Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page...

22
Minutes of 280 th SEAC Meeting Date 01/07/2016 The 280 th meeting of SEAC was held in Directorate of Environment, U.P. on 01/07/2016. Following members were present in the meeting along with Secretary, SEAC: 1. Prof. M. S. Khan, Chairman 2. Dr. S.N. Singh, Member 3. Dr. S.C. Brahmachari, Member 4. Dr. D. C. Gupta, Member 5. Shri Bhawani Singh Khangarot, Secretary, SEAC / Director (I/C), Environment The Chairman welcomed the members to the 280 th SEAC meeting. The Members of SEAC unanimously taken following decisions on the agenda discussed in the meeting: 1- Gitty, Stone and Boulder Mining Project at Plot No-2098, Khand No-79, Vill-Bhatauti, Tehsil-Meja, Distt-Allahabad (Area-20.00 Acres) Sri Krishna Kumar Gupta, 172/413C, Ashok Nagar, Allahabad. File No. 3001/DD-Y The committee noted that an application dated 21/04/2015 was submitted by the project proponent for environmental clearance of Gitty, Stone and Boulder Mining Project at Plot No-2098, Khand No-79, Vill-Bhatauti, Tehsil-Meja, Distt-Allahabad (Area-20.00 Acres). A presentation was made by Shri Krishna Kumar Gupta project proponent alongwith their consultant M/s Development Consultents Pvt. Ltd. The proponent, through the documents submitted and the presentation made, informed the committee that: 1. The environmental clearance is sought for Gitty, Stone and Boulder Mining Project at Plot No-2098, Khand No-79, Vill-Bhatauti, Tehsil-Meja, Distt-Allahabad (Area-20.00 Acres). 2. Salient feature details: Name of Proponent Sh. Krishna Kumar Gupta M/s Samsi Real Estate Development Pvt. Ltd. Project Title Gitti-Stone & Boulder Mine Site Location Plot No. 2098, Khand No. 79 Village : Bhatauti, Tehsil : Meja District : Allahabad, U.P. Mode of Operation Open Cast, Semi-Mechanised Total Area 8.0972 Ha (20.0 Acre ) Proposed Capacity 3,50,000 cum per annum Nature of Site 100% wasteland earmarked for the Gitti- stone mining by the Govt. of Uttar Pradesh. Number of Employees 42 Water Requirement 5.0 KLD (mining, drinking, domestic use, Dust Suppression & Plantation) Total Project Cost Rs. 4.35 Crores

Transcript of Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page...

Page 1: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

The 280th

meeting of SEAC was held in Directorate of Environment, U.P. on

01/07/2016. Following members were present in the meeting along with Secretary, SEAC:

1. Prof. M. S. Khan, Chairman

2. Dr. S.N. Singh, Member

3. Dr. S.C. Brahmachari, Member

4. Dr. D. C. Gupta, Member

5. Shri Bhawani Singh Khangarot, Secretary, SEAC /

Director (I/C), Environment

The Chairman welcomed the members to the 280th

SEAC meeting.

The Members of SEAC unanimously taken following decisions on the agenda discussed in the

meeting:

1- Gitty, Stone and Boulder Mining Project at Plot No-2098, Khand No-79, Vill-Bhatauti,

Tehsil-Meja, Distt-Allahabad (Area-20.00 Acres) Sri Krishna Kumar Gupta, 172/413C,

Ashok Nagar, Allahabad. File No. 3001/DD-Y

The committee noted that an application dated 21/04/2015 was submitted by the project

proponent for environmental clearance of Gitty, Stone and Boulder Mining Project at Plot No-2098,

Khand No-79, Vill-Bhatauti, Tehsil-Meja, Distt-Allahabad (Area-20.00 Acres).

A presentation was made by Shri Krishna Kumar Gupta project proponent alongwith their

consultant M/s Development Consultents Pvt. Ltd. The proponent, through the documents submitted

and the presentation made, informed the committee that:

1. The environmental clearance is sought for Gitty, Stone and Boulder Mining Project at Plot

No-2098, Khand No-79, Vill-Bhatauti, Tehsil-Meja, Distt-Allahabad (Area-20.00 Acres).

2. Salient feature details:

Name of Proponent Sh. Krishna Kumar Gupta M/s Samsi Real Estate Development Pvt. Ltd.

Project Title Gitti-Stone & Boulder Mine

Site Location Plot No. 2098, Khand No. 79 Village : Bhatauti, Tehsil : Meja District : Allahabad, U.P.

Mode of Operation Open Cast, Semi-Mechanised

Total Area 8.0972 Ha (20.0 Acre )

Proposed Capacity 3,50,000 cum per annum

Nature of Site 100% wasteland earmarked for the Gitti- stone mining by the Govt. of Uttar

Pradesh.

Number of Employees 42

Water Requirement 5.0 KLD (mining, drinking, domestic use, Dust Suppression & Plantation)

Total Project Cost Rs. 4.35 Crores

Page 2: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 2 of 22

3. A 7.5 m wide strip will be left at periphery of the lease area which will be used to store

overburden generated and later will be converted into green belt. Bench height will be kept 3

m.

4. The mining plan has been prepared Mr. Pankaj Pande RQP/DDN/086/95/A and has been

approved by DGM dated 23-05-2016.

5. Mining will be opencast & mode of mining is Semi-Mechanized.

6. The mining would be restricted to unsaturated zone only above the phreatic water table and

will not intersect the ground water table at any point of time.

7. The mining operation will not be carried out in safety zone of any bridge or embankment or in

eco-fragile zone such as habitat of any wild fauna.

8. No earth is to be excavated only stone shall be removed.

9. There is no litigation pending in any court regarding the project.

10. This project does not attract any of the general conditions applicable on mining projects

specified in EIA Notification 14/09/2006.

11. The project proposal falls under category 1(a) of EIA Notification, 2006 (as amended).

12. Record with photographs and document shall be made and be submitted to the district

authorities and to Directorate as compliance.

The project proponent submitted a letter dated 10/05/2016 issued by District Mining Officer,

Allahabad through which informed that there is 03 operating mining within 500 m periphery of the

project site and the total leased areas of the entire site are not more than 25 ha. The committee

discussed the matter and recommended grant of environmental clearance for the project

proposal along with general and specific conditions as annexed at annexure 1 & 2 to these

minutes regarding stone mining project. The committee also stipulated following specific

conditions.

1. Trees of height 2.5 to 03 m should be planted on both sides of the approach road at the

distance of 03 m from the centre, saplings should not be planted.

2. Provision for small cylinder to workers should be made for cooking.

3. Six monthly air monitoring report for PM10 & PM2.5 with photographs is to be submitted.

4. The capacity of trucks/tractor for loading purpose will be in tonnes as per PWD and Transport

Department applicable norms and standard fixed by the Government.

5. Provide suitable mask to the worker.

6. Mining will be carried only according to the approved mining plan.

7. Project falling within the norm area of Wild Life Sanctuary is to obtain a clearance from

National Board Wild Life (NBWL) even if the eco-sensitive zone is not earmarked.

8. The total cost of the project is Rs. 22.0 Lac. Corporate Social Responsibility (CSR) plan along

with budgetary provision amounting to Rs. 4.35 lacs shall be prepared and approved by Board

of Directors of the company. A copy of resolution as above shall be submitted to the authority.

A list of beneficiaries with their mobile nos./address should be submitted.

9. Under the CSR toilets has to be proposed with hand pumps.

10. The approach road 2.0 KM katccha is to be made motorable.

11. A buffer/safe zone shall be maintained from the human habitation as per mining guidelines.

Page 3: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 3 of 22

2- Stone (Khanda, Gitti, Boulder) Mining at Gata No-369 & 370, Vill-Sala, Tehsil-Konch,

Distt-Jalaun (Area-9.27 Hac) Sri Gopi Krishna. File No. 3447/DD(SH)

The project proponent did not appear. The committee discussed and deliberated that project

file should be closed and reopened only after request is made by the project proponent. The file

shall not be treated as pending at SEIAA/SEAC.

3- Stone (Building) Mining Project at Araji No-3Kh & 3Gh, Vill-Manikpur, Tehsil-Lalganj,

Distt-Mirzapur (Area-8.09 Hac) Sri Mithilesh Dubey. File No. 3448/DD(Y)

The committee noted that an application dated 15-10-2015 was made by the project proponent

for environmental clearance of Stone (Building) Mining Project at Araji No-3Kh & 3Gh, Vill-

Manikpur, Tehsil-Lalganj, Distt-Mirzapur (Area-8.09 Hac)

A presentation was made by Shri Ramji Dubey, authorized representative of project proponent

alongwith their consultant M/s Ind Tech House Pvt. Ltd. The proponent, through the documents

submitted and the presentation made, informed the committee that:

1. The environmental clearance is sought for Stone (Building) Mining Project at Araji No-3Kh &

3Gh, Vill-Manikpur, Tehsil-Lalganj, Distt-Mirzapur (Area-8.09 Hac)

2. Salient feature details:

S. NO INFORMATION DETAILS

1. Project Name 8.09 Ha (20.0 Acres) Sand Stone (Building Stone) Mining Project at

Aaraji No- 3 ख & 3 घ Village- Manikpur , Tehsil Lalganj, District

Mirzapur, UP

2. Project Proponent & Mailing

Address

Smt. Mithilesh Dubey W/o Shri Ramjee Dhar Dubey Village &

Post- Kalna , Tehsil Lalganj Dist. Mirzapur- 231211

3. Name of Mineral , Lease period, River

Sand Stone/ New ( The Lease is proposed to be sanctioned for ten years from date of execution. The project proponent has applied vide

letter no- 1160/MMC30-Advertisement / Sand Stone/2014 Dated 09-

12-2014)

4. Production Capacity 150,000 Cubic Meter Per Annum/ 390,000 TPA

5. Mining Method Manual Mining Method/ Semi Mechanized Method

6. Water requirements (KLD) Total 7.0 KLD ( 3.0 KLD for Drinking , 2.4 KLD For Dust

Suppression 1.6 KLD for Green Belt

7. Man Power 60-65

8. Project Cost & CSR Project Cost - Rs 44,00,000 (Approximate) CSR- Rs 220,000

9. Mining Plan Status Prepared By Shri U.P.S. Chauhan (RQP/DDN /165/2005/A)

Approved by DGM Dated 16-02-2016

10. Traffic Analysis Per Year Production – 150,000 m3,

Per Day Production – 500 m3 (Maximum Possible)

Capacity of Trucks- 9 m3 or as per Transport Norms

No of Trucks per day- 56

3. Project location :-

COORDINATES

A 25002’34.56 N, 82

020’27.69 E B 25

002’34.67 N, 82

020’37.98 E

I 25002’17.46 N, 82

020’29.69 E Q 25

002’29.28 N, 82

020’23.08 E

4. A 7.5 m wide strip will be left at periphery of the lease area which will be used to store

overburden generated and later will be converted into green belt. Bench height will be kept 3 m.

Page 4: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 4 of 22

5. The mining plan has been prepared by Mr. UPS Chauhan, RQP/DDN/165/2005/A and has been

approved by DGM dated 16-02-2016.

6. Mining will be opencast & mode of mining will be semi-mechanized.

7. The mining would be restricted to unsaturated zone only above the phreatic water table and will

not intersect the ground water table at any point of time.

8. The mining operation will not be carried out in safety zone of any bridge or embankment or in

eco-fragile zone such as habitat of any wild fauna.

9. No earth is to be excavated, only stone shall be removed.

10. There is no litigation pending in any court regarding the project.

11. This project does not attract any of the general conditions applicable on mining projects

specified in EIA Notification 14/09/2006.

12. The project proposal fall under category 1(a) of EIA Notification, 2006 (as amended).

13. Record with photographs and document shall be made and be submitted to the district authorities

and to Directorate as compliance.

The committee discussed the matter and directed the project proponent to submit following

information:

1. Plan for 300 m approach road kachcha is to be made motarable.

2. Plan for 04 number of toilets to be proposed along with hand pumps.

3. Revised 500 m cluster certificate.

4. Total cost of the project is Rs. 44.0 Lakh. Corporate Social Responsibility (CSR) plan along

with budgetary provision amounting to Rs. 2.20 lacs shall be prepared and approved by Board

of Directors of the company. A copy of resolution as above shall be submitted to the

authority. A list of beneficiaries with their mobile nos./address should be submitted.

The matter shall be discussed under the “discussion head” in the next meeting.

4- Sand Stone (Gitti, Patthar, Khandas, Boulder) Mining at Araji No-359/1, Khand No-9, 10

& 14, Vill-Lalrahi, Meja, Allahabad (Area-12.50 Acres) Sri Rakesh Yadav. File No.

3466/OSD(T)

The committee noted that an application dated 28/10/2015 was submitted by the project

proponent for environmental clearance of Sand Stone (Gitti, Patthar, Khandas, Boulder) Mining at

Araji No-359/1, Khand No-9, 10 & 14, Vill-Lalrahi, Meja, Allahabad (Area-12.50 Acres).

A presentation was made by Shri Pramod Kumar Vishwakarma, authorized representative of

project proponent alongwith their consultant M/s Paramarsh. The proponent, through the documents

submitted and the presentation made, informed the committee that:

1. The environmental clearance is sought for Sand Stone (Gitti, Patthar, Khandas, Boulder) Mining

at Araji No-359/1, Khand No-9, 10 & 14, Vill-Lalrahi, Meja, Allahabad (Area-12.50 Acres).

2. Salient feature details:

Name of Project Mining of Gitty, Boulder & Khandas

Category Category- B2

Location of Mine Site Village- Kakrahi, Tehsil-Meja, District- Allahabad, UP

Page 5: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 5 of 22

Project Proponent with address Shri Rakesh Yadav, S/o Ram Chandra Yadav, R/o- 7/3 Shambhu

Barric, Tehsil- Sadar , District- Allahabad

Khand Nos of Mining Lease site Bhukhand No. 359/1, Khand No- 9,10,14

Size of the Mining Lease 5.05 ha (12.50 Acre)

Period of Mining Lease Lease period- Sanction for ten years (Dated: 13/04/2016)

Geological Reserve 20,73381cum and 5,39,079,06 tonnes

Mineable Reserve 12,05,213 cum and 31,33,553 tonnes

Production (per year) 1,20,000 cum/annum and (3,12000 TPA)

Mining Depth Ultimate Depth - 57m

Elevation level (mRL) Highest elevation - 101.0 mRL Lowest elevation – 99.0

Direction – Area has a gentle slope towards west.

Project Cost 1.64 crores per annum for mining plan period and CSR Cost 2%-

8.2 Lakhs/annum

Number of Labours 30nos.

Water requirement details Fresh water for drinking purpose: Approx. 30site workers @

30 LPCD; Fresh water requirement would be 0.9 KLD

For sprinkling on haulage road: Approx. 1.5 KLD for Air Pollution control

3. A 7.5 m wide strip will be left at periphery of the lease area which will be used to store

overburden generated and later will be converted into green belt. Bench height will be kept 3 m.

4. The mining plan has been prepared Mr. UPS Chauhan, RQP/DDN/165/2005/A and has been

approved by DGM dated 11-05-2016.

5. Mining will be opencast & mode of mining is Semi-Mechanized.

6. The mining would be restricted to unsaturated zone only above the phreatic water table and will

not intersect the ground water table at any point of time.

7. The mining operation will not be carried out in safety zone of any bridge or embankment or in

eco-fragile zone such as habitat of any wild fauna.

8. No earth is to be excavated, only stone shall be removed.

9. There is no litigation pending in any court regarding the project.

10. This project does not attract any of the general conditions applicable on mining projects

specified in EIA Notification 14/09/2006.

11. The project proposal falls under category 1(a) of EIA Notification, 2006 (as amended).

12. Record with photographs and document shall be made and be submitted to the district authorities

and to Directorate as compliance.

The project proponent submit 500 m cluster certificate letter dated 20/05/2016 issued by

District Mining Officer, Allahabad through which they informed that there is no existing operating

mine within 500 m periphery of the project site.

The committee discussed the matter and recommended grant of environmental

clearance for the project proposal along with general and specific conditions as annexed at

annexure 1 & 2 to these minutes regarding stone mining project. The committee also stipulated

following specific conditions:

1. Trees of height 2.5 to 03 m should be planted on both sides of the approach road at the

distance of 03 m from the center, saplings should not be planted.

2. Provision for small cylinder to workers should be made for cooking.

Page 6: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 6 of 22

3. Six monthly air monitoring report for PM10 & PM2.5 with photographs is to be submitted.

4. The capacity of trucks/tractor for loading purpose will be in tonnes as per PWD and Transport

Department applicable norms and standard fixed by the Government.

5. Provide suitable mask to the worker.

6. Approach road 690 m kaccha is to be made motarable.

7. Provision for two toilets and handpump should be made.

8. Drinking water for workers would be provided by tankers.

9. Mining will be carried only according to the approved mining plan.

10. Project falling within the norm area of Wild Life Sanctuary is to obtain a clearance from

National Board Wild Life (NBWL) even if the eco-sensitive zone is not earmarked.

11. The total cost of the project is Rs. 1.64 Cr. Corporate Social Responsibility (CSR) plan along

with budgetary provision amounting to Rs. 8.5 lacs shall be prepared and approved by Board of

Directors of the company. A copy of resolution as above shall be submitted to the authority. A

list of beneficiaries with their mobile nos./address should be submitted.

12. A buffer/safe zone shall be maintained from the habitation as per mining guidelines.

5- Sand Stone (Gitti, Boulders) Mining at Gata No-281/4, 281/8. 281/12, 281/24 & 281/39,Vill-

Sukrit, Robertsganj, Sonebhadra (Area-6.00 Hac) Sri Shireen Ansari. File No. 3501/OSD(T)

The project proponent did not appear. The committee discussed and deliberated that project

file should be closed and reopened only after request from the project proponent. The file shall

not be treated as pending at SEAC.

6- Sand Stone Mining at Araji No-493Ka, 493Kha, Vill-Devikalan, Marihan, Distt-Mirzapur.

(Area-12.95 Acre) Sri Irshad Ahamad. File No. 3522/DD-Sh.

The project proponent did not appear. The committee discussed and deliberated that project

file should be closed and reopened only after request from the project proponent. The file shall

not be treated as pending at SEAC.

7- Stone (Gitti, Patthar & Khanda) Mining at Vill-Salaiyakala,Meja, Allahabad (Area-

5.26Hac)-Smt. Mutahira Khatoon,C-207, GTB Nagar, Karaili, Allahabad. File No.

3538/DD-Y

The committee noted that an application dated 17-12-2015 was made by the project proponent

for environmental clearance of Stone (Gitti, Patthar & Khanda) Mining at Vill-Salaiyakala,Meja,

Allahabad (Area-5.26Hac).

A presentation was made by Shri Syed mohd faizan, authorized representative of project

proponent alongwith their consultant M/s Congnizance Research Inida Private Limited. The

proponent, through the documents submitted and the presentation made, informed the committee that:

1. The environmental clearance is sought for Stone (Gitti, Patthar & Khanda) Mining at Vill-

Salaiyakala, 414 Khand No-2 Meja, Allahabad (Area-5.26Hac) M/s S.M.F. Intcon Pvt. Ltd

2. Salient feature details:

Page 7: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 7 of 22

Name of the project Salaiyakala 414 Khand No-2 Gitti, Boulder & Khadas Mining project

Applicant M/s S.M.F. INTCON PVT. LTD. through Director Smt. Mutahira

Khatoon (Director)

Location Village: Salaiyakala, Tehsil: Meja

District : Allahabad, State : Uttar Pradesh

Lease Area 5.26 ha ( 13 Acre )

Mineral Extracted Gitti, Patthar & Boulder

Coordinates 25° 7'12.66"N 81°54'40.08"E

Geological Reserve 4567200 Tonnes

Mineable Reserve 2557770 Tonnes

Rate of production (in TPA) 5, 00,000 TPA (2, 00,000 cum)

Bench Level 105m to 81m (24m)

Project Cost 50 Lakhs

Topo Sheet 63-K/4

Type of land Stony Waste Land

3. During Mine operation

Proposed Capacity of mine/annum : 5, 00,000TPA

No. of working days : 300 days

Proposed Capacity of mine/day :1666.6TPD

Trucks Capacity : 10 tonnes

No. of trucks deployed/day : 166 trippers/dumper

4. Worker Details:-

S. No. Category No of workers

1. Supervisor 1

2. Skilled/ unskilled 31

Total 32

5. Water requirement:-

Total water demand Domestic use Dust Suppression

3.42 KLD 1.44 KLD 1.98 KLD

6. A 7.5 m wide strip will be left at periphery of the lease area which will be used to store

overburden generated and later will be converted into green belt. Bench height will be kept 3 m.

7. The mining plan has been prepared Mr. Pankaj Pande, RQP/DDN/086/95/A and has been

approved by DGM dated 02-04-2016.

8. Mining will be opencast & mode of mining is Semi-Mechanized.

9. The mining would be restricted to unsaturated zone only above the phreatic water table and will

not intersect the ground water table at any point of time.

10. The mining operation will not be carried out in safety zone of any bridge or embankment or in

eco-fragile zone such as habitat of any wild fauna.

11. No earth is to be excavated only stone shall be removed.

12. There is no litigation pending in any court regarding the project.

13. This project does not attract any of the general conditions applicable on mining projects

specified in EIA Notification 14/09/2006.

14. The project proposal falls under category 1(a) of EIA Notification, 2006 (as amended).

15. Record with photographs and document shall be made and be submitted to the district authorities

and to Directorate as compliance.

Page 8: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 8 of 22

The project proponent submit 500 m cluster certificate letter dated 23/04/2016 issued by

District Mining Officer, Allahabad through which they informed that there is no existing operating

mine within 500 m periphery of the project site.

The committee discussed the matter and recommended grant of environmental

clearance for the project proposal along with general and specific conditions as annexed at

annexure 1 & 2 to these minutes regarding stone mining project. The committee also stipulated

following specific conditions:

1. Trees of height 2.5 to 03 m should be planted on both sides of the approach road at the

distance of 03 m from the center, saplings should not be planted.

2. Provision for small cylinder to workers should be made for cooking.

3. Six monthly air monitoring report for PM10 & PM2.5 with photographs is to be submitted.

4. The capacity of trucks/tractor for loading purpose will be in tonnes as per PWD and Transport

Department applicable norms and standard fixed by the Government.

5. Only 25 trucks/day are allowed.

6. Approach road 330 m kaccha is to be made motorable.

7. Provide suitable mask to the worker.

8. Provision for two toilets and hand pump should be made.

9. Mining will be carried only according to the approved mining plan.

10. Project falling within the norm area of Wild Life Sanctuary is to obtain a clearance from

National Board Wild Life (NBWL) even if the eco-sensitive zone is not earmarked.

11. The total cost of the project is Rs. 50.0 Lakh. Corporate Social Responsibility (CSR) plan

along with budgetary provision amounting to Rs. 2.5 lacs shall be prepared and approved by

Board of Directors of the company. A copy of resolution as above shall be submitted to the

authority. A list of beneficiaries with their mobile nos./address should be submitted.

12. A buffer/safe zone shall be maintained from the habitation as per mining guidelines.

8- Mining Project (Gitti, Khand & Boulder) at Plot No-669, Vill-Khailar, Tehsil & Distt-

Jhansi (Abov 5.00 Hac) - Sri Ramesh Kumar Saraogi, Civil Lines, Jhansi. File No. 3605/AD-

Sub.

The project proponent did not appear. The committee discussed and deliberated that project

file should be closed and reopened only after request from the project proponent. The file shall

not be treated as pending at SEIAA/SEAC.

9- Mining Project (Gitti, Khand & Boulder) at Plot No-669, Vill-Khailar, Tehsil & Distt-

Jhansi (Abov 5.00 Hac) - Sri Amit Singh, 1087/1, Civil Lines, Jhansi. File No. 3606/AD-Sub.

The project proponent did not appear. The committee discussed and deliberated that project

file should be closed and reopened only after request from the project proponent. The file shall

not be treated as pending at SEIAA/SEAC.

Page 9: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 9 of 22

10- Mining Project (Gitti, Khand & Boulder) at Plot No-669, Vill-Khailar, Tehsil & Distt-

Jhansi (Abov 5.00 Hac) - Sri Amit Singh, 1087/1, Civil Lines, Jhansi. File No. 3607/AD-Sub.

The project proponent did not appear. The committee discussed and deliberated that project

file should be closed and reopened only after request from the project proponent. The file shall

not be treated as pending at SEIAA/SEAC.

11- Mining Project (Gitti, Khand & Boulder) at Plot No-669, Vill-Khailar, Jhansi (Abov 5.00

Hac) - Sri Ajay Singh, 106, Laxamanpur, Faizabad Road, Lucknow. File No. 3608/AD-Sub.

The committee noted that an application dated 01-02-2016 was made by the project proponent

for environmental clearance of Mining Project (Gitti, Khand & Boulder) at Plot No-669, Vill-Khailar,

Jhansi (Abov 5.00 Hac)

A presentation was made by Sri Ajay Singh, authorized representative of project proponent

alongwith their consultant M/s ITHC Delhi . The committee discussed the matter and directed the

project proponent to submit following information:

1. Submit details of all mining areas within 500 m from the periphery certified by the mining

officer. So that it can be confirmed that the total area is not more than 25 ha.

2. Khasra map is to be submitted certified by mining department showing khasra no. and

area of the project.

12- Mining Project (Gitti, Khand & Boulder) at Plot No-1187, 1189 & 815, Vill-Digara, Jhansi

(Abov 5.00 Hac) - Sri Ashok Kumar Anandani. File No. 3609/OSD-T

The project proponent did not appear. The committee discussed and deliberated that project

file should be closed and reopened only after request from the project proponent. The file shall

not be treated as pending at SEIAA/SEAC.

13- Mining(Gitti, Patthar,Boulder & Khanda) at Araji/Bhukhand No-741, Khand No-1, 2 2A,

Vill-Kanpuri,Allahabad (Area-6.07 Hac)- Sri Raghu Nandan Singh. File No. 3610/DD-Sh.

The project proponent did not appear. The committee discussed and deliberated that project

file should be closed and reopened only after request from the project proponent. The file shall

not be treated as pending at SEIAA/SEAC.

14- Stone Ballast/Khanda Boulder Mine at Araji No. 19, Village-Paraicha, Tehsil-Moth, Jhansi,

U.P. Sri. Sujeet Bahadur Singh. File No. 3683

The committee noted that an application dated 19/05/2016 was made by the project proponent

for environmental clearance of Stone Ballast/Khanda Boulder Mine at Araji No. 19, Village-Paraicha,

Tehsil-Moth, Jhansi, U.P.

A presentation was made by Shri Sujeet Bahadur Singh, project proponent alongwith their

consultant M/s Environmental Research & Analysis. The proponent, through the documents

submitted and the presentation made, informed the committee that:

Page 10: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 10 of 22

1. The environmental clearance is sought for Stone Ballast/Khanda Boulder Mine at Araji No. 19,

Village-Paraicha, Tehsil-Moth, Jhansi, U.P.

2. Salient feature details:

Project Title Stone Ballast/Khanda Boulder Mine

Letter of Intent पत्रांक. 1224/30एमo एमoसीo-नोटिस(2015-16) dated 8/3/2016, District-Jhansi

(Renewal is Applied)

Type of Mining Open Cast Mining of Minor Mineral (Stone Ballast/Khanda Boulder )

Site Location Araji No. 19 Village :Paraichha, Tehsil Moth, District Jhansi, Uttar Pradesh.

Total Area 5.67 Ha

Proposed Excavation 25,75,020 m3 in 10 Years 5,15,000 m

3

in 5 Years (As per Approved Quantity by

DGM LKO)

Lease Period 10 Years

Nature of Mining Site Non-arable, Non- forested, Stony Scrub

Mode of Mining Semi-Mechanized

Drinking Water 2.50 KLD

Water for Dust Suppression 3.65 KLD

Water to Irrigate Plants for

Greening the Site

0.85 KLD

Total Water Required 7.0 KLD

Energy Requirement Project Site will be equipped with the Solar Power Panels (No need of additional

electric lines)

Transportation of the Material The site is connected with the link road and therefore no need of road construction,

however; once project is commissioned the maintenance of the link road will be

taken care off

Total Manpower 43

Shelters Temporary Shelter will be provided for two or three workers and staff members

Toilets Temporary toilets connected to the soak pits will be provided

3. A 7.5 m wide strip will be left at periphery of the lease area which will be used to store

overburden generated and later will be converted into green belt. Bench height will be kept 3 m.

4. The mining plan has been prepared by Mr. Pankaj Pande, RQP/DDN/086/95/A and has been

approved by DGM dated 27-04-2016.

5. Mining will be opencast & mode of mining is Semi-Mechanized.

6. The mining would be restricted to unsaturated zone only above the phreatic water table and will

not intersect the ground water table at any point of time.

7. The mining operation will not be carried out in safety zone of any bridge or embankment or in

eco-fragile zone such as habitat of any wild fauna.

8. No earth is to be excavated only stone shall be removed.

9. There is no litigation pending in any court regarding the project.

10. This project does not attract any of the general conditions applicable on mining projects

specified in EIA Notification 14/09/2006.

11. The project proposal fall under category 1(a) of EIA Notification, 2006 (as amended).

12. Record with photographs and document shall be made and be submitted to the district authorities

and to Directorate as compliance.

Page 11: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 11 of 22

The project proponent submitted a letter dated 20/05/2016 issued by Mining Officer, Jhansi

through which they informed that there is 02 operating mining within 500 m periphery of the project

site and the total leased areas of the entire site are not more than 25 ha.

The committee discussed the matter and recommended grant of environmental

clearance for the project proposal along with general and specific conditions as annexed at

annexure 1 & 2 to these minutes regarding stone mining project. The committee also stipulated

following specific conditions:

1. Trees of height 2.5 to 03 m should be planted on both sides of the approach road at the

distance of 03 m from the center, saplings should not be planted.

2. Provision for small cylinder to workers should be made for cooking.

3. Six monthly air monitoring report for PM10 & PM2.5 with photographs is to be submitted.

4. The capacity of trucks/tractor for loading purpose will be in tonnes as per PWD and Transport

Department applicable norms and standard fixed by the Government.

5. Provide suitable mask to the worker.

6. Provision for two toilets and hand pump should be made.

7. Mining will be carried only according to the approved mining plan.

8. Project falling within the norm area of Wild Life Sanctuary is to obtain a clearance from

National Board Wild Life (NBWL) even if the eco-sensitive zone is not earmarked.

9. The total cost of the project is Rs 52.0 lac. Corporate Social Responsibility (CSR) plan along

with budgetary provision amounting to Rs. 4.16 lacs shall be prepared and approved by Board

of Directors of the company. A copy of resolution as above shall be submitted to the

authority. A list of beneficiaries with their mobile nos./address should be submitted.

10. A buffer/safe zone shall be maintained from the habitation as per mining guidelines.

15- Sand/Morum Mining Project at Gata No-02 & 738, Vill-Mau (Ba), Tehsil-Karvi, Distt-

Chitrakoot (Area 6.07 Ha) Sri Md. Haseeb, Vill-Kajiyana, Hamirpur. File No. 3128/DD-Y

The committee noted that an application dated 23-05-2015 was made by the project proponent

for environmental clearance of Sand/Morum Mining Project at Gata No-02 & 738, Vill-Mau (Ba),

Tehsil-Karvi, Distt-Chitrakoot (Area 6.07 Hac).

A presentation was made by Shri Suraj Bali Yadav, project proponent alongwith their

consultant M/s Environmental Research & Analysis. The proponent, through the documents

submitted and the presentation made, informed the committee that:

1. The environmental clearance is sought for Sand/Morum Mining Project at Gata No-02 & 738,

Vill-Mau (Ba), Tehsil-Karvi, Distt-Chitrakoot (Area 6.07 Hac).

2. Salient feature details:

Project Riverbed Sand Mining (1ai)

Proponent Sh. Mohd. Haseeb S/O Sh. Mohd Aleem

Project Site Location Gata No. 02 & 738 Village:Mau (Ba),

Tehsil:Karvi, District: Chitrakoot,

Uttar Pradesh

Page 12: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 12 of 22

Proposed Production 1,21,400 m3 / 2,18,520 TPA

Letter of Intent Vide letter no.857/86-2015-41/2015 dated 1 April 2015 District-

Chitrakoot

Mining Lease Area New (Lease Period 3 Years)

Gata No. Gata No. 02 & 738

Area 6.07 Ha

Proposed Mining Capacity 1,21,400 m3 / 2,18,520 TPA

Forested Area Nil

Drinking Water 1.80 KLD

Water for Dust Suppression 2.90 KLD

Water to Irrigate Plants for Greening the Site 0.80 KLD

Total Water Required 5.50 KLD

Energy Requirement Project Site will be equipped with the Solar Power Panels (No need of

additional electric lines)

Transportation of the Material The site is connected with the link road through a kaccha road of 2.3

km stretch and therefore need of road construction is required, once the

project is commissioned the maintenance of the link road will be taken

care off

Total Manpower 45

3. A 7.5 m wide strip will be left at periphery of the lease area which will be used to store

overburden generated and later will be converted into green belt. Bench height will be kept 3 m.

4. The mining plan has been prepared Mr. Pankaj Pande, RQP/DDN/086/95/A and has been

approved by DGM dated 06-07-2015.

5. Mining will be opencast & mode of mining is Semi-Mechanized.

6. The mining would be restricted to unsaturated zone only above the phreatic water table and will

not intersect the ground water table at any point of time.

7. The mining operation will not be carried out in safety zone of any bridge or embankment or in

eco-fragile zone such as habitat of any wild fauna.

8. No earth is to be excavated only stone shall be removed.

9. There is no litigation pending in any court regarding the project.

10. This project does not attract any of the general conditions applicable on mining projects

specified in EIA Notification 14/09/2006.

11. The project proposal fall under category 1(a) of EIA Notification, 2006 (as amended).

12. Record with photographs and document shall be made and be submitted to the district authorities

and to Directorate as compliance.

The committee discussed the matter and directed the project proponent to submit following

information:

1. Plan for 2.3 KM approach road kaccha is to be made motorable.

2. Plan for 4 number of toilets to be proposed along with hand pumps.

3. Revised 500 m cluster certificate issued by Mining Officer which showing that approved and

operating mines within 500 mts from the periphery of the site.

4. Total cost of the project is Rs. 48.7 Lakh. Corporate Social Responsibility (CSR) plan along

with budgetary provision amounting to Rs. 4.16 lacs shall be prepared and approved by Board

of Directors of the company. A copy of resolution as above shall be submitted to the

authority. A list of beneficiaries with their mobile nos./address should be submitted.

The matter shall be discussed under the “discussion head” in the next meeting.

Page 13: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 13 of 22

16- Group Housing Project “Meghdutam Encore” Plot No. Gh-05/SC-01 (Sport city) Sector-

Adjoining Sector Techzone IV, Greater Noida , U.P. File No. 3486

The committee noted that an application dated 30-11-2015 was made by the project proponent

for environmental clearance of Group Housing Project “Meghdutam Encore” Plot No. Gh-05/SC-01

(Sport city) Sector-Adjoining Sector Techzone IV, Greater Noida , U.P. M/s Palm Developers Pvt.

Ltd.

A presentation was made by authorized representative of project proponent along with their

consultant M/s YES Enviro Solutions. The proponent, through the documents submitted and the

presentation made, informed the committee that:-

1. The environmental clearance is sought for Group Housing Project “Meghdutam Encore” Plot

No. Gh-05/SC-01 (Sport city) Sector-Adjoining Sector Techzone IV, Greater Noida , U.P.

M/s Palm Developers Pvt. Ltd.

2. Salient feature details:

PROJECT FEATURES DETAILS Estimated Population 1,667 persons

Estimated Water Requirement with source Construction Phase Operation Phase

276 ML(Private Water Tanker supply ) 195 KLD ( Fresh Water 92 KLD) Agency : Greater Noida

Development Authority

Estimated wastewater generation and treatment 114 KLD (STP of 150 KLD, SAFF Technology)

Power Demand and Source Power Back-up

1969 kVA from Paschimanchal Vidyut Vitran Nigam Ltd. 3 no. of DG sets of total capacity of 2250 kVA (3 x 750 each).

Solid Waste Generation 633 kg/day

Rain water harvesting pits 02 nos.

Parking Facilities

Required

Proposed

350 ECS and 438 ECS (as per MoEF &CC and State Bye-

Laws) 439 ECS

Project Cost Rs. 90.98 Cr

3. Land use details:

S. No. Description Area in m

2

Percentage of Total Plot Area

1 Ground Coverage 2,770.09 27.70

2 Landscape Area 3042.75 30.43

3 Road Area 1590 15.9

4. Other paved area 2597.16 25.97

Total Area 10000 100

4. Area details of the project:

S.NO. DESCRIPTION AREA (SQ. M) PERCENT

1 Land Parcel Area/ Plot Area 10,000.00 100

2 Permissible F.A.R. @ 3.5 35,000.00

Proposed F.A.R @ 3.4 34970.16

3 Permissible Ground Coverage (@ 30%) 3,000.00

4 Proposed Ground Coverage 2,770.09 27.70

5 Permissible Service Area (15%) 5250.00

6 Proposed Service Area 4397.53

7 Proposed Basement Area 6405.07

8 Built- up Area

a. Total F.A.R area 34,970.16

b. Basement area 6405.07

c. Ground/Podium 5989.08

Page 14: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 14 of 22

d. First/Podium 4878.96

e. Services area (only residential) 3583.42

Total Buildup area (a + b + c + d) 55,826.71

9 Open Area 7229.91 72.3

10 Required Green Area (25% of Open Area) 1807.47

11 Proposed Green Area (42% of Open Area) 3042.75

5. Proposed area and dwelling unit details:

COMBINED AREA DETAIL

FLOOR F.A.R. AREA (SQ.M.) 15% SERVICES (SQ.M.)

Basement 619.355

GR./PODIUM-1 1804.736 132.601

1st

/PODIUM-2 304.691 194.369

2nd FLOOR 2165.828 217.118

3rd FLOOR 2165.828 217.118

4th FLOOR 2525.804 217.118

5th FLOOR 2525.804 217.118

6th FLOOR 2165.828 217.118

7th FLOOR 2165.828 217.118

8th FLOOR 2165.828 217.118

9th FLOOR 2165.828 217.118

10th FLOOR 2165.828 217.118

11th FLOOR 2165.828 217.118

12th FLOOR 2165.828 217.118

13th FLOOR 2165.828 217.118

14th FLOOR 2165.828 217.118

15th FLOOR 2165.828 217.118

16th FLOOR 1810.196 209.978

MUMTY 0 192.572

GUARD/MTR.RM 9 9

TOTAL 34970.167 4397.527

6. Population details of the project:

S. No. Unit Type DU or Area PPU Total Population

Residential

1 Group Housing 296 4.5 1332

2 Servant 60 2.25 135

3 Staff (5%) 67

4 Visitors (10%) 133

Grand Total(1+2+3+4) 1,667

7. Water calculation details:

S. No.

Description

Area

(in

m2)

Total Occupancy Rate of water

demand (lpcd)

Total Water

Requirement

(KLD)

A. Domestic Water

a) Residential

Population

1332 86 114.5

b) Servant 135 86 11.6

c) Staff 67 45 2.9

d) Visitors 133 15 1.9

Total domestic water demand (A)(a+b+c+d) = 130.9 KLD or 131 KLD

B. Horticulture and

Landscape

development

3042.75 m2 5 l/sq.m 15.2

C. DG Sets Cooling (3

*750 KVA)

0.9 l/KVA/hr 16.2

Page 15: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 15 of 22

D. Floor Washing, Car

washing and water

for Landscape along

service road

- 29

E. STP Filter

Backwashing

- 3

Grand Total (A+B+C+D+E) = 194.4 KLD say 195 KLD

Total Fresh water requirement (70% of domestic req.) 92 KLD

8. Waste water calculation:

Domestic Water Requirement 131 KLD

Fresh (70% of domestic) 92 KLD

Flushing (30% of domestic) 40 KLD

Wastewater Generated (80% fresh + 100% flushing) 113.6 KLD say 114 KLD

9. Solid waste generation details:

S. No. Category Total Occupancy or Area Waste generated (kg/day)

1. Group Housing 1332 599

3. Staff 67 6.7

4. Visitors 133 13.3

TOTAL DOMESTIC WASTE GENERATED 619

5. Landscape waste(for green

belt)

0.7 Acre 3.5

6 STP Waste 10.6

TOTAL SOLID WASTE GENERATED 633 kg/day

10. Proposed parking details:

SI. NO. PARTICULARS AREA

(in m2)

MIN. AREA REQ./ECS as per bye

laws (in m2)

PARKING

PROPOSED (ECS)

1 Surface Parking 439.103 20 22

2 Basement 5114.241 30 170

3 Podium 1 3672.384 30 122

4 Podium 2 3762.129 30 125

Total Parking Proposed 439 ECS

11. The project proposals are covered under category 8(a) of EIA Notification, 2006.

The committee discussed the matter and recommended grant of environmental

clearance on the project proposals along with general conditions as earlier prescribed by the

authority for construction project and following specific conditions:

1. The project proponent submit the NOC from Airport Authority of India within 15 days from the

date of issuance of the minutes, if the project proponent does not submit the NOC within 15

days the EC will deemed to be cancelled.

2. Entry exit should be 06 m on both the sides.

3. Excess treated water of 29 KLD should be used in nearby construction and horticulture and

there should be no discharge from the premises during non monsoon season.

4. Modular STP has to be proposed of 150 KLD in the basement it will be proposed in between

column of the building which will not disturb the column neither any excavation works will be

carried out.

5. Fire and Water tank for drinking purpose if constructed in the basement will not affect the

column of the building neither any excavation work will be carried out. It will be constructed

within column.

6. All the dimension of the fire and water tank will have to be mentioned in the layout plan with

its location.

Page 16: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 16 of 22

7. Evacuation route and alarming system is to be submitted and also shown on the map.

8. Location of site for disposal of organic waste to be submitted and also demarcated in the layout

plan with dimension.

9. Provision of parking should be restricted to ECS as required under Development Authority bye-

laws.

10. Provision of setback on all sides should be made as per Development Authority bye-laws.

11. Copy of all NOCs from different Departments shall be obtained prior to start of construction.

12. Necessary planning for any anticipated expansion should be incorporated in present design in

view of structural stability.

13. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste (Management

and Handling) Rules, 2000 (as amended).

14. 03 m peripheral green shall be provided around the project inside the project boundary.

Minimum 80 trees should be planted.

15. 15% area of the total plot area shall be compulsorily made available for the green belt

development including the peripheral green belt.

16. Project falling with in norm area of Wild Life Sanctuary is to obtain a clearance from National

Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.

17. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for

construction work. Provision of alarm system, to timely notify the residents, in case of

occurrence of earthquake/other natural disasters/fire should be provided. A well defined

evacuation plan should also be prepared and regular mock drills should be arranged for the

residents. Rise of stairs should be constructed in a way, so that it should provide smooth

movement.

18. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more capacity

than waste water generated during operation phase.100% waste water is to be treated in captive

STP conforming to prescribed standards of receiving body for designated use. Monitoring of

STP to be done daily till its stabilization.

19. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken with

regular testing and monitoring of treated water.

20. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be used

in-house as manure and surplus manure should be managed by giving it to end users. STP shall

be suitably located nearest to back side boundary with shortest out let. Operation and the

maintenance cost of the STP shall also be informed along with the compliance of the E-waste

and municipal solid waste disposal.

21. Total cost of the project is Rs. 90.98 Cr. Corporate Social Responsibility (CSR) plan along with

budgetary provision amounting to minimum 2% of the project cost (Rs. 2.0 Cr.) shall be

prepared and approved by Board of Directors of the company. A copy of resolution as above

shall be submitted to the authority. A list of beneficiaries with their mobile nos./address should

be submitted alongwith six monthly compliance reports.

22. LEDs should be used in all common areas and corridors. 100% solar lighting is to be provided

in the open areas/ stairs cases.

23. All entry/exit point should be bell mouth shaped.

24. To discharge excess treated waste water into public drainage system, permission from the

competent authority to be taken prior to any discharge.

25. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only

from the roof top. RWH from green and other open areas shall be done only after permission

from CGWB.

26. An underground Pucca tank for collection/reuse of rain water may be constructed.

Page 17: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 17 of 22

27. Height of the stack should be provided based on combined DG sets capacity and be 6mt higher

than the tallest building.

28. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to be

carried out as CPCB Guidelines.

29. Crèche to be provided during the construction/operation phase.

30. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.

31. Provision of separate room for senior citizen with proper amenities shall be made.

32. Protection shall be provided on the windows of the high rise flats for security of residents.

33. Unless and until all the environmental issues are sorted out the occupancy will be restricted and

would be only allowed after achieving the Permission from the competent authority.

34. The project proponent shall ensure that the project site does not attract/infringe any buffer zone

of no activity identified/declared under law.

35. For any extraction of ground water, prior permission from CGWB shall be taken.

36. Sprinkler to be used for curing and quenching and ready mix concrete may be used for

construction.

37. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip

irrigation should be tried upto extent possible. No fresh water will be used for irrigation

purpose.

38. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc. Shall be

made available to the temporary residents/workers at the project site including the proper

treatment and the disposal of the wastes.

The committee further directed the Secretary, SEAC to put up the file before the

committee for discussion, when the project proponent submits reply of all the queries

including NOC from Airport Authority of India.

(Prof. M.S. Khan)

Chairman, SEAC, UP

(Dr. S.N. Singh)

Member, SEAC, UP

(Dr. S.C. Brahmachari)

Member, SEAC, UP

(Dr. D. C. Gupta)

Member, SEAC, UP

(Shri Bhawani Singh Khangarot)

Secretary, SEAC, UP

Page 18: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 18 of 22

Annexure-1

General Conditions for Stone Mining Projects:

1. This environmental clearance is subject to allotment of mining lease in favour of project

proponent by District Administration/Mining Department.

2. Forest clearance shall be taken by the proponent as necessary under law.

3. Any addition of the mining area, change of Khasra numbers, enhancement of capacity, change

in mining technology, modernization and scope of working shall again required prior

environmental clearance as per EIA notification, 2006.

4. No change in the calendar plan including excavation, quantum of mineral and waste shall be

made.

5. Mining will be carried out as per the approved mining plan. In case of any violation of mining

plan, the Environmental Clearance given by SEIAA will stand cancelled.

6. Four ambient air quality monitoring stations shall be established in the core zone as well as in

the buffer zone for RSPM, SPM, SO2, NOx monitoring. Location of the stations should be

decided based on the meteorological data, topographical features and environmentally and

ecologically sensitive targets and frequency of monitoring should be undertaken in consultation

with the State Pollution Control Board. The monitored data for criteria pollutants shall be

regularly up loaded on the company's website and also displayed at website.

7. Data on ambient air quality (RPM, SPM, SO2, NOx) should be regularly submitted to the

Regional office, MoEF, GoI, Lucknow and the State Pollution Control Board / Central

Pollution Control Board once in six months.

8. Ambient air quality at the boundary of the mine premises shall confirm to the norms prescribed

in MoEF notification no. GSR/826(E) dt. 16.11.09.

9. Fugitive dust emissions from all the sources shall be controlled regularly. Water spraying

arrangement on haul roads, loading and unloading and at transfer points shall be provided and

properly maintained.

10. Measures shall be taken for control of noise levels below 85 dBA in the work

environment. Workers engaged in operations of HEMM, etc. shall be provided with ear plugs /

muffs and health records of the workers shall be maintained.

11. Industrial waste water (workshop and waste water from the mine) should be properly collected,

treated so as to conform to the standards prescribed under GSR 422 (E) dated 19th May, 1993

and 31st December, 1993 or as amended from time to time. Oil and grease trap shall be

installed before discharge of workshop effluents.

12. Personnel working in areas shall be provided with protective respiratory devices like mask

and they shall also be imparted adequate training and information on safety and health aspects.

13. Special measures shall be adopted to prevent the nearby settlements from the impacts of

mining activities.

14. The transportation of the materials shall be limited to day hours time only.

15. Provision shall be made for the housing the labourers within the site with all necessary

infrastructure and facilities such as fuel for cooking, mobile toilets, safe drinking water,

medical health care, crèche etc. The housing may be in the form of temporary structures to be

removed after the completion of the project.

16. A separate Environmental Management Cell with suitable qualified personnel shall be set­up

under the control of a Senior Executive, who will report directly to the Head of the

Organization.

Page 19: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 19 of 22

17. The Project Proponent shall inform to the Regional Office, MoEF, GoI, Lucknow and

State Pollution Control Board regarding date of financial closures and final approval of the

project by the concerned authorities and the date of start of land development work.

18. The funds earmarked for environmental protection measures shall be kept in separate

account and shall not be diverted for other purpose. Year wise expenditure shall be reported to

the MoEF, GoI, Lucknow and State Pollution Control Board

19. The Regional Office, MoEF, GoI, Lucknow and State Pollution Control Board shall monitor

compliance of the stipulated conditions. A complete set a documents including Environment

Impact Assessment Report, Environmental Management Plan, Public hearing and other

documents information should be given to Regional Office of the MoEF, GoI, Lucknow and

State Pollution Control Board

20. A copy of the environmental clearance shall be submitted by the Project Proponent to the Heads

of the Local Bodies, Panchayat and Municipal Bodies as applicable in the matter.

21. The Project Proponent shall advertise at least in two local newspapers widely circulated,

one of which shall be in the vernacular language of the locality concerned, within 7 days of the

issue of the clearance letter informing that the project has been accorded environmental

clearance and a copy of the clearance letter is available with the State Level Environment

Impact Assessment Authority (SEIAA).

22. The Project Proponent has to submit half yearly compliance report of the stipulated prior

environmental clearance terms and conditions in hard and soft copy to the SEIAA, U.P.

on 1st June and 1st December of each calendar year.

23. The SEIAA ma y alter/modify the above conditions or stipulate any further condition in the

interest of environment protection.

24. Concealing factual data or submission of false/fabricated data and failure to comply with

any of the conditions mentioned above may result in withdrawal of this clearance and attract

action under the provisions of Environment (Protection) Act, 1986.

Page 20: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 20 of 22

Annexure-2

Specific Conditions for Stone Mining projects:

1. This environmental clearance does not create or verify any claim of applicant on the proposed

site/activity.

2. This environmental clearance shall be subject to valid lease in favour of project proponent for

the proposed mining proposals. In case, the project proponent does not have a valid lease, this

environmental clearance shall automatically become null and void.

3. The Environmental clearance will be co-terminus with the mining lease period.

4. A comprehensive EIA including mining areas within 15 K.M. to assess impact of the mining

activity on the surrounding area shall be undertaken and report submitted to this Authority

within one year.

5. No two pits shall be simultaneously w o r ked i.e before the first is exhausted and

reclamation work completed, no mineral bearing area shall be worked.

6. After exhausting the first mine pit and before starting mining operations in the next pit,

reclamation and plantation works in the exhausted pit shall be completed so as to ensure that

reclamation, forest cover and vegetation are visible during the first year of mining operations in

the next pit. This process will follow till the last pit is exhausted. Adequate rehabilitation of

mined pit shall be completed before any new ore bearing area is worked for expansion.

7. Adequate buffer zone shall be maintained between two consecutive mineral bearing deposits.

8. Sprinkling of water on haul roads to control dust will be ensured by the project

proponent.

9. Green belt development shall be carried out considering CPCB guidelines including

selection of plant species and in consultation with the local DFO / Agriculture Department.

Herbs and shrubs shall also form a part of afforestation programme besides tree plantation.

The company shall involve local people for plantation programme. Details of year wise

afforestation programme including rehabilitation of mined out area shall be submitted to the

Regional Office, MoEF, GoI, Lucknow every year.

10. Blast vibrations study shall be conducted and a observation report submitted to the

Regional office, MoEF, GoI, Lucknow and UPPCB within six months. The report shall also

include measures for prevention of blasting associated impact on nearby houses and agricultural

fields.

11. Controlled blasting techniques with sequential blasting shall be adopted. The blasting shall be

carried out in the day time only.

12. Appropriate arrangement for shelter and drinking water for the mining workers has to be

ensured at the mining site.

13. Maintenance of village roads used for transportation of minerals are to be done by the

company regularly at its own expenses. The roads shall be black topped.

14. Rain water harvesting shall be undertaken to recharge the ground water source.

15. Status of implementation shall be submitted to the Regional Office, MoEF, GoI,

Lucknow and UP Pollution Control Board within six months and thereafter every year from the

next consequent year.

16. Measures for prevention and control of soil erosion and management of silt shall be undertaken.

Protection of dumps against erosion shall be carried out with geo textile matting or other

suitable material, and thick plantations of native trees and shrubs shall be carried out at the

dump slopes. Dumps shall be protected by retaining walls.

Page 21: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 21 of 22

17. Trenches / garland drains shall be constructed at foot of dumps and coco filters installed at

regular intervals to arrest silt from being carried to water bodies. Adequate number of

Check Dams and Gully Plugs shall be constructed across seasonal/perennial nallahs, if any

flowing through the ML area and silts arrested. De­ silting at regular intervals shall be carried

out.

18. Garland drain of appropriate size, gradient and length shall be constructed for both mine pit

and for waste dump and sump capacity shall be designed keeping 50% safety margin over

and above peak sudden rainfall (based on 50 years data) and maximum discharge in the area

adjoining the mine site. Sump capacity shall also provide adequate retention period to allow

proper settling of silt material. Sedimentation pits shall be constructed at the corners of the

garland drains and de­ silted at regular intervals.

19. Ground and surface water, if any in and near the core zone (within 5.0 km of the lease) shall

be regularly monitored for contamination and depletion due to mining activity and records

maintained. The monitoring data shall be submitted to the Regional Office, MoEF, GoI,

Lucknow and U.P.Pollution Control Board regularly. Further, monitoring points shall be

located between the mine and drainage in the direction of flow of ground water shall be set up

and records maintained.

20. Fugitive dust generation shall be controlled. Fugitive dust emission shall be regularly monitored

at locations of nearest human habitation (including schools and other public amenities

located nearest to sources of dust generation as applicable) and records submitted to the

Regional Office, MoEF, GoI, Lucknow and U.P.Pollution Control Board regularly.

21. Baseline data for ambient air quality shall be generated and maintained and RSPM level in

ambient air in the nearby human habitation (villages) shall also be monitored along with

other parameters.

22. Transportation of minerals shall be done by covering the trucks with tarpaulin or other suitable

mechanism so that no spillage of mineral/dust takes place.

23. Occupational health and safety measures for the workers including identification of work

related health hazards, training on malaria eradication, HIV, and health effects on exposure to

mineral dust etc. shall be carried out. Periodic monitoring for exposure to respirable mineral

dust on the workers shall be conducted and records maintained including health records of the

workers. Awareness programme for workers on impact of mining on their health and

precautionary measures like use of personal equipments etc. shall be carried out periodically.

Review of impact of various health measures shall be conducted followed by follow up action

wherever required.

24. The project proponent will ensure for providing employment to local people as per requirement,

necessary protection measures around the mine pit and waste dump and garland drain around

the mine pit and waste dump.

25. Top soil / solid waste shall be stacked properly with proper slope and adequate safeguards and

shall be utilized for backfilling (wherever applicable) for reclamation and rehabilitation of

mined out area. Top soil shall be separately stacked for utilization later for reclamation and

shall not be stacked along with over burden.

26. Over burden (OB) shall be stacked at earmarked dump site(s) only and shall not be kept active

for long period. The maximum height of the dump shall not exceed 20 m, each stage shall

preferably be of maximum 10 m and overall slope of the dump shall not exceed 35o. The OB

dump shall be backfilled. The OB dumps shall be scientifically vegetated with suitable native

species to prevent erosion and surface run off.

Page 22: Minutes of 280th SEAC Meeting Date 01/07/2016 · Minutes of 280th SEAC Meeting Date 01/07/2016 Page 2 of 22 3. A 7.5 m wide strip will be left at periphery of the lease area which

Minutes of 280th

SEAC Meeting Date 01/07/2016

Page 22 of 22

27. Monitoring and management of rehabilitated areas shall continue until the vegetation becomes

self sustaining. Compliance status shall be submitted to the Regional Office, Ministry of

Environment & Forests, GoI, Lucknow and U.P.Pollution Control Board on six monthly basis.

28. Slope of the mining bench and ultimate pit limit shall be as per the mining scheme approved by

Indian Bureau of Mines.

29. Permission for abstraction of ground water shall be taken from Central Ground Water Board.

Regular monitoring of ground and surface water sources for level and quality shall be carried

out by establishing a network of existing wells and constructing new piezometers

during the mining operation. The monitoring shall be carried out four times in a year i.e.

pre­monsoon (April­May), monsoon (August), post­monsoon (November) and winter (January)

and the data thus collected shall be regularly sent to MoEF, Central Ground Water Authority

and Regional Director, Central Ground Water Board.

30. The waste water from the mine shall be treated to conform to the prescribed standards

before discharging in to the natural stream. The discharged water from the Tailing Dam, if

any shall be regularly monitored and report submitted to the Regional Office, Ministry of

Environment & Forests, GoI, Lucknow, Central Pollution Control Board and the State Pollution

Control Board.

31. Hydro geological study of the area shall be reviewed by the project proponent annually.

In case adverse effect on ground water quality and quantity is observed mining shall be

stopped and resumed only after mitigating steps to contain any adverse impact on ground

water is implemented.

32. Vehicular emissions shall be kept under control and regularly monitored. Vehicles used for

transportation of minerals and others shall have valid permissions as prescribed under

Central Motor Vehicle Rules, 1989 and its amendments. The vehicles transporting

minerals shall be covered with a tarpaulin or other suitable enclosures so that no dust particles /

fine matters escape during the course of transportation. No overloading of minerals for

transportation shall be committed. The trucks transporting minerals shall not pass through wild

life sanctuary, if any in the study area.

33. Prior permission from the Competent Authority shall be obtained for extraction of ground

water, if any.

34. A final mine closure plan, along with details of Corpus Fund, shall be submitted to the Regional

office, Ministry of Environment & Forests, GoI, Lucknow and U.P. Pollution Control Board 5

years in advance of final mine closure for approval.

35. Project Proponent shall explore the possibility of using solar energy where ever possible.

36. Commitment towards CSR has to be followed strictly.

37. Regular health check­up record of the mine workers has to be maintained at site in a proper

register. It should be made available for inspection whenever asked.

38. Project Proponent has to strictly follow the direction/guidelines issued by MoEF, CPCB

and other Govt. Agencies from time to time.

39. The blasting will be done only after getting the permission from the Mining Department.