Mid-Rise Wood Frame: An Architect’s Perspective · Vivek A. Menon Architect AIBC, MAA, MRAIC,...
Transcript of Mid-Rise Wood Frame: An Architect’s Perspective · Vivek A. Menon Architect AIBC, MAA, MRAIC,...
Vivek A. Menon
Architect AIBC, MAA, MRAIC, LEED AP BD + C
JM Architecture Inc.
Mid-Rise Wood Frame:
An Architect’s Perspective
©2015 JM Architecture Inc. 1
Group C - Residential
1 storey
9 000 m2
2 storeys
4 500 m2
3 storeys
3 000 m2
4 storeys
2 250 m2
5 storeys
1 800 m2
6 storeys
1 500 m2
ABC2015
BCBC 2012
1 storey
7 200 m2
2 storeys
3 600 m2
3 storeys
2 400 m2
4 storeys
1 800 m2
5 storeys - 7200 m2
4 storeys - 9000 m2
3 storeys - 12 000 m2
1&2 storeys - Unlimited
6 storeys 6000 m2
NCC
5 storeys 6 storeys 1 440 m2 1 200 m2
©2015 JM Architecture Inc. 2
Mixed Uses Major Occupancies - Group C
Not permitted: • Group A, Divisions 1 and 3 • Group B • Group F, Divisions 1 and 2
©2015 JM Architecture Inc. 3
Mixed Uses Major Occupancies - Group C
Permitted on 1st and 2nd storey: •Group A, Division 2 •Group D & Group E •Group F, Division 3 (also permitted on 3rd storey)
• Increased fire-resistance rating for separation between some major occupancies
©2015 JM Architecture Inc. 4
Height Limit
Limit height of uppermost floor level to 18 m above 1st floor.
≤ 18 m
©2015 JM Architecture Inc. 5
Additional Requirements Sprinklers: • NFPA 13 required, as well as additional sprinklering of exterior balconies (balconies or decks exceeding 610 mm)
Cladding: • noncombustible cladding, or • cladding which passes the requirements when tested in
accordance with CAN/ULC-S134 “Standard Method of Fire Test of Exterior Wall Assemblies”
Roofing: • Roofs >25m above 1st floor require
• Non-combustible construction, or • Fire retardant treated wood
©2015 JM Architecture Inc. 6
Project Started 2008
Phase 3 Completed 2013
Case Study:
Library Square, Kamloops BC
©2015 JM Architecture Inc. 7
Owners: Thompson Nicola Regional District – North Shore Library
Total Concept Developments + TriCity Contracting (BC) Ltd. ©2015 JM Architecture Inc. 8
Phase 3 under construction - 2013
©2015 JM Architecture Inc. 9
LIBRARY SQUARE KAMLOOPS, BC
A mixed use development born from • A need to increase library space • A goal to infuse energy into sleepy
commercial district • A desire to create a responsible project using
a P3-Design/Build contract and • To showcase a model project to other
developers The Program brief called for three distinct users: • 1,900 sm Community Library • 1,500 sm Retail Space • 151 Residential Dwelling Units
©2015 JM Architecture Inc. 10
Kamloops, BC Climate: Semi-Arid Ann. Rain: 225mm Moisture Index: 0.23 Seismic Zone: Low
Climate: Oceanic Ann. Rain: 1,325mm Moisture Index: 1.14 Seismic Zone: High
Metro Vancouver
©2015 JM Architecture Inc. 11
Location Map
PROJECT SITE
CITY CENTER
North Shore Map & Project Site
1. Old Library Site
2. New Library Site
3. Tranquille Rd: North Shore Commercial District
Facts:
Population - +/- 85,000
3
2
1
Project Site Photo ©2015 JM Architecture Inc. 12
< 2004 – School Site – Private School
• 20, 407m2 – Subdivided to three
parcels • 5,378m2 Lib Sq • 7,300m2 overall
< 2012 – Urban Village – Hotel – Library – Residences – Offices – Commercial
Mixed Use
©2015 JM Architecture Inc. 13
The Project Team • Developer:
• Total Concepts Development Casey VanDongen • TriCity Contracting (BC) Ltd. Casey VanDongen
• Owners:
– Thompson Nicola Regional District - Library Sukh Gill – TriCity Contracting (BC) Ltd. – remainder Casey VanDongen
• Design Team:
– Architecture: JM Architecture Inc Joe Minten, Maibc – Fire Engineering + GHL Consultants Gary Chen, P.Eng Code Consultant: – Structural: Siefken Engineering Ltd John Siefken, P.Eng – Mechanical: Perez Engineering Ltd Willie Perez, P.Eng – Electrical: Falcon Engineering Ltd Bruce Candline, P.Eng – Landscape: Sustainable Systems Gary Dewhurst, B.L.A.
• Authority Having Jurisdiction: – City of Kamloops Bruce Barclay, RBO
©2015 JM Architecture Inc. 14
Total Concept Developments • A successful company focusing on the
development and construction of commercial projects since 1981
• Complimentary arm is Tri City Contracting (BC) Ltd.
– Design – Build – Full Service + Turn Key
• Open to exploring new concepts of development and construction they do not shy from the unknown
• Keen to meet the needs of the customer
©2015 JM Architecture Inc. 15
JM Architecture Inc • Small size firm with 10 staff and 1 principal • Diverse group consisting of
– 3 registered architects – 1 planner – 2 Architectural Intern – 1 interior designer – 3 technologist – 1 administrator
• Housing centric – hotels, residential care, multi-family residential & commercial
• Mostly mixed use projects • Service in British Columbia, Alberta and Manitoba
©2015 JM Architecture Inc. 16
AIBC Firm Breakout
©2015 JM Architecture Inc. 17
Library Square - timeline Sept 2007
•TNRD published an EOI for the project
October 2007 •Submission due
November 2007 •Total Concept Developments awarded project
November 2007-July 2008
•Design Development
July 2008
•Issued for Development Permit •BC government is reviewing option of mid-rise wood frame in BC Building Code •Project is currently considered 6 storey non-combustible with steel stud framing.
September 2008
•Reconsider Project for potential wood frame option
October 2008 •Commissioned GHL to join project team as fire engineering and code consultant.
©2015 JM Architecture Inc. 18
November 2008
• Submit Phase 1 construction permit: Concrete only
April 2009
• Full permit submission Phase 1 • Construction begins • BC changes Building Code to allow Combustible construction up to 6 storeys
July 2010 • Permit submission Phase 2
August 2012
• Permit Submission Phase 3
©2015 JM Architecture Inc. 19
Architecture + Community • City Planning Issues in 2008
– Development of the North Shore Neighbourhood Plan using performance-based zoning to:
• reinvigorate the business areas • Increase density especially along the arterial routes • provide a new benchmark for development with a
focus on Sustainability, Urban Design and Environmental Responsibility
• Crime Prevention Through Environmental Design • Incentives initiatives $$$$$$$
– Taxation exemption – Parking relaxations – Reductions on DCC
©2015 JM Architecture Inc. 20
Kamloops Incentives
- 60% Tax Excemption
- Some DCC Reductions
-10% Parking Reduction
- Priority Processing
©2015 JM Architecture Inc. 21
– remember this is 2008 : downturn in the economy
– Adherence to the Tranquille Rd. Design Guidelines
• Form and Character Guidelines • Materials • Called for traditional or historical references
Unrelated but important nonetheless
– Hotel Owner required view corridor
©2015 JM Architecture Inc. 22
• Development Opportunities From the Client the mandate is simple – Maximize unit count and provide the best design for
marketability • Profit - $$$$$ - is the goal • Good design is the driver • Efficient construction is the means
• Architectural Opportunities From the architect – Maximize Design Integrity
• Form & Character • Pedestrian scale • Material and Colour Choice
©2015 JM Architecture Inc. 23
Construction Matters
• Pre-April 2009 • Concrete or Steel or • Mixed
– Concrete + Steel • Post-April 2009 • Wood was added as an option
BCBC Requirements: • 6 storey Assembly Use – 3.2.2.24
– A2 - requires noncombustible • 6 storey Retail Use – 3.2.2.57
– E - requires noncombustible • 6 storey Residential Use – 3.2.2.45
– C - permits combustible • Basement Storage Garage – 3.2.2.79
– F3 – requires noncombustible
Library Square is 5 + 1 Project
©2015 JM Architecture Inc. 24
BCBC 2006 condensed version …..
Fire Rated Separations: • A2 to E = 2 Hr FRR • A2 to C = 1 Hr FRR • E to C = 2 Hr FRR • F3 to A2 + E – 1 1/2 Hr FRR • Sprinkler System throughout • Group C max BA = 1200sm
– Introduce firewalls • 2 Hr & 4 Hr with both F &T ratings
– Level 2 exceeded this value • GHL assisted in obtaining approval
from the AHJ to increase the value slightly to over the 1200sm
©2015 JM Architecture Inc. 25
Project Schematic
©2015 JM Architecture Inc. 26
BCBC continued ...
• 4 storey to 6 storey: – Based on a maximum 7200sm
Floor Area – The Building Area reduces
4 Storey = 1800sm 5 Storey = 1440sm 6 Storey = 1200sm – Same amount of wood framing
regardless of # of storeys
BCBC items not addressed • Firewall (FW) construction • Fire stopping through FW
©2015 JM Architecture Inc. 27
BCBC continued ... • Firewalls are 2 Hr FRR area separation
walls tested to ULC ratings – W312 – 2” of Gypsum Board (2Hr FRR) – Sandwiched between wood frame
assemblies on either side – Tied together with fusible (slotted) alum.
Angle
Also note … • Elevator Shafts are constructed of wood
framing to a 1 Hr FRR vertical shaft
• All wood framing is constructed off-site in a controlled environment with a > 12% Moisture Content and assembled on-site
©2015 JM Architecture Inc. 28
2nd FLOOR PLAN – Firewall Plan
©2015 JM Architecture Inc. 29
Area Separation Wall - FIREWALL
©2015 JM Architecture Inc. 30
©2015 JM Architecture Inc. 31
Firewall Photos We didn’t always get it right the 1st time
©2015 JM Architecture Inc. 32
Firewall Photos With the help of GHL we did
better Concerns related to heat
transfer resulted in heat sink detail using concrete board
©2015 JM Architecture Inc. 33
Construction Photos
©2015 JM Architecture Inc. 34
Construction Photos
Certified to LEED CI Gold
©2015 JM Architecture Inc. 35
Phase 3
©2015 JM Architecture Inc. 36
Code Compliance + Alternate Solutions GHL Consultants provided both fire engineering and code
compliance reviews through reports and alternate solution or engineering judgments
1. General compliance to the new 2006 code changes 2. Firewall noncompliance and solution to meet the equivalent criteria
1. Horizontal firewall design and vertical firewall design 2. Engineering judgments for penetrations
3. Fire protection to meet NFPA 13 as well as alternate means to provide equivalent protection where it could not do so
4. Air space subdivision interpretation as this related to building code.
©2015 JM Architecture Inc. 37
©2015 JM Architecture Inc. 38
Structural Considerations: Wood Shrinkage: • Possibly up to 2” over 6 storeys, Minimized by using engineered products with low
moisture content. – Managed with self tapping shrinkage compensators located at each end of the shear
walls, Located 4th and 6th floor
©2015 JM Architecture Inc. 39
Structural Considerations:
• The difference from 4 to 6 storey in this location was an added 10% design criteria – not too much of a concern but translated to long and more shear walls with added fastening and providing a safer building as well – Added marginally to overall costs
Seismic Design: Kamloops low
©2015 JM Architecture Inc. 40
Structural Considerations: Seismic con’t… • metal flat plates were used across the firewall to maintain
uniformity of building movement in an earthquake event. These are the plates the needed to have the heat sink detail added.
Elevator Design: • To maintain even shrinkage throughout the shaft was designed
similar to a traditional laminated timber design; in this case a 2X6 frame at 12” OC with ¾” plywood liner and gypsum board facing to achieve the 1.0 Hr FRR
Note: APEGBC Technical and Practice Bulletin produced in April 2009 as part of the provincial research and development into 5 – 6 storey wood frame buildings
©2015 JM Architecture Inc. 41
Developer Comments Challenges: • Market Acceptance unknown at the start • Insurance and temporary fire protection difficult to obtain • Concerns regarding shrinkage • Reluctance for initial approval from the city building and fire
departments
Economics: 1. Land use – compared to 4 storey the 6 storey option provides
50% increase in yield 2. Non-combustible option for same building would cost up to
30% more 3. Support to wood industry is sound investment in BC economy
©2015 JM Architecture Inc. 42
Developer Comments con’t… 4. Trade availability is important consideration and easy to get 5. Wiring option saves costs 6. Shorter delivery time than non-combustible construction – get
to market sooner less carrying costs and insurance costs 7. Back to the marketing aspect – prices for upper units pay
more and the spread is quite noticeable from 2 – 6 floors
Fire Protection during construction: 1. Important to activate sprinklers as early as possible into the
construction of wood frame regardless of difficulties for the trades
2. Provide 24 hour diligent security monitoring 3. Install fire doors as soon as possible 4. Retain excellent communications with the fire department
©2015 JM Architecture Inc. 43
On the Boards…
ASAS Condominium, Surrey BC Construction Starting September 2015
©2015 JM Architecture Inc. 44
ASAS Condominium, Surrey BC Construction Starting September 2015
©2015 JM Architecture Inc. 45
ASAS Condominium, Surrey BC Construction Starting September 2015
©2015 JM Architecture Inc. 46
ASAS Condominium, Surrey BC Construction Starting September 2015
©2015 JM Architecture Inc. 47
ASAS Condominium, Surrey BC Construction Starting September 2015
©2015 JM Architecture Inc. 48
Marquess of Lorne, Kamloops BC
©2015 JM Architecture Inc. 49
Marquess of Lorne, Kamloops BC
©2015 JM Architecture Inc. 50
Marquess of Lorne, Kamloops BC
©2015 JM Architecture Inc. 51
Items to Consider 1. Keep an open mind to new ideas and new
methods of construction that come from a very diverse group of interested stakeholders
2. Alert the manufacturing industries to come to terms with this new code provision and thereby address items such as firewall construction and fire stopping methods
3. As designers, engineers and inspectors - we have to try to stay in tune with the constantly growing volume of knowledge bases that affect the wood industry and this building type
4. Accept this is a building with a huge fire load in its early stages and precautions need to be addressed as much as possible to protect it from fire which can affect human safety and cause significant damage to neighbouring structures.
5. Parking!!!! OPPORTUNITIES 1. $$ Construction Cost Savings
1. Material Costs 2. Speed of Construction
2. Explore new forms of wood construction are on the horizon – such as cross laminated timber to produce even taller wood buildings
©2015 JM Architecture Inc. 52
Thank You
©2015 JM Architecture Inc. 53