Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal  held on 31.01.2012 at  12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   ___________________________________________________________________ Name of the members who were present in the meeting are as follows: - 1. Shri  Manoj Kumar Nandi Vice Chairman, SEAC 2. Prof. Subhash Chandra Santra Member, SEAC 3. Dr. Kalyan Rudra Member, SEAC 4. Shri Somnath Bhattacharyya Member, SEAC 5. Shri Arijit Banerjee Member, SEAC 6. Dr. S. P. Sinha Ray Member, SEAC 7. Shri Sandipan Mukherjee, I.F.S. Secretary, SEAC & Member Secretary, WBPCB In the beginning of the 63 rd  meeting of SEAC, which was held on 31.01.2012 at 12:00 hrs at the Conference Room, Paribesh Bhawan, Bidhan Nagar, the Secretary, SEAC welcome all the members. After introductory session, nine cases were placed for reconsideration. One additional issue was discussed under 'Miscellaneous' section. Five applicants were requested to make their presentation before the committee. All the five applicants appeared before the SEAC for technical presentation on their respective project proposal. Session I A. Reconsideration proposals: - Nine reconsideration proposals were placed in the meeting. 1. Proposed Cement Grinding Unit of M/s. U.K. Cement Pvt. Ltd. at Jl. No. – 58, Vill. & Mouza – Bamunara, Bamunara Industrial Area, Durgapur, GP – Gopalpur, PO – Panagarh Bazar, PS – Kanksa, Dist. - Burdwan, Pin – 713212, West Bengal. Activity: This is a proposal for installation of a Cement Grinding unit (1200 TPD) with one no. coal fired Slag drier (500 TPD) for production of Portland Slag Cement & Portland Pozzolana Cement (360000 TPA). Chronology of the event: The proponent obtained Environment Clearance from SEIAA, West Bengal on 17.03.2011 for the proposed site at Jl. No. – 58, Dag No. – 1943 – 1955, Vill. & Mouza – Bamunara, Bamunara Industrial Area, Durgapur, GP – Gopalpur, PO – Panagarh Bazar, PS – Kanksa, Dist. - Burdwan, Pin – 713212, West Bengal, having land area 5.68 acres. Subsequently, the proponent applied for Consent to Establish to the West Bengal Pollution Control Board. On detailed scrutiny it was found that land area in above dag nos. is only 50 decimal or 0.5 acres. The Member Secretary, SEIAA vide letter dated 05.08.2011 intimated that the proponent has applied for amendment of Environmental Clearance regarding dag nos. The proponent has informed vide letter dated 26.08.2011 that there are total 83 nos. of plots covering land area of 5.68 acres. The proponent also submitted supporting documents from BL&LRO, Kanksa Block, Dist. Burdwan. However, dag nos. 1947 – 1950 is not included in the list of dag nos. submitted. Page 1  of 33

Transcript of Minutes of the tenth meeting of the State Level Expert...

Page 1: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Name of the members who were present in the meeting are as follows: ­

1. Shri  Manoj Kumar Nandi Vice Chairman, SEAC2. Prof. Subhash Chandra Santra Member, SEAC3. Dr. Kalyan Rudra Member, SEAC4. Shri Somnath Bhattacharyya Member, SEAC5. Shri Arijit Banerjee Member, SEAC6. Dr. S. P. Sinha Ray Member, SEAC7. Shri Sandipan Mukherjee, I.F.S. Secretary, SEAC & Member Secretary, WBPCB

In   the   beginning   of   the  63rd  meeting   of  SEAC,  which   was   held   on   31.01.2012   at   12:00   hrs   at   the Conference Room, Paribesh Bhawan, Bidhan Nagar, the Secretary, SEAC welcome all the members. After introductory session, nine cases were placed for reconsideration. One additional issue was discussed under 'Miscellaneous' section. Five applicants were requested to make their presentation before the committee. All the five applicants appeared before the SEAC for technical presentation on their respective project proposal.

Session I

A. Reconsideration proposals: ­Nine reconsideration proposals were placed in the meeting.

1. Proposed Cement Grinding Unit of M/s. U.K. Cement Pvt. Ltd. at Jl. No. – 58, Vill. & Mouza – Bamunara, Bamunara Industrial Area, Durgapur, GP – Gopalpur, PO – Panagarh Bazar, PS – Kanksa, Dist. ­ Burdwan, Pin – 713212, West Bengal.

Activity:

This is a proposal for installation of a Cement Grinding unit (1200 TPD) with one no. coal fired Slag drier   (500 TPD)  for  production of  Portland Slag  Cement  & Portland  Pozzolana Cement  (360000 TPA). 

Chronology of the event:

The  proponent obtained Environment Clearance from SEIAA, West Bengal on 17.03.2011 for the proposed  site  at  Jl.  No.  –  58,  Dag No.  –  1943 –  1955,  Vill.  & Mouza  –  Bamunara,  Bamunara Industrial Area, Durgapur, GP – Gopalpur, PO – Panagarh Bazar, PS – Kanksa, Dist. ­ Burdwan, Pin – 713212, West Bengal, having land area 5.68 acres.

Subsequently, the proponent applied for Consent to Establish to the West Bengal Pollution Control Board. On detailed scrutiny it was found that land area in above dag nos. is only 50 decimal or 0.5 acres. 

The Member Secretary, SEIAA vide letter dated 05.08.2011 intimated that the proponent has applied for amendment of Environmental Clearance regarding dag nos.

The proponent has informed vide letter dated 26.08.2011 that there are total 83 nos. of plots covering land area of 5.68 acres. The proponent also submitted supporting documents from BL&LRO, Kanksa Block,   Dist.  Burdwan.  However,  dag  nos.   1947  –  1950  is   not   included   in   the   list   of   dag  nos. submitted.

Page 1 of 33

Page 2: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

The matter is placed for discussion in the 59th SEAC meeting held on 20.09.2011. During discussion in the 59th SEAC meeting held on 20.09.2011, the committee reviewed the letter dated 26.08.2011 and noted that :­

1. The   project   proponent   have   obtained   Environment   Clearance   from  SEIAA,   West   Bengal   on 17.03.2011 for   the proposed site  at  Jl.  No. – 58,  Dag No. –  1943 – 1955,  Vill.  & Mouza – Bamunara, Bamunara Industrial Area, Durgapur,  GP – Gopalpur, PO – Panagarh Bazar, PS – Kanksa, Dist. ­ Burdwan, Pin – 713212, West Bengal, having land area 5.68 acres.

2. However, the project proponent have informed vide letter dated 26.08.2011 that there are total 83 nos. of plots covering land area of 5.68 acres. The unit has submitted supporting documents from BL&LRO, Kanksa Block, Dist. Burdwan. However, dag nos. 1947 – 1950 is not included in the list of dag nos. submitted.

3. It   is   not   clear   from   the   submission   whether   the   land   parcel   which   was   shown   during   the presentation through satellite imagery before the SEAC and the land parcel which comprises of 83 number of plots, are same or there is any difference. The SEAC requests the project proponent to kindly confirm whether the latitude­longitude provided for the project location is still applicable in this case or not.

 The reply of the proponent submitted on 17.11.2011 are as follows :­

a) The proponent has mentioned that the land parcel of 5.68 acres for the proposed cement plant covering  83  nos.  of  plots   is  same as   that   shown during  presentation  before  SEAC. The latitude­longitude mentioned earlier is still applicable for the proposed project.

b) The proponent has also mentioned that dag nos. 1947­1950 are not situated in the 5.68 acres land parcel. However, the index map submitted is not clearly legible.

Further,   the   prayer   for   amendment   of   dag   nos.   in   original   Environmental   Clearance   has   been forwarded by the Member Secretary, State Environment Impact Assessment Authority, West Bengal vide letter dated 15.11.2011. However, the enclosure was not found.

The   letter   dated   17.11.2011   was   placed   for   consideration   in   the  61st  SEAC   meeting   held   on 29.11.2011. During discussion in the 61st SEAC meeting held on 29.11.2011, the committee requested the proponent vide letter dated 19.12.2011 to submit an undertaking that layout with RS no., list of Dag no. and Latitude Longitude has been provided for same land parcel, which was shown in the presentation made in the 49th SEAC meeting held on 03.12.2010.

The project   proponent   submitted   their   reply  on  03.01.2012.  They  submitted   the  undertaking   that layout with RS no., list of Dag no. and Latitude Longitude have been provided for same land parcel, which was shown in the presentation made in the 49th SEAC meeting held on 03.12.2010.

The case was placed for reconsideration in the 63rd SEAC meeting held on 31.01.2012.

After scrutinizing the documents submitted by the unit, the SEAC has approved the amendment of Environmental Clearance with 83 nos. plots as mentioned in the documents of  BL&LRO, Kanksa Block, Dist. Burdwan, in the 63rd meeting held on 31.01.2012. The copy of the summary decision of the said SEAC meeting alongwith other relevant documents is forwarded to the State Environment Impact Assessment Authority, West Bengal for necessary action and perusal.  

Page 2 of 33

Page 3: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

2. Proposed expansion of Cement Grinding Unit by M/s. Shri Shankar Suwan Estate Pvt. Ltd. at Jl. No. 24, Mouza – Balanpur, PS – Kanksa, PO – Ikra, Jamuria Municipality, Pin – 713362, Dist – Burdwan, West Bengal. Name of the Environmental Consultant – M/s. Environ India.

 Activity:

This is a proposal for expansion of an existing Cement Grinding unit through installation of 2x50 TPD grinding mill for additional production of Portland Slag Cement (30000 TPA). The existing plant has 2x50 TPD cement grinding mill with coal fired slag drier (50 TPD). It is noted that clinker will not be manufactured at the site. The manufacturing process will involve grinding of Cement Clinker with Slag and Gypsum. 

Chronology of the event :

During  the  presentation   in   the  61st  SEAC  meeting  held   on  29.11.2011,   the  State  Level  Expert Appraisal Committee (SEAC), West Bengal, has noted that­ 

a) A pond is present in the  factory premises.b) The project proponent has verbally agreed to comply with the stringent standard for particu­

late emission of 50 mg/Nm3 in the existing plant.c) The proponent has not yet obtained permission for groundwater abstraction in the existing 

plant.

Further   the   SEAC   made   the   following   recommendations   in   the  61st  SEAC   meeting   held   on 29.11.2011­  Subsequent response dated 24.01.2012 from the unit is given below : –

Recommendations / Directions of the Committee, issued on 19.12.2011

Response of the Proponent submitted on 24.01.2012

1. The   project   proponent   should   obtain the   permission   for   groundwater abstraction   for   the   existing   plant   at first.

1. The project proponent has mentioned that water is being   used   for   domestic   purposes   only   and   no process water is required for the operation of the Cement Grinding Unit. As per notification issued by Water Resources Investigation & Development Department,   domestic   users   –   with   sump   or overhead tank upto 10000 ltrs. are exempted from obtaining   permission.   However,   for   permission towards abstraction of groundwater which will be used for domestic purposes only, application has already   been   submitted   to   State   Water Investigation Dept. 

2. The   proponent   should   retain   the existing pond and utilise the same for Rainwater Harvesting. The proponent should submit authenticated document regarding   size   of   pond.   The   project proponent should overlay the site plan on   the   Mouza   map   for   showing   the location of the existing pond.

2. The project proponent has submitted that the area marked as pukur and mentioned in the Mutation Certificate is outside the proposed project area of M/s. Sri Shankar Suwan Estate Pvt. Ltd. and M/s. Satwik Metals Pvt. Ltd. and is being kept as an open   area   without   any   construction   or development.   The   area   will   be   utilised   for rainwater harvesting.

Page 3 of 33

Page 4: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Recommendations / Directions of the Committee, issued on 19.12.2011

Response of the Proponent submitted on 24.01.2012

3. Scaled  plant   layout   showing  existing and   proposed   facilities,   Greenbelt area,   Rainwater   Harvesting   storage area, internal roads, storage sheds etc. on a suitable grid should be submitted.

3. The proponent has submitted the copy of layout.

4. The plantation area should be 33% of the land area.

4. The proponent has mentioned that the total land area considered for the project is 3.282 acres, out of which 1.09 acres (33% of total land) has been allocated for greenbelt development. Plantation is being  developed  as   a   continuous  process   along with periphery of the plant in line with the area shown in the plant layout.

The case was put up for reconsideration in the 63rd SEAC meeting held on 31.01.2012. 

After scrutinizing the documents submitted by the unit, the committee has noted that this is a proposal for expansion of existing Red category unit located under Jamuria Municipality, Dist – Burdwan. As per the siting policy of WBPCB, Special Red & Red category industries are not permitted to set up within the municipal areas of Burdwan District except Jamuria Industrial Area. 

Therefore, before consideration of the proposal, the unit is requested to obtain in principle approval from   the  West  Bengal  Pollution  Control  Board   for   the  proposed  expansion  of   the   existing  unit. Furthermore,   the   committee  has   not   yet   received  permission   for   drawl  of   groundwater   from   the concerned authority. 

It has been decided that the case shall be further considered only  after  submission of  the  necessary clarification.

3. Proposed Township Project (PHASE IA) by M/s. Kolkata West International City (P) Ltd. at Mouza – Kona, Balitikuri, Bankra, Pakuria, Tentulkuli, Khalia & Salap, PO & PS – Domjur, Dist – Howrah.

Activity:

This is a proposal for development of a Township with 9000 dwelling units, commercial facilities and other infrastructural facilities. The proposed development shall comprise of 5 phases. 

Chronology of the event :

The   State   Level   Expert   Appraisal   Committee   (SEAC)   has   granted   Provisional   Environmental Clearance for the proposed Township project in the 7th meeting held on 26.07.2007. The proponent mentioned that the proposed development shall comprise of 5 phases.

Subsequently, the proponent obtained Environmental Clearance from the  State Environment Impact Assessment Authority, West Bengal for PHASE – I of the proposed project on 11.11.2008.

Page 4 of 33

Page 5: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

The proponent obtained amendment of the said Environmental Clearance from the State Environment Impact Assessment Authority, West Bengal for PHASE – I of the proposed project on 04.02.2010.The proponent has submitted vide letter dated 08.09.2011, sanctioned plan for PHASE – IA along with key plan sanctioned by KMDA, comparative statement and other documents. The proponent has mentioned that status of construction of PHASE – I is vacant land.Salient features of the proposed PHASE – I is given below: ­

Salient Features As per Provisional EC

Phase I 

(EC Obtained)

Phase IA 

(EC Applied for)Land Area  390.165 acres 89.174 acres 4.283   acres   (17272.98 

sqm.)

Expected Population  45000 4550 2324

Building profile

Water requirement (Operation stage)

10000 KLD 690 KLD 335 KLD

Wastewater generated  7500 KLD 518 KLD 262 KLD

Firefighting Water demand 

700 KL 200 KL 300 KL

Solid waste disposal  24.99 TPD 2.53 TPD 1.12 TPD

Total Built­up Area Not mentioned  165202.4 sqm. 52736.43 sqm.

Ground Coverage  167.77 acres 18.2 acres 0.967   acres   (3913.55 sqm.), 22.578%

Landscaped area with waterbody

128.76 acres 22.85 acres 1.019 acres (23.792%)

Waterbody 3.7 acres NIL NIL

Road & Pathway 93.64 acres 21.4 acres 2.297 acres (53.63%)

No. of Car Parking spaces proposed

33000 nos. 1811 nos.  210 nos.

Power requirement  32 MVA 4.5 MVA 1.9 MVA

Backup Power  DG   Sets   (3x625 KVA, 10x750KVA   & 6x1010 KVA)

DG   Sets   (2x65 KVA)

DG Sets (2x380 KVA)

The case was placed in the 59th SEAC meeting held on 20.09.2011 and the SEAC noted that the total project area is 390.165 acres. The project proponent earlier obtained Environmental Clearance from the State  Environment Impact Assessment Authority,  West  Bengal for PHASE – I  comprising of 89.174 acres. Now the unit applied for PHASE – IA which is only 4.283 acres. The SEAC requested the project proponent vide letter dated 30.09.2011 to consider the project in an integrated manner and also to explain the reasons for reverting to the proposal for sending the sewage to the KMW STP instead of augmenting the capacity of the STP at the project site in a modular form. The SEAC also 

Page 5 of 33

Page 6: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

desired to review the compliance status of the PHASE – I for which Environmental Clearance has already been granted.

The proponent has submitted their reply on 22.11.2011. The proponent has mentioned that as per development agreement with KMDA, the sewer line is to be connected to KMW & SA STP at Kona. However,   Kona  STP   was   too   far   from   PHASE  –   I   development   and  development  planning   for finalisation of the route of the sewer line could not be done for PHASE ­ I. Hence, construction of STP of 650 KLD was considered for PHASE – I. If it is not feasible to connect the sewer line for PHASE – IA, the capacity of the existing STP will be enhanced.

The progress status of PHASE – I as mentioned by the proponent is as follows:­

Total no. of units as per EC

Total No. of units as per sanctioned 

plan.

Completed unit

CC obtained

CC applied Consent­to­Operate obtained

Consent­to­

Operate to be applied 

shortly

910 907 370 269 101 179 191

The comparative statement for PHASE – I and PHASE – II as mentioned by the proponent is given below :­

Salient Features As per Provisional EC

Phase I (EC Obtained) Phase IA (EC Applied for)

Land Area  390.165 acres 89.174 acres 4.283 acres 

(17272.98 sqm.)

Expected Population  45000 4550 (as per the EC)

4535   (as   mentioned   by the proponent)

2324

Building profile

Water requirement (Operation stage)

10000 KLD 690 KLD  335 KLD

Wastewater generated  7500 KLD 518   KLD   (as   per   the amended EC)

513   KLD   (as  mentioned by the proponent)

262 KLD

Firefighting Water demand 

700 KL 200 KL 300 KL

Solid waste disposal  24.99 TPD 2.53 TPD (as per the EC)

2.52  TPD (as  mentioned by the proponent)

1.12 TPD

Page 6 of 33

Page 7: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Salient Features As per Provisional EC

Phase I (EC Obtained) Phase IA (EC Applied for)

Total Built­up Area Not mentioned  165202.4 sqm. 52736.43 sqm.

Ground Coverage  167.77 acres 18.2 acres  0.967 acres 

(3913.55 sqm.), 22.578%

Landscaped area with waterbody

128.76 acres 22.85 acres 1.019 acres (23.792%)

Waterbody 3.7 acres NIL NIL

Road & Pathway 93.64 acres 21.4 acres 1.648 acres (53.63%)

No. of Car Parking spaces proposed

33000 nos. 1811 nos.  210 nos.

Power requirement  32 MVA 4.5 MVA 1.9 MVA

Backup Power  DG   Sets   (3x625 KVA, 10x750KVA   & 6x1010 KVA)

DG Sets (2x65 KVA) DG Sets (2x380 KVA)

The   letter   dated   22.11.2011   was   placed   before   the   SEAC   in   the  61st  SEAC   meeting   held   on 29.11.2011  and the committee requested the project proponent vide letter dated 19.12.2011 that as requested earlier the  renewed agreement / concurrence of KMW&SA for accepting the sewage and treating in KMW&SA STP was not made available to SEAC till 29.11.2011. The SEAC requested the proponent to confirm the STP proposal.

The reply of the proponent submitted on 03.01.2012 are as follows :­

1. The proponent has mentioned that the SEAC already accorded clearance to connect the waste water  of   the  entire   township   to  KMW&SA STP at  Kona having   capacity  40  MLD vide SEAC's letter dated 16.08.2007.

2. The   proponent   has   also   mentioned   that   they   have   already   conveyed   vide   letter   dated 30.04.2009 about some practical difficulties in sending sewer of Phase­I to KMW&SA STP. Accordingly  they  constructed a  separate  650 KLD capacity  STP dedicated for   this  phase within the site and obtained the Environmental Clearance.

3. Further, the proponent mentioned that they propose to construct another 300 KLD STP (Mod­ular   type)  for  Phase IA. The location of   the said proposed STP along with sewer  line  is marked in the annexed plan. 

The case was put up for reconsideration in the 63rd SEAC meeting held on 31.01.2012.

After scrutinizing the documents submitted by the unit,    the committee requested the unit to present the case through a power point presentation in the 64th Meeting scheduled to be held on 16.02.2012 at 12.30 pm at the Conference Room of Paribesh Bhavan, 2nd Floor, Bidhannagar. The following issues must be addressed in the presentation:

1. The compliance status of Phase I for which EC has been already granted including present source and quantity of water consumed

Page 7 of 33

Page 8: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

2. The project proposal for Phase IA. 3. Justification for the proposal of construction of another 300 KLD STP (modular type) for 

Phase IA for sewage treatment. 

It is also informed that the unit is required to comply with the Office Memorandum dated 30.09.2011 and 05.10.2011, issued by the Ministry of Environment & Forests, Government of India.

4. Proposed  Infrastructure cum Logistic Hub “FREIGHT PORT” by M/s. Bengal Anmol South City Infrastructure Ltd. at Jl. No. – 2 & 13, Mouza – Joypurbill & Jagdishpur, PS – Liluah, Dist. – Howrah, West Bengal. 

Activity:

This is a proposal for development of an Infrastructure cum Logistic Hub consisting of Warehouse (4 blocks of B+G+3 storied buildings), Retail Area (2 blocks of G+4 storied buildings), Office (1 block of B+G+6 storied building), Captive Housing (4 blocks of G+5 storied buildings) with 108 flats and MLCP (1 block of G+3 storied building) alongwith loading, unloading bays and parking spaces with total built up area – 1,38,325 sqm. 

Chronology of the event :

The information provided in the application for Environmental Clearance for the proposed project was found to be insufficient. The letter dated 05.04.2010 was issued to the proponent for submission of necessary information. The proponent submitted on 07.04.2010 the status of the writ petition made by Jalabhumi Banchao Committee & Org. at the High Court, Calcutta. 

Further, the SEAC received one copy of order, which states that “it is made clear that the issue before the Court is in respect of filling up or conversion of water body and not agricultural land. In case the authorities are in doubt as to the particular piece of land comes within the definition of water body they  would not  permit   its  conversion without bringing  it   to   the  notice of   this  Court  and seeking appropriate order/direction in the matter, otherwise, in our view, there is no restriction placed by this Court on the State Government in processing the cases of conversion of agricultural land”.

The letter dated  15.07.2010 was placed in the  45th SEAC meeting held on 03.08.2010. The SEAC noted the following : – 

1. The   land   conversion   is   still   under   process   and   the   project   proponent   is   yet   to   submit conversion status for 3.16 acres of water body. 

2. The   copy   of   the   order   of   the   Hon’ble   Chief   Justice   and   the   Hon’ble   Justice   Bhaskar Bhattacharya of Kolkata High Court, which states that “it is made clear that the issue before the Court is in respect of filling up or conversion of water body and not agricultural land. In case the authorities are in doubt as to the particular piece of land comes within the definition of water body they would not permit its conversion without bringing it to the notice of this Court and seeking appropriate order/direction in the matter, otherwise, in our view, there is no restriction placed by this Court on the State Government in processing the cases of conversion of agricultural land”.

The SEAC requested the proponent vide letter dated 17.08.2010 to submit the authenticated document on status of conversion vis­à­vis the project proposal along with concurrence letter from the concerned 

Page 8 of 33

Page 9: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

authority   for  ensuring  water   supply,   emergency  discharge  of   treated  wastewater  and   solid  waste disposal at an earliest. The proponent was also requested to mention the existing vegetation, if any, at the  proposed  site.  The  proponent  was  also   requested   that   as  per   the  circular  by   the  Ministry  of Environment & Forests, Government of India, only the enlisted consultants, if any, other than the proponent themselves, are permitted to appear before the SEAC. 

The proponent stated vide letter dated 10.03.2011 that –

1. The proponent has mentioned that they will retain the waterbody, hence conversion will not be done. The copy of conversion certificate for some plot nos. submitted.

2. The copy of the High Court Order dated 06.07.2010 submitted earlier is again enclosed.

3. The   copy   of   the   letter   dated   25.02.2011   of   the   Executive   Engineer,   Howrah   Irrigation Division, for discharge of additional runoff (not effluent) to Br. No. 1 of Howrah Drainage Canal.

4. The copy of the application for sinking 2nos. tubewell each 12m3/hr x 10hr.

5. Section drawing of the canal submitted.

The proponent has not yet submitted –

1. Concurrence   letter   from   the   concerned   authority   for   ensuring   water   supply,   emergency discharge of treated wastewater and solid waste disposal.

2. Existing   vegetation,   if   any,   at   the   proposed   site   and   the   mouza   map   showing   existing waterbodies.

The SEAC considered the reply dated 03.03.2011 of the proponent in the 53rd SEAC meeting held on 13.04.2011. The SEAC requested the project proponent vide letter dated 28.04.2011 to submit the following – 

1. The concurrence letter from the concerned authority for ensuring water supply, emergency discharge of treated waste water and solid waste disposal. 

2. Details about the existing vegetation, if any, at the proposed site.

3. Master Plan of the proposed project superimposed on an authenticated Mouza Map clearly showing the existing waterbodies and also approved current classification of the land parcel alongwith JL No., LR Khatian No. / Plot No. A comprehensive list of land parcels alongwith area of the parcels for the entire project shall be highly appreciated.

The minutes of the meeting held in Paribesh Bhawan on 12.07.2011 has been received. The matter is placed before the SEAC in the 58th meeting held on 19.08.2011.

The project proponent submitted their reply on 09.01.2012, which is as under :­

1. The  proponent   submitted   that   they  have   received  NOC  from SWID  for   sinking  of  deep tubewell. Further, the Executive Engineer, Irrigation and Water Works was pleased to issue necessary NOC for disposal of treated waste water in case of emergency. For solid waste disposal, they have a plan to put portable dustbin, which will be cleared on a regular basis by vehicle.

2. The proponent submitted the following vegetation found at site :­

a) Palm Tree – 5 nos.

Page 9 of 33

Page 10: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

b) Banana Tree – 13 nos.

c) Ashwattha Tree – 4 nos (small)

d) Other type – 2 nos. (Kadam Tree)

e) Besides part of the site is covered by long wild grass.

3. The proponent enclosed two nos. of Mouza Maps duly authenticated by the concerned BL & LRO Office showing the existence of the waterbodies.

The case was put up for reconsideration in the 63rd SEAC meeting held on 31.01.2012. 

After scrutinizing the documents submitted by the unit, the SEAC has opined that clarifications sought in the 53rd  SEAC meeting has not been properly addressed in the said letter. The unit is therefore requested to provide the following documents for further processing of the application: 

1. Necessary concurrence letter should be obtained from the competent authority for  the solid waste disposal facilities. 

2. Details of the existing vegetation including types of grass cover should be specified.3. Master Plan of the proposed project superimposed on an authenticated Mouza Map clearly 

showing the existing water bodies and also approved current classification of the land parcel alongwith JL No., LR Khatian No. / Plot No. should be submitted. A comprehensive list of land parcels along with area of the parcels for the entire project shall be highly appreciated.

4. Necessary concurrence letter should be obtained from competent authority for ensuring total water supply for the proposed project.

5. A copy of NOC for disposal of treated waste water in case of emergency from competent authority should be submitted.

It has been decided that the case shall be further considered only  after  submission of  the  necessary clarification.

5. Proposed IT Park by M/s.  Phoenix Software Ltd.  at Jl. No. ­ 35, Mouza – Gangapur, Kolkata Information  Technology  Park   (KITP),  Bantala,  PS  –   Kolkata   Leather   Complex,   Dist.   –   24 Parganas (South), West Bengal.

Activity:

This is a proposal for construction of an IT Park (1 block of B+G+10 storied building, 52.625m from GL and 1 block of B+G+12 storied building, 72.075m from GL) alongwith Central block, Service block etc.

Chronology of the event :

The proponent applied for environmental clearance on 08.12.2010 to the State Environmental Impact Assessment Authority (SEIAA), West Bengal. The same was forwarded to the State Level Expert Appraisal Committee (SEAC), West Bengal on 31.12.2010. The proponent was requested to submit necessary information vide letter dated 17.02.2011 as the information provided in the application was inadequate. The letter dated 07.06.2011 was received from the Principal Secretary, Dept. of IT, Govt. of West Bengal. 

Page 10 of 33

Page 11: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

The proponent has submitted their reply on 04.08.2011. The following observations were verbally communicated to the proponent – 

1. The Deed of Assignment of Lease mentions that “The Assignee shall have to apply for supply of electricity, water line (drinking and Construction water separately) to the WBSEB / the Assignor   /   any   other   Authority   engaged   by   the   State   Government   and   on   payment   of prescribed   charges   and   as   and  where   necessary   the  WBSEB   /   the  Assignor   /   any  other Authority engaged by the State Government shall provide the same”. However, the same has not been submitted.

2. The proponent has mentioned that KMDA is the plan sanctioning authority alongwith South 24 Parganas Zilla Parishad. 

3. The proponent has also mentioned that the rainwater storage capacity has been increased to approx. 10.7% of the potential. 

During presentation in the 59th SEAC meeting held on 20.09.2011, the committee recommended the following:­ 

Recommendations / Directions of the Committee issued on 10.10.2011

Response of the Proponent submitted on 24.10.2011

1. The   corrected   site   plan   should   be submitted.   Vertical   profile   of   the building should be clearly specified.

1. The project proponent has submitted revised site   plan.   However,   vertical   profile   of   the building   has   not   been   mentioned,   instead, perspective   view   of   the   building   has   been submitted.

2. Revised   plantation   plan   should   be submitted as discussed in the meeting.

2. The project proponent has submitted revised list of plantation.

3. The   total   impervious   area   of   the   site should   be   limited   within   permissible Ground   Coverage   and   Paved   Area stipulations. 

3. The   proponent   has   mentioned   that   building ground   coverage   does  not   include   extended basement,   underground   STO,   Rainwater Harvesting   tank,   UGR   etc.   The   project proponent has referred to KMDA Notification dated 12.12.2008.  However,   such provisions could  not  be   found   in   the   said  notification. The project proponent has submitted ground floor   plan   with   area   statement.   The   area statement   is   not   clear   and   larger   (with appropriate grid size) print out of the gridded Master Plan  is needed for verification.

4. The   proponent   should   clearly   specify whether  chlorination  or  ozonation  will be   adopted   for   tertiary   treatment   of sewage.

4. The   project   proponent   has   mentioned   that chlorination   will   be   adopted   for   tertiary treatment of sewage.

Page 11 of 33

Page 12: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Recommendations / Directions of the Committee issued on 10.10.2011

Response of the Proponent submitted on 24.10.2011

5. The car  parking  calculation  as  per   the West   Bengal   Municipal   (Building) Rules, 2007 should be submitted.

5. The project proponent has mentioned that as per West Bengal Municipal (Building) Rules 2007   required   car   parking   is   1172   and   car parking   provided   is   1303.   However, supporting calculation has not been provided.

6. Utilisation of fly ash building materials should  be  submitted  as  per   the  MoEF latest Notification.

6. The project proponent has mentioned that fly ash   building   materials   will   be   utilised. However, no details has been provided.

7. The   financial   commitment   along   with the   time   bound   action   programme   for Corporate  Social  Responsibility   (CSR) activity   like   improving   the   health facility,   educational   facility   at   the surrounding   economically   backward area, should be submitted.

7. The   project   proponent   has   mentioned   that financial outlay of 1% of the project cost will be   allocated   for   CSR   activities   for improvement   of   physical   and   social infrastructure  in  the neighbourhood backward areas.   However,   item­wise   detailed   breakup has not been provided.

8. Name   of   Environment   Consultant should be mentioned.

8. The   project   proponent   has   mentioned   that M/s. Ghosh, Bose & Associates Pvt. Ltd. are the Environment Consultant for the proposed project.   However,   no   undertaking   has   been provided on behalf of the consultants as per the   MoEF,   Government   of   India   Office Memorandum dated 05.10.2011.

In this regard it may be mentioned that as per the   clarification   received   from   Director, NABET on 19.09.2011, the SEAC decided in the 59th meeting held on 20.09.2011, to allow M/s. Ghosh, Bose & Associates Pvt. Ltd. Till 30.09.2011.

The matter was placed before the SEAC in the 61st meeting held on 29.11.2011. The committee has noted the following and the project proponent has submitted the reply as follows :­

Recommendations / Directions of the Committee issued on 19.12.2011

Response of the Proponent submitted on 17.01.2012

1. Although   the   perspective   view   of   the building has been submitted but the vertical profile   (i.e.   number   of   floor,   building heights etc.) has not been clearly mentioned in the submission.

1. The   proponent   has   mentioned   that   the building is B+G+10 storied and the height is 54.50 meters.

Page 12 of 33

Page 13: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Recommendations / Directions of the Committee issued on 19.12.2011

Response of the Proponent submitted on 17.01.2012

2. The   provision   of   rule   regarding   ground coverage which was mentioned in  support of   the   claim   about   additional   ground coverage during the presentation could not be found in the copy of KMDA notification dated 12.12.2008 provided by the unit.

2. The project proponent has submitted  the National   Building   Code   of   India,   Para 2.26 highlighting the relevant portion.

3. No back up calculation has been provided in support of the claim that as per the West Bengal   (Building)   Municipal   Rules   2007, the   required   car   parking   is   1172   and   car parking proposed to be provided is 1303. 

3. The project proponent has submitted  the backup   calculation   for   the   required   car parking     of   1172   nos.   as   per   the   West Bengal (Building) Municipal Rules 2007 and the car parking proposed is 1303 nos.

4. The   item­wise   detailed   break   up   of Corporate   Social   Responsibility   (CSR) along with the time bound action plan has not been provided.

4. Item­wise CSR plan proposed but without any   time   bound   programme.   Total budgetary allocation for the CSR has been mentioned as Rs. 55 lacs (approx).

5. It   is  once  again   reiterated   that   all  project proponents  are   required  to  strictly  comply with the Office Memorandum issued by the Ministry   of   Environment   &   Forest, Government   of   India   on   30.09.2011   and 05.10.2011.

5.

The case was put up for reconsideration in the 63rd SEAC meeting held on 31.01.2012. 

After scrutinizing the documents submitted by the unit, the SEAC has opined that the directions of the Committee issued on 19.12.2011 have not been adequately addressed in the said letter. The unit is therefore requested to provide the following documents for further processing of the application: 

1. Regarding the provision of rule for additional ground coverage, the KMDA notification shall prevail.

2. The CSR  initiatives proposed does not have any  time bound programme,  item wise  time frame should be proposed and the activities should be completed within a period of 5 years. Necessary undertaking should be submitted to that effect. 

It has been decided that the case shall be further considered only  after  submission of  the  necessary clarification.

Page 13 of 33

Page 14: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

6. Proposed Residential & Commercial Complex by M/s. P.S. Villa Pvt. Ltd. & Others at Holding No. –  4S/08/Block­P & 4S/09/Block­P,  Jl.  No. – 5  & 6,  Mouza – Kaikhali  & Mondal  Ganti, Rajarhat Gopalpur Municipality  Ward No. – 26 & 27,  PS – Baguihati,  Dist.  – 24 Parganas (North), West Bengal.

Activity:

This  is   a  proposal   for   construction   of   a  Residential   and   Commercial   Complex.   The  Residential Complex (6 blocks of B+G+9 storied buildings) shall consist of 216 apartments. The Commercial block (1 block of  B+G+7 storied building) shall  consist  of  Retail  Area,  Hotels  (with 184 double bedded rooms) and Restaurants.

Chronology of the event :

The  State   Level   Expert   Appraisal   Committee,   West   Bengal   stipulated   the   conditions   for Environmental Clearance in the 45th SEAC meeting held on 03.08.2010. 

The   proponent   has   now   applied   for   Environmental   Clearance   vide   letter   dated   11.11.2011   and 16.11.2011. The proponent has also submitted the copy of the building plans provisionally sanctioned by the Chairman, Rajarhat Gopalpur Municipality on 28.09.2011 upto ground floor. However, the area statement in the plan is not clearly legible. The proponent has also mentioned that piling work is being carried out at the site. The modified salient features of the proposed project as per the comparative statement submitted by the proponent, are as follows:­

Salient Features As per SCEC dated 18.08.2010 Post plan sanction by Rajarhat Gopalpur Municipality 

Land Area 13602.69 sqm. 13602.69 sqm.

No. of Flat 216 216

No. of Building Block Residential – 6Commercial – 1

Residential – 6Commercial – 1

Height of Building Block Residential – B+G+9 storied

Commercial – B+G+7 storied

Residential – B+G+9 storied

Commercial – B+G+7 storied

Expected Population 1080 (fixed)1861 (floating)

1080 (fixed)1861 (floating)

Total Water requirement   451 KLD (operation stage) 451 KLD (operation stage)

Fresh Water requirement   289 KLD (Municipal Supply) 289 KLD (Municipal Supply)

Domestic Water requirement

285 KLD 285 KLD

Wastewater generated 207 KLD 207 KLD

Wastewater treated 166 KLD 166 KLD

Wastewater recycled 162 KLD 162 KLD

Wastewater discharged 4 KLD 4 KLD

Wastewater Treatment To   be   treated   in   Sewage Treatment Plant

To   be   treated   in   Sewage Treatment Plant

Page 14 of 33

Page 15: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Salient Features As per SCEC dated 18.08.2010 Post plan sanction by Rajarhat Gopalpur Municipality 

Solid waste disposal 1.2 tonne per day 1.2 tonne per day

Total Built­up Area 49606.55 sqm. 49606.55 sqm. 

Ground Coverage 5650.04   sqm.   (41.5%   of   land area)

6102.50   sqm.   (44.86%  of   land area)

Green Area 4552.44   sqm.   (33.5%   of   land area)

4099.98.44   sqm.   (30.14%   of land area)

Paved Area 3400.21   sqm.   (25.0%   of   land area)

3400.21   sqm.   (25.0%   of   land area)

No. of Parking Spaces proposed

292 (Covered – 241, Open ­ 51) 302 (Covered – 252, Open ­ 50)

Total Power requirement 1000 KW (WBSEDCL) 1000 KW (WBSEDCL)

Back up Power 4 x 250 KVA D.G. Sets 4 x 250 KVA D.G. Sets

Furthers the SEAC has considered the reply submitted on 16.11.2011 in the  61st  meeting held on 29.11.2011 and the committee has recommended the following :­

Recommendations / Directions of the Committee dated 19.12.2011

Response of the Proponent dated 18.01.2012

1. The ultimate source of water from which the water will be supplied to the project. 

1. The unit has submitted a letter from the office of   Rajarhat­Gopalpur   Municipality   informed that part supply from the Municipality may be availed   and   rest   to  be  obtained  by   installing deep   tubewell   after   getting   permission   from SWID.

2. The capacity of the storm water carrying drain and its route to final disposal point.

2. To be discharged to Municipality drain.

3. As per   the submission of   the unit     the municipality   is supposed to collect  and finally dispose the solid waste, the muni­cipality should possess a valid Municipal Solid Waste Authorisation Certificate. 

3. The project proponent has submitted the letter issued by the Chairman of Rajarhat­Gopalpur Municipality for the collection and dispose of the solid waste.

4. The area statement in the plan submitted is  not   legible.  The  unit   is   requested   to submit a legible copy of the same.

4. The   proponent   has   submitted   the   area statement   ratified   by   Rajarhat­Gopalpur Municipality.

The case was put up for reconsideration in the 63rd SEAC meeting held on 31.01.2012. 

After   scrutinizing   the   documents   submitted  by   the   unit,   the   SEAC  has   noted   that   infrastructure facilities   to  be provided for   the proposed project  need further   introspection.  The unit   is   therefore requested to provide the following documents for further processing of the application:

Page 15 of 33

Page 16: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

a) Permission form SWID for drawl of ground water ;b) The unit may also kindly note that as per the submission the concerned municipality will col­

lect and finally dispose the solid waste. The municipality should possess a valid Municipal Solid Waste Authorization Certificate. Copy of the same is to be submitted.

c) Sanctioned building plan from the concerned municipality clearly suggests that the building plan is provisionally sanctioned up to Ground floor. The unit is required to submit the sanc­tioned plan for the total project.

d) It has also been observed as per the submission of the unit dated 11.11.2011, piling work has been started. The unit is therefore directed not to start any construction activity without ob­taining Environmental Clearance from SEIAA and NOC from the WBPCB. 

7. Proposed Residential Complex & Hospital by M/s. Oriental Sales Agencies (India) Pvt. Ltd. at 2, Jessore Road, Holding No. – 380 (N), 1108 (O), Cal­Jessore Road, Jl. No. – 19, Mouza – Dum Dum House, South Dum Dum Municipality Ward No. ­ 07, PO & PS – Dum Dum, Kolkata – 700028, Dist. – 24 Parganas (North). 

Activity:

This is a proposal for construction of a Residential Complex having 1196 flats (13 blocks of B+G+13 storied buildings, 13 blocks of G+13 storied buildings), Hospital (70 beds, 1 block of G+9 storied building), Club (2 blocks of G+1 storied buildings) and 2 nos. podium.

Chronology of the event :

The  proposal  was  placed  before   the  SEAC  in   the  56th  SEAC meeting  held  on 15.07.2011,  58th 

meeting held on 19.08.2011 and 60th SEAC meeting held on 24.10.2011.

The  proponent  delivered   two  technical  presentations  on  composting  machine  on 25.11.2011.  The committee has considered the letter dated 02.11.2011 of the proponent in the 61st SEAC meeting held on 29.11.2011 and the committee informed that the proposals for in­house Solid Waste Management Technologies are under scrutiny and review by the field experts.

The proponent has submitted letter dated 14.12.2011 stating that South Dum Dum Municipality has undertaken a centralized 'Waste to Energy' programme. The proponent has further mentioned that they would like to join the said scheme of the Municipality. However, in case the said 'Waste to Energy' programme   is   not   ready   in   time,   the   proponent   shall   take   up   the   responsibility   of   operating   an approved technology for onsite treatment of organic solid waste till the time the Municipal facility is ready and operational.

The  SEAC considered   the   reply  dated  14.12.2011   in   the  62nd  meeting  held  on 22.12.2011.  The committee has opined through letter dated 03.01.2012 that the solid waste disposal facilities must be ensured for the upcoming building projects. In this connection the status of Municipal Solid Waste (MSW)  authorisation  of  concerned  urban   local   bodies   shall   be   reviewed  during  appraisal  of   any building projects. As in this present case the municipality does not posses any valid municipal solid waste authorisation, the project proponent should keep adequate space as a future provision for setting up of appropriate onsite biodegradable solid waste treatment plant. The odour control system, leachate disposal  system for  the said  treatment plant  should be adequate.  The output characteristics  of  the compost should be of desired quality as per MSW Rules. The project proponent should also propose 

Page 16 of 33

Page 17: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

the mechanism which would ensure regular operation and maintenance of such treatment plant and would also propose inhouse use of compost as well as for selling out the excess quantity. The project proponent is also required to submit an undertaking that the building shall not be functional   before either the concerned municipality obtains valid MSW authorisation and accepts the solid waste from the above­mentioned project or appropriate onsite solid waste treatment system are made available within the housing complex. The suitable onsite solid waste treatment system shall also be subject to review and scrutiny and approval of concerned authorities.

The  project   proponent  has   submitted   letter   dated  19.01.2012  stating   that   they  have   already  kept adequate space for future provision for onsite treatment of biodegradable fraction of MSW and the location of the MSW management site is shown in a drawing. They also informed that they will adopt the   best   and   approved   technology   by   reputed   manufacturer   of   composite   onsite   treatment   of biodegradable fraction of MSW. In addition they would also take the responsibility that the odour control system and leachate disposal system would be adequate and the characteristics of compost manure would be of desired quality as per MSW (Management & Handling) Rule 2000. The compost manure would be used in landscaping within the project area and the excess quantity will be sold to the prospective vendors. In this regard they also submitted an undertaking on non­judicial stamp paper that the building would not be functional before either the South Dumdum Municipality obtains valid MSW authorisation and accepts the solid waste from the project or appropriate onsite solid waste management system are made available within the project area.  

The case was put up for reconsideration in the 63rd SEAC meeting held on 31.01.2012. 

After scrutinizing the documents submitted by the unit,  the SEAC has opined that the solid waste management and disposal facilities must be ensured for the upcoming building projects.  The SEAC has noted that the waste management facilities to be provided for the proposed project need further introspection.  In   this  connection,   the following points  have been noted by the SEAC and require further clarification:

1. The proposed location of the area allocated for solid waste management was previously earmarked for car parking and appears to be near one of the residential blocks

2. Modalities of Operation and Maintenance of the Solid Waste Management System 

It  has  been  decided   that   the  case shall  be  further  considered  only  after  submission  of   the above documents. 

8. Proposed Residential cum Commercial Complex “SRIJAN HARMONY” by M/s. Srijan Realty Limited & Others at JL No. 77, Holding No. 132, Mouza – Manikpur, PS – Sonarpur, Rajpur Sonarpur Municipality Ward No. 23, Dist – 24 Parganas (South), West Bengal. 

Activity:

This  is a proposal for construction of a Residential cum Commercial complex comprising of 1425 dwelling   units   in  11nos.   G+11   storied   buildings   alongwith   Club   (G+1   storied)   and  Commercial Complex (2nos. G+1 storied buildings).

Page 17 of 33

Page 18: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Chronology of the event :

The  State   Level   Expert   Appraisal   Committee   (SEAC),   West   Bengal   made   the   following recommendations   in   the  62nd  SEAC   meeting   held   on   22.12.2011.  Subsequent   response   dated 25.01.2012 from the unit is given below :­

Recommendations / Directions of the Committee, issued on 30.12.2011

Response of the Proponent submitted on 25.01.2012

1. Fire   fighting   storage   provisions should  be  made as  per  norms.  The open  car  parking   should  be   revised accordingly.

1. The project proponent has mentioned that the fire fighting   provision   should   be   provided   as   per WBFS Norms. The proponent has also submitted the revised open car parking plan.

2. The   design   influent   and   effluent characteristics   considered   for   the STP   should   be   mentioned.   Test reports   of   similar   STPs   should   be submitted.

2. The project proponent has also mentioned that the proposed STP is based on FAB. They submitted the design influent and effluent characteristics of STP.   The   STP,   based   on   the   same   principle (FAB),   is   currently   running   in   their   another project at “PS Srijan Tech Park” at DN­52, Sector –   V,   Salt   Lake   City,   Kolkata   –   700091.   The project proponent has also submitted the influent and effluent characteristics of the STP.

3. Revised   Rainwater   recharging proposal   should   be   submitted   as discussed in the meeting.

3. The   proponent   has   submitted   revised   rainwater recharging proposal.

4. Detail   solar   lighting   proposal   with numbers   and   locations   for installations   “solar   operated   LED” lighting   should   be   specifically mentioned.

4. The proponent has mentioned that the 60 nos. of solar   lighting  system will  be   installed   for  street lights.   All   the   solar   street   lights   will   be   LED operated. They submitted the details of solar light plan.

5. Revised   CSR   proposal   should   be submitted   as   discussed   in   the meeting.

5. The  proponent  has   submitted  revised  Corporate Social  Responsibility   (CSR)  plan  with   financial commitment of Rs. 30 lacs.

The case was put up for reconsideration in the 63rd SEAC meeting held on 31.01.2012. 

The SEAC considered  the submission by  the proponent and  finalised  Stipulated Conditions  for Environmental Clearance. The set of environmental conditions are annexed as Annexure 1.

Page 18 of 33

Page 19: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

9. Proposed   Residential  Complex   by   M/s.   Fortune   Park   Housing   Projects   Pvt.   Ltd.   at   168 Krishnanagar Road, Vill. – Paschim Khilkapur, Mouza – Moynagadi, PS – Barasat, Dist. ­ 24 Parganas (N). 

Activity:

This  is a proposal for construction of a Residential Complex having 819 flats (13nos. G+11 storied buildings and 1no. G+7 storied building) and Club cum Community Building (G+2 storied).

Chronology of the event :

The  State   Level   Expert   Appraisal   Committee   (SEAC),   West   Bengal   made   the   following recommendations   in   the  60th  SEAC   meeting   held   on   24.10.2011.  Subsequent   response   dated 20.01.2012 from the unit is given below :­

Recommendations / Directions of the Committee, issued on 15.11.2011

Response of the Proponent submitted on 20.01.2012

1. The   project   has   been   proposed   in   an arsenic prone zone. Please note that as per the provision of MoEF, New Delhi guidelines   on   large   building   projects, groundwater abstraction and recharging cannot be allowed in this area.

     Further, approx. 632m3/day groundwater is proposed to be abstracted from this arsenic   prone   zone.   However,   no information is available about the depth of borewell and impact of abstraction.

1. The   project   proponent   has   submitted   the concurrence  letter  obtained  from the  Paschim Khilkapur Gram panchayat regarding supply of potable   water   (without   mentioning   the quantity), discharge of treated wastewater and collection and disposal of solid waste.

2. The   proponent   has   mentioned   that water   requirement   will   be   met   from Panchayat   supply.   Details   of   water source,   quality   and   quantity   of Panchayat   water   supply   should   be provided   alongwith   specific commitment from concerned authority.

2. The project proponent has also mentioned that required   freshwater   during   construction   and operational phase is expected to be arranged by Paschim   Khilkapur   Gram   Panchayat.   They submitted the concurrence letter in this regard.

3. No   information   has   been   provided about   the   carrying   capacity   of   the adjacent   drainage   system   in   which runoff from the project site in addition to 380m3/day of treated wastewater has been   proposed   to   be   discharged.   The route of transport of stormwater as well as   treated   wastewater   to   the   final recipient   waterbody   is   also   not specified.

3. The proponent  has submitted  the concurrence letter   from   the   Paschim   Khilkapur   Gram Panchayat  alongwith   the   stormwater  drainage route.   They   also   mentioned   that   stormwater drainage facility exists along the Ardebak Road which ultimately discharges into Sunthi Khal. Stormwater   runoff   and   surplus   treated wastewater from the proposed complex will be discharged into the said drain.

Page 19 of 33

Page 20: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Recommendations / Directions of the Committee, issued on 15.11.2011

Response of the Proponent submitted on 20.01.2012

   Details   of   stormwater   and   treated wastewater   discharge,   conveyance   to the final recipient waterbody should be provided   alongwith   necessary concurrence of concerned authority

4. Details   of   solid   waste   collection, transport   and   disposal   scheme alongwith   concurrence   of   concerned authority. The copy of Municipal Solid Waste (MSW) authorization should be valid.

4. The   proponent   has   mentioned   that   the generated solid waste within the complex will be   handed   over   to   panchayat   solid   waste collection   system.   Paschim   Khilkapur   Gram Panchayat   has   its   solid   waste   collection, transportation and disposal arrangement under P & RD scheme.

5. Existing trees and waterbodies, if any, should be specified.

5. The proponent has  mentioned that there is no existing trees or waterbody within  the project site.

6. Land  conversion   certificate   should  be submitted. The detailed list  of landuse classification   of   dag   nos.   should   be provided.

6. The  unit  has confirmed  that   they  will   submit the land conversion certificate to the SEAC on receipt from the land department. The project proponent has submitted a  list of dagwise land details.

7. It  has been noted that  PVC grass cell structure has been proposed with 25% hard  area  and  75% soft   area.  Typical design drawing should be provided.

7. The unit  has submitted a photograph of  PVC grass paver.

The case was put up for reconsideration in the 63rd SEAC meeting held on 31.01.2012. 

After scrutinizing the documents submitted by the unit, the SEAC has opined that the directions of the Committee  issued on 15.11.2011 has not been adequately addressed in  the said  letter.  The unit is therefore requested to provide the following documents for further processing of the application: 

1. Since the project has been proposed in an arsenic prone zone, necessary concurrence from PHED should be obtained regarding supply of potable water along with quantity. Necessary backup cal­culation about depth of bore well and impact of abstraction should be obtained from PHED. 

2. Regarding solid waste management, the unit has mentioned that the concerned panchayet has it’s waste disposal system under P&RD scheme and valid authorisation from WBPCB. The relevant enclosure, Annexure 1 is not available along with the letter submitted dated 20.01.2012.

3. Typical design drawing of PVC grass cell was required to be submitted as per Direction dated 15.11.2011, however only a photograph of the same has been submitted.

It has been decided that the case shall be further considered only  after  submission of  the  necessary clarification.

Page 20 of 33

Page 21: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

B.  Miscellaneous :­

1. Proposed expansion project for enhancement of production of Unsaturated Polyester Resins by M/s. Strongbonds Polyseal Pvt. Ltd. at Plot No. – 26/C, 26/D/1 & 26/D/2, Kalyani Industrial Estate Phase I, Block – D, Dist. – Nadia, Pin – 741235, West Bengal. 

Activity:

This is an expansion proposal for enhancement of production capacity of Unsaturated Polyester Resins (UPR) by 690 TPA. The proposed plant  will  be located adjacent  to   the existing plant at Kalyani Industrial Estate.

Chronology of the event :

The State Level Expert Appraisal Committee (SEAC)  made the following recommendations  in the 52nd  meeting  held  on 04.03.2011.  During  presentation  it  was  understood  by   the  SEAC  that   the proposed expansion work has been started before obtaining Environmental  Clearance.  Subsequent response from the unit submitted on 16.06.2011, is given below :­

Recommendations / Directions of the Committee issued on 15.03.2011

Response of the Proponent  dated 16.06.2011

1. The unit should not continue any work for the   proposed   expansion   project   before obtaining prior necessary clearances.

1. The proponent has stated that they will  not continue   any   work   for   the   proposed expansion   project   before   obtaining   prior necessary clearances.

2. The Hazardous Waste Authorization must be   obtained   from   the   West   Bengal Pollution   Control   Board     before   further consideration   of   this   case   for Environmental Clearance.

2. The proponent has mentioned that they have applied  for  Hazardous Waste  Authorization to West Bengal Pollution Control Board.

3. The   effluent   characteristics   for   the existing   plant   should   be   submitted. Incremental   load   of   the   proposed enhancement  should  be mentioned  along with  the effluent treatment method to be adopted.

3. The proponent has submitted analysis report of the effluent. The proponent has mentioned that   the   incremental   wastewater   generation will   be   0.2   KLD.   The   proponent   has proposed neutralization and evaporation for treatment of effluent.

4. Adequate no. of trees should be provided. 4. The  proponent  has  mentioned   that   total  47 nos. of trees will be provided.

5. Adequate   storage   volume   for   rainwater harvesting should be provided.

5. The  proponent  has  mentioned  that  100 KL storage volume will be provided.

6. Modified Corporate Social Responsibility (CSR) Plan with specific programmes and financial commitment to be submitted.

6. The   proponent   has   submitted   revised Corporate Social Responsibility (CSR) Plan with financial commitment.

Page 21 of 33

Page 22: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

The reply dated 16.06.2011 was placed in the 56th SEAC meeting held on 15.07.2011. The committee made the following recommendations and the proponent submitted their reply on 14.10.2011 :­

Recommendations / Directions of the Committee issued on 22.07.2011

Response of the Proponent  dated 14.10.2011

i. The  Hazardous  Waste  Authorization  must be obtained from the West Bengal Pollution Control Board before further consideration of this case for Environmental Clearance.

i. The   proponent   has  submitted   copy   of   the Hazardous   waste   Authorisation   valid   upto 30.04.2012.

ii. The unit should not continue any work for the   proposed   expansion   project   before obtaining prior necessary clearances.

ii. The proponent has stated  that  they will  not continue   any   work   for   expansion   project before obtaining all statutory clearances.

The case was placed in the 60th SEAC meeting held on 24.10.2011 and recommended by SEAC.

The Member Secretary, SEIAA noted that there is a lack of clarity regarding effluent treatment unit (both existing as well as proposed unit) and returned the case to SEAC with a request to get the clarification on effluent treatment from the project proponent.

The case was placed for consideration in the 63rd SEAC meeting held on 31.01.2012. 

After scrutinizing the documents submitted by the unit, the committee noted that there is a lack of clarity regarding effluent treatment unit (both existing as well as proposed unit ) and seeks the opinion of the West Bengal Pollution Control Board regarding the present status of effluent treatment plant of the unit.

The unit is therefore requested to send the present status of effluent treatment plant of the existing unit as well as present status of the proposed expansion unit for further processing of the application. 

Session II

C. Technical Presentations: ­

1. Proposed waste paper based plant and Cogeneration Captive Power Plant by M/s.  Balaji Paper & Newsprints Pvt. Ltd. at JL No. 561, 562, 649, 650, Vill & PO – Manikpara, PS – Jhargram, Dist – Paschim Medinipur, Pin – 721 513, West Bengal. Name of the Environmental Consultant – not mentioned. 

Activity:

This  is a proposed Waste Paper Based Paper Plant with additional paper manufacturing capacity of 100 TPD and 6 MW Co­Generation Captive Power Plant. 

Chronology of the event :

The  State Level Expert Appraisal Committee (SEAC) also made the following recommendations in the 46th SEAC meeting held on 06.09.2010. Subsequent response dated 24.02.2011 from the unit is given below:­ 

Page 22 of 33

Page 23: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Recommendations / Directions of the Committee dated 11.10.2010

Response of the Proponent dated 24.02.2011

1. The performance report  of   the existing unit should be submitted. 

1.

2. Prior   permission   should   be   obtained   from DLA   for   ground   water   abstraction   and   the copy should be submitted.

2. The proponent has informed that they have obtained  permission   from DLA  for  8nos. borewell each 10m3/hr, copies enclosed.

3. Water   balance   statement   and   water consumption per tonne of product should be mentioned. 

3. The proponent has submitted revised water balance statement. As per the information provided the water consumption per tonne of product is 4.8 m3.

4. Details of Rainwater Harvesting proposal and Corporate  Social  Responsibility  plan should be submitted.

4. The   proponent   has   submitted  Rainwater Harvesting proposal  and Corporate  Social Responsibility plan.

5. Solid   waste   management   and   Flyash management plans should be submitted.

5.

The response dated 24.02.2011 was placed before SEAC in the 52nd meeting held on 04.03.2011.

Furthers the SEAC has considered the reply submitted on 16.06.2011 in the  58th  meeting held on 19.08.2011 and the committee has recommended the following :­

Recommendations / Directions of the Committee dated 30.08.2011

Response of the Proponent  dated 30.09.2011

1. The influent BOD value has been assumed to be very low in comparison to waste water usually generated from such a waste paper based mill. 

1. The proponent has mentioned that they have assumed influent of  BOD 600 mg/l on the basis   of   their   raw   material   input   and production process.

2. The influent BOD is likely to magnify due to recycling of the treated / partially treated waste water.

2. The proponent has mentioned that they will provide   adequate   treatment   so   that magnification   of  BOD  due   to   recycling   is less.

3. The mass vs water ratio is also not realistic. The project proponent should try to explain those   ratios   or   should   submit   corrected water and mass balance diagram. 

3. The   proponent   has   stated   that   they   have prepared   water   balance   and   mass   balance statement   based   on   their   past   experience. The proponent has also mentioned that  the proposed water balance and mass balance is achievable.

The reply of the proponent submitted on 30.09.2011 was placed in the 60th SEAC meeting held on 24.10.2011. The committee has noted the following and the subsequent reply received on 19.12.2011 of the unit are as under :­

Page 23 of 33

Page 24: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Recommendations / Directions of the Committee dated 04.11.2011

Response of the Proponent  dated 19.12.2011

1. The performance report of the existing unit has not been submitted. 

1. The   proponent   has   submitted   inhouse test reports.

2. The BOD influent has been assumed on lower side and there is no specific proposal available, which   ensure   adequate   treatment   to   prevent magnification of BOD concentration in the re­cycled water.

2. The   proponent   has   submitted   BOD calculation.

3. No plausible explanation has been provided to substantiate the claim that the water balance and mass   balance,   which   were   submitted   to   the SEAC   earlier   and   was   duly   questioned   by SEAC through earlier communications, are cor­rect and validated. 

3. The proponent has submitted mass and water balance diagram.

The reply dated 19.12.2011 of the proponent is placed before the SEAC in the 62nd SEAC meeting held on 22.12.2011 for consideration. The committee noted that  even after several correspondences, the   issues   regarding   water   consumption,   wastewater   characteristics   and   treatment   remained unresolved,  and therefore  the committee  has  requested the project proponent  called for a detailed revised powerpoint presentation  to justify the claim regarding water and wastewater and submit the hard copy of the presentation by 15.01.2012. The proponent submitted a clarification on 18.01.2012, which is placed for consideration. 

The industry also submitted a letter on 25.01.2012 mentioning that they have dropped the project of cogeneration captive power plant of capacity 6 MW. They have further submitted that they would manufacture paper by hydro pulping of waste paper and de­inking by using enzymes which is the latest technology in waste paper recycling in which no beaching or chlorine in any form is used. They also requested to exempt them from obtaining prior Environmental Clearance.

The case was placed for consideration in the 63rd SEAC meeting held on 31.01.2012.

After   carefully   considering   the   proposal   and  presentation   the   committee   has   recommended   the following – 

1. The  project proponent shall submit a fresh FORM – I for the revised proposal which will exclude the project of cogeneration captive power plant of capacity 6 MW.

2. The project proponent should submit appropriate water balance statement and clearly indicate the water consumption per tonne of product. The proponent should indicate the number of borewells that may be required including necessary back up calculation justifying the said water requirement.

It has been decided that the case shall be further considered only after submission of the satisfactory clarification. 

As per the MoEF Office Memorandum dated 30.09.2011, only the enlisted eligible consultants of the concerned sector would be permitted to certify any documents. The Environmental Consultant as well 

Page 24 of 33

Page 25: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

as the Project Proponent should also submit necessary undertakings as per MoEF Office Memorandum dated 05.10.2011.

2. Proposed Residential Complex by Kolkata Metropolitan Development Authority at Plot No. 1/3, CIT Scheme VII (M), PS – Maniktala, PO – Kankurgachi, KMC Ward No. 32, Kolkata – 700 054, West Bengal. Name of the Environmental Consultant – M/s. Envirotech East Pvt. Ltd.

Activity:

This    is a proposal for construction of a Residential Complex having   flats (3 blocks of B+G+27 storied   buildings  with   podium,   2   blocks   of   G+5   storied   buildings   and   5   blocks   of   G+6   storied buildings), max. ht. 102.80m. The project will also comprise of Rehabilitation block and Club house. 

Chronology of the event :

Salient features of the proposed project are – 

Land Area : 5.93 acres (23997.524 sqm.)

Expected Population : 2659 (fixed), 150 (floating)

No. of Units : Towers – 229, Rehabilitation block – 160, Club house  ­ 1, Banquet Hall ­ 400

Total Water requirement : 442 KLD (Operation stage, KMC supply)

Wastewater generated : 325 KLD (to be discharged to KMC sewer)

Solid waste disposal : 1.2 tonnes per day (to be disposed off through municipal authority) 

Total Built­up Area : 76994.52 sqm. 

Ground Coverage : 7899.02 sqm. (32.92% of land area) 

Parking Area : 1308.49 sqm. (5.45% of land area) 

Semi Paved Area : 2726.84 sqm. (11.36% of land area) 

Open Area : 41.26 sqm. (0.17% of land area) 

Facilities Area : 47.62 sqm. (0.20% of land area) 

Roads : 4600.61 sqm. (19.17% of land area) 

Green Area : 7373.65 sqm. (30.73% of land area)

Total No. of plantation proposed

: 600

No. of Parking spaces proposed 

: 580 (Covered ­ 437, Open ­143)

Total Power requirement : 2850 KVA, CESC 

Backup Power  : DG Sets (4x380 KVA, 2x125 KVA)

The case was put up for consideration in the 63rd SEAC meeting held on 31.01.2012.

After   carefully   considering   the   proposal   and  presentation   the   committee   has   recommended   the following – 

Page 25 of 33

Page 26: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

1. It   appears   that   the   process   of   transferring   the   land   to   KMDA   is   underway.     Necessary authenticated land document should be submitted. 

2. Some discrepancy has been noted in the area statement submitted in the EC application and also during presentation. Master plan indicating Ground Coverage, Paved Area, Landscaped Area etc. should be clearly mentioned. Total Paved Area should not exceed 25% of total land area.

3. Detailed calculation for  rainwater harvesting should be submitted. Design of ground water recharge   structure   for   rainwater   harvesting   should   be   checked   as   discussed   during   the meeting. 

4. Scientific names for list of plantation species for greenery development should be checked and  the  landscape planning should include plantation of  native species.  The species  with heavy foliage,  broad leaves and wide canopy cover are  desirable.  Water   intensive and/or invasive species should not be used for landscaping.

5. Concurrence   letter   from   KMC   for   supplying   water   for   the   proposed   project   should   be mentioned.

It has been decided that the case shall be further considered only after submission of the satisfactory clarification. 

It is informed that the unit is required to comply with the Office Memorandum dated 30.09.2011 and 05.10.2011, issued by the Ministry of Environment & Forests, Government of India, if applicable.

3. Proposed  Integrated Industrial  Township  by  M/s.  Kanchan Janga Integrated Infrastructure Development Pvt. Ltd. (A Joint Venture Company of M/s. Shristi Infrastructure Development Corporation Ltd. & M/s. West Bengal Industrial Infrastructure Development Corporation Ltd.) at Fatapukur, JL No. 9, Mouza – Chhat Gujrimari, JL No. 10, Mouza – Kismat Sukani, PS – Rajganj,   Dist   –   Jalpaiguri,   West   Bengal  .   Name   of   the   Environmental   Consultant   –   not mentioned.

Activity:

This is a proposal for development of an Integrated Industrial Township. The proposed Township shall include   small   scale   industries,   Retail,   Hotel   and   Social   Infrastructure   like   School,   Educational Institutes,   Nursing   Home,   Health   Care   Centre   etc.   Further,   Residential   apartments   along   with individual plots are also proposed. 

Chronology of the event :

Salient features of the proposed project are – 

Total Land Area : 124.5 acres / 50.383 ha. Industrial Area – 63.95 acres (51.4%)Residential / Institutional / Commercial – 29.41 acres (23.6%)Infrastructure (Roads / STP) – 31.14 acres (25%)

Expected Population : Industrial Zone – 14940Retail, Social, Residential – 24936Plots – 7359Total ­ 47000

Page 26 of 33

Page 27: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Total Water requirement : 5.5 MLD (Operation stage)

Fresh Water requirement : 3.92 MLD (Ground water)

Wastewater generated : 3.16 MLD (to be treated in STP)

Wastewater recycled : 1.58 MLD (to be reused after treatment in STP)

Wastewater discharged : 1.58 MLD (to be discharged to natural drain / sewer after treatment in STP)

Solid waste disposal : 14 tonnes per day (to be disposed off through panchayat) 

Total Built­up Area : Commercial Complex – 46451.52 sqm.Hotel – 55741.82 sqm. Social Infrastructure – 23225.76 sqm.Residential Complex (1846 flats) – 141515.6 sqm.Individual Plots – 119110.5 sqm.Total – 386045.2 sqm.

Ground Coverage : 37.64 acres (30.23% of land area) 

Landscaped Area : 61.57 acres (49.45% of land area)

Total Paved Area : 25.29 acres (20.31% of land area) 

Total No. of plantation  : 17451 approx.

No. of Parking spaces proposed 

:  Commercial – 1254Industrial – 1200Residential ­ 1415

Total Power requirement : Commercial – 6524 KWIndustrial – 6890 KWResidential – 7150 KW, WBSEDCL

Backup Power  : DG Sets (1x320 KVA, 1x600 KVA) for every alternate street lighting.

The case was put up for consideration in the 63rd SEAC meeting held on 31.01.2012. After carefully considering the proposal and presentation the committee categorized the project as B1 category unit and   recommended   Terms   of   Reference   (ToR)   for   conducting   EIA.  The   ToR   is   annexed   as Annexure 2. 

4. Proposed IT Park “ASTRA TOWERS” by M/s. Rajarhat IT Park Ltd. at Plot No. IIC/1, Action Area – II, New Town, Rajarhat, Kolkata, Dist – 24 Parganas (North), West Bengal. Name of the Environmental Consultant – M/s. Centre for Sustainable Development.

Activity:

This is a proposal for construction of an IT Park alongwith allied facilities (2 blocks of B+G+7 storied buildings, 1 block of B+G+3 storied building having common basement). The project will comprise of IT and General Offices as well as Retail Spaces, Food Court and Hypermarket. 

Page 27 of 33

Page 28: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Chronology of the event :

Salient features of the proposed project are – 

Total Land Area  : 16189 sqm. 

Expected Population : Employee – 3171, Others ­ 2660

Total Water requirement : 294 KLD (Operation stage)

Domestic Water requirement : 205 KLD 

Fresh Water requirement : 137 KLD (WBHIDCO supply)

Wastewater generated  : 164 KLD (to be treated in STP)

Wastewater reclaimed  : 148 KLD (to be reused after treatment in STP)

Wastewater discharged  : Zero discharge

Solid waste disposal : 1.6 tonnes per day 

Total Built­up Area : 54417.05 sqm.

Ground Coverage  : 6475 sqm. (40% of land area)

Plantation Area  : 3237.80 sqm. (20% of land area)

Semi Paved Area for Internal Roads and Surface parking

: 3810.69 sqm. (23.5% of land area)

Other Soft Area  : 2665.51 sqm. (16.5% of land area)

No. of Plantation proposed : 230

No. of Parking spaces proposed  : 651 (covered – 620, open ­ 31)

Total Power requirement : 3446 KW, NTESCL

Backup Power  : DG Sets (3x1500 KVA, 1x500 KVA) 

No. of solar light proposed : 18 (Total street light : 73 nos.)

The case was put up for consideration in the 63rd SEAC meeting held on 31.01.2012.

After   carefully   considering   the   proposal   and  presentation   the   committee   has   recommended   the following – 

The  project proponent should submit the modified proposal of Corporate Social Responsibility and also indicate the annual expenditure for the same for each component

It  has  been  decided   that   the  case  shall  be   further  considered  only  after  submission  of   the  above documents.

It is also informed that the unit is required to comply with the Office Memorandum dated 30.09.2011 and 05.10.2011, issued by the Ministry of Environment & Forests, Government of India, if applicable. 

Page 28 of 33

Page 29: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

5. Proposed expansion of Educational cum Office Building by M/s. Techno India at EM ­ 4/1 & 4/2, Sector – V, Saltlake, Kolkata – 700091, Bidhannagar Municipality, Dist. ­ 24 Parganas (North). Name of the Environmental Consultant – M/s. Envirotech East Pvt. Ltd.

Activity:

This is a proposal for expansion of an Educational cum Office Building (Block 1 – G+4, Block – G+7, Block 3 – G, Block 4 – B+G+18, Block 5 ­ B+G+26, Block 6 – B+G+27, Block 7 – G, Block 8 ­ G). The proposed project shall comprise of Educational buildings (Block 1, 2, 4), Service area (Block 3), Office building (Block 5, 6), Water tank and others (Block 7), Canteen and Others (Block 8). Block 1 & 2 partly exists. 

Chronology of the event :

Salient features of the proposed project are – 

Existing Project Proposal as per FORM – 1 including Expansion

Revised proposal

 Land Area  : 6.2 acres (25090.32 sqm.) : 6.2 acres (25090.32 sqm.)

Expected Population : 13409 : 13409

Total Water requirement

: 761 KLD (Operation stage, NDITA supply)

: 761 KLD (Operation stage, NDITA supply)

Wastewater generated 

: 467 KLD (to be discharged to municipal sewer leading to NDITA STP)

: 467 KLD (to be discharged to municipal sewer leading to NDITA STP)

Solid waste disposal : 2 tonnes per day  : 2 tonnes per day 

Total Built­up Area : 19430.19 sqm.  : 154391.63 sqm. (including parking)

149823.6 sqm. (including parking)

Ground Coverage  : 10030.54 sqm. (39.98% of land area)

: 9726.48 sqm. (38.77% of land area)

Service Area  : 398.93 sqm. (1.59% of land area)

: 616.61 sqm. (2.46% of land area)

Total Paved Area  : 6156.91 sqm. (24.54% of land area)

: 6254.325 sqm. (24.93% of land area)

Road Area  : 4858.12 sqm. (19.36% of land area)

: 4069.39 sqm. (16.22% of land area)

Semi Paved Area (50%) 

: 661.26 sqm. (2.64% of land area)

: 347.565 sqm. (1.39% of land area)

Open Parking Area (50%) 

: 637.53 sqm. (2.54% of land area)

: 1837.37 sqm. (7.32% of land area)

Total Green Area  : 8503.05 sqm. (33.89% of land area)

: 8492.885 sqm. (33.85% of land area)

Page 29 of 33

Page 30: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Existing Project Proposal as per FORM – 1 including Expansion

Revised proposal

Plantation Area  : 7204.26 sqm. (28.71% of land area)

: 5314.70 sqm. (21.18% of land area)

Semi Paved Area (50%) 

: 661.26 sqm. (2.64% of land area)

: 347.565 sqm. (1.39% of land area)

Open Parking Area (50%) 

: 637.53 sqm. (2.54% of land area)

: 1837.37 sqm. (7.32% of land area)

No. of plantation proposed

: 510 : 510

No. of Solar Street lights proposed 

: 51 (Total street light – 102) : 33 (Total street light – 74)

No. of Parking spaces proposed 

: 938 (covered – 854, open – 84)

: 977 (covered – 681, open – 296)

Total Power requirement

: 24540 KVA, WBSEDCL : 24540 KVA, WBSEDCL

Backup Power  :   DG   Sets   (1x550   KVA, 12x2000 KVA) 

:   DG   Sets   (1x550   KVA, 12x2000 KVA) 

The case is put up for consideration in the 63rd SEAC meeting held on 31.01.2012.

After   carefully   considering   the   proposal   and  presentation   the   committee   has   recommended   the following – 

1. Total built­up area for existing project as well as the proposed project should be clearly men­tioned. The date of amalgamation of two plots of land and date of completion of existing pro­ject should be submitted along with necessary supporting documents from competent author­ity.

2. Present status of existing project and proposed project should be clearly mentioned.3. Revised landscape plan should be submitted as discussed in the meeting.4. Provision for solar water heating systems and other energy conservation methods may be in­

cluded in the project proposal. 5. Revised CSR proposal should be submitted as discussed in the meeting.

It has been decided that the case shall be further considered only after submission of the necessary / satisfactory clarification.

It is also informed that the unit is required to comply with the Office Memorandum dated 30.09.2011 and 05.10.2011, issued by the Ministry of Environment & Forests, Government of India.

 Summaries of above decisions are also provided in Table­1.

Page 30 of 33

Page 31: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Table­1 : List of the projects which were placed before the SEAC in the sixty third meeting held on 31.01.2012 at 12:00 hrs. and the Summary Decisions thereof:

A Cases   placed   for   consideration   of   Environment Clearance 

Sl.  No.

 Name of the unit  Summary Decision

1. M/s. U.K. Cement Pvt. Ltd. Proposed  Cement Grinding Unit at Jl. No. – 58, Vill.  & Mouza – Bamunara, Bamunara Industrial Area, Durgapur, GP – Gopalpur, PO – Panagarh Bazar, PS – Kanksa, Dist. ­ Burdwan, Pin – 713212, West Bengal.

Fresh Environmental Clearance to be issued with suggested 

amendments

2. M/s. Shri Shankar Suwan Estate Pvt. Ltd.Proposed expansion of Cement Grinding Unit at  Jl.  No. 24, Mouza – Balanpur,  PS – Kanksa, PO – Ikra, Jamuria Municipality,   Pin   –   713362,   Dist   –   Burdwan,   West Bengal.

Opinion of WBPCB to be obtained with reference to 

siting policy for reconsideration of the proposal

3. M/s. Kolkata West International City (P) Ltd.Proposed  Township   Project   (PHASE   IA)   at   Mouza   – Kona,  Balitikuri,  Bankra,  Pakuria,  Tentulkuli,  Khalia  & Salap, PO & PS – Domjur, Dist – Howrah, West Bengal.

AAS Recommended for fresh 

presentation for Phase I & IA

4. M/s. Bengal Anmol South City Infrastructure Ltd. Proposed   Infrastructure   cum   Logistic   Hub   “FREIGHT PORT”   at   Jl.   No.   –   2   &   13,   Mouza   –   Joypurbill   & Jagdishpur, PS – Liluah, Dist. – Howrah, West Bengal.

AAS

5. M/s. Phoenix Software Ltd. Proposed  IT  Park   at   Jl.  No.   ­   35,  Mouza  –  Gangapur, Kolkata   Information   Technology   Park   (KITP),   Bantala, PS   –   Kolkata   Leather   Complex,   Dist.   –   24   Parganas (South), West Bengal.

AAS

6. M/s. P.S. Villa Pvt. Ltd. & Others Proposed Residential & Commercial Complex at Holding No. – 4S/08/Block­P & 4S/09/Block­P,  Jl. No. – 5 & 6, Mouza  –  Kaikhali  & Mondal  Ganti,  Rajarhat  Gopalpur Municipality Ward No. – 26 & 27, PS – Baguihati, Dist. – 24 Parganas (North), West Bengal.

1. Construction started prior to obtaining   Environmental Clearance.   Referred   to WBPCB   for   necessary action.

2. Asked   for   additional submission

7. M/s. Oriental Sales Agencies (India) Pvt. Ltd. Proposed  Residential  Complex  & Hospital  at  2,   Jessore Road, Holding No. – 380 (N), 1108 (O), Cal­Jessore Road, Jl. No. – 19, Mouza – Dum Dum House, South Dum Dum Municipality   Ward   No.   ­   07,   PO   &   PS   –   Dum   Dum, Kolkata – 700028, Dist. – 24 Parganas (North).

AAS

8. M/s. Srijan Realty Limited & Others Proposed Residential cum Commercial Complex “SRIJAN HARMONY”  at JL No. 77, Holding No. 132, Mouza – Manikpur, PS – Sonarpur, Rajpur Sonarpur Municipality Ward No. 23, Dist – 24 Parganas (South), West Bengal.

SCEC Finalized

Page 31 of 33

Page 32: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

A Cases   placed   for   consideration   of   Environment Clearance 

Sl.  No.

 Name of the unit  Summary Decision

9. M/s. Fortune Park Housing Projects Pvt. Ltd.Proposed Residential Complex at 168 Krishnanagar Road, Vill.   –  Paschim  Khilkapur,   Mouza  –  Moynagadi,  PS  – Barasat, Dist. ­ 24 Parganas (N), West Bengal.

AAS

B Miscellaneous cases

Sl.  No.

Name of the unit & Project address Summary Decision

1. M/s. Strongbonds Polyseal Pvt. Ltd. Proposed   expansion   project   for   enhancement   of production of Unsaturated Polyester Resins at Plot No. – 26/C, 26/D/1 & 26/D/2, Kalyani Industrial Estate Phase I, Block – D, Dist. – Nadia, Pin – 741235, West Bengal.

Asked for observation from WBPCB

C Cases placed for presentationSl.  No.

Name of the unit & Project address Summary Decision

1. M/s. Balaji Paper & Newsprint Private Limited Proposed   Waste   paper   based   plant   and   Cogeneration Captive Power Plant at Jl. No. – 561, 562, 649, 650, Vill. ­ Manikpara, PS – Jhargram, Dist. – Pashim Medinipur, Pin – 721513, West Bengal.

Recommended for submission of fresh Form 1 for the revised 

proposal.

2. Kolkata Metropolitan Development Authority,Proposed   Residential   Complex   at   Plot   No.   1/3,   CIT Scheme   VII   (M),   PS   –   Maniktala,   PO   –   Kankurgachi, KMC Ward No. 32, Kolkata – 700 054, West Bengal.

AAS

3. M/s.   Kanchan   Janga   Integrated   Infrastructure Development Pvt. Ltd.Proposed Integrated Industrial Township (A Joint Venture Company   of   M/s.   Shristi   Infrastructure   Development Corporation   Ltd.   &   M/s.   West   Bengal   Industrial Infrastructure   Development   Corporation   Ltd.)  at Fatapukur, JL No. 9, Mouza – Chhat Gujrimari, JL No. 10,   Mouza   –   Kismat   Sukani,   PS   –   Rajganj,   Dist   – Jalpaiguri, West Bengal.

Appropriate ToR to be issued

Page 32 of 33

Page 33: Minutes of the tenth meeting of the State Level Expert ...web.wbpcb.gov.in/html/SEAC/minute_63.pdfThe proponent has informed vide letter dated 26.08.2011 that there are total 83 nos.

Minutes of the sixty third meeting of the State Level Expert Appraisal Committee, West Bengal held on 31.01.2012 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

C Cases placed for presentationSl.  No.

Name of the unit & Project address Summary Decision

4. M/s. Rajarhat IT Park Ltd. (A Bharti Enterprise)Proposed IT Park “ASTRA TOWERS” at Plot No. IIC/1, Action Area – II, New Town, Rajarhat, Kolkata, Dist – 24 Parganas (North), West Bengal.

AAS

5. M/s. Techno IndiaProposed expansion of Educational cum Office Building at  EM­4/1 & 4/2, Salt Lake, Sector – V,  Kolkata – 700 091,   Bidhannager   Municipality,   Dist   –   24   Parganas (North), West Bengal.

AAS

REC: Recommended Environmental Clearance, SCEC: Stipulated Conditions for Environmental Clearance, AAS: Asked for Additional Submission / Clarification

The meeting ended with a note of thanks to the Chair.