Minutes of 294 th SEAC Meeting Date...
Transcript of Minutes of 294 th SEAC Meeting Date...
Minutes of 294th
SEAC Meeting Date 05/10/2016
The 294
th meeting of SEAC was held in Directorate of Environment, U.P. on
05/10/2016 following members were present in the meeting along with Secretary, SEAC:
1. Dr. M. S. Khan, Chairman
2. Dr. S.N. Singh, Member
3. Dr. S.K. Upadhyay Member
4. Dr. A. K. Singh, Member
5. Dr. D. C. Gupta, Member
6. Shri Ashish Tiwari, Secretary, SEAC
The Chairman welcomed the members to the 294th
SEAC meeting.
General Discussion:
The committee noted that there have been various cases where the SEIAA/SEAC has
directed the proponent to submit information and project proponent, even after longtime, have
not submitted the replies or have submitted replies after long delay. In this situation, even after
the disposal of matter from the level of SEIAA/SEAC, the status of project remains pending (at
the project proponent side) and thus increases the no. of projects in the pendency list. In this
situation, it is advised to submit the information by project proponent within a time limit. The
committee discussed and deliberated that if the project proponent does not submit information as
directed by the committee within 02 months, the matter shall be delisted and shall not be treated
as pending at SEAC. After delisting of the file, the matter shall only be considered after
submission of complete information with a fresh application from the project proponent citing
reasons of delay. After duly submission of replies/form, the matter shall be taken up by the
committee in chronological order as per submission date of replies/application. These
recommendations have to be implemented on all projects being considered by SEAC.
The Members of SEAC unanimously took following decisions on the agenda points
discussed:
1. Group Housing Project “Saya Zion” at GC-6/II, Gaur City, Plot No-GH-01, Sector-4,
Greater Noida. Sri Shivendra Nath, GM, GC-6/II, Gaur City, Plot No-GH-01, Sector-4,
Greater Noida. File No. 3644
The committee noted that the matter was earlier discussed in SEAC meeting dated
21/07/2016 wherein the project proponent was directed to submit information:
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 2 of 62
1- Submit the structural design duly signed by the qualified structural engineer of the
date prior to the start of the project work and approved layout plan of the complete
project should also be submitted along with the building plans.
2- Submit the date of start of construction with 100/- Rs. Affidavit.
The project proponent submitted their replies through letter dated 16/08/2016. A
presentation was made by Shri Shivendra Nath, project proponent along with their consultant
M/s Environment and Technical Research Center. The committee discussed the reply and
observed that the structural design certificate issued by Dr. Khalid Moin mentions the project
details as existing blocks which suggests that vetting has been done regarding the proposed
construction. The project proponent submitted that the details in the certificate have been
mentioned on the basis of approved drawings hence, this language has been used and there is no
construction on the proposed part of the project. However, the committee directed to submit
corrected vetting certificate for 22 floors with mention of proposed blocks. The committee also
directed to get the structural drawings signed by the structural engineer and vetted by the
designated authority with date.
Regarding date of start of construction the project proponent has submitted affidavit
dated 05/08/2016. Necessary additional documents in this regards should also be submitted.
Existing site photographs should also be submitted.
The matter shall be discussed after submission of above information.
2. BEAVE HEART Raj Nagar (Housing Complex) Khasra N0- 1083, Vill-Noor Nagar,
Ghaziabad, U.P. Sri J.P. Malpani, Vice President, B-49, Sector-67, G B Nagar, NOIDA,
U.P. File No. 1667
The committee noted that the matter was earlier discussed in SEAC meeting dated
28/06/2016 wherein the project proponent was directed to submit information:
1. Submit compounding letter with fee receipt.
2. Prima-facia the SEAC feels that this is the case of violation.
3. In tower A, B, G there is increase in units and height by converting stilt into the
ground floor therefore the project proponent has to provide the construction status
date wise of each floor of A, B & G and show that drawing, design, structural
stability certificate were already approved before start of construction. Also
submit the approval of proposed construction of units on ground floor as to be
converted from stilt floor by competent authority.
4. Revised parking is to be submitted for new proposal.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 3 of 62
The project proponent submitted their replies through letter dated 19/08/2016. A
presentation was made by Shri Jaiprakash Malpani, project proponent along with their consultant
M/s Eko Pro Engineers Pvt. Ltd. The proponent, through the documents submitted and the
presentation made, informed the committee that:-
1. The environmental clearance is sought for Group Housing Project “Beave Heart” Raj
Nagar at Khasra N0- 1083, Vill-Noor Nagar, Ghaziabad, U.P. M/s Belgravia Projects Pvt.
Ltd.
2. Salient features details:-
Particulars Details
Total Plot area 20860 m2
Net Plot area 18985 m2
Ground Coverage (Permissible) 5648.0375 m2
Ground Coverage (Achieved) 4386.7 m2
FAR (Permissible) 64549 m2
FAR (achieved) 47995.67 m2
Basement Area (One level) 12178 m2
Stilt Area 1811.79 m2
Built up Area 64008.94 m2
Green Area Approx. 6000 m2 (approx. 32% of plot area) with 17% of plot
under soft green
No. of Floors (Max) Basement + Stilt/Ground + 12 (Max. Height 40 m)
Parking Provided 725 ECS
Domestic Water Requirement
@86 lpcd 238 KLD
Freshwater Requirement 160 KLD
Source of Water Ghaziabad Piped water supply;
Borewells for emergency use
Wastewater Generation 214 KLD
STP Capacity 250 KLD
Treated Wastewater 205 KLD
Reuse of Treated Wastewater 78 KLD in flushing; 6 KLD in irrigation;
Wastewater discharge in Sewerage System 121 KLD
Solid Waste generated Approx. 1621 Kg/day
Solid Waste Management It will be segregated into biodegradable, recyclable and others
components and disposal will be ensured into municipal bins.
Separate bins for biodegradable waste and recyclable waste will
be provided.
Domestic Water Requirement @86 lpcd
238 KLD
Freshwater Requirement 160 KLD
Source of Water Ghaziabad Piped water supply;
Borewells for emergency use
Wastewater Generation 214 KLD
STP Capacity 250 KLD
Treated Wastewater 205 KLD
Reuse of Treated Wastewater 78 KLD in flushing; 6 KLD in irrigation;
Wastewater discharge in Sewerage System 121 KLD
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 4 of 62
Solid Waste generated Approx. 1621 Kg/day
Solid Waste Management It will be segregated into biodegradable, recyclable and others components and disposal will be ensured into municipal bins.
Separate bins for biodegradable waste and recyclable waste will
be provided.
Rainwater Harvesting Terrace area = 4380 m2 (approx.)
Avg. rainfall = 800 mm/year
Hourly rainfall = 60 mm/hour (15 mm/15 m)
Runoff Coefficient = 0.8 (terrace)
Avg. rainwater collection per 15 minute during peak rainfall
= Terrace = 4380 X 0.8 X 0.015
= 53 m3/15 m
No. of Harvesting Wells 2 (only for Rooftop)
Total Electrical Requirement 2009 kw
DG Sets 4 X 320 kVA
Use of Solar energy Solar lighting for common areas and solar water heaters
(approx. 30 kW)
Soil Excavation None
CSR Activity 2% of total project cost (Rs. 1.32 Crore) on Education, health care and village development
3. Ground use details:- Activity/Use Area in SqM Percentage
Residential Blocks 4386.7 23
Hard Green 2859.19 15
Soft Green 3140.81 17
Roads + Services +
Facilities
8598.3 45
Total Plot Area 20860 m2
Area for Road widening 1875 m2
Net Plot Area 18985 m2
4. The project proposals are covered under category 8"a" of EIA Notification, 2006, as
amended.
The project proponent also submitted letter dated 27/11/2016 from Ghaziabad
Development Authority issued for M/s Belgravia Pvt. Ltd. khasra no. 1083, Village-Noornagar,
Ghaziabad. The project proponent also submitted that no construction has been done beyond
compounding and revised drawings after compounding has been approved by GDA. Structural
safety certificate and fire NOC have been submitted. The committee noted that the structural
design for B block was approved for 11 floors before construction, hence, 12th floor can not be
allowed now, when the construction has already been started with approval of 11 floors only. In
block A & G, the project proponent proposal for converting stilt into housing on ground floor
may be allowed with condition that all other layout plan shall remain the same.
The committee discussed the matter and recommended grant of environmental
clearance for proposed expansion in block A & G in the project along with general
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 5 of 62
conditions as earlier prescribed by the authority for construction project and following specific conditions:
1. Provision of parking should be restricted to ECS as required under Development
Authority bye-laws.
2. Provision of setback on all sides should be made as per Development Authority bye-laws.
3. Copy of all NOCs from different Departments shall be obtained prior to start of
construction.
4. Necessary planning for any anticipated expansion should be incorporated in present
design in view of structural stability.
5. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste
(Management and Handling) Rules, 2000 (as amended).
6. 03 m peripheral green shall be provided around the project inside the project boundary.
7. 15% area of the total plot area shall be compulsorily made available for the soft green
belt development including the peripheral green belt.
8. Project falling with in norm area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
9. Criteria/ norms provided by competent Authority regarding the seismic zone be followed
for construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for
the residents. Rise of stairs should be constructed in a way, so that it should provide
smooth movement.
10. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase. 100% waste water is to be
treated in captive STP conforming to prescribed standards of receiving body for
designated use. Monitoring of STP to be done daily till its stabilization.
11. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken
with regular testing and monitoring of treated water.
12. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to
be used in-house as manure and surplus manure should be managed by giving it to end
users. STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
13. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to
minimum 2% of the total project cost shall be prepared phase wise and approved by
Board of Directors of the company. A copy of resolution as above shall be submitted to
the authority. A list of beneficiaries with their mobile nos./address should be submitted
alongwith six monthly compliance reports.
14. LEDs should be used in all common areas and corridors. 100% solar lighting is to be
provided in the open areas/ stairs cases.
15. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
16. All entry/exit point should be bell mouth shaped.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 6 of 62
17. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
18. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done
only from the roof top. RWH from green and other open areas shall be done only after
permission from CGWB.
19. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
20. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to
be carried out as CPCB Guidelines.
21. Crèche to be provided during the construction/operation phase.
22. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
23. Provision of separate room for senior citizen with proper amenities shall be made.
24. Protection shall be provided on the windows of the high rise flats for security of
residents.
25. Unless and until all the environmental issues are sorted out the occupancy will be
restricted and would be only allowed after achieving the Permission from the competent
authority.
26. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
27. For any extraction of ground water, prior permission from CGWB shall be taken.
28. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
29. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
30. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.
Shall be made available to the temporary residents/workers at the project site including
the proper treatment and the disposal of the wastes.
3. Group Housing at Pot No-GH-01D, Sector-16, Greater Noida West- Sri Garav Garg,
Director, A-128, Sector-63, Noida. File No. 2673
The committee noted that the matter was earlier discussed in SEAC meeting dated
28/06/2016 wherein the project proponent was directed to submit information: 1. The project proponent was absent. The consultant has failed to submit evidence for no
construction at the site for which EC has been asked alongwith proof and photographs.
2. In blocks A, B, C, D the floors have been added therefore, the project proponent has to bring
the proof that structural design was approved before the commencement of the project.
Revised approved map from competent authority is to be submitted alongwith comparative
statement showing status of the project.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 7 of 62
3. Total project cost is Rs. 100 Cr. Corporate Social Responsibility (CSR) cost is Rs. 2.0 Cores;
need based project plan of phase wise work to be done along with budgetary provision should
be prepared and approved by Board of Directors of the company. A copy of resolution as
above shall be submitted to the authority. List of beneficiaries and address and photographs is
to be submitted accordingly.
The project proponent submitted their replies through letter dated 12/08/2016. The
proponent submitted affidavit for no construction. An inspection of the site has also been
undertaken by Regional Officer, UPPCB, Greater Noida and Deputy Director, Directorate of
Environment on 18/02/2016 and communicated to Directorate of Environment through letter
dated 16/03/2016. The committee discussed the inspection report according to which there are 04
towers proposed in the project out of which civil work for 02 towers basement is under progress
whereas construction work for rest 02 towers have not been initiated. The project proponent also
submitted that the project has got approval from authority for 3.5 FAR and all the maps and
drawing have been approved by the development authority on this FAR. The project proponent
also submitted construction status of proposed towers in the project.
A presentation was made by Shri Gaurav Garg, project proponent along with their
consultant M/s Eko Pro Engineers Pvt. Ltd. The proponent, through the documents submitted
and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Expansion of Group Housing Project at Pot
No-GH-01D, Sector-16, Greater Noida, U.P. M/s Ratan Buildtech Pvt. Ltd.
2. The environmental clearance for earlier proposals was issued by SEIAA, U.P. through
letter no. 1600/Parya/SEAC/1565/2012/AD(H), dated 08/10/2013.
3. Comparative details for earlier and expansion proposal:
Parameter Earlier Present
Plot Area 16863 m
2
16863 m2
Proposed FAR 46150.75 m
2
58334.96 m2
Ground Coverage 3137.15 m
2
2989.19 m2
Green Area 7168.42 m
2
7271.71 m2
Built Up Area 60293.59 m
2
89094.54 m2
Apartments 450 588
Blocks 5 4
Floors 16 26
Water Requirement 204 KLD 284 KLD
FAR (m2
)
Basement (m2
)
Stilt (m2
)
Built up area (m2
)
46150.75
13463.03
679.81
60293.59
58334.96
12938.94
10664.04
89094.54
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 8 of 62
4. Break-up of ground coverage:
Activity Area (m
2
) %
Built up 2989.19 18
Green 7271.71 43
Roads 2432.62 14
Facilities 4169.48 25
5. Built-up area calculation details:
Activity Area (m
2
) %
FAR 58334.96 65
Basement 12938.94 15
Stilt 10664.04 12
Facilities 7158.57 08
6. Salient features details for expansion project:
Location Plot GH 01-D, Sector 16, Greater Noida
Objective Group Housing with 588 Apartments
Total Plot Area 16863 m
2
Permissible FAR (3.5) 59020.5 m
2
Proposed FAR (3.46) 58334.96 m
2
Buildings 57194.22 m
2
Commercial 589.41 m
2
Common Facilities/Services 7158.57 m
2
Stilt/Podium Area 10664.04 m
2
Basement Area 12938.94 m
2
Built Up Area 89094.54 m
2
Road Area 2432.62 m
2
Permissible Ground Coverage
(35%)
5902.05 m2
Proposed Ground Coverage
(18%)
2989.19 m2
Open Area 13873.81 m2
Required Green Area
(50% of Open Area)
6936.905 m2
Proposed Green Area (43%) 7271.71 m2
Number of Trees Required (one tree/100 m2 of open area)
138
Number of trees proposed 270
Composition of Green Area 50% trees as peripheral greenbelt, 25% shrubs, 25%
grasses;
50% trees would be evergreen (130)
No. of Flats 588 (2 Bed & 3 Bed)
Number of Blocks 4
Number of Person 3308
Maximum Floors B + Stilt + 26
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 9 of 62
Maximum Height 81 m
Required Parking as per Gr. Noida Authority norms (one car/802 of FAR)
729
Proposed Parking 744
Parking under Stilt 230 (@ 20 m2/Car)
Parking in Basement 514 (@ 30 m2/Car)
Electrical Requirement 1920 kW
DG Sets 1 X 250; 1 X 1010 kVA
Fuel in DG set Low Sulphur Diesel
Height of DG Set stack on Cumulative capacity 6 m above terrace
Solar lights In open & some common areas (approx. 11 kW)
Water Requirement 3308 person X 86 = 284 KLD
7271.71 m2 green area X 1 l = 7 KLD
(Freshwater 189 KLD, Source Proposed Piped Water
Supply from GNIDA)
Wastewater generation 256 KLD
A 280 KLD Sewage Treatment Plant is being set up and
treated sewage (250 KLD) will be reused for flushing (95
KLD) & Horticulture (7 KLD).
Sewerage Disposal/Use in external plantation 148 KLD
Solid Waste (0.45 Kg/person/day) 1488 Kg/day
Management of Solid Waste Biodegradable Waste (744 Kg)- Composting
Recyclable waste (446 Kg) – authorised vendors
Other Waste (298 Kg) – Secured landfill site
To be managed by private vendor M/s Antony Waste
Handling Cell Private Limited, Noida
Electronic Waste Collected and stored at safe place, managed as per norms/guidelines.
Hazardous Waste Collected and stored at safe and secured place, managed as
per Hazardous Waste Rules.
STP Sludge Approx. 8 Kg/day, To be managed by private vendor M/s
Antony Waste Handling Cell Private Limited, Noida
Rainwater Harvesting Max. Rainfall – 90 mm/Hr. – 23 mm/15 minutes
Terrace Area – 3000 m2
Open Area – 13000 m2
Runoff Factor for Terrace – 0.8
Runoff Factor for open area – 0.3
Runoff from terrace – 3000 x 0.8 x 0.023 - 55 m3
/15 minute
Runoff from open – 13000 x 0.3 x 0.023 - 58 m3
/15 minute
Total Runoff – 90 m3
/15 minute
Number of Harvesting tank and collection
Chamber
2 sets of recharge pit and desilting tank
Desilting Tank – 6 X 3 X 2 m effective depth- 36 m3
Recharge Pit – 3 X 2.5 X 2 m effective dept - 15 m3
Total Capacity of one set – 51 m3
Soil Excavation 14000 X 6 = 84,000 m
3
Management Top Soil – 12,000 m3 would be stored at a safe and secured
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 10 of 62
place for reuse in greenery development. 40,000 m3 would be used in landscaping, contouring and
internal roads development.
32,000 m3 would be used in external development.
The soil would be transported in covered tractor trolley.
7. The project proposals are covered under category 8"b" of EIA Notification, 2006.
The committee discussed the matter and recommended grant of environmental
clearance on the project proposals along with general conditions as earlier prescribed by the authority for construction project and following specific conditions:
1. Provision of parking should be restricted to ECS as required under Development
Authority bye-laws.
2. Provision of setback on all sides should be made as per Development Authority bye-laws.
3. Copy of all NOCs from different Departments shall be obtained prior to start of
construction.
4. Necessary planning for any anticipated expansion should be incorporated in present
design in view of structural stability.
5. An underground tank shall be planned within the premises for storage of rain water for
water recharge purposes.
6. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste
(Management and Handling) Rules, 2000 (as amended).
7. 03 m peripheral green shall be provided around the project inside the project boundary.
8. 15% area of the total plot area shall be compulsorily made available for the soft green
belt development including the peripheral green belt.
9. Project falling with in norm area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
10. Criteria/ norms provided by competent Authority regarding the seismic zone be followed
for construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for
the residents. Rise of stairs should be constructed in a way, so that it should provide
smooth movement.
11. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase. 100% waste water is to be
treated in captive STP conforming to prescribed standards of receiving body for
designated use. Monitoring of STP to be done daily till its stabilization.
12. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken
with regular testing and monitoring of treated water.
13. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to
be used in-house as manure and surplus manure should be managed by giving it to end
users. STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 11 of 62
14. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to
minimum 2% of the total project cost shall be prepared phase wise and approved by
Board of Directors of the company. A copy of resolution as above shall be submitted to
the authority. A list of beneficiaries with their mobile nos./address should be submitted
alongwith six monthly compliance reports.
15. LEDs should be used in all common areas and corridors. 100% solar lighting is to be
provided in the open areas/ stairs cases.
16. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
17. All entry/exit point should be bell mouth shaped.
18. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
19. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done
only from the roof top. RWH from green and other open areas shall be done only after
permission from CGWB.
20. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
21. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to
be carried out as CPCB Guidelines.
22. Crèche to be provided during the construction/operation phase.
23. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
24. Provision of separate room for senior citizen with proper amenities shall be made.
25. Protection shall be provided on the windows of the high rise flats for security of
residents.
26. Unless and until all the environmental issues are sorted out the occupancy will be
restricted and would be only allowed after achieving the Permission from the competent
authority.
27. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
28. For any extraction of ground water, prior permission from CGWB shall be taken.
29. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
30. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
31. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.
Shall be made available to the temporary residents/workers at the project site including
the proper treatment and the disposal of the wastes.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 12 of 62
4. Common Biomedical Waste Treatment Facility at Plot No. 672, Village- Khumbhi,
kanpur Dehat,UP. M/s Medicare Environmental Management Pvt. Ltd UP. File No.
3677
The committee noted that the matter was earlier discussed in SEAC meeting dated
18/06/2016 wherein the project proponent was directed to submit information:
1- Justification for proposed common biomedical waste treatment facility at Kumbhi,
Kanpur when already 2-3 common biomedical waste treatment facilities have been
installed within 150 km radius.
2- The project proponent to submit the inventory of Hospitals/clinics/Dispensaries
/Health care units including the details of beds with in 150km radius.
3- Status of operation of other nearby common biomedical waste treatment facilities
with capacity of incinerator.
4- All the facts submitted should be verified by C.M.O.
5- The committee also decided to provide objection letter of association of Sangam
Medi Services Pvt. Ltd. dated 14/06/2016 association of Common Bio Medical Waste
facility operation in UP letter dated 21/03/2016 to the proponent to give para wise
comments to be considered in SEAC meeting.
The project proponent submitted their replies through letter dated 16/08/2016. A
presentation was made by Shri Sanjay Prakash Garg, representative of project proponent along
with their consultant M/s Ramky Enviro Engineers Ltd. The proponent, through the documents
submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Common Biomedical Waste Treatment
Facility at Plot No. 672, Village- Khumbhi, Kanpur Dehat, UP. M/s Medicare
Environmental Management Pvt. Ltd.
2. Location of the project:
Project Schedule 7(da) – Category B Bio-Medical Waste Treatment Facilities
Location Plot No 672, On NH 2, Kumbhi Village, Tehsil Akbarpur, Kanpur Dehat, Uttar Pradesh
Land Area 2 Acres
Land Coordinates 260 21’ 47.10” N, 790 52’ 3.61” E
Project Cost Rs.10 Crores.
Elevation 128-130 meters above MSL
Nearest Railway stn. Malasa Railway station- 9.13 km South-East
Nearest City Akbarpur 10km
Nearest Airport Airport- 55km North East, Airstrip(IIT Kanpur)- 40km North East
3. Justification for proposed common Biomedical waste treatment facility at Kumbhi,
Kanpur when already 2-3 common Biomedical waste treatment facilities have been
installed within 150 km radius:
Sr. No. District Population (In Lakhs)
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 13 of 62
1 Kanpur 46
2 Kannauj 17
3 Etawah 16
4 Auraiya 14
5 Jalaun 17
6 Hamirpur 11
7 Mahoba 9
8 Banda 18
9 Fatehpur 26
10 Unnao 31
11 Hardoi 41
Total 246
4. Certified Bed details within Six Districts:
Sr. No. District Govt Pvt No.of Beds Remarks
1 Kanpur Nagar 1522 15674 17,196 Data received by E- mail
2 Kanpur Dehat 964 360 1324 Data received by post
3 Kannauj 1070 1,070 Data received by post
4 Etawah 517 517 Data received by post
5 Auraiya 517 150 667 Data received by post
6 Jalaun 313 220 533 Data received by post
Total 4903 16404 21307
5. Beds within Twelve Districts as per Population:
Sr.
No.
District Population (In Lakhs) Govt Pvt No.of Beds Remarks
1 Kanpur Nagar 27 1522 15674 17,196 Data received by E- mail
2 Kanpur Dehat 19 964 360 1324 Data received by post
3 Kannauj 17 1070 1000 2,070 Govt Certified Pvt Assumed
4 Etawah 16 517 500 1,017 Govt Certified Pvt Assumed
5 Auraiya 14 517 150 667 Data received by post
6 Jalaun 17 313 220 533 Data received by post
7 Fatehpur 26 1067 1000 2067 Assumed Pvt
8 Unnao 31 1220 1200 2420 Assumed Pvt
9 Hardoi 21 1394 1400 2794 Assumed Pvt
10 Hamirpur 11 901 900 1801 Assumed Pvt
11 Mahoba 9 568 600 1168 Assumed Pvt
12 Banda 18 1019 1000 2019 Assumed Pvt
Total 226 11072 24004 35076
6. Quantity of Untreated Waste within Coverage Area:
Total no of
beds (within
Kanpur Zone)
Qty. of
Incinerable
BMW / per Bed
(in grams)
Total
Generation of
BMW / Day
(in Kg)
BMW
Handling
Capacity of
MPCC (in Kg)
BMW Handling
Capacity of
Willword (in
Kg)
BMW not
Handling per
day (in Kg)
30,000 0.350 0.350*30,000
=
10,500
200*16 hr. =
3,200
100*16 hr. =
1,600
10,500 - 3,200 -
1,600 = 5,700
Note: There are two facilities M/S MPCC and M/S Willword Environmental, calculations are being done on the basis of
capacity of 200 kg/hr and 100 kg/hr respectively, which is not sufficient to cater 30,000 beds.
Two Common Bio- Medical Waste Treatment Facilities covering only 45% waste within coverage area
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 14 of 62
As per information only one CBWTF has Authorization. Uttar Pradesh Pollution Control Board (UPPCB) had issued Closure Notice on 27/05/2014 to M/S Willword
Environment due to non-performance. As on date, application is under consideration.
7. Status of Operation of other nearby Common Biomedical Waste Treatment Facilities
with Capacity of Incinerator:
8. All relevant points are explained above and objections are raised in regard to district –
Chandauli and Firozabad but proponent is proposing the CBWTF in Kanpur.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 15 of 62
9. Selected land is in adjoining to existing TSDF (Hazardous facility), far away from
habitation area.
10. The project proposal falls under category 7(da) of EIA Notification, 2006 (as amended).
The committee discussed the matter and recommended following TORs for conducting
EIA studies regarding the proposals in view of amendment in EIA Notification dated
17/04/2015:
Additional TORs :
1. An agreement/membership of hazardous waste management as per the provisions of
revised hazardous waste management rules, 2008 shall be submitted alongwith the EIA
report.
2. Executive summary of the project – giving a prima facie idea of the objectives of the
proposal, use of resources, justification, etc. In addition, it should provide EMP.
3. Justification for selecting the proposed capacity of the incineration facility.
4. Status of project with reference to guidelines of CPCB regarding establishment of Bio
Medical Waste Disposal Facilities.
5. Establishment of the facility as per Bio Medial Waste (Management & Handling) Rules
1998 (as amended).
6. Land requirement for the facility including its break up for various purposes, its
availability and optimization.
7. Details of proposed layout clearly demarcating various activities such as security,
8. Waste Storage Rooms, Waste Treatment Equipment Rooms/Areas, Treated Waste
Storage Room, Pollution Control Devices like APCS and ETP, ash storage/disposal area,
vehicle washing areas, and others such as admin area, worker’s room, health centers,
greenbelt, etc.
9. Details on collection and transportation of Bio Medical Waste from health care
establishments. No. of vehicles and feature of vehicles, etc.
10. Details of waste storage facilities/rooms.
11. Treated water to be recycled and Commitment of zero discharge is to be submitted.
12. Details of the treatment equipment’s capacity and make.
13. Details of the incineration system – a statement on the compliance to the CPCB
guidelines for common bio medical waste incinerators in respect of waste feed cutoffs,
operating parameters of combustion chambers, flue gas cleaning, ash handling, etc.
14. Details on fuel requirement for incineration.
15. Details on flue gas emissions discharge through stack and proposed pollution control
technologies.
16. Details on residue/ash generation and management.
17. Details of waste heat utilization, if any.
18. Details on wastewater management alongwith zero discharge plans as committed by the
project proponent.
19. Details of the proposed overall safety and health protection measures.
20. Details on source of water and power to the facility.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 16 of 62
21. Details of the existing access road(s)/walkways to the designed operations in the site and
its layout.
22. Location of the incineration facility and nearest habitats with distances from the facility
to be demarcated on a toposheet (1: 50000 scale).
23. Landuse map based on satellite imagery including location specific sensitivities such as
national parks / wildlife sanctuary, villages, industries, etc.
24. Topography details.
25. Surface water quality of nearby water bodies.
26. Details on proposed groundwater monitoring wells, locations, frequency of monitoring,
parameters, etc.
27. Environmental Corporate Responsibility (ECR) plan along with budgetary provision
amounting to 2% of total project cost shall be prepared and approved by Board of
Directors of the company. A copy of resolution as above shall be submitted to the
authority alongwith list of beneficiaries with their mobile nos./address.
28. Action plan for the greenbelt development in accordance to CPCB published guidelines.
29. Details on pollution control technologies and online monitoring equipments.
30. Details on monitoring of pollutants at source –performance of the incinerator. including
operating hours, fuel consumption, operating parameters (Combustion chamber –
temperature, pressure, Stack temperature, total particulate matter, HCl, NOx as per Bio
Medial Waste (Management & Handling) Rules 1998.
31. Stack and fugitive emissions may be monitored for SPM, HCL & NO2 as per Bio Medial
Waste (Management & Handling) Rules 1998.
32. Specific programme to monitor safety and health protection of workers.
33. Details of Administrative and technical organizational structure.
34. EMP devised to mitigate the adverse impacts of the project should be provided along
with item-wise cost of its implementation (Capital and recurring costs).
35. Details of the emergency preparedness plan and on-site & off-site disaster management
plan.
36. Affidavit to be submitted for the actual surveys done with detailed photographs of
monitoring etc.
37. NOC from UPPCB shall be taken and submitted to SEAC before submission of EIA
report.
38. In case there will be any dispute or litigation in any Hon'ble Court, the proponent shall be
responsible and in such case, the TOR issued will deemed to be cancelled automatically.
The final EIA report after incorporation of public hearing observations/comments should
be submitted to the committee for further consideration of the matter.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 17 of 62
5. Group Housing Project at Plot No-GC-3F/GH-03, Sector-16C. Greater Noida. M/s
Geotech Homz Pvt Ltd. File No. 3224
The committee noted that the matter was earlier discussed in SEAC meeting dated
19/08/2016 wherein the project proponent was directed to submit information:
"The project proponent submitted their replies through letter dated 19/08/2016. The
committee observed that the submitted photographs are not digital as directed. The
committee again directed to submit digital photographs."
The project proponent submitted their replies through letter dated 22-08-2016. A
presentation was made by authorized representative of project proponent along with their
consultant M/s Ind Tech House Consult, Delhi. The proponent, through the documents submitted
and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Expansion of Group Housing Project at Plot
No-GC-3F/GH-03, Sector-16C, Greater Noida, M/s Geotech Homz Pvt. Ltd.
2. The environmental clearance to the project was earlier issued by SEIAA, U.P. under
Category 8(a) for plot area 10,010 sq. m., built-up area 47,118.596 sq. m. and 330
dwelling units (vide environmental clearance No. 808/Parya/SEAC/1934/2013/JDCA(S),
dated 12-10-2013).
3. The project comprises 04 numbers of residential towers along with community hall,
Community Hall & Commercial Complex and adequate parking facilities.
4. Total Plot Area and Built-up Area of the project is 10,010.00 sq. m. and 56,002.11 sq. m.
respectively. Total dwelling units 438. Maximum no. of proposed floors for residential
tower is 2B+G/ST+19.
5. Comparative salient feature details of earlier and proposed expansion proposal: Description As per Previous EC As per New
Proposal
Difference % Increase /
Decrease
Plot Area 10,010 sq. m. 10,010 sq. m. Nil No Change
Permissible FAR 27,527.50 sq. m.
(@ 275 of the Plot
Area)
35,035 sq. m.
(350)
7,507.5 sq. m. + 27.27
Proposed FAR 27,147.698 sq. m.
(@271 of the Plot
Area)
35,031.12 sq. m.
(349.96)
7,883.422 sq.
m.
+29.03
Permissible Ground Coverage
(@35% of the Plot Area)
3,503.50 sq. m. 3,504 sq. m. 0.5 sq. m. +0.014
Proposed Ground Coverage 2,523.232 sq. m.
(@25.21% of the Plot Area)
2,596.53 sq. m.
(25.9%)
73.298 sq. m. +2.90
Ancillary Area (@14.49% of
FAR)
3,989.072 sq. m. 5,203.20 sq. m. 1,214.128 sq.
m.
+30.43
Stilt Area 786.326 sq. m. 572.28 sq. m. 214.046 sq. m. -27.22
Basement Area 15,195.50 sq. m. 15,196 sq. m. 0.5 sq. m. +0.003
Landscape Area 3,743.24 sq. m. 1,855 sq. m.
(18.53% of plot
1,888.24 sq.
m.
-50.44
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 18 of 62
area)
Built-up Area 47,118.596 sq. m. 56,002.11 sq. m. 8,883.514 sq. m.
+18.85
Dwelling Units 330 DU 438 DU 108 DU +32.72
Estimated Water Requirement - 192 KLD - -
Estimated Waste Water
Generation
126 KLD 152 KLD 26 KLD +20.63
Power Demand 1,060 KVA 1,752 KW 692 KW + 65.28
Power Backup 760 KVA 1200 KVA 440 KVA + 57.89
Parking Facilities 399 ECS 473 ECS 74 ECS + 18.54
Rain Water Harvesting Pits 04 Nos. 03 Nos. 01 - 25
Solid Waste Generation 875 kg/day 1.0 TPD - -
6. Comparative statement of all existing and proposed tower: Particulars No. of Floors (As per
Approved EC)
No. of Floors (As per
Revised proposal)
Addition Construction Status as
on April, 2016
Tower-A G + 7 G + 17 10 Floors G + 2
Tower-B G + 19 G + 19 (No change) N.A. G + 19
Tower-C G + 19 G + 19 (No change) N.A. G + 19
Tower-D G + 7 G + 17 10 Floors G+6
Commercial 275.275 Sq. Meter 350.35 Sq. Meter 75.075 Sq.
Meter
No construction
7. Salient feature details for expansion proposal: S. No. Description Details
AREA DETAILS
1. Plot Area 10,010.00 sq. m.
2. Permissible FAR Area 350% 35,035 sq. m.
3. Proposed FAR Area (349.96)% 35,031.12 sq. m.
4. Ground Coverage Area Permissible (35%) 3,504 sq. m.
5. Ground Coverage Proposed (25.9%) 2,596.53 sq. m.
6. Total Built-up area 56,002.11 sq. m.
7. Total No. of DUs 438
8. Height of the Tallest Building 59.5
9. Project Cost 84
10. Number of Residential Towers 04
11. Max No of Floors (Residential Tower) 2B+G/ST+19
GREEN AREA
12. Green area required (18.51% of Plot Area) 1,853 sq. m.
13. Green area proposed (18.53% of Plot Area) 1,855 sq. m.
PARKING DETAILS
14. No. of ECS required 438 ECS
15. No. of ECS proposed 473 ECS
POPULATION
16. Expected Population Total 2,414person
• Residential – 1,971
• Floating -443
WATER REQUIREMENT
17. Total water requirement 192 KLD
18. Fresh water requirement 136KLD
19. Horticulture water requirement 02 KLD
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 19 of 62
20. Water Cooled DG Cooling 06 KLD
21. Filter Backwash 05 KLD
WASTEWATER & SOLID WASTE GENERATION
22. Waste water Generation 152 KLD
23. STP Capacity 185 KLD
24. Solid waste generation 1.0 TPD
POWER DEMAND
25. Maximum Power Demand 1752 KW
26. DG set backup 1200 KVA (2 x 600 KVA)
PROJECT COST
27. Project Cost 84 Crores
8. Land use details of the project: Particulars Area, sq. m. %
Ground Coverage 2596.52 25.94
Commercial Area 348.74 3.48
Surface Parking 270 2.70
Green Area 1855 18.53
Paved area 3951.2 39.47
Other Open areas 988.54 9.88
Total Plot Area 10010 100.00
9. Population details: Residential DU'S POP/DU TOTAL
Saleable DU‘s 438 4.5 1971
Total 1971
Non residential (sport club / commercial employees)
COMMUNITY Hall 877.33 09
Commercial (Shopping) 348.75 35
Facility Management Staff LS 30
Total 74
Visitors 369
Total Population 2414
10. Water calculation and its source: Sl.
No.
Description Occupancy / Capacity /
Area
Rate
(Liters)
Total Water Demand
(KLD)
A. Residents
Domestic 1971 65 128
Flushing 1971 21 42
B. Non-residential (Working)
Domestic 74 15 01
Flushing 74 30 02
C. Visitors
Domestic 369 06 02
Flushing 369 09 03
C. Gardening 1855.3 01 02
D. Water Cooled DG Cooling ( For 1200 0.9 07
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 20 of 62
6 Hrs.)
E. Filter Backwash LS LS 05
Total Water Requirement 192
Head Source Quantity
Fresh Water Requirement Greater Noida Industrial Development Authority 136 KLD
Treated Water Requirement On site STP 56 KLD
11. Waste water details: Head Quantity, KLD
Total Water Requirement 192
Fresh Water Requirement 136
Treated Water Requirement 56
Water for Flushing 47
Gardening 02
DG Cooling 06
Waste Water Generation (80% of total domestic fresh water demand + 100% of
Flushing Water)
152
Capacity of STP 185
Treated Water Generation 122
Surplus Sewage to be discharged into public sewer with prior permission / or to
be used in nearby construction activity
66
12. Parking details: Particulars
FAR Area (In sq.m)
Number (ECS)
Required Parking as per bylaws(@1ECS/80 SQM FAR Area) 35,031.12 438
Area (in sq. m.) ECS
Proposed Parking 473
Surface Parking 270.00 13
Stilt Parking 540.654 18
Upper Basement Parking 6,655.121 221
Lower Basement Parking 6,655.121 221
13. Waste generation details: Total Waste Generation 1.0 TPD
Organic Waste Generation 0.60 TPD
E- Waste Generation 07 KG/Day
Sludge Generation 54.75 KG/Day
Hazardous Waste Generation (DG Waste Oil) 240 Lts/ Annum
14. The project proposals are covered under category 8"a" of EIA Notification, 2006, as
amended.
15. The comparative statement of all existing and proposed tower as below:
Particulars No. of Floors (As per
Approved EC)
No. of Floors (As per
Revised proposal)
Addition Construction Status as
on April, 2016
Tower-A G + 7 G + 17 10 Floors G + 2
Tower-B G + 19 G + 19 (No change) N.A. G + 19
Tower-C G + 19 G + 19 (No change) N.A. G + 19
Tower-D G + 7 G + 17 10 Floors G+6
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 21 of 62
Commercial 275.275 Sq. Meter 350.35 Sq. Meter 75.075 Sq. Meter
No construction
From the information submitted by the project proponent as per above table it was
informed that in Tower A & D 10 floors have been added while the construction have been done
in G+2 in Tower A and G+6 in Tower D. In Tower B & C the construction has been done in
G+19 as per pervious EC. No construction has been made in the commercial.
1. Through Notarized affidavit dated 28-06-2016, the project proponent informed that the
construction on the tower A & D was started on 1-04-2015. As on date, the tower A& D
are 2B+G+2 and 2B+G+6 respectively. Tower A & D are now proposed as 2B+G+17
and 2B+G+17 respectively.
2. The project proponent also submitted digital photographs of tower A & D as per the
direction of SEAC meeting dated 19-08-2016.
The committee discussed the matter and recommended grant of environmental
clearance for proposed project along with general conditions as earlier prescribed by the authority for construction project and following specific conditions:
1. Provision of parking should be restricted to ECS as required under Development
Authority bye-laws.
2. Provision of setback on all sides should be made as per Development Authority bye-laws.
3. Copy of all NOCs from different Departments shall be obtained prior to start of
construction.
4. Necessary planning for any anticipated expansion should be incorporated in present
design in view of structural stability.
5. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste
(Management and Handling) Rules, 2000 (as amended).
6. 03 m peripheral green shall be provided around the project inside the project boundary.
7. 15% area of the total plot area shall be compulsorily made available for the soft green
belt development including the peripheral green belt.
8. Project falling with in norm area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
9. Criteria/ norms provided by competent Authority regarding the seismic zone be followed
for construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for
the residents. Rise of stairs should be constructed in a way, so that it should provide
smooth movement.
10. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase. 100% waste water is to be
treated in captive STP conforming to prescribed standards of receiving body for
designated use. Monitoring of STP to be done daily till its stabilization.
11. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken
with regular testing and monitoring of treated water.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 22 of 62
12. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to
be used in-house as manure and surplus manure should be managed by giving it to end
users. STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
13. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to
minimum 2% of the total project cost shall be prepared phase wise and approved by
Board of Directors of the company. A copy of resolution as above shall be submitted to
the authority. A list of beneficiaries with their mobile nos./address should be submitted
alongwith six monthly compliance reports.
14. LEDs should be used in all common areas and corridors. 100% solar lighting is to be
provided in the open areas/ stairs cases.
15. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
16. All entry/exit point should be bell mouth shaped.
17. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
18. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done
only from the roof top. RWH from green and other open areas shall be done only after
permission from CGWB.
19. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
20. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to
be carried out as CPCB Guidelines.
21. Crèche to be provided during the construction/operation phase.
22. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
23. Provision of separate room for senior citizen with proper amenities shall be made.
24. Protection shall be provided on the windows of the high rise flats for security of
residents.
25. Unless and until all the environmental issues are sorted out the occupancy will be
restricted and would be only allowed after achieving the Permission from the competent
authority.
26. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
27. For any extraction of ground water, prior permission from CGWB shall be taken.
28. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
29. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
30. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.
Shall be made available to the temporary residents/workers at the project site including
the proper treatment and the disposal of the wastes.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 23 of 62
6. Group Housing Project at Plot No-17/GH-02, Sec-17, Vrindavan Yojana, Gomti Nagar,
Lucknow- Sri Gyan Prakash Mani Tripathi, Director, CP-6, Vikrant Khand, Gomti
Nagar, Lucknow. File No. 3645
The committee noted that the matter was earlier discussed in SEAC meeting dated
01/08/2016 wherein the project proponent was directed to submit information:
1. Structural stability certificate to be issued by IIT and all structural designs to be
vetted.
2. Submit the detail of facilities as proposed.
3. Submit total cost of the project is Rs. 50.0 Cr. and vetted by CA and submit the CSR
details phase wise.
4. Submit the rain water harvesting plan.
5. Landscape plan with park furniture is to be submitted.
6. Drainage plan showing storm water drain for disposal of water during rainy season.
7. Delete 25 nos. of excess parking, accordingly plan is to be submitted.
8. Corporate Social Responsibility (CSR) plan along with budgetary provision
amounting to minimum Rs. 1.0 Cr. shall be prepared and approved by Board of
Directors of the company. A copy of resolution as above shall be submitted to the
authority. A list of beneficiaries with their mobile nos./address should be submitted
alongwith photographs.
The project proponent submitted their replies through letter dated 24-08-2016. A
presentation was made by Shri Vijay Prakash, authorized representative of project proponent
along with their consultant M/s Globus Environment Engineering Services. The proponent,
through the documents submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Group Housing Project “BCC Blue
Mountain”at Plot No-17/GH-02, Sec-17, Vrindavan Yojana, Gomti Nagar, Lucknow,
U.P. M/s Basera City Developers Pvt. Ltd.
2. Salient Features Of The Project: PROJECT REQUIREMENTS DETAILS
Total Plot Area 8,935.99 m2
Permissible Green Area @ 16% 1,431.01 m2
Achieved FAR (3.75 times of total plot
area)
33,507.4 m2
Purchased FAR (9.52 % of FAR 3.75) 3190.36 m2
Total Achieved FAR (4.1 times of total plot area)
36697.76 m2
Total Built-up Area (FAR+ Non-FAR) 43,477.52 m2
No. of Towers 1
No. of Floors Basement + Stilt +14
Max. Height of the Building 48.0 mt.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 24 of 62
Total No. of Flats 54 (3BHK) + 214 (2BHK) = 268 flats
Parking Facilities Required: 503 E.C.S. Provided: 528 E.C.S.
Power Requirement and Source Power Requirement: 1500 kVA, Max. Demand: 1440 kVA Total Demand Load: 1340 kVA, Transformer No. 1x 2000 kVA
SOURCE: Power Supply Receiving from UPPCL Substation
Power Backup DG Sets : 1 x 63 kVA
Stack Height of DG Set 51.54 meter
Water Requirement and Source Fresh/Domestic Water
Requirement
85.75 KLD
Treated Waste water use from
STP
Nil
SOURCE : Water will be taken from the supply
of Awas Vikas /Jalsansthan.
No borewell is proposed at the site.
Sewage Treatment and Disposal The waste water generated during operation phase will be disposed
in the existing Trunk Sewer line of Awas Vikas Passing through the
site in front of the Entry/Exit Gate. Consent letter is enclosed.
Estimated Population 912 (268 Dwelling Units ) + 228 (@25% of the total Population)
Project Cost Rs. 50.0 Crores
ECS required 503 ECS
Achived Total Parking area 503 ECS
Open parking 70 ECS proposed 70-25= 45 ECS
3. Percentage Land Use Detail of The Total Plot Area: Land Use Detail % Land Use Area Statement
(meter square)
Total plot Area 100 % 8,935.99
Green Area
(PARK-1,2,3,4)
16 % 1,431.01
Ground Coverage 33.90 % 3,029.13
Area Under Road 35.42 % 3163.47
Area for Parking (along the boundary
wall)
13.38 % 1196.25
Space for DG Sets and transformer
area
1% 89.13
Area for Guard Room 0.3% 27.0
4. Building Area Statement of The Project: Land Use Detail % Land Use Area Statement
(meter square)
Total Plot Area 100% 8,935.99
Permissible FAR 3.75 times of total plot area 33,509.96
Achieved FAR 3.75 times of total plot area 33,507.4
Purchased FAR 9.52 % of FAR 3.75 3190.36
Total Achieved FAR 4.1 times of total plot area 36,697.76
Permissible Ground Coverage 35 % 3,127.59
Achieved Ground Coverage 33.89 % 3,029.13
Covered Area on Basement Floor - 6,779.6
Area Under Hard Green Area 54.79% of the total Green Area 784.06
Area Under Soft Green Area 45.21% of the total Green Area 646.94
Total Green Area 16% of the total plot area 1,431.01
Total Built-up Area (FAR+ Non-FAR) - 43,477.52
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 25 of 62
No. of Towers - 1
No. of Basement - 1
No. of Floors - Basement + Stilt +14
Max. Height of the Building - 48.0 m
Total No. of Flats - 54 (3BHK) +214 (2 BHK) = 268 Flats
5. Breakup Of Water Requirements For Various Uses: S.
No.
Description Area (m2) Population Rate of
water
demand
(lpcd)
Total Water
Requirement
(KLD)
% in term
of total
water
requirement
A. Domestic Water
• Block A 35557.49
m2
912 86 78.43 79.05 %
• Commercial Shops (6
Nos.), Indoor Games, Hall
1 & 2, Kitchen
1140.27 m2 16 30 0.48
• Floating Population (@25% of total Population)
- 228 30 6.84
Total domestic water demand ~ 85.75
KLD
B. Green Area
1,431.01
m2
1L/
sqm/day
1.43 KLD 1.32 %
C. Car Washing 528 Nos. 30 L/car 15.84 KLD 14.6%
D. Miscellaneous use (make up for
water body, decorative fountain &
general washing)
- - - 5.0 KLD 4.61 %
E. DG Sets (3 Nos.):
1 x 63 KVA (8 hrs)
0.9
l/KVA/hr
0.45 KLD 0.42%
Total Water Requirement (predicted values) KLD (A+B+C+D+E) 108.47
~ 108.5
KLD
100%
6. Rain Water Harvesting Pit Detail: Surface Area (Sqm) Area
(Ha)
Co-
efficient of
run off
Intensity
of rain fall
Run-off Cal.
Building(Terrace/
Hard Paved Area
1144.41 0.1144 0.80 25 10x0.90x25x0.1144 25.74
Roads/Pathway 4475.85 0.4476 0.60 25 10x0.60x25x0.4476 67.14
Landscaped areas 1431.01 0.1431 0.30 25 10x0.30x25x0.1431 10.73
Total 103.61
Volume of Storm Water (V) 51.80 m3
Volume of 1 No. Rain Water Harvesting Pit (v) 16 m3
No. of Rain Water Harvesting Pit (V/v) =
3.24 = 4
7. Total Solid Waste Generation: S. No. Category Population Kg per capita per day
(kg/capita/day) Waste generated (kg/day)
% in term of total waste
generation
1. Residents
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 26 of 62
• Block A
912
@ 0.5 456
92.56
2. • Commercial Shops
(6 Nos.), Indoor
Games, Hall 1 &
2, Kitchen
16 @0.15 2.4 0.49
3. Floating Population
(@25% of total Population)
228 @ 0.15
34.2
6.94
4. Landscape Waste
(1,431.01 m2 = 0.353 acre)
@0.2
Kg/acre/day
0.07 0.01
Total Solid Waste Generated
(predicted values) kg/day
492.67
Say 493 kg/day
100%
1. Biodegradable Waste 345.1 kg/day 70%
2. Non-Biodegradable Waste 147.9 kg/day 30%
8. The project proposals are covered under category 8(a) of EIA Notification, 2006.
The committee discussed the matter and recommended grant of environmental
clearance for proposed project along with general conditions as earlier prescribed by the
authority for construction project and following specific conditions:
1. Provision of parking should be restricted to ECS as required under Development
Authority bye-laws.
2. Provision of setback on all sides should be made as per Development Authority bye-laws.
3. Copy of all NOCs from different Departments shall be obtained prior to start of
construction.
4. Necessary planning for any anticipated expansion should be incorporated in present
design in view of structural stability.
5. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste
(Management and Handling) Rules, 2000 (as amended).
6. 03 m peripheral green shall be provided around the project inside the project boundary.
7. 15% area of the total plot area shall be compulsorily made available for the soft green
belt development including the peripheral green belt.
8. Project falling with in norm area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
9. Criteria/ norms provided by competent Authority regarding the seismic zone be followed
for construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for
the residents. Rise of stairs should be constructed in a way, so that it should provide
smooth movement.
10. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase. 100% waste water is to be
treated in captive STP conforming to prescribed standards of receiving body for
designated use. Monitoring of STP to be done daily till its stabilization.
11. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken
with regular testing and monitoring of treated water.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 27 of 62
12. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to
be used in-house as manure and surplus manure should be managed by giving it to end
users. STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
13. Total cost of the project is Rs. 50 Cr. Corporate Social Responsibility (CSR) plan along
with budgetary provision amounting to minimum 2% of the total project cost (Rs. 1.0
Cr.) shall be prepared phase wise and approved by Board of Directors of the company. A
copy of resolution as above shall be submitted to the authority. A list of beneficiaries
with their mobile nos./address should be submitted alongwith six monthly compliance
reports.
14. LEDs should be used in all common areas and corridors. 100% solar lighting is to be
provided in the open areas/ stairs cases.
15. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
16. All entry/exit point should be bell mouth shaped.
17. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
18. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done
only from the roof top. RWH from green and other open areas shall be done only after
permission from CGWB.
19. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
20. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to
be carried out as CPCB Guidelines.
21. Crèche to be provided during the construction/operation phase.
22. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
23. Provision of separate room for senior citizen with proper amenities shall be made.
24. Protection shall be provided on the windows of the high rise flats for security of
residents. 25. Unless and until all the environmental issues are sorted out the occupancy will be restricted and
would be only allowed after achieving the Permission from the competent authority.
26. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
27. For any extraction of ground water, prior permission from CGWB shall be taken.
28. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
29. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
30. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.
Shall be made available to the temporary residents/workers at the project site including
the proper treatment and the disposal of the wastes.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 28 of 62
7. Cement Grinding Unit of KLK Cement Pvt. Ltd., at Plot N0-E-18,19,20, UPSIDC
Sidhwan,Jaunpur. M/s KLK Cement Pvt. Ltd. File No. 2335
The committee noted that the matter was earlier discussed in SEAC meeting dated
18/06/2016 wherein the project proponent was directed to submit information:
1. The details of the minimum and maximum ground level concentration of the
particulate in the predominant wind direction particularly in the month of winter at
low height to be resubmitted with incremental concentration level.
2. All analysis reports station wise and date of sampling with photographs be
submitted.
3. Details landscape plan be submitted.
4. Proposal for online monitoring of PM 10 and PM 2.5 be submitted.
5. Monitoring stations at Highway should be marked and mentioned in Traffic Study.
The ambient noise level monitoring at all stations be conducted and analysis be
submitted in bar chart form.
6. Details of CSR to be submitted with the name of beneficiaries and phase wise
implementation plan.
7. Rainwater Harvesting Plan for Roof and surface water be submitted separately.
8. Details of water conservation measures along with wastewater treatment plant to be
submitted.
9. The query no. 2 is not well replied and is to be submitted as suggested.
10. 10 m peripheral green is to be submitted duly marked on layout plan. Tree to be
planted at a distance of 5 m, plan in this regard should be submitted.
11. Copy of NOC from UP Pollution Control Board is to be submitted.
The project proponent submitted their replies through letter dated 26-08-2016. The
committee discussed the matter and directed the project proponent to submit following
information:
1. Actual air quality monitoring data for one month period to be resubmitted
2. Plan for 10 meter peripheral green belt along with the proposal of tree plantation with
suitable tree species.
3. Running/production status from regional office UPPCB.
4. Plan for kuttcha pond on layout.
5. NOC from UPPCB to be submitted.
6. Location of sampling point showing and certifying on Google map with wind direction.
7. Permission from CGWA for ground water abstraction to be submitted.
The matter shall be discussed after submission of information as above.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 29 of 62
8. Proposed Commercial Project at plot no- 2B, Sector 94, Noida, U.P. M/s BPTP
International Trade Centre Ltd. File No. 3693
The committee noted that the matter was earlier discussed in SEAC meeting dated
01/08/2016 wherein the project proponent was directed to submit information:
1. The proponent to submit the fresh proposal for the grant of EC for plot 2B and if
required for 2A separately as EC was granted for entire plot 2 for which EC as
expired.
2. Building plan, Services plan, Landscaping plan, parking plan, approved by competent
authority and stability certificate vetted by IIT is be submitted for plot no. 2B.
3. Complete area statement in single unit of sqm to be submitted alongwith the area
details of all features in percentage.
4. Plan for bio composting at the site is to be submitted.
5. Corporate Social Responsibility (CSR) plan along with budgetary provision
amounting to minimum 2% of the project cost shall be prepared and approved by
Board of Directors of the company. A copy of resolution as above shall be submitted
to the authority. A list of beneficiaries with their mobile nos./address should be
submitted.
6. Construction details alongwith an affidavit have to be submitted.
The project proponent submitted their replies through letter dated 29-08-2016. A
presentation was made by Shri Rajeev Gupta, project proponent along with their consultant M/s
Envirta Sustainable Solutions India Pvt. Ltd., New Delhi. The proponent, through the documents
submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Commercial Project “Capital City” at plot no-
2B, Sector 94, Noida, U.P. M/s BPTP International Trade Centre Limited.
2. Environmental clearance for the earlier proposal was issued through SEIAA letter no.
7/SEAC/277/2008/TA(J)/ dated 01/06/2009 for total built up area of 2,40,232.58 sq.m.
Out of the total EC accorded built up area of 2,40,232.58 sq.m the proponrnt have
constructed one tower of G + 15 height with built up area of 76,644 sqm.
3. Comparative Salient Features: S. No. Description Details (EC accorded) Details (After Revision)
1. Location Plot no. 2, Sector – 94, Noida, Uttar Pradesh
Plot no. 2B, Sector – 94, Noida, Uttar Pradesh
2. Geographical
coordinates of the
Project Site
Latitude: 28°33'8.43"N
Longitude: 77°19'34.55"E
3. Category 8 (b)
4. Plot Area 85,672.17 sq m (21.17 acres) 57,344.10 sq m (14.17 acres) (-33%)
5. Estimated Population 16,991 16,790 (- 1 %)
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 30 of 62
6. Built-up Area 2,40,232.58 m2 2,73,130.32 m2 (+13.7%)
8. Electricity load 25 MVA provided by State Electricity Board
19.2 MVA provided by State Electricity Board (- 23 %)
9. No. of RWH pits 5 Pits 2 Pits + 2 tanks
10. Water Requirement Total water Demand - 2322KLD Total water Demand - 1760KLD (-
24%)
11. Source of water Ground water for Drinking +
Municipal Water supply
STP Treated Water + Municipal Water
supply
4. Percentage wise area details: S. No Particulars Earlier EC Area Details in
SQM
Revised Area Details in SQM
1 Total Plot Area 85672.17 57344.10 (- 33%)
2 Ground Coverage 20784.07 14261.85 (-31.38%)
3 Proposed FAR Area
Retail & Office
Hotel
1,67,412.16
1,18,849.96
48,562.2
1,29,715.32 (-22.52%)
1,14,510.18(-3.66%)
No (Sold out)
4 No. of Tower Total Tower 05 Total Tower 04
6 Total Built-up Area 2,40,232.58 2,73,130.2 (+ 13.69%)
7 Green Area 28129.76 25162.92 (+ 11.05%)
5. Green Area Requirement: • Open Area=Site Area-Ground Coverage
• Green Area Required @50% of open area
• =21541.13 SQM
• Green area proposed : 25,162 sq.m
• i.e. 43.88 % of revised plot area
• No. of trees required = 1 tree/80 sq.m of plot area i.e. 716 trees
• Number of trees proposed = 720
6. Solid waste generation details: S. No. Description of
Population
Occupancy Waste Generated (Kg per
capita / day)
Waste Generated (kg/day)
Municipal Solid waste
1. Working Staff 13,084 @ 0.20 2617
2. Visitors 17,425 @ 0.15 2614
Total 5231
Landscape Waste
Area Waste Generated
3. Landscape Waste 25,162.92 sq.m /6.22 acres
@ 0.2 kg/acre/day 1.244
Total Waste Generation = 5232 kg/day
7. The project proposals are covered under category 8"b" of EIA Notification, 2006, as
amended.
The committee discussed the matter and recommended following TORs and general
guidelines for conducting EIA studies:
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 31 of 62
Additional TORs: 1. Structural design certificate signed by architect and vetting authority should be submitted.
All structural design drawings should be signed by architect and counter signed by
vetting authority.
2. Revised area in percentage, affidavit showing tower wise details
3. NABL certificate copy of lab though which the monitoring data is submitted
4. Master plan of the area showing proposed project. Permissible uses of the proposed site
as per zoning regulation.
5. Allotment letter from concerned development authority.
6. All approved drawings/maps alongwith all approved services plans.
7. A site plan showing the project site and its surroundings with physical features and
topographical details, such as land use, contours and drainage pattern, along with
photographs of the site from all four sides, should be included in the background
information.
8. Physical features within 30 m of the project sites with their ownership.
9. Section of all internal roads as proposed along R/W and C /W as well dimension is to be
to map.
10. Complete details of facilities to be developed by the project proponent i.e. for which
environment clearance is sought.
11. Area details showing proposed uses as residential, commercial, parks, parking, roads,
other services, facilities of the project also in percentage. FAR and Non FAR area should
be clearly mention
12. Details of landscape plan with park furniture.
13. Plan for no of trees, one tree per 80 sq.mt. of area.
14. Use of reflecting paints on roof top and side walls.
15. Details of rain water harvesting are to be given.
16. Provision of 100% solar lighting along the road side, stair cases, common places.
17. Hydro-geological investigations be carried out and obtain permission from Central
Ground Water Authority for withdrawal of ground water.
18. Water requirement and water management plan alongwith necessary permissions for
discharge. STP details. The project is proposed as zero liquid discharge. Complete
proposal and various treated water uses as recycled should be mentioned.
19. 10% EWS/LIG housing provision shall be made as per Development Authority bye-laws.
20. Examine in detail the proposed site with reference to impact on infrastructure covering
water supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw
wastes from the complex on land/water body and into sewerage system.
21. Consider soil characteristics and permeability for rainwater harvesting proposals, should
be made to prevent ground water contamination. Maximize use of treated water by
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 32 of 62
recycling and utilization of rainwater.
22. Make provision for safety against failure in the operation of wastewater treatment
facilities. Identify acceptable outfall for treated effluent.
23. Details of green belt as a measure for mitigation of dust and noise and buffer between
habitation and proposed project.
24. Landscape plan, green belts and open spaces may be described separately.
25. Study the existing flora and fauna of the area and the impact of the project on them.
26. Examine existing crèche, education, health facilities, police, post Office, Banks and other
services and make adequate provisions in the proposal.
27. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.
28. Application of renewable energy/alternate energy, such as solar and wind energy may be
described including solar water heating in the guidelines for entrepreneurs.
29. Consider solid wastes, including e-waste in addition to other solid wastes and their
disposal.
30. Identification of recyclable wastes and waste utilization arrangements may be made.
31. Explore possibility of generating biogas from biodegradable wastes.
32. Arrangements for hazardous waste management may be described as also the common
facilities for waste collection, treatment, recycling and disposal of all effluent, emission
and refuse including MSW, biomedical and hazardous wastes. Special attention should be
made with respect to bird menace.
33. All community facilities is to be proposed as per norms and is to be submitted.
34. Provisions made for safety in storage of materials, products and wastes may be described.
35. Disaster management plan should be prepared.
36. Traffic management plan including parking and loading/unloading areas may be
described. Traffic survey should be carried out both on weekdays and weekend.
37. Parking provision is to be made for higher ECS worked out either as per state bye-laws or
construction manual of the MoEF.
38. Exclusive Parking area in the basement (excluding other facilities) and surface is to be
clearly mentioned.
39. Use of local building materials should be described.
40. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details
with provisos of sampling port for monitoring be described.
41. Work out MGLC for the combined capacity of DG sets.
42. Provide for conservation of resources, energy efficiency and use of renewable sources of
energy in the light of ECBC code.
43. Application of resettlement and rehabilitation policy may be described. Project affected
persons should be identified and rehabilitation and resettlement plan should be prepared.
44. Examine separately the details for construction and operation phases both for
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 33 of 62
Environmental Management Plan and Environmental Monitoring Plan.
45. Total cost of the project should be certified by Chartered Accountant. Corporate Social
Responsibility (CSR) plan along with budgetary provision amounting to 2% of project
cost shall be prepared and approved by Board of Directors of the company. A copy of
resolution as above shall be submitted to the authority alongwith list of beneficiaries with
their mobile nos./address.
46. Details of all internal and peripheral roads width.
47. Source and quantity of required water during construction and management of generated
waste water.
48. Project falling with in norm area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
49. Declare/submit the running cost of STP and other environmental management services
(e.g., Municipal Solid Waste Disposal, Green belt Maintenance, Water Management etc.)
in the proposals which are to be including in the allotment letters.
50. The proponent will submit the schedule of monitoring/data collection programme to the
Office of Directorate, Member Secretary, UP Pollution Control Board and District
Magistrate of related District.
General Guidelines:
a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly
attested by Public Notary, stating that:
I. “There is no litigation pending against the project and/or land in which the project is
proposed to be set up (please give name & ownership etc. of the project) and that for any
such litigation what so ever, the sole responsibility will be borne by the Project
proponent.”
II. “No activity relating to this project (i.e. name of the project) including civil construction
has been undertaken at site except fencing of the site to protect it from getting
encroached and construction of temporary shed(s) for the guard(s). (if fencing has not
been done, then the same may be deleted).
III. “I/We hereby give undertaking that the data and information given in the application,
enclosures and other documents are true to the best of my knowledge and belief and
I/We am/are aware that if any part of the data and information submitted is found to be
false or misleading at any stage, the project will be rejected and clearance given, if any
to the Project will be revoked at our risk and cost.” IV. Project does not fall under any buffer zone of no-development as declared /identified under
any law.
b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been
complied with (to be deleted if not applicable) & (b) that details and the data presented are
factually correct”, as per MoEF circular dated 04.08.2009 is also to be submitted along
with EIA.
c. Current, site photographs viewing towards the project area from four directions indicating
date of photograph taken, direction from which taken, name of the project, and signature of
Project proponent along with consultant with seal should be submitted, so as to ensure that
no construction has been started before the grant of EC.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 34 of 62
d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification
of 2006 and the Methods of Monitoring and analysis (Annexure-IV): Guidance for
assessment of representativeness and reliability of baseline environmental attributes
detailed under EIA manual January, 2001 and other guidelines in the matter.
e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically
mentioned. The consultant shall certify that his accreditation is for the sector for which this
EIA is prepared.
f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along
with their complete details including their accreditation, if any shall be indicated.
g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in
the preparation of these reports and the Name of laboratory through which the samples
have been got analysed should be stated in the report. It shall clearly be indicated whether
said laboratory is accredited by NABL or approved under the Environment (Protection)
Act, 1986 (Please refer MoEF office memorandum dated 4th
August, 2009). The name
project leader of the EIA study shall also be mentioned.
h. The EIA document shall be printed on both sides, as for as possible.
The Information’s no (a I , II, III & c) asked under the general guidelines is to be
submitted within 15 days from the date of receipt of the letter and remaining of the information’s
is to be submitted along with the EIA.
9. Group Housing at Plot No-SC-1/B-4, Sector-150, Noida- Si Abhishek Goyal, MD,
302/303, 3rd Floor, Aggarwal Mall, Plot No-3, Sector-5, Dwarka, New Delhi. File No.
3599
The committee noted that the matter was earlier discussed in SEAC meeting dated
20/07/2016 wherein the project proponent was directed to submit information:
1. Approved maps/drawings to be submitted.
2. Structural safety certificate alongwith the signed copy of the drawings be submitted.
3. Digital photographs with date for the site to be submitted.
4. No construction affidavit to be submitted.
5. Minimum 09 m service road should be provide.
6. Submit the internal road section with right of way.
7. Increase the soft green upto 15% of the total plot area.
8. Name of the approved agency for MSW management.
9. Area of STP to be calculated and submitted alongwith its location on the surface.
10. Kachha tank to be provided as per the contour map for RWH. Submit the surface area
of the pond/tank proposed for surface water runoff collection and recharging of
ground water.
11. Creche and convenient shopping provision be made.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 35 of 62
12. Provision of mechanical sludge handling device to be made to dry the sludge. No wet
sludge storage to be allowed.
13. Revise the tree species to include ornamental and short height trees.
14. Evacuation route and traffic circulation plan is to be submitted.
15. A fire hydrant is to be provided for fire fighting.
16. Delete 313 ECS parking as excess proposed and submit revised parking plan.
17. Peripheral green is to be left 6.0 m as committed, revised plan should be submitted.
Landscape plan with park furniture is to be submitted.
18. Total cost of the project is Rs. 50.0 Cr. Corporate Social Responsibility (CSR) plan
along with budgetary provision amounting to 2% of total project cost (Rs. 1.0 Cr.)
shall be prepared and approved by Board of Directors of the company. A copy of
resolution as above shall be submitted to the authority. A list of beneficiaries with
their mobile nos./address with photographs should be submitted.
The project proponent submitted their replies through undated letter received on
02/09/2016. A presentation was made by Shri Ashish Malik, authorized representative of project
proponent along with their consultant M/s Greencindia Consulting (P) Ltd. The proponent,
through the documents submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for of Plot No-SC-1/B-4, Sector-150, Noida, U.P.,
M/s Implex Infrastructure (P) Ltd.
2. Project Details: Project Name Group Housing Project at Plot No. SC-01/ B-4, Sector - 150, Noida, Uttar Pradesh
Land Requirement Net Plot area Built-up Area Remarks
29,545.80 m2 or
7.30 Acres
80,222.8 m2 Implex Infrastructure has obtained General Power of Attorney to develop the Group
Housing Project from M/s Logix
Infradevelopers Pvt. Ltd. which had
obtained the land allotment from Noida
Authority.
Water
Requirement (In
KLD)
Phases Fresh
Water
Treated Water Total Water Requirement
Construction 11 KLD 100 KLD 111 KLD
Operation 107 KLD 106 KLD 173 KLD
STP Capacity - 160 KLD, based on MBBR Technology
Power
Requirement
Power demand: 1,250 KVA Source: Paschimanchal Vidyut Vitran Nigam Ltd.
Back-up power: 3 nos. of DG sets of capacity (3 x 600 KVA) out of which 1 DG set of 600
KVA will be provided as a standby.
Project Cost 216.06 crores
3. Area Statement: S.N. Description Area (In sq.mt.) %age
1 Plot Area 29,545.80
2 Permissible Ground Coverage (26.65% of the plot
area)
7872.8
3 Achieved Ground coverage 4139.6 14.01
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 36 of 62
4 Green area (@79.16% of the open area) 20,113.2 68.07
5 Area under Roads/ Pavements 5293.07 17.9
6 Permissible FAR 55,057.8
7 Achieved FAR 53,993.7
8. Non-FAR 26229.061
9. Total Built-up Area (B1+B3) 80,222.8
10. Maximum Height of Building 91.05 m
4. The total soft green area of the project site is approximately 4431.87 sqm which accounts
for approx. 15 % of the total plot area.
5. Detailed Built-up Area: S.
No.
Towers No. of Floors FAR (sq.mt.) Facility area/ Non
FAR (sq.mt.)
Built-up Area (FAR +
Non FAR) (sq.mt.)
1. Tower-A G + 27 7241.0 1024.626 8265.6
2. Tower-B G + 27 4909.2 1246.193 6155.4
3. Tower-C G + 27 7241.0 1024.626 8265.6
4. Tower-D G + 26 9664.2 913.465 10577.7
5. Tower-E G + 27 7241.0 1024.626 8265.6
6. Tower-F G + 27 4909.2 1246.193 6155.4
7. Tower-G G + 27 6982.8 1024.626 8007.4
8. Villas G + 2 5005.5 - 5005.5
9. Community G + 2 - 623.604 623.6
10. Cricket Academy G 800 - 800
11. Guard Room - - 10 10
12. STP - - 67.5 67.5
13. Basement - - 18023.6 18023.6
Grand Total - 53993.7 26229.061 80222.8
6. Population Details: S.N. Particular Dwelling Units Area (in sq.
mt.) Density/PPU Population
1 Residential Population 376 - - 1,692
2 (a) Community Facility - 623.6 1 person per 10 sq.mt. 62
2 (b) Staff - (@10% of the community building
population)
6
3 (a) Cricket Academy - 800 1 person per15 sq.mt. 53
3 (b) Staff - (@10% of the Cricket Academy population) 5
3 (c) Trainees - (@90% of the Cricket Academy population) 48
4 Service Staff - (@5% of the main residential population) 85
5 Visitors - (@10% of the main residential population) 169
Total Population 2,005
7. Water Requirement-Construction Phase: Description Area (m2) Total Occupancy Rate of water
demand
Total water
requirement (KL)
Labors - 250 45 lpcd 11.25
Water Curing 80222.792 - 1 l/sqm 80.22
Landscaping 20,113.16 - 1 l/sqm 20.11
Total 111.58 ~ 112
8. Population & Water Calculation: Description Area in
sq.mt.
Total
Occupancy
Rate of
water
Fresh
Water
Treated
Water
Total water
requirement
Waste Water
Generation
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 37 of 62
demand (lpcd)
(KLD) (KLD) (KLD) (KLD)
Residential
Population
- 1692 86 101.86 43.65 145.51 125.14
Staff (cricket
academy +
service staff +
community)
- 144 30 3.02 1.30 4.32 3.72
Visitors - 169 15 1.77 0.76 2.54 2.18
Total Domestic Water Requirement in KLD 106.66 45.71 152.37 131.04
Horticulture
& Landscape
20113.2 - 1 liter/m2 - 20 20 -
Fire Fighting - - - - 5 5 -
Total 106.66 65.71 172.37 131.04
9. Parking Details-Required & Proposed: Parking Proposed:
1. Area for Mechanical Parking 12,510.195 sqm
2. Area required for 1 ECS in Mechanical Parking 18 m2
3. Parking provided Mechanical parking in Basement 695 ECS
Total Parking Proposed 695 ECS
10. Solid Waste Calculation: S. N. Category Occupancy Kg per capita per day Waste Generated
(kg/day)
1. Residential Population 1692 0.5 kg/day 846
2. Staff (cricket academy +
service staff + community)
144 0.25 kg/day 36
3. Visitors 169 0.15 kg/day 25.35
4. Horticultural Waste (4.97 acres) @ 0.2 kg/acre/day 0.994
Total Solid Waste Generation = 908.34 kg/day say 908 kg/day
Sludge Generation : 22.86 kg/day
11. Composition of Solid Waste: S. No. Type of Waste Quantity of Waste (Kg/day)
1. Total Waste 908.34
2. Bio-degradable Waste(@60 % of the domestic waste) 545
3. Recyclable Waste (@30% of the domestic waste) 272.50
4. Inert Waste (@10 % of the domestic waste) 90.83
12. Power Requirement: Parameters Operation Phase
Power requirement 1250 KVA
Supply by Paschimanchal Vidyut Vitran Nigam Ltd.
Back-up power supply 3 x 600 KVA DG sets out of which 1 DG set of 600 KVA will be in standby mode
13. The project proposals are covered under category 8(a) of EIA Notification, 2006.
The project proponent submitted approved building plans by Noida Authority, structural
safety certificate dated 26/11/2015 from Jamia Milia Islamia with project details, undated site
photographs, no construction affidavit from the project proponent, site layout plan showing 09 m
service road, internal road section, soft green area, calculation of area for STP (160 KLD), plan
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 38 of 62
for provision of creche and convenient shopping and list of tress to be planted alongwith revised
parking plan. Minimum 03 m peripheral green is also committed by the proponent as per
landscape plan.
The committee discussed the matter and recommended grant of environmental
clearance on the project proposals along with general conditions as earlier prescribed by the authority for construction project and following specific conditions:
1. 18 nos. of fire hydrant should be installed.
2. Provision of parking should be restricted to ECS as required under Development
Authority bye-laws.
3. Provision of setback on all sides should be made as per Development Authority bye-laws.
4. Copy of all NOCs from different Departments shall be obtained prior to start of
construction.
5. Necessary planning for any anticipated expansion should be incorporated in present
design in view of structural stability.
6. An underground tank shall be planned within the premises for storage of rain water for
water recharge purposes.
7. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste
(Management and Handling) Rules, 2000 (as amended). Municipal solid waste
management plan alongwith list of identified vendors.
8. 03 m peripheral green shall be provided around the project inside the project boundary.
9. 15% area of the total plot area shall be compulsorily made available for the soft green
belt development including the peripheral green belt.
10. Project falling with in norm area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
11. Criteria/ norms provided by competent Authority regarding the seismic zone be followed
for construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for
the residents. Rise of stairs should be constructed in a way, so that it should provide
smooth movement. Evacuation route is to be shown on map.
12. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase. 100% waste water is to be
treated in captive STP conforming to prescribed standards of receiving body for
designated use. Monitoring of STP to be done daily till its stabilization.
13. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken
with regular testing and monitoring of treated water.
14. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to
be used in-house as manure and surplus manure should be managed by giving it to end
users. STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 39 of 62
15. The cost of the project is Rs. 216.6 Cr. Corporate Social Responsibility (CSR) plan along
with budgetary provision amounting to minimum 2% of the total project cost (Rs. 4.32
Cr.) shall be prepared phase wise and approved by Board of Directors of the company. A
copy of resolution as above shall be submitted to the authority. A list of beneficiaries
with their mobile nos./address should be submitted alongwith six monthly compliance
reports.
16. LEDs should be used in all common areas and corridors. 100% solar lighting is to be
provided in the open areas/ stairs cases.
17. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
18. All entry/exit point should be bell mouth shaped.
19. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
20. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done
only from the roof top. RWH from green and other open areas shall be done only after
permission from CGWB.
21. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
22. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to
be carried out as CPCB Guidelines.
23. Crèche to be provided during the construction/operation phase.
24. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
25. Provision of separate room for senior citizen with proper amenities shall be made.
26. Protection shall be provided on the windows of the high rise flats for security of
residents.
27. Unless and until all the environmental issues are sorted out the occupancy will be
restricted and would be only allowed after achieving the Permission from the competent
authority.
28. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
29. For any extraction of ground water, prior permission from CGWB shall be taken.
30. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
31. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
32. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.
Shall be made available to the temporary residents/workers at the project site including
the proper treatment and the disposal of the wastes.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 40 of 62
10. Revision & Expansion of "The Jewel of Noida"at plot no. GH-14,Sector- 75, Noida,
U.P. M/s E-Homes Infrastructure Pvt. Ltd. File 3688
The committee noted that the matter was earlier discussed in SEAC meeting dated
02/08/2016 wherein the project proponent was directed to submit information:
1. Green building certificate is to be submitted and then after additional FAR will be
considered as green building.
2. Affidavit for no construction on Rs.100/- Non judicial stamp paper alongwith the latest
site photographs.
3. Submit calculation of soft green area showing on landscape plan including peripheral
green of 03 m wide alongwith park furniture.
4. Kachha tank to be proposed for rain water surface runoff collection and ground water
recharging.
5. STP to be provided on surface, site to be located on the map and detail submitted.
6. Organic waste compactor to be installed and area to be marked on the map.
7. List of approved vendors of SWM disposal.
8. Details of water recycling and the final disposal from the treated waste alongwith the
permission letter from concerned authority.
9. Total cost of the project is Rs. 115.65 Cr. Corporate Social Responsibility (CSR) plan
along with budgetary provision amounting to minimum Rs. 2.3 Cr. shall be prepared and
approved by Board of Directors of the company. A copy of resolution as above shall be
submitted to the authority. A list of beneficiaries with their mobile nos./address should be
submitted alongwith photographs.
The project proponent submitted their replies through letter dated 27/09/2016. A
presentation was made by Shri Nitin Rohatgi, authorized representative of project proponent
along with their consultant M/s YES Enviro Solutions. The proponent, through the documents
submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Group Housing Project "The Jewel of
Noida"at plot no. GH-14,Sector- 75, Noida, U.P. M/s E-Homes Infrastructure Pvt. Ltd.
2. Brief of The Project: PROJECT
FEATURES
EC
ACCORDED
Expansion Total (EC Accorded +
Expansion)
Estimated Population 3087 persons 921 persons 4,008 persons
Estimated Water
Requirement with
source
Construction Phase
Operation Phase
264KLD (Fresh
water=176KL)
Agency:
Municipal
Supply
113 KLD(Fresh water=50 KLD)
Agency: New Okhla Industrial
Development Authority
(NOIDA)
624 ML (Private Water Tanker
supply )
377 KLD ( Fresh Water = 226
KLD)
Agency: New Okhla Industrial
Development Authority
(NOIDA)
Estimated waste water
generation and
treatment
203 KLD (STP
of 150KLD,
FAB
Technology)
71 KLD(STP of 210 KLD is
required Of FAB Technology)
274 KLD (STP of 360 KLD,
FAB Technology)
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 41 of 62
Power Demand and Source
Power Back-up
2830kVA Noida Power
Company Ltd
4 no. of DG
sets of total
capacity of
2000 kVA (4x
500 kVA )
460 kVA Noida Power Company Ltd
1 DG set 280kVA(increment
takes place)
3290 kVA; Noida Power Company Ltd
4 no. of DG sets of total
capacity of 2280 kVA (2 x 640
kVA + 2 x 500 kVA (stand by)
Solid Waste
Generation
1,398kg/day 300kg/day 1698 kg/day
Parking Facilities
Required
Proposed
583as per
MoEF&CC
733as per
Noida Bye
laws 958
259 as per MoEF&CC
316 as per Noida Bye laws
92 ECS
842 ECS as per MoEF&CC
1049 ECS as per Noida Bye-
Laws
1050 ECS
Project Cost 115.65 crores
3. Land Use of Project(Existing + Expansion) LANDUSE AS PER RECENT APPROVAL
A RESIDENTIAL GROUND COVERAGE AREA IN SQ.M PERCENTAGE
1 TOWER A 960.942 4.8
2 TOWER B 614.673 3.1
3 TOWER C 421.9 2.1
4 TOWER D 488.79 2.4
5 TOWER E 421.9 2.1
6 TOWER F 494.904 2.5
7 TOWER G 609.552 3.0
8 GUARD ROOM 28.5 0.1
9 METER ROOM 11.94 0.1
10 PODIUM AREA 1213.61 6.1
11 CONNECTION BRIDGE 81.38 0.4
B OPEN AREA 14651.91 73.3
1 PAVED AREA 8334.91 41.7
2 ROAD AREA 6317 31.6
A+B TOTAL PLOT AREA 20000 100
4. Area Details: S. DESCRIPTION Existing Area (EC
Accorded) (m2) Expansion (m2)
Revision (m2)
Total Area (m2)
Percentage
1 Total Plot Area 20,000 20,000 100
2 Permissible
Ground Coverage
@ 35% of total
plot area
7,000
3 Total Ground
Coverage
5,274.25 73.84 5348.09 26.74
4 Permissible FAR
for Facility
8250 -----
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 42 of 62
Area@15% of 2.75 FAR
5 Permissible FAR
for Facility
Area@15%
additional 0.75
FAR
--- 2,250
6 Total permissible
facility FAR
8250 2,250 10500
7 Permissible
Commercial
FAR(@1% of
55000 FAR)
550 ----
8 Permissible
Commercial
FAR(@1% of
Residential FAR + Purchasable FAR)
---- 150
9 Total Permissible
Commercial FAR
550 150 700
10 Residential FAR of
Group Housing
55,000
11 Additional FAR on
2.75 FAR
2,750
12 Additional Green
building FAR on
0.75 FAR
750
13 Additional FAR for
Metro Corridor
10000
14 Permissible
Purchasable FAR on
0.75 FAR
15000
15 Total Residential
FAR
57,750 25750 83,500
16 Total Permissible
FAR
66,550 28,150 9,47,400
17 Residential FAR 57197.23 25,569 82,766
18 Proposed Commercial FAR
544.58 154 698.399
19 Proposed Facility
FAR
8081.09 2418.567 10499.657
20 Total Achieved FAR 65,823 28,141 93,964.06
21 Stilt area 1,790.58 -13.75 1776.833
22 Basement Area 27,726.72 -36.722 27,763.44
Upper basement 13863.36 -92.533 13770.827
Lower basement 13863.36 -29.255 13992.615
23 Podium Area 1213.61 1213.61
24 Total Built- up Area 95,340.20 29,377.80 124718
25 Total open Area 14,725.75 14,652 73.26
26 Total Proposed
Green [email protected]%
8,255.43 79.54 8334.974
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 43 of 62
of Open area
27 Maximum height of the building
95.325m 65.675m 161 m
5. Green area details of the project site are as follows: S. No Green Area Permissible ( m
2 ) Proposed(m
2) Area in %
1 Required Green Area=50% of
Open Area
7309.44 8334.975 m2 41.67 %
2 Soft Green Area 3654.722 4187.487 m2 20.83 %
3 Hard Green Area 3654.722 4187.487 m2 20.83 %
4 Periphery Green Area ------------ 3645.18 18.22 %
6. Population Breakup: S. No.
Unit Type DU or Area
PPU Total Population
Residential
Group Housing 770 4.5 3,465
Staff (5%) 173
Visitors (10%) 347
Total 3,985
Commercial 698.399 3person
/m2
Staff (10%) 23
Grand Total(1+2+3) 4,008
7. Water requirement details: S.NO. Unit type EC accorded Expansion Total (Existing+ Expansion)
1 Total water required 264 113 377
2 Fresh water 176 50 226
3 Wastewater generation 203 71 274
4 STP Capacity 150 210 360
8. Wastewater Calculations: Domestic Water Requirement 309 KLD
• Fresh (70% of domestic) 216 KLD
• Total Fresh water – ((70% of domestic)+10KLD as make
up water demand for swimming pool)
226 KLD
• Flushing (30% of domestic) 93 KLD
Wastewater Generated (80% fresh domestic+80%
Swimming pool + 100% flushing)
273.8 say 274 KLD
9. Wastewater generated from the project site will be treated in the onsite STP of capacity
360KLD. Approx 247 KLD of water will be recovered from STP which will be utilized
within the project. 93 KLD will be utilized for flushing, 42 KLD for Horticulture
purpose, 16 KLD for D.G sets. Approx. 96 KLD during dry season and 138 KLD during
rainy season will be discharged in CSTP.
10. The project proposals are covered under category 8(a) of EIA Notification, 2006.
The project proponent submitted green building certificate February, 2014. 360 KLD
STP shall be installed on surface. A list of vendor for management of municipal solid waste has
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 44 of 62
been submitted. 138 KLD treated waste water shall be discharged in to CSTP. The committee
discussed the replies and directed to submit following information:
1. Distance of the site from Okhla Bird Sanctuary is 6.4 KM. MoEF Notification dated
01/12/2009 provisions as follows:
"The projects to be located within 10 KM of the National Parks, Sanctuaries,
Biosphere Reserves, Migratory Corridors of Wild animals , the project proponent
shall submit the maps duly authenticated by Chief Wildlife Warden showing these
features vis-a-vis the project location and the recommendations or comments of the
Chief Wildlife Warden thereon (at the stage of EC)."
In compliance to above, certification on map should be submitted from Chief
Wildlife Warden as required.
2. Digital photographs of all proposed towers showing that no construction has been
started yet.
3. Plan for water body with Kachha base should be submitted for storm water collection
for water recharge.
4. Permission for discharge of 138 KLD into CSTP by the competent authority.
5. Total cost of the project is Rs. 115.65 Cr. Corporate Social Responsibility (CSR) plan
along with budgetary provision amounting to minimum 2% of project cost (Rs. 2.3
Cr.) shall be prepared and approved by Board of Directors of the company. A copy of
resolution as above shall be submitted to the authority alongwith list of beneficiaries
with their mobile nos./address.
The matter shall be discussed after submission of information as above.
11. Modernization of integrated Township ''Gomti Green” at Village-Sarsawan,
Ahmamau, Ahdonamau, Lucknow. M/s Emaar MGF Land Ltd. File No. 3685
The committee noted that the matter was earlier discussed in SEAC meeting dated
02/08/2016 wherein the project proponent was directed to submit information:
1. Submit the status of the project about how much construction has been done alongwith
date and photographs and all structural design certificate by structural engineer alongwith
vetted drawings.
2. Submit all services plan, approved layout plan, landscape plan, water balance, solid waste
management and requisite NOCs.
3. Comparative details of existing and expansion project alongwith all the parameters.
4. Compliance report of the earlier EC.
The project proponent submitted their replies through letter dated 05/09/2016. A
presentation was made by Shri Pankaj Tyagi, representative of project proponent along with their
consultant M/s Earthvision Envirotech Pvt. Ltd. The proponent, through the documents
submitted and the presentation made, informed the committee that:-
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 45 of 62
1. The environmental clearance is sought for Modernization of integrated Township ''Gomti
Green” at Village-Sarsawan, Ahmamau, Ahdonamau, Lucknow. M/s Emaar MGF Land
Ltd.
2. Details Of The Township:- Description Of Land Use
Plot Area (sq.m.)
FAR FAR area (sq. m.)
Ground Coverage
Ground Coverage (sq. m.)
Group Housing 86642 2.50 216606 0.35 30325
Plotted 362514 591998 0.65
Type (9X18) 499 86875 1.75 152031 0.65 56469
Type (10X20) 648 133944 1.75 234402 0.65 87064
Type (12X24) 125 37262 1.75 65208 0.65 24220
Type (15X30) 91 39261 1.50 58892 0.55 21594
Type (20X40) 72 65172 1.25 81465 0.45 29327
EWS & LIG 16586 2.00 33172 0.50 8293
Educational Facility
Nursery School 6057 0.80 4846 0.35 2120
Primary School 6072 0.80 4857 0.35 2125
High School 8190 1.00 8190 0.30 2867
Inter College 12077 1.00 12077 0.30 3623
Police Chauki 3030 1.00 3030 0.35 1061
Health Centre 1600 1.50 2400 0.50 800
Post Office 300 1.00 300 0.50 150
Community Centre 4908 1.00 4908 0.35 1718
Commercial 46698 1.75 81722 0.40 18679
Electric Sub Station 8094
STP, Garbage
handling
1820
Green/Open spaces 128953.93
Roads/Circulation 165109
Total FAR Area 858652 964106 290435
Description of Land
Use
Parking area
(basements)
Other non-FAR area Sub total
Group housing 69200 4874 74074
Commercial 40058 1839 41896
EWS & LIG 3623 746 4369
Total Non FAR
Area
120339
Totak Built Up
Area ( FAR+ Non
FAR Area)
1084445
3. Comparative Details: Description Approved Revised Increase/
Decrease
Reason Impact
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 46 of 62
Residential Area
Plotted
Group Housing
EWS & LG
42.11 hac 30.78 hac
8.71 hac
2.62 hac
46.57 hac 36.25 hac
8.66 hac
1.66 hac
(+)4.46 hac (+)5.47 hac
(-)0.05 hac
(-)0.96 hac
The total no. of plots has
increased from
1277 to 1435.
No impact as the covered
area is within
the norms.
Public- Semi
Public Facility
Educational
Health
Community
33 KVA
Electrical Substation
Sub Post Office
Police Station
Police Chowky
S.T.P.
Garbage
Disposal
6.33 hac
3.19
0.48
0.60
0.81
0.03
0.41
0.31
0.50
5.34 hac
3.24
0.16
0.49
0.81
0.03
0.30
0.11
0.20
(-)0.99 hac
(+)0.05 hac
(-)0.32 hac
(-)0.14 hac
0.0
hac
(-)0.11 hac
(-)0.2 hac
(-)0.3 hac
No. of schools
is same only
area has
increased
As per
requirement
Area reduced as
req
No Change
No Change
As per
requirement
As per
requirement
As per
requirement
No impact as
the covered
area is within
the norms.
4. Landscape plan: S.
No.
Particulars Plot Area Area Under Green
1 Green spaces 12.90 ha 12.90 ha
2 Group Housing @ 35% 8.66 3.05 ha
3 Plotted @ 30% 36.25 ha 10.8 ha
4 EWS & LIG @ 35% 1.66 ha 0.5 ha
5 Institutional area @ 25% 5.34 ha 1.3 ha
6 Commercial area @ 25% 4.67 ha 1.16 ha
7 Road (Area under green) 16.38 ha 4.9 ha
Total 33.9
Area of Pond 4.3
Effective Area Under
Green
29.6
5. 33.490 MW power requirements are proposed which will be met by UPVN and for 1 x
1430 KVA. 3×2000 KVA, 6×600 KVA and 19×250 KVA DG sets will be used for back
up power supply.
6. Total ECUs required : 7269 ECU
7. Total ECUs provided : 7269 ECU
8. Water requirement :-
S.
No.
Particular Persons Water
Supply
(KLD)
Fresh Water
(KLD)
Recycled Water
(KLD)
1 Domestic 30125 2590 1604 986
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 47 of 62
(86 lit/day/capita for plots/Gr
housing, EWS &
LIG)
2 Commercial area
@45 lpcd
7491 530 400 130
3 Health Care
@340/bed
100 34 30 4
4 Services areas @45
lpcd
1200 152 90 62
5 Schools @45 lpcd 2997 135 91.45 43.55
6 Swimming Pool
makeup water 7.88 7.88 0
7 Floating population
10% of
residential @15
lpcd
4191 189 120 69
8 Horticulture water
(within
township) @ 3litre/sq m
295
9 AC makeup & DG
cooling
makeup water
698.55
10 Car washing @50
litre/car 32.72
11 Water bodies
makeup water 452
12 Fire Fighting &
UFW 1300
Total Water Consumption 4937.88 2343 2593
Total Net Water Requirement 2343
9. Calculation of Waste water Generation: S. No. Description Waste Water (MLD)
1 Plotted 1.0
2 Group Housing 0.90
3 EWS or LIG 0.50
4 Commercial 0.30
5 Education 0.12
6 Health Centers 0.01
7 Other Facilities 0.05
8 Floating Population 0.1
Total 3.1 approx.
10. Solid Waste Generation: S.
No.
Particulars Population Waste Generated
(Kg/Day)
1 Residential (@ 0.5 Kg/day) 30125 15062.5
2 Visitors (@ 0.15 Kg/day) 4191 628.5
3 Others 2554
Total Solid Waste Generated 1080
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 48 of 62
Horticulture Waste (@ 0.0037 Kg/day) 17
E-Waste (0.15 Kg/C/Yr) <1.0
STP Sludge 38
11. The project proposals are covered under category 8(b) of EIA Notification, 2006.
The committee discussed the matter and found that there is increase in the residential area
from 42 Ha. to 46 Ha. and recommended following TORs and general guidelines for conducting
EIA studies:
Additional TORs: 1. Master plan of the area showing proposed project.
2. Permissible uses of the proposed site as per zoning regulation.
3. Allotment letter/land documents from concerned development authority/sale deed.
4. Copy of agreement of development with LDA.
5. Specific area statements regarding proposed expansion and comparative statements regarding
population and DU, water consumption, waste generation, etc.
6. Comparative area and other environmental parameter statement showing values earlier and
proposed after expansion showing FAR and non FAR area.
7. Submit the status of the project about how much construction has been done alongwith
date and photographs and all structural design certificate by structural engineer alongwith
vetted drawings. 8. All approved revised drawings/maps alongwith all approved revised services plans. All
original maps should be shown during EIA presentation.
9. Structural design certificate signed by architect and vetting authority for already existing
structure should be submitted. All structural design drawings should be signed by architect
and counter signed by vetting authority.
10. Structural design certificate signed by architect and vetting authority after incorporating
proposed expansion structure should be submitted. All structural design drawings should be
signed by architect and counter signed by vetting authority.
11. Status of construction undertaken till date (block wise/tower wise/floor wise)
(proposed/constructed).
12. Compliance of earlier EC.
13. Physical features within 30 m of the project sites with their ownership.
14. Area details showing proposed uses as residential, commercial, parks, parking, roads, other
services, facilities of the project also in percentage.
15. Details of landscape plan with park furniture.
16. Complete details of facilities to be developed by the project proponent i.e. for which
environment clearance is sought.
17. Plan for no of trees, one tree per 80 sq.mt. of area.
18. Use of reflecting paints on roof top and side walls.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 49 of 62
19. Details of rain water harvesting are to be given.
20. Provision of 100% solar lighting along the road side, stair cases, common places.
21. A site plan showing the project site and its surroundings with physical features and
topographical details, such as land use, contours and drainage pattern, along with
photographs of the site from all four sides, should be included in the background information.
22. 10% EWS/LIG housing provision shall be made as per Development Authority bye-laws.
23. Sanctioned plans/maps regarding the project with all services plans.
24. Section of all internal roads as proposed along R/W and C /W as well dimension is to be
to map.
25. Examine in detail the proposed site with reference to impact on infrastructure covering water
supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw wastes
from the complex on land/water body and into sewerage system.
26. Water requirement and water management plan alongwith necessary permissions for
discharge. STP details.
27. Hydro-geological investigations be carried out and obtain permission from Central Ground
Water Authority for withdrawal of ground water.
28. Consider soil characteristics and permeability for rainwater harvesting proposals, should be
made to prevent ground water contamination. Maximize use of treated water by recycling and
utilization of rainwater.
29. Make provision for safety against failure in the operation of wastewater treatment facilities.
Identify acceptable outfall for treated effluent.
30. Details of green belt as a measure for mitigation of dust and noise and buffer between
habitation and proposed project.
31. Landscape plan, green belts and open spaces may be described separately.
32. Study the existing flora and fauna of the area and the impact of the project on them.
33. Examine existing crèche, education, health facilities, police, post Office, Banks and other
services and make adequate provisions in the proposal.
34. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.
35. Application of renewable energy/alternate energy, such as solar and wind energy may be
described including solar water heating in the guidelines for entrepreneurs.
36. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.
37. Identification of recyclable wastes and waste utilization arrangements may be made.
38. Explore possibility of generating biogas from biodegradable wastes.
39. Arrangements for hazardous waste management may be described as also the common
facilities for waste collection, treatment, recycling and disposal of all effluent, emission and
refuse including MSW, biomedical and hazardous wastes. Special attention should be made
with respect to bird menace.
40. Provisions made for safety in storage of materials, products and wastes may be described.
41. Disaster management plan should be prepared.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 50 of 62
42. Traffic management plan including parking and loading/unloading areas may be described.
Traffic survey should be carried out both on weekdays and weekend.
43. Parking provision is to be made for higher ECS worked out either as per state bye-laws or
construction manual of the MoEF.
44. Exclusive Parking area in the basement (excluding other facilities) and surface is to be clearly
mentioned.
45. Use of local building materials should be described.
46. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with
provisos of sampling port for monitoring be described.
47. Work out MGLC for the combined capacity of DG sets.
48. Provide for conservation of resources, energy efficiency and use of renewable sources of
energy in the light of ECBC code.
49. Application of resettlement and rehabilitation policy may be described. Project affected
persons should be identified and rehabilitation and resettlement plan should be prepared.
50. Examine separately the details for construction and operation phases both for Environmental
Management Plan and Environmental Monitoring Plan.
51. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to 2%
of project cost shall be prepared and approved by Board of Directors of the company. A copy
of resolution as above shall be submitted to the authority alongwith list of beneficiaries with
their mobile nos./address.
52. Details of all internal and peripheral roads width.
53. Source and quantity of required water during construction and management of generated
waste water.
54. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
55. Declare/submit the running cost of STP and other environmental management services (e.g.,
Municipal Solid Waste Disposal, Green belt Maintenance, Water Management etc.) in the
proposals which are to be including in the allotment letters.
56. The proponent will submit the schedule of monitoring/data collection programme to the
Office of Directorate, Member Secretary, UP Pollution Control Board and District Magistrate
of related District.
General Guidelines: a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested by
Public Notary, stating that:
I. “There is no litigation pending against the project and/or land in which the project is
proposed to be set up (please give name & ownership etc. of the project) and that for any
such litigation what so ever, the sole responsibility will be borne by the Project proponent.”
II. “No activity relating to this project (i.e. name of the project) including civil construction has
been undertaken at site except fencing of the site to protect it from getting encroached and
construction of temporary shed(s) for the guard(s). (if fencing has not been done, then the
same may be deleted).
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 51 of 62
III. “I/We hereby give undertaking that the data and information given in the application,
enclosures and other documents are true to the best of my knowledge and belief and I/We
am/are aware that if any part of the data and information submitted is found to be false or
misleading at any stage, the project will be rejected and clearance given, if any to the Project
will be revoked at our risk and cost.”
IV. Project does not fall under any buffer zone of no-development as declared /identified under
any law.
b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been
complied with (to be deleted if not applicable) & (b) that details and the data presented are
factually correct”, as per MoEF circular dated 04.08.2009 is also to be submitted along with
EIA.
c. Current, site photographs viewing towards the project area from four directions indicating date
of photograph taken, direction from which taken, name of the project, and signature of Project
proponent along with consultant with seal should be submitted, so as to ensure that no
construction has been started before the grant of EC.
d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification of
2006 and the Methods of Monitoring and analysis (Annexure-IV): Guidance for assessment of
representativeness and reliability of baseline environmental attributes detailed under EIA
manual January, 2001 and other guidelines in the matter.
e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically
mentioned. The consultant shall certify that his accreditation is for the sector for which this
EIA is prepared.
f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with
their complete details including their accreditation, if any shall be indicated.
g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in the
preparation of these reports and the Name of laboratory through which the samples have been
got analysed should be stated in the report. It shall clearly be indicated whether said laboratory
is accredited by NABL or approved under the Environment (Protection) Act, 1986 (Please refer
MoEF office memorandum dated 4th August, 2009). The name project leader of the EIA study
shall also be mentioned.
h. The EIA document shall be printed on both sides, as for as possible.
The Information’s no (a I , II, III & c) asked under the general guidelines is to be submitted
within 15 days from the date of receipt of the letter and remaining of the information’s is to be
submitted along with the EIA.
12. Proposed Mix Use Project at Plot No.-TCG/1-A-V-6 & TCG/1-A-V-7, Gomti Nagar,
Phase 1, Vibhuti Khand, Lucknow, U.P. File No. 3723
The project proponent did not appear in the meeting. However, their consultant M/s ENV
DAS India Pvt. Ltd. submitted letter dated 05/10/2016 that approved layout plan and structural
certificate are still awaited therefore they should be allowed to present the case after receipt of
the same from the concerned authorities. The matter shall be discussed after submission of
complete information and request from project proponent to consider the matter in chronological
order.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 52 of 62
13. Group Housing at Vill-Jatoli, Tehsil-Sardhna, Meerut. Sri Suman Kumar Guha, GM,
C-60, Sikka House, Preet Vihar, New Delhi. File No. 3096
The committee noted that the matter was earlier discussed in SEAC meeting dated
28/06/2016 wherein the project proponent was directed to submit information:
1. Notarized affidavit for no construction is to be submitted in Rs. 100/- non judicial stamp.
2. All maps and designs signed by architect are to be submitted.
3. Revised structural Certificate by structural engineer preferably of IIT/CBRI mentioning
the details tower wise are to be submitted.
4. Revised built-up area statement of all towers with basement+stilt+floors is to be
submitted.
5. ECS to be provided as per building bye-laws and 71 ECS to be deleted. Revised parking
plan is to be submitted.
6. Landscape plan showing detail of park furniture is to be submitted.
7. Total project cost is Rs. 94.73 Cr. Corporate Social Responsibility (CSR) cost is Rs. 1.90
Cores; need based project plan of phase wise work to be done along with budgetary
provision should be prepared and approved by Board of Directors of the company. A
copy of resolution as above shall be submitted to the authority. List of beneficiaries and
address and photographs is to be submitted accordingly.
The project proponent submitted their replies through letter dated 06/09/2016. A
presentation was made by Shri Suman Kumar Guha, project proponent along with their
consultant M/s YES Enviro Solutions. The proponent, through the documents submitted and the
presentation made, informed the committee that:-
1. The environmental clearance is sought for Group Housing Project at Vill-Jatoli, Tehsil-
Sardhna, Distt-Meerut, U.P. M/s Nav Grih Developers Pvt. Ltd.
2. Area details of the project: S.No. Particulars
Area m2
1. Plot Area 17,485.00
2. Perm. Ground Coverage ( 40 % ofTotal Plot Area) 6,994
3. Proposed Ground Coverage (29.21 % ofTotal Plot Area) 5,107.88
4.
Permissible FAR(@ 2.5)
• Permissible FAR for Group Housing (@2)
• Permissible FAR for Commercial(@ 0.5)
43 ,712.50
34,970
8,742.5
5.
Proposed FAR (2.49)
• Residential FAR(@ 2)
• Commercial FAR (@ 0.499)
43,704.50 34,970
8,734.5
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 53 of 62
6. Built Up Area 57921.612
7. Landscape Area ( 15 % of Plot Area) 2,622.75
8. Fire Escape Area 2,313.70
9. Mumty & Machine Room Area 664.88
10.
Stilt Area
• Stilt - 1
• Stilt- 2
10,750.47
4,591.15
6,159.32
11. Open Area 9,754.37
3. Revised built-up area statement of all towers with basement + stilt + floors: S.No Tower Ground 1
st to 11
th Total
R-
FAR/SANC
R-Built
up/
SANC
R-
FAR/SANC
R-Built
up/
SANC
R-
FAR/SANC
R-Built up/
SANC
SQ.MT. SQ.MT. SQ.MT. SQ.MT. SQ.MT. SQ.MT.
1 AAMOD B-01 541.247 560.527 530.791 550.071 6379.958 6611.308
2 DIVJOT B-02 391.087 410.367 381.145 400.425 4583.690 4815.042
3 DAINIK B-03 421.702 440.982 411.665 430.945 4950.021 5181.377
4 SATYAM B-04 350.291 369.571 340.473 359.753 4095.502 4326.854
5 VAIBHAV B-05 325.849 345.129 316.114 335.394 3803.103 4034.463
6 VILAS B-06 316.269 335.549 306.582 325.862 3688.667 3920.031
7 NYAAS B-07 353.961 373.241 344.132 363.412 4139.415 4370.773
8 UNNATI B-08 550.720 570.000 540.284 559.564 6493.864 6725.204
9 BASEMENT (STILT-1)
11576.280
10 STILT-2 5232.680
11 FIRE
ESCAPE
462.720
12 MUMTY 505.000
13 MACHINE
ROOM
159.880
Total 38134.220 57921.612
4. Solid waste generation details: s.
No.
Category kg per capita per day Waste generated (kg/day)
1. General Population 2,550 @ 0.4 kg/day 1,020
2. Staff (Commercial +
Residential)
124 @ 0.25 kg/day
31
3. Visitors 128 @0.15 kg/day 19.2
4. Landscape waste (0.65
acre
@ 0.2 kg/acre/day
0.13
TOTAL SOLId WASTE GENERATED 1,070.33 = 1,070
kg/day
5. The total water requirement is 246 KLD, out of which total domestic water requirement
is 225 KLD. The fresh water requirement is 168 KLD (which is 70% of the domestic
water demand+ Make up Water for swimming pool). The water supply will be provided
through the Municipal Authority.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 54 of 62
6. It is expected that the project will generate approx 194 KLD of wastewater. The
wastewater will be treated in the STP provided within the complex generating 155 KLD
of recoverable water from STP which will be recycled within the project but 76 KLD will
become surplus during non rainy season and 79 KLD during rainy season.
7. 04 nos. of rain water harvesting pits are proposed.
8. The power supply shall be supplied by Paschimanchal Vidyut Vitaran Nigam Limited.
Total electrical load for the Group Housing Project will be approx. 3210 KVA.
9. 02 no. of DG sets of (1 x 1000 KVA, 1 x 500 KVA) capacity each i.e. 1500 KVA for
power back up in the Group Housing Project.
10. 646 ECS parking is proposed for the project.
11. The total population of the project will be 2,802 persons that include staff as well as
commercial population.
12. The project proposals are covered under category 8 "a" of EIA Notification, 2006, as
amended.
The project proponent submitted structural stability certificate dated 06/09/2014 from
Jamia Milia Islamia alongwith details of the project. Approved maps and drawings of the project
have also been submitted. Revised built up area statement of all towers with basement+stile +
floors have been submitted. 71 excess parking have been deleted and plan submitted. An
affidavit regarding CSR plan has also been submitted. The committee discussed the replies
submitted by the project proponent and recommended grant of environmental clearance
on the project proposals along with general conditions as earlier prescribed by the authority for construction project and following specific conditions:
1. Provision of parking should be restricted to ECS as required under Development
Authority bye-laws.
2. Provision of setback on all sides should be made as per Development Authority bye-laws.
3. Copy of all NOCs from different Departments shall be obtained prior to start of
construction.
4. Necessary planning for any anticipated expansion should be incorporated in present
design in view of structural stability.
5. An underground tank shall be planned within the premises for storage of rain water for
water recharge purposes.
6. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste
(Management and Handling) Rules, 2000 (as amended).
7. 03 m peripheral green shall be provided around the project inside the project boundary.
8. 15% area of the total plot area shall be compulsorily made available for the soft green
belt development including the peripheral green belt.
9. Project falling with in norm area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
10. Criteria/ norms provided by competent Authority regarding the seismic zone be followed
for construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 55 of 62
the residents. Rise of stairs should be constructed in a way, so that it should provide
smooth movement.
11. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase. 100% waste water is to be
treated in captive STP conforming to prescribed standards of receiving body for
designated use. Monitoring of STP to be done daily till its stabilization.
12. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken
with regular testing and monitoring of treated water.
13. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to
be used in-house as manure and surplus manure should be managed by giving it to end
users. STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
14. Total cost of the project is Rs. 94.73 Cr. Corporate Social Responsibility (CSR) plan
along with budgetary provision amounting to minimum 2% of the total project cost (Rs.
1.90 Cr.) shall be prepared phase wise and approved by Board of Directors of the
company. A copy of resolution as above shall be submitted to the authority. A list of
beneficiaries with their mobile nos./address should be submitted alongwith six monthly
compliance reports.
15. LEDs should be used in all common areas and corridors. 100% solar lighting is to be
provided in the open areas/ stairs cases.
16. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
17. All entry/exit point should be bell mouth shaped.
18. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
19. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done
only from the roof top. RWH from green and other open areas shall be done only after
permission from CGWB.
20. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
21. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to
be carried out as CPCB Guidelines.
22. Crèche to be provided during the construction/operation phase.
23. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
24. Provision of separate room for senior citizen with proper amenities shall be made.
25. Protection shall be provided on the windows of the high rise flats for security of
residents.
26. Unless and until all the environmental issues are sorted out the occupancy will be
restricted and would be only allowed after achieving the Permission from the competent
authority.
27. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 56 of 62
28. For any extraction of ground water, prior permission from CGWB shall be taken.
29. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
30. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
31. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.
Shall be made available to the temporary residents/workers at the project site including
the proper treatment and the disposal of the wastes.
14. Mining (Gitti, Patthar, Boulder & Khanda) at ARaji/ Bhukhand No-741, Khand No-1,
2 2A, Vill-Kanpuri-Bhraiyam Meja, Allahabad (Area-6.07 Hac). Sri Raghu Nandan
Singh, Vill & Post-Sinkikala, -Meja, Allahabad. File No. 3610
The committee noted that the matter was earlier discussed in SEAC meeting dated
19/08/2016 wherein the project proponent was directed to submit information:
1. A certificate from District Magistrate, Allahabad that the mining on the proposed site
is not restricted under any order issued by Hon'ble Court.
2. A certificate from District Magistrate, Allahabad that no mining work is being
undertaken on the site as on date.
The project proponent submitted letter from District Mining Officer, Allahabad to
Secretary, SEAC dated 06/09/2016 certifying information as above. The committee discussed the
letter and deliberated that certificate should be issued by District Magistrate, Allahabad and
directed the proponent to submit the required document as above from District Magistrate,
Allahabad.
15. Type-V Residential for Judicial Officers (Multi Storeyed Apartment) at Khasra No-
513M & 514M, Vill-Nasarpur, Loni, Ghaziabad. Sri Shivraj Singh, Sr. Project
Manager, Unit-28, C & D S, U P Jal Nigam, Shastri Nagar, Ghaziabad. File No. 3548
The committee noted that the matter was earlier discussed in SEAC meeting dated
11/04/2016 wherein the project proponent was directed to submit information:
1. Comparative details of the project as earlier with builtup area 18,107.93 sqm and revised
proposal with builtup area 20817.77 sqm alongwith present status of construction.
2. Setback details as per building bye-laws.
3. Location of proposed site as per master plan should be submitted.
4. Copy of approved layout plan/maps/services plans.
5. Physical features within 30 m of the project site with their ownership.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 57 of 62
6. Details about approach roads to proposed site. Internal roads layout alongwith width of
the road, within the project. Section of all internal roads should be provided. Right of way
and carriage way width should be clearly marked on the map. Vehicular
movement/circulation plan. Revised parking plan as per bye-laws. It is also to be ensured
that the width of the proposed road as to be admissible as per building bye laws specially
4.5 metre wide road bye laws to be submitted.
7. Area statement with tower wise and floor wise details alongwith no. of units also in
percentage. Details of all block with dimensions set back and area chart details are to be
submitted.
8. Green area details have to be submitted.
9. Structural design certificate signed by structural engineer and vetting authority should be
submitted. All structural design drawings should be signed by structural engineer and
counter signed by vetting authority.
10. Structural design certificate signed by architect and vetting authority after incorporating
proposed expansion structure should be submitted. All structural design drawings should
be signed by architect and counter signed by vetting authority.
The project proponent submitted their replies through letter dated 08/09/2016. A
presentation was made by Shri Shivraaj Singh, Project Manager, Construction and Design
Services, UP Jal Nigam, representative of project proponent along with their consultant M/s
Development Consultants Pvt. Ltd., Kolkata. The proponent, through the documents submitted
and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Type-V Residential for Judicial Officers
(Multi Storied Apartment) at Khasra No-513 M & 514 M, Vill-Nasarpur, Loni,
Ghaziabad.
2. The deposit work for above mentioned project is awarded to Unit-28, Construction &
Design Services, U.P. Jal Nigam (A U.P. Government Undertaking) by the Uttar Pradesh
Shashan, Lucknow in the Judgeship of Chairman Infrastructure Committee, Honable
High Court, Allahabad in the year 2012.
3. Previously, the project was proposed for the built-up area 18,107.93m2 and this office
obtained the NOC for “Consent to Establishment” from State Pollution Control Board to
start the construction at the site and subsequently we started the construction. But Later
the area of each floor is revised from 985.35m2 to 1145.90 m2 by U.P. Govt. So the total
proposed built-up area for the project gets changed to 20,817.77 m2
4. It has been brought to our notice that when the built-up area of the project is > 20,000 sq.
mtrs. it comes under the purview of EIA Notification 2006 of schedule 8(a), Category B.
Hence, we have applied for Environmental Clearance (EC) under schedule 8(a), Category
B.
5. Project details: FEATURES PROPOSED PROJECT
Name of the Project Type-V Residence for Judicial Officers
(Multi-Storeyed Apartment)
Location of Project Khasra No. 513M, 514M
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 58 of 62
Village: Nasarpur, Tehsil/Pargana: Loni District: Ghaziabad (U.P.)
Name of the Applicant District Judge, Ghaziabad
Model Town, Ghaziabad (U.P.)
Pin Code: 201001
Email: [email protected]
S. No. in the schedule 8 (a)
Category of Project i.e. `A’ or `B’ ‘B’
Total Plot Area 21,751.99 m2
Total Built-up Area of the Project 20,817.77 m
2
Coordinate of the Proposed Project Site Pillars Latitude Longitude
A 28° 39.157'N 77° 26.310'E
B 28° 39.112'N 77° 26.368'E
C 28° 39.187'N 77° 26.433'E
D 28° 39.232'N 77° 26.374'E
Toposheet No. 53H/6
Altitude MSL 216 m
6. Salient features details: Project Requirements DETAILS
Total Plot Area 21,751.99 m2
Permissible Maximum Ground Coverage 6,525.59 m2
Existing Ground Coverage 758.68 m2
Proposed Ground Coverage 3,859.01 m2
Total Ground Coverage (Existing + Proposed)
4,617.69 m2
Permissible [email protected] of Total Plot Area 32,626.49 m2
Achieved FAR 19,480.30 m2
Total Built up Area 20,817.77 m2
Exclusive Green Area 22.98% of Total Plot
Area 5000.00 m
2
No. of Towers 2
No. of Floors Stilt + 11 (Block A)
Stilt + 4 (Block B)
Building Height 44.85 m
Parking Facilities Provided Space for 90 Cars
Power Requirement and Source Connected Load : 961.40 KW
Max. Demand : 737.12 KW
Total Demand Load : 644 KW
SOURCE: Power Supply Receiving from UPPCL Substation (Uttar
Pradesh Power Corporation Limited)
Power Backup DG Sets (3 Nos.) : 2 x 200 KVA + 1 x 62.50 KVA
Stack Height of DG Set 47.67 meter
Water Requirement and Source Fresh/Domestic Water Requirement
Treated Waste water use from STP
SOURCE : Bore Wells
Sewage Treatment and Disposal The waste water generated during operation phase will be disposed
in the existing Trunk Sewer line on the Arya Samaj Mandir road demarcated in the site layout plan.
Application for obtaining the consent for the disposal of sewage in
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 59 of 62
the main sewer lines of Municipal Corporation of Ghaziabad is applied and letter related to which is attached as Annexure in the
Project Report.
Estimated Population 318 (+ 86 floating)
Project Cost Rs. 2747.93 Lacs
7. Area statement of the project: Land Use Detail % Land Use Area Statement
(m2
) Total Plot Area 100% 21,751.99 m
2
Permissible Maximum Ground Coverage 30% 6,525.59 m2
Existing Ground Coverage 3.49% 758.68 m2
Proposed Ground Coverage 17.74% 3,859.01 m2
Total Ground Coverage
(Existing + Proposed)
21.23% 4,617.69 m2
Permissible F.A.R.
(all existing structures to be demolished except Anticorruption
Judge Residence)
1.5 times of total plot
area. 32,626.49 m
2
Achieved F.A.R. - 19,480.30 m2
Covered Area of Existing Anticorruption Judge Residence 3.49% 758.68 m2
Proposed Covered Area of District Judge Residence (Existing
Structure)
2.238% 486.88 m2
Proposed Covered Area of Barrack Building 0.86% 188.74 m2
Proposed Covered Area of Garrage + Servant Room
(52.65 + 46.48) {Existing Structure}
0.45% 99.13 m2
Proposed Covered Area of Guard Barrack
{Existing Structure}
0.31% 67.75 m2
Proposed Covered Area of Club Building 5.23% 1,139.47 m2
Proposed Covered Area of Sentry Post 0.0004% (4.63 x 2) 9.26 m2
Proposed Covered Area of All floors of Type-V, Block-A, (Stilt +
11)
(1145.90 x 12) 13,750.80 m2
Proposed Covered Area of All floors of Type-V, Block-B, (Stilt + 4) (1145.90 x 5) 5,729.50 m2
Total Covered Area of the Project (Existing + Proposed) 19,947.67 m2
Landscape Area 22.98% of Total Plot
Area
5000.00 m2
Total Constructed Built-up Area of the Project 20,817.77 m2
No. of Towers 2 (Block A + Block B)
No. of Floors Stilt + 11 (Block A)
Stilt + 4 (Block B)
Max. Height of Tower 44.850 m
Total No. of Flats 60
Total Occupancy 300
8. Parking details: Required No. of Cars
No. of Unit 60 1.5@100 m
2
90
Permissible Parking :
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 60 of 62
Stilt Open
28 ECS
23 ECS
Total No. of Cars 90
PROVIDED
Ground (stilt) 2291.8/28 81
Ground (open) 214.32/23 09
Total No. of Car parking Provided 90
9. Water requirement details: S.No. Description Area (m
2
) Population Rate of water
demand (lpcd)
Total Water Requirement
(KLD)
% in term of
total water
requirement
A. Domestic Water
• Type V
Block A
• Type V
Block B
• Barrack
• Club Building
• Floating Population
(@25% of total Population)
13,750.80 m2
220 86 18.920 63.16%
5,729.50 m2
80 86 6.880
188.74 m2
18 86 1.548
1,139.47 m2
25 30 0.750
86 15 1.290
Total domestic water demand 29.388 Say 30 KLD
B. Landscape Waste
5000 m2 1 l/sqm/day
5.0 KLD 10.52%
C. Miscellaneous use like back wash and make up for water
body and decorative fountain and general washing (L.S.)
- - - 10 KLD 21.05%
D. DG Sets (3 Nos.): 2 x 200 KVA + 1 x 62.50 KVA
0.9 l/KVA/hr
(Assuming 6 hours of operation per day)
2.5 KLD 5.27%
Total Water Requirement (predicted values) KLD (A+B+C+D) 47.5 KLD 100%
1. Domestic Water Requirement 30 KLD
2. Total Fresh water = Fresh (@ 70% of domestic) 21 KLD
• Quantification: Total water requirement of the project is 47.5 KLD (Fresh Water)
Overhead Water Storage Tank:
a. Domestic water tank: 50 KL
b. Fire Water tank: 5 KL
• Under Ground Water Tank: a. Domestic water tank: 100 KL
b. Fire Water tank: 75 KL
• Source of Water Supply: 1. Bore well: 2 Nos.
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 61 of 62
2. Municipal Water Supply
• Waste Water Generation & Disposal: � It is expected that the project will generate 38 KLD (@ 80% of total fresh water used)
of wastewater. The waste water generated during operation phase will be disposed in
the existing Trunk Sewer line on the Arya Samaj Mandir Road demarcated in the site
layout plan. STP is not proposed in the plan.
• Usage: Breakup of water requirements for various usages:
� Irrigation: 5.0 KLD
� Domestic: 30 KLD
� Miscellaneous use like back wash and make up for water body and decorative
fountain and general washing (L.S.): 10 KLD
� D.G. Sets: 2.5 KLD
10. Power requirement details: Power Requirement 644 KW
Transformer Selection Connected Load : 961.40 KW
Max. Demand : 737.12 KW
Total Demand Load : 644 KW
Transformers 1 Nos. of 1000 kVA capacity
Source of Power Supply UPPCL Substation
Backup power supply arrangement No. of DG Sets: 3 Nos.
Capacity : 2x 200 kVA + 1 x 62.50 kVA
Location of DG Sets DG sets shall be placed at ground floor
Stack Height of DG Set 47.67 meter
Consumption of Fuel Individual DG Set shall be provided with a day oil tank of capacity
990 liters, near DG set.
HSD tank location shall be minimum 4.5 meter or dia. Of tank away
from the building as per the Petroleum Acts 30 vide GSR 204 (E)
date 13.02.2002.
11. Waste generation details: S.No. Category Population Kg per capita per
day
(kg/capita/day)
Waste generated
(kg/day)
% in term of
total waste
generation
1. Residents
• Type V
Block A
• Type V
Block B
• Barrack
220
80
18
@ 0.5
159
90.34
Total Occupancy 318
2. • Club
Building
25 @0.15 3.75 2.13
3. Floating Population
(@25% of total Population)
86 @ 0.15
12.9
7.33
4. Landscape Waste @0.2
Kg/acre/day
0.040 0.023
Total Solid Waste Generated 175.69 100%
Minutes of 294th
SEAC Meeting Date 05/10/2016
Page 62 of 62
(predicted values) kg/day Say 176 kg/day
1. Biodegradable Waste 88 kg/day 50%
2. Non-Biodegradable Waste 52.80 kg/day 30%
3. Other Waste 35.20 kg/day 20%
12. The project proposals are covered under category 8"a" of EIA Notification, 2006, as
amended.
The committee discussed the replies submitted by the project proponent and observed
that block A was earlier approved for G+7 and now it is proposed for G+11. The committee
noted that structural drawings are undated and directed to get the date of vetting to be mentioned
on the drawings. Approved maps and drawings for the project should also be submitted.
The matter shall be discussed after submission of information as above.
(Dr. M. S. Khan)
Chairman, SEAC,UP
(Dr. S. N. Singh)
Member, SEAC, UP
(Dr. A.K. Singh)
Member, SEAC, UP
(Dr. S.K. Upadhyay)
Member, SEAC, UP
(Dr. D. C. Gupta)
Member, SEAC, UP
(Shri Ashish Tiwari)
Secretary, SEAC/
Director, Environment, UP