MODERN BIOGAS PLANTS
Dipl.-Ing. Helmut Muche
FFE Solutions GmbH – Kolberger Straße 13 – 24589 Nortorf – Germanywww.farmatic.com
Jakarta - 11. October 2016
1
www.farmatic.comwww.farmatic.com
FFE-Solutions company profileCompany history of 50 years
Annual turn-over approx. 15 - 20 Mio €
50 Employees
Headquarters in Nortorf (70 km North of Hamburg, Germany)
ISO certified quality management
Over 100 biogas plant references Over 100 wastewater treatment plant referencesOver 3,000 bolted steel tanks constructed worldwide
2
www.farmatic.comwww.farmatic.com
Business Sectors
Biogas Plants Wastewater TreatmentTank and Storage
Solutions
Digestion Plants for organic Waste
Agricultural Biogas Plants
Engineering Services
Biogas
Agriculture
Energy Storage
Industry
SBR-Plants
Continuous Flow Plants
Equipment: Aerators, Mixers, Decanters
Thermal Energy Storage TES
Cold Water Storage
Hot Water Storage
PTH: Power-To-Heat
Industrial & Municipal WWTP
3
www.farmatic.comwww.farmatic.com
We use bolted steel tanks for our biogas plants
Storage solutions with capacity up to 20,000 m³
Digesters up to 8,000 m³
Our modular design allows flexible solutions
Tanks can have any size and any width from 50 m³ - 20,000 m³
4
www.farmatic.comwww.farmatic.com 5
Tank Construction on Site
silo bolt
PE cover
permanently elastic and
UV resistant sealant
Tank Interior Tank Exterior
glass coated steel panel 2 glass coated steel panel 1
No scaffolding necessary – tanks are built on the ground and then lifted by a special jack system.
5
www.farmatic.comwww.farmatic.com
Digester Material
Liquid Zone Glass Coated Steel (GCS)Gas Zone Stainless Steel or GCS Roof Stainless Steel
Insulation and Sealant
10 – 20 cm of mineral woolPermanently elastic sealant (Sikaflex)
Operational Temperatures
Thermophilic 50° – 56° CMesophilic: 36° – 38° C
Watch the 3D animation on Youtube:
www.youtube.com/FarmaticAnlagenbau
Farmatic‘s signature – vertical constantly stirred digesters
6
www.farmatic.comwww.farmatic.com
We use CSTR digesters for our biogas plants
• No sedimentation, no floating layers• constant substrate circulation
7
www.farmatic.comwww.farmatic.com
Biogas
SubstratesSubstrates
Waste from the processing of vegetable raw materials and energy crops
Palm Oil MillEffluent
Spent wash
Empty fruitbunches
► Wastes from the processing of plants
► Energy crops
Napier grass
8
www.farmatic.comwww.farmatic.com
INPUT PROCESS OUTPUT
PlantationFresh Fruit Bunch
FFB
Mineral fertilizer
Diesel
Crop protection products
Water
Solar energy
Palm Oil Mill
Products
Palm oil
Kernel
Power plantBoiler
Energy conversion
Water
Composting
Biogas plant
Compost Waste water
Emissions
Ash
PALM OIL PRODUCTION
Shells
Natural fertilizer
Biogas plant
Methane
Wood
OFB
Power plantGas engine
Grid
Water
Biogasupgrading
CNG
By-productsEmpty Fruit
Bunch Palm Oil
Mill Effluent Fibres Shells
Electricity
Steam
Decanter cake
Heat exchanger
Soil
Biogas
Compost
Waste water
Ash
Exhaust gas
9
www.farmatic.comwww.farmatic.com
Separate anaerobic digestion of Empty Fruit Bunches and POME
Mechanicalsize reduction
DigesterV = 30,800 m³
EFB276 Mg/d
Biogas33,085 m³/d
Solid phase232 Mg/d19 % TS
Liquid phase695 m³/d
Composting
Fertilizer
60 Mg FFB/h
Dehydration
DigesterV = 7,336 m³
POME648 m³/d
Biogas19,790 m³/d
Effluent648 m³/d
Waste water treatment
648 m³/d
2015.11.19
Gas treatment
Power plant4,600 kW
Separation
Power plant1,800 kW
Power plant2,800 kW
10
www.farmatic.comwww.farmatic.com
Comparison: CSTR digester – lagoon digester
Advantages
● simple design● high material quality● high volumetric load possible● High dry matter content possible
→ smaller digester volume needed● uses highly efficient vertical mixers● low energy consumption for mixing● External heat exchangers, easy maintenance● heat insulation
→ low heat loss● danger to groundwater easily eliminated● easy explosion protection● easy lightning protection● very low maintenance ● very long life span of the system● low overall life cycle cost● low footprint of facility
Continuous Stirred Tank Reactor Lagoon System
● simple design● easy access to construction materials
11
www.farmatic.comwww.farmatic.com
Disadvantages
Lagoon System
● high initial investment cost● complex construction
● low material quality● only low volumetric load possible● only low dry matter content possible
→ larger digester volume necessary● low digester height results in very large
surface area→ bad mixing results→ high energy demand for mixing
● no heat insulation● groundwater protection difficult● entire facility is explosion hazard● lightning protection difficult● high running maintenance cost● very low life span● high overall life cycle cost● large footprint and land use
Comparison: CSTR digester – lagoon digester
Continuous Stirred Tank Reactor
12
www.farmatic.comwww.farmatic.com
Capital and operating costs
Comparison: CSTR digester – lagoon digester
Lagoon System
Continuous Stirred Tank Reactor
Unit
Fresh Fruit Bunch 50 50 to/h
Volume flow POME 450 450 m³/d
Volume digester 22,000 5,400 m³
Hydraulic Retention Time ≈ 45 ≈ 11 d
Investment cost 685,000 790,000 €
Installed power agitators 18 30 kW
Energy consumption 130,000 170,000 kWh/y
Maintenance cost 116,000 3,400 €/y
Interruption 2 0 months
13
www.farmatic.comwww.farmatic.com
FFE-Solutions GmbH · Kolberger Straße 13 · 24589 Nortorf
Telephone +49 43 92 / 91 77 - 0 · Fax +49 43 92 / 5864 · [email protected]
R E F E R E N C E S BIOGAS PLANT SKÖVDE, SEGöteborg Energi AB, Skövde, Sweden
Year of commissioning 2011
Gas yield 800 Nm³/h
Digester volume 2 x 4,350 m³
Post-digester volume 1 x 2,400 m³
Substrates:
Whey 71,000 t/a
Expired food 10,000 t/a
Slaughterhouse waste 8,000 t/a
Wastewater 7,000 t/a
Spoiled milk 3,000 t/a
Special Features
• Gas upgrading
• Thermophilic process (55°C) as pasteurisation
method
• Sophisticated heat management through heat
storage and recovery
• Very few pumps required, 80 % of the plant
operates through hydrostatic pressure
14
www.farmatic.comwww.farmatic.com
FFE-Solutions GmbH · Kolberger Straße 13 · 24589 Nortorf
Telephone +49 43 92 / 91 77 - 0 · Fax +49 43 92 / 5864 · [email protected]
R E F E R E N C E S BIOGAS PLANT LUSTENAU, ATHäusle GmbH, Lustenau, Austria
Year of commissioning 2013
Gas yield 600 Nm³/h
Digester volume 1 x 3,900 m³
Post-digester volume 1 x 5,100 m³
Substrates:
Organic fraction of MSW 17,000 t/a
Cattle manure 5,000 t/a
Grease trap contents (fat) 2,000 t/a
Special Features
• Expansion of an existing dry fermentation
plant with a wet digestion line
• Hygienisation at 70 °C
• Sophisticated separation of solids,
impurities and other unwanted materials
by screw press and hydro cyclone
15
www.farmatic.comwww.farmatic.com
FFE-Solutions GmbH · Kolberger Straße 13 · 24589 Nortorf
Telephone +49 43 92 / 91 77 - 0 · Fax +49 43 92 / 5864 · [email protected]
R E F E R E N C E S BIOGAS PLANT ARAVETE, ESTAravete Biogas, Aravete, Ambla, Estonia
Year of commissioning 2012
Installed power 2,000 kW
Digester volume 2 x 3,500 m³
Post-digester volume 1 x 2,500 m³
Substrates
Cow manure 63,000 t/a
Dry dung 25,000 t/a
Poultry manure 5,200 t/a
Gras silage 1,000 t/a
Brewery waste 8,000 t/a
Whey 4,000 t/a
Special Features
• Complex mix of substrates
• High dry matter content in some
substrates requires heavy duty cutting
and feeding machinery
16
www.farmatic.comwww.farmatic.com
FFE-Solutions GmbH · Kolberger Straße 13 · 24589 Nortorf
Telephone +49 43 92 / 91 77 - 0 · Fax +49 43 92 / 5864 · [email protected]
R E F E R E N C E S BIOGAS PLANT SØNDERJYSK, DKSønderjysk Biogas Bevtovt A/S, Vojens, Denmark
Year of commissioning 2016*
Gas yield 5,000 Nm³/h
Digester volume 6 x 6,100 m³
Post-digester volume 4 x 6,800 m³
Substrates:
Cattle manure 225,000 t/a
Pig slurry 200,000 t/a
Straw 50,000 t/a
Sugar beet and pulp 50,000 t/a
Maize 15,000 t/a
Dry dung 10,000 t/a
Special Features
• Gas upgrading
• Thermophilic process (55°C) as
pasteurisation method
• Heat recovery from low temperature
return flow from gas upgrading facility
17
www.farmatic.comwww.farmatic.com
FFE-Solutions GmbH · Kolberger Straße 13 · 24589 Nortorf
Telephone +49 43 92 / 91 77 - 0 · Fax +49 43 92 / 5864 · [email protected]
R E F E R E N C E S BIOGAS PLANT SØNDERJYSK, DKSønderjysk Biogas Bevtovt A/S, Vojens, Denmark
Year of commissioning 2016*
Gas yield 5,000 Nm³/h
Digester volume 6 x 6,100 m³
Post-digester volume 4 x 6,800 m³
Substrates:
Cattle manure 225,000 t/a
Pig slurry 200,000 t/a
Straw 50,000 t/a
Sugar beet and pulp 50,000 t/a
Maize 15,000 t/a
Dry dung 10,000 t/a
Special Features
• Gas upgrading
• Thermophilic process (55°C) as
pasteurisation method
• Heat recovery from low temperature
return flow from gas upgrading facility
18
www.farmatic.comwww.farmatic.com 19
Thank you!
FFE-Solutions GmbH Kolberger Straße 13 · 24589 Nortorf
phone +49 43 92 / 91 77 - 0 · fax +49 43 92 / 5864 · [email protected]
Helmut MucheInternational Sales
[email protected]+ 49 176 11 2222 02 (Germany)+ 66 917160021 (Thailand)