Mm Zg538 L6 Part2

download Mm Zg538 L6 Part2

of 51

Transcript of Mm Zg538 L6 Part2

  • 8/12/2019 Mm Zg538 L6 Part2

    1/51

    MMZG 538 Toyota Production

    System

    Rajiv Gupta

    BITS PilaniFebruary 2014

    Session 6

  • 8/12/2019 Mm Zg538 L6 Part2

    2/51

    Module 1 Recap of Session 5

    Module 2 Pull Production

    Rules of Kanban Module 3 Small Batch Production

    Level Production

    Module 4

    Set-up reduction Jidoka

    Module 5 Summary and wrap up

    2

  • 8/12/2019 Mm Zg538 L6 Part2

    3/51

    Session 6

    Begin Module 1

    Recap of Session 5

    3

  • 8/12/2019 Mm Zg538 L6 Part2

    4/51

    Recap

    Machine cell design involves the determination of

    the number of workers and the assignment of

    workers to machines in the cell

    Machine cell design cannot be done unless weprepare for it, i.e., we must ensure the proper

    systems are in place such as setup reduction, TPM,

    quality, etc.

    Lean tools are what people attempt to apply whenthey think of TPS. Applying one or two tools in

    isolation without full management commitment has a

    good chance of failure

    4

  • 8/12/2019 Mm Zg538 L6 Part2

    5/51

    Recap

    Inventory is a symptom of other problems in the

    system. We use inventory to cover for inefficiencies

    and problems. Carrying inventory takes the focus

    away from solving the problems so that they do notrecur

    Inventory reduction should not be attempted without

    working on the root causes for carrying inventory.

    Several failed attempts at the reducing inventoryalone can be attributed to this approach.

    5

  • 8/12/2019 Mm Zg538 L6 Part2

    6/51

    Session 6

    End of module 1

    6

  • 8/12/2019 Mm Zg538 L6 Part2

    7/51

    Session 6

    Begin Module 2

    Pull Sceduling

    Types of Kanban

    Rules of Kanban

    7

  • 8/12/2019 Mm Zg538 L6 Part2

    8/51

    Pull Production

    In Push scheduling each work center gets

    individual schedule based on a forecast

    Push scheduling is typically found with

    systems such as MRP/ERP etc.

    When there are changes in the requirements,

    the system has no means to self correct

    The result is confusion, excess inventory andlong lead times

    8

  • 8/12/2019 Mm Zg538 L6 Part2

    9/51

    Pull Production

    In Pull scheduling, only one work center

    gets scheduled

    It pulls material from its upstream

    operation

    This continues through all upstream

    operations

    The normal approach is known as Kan

    Ban

    Borrowed from the grocery industry9

  • 8/12/2019 Mm Zg538 L6 Part2

    10/51

    Types of Kanban

    Kanban

    Production

    Instruction

    PartsWithdrawal

    In-process kanban for schedulingflow processes

    Signal kanban for scheduling

    batch processes

    Interprocess kanban for

    internal purposes

    Supplier kanban for

    external purposes

    10

  • 8/12/2019 Mm Zg538 L6 Part2

    11/51

    Types of Kanban

    In-process kanban used to conveyinstruction to produce small quantities (apitch) to an upstream process

    Signal kanban used to convey instructionsto produce a batch to an upstream process.Used when production is in batches due tohigh set ups

    Inter-process kanban used to signal theneed to withdraw parts from a storage areaand convey them to a downstreamworkstation in the same facility

    11

  • 8/12/2019 Mm Zg538 L6 Part2

    12/51

    Types of Kanban (contd.)

    Supplier kanban used to signal the need

    to withdraw parts from an external supplier

    to be conveyed to the plant storage or

    marketplace

    12

  • 8/12/2019 Mm Zg538 L6 Part2

    13/51

    Kanban Rules

    Rule 1

    The downstream process should withdraw the

    necessary products from the upstream processes

    in the necessary quantities at the necessary pointin time

    Any withdrawal without a Kanban should be prohibited

    Any withdrawal which is greater than the number of

    Kanbans should be prohibited

    13

  • 8/12/2019 Mm Zg538 L6 Part2

    14/51

    Kanban Rules

    Rule 2

    The upstream process should produce its

    products in the quantities withdrawn by the

    downstream process Production greater than the number of Kanbans should

    not be permitted

    When several parts are to be produced, the production

    should follow the original sequence in which eachKanban has been delivered.

    14

  • 8/12/2019 Mm Zg538 L6 Part2

    15/51

    Kanban Rules

    Rule 3

    No items are made or transported without a

    Kanban (Prevent excess production and

    transportation) Rule 4

    Always attach a Kanban to the goods (It serves

    as a work order

    Rule 5

    Defective products are not sent to subsequent

    process

    15

  • 8/12/2019 Mm Zg538 L6 Part2

    16/51

    Kanban Rules

    Rule 6

    Reducing the number of Kanbans increases their

    sensitivity

    Kanbans should be used to adapt to small fluctuationsin demand

    Reducing Kanbans reveal existing problems

    16

  • 8/12/2019 Mm Zg538 L6 Part2

    17/51

    Two Kinds of Conveyance

    There are two kinds of conveyance in the kanban system:

    Fixed time and variable quantity conveyance. Fixed quantity and variable time conveyance.

    Fixed time conveyance is preferable when processes aredisconnected and conveyance distances are long.

    Easy to follow or "milk run" routes can be readily set up.

    External suppliers almost always use this form of conveyance. Fixed quantity conveyance is preferable when processes are

    connected (e.g., an assembly line) and conveyance distancesare short, or when lot sizes are large (e.g., stamping).

    Toyota uses fixed quantity conveyance for stamped parts andfor large injection-molded parts such as instrument panels.

    17

  • 8/12/2019 Mm Zg538 L6 Part2

    18/51

    Session 6

    End of module 2

    18

  • 8/12/2019 Mm Zg538 L6 Part2

    19/51

  • 8/12/2019 Mm Zg538 L6 Part2

    20/51

    Small Batch Production

    Batch sizes are a result of long set-up times,

    long handling distances, and a focus on unit

    costs

    As long as product variety was not too much,production in larger batches did not affect

    responsiveness of production, e.g., Henry Ford

    and his model T

    However, as product variety proliferated, large

    batch production led to various problems and

    inefficiencies in the system

    20

  • 8/12/2019 Mm Zg538 L6 Part2

    21/51

    Small Batch Production

    There are two types of batches sizes; production

    and transfer batches

    A production batch is the quantity that is produced at

    one time A transfer batch is the quantity that is moved between

    processes at one time

    Large batches result in larger inventory

    Larger batches result in poor quality feedback

    Larger batches result in less responsiveness to

    the customer

    21

  • 8/12/2019 Mm Zg538 L6 Part2

    22/51

    Batch Sizes and Inventory

    22

  • 8/12/2019 Mm Zg538 L6 Part2

    23/51

    Batch Sizes and Lead Times

    Station 1

    Station 2

    Station 1

    Station 2

    23

  • 8/12/2019 Mm Zg538 L6 Part2

    24/51

    Batch Sizes and Flexibility

    Workcenter

    Workcenter

    24

  • 8/12/2019 Mm Zg538 L6 Part2

    25/51

    Level Production Tied to Customer

    Demand

    Takt time = No. of working seconds in a day/Demand per day

    This establishes a rhythm for the entire supply chain,through the plant and to the suppliers

    Example: Demand for a product is 600 pieces per day.

    Assuming a single shift operation, 450 working minutesper shift or 27000 secs per shift.

    Takt time = 27000/600 = 45 seconds

    i.e., the line should be running at 45 secs/piece

    25

  • 8/12/2019 Mm Zg538 L6 Part2

    26/51

    Level Production Tied to Customer

    Demand

    The takt time represents the rate of demand. It is sometimes

    confused with the machine cycle time. This is incorrect.

    Producing at the rate of demand ensures no inventory buildup

    while meeting demand.

    The suppliers rate of production should also be matched

    to the takt rate. Then the entire supply chain will run in sync.

    The actual demand may vary somewhat from day to day, but

    this is absorbed by some inventory of finished product.

    26

  • 8/12/2019 Mm Zg538 L6 Part2

    27/51

    Level Production Tied to Customer

    Demand

    Assume there are 3 products being produced. The deman

    per week is 500, 200 and 100. There are several ways in

    which this can be accomplished.

    500 200 100

    This is not leveled production. The production variesfrom day to day.

    27

  • 8/12/2019 Mm Zg538 L6 Part2

    28/51

  • 8/12/2019 Mm Zg538 L6 Part2

    29/51

    Level Production Tied to Customer

    Demand

    The ultimate schedule would produce the 3 products in sets

    of 5, 2, 1. This is called the pitch.

    This method of production leveling is called Heijunka.

    29

  • 8/12/2019 Mm Zg538 L6 Part2

    30/51

    Session 6

    End of module 3

    30

  • 8/12/2019 Mm Zg538 L6 Part2

    31/51

    Session 6

    Begin Module 4

    Setup reduction

    Autonomation/Jidoka

    31

  • 8/12/2019 Mm Zg538 L6 Part2

    32/51

    Set Up Reduction

    Traditional inventory models, such as EOQ, assume

    that the set up cost/time is a fixed quantity.

    Some large automated lines and presses can take

    more than a shift to change over from one product toanother.

    With such long set up times, the batch sizes had to

    be large. Also, it was impractical to do much load

    leveling. Toyota challenged the assumption of fixed setup

    times

    32

  • 8/12/2019 Mm Zg538 L6 Part2

    33/51

    Set Up Reduction

    Setup Time Die retrieval from storage

    Tools readied

    Setup person scheduled

    Material handling equipment scheduled

    Removal of previous die

    Installation of new die

    Adjustment

    Tryout of new die

    Moving old die to storage

    Time elapsed from good piece to good piece

    33

  • 8/12/2019 Mm Zg538 L6 Part2

    34/51

    Set Up Reduction

    Problems with existing method of setup

    Scheduling not done in time resulting in long

    waiting times.

    Non standard procedures. Insufficient training.

    Non standard equipment and dies of different

    sizes and heights. Searching time.

    Different shut heights require longeradjustment.

    Tools, nuts, bolts missing.

    Excessive adjustment.34

  • 8/12/2019 Mm Zg538 L6 Part2

    35/51

    Set Up Reduction

    Steps in set up reduction (SMED) Determine existing setup procedure

    Divide activities into internal elements and

    external elements Internal elements are those that require the machine tobe stopped

    External elements can be performed while the machineis running

    Try to convert internal elements to externalelements

    Try to improve external elements

    35

  • 8/12/2019 Mm Zg538 L6 Part2

    36/51

  • 8/12/2019 Mm Zg538 L6 Part2

    37/51

    Jidoka

    The normal approach when a machine

    breaks down or if there is a quality problem isto find a quick solution so that the line does

    not stop.

    This thinking stems from the numbersmentality that pervades the western

    approach to manufacturing (the R orientation)

    The focus on keeping production going

    prevents the problem from being fully

    recognized and addressed. The result is that

    the problem will recur in the future

    37

  • 8/12/2019 Mm Zg538 L6 Part2

    38/51

    Jidoka

    Problems can occur in production due to a

    variety of reasons:

    Human error

    Lack of proper training/instructions

    Lack of proper tools

    Quality of incoming parts

    Poor design of task

    Machine problems

    Problems in the material flow

    38

  • 8/12/2019 Mm Zg538 L6 Part2

    39/51

    Jidoka

    Human error

    Sometimes the worker on the shop floor can make

    mistakes as no one is perfect. This may be due to

    carelessness, fatigue, or may be just a random

    occurrence

    Lack of proper training/instructions

    In several plants, the only real training a worker

    receives is brief instructions and then he/she is sent

    to the line to work

    This leads to variation in the way in which each task is

    completed.

    39

  • 8/12/2019 Mm Zg538 L6 Part2

    40/51

    Jidoka

    Lack of proper tools

    Due to lack of standardization and work

    structuring, or poor 5s/housekeeping, the right

    tools are not available at the workplace, whichrequires the worker to improvise. This can and

    does lead to mistakes

    Quality of incoming parts

    Poor quality of incoming parts can lead to

    machining and other production problems over

    which the worker has no control

    40

  • 8/12/2019 Mm Zg538 L6 Part2

    41/51

    Jidoka

    Poor design of task

    Due to the result orientation in several

    western production plants, the focus is to

    maximize production without the concern forhow this is to be achieved.

    This leads to shortcuts and pressure on the

    supervisors and workers

    This results in little effort in the design of tasks

    to ensure that it can be consistently

    completed by the worker in the time allotted

    41

  • 8/12/2019 Mm Zg538 L6 Part2

    42/51

    Jidoka

    Machine problems

    If a machine breaks down, instead of ensuring

    that proper maintenance be performed, the

    focus is to get the machine up and running asfast as possible to minimize the loss in

    production

    The lack of focus on maintenance results in

    subsequent breakdowns in the machine and

    the same cycle repeats itself

    42

  • 8/12/2019 Mm Zg538 L6 Part2

    43/51

    Jidoka

    Problems in the material flow

    When production flow is not smooth, there

    may be problems due to non-availability of

    parts at a machine When there is a part shortage, attempts are

    made to address the problem as fast as

    possible, without looking at the root cause,

    which may be in the material flow design

    The problem will likely recur and the same

    cycle repeated43

  • 8/12/2019 Mm Zg538 L6 Part2

    44/51

    Jidoka

    The focus in Toyota is first to spend time in the

    proper design of the system

    However, in order to ensure that the system is

    operating as planned, any time there is a systembreakdown, instead of taking shortcuts, the

    problem is analyzed to ensure that it does not

    recur

    This may lead to a short term stoppage in work,but eliminates stoppages in the long term

    44

    Wh Jid k B

  • 8/12/2019 Mm Zg538 L6 Part2

    45/51

    Why Jidoka Becomes

    Necessary The focus on numbers

    One thing that a plant manager or a supervisor does

    not want is a stoppage in production. The machine

    loss time is measured by corporate and few

    manufacturing personnel will risk their career by

    permitting lines to stop

    Fear of blame

    When a problem occurs, the normal tendency is toask, who is responsible? rather thanwhy did this

    problem occur? So people try to hide problems to

    prevent being found out

    45

  • 8/12/2019 Mm Zg538 L6 Part2

    46/51

    Jidoka

    The Japanese approach is to bring problems to

    the surface, analyze the problem going to the

    root cause, applying countermeasures and then

    monitoring to ensure that the problem does notrecur

    The production capacity in a Japanese plant

    takes into account a certain number of andon

    pulls in a shift. If the number of andon pulls isless than planned, the management feels that

    either people are hiding problems or not pushing

    the system to its limits46

  • 8/12/2019 Mm Zg538 L6 Part2

    47/51

    Session 6

    End of module 4

    47

  • 8/12/2019 Mm Zg538 L6 Part2

    48/51

    Session 6

    Begin Module 5

    Summary and wrap up

    48

  • 8/12/2019 Mm Zg538 L6 Part2

    49/51

  • 8/12/2019 Mm Zg538 L6 Part2

    50/51

    Summary

    Set-up times can be reduced drastically. Some

    of the changes require little or no investments.

    Others may require changes to the equipment

    Jidoka requires that we shut down a processwhen a problem occurs and take corrective

    action to prevent the problem from recurring

    If the line stops once and the focus is on

    countermeasures preventing the problem, thenthe loss of production is more than offset by the

    elimination of future stoppages

    50

  • 8/12/2019 Mm Zg538 L6 Part2

    51/51

    End Module 5

    Summary and wrap up

    51