Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River...

90
December 2017 MID-PACIFIC CONSTRUCTION OFFICE Willows, California Construction Progress Report L-29

Transcript of Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River...

Page 1: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

December 2017

MID-PACIFIC CONSTRUCTION OFFICE Willows, California

Construction Progress Report L-29

Page 2: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

(This Page Intentionally Left Blank)

Page 3: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

CONSTRUCTION PROGRESS REPORT (L-29) MID-PACIFIC CONSTRUCTION OFFICE MID-PACIFIC REGION December 2017

TABLE OF CONTENTS TITLE PAGE LOCATION MAP i STAFFING ii GLOSSARY OF TERMS iii CONTRACT/SPECS OR P.O. NO., CONTRACTOR, AND CONTRACT NAME PAGE MAP NO. NO. Central California Area Office 1 R10PC20019 20-C0689 Andritz Hydro 3 1 Folsom Power Plant Generators U1, U2, and U3 Rewind and Excitation System Replacement – Folsom Unit, American River Division, Central Valley Project, California

R14PC00096 20-C0816 Alltech Engineering Corporation 4 1

Nimbus Dam Radial Gate Repairs, Phase III - Nimbus Dam, American River Division,

Central Valley Project, California

R16PC00075 20-C0838 Cal Electro, Inc. 5 1

Folsom UHA Switchgear Replacement – Folsom Unit, American River Division,

Central Valley Project, California

R16PC00113 20-C0858 Sapper West, Inc. 7 1

Folsom Dam Municipal and Industrial Temperature Control Device Safety Measures -

Folsom Unit, American River Division, Central Valley Project, California

R17PC00100 None Harrison Western Construction Corporation 12 1

Folsom Dam Auxiliary Spillway American River Phase V – Right Bank Stabilization,

Folsom Unit, American River Division, Central Valley Project, California

R17PC00139 None Site Work Solutions Inc. 19 1

Folsom Aggregate Structure Demolition, Removal & Disposal - Folsom Unit,

American River Division, Central Valley Project, California

Klamath Basin Area Office 23

R17PC00083 None Coleman Environmental Engineering, Inc. 25 2

Tule Lake Road Improvement Phase 2- Klamath Project, Oregon - California

Lahontan Basin Area Office 31

R16PC00062 20-C0850 NW Constructors, Inc. 33 3

Stampede Dam, Dam Safety Modifications - Stampede Division, Washoe Project,

Nevada-California

Page 4: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

(This Page Intentionally Left Blank)

Page 5: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

R17PC00063 20-C0860 Diana Prince Construction, Inc. 34 4

Marble Bluff Dam and Fish Passage Facility Radial Gate Rehabilitation – Washoe Project,

Nevada-California

R17PC00067 None Sentinel Builders LLC 36 5

Lahontan Dam Rated Vehicle Barrier System - Lahontan Basin Area Office,

Newlands Project, Fallon, Nevada

Northern California Area Office 37 R15PC00089 20-C0831 Contractor Services Group, Inc. 39 7

Intake 3 Screen Extension, Coleman National Fish Hatchery - Shasta Division, Central Valley

Project, California

R16PC00006 20-C0841 Voith Hydro, Inc. 40 6

Trinity Powerplant Generator Rewinds - Trinity River Division, Central Valley Project,

California

R17PC00029 20-C0847 Gardner Zemke 46 6

Trinity River Division Powerplants Replacement of Station Service Transformers

and Low Voltage Bus System – Trinity River Division, Central Valley Project, California

R16PC00134 20-C0852 BCI Construction USA, Inc. 47 8

Whiskeytown Lake, Spring Creek Temperature Control Curtain - Trinity River Division,

Central Valley Project, California

R17PC00103 20-C0866 Air-O-Service 48 6

Keswick & Shasta Powerplant Weldshop Ventilation System Procurement & Installation –

Shasta and Keswick Powerplant - Central Valley Project, California

R17PC00091 20-C0869 Tompco-Triton 49 7

Intake 3 Trash Rake, Coleman National Fish Hatchery, Shasta Division, Central Valley Project,

California

R17PC00092 None Purgatory Fence Company, Inc. 50 6

Install K12 Rated Vehicle Barriers at Keswick, Shasta and Trinity Power Plants

Shasta and Trinity Division, Central Valley Project, California

South-Central California Area Office 51

San Joaquin River Restoration Program 55

Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial Contractors, Inc. 61 9

North Fork Screens and Ladders Completion Contract - Battle Creek Salmon and

Steelhead Restoration Project, California

Page 6: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

(This Page Intentionally Left Blank)

Page 7: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

Contracts in Warranty Status 67

R11PC20185 20-C0778 69 Tracy 13.8kV Switchgear/Breaker Replacement – Tracy Pumping Plant and Substation, Delta Division, Central Valley Project, California

R13PC20159 20-C0819 GD Nielson Construction, Inc. 69

Lake Berryessa Concessions Areas Improvements – Lake Berryessa, Solano Project,

California

R16PC00079 20-C0851 E.C. Smith, Inc. 69

Red Bluff Flap Gate Retrofit - Sacramento Canals Unit, Sacramento River Division,

Central Valley Project, California

R17PC00022 20-C0857 Salter and Sons Construction 69

Western Tracy Switchyard, Chain Link Fence Project - Tracy Pumping Plant and Substation,

Delta Division, Central Valley Project, California

R11PC2023S None Tehama Environmental Solutions, Inc. 69

Red Bluff Diversion Dam, Fish Passage Improvement Project Terrestrial Mitigation,

Sacramento River Division, Central Valley Project, California

R16PC00099 None Chigosi Company 69

Folsom Resource Building – Folsom Unit, American River Division,

Central Valley Project, California

R16PC00100 None Construction Solutions Group, LLC 69

Lake Woollomes Recreation Area Asphalt Replacement - Central Valley Project, California

R15PC00080 20-C0836 Andrews Contracting Services, LLC 69

Klamath Basin Area Office Sewer Lift Station - Klamath Basin Area Office, Klamath Falls,

Oregon

R16PC00111 20-C0855 BCI Construction USA, Inc. 69

San Joaquin Hatchery Water Supply Pipeline – San Joaquin River Restoration Program,

Friant Division, Central Valley Project, California

R16PC00110 20-C0853 BCI Construction USA, Inc. 70

Madera Canal Headworks Low-Flow Valve – San Joaquin River Restoration Program,

Friant Division, Central Valley Project, California

Lab Reports 71

Stampede Safety of Dams Project Lab Reports 73

North Fork Screens and Ladders Completion Contract Lab Reports 75

Page 8: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

(This Page Intentionally Left Blank)

Page 9: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

i

Areas in the Mid-Pacific Region Where Work was Performed

4

5 3

7

2

9

1

6 8

Page 10: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

(This Page Intentionally Left Blank)

Page 11: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

ii

STAFFING MID-PACIFIC CONSTRUCTION OFFICE

The Mid-Pacific Construction Office had 32 construction and administrative employees at the close of this month as follows: Construction Engineer's Office 1 Preaward and Project Management Group 3 Administrative Management 4 Division of Field Engineering 17 Division of Office Engineering 4 Materials Lab Branch 3

Page 12: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

(This Page Intentionally Left Blank)

Page 13: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

iii

GLOSSARY ACRONYMS AND ABBREVIATIONS

ACRONYM MEANING CCAO Central California Area Office CVP Central Valley Project KBAO Klamath Basin Area Office LBAO Lahontan Basin Area Office MP Mid-Pacific Regional Office MPCO Mid-Pacific Construction Office NCAO Northern California Area Office SCCAO South Central California Area Office SJRRP San Joaquin River Restoration Program TO Tracy Office

Page 14: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

(This Page Intentionally Left Blank)

Page 15: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

1 | P a g e

Central California Area Office

Page 16: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

2 | P a g e

(This Page Intentionally Left Blank)

Page 17: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

3 | P a g e

Contract No. R10PC20019 Specification No. 20-C0689 Folsom Power Plant Generators U1, U2, and U3 Rewind and Excitation System Replacement - Folsom Unit, American River Division, Central Valley Project, California Andritz Hydro, Charlotte, NC

Work Performed December 0.0%

Time Elapsed 100.0%

Work Completed 100.0%

Contractor Earnings December $0.00

Previous $20,610,792.74

Total to Date $20,610,792.74

MPCO Noncontract Costs 1st Quarter Expenditures $12,328.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $12,328.00

FY18 Budgeted $25,680.00

Amount Remaining $13,352.00

Percent Remaining 51.99%

Area Office Project Management Project Manager: Jonathan Rogado, MP-250

Office Engineering Contract Administrator: Larry Bowman, MPCO-240

Before contract completion the following work will be performed:

Acceptance testing for Unit 3.

Remaining warranty inspections for Units 1, 2, and 3.

Final submittals (including As-built Drawings and O&M Manuals).

Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310

Construction Representative: Todd Dooley, MPCO-314.

Number of Contractor Employees: 1

Work Performed No onsite work was performed during this period.

Page 18: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

4 | P a g e

Contract No. R14PC00096 Specification No. 20-C0816 Nimbus Dam Radial Gate Repairs, Phase III – Nimbus Dam, American River Division, Central Valley Project, California Alltech Engineering Corporation, Mendota Heights, MN

Work Performed December 2.1%

Time Elapsed 58.0%

Work Completed 62.9%

Contractor Earnings December $358,576.85

Previous $10,556,025.46

Total to Date $10,914,602.31

MPCO Noncontract Costs 1st Quarter Expenditures $68,661.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $68,661.00

FY18 Budgeted $377,180.00

Amount Remaining $308,519.00

Percent Remaining 81.80%

Area Office Project Management Project Manager: Jonathan Rogado, CC-611

Office Engineering Contract Administrator: Larry Bowman, MPCO-240

Invoice number 29 was received this reporting period, in the amount of $358,576.85, for work

performed from November 1, 2017 to November 30, 2017.

Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310

Construction Representative: Michael Manlick, MPCO-313

Number of Contractor Employees: 14

Work Performed No onsite work was performed during this period.

Page 19: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

5 | P a g e

Contract No. R16PC00075 Specification No. 20-C0838 Folsom UHA Switchgear Replacement – Folsom Unit, American River Division, Central Valley Project, California Cal Electro, Inc., Redding, CA

Work Performed December 0.0%

Time Elapsed 100%

Work Completed 84.5%

Contractor Earnings December $0.00

Previous $2,996,939.22

Total to Date $2,996,939.22

MPCO Noncontract Costs 1st Quarter Expenditures $46,805.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $46,805.00

FY18 Budgeted $57,060.00

Amount Remaining $10,255.00

Percent Remaining 17.97%

Area Office Project Management Project Manager: Vanhue Ly, CC-614

Office Engineering Contract Administrator: Larry Bowman, MPCO-240

Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310

Construction Representative: Sean Frische, MPCO-317

Number of Contractor Employees: 4

Work Performed Installation of new switchgear (UHA) completed. All punch list items have been addressed.

Formal training has not yet been rescheduled. Contractor has completed demobilization and

final site cleanup.

Page 20: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

6 | P a g e

Syblon Reid performed the final work on the safety door and hatch, drilling and epoxy-setting an

eye-bolt into the concrete wall. This will be used to latch the hatch in the open position when

accessing the upper ladder.

The clamps securing the grating onto the platform frame had been ordered incorrectly (for 2-inch

deep grates). With the correct 1-inch clamps obtained, Syblon-Reid installed them on each of the

two grates, securely attaching them to the platform frames.

Wire Rope

Syblon-Reid completed the wire rope installation that was started November 30, 2017. The

existing bolts used to temporarily hold the new rope clamps on the drum were replaced with the

correctly sized, new bolts. The bolts were torqued to the manufacturer’s recommended 360 ft. lbs.

The rope drum was operated to tension the new cables and the gate was raised to its original full-

up position, releasing the tension on the temporary rigging which was then removed.

The mechanical counter was reset to 422.4 simultaneously with resetting the electronic counter to

422.1. CCAO’s operator then reinstalled the drive sprocket and belt that operates the upper and

lower limit switch component. The gate was then lowered to the bottom limit, and then cycled to

the upper limit.

The bonnet was reset over the rope drum, where workers re-bolted it into place.

Coatings

Mason Painting applied an epoxy coating to the maintenance pad eyes, including the welded

connection between the maintenance pad eyes and the control gate. Using a Bristol Blaster, he

prepared the bare steel surfaces on the maintenance pad eyes. He also performed two surface

profile tests and checked environmental conditions prior to applying coatings.

After a 24-hour cure of the epoxy coating, Mason Painting applied the UV Resistant Polyurethane

top coat to the new maintenance pad eyes. It took only a few minutes to hand-brush the coating

on each of the two new maintenance pad eyes. The material is very thin; and it was applied with

a wet thickness that will cure to a dry thickness of 2 mils or better.

Syblon Reid marked damaged galvanized surfaces in the galvanized ladders, cages, landings, and

railings. Mason Painting then prepared these surfaces for re-coating with sand paper and thinner.

A single coat of AllPro 11106 Cold Galvanizing was then spray-applied to prepared surfaces.

Page 21: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

7 | P a g e

;Contract No. R16PC00113 Specification No. 20-C0858 Folsom Dam Municipal and Industrial Temperature Control Device Safety Measures, Folsom Unit, American River Division, Central Valley Project, California Sapper West, Inc., Sacramento, CA

Work Performed December 0%

Time Elapsed 100%

Work Completed 21%

Contractor Earnings December $0.00

Previous $63,021.24

Total to Date $63,021.24

MPCO Noncontract Costs 1st Quarter Expenditures $17,481.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $17,481.00

FY18 Budgeted $64,670.00

Amount Remaining $47,189.00

Percent Remaining 72.97%

Area Office Project Management Project Manager: Brian Zewe, CC-612

Office Engineering Contract Manager: Kent Perkes, MPCO-225

The work was substantially complete as of December 12, 2017.

The work was transferred to the Bureau of Reclamation Central California Area Office for

operation and maintenance as of December 14, 2017.

The period of performance ended December 29, 2017.

Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310

Construction Representative: Michael Manlick, MPCO-312

Number of Contractor Employees: 6

Work Performed

Page 22: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

8 | P a g e

The substantial completion walk-through/inspection was conducted on December 12, 2017. Aside

from a small punch-list, CCAO and MPCO personnel agreed that the project was substantially

complete as of this day.

The project was inspected and transferred to the Central California Area Office for operation and

maintenance on December 14, 2017.

Miscellaneous Metals

Syblon Reid performed the final work on the safety door and hatch, drilling and epoxy-setting an

eye-bolt into the concrete wall. This will be used to latch the hatch in the open position when

accessing the upper ladder.

The clamps securing the grating onto the platform frame had been ordered incorrectly (for 2-inch

deep grates). With the correct 1-inch clamps obtained, Syblon-Reid installed them on each of the

two grates, securely attaching them to the platform frames.

Wire Rope

Syblon-Reid completed the wire rope installation that was started November 30, 2017. The

existing bolts used to temporarily hold the new rope clamps on the drum were replaced with the

correctly sized, new bolts. The bolts were torqued to the manufacturer’s recommended 360 ft. lbs.

The rope drum was operated to tension the new cables and the gate was raised to its original full-

up position, releasing the tension on the temporary rigging which was then removed.

The mechanical counter was reset to 422.4 simultaneously with resetting the electronic counter to

422.1. CCAO’s operator then reinstalled the drive sprocket and belt that operates the upper and

lower limit switch component. The gate was then lowered to the bottom limit, and then cycled to

the upper limit.

The bonnet was reset over the rope drum, where workers re-bolted it into place.

Coatings

Mason Painting applied an epoxy coating to the maintenance pad eyes, including the welded

connection between the maintenance pad eyes and the control gate. Using a Bristol Blaster, he

prepared the bare steel surfaces on the maintenance pad eyes. He also performed two surface

profile tests and checked environmental conditions prior to applying coatings.

After a 24-hour cure of the epoxy coating, Mason Painting applied the UV Resistant Polyurethane

top coat to the new maintenance pad eyes. It took only a few minutes to hand-brush the coating

on each of the two new maintenance pad eyes. The material is very thin; and it was applied with

a wet thickness that will cure to a dry thickness of 2 mils or better.

Syblon Reid marked damaged galvanized surfaces in the galvanized ladders, cages, landings, and

railings. Mason Painting then prepared these surfaces for re-coating with sand paper and thinner.

A single coat of AllPro 11106 Cold Galvanizing was then spray-applied to prepared surfaces

Page 23: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

9 | P a g e

The workers are torqueing the rope clamp bolts to 360 foot-pounds.

Page 24: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

10 | P a g e

The worker is injecting epoxy into a predrilled hole to set the ladder hatch latch

eye bolt.

Page 25: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

11 | P a g e

The crane resets the protective bonnet over the gate hoist’s rope drum.

Page 26: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

12 | P a g e

Contract No. R17PC00100 Specification No. None Folsom Dam Auxiliary Spillway American River Phase V – Right Bank Stabilization, Folsom Unit, American River Division, Central Valley Project, California Harrison Western Construction Corporation, Lakewood, CO

Work Performed December 44.5%

Time Elapsed 87%

Work Completed 66.5%

Contractor Earnings December $596,600.00

Previous $289,500.00

Total to Date $886,100.00

MPCO Noncontract Costs 1st Quarter Expenditures $106,860.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $106,860.00

FY18 Budgeted $179,160.00

Amount Remaining $72,300.00

Percent Remaining 40.35%

Area Office Project Management Project Manager: Kyle Keer, CC-108

Office Engineering Contract Manager: Kent Perkes, MPCO-225

Invoice No. 3, received December 13, 2017, in the amount of $596,600.00, for work performed

through December 10, 2017.

The work was substantially completed as of December 8, 2017.

Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310

Construction Representative: Ben Richburg, MPCO-318

Number of Contractor Employees: 11

Work Performed De-mobilization

Page 27: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

13 | P a g e

Contractor completed demobilization offsite, removing project equipment/materials necessary to

complete field activities. The contractors’ main staging and auxiliary staging areas were

restored. The 330 ton Liebherr Crane was safely removed offsite. Environmental and

Hazardous Energy Control Programs were terminated with dam releases monitored. All contract

personnel returned CCAO security badges. An environmental assessment of the main staging

area was performed.

Stressing Installed Rock Bolts

The Contractor completed grouting of all rock bolts. The contractor successfully stressed all

rock bolts and completed the bolt disposition with grouted and bolted rock bolt caps.

Concrete Entrants

The contractor repaired concrete surfaces and voids.

Concrete strength testing successfully met contract requirements.

Page 28: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

14 | P a g e

Testing rock bolts

Page 29: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

15 | P a g e

Concrete repair at the bottom of entrant 1

Page 30: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

16 | P a g e

Concrete repair at the bottom of entrant 3

Page 31: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

17 | P a g e

Finished rock bolts

Page 32: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

18 | P a g e

Completed Right Bank Stabilization Project before crane removal

Page 33: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

19 | P a g e

Contract No. R17PC00139 Specification No. None Folsom Aggregate Structure Demolition, Removal & Disposal - Folsom Unit, American River Division, Central Valley Project, California Site Work Solutions Inc., Redding, CA

Work Performed December 13.5%

Time Elapsed 100.0%

Work Completed 100.0%

Contractor Earnings December $0.00

Previous $349,221.55

Total to Date $349,221.55

MPCO Noncontract Costs 1st Quarter Expenditures $54,422.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $54,422.00

FY18 Budgeted $64,800.00

Amount Remaining $10,378.00

Percent Remaining 16.02%

Area Office Project Management Project Manager: Mark Lewis, CC-641

Office Engineering Contract Manager: Madelyn Giles, MPCO-230

Field Engineering Construction Manager: Reynaldo Garcia, MPCO-310

Construction Representative: Sean Frische, MPCO-317

Number of Contractor Employees: 6

Work Performed The remaining concrete debris was removed from the site this month to a local recycling facility.

The Contractor completed placing and compacting fill on the slope where the concrete aggregate

processing structure was previously located. Quality assurance and quality control soil testing

confirmed adequate compaction on the slope. The Contractor tracked walked the entire

Page 34: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

20 | P a g e

embankment prior to applying a coating of hydro-seed with fertilizer, mulch, and tackifier. The

entire embankment was then covered with a straw erosion control blankets with fiber rolls

installed on top of the blankets. Site restoration and installation of final BMPs was completed

this month. The Contractor began and completed demobilization this shift.

Page 35: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

21 | P a g e

Photo of Contractor installing the straw erosion control blankets on the hydro-

seeded embankment.

Page 36: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

22 | P a g e

(This Page Intentionally Left Blank)

Page 37: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

23 | P a g e

Klamath Basin Area Office

Page 38: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

24 | P a g e

(This Page Intentionally Left Blank)

Page 39: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

25 | P a g e

Contract No. R17PC00083 Specification No. None Tule Lake Road Improvement Phase 2- Klamath Project, Oregon - California Coleman Environmental Engineering, Inc., Upper Lake, CA

Work Performed December 24.8%

Time Elapsed 45.4%

Work Completed 24.8%

Contractor Earnings December $167,400.00

Previous $0.00

Total to Date $167,400.00

MPCO Noncontract Costs 1st Quarter Expenditures $44,972.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $44,972.00

FY18 Budgeted $72,345.00

Amount Remaining $27,373.00

Percent Remaining 37.84%

Area Office Project Management Project Manager: Mike Green, KO-400

Office Engineering Contract Management: Amber Pierce, MPCO-205

Invoice No. 1 was received during this period, in the amount of $167,400.00, for work performed

during the months of September through part of December.

Field Engineering Field Engineer: Brian Wagner, MPCO-300

Onsite Government Representative: Dennis Schuenemann, MPCO-338.

Number of Contractor Employees: 4

Work Performed The contractor, Coleman Environmental Engineering, Inc. (CEE) continues to prepare the road

foundations for 4” minus gravel placement. A grader was used to strike off top layer of wet soil

and blading it back over onto the existing road after all material had a chance to dry. A CAT 563

vibratory steel wheel roller (VSWR) was utilized to proof roll the foundation prior to placing 4”

minus base. The roadway widths were prepared to receive gravel from the belly dump trucks for

Page 40: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

26 | P a g e

4” minus base rock form the O’Connor pit. 22 belly dump trucks were utilized each day to

deliver gravels to each roadway section. 6” lifts were placed along the various roadways to

achieve the required gravel placement thicknesses. A CAT 140H grader was utilized to spread

the gravels to the required thicknesses. Grading was them followed by VSWR to compact and

proof roll each lift. CEE’s personnel were onsite performing work for 20 days during this

period.

Approximately 18,500 tons of 4” minus gravels were placed this month to complete the

construction of the seven following roadways: A Middle Dike Rd., Pump 10 East Rd., East Rd.,

and N. 13 Rd. Roads that remain to be completed for the 4” minus placement are Pump 10,

Pump 11 and N. 13. About 90 tons remain to be placed to complete the 4” minus placement for

all remaining roadways. Approximately 5000 tons of ¾” minus gravels were placed atop the 4”

minus material base gravels.

The monthly joint safety policy meeting was held during this period in addition to two weekly

safety meetings which were also held by the contractor.

Page 41: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

27 | P a g e

Belly Dump Trucks delivering 4” minus to Middle A Dike Road.

Page 42: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

28 | P a g e

Cat 140G grader after placement of 4” minus along Middle A Dike Road.

Page 43: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

29 | P a g e

Belly dump trucks deliver 4” minus followed by Cat 140G grader which leveled

the rock

Page 44: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

30 | P a g e

East Rd receiving a lift of 4” minus Base Rock

Page 45: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

31 | P a g e

Lahontan Basin Area Office

Page 46: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

32 | P a g e

(This Page Intentionally Left Blank)

Page 47: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

33 | P a g e

Contract No. R16PC00062 Specification No. 20-C0850 Stampede Dam, Dam Safety Modifications - Stampede Division, Washoe Project, Nevada-California NW Constructors, Inc., Bozeman, MT

Work Performed December 4%

Time Elapsed 65.9%

Work Completed 74.9%

Contractor Earnings December $1,527,503.00

Previous $15,748,808.42

Total to Date $17,276,311.56

MPCO Noncontract Costs 1st Quarter Expenditures $209,955.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $209,955.00

FY18 Budgeted $925,520.00

Amount Remaining $715,565.00

Percent Remaining 77.31%

Area Office Project Management Project Manager: Todd Hill, MP-240

Office Engineering Contract Manager: Kent Perkes, MPCO-225

Processed Pay Application No. 13, received December 7, 2017, in the amount of $1,527,503.14

for work performed through December 1, 2017.

Field Engineering Construction Manager: Kyle Hughes, MPCO-324

Construction Representative: Zahid Wazid, MPCO-349; Sean Hill, MPCO-328

Number of Contractor Employees: 0

Work Performed No onsite work performed during this period. The project is closed for the winter.

Page 48: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

34 | P a g e

Contract No. R17PC00063 Specification No. 20-C0860 Marble Bluff Dam and Fish Passage Facility Radial Gate Rehabilitation - Washoe Project, Nevada-California Diana Prince Construction, Inc., Irvine, CA

Work Performed December 22.2%

Time Elapsed 80.0%

Work Completed 51.2%

Contractor Earnings December $197,739.83

Previous $257,883.77

Total to Date $455,623.60

MPCO Noncontract Costs 1st Quarter Expenditures $128,281.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $128,281.00

FY18 Budgeted $186,040.00

Amount Remaining $57,759.00

Percent Remaining 31.05%

Area Office Project Management Project Manager: Steven Sprague, LO-470

Office Engineering Contract Administrator: Madelyn Giles, MPCO-230

Invoice 04 was received this reporting period, in the amount of $197,739.83, for work performed

from November 1, 2017 to November 30, 2017.

No Modifications were executed this reporting period.

Field Engineering Construction Engineer: Reynaldo Garcia, MPCO-310

Construction Representative: Todd Dooley, MPCO-314, Bill Linder, MPCO-312

Number of Contractor Employees: 7

Work Performed

DPC removed the bulkhead gate installed upstream of Marble Bluff Dam’s radial gate.

DPC with ASI completed the installation of new guardrails on the Marble Bluff Dam’s left

abutment and the installation of new guardrail gates. They also completed the application of

Page 49: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

35 | P a g e

Pro-Cryl Universal primer and Pro Industrial Acrylic Topcoat to new guardrails and new

guardrail gates. DPC with ASI completed coating existing guardrails. They also completed the

installation of fence fabric to new and existing guardrails. They also completed applying

DynaTrol-I-XL-DS polyurethane sealant to the bottom of new and existing guardrail posts.

DPC with ASI completed surface preparation for radial gate hoist machinery and the application

of a topcoat of Pro-Industrial Acrylic Topcoat. DPC removed all pumps and equipment from the

entry channel and removed the cover plate installed on the downstream side of the entry

channel’s 24-inch drain pipe. DPC with ASI installed the fish lock brush assemblies. They also

removed both the containment and the scaffolding surrounding the fish lock elevator. DPC with

PEC installed the fish lock hoist. Reclamation operated the hoist with the attached fish lock

elevator through a few cycles without incident. DPC staged equipment no longer in use at

Marble Bluff Dam’s staging area west of the Fish Facility Building. PEC removed existing

panels DFBA and LFBP. They also removed motor starters for Marble Bluff Dam’s Dope Tank,

Turbine Pump, Auxiliary Turbine Pump and the Air Compressor. PEC installed new panels

DFBA and LFBP and motor starter panels for the Dope Tank, Turbine Pump, and Auxiliary

Turbine Pump to replace existing. They also installed a 15-kVA transformer panel between

panels DFBA and LFBP. They also installed new stainless-steel raceways and new ¾-inch rigid

conduit. PEC completed insulation resistance tests of wires between new panels and existing

equipment. They also confirmed the correct phase rotation for each of the existing motors fed

from new panels.

Page 50: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

36 | P a g e

Contract No. R17PC00067 Specification No. None Lahontan Dam Rated Vehicle Barrier System - Newlands Project, Fallon, Nevada Sentinel Builders LCC, Sparks NV

Work Performed December 0.0%

Time Elapsed 100%

Work Completed 100%

Contractor Earnings December $0.00

Previous $146,535.00

Total to Date $146,535.00

MPCO Noncontract Costs 1st Quarter Expenditures $18,548.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $18,548.00

FY18 Budgeted $16,605.00

Amount Remaining $0.00

Percent Remaining 0.0%

Area Office Project Management Project Manager: Scott Schoenfeld, LO-410

Office Engineering Contract Administrator: Lawrence Bowman, MPCO-240

This contract was awarded on June 1, 2017 in the amount of $146,535.00.

Field Engineering Construction Engineer: Reynaldo Garcia, MPCO-310

Construction Representative: Reynaldo Garcia, MPCO-310

Number of Contractor Employees: 0

Work Performed No onsite work was performed during this period.

Page 51: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

37 | P a g e

Northern California Area Office

Page 52: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

38 | P a g e

(This Page Intentionally Left Blank)

Page 53: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

39 | P a g e

Contract No. R15PC00089 Specification No. 20-C0831 Intake 3 Screen Extension, Coleman National Fish Hatchery, Shasta Division, Central Valley Project, California Contractor Services Group, Inc., West Sacramento, CA

Work Performed December 3.8%

Time Elapsed 100.0%

Work Completed 90.3%

Contractor Earnings December $0.00

Previous $1,815,088.05

Total to Date $1,815,088.05

MPCO Noncontract Costs 1st Quarter Expenditures $20,270.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $20,270.00

FY18 Budgeted $67,235.00

Amount Remaining $46,965.00

Percent Remaining 69.85%

Area Office Project Management Project Manager: Hank Harrington, NC-210

Office Engineering Contract Manager: Kent Perkes, MPCO-225

The work was substantially completed as of December 12, 2017.

The work was transferred to the Bureau of Reclamation Northern California Area Office for

operation and maintenance as of November 2, 2017.

Field Engineering Construction Manager: Brian Wagner, MPCO-300

Construction Representative: Fernando Pavone, MPCO-333

Number of Contractor Employees: 0

Work Performed No onsite work performed during this period.

Page 54: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

40 | P a g e

Contract No. R16PC00006 Specification No. 20-C0841 Trinity Powerplant Generator Rewinds - Trinity River Division, Central Valley Project, California Voith Hydro, Inc., York, PA

Work Performed December 4.6%

Time Elapsed 76.7%

Work Completed 77.7%

Contractor Earnings December $611,483.00

Previous $9,768,798.06

Total to Date $10,380,281.06

MPCO Noncontract Costs 1st Quarter Expenditures $106,542.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $106,542.00

FY18 Budgeted $442,535.00

Amount Remaining $335,993.00

Percent Remaining 75.92%

Area Office Project Management Project Manager: Joe Ascoli, NC-650

Office Engineering Contract Administrator: Madelyn Giles, MPCO-230

Invoice 07 was received this reporting period, in the amount of $611,483.00, for work performed

from November 1, 2017 to November 30, 2017.

No Modifications were received this reporting period.

Field Engineering Construction Manager: Brian Wagner, MPCO-300

Construction Representative: Stephen Holmes, MPCO-320

Number of Contractor Employees: 14

Work Performed Subcontractor Metrology Services was on site checking verticality and roundness of the stator

core. Using a FARO laser, the technician programed unit centerline coordinates from previously

established monuments beneath the core. Once programed the technician shot the core in 24

Page 55: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

41 | P a g e

locations equally spaced around the circumference. One shot was taken at the top and bottom of

the core slots.

With acceptance of the roundness and verticality of the stator core the Voith crew began

installation of the armature winding, completing installation of all 432 bottom Roebel bars and

approximately 300 of 432 top bars prior to Christmas break. Each of the bars installed were

wrapped with conductive paper with a layer of conductive putty on the inside of the paper as it is

wrapped around each bar on three sides. The putty is applied with a grooved trowel. The bars

are inserting into their slots by hand and temporarily wedged in place until secured with lashing

to the surge rings on the upper and lower ends.

The crew was able to secure the bottom bars to the rings with epoxy saturated fiberglass cord as

they were tested and accepted and installed before the top bars were started.

During the early part of the month as fill in work, Voith crew members cleaned rotor fan

components with a mild household cleaner removing built-up oil and break dust.

The thrust bearing high pressure lift pump was mounted on the exterior of the unit air housing

and electrical conduits run from the pump’s starter to the Generator ‘A’ box.

A unilateral modification was issued to Voith in November for their rotor pole refurbishment

contractor to investigate obvious arc burns on the amortisseur windings. Representatives from

Voith engineering and the Bureau’s Denver Technical Service Center met at the refurbishment

facility (Delstar) in Montreal, Canada.

The result from dissecting the windings showed the through rods were loose and may have

contributed to the issue.

Unilateral direction was then issued in December for the facility to replace 30 top and 30 bottom

laminations on each of the 36 rotor poles and to peen the five rods connecting the top and bottom

shorting bars of the amortisseur winding.

Page 56: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

42 | P a g e

Preparing conductive paper with putty.

Page 57: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

43 | P a g e

Crew wrapping Roebel bar with the conductive paper.

Page 58: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

44 | P a g e

Crew members inserting bar in the core slot.

Page 59: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

45 | P a g e

Thrust bearing high pressure lift pump and starter

Page 60: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

46 | P a g e

Contract No. R17PC00029 Specification No. 20-C0847 Trinity River Division Powerplants Replacement of Station Service Transformers and Low Voltage Bus System – Trinity River Division, Central Valley Project, Trinity and Shasta Counties, California Gardner Zemke, Albuquerque, NM

Work Performed December 1.5%

Time Elapsed 35.6%

Work Completed 7.0%

Contractor Earnings December $42,928.00

Previous $155,144.00

Total to Date $198,072.00

MPCO Noncontract Costs 1st Quarter Expenditures $28,553.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $28,553.00

FY18 Budgeted $135,905.00

Amount Remaining $107,353.00

Percent Remaining 78.99%

Area Office Project Management Project Manager: Laurie Larson, NC-211

Office Engineering Contract Administrator: Madelyn Giles, MPCO-230

Invoice No. 04, in the amount of $42,928.00, was received this reporting period for work

performed November 21, 2017 to December 18, 2017.

No Modifications were received this reporting period.

Field Engineering Construction Engineer: Brian Wagner, MPCO-300

Construction Representative: Stephen Holmes, MPCO-320

Number of Contractor Employees: 0

Work Performed: No onsite work was performed during this reporting period.

Page 61: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

47 | P a g e

Contract No. R16PC00134 Specification No. 20-C0852 Whiskeytown Lake, Spring Creek Temperature Control Curtain - Trinity River Division, Central Valley Project, California BCI Construction USA, Inc., Belleville IL

Work Performed December 18.3%

Time Elapsed 99.3%

Work Completed 99.5%

Contractor Earnings December $356,169.88

Previous $1,579,325.13

Total to Date $1,935,495.01

MPCO Noncontract Costs 1st Quarter Expenditures $53,464.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $53,464.00

FY18 Budgeted $150,525.00

Amount Remaining $97,061.00

Percent Remaining 64.48%

Area Office Project Management Project Manager: Robert Gee, NC-230

Office Engineering Contract Manager: Amber Pierce, MPCO-205

Invoice No. 05, in the amount of $356,169.88, was received this reporting period, for work

performed during the month of November.

Field Engineering Construction Manager: Brian Wagner, MPCO-300

Construction Representative: Stephen M. Holmes, MPCO-320, Russell Davies, MPCO-341

Number of Contractors Employees: 0

Work performed No onsite work was performed during this period. The contractor demobilized from the site on

November 20, 2017. This work was determined to be substantially complete as of November 16,

2017

Page 62: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

48 | P a g e

Contract No. R17PC00103 Specification No. 20-C0866 Keswick & Shasta Powerplant Weldshop Ventilation System Procurement & Installation - Shasta and Keswick Powerplant - Central Valley Project - California Air-O-Service, Redding, CA

Work Performed December 0.00%

Time Elapsed 56.7%

Work Completed 0.00%

Contractor Earnings December $0.00

Previous $0.00

Total to Date $0.00

MPCO Noncontract Costs 1st Quarter Expenditures $10,970.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $10,970.00

FY18 Budgeted $123,045.00

Amount Remaining $84,460.00

Percent Remaining 68.64%

Area Office Project Management Project Manager: Thomas Darlington, NC-232

Office Engineering Contract Administrator: Casandra Arthur, MPCO-111

Field Engineering Construction Manager: Stephen Holmes, MPCO-320

Construction Representative: David Derk, MPCO-334

Number of Contractor Employees: 0

Work Performed No onsite work was performed during this period.

Page 63: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

49 | P a g e

Contract No. R17PC00091 Specification No. 20-C0869 Intake 3 Trash Rake, Coleman National Fish Hatchery, Shasta Division, Central Valley Project, California Tompco-Triton, Seabeck, WA

Work Performed December 0.0%

Time Elapsed 22.0%

Work Completed 1.1%

Contractor Earnings December $0.00

Previous $16,143.00

Total to Date $16,143.00

MPCO Noncontract Costs 1st Quarter Expenditures $0.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $0.00

FY18 Budgeted $0.00

Amount Remaining $0.00

Percent Remaining 0.0%

Area Office Project Management Project Manager: Hank Harrington, NC-210

Office Engineering Contract Manager: Kent Perkes, MPCO-225

Approved Request for Change No. 001, Festoon Location, on December 12, 2017, as a no cost

change.

Field Engineering Construction Manager: Brian Wagner, MPCO-300

Construction Representative:

Number of Contractor Employees: 0

Work Performed No onsite work was performed during this period.

Page 64: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

50 | P a g e

Contract No. R17PC00092 Specification None Install K12 Rated Vehicle Barriers at Keswick, Shasta and Trinity Power Plants Shasta and Trinity Division, Central Valley Project, California Purgatory Fence Company, Inc., Boise, ID

Work Performed December 0.0%

Time Elapsed 10.1%

Work Completed 6.1%

Contractor Earnings December $0.00

Previous $29,700.00

Total to Date $29,700.00

MPCO Noncontract Costs 1st Quarter Expenditures $19,352.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $19,352.00

FY18 Budgeted $123,045.00

Amount Remaining $103,693.00

Percent Remaining 84.27%

Area Office Project Management Project Manager: Robert Gee, NC-230

Office Engineering Contract Manager: Amber Pierce, MPCO-205

Field Engineering Field Engineer: Brian Wagner, MPCO-300

Construction Manager: Stephen Holmes, MPCO-320.

Number of Contractor Employees: 0

Work Performed No onsite work was performed during this period.

Page 65: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

51 | P a g e

South Central California Area

Office

Page 66: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

52 | P a g e

(This Page Intentionally Left Blank)

Page 67: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

53 | P a g e

There was no work performed during this period for the South Central California Area Office.

Page 68: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

54 | P a g e

(This Page Intentionally Left Blank)

Page 69: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

55 | P a g e

San Joaquin River Restoration

Program

Page 70: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

56 | P a g e

(This Page Intentionally Left Blank)

Page 71: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

57 | P a g e

There was no work performed during this period for the South Central California Area Office.

Page 72: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

58 | P a g e

(This Page Intentionally Left Blank)

Page 73: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

59 | P a g e

Mid-Pacific Regional Office

Page 74: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

60 | P a g e

(This Page Intentionally Left Blank)

Page 75: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

61 | P a g e

Contract No. R16PC00091 Specification No. 20-C0843 North Fork Screens and Ladder Completion Contract - Battle Creek Salmon and Steelhead Restoration Project, California TNT Industrial Contractors, Inc., Sacramento, CA

Work Performed December 0.00%

Time Elapsed 81.0%

Work Completed 77.5%

Contractor Earnings December $0.00

Previous $4,260,023.10

Total to Date $4,260,023.10

MPCO Noncontract Costs 1st Quarter Expenditures $141,104.00

2nd Quarter Expenditures $0.00

3rd Quarter Expenditures $0.00

4th Quarter Expenditures $0.00

FY18 Cumulative Total $141,104.00

FY18 Budgeted $414,120.00

Amount Remaining $273,016.00

Percent Remaining 65.93%

Area Office Project Management Project Manager: Mary Marshall, MP-203

Office Engineering Contract Administrator: Casandra Arthur, MPCO-111

No invoices were received during this reporting period.

Two modifications were executed during this reporting period; Unilateral Modification 006 in

the amount of $195,000 and Bilateral Modification 007 in the amount of $7,296.04.

Field Engineering Construction Manager: Brian Wagner, MPCO-300

Construction Representative: Jason Foust, MPCO-325

Number of Contractor Employees: 12

Work Performed The following work took place at the North Battle Creek Feeder Diversion Dam (NBCFDD) site;

Subcontractor Syblon Reid (SRCO) finished installing the fish screens and associated parts

including the upper and lower channels for the louvers, the louvers, the upper and lower fish

screen support brackets, the fish screen panels and blanking plates at the fish screen structure.

Page 76: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

62 | P a g e

All the connections between the dissimilar metals were isolated. Also at the fish screen

structure, the brush motor and counterweight assemblies were aligned, the electrical for the brush

cleaners was connected and the flashboards were installed in the guide vanes.

SRCO continued work under unilateral modification 006 and installed the transition step on the

downstream of the fish screen structure.

SRCO began demobilizing equipment from the NBCFDD project site. No work occurred at Eagle

Canyon during this reporting period.

Page 77: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

63 | P a g e

North Fork Screens and Ladders Completion Contract

Installation of the NBCFDD lower louver channel supports at the fish screen structure

Page 78: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

64 | P a g e

North Fork Screens and Ladders Completion Contract

Installation of Fish Screen Louvers

Page 79: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

65 | P a g e

North Fork Screens and Ladders Completion Contract

Electrical connections for the Fish Screen Brush Cleaner

Page 80: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

66 | P a g e

(This Page Intentionally Left Blank

Page 81: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

67 | P a g e

Contracts in Warranty Status

Page 82: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

68 | P a g e

(This Page Intentionally Left Blank)

Page 83: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

69 | P a g e

R11PC20185 No. 20-C0778 Tracy 13.8kV Switchgear/Breaker Replacement – Tracy Pumping Plant and Substation - Delta Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The warranty work for the

B15 DFR will extend the 1-year warranty from June 29, 2017 through June 28, 2018.

R13PC20159 No. 20-C0819 Lake Berryessa Concessions Areas Improvements – Lake Berryessa, Solano Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty

period began on March 31, 2017 and will end March 30, 2018.

R16PC00079 No. 20-C0851 Red Bluff Flap Gate Retrofit - Sacramento Canals Unit, Sacramento River Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty

period began March 16, 2017 and will end March 15, 2018.

R17PC00022 No. 20-C0857 Western Tracy Switchyard - Chain Link Fence Project Tracy Pumping Plant and Substation - Delta Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty

period began May 11, 2017 and will end May 10, 2018.

R11PC2023S None Red Bluff Diversion Dam, Fish Passage Improvement Project Terrestrial Mitigation - Sacramento River Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty

period began December 31, 2016 and will end December 30, 2017.

R16PC00099 None Folsom Dam Resource Building Replacement - Folsom Unit, American River Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty

period began February 14, 2017 and will end February 13, 2018.

R16PC00100 None Lake Woollomes Recreation Area Asphalt Replacement - Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty

period began April 26, 2017 and will end April 25, 2018.

R15PC00080 20-C0836 Klamath Basin Area Office Sewer Lift Station, Klamath Basin Area Office, Klamath Falls, Oregon Office Engineering is reviewing required submittals. The 1-year warranty period began January

20, 2017 and will end January 19, 2018.

R16PC00111 20-C0855 San Joaquin Hatchery Water Supply Pipeline - Friant Division, Central Valley Project, California Invoice No. 09 was received this reporting period for work performed in August. The 1-year

warranty period began June 29, 2017 and will end June 28, 2018.

Page 84: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

70 | P a g e

R16PC00110 20-C0853 Madera Canal Headworks Low-Flow Valve - Friant Division, Central Valley Project, California There was no Office Engineering Administrative activity this period. The 1-year warranty

period began June 29, 2017 and will end June 28, 2018

Page 85: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

71 | P a g e

Lab Reports

Page 86: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

72 | P a g e

(This Page Intentionally Left Blank)

Page 87: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

73 | P a g e

Stampede Safety of Dams Project

There was no laboratory information provided from the Materials Lab for this

project during this period.

Page 88: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

74 | P a g e

(This Page Intentionally Left Blank)

Page 89: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

75 | P a g e

North Fork Screens and Ladders Completion Contract

There was no laboratory information provided from the Materials Lab for this project during this period.

Page 90: Mid-Pacific Construction Office L-29 ReportSouth-Central California Area Office 51 San Joaquin River Restoration Program 55 Mid-Pacific Regional Office 59 R16PC00091 20-C0843 TNT Industrial

76 | P a g e

(This Page Intentionally Left Blank)