1
VIKASH KULSHRESTHA
From: VIKASH KULSHRESTHA
Sent: 19 October 2015 10:37
To: Manohar S
Cc: Arivazhagan P; Sivakumar S; Arivazhagan P ([email protected]); Saran S;
Diwakar Nandan; MV Ramana; Sachin Murumkar
Subject: RE: SPCON - LT00002034- Hard operation of valves- Most urgent
SM,
Refer below list of valves operating hard, checked by our service engineer available at site from last 10 days.
Today also he is checking valves and shall come back with feedback.
Technician along with material “modified seat and seal (extra set) and torque wrench” need to be sent on urgent
basis.
Sr. Size Class Tag. Sr. no. Nature of Problem
1 50 300 VB166 15419302 Hard operation
2 80 300 VB166 15419363 Hard operation
3 80 300 VB166 15420135 Hard operation
4 100 150 VB165 15422241 Hard operation
5 100 150 VB165 15422243 Hard operation
6 80 300 VB166 15419864 Hard operation
7 80 300 VB166 15419865 Hard operation
8 40 800 VB133 14431419 Hard operation
9 40 800 VB133 14431420 Hard operation
10 40 800 VB133 14431413 Hard operation
11 40 800 VB133 14431416 Hard operation
12 80 300 VB166 15419857 Hard operation
13 25 800 VB133 15409524 Hard operation
14 50 300 VB166 15419302 Hard operation
15 50 300 VB166 15419305 Hard operation
16 50 300 VB166 15419951 Hard operation
17 50 300 VB166 15419304 Hard operation
18 50 300 VB166 15418952 Hard operation
19 50 300 VB166 15413745 Hard operation
20 50 300 VB166 15419275 Hard operation
21 50 300 VB166 15418994 Hard operation
22 50 300 VB166 15418991 Hard operation
23 50 150 VB196 15420304 Hard operation
Regards,
Vikash Kulshrestha
From: VIKASH KULSHRESTHA
Sent: 17 October 2015 10:04
To: Manohar S Cc: Arivazhagan P; Sivakumar S; Arivazhagan P ([email protected]); Saran S; Vaibhav Dhas
Subject: RE: SPCON - Service Engineer details required - L&T Valves- LT00002034
2
SM,
Pl advise to inform despatch details.
“Point no. 2 of Note: Hard/not operating – Size 2”VB166, 1” 1.5”VB133 around 30 nos. in GTG.- (Seat and body
seal)”
Diwakar is on site, checking all valves today.
Regards,
Vikash Kulshrestha
From: VIKASH KULSHRESTHA
Sent: 14 October 2015 17:44
To: Manohar S Cc: Arivazhagan P; Sivakumar S; Arivazhagan P ([email protected]); Saran S; Vaibhav Dhas
Subject: RE: SPCON - Service Engineer details required - L&T Valves- LT00002034
SM,
Pl advise to inform despatch details.
Regards,
Vikash Kulshrestha
From: VIKASH KULSHRESTHA
Sent: 08 October 2015 14:22 To: Manohar S
Cc: Arivazhagan P; Sivakumar S; Arivazhagan P ([email protected]); Saran S; Vaibhav Dhas
Subject: RE: SPCON - Service Engineer details required - L&T Valves
SM,
As per attached MOM followings are the pending issues:-
1. Point no. 27 – Coupling
2. Point no. 2 of Note: Hard/not operating – Size 2”VB166, 1” 1.5”VB133 around 30 nos. in GTG.- (Seat and
body seal)
3. Attached mail for passing in ¾”VB45BM- 01 no. (Seat and body seal)
Material needs to be couriered urgently today, if not despatched.
Regards,
Vikash Kulshrestha
From: Jagdish Dhamane [mailto:[email protected]]
Sent: 02 October 2015 11:02
To: Sivakumar S Cc: Arivazhagan P; Devendra Thakare; Dharmaraj B; M S Rajaraman; A V Rajesh; Ramajeyam K; Ram Singh; Sachin
Murumkar; Suresh Kumar B (QC); Vaibhav Dhas; VIKASH KULSHRESTHA; Vipul Jamdade; Devakumar K Subject: Fw: SPCON - Service Engineer details required - L&T Valves
Dear Sivakumar, Please reply on below mail urgently. Rectification of 1 valve is balance due to unavailability of Coupler. Kindly revert with action plan by today COB positively. Thanks & Regards, Jagdish Dhamane.
3
L&T Hydrocarbon Engineering Limited Procurement - Hydrocarbon Upstream EPC Block| 3rd Floor | A-Wing | Gate No.1 |
Saki Vihar Road | Powai | Mumbai - 400 072 | INDIA Tel: +91 22 6705 3764 Fax: +91 22 6705 1951/1988 E-mail: [email protected] Web: www.Lntenc.com ----- Forwarded by Jagdish Dhamane/LNTENC on 10/02/2015 10:58 AM ----- From: Jagdish Dhamane/LNTENC To: "Devakumar K" <[email protected]> Cc: Arivazhagan P <[email protected]>, Devendra Thakare <[email protected]>, Dharmaraj B <[email protected]>, M S Rajaraman <[email protected]>, A V Rajesh <[email protected]>, Ramajeyam K <[email protected]>, "Ram Singh" <[email protected]>, Sachin Murumkar <[email protected]>, Sivakumar S <[email protected]>, "Suresh Kumar B (QC)" <[email protected]>, Vaibhav Dhas <[email protected]>, VIKASH KULSHRESTHA <[email protected]>, Vipul Jamdade <[email protected]> Date: 09/25/2015 12:30 PM Subject: RE: SPCON - Service Engineer details required - L&T Valves
Dear Sivakumar, Please refer attached MOM made during visit of Mr. S. Ramkumar. Rectification of 1 valve is balance due to unavailability of Coupler. Kindly arrange for the material and rectification of the valve.
(See attached file: List of Valves with Leakages Observed-As on 24-Sept-15.xlsx)(See attached file:
MOM_Visit LnT Valve Service Engg_22-Sept to 24 Sept.pdf)
Thanks & Regards, Jagdish Dhamane.
L&T Hydrocarbon Engineering Limited Procurement - Hydrocarbon Upstream EPC Block| 3rd Floor | A-Wing | Gate No.1 |
Saki Vihar Road | Powai | Mumbai - 400 072 | INDIA Tel: +91 22 6705 3764 Fax: +91 22 6705 1951/1988 E-mail: [email protected] Web: www.Lntenc.com
"Devakumar K" ---09/21/2015 12:55:29 PM---Dear Jagdish, As discussed, we are sending our service engineer for rectify TMBV valves(2Nos) and wh From: "Devakumar K" <[email protected]> To: Jagdish R Dhamane <[email protected]>, Vaibhav Dhas <[email protected]>, Cc: Arivazhagan P <[email protected]>, Chinmay Sanjay Amrute <[email protected]>, Devendra Thakare <[email protected]>, Dharmaraj B <[email protected]>, M S Rajaraman <[email protected]>, Ramajeyam K <[email protected]>, "Ram Singh" <[email protected]>, Sachin Murumkar <[email protected]>, Sivakumar S <[email protected]>, "Suresh Kumar B (QC)" <[email protected]>, VIKASH KULSHRESTHA <[email protected]>, Vipul Jamdade <[email protected]>, A V Rajesh <[email protected]> Date: 09/21/2015 12:55 PM Subject: RE: SPCON - Service Engineer details required - L&T Valves
4
Dear Jagdish, As discussed, we are sending our service engineer for rectify TMBV valves(2Nos) and who will be available at site on 22
nd Sep’15.
Service Engineer Name :- Mr. S. Ramkumar Mobile Number :- 9894979057 Thanks Devakumar K From: Jagdish Dhamane [mailto:[email protected]]
Sent: Monday, September 07, 2015 5:53 PM
To: Vaibhav Dhas Cc: Arivazhagan P; Chinmay Sanjay Amrute; Devakumar K; Devendra Thakare; Dharmaraj B; M S Rajaraman;
Ramajeyam K; Ram Singh; Sachin Murumkar; Sivakumar S; Suresh Kumar B (QC); VIKASH KULSHRESTHA; Vipul Jamdade; A V Rajesh
Subject: RE: SPCON - Service Engineer details required - L&T Valves
Dear Mr. Vaibhav, Kindly note that 12" Cl 900 valve is already installed in line on platform and sending it back for rectification work is not possible at this stage. Considering this, kindly arrange for the rectification of this valve at site itself. Also, please provide confirmation on status of spares required for rectification of balance valves. Thanks & Regards,
Jagdish Dhamane.
L&T Hydrocarbon Engineering Limited Procurement - Hydrocarbon Upstream EPC Block| 3rd Floor | A-Wing | Gate No.1 |
Saki Vihar Road | Powai | Mumbai - 400 072 | INDIA Tel: +91 22 6705 3764 Fax: +91 22 6705 1951/1988 E-mail: [email protected] Web: www.Lntenc.com
Vaibhav Dhas ---09/07/2015 03:43:42 PM---Dear Sir, We have discussed the issues with our plant and asked to send the material to your site fo From: Vaibhav Dhas <[email protected]> To: Jagdish R Dhamane <[email protected]>, Cc: Arivazhagan P <[email protected]>, Chinmay Sanjay Amrute <[email protected]>, Devendra Thakare <[email protected]>, M S Rajaraman <[email protected]>, Ram Singh <[email protected]>, Sachin Murumkar <[email protected]>, VIKASH KULSHRESTHA <[email protected]>, Vipul Jamdade <[email protected]>, Sivakumar S <[email protected]>, Ramajeyam K <[email protected]>, "Suresh Kumar B (QC)" <[email protected]>, Dharmaraj B <[email protected]>, "Devakumar K" <[email protected]> Date: 09/07/2015 03:43 PM Subject: RE: SPCON - Service Engineer details required - L&T Valves
Dear Sir,
We have discussed the issues with our plant and asked to send the material to your site for TMBV valve 3”900 TMBV.
5
Also got feedback from plant that 12”Cl-900 TMBV valve is not possible to rectify at site, please arrange to send it to our
Kanchipuram Plant. We will rectify it and send it back to you as early as possible.
We shall plan our visit once the material for valve 3”900 TMBV will reach to your site.
Thanking you.
Regards,
Vaibhav Dhas.
From: Jagdish Dhamane [mailto:[email protected]]
Sent: Saturday, September 05, 2015 9:08 AM To: Sivakumar S
Cc: Arivazhagan P; Chinmay Sanjay Amrute; Devendra Thakare; M S Rajaraman; Ram Singh; Sachin Murumkar; Vaibhav Dhas; VIKASH KULSHRESTHA; Vipul Jamdade
Subject: Fw: SPCON - Service Engineer details required - L&T Valves
Dear Sivakumar, Please note that 10 Nos valves are pending for rectification at site in SPCON Project as per attached file. Kindly arrange for the deputation of Service Engineer along with required spares immediately. Required spares have been mentioned in Remarks column.
(See attached file: List of Valves with Leakages Observed-As on 03-Sept-15.xlsx) Thanks & Regards,
Jagdish Dhamane.
L&T Hydrocarbon Engineering Limited Procurement - Hydrocarbon Upstream EPC Block| 3rd Floor | A-Wing | Gate No.1 |
Saki Vihar Road | Powai | Mumbai - 400 072 | INDIA Tel: +91 22 6705 3764 Fax: +91 22 6705 1951/1988 E-mail: [email protected] Web: www.Lntenc.com
----- Forwarded by Jagdish Dhamane/LNTENC on 09/05/2015 09:00 AM ----- From: Jagdish Dhamane/LNTENC To: Sivakumar S <[email protected]>, Cc: Arivazhagan P <[email protected]>, Chinmay Sanjay Amrute <[email protected]>, Devendra Thakare <[email protected]>, M S Rajaraman <[email protected]>, Ram Singh <[email protected]>, "Sachin Murumkar" <[email protected]>, Vaibhav Dhas <[email protected]>, VIKASH KULSHRESTHA <[email protected]>, Vipul Jamdade/LNTENC@ENC Date: 08/31/2015 09:21 AM Subject: SPCON - Service Engineer details required - L&T Valves
Dear Sivakumar, Please provide Service Engineer details for servicing of SPCON valves. Kindly note that repair of these valves needs to be taken on priority considering yard activities.
6
List of open points is attached for ready reference. Kindly ensure that all valves will be serviced during next visit of Service Engineer, [attachment "List of Valves with Leakages Observed-As on 24-Aug-15.xlsx" deleted by Jagdish Dhamane/LNTENC] Thanks & Regards,
Jagdish Dhamane.
L&T Hydrocarbon Engineering Limited Procurement - Hydrocarbon Upstream EPC Block| 3rd Floor | A-Wing | Gate No.1 |
Saki Vihar Road | Powai | Mumbai - 400 072 | INDIA Tel: +91 22 6705 3764 Fax: +91 22 6705 1951/1988 E-mail: [email protected] Web: www.Lntenc.com
----- Forwarded by Jagdish Dhamane/LNTENC on 08/31/2015 09:12 AM ----- From: Vipul Jamdade/LNTENC To: Sivakumar S <[email protected]>, Cc: Arivazhagan P <[email protected]>, Chinmay Sanjay Amrute <[email protected]>, Devendra Thakare <[email protected]>, M S Rajaraman <[email protected]>, Ram Singh <[email protected]>, "Sachin Murumkar" <[email protected]>, Vaibhav Dhas <[email protected]>, VIKASH KULSHRESTHA <[email protected]>, Jagdish Dhamane/LNTENC@ENC Date: 08/29/2015 10:52 AM Subject: RE: LTHE - MHNRD: Valve handle orientation matter Urgent ! LNT Valves
Dear Sivakumar, Please provide L&T service engineer details for servicing SPCON valves. Thank You Vipul Jamdade | Manager - Proc & SCM | L&T Hydrocarbon Engineering Limited | Gate No. 1, EPC Block, 3rd Floor, A-Wing, Saki Vihar Road, Powai, Mumbai - 400 072, INDIA | T : +91 22 6705 4687 | M : +91 98202 41183 | F : +91 22 6705 1951 | E : [email protected] | Website : www.LNTENC.com |
Vipul Jamdade---08/26/2015 10:44:32 AM---Dear Sivakumar, Further to the below email, please note that the Mr. J. Manikandan is not ready to s
From: Vipul Jamdade/LNTENC To: Sivakumar S <[email protected]> Cc: Arivazhagan P <[email protected]>, Chinmay Sanjay Amrute <[email protected]>, Devendra Thakare <[email protected]>, M S Rajaraman <[email protected]>, Ram Singh <[email protected]>, "Sachin Murumkar" <[email protected]>, Vaibhav Dhas <[email protected]>, VIKASH KULSHRESTHA <[email protected]>, Jagdish Dhamane/LNTENC@ENC Date: 08/26/2015 10:44 AM Subject: RE: LTHE - MHNRD: Valve handle orientation matter Urgent ! LNT Valves
Dear Sivakumar, Further to the below email, please note that the Mr. J. Manikandan is not ready to service SPCON leaking valves. Request you to talk to him.
7
Thank You Vipul Jamdade | Manager - Proc & SCM | L&T Hydrocarbon Engineering Limited | Gate No. 1, EPC Block, 3rd Floor, A-Wing, Saki Vihar Road, Powai, Mumbai - 400 072, INDIA | T : +91 22 6705 4687 | M : +91 98202 41183 | F : +91 22 6705 1951 | E : [email protected] | Website : www.LNTENC.com |
Jagdish Dhamane---08/24/2015 11:15:59 AM---Dear Sivakumar, Please refer below updated list of valves having leakage problem in SPCON Project. From: Jagdish Dhamane/LNTENC To: Sivakumar S <[email protected]> Cc: Arivazhagan P <[email protected]>, Chinmay Sanjay Amrute <[email protected]>, Devendra Thakare <[email protected]>, M S Rajaraman <[email protected]>, Ram Singh <[email protected]>, "Sachin Murumkar" <[email protected]>, Vaibhav Dhas <[email protected]>, VIKASH KULSHRESTHA <[email protected]>, Vipul Jamdade <[email protected]> Date: 08/24/2015 11:15 AM Subject: RE: LTHE - MHNRD: Valve handle orientation matter Urgent ! LNT Valves
Dear Sivakumar, Please refer below updated list of valves having leakage problem in SPCON Project. Kindly take necessary action at your end and instruct technician to attend these valves as well. [attachment "List of Valves with Leakages Observed-As on 24-Aug-15.xlsx" deleted by Jagdish Dhamane/LNTENC] Thanks & Regards,
Jagdish Dhamane.
L&T Hydrocarbon Engineering Limited Procurement - Hydrocarbon Upstream EPC Block| 3rd Floor | A-Wing | Gate No.1 |
Saki Vihar Road | Powai | Mumbai - 400 072 | INDIA Tel: +91 22 6705 3764 Fax: +91 22 6705 1951/1988 E-mail: [email protected] Web: www.Lntenc.com
Sivakumar S ---08/24/2015 10:40:33 AM---Dear Vipul / Jagdish, We are sending our assembler J. Manikandan (Mobile No 9600843599) from our Kan
From: Sivakumar S <[email protected]> To: Vipul Jamdade <[email protected]>, Jagdish R Dhamane <[email protected]>, Cc: Arivazhagan P <[email protected]>, Chinmay Sanjay Amrute <[email protected]>, Devendra Thakare <[email protected]>, M S Rajaraman <[email protected]>, Ram Singh <[email protected]>, "Sachin Murumkar" <[email protected]>, Vaibhav Dhas <[email protected]>, VIKASH KULSHRESTHA <[email protected]> Date: 08/24/2015 10:40 AM Subject: RE: LTHE - MHNRD: Valve handle orientation matter Urgent ! LNT Valves
8
Dear Vipul / Jagdish,
We are sending our assembler J. Manikandan (Mobile No 9600843599) from our Kancheepuram factory.
He has already started from Chennai and will be reaching site on 26.08.2015.
This is for your information please.
With warm regards,
S Sivakumar
Contracts Management
L&T Valves Limited
Manapakkam
Chennai – 600 089, India
Phone : +91 44 2249 8237
Fax : +91 44 2249 5055
Mobile : +91 9884 298800
E mail : [email protected]
Website : www.lntvalves.com
From: Jagdish Dhamane [mailto:[email protected]]
Sent: 21 August 2015 13:40
To: Sivakumar S Cc: Arivazhagan P; Chinmay Sanjay Amrute; Devendra Thakare; M S Rajaraman; Ram Singh; Sachin Murumkar;
Vaibhav Dhas; VIKASH KULSHRESTHA; Vipul Jamdade Subject: RE: LTHE - MHNRD: Valve handle orientation matter Urgent ! LNT Valves
Dear Sivakumar, It is to be noted that Mr. Vaibhav Dhas rectified some of the valves and left yesterday itself. Kindly arrange to depute alternate Service Engineer at yard on immediate basis. Thanks & Regards,
Jagdish Dhamane.
L&T Hydrocarbon Engineering Limited Procurement - Hydrocarbon Upstream EPC Block| 3rd Floor | A-Wing | Gate No.1 |
Saki Vihar Road | Powai | Mumbai - 400 072 | INDIA Tel: +91 22 6705 3764 Fax: +91 22 6705 1951/1988 E-mail: [email protected] Web: www.Lntenc.com
Sivakumar S ---08/18/2015 04:27:50 PM---Dear Vipul / Jagdish, The lever needs to be rotated to bring it in line with GAD requirement. Photog
From: Sivakumar S <[email protected]> To: Vipul Jamdade <[email protected]>, Jagdish R Dhamane <[email protected]>, Cc: Arivazhagan P <[email protected]>, Chinmay Sanjay Amrute <[email protected]>, Devendra Thakare <[email protected]>, M S Rajaraman <[email protected]>, Ram Singh <[email protected]>, "Sachin Murumkar" <[email protected]>, VIKASH KULSHRESTHA <[email protected]>, Vaibhav Dhas <[email protected]> Date: 08/18/2015 04:27 PM Subject: RE: LTHE - MHNRD: Valve handle orientation matter Urgent ! LNT Valves
9
Dear Vipul / Jagdish,
The lever needs to be rotated to bring it in line with GAD requirement. Photographs of the revised assembly are as below.
Our service engineer Mr.Vaibhav will attend to resolve this issue. I will inform you his visit plan shortly.
Open condition
Close condition
10
With warm regards,
S Sivakumar
Contracts Management
L&T Valves Limited
Manapakkam
Chennai – 600 089, India
Phone : +91 44 2249 8237
Fax : +91 44 2249 5055
Mobile : +91 9884 298800
E mail : [email protected]
Website : www.lntvalves.com
From: Vipul Jamdade [mailto:[email protected]] Sent: 14 August 2015 16:22
To: Sivakumar S
Cc: Arivazhagan P; Chinmay Sanjay Amrute; Devendra Thakare; Jagdish R Dhamane; M S Rajaraman; Ram Singh; Sachin Murumkar
Subject: LTHE - MHNRD: Valve handle orientation matter Urgent ! LNT Valves
Dear Sivakumar,
Please respond to below email urgently.
Thank You
Vipul Jamdade | Manager - Proc & SCM | L&T Hydrocarbon Engineering Limited |
Gate No. 1, EPC Block, 3rd Floor, A-Wing, Saki Vihar Road, Powai, Mumbai - 400 072, INDIA |
T : +91 22 6705 4687 | M : +91 98202 41183 | F : +91 22 6705 1951 |
E : [email protected] | Website : www.LNTENC.com |
----- Forwarded by Vipul Jamdade/LNTENC on 08/14/2015 04:17 PM -----
11
From: Sanjay Kumar Parmar/LNTENC
To: Vipul Jamdade/LNTENC@ENC Cc: Jagdish Dhamane/LNTENC@ENC, Devendra Thakare/LNTENC@ENC, Ram T Singh/LNTENC@ENC, Saibal Sinha/LNTENC@ENC, Subhashis Parashar/LNTENC@ENC, Digambar Jadhav/LNTENC@ENC, Kalpesh Jadhav/LNTENC@ENC, Shailendra Nikhare/LNTENC@ENC, Kapil
Kokane/LNTENC@ENC, Dibyendu Das/LNTENC@ENC
Date: 08/14/2015 04:05 PM
Subject: Fw: MHNRD: Valve handle orientation matter Urgent ! LNT Valves
Dear Vipul, While spools fabrication at site, it is observed that for 0.75" VB-45BM valve lever is found plain end side of the valve whereas it lever should be NPT end side as per valve GAD(LNT Valves). If we keep lever plain end side then while operating the valve it may clash to other lines due to layout constraint. Kindly ask clarification from vendor and also ask the possibilities if lever can be rotated locally without affect the locking arrangement. Please revert on priority, matter urgent. Regards Sanjay K Parmar L&T-OGSP MHNRD-III Piping
13
Sent from my iPhone Disclaimer :"This email and any files transmitted with it are intended solely for the use of the addressee(s) only and may contain confidential and/or privileged information. If you are not the addressee, then this message is not intended for you and be advised that you have received this email in error and that any use, dissemination, forwarding, printing or copying of this email is strictly prohibited. In such case please notify the sender and delete this email and any attachments with it from your system immediately. Receipt of this email by you shall not give rise to any liability on the part of L&T Hydrocarbon Engineering" Disclaimer :"This email and any files transmitted with it are intended solely for the use of the addressee(s) only and may contain confidential and/or privileged information. If you are not the addressee, then this message is not intended for you and be advised that you have received this email in error and that any use, dissemination, forwarding, printing or copying of this email is strictly prohibited. In such case please notify the sender and delete this email and any attachments with it from your system immediately. Receipt of this email by you shall not give rise to any liability on the
part of L&T Hydrocarbon Engineering"
L&T Valves Limited
www.lntvalves.com
The information contained in this e-mail and attachments thereto is confidential and may also be privileged
for the sole use of the intended recipient(s) only. If you are not the intended recipient, please notify the
sender immediately by e-mail and delete all copies of this e-mail.. you should not copy or use it for any
purpose,nor disclose its contents to any other person which is strictly prohibited.
L&T Valves Limited
www.lntvalves.com
The information contained in this e-mail and attachments thereto is confidential and may also be privileged
for the sole use of the intended recipient(s) only. If you are not the intended recipient, please notify the
sender immediately by e-mail and delete all copies of this e-mail.. you should not copy or use it for any
purpose,nor disclose its contents to any other person which is strictly prohibited. Disclaimer :"This email and any files transmitted with it are intended solely for the use of the addressee(s) only and may contain confidential and/or privileged information. If you are not the addressee, then this message is not intended for you and be advised that you have received this email in error and that any use, dissemination, forwarding, printing or copying of this email is strictly prohibited. In such case please notify the sender and delete this email and any attachments with it from your system immediately. Receipt of this email by you shall not give rise to any liability on the part of L&T Hydrocarbon Engineering" Disclaimer :"This email and any files transmitted with it are intended solely for the use of the addressee(s) only and may contain confidential and/or privileged information. If you are not the addressee, then this message is not intended for you and be advised that you have received this email in error and that any use, dissemination, forwarding, printing or copying of this email is strictly prohibited. In such case please notify the sender and delete this email and any attachments with it from your system immediately. Receipt of this email by you shall not give rise to any liability on the
part of L&T Hydrocarbon Engineering"
L&T Valves Limited
www.lntvalves.com
The information contained in this e-mail and attachments thereto is confidential and may also be privileged
for the sole use of the intended recipient(s) only. If you are not the intended recipient, please notify the
sender immediately by e-mail and delete all copies of this e-mail.. you should not copy or use it for any
purpose,nor disclose its contents to any other person which is strictly prohibited.(See attached file: List of
Valves with Leakages Observed-As on 03-Sept-15.xlsx)
14
L&T Valves Limited
www.lntvalves.com
The information contained in this e-mail and attachments thereto is confidential and may also be privileged
for the sole use of the intended recipient(s) only. If you are not the intended recipient, please notify the
sender immediately by e-mail and delete all copies of this e-mail.. you should not copy or use it for any
purpose,nor disclose its contents to any other person which is strictly prohibited. Disclaimer :"This email and any files transmitted with it are intended solely for the use of the addressee(s) only and may contain confidential and/or privileged information. If you are not the addressee, then this message is not intended for you and be advised that you have received this email in error and that any use, dissemination, forwarding, printing or copying of this email is strictly prohibited. In such case please notify the sender and delete this email and any attachments with it from your system immediately. Receipt of this email by you shall not give rise to any liability on the part of L&T Hydrocarbon Engineering"