CHIEF ENGINEER WRD, IRRIGATION CENTRAL ZONE MUNIRABAD KARNATAKA NEERAVARI NIGAM LIMITED (A Government of Karnataka undertaking) DETAILED PROJECT REPORT VOLUME – I REPORT ESTIMATED COST – Rs. 432.55 Crores MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

Transcript of MODERNISATION OF VIJAYANAGARA CHANNELS …knnlindia.com/kaveri2/KISWRMIP/Documents/VNC - DPR _ with...

CHIEF ENGINEER WRD, IRRIGATION CENTRAL ZONE

MUNIRABAD

KARNATAKA NEERAVARI NIGAM LIMITED

(A Government of Karnataka undertaking)

DETAILED PROJECT REPORT

VOLUME – I

REPORT

ESTIMATED COST – Rs. 432.55 Crores

MODERNISATION OF VIJAYANAGARA

CHANNELS IN TUNGABHADRA

PROJECT

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Contents Section 1 – Checklist

Section 2 – Salient features

Section 3 – Report

Chapter 1. Introduction ...................................................................................................................1

1.1. Vijayanagara channels ............................................................................................................1

1.2. Weir/Anicuts ..........................................................................................................................3

1.3. Location .................................................................................................................................4

1.4. Details of Canal System ........................................................................................................4

1.5. Accessibility ..........................................................................................................................6

1.6. Toposheet Mosaic of the project .........................................................................................6

1.7. Present condition ....................................................................................................................7

1.8. Deficiencies in the existing system ..........................................................................................7

1.9. Need for Modernization ...........................................................................................................8

Chapter 2. Hydrology .................................................................................................................... 10

2.1. Water availability ................................................................................................................. 11

Chapter 3. Reservoir ...................................................................................................................... 12

Chapter 4. Weir/Anicut .................................................................................................................. 12

4.1. Vijayanagara Channels ......................................................................................................... 12

4.2. Details of Channel Systems .................................................................................................. 13

Chapter 5. Land Potential ............................................................................................................. 16

5.1. Culturable Command area .................................................................................................... 16

Chapter 6. Cropping pattern and Crop Water Requirement ....................................................... 17

6.1. Details of Pre –Project / Original cropping pattern ................................................................ 17

6.2. Details of Post –Modernisation/ proposed cropping pattern .......................................... 18

6.2.1. Field application efficiency ............................................................................................ 19

6.3. Assessment of Crop Water Requirement .............................................................................. 20

6.4. Crop Water Requirement ...................................................................................................... 21

6.5. Results .................................................................................................................................. 21

6.6. Conclusions ........................................................................................................................... 22

6.6.1. Achieving required savings ........................................................................................... 22

Chapter 7. Pissiculture .................................................................................................................. 23

Chapter 8. Horticulture .................................................................................................................. 23

Chapter 9. Domestic and Industrial water supply etc. ................................................................ 23

Chapter 10. Demand Table .............................................................................................................. 24

Chapter 11. Impact of Modernisation ............................................................................................. 25

11.1. Upstream and Downstream Projects ..................................................................................... 25

Chapter 12. Interstate aspects ........................................................................................................ 25

Chapter 13. Channel system ........................................................................................................... 26

13.1. Preamble ............................................................................................................................... 26

13.2. Survey of channel system ..................................................................................................... 26

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

13.3. Site Inventory and survey of channels and structures ........................................................... 27

13.4. Review of capacity of existing channel and distribution system. ........................................... 32

13.4.1. Original design .............................................................................................................. 32

13.4.2. Present capacity ............................................................................................................ 32

13.4.3. Design of revised section (lined) ................................................................................... 32

13.5. Identification of the reaches needing improvements ............................................................. 33

13.5.1. Lining............................................................................................................................. 33

13.5.2. Strengthening and stabilization of banks ....................................................................... 34

13.6. Preparation of capacity statement ......................................................................................... 34

13.7. Need for remodeling / distribution system ............................................................................. 34

Chapter 14. Power ........................................................................................................................... 35

14.1. Power status ......................................................................................................................... 35

14.2. Modernization / upgrading proposal ...................................................................................... 35

Chapter 15. Navigation .................................................................................................................... 35

Chapter 16. Groundwater ................................................................................................................ 36

16.1. Depth of Groundwater level ................................................................................................... 36

16.2. Assessment of Groundwater potential in the command area ................................................ 37

16.3. Quality of Groundwater ......................................................................................................... 38

16.4. Assessment of possible impact on Groundwater .................................................................. 38

16.5. Conjunctive use of surface and groundwater ........................................................................ 38

Chapter 17. Drainage and land reclamation .................................................................................. 39

17.1. Review of drainage ............................................................................................................... 39

17.2. Type of reclamation ............................................................................................................... 39

17.2.1. Field drains .................................................................................................................... 39

Chapter 18. Land acquisition, Rehabilitation and Resettlement ................................................. 40

18.1. Land acquisition, Rehabilitation / Resettlement ..................................................................... 40

Chapter 19. Water management and maintenance ....................................................................... 41

Chapter 20. On farm development works ...................................................................................... 42

20.1. Command Area Development Authority ................................................................................ 42

20.1. Organization setup of On Farm Development ....................................................................... 42

20.1.1. Land leveling ................................................................................................................. 42

20.1.2. Field Irrigation Channels (FICs) .................................................................................... 42

20.1.3. Construction of field drains ............................................................................................ 43

20.1.4. Warabandi ..................................................................................................................... 43

20.1.5. Ayacut roads ................................................................................................................. 43

Chapter 21. Construction programme ........................................................................................... 44

Chapter 22. Construction organization .......................................................................................... 45

22.1. Organization setup for modernization.................................................................................... 45

Chapter 23. Environment, Ecology and Forest aspects ............................................................... 47

23.1. World Heritage Zone ............................................................................................................. 47

Chapter 24. Economic Evaluation .................................................................................................. 48

24.1. For Channels ......................................................................................................................... 48

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

24.2. For Structures ....................................................................................................................... 48

Chapter 25. Administrative and Legislative provisions................................................................ 61

25.1. Administrative set up ............................................................................................................. 61

25.2. Legal status & Policy framework ........................................................................................... 61

Chapter 26. Facilities for training the operational and maintenance personnel ........................ 62

26.1. Existing.................................................................................................................................. 62

26.2. Proposals for improvement and extension ............................................................................ 62

26.2.1. Institution framework ..................................................................................................... 62

Chapter 27. Operation and Maintenance ....................................................................................... 63

27.1. Training and Visit system ...................................................................................................... 63

Chapter 28. B C Ratio ...................................................................................................................... 64

28.1. Benefit Cost ratio ................................................................................................................... 64

28.1.1. Estimated value of produce before channel modernization ........................................... 64

28.1.2. Estimated value of produce after channel modernization .............................................. 64

Conclusion 68

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

List of Annexures

Annexure 2.1 Statement showing the year wise details of inflows, outflows (utilisation) under different canal system of Tungabhadra project. (Karnataka portion) for the period (water year) from 1990-91 to 2009-10

Annexure 2.2 Details of River releases for Vijayanagar channels and Rajolibanda Diversion Scheme

Annexure 6.1 Monthly rainfall data from year 1980 to 2009 (mm)

Annexure 6.1/1 Monthly rainfall data of Station Munirabad

Annexure 6.1/2 Monthly rainfall data of Station Kamalapura

Annexure 6.1/3 Monthly rainfall data of Station Gangavathi

Annexure 6.1/4 Monthly rainfall data of Station Kampli

Annexure 6.1/5 Monthly rainfall data of Station Sirguppa

Annexure 6.2 Average annual rainfall and monthly normal rainfall of influencing rain gauge stations (according to Theissen polygon)

Annexure 6.3 Agro-climatological data of Bellary IMD station

Annexure 6.4 Detailed calculations of Crop water requirements (Channel wise/Crop wise)

Annexure 12.1 Allocation of water (KWDT I) - Revised Master Plan – 2003

Annexure 13.1 Particulars of Canal System

Annexure 24.1 Cost Estimate (General Abstract)

Annexure 24.2 Letter from State Government for clearance of Designs

Annexure 24.3 Place of Quarries considered for different materials under Vijaynagar channels

Annexure 28.1 Benefit Cost Ratio

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

List of Figures

Fig 1.1– Top sheet mosaic of the project area ................................................................................. 7

Fig 13.1 – Survey work in progress .................................................................................................26

Fig 13.2 – Figure showing untidy channels .....................................................................................28

Fig 13.3 – Channel used as disposal point ......................................................................................28

Fig 13.4 – Channel reaches with size stone masonry lining ............................................................29

Fig 13.5 – Damage due to seepage and poor maintenance ............................................................29

Fig 13.6 – Crocodile in the reaches of Raya channel ......................................................................30

Fig 13.7 – Snake found in the initial reache of Belagodahala channel ............................................30

Fig 13.8 – Thick vegetation around the Channel .............................................................................30

Fig 13.9 – Damaged Service road ...................................................................................................31

Fig 13.10 – Poor crossing structure ................................................................................................31

Fig 13.11 – Channel flowing full ......................................................................................................31

Fig 13.12 – Service road .................................................................................................................31

Fig 13.13 –Banana plantation .........................................................................................................32

Fig 13.14 –Sugarcane plantation ....................................................................................................32

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

List of Tables

Table 1.1 – List of Channels .............................................................................................................. 2

Table 1.2 – Table showing Location details of Canal system ............................................................ 4

Table 1.3 – Table showing Hydraulic details of Canal system .......................................................... 5

Table 1.4 – Details of toposheet which cover the project area .......................................................... 6

Table 4.1 – Table showing Location details of Channel system ...................................................... 13

Table 4.2 – Table showing Hydraulic details of Channel system .................................................... 14

Table 6.1 –Existing (Pre modernization) Cropping Pattern ............................................................. 17

Table 6.2 – Proposed (Post modernization) cropping pattern ......................................................... 18

Table 6.3–Table showing the breakup of Irrigation efficiency .......................................................... 20

Table 6.4 –Demand Table ............................................................................................................... 21

Table 6.5 –Savings Achieved .......................................................................................................... 22

Table 16.1 – Table showing depth of Groundwater for Pre monsoon and Post monsoon ............... 36

Table 16.2 – Table showing Administrative wise assessment of Dynamic Groundwater resources 37

Table 16.3 – Table showing administrative assessment of unit wise categorization ....................... 37

Table 21.1 – Implementation program of Modernization of Vijayanagara channels ........................ 44

Table 22.1 – Divisions in- charge of the channels ........................................................................... 46

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Abbreviation

B.C.R Benefit Cost Ratio

CA Catchment Area

CADA Command Area Development Authority

CBL Channel Bed Level

CC Cement Concrete

CD Cross Drainage

CNS Cohesive Non Swelling

CTC Cart Track Crossing

CWC Central Water Commission

CWR Crop Water Requirement

DPR Detailed Project Report

DT Double tertiary

DTP Draft Tender Paper

EOT Electric Overhead Travelling

ETC Crop Evapo-transpiration

FIC Field Irrigation Channel

FTL Full Tank Level

GEMS Groundwater Estimation and Management system

GIR Gross Irrigation Requirement

GTS Great Trigonometric Survey

Ha Hectares

IP Inspection Path

KNNL Karnataka Neeravari Nigam Limited

MCM Million cubic meter

NIR Net Irrigation Requirement

SOR Schedule of Rates

SR Service Road

TMC Thousand Million cubic feet

WUA Waters Users Association

USDA United States Department of Agriculture

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

SECTION 1

CHECKLIST

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Checklist

No. Particulars Remarks

1 Was the original project given investment clearance by Planning

Commission?

Does not arise.

2 Has the performance evaluation of the existing project been carried out? Yes

3 Have the salient features of the project as envisaged at the time of

execution of project and as present, been indicated?

Salient features as of now.

4 Have the irrigation potential of the existing project as originally envisaged,

potential created and utilized and reasons for variations been indicated?

Yes

5 Has the Culturable command area been actually assessed and compared

with that at the time of planning of the project and shortfalls/excesses, if

any, discussed?

Yes

6 Has the Hydraulic survey of channel/distribution system been carried out? Yes

7 Have the deficiencies in the existing irrigation system been identified? Yes

8 Has the need for modernization been justified? Yes

9 Have the hydrological studies been reviewed ,compared with those made

at the time of preparation of the original project if available and reasons

for variations recorded in respect of:

(i) Rainfall

(ii) Runoff

(iii) Flood

(iv) Sediment

(v) Ground water

(vi) Evaporation.

These are run of the river schemes

downstream of Tungabhadra dam

(TB dam)

10 (a) Have changes in the upstream withdrawals/diversions for

industrial use, power generation, drinking requirement and other

developments in the upper catchments to the extent which can be

collected with reasonable efforts be described?

(b) Have the changes in the power generation / consumption in

power for the lift irrigation schemes being described?

NA

NA

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

No. Particulars Remarks

11 Have the semi-detailed soil surveys been carried out for the entire

command (if not entire command then extent cornered) and soil and land

irritability classification brought out in the report? (Project to be

acceptable, semi detailed soil survey in at least 50% of command should

have been carried.)

NA

12 Is the crop water requirement determined by the modified Penman

method?

Yes

13 Have water requirements for other uses been worked out? NA

14 Has justification for the proposed cropping pattern been furnished? Yes

15 Have the cropping pattern & proper cropping calendar been devised with

a view to maximize the production and channel closure for maintenance

etc. ensured? Have these been concurred by the agriculture department?

Yes

16 Are the areas and percentage of CCA that will be irrigated during kharif,

rabi, two seasonal, hot weather and perennial been indicated and

compared with cropping pattern as existing prior to taking up the project,

originally envisaged and actually developed after completion of the

project?

Yes

17 Is the justification furnished for continuing with/or taking up perennial and

hot weather crops from the reservoir?

Existing crops have

been retained

18 Have the most suitable depths and frequencies of irrigation to be adopted,

based on the characteristics of the soil and crops been worked out?

Yes

19 Have the values of conveyance efficiency, field application efficiency and

overall water use efficiency been indicated with basis therefore?

Yes

20 Has the pattern of releases (10 daily/monthly) from the diversion/storage

headworks been worked out & compared with those envisaged originally?

Yes

21 Has the channel been redesigned to cater for peak requirement + 10

percent (20% for small reservoirs) for rush irrigation. If, not have the

alternative proposals for carrying the required discharge been discussed?

Yes

22 Whether supplementation from ground water has been considered? NA

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

No. Particulars Remarks

23 Are the supplies available sufficient to meet the requirements for ensuring

75 per cent dependability? If not, have the possibilities of augmentation of

the supplies been discussed either by increasing the storage or by

supplementing by ground water etc.? Have the revised reservoir

operation tables been furnished?

Yes

24 Has the study of ground water potential of the command area, the present

level of the ground water use and the scope of the future ground water

utilization been carried out and included in the project report?

Yes

25 Have the economics of the ground water development been studied? NA

26 Has the possible impact on ground water recharge on account of lining of

the system been kept in view in the scheme of ground water utilization?

NA

27 Has the possibility of ground water and irrigation area not commanded by

the channel system been considered?

NA

28 Has the quality of surface water and also ground water, drainage water, if

intended for irrigation use, been tested?

Yes

29 Have the requirements of the drainage in the command area been studied

and a suitable intended for irrigation use been tested?

NA

30 Have the arrangements for the following been considered and provided

for?

Execution of OFD works

(a) Training programmers for field staff and farmers – existing

position and proposals for strengthening.

(b) Participatory Irrigation Management (PIM), Water Users

Association (WUA) and turnover of the system to WUAs.

(c) Provision of extension services.

(d) Providing important inputs like seeds, fertilizers etc.

These activities are implemented by CADA

31 Have adequacy of road communication facilities and if not, the necessity

of improvements been discussed and provided for?

NA

32 Have matters about the improvement in reliability/dependability of the

annual irrigation of the existing proposed command area been discussed

in the light of modernization?

Yes

33 Have the net benefits due to the project been estimated and concurred by Yes

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

No. Particulars Remarks

the agricultural Dept.?

34 Has the concurrence of the State Finance Department been obtained for

taking up the project at the estimated cost?

Yes

35 Whether the scheme has already been started? If so, is the stage

construction indicated?

-

36 Is the scheme included in the plan? If not, what is the present position

regarding it’s inclusion in the plan?

-

37 Have the year wise requirement of funds been indicated? -

38 Is the scheme covered under State Sector or Central Sector? State Sector

39 Is the scheme covered or proposed to be covered under any foreign

assistance/aid agreement?

No

40 Are the detailed cost estimates included in the report? Yes

41 Has the benefit-cost ratio been worked out? Whether proportionate cost

of completed works included in the calculations?

Yes

42 Whether Internal Rate of Return (IRR) worked out? NA

43 Are the financial results attached? No

44 Are there any special reasons to undertake the project if it is unproductive

and whether these have been recorded in the Report?

Yes. To use water more efficiently thereby save water, modernization is proposed.

45 Are the rates of betterment levy proposed, the period of recovery and the

estimated total recovery indicated?

-

46 Are there any charges levied for irrigation facilities as distinct from water

charges?

-

47 Are the scales of water rate indicated? -

48 Have the rates of betterment levy, water charges, etc. been compared

with those obtained in other regions of the state?

NA

49 Has the concurrence of the State Revenue Department been obtained for

these rates?

Yes

50 Have the O&M aspects (both financial as well as management) been

discussed? How are the O&M cost proposed to be met?

Yes.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

No. Particulars Remarks

51 Have the programmer of construction and the expenditure involved been

furnished?

Yes

52 Has the requirement of staff been estimated and furnished with

justification?

Yes

53 Has the adequacy of the existing irrigation laws and revisions, if any,

considered necessary been discussed?

Yes

54 Have the impact of the scheme on the overall development of water

resources in the basin/state been discussed?

Yes

55 Whether views of water users about proposed works in modernization

projects been obtained and described in the Report?

Yes

56 Have environmental / ecological aspects been discussed in the Report? NA

57 Does the project involve acquisition of forest land? Has the MOE&F been

approached for clearance under Forest Conservation Act 1980?

No. NA

58 Dose the project involve any re-settlement? Whether rehabilitation of

PAFs provided for?

No. NA

59 Does the project involve rehabilitation of SC/ST population? Has the

rehabilitation package for them been cleared by Ministry of Social Justice

& Empowerment?

No

60 Have the socio economic studies (bench mark surveys) been carried out? No

61 Have the interstate aspects been examined & discussed? Yes

62 Have the list of ongoing programs of Agriculture Department in command

Area been given?

Yes

Chief Engineer KNNL, Irrigation Central Zone

Munirabad

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

SECTION 2

SALIENT FEATURES

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Salient features

1.0 Name of the Project Modernisation of Vijayanagara Channels in Tungabhadra Project

2.0 General Data

2.1 District(s) Bellary, Koppal, Raichur

2.2 Tehsil(s)/Taluk(s) Hospet, Gangavathi, Sirguppa and Raichur

2.3 River/Tributary Tungabhadra River

2.4 Location of Dam/Diversion Structures

2.5 Name of River/Basin Tungabhadra River/ Krishna

2.6 Longitude and Latitude

a) Longitude 75° 40' to 77° 35' E

b) Latitude 14° 30' to 16° 34' N

3.0 Socio-economic aspects Original Revised

3.1 District(s) Benefited Bellary, Koppal, Raichur

Bellary, Koppal, Raichur

3.2 Income

3.3 Land holdings

3.4 Population benefited

a) Total

b) Schedule cast

c) Schedule Tribe

d) Other Backward casts

4.0 Hydrological Data

4.1 Catchment area at dam site (Ha) 28,179.20 Sq. Km at Tungabhadra dam site

4.2 Rainfall (mm) Original Revised

a) Maximum annual rainfall 1540 1540

b) Minimum annual rainfall 244 244

c) Mean annual rainfall ( As per Thessien

average)

629.20 629.20

4.3 Annual runoff (M cum) Original Proposed

a) Average

-NA- b) Maximum

c) Minimum

d) 75% dependability

4.4 Design Flood -NA-

5.0 Water Utilization (TMC) Present Proposed

a) Reservation for upstream use

b) Reservation for downstream use

c) Utilisation through the project

i) Irrigation 12.05 5.80

ii) Power Generation -NA-

iii) Drinking water -NA-

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

iv) Industrial Use -NA-

v) Others (Evaporation) -NA-

d) Water saved through Modernization 6.25 TMC

6.0 Groundwater (TMC)

a) Potential 12.88 TMC

b) Present use No groundwater is utilized for Irrigation at

present

c) Proposed use after Modernisation -NA-

d) Balance for future utilization after

Modernisation

-NA-

7.0 Reservoir data (Tungabhadra Dam)

a) Storage (TMC) Existing Proposed

i) Gross storage 132.00 132.00

ii) Dead storage 2.300 2.300

iii) Live storage 116.84 116.84

iv) Annual carry over

b) Elevation (El-m) Original Proposed

i) Maximum water level (MWL) 497.74 497.74

ii) Full reservoir level (FRL) 497.74 497.74

c) Water spread area (sq.km) at

Full reservoir level 378.14 378.14

d) Water Quality Reservoir/Canal/River (Downstream)

i) Physical Good

ii) Chemical Good

iii) Bacteriological Good

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

8.0 Canal system (Irrigation) Information to be

furnished for each Main/Branch canal separately

Existing Proposed

a) Length of canal(Km)

Refer Annexure 13.1

b) Full supply level at canal head (m)

c) Full supply discharge at canal head

(m3/sec)

d) Length of complete distribution system up

to minors

e) Number of villages surveyed

f) Area (Ha)

i) Gross command area (GCA)

ii) Culturable command area (CCA

iii) Annual Irrigation (AI)

iv) Intensity of Irrigation (% of CCA)

g) Automation and SCADA Existing Proposed

i) Flow measurement and data

acquisition at all control points

No No

ii) Automatic control of gates No No

iii) Control philosophy NA NA

iv) Communication NA NA

9.0 Power -NA-

10 Cropping pattern (crop wise)-Season wise

Name of crop

season wise

Pre-Modernisation (Ha)

% of CCA

Post Modernisation (Ha)

% of CCA

Intensity of Irrigation 100% 100%

Khariff 1. Paddy 4056 (30.9 %) 2304 (14.18%) 2. Jowar 735 (5.6 %) 6326 (38.95%)

Rabi 1. Paddy 1825 (13.9 %) 1655 (10.19%) 2. Groundnut 1903 (14.50 %) 3755 (23.12%)

Perennial 1. Sugarcane 3176 (24.20 %) 1229 (7.57%) 2. Garden 1431 (10.90 %) 974 (6.0%) Total 13,125 16,243

11. Benefits (Additional, annual) Amount (Rs.)

a) Food grains 3812.67

b) Commercial crops 3216.59

c) Others -

12.0 Revenue (Rs) Existing Proposed

12.1 Revenue from water rates

a) Irrigation - -

b) Domestic water supply - -

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

c) Industrial water supply - -

d) Power - -

e) Others - -

12.2 Revenue from Irrigation cess other than water

rates

12.3 Recovery of Betterment levy -

12.4 Other sources of revenue, if any, -

13.0 Cost

13.1 Estimated cost of Modernization works

a) Irrigation 40322 Lakhs

b) Domestic water supply -

c) Industrial water supply -

d) Power -

e) Others -

13.2 Cost of completed works (Rs. Lakhs) -

13.3 Annual cost 4703.78 Lakhs

14.0 Benefit Cost Ratio 1.65

Chief Engineer KNNL, Irrigation Central Zone

Munirabad

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

SECTION 3

REPORT

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 1

Chapter 1. Introduction

1.1. Vijayanagara channels

The river Tungabhadra is a major tributary to Krishna River and is so called after the confluence of

two rivers Tunga and Bhadra, which rise in the Western Ghats at an altitude of about 1198 M above

mean sea level (MSL). The Tungabhadra river flows for about 531 Kms in the north-east direction in

Karnataka and Andhra Pradesh before joining Krishna river near Kurnool at an altitude of 294.10 M.

The vast drainage area of Tungabhadra river comprises of the following main tributaries (a)

Kumadvathi river (b) Dharma river (c) Varada river (d) Dodda halla (e) Murdha halla and (f) Haridhra

river.

The Vijayanagara Channel system is spread over 3 districts namely Bellary, Raichur and Koppal. The

Geographical area lies between latitude 14° 30' to 16° 34' N and Longitude 75° 40' to 77° 35' E.

Originally, Vijayanagara Channels are the run-of-the river irrigation channels and are historically

important serving the irrigation needs of the local population. They have been built during

Vijayanagara dynasty about 400 years back. In all, there are 19 Channels taking off from

Tungabhadra river of which 18 are in Karnataka and one is in Andhra Pradesh.

BELLARY

KOPPAL

RAICHUR

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 2

During Vijayanagara dynasty, 18 Channel networks were constructed in Tungabhadra basin in the

reach from Tungabhadra reservoir to Siraguppa. The list of the Channels is indicated in Table 1.1

Table 1.1 – List of Channels

A. On Right Bank of TB River B. On Left Bank of TB River

1. Raya 11. Koregal

2. Basavana 12. Hulugi

3. Bella 13. Shivapura

4. Kalaghatta 14. Anegundi

5. Turtha 15. Gangavathi Upper

6. Ramasagar 16. Gangavathi Lower

7. Kampli 17. Bichal

8. Belagodhala 18. Bennur

9. Deshnur

10. Siraguppa

Of these 18 Channels, Bennur channel is in ruins and Koregal channel command is supplied water

from Tungabhadra Left Bank Channel. In view of this, presently, Vijayanagara Channel system

comprises of 16 Channels. This modernization report deals with the 16 Channels.

The Raya and Basavanna canals were on the right bank of river Tungabhadra and were being fed

through the respective weirs located on the upstream of the present Tungabhadra dam. The

Basavanna channel was crossing the present dam alignment at Km 18 below its weir whereas Raya

Channel was crossing at about 3.5 Kms below the weir. In order to protect the irrigation in these two

channels, an irrigation sluice has been provided in the right side of Tungabhadra dam.

Two channels; Raya and Basavanna take off from TB dam. All other channels except Kalghatta and

Belgodhal take off from anicuts constructed across Tungabhadra river at various locations on

downstream of TB dam and are being partially fed by Raya and Basavanna channels.

The Raya Channel runs for about 27.74 Km and joins at 4th Km of Turtha channel. In addition, it has

a separate sluice which was constructed at 2.5 Km to fulfill the shortage of water to Bella channel.

Bella Channel runs for about 5.55 Km and joins at Ch 0.2 Km of Kalghatta channel. The Kalghatta

Channel runs for about 7.02 Km and joins Turtha Channel at Ch 0.7 Km. Turtha channel runs for

about 18.69 Km and joins Ramsagar channel at Ch 1.40 Km. Ramsagar channel runs for about 15.50

Km. It has two drainage channels joining Kampli channel. The Kampli channel runs for about 23.55

Km. It has Belgodhal channel taking off at Ch 3.20 Km and runs for a length of11.22 Kms.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 3

The discharges of each channel are considered while arriving at the channel section for the channels

Raya, Bella, Kalaghatta, Turtha, Ramsagar, Kampli and Belgodhal. The 4 Channels; Bella, Turtha,

Ramsagar and Kampli get a share from river assistance.

The Channels; Sirguppa and Deshnur on the right side and other 6 channels on the left side of

Tungabhadra River get water exclusively from river assistance, released from Tungabhadra dam.

The Index Map showing the Command area of the Scheme (16 channels) is appended in Volume V.

1.2. Weir/Anicuts

There are 12 no’s of Anicuts and the details are enclosed separately. Vijayanagara channels are

being fed from the anicuts constructed in the earlier days for providing irrigation. These anicuts were

constructed during the regime of Vijayanagar empires. They have been constructed using huge

boulders and set in Zig-Zag manner without any kind of mortar for bond. Due to this, the anicuts are

subject to leakage of water exacerbated by the displacement of boulders during high floods. Over a

period of time, the system has deteriorated and needs urgent attention and improvements. The

farmers of Vijayanagara channels are demanding improvements to anicuts.

The improvements proposed to anicuts are:

1. Providing 200 mm thick skin wall encasement to the anicut and grouting.

2. Providing anchor rods at every 1m interval on upstream and downstream of anicut for a width

of 5 m all along the length.

3. Providing concrete toe walls on both ends

4. Formation of approach roads to the anicuts wherever required from the nearest road.

The details of the channels system are tabulated below:

The Irrigation schemes comprising 17 Nos of anicuts across Tungabhadra River together known as

Vijayanagara Channels were implemented during Vijayanagara dynasty to provide irrigation facilities.

Out of these, Vallabhapur and Hoskote anicuts were submerged in the backwaters of Tungabhadra

reservoir. In order to cater to the command of Vallabhapur and Hoskote anicuts, one vent of size 1.8

m X 3.6 m is constructed in the reservoir as a permanent sluice and these commands are fed through

Raya and Basavanna channels. A total of 12.05 TMC has been allocated by the tribunal to

Vijayanagara channels with a break up of 5.71 TMC as protected utilisation and 6.35 TMC as worth

consideration.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 4

As per clause IX - E of KWDT award, 7 TMC of water from Tungabhadra reservoir is earmarked for

Raya and Basavanna channels. An allocation of 2 TMC was made by way of assistance through

other regulated discharges other than Raya and Basavanna channels from Tungabhadra reservoir.

In the 1993 master plan, an allocation of 12.05 TMC is made for the Vijayanagara channels without

channel wise breakup and river assistance.

The revised Master plan of 2003 has an allocation of 5.80 TMC for all the 16 Vijayanagara channels.

The Government of Karnataka is proposing the modernization of these Channels to improve the

channel efficiency thereby saving 6.25 TMC of water.

1.3. Location

Vijayanagara is located in Bellary District, northern Karnataka. The geographical location is at

Latitude 15°19′N and Longitude 76°28′E. It is also known as ruined capital city. The nearest town

and railway station is Hospet and the nearest canal is 13 km away by road. Hospet also lies within

the original extents of the old city.

1.4. Details of Canal System

The details of canal system considered for modernization are indicated in Table 1.2

Table 1.2 – Table showing Location details of Canal system

No Name of the

channel Name of weir &

length in Km Name of stream

Distance d/s of TB Dam in

Km Remarks

Bellary District (on right side of river)

1. Basavanna Vallabhapur Submerged in Tungabhadra

reservoir

Channel takes off directly from

Tungabhadra dam on right side

2. Raya Hosakote --do-- --do-

3. Bella Hosur-0.602 Tungabhadra 2.4 Channel utilizes

seepage from

higher level

channels

4. Kalaghatta Drainage channel Halla 8

5. Turtha Turtha 3.048 Tungabhadra 16

6. Ramsagar Ramsagar 2.042 --do-- 28.8

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 5

No Name of the

channel Name of weir &

length in Km Name of stream

Distance d/s of TB Dam in

Km Remarks

7. Kampli Kampli anicut

0.94

--do- 30.4

8. Belagodahal Drainage

channel

Halla 35.2 Channel utilizes

seepage from

higher level

channels

9. Siruguppa Siruguppa 1.95 Tungabhadra 80 Consists of 7 bits.

10. Deshnur Deshnur 0.96 ~do-- 80

Koppal District (on left side of river) 11. Koregal

Koregal Submerged in Tungabhadra

reservoir

Channel takes off directly from

Tungabhadra Left Bank Channel

12. Hulugi Hulugi - 0.518 Tungabhadra 2.4

13. Shivapura Shivapura - 0.17 do 8

14. Anegundi Sanapur - 0.518 do 16

15. Upper Gangavathi Upper

Gangavathi0.78 do 27.2

16. Lower Gangavathi Lower Gangavathi 0.45

do 30.4

Raichur district 17. Bichal Bichal - 1.192 do 137.6

Table 1.3 – Table showing Hydraulic details of Canal system

(20 years average cropped area is considered)

No. Name of the Channel Length of

Channel in Kms

Cropped area in Ha

Offtake

On right bank of TB River

1 Raya Channel 27.74 2855 Tungabhadra Dam

2 Basavanna Channel 16.50 1447 Tungabhadra Dam

3 Bella Channel 5.50 741 Hosur Anicut

4 Kalaghatta Channel 7.020 349 Drainage channel

5 Turtha Channel 18.69 1171 Turtha anicut

6 Ramasagar Channel 15.50 1024 Ramasagar Anicut

7 Kampli Channel 23.550 894 Kampli Anicut

8 Belagodahala 11.220 328 Drainage channel

9 Deshnur Channel 9.03 815 Deshnur Anicut

10 Siruguppa Channel 10.85 1344 Sirguppa Anicut

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 6

No. Name of the Channel Length of

Channel in Kms

Cropped area in Ha

Offtake

On left bank of TB River

11 Hulugi Channel 10.69 419 Hulugi anicut

12 Shivapura Channel 6.54 717 Shivapura anicut

13 Anegundi Channel 19.44 1359 Sanapur anicut

14 Gangavathi upper Channel

9.00 1363 Upper Gangavathi anicut

15 Gangavathi lower Channel

9.54 1141 Lower Gangavathi anicut

16 Bichal Channel 14.50 276 Bichal Anicut

Total 16241

The Schematic diagram of Vijayanagar channels is appended as KNNL-VNC-SD-002 vide

Volume V - Drawings

1.5. Accessibility

The project channels located at downstream of TB dam are best approached from Hospet,

Munirabad and Kamalapur on the upper reach and from Gangavathi on the lower reach.

1.6. Toposheet Mosaic of the project

The details of toposheets showing the channel network and their command area are given as below

in Table 1.4.

Table 1.4 – Details of toposheet which cover the project area

No Topo Sheet No. Scale

1. 57 A/7 1:50,000

2 57 A/8 1:50,000

3. 57 A/10 1:50,000

4 57 A/11 1:50,000

5 57 A/12 1:50,000

6 57 A/13 1:50,000

7 57 A/14 1:50,000

8 57 A/15 1:50,000

9 57 E/2 1:50,000

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 7

The mosaic of toposheets relevant to the project area is indicated in Fig 1.1

Fig 1.1– Top sheet mosaic of the project area

1.7. Present condition

Presently, the Vijayanagara channel systems comprising of the above 16 Channels are not in good

condition. The system has been in operation over the last 400 years. The reconnaissance survey has

revealed that the channels are lined with size stone masonry partly and have since lost their shape over the

years. The bed of the channels has scoured in some reaches and is silted up heavily in some reaches.

Heavy weed growth (water hyacinth) is noticed in and around the channels. Some of the structures are in

dilapidated condition which requires to be rehabilitated to make them functional.

1.8. Deficiencies in the existing system

The Vijayanagara channels were constructed during Vijayanagar dynasty i.e. about 400 years back. The

duty- delta considered for calculation of crop water requirement is not available. The duty-delta method of

calculating crop water requirements started in the 18th century. Thus, the farmers were used to the liberal

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 8

use of water for hundreds of years. With plenty of water, the crops grown were mostly rice, sugarcane etc.

Presently main channels are in bad condition and the pipe outlets are not having flow control. The

Tungabhadra project commissioned in the 50s considers the duty- delta for calculation of crop water

requirements and the channel design. However, the existing atchkat under Vijayanagar channels were

considered as part of the command under the Tungabhadra project.

Other problems encountered in the Vijayanagara channels in terms of operation and maintenance are;

a) Existing Channels have lost their section, thereby having difficulty in ensuring adequacy of flow.

b) Absence of measuring devices.

c) Inlets and outlets requiring redesign.

d) Unlined channels causing undesirable seepage, weed growth (water hyacinth)

e) Leakages in the main channels and cross drainage structures resulting in wastage of water.

1.9. Need for Modernization

The report Vol III of expert committee for preparation of master plan for river basin of Karnataka (constituted

vide G.O.No.PWD 70 NPC 85 dt.29/7/85) vide page no. 106 Para 2 mentions;

“ If this Channel system is lined and water measuring devices are provided and Warabandi system is

introduced it would be possible to manage about half the present discharge, thereby affecting the substantial

savings of about 7 TMC of scarce water resources which could be utilized for providing protective irrigation

to drought prone area in the State.”

The committee after deliberations, recommended for modernization of entire channel network of Vijayanagar

Channel system, as early as possible.

Hence, modernization of Vijayanagara Channels is proposed to save water as it was noticed that excess

water is being utilized in these channels. The Master Plan of 2003 revised the plan and made a suggestion

to modernize the existing Channel system by improvements in infrastructure to save water to an extent of

6.25 TMC which could be allocated to the Upper Bhadra project. In order to establish savings in water,

following measures are contemplated.

As the Channel systems are designed as unlined channels which are not efficient, it is proposed to redesign

the channels as lined channels to improve conveyance efficiency. The designed discharge is worked out

considering average cropped area of the last 20 years. This will facilitate reducing seepage losses thereby

improving the system efficiency and convey required discharge in the distributaries, minors and laterals

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 9

which will ensure water to the tail end of the channels thereby achieving reliability and equity in the

command area.

i. It is proposed to reconstruct the structures which are in bad condition. In addition, new structures are

proposed as per requirement of the farmers.

ii. Provision is made to install measuring devices in main channels, branch channels and minors for

improving operation.

Further, with the proposed improvements in channel infrastructure and operation, it is expected that there will

not be violation of cropping pattern by the farmers.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 10

Chapter 2. Hydrology

Extract from the further report of the Krishna Water Disputes Tribunal (KWDT)-I, the concerned paras

related to allocation of water for Raya and Basavanna Channels and Vijayanagar channels are reproduced

below

-“Raya channel and Basavanna Channel both of which take water directly from the Tungabhadra Dam on

the right side. 12.06 TMC of water (out of which 5.71 TMC is protected and 6.35 TMC is held as worth

consideration by the Tribunal) has been allocated in respect of all the Vijayanagar Channels of the state of

Karnataka including Raya and Basavanna Channels.”

“Further as per the final orders of Tribunal (KWDT-1), under the Clause IX (E), 7 TMC of water from

Tungabhadra reservoir is earmarked for Raya and Basavanna channels and an allocation of 2 TMC was

made by way of assistance through other regulated releases / discharges for Vijayanagar Channels other

than Raya and Basavanna channels in a water Year.”

As regard the provision made in KWDT-II is concerned, the order of the tribunal (KWDT-II) contained in

volume–IV of the Report (Page 800 to 811) did not mention anything on the above decision of KWDT-I.

As for as the suggestion to carry out water available studies at the off take points of these channels, it is to

report as under

The Tungabhadra Board, maintains the water account in details by bringing out Annual Report furnishing

there with the Performance of Tungabhadra Reservoir for each water year in a form of statement showing

the 10 daily inflows to Reservoir and corresponding outflows (drawals) by Karnataka state and Andhra

Pradesh and publishing it as working table for operation of Tungabhadra reservoir for the each water year.

The performance of Tungabhadra reservoir for each water year (from June to May) contains the 10 daily

inflow to the reservoir and drawals by Karnataka state and Andhra Pradesh for the different canal systems

of Tungabhadra Project.

From the above, extract of Abstract from performance of Tungabhadra reservoir is enclosed as “Statement

showing the year wise details of inflows, outflows (Utilisation) under different canal system of Tungabhadra

project (Karnataka portion) for the period (water year) from 1990-91 to 2009-2010 separately vide

Annexure 2.1

From the above Annexure 2.1, the RR (River Releases) under column 7 has been further bifurcated for

VNC (Vijayanagar Channels) and RDS (Rajolibanda Diversion Scheme) in the Annexure 2.2 enclosed

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 11

here with. Thus the actual drawals (Utilisation) from Tungabhadra reservoir for Raya, Basavanna canals

and Vijayanagar Channels have been worked out and indicated under column 7 of Annexure 2.2. It may

be seen from the column 7 that an average of 6.80 TMC being utilized in a water year for Vijayanagar

Channels system (including Raya, Basavanna canal).

From the above para’s it may be concluded that the water available for these Vijayanagar channels at the

off take points (Releases from Tungabhadra Dam) is much more than the proposed/estimated crop water

requirement of 5.80 TMC on Modernisation of Vijayanagar channels in Tungabhadra project .

2.1. Water availability

The Vijayanagar channels system consists of 16 channels with the physical area (average) of 11154 ha.

The Krishna Water Disputes Tribunal (KWDT) - 1, in its award has allocated 12.05 TMC annually as

committed utilization.

Out of the above 16 channels, two channels namely Raya and Basavanna channels gets the water through

gated sluices provided in the right side of the T B Dam.

For the remaining 14 channels, the release of water is through weirs/anicuts/runoff across them.

Government of Karnataka has carried out two performance appraisal of Tungabhadra reservoir for the

years 1976 – 77 to 2005-06. The result of appraisal shows that Vijayanagara channels get their due share

of allocated water.

Further, the return flow from main channels of Tungabhadra project and Vijayanagara channels contributes

sufficiently to the downstream section of Tungabhadra River.

Thus with the proposed utilization in Vijayanagara channels, there will be sufficient water in the river to feed

these channels.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 12

Chapter 3. Reservoir

As the report pertains to Modernisation of Vijayanagar Channels and does not involve reservoir, the above

chapter is not discussed.

Chapter 4. Weir/Anicut

There are 12 no’s of Anicuts and the details are enclosed separately. Vijayanagar channels are being fed

from the anicuts constructed in the earlier days for providing irrigation. These anicuts were constructed

during the regime of Vijayanagar empires. They have been constructed using huge boulders and set in Zig-

Zag manner without any kind of mortar for bond. Due to this, the anicuts are subject to leakage of water

exacerbated by the displacement of boulders during high floods. Over a period of time, the system has

deteriorated and needs urgent attention and improvements. The farmers of Vijayanagar channels are

demanding improvements to anicuts.

The improvements proposed to anicuts are:

5. Providing 200 mm thick skin wall encasement to the anicut and grouting.

6. Providing anchor rods at every 1m interval on upstream and downstream of anicut for a width of 5

M all along the length.

7. Providing concrete toe walls on both ends

8. Formation of approach roads to the anicuts wherever required from the nearest road.

The details of the channels system are tabulated below:

4.1. Vijayanagara Channels

The Irrigation schemes comprising 17 Nos of anicuts across Tungabhadra river together known as

Vijayanagara Channels were implemented during Vijayanagara dynasty to provide irrigation facilities. Out

of these, Vallabhapur and Hoskote anicuts were submerged in the backwaters of Tungabhadra reservoir. In

order to cater to the command of Vallabhapur and Hoskote anicuts, one vent of size 1.8 m X 3.6 m is

constructed in the reservoir as a permanent sluice and these commands are fed through Raya and

Basavanna channels. A total of 12.06 TMC has been allocated by the tribunal to Vijayanagara channels

with a break up of 5.71 TMC as protected utilisation and 6.35 TMC as worth consideration.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 13

As per clause IX - E of KWDT award, 7 TMC of water from Tungabhadra reservoir is earmarked for Raya

and Basavanna channels. An allocation of 2 TMC was made by way of assistance through other regulated

discharges other than Raya and Basavanna channels from Tungabhadra reservoir.

In the 1993 master plan, an allocation of 12.05 TMC is made for the Vijayanagara channels without

channel wise breakup and river assistance.

The revised Master plan of 2003 has an allocation of 5.80 TMC for all the 16 Vijayanagara channels.

The Government of Karnataka is proposing the modernization of these Channels to improve the channel

efficiency thereby saving 6.25 TMC of water.

4.2. Details of Channel Systems

Table 4.1 – Table showing Location details of Channel system

No Name of the

channel Name of weir &

length in Km Name of stream

Distance d/s of TB Dam in

Km Remarks

Bellary District (on right side of river)

1. Basavanna Vallabhapur Submerged in Tungabhadra

reservoir

Channel takes off directly from

Tungabhadra dam on right side

2. Raya Hosakote --do-- --do-

3. Bella Hosur-0.602 Tungabhadra 2.4 Channel utilizes

seepage from

higher level

channels

4. Kalaghatta Drainage channel Halla 8

5. Turtha Turtha 3.048 Tungabhadra 16

6. Ramsagar Ramsagar 2.042 --do-- 28.8

7. Kampli Kampli anicut

0.94

--do~ 30.4

8. Belagodahal Drainage

channel

Halla 35.2 Channel utilizes

seepage from

higher level

channels

9. Siruguppa Siruguppa 1.95 Tungabhadra 80 Consists of 7 bits.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 14

No Name of the

channel Name of weir &

length in Km Name of stream

Distance d/s of TB Dam in

Km Remarks

10. Deshnur Deshnur 0.96 ~do-- 80

Koppal District (on left side of river) 11. Koregal

Koregal Submerged in Tungabhadra

reservoir

Channel takes off directly from

Tungabhadra Left Bank Channel

12. Hulugi Hulugi - 0.518 Tungabhadra 2.4

18. Shivapura Shivapura - 0.17 do 8

19. Anegundi Sanapur - 0.518 do 16

20. Upper Gangavathi Upper

Gangavathi0.78 do 27.2

21. Lower Gangavathi Lower Gangavathi 0.45

do 30.4

Raichur district 22. Bichal Bichal - 1.192 do 137.6

Table 4.2 – Table showing Hydraulic details of Channel system

No. Name of the Channel

Length of

Channel in Kms

Cropped area in Ha

Offtake

On right bank of TB River

1 Raya Channel 27.74 2855 Tungabhadra Dam

2 Basavanna Channel 16.50 1447 Tungabhadra Dam

3 Bella Channel 5.50 741 Hosur Anicut

4 Kalaghatta Channel 7.020 349 Drainage channel

5 Turtha Channel 18.69 1171 Turtha anicut

6 Ramasagar Channel 15.50 1024 Ramasagar Anicut

7 Kampli Channel 23.550 894 Kampli Anicut

8 Belagodahala 11.220 328 Drainage channel

9 Deshnur Channel 9.03 815 Deshnur Anicut

10 Siruguppa Channel 10.85 1344 Sirguppa Anicut

On left bank of TB River

11 Hulugi Channel 10.69 419 Hulugi anicut

12 Shivapura Channel 6.54 717 Shivapura anicut

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 15

No. Name of the Channel

Length of

Channel in Kms

Cropped area in Ha

Offtake

13 Anegundi Channel 19.44 1359 Sanapur anicut

14 Gangavathi upper Channel 9.00 1363 Upper Gangavathi anicut

15 Gangavathi lower Channel 9.54 1141 Lower Gangavathi anicut

16 Bichal Channel 14.50 276 Bichal Anicut

16243 Ha

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 16

Chapter 5. Land Potential

5.1. Culturable Command area

a) Originally adopted with basis

The Vijayanagar channels are the oldest, dating back to 17th century. It is observed that the CCA and net

irrigable area are not arrived at scientifically. As such, the existing CCA is considered.

b) Basis for fixing CCA

i. The general topographical maps of Survey of India (scale 1:50,000)

ii. Survey conducted the area plotted on a scale 1:15,000 conforming availability of land

iii. Based on village maps

iv. Actual atchkat attained at present under the outlets

Over the last few centuries of cultivation and irrigation, the farmers have been growing different crops.

However, for the present proposal, the irrigated area has been arrived at taking 20 years average of actual

cultivation which works out to the physical area as 11154.00 Ha and cropped area as 16243.00 Ha

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 17

Chapter 6. Cropping pattern and Crop Water Requirement

6.1. Details of Pre –Project / Original cropping pattern

The existing cropping pattern of Vijayanagar channels are as detailed below

Table 6.1 –Existing (Pre modernization) Cropping Pattern

The physical area (CCA) of each channel of Vijayanagar channel system is as per the register maintained

by the Tungabhadra Project Authorities. The cropped area under each channel for a period of 20 years

(1990-91 to 2009-10) as per records available in the Tungabhadra project has been considered for the

studies. The minimum cropped area of each channel during the last 20 years has been considered as

cropping pattern for pre-modernization period.

Unit : Area in ha

No Name of

canal

Phy. Area

(CCA)

Khariff Rabi Bi seasonal

Total Sugar cane

Garden Paddy Jowar Paddy Groundnut

1 Basavanna 1240 311 135 66 310 281 9 1113

2 Raya 2226 501 163 446 243 1349 78 2780

3 Bella 600 67 64 10 130 381 58 710

4 Kalaghatta 237 69 68 7 98 43 6 291

5 Turtha 931 175 42 109 110 119 545 1100

6 Ramasagar 673 202 91 248 215 2 96 854

7 Kampli 620 241 38 67 0 218 109 673

8 Belagodahala 210 89 12 74 44 12 65 296

9 Sirguppa 764 316 97 201 161 180 54 1008

10 Deshnur 478 141 6 104 30 312 26 619

Total 7979 2112 717 1332 1340 2897 1046 9443

11 Hulugi 265 170 12 0 10 0 48 241

12 Shivapura 403 120 2 116 13 0 29 280

13 Anegondi 789 389 5 182 316 10 177 1078

14 Upper Gangavathi

775 666 0 134 53 43 45 941

15 Lower Gangavathi

667 590 0 49 165 51 12 867

16 Bichal 276 13 0 13 0 170 79 275

Total 3175 1949 19 493 557 274 390 3682

Total Area 11154 4061 735 1825 1896 3171 1436 13125

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 18

It may be seen from the table that against a physical area of (CCA) 11,154 ha, the minimum cropped area

of the Vijayanagar channel system works out to 13,125 ha. Thus the crop intensity of 117.67% could be

achieved in pre- modernization period.

The overall cropping pattern of Vijayanagar channel system during pre-modernization period is as below:

Season/Crop Cropped area in ha % of cropped area

Khariff

1. Paddy 4056 30.9

2. Jowar 735 5.6

Rabi

1. Paddy 1824 13.9

2. Groundnut 1903 14.5

Perennial (Bi-seasonal)

1. Sugarcane 3176 24.2

2. Garden (Banana) 1431 10.9

Total 13,125 100.00

6.2. Details of Post –Modernisation/ proposed cropping pattern

Table 6.2 – Proposed (Post modernization) cropping pattern

The physical area (CCA) of each channel of Vijayanagar channel system is as per the register maintained

by the Tungabhadra Project Authorities. The cropped area under each channel for a period of 20 years

(1990-91 to 2009-10) with slight modification has been considered for the studies. The average cropped

area of each channel during the last 20 years has been considered as cropping pattern for post-

modernization period.

No Name of canal Phy. Area

(CCA)

Khariff Rabi Bi seasonal Total

Paddy Jowar Paddy Groundnut Sugarcane Garden

1 Raya 2226 441 1285 250 429 400 50 2855

2 Basavanna 1240 100 740 20 388 170 29 1447

3 Bella 600 70 396 14 127 80 54 741

4 Kalaghatta 237 30 172 10 102 15 20 349

5 Turtha 931 110 461 75 165 100 260 1171

6 Ramasagar 673 98 440 75 276 50 85 1024

7 Kampli 620 152 301 152 125 60 104 894

8 Belagodahala 210 41 112 35 83 17 40 328

9 Sirguppa 764 165 476 202 381 90 30 1344

10 Deshnur 478 188 224 121 217 55 10 815

Total 1395 4607 954 2293 1037 682 10968

11 Hulugi 265 91 129 82 77 20 20 419

12 Shivapura 403 190 176 117 202 2 30 717

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 19

No Name of canal Phy. Area

(CCA)

Khariff Rabi Bi seasonal Total

Paddy Jowar Paddy Groundnut Sugarcane Garden

13 Anegundi 789 234 417 128 450 6 124 1359

14 Upper Gangavathi

775 217 453 195 412 56 30 1363

15 Lower Gangavathi

667 164 404 170 317 48 38 1141

16 Bichal 276 13 140 9 4 60 50 276

Total 909 1719 701 1462 192 292 5275

Total Area 11154 2304 6326 1655 3755 1229 974 16243

It may be seen from the above table that against a physical area of (CCA) 11,154 ha, the average

cropped area of the Vijayanagar channel system works out to 16,243 ha. Thus the crop intensity of

145.6% could be achieved in post- modernization period.

The overall cropping pattern of Vijayanagar channel system during post-modernization period is as below:

Season/Crop Cropped area in ha % of cropped area

Khariff

3. Paddy 2304 14.18

4. Jowar 6326 38.95

Rabi

3. Paddy 1655 10.19

4. Groundnut 3755 23.12

Perennial (Bi-seasonal)

3. Sugarcane 1229 7.57

4. Garden (Banana) 974 6.00

Total 16,243 100.00

6.2.1. Field application efficiency

The Channel network of Vijayanagara Channel system is partially lined leaving a major portion unlined.

Now, to optimize utilization of water, it is proposed to line the entire Channel system (from main Channel

to field irrigation channels). The crop water requirements are calculated using “Modified Penman Method”

considering the field application efficiency as 85 % of ponded crops and 65 % for non ponded crops and

conveyance efficiency as 75%.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 20

Table 6.3–Table showing the breakup of Irrigation efficiency

No Type of Efficiency Ponded Non ponded

Conveyance efficiency of Channel system upto out let 75% 75%

Field application efficiency 85% 65%

Overall Irrigation efficiency 0.75 x 0.85

=0.6375

0.75 x 0.65 =0.4875

Say 64 %. Say 49 %.

Water requirement for crops under the scheme is calculated as per Modified Penman’s method for the

present notified area by considering the overall irrigation efficiency of 64% for ponded crops and 49% for

non ponded crops.

6.3. Assessment of Crop Water Requirement

The crop water requirement is computed based on Modified Penman’s method. The method consists of

computing evapotranspiration of crop (ETc) using the formula;

ETc = Kc x ET0

Where Kc - Crop coefficient

ET0 - Potential evapotranspiration

The ET0 values of Bellary station are considered for calculation as notified by Indian Meteorological

Department, PPSR - 136 and is tabulated below.

No Month ET0

1. Jan 115.1

2. Feb 128.5

3. Mar 170.9

4. Apr 180.9

5. Jul 155.7

6. May 194.8

7. Jun 167.0

8. Aug 152.8

9. Sep 138.4

10. Oct 123.4

11. Nov 106.0

12. Dec 104.0

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 21

6.4. Crop Water Requirement

The main objective of Modernisation of Vijayanagar channels is to improve efficiency of the channel

system. Minimize water losses and to establish savings of water. The crop water requirement are

calculated based on modified Penman’s method considering Hydrometerological data of Bellary and

weighted average rainfall of the atchkat. The Vijayanagar channel was allocated 12.05 TMC of water as

per the actual utilisation. Now the proposed utilisation is 5.80 TMC resulting in a savings of 6.25 TMC. For

Details regarding calculation of water requirements of crops refer Annexure 6.1 to 6.4.

Table 6.4 –Demand Table

No

Nam

e o

f ca

nal

Ph

y. A

rea

(CC

A)

Khariff Rabi Bi seasonal

To

tal

Pea

k d

isch

arg

e

m3/

sec

WR

in T

MC

Pad

dy

Jow

ar

Pad

dy

Gro

un

dn

ut

Su

gar

can

e

Gar

den

1 Raya 2226 441 1285 250 429 400 50 2855 1.75 1.03

2 Basavanna 1240 100 740 20 388 170 29 1447 0.81 0.45

3 Bella 600 70 396 14 127 80 54 741 0.37 0.24

4 Kalaghatta 237 30 172 10 102 15 20 349 0.19 0.1

5 Turtha 931 110 461 75 165 100 260 1171 0.82 0.47

6 Ramasagar 673 98 440 75 276 50 85 1024 0.66 0.34

7 Kampli 620 152 301 152 125 60 104 894 0.75 0.36

8 Belagodahala 210 41 112 35 83 17 40 328 0.24 0.12

9 Sirguppa 764 165 476 202 381 90 30 1344 1.09 0.48

10 Deshnur 478 188 224 121 217 55 10 815 0.64 0.31

Total 1395 4607 954 2293 1037 682 10968 3.90

11 Hulugi 265 91 129 82 77 20 20 419 0.36 0.16

12 Shivapura 403 190 176 117 202 2 30 717 0.57 0.27

13 Anegundi 789 234 417 128 450 6 124 1359 0.96 0.48

14 Upper Gangavathi

775 217 453 195 412 56 30 1363 1.05 0.48

15 Lower Gangavathi

667 164 404 170 317 48 38 1141 0.89 0.4

16 Bichal 276 13 140 9 4 60 50 276 0.18 0.11

Total 909 1719 701 1462 192 292 5275 1.90

Total Area 11154 2304 6326 1655 3755 1229 974 16243 5.80

6.5. Results

It is seen that channel wise allocation of water was not made. An overall allocation of 12.05 TMC of water

was made in the Master plan considering the present water utilization.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 22

Table 6.5 –Savings Achieved

SI No Unit Existing Allocation

(During 1993)

Utilisation as per Penman’s Method (With lining) after

modernization

Savings achieved

1 In MCM 341.36 164.44 177.00

2 In TMC 12.05 5.80 6.25

As seen from the above table, the savings achieved after Modernisation of the Vijayanagara Channels is

6.25 TMC. (Refer Annexure 6.4 for Crop water requirement tables)

6.6. Conclusions

6.6.1. Achieving required savings

It is seen from the above table, the savings achieved after Modernisation of the Vijayanagara Channels is

6.25 TMC.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 23

Chapter 7. Pissiculture

Pissiculture is being carried out in Basavanna Channel by Tungabhadra Board (Govt. of India). Pissiculture

is not being carried out in other channels.

Chapter 8. Horticulture

The garden crop viz Banana is only grown in the command area.

Chapter 9. Domestic and Industrial water supply etc.

Domestic water supply scheme to the tune of 25 MLD is in operation supplying water to Hospet town from

Basavanna Channel. A small quantity of 3.7 MLD is being supplied to Mariyammanahalli Village.

No water from the channel systems is being used for industrial purposes.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 24

Chapter 10. Demand Table

No Name of canal Phy. Area

(CCA)

Khariff Rabi Bi seasonal Total

Peak discharge

m3/sec

WR in TMC

Paddy Jowar Paddy Groundnut Sugarcane Garden

1 Raya 2226 441 1285 250 429 400 50 2855 1.75 1.03

2 Basavanna 1240 100 740 20 388 170 29 1447 0.81 0.45

3 Bella 600 70 396 14 127 80 54 741 0.37 0.24

4 Kalaghatta 237 30 172 10 102 15 20 349 0.19 0.1

5 Turtha 931 110 461 75 165 100 260 1171 0.82 0.47

6 Ramasagar 673 98 440 75 276 50 85 1024 0.66 0.34

7 Kampli 620 152 301 152 125 60 104 894 0.75 0.36

8 Belagodahala 210 41 112 35 83 17 40 328 0.24 0.12

9 Sirguppa 764 165 476 202 381 90 30 1344 1.09 0.48

10 Deshnur 478 188 224 121 217 55 10 815 0.64 0.31

Total 1395 4607 954 2293 1037 682 10968 3.90

11 Hulugi 265 91 129 82 77 20 20 419 0.36 0.16

12 Shivapura 403 190 176 117 202 2 30 717 0.57 0.27

13 Anegundi 789 234 417 128 450 6 124 1359 0.96 0.48

14 Upper Gangavathi 775 217 453 195 412 56 30 1363 1.05 0.48

15 Lower Gangavathi 667 164 404 170 317 48 38 1141 0.89 0.4

16 Bichal 276 13 140 9 4 60 50 276 0.18 0.11

Total 909 1719 701 1462 192 292 5275 1.90

Total Area 11154 2304 6326 1655 3755 1229 974 16243 5.80

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 25

Chapter 11. Impact of Modernisation

11.1. Upstream and Downstream Projects

As the Modernisation is proposed for channel system resulting in savings of water, there will be no negative

impact on the upstream and downstream projects. In fact, the modernization has positive impact enabling

to take up Upper Bhadra Project (UBP) out of the savings in the Channels and meeting requirement of UBP

to an extent of 6.25 TMC.

Chapter 12. Interstate aspects

KWDT-1 has made enblock allocation. Scheme-wise allocation is made in 1993 Master plan and revised

Master plan of 2002.

As per the revised Master Plan of 2002, an allocation of 12.05 TMC is made for all the Vijayanagara

channels without any break-up of channel wise allocation and river assistance vide Annexure 12.1

The revised Master plan of 2003 has allocated 5.80 TMC for all the 16 Vijayanagara channels.

The Government of Karnataka is now proposing to modernize these Channels to improve the efficiency and

effectiveness of them thereby saving 6.25 TMC of water. Supply of 5.80 TMC to these channels as per crop

water requirement will be ensured.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 26

Chapter 13. Channel system

13.1. Preamble

The Vijayanagar channels are one of the oldest canal system built in India by the Vijayanagar Dynasty

which ruled the Deccan Plateau for nearly 100 – 150 years. This dynasty ruled between 15th and 16th

century AD. The said canals supposed to have been built around 15th Century (about 450-500 years

back). As such, no records on designs and other technical data of channels are available. This has

necessitated that detailed surveys had to be conducted in order to arrive at Modernization activities to be

undertaken.

13.2. Survey of channel system

All Levels are based on GTS Bench Mark, located at the top of step of Vaikuntam IB having value

500.416 m above MSL.

Fig 13.1 – Survey work in progress

Double tertiary fly leveling has been carried out from GTS bench mark using Automatic level and

Temporary benchmarks have been established enroute.

TBMs are established at every 1 Km on the existing permanent structures like buildings, Km stones,

Sheet rocks, Survey boundary stones adjacent to the channels.

A detailed strip survey along the existing channel has been carried out by taking L-sections and Cross

sections at every 30 m intervals.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 27

Cross section levels are taken at closer intervals to get the true shape of channel section in the water

prism which is required to design the channels. The levels are extended up to 15 m beyond the edge of

service road. All the planimetric features are collected for a corridor width of 30 m along the alignment

and in addition, cross sections are taken at structures.

13.3. Site Inventory and survey of channels and structures

Field reconnaissance survey along the existing channel network is carried out in order to identify the take

off point, alignment, various constraints along the existing channels, accessibility, topography, terrain, soil

formation including crops that are being cultivated.

The bigger channels are the Raya and the Basavanna channels. These channels take off from the

Tungabhadra dam and other channels take off from pick up weirs (PUWs) i.e Anicuts on Tungabhadra

river.

Anicuts have been constructed with huge boulders / cut stones dumped or set in zigzag manner. The

existing rip-rap boulders are having lot of voids which cause leakage of water and displacement of

boulders during high floods. Most of the channels take off from such PUWs across Tungabhadra river and

no head regulators or control structures exist. Actually, the Vijayanagara channels is a run-of- the river

scheme. Therefore, it is necessary to construct head regulators and measuring structures on the

channels which are absent. It is observed that the PUWs need major repairs.

Improvements to anicuts are a long felt desire of ayacutdars of Vijayanagara channels. In order to make

use of the run off from the river effectively, it is proposed to take up repairs of existing anicuts.

Irrigation under Vijayanagara channels has a long history. The anicuts and channel systems were

constructed during the regime of Vijayanagara Empire and are still in operation. With passage of time, the

system has deteriorated needing improvements which are critically needed.

A brief description of all the points observed during site visits is as follows;

The alignment of both Raya and Basavanna channels generally run through Municipal area of the

Hospet town where the urban development has taken place right up to the channel boundary and

in certain places, the channel land has also been encroached. The used water, filth including the

drainage is let into the channels at several locations and the water appears to be contaminated.

Photographs of select locations along channels showing the above observations are furnished as

below.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 28

1. The channel water being extensively used by the people residing adjacent to the channel for the

purpose of bathing, washing, cattle feeding etc. It has also been reported that some of the people

drink the water on account of which several water-bourne diseases have been reported.

Fig 13.2 – Figure showing untidy channels

2. Several inlets in the form of well-constructed pipelines, open channels etc., has been directly

linked to the channel and as such at several locations, the channel functions as either a seepage

disposal point or drainage line.

Fig 13.3 – Channel used as disposal point

3. In most of the locations, the channel has been aligned in restricted right of way due to presence

of huge rocks and boulders.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 29

4. Some of the sections of the channel have been laid using size stone masonry and concrete, but

these are all limited to the town limit.

Fig 13.4 – Channel reaches with size stone masonry lining

5. Substantial seepage has been noticed from the channel at several locations due to poor

maintenance.

Fig 13.5 – Damage due to seepage and poor maintenance

6. While reptiles such as snakes and crocodiles have been noticed in the channel water and on the

banks.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 30

Fig 13.6 – Crocodile in the reaches of Raya channel Fig 13.7 – Snake found in the initial reache of Belagodahala channel

7. Thick vegetation growth has been noticed at several locations along the channel within the water

spread area.

Fig 13.8 – Thick vegetation around the Channel

8. Most of the structures are deteriorated.

9. The entire channel network lacks proper crossing and connection. The service roads are heavily

damaged and it is difficult to carry out the inspection of the channel.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 31

Fig 13.9 – Damaged Service road Fig 13.10 – Poor crossing structure

10. Channel water happens to be the lifeline for most of the villages en-route since there is no

dedicated water supply for meeting their day to day domestic water requirement.

Fig 13.11 – Channel flowing full Fig 13.12 – Service road

11. The surface soil is generally black cotton. However, murrum, gravel and hard rock are also

encountered at select locations

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 32

Fig 13.13 –Banana plantation Fig 13.14 –Sugarcane plantation

12. Banana, sugarcane and paddy are the major crops in the command area.

13. Certain channels run in deep cut.

14. There are no proper sign boards or indicative marks, km stones, hectometer stones, chainage

stones etc. along the channel.

13.4. Review of capacity of existing channel and distribution system.

13.4.1. Original design

The Channels have been constructed during the period of Vijayanagara kingdom about 400 years ago. As

such, the channels designed and constructed are outdated in terms of water delivery service (reliability,

flexibility and equity) due to inadequate maintenance and low efficiency.

13.4.2. Present capacity

The Channel systems being unlined are utilizing 12.05 TMC for irrigating 16,241.00 Ha (both Khariff and

Rabi) of cropped area. The command area is 11,154.00 Ha.

13.4.3. Design of revised section (lined)

The Channels Raya and Basavanna take off from Tungabhadra Dam and all other channels except

Kalghatta and Belgodhal take off from anicuts. The Raya channel runs for about 27.7 Kms and joins

Turtha channel at Km 4.0. There is a separate sluice at Km 2.5 of Raya Channel to fulfill the shortage of

water to Bella channel. The Bella Channel runs for about 5.55 Kms and joins Kalghatta channel at 0.2

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 33

Km. The Kalghatta channel runs for about 7.02 Km and joins Turtha channel at K m 0.7. The Turtha

channel runs for about 18.69 Km and joins Ramasagar channel at Km 1.4. The Ramsagar channel runs

for about 15.5 km and joins Kampli channel. The Kampli channel runs for about 23.55 Kms and joins

Belgodhal channel.

The Raya channel is designed by considering its peak discharge as per Modified Penman Method plus

10% extra for rush irrigation including discharges of downstream channels like Bella, Turtha, Ramsagar

and Kampli. Likewise, the downstream channels Bella, Kalghatta, Turtha, Ramsagar and Kampli are

designed for peak discharge plus 10% for rush irrigation.

Belgodhal and Basavanna channels are also designed considering Modified Penman method plus 10%

extra for rush irrigation.

The Channels on left side of Tungabhadra river runs parallel to the Left Bank Main Channel (LBMC)

namely Hulugi, Shivpura, Anegundi, Gangavathi Upper, Gangavathi Lower, and Bichal. There are number

of direct Inlets to these Channels. The Channels are designed for peak discharge obtained from Modified

Penman Method plus 10% rush irrigation requirement.

Based on this, channel sections are designed reach wise considering the existing bed gradient with

Rugosity coefficient (n) of 0.018 for concrete lined channels. Inlets are proposed based on the site

conditions and surplussing weirs are proposed at defined nalas. Refer Annexure 13.1 for particulars of

channel system

13.5. Identification of the reaches needing improvements

A reconnaissance survey was carried out along with the officials of the department to assess the

condition of channels and structures. Looking at the poor state of the channel infrastructure,

modernization estimate is prepared incorporating dismantling and reconstruction of dilapidated structures

and providing concrete lining throughout the length of the channel to enable conveyance of water to tail

ends of the channel and to prevent seepage losses, thereby save water.

13.5.1. Lining

The channels are under operation for more than 400 years providing irrigation for two seasons. Due to the

operation of channels for two seasons in a year, it has lost its shape in several stretches due to scouring

effect and also accumulation of silt over a period. This has resulted in reduction in the velocity of water.

On account of this, it is difficult to convey water to the tail end areas during irrigation season. As a result,

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 34

standing crops at the tail end are not getting enough water. In order to mitigate this problem, water is

being allowed into the channels for saving standing crops during both seasons. Hence, it is necessary to

redesign the channel section with concrete lining. This will also help in improving the efficiency in the

channel system and achieve the desired savings in water. To have uniform quality of concrete lining and

for better compaction, mechanical paver lining is proposed where the bed width is more than 1.20 M from

practical considerations of availability of mechanical pavers. For other reaches where bed width is less

than 1.2 M, manual concrete lining is proposed. The lining has been proposed for entire length upto free

board level with concrete coping on either side for a width of 0.30 M. Since the channels are running in

black cotton soils area which is having swelling nature, CNS layer is proposed below concrete lining as

per BIS.

13.5.2. Strengthening and stabilization of banks

The works of strengthening and stabilization of banks are proposed wherever required as per site

conditions.

13.6. Preparation of capacity statement

No assessment has been made regarding the discharges in the channels as channel system is very old

and infrastructure is not in good condition.

13.7. Need for remodeling / distribution system

The distribution systems of all the channels are not in good condition. Hence, remodeling of distribution

system with concrete lining is proposed.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 35

Chapter 14. Power

14.1. Power status

No proposal for generation of electrical power is envisaged in the modernization project.

14.2. Modernization / upgrading proposal

No power generation is proposed in the 16 channels of Vijayanagara Channels and as such there will be no

impact on the existing Power generation of Tungabhadra Reservoir.

Chapter 15. Navigation

The proposal is to modernize the existing channel system and as the channels are small ones in terms of

carrying capacity, navigation is not considered in this project.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 36

Chapter 16. Groundwater

Dynamic groundwater resources of Karnataka – March 2009 is published by joint efforts put by Department

of Mines and Geology, Govt of Karnataka and Central Groundwater Board, South Western Region,

Bangalore during Dec 2010. The report mainly provides groundwater resources available in Karnataka.

The details of Groundwater resources pertaining to Vijaynagar Channels is as follows:

16.1. Depth of Groundwater level

As per assessment, the depth of Groundwater for Pre monsoon and Post monsoon is as follows:

Table 16.1 – Table showing depth of Groundwater for Pre monsoon and Post monsoon

No Assessment

Unit Command/Non

command Rainfall in

mm

Average Pre monsoon

water level (mbgl)

Average Post

monsoon water level

(mbgl)

Average fluctuation

(m)

1. 4D3A3 Command 666.7 - - -

Non Command 666.7 - - -

2. 4D3A8 Command 612.6 - - -

Non Command 612.6 5.94 3.21 2.73

3. 4D3C2 Command 682.6 - - -

Non Command 682.6 - - -

4. 4D3F2 Command 721.8 - - -

Non Command 721.8 - - -

Note:

Delineation and codification of watersheds

The delineation of watersheds has been done in 5 stages. For ex: 4D3A3 indicates 4 as water resource

region, D indicated basin code, 3 indicate catchment code, A indicates sub catchment code and 3 indicate

watershed code.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 37

16.2. Assessment of Groundwater potential in the command area

As per assessment the groundwater potential is as follows:

Table 16.2 – Table showing Administrative wise assessment of Dynamic Groundwater resources

Administrative wise assessment of Dynamic Groundwater resources in ha-m

No

Nam

e o

f D

istr

ict

Nam

e o

f T

alu

k

Co

mm

and

/No

n c

om

man

d

Rec

har

ge

fro

m r

ain

fall

du

rin

g m

on

soo

n s

easo

n

Rec

har

ge

fro

m o

ther

sou

rces

du

rin

g m

on

soo

n

seas

on

Rec

har

ge

fro

m r

ain

fall

du

rin

g N

on

- m

on

soo

n

seas

on

Rec

har

ge

fro

m o

ther

sou

rces

du

rin

g N

on

-

mo

nso

on

sea

son

To

tal A

nn

ual

GW

rech

arg

e

Pro

visi

on

fo

r n

atu

ral

dis

char

ge

Net

an

nu

al G

W

avai

lab

ility

1. Raichur Raichur Command 712 467 302 645 2126 213 1913

Non Command 3502 399 1501 759 6160 609 5552

Total 4214 866 1802 1405 8287 821 7465

2. Koppal Gangavathi Command 1453 15607 790 14336 32186 3219 28968

Non Command 1765 503 836 614 3718 244 3474

Total 3218 16110 1626 14951 35904 3463 32442

3. Bellary Sirguppa Command 2231 7729 1309 4827 16097 1610 14487

Non Command 323 791 164 695 1974 197 1776

Total 2553 8521 1473 5523 18070 1807 16263

4. Bellary Hospet Command 1520 4176 826 2412 8935 894 8042

Non Command 1408 173 787 260 2629 263 2366

Total 2929 4349 1614 2673 11564 1156 1048

As per administrative assessment of unit wise categorization is as follows:

Table 16.3 – Table showing administrative assessment of unit wise categorization

No

Nam

e o

f D

istr

ict

Nam

e o

f T

alu

k

Co

mm

and

/No

n

com

man

d

Sta

ge

of

GW

dev

elo

pm

ent

(%)

Pre Monsoon Post Monsoon C

ateg

ory

Wat

er le

vel t

ren

d

Is t

her

e a

sig

nif

ican

t d

eclin

e

Wat

er le

vel t

ren

d

Is t

her

e a

sig

nif

ican

t d

eclin

e

1. Raichur Raichur Command 50 No decline No No decline No Safe

Non Command 73 No decline No No decline No Safe

2. Koppal Gangavathi Command 11 No decline No No decline No Safe

Non Command 120 Declining Yes Declining Yes OE

3. Bellary Sirguppa Command 70 No decline No No decline No Safe

4. Bellary Hospet Command 19 No decline No No decline No Safe

Non Command 57 No decline No No decline No Safe

*OE – Over Exploited

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 38

16.3. Quality of Groundwater

The information on ground water quality with respect to Vijayanagara channels are briefed below:

As per hydro chemical data of N.H.S of May 2003 in the district E.C.values range from 730-2870 micro

mhos /cm at 25°c is recorded. Chloride is in the range of 43 to639 mg/l and floride in the range of 0.6 to 2.7

mg/l as based on the Bureau of Indian standards recommendations for drinking water the water E.C having

less than 750 micro mhos/cm at 25°C is desirable and unsuitable more than3000 micro mhos/cm at

25°C.The concentration of fluoride is distributed in the district in the range of 1.0 to1.5 mg/l up to maximum

of 2.7 mg/l. The desirable limits for drinking purposes are less than 1 ppm. The concentration beyond 1

ppm is unsuitable, noticed as pockets in Gangavathi and Kushtagi taluks.

16.4. Assessment of possible impact on Groundwater

Due to Modernisation of the existing canal system under Vijayanagara Channels, the possible impact on

Groundwater is negligible.

16.5. Conjunctive use of surface and groundwater

By adopting Conjunctive use of surface and Groundwater, the entire command of all the canals can be

irrigated with use of optimal quantity of water thereby helping to save water.

With this, the farmers can arrest further water logging menace in the command of the canals.

The conjunctive use of the ground water particularly in tail end area will also help in supplementing the

canal irrigation by which entire command area could be served with 5.80 TMC thus saving about 6.25 TMC

of water.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 39

Chapter 17. Drainage and land reclamation

17.1. Review of drainage

The drainage system is sufficient to drain the water and no water logging, soil salinity and alkalinity has

been noticed. Anyway, it is recommended to propose surface drainage, water logging and such measures.

In the command area of 11154 ha under Vijayanagara channel system, an area of 340 ha is affected by

water logging, salinity and alkalinity. The Command Area Development Authority (CADA) of Tungabhadra

project has taken up the reclamation of these water logged area. This area has been reclaimed which can

be brought under cultivation with the proposed crop intensity of 145.6%.

17.2. Type of reclamation

17.2.1. Field drains

As curative and preventive measures to water logging and salinity problems, field drains treatment is given

which drains of excess water and lowers the salt concentration in the root zone and thus helps to improve

the crop yields. The field drains has been taken up in various programs.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 40

Chapter 18. Land acquisition, Rehabilitation and Resettlement

18.1. Land acquisition, Rehabilitation / Resettlement

Since the proposal is Modernization of the existing canal system (already in practice for more than 400

years), no acquisition of lands is envisaged.

The Vijayanagar channels do not have any reservoir which leads to submersion. Hence, question of

Rehabilitation and Resettlement (R&R) does not arise.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 41

Chapter 19. Water management and maintenance

The majority of the cultivated area belongs to small land holders. This is due to the increase in number of

families over the years depending on the same piece of land which is shared among the families. The

farmers generally own bullocks to plough the farm land. But the use of tractors, power tillers and tractor-

trailers are gradually increasing in the farm work in recent years.

The responsibility of the water management has been handed over to the Water User’s Cooperative

Societies (WUCS) formed in the villages of the command area by the Tungabhadra CADA, Munirabad..

However, water Resources Department i.e. with CADA of Tungabhadra project, will be responsible for water

distribution and maintenance of the channel system.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 42

Chapter 20. On farm development works

20.1. Command Area Development Authority

The Command area of Vijayanagar channels comes under the jurisdiction of Tungabhadra Command Area

Development authority. The functions of CADA are;

Preparation of plans and programs for the development of command area.

Distribution of agricultural implements and inputs such as ploughs, seeds, pesticides etc

Conducting farm trials and demonstration of new technologies in the agricultural field

Conserving and developing soil fertility

Equitable distribution of water to the entire command

Effective utilisation of surface water

Providing financial assistance through cooperative societies, banks etc.

20.1. Organization setup of On Farm Development

On farm development works are taken up by CADA, Tungabhadra Project with the assistance of officers of

concerned departments’ viz., Water Resources Department, Agriculture Department and Co-operative

Department.

20.1.1. Land leveling

The land leveling works were initially carried out by concerned farmers with subsidy grant and technical

assistance from CADA. Now, no subsidy grant is being provided, however, technical guidance is continued

to be provided.

20.1.2. Field Irrigation Channels (FICs)

In many parts of paddy growing area, use of field-to-field irrigation or katcha field channels is in practice. In

order to ensure timely and equitable distribution of water to each field and feed the water to the tail-end

farmers in the command area, construction of pakka Field Irrigation Channels (FICs) in vulnerable stretches

have been constructed by CADA Tungabhadra Project.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 43

20.1.3. Construction of field drains

The field drains are also being executed in the command area with the Central Assistance. The field drains

to serve as drainage area is 25% of the total command area i.e. 4,060 ha. Necessary provision is made in

the estimate for construction of field drains.

20.1.4. Warabandi

To ensure equitable distribution of water to all the lands under each outlet of the command area,

Warabandi system is to be brought into practice. In this system, each farmer gets water turn by turn for a

fixed time-interval proportionate to the extent of his land. For efficient and satisfactory water management,

Wireless Communication System has been established by CADA Tungabhadra project.

20.1.5. Ayacut roads

The ayacut roads in the command area of Vijayanagara channels are very old. The new ayacut roads

wherever essential as demanded by farmers is constructed by CADA Tungabhadra project.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 44

Chapter 21. Construction programme

The construction program is planned in a phased manner to be executed without affecting the irrigation.as

shown in table below;

Table 21.1 – Implementation program of Modernization of Vijayanagara channels

Name of the Channel Phases Remarks

1. Raya Phase – I during Nov-Dec closure period

-- 2. Basavanna

3. Bella

4. Kalghatta

5. Turtha

6. Ramsagar

7. Kampli

8. Belgodhal

1. Bella Phase – II during Apr-Jun closure period

Anicut works are taken up in Phase II due to lean flow in Tungabhadra river during April to June.

Anicuts in Phase I Channels are taken up under Phase II.

2. Turtha

3. Ramasagar

4. Kampli

5. Deshnur

6. Shirguppa

7. Hulugi

8. Shivpura

9. Anegundi

10. Upper Gangavathi

11. Lower Gangavathi

12. Bichal

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 45

Chapter 22. Construction organization

22.1. Organization setup for modernization

The Vijayanagar channels come under the control of Chief Engineer, ICZ, Munirabad. The hierarchical structure of the controlling officers is as follows:

Chief Engineer Irrigation Central Zone

Munirabad

Superintending Engineer TBP Circle Munirabad

Executive Engineer No 1 T.R. Division

Munirabad

Asst. Executive Engineer Vijayanagara Channel Sub

division, Kamalapura

Asst. Executive Engineer No.1Channel Sub Division

Oddarahatti camp

Asst. Executive Engineer No.2TR Sub Division

Agalkera

Asst. Executive Engineer No.2Low level Channel Sub

Division

Sirguppa

Superintending Engineer Tungabhadra Channel

Construction Circle Yarmarus

Executive Engineer No 2Channel Division

Oddarahatti

Executive Engineer No 6Channel Division

Bellary

Executive Engineer No 5Channel . Division

Yarmarus

Asst. Executive Engineer RDS Sub Division

Gilesgur Camp

Executive Engineer QC Division Munirabad

Asst.Executive Engineer

Q.C Sub Division

Munirabad

Asst.Executive Engineer

Q.C Sub Division

Bellary

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 46

Table 22.1 shows the Engineering divisions in charge of the channels.

Table 22.1 – Divisions in- charge of the channels

No. Name of the channel Name of the division

On right bank of TB river

1 Raya channel

Executive Engineer No.1 T.R.Division, Munirabad

2 Basavanna Channel

3 Bella Channel

4 Kalghatta Channel

5 Turtha Channel

6 Ramasagar Channel

7 Kampli Channel

8 Belagodahala

9 Deshnur Channel Executive Engineer, No.6 Channel Division, Bellary 10 Siruguppa Channel

On left bank of TB river

11 Hulugi Channel

Executive Engineer, No.6 Channel Division, Oddarahatti

12 Shivapura Channel

13 Anegundi Channel

14 Gangavathi upper channel

15 Gangavathi lower channel

16 Bichal Channel Executive Engineer, No.5 channel Division Yermarus

Except in the case of Raya and Basavanna channels, where water is let out through a vent, in the case of

other channels, the water flows into channel system continuously and the maintenance is carried out by the

irrigation department.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 47

Chapter 23. Environment, Ecology and Forest aspects

Since the proposal is Modernization of the existing canal system (already in practice for more than 400

years,) there will be no effect on the Environment and Ecology of the area. No acquision is envisaged and

no forest lands are involved.

23.1. World Heritage Zone

Hampi and its surroundings are located in the buffer zone area of Hampi heritage site which is declared as

one of the world heritage center. Any activity of improvement or development are needs to be in sync with

its world heritage regulation .Turtha channel (0.00 to 8.00 Km) and Anegundi channel (0.00 to 19.44 Km )

runs in this buffer zone area and as such in order to abide by the regulations, these channels are provided

with stone pitching (above FSL) instead of cc lining as per the guidelines of the Archeological Survey of

India and also Hampi World Heritage Area Management Authority (HWHAMA).

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 48

Chapter 24. Economic Evaluation

24.1. For Channels

The estimate is prepared based on the designed section and cut-off statement of the channel. Provisions

made are as follows:

CC lining of 80 mm thickness is proposed using mechanical pavers where the channel bed is more

than 1.2 m.

Manual lining is proposed where the channel bed width is less than 1.2 m.

CNS backing is provided as the stratum met with is of B C soil as per BIS.

Provision of lugs and template walls as per standards

Improvement of service road

Improvement of inspection path.

Removal of silt.

Earthwork excavation in ordinary soil.

Constructing uncoursed rubble masonry

Tarfelt expansion joint for CC lining

Perforated GI pressure relief pipes for pressure relief arrangement

Hectometer, kilometre and boundary stones.

24.2. For Structures

Earthwork excavation in ordinary soil

M10 , 40 mm CC for foundation

M15, 40 mm CC for abutment.

M15, 20 mm CC for sub structure

M20 , 20 mm for Deck slab, kerb and wearing coat for bridges

Provision for steel reinforcement

Provision for stone pitching

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 49

An estimate for Rs.403.22 Crores is prepared for various works envisaged in the project with the following

provisions. The cost estimate is based on the latest schedule of rates of WRD, Bangalore (2013 -14). This

includes 25% extra weightage for closure period as provided in the SR. The total cost of modernization is

classified into different sub-heads shown below;

A. PRELIMINARY

A provision of Rs.174.59 lakhs is made for charges towards consultancy services viz, detailed survey,

investigation, Preparation of DPR etc and other preliminary works as required for the project.

B. LAND

No provision is made in the estimate towards land acquisition.

C. WORKS (ANICUT)

There are 11 anicuts. These anicuts are constructed using huge boulders in a Zig Zag manner. Due to

constant wear and tear during the last 400 years of existence, the boulders have been displaced and huge

leakages are noticed.

It is proposed to strengthen the anicut by providing cement concrete M 20 skin wall encasement.

The provisions made are as follows:

Providing anchor rods

Provision for curtain grouting

Providing skin wall to the entire length of anicut

Providing contraction joint

Providing concrete toe walls on both ends

Formation of approach roads to anicuts wherever required from the nearest road.

In addition, provision for coffer dam to facilitate unhindered repair works is made.

A provision of Rs. 6126.33 lakhs is made for Improvements of 11 anicuts. This involves providing anchor

rods to the bed and skin walls with CC M 20 throughout the length and width of the weir.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 50

D. REGULATORS AND MEASURING DEVICES

A provision of Rs. 2919.56 lakhs is made towards Repair/Reconstruction/new construction of head

regulators, Cross Regulators and measuring devices under main Channel and its networks. The details are

as follows:

No Name of the

Channel Name of

Structures

No of Structures

Construction Dismantling &

Reconstruction 1. Raya Head Regulator

Cross Regulator 1

Measuring Device 1

DPO 2 50 2. Basavanna Head Regulator 1

Cross Regulator 2

Measuring Device 1

DPO 42 3. Bella Head Regulator 2

Cross Regulator 1

Measuring Device 1

Distribution box 1

DPO 2 10 4. Kalghatta Head Regulator

Cross Regulator

Measuring Device 1

DPO 29 5. Turtha Head Regulator

Cross Regulator 3

Measuring Device 1

DPO 40

6. Ramsagar Head Regulator 1

Cross Regulator 2

Measuring Device 1

DPO 20 8 7. Kampli Head Regulator

Cross Regulator 1

Measuring Device 1

DPO 34 4 8. Belgodhalla Head Regulator

Cross Regulator

Measuring Device 1

DPO 21 8 9. Sirguppa Head Regulator

Cross Regulator 2 2

Measuring Device 1

DPO 2 0 10. Deshnur Head Regulator

Cross Regulator 4

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 51

No Name of the

Channel Name of

Structures

No of Structures

Construction Dismantling &

Reconstruction

Measuring Device 1

DPO 14 11. Hulugi Head Regulator

Cross Regulator

Measuring Device 1

DPO 55 12. Shivpura Head Regulator

Cross Regulator 1

Measuring Device 1

DPO 1 23 13. Anegundi Head Regulator

Cross Regulator 1

Measuring Device 1

DPO 54 14. Gangavathi

Upper Head Regulator 3

Cross Regulator 1

Measuring Device 1

DPO 26 15. Gangavathi

Lower Head Regulator 3

Cross Regulator 1 1

Measuring Device 1

DPO 29 16. B Bichal Head Regulator

Cross Regulator 1

Measuring Device 1

DPO 10

E. FALLS

A provision of Rs. 152.27 lakhs is made towards construction of channel drops for different channels and

also construction of chambers for linked channels, where the higher level channel joins the lower level

channel.

No Name of the Channel

Name of Structures

No of Structures

Construction Dismantling & Reconstruction

1. Raya Canal drop 9 2. Basavanna Canal drop 7 3. Bella Canal drop 4. Kalghatta Canal drop 1 5. Turtha Canal drop 7 6. Ramsagar Canal drop 7. Kampli Canal drop 8. Belgodhalla Canal drop

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 52

9. Sirguppa Canal drop 10. Deshnur Canal drop 11. Hulugi Canal drop 1 12. Shivpura Canal drop 1 13. Anegundi Canal drop 2 14. Gangavathi

Upper Canal drop

15. Gangavathi Lower

Canal drop 1

16. B Bichal Canal drop

F. CROSS DRAINAGE WORKS

A provision of Rs. 912.10 lakhs is made towards construction of inlets with CC M15 and under tunnels.

No Name of the Channel

Name of Structures

No of Structures

Construction

Dismantling & Reconstruction

1. Raya Inlet 2

Undertunnel 2 1 2. Basavanna Inlet 2

Undertunnel 2 2 3. Bella Inlet 4

Undertunnel 4. Kalghatta Trough 2

Undertunnel 5. Turtha Inlet

Undertunnel 6. Ramsagar Inlet 11

Undertunnel 7. Kampli Inlet 9

Trough 2 8. Belgodhalla Inlet 2

Undertunnel 9. Sirguppa Inlet

Undertunnel

Super passage 1 10. Deshnur Inlet

Undertunnel 11. Hulugi Inlet 2

Undertunnel 12. Shivpura Inlet 6

Undertunnel 1 13. Anegundi Inlet 10

Undertunnel 2 14. Gangavathi

Upper Inlet 13

Undertunnel 15. Gangavathi Inlet 3 1

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 53

Lower Undertunnel 16. B Bichal Inlet

Undertunnel

G. BRIDGES

A provision of Rs.1960.48 lakhs is made towards construction of Cart Track Crossings/ Village road

bridges with deck slab of CC M20, Foot Bridges and Sopanams.

No Name of the

Channel Name of Structures

No of Structures

Construction Dismantling &

Reconstruction 1. Raya Cart track Crossing 12 7

Major Road Bridge 1

Village road bridge 3

Foot bridges 1

Sopanams 1 2. Basavanna Cart track Crossing 7

Village road bridge 3

Foot bridges 1

Sopanams 6 3. Bella Cart track Crossing 1 4

Village road bridge 1 2

Foot bridges 1

Sopanams 1

Cattle ramp 3 4. Kalghatta Cart track Crossing 1 7

Village road bridge 2

Foot bridges 1

Sopanams 5. Turtha Cart track Crossing 7

Village road bridge

Foot bridges

Sopanams 2

Cattle ramp 1

6. Ramsagar Cart track Crossing 6 4

Village road bridge

Foot bridges

Sopanams

Cattle ramp 1 7. Kampli Cart track Crossing 20 16

Village road bridge 3 2

Foot bridges 15 5

Sopanams 3 8. Belgodhalla Cart track Crossing 12 4

Village road bridge 1

Foot bridges 1

Sopanams

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 54

No Name of the

Channel Name of Structures

No of Structures

Construction Dismantling &

Reconstruction 9. Sirguppa Cart track Crossing 2 3

Village road bridge

Retaining Wall 1

Sopanams 1 10. Deshnur Cart track Crossing 4 4

Road bridge 1

Foot bridges

Sopanams 11. Hulugi Cart track Crossing 8

Village road bridge 1

Foot bridges 1

Sopanams 12. Shivpura Cart track Crossing 2

Village road bridge 5

Foot bridges

Sopanams 13. Anegundi Cart track Crossing 2 9

Village road bridge 1

Foot bridges

Sopanams 5

Cattle ramp 3 1 14. Gangavathi

Upper Cart track Crossing 6

Village road bridge 1

Foot bridges

Sopanams 6 15. Gangavathi

Lower Cart track Crossing 4

Village road bridge

Foot bridges

Sopanams 16. B Bichal Cart track Crossing 11

Village road bridge

Foot bridges

Sopanams

H. ESCAPES

A provision of Rs.561.84 lakhs is made towards construction of Escapes, relieving weirs, and scouring

sluices with CC M15.

No Name of the

Channel Name of

Structures

No of Structures

Construction Dismantling &

Reconstruction 1. Raya Escapes 2

Relieving weirs

Scouring sluices 1 3 2. Basavanna Escapes

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 55

No Name of the

Channel Name of

Structures

No of Structures

Construction Dismantling &

Reconstruction

Relieving weirs 1

Scouring sluices 2 3. Bella Escapes

Relieving weirs 1

Scouring sluices 1 4. Kalghatta Escapes

Relieving weirs

Scouring sluices 1 5. Turtha Escapes 2

Relieving weirs 1

Scouring sluices 1

6. Ramsagar Escapes 2

Relieving weirs 1

Scouring sluices 7. Kampli Escapes

Relieving weirs

Scouring sluices 5 1 8. Belgodhalla Escapes

Relieving weirs

Scouring sluices 3 3 9. Sirguppa Escapes

Relieving weirs

Scouring sluices 1 10. Deshnur Escapes

Relieving weirs

Scouring sluices 2 11. Hulugi Escapes 1

Relieving weirs

Scouring sluices 7 12. Shivpura Escapes

Relieving weirs

Scouring sluices 1 13. Anegundi Escapes 5

Relieving weirs 2 7

Scouring sluices 14. Gangavathi

Upper Escapes 1

Relieving weirs

Scouring sluices 1 15. Gangavathi

Lower Escapes 1

Relieving weirs

Scouring sluices 1 16. B Bichal Escapes

Relieving weirs

Scouring sluices

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 56

I. NAVIGATION WORKS

No provision is made in the estimate as there is no navigation needs.

J. POWER PLANT CIVIL WORKS

No provision is made in the estimate as no power generation is involved.

K. BUILDINGS

A provision of Rs.155.00 lakhs is made in the estimate.

L. EARTHWORK, LINING AND SERVICE ROAD (MAIN CHANNEL)

A provision of Rs.20621.53 lakhs is made for 16 Nos channels of total length 215.93 Km towards

earthwork, lining and service road for main channels and its networks. CC mechanical paver lining of 80

mm thick is proposed where the bed width is greater than 1.2 m and for other reaches 75 mm thick manual

lining with M15 grade is proposed. At every 15 m interval, CC template walls are proposed. Provision of

CNS backing is made as the soil met with is of black cotton soil which is expansive in nature..

M. PLANTATION

A provision of Rs.67.95 lakhs is made for plantation on either side of the main channel at 15 m c/c. The

rate per Km works out to Rs. 31,500/-

N. TANKS AND RESERVOIRS

No provision is made in the estimate as it is not applicable to the current project.

O. MISCELLANEOUS

No provision is made in the estimate.

P. MAINTENANCE

A provision of Rs.391.41 lakhs is made towards maintenance at 1% of the cost of I – works less A,

B,O,M,P,Q and X as per CWC guidance. This covers the cost of maintenance of roads and other structures

during the period of construction.

Q. SPECIAL TOOLS AND PLANTS

A provision of Rs.40.46 lakhs is made in the estimate.

R. COMMUNICATIONS

No provision is made in the estimate.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 57

S. POWER PLANT AND ELECTRICAL MECHANICAL SYSTEM

No provision is made in the estimate.

T. WATER SUPPLY WORKS

No provision is made in the estimate.

U. DISTRIBUTARIES MINORS AND SUB-MINORS

A provision of Rs. 5454.41 lakhs is made for modernization of 64.92 Kms of distributory networks and

161 Kms of minors coming under Vijayanagara channels. Provision of CNS backing with 75 mm thick

manual CC lining of grade M15 is made in the estimate.

V. WATER COURSES

No provision is made in the estimate.

W. DRAINAGE

A provision of Rs.277.76 lakhs is made towards construction of drains as two of the channels namely

Raya and Basavanna runs in part of municipal area.

X. ENVIRONMENT AND ECOLOGY

No provision is made in the estimate.

Y. LOSSES OF STOCK

A provision of Rs.97.85 lakhs is made in the estimate at 0.25% of the cost of I – works less A, B,O,M,P,Q

and X as per CWC guidance.

Z. PROVISION FOR POWER GENERATION

No provision is made in the estimate.

TOTAL OF I - WORKS – 39913.55 LAKHS

II. ESTABLISHMENT CHARGES

No provision is made in the estimate.

III. TOOLS AND PLANTS

A provision of Rs. 9.12 lakhs is made in the estimate

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 58

IV. SUSPENSE

No provision is made in the estimate.

V. RECEIPTS AND RECOVERIES ON CAPITAL ACCOUNT

No provision is made under this sub head.

TOTAL DIRECT CHARGES

The total direct charges from the above sub head works out to Rs. 39922.67 lakhs.

INDIRECT CHARGES

A. Audit and accounts charges (1% of I –

works)

Rs 399.23 lakhs has

been made in this

sub head

B. Miscellaneous unforeseen works and

rounding of

TOTAL INDIRECT CHARGES

Total indirect charges as mentioned above Rs. 403.21 lakhs.

GRAND TOTAL = 40321.89 LAKHS

SAY 403.22 CRORES

Refer Annexure 24.1 for General Abstract

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 59

ABSTRACT COST FOR MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

Sl. No Particulars

(Rs. In Lakhs)

UNIT I Headworks (Anecuts)

UNIT II Canal Works

Total

I Direct Charges of Works

1 A - Preliminaries 174.59 174.59

2 B - Land - -

3 C - Works 6126.33 - 6126.33

4 D - Regulator 2919.56 2919.56

5 E - Falls 152.27 152.27

6 F - Cross Drainage Works 912.10 912.10

7 G - Bridges 1960.48 1960.48

8 H - Escapes 561.84 561.84

9 I - Navigation works - -

10 J - Power plants and Civil Works - -

11 K - Buildings 155.00 155.00

12

L - Earthwork

L1 - Lining 20621.53 20621.53

L2 - Service Road

13 M - Plantation 67.95 67.95

14 N - Tank and Reservoirs - -

15 O - Miscellaneous - -

16 P - Maintenance (1% of cost of I - works except A,B,M,O,Q and X)

61.26 330.15 391.41

17 Q - Special Tools and plants 40.46 40.46

18 R - Communication - -

19 S - Power plant and Electrical systems - -

20 T - Watersupply works - -

21 U - Distributories and Minors 5454.41 5454.41

22 V - Water Courses and Field Channels - -

23 W - Drainage 277.76 277.76

24 X - Environment and Ecology - -

25 Y - Loss of stocks and unforseen (0.25% of cost of I - works except A,B,M,O,Q and X)

15.32 82.54 97.85

Total of I - Works 6202.91 33710.64 39913.55

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 60

Sl. No Particulars

(Rs. In Lakhs)

UNIT I Headworks (Anecuts)

UNIT II Canal Works

Total

II Establishment charges -

III Small Tools & Plants 9.12 9.12

IV Suspens - -

V Reciepts & Recoveries on capital accounts deductions - -

Total Direct charges 6202.91 33719.76 39922.67

INDIRECT CHARGES

b)Audit and Account charges (1% of cost of I works) 62.03 337.20 399.23

Total Indirect charges 62.03 337.20 399.23

TOTAL DIRECT AND INDIRECT CHARGES 6264.94 34056.96 40321.89

Grand Total Say Rs 403.22 Crores

Chief Engineer KNNL, Irrigation Central Zone

Munirabad

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 61

Chapter 25. Administrative and Legislative provisions

25.1. Administrative set up

The present administration is under the Department of Water resources. It is oriented more towards

engineering aspects and is headed by one Chief Engineer (Irrigation Central zone). There are two circles with

four divisions and five sub-divisions to monitor the canal system. This department is responsible for

construction, maintenance of all structures within the command area and the canal system. In the past few

years, WUAS (Waters Users Association Society) named as Water Users Cooperative Society (WUCS) are

set up at the village / tank level. However, it is found that even after formation of the WUCS, there has been

low impact on the overall operation and maintenance of canal system.

Presently water demands are being done by the Water Resources Dept. /Nigam and the collection is being

done by WUCS. After registration of WUCSs, the Asst. Executive Engineer will issue the demand notice to the

WUCS and the societies will collect the charges and remit to the Govt. /Nigam as per the notification of the

Govt.

25.2. Legal status & Policy framework

The construction and O & M of the Vijayanagar channels are governed by various Government policies, which

include:

1. Karnataka Irrigation Act - 1965

2. Karnataka Community based Integrated Tank System Management Act – 2002

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 62

Chapter 26. Facilities for training the operational and maintenance personnel

26.1. Existing

No facilities for training the O& M personal have been noticed.

26.2. Proposals for improvement and extension

26.2.1. Institution framework

The water User’s Association needs to be constituted at the beginning of the implementation of the scheme

involving all the direct and indirect beneficiaries. This association shall function within the rules, regulations

and the byelaws of the society. There should be an organizing committee of the society and should contain

representative of all the sections of the beneficiaries with due representation to various sections such as

SC/ST, women, labour, backward class people etc. A proper training for management of its finance is of

utmost importance. The Programme / mechanism needs to be provided to make them aware of and be

informed to upgrade their managerial skill by way of various courses, training, discussions etc. The society

should run on a transparent basis with its finance being audited duly by the competent authority of the year.

The Government agencies should in their advisory capacity provides the society with technical inputs.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 63

Chapter 27. Operation and Maintenance

27.1. Training and Visit system

The Karnataka State Agricultural Department has taken up the training and visit system (T&V) of extensions in

the entire State of Karnataka. Under this system, the training programs have been conducted by the Assistant

Directors of Agriculture of concerned taluk, with the assistance of village extension workers and progress

would be reported to Principal Agriculture Officer. One village extension worker covers 400 farmer families.

The village extension worker will conduct regular contact programme once in fortnight. The Department will

also conduct regular workshops for every two months to educate farmers on agronomy, land protection,

introduction of new technology in the agricultural field etc.

In addition to the above, department has responsibility of proper distribution of subsidized seeds and

pesticides through agro centers and private agencies.

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 64

Chapter 28. B C Ratio

28.1. Benefit Cost ratio

The Benefit Cost Ratio (BCR) of the Modernisation of Vijayanagara channels has been prepared as per the

guidelines of Central Water Commission (CWC).

The Benefit cost ratio is worked out to 1.65

While calculating BCR, following have been considered.

28.1.1. Estimated value of produce before channel modernization

The yield of the crops, rate, and particulars of input i.e. seeds; fertilizers and pesticides and hired laborers

have been taken into account. Thus the net value of the produce is arrived at Rs. 4159.28 lakhs.

28.1.2. Estimated value of produce after channel modernization

After completion of channel Modernisation, to achieve increased production of crops, the cropping pattern

has been revised taking into consideration of water availability, soil conditions, present agricultural practice

including farmer’s attitude to grow the suggested cropping pattern.

Similarly, the yield of the crops, rate, and particulars of input i.e. seeds; fertilizers and pesticides and hired

laborers have been taken into account. The net value of the produce after Modernisation is arrived at

Rs.11899.78 lakhs. The increase in the yield of the crops after completion of Modernisation of Vijayanagara

channels, following factors contribute in the increased agricultural activities and thereby increase in the yield.

1. Seepage / wastage are minimised, thereby ensuring the supply of sufficient water to the tail end

achkat.

2. Proper and quick distribution and timely supply is assured.

The calculation of B.C. Ratio is appended in Annexure 28.1

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 65

Figures are in Rs lakhs

A Gross Receipts Before

Modernisation After

Modernisation

1 Gross value of farm produce 17355.35 25870.56

2 Dung receipts(at 30%of the fodder expenditure) 780.99 776.12

3 Total A : Gross Receipts(1+2) 18136.34 26646.68

B EXPENSES:

1 Expenditure on seeds 1048.89 688.09

2 Expenditure on manure etc. 5170.33 4305.61

3 Expenditure on hired labour(human and bullock) 3471.07 5174.11

4 Fodder expenses(as percentage of gross value of produce)

(15% ,10% of item A.1) 2603.30 2587.06

5 Depriciation on implements (2.7% of Item A.1) 468.59 698.51

6 Share and cash rent (5% 3% of Item A.1) 867.77 776.12

7 Land Revenue (2% of Item A.1) 347.11 517.41

8 Total B : Expenses (1 to 7) 13977.06 14746.89

C NET VALUE OF PRODUCE

1 Total gross receipts(Total A.3) 18136.34 26646.68

2 Minus total expenses (Total B.8) 13977.06 14746.89

3 Net value of produc © : [1-2] 4159.28 11899.78

D ANNUAL BENEFITS:

1 Net value after irrigation (C:3) 11899.78

2 Minus Net value before irrigation (C:3) 4159.28

3 Net annual benefits (D):[1-2] 7740.50

TOTAL NET ANNUAL BENEFITS (D3) 7740.50

E ANNUAL COSTS

1 Intrest on Capital @10% ( Esimated total cost of the project including cost of land development @ Rs.1000/- per Ha) (Rs 40322.00 Lakhs + 16.24 Lakhs)

4048.44

2 Depreciation of the project at 1 % of the cost of the project for 100 years life excluding cost of Land, R&R cost.(40322.00 Lakhs x 1%)

403.22

3 Annual operation and maintenance charge at Rs. 1175/ ha 190.86

4 Maintainance of the Head works at 1% its cost (Improvements to anicuts)

61.26

5 Total (E):Annual costs (1 to 4) 4703.78

BENEFITS COST RATIO = D 3 : Annual Benefits E.5: Annual cost

7740.50/4703.78 1.65

Chief Engineer KNNL, Irrigation Central Zone

Munirabad

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 66

MODERNISATION OF VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT

ESTIMATED VALUE OF PRODUCE BEFORE MODERNISATION

Crop % Area Area Ha

Produce (Qtls/Ha)

Rate per Qtl.

(Rs)

Value of produce

( Rs lakhs)

Input Seed Manure (Input) Hired Labour (Human & bullock)

Quantity Kg/Ha

Rate Rs/Kg

Amount (Rs

Lakhs)

Rate Rs/Ha

Amount (Rs Lakhs)

20% of total value of produce (Rs Lakhs)

1 2 3 4 5 6 7 8 9 10 11 12

Khariff

Paddy 30.90 4056 60 1979.00 4815.65 60.00 24 58.40 40000 1622.25 963.13

Hy. Jowar 5.60 735 20 2615.00 384.41 60.00 24 10.58 23000 169.05 76.88

Rabi

Paddy 13.90 1824 60 1979.00 2166.26 60.00 24 26.27 40000 729.75 433.25

Groundnut 14.50 1903 20 6009.00 2287.18 100.00 41 78.03 23000 437.72 457.44

Bi seasonal

Sugarcane 24.20 3176 60 2540.00 4840.61 7500.00 3 714.66 39000 1238.74 968.12

Garden (Banana) 10.90 1431 100 2000.00 2861.25 2250.00 5 160.95 68000 972.83 572.25

TOTAL 100.00 13125 17355.35 1048.89 5170.33 3471.07

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 67

MODERNISATION OF VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT

ESTIMATED VALUE OF PRODUCE AFTER MODERNISATION

Crop % Area Area Ha

Produce (Qtls/Ha)

Rate per Qtl. (Rs)

Value of produce

( Rs lakhs)

Input Seed Manure (Input) Hired Labour (Human & bullock)

Quantity Kg/Ha

Rate Rs/Kg

Amount (Rs

Lakhs)

Rate Rs/Ha

Amount (Rs Lakhs)

20% of total value of

produce (Rs Lakhs)

1 2 3 4 5 6 7 8 9 10 11 12

Khariff

Paddy 14.18 2304 75.0 1979.00 3419.71 60.00 24 33.18 30000 691.20 683.94

Hy. Jowar 38.95 6326 50.0 2615.00 8271.11 60.00 24 91.09 20000 1265.18 1654.22

Rabi

Paddy 10.19 1655 75.0 1979.00 2456.43 60.00 24 23.83 30000 496.50 491.29

Groundnut 23.12 3755 25.0 6009.00 5640.80 100.00 41 153.95 22000 826.08 1128.16

Bi seasonal

Sugarcane 7.57 1229 120.0 2540.00 3745.38 7500.00 3 276.48 36000 442.37 749.08

Garden (Banana) 6.00 974 120.0 2000.00 2337.12 2250.00 5 109.55 60000 584.28 467.42

TOTAL 100.00 16243 25870.56 688.09 4305.61 5174.11

Karnataka Neeravari Nigam Limited Modernisation of Vijayanagara Channels in Tungabhadra Project

Detailed Project Report 68

Conclusion

The Vijayanagara channels comprising of 16 channels are in existence for over 400 years. These channels

are very old and unlined. Due to lack of adequate maintenance, the channels have lost their shape and the

infrastructure is a bad state. Tail end farmers are not getting adequate water. This is resulting in inequity, low

productivity. There is dire need to modernize the channels for bringing down the over utilization in a scientific

way and for improving water delivery service (reliability, flexibility and equity). Furthermore, due to many

factors such as unlined channels, excessive seepage losses, over use of water, cropping pattern etc, the

existing channel system is utilizing excess water for irrigation. The master plan of 2003 has recommended

modernizing these channels thereby effectively bringing down the utilisation.

The report is prepared considering the above factors and proposal with estimate is prepared with the

objective to bring down the utilisation from 12.05 TMC. It is now seen that, on modernization and reworking

out crop water requirements as per Modified Penman Method, there is a savings of 6.25 TMC.

The total cost of proposed modernization is Rs. 403.22 Crores based on current WRD Bangalore SR of

2013-14 & PWD Bellary Circle SR of 2013-14 and the B.C. ratio works out to 1.65. Hence the project is

technically and financially viable. The DPR is submitted for administrative approval and technical sanction.

Chief Engineer KNNL, Irrigation Central Zone

Munirabad

UNIT I

Headworks

(Anecuts)

UNIT II

Canal

Works

Total

I

1 A - Preliminaries 174.59 174.59

2 B - Land - -

3 C - Works 6126.33 - 6126.33

4 D - Regulator 2919.56 2919.56

5 E - Falls 152.27 152.27

6 F - Cross Drainage Works 912.10 912.10

7 G - Bridges 1960.48 1960.48

8 H - Escapes 561.84 561.84

9 I - Navigation works - -

10 J - Power plants and Civil Works - -

11 K - Buildings 155.00 155.00

12 L - Earthwork

L1 - Lining 20621.53 20621.53

L2 - Service Road

13 M - Plantation 67.95 67.95

14 N - Tank and Reservoirs - -

15 O - Miscellaneous - -

16P - Maintenance (1% of cost of I - works except A,B,M,O,Q

and X)61.26 330.15 391.41

17 Q - Special Tools and plants 40.46 40.46

18 R - Communication - -

19 S - Power plant and Electrical systems - -

20 T - Watersupply works - -

21 U - Distributories and Minors 5454.41 5454.41

22 V - Water Courses and Field Channels - -

23 W - Drainage 277.76 277.76

24 X - Environment and Ecology - -

25Y - Loss of stocks and unforseen (0.25% of cost of I - works

except A,B,M,O,Q and X)15.32 82.54 97.85

Total of I - Works 6202.91 33710.64 39913.55

Direct Charges of Works

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

ABSTRACT COST FOR MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA

PROJECT

Sl. No Particulars

(Rs. In Lakhs)

UNIT I

Headworks

(Anecuts)

UNIT II

Canal

Works

Total Sl. No Particulars

(Rs. In Lakhs)

II Establishment charges -

III Small Tools & Plants 9.12 9.12

IV Suspens - -

V Reciepts & Recoveries on capital accounts deductions - -

Total Direct charges 6202.91 33719.76 39922.67

INDIRECT CHARGES

b)Audit and Account charges (1% of cost of I works) 62.03 337.20 399.23

Total Indirect charges 62.03 337.20 399.23

TOTAL DIRECT AND INDIRECT CHARGES 6264.94 34056.96 40321.89

Grand Total Say Rs 403.22 Crores

Chief Engineer KNNL, Irrigation Central Zone

Munirabad

(Rs. In Lakhs)

UNIT I

Headworks (Anecuts)

I

1 A - Preliminaries

2 B - Land

3 C - Works 6126.33

4 D - Regulator

5 E - Falls

6 F - Cross Drainage Works

7 G - Bridges

8 H - Escapes

9 I - Navigation works

10 J - Power plants and Civil Works

11 K - Buildings

12 L - Earthwork

L1 - Lining

L2 - Service Road

13 M - Plantation

14 N - Tank and Reservoirs

15 O - Miscellaneous

16 P - Maintenance (1% of cost of I - works except A,B,M,O,Q and X) 61.26

17 Q - Special Tools and plants

18 R - Communication

19 S - Power plant and Electrical systems

20 T - Watersupply works

21 U - Distributories and Minors

22 V - Water Courses and Field Channels

23 W - Drainage

24 X - Environment and Ecology

25Y - Loss of stocks and unforseen (0.25% of cost of I - works except

A,B,M,O,Q and X)15.32

Total of I - Works 6202.91

Direct Charges of Works

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

ABSTRACT COST FOR MODERNISATION OF VIJAYANAGARA CHANNELS IN

TUNGABHADRA PROJECT

Sl. No Particulars

(Rs. In Lakhs)

UNIT I

Headworks (Anecuts)

Sl. No Particulars

II Establishment charges

III Small Tools & Plants

IV Suspens

V Reciepts & Recoveries on capital accounts deductions

Total Direct charges 6202.91

INDIRECT CHARGES

b)Audit and Account charges (1% of cost of I works) 62.03

Total Indirect charges 62.03

TOTAL DIRECT AND INDIRECT CHARGES 6264.94

Sl

No.Description

Amount

Rs in Lakhs

Improvements to anicuts

1 Bella Channel 386.33

2 Turtha Channel 915.86

3 Ramasagara Channel 538.61

4 Kampli Channel 425.28

5 Deshnur Channel 561.40

6 Siruguppa Channel 248.18

7 Hulugi Channel 318.78

8 Anegundi Channel 265.38

9 Upper Gangavathi Channel 1352.52

10 Lower Gangavathi Channel 532.85

11 Bichal Channel 581.15

Total Rs 6126.33 Lakhs

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

C-WORKS

ABSTRACT

COST OF C-WORKS: Rs.6126.33 LAKHS

Sl.No Particulars Amount in Rupees Remarks

1Improvements to Hosur Anicut by provision of

skin walls3,69,39,330/-

2 Approach road to Hosur anicut 7,25,540/-

3 Coffer dam 9,68,497/-

TOTAL 3,86,33,367/-

386.33 Lakhs

2. Remodelling of Turtha Anicut

1 Improvements to Turtha Anicut 8,72,98,143/-

Details enclosed Refer

Volume-III of Annexure-1,

Page No.3

2 Construction of Coffer Dam 14,10,084/-

Details enclosed Refer

Volume-III of Annexure-1,

Page No.7

3 Construction of Approach Road 28,77,361/-

Details enclosed Refer

Volume-III of Annexure-1,

Page No.12

TOTAL 9,15,85,588/-

915.86 Lakhs

1 Improvements to Anicut 4,98,28,135/-

2 Construction of Coffer Dam 14,35,111/-

3 Construction of Approach Road 25,97,503/-

TOTAL 5,38,60,748/-

538.61 Lakhs

1 Improvements to Kampli Anicut 3,95,17,060/-

2 Construction of Coffer Dam 10,12,262/-

3 Construction of Approach Road 19,98,198/-

TOTAL 4,25,27,520/-

425.28 Lakhs

1 Improvements to Deshnur Anicut 5,47,32,203/-

2 Construction of Coffer Dam 14,07,370/-

TOTAL 5,61,39,573/-

561.40 Lakhs

1 Improvements to Siruguppa Anicut 2,41,09,418/-

2 Coffer dam 7,08,435/-

TOTAL 2,48,17,853/-

248.18 Lakhs

C-WORKS

5. Remodelling of Structures under Deshnur Channel

6. Remodelling of Structures under Siruguppa Channel

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

1. Remodelling of Structures under Bella Channel

3. Remodelling of Structures under Ramasagara Channel

4. Remodelling of Structures under Kampli Channel

Sl.No Particulars Amount in Rupees Remarks

1 Improvements to Hulugi Anicut 80,89,585/-

2 Construction of Coffer Dam 6,66,336/-

3Improvements to existing walls of the

Approach canal1,38,71,094/-

4Reconstruction of Hulugi anecut (Breached

portion) 70,24,303/-

5 Improvements to Hulugi Balancing Anicut 22,27,168/-

TOTAL 3,18,78,487/-

318.78 Lakhs

1 Improvements to Sanapur Anicut 2,55,39,606/-

2 Coffer dam 9,98,147/-

TOTAL 2,65,37,753/-

265.38 Lakhs

1 Improvements to Upper Gangavati Anicut 13,10,52,428/-

2 Construction of Coffer Dam 13,30,862/-

3 Construction of Approach Road 28,69,201/-

TOTAL 13,52,52,491/-

1352.52 Lakhs

1 Improvements to Lower Gangavathi Anicut 3,66,70,000/-

2Improvements to Lower Gangavathi Approch

Anicut1,11,49,901/-

3 Construction of side Wall to Approch Channel 37,47,075/-

4Construction of Causeway near Gangavathi

Lower anicut 10,12,653/-

5Construction of Coffer Dam for Approch

Anicut 1,17,507/-

6Construction of Coffer Dam for Gangavathi

Anicut 5,87,535/-

TOTAL 5,32,84,670/-

532.85 Lakhs

1 Improvements to Bichal Anicut 5,71,04,158/-

2 Construction of Coffer Dam 10,10,560/-

TOTAL 5,81,14,718/-

581.15 Lakhs

7. Remodelling of Structures under Hulugi Channel

8. Remodelling of Structures under Anegundi Channel

10. Remodelling of Structures under Lower Gangavathi Channel

11. Remodelling of Structures under Bichal Channel

9. Remodelling of Structures under Upper Gangavathi Channel

Amount

(Rs. In Lakhs)

UNIT I

Headworks (Anecuts)

I Direct Charges of Works

1 P - ` (1% of cost of I - works except A,B,M,O,Q and X) 61.26

Particulars

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

UNIT – I

P – MAINTENANCE

Sl. No

Amount

(Rs. In Lakhs)

UNIT I

Headworks (Anecuts)

1Y - Loss of stocks and unforseen (0.25% of cost of I - works except

A,B,M,O,Q and X)15.32

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

UNIT – I

Y – LOSS OF STOCKS AND UNFORSEEN

Sl. No Particulars

Amount

(Rs. In Lakhs)

UNIT II

Canal Works

I Direct Charges of Works

1 A - Preliminaries 174.59

2 B - Land -

3 C - Works -

4 D - Regulator 2919.56

5 E - Falls 152.27

6 F - Cross Drainage Works 912.10

7 G - Bridges 1960.48

8 H - Escapes 561.84

9 I - Navigation works -

10 J - Power plants and Civil Works -

11 K - Buildings 155.00

12 L - Earthwork

L1 - Lining 20621.53

L2 - Service Road

13 M - Plantation 67.95

14 N - Tank and Reservoirs -

15 O - Miscellaneous -

16P - Maintenance (1% of cost of I - works except A,B,M,O,Q and

X)330.15

17 Q - Special Tools and plants 40.46

18 R - Communication -

19 S - Power plant and Electrical systems -

20 T - Watersupply works -

21 U - Distributories and Minors 5454.41

22 V - Water Courses and Field Channels -

23 W - Drainage 277.76

24 X - Environment and Ecology -

25Y - Loss of stocks and unforseen (0.25% of cost of I - works

except A,B,M,O,Q and X)82.54

Total of I - Works 33710.64

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

ABSTRACT COST FOR MODERNISATION OF VIJAYANAGARA CHANNELS IN

TUNGABHADRA PROJECT

Sl. No Particulars

Amount

(Rs. In Lakhs)

UNIT II

Canal Works

Sl. No Particulars

II Establishment charges

III Small Tools & Plants 9.12

IV Suspens -

V Reciepts & Recoveries on capital accounts deductions -

Total Direct charges 33719.76

INDIRECT CHARGES

b)Audit and Account charges (1% of cost of I works) 337.20

Total Indirect charges 337.20

TOTAL DIRECT AND INDIRECT CHARGES 34056.96

Sl.

No.Description

Amount

Rs in LakhsRemarks

a

Consultancy charges for Detailed Survey, Investigation, Preparation of

designs, drawings and estimates for modernisation of Vijayanagar

Channels(Rs 74.88 Lakhs+ Tax @ 10.3 % Rs 7.71 lakhs) 82.59

Copy of

Agreement and

Shedule B

enclosed

bConsultancy charges for Preparation of Detailed Project Report as per

Central Water Commission Guidelines - 2010 19.50Quotation

enclosed

c Consultancy charges for Detailed Survey For Preparation Of Command

Area Maps, GIS Mapping For Vijayanagar Channels Command Area

72.50Quotation

enclosed

dConsultancy charges for Cost of Project Management Consultancy and

Quality Control 0.00

TOTAL 174.59

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

A -PRELIMINARIES

COST OF A-PRELIMINARIES : Rs.174.59 LAKHS

Sl.

No.Description Unit QTY

Rate

( Rs. Ps.)

Amount

( Rs. Ps.)

1 a.Concept planning

Preparation of detailed concept planning for

modernisation of vijayanagara channels including revised

hydrology,irrigation planning etc. as per guidelines of

CWC

Km 212 12000.00 25,44,000/-

2 b.Alignment / Strip survey for the main canal

Detailed survey of existing main canal km wise by taking

L section levels at 30mts interval and including alignment

plan,apex details,location of CD works. Cross sections at

30mt interval, with levels at 5mt intervl or at closer

intervals in order to describe the true shape of the

canal.Levels will be taken for a width of 15mt on either

side of main canal duly superimposing the approved

hydraulic section as per CBL and bed gradient.

3 Design and Estimates

Preparation of detailed designs, drawings, cost estimates

and DTP for modernisation main canals, branch canals

including structures as per approved concept planning for

Vijayanagara channels.

Km 212 12000.00 25,44,000/-

4 Detailed survey of distribution system (excluding FIC's)

including taking L section, and cross sections,preparation

of detailed design,drawings,cost estimates and DTP for

modernisation of distribution networks under vijayanagara

channels as per approved concept planning and to

provide irrigation facility to 16222 Ha of command area.

Km 200 12000.00 24,00,000/-

74,88,000/-

74.88 Lakhs

7,71,264/-

Rs 82.59 LakhsTotal =

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

A -PRELIMINARIES

Sub Total =

Add service tax at 10.3% as per GoI norms =

I. Detailed Survey, Investigation, Preparation of designs, drawings and estimates for modernisation of

Vijayanagar Channels

DISTRIBUTION NETWORK

Sl.

No.Description Unit QTY

Rate

( Rs. Ps.)

Amount

( Rs. Ps.)

1 Preparation of DPR in bound volumes and submitting to

MoWR/Central Water Commission for scrutiny at various

directorates

Set 15 5,000.00 75,000/-

2 Preparation of Km wise estimates of Main canal (216

Kms.) and Km wise estimates of Distributaries and minors

covering command area of 1,120 Ha (27 Kms), which is

10% of total command area, as deliberated in DPR, to

cost appraisal committee,

consisting of 216 Main canal Booklets and 27 Distributary

and Minors Booklets

Set 1 150000.00 1,50,000/-

3 Attend to the Comments & Observations of Central Water

Commission (CWC), Ministry of Water Resources

(MoWR) during Scrutiny of Detailed Project Report by

Concerned specialized directorates of CWC, CSMRS,

Central Water Board, Ministry of Agriculture (Crop

Division) & other connected departments of Govt. of India.

Attend to the Comments and Compliance/Observations

including Submission of Compliance/Clarification etc., and

finally get acceptance of Technical Advisory Committee of

MoWR/CWC.

Job 1 1400000.00 14,00,000/-

4 Submission of 10 sets of hard copies and 2 sets of soft

copies for record purpose after approval of CWC.Job 1 325000.00 3,25,000/-

19,50,000/-

19.50 Lakhs

Sub Total =

Note: Copy of quotation received from E I Technologies Pvt. Ltd. Bangalore is enclosed.

II. Preparation of Detailed Project Report as per Central Water Commission Guidelines -

Sl.

No.Description Unit QTY

Rate

( Rs. Ps.)

Amount

( Rs. Ps.)

1

Topographical survey of the Gross Command area of

Tungabhadra Project including demarcation of Main

Canal, Distributary Network, FIC network already

executed, preparation of C-planning map,

identification of realignment of canals required if any,

preparation of contours at 0.50 m interval,

mosaicking the village maps falling under the

command area and superimposing the topographical

contour/ C- planning map on th same, preparation of

Tree plan and hydraulic flow diagrams and other

data for GIS mapping, identification of reaches for

introducing Micro-Irrigation in the command area,

formation of WUC's, agriculture measures etc as

required for the scheme. Preparation of maps shall

also contain following details

Ha 11154.0 650.00 72,50,100/-

Establishing of Ground Control (GCP's) using

DGPS.

Survey number aqnd Hissa number of land

Total land under the pahani.

Land Revenue details.

Land owner's name with Extent's and Khatha

number.

The way land is acquired by the owner

Government / Public rights on the land.

Liabilities of the owners on the land.

Classification of the soil.

Number of Trees.

Source of irrigation and area irrigated.

Cultivators Details.

Utilization of land under Various categories.

Details crops grown season wise.

Details mixed crops.

Canal network as GIS layer File.

GPS Survey to be conducted to identify FIC network

upto distributory level with accuracy of + 5m.The structures to be identified as per tree plan

spatial on the ground along the canal such as DPO's Features of the Canal, Design Details of the

structures and canal to be attached to attribute data Developing database for the command area.

Land parcel wise attribute information to be attached

to the respective parcels.

The Scale of the output maps would be around

1:50000 ( + 12m accuracy) and reduced to + 5M

accuracy maps.

III. DETAILED SURVEY FOR PREPARATION OF COMMAND AREA MAPS, GIS MAPPING FOR VIJAYANAGAR

CHANNELS COMMAND AREA

Sl.

No.Description Unit QTY

Rate

( Rs. Ps.)

Amount

( Rs. Ps.)

Not only the gross command but also cultivable

command area can be authentically brought into

records by this management system.

Suffering atchkiats can be reorganized by balancing

excess and deficit water.3. Bore wells location GPS survey in the command.

4. Balancing Reservoirs/MI Tanks data with

attributes in the command.

72,50,100/-

72.50 Lakhs

Sub Total =

Note: Copy of quotation received from E I Technologies Pvt. Ltd. Bangalore is enclosed.

Sl

No.Description

Amount

Rs in Lakhs

Construction of Regulators and Measuring Device Coming

under entire Vijayanagar Channel system(16 Nos.)

1 Raya Channel 375.36

2 Basavanna Channel 259.32

3 Bella Channel 125.52

4 Kalaghatta Channel 172.92

5 Turtha Channel 244.55

6 Ramasagara Channel 216.48

7 Kampli Channel 190.26

8 Belagodhalla Channel 117.25

9 Deshnur Channel 92.85

10 Siruguppa Channel 70.40

11 Hulugi Channel 243.68

12 Shivapura Channel 116.03

13 Anegundi Channel 289.40

14 Upper Gangavathi Channel 157.06

15 Lower Gangavathi Channel 193.86

16 Bichal Channel 54.62

2919.56 Lakhs

COST OF D-REGULATORS: Rs.2919.56 LAKHS

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

D-REGULATORS

ABSTRACT

TOTAL

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1Dismantling and Reconstruction of CR with

drop0 .000 95,07,200/-

2 Construction of Measuring Device 0.8 10,32,472/-

3 Dismantling and Reconstruction of DPO 1 .298 5,37,273/-

4 Dismantling and Reconstruction of DPO 1 .416 5,37,273/-

5 Dismantling and Reconstruction of DPO 2 .398 5,37,527/-

6 Dismantling and Reconstruction of DPO 2 .497 5,37,527/-

7 Dismantling and Reconstruction of DPO 2 .646 5,37,527/-

8 Dismantling and Reconstruction of DPO 2 .792 5,37,527/-

9 Dismantling and Reconstruction of DPO 2 .871 5,37,527/-

10 Dismantling and Reconstruction of DPO 2 .964 5,37,527/-

11 Dismantling and Reconstruction of DPO 3 .198 6,40,413/-

12 Dismantling and Reconstruction of DPO 3 .274 6,40,413/-

13 Dismantling and Reconstruction of DPO 3 .426 6,40,413/-

14 Dismantling and Reconstruction of DPO 3 .875 6,40,413/-

15 Dismantling and Reconstruction of DPO 5 .572 5,33,332/-

16 Dismantling and Reconstruction of DPO 5 .665 5,33,332/-

17 Dismantling and Reconstruction of DPO 5 .750 5,33,332/-

18 Dismantling and Reconstruction of DPO 5 .857 5,33,332/-

19 Dismantling and Reconstruction of DPO 6 .385 3,93,083/-

Details enclosed Refer

Volume-III of Annexure-2,

Page No.30

20 Dismantling and Reconstruction of DPO 6 .493 3,95,899/-

21 Dismantling and Reconstruction of DPO 6 .671 3,95,899/-

22 Dismantling and Reconstruction of DPO 6 .769 3,95,899/-

23 Dismantling and Reconstruction of DPO 6 .937 3,95,899/-

24 Dismantling and Reconstruction of DPO 7 .171 4,43,536/-

25 Dismantling and Reconstruction of DPO 7 .778 4,43,536/-

26 Dismantling and Reconstruction of DPO 8 .090 3,95,029/-

27 Dismantling and Reconstruction of DPO 8 .251 3,95,029/-

28 Dismantling and Reconstruction of DPO 10 .845 5,13,007/-

29 Dismantling and Reconstruction of DPO 11 .150 5,14,612/-

30 Dismantling and Reconstruction of DPO 11 .360 5,14,612/-

31 Dismantling and Reconstruction of DPO 12 .032 5,14,459/-

32 Dismantling and Reconstruction of DPO 12 .704 5,14,459/-

33 Dismantling and Reconstruction of DPO 13 .588 5,63,709/-

34 Dismantling and Reconstruction of DPO 14 .702 5,61,170/-

35 Dismantling and Reconstruction of DPO 15 .433 5,61,440/-

36 Dismantling and Reconstruction of DPO 16 .946 5,61,705/-

37 Dismantling and Reconstruction of DPO 17 .307 5,62,974/-

1. Remodelling of Structures under Raya Channel

D- REGULATORS / DIRECT PIPE OUTLETS ( DPOs)

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

38 Dismantling and Reconstruction of DPO 17 .780 5,62,974/-

39 Dismantling and Reconstruction of DPO 18 .499 5,62,782/-

40 Dismantling and Reconstruction of DPO 18 .884 5,28,473/-

41 Dismantling and Reconstruction of DPO 19 .377 5,28,473/-

42 Dismantling and Reconstruction of DPO 19 .850 5,28,473/-

43 Dismantling and Reconstruction of DPO 20 .590 5,29,451/-

44 Construction of DPO 21 .294 5,29,112/-

45 Construction of DPO 22 .104 5,62,401/-

46 Dismantling and Reconstruction of DPO 22 .725 5,62,401/-

47 Dismantling and Reconstruction of DPO 23 .883 5,62,401/-

48 Dismantling and Reconstruction of DPO 23 .900 5,62,401/-

49 Dismantling and Reconstruction of DPO 24 .270 5,63,021/-

50 Dismantling and Reconstruction of DPO 24 .929 5,63,021/-

51 Dismantling and Reconstruction of DPO 25 .348 4,54,293/-

52 Dismantling and Reconstruction of DPO 25 .960 4,54,293/-

53 Dismantling and Reconstruction of DPO 26 .330 4,55,780/-

54 Dismantling and Reconstruction of DPO 26 .340 4,55,780/-

TOTAL 3,75,35,850/-

375.36 Lakhs

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1Dismantling and Reconstruction of Cross

Regulator0.000 29,07,145/-

2 Dismantling and Reconstruction of DPO 0.276 4,98,744/-

3 Construction of Measuring Device 0.500 3,57,464/-

4 Dismantling and Reconstruction of DPO 0.719 4,97,485/-

5Dismantling and Reconstruction Head regulator

1.343 6,68,144/-

6 Dismantling and Reconstruction of DPO 2.932 4,97,520/-

7 Dismantling and Reconstruction of DPO 3.603 4,98,515/-

8 Dismantling and Reconstruction of DPO 3.610 4,18,248/-

9Dismantling and Reconstruction of Cross

Regulator4.716

13,45,492/-

10 Dismantling and Reconstruction of DPO 5.200 5,78,782/-

11 Dismantling and Reconstruction of DPO 5.643 5,78,782/-

12 Dismantling and Reconstruction of DPO 6.800 5,78,782/-

13 Dismantling and Reconstruction of DPO 7.350 5,78,782/-

14 Dismantling and Reconstruction of DPO 8.155 5,78,782/-

15 Dismantling and Reconstruction of DPO 11.190 5,78,782/-

16 Dismantling and Reconstruction of DPO 11.486 5,78,782/-

17 Dismantling and Reconstruction of DPO 12.827 4,98,782/-

18 Dismantling and Reconstruction of DPO 13.094 4,98,782/-

19 Dismantling and Reconstruction of DPO 13.285 4,98,782/-

20 Dismantling and Reconstruction of DPO 13.289 4,98,782/-

21 Dismantling and Reconstruction of DPO 13.408 4,98,782/-

22 Dismantling and Reconstruction of DPO 13.504 4,98,782/-

23 Dismantling and Reconstruction of DPO 13.604 4,98,782/-

24 Dismantling and Reconstruction of DPO 13.710 4,98,782/-

25 Dismantling and Reconstruction of DPO 13.812 4,98,782/-

26 Dismantling and Reconstruction of DPO 13.934 4,98,782/-

27 Dismantling and Reconstruction of DPO 14.203 4,98,782/-

28 Dismantling and Reconstruction of DPO 14.169 4,98,782/-

29 Dismantling and Reconstruction of DPO 14.236 4,98,782/-

30 Dismantling and Reconstruction of DPO 14.242 4,98,782/-

31 Dismantling and Reconstruction of DPO 14.417 4,98,782/-

32 Dismantling and Reconstruction of DPO 14.435 4,98,782/-

33 Dismantling and Reconstruction of DPO 14.689 4,98,782/-

34 Dismantling and Reconstruction of DPO 14.706 4,98,782/-

35 Dismantling and Reconstruction of DPO 14.960 4,98,782/-

36 Dismantling and Reconstruction of DPO 15.145 4,28,650/-

37 Dismantling and Reconstruction of DPO 15.341 4,28,650/-

2. Remodelling of Structures under Basavanna Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

38 Dismantling and Reconstruction of DPO 15.422 4,28,650/-

39 Dismantling and Reconstruction of DPO 15.520 4,28,650/-

40 Dismantling and Reconstruction of DPO 15.658 4,28,650/-

41 Dismantling and Reconstruction of DPO 15.766 4,28,650/-

42 Dismantling and Reconstruction of DPO 15.892 4,28,650/-

43 Dismantling and Reconstruction of DPO 15.970 4,28,650/-

44 Dismantling and Reconstruction of DPO 16.044 4,28,650/-

45 Dismantling and Reconstruction of DPO 16.226 4,28,650/-

46 Dismantling and Reconstruction of DPO 16.408 4,28,650/-

TOTAL 2,59,32,247/-

259.32 Lakhs

1 Dismantling and Reconstruction of CR 0.184 23,04,475/-

2 Construction of Measuring Device 0.430 5,89,428/-

3 Dismantle and Reconstruction of DPO 0.664 4,51,383/-

4 Construction of DPO 1.180 4,53,835/-

5 Construction of DPO 1.479 4,52,468/-

6 Dismantle and reconstruction of DPO 3.002 4,56,283/-

7 Dismantle and reconstruction of DPO 3.177 4,48,211/-

8Dismantling and Reconstruction of Head

Regulator3.281 12,15,804/-

9 Dismantle and reconstruction of DPO 3.912 4,56,283/-

10 Dismantling and Reconstruction of Offtake 4.240 21,21,659/-

11 Dismantling and Reconstruction of DPO 4.652 4,57,581/-

12 Dismantle and reconstruction of DPO 4.759 4,57,581/-

13 Dismantling and Reconstruction of DPO 4.853 4,57,581/-

14 Dismantling and Reconstruction of DPO 5.100 4,59,164/-

15 Dismantle and reconstruction of DPO 5.115 4,59,151/-

16 Dismantle and reconstruction of DPO 5.121 4,59,151/-

17Dismantling and Reconstruction of

Distribution Box5.550 8,51,921/-

TOTAL 1,25,51,961/-

125.52 Lakhs

3. Remodelling of Structures under Bella Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1Dismantling and Reconstruction of Offtake

cum CTC 0.014 25,00,680/-

2 Construction of Measuring Device 0.500 4,81,822/-

3 Dismantling and Reconstruction of DPO 1.351 4,92,632/-

4 Dismantling and Reconstruction of DPO 1.474 4,92,632/-

5 Dismantling and Reconstruction of DPO 2.215 4,92,723/-

6 Dismantling and Reconstruction of DPO 2.613 4,92,723/-

7 Dismantling and Reconstruction of DPO 2.805 4,91,356/-

8 Dismantling and Reconstruction of DPO 2.850 4,92,723/-

9 Dismantle and reconstruction of DPO 3.074 4,94,010/-

10 Dismantle and reconstruction of DPO 3.178 4,94,010/-

11 Dismantle and reconstruction of DPO 3.436 4,94,010/-

12 Dismantle and reconstruction of DPO 3.727 4,88,095/-

13 Dismantle and reconstruction of DPO 3.834 4,94,010/-

14 Dismantle and reconstruction of DPO 3.923 4,94,010/-

15 Dismantling and Reconstruction of DPO 4.072 4,93,317/-

16 Dismantling and Reconstruction of DPO 4.187 4,93,317/-

17 Dismantling and Reconstruction of DPO 4.305 4,93,317/-

18 Dismantling and Reconstruction of DPO 4.437 4,93,317/-

19 Dismantling and Reconstruction of DPO 4.658 4,92,234/-

20 Dismantling and Reconstruction of DPO 4.739 4,92,234/-

21 Dismantling and Reconstruction of DPO 4.837 4,93,317/-

22 Dismantling and Reconstruction of DPO 4.843 4,92,234/-

23 Dismantle and reconstruction of DPO 5.297 4,94,803/-

24 Dismantle and reconstruction of DPO 5.341 4,94,803/-

25 Dismantle and reconstruction of DPO 5.466 4,94,803/-

26 Dismantle and reconstruction of DPO 5.554 4,94,803/-

27 Dismantling and Reconstruction of DPO 6.110 4,94,803/-

28 Dismantling and Reconstruction of DPO 6.230 4,94,803/-

29 Dismantling and Reconstruction of DPO 6.250 4,94,803/-

30 Dismantling and Reconstruction of DPO 6.358 4,94,803/-

31 Dismantling and Reconstruction of DPO 6.516 4,94,803/-

TOTAL 1,72,91,953/-

172.92 Lakhs

4. Remodelling of Structures under Kalaghatta Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1 Dismantling and Reconstruction of CR 0.926 29,70,635/-

2 Construction of Measuring Device 0.500 5,53,638/-

Details enclosed Refer

Volume-III of Annexure-4,

Page No.123

3 Dismantling and Reconstruction of DPO 2.932 4,74,394/-

4 Dismantling and Reconstruction of DPO 3.603 4,74,488/-

5 Dismantling and Reconstruction of DPO 3.610 4,13,312/-

6 Dismantling and Reconstruction of CR 4.716 13,00,838/-

7 Dismantling and Reconstruction of DPO 5.200 5,51,299/-

8 Dismantling and Reconstruction of DPO 5.643 5,55,400/-

9 Dismantling and Reconstruction of DPO 6.800 5,56,493/-

10 Dismantling and Reconstruction of DPO 7.350 5,54,486/-

11 Dismantling and Reconstruction of DPO 8.155 5,54,748/-

12 Dismantling and Reconstruction of DPO 11.190 5,57,902/-

13 Dismantling and Reconstruction of DPO 11.486 5,57,902/-

14 Dismantling and Reconstruction of DPO 12.827 4,62,419/-

15 Dismantling and Reconstruction of DPO 13.094 4,64,460/-

16 Dismantling and Reconstruction of DPO 13.285 4,64,460/-

17 Dismantling and Reconstruction of DPO 13.289 4,64,460/-

18 Dismantling and Reconstruction of DPO 13.408 4,64,460/-

19 Dismantling and Reconstruction of DPO 13.504 4,64,460/-

20 Dismantling and Reconstruction of DPO 13.604 4,64,460/-

21 Dismantling and Reconstruction of DPO 13.710 4,64,460/-

22 Dismantling and Reconstruction of DPO 13.812 4,64,460/-

23 Dismantling and Reconstruction of DPO 13.934 4,64,460/-

24 Dismantling and Reconstruction of DPO 14.203 4,66,335/-

25 Dismantling and Reconstruction of DPO 14.169 4,66,335/-

26 Dismantling and Reconstruction of DPO 14.236 4,66,335/-

27 Dismantling and Reconstruction of DPO 14.242 4,66,335/-

28 Dismantling and Reconstruction of DPO 14.417 4,66,335/-

29 Dismantling and Reconstruction of DPO 14.435 4,66,335/-

30 Dismantling and Reconstruction of DPO 14.689 4,66,335/-

31 Dismantling and Reconstruction of DPO 14.706 4,66,335/-

32 Dismantling and Reconstruction of DPO 14.960 4,66,335/-

33 Dismantling and Reconstruction of DPO 15.145 3,99,361/-

34 Dismantling and Reconstruction of DPO 15.341 3,99,361/-

35 Dismantling and Reconstruction of DPO 15.422 3,99,361/-

36 Dismantling and Reconstruction of DPO 15.520 3,99,361/-

37 Dismantling and Reconstruction of DPO 15.658 3,99,361/-

38 Dismantling and Reconstruction of DPO 15.766 3,99,361/-

39 Dismantling and Reconstruction of DPO 15.892 3,99,361/-

40 Dismantling and Reconstruction of DPO 15.970 3,99,361/-

41 Dismantling and Reconstruction of DPO 16.044 3,98,757/-

42 Dismantling and Reconstruction of DPO 16.226 3,98,757/-

43 Dismantling and Reconstruction of DPO 16.408 3,98,757/-

44 Dismantling and Reconstruction of CR 17.577 11,48,679/-

TOTAL 2,44,54,946/-

244.55 Lakhs

5. Remodelling of Structures under Turtha Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1Dismantling and Reconstruction of Cross

regulator cum escape cum VRB0.000 39,83,909/-

2 Construction of Measuring Device 0.800 2,61,908/-

3 Construction of DPO 2.886 6,45,382/-

4 Construction of DPO 2.946 6,45,382/-

5 Dismantling and Construction of DPO 3.344 6,46,749/-

6 Dismantling and Construction of DPO 6.817 6,44,828/-

7 Construction of HR 6.973 7,34,061/-

Details enclosed Refer

Volume-III of Annexure-5,

Page No.139

8 Construction of DPO 7.099 4,36,921/-

9 Dismantling and Construction of DPO 7.399 4,38,288/-

10 Dismantling and Construction of DPO 7.749 4,36,921/-

11 Construction of DPO 8.030 4,35,293/-

12 Construction of DPO 8.283 4,35,293/-

13 Construction of DPO 8.344 4,35,293/-

14 Construction of DPO 8.413 4,35,293/-

15 Construction of DPO 9.805 4,34,982/-

16 Dismantling and Construction of DPO 10.238 4,35,036/-

17 Dismantling and Construction of DPO 10.495 4,35,036/-

18 Dismantling and Construction of DPO 10.667 4,35,036/-

19 Dismantling and Construction of DPO 10.901 4,35,036/-

20 Construction of DPO 11.264 4,34,208/-

21 Construction of DPO 11.800 4,34,208/-

22 Construction of DPO 12.100 4,33,622/-

23 Construction of DPO 12.419 4,33,622/-

24 Construction of DPO 12.472 4,33,622/-

25 Construction of DPO 12.651 4,33,622/-

26 Construction of DPO 13.020 6,23,165/-

27 Construction of DPO 13.549 6,23,165/-

28 Construction of DPO 13.648 6,23,165/-

29 Construction of DPO 13.912 6,23,165/-

30 Construction of DPO 13.994 6,23,165/-

31 Construction of DPO 14.750 6,23,165/-

32Dismantling and Reconstruction of Cross

regulator cum CTC15.386 25,15,064/-

TOTAL 2,16,47,602/-

216.48 Lakhs

6. Remodelling of Structures under Ramasagara Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1Dismantling and Reconstruction of CR cum

CTC 0.000 23,64,666/-

2 Construction of Measuring Device 0.500 4,34,698/-

3 Construction of DPO 0.680 4,40,042/-

4 Construction of DPO 1.540 4,29,800/-

5 Dismantling and Reconstruction of DPO 1.628 4,31,167/-

6 Construction of DPO 1.760 4,29,800/-

7 Construction of DPO 1.866 4,29,800/-

8 Construction of DPO 1.940 4,29,800/-

9 Construction of DPO 2.050 4,46,826/-

10 Dismantling and Reconstruction of DPO 2.162 4,41,888/-

11 Construction of DPO 3.360 4,48,404/-

12 Construction of DPO 3.510 4,48,404/-

13 Construction of DPO 3.650 4,48,404/-

14 Construction of DPO 3.830 4,48,404/-

15 Construction of DPO 3.980 4,48,404/-

16 Construction of DPO 5.660 4,47,450/-

17 Construction of DPO 6.050 4,46,953/-

18 Construction of DPO 6.470 4,46,953/-

19 Construction of DPO 6.950 4,46,953/-

20 Construction of DPO 7.450 4,63,555/-

21 Construction of DPO 7.830 4,63,555/-

22 Construction of DPO 7.950 4,63,555/-

23 Dismantling and Reconstruction of DPO 8.015 4,45,869/-

24 Construction of DPO 9.240 4,39,583/-

25 Construction of DPO 9.710 4,39,583/-

26 Construction of DPO 10.050 4,44,038/-

27 Construction of DPO 10.420 4,44,038/-

28 Construction of DPO 11.650 4,43,229/-

29 Construction of DPO 12.035 3,62,021/-

30 Construction of DPO 13.650 4,43,269/-

31 Construction of DPO 14.450 3,96,457/-

32 Construction of DPO 14.960 3,96,457/-

33 Construction of DPO 15.620 4,11,172/-

34 Construction of DPO 15.630 4,11,172/-

35 Construction of DPO 16.088 3,25,184/-

36 Construction of DPO 16.330 3,25,184/-

37 Construction of DPO 20.780 3,98,977/-

38 Dismantling and Reconstruction of DPO 21.452 4,00,867/-

39 Construction of DPO 21.960 3,99,500/-

40 Construction of DPO 22.350 3,99,438/-

TOTAL 1,90,25,516/-

190.26 Lakhs

7. Remodelling of Structures under Kampli Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1 Construction of DPO 0.430 3,96,097/-

2 Construction of Measuring Device 0.500 3,49,968/-

3 Dismantle and Reconstruction of DPO 0.526 3,96,985/-

4 Construction of DPO 0.835 3,96,097/-

5 Construction of DPO 1.350 3,94,577/-

6 Construction of DPO 2.310 3,87,003/-

7 Construction of DPO 2.920 3,87,003/-

8 Construction of DPO 3.170 3,91,924/-

9 Dismantle and Reconstruction of DPO 3.309 3,93,291/-

10 Construction of DPO 3.460 3,91,924/-

11 Construction of DPO 3.610 3,91,924/-

12 Dismantle and Reconstruction of DPO 3.744 3,93,291/-

13 Dismantle and Reconstruction of DPO 3.796 3,93,291/-

14 Dismantle and Reconstruction of DPO 3.919 3,93,291/-

15 Construction of DPO 4.500 3,91,924/-

16 Construction of DPO 5.120 3,91,399/-

17 Dismantle and Reconstruction of DPO 5.257 3,92,766/-

18 Dismantle and Reconstruction of DPO 5.323 3,92,766/-

19 Construction of DPO 5.730 3,91,399/-

20 Construction of DPO 5.940 3,91,399/-

21 Construction of DPO 6.020 3,90,710/-

22 Dismantle and Reconstruction of DPO 6.141 3,92,077/-

23 Construction of DPO 6.650 3,90,710/-

24 Construction of DPO 6.950 3,90,710/-

25 Construction of DPO 7.070 3,91,435/-

26 Construction of DPO 7.450 3,91,435/-

27 Construction of DPO 8.020 3,91,634/-

28 Construction of DPO 8.550 3,91,634/-

29 Construction of DPO 8.880 3,91,634/-

30 Construction of DPO 10.850 3,94,649/-

TOTAL 1,17,24,946/-

117.25 Lakhs

8. Remodelling of Structures under Belgodhalla Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1 Construction of Measuring Device 0.51 1,69,525/-

2Dismantling and Reconstruction of Cross

Regulator 1.51

12,39,299/-

3 Dismantling and Reconstruction of DPO 1.53 3,62,709/-

4Dismantling and Reconstruction of Cross

Regulator 2.235

12,35,057/-

5 Dismantling and Reconstruction of DPO 2.76 3,82,979/-

6 Dismantling and Reconstruction of DPO 2.955 3,82,979/-

7 Dismantling and Reconstruction of DPO 3.405 3,59,858/-

8Dismantling and Reconstruction of Cross

Regulator 3.63 7,58,864/-

9Dismantling and Reconstruction of Cross

Regulator 3.75 7,58,864/-

10 Dismantling and Reconstruction of DPO 4.095 3,56,368/-

11 Dismantling and Reconstruction of DPO 4.68 3,56,368/-

12 Dismantling and Reconstruction of DPO 4.715 3,56,368/-

13 Dismantling and Reconstruction of DPO 5.12 3,55,917/-

14 Dismantling and Reconstruction of DPO 5.283 3,55,917/-

15 Dismantling and Reconstruction of DPO 5.658 3,55,917/-

16 Dismantling and Reconstruction of DPO 5.690 3,55,917/-

17 Dismantling and Reconstruction of DPO 6.455 3,57,129/-

18 Dismantling and Reconstruction of DPO 7.210 3,92,358/-

19 Dismantling and Reconstruction of DPO 7.260 3,92,358/-

TOTAL 92,84,750/-

92.85 Lakhs

1 Construction of Measuring Device 0.210 2,43,632/-

2 Construction of DPO-1 0.762 3,39,836/-

3 Construction of DPO-2 0.824 3,39,836/-

4Dismantling and Reconstruction of Cross

Regulator3.060 20,66,016/-

5 Construction of Cross Regulator 4.700 15,11,739/-

6 Construction of Cross Regulator 6.345 12,69,585/-

7Dismantling and Reconstruction of Cross

Regulator6.705 12,69,585/-

TOTAL 70,40,230/-

70.40 Lakhs

9. Remodelling of Structures under Deshnur Channel

10. Remodelling of Structures under Siruguppa Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1Dismantling and Reconstruction of Measuring

Device0.510 57,337/-

2 Dismantling and Reconstruction of DPO 1.317 4,85,397/-

3 Dismantling and Reconstruction of DPO 1.410 4,85,397/-

4 Dismantling and Reconstruction of DPO 1.805 4,85,397/-

5 Dismantling and Reconstruction of DPO 1.901 4,85,397/-

6 Dismantling and Reconstruction of DPO 1.976 4,85,397/-

7 Dismantling and Reconstruction of DPO 2.108 4,50,295/-

8 Dismantling and Reconstruction of DPO 2.320 4,50,295/-

9 Dismantling and Reconstruction of DPO 2.812 4,50,295/-

10 Dismantling and Reconstruction of DPO 3.076 4,50,767/-

11 Dismantling and Reconstruction of DPO 3.186 4,50,767/-

12 Dismantling and Reconstruction of DPO 3.350 4,50,767/-

13 Dismantling and Reconstruction of DPO 3.460 4,50,767/-

14 Dismantling and Reconstruction of DPO 3.587 4,50,767/-

15 Dismantling and Reconstruction of DPO 3.670 4,50,767/-

16 Dismantling and Reconstruction of DPO 3.798 4,50,767/-

17 Dismantling and Reconstruction of DPO 4.095 4,96,407/-

18 Dismantling and Reconstruction of DPO 4.191 4,96,407/-

19 Dismantling and Reconstruction of DPO 4.266 4,96,407/-

20 Dismantling and Reconstruction of DPO 4.480 4,96,407/-

21 Dismantling and Reconstruction of DPO 4.615 4,96,407/-

22 Dismantling and Reconstruction of DPO 4.767 4,96,407/-

23 Dismantling and Reconstruction of DPO 5.346 4,96,366/-

24 Dismantling and Reconstruction of DPO 5.674 4,96,366/-

25 Dismantling and Reconstruction of DPO 5.870 4,96,366/-

26 Dismantling and Reconstruction of DPO 5.904 4,96,366/-

27 Dismantling and Reconstruction of DPO 6.082 4,75,557/-

28 Dismantling and Reconstruction of DPO 6.176 4,75,557/-

29 Dismantling and Reconstruction of DPO 6.201 4,75,557/-

30 Dismantling and Reconstruction of DPO 6.256 4,75,557/-

31 Dismantling and Reconstruction of DPO 6.415 4,75,557/-

32 Dismantling and Reconstruction of DPO 6.600 4,75,557/-

33 Dismantling and Reconstruction of DPO 6.695 4,75,557/-

34 Dismantling and Reconstruction of DPO 7.240 3,88,573/-

35 Dismantling and Reconstruction of DPO 7.496 3,88,573/-

36 Dismantling and Reconstruction of DPO 7.595 3,88,573/-

37 Dismantling and Reconstruction of DPO 7.856 3,88,573/-

38 Dismantling and Reconstruction of DPO 7.979 3,88,573/-

39 Dismantling and Reconstruction of DPO 8.081 3,91,700/-

40 Dismantling and Reconstruction of DPO 8.299 3,98,210/-

41 Dismantling and Reconstruction of DPO 8.370 3,98,210/-

42 Dismantling and Reconstruction of DPO 8.648 3,98,210/-

11. Remodelling of Structures under Hulugi Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

43 Dismantling and Reconstruction of DPO 8.794 3,98,210/-

44 Dismantling and Reconstruction of DPO 8.828 3,98,210/-

45 Dismantling and Reconstruction of DPO 8.961 3,98,210/-

46 Dismantling and Reconstruction of DPO 9.210 3,96,794/-

47 Dismantling and Reconstruction of DPO 9.383 3,96,794/-

48 Dismantling and Reconstruction of DPO 9.496 3,96,794/-

49 Dismantling and Reconstruction of DPO 9.663 3,96,794/-

50 Dismantling and Reconstruction of DPO 9.762 3,96,794/-

51 Dismantling and Reconstruction of DPO 9.816 3,96,794/-

52 Dismantling and Reconstruction of DPO 10.009 3,95,991/-

53 Dismantling and Reconstruction of DPO 10.122 3,95,991/-

54 Dismantling and Reconstruction of DPO 10.143 3,95,991/-

55 Dismantling and Reconstruction of DPO 10.407 3,95,991/-

56 Dismantling and Reconstruction of DPO 10.584 3,95,991/-

TOTAL 2,43,67,926/-

243.68 Lakhs

1 Construction of CR/CTC 1.133 19,26,844/-

2 Construction of MD 1.200 78,899/-

3 Dismantling and Construction of DPO 1.385 407,431/-

4 Dismantling and Construction of DPO 1.778 4,07,431/-

5 Construction of DPO 1.945 4,07,431/-

6 Dismantling and Construction of DPO 2.128 4,09,258/-

7 Dismantling and Construction of DPO 2.678 4,09,258/-

8 Dismantling and Construction of DPO 2.988 4,09,258/-

9 Dismantling and Construction of DPO 3.285 4,11,738/-

10 Dismantling and Construction of DPO 3.405 4,11,738/-

11 Dismantling and Construction of DPO 3.525 4,11,738/-

12 Dismantling and Construction of DPO 3.657 4,11,738/-

13 Dismantling and Construction of DPO 3.826 4,11,738/-

14 Dismantling and Construction of DPO 3.899 4,11,738/-

15 Dismantling and Construction of DPO 3.944 4,11,738/-

16 Dismantling and Construction of DPO 4.638 4,12,126/-

17 Dismantling and Construction of DPO 4.870 4,12,126/-

18 Dismantling and Construction of DPO 5.188 4,13,922/-

19 Dismantling and Construction of DPO 5.280 4,13,922/-

20 Dismantling and Construction of DPO 5.635 3,73,196/-

21 Dismantling and Construction of DPO 5.784 3,73,196/-

22 Dismantling and Construction of DPO 6.012 3,73,400/-

23 Dismantling and Construction of DPO 6.184 3,73,400/-

24 Dismantling and Construction of DPO 6.340 3,73,400/-

25 Dismantling and Construction of DPO 6.360 3,73,400/-

26 Dismantling and Construction of DPO 6.515 3,73,400/-

TOTAL 1,16,03,462/-

116.03 Lakhs

12. Remodelling of Structures under Shivapura Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1 Construction of Measuring Device 0.500 1,99,867/-

2 Dismantling and Reconstruction of DPO-2 0.797 4,73,942/-

3 Dismantling and Reconstruction of DPO-3 1.119 5,31,979/-

4 Dismantling and Reconstruction of DPO-4 1.885 5,31,979/-

5 Dismantling and Reconstruction of DPO-6 3.075 5,06,401/-

6 Dismantling and Reconstruction of DPO-9 3.759 3,74,065/-

7 Dismantling and Reconstruction of DPO-10 4.467 3,35,281/-

8 Dismantling and Reconstruction of DPO-11 4.838 5,04,080/-

9 Dismantling and Reconstruction of DPO-12 4.995 5,04,080/-

10 Dismantling and Reconstruction of DPO-13 5.273 4,99,917/-

11 Dismantling and Reconstruction of DPO-14 5.539 4,99,917/-

12 Dismantling and Reconstruction of DPO-16 5.820 4,99,917/-

13 Dismantling and Reconstruction of DPO-17 6.839 4,99,842/-

14 Dismantling and Reconstruction of DPO-18 6.974 4,99,842/-

15 Dismantling and Reconstruction of DPO-19 7.093 4,99,540/-

16 Dismantling and Reconstruction of DPO-20 7.265 4,99,540/-

17 Dismantling and Reconstruction of DPO-22 7.948 4,27,364/-

18 Dismantling and Reconstruction of DPO-23 8.286 4,44,308/-

19 Dismantling and Reconstruction of DPO-24 8.461 4,44,308/-

20 Dismantling and Reconstruction of DPO-25 8.715 4,44,308/-

21 Dismantling and Reconstruction of DPO-26 8.808 4,44,308/-

22 Dismantling and Reconstruction of DPO-27 8.835 4,44,308/-

23 Dismantling and Reconstruction of DPO-28 8.990 4,44,308/-

24 Dismantling and Reconstruction of DPO-30 9.183 4,45,256/-

25 Dismantling and Reconstruction of DPO-31 9.400 5,01,515/-

26 Dismantling and Reconstruction of DPO-32 9.652 4,27,048/-

27 Dismantling and Reconstruction of DPO-33 9.818 4,27,048/-

28 Dismantling and Reconstruction of DPO-34 10.693 4,26,608/-

29 Dismantling and Reconstruction of DPO-36 11.008 4,26,174/-

30 Dismantling and Reconstruction of DPO-37 11.352 5,42,026/-

31 Dismantling and Reconstruction of DPO-42 12.715 5,42,059/-

32 Dismantling and Reconstruction of DPO-43 12.811 5,42,059/-

33 Dismantling and Reconstruction of DPO-44 12.916 5,42,059/-

34 Dismantling and Reconstruction of DPO-45 12.918 5,42,059/-

35 Dismantling and Reconstruction of DPO-46 13.465 5,42,099/-

36 Dismantling and Reconstruction of DPO-47 13.572 5,42,099/-

37 Dismantling and Reconstruction of DPO-50 14.415 5,56,412/-

38 Dismantling and Reconstruction of DPO-52 14.709 5,56,412/-

39 Dismantling and Reconstruction of DPO-53 14.782 5,56,412/-

40 Dismantling and Reconstruction of DPO-54 14.960 5,56,412/-

41 Dismantling and Reconstruction of DPO-57 15.046 5,37,299/-

42 Dismantling and Reconstruction of DPO-58 15.162 5,37,299/-

43 Dismantling and Reconstruction of DPO-59 15.350 5,37,299/-

13. Remodelling of Structures under Anegundi Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

44 Dismantling and Reconstruction of DPO-60 15.440 5,37,299/-

45 Dismantling and Reconstruction of DPO-61 15.668 5,37,299/-

46 Dismantling and Reconstruction of DPO-62 15.820 5,37,299/-

47 Dismantling and Reconstruction of DPO-64 16.495 5,35,595/-

48 Dismantling and Reconstruction of DPO-65 16.725 5,35,595/-

49 Dismantling and Reconstruction of DPO-66 16.785 5,35,595/-

50 Dismantling and Reconstruction of DPO-68 17.052 5,33,149/-

51 Dismantling and Reconstruction of DPO-69 17.130 5,33,149/-

52 Dismantling and Reconstruction of DPO-70 17.178 5,33,149/-

53 Dismantling and Reconstruction of DPO-72 17.245 5,33,149/-

54 Dismantling and Reconstruction of DPO-74 17.444 5,33,149/-

55 Dismantling and Reconstruction of DPO-77 18.737 5,33,149/-

56Dismantling and Reconstruction of Cross

Regulator0.000 16,83,551/-

TOTAL 2,89,40,182/-

289.40 Lakhs

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1 Dismantling and Reconstruction of CR 0.000 17,24,895/-

Details enclosed Refer

Volume-III of Annexure-3,

Page No.69

2 Dismantling and Reconstruction of Measuring

Device0.210 2,21,596/-

3 Dismantling and Reconstruction of DPO 0.280 5,23,094/-

4 Dismantling and Reconstruction of DPO 0.900 5,23,094/-

5 Dismantling and Reconstruction of DPO 1.530 5,23,675/-

6 Dismantling and Reconstruction of DPO 1.588 5,23,675/-

7 Dismantling and Reconstruction of DPO 1.827 5,23,675/-

8 Dismantling and Reconstruction of DPO 2.618 5,21,539/-

9 Dismantling and Reconstruction of DPO 2.894 5,21,539/-

10 Dismantling and Reconstruction of DPO 3.065 5,19,082/-

11 Dismantling and Reconstruction of DPO 3.723 5,19,082/-

12 Dismantling and Reconstruction of DPO 4.640 5,17,894/-

13 Dismantling and Reconstruction of DPO 5.163 4,98,697/-

14 Dismantling and Reconstruction of DPO 5.317 4,98,697/-

15 Dismantling and Reconstruction of DPO 6.090 5,16,816/-

16 Dismantling and Reconstruction of DPO 6.150 5,16,816/-

17 Dismantling and Reconstruction of DPO 6.196 6,57,847/-

18 Dismantling and Reconstruction of DPO 6.312 4,45,675/-

19 Dismantling and Reconstruction of DPO 6.450 4,45,675/-

20 Dismantling and Reconstruction of DPO 6.494 6,70,012/-

21 Dismantling and Reconstruction of DPO 7.410 8,07,872/-

22 Dismantling and Reconstruction of DPO 7.560 5,11,636/-

23 Dismantling and Reconstruction of DPO 7.670 5,10,269/-

24 Dismantling and Reconstruction of DPO 7.912 7,25,216/-

25 Dismantling and Reconstruction of DPO 8.107 4,34,474/-

26 Dismantling and Reconstruction of DPO 8.163 4,34,474/-

27 Dismantling and Reconstruction of DPO 8.295 4,34,474/-

28 Dismantling and Reconstruction of DPO 8.490 4,34,474/-

TOTAL 1,57,05,965/-

157.06 Lakhs

14. Remodelling of Structures under Upper Gangavathi Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1 Dismantling and Reconstruction of CR cum CTC0.000 19,66,237/-

2 Construction of CR with CTC 0.020 19,66,237/-

3 Dismantling and Reconstruction of DPO 0.217 4,66,739/-

4 Construction of Measuring Device 0.510 1,87,125/-

5Dismantling and Reconstruction of Head

Regulator 0.730 6,25,360/-

6 Dismantling and Reconstruction of DPO 1.405 4,48,085/-

7 Dismantling and Reconstruction of DPO 3.494 4,44,810/-

8 Dismantling and Reconstruction of DPO 3.872 4,44,810/-

9 Dismantling and Reconstruction of DPO 3.900 4,44,810/-

10 Dismantling and Reconstruction of DPO 4.144 4,47,615/-

11 Dismantling and Reconstruction of DPO 4.802 4,47,615/-

12Dismantling and Reconstruction of Head

Regulator 4.965 6,79,852/-

13 Dismantling and Reconstruction of DPO 5.045 4,48,923/-

14 Dismantling and Reconstruction of DPO 5.280 4,48,923/-

15 Dismantling and Reconstruction of DPO 5.485 4,48,923/-

16 Dismantling and Reconstruction of DPO 5.643 4,48,923/-

17 Dismantling and Reconstruction of DPO 6.060 4,49,397/-

18 Dismantling and Reconstruction of DPO 6.281 4,49,397/-

19 Dismantling and Reconstruction of DPO 6.300 4,49,397/-

20 Dismantling and Reconstruction of DPO 6.614 4,49,397/-

21 Dismantling and Reconstruction of DPO 6.715 4,49,397/-

22 Dismantling and Reconstruction of DPO 6.896 4,49,397/-

23 Dismantling and Reconstruction of DPO 7.115 4,96,355/-

24 Dismantling and Reconstruction of DPO 7.402 4,96,355/-

25 Dismantling and Reconstruction of DPO 7.421 4,96,355/-

26Dismantling and Reconstruction of Head

Regulator 7.800 4,96,355/-

27 Dismantling and Reconstruction of DPO 7.810 6,97,621/-

28 Dismantling and Reconstruction of DPO 7.860 4,96,355/-

29 Dismantling and Reconstruction of DPO 7.915 4,96,355/-

30 Dismantling and Reconstruction of DPO 8.077 4,50,364/-

31 Dismantling and Reconstruction of DPO 8.444 4,50,364/-

32 Dismantling and Reconstruction of DPO 8.465 4,50,364/-

33 Dismantling and Reconstruction of DPO 8.647 4,50,364/-

34 Dismantling and Reconstruction of DPO 8.702 4,50,364/-

35 Dismantling and Reconstruction of DPO 9.495 3,97,194/-

TOTAL 1,93,86,133/-

193.86 Lakhs

15. Remodelling of Structures under Lower Gangavathi Channel

Sl.N

oType of structure

Chainage in

Km

Amount in

RupeesRemarks

1Dismantling and Reconstruction of Cross

Regulator0.002

5,27,632/-

2 Dismantling and Reconstruction of DPO 0.225 5,14,564/-

3 Construction of Measuring Device 0.500 94,634/-

4 Dismantling and Reconstruction of DPO 1.385 4,85,154/-

5 Dismantling and Reconstruction of DPO 1.710 4,85,154/-

6 Dismantling and Reconstruction of DPO 2.910 5,16,628/-

7 Dismantling and Reconstruction of DPO 3.075 5,20,888/-

8 Dismantling and Reconstruction of DPO 3.780 5,20,888/-

9 Dismantling and Reconstruction of DPO 6.150 4,31,767/-

10 Dismantling and Reconstruction of DPO 11.295 4,54,476/-

11 Dismantling and Reconstruction of DPO 11.502 4,54,476/-

12 Dismantling and Reconstruction of DPO 12.080 4,55,917/-

TOTAL 54,62,178/-

54.62 Lakhs

16. Remodelling of Structures under Bichal Channel

Sl

No.Description

Amount

Rs in Lakhs

Construction of Falls Coming under entire Vijayanagar Channel

system(16 Nos.)

1 Raya Channel 51.94

2 Basavanna Channel 39.24

3 Kalaghatta Channel 9.22

4 Turtha Channel 38.44

5 Hulugi Channel 1.97

6 Shivapura Channel 1.78

7 Anegundi Channel 6.23

8 Lower Gangavathi Channel 3.46

152.27

COST OF E-FALLS Rs.152.27 LAKHS

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

E-FALLS

ABSTRACT

TOTAL

Sl.

NoType of structure

Chainage in

Km

Amount in

RupeesRemarks

1 Construction of Canal Drop (0.5 m ) 0.318 4,84,648/-

2 Construction of Canal Drop (1.0m ) 0.630 8,00,266/-

3 Construction of Canal Drop (1.0m ) 12.230 7,47,360/-

4 Construction of Canal Drop (0.5 m ) 16.613 4,53,271/-

5 Construction of Canal Drop (1.0m ) 18.710 8,36,934/-

6 Construction of Canal Drop (0.5 m ) 21.560 4,50,118/-

7 Construction of Canal Drop (0.5 m ) 24.574 4,50,914/-

8 Construction of Canal Drop (1.0m ) 25.085 4,85,338/-

9 Construction of Canal Drop (1.0m ) 25.800 4,85,338/-

TOTAL 51,94,188/-

51.94 Lakhs

1 Construction of Canal Drop (1.0m ) 3.800 5,89,455/-

2 Construction of Canal Drop (1.0m ) 3.890 5,89,153/-

3 Construction of Canal Drop (1.5 m ) 3.960 8,28,620/-

4 Construction of Canal Drop (1.0m ) 4.290 5,89,821/-

5 Construction of Canal Drop (1.0m ) 4.662 4,79,515/-

6 Construction of Canal Drop (1.0m ) 5.430 4,78,720/-

7 Construction of Canal Drop (0.5 m ) 6.180 3,69,122/-

TOTAL 39,24,407/-

39.24 Lakhs

1 Construction of Canal Drop (1.0m ) 6.737 9,22,013/-

TOTAL 9,22,013/-

9.22 Lakhs

1 Construction of Canal Drop (1.0m ) 3.800 5,71,885/-

2 Construction of Canal Drop (1.0m ) 3.890 5,71,885/-

3 Construction of Canal Drop (1.5 m ) 3.960 8,26,815/-

Details enclosed Refer

Volume-III of Annexure-

6, Page No.176

4 Construction of Canal Drop (1.0m ) 4.290 5,69,992/-

5 Construction of Canal Drop (1.0m ) 4.662 4,72,104/-

6 Construction of Canal Drop (1.0m ) 5.430 4,70,614/-

7 Construction of Canal Drop (0.5 m ) 6.180 3,60,570/-

TOTAL 38,43,865/-

38.44 Lakhs

4. Remodelling of Structures under Turtha Channel

1. Remodelling of Structures under Raya Channel

2. Remodelling of Structures under Basavanna Channel

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

E- FALLS

3. Remodelling of Structures under Kalaghatta Channel

Sl.

NoType of structure

Chainage in

Km

Amount in

RupeesRemarks

1 Construction of Canal Drop (0.5 m ) 8.130 1,96,537/-

TOTAL 1,96,537/-

1.97 Lakhs

Construction of Canal Drop (0.5 m ) 5.045 1,77,823/-

TOTAL 1,77,823/-

1.78 Lakhs

1 Construction of Canal Drop (0.5 m ) 3.600 2,92,087/-

2 Construction of Canal Drop (0.60 m) 11.22 3,30,790/-

TOTAL 6,22,877/-

6.23 Lakhs

1 Construction of Canal Drop (0.5 m ) 9.000 3,45,729/-

TOTAL 3,45,729/-

3.46 Lakhs

8. Remodelling of Structures under Lower Gangavathi Channel

5. Remodelling of Structures under Hulugi Channel

6. Remodelling of Structures under Shivapura Channel

7. Remodelling of Structures under Anegundi Channel

Sl

No.Description

Amount

Rs in Lakhs

Construction of Cross Drainage Works Coming under entire

Vijayanagar Channel system(16 Nos.)

1 Raya Channel 67.22

2 Basavanna Channel 72.85

3 Bella Channel 27.80

4 Kalaghatta Channel 155.77

5 Ramasagara Channel 75.41

6 Kampli Channel 166.68

7 Belagodhalla Channel 13.78

8 Siruguppa Channel 8.37

9 Hulugi Channel 10.35

10 Shivapura Channel 55.00

11 Anegundi Channel 133.70

12 Upper Gangavathi Channel 104.55

13 Lower Gangavathi Channel 20.62

912.10

COST OF F-CROSS DRAINAGE WORKS Rs.912.10 LAKHS

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

F-CROSS DRAINAGE WORKS

ABSTRACT

TOTAL

Sl.No Type of structure Chainage in

Km

Amount in

RupeesRemarks

1 Construction of Inlet 11 .917 6,36,689/-

2 Construction of Inlet 26 .355 6,30,673/-

3 Dismantling and Reconstruction of Under 0 .435 8,44,758/-

4 Construction of Under Tunnel 3 .900 19,26,216/-

5 Construction of Under Tunnel 9 .351 26,83,810/-

TOTAL 67,22,146/-

67.22 Lakhs

1 Construction of Inlet 0.610 8,05,432/-

2 Construction of Undertunnel 0.710 28,36,855/-

3 Construction of Inlet 1.298 8,05,432/-

4 Construction of Undertunnel 1.900 28,36,855/-

TOTAL 72,84,574/-

72.85 Lakhs

1 Construction of Inlet 0.295 7,05,373/-

2 Construction of inlet 1.794 6,91,678/-

3 Construction of inlet 1.844 6,91,678/-

4 Construction of inlet 1.944 6,91,678/-

TOTAL 27,80,406/-

27.80 Lakhs

1 33,25,500/-

Details enclosed Refer

Volume-III of Annexure-

7, Page No.202

2 1,22,51,241/-

TOTAL 1,55,76,741/-

155.77 Lakhs

1 Construction of Inlet 0.350 6,97,372/-

2 Construction of Inlet 0.128 6,97,372/-

3 Construction of Inlet 0.242 6,97,372/-

4 Construction of Inlet 0.300 6,97,372/-

5 Construction of Inlet 1.360 6,97,372/-

6 Construction of Inlet 1.644 6,97,372/-

7 Construction of Inlet 6.960 6,93,581/-

8 Construction of Inlet 8.335 6,91,127/-

9 Construction of Inlet 10.600 6,75,856/-

10 Construction of Inlet 10.642 6,75,856/-

11 Construction of Inlet 14.407 6,19,984/-

TOTAL 75,40,636/-

75.41 Lakhs

1. Remodelling of Structures under Raya Channel

2. Remodelling of Structures under Basavanna Channel

3. Remodelling of Structures under Bella Channel

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

F- CROSS DRAINAGE WORKS

4. Remodelling of Structures under Kalaghatta Channel

5. Remodelling of Structures under Ramasagara Channel

Construction of Trough from Ch:1900.00 m to 2000.00m

Construction of Trough from Ch:2000.00 m to 2400.00m

Sl.No Type of structure Chainage in

Km

Amount in

RupeesRemarks

1 27,05,680/-

2 78,06,298/-

3 6,78,643/-

4 6,78,643/-

5 6,94,413/-

6 6,94,413/-

7 6,89,279/-

8 6,65,007/-

9 6,85,326/-

10 6,85,326/-

11 6,85,008/-

TOTAL 1,66,68,037/-

166.68 Lakhs

1 Construction of Inlet 2.426 6,91,810/-

2 Construction of Inlet 6.975 6,86,099/-

TOTAL 13,77,909/-

13.78 Lakhs

1 Construction of Super Passage 2.950 8,36,733/-

Details enclosed Refer

Volume-III of Annexure-

8, Page No.222

TOTAL 8,36,733/-

8.37 Lakhs

1 Construction of Inlet 2.385 5,19,699/-

Details enclosed Refer

Volume-III of Annexure-

9, Page No.251

2 Construction of Inlet 8.820 5,14,826/-

TOTAL 10,34,525/-

10.35 Lakhs

1 Construction of Inlet 1.145 4,19,914/-

2 Construction of Inlet 1.462 4,19,914/-

3 Construction of Inlet 2.098 4,22,622/-

4 Construction of Inlet 2.210 4,22,622/-

5 Construction of Inlet 2.242 4,22,622/-

6 Construction of Inlet 2.542 4,22,622/-

7 Construction of Under Tunnel 6.400 29,70,161/-

TOTAL 55,00,478/-

55.00 Lakhs

Construction of Inlet Ch:5.520 Km

10. Remodelling of Structures under Shivapura Channel

6. Remodelling of Structures under Kampli Channel

Construction of Inlet Ch:10.920 Km

7. Remodelling of Structures under Belgodhalla Channel

Construction of Inlet Ch:11.120 Km

Construction of Inlet Ch:12.920 Km

Construction of Inlet Ch:11.290 Km

9. Remodelling of Structures under Hulugi Channel

8. Remodelling of Structures under Siruguppa Channel

Construction of Inlet Ch:8.550 Km

Construction of Trough from Ch:3900.00 m to 4000.00m

Construction of Trough from Ch:4000.00 m to 4400.00m

Construction of Inlet Ch:0.670 Km

Construction of Inlet Ch:0.750 Km

Construction of Inlet Ch:5.280 Km

Sl.No Type of structure Chainage in

Km

Amount in

RupeesRemarks

1 Construction of Inlet 0.408 4,59,215/-

2 Construction of Inlet 3.376 5,95,272/-

3 Construction of Inlet 5.297 8,50,833/-

4 Construction of Inlet 7.325 8,50,663/-

5 Construction of Inlet 8.600 5,07,707/-

6 Construction of Inlet 12.000 8,74,409/-

7 Construction of Inlet 12.230 8,74,409/-

8 Construction of Inlet 16.325 8,62,256/-

9 Construction of Inlet 17.600 8,57,762/-

10 Construction of Inlet 17.680 8,57,762/-

11 Construction of Under Tunnel 7.431 28,64,634/-

Details enclosed Refer

Volume-III of Annexure-

10, Page No.267

12 Construction of Under Tunnel 8.015 29,15,336/-

TOTAL 1,33,70,258/-

133.70 Lakhs

1 Construction of Inlet 0.465 8,60,895/-

2 Construction of Inlet 0.840 8,60,895/-

3 Construction of Inlet 3.230 8,50,580/-

4 Construction of Inlet 3.900 8,50,580/-

5 Construction of Inlet 4.060 8,46,797/-

6 Construction of Inlet 5.685 8,41,920/-

7 Construction of Inlet 5.900 8,41,920/-

8 Construction of Inlet 5.950 8,41,920/-

9 Construction of Inlet 6.730 7,30,678/-

10 Construction of Inlet 6.760 7,30,678/-

11 Construction of Inlet 6.860 7,30,678/-

12 Construction of Inlet 7.620 7,33,937/-

13 Construction of Inlet 7.950 7,33,937/-

TOTAL 1,04,55,413/-

104.55 Lakhs

1 Dismantling and Reconstruction of Inlet 0.883 5,19,647/-

2 Construction of Inlet 3.060 5,04,805/-

3 Construction of Inlet 5.160 5,18,911/-

4 Construction of Inlet 5.730 5,18,911/-

TOTAL 20,62,274/-

20.62 Lakhs

13. Remodelling of Structures under Lower Gangavathi Channel

11. Remodelling of Structures under Anegundi Channel

12. Remodelling of Structures under Upper Gangavathi Channel

Sl

No.Description

Amount

Rs in Lakhs

Construction of Bridges Coming under entire Vijayanagar Channel

system(16 Nos.)

1 Raya Channel 317.25

2 Basavanna Channel 119.64

3 Bella Channel 123.11

4 Kalaghatta Channel 98.61

5 Turtha Channel 66.72

6 Ramasagara Channel 114.08

7 Kampli Channel 395.33

8 Belagodhalla Channel 109.03

9 Deshnur Channel 64.35

10 Siruguppa Channel 94.00

11 Hulugi Channel 84.43

12 Shivapura Channel 73.67

13 Anegundi Channel 117.07

14 Upper Gangavathi Channel 73.80

15 Lower Gangavathi Channel 36.17

16 Bichal Channel 73.22

1960.48

COST OF G-BRIDGES Rs.1960.48 LAKHS

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

G-BRIDGES

ABSTRACT

TOTAL

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1 Construction of Foot Bridge 9 .598 3,24,891/-

2 Dismantling and Reconstruction of CTC 1 .475 19,31,861/-

3 Dismantling and Reconstruction of CTC 2 .512 19,32,723/-

4 Dismantling and Reconstruction of CTC 3 .473 15,93,293/-

5 Dismantling and Reconstruction of CTC 6 .600 10,01,765/-

6 Construction of CTC 8 .345 9,91,674/-

7 Construction of CTC 9 .148 9,91,674/-

8 Construction of CTC 9 .211 9,91,674/-

9 Construction of CTC 12 .651 13,36,101/-

10 Construction of CTC 15 .806 8,20,149/-

11 Construction of CTC 20 .805 8,23,989/-

12 Construction of CTC 22 .330 8,42,444/-

13 Dismantling and Reconstruction of CTC 22 .653 8,42,444/-

14 Construction of CTC 23 .014 8,34,085/-

15 Construction of CTC 23 .041 8,34,085/-

16 Construction of CTC 23 .633 8,34,085/-

17 Dismantling and Reconstruction of CTC 24 .652 8,42,931/-

18 Dismantling and Reconstruction of CTC 26 .346 9,73,459/-

19 Construction of CTC 27 .075 9,65,100/-

20 Construction of CTC 27 .222 9,65,100/-

21Dismantling and Reconstruction of Major

Road Bridge8 .196 25,65,133/-

Details enclosed Refer

Volume-III of Annexure-

11, Page No.303

22 Construction of Major Road Bridge 17 .990 20,16,499/-

23Dismantling and Reconstruction of Village

Road Bridge12 .145 24,85,857/-

24 Dismantling and Reconstruction Village 13 .737 19,14,112/-

25 Construction of Village Road Bridge 22 .735 19,18,093/-

26 Construction of Sopanam (washing ghat) 19 .370 1,51,510/-

TOTAL 3,17,24,731/-

317.25 Lakhs

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

G- BRIDGES

1. Remodelling of Structures under Raya Channel

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1 Dismantling and Reconstruction of Foot Bridge 0.956 4,03,844/-

2 Construction of Sopanam (Washing Ghat) 0.805 2,96,897/-

3 Construction of Sopanam (Washing Ghat) 0.914 2,96,897/-

4 Dismantling and Reconstruction of VRB 0.307 11,75,345/-

5 Dismantling and Reconstruction of VRB 0.810 11,75,345/-

6 Construction of Sopanam (Washing Ghat) 1.092 2,96,870/-

7 Dismantling and Reconstruction of VRB 1.917 11,75,345/-

8 Construction of Sopanam (Washing Ghat) 2.200 2,47,435/-

9 Construction of Sopanam (Washing Ghat) 4.180 2,78,532/-

10 Dismantling and Reconstruction of CTC 10.830 8,27,486/-

11 Dismantling and Reconstruction of CTC 11.695 7,96,585/-

12 Construction of Sopanam (Washing Ghat) 11.700 2,18,974/-

13 Dismantling and Reconstruction of CTC 11.710 7,88,218/-

14 Dismantling and Reconstruction of CTC 12.643 9,96,440/-

15 Dismantling and Reconstruction of CTC 13.799 9,96,440/-

16 Dismantling and Reconstruction of CTC 14.566 9,96,440/-

17 Dismantling and Reconstruction of CTC 14.917 9,96,440/-

TOTAL 119,63,533 / -

119.64 Lakhs

1Dismantle and Reconstruction of Sopanam

(Washing Ghat)0.184 3,06,091/-

2Dismantling and Reconstruction of Village

Road Bridge 0.484 16,23,613/-

3Dismantling and Reconstruction of Road

Bridge 1.163 24,97,559/-

4 Construction of cattle ramp 1.300 2,23,953/-

5 Construction of Foot Bridge 1.499 4,45,708/-

6 Construction of cattle ramp 3.100 2,24,870/-

7 Construction of CTC 3.500 15,85,186/-

8 Construction of cattle ramp 3.900 2,24,870/-

9 Dismantling and Reconstruction of CTC 3.930 16,34,714/-

10 Construction of cattle ramp 4.100 2,25,311/-

11 Dismantling and Reconstruction of CTC 4.181 16,37,293/-

12 Dismantling and Reconstruction of CTC 4.882 8,42,244/-

13 Dismantle and reconstruction of CTC 5.369 8,39,976/-

TOTAL 1,23,11,388/-

123.11 Lakhs

2. Remodelling of Structures under Basavanna Channel

3. Remodelling of Structures under Bella Channel

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1 Construction of Foot Bridge 0.144 4,01,147/-

Details enclosed Refer

Volume-III of Annexure-

12, Page No.336

2 Dismantling and Reconstruction of CTC 1.116 9,49,770/-

3Dismantling and Reconstruction of Village

Road Bridge1.960 10,62,338/-

4Dismantling and Reconstruction of Village

Road Bridge2.740 10,49,523/-

5 Dismantling and Reconstruction of CTC 3.359 9,54,915/-

6 Dismantling and Reconstruction of CTC 3.903 9,54,915/-

7 Dismantling and Reconstruction of CTC 5.170 9,39,924/-

8 Dismantling and Reconstruction of CTC 5.944 9,39,924/-

9 Dismantling and Reconstruction of CTC 6.563 9,39,924/-

10 Construction of CTC 6.725 8,90,396/-

11 Dismantling and Reconstruction of CTC 6.868 7,78,068/-

TOTAL 98,60,845/-

98.61 Lakhs

1 Construction of Sopanam (Washing Ghat) 4.180 2,73,293/-

Details enclosed Refer

Volume-III of Annexure-

13, Page No.358

2 Dismantling and Reconstruction of CTC 10.830 8,16,933/-

3 Dismantling and Reconstruction of CTC 11.695 7,71,813/-

Details enclosed Refer

Volume-III of Annexure-

14, Page No.370

4 Construction of Sopanam (Washing Ghat) 11.700 1,98,960/-

5 Dismantling and Reconstruction of CTC 11.710 7,58,570/-

6 Dismantling and Reconstruction of CTC 12.643 9,60,779/-

7 Dismantling and Reconstruction of CTC 13.799 9,62,788/-

8 Dismantling and Reconstruction of CTC 14.566 9,64,548/-

9 Dismantling and Reconstruction of CTC 14.917 9,64,548/-

TOTAL 66,72,232/-

66.72 Lakhs

4. Remodelling of Structures under Kalaghatta Channel

5. Remodelling of Structures under Turtha Channel

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1 Construction of CTC 2.86 14,44,890/-

2 Dismantling and Reconstruction of CTC 5.445 14,52,527/-

3 Construction of Cattle ramp 7.037 2,20,670/-

4 Dismantling and Reconstruction of CTC 7.037 10,70,143/-

5 Dismantling and Reconstruction of CTC 7.865 10,70,143/-

6 Construction of CTC 8.316 10,67,517/-

7 Dismanteling and Reconstruction of CTC 10.186 10,66,764/-

8 Construction of CTC 11.923 10,65,587/-

9 Construction of CTC 12.271 10,64,178/-

10 Construction of CTC 12.895 10,64,178/-

11 Construction of CTC 14.233 8,21,079/-

TOTAL 1,14,07,674/-

114.08 Lakhs

1 Construction of Sopanam 0.000 2,95,134/-

2 Construction of Foot Bridge 0.300 3,61,604/-

3Dismantling and Reconstruction of Foot

Bridge0.600 3,69,573/-

4 Construction of Foot Bridge 1.039 3,70,000/-

5 Construction Village Road Bridge 1.450 8,74,496/-

6 Construction Village Road Bridge 1.730 13,56,498/-

7 Dismantling and Reconstruction of CTC 1.784 9,31,940/-

8 Construction of Foot Bridge 2.330 3,62,145/-

9 Construction of Foot Bridge 2.850 3,62,145/-

10 Dismantling and Reconstruction of CTC 3.920 9,68,143/-

11 Construction of CTC 4.850 9,00,356/-

12 Dismantling and Reconstruction of CTC 5.015 9,66,781/-

13 Construction of Foot Bridge 5.150 3,26,322/-

14 Construction of Foot Bridge 5.430 3,26,322/-

15 Construction of CTC 5.580 9,26,413/-

16 Construction of Foot Bridge 5.595 3,26,322/-

17 Dismantling and Reconstruction of CTC 5.753 9,66,781/-

18Dismantling and Reconstruction of Foot

Bridge5.946 3,34,291/-

19 Construction of Foot Bridge 7.050 3,73,303/-

20Dismantling and Reconstruction of Foot

Bridge7.142 3,82,280/-

21 Construction of Foot Bridge 7.210 3,73,303/-

22 Construction of Foot Bridge 7.405 3,73,303/-

23 Construction of Sopanam (Washing Ghat) 7.665 3,02,128/-

6. Remodelling of Structures under Ramasagara Channel

7. Remodelling of Structures under Kampli Channel

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

24Dismantling and Reconstruction of Foot

Bridge7.665 3,82,280/-

25Dismantling and Reconstruction of Foot

Bridge8.010 3,07,017/-

26 Construction of CTC 9.340 9,21,669/-

27Dismantling and Reconstruction of Village

Road Bridge9.567 9,42,797/-

28 Construction of Foot Bridge 9.610 3,73,715/-

29 Construction of Sopanam (Washing Ghat) 9.670 3,01,487/-

30 Construction of Foot Bridge 9.730 3,73,715/-

31 Construction Village Road Bridge 9.940 9,02,429/-

32Dismantling and Reconstruction of Village

Road Bridge10.204 9,42,183/-

33 Construction of CTC 10.520 9,21,003/-

34 Dismantling and Reconstruction of CTC 10.852 9,61,371/-

35 Construction of CTC 12.040 9,19,554/-

36 Dismantling and Reconstruction of CTC 12.415 9,61,755/-

37 Construction of CTC 13.400 7,38,176/-

38 Dismantling and Reconstruction of CTC 13.680 9,62,160/-

39 Construction of CTC 13.840 7,38,176/-

40 Construction of Foot Bridge 14.340 3,13,853/-

41 Construction of Foot Bridge 14.520 3,13,853/-

42 Construction of CTC 14.568 6,02,050/-

43 Construction of Foot Bridge 14.580 3,13,853/-

44 Construction of Sopanam (Washing Ghat) 14.710 2,94,513/-

45 Construction of CTC 15.910 6,21,594/-

46 Dismantling and Reconstruction of CTC 16.197 6,11,093/-

47 Construction of Foot Bridge 16.520 3,14,144/-

48 Dismantling and Reconstruction of CTC 16.545 6,11,093/-

49 Construction of CTC 17.320 6,00,375/-

50 Dismantling and Reconstruction of CTC 17.627 6,12,029/-

51 Construction of CTC 17.940 6,00,375/-

52 Construction of CTC 18.130 6,00,375/-

53 Construction of CTC 18.250 6,00,375/-

54 Construction of CTC 18.380 6,00,375/-

55 Construction of CTC 18.610 6,00,375/-

56 Construction of CTC 18.920 6,00,375/-

57 Dismantling and Reconstruction of CTC 19.207 6,12,821/-

58 Dismantling and Reconstruction of CTC 20.140 6,12,821/-

59 Construction of CTC 20.140 4,84,645/-

60 Construction of CTC 20.230 4,84,645/-

61 Construction of CTC 20.690 4,84,645/-

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

62 Construction of CTC 20.830 4,84,645/-

63 Dismantling and Reconstruction of CTC 20.890 6,13,339/-

64 Dismantling and Reconstruction of CTC 21.103 6,13,892/-

65 Dismantling and Reconstruction of CTC 21.394 6,13,892/-

66 Dismantling and Reconstruction of CTC 21.607 6,13,892/-

67Dismantling and Reconstruction of Foot

Bridge22.673 3,24,446/-

TOTAL 3,95,33,453/-

395.33 Lakhs

1 Construction of Foot Bridge 0.310 2,11,119/-

2 Construction of CTC 0.610 6,10,198/-

3 Construction of CTC 0.865 6,10,198/-

4 Construction of CTC 0.940 6,10,198/-

5 Construction of CTC 1.320 6,08,656/-

6 Dismantle and Reconstruction of CTC 1.670 6,17,005/-

7 Construction of CTC 2.620 6,07,567/-

8 Construction of CTC 3.820 6,05,939/-

9 Dismantle and Reconstruction of CTC 3.966 6,14,288/-

10 Construction of Road Bridge 4.890 9,30,742/-

11 Construction of CTC 6.180 6,04,817/-

12 Dismantle and Reconstruction of CTC 6.364 6,13,166/-

13 Construction of CTC 8.050 6,05,887/-

14 Dismantle and Reconstruction of CTC 8.301 6,14,237/-

15 Construction of CTC 9.377 6,06,709/-

16 Construction of CTC 10.930 6,10,790/-

17 Construction of CTC 10.980 6,10,790/-

18 Construction of CTC 11.220 6,10,790/-

TOTAL 1,09,03,098/-

109.03 Lakhs

8. Remodelling of Structures under Belgodhalla Channel

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1 Dismantling and Reconstruction of CTC 2.753 7,57,493/-

2 Dismantling and Reconstruction of CTC 3.150 7,54,602/-

3 Construction of CTC 4.110 6,54,547/-

4 Construction of CTC 5.010 6,50,881/-

5 Construction of Road Bridge 5.110 10,37,849/-

Details enclosed Refer

Volume-III of Annexure-

15, Page No.402

6 Construction of CTC 5.310 6,50,881/-

7 Construction of CTC 5.670 6,50,881/-

8 Dismantling and Reconstruction of CTC 7.310 6,38,762/-

9 Dismantling and Reconstruction of CTC 8.010 6,39,238/-

TOTAL 64,35,134/-

64.35 Lakhs

1 Construction of CTC 3.600 9,48,469/-

2 Construction of Retaining Wall 0.000 47,92,084/-

Details enclosed Refer

Volume-III of Annexure-

16, Page No.432

3 Dismantling and Reconstruction of CTC 5.665 8,67,924/-

4 Construction of CTC 7.200 8,36,732/-

5 Dismantling and Reconstruction of CTC 7.935 8,45,081/-

6 Construction of Sopanam (Washing Ghat) 5.700 2,41,702/-

7 Dismantling and Reconstruction of CTC 5.665 8,67,924/-

TOTAL 93,99,916/-

94.00 Lakhs

1 Dismantling and Reconstruction of CTC 1.179 9,81,130/-

2 Dismantling and Reconstruction of CTC 2.040 11,91,983/-

3 Dismantling and Reconstruction of CTC 2.335 11,91,983/-

4 Dismantling and Reconstruction of Foot Bridge 2.272 4,06,978/-

5 Dismantling and Reconstruction of CTC 3.128 11,93,103/-

6Dismantling and Reconstruction of Village Road

Bridge4.000 11,53,927/-

Details enclosed Refer

Volume-III of Annexure-

17, Page No.457

7 Dismantling and Reconstruction of CTC 5.160 5,23,086/-

8 Dismantling and Reconstruction of CTC 7.158 6,04,900/-

9 Dismantling and Reconstruction of CTC 7.234 6,04,900/-

10 Dismantling and Reconstruction of CTC 8.800 5,91,040/-

TOTAL 84,43,027/-

84.43 Lakhs

9. Remodelling of Structures under Deshnur Channel

10. Remodelling of Structures under Siruguppa Channel

11. Remodelling of Structures under Hulugi Channel

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1Dismantling and Reconstruction of Village

Road Bridge 0.152 13,58,665/-

2 Dismantling and Reconstruction of CTC 1.949 6,23,080/-

3Dismantling and Reconstruction of Village

Road Bridge 3.873 11,42,156/-

4Dismantling and Reconstruction of Village

Road Bridge 4.478 11,43,793/-

5Dismantling and Reconstruction of Village

Road Bridge 5.045 11,44,836/-

6 Dismantling and Reconstruction of CTC 6.442 8,00,389/-

7Dismantling and Reconstruction of Village

Road Bridge 6.475 11,54,543/-

TOTAL 73,67,464/-

73.67 Lakhs

1Dismantling and Reconstruction of Village Road

Bridge0.489 12,84,561/-

2 Dismantling and Reconstruction of CTC 7.624 7,33,372/-

3 Dismantling and Reconstruction of CTC 9.645 7,36,764/-

4 Dismantling and Reconstruction of CTC 9.826 7,36,734/-

5 Dismantling and Reconstruction of CTC 10.320 7,33,620/-

6 Construction of CTC 11.840 7,38,060/-

7 Dismantling and Reconstruction of CTC 13.364 7,37,664/-

8 Dismantling and Reconstruction of CTC 16.115 6,86,226/-

9 Dismantling and Reconstruction of CTC 17.044 7,29,783/-

10 Dismantling and Reconstruction of CTC 17.379 7,29,783/-

11 Construction of CTC 18.176 7,29,799/-

12 Dismantling and Reconstruction of CTC 18.753 7,29,799/-

13 Construction of Sopanam (Washing Ghat) 16.745 2,18,397/-

14Dismantling and Reconstruction of CTC and

Sopanam (Washing Ghat)18.176 3,20,435/-

15Dismantling and Reconstruction of Sopanam

(Washing Ghat)18.360 3,20,435/-

16Dismantling and Reconstruction of Sopanam

(Washing Ghat)18.616 3,20,435/-

17 Construction of Sopanam (Washing Ghat) 18.738 3,20,435/-

18 Construction of Cattle Ramp 15.569 2,27,152/-

Details enclosed Refer

Volume-III of Annexure-

18, Page No.489

19Dismantling and Reconstruction of Cattle Ramp

and Sopanam16.745 2,25,272/-

20 Construction of Cattle Ramp 17.389 2,24,280/-

21 Construction of Cattle Ramp 18.738 2,24,280/-

TOTAL 1,17,07,286/-

117.07 Lakhs

13. Remodelling of Structures under Anegundi Channel

12. Remodelling of Structures under Shivapura Channel

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1 Dismantling and Reconstruction of CTC 0.250 11,27,473/-

2 Dismantling and Reconstruction of VRB 4.099 13,60,334/-

3 Construction of Sopanam (Washing Ghat) 5.370 2,04,642/-

4 Dismantling and Reconstruction of CTC 5.535 10,94,872/-

5 Construction of Sopanam (Washing Ghat) 5.970 2,04,642/-

6 Dismantling and Reconstruction of CTC 6.214 7,05,401/-

7 Construction of Sopanam (Washing Ghat) 6.250 1,67,097/-

8 Construction of Sopanam (Washing Ghat) 6.270 1,67,097/-

9 Construction of Sopanam (Washing Ghat) 6.480 1,67,097/-

10 Construction of Sopanam (Washing Ghat) 6.510 1,55,084/-

11 Dismantling and Reconstruction of CTC 6.665 7,51,945/-

12 Dismantling and Reconstruction of CTC 8.697 6,37,060/-

13 Dismantling and Reconstruction of CTC 8.782 6,37,060/-

TOTAL 73,79,803/-

73.80 Lakhs

1 Dismantling and Reconstruction of CTC 1.700 12,54,172/-

2 Dismantling and Reconstruction of CTC 2.242 8,34,481/-

3 Dismantling and Reconstruction of CTC 5.790 8,13,175/-

4 Dismantling and Reconstruction of CTC 8.325 7,14,727/-

TOTAL 36,16,556/-

36.17 Lakhs

1 Dismantling and Reconstruction of CTC 0.315 10,38,855/-

2 Dismantling and Reconstruction of CTC 1.44 10,09,001/-

3 Dismantling and Reconstruction of CTC 2.103 10,44,565/-

4 Dismantling and Reconstruction of CTC 3.89 10,05,115/-

5 Dismantling and Reconstruction of CTC 10.83 4,58,137/-

6 Dismantling and Reconstruction of CTC 12.06 4,60,479/-

7 Dismantling and Reconstruction of CTC 12.834 4,60,479/-

8 Dismantling and Reconstruction of CTC 12.942 4,60,479/-

9 Dismantling and Reconstruction of CTC 13.145 4,61,658/-

10 Dismantling and Reconstruction of CTC 13.427 4,61,658/-

11 Dismantling and Reconstruction of CTC 14.195 4,61,658/-

TOTAL 73,22,083/-

73.22 Lakhs

16. Remodelling of Structures under Bichal Channel

14. Remodelling of Structures under Upper Gangavathi Channel

15. Remodelling of Structures under Lower Gangavathi Channel

Sl

No.Description

Amount

Rs in Lakhs

Construction of Escapes coming under entire Vijayanagar Channel

system(16 Nos.)

1 Raya Channel 68.93

2 Basavanna Channel 6.96

3 Bella Channel 24.86

4 Kalaghatta Channel 7.86

5 Turtha Channel 36.32

6 Ramasagara Channel 31.07

7 Kampli Channel 33.10

8 Belagodhalla Channel 25.67

9 Deshnur Channel 12.14

10 Siruguppa Channel 6.26

11 Hulugi Channel 41.06

12 Shivapura Channel 5.65

13 Anegundi Channel 233.69

14 Upper Gangavathi Channel 10.13

15 Lower Gangavathi Channel 18.14

561.84 Lakhs

COST OF H-ESCAPES Rs.561.84 LAKHS

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

H-Escapes

ABSTRACT

TOTAL

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1 Construction of Canal Escape 11.721 9,15,092/-

2 Construction of Canal Escape 15 .616 19,30,126/-

3Dismantling and Reconstruction of

Scouring Sluice2 .169

21,43,263/-

4Dismantling and Reconstruction of

Scouring Sluice3 .440

7,46,448/-

5 Construction of Scouring Sluice 8 .332 5,72,822/-

6Dismantling and Reconstruction of

Scouring Sluice22 .347

5,85,602/-

TOTAL 68,93,353/-

68.93 Lakhs

1 Construction of Canal Escape 10.9 6,95,798/-

TOTAL 6,95,798/-

6.96 Lakhs

1Dismantle and Reconstruction of

Scouring sluice 0.447 9,30,223/-

2Dismantle and Reconstruction of

Relieving Weir0.628 15,55,720/-

TOTAL 24,85,944/-

24.86 Lakhs

1Dismantle and Reconstruction of

Scouring sluice0.893 7,85,711/-

TOTAL 7,85,711/-

7.86 Lakhs

1 Construction of Canal Escape 0.000 4,75,627/-

2 Construction of Releiving Weir 0.880 19,11,947/-

Details enclosed Refer

Volume-III of Annexure-19,

Page No.504

3Dismantle and Reconstruction of

Scouring sluice1.221 5,88,954/-

Details enclosed Refer

Volume-III of Annexure-20,

Page No.525

4 Construction of Canal Escape 10.900 6,55,475/-

Details enclosed Refer

Volume-III of Annexure-21,

Page No.572

TOTAL 36,32,003/-

36.32 Lakhs

4. Remodelling of Structures under Kalaghatta Channel

5. Remodelling of Structures under Turtha Channel

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

H- Escapes

1. Remodelling of Structures under Raya Channel

2. Remodelling of Structures under Basavanna Channel

3. Remodelling of Structures under Bella Channel

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1Dismantling and Reconstruction of

Relieving Weir 2.200 20,46,598/-

2 Construction of Canal Escape 11.310 4,95,147/-

3 Construction of Canal Escape 13.718 5,65,204/-

TOTAL 31,06,950/-

31.07 Lakhs

1 Construction of Scouring sluice 1.150 5,55,577/-

2 Construction of Scouring sluice 1.320 5,55,577/-

3 Construction of Scouring sluice 2.070 5,52,101/-

4 Construction of Scouring sluice 3.150 5,76,084/-

5Dismantle and Reconstruction of

Scouring sluice5.548 5,85,725/-

6 Construction of Scouring sluice 14.050 4,85,407/-

TOTAL 33,10,469/-

33.10 Lakhs

1 Construction of Scouring Sluice 4.32 4,30,713/-

2

Dismantle and Reconstruction of

Scouring Sluice 4.545 4,32,080/-

3 Construction of Scouring Sluice 7.33 4,30,554/-

4

Dismantle and Reconstruction of

Scouring Sluice7.567 4,22,922/-

5 Construction of Scouring Sluice 10.72 4,20,177/-

6

Dismantle And Reconstruction of

Scouring Sluice 11.001 4,30,544/-

TOTAL 25,66,990/-

25.67 Lakhs

1Dismantling and Reconstruction of

Scouring sluice0.305 5,81,783/-

2Dismantling and Reconstruction of

Scouring sluice1.41 6,32,364/-

TOTAL 12,14,146/-

12.14 Lakhs

1 Construction of Scouring Sluice 0.362 6,25,869/-

TOTAL 6,25,869/-

6.26 Lakhs

6. Remodelling of Structures under Ramasagara Channel

7. Remodelling of Structures under Kampli Channel

8. Remodelling of Structures under Belgodhalla Channel

9. Remodelling of Structures under Deshnur Channel

10. Remodelling of Structures under Siruguppa Channel

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1Dismantling and Reconstruction of

Scouring Sluice0.219 3,43,333/-

2Dismantling and Reconstruction of

Scouring Sluice0.317 3,43,333/-

3Dismantling and Reconstruction of

Scouring Sluice0.585 3,43,333/-

4Dismantling and Reconstruction of

Scouring Sluice0.990 3,43,333/-

5Dismantling and Reconstruction of

Scouring Sluice3.216 4,96,413/-

6 Construction of Canal Escape 4.277 3,46,469/-

7Dismantling and Reconstruction of

Scouring Sluice7.393 9,44,679/-

8Dismantling and Reconstruction of

Scouring Sluice7.600 9,44,679/-

TOTAL 41,05,571/-

41.06 Lakhs

1Dismantling and Reconstruction of

Scouring Sluice 3.510 5,65,088/-

TOTAL 5,65,088/-

5.65 Lakhs

11. Remodelling of Structures under Hulugi Channel

12. Remodelling of Structures under Shivapura Channel

Sl.No Type of structure Chainage in KmAmount in

RupeesRemarks

1Dismantling and Reconstruction of

Escape0.024 16,79,450/-

2Dismantling and Reconstruction of

Escape0.754 13,85,348/-

3Dismantling and Reconstruction of

Escape2.843 13,86,783/-

4Dismantling and Reconstruction of

Escape cum Releiving Weir 3.400 15,19,897/-

5Dismantling and Reconstruction of

Escape cum Releiving Weir 8.900 21,86,227/-

6Dismantling and Reconstruction of

Releiving Weir 5.799 20,40,221/-

7 Construction of Releiving Weir 9.502 18,14,722/-

8Dismantling and Reconstruction of

Releiving Weir 11.435 15,09,483/-

9Dismantling and Reconstruction of

Releiving Weir 11.725 15,09,483/-

10Dismantling and Reconstruction of

Releiving Weir 11.850 15,09,483/-

11Dismantling and Reconstruction of

Releiving Weir 14.376 16,04,293/-

12Dismantling and Reconstruction of

Releiving Weir 14.800 16,04,293/-

13Dismantling and Reconstruction of

Releiving Weir 15.760 14,91,087/-

14 Construction of Releiving Weir 18.736 21,27,983/-

TOTAL 2,33,68,753/-

233.69 Lakhs

1

Dismantling and Reconstruction of

Canal Escape7.44 10,13,446/-

TOTAL 10,13,446/-

10.13 Lakhs

1Dismantling and Reconstruction of

Scouring Sluice 0.000 7,22,015/-

2Dismantling and Reconstruction of

Escape cum CTC 3.150 10,92,022/-

TOTAL 18,14,037/-

18.14 Lakhs

14. Remodelling of Structures under Upper Gangavathi Channel

15. Remodelling of Structures under Lower Gangavathi Channel

13. Remodelling of Structures under Anegundi Channel

Sl

No.Description No.

Plinth Area

(Sq Ft)

Rate/Sq ft in

Rs

Amount

Rs in Lakhs

Non - Residential Buildings

1 Construction of office Building 1 2000 1750 35.00

Residential Buildings

2 Construction of AEE Quarters 1 1200 2000 24.00

3 Construction of 3 Nos AE Quarters 2 900 2000 36.00

4 Construction of Staff quarters (5 Nos) 5 600 2000 60.00

155.00

Note: Rates is as per SR of State PWD Circle, Bellary

All the above Residential and Non-Residential Buildings are permanent one which is exclusively

meant for operation and maintainance of Canal Network.As such item Receipts & Recoveries on

capital accounts on Buildings is Nil

Works under Head works Sub division

TOTAL

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

K - Buildings

COST OF K - Buildings = Rs.155.00 LAKHS

Sl

No.Description

Amount

Rs in Lakhs

Remodelling of Main Canal

1 Raya Channel 3423.52

2 Basavanna Channel 1291.70

3 Bella Channel 544.41

4 Kalaghatta Channel 611.03

5 Turtha Channel 1845.46

6 Ramasagara Channel 1567.33

7 Kampli Channel 1685.75

8 Belagodhalla Channel 649.03

9 Deshnur Channel 607.59

10 Siruguppa Channel 946.81

11 Hulugi Channel 887.76

12 Shivapura Channel 411.45

13 Anegundi Channel 2881.60

14 Upper Gangavathi Channel 1278.95

15 Lower Gangavathi Channel 1056.00

16 Bichal Channel 933.14

Total = 20621.53

`

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

L- Earth Work,Lining,Formation of Service Roads for Canals.

ABSTRACT

COST OF L-EARTHWORK Rs.20621.53 LAKHS

No. Particulars Cost( in Rupees) Remarks

1 Estimates for Earthwork and Lining for Km 1 1,54,79,772/-

2 Estimates for Earthwork and Lining for Km 2 1,65,66,608/-

3 Estimates for Earthwork and Lining for Km 3 1,63,38,424/-

4 Estimates for Earthwork and Lining for Km 4 1,51,66,652/-

5 Estimates for Earthwork and Lining for Km 5 1,33,64,031/-

6 Estimates for Earthwork and Lining for Km 6 1,42,44,897/-

7 Estimates for Earthwork and Lining for Km 7 1,87,09,235/-

8 Estimates for Earthwork and Lining for Km 8 1,88,10,719/-

9 Estimates for Earthwork and Lining for Km 9 1,40,69,969/-

10 Estimates for Earthwork and Lining for Km 10 1,44,98,098/-

11 Estimates for Earthwork and Lining for Km 11 1,35,55,412/-

12 Estimates for Earthwork and Lining for Km 12 1,46,70,031/-

13 Estimates for Earthwork and Lining for Km 13 1,51,18,666/-

14 Estimates for Earthwork and Lining for Km 14 1,18,34,292/-

15 Estimates for Earthwork and Lining for Km 15 1,34,65,956/-

16 Estimates for Earthwork and Lining for Km 16 1,29,47,262/-

17 Estimates for Earthwork and Lining for Km 17 94,18,686/-

18 Estimates for Earthwork and Lining for Km 18 92,48,686/-

19 Estimates for Earthwork and Lining for Km 19 1,23,88,118/-

20 Estimates for Earthwork and Lining for Km 20 94,95,459/-

21 Estimates for Earthwork and Lining for Km 21 86,86,729/-

22 Estimates for Earthwork and Lining for Km 22 97,37,809/-

23 Estimates for Earthwork and Lining for Km 23 91,87,577/-

24 Estimates for Earthwork and Lining for Km 24 84,92,699/-

25 Estimates for Earthwork and Lining for Km 25 85,99,780/-

26 Estimates for Earthwork and Lining for Km 26 86,39,236/-

27 Estimates for Earthwork and Lining for Km 27.6 1,03,25,665/-

28 Deduct Lining Cost for Structures -7,08,494

TOTAL 34,23,51,974/-

Rs 3423.52 Lakhs

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

ABSTRACT ESTIMATE FOR EARTHWORK , LINING AND FORMATION OF SERVICE ROAD UNDER

MODERNISATION OF VIJAYANAGARA CHANNELS.

L - WORKS

1. Remodelling of Raya Channel

No. Particulars Cost( in Rupees) Remarks

1 Estimates for Earthwork and Lining for Km 1 87,19,237/-

2 Estimates for Earthwork and Lining for Km 2 88,60,653/-

3 Estimates for Earthwork and Lining for Km 3 86,73,798/-

4 Estimates for Earthwork and Lining for Km 4 84,27,834/-

5 Estimates for Earthwork and Lining for Km 5 80,82,383/-

6 Estimates for Earthwork and Lining for Km 6 81,16,560/-

7 Estimates for Earthwork and Lining for Km 7 76,93,858/-

8 Estimates for Earthwork and Lining for Km 8 76,03,795/-

9 Estimates for Earthwork and Lining for Km 9 76,34,523/-

10 Estimates for Earthwork and Lining for Km 10 78,43,083/-

11 Estimates for Earthwork and Lining for Km 11 79,03,842/-

12 Estimates for Earthwork and Lining for Km 12 79,33,844/-

13 Estimates for Earthwork and Lining for Km 13 67,84,600/-

14 Estimates for Earthwork and Lining for Km 14 73,24,858/-

15 Estimates for Earthwork and Lining for Km 15 77,72,871/-

16 Estimates for Earthwork and Lining for Km 16 62,29,568/-

17 Estimates for Earthwork and Lining for Km 16.5 42,10,039/-

18 Deduct Lining Cost for Structures -6,45,143 /-

TOTAL 12,91,70,203/-

Rs 1291.70 Lakhs

1 Estimates for Earthwork and Lining for Km 1 78,02,099/-

2 Estimates for Earthwork and Lining for Km 2 1,50,54,712/-

3 Estimates for Earthwork and Lining for Km 3 9,44,495/-

4 Estimates for Earthwork and Lining for Km 4 1,56,90,483/-

5 Estimates for Earthwork and Lining for Km 5 84,57,289/-

6 Estimates for Earthwork and Lining for Km 5.5 69,91,125/-

7 Deduct Lining Cost for Structures -4,99,456/-

TOTAL 5,44,40,747/-

Rs 544.41 Lakhs

1 Estimates for Earthwork and Lining for Km 1 94,31,020/-

2 Estimates for Earthwork and Lining for Km 2 85,79,328/-

3 Estimates for Earthwork and Lining for Km 3 56,96,975/-

4 Estimates for Earthwork and Lining for Km 4 96,59,216/-

5 Estimates for Earthwork and Lining for Km 5 95,37,422/-

6 Estimates for Earthwork and Lining for Km 6 84,42,011/-

7 Estimates for Earthwork and Lining for Km 7.2 98,33,766/-

8 Deduct Lining Cost for Structures -76,475/-

TOTAL 6,11,03,262/-

Rs 611.03 Lakhs

3. Remodelling of Bella Channel

2. Remodelling of Basavanna Channel

4. Remodelling of Kalaghatta Channel

No. Particulars Cost( in Rupees) Remarks

1 Estimates for Earthwork and Lining for Km 1 1,11,74,219/-

Details enclosed Refer

Volume-III of Annexure-22,

Page No.622

2 Estimates for Earthwork and Lining for Km 2 1,13,53,337/-

3 Estimates for Earthwork and Lining for Km 3 1,10,62,435/-

4 Estimates for Earthwork and Lining for Km 4 1,08,75,507/-

5 Estimates for Earthwork and Lining for Km 5 1,02,83,157/-

6 Estimates for Earthwork and Lining for Km 6 1,07,60,852/-

7 Estimates for Earthwork and Lining for Km 7 1,06,83,952/-

8 Estimates for Earthwork and Lining for Km 8 1,00,83,626/-

9 Estimates for Earthwork and Lining for Km 9 96,94,056/-

10 Estimates for Earthwork and Lining for Km 10 99,81,898/-

11 Estimates for Earthwork and Lining for Km 11 99,75,490/-

12 Estimates for Earthwork and Lining for Km 12 1,08,08,782/-

13 Estimates for Earthwork and Lining for Km 13 90,28,363/-

14 Estimates for Earthwork and Lining for Km 14 97,63,501/-

15 Estimates for Earthwork and Lining for Km 15 1,03,43,039/-

16 Estimates for Earthwork and Lining for Km 16 81,69,862/-

17 Estimates for Earthwork and Lining for Km 17 83,46,545/-

18 Estimates for Earthwork and Lining for Km 18.692 1,27,01,816/-

19 Deduct Lining Cost for Structures -5,44,617/-

Details enclosed Refer

Volume-III of Annexure-22,

Page No.641

TOTAL 18,45,45,820/-

Rs 1845.46 Lakhs

5. Remodelling of Turtha Channel

No. Particulars Cost( in Rupees) Remarks

1 Estimates for Earthwork and Lining for Km 1 1,19,49,295/-

2 Estimates for Earthwork and Lining for Km 2 1,16,70,587/-

3 Estimates for Earthwork and Lining for Km 3 1,15,36,086/-

4 Estimates for Earthwork and Lining for Km 4 1,17,01,977/-

5 Estimates for Earthwork and Lining for Km 5 1,12,07,474/-

6 Estimates for Earthwork and Lining for Km 6 1,21,33,240/-

7 Estimates for Earthwork and Lining for Km 7 1,03,35,919/-

8 Estimates for Earthwork and Lining for Km 8 94,06,068/-

9 Estimates for Earthwork and Lining for Km 9 91,15,240/-

10 Estimates for Earthwork and Lining for Km 10 95,26,732/-

11 Estimates for Earthwork and Lining for Km 11 99,66,122/-

12 Estimates for Earthwork and Lining for Km 12 95,35,910/-

13 Estimates for Earthwork and Lining for Km 13 92,05,254/-

14 Estimates for Earthwork and Lining for Km 14 86,15,003/-

15 Estimates for Earthwork and Lining for Km 15.386 1,19,56,759/-

16 Deduct Lining Cost for Structures -11,28,609/-

TOTAL 15,67,33,055/-

Rs 1567.33 Lakhs

1 Estimates for Earthwork and Lining for Km 1 74,35,572/-

2 Estimates for Earthwork and Lining for Km 2 79,75,878/-

3 Estimates for Earthwork and Lining for Km 3 80,18,323/-

4 Estimates for Earthwork and Lining for Km 4 82,75,875/-

5 Estimates for Earthwork and Lining for Km 5 50,79,755/-

6 Estimates for Earthwork and Lining for Km 6 84,86,354/-

7 Estimates for Earthwork and Lining for Km 7 82,17,206/-

8 Estimates for Earthwork and Lining for Km 8 81,86,501/-

9 Estimates for Earthwork and Lining for Km 9 77,10,058/-

10 Estimates for Earthwork and Lining for Km 10 78,29,497/-

11 Estimates for Earthwork and Lining for Km 11 79,53,836/-

12 Estimates for Earthwork and Lining for Km 12 80,97,969/-

13 Estimates for Earthwork and Lining for Km 13 78,51,627/-

14 Estimates for Earthwork and Lining for Km 14 79,63,833/-

15 Estimates for Earthwork and Lining for Km 15 67,85,445/-

16 Estimates for Earthwork and Lining for Km 16 75,01,232/-

17 Estimates for Earthwork and Lining for Km 17 70,80,188/-

18 Estimates for Earthwork and Lining for Km 18 64,22,426/-

19 Estimates for Earthwork and Lining for Km 19 62,90,346/-

20 Estimates for Earthwork and Lining for Km 20 62,99,875/-

21 Estimates for Earthwork and Lining for Km 21 54,74,419/-

7. Remodelling of Kampli Channel

6. Remodelling of Ramasagara Channel

No. Particulars Cost( in Rupees) Remarks

22 Estimates for Earthwork and Lining for Km 22 57,57,861/-

23 Estimates for Earthwork and Lining for Km 23.55 88,17,064/-

24 Deduct Lining Cost for Structures -9,35,730

TOTAL 16,85,75,410/-

Rs 1685.75 Lakhs

1 Estimates for Earthwork and Lining for Km 1 64,05,264/-

2 Estimates for Earthwork and Lining for Km 2 62,68,616/-

3 Estimates for Earthwork and Lining for Km 3 60,51,742/-

4 Estimates for Earthwork and Lining for Km 4 59,28,189/-

5 Estimates for Earthwork and Lining for Km 5 60,33,132/-

6 Estimates for Earthwork and Lining for Km 6 49,66,926/-

7 Estimates for Earthwork and Lining for Km 7 54,43,462/-

8 Estimates for Earthwork and Lining for Km 8 57,01,197/-

9 Estimates for Earthwork and Lining for Km 9 55,82,278/-

10 Estimates for Earthwork and Lining for Km 10 56,95,595/-

11 Estimates for Earthwork and Lining for Km 11.22 69,42,525/-

12 Deduct Lining Cost for Structures -1,15,898

TOTAL 6,49,03,028/-

Rs 649.03 Lakhs

1 Estimates for Earthwork and Lining for Km 1 1,00,11,569/-

2 Estimates for Earthwork and Lining for Km 2 77,74,464/-

3 Estimates for Earthwork and Lining for Km 3 71,73,114/-

4 Estimates for Earthwork and Lining for Km 4 72,03,935/-

5 Estimates for Earthwork and Lining for Km 5 57,41,265/-

6 Estimates for Earthwork and Lining for Km 6 56,85,321/-

7 Estimates for Earthwork and Lining for Km 7 55,75,114/-

8 Estimates for Earthwork and Lining for Km 8 55,81,867/-

9 Estimates for Earthwork and Lining for Km 9 60,11,963/-

TOTAL 6,07,58,612/-

Rs 607.59 Lakhs

8. Remodelling of Belgodhalla Channel

9. Remodelling of Deshnur Channel

No. Particulars Cost( in Rupees) Remarks

1 Estimates for Earthwork and Lining for Km 1 1,01,68,647/-

2 Estimates for Earthwork and Lining for Km 2 1,02,48,901/-

3 Estimates for Earthwork and Lining for Km 3 1,12,63,291/-

4 Estimates for Earthwork and Lining for Km 4 1,16,41,685/-

5 Estimates for Earthwork and Lining for Km 5 90,66,717/-

6 Estimates for Earthwork and Lining for Km 6 98,97,942/-

7 Estimates for Earthwork and Lining for Km 7 74,73,246/-

8 Estimates for Earthwork and Lining for Km 8 73,65,085/-

9 Estimates for Earthwork and Lining for Km 9 69,35,216/-

10 Estimates for Earthwork and Lining for Km 10.85 1,07,07,399/-

11 Deduct Lining Cost for Structures -87,344/-

TOTAL 9,46,80,785/-

Rs 946.81 Lakhs

1 Earthwork of Canal including cost of lining 0 - 1 Km 87,07,620/-

2 Earthwork of Canal including cost of lining 1 - 2 Km 88,06,666/-

3 Earthwork of Canal including cost of lining 2 - 3 Km 83,64,822/-

4 Earthwork of Canal including cost of lining 3 - 4 Km 81,21,358/-

5 Earthwork of Canal including cost of lining 4 - 5 Km 94,00,829/-

6 Earthwork of Canal including cost of lining 5 - 6 Km 93,32,418/-

7 Earthwork of Canal including cost of lining 6 - 7 Km 85,13,349/-

8 Earthwork of Canal including cost of lining 7 - 8 Km 79,21,442/-

9 Earthwork of Canal including cost of lining 8 - 9 Km 76,55,035/-

10 Earthwork of Canal including cost of lining 9 - 10 Km 73,34,008/-

11 Earthwork of Canal including cost of lining 10-10.692 Km 48,10,000/-

12 Deduct Lining Cost for Structures -1,91,382/-

TOTAL 8,87,76,165/-

Rs 887.76 Lakhs

1 Estimates for Earthwork and Lining for Km 1 83,03,561/-

2 Estimates for Earthwork and Lining for Km 2 59,50,619/-

3 Estimates for Earthwork and Lining for Km 3 60,00,708/-

4 Estimates for Earthwork and Lining for Km 4 61,21,292/-

5 Estimates for Earthwork and Lining for Km 5 60,95,831/-

6 Estimates for Earthwork and Lining for Km 6 58,27,586/-

7 Estimates for Earthwork and Lining for Km 7 32,18,752/-

8 Deduct Lining Cost for Structures -3,73,665/-

TOTAL 4,11,44,683/-

Rs 411.45 Lakhs

11. Remodelling of Hulugi Channel

10. Remodelling of Siruguppa Channel

12. Remodelling of Shivapura Channel

No. Particulars Cost( in Rupees) Remarks

1 Estimates for Earthwork and Lining for Km 1 1,52,14,935/-

2 Estimates for Earthwork and Lining for Km 2 1,42,58,405/-

3 Estimates for Earthwork and Lining for Km 3 1,64,17,796/-

4 Estimates for Earthwork and Lining for Km 4 1,64,92,322/-

5 Estimates for Earthwork and Lining for Km 5 1,58,47,372/-

6 Estimates for Earthwork and Lining for Km 6 1,67,06,102/-

7 Estimates for Earthwork and Lining for Km 7 1,48,92,138/-

8 Estimates for Earthwork and Lining for Km 8 1,43,55,924/-

9 Estimates for Earthwork and Lining for Km 9 1,41,69,963/-

10 Estimates for Earthwork and Lining for Km 10 1,55,57,250/-

11 Estimates for Earthwork and Lining for Km 11 1,37,30,544/-

12 Estimates for Earthwork and Lining for Km 12 1,51,05,735/-

13 Estimates for Earthwork and Lining for Km 13 1,31,78,438/-

14 Estimates for Earthwork and Lining for Km 14 1,67,60,488/-

15 Estimates for Earthwork and Lining for Km 15 1,59,07,867/-

16 Estimates for Earthwork and Lining for Km 16 1,24,50,361/-

17 Estimates for Earthwork and Lining for Km 17 1,54,42,819/-

18 Estimates for Earthwork and Lining for Km 18 1,51,25,473/-

19 Estimates for Earthwork and Lining for Km 19.44 1,84,26,450/-

20 Deduct Lining Cost for Structures -18,79,891/-

TOTAL 28,81,60,490/-

Rs 2881.60 Lakhs

1 Estimates for Earthwork and Lining for Km 1 1,64,77,233/-

2 Estimates for Earthwork and Lining for Km 2 1,95,25,435/-

3 Estimates for Earthwork and Lining for Km 3 1,56,31,309/-

4 Estimates for Earthwork and Lining for Km 4 2,20,07,755/-

5 Estimates for Earthwork and Lining for Km 5 1,42,37,048/-

6 Estimates for Earthwork and Lining for Km 6 1,45,65,839/-

7 Estimates for Earthwork and Lining for Km 7 1,09,59,184/-

8 Estimates for Earthwork and Lining for Km 8 90,61,505/-

9 Estimates for Earthwork and Lining for Km 9.03 81,78,973/-

10 Deduct Lining Cost for Structures -27,48,883/-

TOTAL 12,78,95,398/-

Rs 1278.95 Lakhs

14. Remodelling of Upper Gangavathi Channel

13. Remodelling of Anegundi Channel

No. Particulars Cost( in Rupees) Remarks

1 Estimates for Earthwork and Lining for Km 1 1,14,08,253/-

2 Estimates for Earthwork and Lining for Km 2 1,21,78,708/-

3 Estimates for Earthwork and Lining for Km 3 1,13,38,353/-

4 Estimates for Earthwork and Lining for Km 4 1,07,31,509/-

5 Estimates for Earthwork and Lining for Km 5 1,04,71,646/-

6 Estimates for Earthwork and Lining for Km 6 1,31,71,089/-

7 Estimates for Earthwork and Lining for Km 7 1,16,71,452/-

8 Estimates for Earthwork and Lining for Km 8 1,05,89,778/-

9 Estimates for Earthwork and Lining for Km 9 76,80,550/-

10 Estimates for Earthwork and Lining for Km 9.54 68,36,513/-

11 Deduct Lining Cost for Structures -4,78,129/-

TOTAL 10,55,99,722/-

Rs 1056.00 Lakhs

1 Estimates for Earthwork and Lining for Km 1 67,83,960/-

2 Estimates for Earthwork and Lining for Km 2 69,34,425/-

3 Estimates for Earthwork and Lining for Km 3 65,28,897/-

4 Estimates for Earthwork and Lining for Km 4 68,71,047/-

5 Estimates for Earthwork and Lining for Km 5 70,96,298/-

6 Estimates for Earthwork and Lining for Km 6 85,36,597/-

7 Estimates for Earthwork and Lining for Km 7 58,54,046/-

8 Estimates for Earthwork and Lining for Km 8 59,20,989/-

9 Estimates for Earthwork and Lining for Km 9 57,36,208/-

10 Estimates for Earthwork and Lining for Km 10 59,41,438/-

11 Estimates for Earthwork and Lining for Km 11 51,05,371/-

12 Estimates for Earthwork and Lining for Km 12 61,32,141/-

13 Estimates for Earthwork and Lining for Km 13 61,76,966/-

14 Estimates for Earthwork and Lining for Km 14.52 96,95,705/-

TOTAL 9,33,14,087/-

Rs 933.14 Lakhs

15. Remodelling of Lower Gangavathi Channel

16. Remodelling of Bichal Channel

Sl No. Unit QuantityRate

(in Rs)

Amount in

Rs.

1KM

Approach Channel 0.57 31500.07 17,955/-

Raya Channel 27.74 31500.07 8,73,812/-

Basavanna Channel 16.50 31500.07 5,19,751/-

Bella Channel 5.50 31500.07 1,73,250/-

Kalaghatta Channel 7.00 31500.07 2,20,500/-

Turtha Channel 18.70 31500.07 5,89,051/-

Ramasagara Channel 15.50 31500.07 4,88,251/-

Kampli Channel 23.50 31500.07 7,40,252/-

Belagodhalla Channel 11.20 31500.07 3,52,801/-

Deshnur Channel 9.00 31500.07 2,83,501/-

Siruguppa Channel 10.80 31500.07 3,40,201/-

Hulugi Channel 10.70 31500.07 3,37,051/-

Shivapurra Channel 6.50 31500.07 2,04,750/-

Anegundi Channel 19.50 31500.07 6,14,251/-

Upper Gangavathi Channel 9.00 31500.07 2,83,501/-

Lower Gangavathi Channel 9.50 31500.07 2,99,251/-

Bichal Channel 14.50 31500.07 4,56,751/-

Total Length 215.71 67,94,880/-

Say Rs. (in Lakhs) 67.95

Providing trees along the Vijayanagar Channels

including protection, watering etc complete

COST OF M- PLANTATION Rs. 67.95 LAKHS

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

M - PLANTATION

Types of structures

NO.SSR I

NOPARTICULARS OF WORK QUANTITY RATE PER AMOUNT

1 2 3 4 5 6 7

1 129

Aligning the planting area along the

contours and marking for pits (without

stacking)28 300 1000 8.40

.

2 130

Excavation of pits of size 1mx1mx1m in

hard soil with vertically cut edges to

make uniform cube 7 heaping the

excavated soil on the lower side of the

pits(1/3rd top soil to be deposited on the

upper side 2/3rd on thelower side)1.00mx1.00mx1.00mm=250.00pits

==>250.0 Cum 134.00 90 Pit 12060.00

3 131

Refilling of pits,cutting of edge of the pit

on the lower side and refilling 75% of the

pit with the excavated soil,duly breaking

the clods & information of sucer shaped

mound on the lower sude of the pit of

size 1mx1mx1m1.00mx1.00mx1.00mm=250.00pits

==>250.0 Cum 134.00 10 pit 1340.00

4 86(f)

Loading of 8-10 ft. tall seedlings raised

in the H.D.P.E bags of size 14" x 20" into

the truck at the nursery site and

unloading nearest to the(irrespective of

the distance)

134.00 15 Each 2010.00

5 87(f)

Transportation of 14" X 20" P.B.

Seedlings in hired truck from the nursery

site to planting site.Distance from 31-

40kms.

134.00 8000.00 1000.00 1072.00

6 R.Q

Provindin 8- 10 feet along & 15 -20cms

grith plantation stakes treated with coal

tar at the bottom of the stakes up to 3

feet.

27 12 Each 324.00

ANNEXURE NO-16

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

M - PLANTATION

Length considered- 1000 m (1 Km)

No. of plants required per Km = '(1000/15) x 2 = 134 nos

NO.SSR I

NOPARTICULARS OF WORK QUANTITY RATE PER AMOUNT

1 2 3 4 5 6 7

7 132

Conveyance of tall seedlings raised in

HDPE bas of size 14" x 20" from the

dumping point to the planting site near

each pit on head load,fixing the

supporting stake firmly in the pit,planting

the tall seedling to the supporting stake

at 3 points.

134.00 10 Each 1340.00

8 M.RProcuring of Bindings wire @ 35

Plants/kg.20 40 kg 800.00

9 M.RProcuring of Bindings wire @20

grams/Plant.20 60 kg 1200.00

10 M.R Procuring of DAP wire @ 35 Plants/kg. 20 30 kg 600.00

11 133

Curring and collection of P.J. branches

loading the same into the lorry and

unloading at the planting site(8-

10branches/tall plant.)

134.000 15.00 Each 2010.00

12 134

Convenyance of P.J Branches to

individual pit,tying P.J branches around

the supporting stake properly converting

the tall plant with P.J thorny branches to

a height more than 2m and tying the P.J

branches G.I.Wire at 3 places (10 P.J

branches to be used)

134.000 6.30 Each 844.20

13 100

Apllication of lime/chemical fertiliser

around the plants about 15cm,away in a

furrow duly covering the soil(excluding

the cost of materials)

25.000 70.80 1000.00 1.77

14 135I weeding around the plants (pits) to a

radius of 60cm 134.000 1500.00 1000.00 201.00

15 137

Scraping of grass and other growth

around the tall plant to a radius of 1.00

m planted pits.(for 0.75m 3 pits only) 27.000 2500.00 1000.00 67.50

NO.SSR I

NOPARTICULARS OF WORK QUANTITY RATE PER AMOUNT

1 2 3 4 5 6 7

16 138

Saucer Bhavan to the plant with semi-

circular bound on the lower slope with

one meter distance between the ends of

two arms of the bund.

27.000 4.30 Each 116.10

17 139 Watering to the plants planted in the

pits/trench along roadside and in the city

limits at 50litres/plant.By Hiring the

private vehicle 2 times.

54.000 7.15 Each 386.10

18 Cost of poly based seedlings - - - 6500.00

19Add for miscellaneous and rounding off 619.00

Total = 31,500/-

Rs. 31,500 /-

The Rates considered for each item under M plantation ia as per as per SR of State Forest

Department

Range Forest Officer

Note: Rate of each item is as per SR of State Forest Department

Cost per Km of Plantation=

Sl

No.Description Unit Quantity

Rate

(Rs)

Amount

Rs in Lakhs

Purchasing Bollero Van for Sub-division office No. 5 8,09,136/- 40.46

40.46 Lakhs

COST OF SPECIAL TOOLS AND PLANTS Rs.40.46 LAKHS

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

Q- SPECIAL TOOLS AND PLANTS

ABSTRACT

TOTAL

Sl

No.Description Unit Qty Rate in Rs

Amount

Rs in Lakhs

Bolero Van for following sub-division

1AEE , Vijayanagar canal sub division,

KamalapurNo 1 809136 8.09

2AEE , No.1 canal sub division, Agalkera

No 1 809136 8.09

3 AEE , Vaddarahatti sub division No 1 809136 8.09

4 AEE , Siruguppa sub division No 1 809136 8.09

5 AEE , Yaramarus sub division No 1 809136 8.09TOTAL 40.46 Lakhs

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

Q- SPECIAL TOOLS AND PLANTS

Note: Rate for 1 no. of Bolero Van as per Quotation by M/S Bellary Motor Sales Pvt. Ltd., Bellary ( Copy

enclosed)

TOTAL COST OF Q- SPECIAL TOOLS AND PLANTS Rs. 40.46 LAKHS

Sl

No.Description

Amount

Rs in Lakhs

1Distributaries Network and Minors for 16 canals under Vijayanagar

Channels 5454.41 Lakhs

5454.41 Lakhs

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

U-DISTRIBUTARIES AND MINORS

TOTAL

ABSTRACT

COST OF U-WORKS Rs.5454.41 LAKHS

Executive Engineer

Details of Distributary System :

Total No. canals under Vijayanagar Channels = 16 Nos.

Total CCA of 16 Channels = 11154 ha.

Details estimate for distributary network of 10% CCA covering

No CCA in Ha

1 600

2 620

1220

1)

2)

= Rs 5,96,59,099 /-

5,96,59,099 /-

1220

Rs 3,93,75,239 /-

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

U-DISTRIBUTARIES & MINORS

Modernisation of Bella Channel

Modernisation of Kampli Channel

Particulars

TOTAL

Note: Detailed estimate for Item No 1 = Rs 2,02,83,859/- and item No 2 = 3,93,75,239/- is appended

saperately as Volume IV

Total amount for 1220 ha

=Rate per 1 ha of CCA = Rs 48,901 /ha

Total cost for distributary network of Bella canal

( 600 ha)= Rs 2,02,83,859 /-

Total cost for distributary network of Kampli canal (

620 ha)=

Executive Engineer

Details of Distributary System :

No ParticularsDistributary

Length in Km

Minor Length

in KmCCA in Ha

1 Raya Channel 1.313 44.595 2226

2 Basavanna Channel 4.36 9.286 1240

3 Bella Channel 0.9 7.951 600

4 Kalaghatta Channel 16.6 237

5 Turtha Channel 931

6 Ramasagara Channel 7.65 23.33 673

7 Kampli Channel 1.5 18.69 620

8 Belagodhalla Channel 5.63 210

9 Deshnur Channel 3.62 478

10Siruguppa Channel 3.93 764

11 Hulugi Channel 4.44 265

12 Shivapura Channel 4.05 2.4 403

13 Anegundi Channel 4.72 789

14 Upper Gangavathi Channel 11.695 5.37 775

15 Lower Gangavathi Channel 15.44 1.51 667

16 Bichal Channel 276

TOTAL 46.908 152.072 11154

= 11154 x 48,901

=

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

U-DISTRIBUTARIES & MINORS

Cost for distributary network of 16 canals under Vijayangar Channels

covering 11154 ha of CCA= Rs 48,901 /ha

Rs 54,54,40,644 /-

Total Cost = 5454.41 Lakhs

No. Particulars Cost( in Rupees) Remarks

1Estimates for Earthwork of Narsapura Branch Canal

including cost of lining 18,42,132/-

Details enclosed

Refer Volume-IV,

Page No.5

2 Earthwork and Lining of Minor-1 of Bella Canal 25,81,914/-

Details enclosed

Refer Volume-IV,

Page No.18

3 Earthwork and Lining of Minor-2 of Bella Canal 12,56,308/-

Details enclosed

Refer Volume-IV,

Page No.31

4 Earthwork and Lining of Minor-3 of Bella Canal 15,03,812/-

5 Earthwork and Lining of Minor-4 of Bella Canal 21,40,107/-

6 Earthwork and Lining of Minor-5 of Bella Canal 28,11,646/-

7 Earthwork and Lining of Minor-6 of Bella Canal 21,40,107/-

8 Earthwork and Lining of Minor-7 of Bella Canal 16,29,824/-

9Estimates for Retaining wall of Narsapura Branch

Canal 30,92,246/-

Details enclosed

Refer Volume-IV,

Page No.42

10Estimates for Drop at Ch. 0+782 Km of Narsapura

Branch Canal 3,69,562/-

Details enclosed

Refer Volume-IV,

Page No.54

11Estimates for Distribution Box at Ch. 0+900 Km (Tail

end) of Narsapura Branch Canal 7,82,021/-

Details enclosed

Refer Volume-IV,

Page No.73

12 Estimates for Silt removal for DPO - 1 24,639/-

Details enclosed

Refer Volume-IV,

Page No.89

13 Estimates for Silt removal for DPO - 2 11,982/-

Details enclosed

Refer Volume-IV,

Page No.91

14 Estimates for Silt removal for DPO - 3 14,345/-

Details enclosed

Refer Volume-IV,

Page No.93

15 Estimates for Silt removal for DPO - 4 20,420/-

16 Estimates for Silt removal for DPO - 5 26,833/-

17 Estimates for Silt removal for DPO - 6 20,420/-

18 Estimates for Silt removal for DPO - 7 15,543/-

TOTAL 2,02,83,859/-

Rs 202.84 Lakhs

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

DETAIL ESTIMATE FOR DISTRIBUTARY NETWORK OF BELLA CANAL = CCA 600 Ha

U-DISTRIBUTARIES & MINORS

No. Particulars Cost( in Rupees) Remarks

No. Particulars Cost( in Rupees) Remarks

1Estimates for Earthwork of Distributary including cost

of lining 56,27,143/-

Details enclosed

Refer Volume-IV,

Page No.121

2 Earthwork and Lining of Minor-1 of Kampli Canal 10,36,188/-

Details enclosed

Refer Volume-IV,

Page No.134

3 Earthwork and Lining of Minor-2 of Kampli Canal 7,77,477/-

Details enclosed

Refer Volume-IV,

Page No.147

4 Earthwork and Lining of Minor-3 of Kampli Canal 9,50,057/-

5 Earthwork and Lining of Minor-4 of Kampli Canal 12,94,900/-

6 Earthwork and Lining of Minor-5 of Kampli Canal 5,18,765/-

7 Earthwork and Lining of Minor-6 of Kampli Canal 7,08,529/-

8 Earthwork and Lining of Minor-7 of Kampli Canal 8,29,219/-

9 Earthwork and Lining of Minor-8 of Kampli Canal 9,50,057/-

10 Earthwork and Lining of Minor-9 of Kampli Canal 12,43,158/-

11 Earthwork and Lining of Minor-10 of Kampli Canal 10,36,188/-

12 Earthwork and Lining of Minor-11 of Kampli Canal 14,67,480/-

13 Earthwork and Lining of Minor-12 of Kampli Canal 13,46,642/-

14 Earthwork and Lining of Minor-13 of Kampli Canal 13,98,384/-

15 Earthwork and Lining of Minor-14 of Kampli Canal 15,53,611/-

16 Earthwork and Lining of Minor-15 of Kampli Canal 11,39,673/-

17 Earthwork and Lining of Minor-16 of Kampli Canal 5,18,765/-

18 Earthwork and Lining of Minor-17 of Kampli Canal 10,70,725/-

19 Earthwork and Lining of Minor-18 of Kampli Canal 11,22,467/-

20 Earthwork and Lining of Minor-19 of Kampli Canal 13,46,642/-

21 Earthwork and Lining of Minor-20 of Kampli Canal 6,73,992/-

22 Earthwork and Lining of Minor-21 of Kampli Canal 11,22,467/-

23 Earthwork and Lining of Minor-22 of Kampli Canal 9,32,704/-

24 Earthwork and Lining of Minor-23 of Kampli Canal 8,98,315/-

25 Earthwork and Lining of Minor-24 of Kampli Canal 11,05,284/-

U-DISTRIBUTARIES & MINORS

DETAIL ESTIMATE FOR DISTRIBUTARY NETWORK OF KAMPLI CANAL = CCA 620 Ha

No. Particulars Cost( in Rupees) Remarks

26 Earthwork and Lining of Minor-25 of Kampli Canal 9,84,446/-

27 Earthwork and Lining of Minor-26 Of Kampli Canal 6,73,992/-

28 Earthwork and Lining of Minor-27 of Kampli Canal 11,05,284/-

29 Earthwork and Lining of Minor-28 of Kampli Canal 4,15,281/-

30 Earthwork and Lining of Minor-29 of Kampli Canal 11,57,321/-

31 Earthwork and Lining of Minor-30 of Kampli Canal 8,46,572/-

32 Earthwork and Lining of Minor-31 of Kampli Canal 7,25,735/-

33 Earthwork and Lining of Minor-32 of Kampli Canal 9,67,240/-

34 Earthwork and Lining of Minor-33 of Kampli Canal 3,63,539/-

35 Estimates for Drop at Ch. 0+982 Km of Distributary-1 3,69,562/-

Details enclosed

Refer Volume-IV,

Page No.160

36Estimates for Distribution Box at Ch. 1+500 Km (Tail

end) of Distributary-1 7,82,021/-

Details enclosed

Refer Volume-IV,

Page No.179

37 Estimates for Silt removal for DPO - 1 10,126/-

Details enclosed

Refer Volume-IV,

Page No.195

38 Estimates for Silt removal for DPO - 2 7,594/-

Details enclosed

Refer Volume-IV,

Page No.197

39 Estimates for Silt removal for DPO - 3 9,282/-

Details enclosed

Refer Volume-IV,

Page No.199

40 Estimates for Silt removal for DPO - 4 12,657/-

Details enclosed

Refer Volume-IV,

Page No.201

41 Estimates for Silt removal for DPO - 5 5,063/-

42 Estimates for Silt removal for DPO - 6 6,919/-

43 Estimates for Silt removal for DPO - 7 8,100/-

44 Estimates for Silt removal for DPO - 8 9,282/-

45 Estimates for Silt removal for DPO - 9 12,151/-

46 Estimates for Silt removal for DPO - 10 10,126/-

47 Estimates for Silt removal for DPO - 11 14,345/-

48 Estimates for Silt removal for DPO - 12 13,163/-

49 Estimates for Silt removal for DPO - 13 13,670/-

50 Estimates for Silt removal for DPO - 14 15,188/-

51 Estimates for Silt removal for DPO - 15 11,138/-

No. Particulars Cost( in Rupees) Remarks

52 Estimates for Silt removal for DPO - 16 5,063/-

53 Estimates for Silt removal for DPO - 17 10,463/-

54 Estimates for Silt removal for DPO - 18 10,969/-

55 Estimates for Silt removal for DPO - 19 13,163/-

56 Estimates for Silt removal for DPO - 20 6,582/-

57 Estimates for Silt removal for DPO - 21 10,969/-

58 Estimates for Silt removal for DPO - 22 9,113/-

59 Estimates for Silt removal for DPO - 23 8,776/-

60 Estimates for Silt removal for DPO - 24 10,801/-

61 Estimates for Silt removal for DPO - 25 9,619/-

62 Estimates for Silt removal for DPO - 26 6,582/-

63 Estimates for Silt removal for DPO - 27 10,801/-

64 Estimates for Silt removal for DPO - 28 4,050/-

65 Estimates for Silt removal for DPO - 29 11,307/-

66 Estimates for Silt removal for DPO - 30 8,269/-

67 Estimates for Silt removal for DPO - 31 7,088/-

68 Estimates for Silt removal for DPO - 32 9,451/-

69 Estimates for Silt removal for DPO - 33 3,544/-

TOTAL A+B+C 3,93,75,239/-

Rs 393.75 Lakhs

Sl no Length in mtr Amount @ Rs 2778 per Rmtr

1 6000 1,66,65,431/-

2 4000 1,11,10,287/-

2,77,75,718/-

277.76 Lakhs

Note: Typical estimate for 100 m length drain is enclosed

Rs 2,77,757 /-

Rs 2,778 /-

Particulars

Basavanna Channel

Raya Channel

MODERNISATION OF VIJAYANAGARA CHANNELS

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

W - Drainage

Total

Say

Rate for 100 m =

Rate for 1 m length =

Drainage provided for leading out seepage water of the canal into nearest natural Drain within the

city Limits of Hospet Town

No DESCRIPTION OF WORK UNIT QUANTITY RATE AMOUNT

1 Excavation in all kinds of soil including boulders upto

0.6m diameter (0.113 cum) for foundations of canal cross

drainage and other appurtenant structures and placing

excavated stuff neatly in specified dump area or disposing

off the same as directed including cost of materials,

machinery,labour etc., complete with initial lead upto 50 m

and initial lift upto 1.50 m.

(SR Item No.WRD: 4.1, page 84 , for 2013-14)

a) Lift 0.00 m to 1.50 m cum 70.00 126.88 8,882/-

Weightage 25% 31.72 2,220/-

2 Providing and laying insitu vibrated M-10 (28 days cube

compressive strength not less than 10 N/sqmm) grade

cement concrete using 40 mm down approved, clean,

hard, graded aggregates for foundation filling including

cost of all materials, machinery, labour, formwork,

cleaning, batching, mixing, placing in position, levelling,

vibrating, finishing, curing etc., complete with initial lead

upto 50 m and depth of foundation upto 1.5 m from

surface. (Cement content :220 kg/cum with use of super

plasticiser)

(SR Item No.WRD: 4.10, page 86 , for 2013-14) cum 7.00 4812.126 33,685/-

Weightage 25% 1203.031 8,421/-

3 Providing and laying insitu vibrated M-15 (28 days cube

compressive strength not less than 15 N/sqmm) grade

cement concrete using 20 mm downsize approved, clean,

hard, graded aggregates for sub-structure works including

cost of all materials, machinery, labour, formwork,

scaffolding, cleaning, batching, mixing, placing in position,

levelling, vibrating, finishing, curing etc., complete with

initial lead upto 50 m and lift upto 1.5 m from surface.

(Cement content :270 kg/cum with use of super

plasticiser)

(SR Item No.WRD: 4.15, page 87 , for 2013-14) cum 21.00 5933.106 124,595/-

Weightage 25% 1483.278 31,149/-

MODERNISATION OF VIJAYNAGAR CHANNELS IN TUNGABHADRA PROJECT

ABSTRACT ESTIMATE FOR THE CONSTRUCTION OF DRAINAGE UNDER RAYA CHANNEL

No DESCRIPTION OF WORK UNIT QUANTITY RATE AMOUNT

4 Providing, fabricating and placing in position

reinforcement steel bars for RCC works including cost of

all materials,machinery, labour,cleaning, straightening,

cutting, bending, hooking, lapping, welding wherever

required, tying with 1.25 mm dia soft annealed steel

wire,etc., complete with initial lead upto 50 m and all lifts.

(SR Item No.WRD: 4.6, page 85 , for 2013-14) kgs 824.25 66.78 55,043/-

Weightage 25% 16.70 13,762/-

Total 2,77,757/-

Say 2,77,757 /-Total 2,778/-

Rupees Two Thousand Seven Hundred Seventy Seven And Paise Fifty Seven Only

Cost for 100 m Drainage

Cost for 1 m Drainage

No DESCRIPTION OF WORK UNIT No L B D QUANTITY REMARKS

1 2 3 4 5 6 7 8 9

1 Excavation in all kinds of soil including boulders

upto 0.6m diameter (0.113 cum) for foundations of

canal cross drainage and other appurtenant

structures and placing excavated stuff neatly in

specified dump area or disposing off the same as

directed including cost of materials,

machinery,labour etc., complete with initial lead

upto 50 m and initial lift upto 1.50 m.(SR Item No.WRD: 4.1, page 84 , for 2013-14)

a) Lift 0.00 m to 1.50 m cum

U/S , D/S Head wall & Sidewall alround 1 100.00 0.70 1.00 70.00

Total 70.00

Say 70.00

2 Providing and laying insitu vibrated M-10 (28 days

cube compressive strength not less than 10

N/sqmm) grade cement concrete using 40 mm

down approved, clean, hard, graded aggregates for

foundation filling including cost of all materials,

machinery, labour, formwork, cleaning, batching,

mixing, placing in position, levelling, vibrating,

finishing, curing etc., complete with initial lead upto

50 m and depth of foundation upto 1.5 m from

surface. (Cement content :220 kg/cum with use of

super plasticiser)

(SR Item No.WRD: 4.10, page 86 , for 2013-14)

cum

1 100.00 0.70 0.10 7.00

Total 7.00

Say 7.00

MODERNISATION OF VIJAYNAGAR CHANNELS IN TUNGABHADRA PROJECT

DETAILED ESTIMATE FOR THE CONSTRUCTION OF DRAINAGE ( Qty for 100m length)

No DESCRIPTION OF WORK UNIT No L B D QUANTITY REMARKS

1 2 3 4 5 6 7 8 9

3 Providing and laying insitu vibrated M-15 (28 days

cube compressive strength not less than 15

N/sqmm) grade cement concrete using 20 mm

downsize approved, clean, hard, graded

aggregates for sub-structure works including cost of

all materials, machinery, labour, formwork,

scaffolding, cleaning, batching, mixing, placing in

position, levelling, vibrating, finishing, curing etc.,

complete with initial lead upto 50 m and lift upto 1.5

m from surface. (Cement content :270 kg/cum with

use of super plasticiser)

(SR Item No.WRD: 4.15, page 87 , for 2013-14)

cum

Allround 1 100.00 0.10 2.10 21.00

Total 21.00

Say 21.00

4 Providing, fabricating and placing in position

reinforcement steel bars for RCC works including

cost of all materials,machinery, labour,cleaning,

straightening, cutting, bending, hooking, lapping,

welding wherever required, tying with 1.25 mm dia

soft annealed steel wire,etc., complete with initial

lead upto 50 m and all lifts.

(SR Item No.WRD: 4.6, page 85 , for 2013-14) kgs

All round 1 824.25

Total 824.25

Say 824.25

0.5/100 x 78.5 x 21

Sl

No.Description Unit Qty Rate in Rs

Amount

Rs in Lakhs

AEE , Vijayanagar canal sub division, Kamalapur

1 Levelling Instrument No 1 40000 0.4

2 Theodolite No 1 60000 0.6

3 Computer No 1 128000 1.28

AEE , No.1 canal sub division, Agalkera

1 Levelling Instrument No 1 40000 0.4

2 Theodolite No 1 60000 0.6

3 Computer No 1 128000 1.28

AEE , Vaddarahatti sub division

1 Levelling Instrument No 1 40000 0.4

2 Theodolite No 1 60000 0.6

3 Computer No 1 128000 1.28

AEE , Siruguppa sub division

1 Levelling Instrument No 1 40000 0.4

2 Theodolite No 1 60000 0.6

3 Computer No 1 128000 1.28TOTAL 9.12 Lakhs

MODERNISATION OF VIJAYANAGARA CHANNELS IN TUNGABHADRA PROJECT

III TOOLS AND PLANTS (Survey Instruments)

TOTAL COST OF SMALL AND PLANTS Rs. 9.12 LAKHS

Assistant Executive Engineer KNNL, Vijayanagar canal Sub Division

Kamalapura

Executive Engineer KNNL, No.1 T.R Division

Munirabad

Karnataka Neeravari Nigam Limited

20% of total value of

produce (Rs

Lakhs)

1 2 3 4 5 6 7 8 9 10 11 12

Khariff

Paddy 30.90 4056 60 1979.00 4815.65 60.00 24 58.40 40000 1622.25 963.13

Hy. Jowar 5.60 735 20 2615.00 384.41 60.00 24 10.58 23000 169.05 76.88

Rabi

Paddy 13.90 1824 60 1979.00 2166.26 60.00 24 26.27 40000 729.75 433.25

Groundnut 14.50 1903 20 6009.00 2287.18 100.00 41 78.03 23000 437.72 457.44

Bi seasonal

Sugarcane 24.20 3176 60 2540.00 4840.61 7500.00 3 714.66 39000 1238.74 968.12

Garden (Banana) 10.90 1431 100 2000.00 2861.25 2250.00 5 160.95 68000 972.83 572.25

TOTAL 100.00 13125 17355.35 1048.89 5170.33 3471.07

MODERNISATION OF VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT

ESTIMATED VALUE OF PRODUCE BEFORE MODERNISATION

Quantity

Kg/Ha

Rate

Rs/Kg

Amount

(Rs

Lakhs)

Rate

Rs/Ha

Amount

(Rs Lakhs)

Input Seed

Value of

produce

( Rs lakhs)

Manure (Input) Hired Labour

(Human & bullock)

Crop % Area Area

Ha

Produce

(Qtls/Ha)

Rate per

Qtl.

(Rs)

Benefit-Cost Ratio

Karnataka Neeravari Nigam Limited

20% of total value of

produce (Rs Lakhs)

1 2 3 4 5 6 7 8 9 10 11 12

Khariff

Paddy 14.18 2304 75.0 1979.00 3419.71 60.00 24 33.18 30000 691.20 683.94

Hy. Jowar 38.95 6326 50.0 2615.00 8271.11 60.00 24 91.09 20000 1265.18 1654.22

Rabi

Paddy 10.19 1655 75.0 1979.00 2456.43 60.00 24 23.83 30000 496.50 491.29

Groundnut 23.12 3755 25.0 6009.00 5640.80 100.00 41 153.95 22000 826.08 1128.16

Bi seasonal

Sugarcane 7.57 1229 120.0 2540.00 3745.38 7500.00 3 276.48 36000 442.37 749.08

Garden (Banana) 6.00 974 120.0 2000.00 2337.12 2250.00 5 109.55 60000 584.28 467.42

TOTAL 100.00 16243 25870.56 688.09 4305.61 5174.11

MODERNISATION OF VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT

ESTIMATED VALUE OF PRODUCE AFTER MODERNISATION

Crop % Area Area

Ha

Produce

(Qtls/Ha)

Rate per Qtl.

(Rs)

Value of

produce (

Rs lakhs)

Input Seed Manure (Input) Hired Labour (Human &

bullock)

Quantity Kg/HaRate

Rs/Kg

Amount

(Rs Lakhs)

Rate

Rs/Ha

Amount (Rs

Lakhs)

Benefit-Cost Ratio

Karnataka Neeravari Nigam Limited

A Gross ReceiptsBefore

Modernisation

After

Modernisation

1 Gross value of farm produce 17355.35 25870.56

2 Dung receipts(at 30%of the fodder expenditure) 780.99 776.12

3 Total A : Gross Receipts(1+2) 18136.34 26646.68

B EXPENSES:

1 Expenditure on seeds 1048.89 688.09

2 Expenditure on manure etc. 5170.33 4305.61

3 Expenditure on hired labour(human and bullock) 3471.07 5174.11

4 Fodder expenses(as percentage of gross value of produce)

(15% ,10% of item A.1) 2603.30 2587.06

5 Depriciation on implements (2.7% of Item A.1) 468.59 698.51

6 Share and cash rent (5% 3% of Item A.1) 867.77 776.12

7 Land Revenue (2% of Item A.1) 347.11 517.41

8 Total B : Expenses (1 to 7) 13977.06 14746.89

C NET VALUE OF PRODUCE

1 Total gross receipts(Total A.3) 18136.34 26646.68

2 Minus total expenses (Total B.8) 13977.06 14746.89

3 Net value of produc © : [1-2] 4159.28 11899.78

D ANNUAL BENEFITS:

1 Net value after irrigation (C:3) 11899.78

2 Minus Net value before irrigation (C:3) 4159.28

3 Net annual benefits (D):[1-2] 7740.50

TOTAL NET ANNUAL BENEFITS (D3) 7740.50

E ANNUAL COSTS

1

Intrest on Capital @10% ( Esimated total cost of the project

including cost of land development @ Rs.1000/- per Ha) (Rs

40322.00 Lakhs + 16.24 Lakhs)

4048.44

2Depreciation of the project at 1 % of the cost of the project for 100

years life excluding cost of Land, R&R cost.(40322.00 Lakhs x 1%)403.22

3 Annual operation and maintenance charge at Rs. 1175/ ha 190.86

4Maintainance of the Head works at 1% its cost (Improvements to

anicuts)61.26

5 Total (E):Annual costs (1 to 4) 4703.78

BENEFITS COST RATIO = D 3 : Annual Benefits 7740.50

E.5: Annual cost 4703.78

MODERNISATION OF VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT

CALCULATION OF BENEFIT COST RATIO (BCR)

AS ADOPTED BY THE TECHNICAL ADVISORY COMMITTEE

Figures are in Rs lakhs

1.65

Benefit-Cost Analysis

Rate in Rs. /ha

1 2 3 4 5 6 7 8

Khariff

Paddy 4056 60 1500 1440 40000 17650 59090

Hy. Jowar 735 20 1500 1440 23000 6000 30440

Rabi

Paddy 1824 60 1500 1440 40000 17650 59090

Groundnut 1903 20 3000 4100 23000 12000 39100

Bi seasonal

Sugarcane 3176 60 2540 22500 39000 30000 91500

Garden (Banana) 1431 100 2000 11200 68000 40000 119200

TOTAL 13125 123300.00

Joint Director of Agriculture

Bellary

Input/ha ( Rate in Rs.) Total cost of

cultivation (Rs.

per ha)

Hired Labour

(Human & bullock)Seeds Manure

DETAILS OF CROP YIELD, RATE OF PRODUCE AND COST OF CULTIVATION FOR MODERNISATION OF

VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT

(BEFORE MODERNISATION)

CropArea

Ha

Produce

(Qtls/Ha)

Rate per Qtl.

(Rs)

Rate in Rs. /ha

1 2 3 4 5 6 7 8

Khariff

Paddy 4661 75 1500 1440 30000 13000 44440

Hy. Jowar 812 30 1500 1440 20000 9000 30440

Rabi

Paddy 3086 75 1500 1440 30000 13000 44440

Groundnut 2323 25 3000 4100 22000 13500 39600

Bi seasonal

Sugarcane 3427 120 2540 22500 36000 33200 91700

Garden (Banana) 1933 120 2000 11200 60000 48000 119200

TOTAL 16241 129700.00

Joint Director of Agriculture

Bellary

DETAILS OF CROP YIELD, RATE OF PRODUCE AND COST OF CULTIVATION FOR MODERNISATION OF

VIJAYANAGAR CHANNELS IN TUNGABHADRA PROJECT

(AFTER MODERNISATION)

CropArea

Ha

Produce

(Qtls/Ha)

Rate per Qtl.

(Rs)

Input/ha ( Rate in Rs.) Hired Labour

(Human & bullock)Total cost of

cultivation (Rs.

per ha)Seeds Manure