Minimizing Bulk Power Costs Study - SPP
Transcript of Minimizing Bulk Power Costs Study - SPP
© ABB Group August 23,2010 | Slide 1
Minimizing Bulk Power Costs Study in the Entergy System
Entergy Regional State Committee (ERSC)Southwest Power Pool (SPP)
November 17, 2010
ABB Inc. , Electric System Consulting Dept.
ERSC
ERSC
© ABB Group August 23,2010 | Slide 4
Minimizing Bulk Power Costs Study
Objective
“Determine what (if any) transmission expansion, reconfiguration, and/or
upgrades can reduce the production costs of generating units that
Entergy operates as must-run”.
Specifically, identify transmission projects which are cost
effective and meet Transmission Reliability Criteria for:
(1) Displacing those Reliability Must-Run (RMR) generating
units which are presently required to be committed and dispatched
for either voltage support or prevent overloading of transmission
lines, upon contingencies (including base case)
and/or
(2) Displacing those generating units that Entergy operates to
provide “flexible capacity” (e.g., load-following, operating reserves).
ERSC
© ABB Group August 23,2010 | Slide 5
Economic Comparison of Benefits and Costs
FINDING AN OVERALL and ACCEPTABLE BALANCE
RELIABILITY COST
ERSC
© ABB Group August 23,2010 | Slide 7
Study Tasks
Task 1 – Develop Data base and System Models
Task 2 – Transmission Analyses with RMR Unit
Task 3 – Transmission Analyses w/o RMR Unit & no Transmission Change
Task 4 – Transmission Analyses w/o RMR Unit & Transmission Change
Task 5 – Production Cost Simulation with RMR Unit
Task 6 – Production Cost Simulation w/o RMR Unit & no related Transfer Limit Constraint
Task 7 – Production Cost Simulation w/o RMR Unit & with Transmission Changes
Task 8 – Economic Comparison of Benefits and Costs
Task 9 – Collate results by Units, Plants and Groups.
Task 10 – Congestion Analysis
Task 11 – Fuel Price Elasticity
Task 12 – Sensitivity Analysis
Task 13 – Perform ATC Calculations
Task 14 – Study Report Preparation, Discussion and Presentation
Task 15 – Additional Transmission Upgrades required for Flexible Capacity
(Optional)
ERSC
© ABB Group August 23,2010 | Slide 8
GridView Software Main Inputs & Outputs
ABB GridView®
Hourly Production
Cost Simulation
Security Constrained
Unit Commitment &
Economic Dispatch
Generation
Units• size• fuel• availability
Transmission
Network• power flow• constraints• availability
Load• location • hourly variation• growth
Total Reserve Level
flows / congestion
system production costwind curtailment
Post Processing
Production Cost Reduction
Flexible Capacity
System Loss Reduction
Emission Reduction
Congestion
Wind Generation• location• hourly production
ERSC
© ABB Group August 23,2010 | Slide 9
Production Cost Input Assumption
Data Source
SPP
Entergy
CBA study report
Public sources: EIA, EPA
Transmission Data
Powerflow case
Flowgate/ Interface details
Load
Annual forecast for peak load and total energy
8760 hourly load curve for each area
Entergy and Non-Entergy load definition
ERSC
© ABB Group August 23,2010 | Slide 10
Production Cost Input Assumption
Thermal unit characteristics
Nuclear units
Hydro units
Renewable resources
Capacity additions and retirements
Emission data
Boundary conditions
ERSC
© ABB Group August 23,2010 | Slide 11
Production Cost Model Assumption
Marginal cost bidding
Marginal loss with distributed reference bus
Wheeling Rates
Fuel Price
Operating reserve requirement (Flexible Capacity)
ERSC
© ABB Group August 23,2010 | Slide 12
Production Costing Considerations
RMR Requirement
Flexible Capacity
Transmission Constraints
ERSC
© ABB Group August 23,2010 | Slide 13
Transmission Constraints’ Enforcement in GridView
Full transmission network representation
Transmission facility (lines and transformers) thermal ratings:
Summer and Winter
Normal, LTE and STE
Interfaces/flowgates limits, non-simultaneous and simultaneous,
including interfaces/flowgates limits or nomograms due to voltage and
stability problems
Interfaces/flowgates and nomograms under contingency conditions
Operating contingency: N-1, N-2 …
ERSC
© ABB Group August 23,2010 | Slide 14
Transmission Analyses
Transmission analyses are needed to…
Identify reliability criteria violations associated with displacement of an
RMR unit (or RMR units / plants) under study
Thermal overloads
Under / over-voltages
Run power flow analysis under all lines in and contingency case conditions
Identify transmission solutions to resolve reliability criteria violations
Test effectiveness of transmission solutions in resolving such violations through
power flow analysis
After identifying candidate solutions, need to come up with cost-
effective transmission (more on this later)
ERSC
© ABB Group August 23,2010 | Slide 15
Transmission Analyses
√ COMPLIANCE WITH THERMAL CRITERIA
√ CONVERGENCE
√ COMPLIANCE WITH VOLTAGE CRITERIA
COMPREHENSIVE CONTINGENCY ANALYSES
Identify possible solutions
• Topology, New Lines, Upgrades
• Compensation levels
THERMAL VIOLATIONS
Perform MUST, OPF
& Conventional Power Flow
NON-CONVERGENCE & VOLTAGE VIOLATIONS
OPF
Characterize reactive
deficiency
Add shunt compensation,
Amount & Location
Flow optimization
Conventional Powerflow
QV Curves
highlight needs for
SVC, STATCOM, etc.
PV Curves
Confirm adequate
margin for voltage
stability
ERSC
© ABB Group August 23,2010 | Slide 16
Economic Comparison of Benefits and Costs
Economic Comparison of Cases A (with RMR) & B (w/o RMR)
1000
3000
5000
7000
9000
11000
13000
1 6 11 16New Transmission Projects
Co
st
Annualized
Capital Cost
for New
Transmission
Pa A
PbB
Ca
Total
Cost
Cb
Ta=Pa + Ca
Tb=Pb +Cb
S
A
V
I
N
G
S
Cost
Ta - Tb = Net Benefit
Annual
Production
Cost
Beside production cost reduction benefit, following benefits can be quantified:
- Transmission loss reduction (MW reduction from peak power-flow case)
- Reduction or elimination of fixed costs (ERSC/SPP to estimate)
- Emission/Carbon reduction (implicitly or explicitly, to be agreed upon at the beginning of the study)
Scales for
Annual
Operating Costs
and Annual
Transmission
Costs are not
one to one and
somewhat
exaggerated for
illustration
purposes.
ERSC
© ABB Group August 23,2010 | Slide 17
Collate results by Units, Plants and Groups
Results by unit(s) in the following 3-phases (in the Original Scope);
Phase I – Top three units based on highest capacity factor (RFP Table)
Phase II – Includes Phase I with next three units in capacity factor order
Phase III – Includes Phase II with remaining units in capacity factor order
Results by Individual Load Pocket in a
Top-down Approach
Phase I – One Load Pocket at a time, independently of other Load pockets
as well as all the Load Pockets together
Other Phases – Depends upon the results from Phase I.