20 1500 1440 23000 6000 30440
Rabi
Paddy 1824 60 1500 1440 40000 17650 59090
Groundnut 1903 20 3000 4100 23000 12000 39100
Bi seasonal
Sugarcane 3176 60 2540 22500 39000 30000 91500
Garden (Banana) 1431 100 2000 11200 68000 40000 119200
TOTAL 13125 123300.00
Joint Director of Agriculture
Bellary
Input/ha ( Rate in Rs.) Total cost of
cultivation (Rs.
per ha)
Hired Labour
(Human & bullock)Seeds Manure
DETAILS OF CROP YIELD, RATE OF PRODUCE AND COST OF CULTIVATION FOR MODERNISATION OF
VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT
(BEFORE MODERNISATION)
CropArea
Ha
Produce
(Qtls/Ha)
Rate per Qtl.
(Rs)
Rate in Rs. /ha
1 2 3 4 5 6 7 8
Khariff
Paddy 4661 75 1500 1440 30000 13000 44440
Hy. Jowar 812 30 1500 1440 20000 9000 30440
Rabi
Paddy 3086 75 1500 1440 30000 13000 44440
Groundnut 2323 25 3000 4100 22000 13500 39600
Bi seasonal
Sugarcane 3427 120 2540 22500 36000 33200 91700
Garden (Banana) 1933 120 2000 11200 60000 48000 119200
TOTAL 16241 129700.00
Joint Director of Agriculture
Bellary
DETAILS OF CROP YIELD, RATE OF PRODUCE AND COST OF CULTIVATION FOR MODERNISATION OF
VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT
(AFTER MODERNISATION)
CropArea
Ha
Produce
(Qtls/Ha)
Rate per Qtl.
(Rs)
Input/ha ( Rate in Rs.) Hired Labour
(Human & bullock)Total cost of
cultivation (Rs.
per ha)Seeds Manure