MID-YEAR BUDGET AND PERFORMANCE ASSESSMENT REPORT
Purpose
The purpose of this report is to outline to the Executive Committee/Council the mid-year budget and
performance assessment of the municipality.
Background
Section 88 (1) of the MFMA state that, the accounting officer of a municipal entity must by 20 January of
each year –
a. Assess the performance of the entity during the first half of the financial year, taking into account -
i. The monthly statement referred to in section 87 for the first half of the Financial year and the targets
set in the service delivery, business plan or other agreement with the entity’s parent municipality; and
ii. the entity’s annual report for the past year, and progress on resolving problems identified in the
annual report; and
b. Submit a report on such assessment to –
i. The board of directors of the entity; and
ii. The parent municipality of the entity.
It is against this background that the report is presented to the Executive Committee/Council for
consideration.
PERFORMANCE MANAGEMENT SUMMARY
The report presents the mid-year performance achievements for 2012/13 financial year.
1. Municipal Manager’s Office
1.1. Good Governance
Achievements:
Internal audit and Audit committee Charters were reviewed
Approved internal audit annual coverage plan
Audit Committee held quarterly meetings
Challenges Interventions
Lack of communication between Audit
Committee and Council
The audit committee to report quarterly to the
Council
Capacity of internal audit unit To be improved in the next financial year
2
1.2. PMU
Achievements:
We have Constructed Sekwena Arts & Craft and the project is completed at the value of
R830 497.41.
Construction of Sefoloko Low Level Bridge in progress.
Renovated Mogwadi Community Hall at a value of R197 229.12.
Challenges Interventions
Sefoloko low level bridge was delayed due
to lack of communication with external
stakeholders i.e. Makgoshi
Regular engaged are ongoing with all
affected stakeholders.
1.3. Communication
Achievements:
Advertising has been improved. Municipal has extended advertising to the media
i.e. Radio.
Municipal affairs receive a wider audience as a result of better advertising.
Challenges Interventions
Lack of municipal branding material To be proposed in the budget adjustment
2. COMMUNITY SERVICES DEPARTMENT
2.1. Public Amenities (Pre-schools, Community Halls, Parks, Taxi Ranks)
Achievements
Construction of Pre-schools/Community Halls at Dipateng and Brussels are at roof level.
Thorough consultations and soliciting of information in drafting of specifications for establishment of
the Mogwadi Park have been completed.
Illegal structures in and around the Morebeng Taxi Rank have been demolished. The facility is now
ready for refurbishment.
Challenges Interventions
3
Illegal structures and traders in and around
the Morebeng taxi rank caused a delay in
the commencement of refurbishment of the
facility.
Consultations with experienced providers for
establishment of a fully fledged park which
will provide better value for money in the
end. Appointment of service provider will
take place in the 3rd
quarter. A Bid
Specification Committee has been
established in order to validate all tender
bids before they go for adverts and to
ensure compliance to regulations.
Problems surrounding taking over of the
Nthabiseng Community Hall by the
Municipality resulted in suspension of the
refurbishment of the facility.
LEDP has been roped in to address
challenges of illegal structures at the
Morebeng Taxi Rank.
Water shortages at Mogwadi and Morebeng
towns resulted in suspension of construction
of ablution facilities at the cemeteries.
2.2. Waste & Environmental Management
Achievements:
Improved environment in terms of cleanliness and consistent waste removal services at Morebeng
and Mogwadi towns.
Challenges Interventions
Water shortages at Mogwadi and Morebeng
resulted in suspension of construction of
ablution facilities at the cemeteries.
Services of digging of graves and provision
of portable mobile toilets will be outsourced
per funeral at Mogwadi and Morebeng
cemeteries.
2.3. Traffic & Licensing
Achievements:
2 collaborative roadblocks with SAPS, Dept of Roads and Transport have been staged in the 2nd
quarter.
Challenges Interventions
Lack of traffic and street trading by-laws in
the Municipality.
1st completed draft for Traffic and Street
Trading by-laws have been forwarded to
external stakeholders for inputs
4
2.4. Sports, Arts & Culture
Achievements:
Participation in Golden and Indigenous games in the 2nd
quarter.
Challenges Interventions
Postponement of Mayoral Cup into the 3rd
quarter.
Co-coordinating Mayoral Cup Committees
have been elected per cluster to drive the
process.
2.5. Housing
Achievements:
The first phase of the Normalization Process has been completed. COGHSTA is in the process of
appointing conveyances to drive the process.
2.6. Libraries
Achievements
5 mobile library visits took place at Molemole. New publications have been bought and shelves have
been updated.
3. TECHNICAL SERVICES DEPARTMENT
3.1. Electrical & Mechanical
Achievements:
Contractor appointed for the Replacement of rotten poles and Replacement of MV and LV
conductors in Morebeng.
The process of appointing the contractor for the smart metering is has been adjudicated.
Challenges Interventions
Electrification backlog in the villages. Facilitation for more funds allocation from
DOE.
Delays in the supply chain management
process.
Liaison with CDM to provide more funds to
address electrification backlog.
Breakdowns on our maintenance Advertised for the appointment of service
5
machineries and fleet. provider to maintain our machineries.
3.2. Water & Sanitation
Achievements:
Appointment of service provider to supply water maintenance materials.
Approval of Operation and Maintenance Plan.
Supply of water thorough tankers to 18 villages.
Challenges Interventions
Frequent breakdowns on our water
sources/boreholes.
Appointed service provider to supply water
maintenance materials.
Unreliable water sources. Identify other water sources.
Aging water infrastructure.
3.3. Roads & Storm water
Achievements:
Grading of 187.6 km.
Challenges Interventions
Frequent breakdowns on our machineries. Appointment of service provider for
maintenance of our machineries.
4. CORPORATE SERVICES
4.1. Administration
Achievements:
Construction of Walkway at Mogwadi main offices completed
Appointed Dimension Data for supply and installation of Access Control system at Mogwadi main
office. Project estimated to be completed by March 2013.
Installed office hygiene equipment in all municipal service points.
Feasibility assessment for installation of telephone management system at Morebeng and
Sekgosese DLTC conducted and awaiting project proposal from the service provider.
Challenges Interventions
Unavailability of funds for installation of Defer installation of Security surveillance
6
security surveillance system
system to 2013-2014 Financial year
4.2. Human Resources Management
Achievements:
(a) Developed advertisement for appointment of a provider for organizational re-engineering
(b) Filled 17 vacancies during the quarter
(c) Held a local labour forum meeting
(d) Held a safety audit outreach programme at Mogwadi offices
Challenges Interventions
Employee discipline in particular work
attendance and unauthorized absence
Employees alerted of the disciplinary code
and code of conduct
Non-adherence to working hours Strict monitoring of work attendance
registers
Failure to attract skilled personnel in the
highly specialized fields and people with
disabilities
Review of condition of service
4.3. Council Support and Legal Services
Achievements:
(a) Held 2 x outreach programmes during the quarter
(b) All ward committee reports submitted and paid
(c) Contract register has been developed and updated timeously
Challenges Interventions
Additional funds required for increase in
ward committee allowance
Developed by-election programme to fill
vacant ward committee position arising from
sporadic resignations
Delays by Service Providers to finalize
agreements
Expedite finalization of remaining contracts
through consultation with relevant
institutions.
Budget for ward committee allowance
increments during 2013-2014 Financial year
5. FINANCE DEPARTMENT
5.1. Budgets & Reporting
Achievements:
7
Improved MFMA Section 71 Reports Integrity/credibility (July to December).
Grant Register Initiated & Compiled/Updated for July, August and Sept 2012.
Budget Statement Reports Maintained; July, August and Sept 2012.
Successfully keeping Audit Information Requests.
Plans advanced to keep performance Information kept as portfolio of evidence in CFO’s office.
Challenges Interventions
Need for specific training on Venus Software
just started in January 2013
Accountant have been appointed and
working efficiently.
Under skilled on Fin. Acc. Software (Venus). Further Formal Training on other Venus
arranged in third quarter.
No integration between the accounting
software (Venus) and AFS (excel based
spreadsheet template).
Have performance Information ready to be
published on the website if appropriate.
Clearing and control accounts not utilised for
the intended purpose (Bank recon, salaries
recons etc.)
CFO to review and sign all clearing and
control accounts monthly for action on
recurring items.
Keep hard copy of performance information
in hard copy files monthly, in CFO’s office.
5.2. Revenue & Income Managements
Achievements:
(e) Bank Reconcilliation now done manually and available for relieving long outstanding items for July,
Aug & Sept.
(f) Receivables from exchange and non-exchange transactions now separated and fully aged and
categorized i.t.o the Grap 9.
(g) Meter readings now accurate and reliable.
(h) Cash and cash equivalent now disclosed properly in accordance with appropriate accounting
standard (GRAP 104)
(i) Plans advanced to keep performance Information kept as portfolio of evidence in CFO’s office.
(j) Indigent Register now fully compiled and kept in compliance policy.
Challenges Interventions
Collection rate has still improved to 19.5%
but lower than disirerable due to historical
culture of non-payment.
Notices for service discontinuation will after
consultation, be issued in October and
actuated in November 2012.
Substandard skill on accounting software
(Venus).
Notices and reminders to be issued
monthly as an ongoing standard process.
Substandard skill on accounting software
(Venus).
A great deal of households is found locked
at meter reading times.
8
5.3. Expenditure & Capital Projects Implementation(Funding)
Achievements:
(d) Capital expenditure within schedule.
(e) Vat 201 reconciliations are now done regularly (bi-monthly) for 1st Quarter.
(f) Plans advanced to keep performance Information kept as portfolio of evidence in CFO’s office.
Challenges Interventions
Substandard skill on accounting software
(Venus).
Training arranged and up
Substandard skill on salaries software (Pay
Day V3.8).
Training arranged and up
Not yet developed an automated pro-active
capital expenditure monitoring system and
an early warning system.
To request IT to design an electronic
flagging or pro
5.4. Supply Chain & Assets Management
Achievements:
(a) A credible Asset Register unbundled in compliance with GRAP 17 and other relevant related
accounting standards.
(b) A credible Lease Register in compliance with GRAP 13.
(c) Correctly Measured Asset; valued in compliance with Grap17.
(d) Documents in support of capital and operational expenditure made in the current financial year are
available and filed.
(e) Short term Insurance; covering the Municipal Assets for the period 2012/2013 financial year.
(f) A commitment Register in compliance with Treasury Regulation SCM 3 of 2004.xx.
(g) A Register of Unauthorised, Irregular or fruitless and Wasteful Expenditure in terms of section 32(1)-
(4).
(h) Plans advanced to keep performance Information kept as portfolio of evidence in CFO’s office.
(i) Inventory in the form of stationery is well packed, and received, kept, issued and recorded in terms
of Grap12.
Challenges Interventions
Supply Chain Management under resourced
and staff undertrained and unfed with latest
regulatory information.
Training session is arranged for Mid
October 2012.
No automated and integrated ordering
system (e-Venus Enterprise Resource &
Planning) module.
To study latest version of e-Venus & check
if an integrated ordering ERP module can
be added on the current system.
No capabilities to identify assets from
operational expenses at source or ordering.
A chart of accounts will be circulated to all
accounting staff to guide accounts allocation
at source.
No library to keep legislation, regulations,
policies and practice notes by all staff.
9
6. LOCAL ECONOMIC DEVELOPMENT AND PLANNING
6.1. Internship Programme for Unemployed Agriculture Graduates
Achievements:
Service- level agreement with two commercial farmers is in place and still with the farmers for
scrutiny before signing. Selection of graduates done and enrolment expected in the third quarter.
Challenges Interventions
None None
6.2. Development of Investment Opportunity brochure and DVD.
Achievements:
Service provider not appointed yet.
Challenges Interventions
Insufficient funds. Proposed in- house execution of the project
6.3. Establishment of an Agrihub.
Achievements:
Concept document in place. Multi- stakeholder task comprising of Department of Agriculture, ARC,
CDM, neibouring municipalities and Commercial and subsistence farmers was established.
Challenges Interventions
Insufficient fund to conduct a feasibility
study.
Department of Agriculture has taken over
the project and a feasibility study is being
conducted.
6.4. Job creation through EPWP and CWP.
Achievements:
1000 CWP participants enrolled in the programme.
Challenges Interventions
None None
Annual SMME Training Programme
10
The financial performance of the municipality for second quarter for financial year 2012/2013:
1.1. REVENUE
The approved budget for 2012/2013 amounts to R162, 939,451 and Actual revenue collected as at 31
December 2012 Amounts to R75,019,649.00(46%) compared to the proportional percentage of 50%.The
45% revenue recognized is based on cash based accounting concept. Collection levels for own revenue
from service charges is considerably low. From July 2012 to December 2012 ,The Municipality billed
R9,759,195.00 and only collected R1,899,757.00 which translates to 19.5% Debtors collection
ratio.,R70,544,392.00 received from grants and subsidies , R1,175,952.00 from licenses and permits,
R57,250.00 from traffic fines, Debt collected amounts to R357,802.51,R889,357.00 from selling prepaid
electricity meters and other revenue amounts to R259,387.00.The Municipality is highly depending on
grants with the percentage of 94% against the total collection of R75,019,649.00.
Description Total
Annual
Budget
Six
Months
budget
Six
months
Actual
Six months
%
expenditure
Variance
from six
months
budget
Reasons for
variance
R
R
R
% R
Revenue By
source
Property
rates
5,599,749 2,799,875 460,021 16 2,339,85
4
Inherent
culture on
non-payment
by ratepayers
Service
Charges-
electricity
revenue
including
selling of
prepaid
electricity
6,661,800
3,330,900
1,676,268
50
1,654,63
2
None
Service
charges-
water
revenue 3,431,157 1,715,578
141,546
8 1,574,03
2
Inherent
culture on
non-payment
by ratepayers
11
Service
charges-
sanitation
revenue
73,183 36,591 64,479
176
(27.888)
Under
budgeted will
be adjusted
during
adjustment
budget
Service
charges-
refuse
revenue 946,972 473,486 87,509
18%
82%
Inherent
culture on
non-payment
by ratepayers
Rental of
facilities and
equipment 126,227 63,113 29,474
47% 53%
Interest
earned-
external
investments 2,000,000 1,000,000 388,984.50
39%
61%
Interest
earned-
outstanding
debtors 2,000,000
1,000,000 137,611
14%
86%
Fines
1,000,000
500,000 57,250
11% 89%
License and
permits 3,710,000 1,855,000 1,175,952
63%
27%
Transfers
recognized-
operational
82,848,00
0 41,424,000 55,662,052
134% -34%
Transfers
recognized-
capital
35,369,98
6 17,684,992 14,882,340
84% 16%
Other
revenue
19,173,00
0 9,586,500 617,190
6%
94%
Total
revenue
(including
capital
transfers )
162,939,9
86 81,469,993
75,380,677
93% 7%
12
1.2. OPERATING EXPENDITURE
The approved budget for 2012/2013 amounts to. R104, 155, 055. Actual expenditure as at 31 December
2012 amounts to R38, 044,424.00. On average 50% of the allocated budget should be spent by the end of
2nd
quarter, The Municipality has only spent 37% on operating expenditure inclusive of staff benefits.
Actual expenditure is as follows:
SUMMARY OF EXPENDITURE PER BUDGET CATEGORY DECEMBER 2012
Description Total
Annual
Budget
Six Monthly
Actual
Six
Months
Actual
Six Months
%
Expenditure
Variance
from six
months
budget
Reason for variance
Salaries And
Allowances
57,981,797
28,990,898 24,052,879
83% 17%
Not all funded posts are
being filled.
Electric
Purchases
6,000,000 3,000,000 3,812,422
127% -27%
Due to increase in tariff
of electricity it was
under budgeted and will
be adjusted in
adjustment budget
General
Expenses 28,736,258 14,368,812 8,588,295
59% 41% None
Repairs and
maintenance 6,328,000 3,164,000 1,298,934
41% 59% None
Interdepartm
ental
Charges 509,000 254,500 291,894
115% -15%
Under budgeted will be
adjusted
Depreciation
4,600,000 2,300,000 0
0%
100%
Depreciation not
updated
GRAND
104,155,055
52,077,527 38,044,424
27%
13
TOTAL 73%
Capital expenditure
Description Total
Annual
Budget
Six Months
Budget
Six
Months
Actual
Six
Months
%
expendi
ture
Varianc
e from
six
months
budget
Reason for variance
Assets from Own
Funds
24,478,686
12,239,343
5,261,761
43%
57%
Most of internally
funded still on
procurement processes
Assets From Grants
And Subsidies
34,004,396
17,002,198
19,576,657
115%
-15%
Most of expenditure is
from Matipana
Madikana which stared
the beginning of
financial year
TOTAL CAPITAL
EXPENDITURE
58,483,082
29,241,541
24,838,418
85%
15%
Payments in respect of Capital Projects funded internally up to 31 December 2012 amounts to R5, 261,761
against six months budget of R12, 239,343.
Payments in respect of capital projects funded by grants up to 31 December 2012 amounts to R19,576,657
against six months budget of R17,002,198
Total payments of capital projects is R24,838,418 as at 31 December 2012 against six months budget of
R29,241,541
DEBTORS
Comprehensive analysis of services debtors
The net outstanding service debtors as at 31 December 2012 amounts to Rand is made up as follows:
Current Debt Amount
30 Days 1,735,673
14
60 Days 1,628,269
90 Days 1,503,537
120+ Days 41,694,786
Plus Journals 0
Sub Total 46,562,265
Less: Credit Amounts 0
Total 46,562,265
The outstanding amount of R46,562,265 is divided as follows:
Category Amount
Government 4,040160
Business 16,322,966
Households 26,199,139
Total 46,562,265
15
16
MUNICIPAL MANAGER’S OFFICE
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achieveme
nt)
Reason for variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditu
re
Rating
To provide assurance to management and council on the internal control, risk management and governance processes
Good Governance
-Approved internal audit strategic audit plans -Approved internal audit reports by the Audit Committee
Perform regulatory, internal control and performance audits as per audit plans
Poor coordination of internal controls
Approved Internal Audit report by the audit committee
Report on PMS and Revenue are done
and awaiting to serve at the
Audit Committee
N/A None 40% None Not Applicable
To implement performance management processes to enhance service delivery
Service Delivery Improvement
-Approved departmental SDBIP’s. -Signed Performance Agreements -Sessions conducted.
Performance Management Coordination.
Improvement on SDBIPs.
Assessment of quarterly reports and compilation of mid-year report. Compilation of the Annual Report
In progress N/A None 50% None Not Applicable
To monitor and evaluate service delivery in line with the SDBIP.
Monitoring and Evaluation
-Quarterly performance progress reports submitted -Quarterly assessments concluded -Completed report and submitted.
Performance Management Monitoring and Evaluation.
M&E need improvement
Monitoring and Evaluation of projects. Ensuring compliance to legislation.
Projects are monitored
and evaluated
by PMU on a weekly
basis.
N/A None 100% None Not Applicable
17
To monitor and evaluate all infrastructure projects within the municipality
PMU % compliance with projects implementation plans.
Improve Project Management System
Non-compliance on Project management
Monitoring & evaluation of projects. Ensuring compliance to specifications
All Service providers
are complying
with specification
s set.
N/A None 100% None Not Applicable
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achieveme
nt)
Reason for variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditu
re
Rating
To monitor and evaluate all infrastructure projects within the municipality
PMU Improved roads & internal Streets within our Municipality
Matipane/Madikana Gravel to Tar road
Most of the roads are flooded and required re-gravelling & tarring(paving)
Road Surfacing
Construction
N/A
NONE 50%
NONE
R10,937,915.00
Improved roads & internal streets within our Municipality
Morebeng internal streets and storm water
Appointment of contractor
Construction Stage
N/A
100%
R4,576,627.92
Improved roads & internal streets within our Municipality
Makgato internal streets and storm water.
Appointment of contractor
Construction Stage
N/A
100%
R6,771,914.88
Improved roads & internal streets within our Municipality
Upgrading Mogwadi Storm Water
Storm water excavations
Construction.
N/A
100%
R533,741.21
Building of Dipateng Pre – Lack of early Construction Constructio None 50% R1,109,37
18
pre schools and community halls
School childhood learning/community halls at 29 settlements.
of pre-schools
n
6.73
Building of pre schools and community halls.
Brussels Pre – School
Lack of early childhood learning/community halls at 29 settlements.
Construction of pre-schools
Construction.
None 30%
R250,036.089
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achieveme
nt)
Reason for variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditu
re
Rating
To enhance corporate identity
Communication -Displays at municipal events. -Municipal events advertised. Different communication medium utilized to reach audiences. -Conducted imbizos and open Council. -Compiled newsletter.
Branding and advertising of municipal events. -Municipal Affairs communication -Compile a news letter
Municipal affairs Communication Strategy need to be reviewed
Compilation of municipal news letter
Is in progress, The newsletter is ready for print
None None 80% None R57 0000.00
To promote and sustain interrelations within the three spheres of government
IGR
Developed comprehensive programme
Developed comprehensive programme
Poor coordination of activities
Implementation of Comprehensive Programme
Corporate diary was developed
N/A None 100% Not Applicable
Not Applicable
To build and encourage stakeholder participation
STAKEHOLDER RELATION
Maximum participation of stakeholders
Public participation meetings.
Minimal participation of stakeholders
Implementation of scheduled participation meetings
IDP process plan and corporate diary was developed
N/A None 100% Not Applicable
Not Applicable
To bring together all relevant stakeholders to advance knowledge
HIV/AIDS Adopted policy
Develop a policy
No HIV/AIDS policy
Development of the draft
Local aids council technical committee
Technical Committee didn’t hold its meeting
Deferred to third quarter
0% 30th March
2013 Not Applicable
19
about the disease was established
To establish comprehensive special focus programmes that will encourage participation and partnerships with all groups
SPECIAL PROGRAMMES
Adopted policy
Develop a policy
No policy on special focus programmes
Development of the draft
Special focus programme technical committee was established
Technical Committee didn’t hold its meeting
Deferred to third quarter
0% 30th March
2013 Not Applicable
COMMUNITY SERVICES
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achieveme
nt)
Reason for
variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditure
Rating
To provide, operate and maintain public amenities to the benefit and satisfaction of communities. .
Public amenities Constructed early
childhood learning
facilities/community halls at
Molemole settlements.
Dipatene & Brussels pre-
schools/ community
halls.
Lack of early childhood
facilities/community halls at
Molemole settlements
Construction of pre-
schools/community halls
Construction at roof level
- - 100% - Dipateng Budget
R2 150 000.00
Expenditure R1 109 376.73
Brussels Budget
R2 150 000.00
Expenditure R250 036.89
Constructed
ablution facilities at
Construction of
ablution facilities at
Lack of ablution
facilities at Mogwadi
Construction of ablution facilities
None
Scarcity of
water in the area.
Outsourc
ing of burial
0%
-
R150 000.00
20
cemetery
Constructed ablution
facilities at cemetery
Mogwadi cemetery
Construction of ablution
facilities at Morebeng cemetery
cemetery
Lack of ablution facilities at Morebeng cemetery
Construction of ablution facilities
None
Scarcity of water
services
Outsourcing of
services per
funeral
0%
-
R150 000.00
Refurbished taxi rank at Morebeng
Refurbishment of Morebeng
taxi rank
Taxi rank not fenced and
malfunctioning ablution facilities.
Advert for appointment of contractor
None Challenges around
illegal structures& traders
in and around the
facility.
Collaborative
efforts with
LEDP & concernedstakeho
lders
0% 31 January
2013
R500 000.00
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achieveme
nt)
Reason for
variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditure
Rating
To provide, operate and maintain public amenities to the benefit and satisfaction of communities. .
Public amenities Renovated Nthabiseng community
hall
Renovation of Nthabiseng community hall
Dilapidated community hall
Advert for appointment of contractor
None Resistance by
Nthabiseng
community
Intervention by
relevant stakehol
ders
0% None R300 000.00
Refurbished Ramokgopa
stadium
Refurbishment of Ramokgopa
stadium
Dilapidated
sporting facility
Advert for
appointment of contractor
Specification developed
and approved,
advert placed.
Bid recommended for re-advert
Specifica
tion committe
e to update for re-advert
0%
31
January 2013
R500 000.00
To comply with relevant environmental legislation
Waste & Environmental Management
Adopted waste by-
laws
By-law processes
No waste by-laws
Solicit reference
documents, customizatio
n & managemen
Consultation/inputs from
relevant stakeholders
- - 80% Awaiting reviewing of by-laws
-
21
t processes
To provide and improve compliance to municipal traffic regulatory environment.
Traffic & Licensing
Adopted traffic by-
laws
By-law processes
No traffic by-laws
No street
trading by-laws
External stakeholders inputs and
public comments
1st draft has been
completed with
additions of new
amendments of the NRTA
Draft document has been forwarded to external stakeholde
rs for inputs
Awaiting inputs from
external stakehol
ders
50% 31 March 2013
-
To coordinate and conduct sports, arts and culture and recreation programmes
Sports, Arts & Culture
Functional Sports &
Recreation Council
Re-election of Sports &
Recreation Council
Poor coordination of Sports, Arts &
Culture
Hosting of Mayor’s
tournament
Cluster committees for Mayor’s tournament
were elected. Preparatory
meetings took place.
Logistical arrangements led to postpone
ment
Resumption of preparations for Mayoral Cup
10% 31 March 2013
R50 000.00
R
To establish a database of RDP housing needs.
Housing Credible waiting list
system
RDP Normalization
Process
No waiting list system for RDP
housing allocation
Physical verification
process
1st phase of
Normalization process has been
completed at Mogwadi
None - 90% - -
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achieveme
nt)
Reason for
variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditure
Rating
To render efficient library services to communities.
Libraries More recent publications on shelves
Procurement of new publications Coordination of mobile library visits.
Outdated publications on shelves.
Updating of shelves with new publications & Mobile library visits
Library shelves have been updated with new publications & 5 mobile library visits took place
None
-
100%
Nov 2012 -
R20 000.00 -
TECHNICAL SERVICES
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achieveme
nt)
Reason for
variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditure
Rating
22
To provide, operate and maintain effective electrical services in order to improve the lives of our people.
Electrical Services.
Compliance with Eskom and SANS 10142 standard.
Upgrading of electrical network(Mogwadi & Morebeng)
Overloaded aging infrastructure
Replace 15 rotten
electrical poles at
Morebeng, Replace MV
& LV conductors
at Morebeng,
Appointed the Service provider to replace 15 rotten poles
and MV & LV conductors
at Morebeng.
Awaiting Eskom’s
shut down date
None 25% n/a R 0
Electrical Services.
Installed Smart Metering System in Mogwadi
Smart Metering System
Overloaded aging infrastructure
450 households
installed with Smart Meters
Advertised, Evaluated and Adjuducated.
Delays in advertisement due to benchmarking with other municipalities
To implement in the
3rd
quarter
0 % n/a R 0
Adequate water supply and maintenance of water & sanitation infrastructure
Water & sanitation
Decrease in number of people without access to water & reduction in water losses
Operate & Maintain water service infrastructure
Un-quantified aging infrastructure
Full implementation on O & M Plan Replace 50 dysfunctional water meters. Maintain 10 borehole pumps and diesel engines. Supply water to 10 specified villages through tankers
Implementation of O & M Plan Replaced 33 dysfunctional water meters Maintained only 13 pumps and engines Supplied water to 18 villages
None Delays in supply of water meters None None
Appointed service provider to supply materials as and when needed.
75%
n/a R 1,256, 899,89
To improve and maintain roads to enable economic growth and
Roads and Stormwater
Improved roads and stormwater
infrastructure
Maintenance and tarring of major roads
383 km of gravel roads
275 km of gravel roads
graded
187.6 km of gravel roads
graded
Mechanical
breakdown on the
Appoint service provider
for
68% n/a R 71,586.08
23
transportation system.
within our municipal area
graders and TLB’s
mechanical
services
FINANCE
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achievement)
Reason for
variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditure
Rating
To ensure efficient and effective budget and reporting in compliance with legislation
Budget & Reporting
Compiled and submitted MFMA section 71 and 72 reports.
Timeous submission of Annual Financial Statements.
Engage all sections to complete their part on AFS processes.
MFMA section 71 and 72 reports compiled and submitted timeously.
AFS submitted after due date
Compilation of 3 credible section 71 reports. Submission of AFS
Compiled 3 section reports AFS submitted 31 August 2012 and re-submitted 31 October 2012.
None
AFS Withdrawn from Auditor General
None
The new appointed consult to assist
to compile credible AFS is on site
100%
50%
None
28 February
2013
0
R400,000.00
To ensure increased revenue generation
Revenue 75% of projected revenue collected
Billing Increase traffic fine collection
Under collection of
revenue
18.75% collection.
3X reminders.
3X Disconnections
1X submission to debt collectors
19.5% debt collection ratio. 6 Reminders sent 1 Disconnection done 3 x submissions to debt collectors
Reminders not sent Disconnections not done
Reminders to be sent monthly Disconnections to be done in November
100%
None 0
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achievement)
Reason for
variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditure
Rating
To ensure efficient payroll administration and timeous payment of trade payables
Expenditure/ Payments
Compile salary & creditors reconciliation
Reduced penalties and
Salary & creditors reconciliation Compilation of a register for section 32
expenditures
No system in place to identify and recognize
irregular expenditure
3X salary & creditors reconciliation
3X Compilation
3 X Salaries & Creditors reconciliation have been prepared 3 X List of relevant tender
None None 100% None None
24
interests for late payments
of a list for all relevant tender supporting documents
documents have been prepared
To procure goods and services according to a system which is fair and competitive.
To safeguard municipal assets.
Supply Chain Management
Safeguarding Municipal Assets
Goods and services procured in terms of the policy.
Asset register updated
Compilation of Bid reports.
Verification
Competitive bidding is circumvented.
Schedule of insured asset.
Prepare a register of tenders awarded.
Invitation for quotations of goods & services
Advertisement of tenders on media.
1X Asset Verification. 1X Updated Inventory List.
Register of awarded tenders have been prepared.
Invitation for quotations process is being performed.
Adverts are being made according to the policy.
None None 100% None None
LOCAL ECONOMIC DEVELOPMENT AND PLANNING
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achieveme
nt)
Reason for variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditure
Rating
To formalize partnership with potential investors and local SMMEs to ensure sustainable economic growth
LED 5 Capacitated Graduates
Internship programme for 5 agricultural graduates.
No programmes
SLA with farmers
SLA available and awaiting signature.
Project in progress, implementation phase
None 30 None 0
Comprehensive brochure &
DVD
Develop brochure on investment
opportunities in the
municipality.
No brochure Appoint service provider
None Advertising process curbed, insufficient funds
Proposed-in
house execution of the project
10 0
25
Established Agric-Hub.
Establishment of Agric-Hub.
Un-coordinated farming activities
Development of
concept document
in consultatio
n with experts
In progress, Insufficient funds to implement the project
Dept. Agriculture to implement the project
10 31 March. 0
Number of EPWP & CWP jobs created.
Job Creation. No specific labour intensive environmental management
project on EPWP
Recruitment of
participants.
1000 participants appointed.
None 100 none 0
25 SMME’s Trained
Annual SMME’s Training
Programme
MoU with LIBSA
Signed MoU with
LIBSA
Delay from LIBSA
regarding signing of the
MoU, Training in progress
Changes in institutional arrangements at LIBSA
Negotiate for
signing of MoU
with interim
leadership
50 31 March 0
Constructed Arts & Crafts
centre.
Construction of Sekwena Arts &
Culture.
100% completed structure
Completion of the project.
Project completed
None None 100 none 0
Strategic Objective
Priority Area Indicator Project/ Programme
Baseline 2012 2nd
Quarter Target
Actual (achieveme
nt)
Reason for variance
Corrective
action
Progress
(% to target)
Revised Target
Budget Expenditure
Rating
To promote orderly development by implementing Integrated Development Planning and Spatial Rationale Principles
Spatial Planning
Installed GIS with e.g. infrastructural maps.
Installation of GIS.
Appointment of service provider.
Service provider appointed.
Project in progress
None None 100 None 0
Updated land use maps.
Reviewing of layout plans.
Appointment of service provider
Service provider
appointed
1st draft
available, subject for discuss & comments
None None 100 None 0
26
CORPORATE SERVICES
Strategic Objective Priority Area Indicator Project/ Programme
Baseline 2012 2nd Quarter Target
Actual (achievement)
Reason for variance
Corrective action
Progress (% to target)
Revised Target
Budget Expenditure
Rating
To ensure provision of sound legal advice, representation, contract, policy development and management are compliant with legislation and standards
Legal services
Number of valid contracts registered in the contract register.
Review of contract Management register and contracts
Contract register in place
25% Contracts are developed for relevant projects in all departments and are updated in the applicable register.
Delays by service
providers and clients
Compile remaining Contracts by consultation relevant departments / institutions
25% Ongoing Budget R 50001 Expenditure R0
To provide reliable, qualitative and efficient administrative support services
Administration
Number of municipal building(s) installed with security surveillance system.
Installation of office security surveillance system
No electronic security surveillance system installed
Appointment of service provider, implementation and monitoring
None. Funds allocated for security surveillance system re-allocated to fund Installation of Access Control system at Mogwadi main office
Defer the project for IDP prioritization and implementation during 2013/2014 financial year.
0% 2013-2014 Budget R 0 Expenditure R 0
Installed Fence at Sekgosese DLTC
Construction of fence at sekgosese DLTC
Current fence damaged
Prepare Specification. Source
None Backlogs in completing outstanding
Specification and appointme
0% 3Rd Quarter Budget R 100 000
27
Service Providers
projects nt to be finalized in the 3rd Quarter
Expenditure R 0
Number of municipal service points / offices installed with functional electronic Access Control system
Electronic Access Control System
Access control system not operational
Appointment of service provider, implementation and monitoring
Service provider has been appointed for supply and installation of Access control system
Procurement process delays
Project implementation to be finalized in the 3rd quarter
60% 3rd quarter. Budget R 400 000 Expenditure R362 604
Number of service points linked through wireless network
ICT wireless network connection
Network Connectivity only available for Mogwadi offices & Mogwadi Traffic Station.
Prepare Specification. Source Service Providers
Feasibility study concluded by COGHSTA and have received the specification report
Inadequate specialized internal technical skills resulting in dependency on expert support from COGHSTA.
Appointment of a service provider to be finalized by February 2013. Project implementation to commence during March 2013 and finalized during June 2013.
100% 4th
Quarter Budget R300 000
Expenditure R0
100%
No of offsite disaster recovery system installed
Installation of ICT Offsite Data Disaster Recovery system
No offsite data disaster recovery system in place
Prepare Specification. Source Service Providers
Feasibility study concluded by COGHSTA and has received the report for customization to municipal unique requireme
Inadequate specialized internal technical skills resulting in dependency on expert support from COGHSTA.
Specification and appointment to be finalized by February 2013 Project implementation to commence during March
50% 4th Quarter
Budget R 500 000 Expenditure R 0
100%
28
nts (specification included).
2013 and finalized during June 2013.
To provide for an accountable & transparent organization that supports council and community interests through effective public participation
Council Support & Secretariat Services
Number of outreach programmes done
Council Outreach Programmes
One Council Outreach Programme held during 2011/2012 FY
1 outreach programme
1. Outreach at Mphakane village 2. Outreach at Mohodi village
None None 100% Budget R70 000.00 Expenditure R0
100%
To implement Human Resource Management services that facilitate development of a workforce that is productive, accountable, stable and foster stakeholder relations
Human Resource Management
Approved HR strategy
Development of HR Strategy
No HR Strategy in place
Appointment of service provider, implementation and monitoring
Advertisement for proposals for organizational re-engineering process developed and procurement process underway
Procurement of provider for the development of HR Strategy put on hold and funds redirected to fund organizational re-engineering project following management decision on the matter.
Reallocate the funds for organizational engineering process
40% 3rd Quarter Budget
R450 000.00 Expenditure R 0