MIT WestGate Bridge

download MIT WestGate Bridge

of 96

Transcript of MIT WestGate Bridge

  • 8/11/2019 MIT WestGate Bridge

    1/96

    Lessons Learned in the Design and Erection of Box Girder Bridges fromthe West Gate Collapse

    by

    Alia Christine Burton

    S.B., Civil EngineeringMassachusettsInstitute of Technology, 2005

    Submitted to the Departmentof Civil and EnvironmentalEngineering inPartialFulfillmentof the Requirements for the Degree of

    Master of Engineeringin Civil and EnvironmentalEngineeringat the

    MassachusettsInstitute of Technology

    June 2007

    C 2007 Alia ChristineBurton. All rights reserved.

    The author herebygrants to MIT permissionto reproduceand to distributepubliclypaper and electroniccopies of this

    thesis documentin whole or in part in any mediumnowknown orhereafter created.

    Signatureof Author ......... ............... , .. .. .v. ...................................Department of Civil andEnvironmentalEngineering

    May 21, 2007

    Certified by ................ ................... .................. .......JeromeJ. onnor

    rofessor of Civil and EnvironmentalEngineeringThesis Supervisor

    Accepted by .......... ............................................... .......................- DanieleVeneziano

    Chairman, DepartmentalCommitteefor Graduate Students

    ARCHIVES

    MASSACHUSETTS INSTITUTEOF TECHNOLOGY

    JUN 0 7 2007

    LIBRARIES

  • 8/11/2019 MIT WestGate Bridge

    2/96

  • 8/11/2019 MIT WestGate Bridge

    3/96

    Lessons Learned in the Design and Erection of Box Girder Bridges fromthe West Gate Collapse

    by

    Alia Christine Burton

    S.B., Civil EngineeringMassachusettsInstitute of Technology, 2005

    Submitted to the Departmentof Civil andEnvironmentalEngineeringon May 21st 2007 in Partial Fulfillmentof theRequirements for the Degree of Master of Engineeringin

    Civil and Environmental Engineering

    ABSTRACT

    The West Gate Bridge, intendedto span the Yarra Riverin Australia, collapsedduring itsthird year of construction in 1970. Investigationinto the project revealed numerousissuesin the bridge's design and construction.The West Gate Bridge is one of a numberof boxgirder bridgesbuilt during the mid 2 0 th century, and was oneof four to fail in a three yearperiod.

    An overview of the design and erection issues is presented, particularlythose dealingwith thin elementsin compression.A comparisonof momentsand stresses resulting fromthe use of concrete blocks and jacks to reduce the camber difference encounteredon span10-11 shows that the latter methodwould have been preferable.

    The failure of three other box girder bridges between1969 and 1971, and the requiredstrengthening of dozens of others, reveal the lack of understanding of the slendercompressiveelementspresent in such structures.

    A brief literature review presentsthe bucklingand deformation modes found instiffenedplates under compressive loading, showing the developmentof understanding of thesesystems from papers written or published in 1997, 2001, 2004 and 2006- over threedecades after the West Gate collapse.

    Criteria by AASHTO andby B. H. Choi and C. H. Yoo for the minimum moment ofinertia of longitudinal andtransverse stiffeners of box girders are presented. The resultingvalues are compared to the moment of inertia of sections used to strengthen the WestGate Bridge after the collapse of a similar bridge. Thiscomparison shows that therequirementsare quite sensitiveto scale and can provide inconsistent requirements forstiffness. Thus, thereis currently a lack of guidance andregulation from codes for thedesign of wider single-cell boxgirders. The complex andnon-linear nature of the slenderelements in compression used in box girders does not allow the extrapolationof simplerrules developed for the design of smaller bridges.Despite the complex behavior of box

  • 8/11/2019 MIT WestGate Bridge

    4/96

  • 8/11/2019 MIT WestGate Bridge

    5/96

    girders, they offer a numberof advantagesand further researchis needed to improve theiranalysis,design, construction,repair and maintenance.

    Thesis Supervisor: JeromeJ. ConnorTitle: Professor of Civil and Environmental Engineering

  • 8/11/2019 MIT WestGate Bridge

    6/96

  • 8/11/2019 MIT WestGate Bridge

    7/96

    Acknowledgements

    I wish toacknowledgeProfessor Connor for his guidancethroughout the program and mymother, who held my hand three hundredmiles away.

  • 8/11/2019 MIT WestGate Bridge

    8/96

    Table of Contents

    1. INTRODUCTION ....................................... 112. BACKGROUND ............................................................................................................... 12

    2.1. INITIAL DESIGN .............................................................. 122.2. CONTRACTUAL RELATIONSHIPS........................... ......................... 162.3. CONSTRUCTION ............................................ ................. 172.4. THE COLLAPSE ............................................................... 18

    3. ADVANTAGES AND DISADVANTAGES OF BOX GIRDERS ....................................... 24

    3.1. A DVANTAG ES .................................................................................... 243.2. D ISA DVANTA GES ....................................................................................................................... 25

    4. WEST GATE BRIDGE ISSUES .................................................. 26

    4 .1. D ESIG N .................................................................................................. .......................... ... 264 .2. E REC T IO N ............................................................................................................... 354.3. COMPARISON OF USE OF CONCRETE KENTLEDGES WITH JACKING ..................................... 37

    5. OTHER FAILURES ................................................................................................................... 43

    5.1. FOURTHDANUBE BRIDGE.................................................. 435.2. M ILFORD H AVEN B RIDGE........................................................................ ............................. 445.3. RHINE BRIDGEIN KOBLENZ ....................................... ........................... 475.4. IMPACTS ON OTHER BRIDGES ................... ................................. 50

    6. BEHAVIOR OF STIFFENED PANELS .................................................................................. 52

    6.1. A CONTRIBUTION TO THESTABILITY OFSTIFFENED PLATES UNDER UNIFORM COMPRESSION(1997) 526.2. STIFFENED STEEL PLATES UNDER UNIAXIAL COMPRESSION(2001)............................... . 54

    6.3. BUCKLING OF STIFFENED PLATES WITH BULB FLAT FLANGES (2004) ................................. 567. STIFFNESS REQUIREMENTS FOR STIFFENERS OF COM PRESSION PANELS.......... 59

    7.1. RESEARCHBY CHOI AND YOO (2006) ................................... ........ ....................... 597.2. COMPARISON OF STIFFENER REQUIREMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66

    8. RECENT EXAMPLE OF A SUCCESSFUL BOX GIRDER BRIDGE................................ 69

    9. CONCLUSION .................................................. 71

    10. REFER EN CES ............................................................................................................................. 73

    11. APPENDICES ................................................. 76

    8

  • 8/11/2019 MIT WestGate Bridge

    9/96

    List of Figures

    FIGURE 1: PLAN VIEW ................................................ 13FIGURE 2: ELEVATION, PLAN ANDSECTIONVIEWS ................................................................ .. 14FIGURE 3: PHOTOGRAPHOF BRIDGE MODEL.................................................................... 14

    FIGURE 4: ASSEMBLY DIAGRAM................................................................. 15FIGURE 5: ELEVATION AND PLAN OF COLLAPSEDSPAN .......................................................... .. 19FIGURE 6: SHORTLY AFTER COLLAPSE.......................................................................... ......................... 20FIGURE 7: IMPACT OF COLLAPSEFORCED A STEEL BEAM THROUGH CONCRETEOF DECK ........................... 20FIGURE 8: COLLAPSEDDECK VIEWED FROM NEIGHBORING PIER. . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . 21FIGURE 9: CLOSE-UPOF SHATTERED BOX STRUCTUREOF DECK .............................................................. .. 21FIGURE 10: D YNAMICS OF FAILURE................................................................................ .......................... 22FIGURE 11: SKETCHOF C O LL A PS E. . . . . . . . . . . . .. . . . . . .. . . . . . .. . . . . . .. . . . . . .. . . . . .......................... 23FIGURE 12: SIDEVIEW OFBRITANNIA BRIDGE.................................................... 24FIGURE 13: CROSS-SECTIONOF BRITANNIA BRIDGE.................................................................. 24FIGURE 14: MOMENT UNDERSELF-WEIGHTAND KENTLEDGES................................................... 38FIGURE 15: MOMENT UNDERSELF-WEIGHTAND JACKING.... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38FIGURE 16: STRESS IN TOP FLANGE FROM SELF-WEIGHTAND KENTLEDGES........................................... 39FIGURE 17: STRESS IN TOP FLANGEFROM SELF-WEIGHTAND JACKING ...................................................... 39

    FIGURE 18: STRESS IN BOTTOM FLANGE FROM SELF-WEIGHTAND KENTLEDGES..................................... 40FIGURE 19: STRESS IN BOTTOM FLANGEFROM SELF-WEIGHTAND JACKING........................................... 40FIGURE 20: MILFORD HAVENBRIDGE AFTER COLLAPSE......................................................... 46FIGURE 21: SCHEMATIC DIAGRAM OFBRIDGE AND FAILURE..................................... ........................ 46FIGURE 22: DIAPHRAGMOVER PIER 6 OF MILFORDHAVEN BRIDGE............................... .......... 47FIGURE 23: SCHEMATIC DIAGRAM OF FAILUREOF KOBLENZ BRIDGE........................................................ 49FIGURE24: BOTTOMFLANGE SPLICEOF KOBLENZ BRIDGE.................................... ...................... 49FIGURE 25: SCHEMATIC DIAGRAM OF CONSTRUCTION JOINTSAND THEIR INFLUENCEON FAILURE ............... 50FIGURE 26: VARIOUS BUCKLING MODESOF STIFFENED PLATES.............................. ........................ 53FIGURE 27: TYPICAL BUCKLINGMODES ..................................................................................... .............. 55FIGURE 28: LOAD VERSUS DEFORMATION BEHAVIOR. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55FIGURE 29: VARIOUS MODES OF DEFLECTION .. . . . . . . . . .. . . . . . . . . . . .. . . . . . . . . . . .. . . . . . . . . . . .. . . . . . . . . . . .. . . . . . . . . 58FIGURE 30: COLUMNAPPROXIMATION OF A TYPICAL STIFFENED FLANGE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61FIGURE 3 1: TYPICAL BUCKLING MODE SHAPES................................................................. 63FIGURE 32: ULTIMATE FAILURE MODESOF TRANSVERSELY STIFFENED FLANGES...................................... 65FIGURE 33: SIDE VIEW OFSTORROW DRIVE CONNECTOR BRIDGE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70FIGURE 34: SIDE VIEW OFSTORROW DRIVE CONNECTOR BRIDGEDURING CONSTRUCTION......................... 70

  • 8/11/2019 MIT WestGate Bridge

    10/96

    List of Tables

    TABLE 1: COMPARISON OF MOMENT AND STRESSESFROM SELF-WEIGHT, KENTLEDGES ANDJACKING.......... 41TABLE 2: COMPARISON OF REQUIRED STIFFNESSES.................................. ...................................... 67

  • 8/11/2019 MIT WestGate Bridge

    11/96

    1. Introduction

    This thesis will explore issuesin the design, erection,and behavior of box girder

    bridges using the West Gate Bridge collapseas a case study. The behavior of the thin

    compressive elements in box girders is complex andwas not well understood at the time

    the West Gate Bridge, andother similar bridges,were designed and erected.This lack of

    understanding resultedin several failuresof bridgesof this type.

    We will begin withan overview of the West Gate Bridge project, the box girder bridge

    as a structural system, and key designand construction issues specific to the West Gate

    Bridge. Thechallenges encounteredin the design and erectionof the West Gate Bridge

    are numerous andthis paper does not aim to conduct a full account or analysis of them

    all. However, keyconcerns of calculations of loads and stresses duringthe constructionand service conditions will be noted. Particular attentionis paid to matters regarding

    elementsof the bridge under compressive loading.

    One of the critical challenges in the erection phase was the presence of large

    differences in camber of two similar sets of half spans. Two tactics for removing the

    camberdifference of span 10-11 will be compared.A brief presentationof failures of box

    girder bridgesconstructedduring the same time periodwill follow.

    Next, a summary of the understandingof buckling and failure modesof stiffened

    panels under compressive loading as described in papers written or published in 1997,2001, and 2004 is presented. An overview of design criteria suggestedby AASHTO

    (AmericanAssociationof State Highway and TransportationOfficials) and by B. H. Choi

    and C. H. Yoo (2006) for the minimum moment of inertia of stiffening elements follows.

    These design requirements will be compared to one another and to the properties of the

    stiffeningelementsused in the West Gate Bridge.

  • 8/11/2019 MIT WestGate Bridge

    12/96

    2. Background

    On October 15, 1970, the West Gate Bridge dramatically collapsed duringthe third

    year of its construction,killing 35 membersof the workforce [6].

    The bridge was chosento replace the existing ferry crossing of the Yarra River in

    Melbourne,Victoria, Australia. Constructionof the foundations started in April 1968 and

    the bridge was scheduled for completionin early 1971 [6].

    The bridge would have been the largest built in Australia (Hitchings169), and now

    follows Houghton Highwayas the second longestin the country [15].

    2.1. Initial DesignThe total lengthof the West Gate Bridge is 2,585 m and the width is 37 m. It has two

    four 17 m wide lane lanes, separated by a median strip. The bridge was to consist of

    spans of varying lengths in either prestressed concreteor steel. The centralsteel main

    span over the Yarra River is 336 m long with shorter spans on either side, for a steel

    structure with a total length of 859 m. There are ten approach spans on the western

    approach and thirteen approach spans on the eastern approach, each of prestressed

    concrete and67 m in length [6].

  • 8/11/2019 MIT WestGate Bridge

    13/96

    Figure 1: Plan view

    13

    `~t -\

    7

    WE T CATIE g [

    IN *N

    ~I ___

    r.,

    I

    S 3 5Q90/i

  • 8/11/2019 MIT WestGate Bridge

    14/96

    ELEVATION

    Crown of roadExpansion 192.175Epansonjoint Pinjonlt Pin oint jont

    irm i Fix = ixed

    it fcontrctSSaondE Limitofcontracts andE

    a: PLAN

    > Cross m at\,i , O'6' crs

    WScale .. .0 2 o 400

    % 1:40 1:40L panddown constanton concaveside

    / Variable gap/ ection from Box 16 to mid span o

    -Section at max superelevation at box Iponvex side of curve

    TAPER - OUT OF SUPERELEVATION ON CONVEX SIDE

    Figure 2: Elevation, plan and section views

    The central three steel spans form a cable-stayed structure supported from two

    central steel towers rising 46 m above the roadway. The navigational clearance provided

    is 54 m above the low water level [6].

    Figure 3: Photograph of bridge model

  • 8/11/2019 MIT WestGate Bridge

    15/96

    The central span structure consists of a simple central tower with cable stays

    anchored within the central cell of the box girder. This arrangementhas been foundbest

    suited to the roadway layout, since the tower and anchoragescan be accommodatedin the

    central median strip between the lanes. Inequalitiesof loading on the two lanes are dealtwith by providingadequate torsional stiffness in the deck structure [6].

    The hollow box section consists of a trapezoidalsection 4.05 m deep, 19.06 m wide

    along the bottom flange, and 25.47m at the top flange. Minimizingplate thickness was

    one of the primary aims of the design since most of the problems associated with the

    production and welding of high yield steel would be eliminated. The boxes are made up

    from stiffened panels for standardizationand economy. The box girder is divided into

    three compartmentsby verticalwebs and outer inclined web panels.Each web and flange

    plate is 16 m long and stiffened with either bent plates, angles, or bulb flats welded to

    them. All web andbottom flange splices connectingthese panels are made with grip bolts

    [6].

    Figure 4: Assembly diagram

  • 8/11/2019 MIT WestGate Bridge

    16/96

    The cable-stayedsystem operates only between columns 11 and 14. Spans 10-11 and

    14-15 are therefore unstayed box girders, rollersupported at the outermost ends but pin

    supportedand continuousat the inner ends. Therefore,the investigationinto the causes of

    failure of span 10-11 was limited to a comparatively simple structural system(Royal

    Commission36).

    2.2. Contractual Relationships

    In 1961, the Lower Yarra CrossingAuthority (LYCA)was established as a non

    profit company to construct and operate a bridge crossing the Lower YarraRiver. In

    1965, LYCA had informal talks with consulting engineers Maunsell and Partnersof

    Melbourne. Maunsell and Partners had limited experiencein major bridge designand in1966, they recommended thatLYCA approach the internationally recognizedfirm

    Freeman, Fox and Partners (FF&P)of London. FF&P hada world reputation for their

    work on such structures as the Forth Road Bridge(1963) and the Severn Bridge(1968)

    [6].

    Time was very important becauseof the high level of interest charges to LYCA. In

    order to meet the completion deadlineit was decided fromthe beginning that detailed

    designs must be rapidly prepared so that tenderscould be called for constructionas soon

    as possible [6].

    In 1967, LYCA formally appointedthe two firms as joint consultants for detailed

    design up to the preparation of tender documents.The contracts for foundationwork and

    concrete construction were awardedto John HollandConstruction (JHC) of Melbourne in

    1968. The contract for steelwork constructionwas awarded to World Services and

    Construction(WSC), a subsidiaryof a Dutch constructioncompany, also in 1968. By the

    end of 1969, it was apparent thatWSC was falling behind the construction schedule for

    steelworkerection [6].

    To avoid furtherdelay LYCA made new contractual arrangementsin which WSC

    continued to make the steel parts for the bridge but JHC was to erect and join the

    steelworktogether. This is a specializedarea in which JHC lacked experience[6].

  • 8/11/2019 MIT WestGate Bridge

    17/96

    2.3. Construction

    The foundations, which involved sinking cylinder and driving octagonal steel piles,

    were started in April 1968 and ended without incidentin September 1969 [6].

    Cantilevered forms wereused to construct the concretepiers in 2.44 m sections. Foursets of formworkwere used so that the four piers couldbe constructed simultaneously.

    The 67 m approach spans consisted of eighteen spine beam units whichwere

    manufactured on site. Special equipmentwas designed and built to lift and handle the

    units into position [6].

    Each steel box of the central span structureconsisted of twenty-one stiffened plate

    panels which were fabricated in two workshops at the bridge site. Plate steel was

    prepared to specialspecificationsand rigorously tested for such properties as strength and

    impact resistance[6].

    By October 1970, twelve pairs of half boxes had been erected on the east bank

    extending from Pier 15 to a point mid-way between Piers 13 and 14. Span 10-11 had

    been started on the west bank. The three middle spans- 11-12, 12-13 and 13-14 - were

    designed to be erected by the cantilevermethod in which sectionsof the steel box were

    raised and attached to the last section. Thiscould havebeen done from one pier only or

    from both endsso that the cantilevered spans met in the middle- however, this stage was

    not reachedin construction.

    Span 10-11 and span 14-15 were designed to be erected in a different fashion by

    assembling each span in two halves on the ground in full length and half width. Each

    span was then lifted into position at the top of the piers. The next stage, which proved

    extremelydifficult,was to join the two half spans together [6].

    The erection of span 14-15 gave an indication of the problems to be expected with

    the chosen erection procedure. The boxes were bolted together on temporary staging at

    ground level. When the span was lifted off the temporary staging the upper plates of the

    boxes buckled at the unsupported edges. Thus, inadequate temporary bracing led tosignificant compression instability. When both halves were jacked and placed on the

    piers, a 90 mm (3.5 in) difference in camber was observed.To eliminate this difference,the end of the south half span was jacked up to about twice the camber difference, andwhen aligned, the two halves were jacked together, closing the horizontal gap. Some

  • 8/11/2019 MIT WestGate Bridge

    18/96

    local buckling remainedand this was pressed out using long bolts tightened on stiff

    beams. Working from both ends left one section in the middle where the buckles

    remained. Theonly way to remove these, in the opinion of the engineers, was to undo

    some of the bolts connectingthe stressedstructure, and when displacementhad eased out

    the buckles, replace the boltsafter enlargingthe holes [6].

    The first half spans werejoined successfullyby WSC, with a system of hydraulic

    jacks to ensure thatthe total load of the partly constructed span would be more or less

    equally shared betweenall the trestles. However,when JHC took overthis assembly,they

    had difficultyin understandingthe logicbehind this system [6].

    The success of the erection of span 14-15 lead to a "degree of unconcern" when

    similar problems were encounteredon span 10-11 [6].

    The Collapsed Span

    At the time when span 10-11 was partially assembledon the ground, the contract for

    steel erection was awardedto JHC. Similar to the constructionof span 14-15, span 10-11

    was also erected by assemblinghalf spans and joining them together after placingthem

    on the piers [6].

    The half boxes were surveyed for alignmenton the ground, but due to temperature

    changes and the fact that one half span had a crane on it, thesurveys were likely to be

    inconsistentand unreliable [6].

    When the two sections werebrought together afterbeing lifted onto the piers, the

    difference in camber was foundto be as much as 114 mm (4.5 in). JHC proposed to use

    10 8-tonne kentledges (concrete blocks) placed near the midspan, to remove the

    difference. With seven of these blocks in place a major bucklehad occurredin the upper

    panel of the north span.In order to allow thebuckle to be removed, bolts connectingthe

    transverse splicein the top deck near the mid span were undone [6].

    2.4. The Collapse

    On October 15, after about sixteen bolts hadbeen loosed, therewas significant

    slipping of the two plates relative to one another such that the loosened bolts were

    jammed tightly into their holes and couldnot be removed [6].

  • 8/11/2019 MIT WestGate Bridge

    19/96

    After about 30 bolts were removed,a dramatic changetook place. First, the buckle

    spread into the adjacent outer panels, accompaniedby the buckling failure of the upper

    part of the inner web plate. Plasticcreep in the steel, and possibly the effect of thermal

    changes, all contributed to a slow diffusionof yielding, which lasted50 minutes beforethe finalcollapse [6].

    Images captured following the failure andsketchesof the collapse are shown below.

    Figure 5: Elevation and plan of collapsed span

    'rI~~.2. .... I

    L...1,,,,Pc4 ,,_,... ,,__r , ) 4vwJcrt Q: , * j' " ' t/ ?ae i, i .S ., or,d i

  • 8/11/2019 MIT WestGate Bridge

    20/96

    Figure 6: Shortly after collapse

    Figure 7: Impact of collapse forced a steel beam through concrete of deck

  • 8/11/2019 MIT WestGate Bridge

    21/96

    Figure 8: Collapseddeck viewed from neighboringpier

    Figure 9: Close-up of shattered box structure of deck

  • 8/11/2019 MIT WestGate Bridge

    22/96

    -C- -. ...l.J/

    1 I , _

    BUc(ki Srts ntS4'bSpofce

    go. I pu i s cOf P e r hOBoxes -, o,5'; , ,hor.zowotc

    Boxe r-.4 ht grounrd sti Sor,izontoLtosonraeous U r of ns 5S-

    hamnges frcm fop itf o 4/5 p iceCrone er)ked Off

    eotory momentum cc:rjes ic~s, 5 - 8clear of Prer 1f

    toxes 5 8 ~ rse -oorn ii0 ctish oPer ft erbag aearmysre mnIo Lck of r d9e

    per f pu7 o, ,e

    Beor'rm5

    ,oling beom.,

    h Ir:eck of c r n e .B ar g ,

    4osffm beartngf

    Pier ft bits mud ndi s des siieways

    Figure 10: Dynamics of failure

  • 8/11/2019 MIT WestGate Bridge

    23/96

    L

    Figure 11: Sketch of collapse

  • 8/11/2019 MIT WestGate Bridge

    24/96

    3. Advantages and Disadvantages of Box Girders

    Robert Stephenson, an English civil engineer, first decided on light metal

    construction for the rational use of material for the Britannia Bridgein 1850. This

    structure was a continuous girderof puddle iron with maximum spans of 142 m in the

    form of a box. He is consideredto be ahead of his time, and his ideawas not followedup

    until a century later (Inst. Civil Engineers21). Stiffened steel plate box girders for bridge

    construction were first developed andused in Germany in the 1950s for post-war

    reconstruction. Stiffened plates are basic components of many structures, including

    bridges,buildings, automobiles,aircrafts, offshoreplatforms, and naval vessels [8].

    The main advantagesand disadvantagesof box girderbridges are describedbelow.

    Figure 12: Side view of Britannia Bridge

    Figure 13: Cross-section of Britannia Bridge

    3.1. Advantages

    During the mid 20 th century, engineers favored the box girder, pioneered by

    Freeman, Fox and Partners, because of its relative lightness, speedof construction and

    cost. They said box girders could cut cost of constructionby between 30 and 50 percent

    (Hitchings 98).

    Because box girders are closed-section members, they are often used in highway

    bridges because of their high torsionalrigidity, economy, appearance, and resistance to

  • 8/11/2019 MIT WestGate Bridge

    25/96

    corrosion. With their wide bottom flanges, relativelyshallow depths can be used

    economically. And for continuous box girders, intermediatesupports often can be

    individual, slender columnssimply connectedto concealed cross frames (Brockenbrough

    11.56).

    3.2. Disadvantages

    Because relatively thinmembers take significantcompressive forces, bucklingis a

    key design concern forsteel box girders. Moreover, the behavior of this system is very

    complex and requires a high design effort. A view contradictory to the previous

    subsection is that box girder bridgesare more expensive to fabricate, andmay also be

    more difficult to maintain because of the need for access toa confined space inside the

    box [4].

    At the time of the publication of Steel Box Girder Bridges by the Institutionof Civil

    Engineers in 1973, there was no comprehensivetheory that embraced all the stability

    problems typical of steel box girders. This is because a number of factors work together

    to make it difficult to analyze the physical nature of the problem, such as: a) the complex

    form of the cross-section and the difficulty of taking into account the interaction of its

    various parts, b) the compound and three dimensional stateof stress and c) the non-

    linearity of geometry and of the constitutive laws of the material, both of which much be

    consideredfor a correct interpretationof the problem(Inst. CivilEngineers25).

    Informationderived from experimentswas also insufficientwith only one person - P.

    Dubas - havingworked in the field at the time (Inst. CivilEngineers 25).

  • 8/11/2019 MIT WestGate Bridge

    26/96

    4. West Gate Bridge Issues

    4.1. Design

    The design process of the original West Gate Bridge had manycomplications, and

    calculations containednumerous errors in arithmetic andin engineeringprinciple. This

    subsection is intended only to highlight certain issues relating to engineering practice,

    and to the events leadingto the collapseof the bridge.

    Administrative Matters

    A number of administrative,communicationand managerialproblems characterized

    the design and erectionof the bridge.In writing the report, the Royal Commision foundithard to determine the sequence of calculationsmade because neither Freeman,Fox and

    Partners (FF&P) nor WorldServices and Construction(WSC) made a regular practice of

    dating or signing their calculations. WSC repeatedly requested designcalculations from

    FF&P but were often leftwithout a response.

    WSC also facedlabor problemson site, including disputes,strikes, protest meetings,

    walk-offs and absenteeism. John Holland Construction (JHC) also experienced

    challengeswhen they tookover the steel erection, as the companyhad no experience with

    box girder constructionand was stronglyopposed by FF&P [6].

    General Design

    Overall, the design - as a process and as a deliverable - was troubled. Because the

    Lower Yarra Crossing Authority (LYCA) was very concernedabout having the bridge

    completed on time, it was decided that detaileddesigns were to be rapidly prepared so

    that tenderscould be calledfor constructionas soon as possible [6].

    Almost the only calculationswhich FF&P presentedto the Royal Commission(after

    the collapse)relating to the tender design were the computeroutputs made in early 1967.

    Neither Sir G. Roberts nor Dr. W. C. Brown, senior engineersof FF&P, would admit to a

    knowledge of the details of the computerprogram used to make their calculations.And,

    in setting up a model for the program, sweeping simplifications weremade when

    representing the structure (Royal Commission52).

  • 8/11/2019 MIT WestGate Bridge

    27/96

    Brown, saidthe "bridge was a new development.The design remainedin a complete

    state of flux for some considerable time...because this type of bridge involves new

    concepts and calls for muchthought to arrive at acceptablepractical solutions." While the

    box girder bridge was ahighly advanced systemand had been popular for only a shorttime, FF&P actuallyhad great dealof experience withbox girder bridges, includingthose

    with trapezoidal sections andwith cablestays (Royal Commission49).

    FF&P stated that tender design was preliminary only andthat they would have

    expected the contractor to introduce changes when preparing workingdrawings. Yet, the

    tender drawings showthat design detailsare fully worked out, to the location of every

    bolt (Royal Commission49).

    FF&P's design activity was at a very low level from early 1969 until April 1970,

    when, in the opinion of the Royal Commission,they should have been checkingthe final

    design of the structure. Their own checks, madeat the end of 1968, showed stresses in

    some areas considerably higher than permitted by any code. Construction, meanwhile,

    was proceeding despitethe unsatisfactorystate of the calculations (Royal Commission

    51).

    Specificdesign issues are addressed in the following sections.

    Loading

    The self-weightand dead load reactions on piers were determinedearly in the design

    by FF&P and were generally agreed upon by WSC, A.P. Sewell of JHC and J.J. Grassl,consulting engineer. The reactions on two piers due to live load were found to be 280

    tons by FF&P while A.P. Sewell and G. Maunsell found about845 tons. This major

    discrepancyis explained in the following paragraphs(Royal Commission47).

    Early in 1967, Maunsell was anxious to find reaction values so that they could

    proceed withthe design of concrete piers. A calculation done by FF&P in April of that

    year showed that the live load reactions were assessedby a simple proportion of the deadload reactions(Royal Commission47).

    Roberts stated that the live loads in question were preliminary only, but there is no

    evidence that estimates of live load reactions were everrevised. And, the values obtained

  • 8/11/2019 MIT WestGate Bridge

    28/96

    at that time appear to have beenin use by both FF&P and Maunsellright up to the time of

    failure (Royal Commission47).

    There was also a discrepancyon the number of lanes needed forthe basic function of

    the bridge, as well as in the live load reduction.One of LYCA's design requirements was

    that planning shouldbe made for "four lanes of traffic with a breakdown lane allowing

    for a possible extensionto five lane operation withouta breakdown lane." Thus, the two

    55 ft 2 in carriageways would be required by the NAASRA (National Association of

    Australian State Road Authorities)to carry ten lanesof traffic. However,FF&P designed

    the bridge to carry eight lanes of traffic. According to the AASHO (American

    Association of State Highway Officials), and hencethe NAASRA, code,FF&P could

    reduce live loadby 25%, which is based on statistical grounds. However, the values onthe curve used by FF&P were already calculated assuming75% of the lanes would be

    fully loaded (RoyalCommission46).

    Factors of Safety

    In statements to LYCA, FF&P made it clear that where appropriate,the design

    stresses wouldbe in accordance with BS 153 (British Standard),including the increase of

    30 percent above workingstressesfor the erection conditions (RoyalCommission42).

    The safety factor for the service condition is 1.70, although it would be morecorrect

    to describe this as a load factor- the factor by whichthe factored loads must be multiplied

    for yielding of some structuralmember to occur. The elasticanalysis made in design

    must account for all factors involved,particularly when dealing withpanels of plating

    under compression or shear (RoyalCommission42).

    BS153 setout various combinationsof forces which must be taken into account. In

    presenting the stress analysisfor the service condition,FF&P included only the dead and

    live load and ignored othereffects such as wind pressure,temperature, and resistanceof

    expansion bearing to movement. The neglect of these minor effects reduced the safety

    factor, and they weremore dangerousbecause their significance, neither individuallynor

    collectively, was assessed (RoyalCommission42).

    The safety factor has a particularly high significance in the design of this bridge

    because of the uncertaintyassociatedwith stiffenedplates under compression.In addition

  • 8/11/2019 MIT WestGate Bridge

    29/96

    to the possible initial distortions and locked-in stresses, thereis also considerable

    difference of opinion on the exact manner in which suchpanels behave whenloaded to

    failure. Furthermore, when failure occurs, it will usually be catastrophic (Royal

    Commission43).Experts could not agree on the determinationof the theoretical failure loads for the

    panels, and thus, the appropriate allowable working stress. Therefore, the factor of

    ignorance for these elements is large. It would appear inappropriateto use the same

    safety margin as that used for elements whose behavioris more certain, suchas simple

    beams. Given this,the Royal Commissionbelieved the factor of 1.31 (1.70/1.30) wastoo

    low for the design of compressionpanels in a box girder (43).

    Finally, the FF&P design calculationsbarely contain any statement on, or values of,allowable stressor any comparisonsof allowable or actual stresses. In some of the rare

    cases where valuesare given, BS153 has been used.

    Stiffened Panels in Compression

    The stiffened panelsof the upper flange were intendedto work compositelywith the

    concrete deck in the service condition to add significantly to the stability of the upper

    sections. However, for the pre-concretedstages of erection it was necessary to provide

    stiffening sufficientto stabilize the parts of the upper flange which were in compression.

    It was thefailure of these panelsthat led to the collapse (RoyalCommission37).

    This stiffening included longitudinal bulb flats and transverse stiffeners. The

    connectiondetails wereflawed in that the transverse stiffenerswere connectedonly to the

    bulb flats and therefore, only indirectly connected to the flange plate in many cases.

    These fish plates (or, K-plates), used to splice the bulb flats, were not designed with

    consideration of their high slenderness ratio and eccentricity. For this reason, the

    connection of the longitudinal stiffeners was less strong than the elements themselves

    (Royal Commission37-8).The effective length of 0.71 (fixed-pinned condition) for the stiffened panel and K-

    plates used by Dr. W. C. Brown was also a point of disagreement because they werebased upon assumptions that the panels would be bent slightly downwards initially andwould behave as if fixed. The Royal Commission determined that this assumptionwas

  • 8/11/2019 MIT WestGate Bridge

    30/96

    unacceptable because these conditionswere not met on site. They doubt that the

    assumption would have been justifiable even if the conditions had been met (Royal

    Commission45).

    FF&P used the simple theory of bending to calculate the buckling load of the

    stiffened plates. However, the Royal Commission claimed this theory could lead to

    significant errors due to the fact that plane sections, on bending, do not necessarily

    remain plane(RoyalCommission37).

    The critical stress for buckling of longitudinally stiffenedpanels betweentransverse

    beams was found to be 18.3 tons/in2 (40.4 ksi) - only slightly higher than theEuler value

    for one longitudinally stiffenedpanel and its attached plate, whichwas 17.7 tons/in2

    (39.0 ksi). The Royal Commission asserts that failure would occurat a stress well belowthe elastic crippling stress because of the imperfections of flatness inherent in any

    practical panel and the limits imposed bythe onset of yield (Royal Commission54).

    The classical theory of elasticity gives three modes of buckling for such panels in

    compression.While FF&P gave a formulas for the most complex mode (which is also the

    least practical fornormal design purposes)to WSC, there is no evidence that FF&P used

    the method for either the tender design or post-tendercheck (RoyalCommission55).

    Furthermore,the formulas forthe various bucklingmodes only give elastic critical

    stress. They can be of some help in determining the appropriate allowablestress, but

    other factors such as the yield stress, the initial unfairness of the panels and the

    appropriatesafety factor must be taken into account.

    Lastly, there is no evidence that post-bucklingbehaviorwas investigated.And, in the

    design, FF&P ignoredthe presenceof the splices in the way it might affect the stabilityof

    the panels (RoyalCommission55-56).

    Factors Not Addressed in Report of Royal Commission

    While the report presented by the Royal Commission is very comprehensivein the

    review of calculations and design features of the West Gate Bridge, we may note that

    certain typesof loading werenot discussedby the designers or contractors,nor by the

    Commission.

  • 8/11/2019 MIT WestGate Bridge

    31/96

    These include seismic loading,dynamic loading andresponse, and fatigue. It could

    be that these effects were not consideredas often in that timeperiod. Or, the reason could

    be that the factors were not considered relevant for the inquiry given that they did not

    directly relateto the collapse.

    Shear lag

    Calculations by FF&P did not account for shear lag effects in the webs and

    diaphragms, which involve the distributionof load between inner and outerwebs (Royal

    Commission61).

    The Royal Commission states that the distribution is not a statically determinate

    problem and a reasonably complex analysis would be needed to get a meaningful

    distribution(Royal Commission62).

    After the collapse, Maunsell,London performed finite element analysisand

    calculated shear lag effects of up to 80 percent. In certain locations of the box girder,

    Maunsell, London's analysis showed peakstresses caused by shearlag in excess of the

    yield stress andthere wereareas of up to about 30 ft2 where thestress wasnever less than

    90 percent of the yield stress (Royal Commission62).

    After the Milford Haven Bridge collapse in June 1970, FF&P used a 50/50

    distribution, then59/41 and 42/58 distributions,where the outer webstake 59 and 42

    percent of the total shear and the innerwebs take 41 and 58 percent. The analysis by

    Maunsell, London foundthat a distribution of 40/60 seemed more rationalwhen

    considering compatibilityof shear deflectionsin the four webs (Royal Commission62).

    The assumption that the loadfolloweda 50/50 distributionwould imply overstressed

    conditions in the bolted connections between the webs and the load bearing diaphragm

    (Royal Commission62).

    ErectionWhen the principle dimensions of the bridge had been established and the tender

    design was carried out in mid-1967, it appears that no serious consideration was given to

    potential erection schemes,even though one of the computer runs was claimed to be an"erection analysis." The analysis made at that time was limited to an examination of

  • 8/11/2019 MIT WestGate Bridge

    32/96

    stresses in the steel bridge except for the concrete deck and another similaranalysis for

    the stresses in the bridge with all the concrete in place and already hardenedin order to

    act compositely withthe steel (RoyalCommission41).

    The instantaneous placement and hardening of the whole concrete deck cannotbe

    considered a practical condition and one can assume that any practical scheme for

    concreting would be likely to impose higher stresses at some placesduring erection

    (Royal Commission41).

    By adopting this oversimplified approach, FF&P achieved a design which they

    believed was satisfactory for the service condition, but required considerableextra

    strengthening at many places to meet the stresses imposed by any practicalerection

    scheme (Royal Commission41).According to B. W. Smith, the erection stages of a large bridge are often the most

    critical fromthe point of view of safety. As erection continues,additional elements may

    be added to parts of the structure already erected.These may include deck panels,

    concrete, or additional crossmembersto be integrated witha spine that is already erected.

    This will affect the stiffness on the part of the structurealready erected and consequently,

    it will behave differently when subjectedto loadings in its stiffened state. This must be

    consideredin large-span bridges, as the effects of deformations and locked-in stresses can

    be significant. An incremental loading approachis suggested for analysis that addresses

    these changes [20].

    Other effects on stresses

    BS153, and all other codes on the design of bridges call for consideration of

    secondary effects from wind, temperature (uniform and differential), stresses

    permanently induced by erectionforces, stresses induced by settlement of supports, and

    stresses caused by creep effects in the concrete of the composite deck (Royal

    Commission60).

    Wind stresses could have been relatively highbecause the half girders would have

    not only a larger coefficientof drag than the more streamlinedfull section, but also a

    much smaller section modulus for bending in the horizontal plane (Royal Commission

    61).

  • 8/11/2019 MIT WestGate Bridge

    33/96

    The bridge is most sensitive to differential temperaturebetween the upper and lower

    flanges. And, it is most sensitive to this effect duringthe erection stages before the

    concrete deck is placed (Royal Commission61).

    The method of erecting spans 10-11 and 14-15 in two halves meant that unless thetwo halves were made with exactlythe same camber, permanently locked-up stresses

    would be induced when bringing the two halves to the same level (RoyalCommission

    61).

    Other erection-inducedstresses would occurif the cantileverswere not set out to the

    correct profile,so that theirreactions onto the piers would be other than thoseassumed in

    the calculations. There was some evidence that thishad already happened when

    cantilevering out from pier 14 towards the temporary prop on the east side (Royal

    Commission61).

    The concrete deck had been assumed to work in a compositemanner with the steel,

    as long as the concrete remained uncracked.The creep of concrete understress would

    gradually change the stressdistribution, and this effect also could become significant

    (Royal Commission61).

    FF&P stated that they considered stresses induced by wind and temperature, butdid

    not produce calculations showing the effects of these stresses. The wind pressure on the

    bridge during erectionwas estimated to be as high as 2.1 tons/in2 (4.6 ksi) at box 17. The

    magnitude of the temperature-induced stress depends on the differential, but a rough

    estimate could be 1 ton/in2. The permanent stress induced fromreducing the camber

    difference between the half spans was approximately1 ton/in2 (Royal Commission61).

    While none of the secondary effects are very large, they could have dangerously

    reduced the safety margin. The effects probably wouldnot act together for a cumulative

    effect at any one point, but it is suggested that certain combinations are statistically

    probable and should have beeninvestigated(Royal Commission61).

    Strengthening Following the Collapse of the Milford Haven Bridge

    WSC found certain areas of the structure where additional stiffening was needed.

    According to their calculationssome of this extra strengtheningwas required not only for

    the erection conditions but for the service condition as well. Most of the strengthening

  • 8/11/2019 MIT WestGate Bridge

    34/96

    added to the West Gate Bridge after the Milford Haven failure wasfor the strengthening

    of details overlookedearlier (Royal Commission59-60).

    Since the Milford Haven Bridge was of a somewhat similar designand becuase

    FF&P were thedesigners of both bridges,LYCA arranged forG. Maunsell and company

    in London, to make an immediate checkof the design of the steel spansin the West Gate

    Bridge. Followingthe Milford Haven collapse,certain steps were takento strengthen the

    steel spansof the West Gate Bridge (Royal Commission12, 59-60).

    The main steps, taken in certain boxes,were:

    * doubling thelongitudinal stiffeners

    * substitutionof angle splices forthe K-plates

    * increasingthe number of bolts in the transverse seam* connectingthe main diaphragmto the outer sloping webs

    * additionof 15 in channels as further transverse stiffeners

    * additional longitudinaland transverse stiffenersto the outer slopingwebs

    * additionof reinforcingplate aroundthe opening forthe main tower in box 17

    * massive strengtheningof transverse diaphragms

    * concreting in of K-plates on the already erected east span14-15 (Royal

    Commission60).

    The Report of the Royal Commissionstated that while this stiffening was vitally

    necessary, none of it directly affected the section which collapsed. Theyalso believed

    there are a number of places in the box girder which would fail to meet the requirement

    even after the post Milford Haven stiffening had beenadded (Royal Commission60).

    As an example of a more comprehensive design, the planning for the new bridge

    crossing the Lower Yarra River included wind tunnel tests, carried out by theaerodynamics divisions of the natural physical laboratories at England and Monash

    Universities. The model tests showedthat the bridge would behavesatisfactorilyin wind

    speeds of twice the maximumvalue to be expected in a 100 year period (Hitchings 171).

  • 8/11/2019 MIT WestGate Bridge

    35/96

    4.2. Erection

    In addition to concerns raised in the design process, there were numerous challenges

    encounteredin the erection of steel workfor the West GateBridge.

    Bulge

    In early September 1970, a bulge was found in the sloping outer web around the

    south 8-9 splice. This bulge tookthe form of a dishing inwardsof the web to a maximum

    of about 1 1Ain. It covered a roughly circular area witha diameterof about 10 ft, but was

    difficult to see because of lighting and the perspective of observers (Royal Commission

    29).

    It was established that the bulge was the result of a fabrication distortionor an

    accident in erection which had gone unnoticed for two months. It was uncertain thatthe

    outer web plating had notbecome unstable due to the stresses in it and that the situation

    would notworsen as further boxes were cantilevered out (RoyalCommission29).

    Transition Curves

    The transition curves of the approach viaducts were carried overonto the steel

    bridge. The twist of the boxes on the convex side of the curve- the north boxes of span

    10-11 and the southboxes of span 14-15 - amountedto 23 minutes of arc (0.38 degrees)

    per 100-ft length. To achieve this twist when fabricatingthe boxes, it was necessary for

    all the panels involved in the twist to be made as rhomboids, slightly off the perfect

    rectangle. In practice the panels themselveswere kept rectangularbut the holes around

    the edge were set out on lines whichformed a rhomboid.The use of transition curves on

    the steel bridge was seen to have introduced significant complicationin detailing and

    resulted in many non-standardpanels (Royal Commission36).

    Events Leading Directly to Collapse

    As discussed in a previous section, the 14-15 and 10-11 spans were erected by

    assembling, lifting and joining half-spans. This methodwas consideredunusual and had

    not been attempted anywhere else in the world. Especiallygreat care would have been

  • 8/11/2019 MIT WestGate Bridge

    36/96

    required to reduce any camber difference, but was not exercised (Royal Commission 16),[6].

    The Royal Commissionasserts that the difficulty in getting the two half girders to

    the correct relative positions throughouttheir lengths was due to the fact that the camber

    curves on the two halves were different not only in amplitude but also in shape.

    Therefore, even when connectionshad been made at a number of diaphragmsit was still

    necessary to use large forces to make the remaining parts fit (RoyalCommission22).

    A more detailed descriptionof the events leading to failure, beginning with the

    observed differencein camber and resultingin the creation of a hinge was presented in

    Chapter 2.

    This subsection ends with a simple suggestion for the loosening of the bolts in orderto remove the buckles in the upper flange. Temporary supports below the box girder

    would have reducedthe positive bending momentin the middle of the span, reducing the

    compressive andtensile stressesin the flanges.The removal of bolts at the center of the

    girder, while successful on span 14-15, could be thought to create a hinge if the

    compressive and tensile stressesbecome too high. The hinge would create a mechanism,

    as the ends of the girder have almostno moment capacity.

    The bolts were jammed tightly into their holes afterabout sixteen had beenremoved

    in the method chosen;the decrease in moment andin compressive stressin the top flange

    through temporary supportsor jacks would have made this job easier and safer.

    While this simple tactic would noteliminate the more seriousissues with the design

    and erection of the bridge, it would have reducedstresses in the girder whilecalculations

    continued to be made and extra strengtheningwas added. More importantly,it could have

    saved human life on the site.

    Following the October 1970 disaster the erection method of the new bridge crossing

    the Yarra River was changed suchthat each box-girder was cantileveredonto an existing

    box-girder. Overhead crane and underpinningprops were used to provide extrasafety and

    ease of operation (Hitchings171).

  • 8/11/2019 MIT WestGate Bridge

    37/96

    4.3. Comparison of use of concrete kentledges with jacking

    This sectionof the chapter quantifies the benefits of jacking to remove the 114 mm

    (4.5 in) camber difference found when trying to join the halves of span 10-1 1. Rather

    than applying gravity load to reduce the vertical camber of one half span, jacking could

    have beenused to increase thevertical camber of the other half span.

    The deformnation resulting from the 80 tonne (176.4 kips) load, both modeled as a

    point load and as three point loads, was used to estimate the moment of inertia of the half

    box section. These values werecompared withcalculations made based on the geometry

    of the cross-section. The schemes of kentledge and jack placement are listed and

    described below.

    * Kentledge Load Scheme 1: The load of the kentledgeswas modeled as a point

    load at the midpoint of the span.* Kentledge Load Scheme 2: Four kentledge blocks are placed at the midpoint of

    the span and three kentledgeblocks are placed atone third of the length from the

    ends. Thisscheme is probably the more realistic of the two kentledgeschemes.

    * Jacking Scheme 1: The jacking force is modeled as a point load at the center of

    the span. The force is equal in magnitude to and opposite in direction of the

    concentratedforce in Kentledge Load Scheme 1.

    * Jacking Scheme 2: The jacking force is modeled as a point load at the midpoint

    of the span and two pointloads one third the length of the span from theends. The

    three forces are equal and were recalculated to achieve the desired displacementat

    the midpoint. This scheme is more realistic than Jacking Scheme 1 nd is more

    appropriate if a small number of jacks, each with a relatively high capacity, is

    available on the site.

    * Jacking Scheme 3: The jacking force is modeled as five point loads with spacing

    equal to one sixth the length of the span. The five forces are equal and were

    recalculated to achieve the desired displacement at the midpoint. This scheme ismore realistic than Jacking Scheme 1 and is more appropriate if there are more

    jacks with lower capacityavailable on the site.

    Stresses that might result from wind, temperature, erection were each estimated at Iton/square inch, or 6.615 ksi in total (Royal Commission 61). These were added to the

  • 8/11/2019 MIT WestGate Bridge

    38/96

    compressive and tensile stresses at the top and bottom of the flange, respectively, for

    conservative treatment. The following graphs and table show the moment and stresses

    present on the entire length of the half spans.

    Figure 14: Moment under self-weight and kentledges

    Figure 15: Moment under self-weight and jacking

    Moment Under Self-Weight and Kentledges

    U

    5000

    10000

    15

    20000

    25000E30000

    35000

    40000

    4 5 00 0

    -- Self-Weight

    S- - Kontledges(Scheme 1)

    - Kentledges(Scheme 2)

    250 300 3550 100 150 200

    Position (ft)

    Moment Under Self-Weight and Jacking

    0

    5000

    10000

    15000

    E

    20000

    25000

    30000

    SSelf-Weight

    - -Jacking(Scheme 1)

    Jacking(Scheme 2)

    Jacking(Scheme 3)1

    0 50 1 15 200 25 3 35

    Position (if)

    45

  • 8/11/2019 MIT WestGate Bridge

    39/96

    Compressive Stress in Top Flange:Self-Weight and Kentledges

    I

    /I

    /\\ /\\ /

    \ . /

    \\ /

    \ / //

    \ //

    N.. . -.. -,, . , , .-

    t

    -- Self-Weight

    K----Kentledges(Scheme 1)

    - Kentledges(Scheme 2)

    0 50 100 150 200 250 300 350

    Position (ft)

    Figure 16: Stress in top flange from self-weight and kentledges

    Figure 17: Stress in top flange from self-weight and jacking

    2

    4

    6

    3 8

    C,10

    12

    14

    16

    Compressive Stress in Top Flange:Self-Weight and Jacking

    0

    2

    4

    6

    8

    10

    Self-Weight

    - - - Jacking(Scheme 1)

    Jacking(Scheme 2)

    Jacking(Scheme 3)

    0 50 1 15 200 25 3 35

    Position (ft)

    .v0 5 1 15 2 25

    3 35

    Position

    (ft)

  • 8/11/2019 MIT WestGate Bridge

    40/96

    Tensile Stress in Bottom Flange:Self-Weight and Kentledges

    u

    2

    4

    6

    8

    A 10

    12

    14

    16

    18

    20

    - Self Weight

    - - - Kentledges(Scheme 1)

    Kentledges(Scheme )

    300 35000 15 200 25

    Position (ft)

    Figure 18: Stress in bottom flange from self-weight and kentledges

    Figure 19: Stress in bottom flange from self-weight and jacking

    0 50

    Tensile Stress in Bottom Flange:Self-Weight and Jacking

    0

    2

    4

    6

    8

    10

    12

    -- Self-Weight

    --- Jacking(Scheme 1)

    -Jacking(Scheme 2)

    . Jacking(Scheme 3)

    0 50 100 150 200 250 300 350

    Posi t ion (ft)

    20

    0 50 1 15 225 3 35

    Position(ft)

  • 8/11/2019 MIT WestGate Bridge

    41/96

    y, (fi) yt, (ft) I (ft) a, , (ksi)5.96 7.33 115.60 6.615

    Self-Weight Kentledge Kentledge Jacking Jacking JackingOnly Scheme1 Scheme 2 Scheme 1 Scheme 2 Scheme3

    Max Moment(kip-ft) 26674 42880 39639 12905 13141 13728Percent Difference 0% 61% 49% -52% -51% -49%

    Top Flange:o (ksi) 9.56 15.36 14.20 4.62 4.71 4.92

    plus o, (ksi) 16.17 21.98 20.82 11.24 11.32 11.53

    Bottom Flange:a, (ksi) 11.74 18.87 17.45 5.68 5.78 6.04

    plus a,,, (ksi) 18.35 25.49 24.06 12.29 12.40 12.66

    Table 1: Comparison of moment and stresses from self-weight, kentledges and jacking

    Conclusion

    Jacking Scheme 1 results in the lowest bendingmoment, and the lowest stresseson

    the half span. It may not be feasible to provide one jack with a capacity of 80 tonnes

    (176.4 kips), but the goal of the contractor shouldbe to provide the most upward force as

    close to the midspan as possible.

    Kentledge Scheme1 resulted in the highest bendingmoment, and highest stresses at

    the midspan. The worst case arises when concentratingthe downward force closest to the

    midpoint- thus, it would be better to distribute the load and keepsome weight away from

    the center of the span if weight is used to remove camber.

    The stresses calculated in both kentledge schemes are between 14-19 ksi for both

    flanges. Yet, when adding the approximatestresses thatmight have resulted from wind,

    temperature (uniform and differential) and erection forces, the maximum stresses are

    between 20-26 ksi.

    The stresses in the top flange of span 10-11 would be the greatest concern during

    construction because of the potential compressiveinstability of the flanges working

    without a concrete deck. The range of allowable stress given by BS153 for l/r values

    ranging from 50-90 is 6.8-10.9 tons/in2, or 15.0-24.0 ksi (Royal Commission59). The

    maximum compressive stresses under the two kentledge schemes are just below the

  • 8/11/2019 MIT WestGate Bridge

    42/96

  • 8/11/2019 MIT WestGate Bridge

    43/96

    5. Other Failures

    While box girder bridges offer the benefits mentioned in Chapter 3, they were not

    very well understood at the time. Including the WestGate collapse, therewere fourfailures of box girderbridges of somewhat similar designduring construction in different

    parts of the world from 1969 to 1971. Remarkably, no two of these failures much alike.

    All four, however, were associated with instabilityof thin platesin compression[14].

    The main causesof these failures were: a) the application of buckling theory with

    inadequate factors of safety, and b) poor detailing rules andthe absence of fabrication

    tolerances [14].

    The bridges thatfailed were,in chronological order:

    * The Fourth Danube Bridge (Vienna, Austria,November6, 1969)

    * The MilfordHaven Bridge (now,the Cleddau Bridge) (United Kingdom,June

    2, 1970)

    * The West Gate Bridge(Melbourne,Australia,October, 15, 1970)

    * The RhineBridge (Koblenz,West Germany,November, 10, 1971) [14].

    5.1. Fourth Danube BridgeThe Fourth Danube Bridge consisted of twin box girders in three spans of 393 ft, 688

    ft, and 269 ft. During construction,bucklingwas foundon both box girders at two points:

    at the center of the 393 ft span, and about 197 ft from the right bankpier in the center

    span. The resulting shorteningof the superstructure damagedthe abutment bearings and

    support at the pier. The closing point,havingonly fourweb plates with small flanges, had

    to withstand the full dead weightmoment of the steel loads, andthe web plates were

    stressedbeyond the elastic limit.As a result, the smallupper flanges were twisted and the

    upper sections of the webs plasticallybuckled(Xanthakos 508).Three causesfor the buckling were expressed:

    1) The theoreticalbuckling stress curve used as a basis for the safety checkwas 7%

    higher than the actual buckling stresses in the elastic-plastictransitional range, and the

    bottom plates wherethe damageoccurredwere within this rangeof maximumdeviation.

  • 8/11/2019 MIT WestGate Bridge

    44/96

    2) Deformations caused by welding seams in the bottom plate and its ribs and

    variations in plate thicknessrepresented deviationfrom the assumed ideal straightplane

    of the panel.

    3) Differential temperature in the deck-steel box system,particularly a temperature

    drop during the night, was stated as the principal cause. The roadway deckwas heated

    above air temperature under sunshine, but cooling after sunset caused additional

    compressionstresses in the bottomplates (Xanthakos 508).

    5.2. Milford Haven Bridge

    The Milford Haven Bridge, locatedin Wales, UK, had many featuresin common

    with the West Gate Bridge, includingthe use of a trapezoidal box girder.It consisted of awelded box girder superstructurewith a main span of 700 ft and was claimedto be

    Europe's longest bridge withoutcable support. The trapezoidal box is 20 ft deep, 66 ft

    wide at the top,and 22 ft wide at the bottom (Xanthakos507). The box girderwas much

    smaller in width but much largerin depth thanthe West GateBridge. It was also a single

    cell sectionhaving no internal webs(Royal Commission26).

    The collapse, however,was dissimilar to that of the West Gate Bridge in that it

    originated at a point of negative moment overone of the columns when a span was being

    cantileveredout, whereasin the West Gate Bridge, the failure was ata region of positive

    moment near the center of what was, at the time, a simply supportedspan (Royal

    Commission 12).

    It is clear from the reports of the failure that it was initiated by bucklingof the

    support diaphragm at the root of the cantilever being erected. This diaphragm was

    subjected to a hogging bending momentand a large vertical shear force.The diaphragm

    was torn away from the sloping websnear the bottom of the box, allowing bucklingof

    the lower web and bottom flange to take place [14].

    The diaphragm plate nearthe outer bottom cornerswas subjected to a complex

    combinationof actions. The shearof the transverse girder anddiffusion of the point load

    from the bearings was compoundedwith out-of-plane bendingeffects caused by bearing

    eccentricityand the effects of inclination of the webs of the main bridge girder which

    producedadditionalhorizontalcompressiveaction [14].

  • 8/11/2019 MIT WestGate Bridge

    45/96

    As the diaphragmbuckled it shortened, reducingthe overall depth of the box girder;

    the tendency of the bottom flange to buckle was increased by this reduction of distance

    between flanges,which increasedthe force needed in each flange to carry the moment

    with a reduced lever arm. The weakened section was unableto sustain the momentsimposed and thecantilever rotated about the virtual hinge that was formed (Royal

    Commission12).

    Xanthakos notesthree unforeseen hazardsin the construction of the Milford Haven

    Bridge: a) the diaphragm couldhave been as much as % in out of flat, making it

    susceptible to local buckling, b) the bearing on the pier was out of line with the neutral

    axis of the diaphragm and could impose bendingmoment, and c) some bolts intended to

    be loose in oversized holes were tight, and under loadmovement they couldhave tornthe

    longitudinal stiffenersfrom the bottom flange and made itunstable in compression.Inaddition, subsequent calculations indicated that the diaphragmwould be prone to failure

    when the reactions at the pier supportingthe cantilevered span exceeded900 long tons.

    At the time of failure the reactionwas 963 long tons (507-8).

  • 8/11/2019 MIT WestGate Bridge

    46/96

  • 8/11/2019 MIT WestGate Bridge

    47/96

    In i l.-.,

    Figure 22: Diaphragm over Pier 6 of Milford Haven Bridge

    5.3. Rhine Bridge in Koblenz

    The center span of the Koblenz Bridge over the Rhine River collapsed during

    constructionon November 10, 1971, when erection had almost reached the mid-point of

    the 235 m span. The bridge was a single steel box, 16.4 m wide at the top plus

    cantilevers,and 11 m wide at the bottom. The box was erectedby cantilevering,with 85tons beinglifted at a time [14].

    The bottom flange was stiffened longitudinally by T-stiffeners, and the box was

    stiffened transverselyby frames with diagonals made of 300 mm diameter steel tubes. All

    site joints were welded, a relatively new techniquein Germany at the time. As shown in

    the following figure, a 460 mm gap was provided in the longitudinal T-stiffeners of the

    lower flange to permit the passage of automatic weldingequipmentmaking the transverse

    butt weld splicing the flange plate.The T-stiffenerwas then itself spliced by welding in

    two plates, with the plate splicingthe web of the stiffener being just 460 mm long and

    butt welded. To avoid a local concentration of residual welding stresses, this plate was

    not welded to the bottom flange of the box, but was set with its bottom edge 30 mm clear

    of the flange. The platesplicing the table of the T-stiffener was lappedon top of the ends

    of the two T sections [14].

    S3 -;JII ~L 410 U,'. 11 -

    Elevation Section

    ,I I

  • 8/11/2019 MIT WestGate Bridge

    48/96

    It was determined that:

    * The bottom flange plate, which carriedlarge compressive stresses during

    construction, wasunsupportedover a 460 mm length at each site splice.

    * The main butt weld in the bottom flange plate was atthe center of this 460 mm

    length, possibly introducinga slight lack of straightness.

    * The centroid of the splice of the T-stiffener wasalmost certainlyfurther from the

    flange than that of the T itself, causing an eccentricity that put the flangeplate undera

    larger compressivestress at this point [14].

    The followinginvestigation showed thatthe bottom flange platecould carry its stress

    safely if out-of-straightnesswas no more than 0.95 mm on the 460 mm unsupportedlength. Infact the plate was out-of-straightby as much as 2 mm at some points[14].

    The failure began whenthe flange plate suddenly foldedup at the splice into the 30

    mm recess. Much of the stress that should have been carried by the plate was

    consequently thrownoff onto the T-stiffeners. They were then takingthree times their

    design stress, and they buckled as well, leading toglobal collapse [14].

    An inquiry into the failure concluded thatthere had been no negligence. The design

    calculationshad all been done correctly accordingto the methods normallyused at that

    time in Germany. However, it was the methodsthat needed revision[14].

    A report by the Technical University of Karlruhe indicated that the Rhine River

    Bridge failed because of inadequate stiffeningacross the transverse weld seam in the

    lower flange. Without direct support, the flange plate had a theoretical safetyfactor of

    1.79, but in the presence of the smallestwave in the flange platethis factorwas reduced

    to 1.0. The conclusion was reached thatthe linear theory used to calculate the critical

    buckling stress on the steel plates was inadequate (Xanthakos508-9).

  • 8/11/2019 MIT WestGate Bridge

    49/96

  • 8/11/2019 MIT WestGate Bridge

    50/96

    Figure 25: Schematic diagram of construction joints and their influence on failure

    5.4. Impacts on Other Bridges

    According to Hitchings, the West Gate Bridge was one of the world's most

    troublesome, costly and controversial projects.More than fifty bridges throughoutEurope

    were closed down for examination afterthe collapse, and thirty-four of these had to be

    strengthened beforebring reopened(5).

    One example of a bridge whose design was altered as a result of the failures is the

    Erskine Bridge, a box girder bridge which openedin July 1971, spanning the River Clyde

    in west central Scotland.It was under constructionwhen the Milford Haven and West

    Gate Bridges collapsed. Calculationsin design were remade andit was found that it

    would fail tomeet in the middle. As a result, two cable stayswere added to the box girder

    structure as support [9].

    These failures drew attentionto several fundamental problems associated with the

    ultimate limit stateof box girder bridges, such as: a) the margin of safety during

    Staggered deck platejoints (3 sections perjoints (3ections per Welded joints between adjacenttrough length) 16m long trough units

    Steel plate overjoint in eachstiffener

    One open bulkhead per unit (300mm diagonaltubes and cross beams set back from troughjoint)

    Prior to failure

    Deck flange rotates

    After failure

    noed bulkhead

    ttom flange folds alonga of trough joint

  • 8/11/2019 MIT WestGate Bridge

    51/96

    construction as it relates to theoretical aspectsof failure probabilities,b) the inadequacy

    of linear buckling theoryfor sections thatare wide in comparison to their length, and c)

    the understanding of the ultimate capacity of partially completed steel box girders

    (Xanthakos509).

  • 8/11/2019 MIT WestGate Bridge

    52/96

    6. Behavior of Stiffened Panels

    This chapter providesan overview of the modes of buckling of stiffened panels as

    understoodfrom 1997 to 2004.

    6.1. A contribution to the stability of stiffened plates under uniform compression

    (1997)

    This paper first presents a comprehensive literature review of research done on the

    stability of stiffened platesunder compressive load, covering global (or overall)buckling,

    local buckling, ultimatestrength, andsensitivityto imperfection.

    Six modes of bucklingare presented:

    Mode I (Fig. 26 a) - This mode is symmetric andis commonly knownas global or

    overall mode. It occurs whena wide plate buckles together withthe stiffener, which may

    be considered "light."

    Mode II (Fig. 26 b) - This mode is antisymmetric andis commonly knownas the

    local mode. It occurs when the stiffener is flexurally stiff and torsionally weak.In this

    case, the stiffener subdivides the plate into several segments of width "S," with

    longitudinal edges almostrotationallyfree.

    Mode III (Fig. 26 c) - This is an intermediate modethat is possible if the stiffener is

    not flexurallystiff.

    Mode IV (Fig. 26 d) - This is a symmetric modethat is possible if the stiffener is

    both flexurally and torsionally stiff. In this case, the longitudinal edge of each panel is

    rotationally clamped,leading to a higher bucklingload for eachpanel than in Mode II.

    Mode V and VI (Fig. 26 e and f) - These modes occurif the stiffener is slender and a

    torsional bucklingmode or localbuckling of the plate componentsof the stiffener results

    without participationof the plate [2].

  • 8/11/2019 MIT WestGate Bridge

    53/96

    ia)- Mode [ ib)- Mode 11

    ic0- Mode Ill d)- Mdxle IV

    'e)- Mode V (rb- Mode VI

    Figure 26: Various buckling modes of stiffened plates

    Combinations of these buckling modes are also possible when two or more local

    modes interact. Therefore, the buckling mode of the structure depends onthe geometric

    characteristicsof the attached stiffener [2].

    Despite the wide literature on stiffened plates, littleis known aboutthe geometric

    proportionsof the plate andstiffeners requiredto triggerthese bucklingmodes [2].

    From a design perspective, it is important to first study the geometric interaction

    between the plate and the stiffener elements, and to showthe transitionfrom the overallto the local mode. Then,it might be possible to proportion the structure to either buckle

    locally orin a global mode. The ultimatestrengthof the structurecan then be determined

    based on this information [2].

    The second part of the paper presents theoretical formulations for the stability

    analysisof stiffenedplates underuniform compression.The strain energycomponents fo r

    the plate and stiffener elements are derived in terms of the out-of and in-planedisplacement functions and sequential quadratic programming is used to find the

    buckling load of the structure for the given plate/stiffenergeometric proportions.Theefficiencyof this methodis comparedwith the finiteelementmethod [2].

  • 8/11/2019 MIT WestGate Bridge

    54/96

    6.2. Stiffened steel plates under uniaxial compression (2001)

    Stiffened plates under uniaxial compression or under combined bending and

    compression can buckle in one of four forms:

    Plate-inducedbuckling (Fig. 27 a) and stiffener-inducedoverall buckling (Fig. 27 b):Overall buckling (sometimes referred to as Euler buckling) is characterized by the

    simultaneous buckling of the stiffener and the plate. If the buckling occurs with the

    stiffener on the concave (compression)side of the plate, overall bucklingis said to be

    stiffener-induced.If the stiffener is on the convex side of the plate, overallbuckling is

    said to be plate-induced. These two failure modes are typically characterizedby a very

    stable post-buckling responsewhere buckling is characterized by a sharp change in

    stiffness.

    Plate buckling (Fig.27 c):

    Plate buckling failure is characterizedby buckling of the plate between the stiffeners,

    resulting in a load redistributionfrom the plate to the stiffeners. This failure mode tends

    to have a more significant drop in load carrying capacityin the post-bucklingrange than

    the overallbuckling failure modes.

    Stiffener tripping(Fig. 27 d):

    Stiffener trippingis characterizedby the rotation of the stiffener aboutthe stiffener-

    to-plate junction. Therefore, it is a form of lateral-torsionalbuckling where torsion takes

    place about this junction. As opposed to other modes of failure, stiffener tripping

    generally results in a sudden loss of load carrying capacity. Becauseof this suddendrop

    in capacity accompanying stiffener tripping,this mode of failure is considered a more

    critical failure mode than the other stiffened plate failuremodes previously identified.

    However, this failure modehas received far less attention than the other modes [19].

  • 8/11/2019 MIT WestGate Bridge

    55/96

    (d)

    Figure 27: Typical buckling modes

    The following figure illustrates load versus deformationbehavior of the modes

    described above. These relationshipswere also observed experimentally[19].

    1.2Overall Buckding(Plate induced)

    1 . 0 .--- __ __ _

    / OverallBuckling (Stiffener induced)S 0.8 -... . . - ------------

    P 0.6 - - . Plate Buckling

    0.4

    0.2Stiffener Tripping

    0.00.000 0.002 0.004 0.006 0.008 0.010 0.012

    U 1/Lu

    Figure 28: Load versus deformation behavior

    The failure modes observedwhen a stiffenedplate is subjected to a concentric load

    consist of overall buckling, plate buckling, or a combinationof these twomodes, referred

    to as "interaction buckling." In all the cases investigatedwith stiffened plates subjectedto

    axial load only, no failure took place by stiffener tripping. Both the plate buckling and

    plate-induced overall buckling behaviors are considered to be stable failure modes,characterized by a very slow decrease in capacity. However, the interaction between

  • 8/11/2019 MIT WestGate Bridge

    56/96

  • 8/11/2019 MIT WestGate Bridge

    57/96

    save significant repair and maintenancecosts over the lifetime of the vessel [8]. These

    benefitsmay be related to thoseof usingbulb flatsin bridges.

    The investigationof stiffened plates is carried out in three general forms: theoretical,

    using classical and emerging theory; numerical, using finite element methods andcomputer-aidedsimulation; and experimental,using stiffened plates under compressive

    loading. Most of what is known of the behavior of bulb flat stiffenedplates appears to

    come from numerical and experimentalinvestigations. The paper attempts to consider

    new theoretical insights into the behaviorof stiffenedplates [8].

    Previously, the onlypublishedwork on bucklingbehavior of bulb plates consisted of

    Chou (1997), Chou and Chapman(2000) and Chou et al. (2000). Their analysis idealizes

    the bulb flat flangeas an equivalent angle flange, treating the bulb flat cross section like a

    rectangular cross section with regard to the bulb flat torsional and warping properties.

    Danielson and Wilmer show that this idealization creates errorin the calculation of the

    bulb flat stiffener's torsional rigidity, resulting in conservative estimates. Finite element

    analysis shows that the torque-carryingcapacity of a bulb flat stiffener(with no structural

    flaws) is greater than that of an angle stiffenerwith an equivalent area [8].

    The authors used an energy method to derive general expressions to predict the

    buckling stress due to stiffener tripping of a simply supported rectangular stiffened plate

    subjected to axial compression. The onset of stiffener tripping negates the stiffener's

    support to the plate panel and leads to the eventual collapseof the structure[8].

    For stiffeners with a bulb flat flange, the values predicted with a simple formula are

    less than 4% higher than the finite element results [8].

    The modesof deflection identified in the paper are:

    Mode 1 (Fig. 29 a) - This mode is described as a bending of the web in one half-

    wave anda rotation of the flange about a point at the top of the web. There is no flange

    bending along its length. This mode could occur when the flange bending stiffness is

    large comparedto the flange torsionaland webbendingstiffnesses.Mode 2 (Fig. 29 b) - This deflection corresponds to a significant bending of the

    flange and web with no flange torsion. This mode could occur when the flange torsional

    stiffness is large comparedto the flangeand web bendingstiffnesses.

  • 8/11/2019 MIT WestGate Bridge

    58/96

    Mode 3 (Fig. 29 c) - This deflection correspondsto the flange exhibiting a

    combinationof bending and twistingwhile the web tends to remain straight. Thismode

    could occur when the web bending stiffness is large comparedto the flange torsional and

    bending stiffnesses. This case is likely to occur when the flange offers little or noadditionalstiffness to the platestructure comparedto the contribution of the web [8].

    - -)

    Figure 29: Various modes ofdeflection

    -

  • 8/11/2019 MIT WestGate Bridge

    59/96

    7. Stiffness Requirements for Stiffeners of Compression Panels

    7.1. Research by Choi and Yoo (2006)

    In light of the complex nature of the behavior and analysis of stiffened panelsundercompressionthere are few, if any, "hard and fast" rules to their design. Several codes,

    including Eurocode,British Standard, and AASHTO(AmericanAssociation of State and

    Highway Transportation Officials) specify minimum stiffnesses for transverse and

    longitudinal stiffeners of compression panels. However, these requirements are for

    narrower box girders with fewer longitudinalstiffeners, compared to the West Gate

    Bridge. Thischapter will show that extrapolationof AASHTO requirementsfor single-

    cell box girders of larger scales (greaterwidth and more longitudinal stiffeners) is not an

    effective method for the designof such a structure.

    Choi and Yoo say the AASHTO requirementsare inconsistent. In recent yearssome

    confusion has arisen due to the differentrules adopted in the AASHTO specifications

    guiding the design of transverse flange stiffeners. Articles10.39.4.4.1 and 10.39.4.4.2

    state that the transverse stiffeners mustbe proportionedso that the moment of inertia of

    each stiffener aboutan axis throughthe centroid of the section and parallelto its bottom

    edge is at least equal to:

    I, =0.10(n +1) 3 W3 fs A()E a

    where:

    w = width of flange between longitudinal stiffeners ordifference from a web to the

    nearest longitudinalstiffener

    Aj= area of the bottom flange, including longitudinal stiffeners

    a = spacingof transverse stiffeners

    E = modulus of elasticity

    fi = maximum longitudinalbending stress in the flange of the panels on eitherside ofthe transverse stiffeners [5].

    Because Af and f, are mutually interdependent, there can be a large number of

    combinations of these two parameters thatsatisfy the equation. Therefore, the proper

  • 8/11/2019 MIT WestGate Bridge

    60/96

    choice of the parameters is an iterative process in which the designer's intuition is

    significant [5].

    The Eurocode specification for stiffness of transverse stiffeners requires a

    "complicated iterative process" becauseof parameters thatare interdependentor directlycoupled with It, [5].

    Article 10.51.5.4.4 of the load factor design of AASHTO requires the minimum

    stiffness fortransverse stiffeners to be:

    I s = p t w (2)

    where p = 0.125k 3 for n = 1 and (p = 0.07k 3n 4 for n = 2, 3, 4, or 5. k is a bucklingfactor

    which shouldnot exceed 4. These rules are the same as those adoptedin the 2 nd editionof

    the AASHTO LRFD manual. Morerecently, the 3

    rdedition of the AASHTO LRFD

    manual uses equation (1) for the design of transverse stiffeners and equation(2) for the

    longitudinal stiffeners. It has been suggestedthat equation(2) requires an unreasonably

    high value of ridigity, especially when the number of longitudinal stiffeners becomes

    large. Choi and Yoo believe that an overly conservative approachhas been adopted

    during the course of simplifying and extrapolating the limited research results for

    multiple stiffeners. Recognizing this "awkwardness," the latest AASHTOspecifications

    suggest that the number of longitudinal stiffeners should be preferably limitedto two.

    The authors say that a thorough examination is clearly required to clarify this issueofrequiredminimum stiffness [5].

    Yoo et al. numerically identified the minimum stiffnessrequirement for longitudinal

    flange stiffeners andproposed a new equation that couldrationally replacethe current

    AASHTO design standard. This relationshipis:

    I, = 0.3a 2 ntf3w (3)

    where a = a / w = aspect ratioof a subpanelof a stiffened flange[5].

    The term "subpanel" refers to a portion of a steel panel bounded by adjacent

    longitudinalstiffenersor webs and their adjacenttransverse stiffeners[5].

    Transverse stiffenersused as bracing members for longitudinal stiffeners should

    have sufficient bending stiffness to effectively restrainthe longitudinal stiffeners. This

    requirement pertainsto both the "column behavior" model adopted in Eurocode and BS

  • 8/11/2019 MIT WestGate Bridge

    61/96

    5400 and the "plate behavior" approach adopted in AASHTO. As the aspect ratio of the

    subpanel is one of the most influential parameters determiningthe minimumstiffness ofthe longitudinal stiffener, it should also be an equally important parameter defining the

    required strength andspacingof adjacent transversestiffeners [5].The authors say that there are no reliable design guides that rationally define the

    minimum stiffnessrequirement and the spacing of transverse stiffeners,particularlyfor

    the "plate behavior" approach adoptedby AASHTO[5].

    The data resulting froma series of non-linear incremental analyses and elastic

    buckling analyseswas reduced by means of a regression processto extract analytical

    equations. The validity of these equations wasthen tested usingthe results of parametric

    studies for the minimum stiffness requirementof transverse stiffeners[5].

    td)

    Lki. udinSlif ener

    Sliri

    t

    -tQ

    I=.

    IZ= ------A=

    ColumnApproximaliin

    ip ,

    cQ.I

    Q = k '

    P [) I~c'

    (h~) C

    Figure 30: Column approximation of a typical stiffened flange

    The figure above gives an overview of the column approximation of a typical

    longitudinallyand transverselystiffened flange.

  • 8/11/2019 MIT WestGate Bridge

    62/96

    Fig. 30 (a) shows the stiffened flange, Fig. 30 (b) shows the laterallybraced column

    approximation, Fig. 30 (c) shows behavior when the transverse rigidity k, is sufficient,

    and Fig. 30 (d) shows the simple beam approximationof a transverse stiffener.

    In both the "columnbehavior" and "platebehavior" concepts, the roleof a transversestif