Midwest Project Presentation to Engineering consulting firms
description
Transcript of Midwest Project Presentation to Engineering consulting firms
Areva Resources Canada Inc.
Midwest Project
Presentation to Engineering consulting firms
Vincent Lanièce, Director of Project Development September 2006
AREVA Resources Canada Inc.
> Titre de la présentation - Date - Références - 2> Midwest project – presentation to Engineering consulting firms, Sept 2006 2Areva Resources Canada Inc.
Midwest location
Cluff Lake
McClean Lake
Key Lake
McArthur River
Cigar Lake
Rabbit Lake
WollastonLake
Midwest
SASKATCHEWAN
ALBERTA
Athabasca Lake
N
AthabascaSandstone
Basin
Athabasca Basin
Saskatoon
Projects Operated by COGEMA Resources Inc.
> Titre de la présentation - Date - Références - 3> Midwest project – presentation to Engineering consulting firms, Sept 2006 3Areva Resources Canada Inc.
Midwest site picture
> Titre de la présentation - Date - Références - 4> Midwest project – presentation to Engineering consulting firms, Sept 2006 4Areva Resources Canada Inc.
Midwest Project and overall schedule
The Midwest project is divided in 4 parts 1. Mining (Open Pit) – done internally2. Transportation (dedicated haul road) – done with local
consultants/contractors3. Midwest water treatment system – looking for EPCM4. Milling - Midwest expansion Project (Increase the JEB Mill production
from 12 to 16 Mlbs/y U3O8) – looking for feasibility studyKey datesMine: dam and dewatering of Mink Arm starts in summer 2007 – mine
stripping starting in Apr 2008
Water treatment plant, pipeline, road and power line: operational for Apr 2008
Mill modifications: in production by Nov 2009
> Titre de la présentation - Date - Références - 5> Midwest project – presentation to Engineering consulting firms, Sept 2006 5Areva Resources Canada Inc.
Preliminary Midwest site layout
> Titre de la présentation - Date - Références - 6> Midwest project – presentation to Engineering consulting firms, Sept 2006 6Areva Resources Canada Inc.
Midwest and McClean road connection
> Titre de la présentation - Date - Références - 7> Midwest project – presentation to Engineering consulting firms, Sept 2006 7Areva Resources Canada Inc.
Preliminary 3D picture of mill expansion
Tailings Neutralization
Solution Shipping
Oxygen Plant
Ore Receiving
CCC
Grinding Circuit Neutral Thickener
Yellowcake Storage
Molybdenum Recovery
SX AdditionMidwest WTP
cancelled – located at
Midwest
> Titre de la présentation - Date - Références - 8> Midwest project – presentation to Engineering consulting firms, Sept 2006 8Areva Resources Canada Inc.
2 services requested from Engineering firm
1. Midwest water treatment plant system: Detailed Engineering, Procurement and Construction Management
2. McClean Lake JEB mill expansion: Feasibility Study, including detailed cost estimate and level 1 schedule
> Titre de la présentation - Date - Références - 9> Midwest project – presentation to Engineering consulting firms, Sept 2006 9Areva Resources Canada Inc.
Midwest water treatment plant “System” - overview
Need to treat water, 25,000m3/day expected, released to the McClean Lake effluent system called “Sink reservoir” (20 km distant).
Current process contemplates: Combination of membranes and conventional water
treatment plants, with the treated water quality greater than the Sask Surface Water Quality Objectives (SSWQO)
Single wall pipe (20 km long) that would carry the treated water from Midwest to Sink Reservoir
> Titre de la présentation - Date - Références - 10> Midwest project – presentation to Engineering consulting firms, Sept 2006 10Areva Resources Canada Inc.
Midwest water treatment plant “System” – Engineering status
Feasibility study in progress, including flow sheets, P&IDs, detailed cost estimate
The feasibility report should be available by end of November 2006 and will be used as the basis to tender the EPCM portion
Note that the Procurement of the EPCM will be supervised by the Areva Resources Project Contract Manager
Time line short (schedule driven project) as we need to use the 2007 fall season to start construction
System in operation (including commissioning) by early April 2008
> Titre de la présentation - Date - Références - 11> Midwest project – presentation to Engineering consulting firms, Sept 2006 11Areva Resources Canada Inc.
Midwest Mill expansion - description
McClean Lake uranium mill (called “JEB”) currently expanded from 8 to 12 Mlbs/year – should be in operation by 1st quarter 2007
JEB expansion to mill Midwest ore: increase of annual production from 12 to 16 Mlbs contemplated, in operation by Nov 2009
Expansion scope described in the next slides
> Titre de la présentation - Date - Références - 12> Midwest project – presentation to Engineering consulting firms, Sept 2006 12Areva Resources Canada Inc.
Mill expansion Project scope 16 Mlbs (1/4)Ore receiving:Existing ore pad large enough to receive additional MW ore.
Grinding:Capacity OK.
Pulp Density:An additional neutral thickener will increase the density up to 50% solid.
Pulp Storage:One additional pulp pachuca required
Leaching:3rd leach circuit located in current tailings neutralization vault O2 used as the oxydant with mild pressure leaching (2 bars in average)
> Titre de la présentation - Date - Références - 13> Midwest project – presentation to Engineering consulting firms, Sept 2006 13Areva Resources Canada Inc.
Mill expansion Project scope 16 Mlbs (2/4)CCC-CCD: No modifications anticipated
Clarification: 1 additional sand filter requiredPregnant aqueous storage capacity fine
Solvent extraction:New extraction circuit (cells available recovered from other uranium
mill) Current extraction cells used as Arsenic scrub and water wash cellsStripping and regeneration are OK.
Mo, Ni and Co recovery circuits:Assessing potential process and cost/benefit analysis in progress
> Titre de la présentation - Date - Références - 14> Midwest project – presentation to Engineering consulting firms, Sept 2006 14Areva Resources Canada Inc.
Mill expansion Project scope 16 Mlbs (3/4)
YC precipitation:
Addition of a second centrifuge and barren strip solution sand filter
Calcining/Packaging:
Addition of a yellow cake drum storage area (report currently exists)
Tailings Neutralization:New circuit – 2 mix tanks followed by 3 tailings neutralization tanks
Mill Water Treatment Plant:No change
Ferric Sulphate Plant:
Addition of a 3rd reactor, ferric sulphate storage tank and iron ore pad to expand
> Titre de la présentation - Date - Références - 15> Midwest project – presentation to Engineering consulting firms, Sept 2006 15Areva Resources Canada Inc.
Mill expansion Project scope 16 Mlbs (4/4)
Acid Plant:Upgrade of the plant from 150 to 285 t/d H2SO4 (acid strength of 100%)
Reagents:Additional lime slurry storageAdditional ammonia storage tank
Ammonium Sulphate Crystallisation:No change
Utilities:No change
Electrical Substation:No change
> Titre de la présentation - Date - Références - 16> Midwest project – presentation to Engineering consulting firms, Sept 2006 16Areva Resources Canada Inc.
Midwest Mill expansion – Engineering status
Pre-feasibility in progress, done internallyPre-feasibility report available by end of November
2006 – it will be the basis for tendering the feasibility study
> Titre de la présentation - Date - Références - 17> Midwest project – presentation to Engineering consulting firms, Sept 2006 17Areva Resources Canada Inc.
Project organization
Engineering consulting firm in charge of design, cost estimate, schedule
Areva resources Canada Inc. bringing input and in charge of review
Procurement/Contracting: strong interface with Areva Resources Contract Manager
Very close and efficient relation expected
> Titre de la présentation - Date - Références - 18> Midwest project – presentation to Engineering consulting firms, Sept 2006 18Areva Resources Canada Inc.
Key assets expected from Consulting firm
Engineering team based in Saskatoon, Saskatchewan so that the design control can be done efficiently
Experienced Engineers and project Manager during the entire life of the project with very limited turn-over
Quality system in placeGood understanding of the Uranium/Nuclear industryDocuments and Project cost tracking system availableTenders submitted in December 2006 with decision
made in January and start of work early February 2006