KERTAS CADANGAN
MINI GASIFIKASI
SISA PEPEJAL (Mini Gasification Waste Plant)
Sesuai Untuk
Mengurus Sisa Pepejal Perbandaran
(MSW)
![Page 2: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/2.jpg)
• Pelupusan sisa pepejal
• Matlamat Pembentangan
• Pengenalan teknologi gasifikasi
• Gasifikasi berbeda dengan inserinasi
• Sistem loji inserinasi
• Sistem loji gasifikasi WCS
• Gas toksik dioksin adalah pencemaran utama
• Sistem Emission control
• Tidak semua gasifikasi boleh menghapus dioksin
• Bukti gasifikasi WCS patuhi standard DOE
• Gasifikasi mampu lupus sisa cecair
* Perbandingan gasifikasi & inserinasi
• Gasifikasi WCS terbukti banyak beroperasi
• Mengapa pilih KNM-WCS
• CADANGAN PROJEK 2
KANDUNGAN PEMBENTANGAN
![Page 3: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/3.jpg)
PENGENALAN &
MATLAMAT
3
![Page 4: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/4.jpg)
MATLAMAT PEMBENTANGAN
Memperkenalkan teknologi gasifikasi WCS agar ia di gunapakai di PRIDE bagi
mengendali sisapepejal agar ia dilupus secara terbaik AT SOURCE di mana ia
dapat memberi nilaitambah di segi ekonomi, keselamatan, mesra alam sekitar,
efisen dan teknoloji.
TEKNOLOJI GASIFIKASI WCS ADALAH BERBEDA & LEBIH BAIK &
SELAMAT DARI INSERINASI
4
![Page 5: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/5.jpg)
PELUPUSAN SISA PEPEJAL
Sisa pepejal perbandaran(MSW) menjadi isu panas kerana ia membabitkan
masalah kesihatan & pencemaran alam sekitar. Beberapa cara sisa ini di
kendalikan:-
1) Pelupusan di tapak pelupusan
2) Pembakaran dengan kaedah inserinator
3) Kaedah gasifikasi (contoh nya plasma gasification, fluid bed, dsb)
Pelupusan di tapak pelupusan menimbulkan masalah bau busuk, pencemaran
alam sekitar, penyebab penyakit & bantahan penduduk
Kaedah inserinator pula mengalami prestasi buruk di segi kegagalan operasi
contohnya di Semenyih, Cameron Highland, Pangkor di sebabkan sampah basah
dan pembakaran separa menyebabkan terbentuk bahan melekit & merosakkan
peralatan.
Kaedah gasifikasi adalah terbaik kerana ia mesra alam sekitar & kebal basah
(sebab bukan pembakaran biasa) namun pemilihan teknologi adalah penting kerana
ia mesti lah telah terbukti beroperasi & di- iktiraf Badan Berkuasa Alam Sekitar
5
![Page 6: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/6.jpg)
Contoh innovasi pengurusan sampah
6
![Page 7: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/7.jpg)
Apa dia gasifikasi
7
![Page 8: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/8.jpg)
Perbedaan gasifikasi & inserinasi
Kentuhar gasifikasi
(penghancuran dengan haba) Inserinasi
(bakar dengan api)
8
![Page 9: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/9.jpg)
Gasifikasi berbeda dari inserinasi
Gasifikasi mengubah sampah (memecahkan kepada molikul kecil) dalam proses
konversi kimia bersuhu tinggi dan menukarnya kepada gas sintesis (syngas).
Pengeluaran syngas inilah yang menjadikan gasifikasi berbeza dari inserinasi.
Dalam peroses gasifikasi, sampah bukan sebagai bahan bakar, tetapi suatu
bahan fidstok yang diperoses dalam ketuhar gasifikasi tanpa atau dengan oksijen
minima.
Inserinasi guna sampah sebagai bahan bakar, dibakar bersama udara yang
banyak untuk hasilkan haba panas yang kemudian di guna untuk menghasil stim,
seterusnya menjana elektrik.
9
![Page 10: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/10.jpg)
Berkenaan Alam
Sekitar
10
![Page 11: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/11.jpg)
Dalam inserinasi, perkara paling kritikal ialah terbentuknya bahan toksik dioksin
&furan apabila bahan plastik & PVC di bakar. Pembersihan dioksin mengunakan
penapis beg hanya di lakukan selepas pembakaran & ia tidak mudah di lakukan
kerana partikul gas adalah halus.
11
Inserinasi mengeluarkan dioksin
![Page 12: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/12.jpg)
Dalam gasifikasi, molekul besar spt plastik di hancur sepenuhnya menjadi syngas, &
diperoses selanjutnya dalam KETUHAR(chamber) ke-2 bagi hilangkan dioksin & selanjutnya
dibersihkan sebelum diguna untuk menghasil stim / elektrik. Dioksin memerlukan oksijen yang
cukup untuk terbentuk, olehitu ia sukar terjadi kerana oksijen di kurang /di tiadakan. Juga,
dioksin memerlukan partikul logam halus di ekzoz untuk ia membentuk semula, ini tidak
berlaku dalam gasifikasi kerana syngas di bersihkan ( dlm chamber ke-2 & cleaning) dari
partikul halus logam sebelum di guna.
Gas being
further heated at
1200 degree C
to clear metal
particulate
12
Gasifikasi - Dioksin dapat dihapus
![Page 13: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/13.jpg)
Dioksin adalah satu kumpulan kompaun kimia terdiri dari atom2 karbon, oksijen, hidrojen
dan klorin . Jumlah klorin & posisi dalam molikul dioksin akan menentukan kekuatan toksik
dioksin. Yang paling toksik ialah dimana 4 atom klorin di posisi 2, 3, 7 dan 8-
tetrachlorodibenzo-p-dioxin, yang biasa di panggil TCDD or “dioxin”.
TCDD, 2, 3, 7, 8-
tetrachlorodibenzo-p-dioxin
Antara punca dioksin: Pembakaran sisa pepejal sampah / sisa hospital, pembakaran
backyard & emissi kenderaan
Gas dioksin- pencemar utama
Elakkan sistem pembakaran yang boleh mengeluarkan dioksin & mencemar ikan di
Negeri Selangor 13
![Page 14: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/14.jpg)
Gasifikasi WCS dapat hapus dioksin
Dalam ketuhar pertama sampah di hancurkan dengan pemanasan haba 500
degree C menjadi molikul kecil melalui proses pyrolysis>> pemanasan haba>>
reduksi>> syngas.
Dalam ketuhar kedua syngas di panaskan lagi dengan suhu lebih tinggi 1200
degree C supaya dioksin di hapuskan dengan menghancurkan lagi partikul logam
kecil dalam gas. Dioksin akan membentuk semula jika ia bertemu partikul
logam halus di ekzoz
Ini tidak terdapat dalam sistem gasifikasi lain selain dari WCS.
Untuk menambah lagi penghilangan total toksik, syngas di cuci menggunakan
sistem gas cleaning
Syngas is then combusted with
violent turbulent air to about 1000
C for over 5 seconds for complete
combustion of toxic gasses
14
![Page 15: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/15.jpg)
Gasifikasi WCS patuhi std DOE
15
![Page 16: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/16.jpg)
Masalah Sampah
Basah
16
![Page 17: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/17.jpg)
Gasifikasi mampu lupus sisa cecair
![Page 18: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/18.jpg)
Perbandingan
Inserinator Vs
Gasifikasi
18
![Page 19: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/19.jpg)
PERBANDINGAN
Incinerator Gasification
Design Niche *Only suits Large installations
*And Built for large Cities
*Due to Complex & sophisticated
(costly)
*Can also suit Smaller Plants
(400tpd & below)
*Feasible for Built for small township
*Simple &easy operation
Capital Cost *Expensive due to complexity
* Suit only if Cost not an issue
*Cheaper because simple
*Optimized cost-benefit (ROI)
Operating Cost High with more manpower &
expertise
Low with small manpower,
normal expertise
Waste Quality *Poor quality and wet
*Pit Storage and unsorted
*No Moisture/odor control
*Controlled quality
*Floor Storage and sorted
*Pre-treatment of waste
Process *Lots of moveable parts
*More process control
*Black smoke &Gas
*Dioxin Formations toxicity
*Less movable parts
*Much less controls
*Inherent Clean Air & ash
* Very Little Dioxin formation
Maintenance *Frequent & expensive
*Black Smoke and odor
*Boiler soot clogging& movable chain
stoppage
*Low Requirement
*Clean complete combustion
*Particulate fully removed
*Free flow of clean hot air
19
![Page 20: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/20.jpg)
Pengalaman WCS
(loji beroperasi)
20
![Page 21: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/21.jpg)
GAMBAR2 LOJI BEROPERASI
21
83MW MSW Energy
Plant, ITALY
50MWe Public Utility,
Tacoma, California-
Scotgen Scotland MSW180tpd
38tpd Atol,Marshal Islands MSW
Husavik, Iceland MSW& Tires
Wake Island, USA MSW
Cayman Islands MSW
Manitoba, 400 TPD
Industrial Waste West Caicos Island MSW
![Page 22: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/22.jpg)
• US Air Force, Wake Island, USA – Municipal Solid Waste, Tires &
Waste Oil
• Scotgen Ltd, SCOTLAND – Municipal Solid Waste
• US Department of Defense, Kwajalein Atoll, Marshall Islands,USA –
Municipal and Industrial Waste
• Husavik, Iceland – Municipal Solid Waste & Tires
• Cayman Islands – Municipal Solid Waste .
• West Caicos Island – Municipal Solid Waste
• ConocoPhillips, Alaska – Industrial Waste
Gasifikasi WCS telah banyak beroperasi
(TranVIT)
22
![Page 23: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/23.jpg)
• US Air Force, Wake Island, USA – Municipal Solid Waste, Tires & Waste Oil • Scotgen Ltd, Scotland – Municipal Solid Waste 180tpd. • US Department of Defense, Kwajalein Atoll, Marshall Islands – Municipal and Industrial Waste . • Husavik, Iceland – Municipal Solid Waste & Tires.
• Lomati Houtverwerkers-180 TPD Industrial Waste, Barberton, South Africa
• Goodwood Management Corp - 50 TPD Mass Burn Municipal Waste
• Ainsworth Lumber, High Level, British Columbia,- 600 TPD wood waste Con
• Spruce Products Ltd, Swan River, MB - 140 TPD Bio-mass Waste
•Thora, Coffs Harbor Australia - 200 tpd mass burn, industrial waste,
• Louisiana Pacific, Manitoba,- 400 TPD Industrial Waste
Gasifikasi WCS yang beroperasi
(V Health)
23
![Page 24: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/24.jpg)
• Renewable Energy Plant, Oregon :Biomass Fuel 35MWe
• Renewable Energy Plant, Georgia: Biomass Fuel 53.5MWe
• Renewable Energy Plant, Italy: Tree Waste 18MWe
• Renewable Energy Plant, ITALY : Municipal Waste 83MWe
• Hudson County Utility Authority – Sewage Sludge 75MWe .
• Thermo Electron/ABB, California– Municipal Wood Waste 32MWe.
• San Joaquin Valley Energy, California – Municipal Wood Waste 28 Mwe
• Dept of Public Utility, Tacoma, California- Municipal Solid Waste 50MWe
• General Electic Companies, California- Municipal Wood Waste 12.5MWe.
•Crisstad Power Plant, Oregon: Wood Waste 5MWe
•Ultra Power Station, California; Wood Waste 25MWe
Gasifikasi WCS yang beroperasi
(Fluid Bed)
24
![Page 25: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/25.jpg)
Mengapa Pilih Sistem
Kami
25
![Page 26: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/26.jpg)
a) Berkenaan alam sekitar
1- Telah mendapat persijilan alam sekitar DOE antara bangsa.
2- Telah di ujikaji oleh DOE antara bangsa di-loji-loji yang
beroperasi.
3- Sistem dua chamber/ketuhar dimana chamber ke-2 akan
memecah/menghapus partikul logam yang boleh membina
semula dioksin apabila tiba di cerobong.
4- Sistem WCS memberi peralatan alternatif untuk membuat
auto-sorting untuk mendapatkan produk kitar semula.
5- Produk kitar semula seperti kaca dan logam terhasil
26
![Page 27: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/27.jpg)
b) Berkenaan prestasi
6-WCS dalam tempoh 20 tahun telah menyediakan lebih 100 loji gasifikasi dimana
19 buah menggunakan sisa pepejal MSW
7- Tidak mempunyai banyak mesin bergerak, jadi kurang peralatan rosak, dapat
kurangkan kos operasi
8- Tidak perlu menambah additional fuel seperti arang batu untuk menambah nilai
kalorifik.
9- Lebih murah kerana tak perlu membina loji pembuat pelet
10- Kurang kos operasi kerana kurang mesin bergerak seperti mesin2 pembuat
pelet
11- WCS boleh membantu mengurus dana EXIM bank kerana telah lama
berkecimpung
12- WCS ada cawangan berdaftar di Malaysia, memudahkan lojistik, pengurusan,
komunikasi dan latihan.
13 WCS yang beribupejabat di USA, mendapat sokongan kerajaan USA dan
rangkaian bank
14- WCS mengunakan sistem komputer, kurang guna tenaga dan
penyelenggaraan
27
![Page 28: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/28.jpg)
CADANGAN PROJEK
(PRIDE)
28
![Page 29: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/29.jpg)
29
BOS Thermal Gasification
Boleh menyelesaikan masaalah
pembuangan sampah untuk:
• Komuniti Kondomium/ rumah pangsa
• Bangunan bertingkat
• Pasar Borong
• Majlis Perbandaran
• Kepulauan
• Hospital
• Lapangan Terbang
![Page 30: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/30.jpg)
30
TENAGA
ELEKTRIK
Sampah
Campuran Ketuhar
Tiada
asap
![Page 31: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/31.jpg)
31
* Menggunakan ia seperti tempat buang sampah
* Boleh di penuhi hanya sekali sehari
* Tiada sorting/pemilihan sampah di perlukan
* Cuma tekan buton dan tinggalkan
* PLC Panel kontrol-boleh di lakukan secara remote dari pejabat
* Boleh untuk kuantiti kecil cuma 1 tan sampah sehari
* Bank EXIM USA boleh membiayai
* Boleh mendapat barang kitar semula seperti logam dan kaca
* Peroses pelupusan 99%, sampah menjadi ash/debu
* Tiada kelihatan emissi
* Pekerja separuh masa
Kebaikan BOS WCS
99%
Tiada
asap
![Page 32: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/32.jpg)
32
SESUAI UNTUK MELUPUSKAN
![Page 33: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/33.jpg)
33
TENAGA ELEKTRIK
BOLEH DI KELUARKAN
![Page 34: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/34.jpg)
KOS PEMBINAAN 5 t.p.d.
Kapasiti 5 tan/hari –Untuk Komuniti dalam residential& commercial area
5 Metric tons/day
Mixed Solid Waste Batch processing &waste disposal equipment
a) Gasification Processing Equipment US$ 822,000
Primary Chamber: one Unit (Height: 3.05 Meters, Width: 2.74 Meters
Length: 3.81 Meters, Volume:26 m3)
Secondary Chamber:1 Unit (Height: 4.27 Meters, Diameter:2.44 Meters)
Total Shipping Weight: 35.00 tons
Insulation:51mm, Refractory 102mm
Process Control Panel and Instrumentation etc
b) Hot Water Recovery Process US$ 50,000
Boiler: Fire tube, heat recovery boiler:
Steam Production: 3,000 kg/hr at 8 bar and 170deg C
Ducting, Stack, and ID Fan etc
c) Related Accessories
I, Waste Oil Injection System US$ 18,000
ii. Cog Belt Conveyor for top loading US$ 20,000
Sub total: US$ 910,000
1. Building 82’L x 60’W x 30’H US$182,000
2. Site Preparation
3. Paved Road to the Building
4. Movable Items
5. Diesel skid Tank 4,000 liters
`d) Installation, engineering, commission US$500,000
Total Contract Price: US$1,592,000
(RM5,090,000)
34
![Page 35: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/35.jpg)
PELAN TAPAK
Kapasiti 5 tan/hari
![Page 36: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/36.jpg)
PELAN SISI LOJI Kapasiti 5 tan/hari
![Page 37: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/37.jpg)
PULANGAN KEPADA PRIDE
Oleh kerana loji PERINTIS ini adalah kecil (1-10 tpd), maka jika di adakan
pengeluaran elektrik secara kommersial, ia tidak ekonomik kerana perlu
menambah sistem penjanaan elektrik. Maka pulangan kepada PRIDE
adalah:-
1- Menyumbang kepada menghijaukan bumi & kadar pelepasan karbon ke
udara
2- Dapat menjaga alam sekitar & mengurangkan risiko penyakit
3- Penghasilan tenaga elektrik/air panas/stim untuk kegunaan sendiri seperti
hotel,etc (elektrik tidak di ekspot ke grid)
4- Mendapat bayaran sijil CER melalui perjanjian CDM (PBB)
5- Koleksi barang kitar semula seperti logam, kaca & abu
6- Tidak perlu pengangkutan sampah kerana loji boleh di pasang di setiap
kawasan bangunan di mana pengguna seolah seperti membuang sampah ke
tong sampah.
UNTUK LOJI CADANGAN INI
37
![Page 38: mini gasification for handling MSW at upstream](https://reader030.fdocuments.net/reader030/viewer/2022020218/559b7e041a28ab15768b45ca/html5/thumbnails/38.jpg)
UNTUK LOJI YANG BESAR
Secara amnya PEMAJU yang membina loji sisa pepejal ke-tenaga akan dapat
pulangan seperti berikut:-
1-Tarif Fit dari SEDA( kementerian KETTHA) lingkungan 42 sen/kwh jualan elektrik
ke-grid.
2-Fi Tipping ( bergantung kadar yang di persetujui Majlis Perbandaran) lingkungan
RM30 ke RM 62 setan bergantung kawasan
3- Jualan stim / air panas jika loji di ubahsuai sebagai co-generation.
4- Jualan sijil CER(Carbon Emission Reduction) – dikendali Bangsa2 Bersatu
melalui perjanjian CDM(Carbon Development Mechanism), di bawah Kyoto Protocol-
lingkungan USD10/ton CO2
5- Jualan kitar semula seperti logam, kaca, debu ash, dsb
38