Mm Zg538 L6 Part2
-
Upload
vignesh-vaitheeswaran -
Category
Documents
-
view
218 -
download
0
Transcript of Mm Zg538 L6 Part2
-
8/12/2019 Mm Zg538 L6 Part2
1/51
MMZG 538 Toyota Production
System
Rajiv Gupta
BITS PilaniFebruary 2014
Session 6
-
8/12/2019 Mm Zg538 L6 Part2
2/51
Module 1 Recap of Session 5
Module 2 Pull Production
Rules of Kanban Module 3 Small Batch Production
Level Production
Module 4
Set-up reduction Jidoka
Module 5 Summary and wrap up
2
-
8/12/2019 Mm Zg538 L6 Part2
3/51
Session 6
Begin Module 1
Recap of Session 5
3
-
8/12/2019 Mm Zg538 L6 Part2
4/51
Recap
Machine cell design involves the determination of
the number of workers and the assignment of
workers to machines in the cell
Machine cell design cannot be done unless weprepare for it, i.e., we must ensure the proper
systems are in place such as setup reduction, TPM,
quality, etc.
Lean tools are what people attempt to apply whenthey think of TPS. Applying one or two tools in
isolation without full management commitment has a
good chance of failure
4
-
8/12/2019 Mm Zg538 L6 Part2
5/51
Recap
Inventory is a symptom of other problems in the
system. We use inventory to cover for inefficiencies
and problems. Carrying inventory takes the focus
away from solving the problems so that they do notrecur
Inventory reduction should not be attempted without
working on the root causes for carrying inventory.
Several failed attempts at the reducing inventoryalone can be attributed to this approach.
5
-
8/12/2019 Mm Zg538 L6 Part2
6/51
Session 6
End of module 1
6
-
8/12/2019 Mm Zg538 L6 Part2
7/51
Session 6
Begin Module 2
Pull Sceduling
Types of Kanban
Rules of Kanban
7
-
8/12/2019 Mm Zg538 L6 Part2
8/51
Pull Production
In Push scheduling each work center gets
individual schedule based on a forecast
Push scheduling is typically found with
systems such as MRP/ERP etc.
When there are changes in the requirements,
the system has no means to self correct
The result is confusion, excess inventory andlong lead times
8
-
8/12/2019 Mm Zg538 L6 Part2
9/51
Pull Production
In Pull scheduling, only one work center
gets scheduled
It pulls material from its upstream
operation
This continues through all upstream
operations
The normal approach is known as Kan
Ban
Borrowed from the grocery industry9
-
8/12/2019 Mm Zg538 L6 Part2
10/51
Types of Kanban
Kanban
Production
Instruction
PartsWithdrawal
In-process kanban for schedulingflow processes
Signal kanban for scheduling
batch processes
Interprocess kanban for
internal purposes
Supplier kanban for
external purposes
10
-
8/12/2019 Mm Zg538 L6 Part2
11/51
Types of Kanban
In-process kanban used to conveyinstruction to produce small quantities (apitch) to an upstream process
Signal kanban used to convey instructionsto produce a batch to an upstream process.Used when production is in batches due tohigh set ups
Inter-process kanban used to signal theneed to withdraw parts from a storage areaand convey them to a downstreamworkstation in the same facility
11
-
8/12/2019 Mm Zg538 L6 Part2
12/51
Types of Kanban (contd.)
Supplier kanban used to signal the need
to withdraw parts from an external supplier
to be conveyed to the plant storage or
marketplace
12
-
8/12/2019 Mm Zg538 L6 Part2
13/51
Kanban Rules
Rule 1
The downstream process should withdraw the
necessary products from the upstream processes
in the necessary quantities at the necessary pointin time
Any withdrawal without a Kanban should be prohibited
Any withdrawal which is greater than the number of
Kanbans should be prohibited
13
-
8/12/2019 Mm Zg538 L6 Part2
14/51
Kanban Rules
Rule 2
The upstream process should produce its
products in the quantities withdrawn by the
downstream process Production greater than the number of Kanbans should
not be permitted
When several parts are to be produced, the production
should follow the original sequence in which eachKanban has been delivered.
14
-
8/12/2019 Mm Zg538 L6 Part2
15/51
Kanban Rules
Rule 3
No items are made or transported without a
Kanban (Prevent excess production and
transportation) Rule 4
Always attach a Kanban to the goods (It serves
as a work order
Rule 5
Defective products are not sent to subsequent
process
15
-
8/12/2019 Mm Zg538 L6 Part2
16/51
Kanban Rules
Rule 6
Reducing the number of Kanbans increases their
sensitivity
Kanbans should be used to adapt to small fluctuationsin demand
Reducing Kanbans reveal existing problems
16
-
8/12/2019 Mm Zg538 L6 Part2
17/51
Two Kinds of Conveyance
There are two kinds of conveyance in the kanban system:
Fixed time and variable quantity conveyance. Fixed quantity and variable time conveyance.
Fixed time conveyance is preferable when processes aredisconnected and conveyance distances are long.
Easy to follow or "milk run" routes can be readily set up.
External suppliers almost always use this form of conveyance. Fixed quantity conveyance is preferable when processes are
connected (e.g., an assembly line) and conveyance distancesare short, or when lot sizes are large (e.g., stamping).
Toyota uses fixed quantity conveyance for stamped parts andfor large injection-molded parts such as instrument panels.
17
-
8/12/2019 Mm Zg538 L6 Part2
18/51
Session 6
End of module 2
18
-
8/12/2019 Mm Zg538 L6 Part2
19/51
-
8/12/2019 Mm Zg538 L6 Part2
20/51
Small Batch Production
Batch sizes are a result of long set-up times,
long handling distances, and a focus on unit
costs
As long as product variety was not too much,production in larger batches did not affect
responsiveness of production, e.g., Henry Ford
and his model T
However, as product variety proliferated, large
batch production led to various problems and
inefficiencies in the system
20
-
8/12/2019 Mm Zg538 L6 Part2
21/51
Small Batch Production
There are two types of batches sizes; production
and transfer batches
A production batch is the quantity that is produced at
one time A transfer batch is the quantity that is moved between
processes at one time
Large batches result in larger inventory
Larger batches result in poor quality feedback
Larger batches result in less responsiveness to
the customer
21
-
8/12/2019 Mm Zg538 L6 Part2
22/51
Batch Sizes and Inventory
22
-
8/12/2019 Mm Zg538 L6 Part2
23/51
Batch Sizes and Lead Times
Station 1
Station 2
Station 1
Station 2
23
-
8/12/2019 Mm Zg538 L6 Part2
24/51
Batch Sizes and Flexibility
Workcenter
Workcenter
24
-
8/12/2019 Mm Zg538 L6 Part2
25/51
Level Production Tied to Customer
Demand
Takt time = No. of working seconds in a day/Demand per day
This establishes a rhythm for the entire supply chain,through the plant and to the suppliers
Example: Demand for a product is 600 pieces per day.
Assuming a single shift operation, 450 working minutesper shift or 27000 secs per shift.
Takt time = 27000/600 = 45 seconds
i.e., the line should be running at 45 secs/piece
25
-
8/12/2019 Mm Zg538 L6 Part2
26/51
Level Production Tied to Customer
Demand
The takt time represents the rate of demand. It is sometimes
confused with the machine cycle time. This is incorrect.
Producing at the rate of demand ensures no inventory buildup
while meeting demand.
The suppliers rate of production should also be matched
to the takt rate. Then the entire supply chain will run in sync.
The actual demand may vary somewhat from day to day, but
this is absorbed by some inventory of finished product.
26
-
8/12/2019 Mm Zg538 L6 Part2
27/51
Level Production Tied to Customer
Demand
Assume there are 3 products being produced. The deman
per week is 500, 200 and 100. There are several ways in
which this can be accomplished.
500 200 100
This is not leveled production. The production variesfrom day to day.
27
-
8/12/2019 Mm Zg538 L6 Part2
28/51
-
8/12/2019 Mm Zg538 L6 Part2
29/51
Level Production Tied to Customer
Demand
The ultimate schedule would produce the 3 products in sets
of 5, 2, 1. This is called the pitch.
This method of production leveling is called Heijunka.
29
-
8/12/2019 Mm Zg538 L6 Part2
30/51
Session 6
End of module 3
30
-
8/12/2019 Mm Zg538 L6 Part2
31/51
Session 6
Begin Module 4
Setup reduction
Autonomation/Jidoka
31
-
8/12/2019 Mm Zg538 L6 Part2
32/51
Set Up Reduction
Traditional inventory models, such as EOQ, assume
that the set up cost/time is a fixed quantity.
Some large automated lines and presses can take
more than a shift to change over from one product toanother.
With such long set up times, the batch sizes had to
be large. Also, it was impractical to do much load
leveling. Toyota challenged the assumption of fixed setup
times
32
-
8/12/2019 Mm Zg538 L6 Part2
33/51
Set Up Reduction
Setup Time Die retrieval from storage
Tools readied
Setup person scheduled
Material handling equipment scheduled
Removal of previous die
Installation of new die
Adjustment
Tryout of new die
Moving old die to storage
Time elapsed from good piece to good piece
33
-
8/12/2019 Mm Zg538 L6 Part2
34/51
Set Up Reduction
Problems with existing method of setup
Scheduling not done in time resulting in long
waiting times.
Non standard procedures. Insufficient training.
Non standard equipment and dies of different
sizes and heights. Searching time.
Different shut heights require longeradjustment.
Tools, nuts, bolts missing.
Excessive adjustment.34
-
8/12/2019 Mm Zg538 L6 Part2
35/51
Set Up Reduction
Steps in set up reduction (SMED) Determine existing setup procedure
Divide activities into internal elements and
external elements Internal elements are those that require the machine tobe stopped
External elements can be performed while the machineis running
Try to convert internal elements to externalelements
Try to improve external elements
35
-
8/12/2019 Mm Zg538 L6 Part2
36/51
-
8/12/2019 Mm Zg538 L6 Part2
37/51
Jidoka
The normal approach when a machine
breaks down or if there is a quality problem isto find a quick solution so that the line does
not stop.
This thinking stems from the numbersmentality that pervades the western
approach to manufacturing (the R orientation)
The focus on keeping production going
prevents the problem from being fully
recognized and addressed. The result is that
the problem will recur in the future
37
-
8/12/2019 Mm Zg538 L6 Part2
38/51
Jidoka
Problems can occur in production due to a
variety of reasons:
Human error
Lack of proper training/instructions
Lack of proper tools
Quality of incoming parts
Poor design of task
Machine problems
Problems in the material flow
38
-
8/12/2019 Mm Zg538 L6 Part2
39/51
Jidoka
Human error
Sometimes the worker on the shop floor can make
mistakes as no one is perfect. This may be due to
carelessness, fatigue, or may be just a random
occurrence
Lack of proper training/instructions
In several plants, the only real training a worker
receives is brief instructions and then he/she is sent
to the line to work
This leads to variation in the way in which each task is
completed.
39
-
8/12/2019 Mm Zg538 L6 Part2
40/51
Jidoka
Lack of proper tools
Due to lack of standardization and work
structuring, or poor 5s/housekeeping, the right
tools are not available at the workplace, whichrequires the worker to improvise. This can and
does lead to mistakes
Quality of incoming parts
Poor quality of incoming parts can lead to
machining and other production problems over
which the worker has no control
40
-
8/12/2019 Mm Zg538 L6 Part2
41/51
Jidoka
Poor design of task
Due to the result orientation in several
western production plants, the focus is to
maximize production without the concern forhow this is to be achieved.
This leads to shortcuts and pressure on the
supervisors and workers
This results in little effort in the design of tasks
to ensure that it can be consistently
completed by the worker in the time allotted
41
-
8/12/2019 Mm Zg538 L6 Part2
42/51
Jidoka
Machine problems
If a machine breaks down, instead of ensuring
that proper maintenance be performed, the
focus is to get the machine up and running asfast as possible to minimize the loss in
production
The lack of focus on maintenance results in
subsequent breakdowns in the machine and
the same cycle repeats itself
42
-
8/12/2019 Mm Zg538 L6 Part2
43/51
Jidoka
Problems in the material flow
When production flow is not smooth, there
may be problems due to non-availability of
parts at a machine When there is a part shortage, attempts are
made to address the problem as fast as
possible, without looking at the root cause,
which may be in the material flow design
The problem will likely recur and the same
cycle repeated43
-
8/12/2019 Mm Zg538 L6 Part2
44/51
Jidoka
The focus in Toyota is first to spend time in the
proper design of the system
However, in order to ensure that the system is
operating as planned, any time there is a systembreakdown, instead of taking shortcuts, the
problem is analyzed to ensure that it does not
recur
This may lead to a short term stoppage in work,but eliminates stoppages in the long term
44
Wh Jid k B
-
8/12/2019 Mm Zg538 L6 Part2
45/51
Why Jidoka Becomes
Necessary The focus on numbers
One thing that a plant manager or a supervisor does
not want is a stoppage in production. The machine
loss time is measured by corporate and few
manufacturing personnel will risk their career by
permitting lines to stop
Fear of blame
When a problem occurs, the normal tendency is toask, who is responsible? rather thanwhy did this
problem occur? So people try to hide problems to
prevent being found out
45
-
8/12/2019 Mm Zg538 L6 Part2
46/51
Jidoka
The Japanese approach is to bring problems to
the surface, analyze the problem going to the
root cause, applying countermeasures and then
monitoring to ensure that the problem does notrecur
The production capacity in a Japanese plant
takes into account a certain number of andon
pulls in a shift. If the number of andon pulls isless than planned, the management feels that
either people are hiding problems or not pushing
the system to its limits46
-
8/12/2019 Mm Zg538 L6 Part2
47/51
Session 6
End of module 4
47
-
8/12/2019 Mm Zg538 L6 Part2
48/51
Session 6
Begin Module 5
Summary and wrap up
48
-
8/12/2019 Mm Zg538 L6 Part2
49/51
-
8/12/2019 Mm Zg538 L6 Part2
50/51
Summary
Set-up times can be reduced drastically. Some
of the changes require little or no investments.
Others may require changes to the equipment
Jidoka requires that we shut down a processwhen a problem occurs and take corrective
action to prevent the problem from recurring
If the line stops once and the focus is on
countermeasures preventing the problem, thenthe loss of production is more than offset by the
elimination of future stoppages
50
-
8/12/2019 Mm Zg538 L6 Part2
51/51
End Module 5
Summary and wrap up
51