MICHIGAN DEPARTMENT OF TRANSPORTATION · destructive examinations, paint, etc. In some cases the...
Transcript of MICHIGAN DEPARTMENT OF TRANSPORTATION · destructive examinations, paint, etc. In some cases the...
#
STRUCTURAL FABRICATION UNIT
V112917
TABLE OF CONTENTS
PAGE 1 of 1
MICHIGAN DEPARTMENT OF TRANSPORTATION
Table of Contents
1. Quality Assurance
# Structural Fabrication Inspection Flowchart 1
# Structural Fabrication Inspection Web Links 2
# Structural Fabrication Quality Assurance Guidance Document 3
# Materials Quality Assurance Procedures Manual Section 4.04 12
# Materials Quality Assurance Procedures Manual Section 4.11 24
2. Request for Information
# Structural Fabrication Request for Information Process 33
3. Nonconformance Program
# Structural Fabrication Nonconformance Policy 37
# Structural Fabrication Nonconformance Process 42
# Structural Precast Concrete Repair Guidance Document 50
4. Buy America
# Structural Fabrication Buy America Guidance Document 69
# Buy America Sample Letters 74
5. Material Sampling
# Metals Laboratory Sampling Guidance Document 77
# Sample Identification (Form 1923) 83
# Sample Identification (Form 1923) – Example 84
6. Miscellaneous
# Structural Fabrication E-construction Process 85
# Structural Fabrication Bookmarking Template 87
# Industry Letters 88
# Commentary for Project Folder Checklist 103
7. Forms
# Project Folder Checklist (Form 2001) 111
# Fabrication Inspection Report (Form 5617) 114
# Strand Tensioning Report (Form 0513) 115
# Bar Reinforcement Report (Form 1985) 118
# Pre and Post Pour Inspection Checklist (Form 5616) 119
# Field and Lab Test Report (Form 0590) 121
# Repair Observation Report (Form 1981) 122
(This page intentionally left blank)
)
#
(This page intentionally left blank)
(This page intentionally left blank)
(This page intentionally left blank)
STRUCTURAL FABRICATION UNIT
V012418
STRUCTURAL FABRICATION INSPECTION WEB LINKS
PAGE 1 OF 1
MICHIGAN DEPARTMENT OF TRANSPORTATION
Structural Fabrication Inspection Web Links
DescriptionThis document contains several important links to resources related to structural fabrication inspection for
the Michigan Department of Transportation. Click on the title of each section for the link.
" 2012 Standard Specifications for Construction This link will take you to a printable/downloadable copy of the MDOT 2012 Standard Specifications for Construction as well as the Supplemental Specifications for Errata to these Specifications. These specifications detail all of MDOT’s policies on construction. There are subsections that are related specifically to structural precast concrete and Structural Steel inspection.
" Materials Quality Assurance Procedures Manual This document provides guidance on MDOT’s requirements for performing QA inspections.
" Materials Source Guide This document describes the acceptance criteria for materials, and should be looked at prior to the materials being incorporated into a project.
" Forms All of the inspection forms are stored on this site which can be searched by the form number.
" Bridge Field Services
This site serves as a statewide resource for structures, and contains reference materials for bridge personnel.
1. Field Manual for Concrete Anchoring
2. Field Manual for Structural Welding
3. Field Manual for Structural Bolting
" Structure Technical SectionThis site contains all of the contact information for the Structural Fabrication Unit for which the inspector is working for. You can also find the current QAI Fabrication Portfolios.
1. MDOT Shop Drawing Review Process
2. 2018 MDOT Structural Steel QAI Manual
3. 2018 MDOT Structural Precast Concrete QAI Manual
" MDOT Buy America Compliance Listing This site contains a listing of Approved Manufacturers, QPL’s and Tested Stock Suppliers that are either fully compliant, partially compliant, or do not have any steel/iron in their product as noted next to each company name. For our use we only need to look at the BA+ or BA- listings.
2019 Interim 2
(This page intentionally left blank)
(This page intentionally left blank)
(This page intentionally left blank)
STRUCTURAL FABRICATION UNIT
V092517
QA GUIDANCE DOCUMENT
PAGE 1 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
Structural Fabrication Quality Assurance Guidance Document
Description The purpose of this document is to provide the Michigan Department of Transportationj` (MDOT)
Structural Fabrication Unit guidance to supplement C;EJj` CNaR_VNY` GbNYVaf 7``urance Procedures
(MQAP) Manual. This guidance document will be used to ensure statewide consistency in performing
quality assurance (QA) verification inspection at fabrication facilities. The Structural Fabrication Unit is
_R`]\[`VOYR S\_ VZ]YRZR[aV[T aUR ;R]N_aZR[aj` ^bNYVaf N``b_N[PR ]_\T_NZ S\_ `a_bPab_NY RYRZR[a`
_R^bV_RQ a\ OR NPPR]aRQ ON`RQ \[ h=NO_VPNaV\[ @[`]RPaV\[i ]R_ C;EJj` CG7F Canual and utilizes
vendors to provide the shop inspection. It is imperative for the quality assurance inspector (QAI) to
completely understand their role and responsibilities when performing QA verification inspection on
MDOT projects to ensure a successful QA program. It is important to note that this document is not
contractual and all project related decisions should be based on the project specifications. This
document is broken down into the following sections:
1. Definitions
2. Contact Information
3. Responsibilities
4. QAI Roles and Responsibilities
5. QAI Frequent Questions and Answers
1. DefinitionsBelow is a list of terms that are significant to this guidance document:
1.1 Contractor The Contractor is responsible for proper completion of all tasks required by the contract.
Subcontractors, including fabricators, erectors, and field painters, may be used by the Contractor,
but the Contractor retains responsibility for all material, operations, and the final product. The
Contractor should permit direct subcontractor interaction with MDOT to expedite the project, but
subcontractors must inform the Contractor of any proposed modifications to contract requirements.
1.2 Design Project Manager (PM) The Design PM can be the Engineer of Record or could be managing a consultant contract where
the consultant is the Engineer of Record.
1.3 Engineer The Engineer can be the Director of the Department of Transportation or the MDOT Construction
Engineer designated by the Director, acting directly or through authorized representatives, who is
responsible for engineering supervision of the construction. The Engineer has the authority to allow
exceptions to contract document requirements.
3
STRUCTURAL FABRICATION UNIT
V092517
QA GUIDANCE DOCUMENT
PAGE 2 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
1.4 Engineer of Record (EOR) JU\`R ]_R]N_V[T aUR P\[a_NPa Q\PbZR[a`& V[PYbQV[T aU\`R _R`]\[`VOYR S\_ aUR `a_bPab_Rjs adequate
design. The Engineer of Record seals and signs the contract plans.
1.5 Fabricator The facility performing such shop activities as cutting, welding, drilling, punching, tying rebar,
tensioning strand, pouring concrete, cleaning and painting of structural steel, etc. The Fabricator also
includes any agents of the Fabricator, such as those who prepare shop detail drawings, perform non-
destructive examinations, paint, etc. In some cases the Fabricator may also be the Contractor, but
the Fabricator is typically a subcontractor.
1.6 Fabrication Inspection The examination by MDOT or the Fabricator of processes and products to verify general
conformance with contract requirements.
1.7 Fabrication Inspection Acceptance JUR SV_`a `aR] V[ C;EJj` ad\ ]N_a NPPR]aN[PR ]_\PR`` S\_ `a_bPab_NY RYRZR[a` _R^bV_RQ a\ OR NPPR]aRQ
ON`RQ \[ h=NO_VPNaV\[ @[`]RPaV\[i ]R_ C;EJj` CG7F Manual.
1.8 Field Inspection Acceptance The second `aR] V[ C;EJj` ad\ ]N_a NPPR]aN[PR ]_\PR`` S\_ `a_bPab_NY RYRZR[a` _R^bV_RQ a\ OR
NPPR]aRQ ON`RQ \[ h=NO_VPNaV\[ @[`]RPaV\[i ]R_ C;EJj` CG7F Manual.
1.9 Materials Quality Assurance Procedures Manual (MQAP) The formal written document prepared by MDOT that describes the policies and procedures used to
accept materials for incorporation into MDOT projects. The document contains inspection
procedures for fabricated structural precast (prestressed and non-prestressed) concrete, structural
steel, and other structural elements.
1.10 Michigan Department of Transportation (MDOT) The entity (owner) paying the Contractor to fulfill the terms of the contract. MDOT also encompasses
the Engineer who is authorized and responsible for engineering supervision of the construction. The
Engineer is an employee of MDOT; however, MDOT may contract with a professional firm to oversee
the day to day supervision with all critical decisions coming through the Engineer.
1.11 Nonconformance Report (NCR) An alteration in the work or a fabrication error that results in the element not meeting project
specifications. The fabricator generates a NCR submittal after fabrication has begun and their quality
control inspector (QCI) has noted a nonconformance to the project specifications.
Nonconformances are generally defined to be material or workmanship in nature and are further
classified by MDOT to be minor or major. Minor nonconformances can be repaired by the fabricator
without approval of a NCR, whereas major nonconformances require approval of a NCR.
1.12 Precast Concrete Precast concrete is a construction product produced by casting concrete in a reusable form, which is
then cured in a somewhat controlled environment, transported to the construction site, and lifted into
4
STRUCTURAL FABRICATION UNIT
V092517
QA GUIDANCE DOCUMENT
PAGE 3 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
place. Precast concrete can be either prestressed or non-prestressed. In contrast, cast-in-place (CIP)
concrete is poured into site-specific forms and cured on site.
1.13 Procedure Qualification Record (PQR) A production welding procedure specification (WPS) qualification is based on a procedure
qualification test record (PQR) produced by the Contractor in conformance with required heat input
qualifications and other code requirements. The test is designed to provide assurance that the weld
metal produced by welding in conformance with the provisions of the code must produce weld
metal strength, ductility, and toughness conforming to the code.
1.14 Quality Assurance (QA) Quality assurance (QA) encompasses the activities undertaken by the Owner to verify that the final
product satisfies contract requirements, including verifying that quality control is performed
effectively.
1.15 Quality Assurance Inspector (QAI) C;EJj` representative that is responsible for duties specified in the MDOT MQAP, with the authority to
accept work that meets contract requirements.
1.16 Quality Control (QC) The activities undertaken by the Contractor/Fabricator to ensure a product is provided that meets
contract requirements.
1.17 Quality Control Inspector (QCI) 7 ^bNYVSVRQ RZ]Y\fRR \S aUR =NO_VPNa\_ dU\ ]R_S\_Z` V[`]RPaV\[ N` QRSV[RQ Of aUR =NO_VPNa\_j`
Quality Control Plan.
1.18 Quality Control Plan (QCP) The formal written document prepared by the Fabricator and reviewed by a certification agency
(AISC, NPCA, PCI, etc.) that describes the policies and procedures used to verify that fabricated
structural precast (prestressed and non-prestressed) concrete, structural steel, and other structural
elements will satisfy the contract requirements.
1.19 Request for Information (RFI) Requests by the Fabricator seeking additional information or proposing alternate material, fabrication
method, or inspection method for the structural element.
1.20 Spot Inspection JUR _N[Q\Z ReNZV[NaV\[ \S aUR =NO_VPNa\_js processes or products for verification of conformance
with contract requirements.
1.21 Structural Fabrication Unit C;EJj` `]RPVNYVgRQ QA unit that is _R`]\[`VOYR S\_ VZ]YRZR[aV[T aUR ;R]N_aZR[aj` G7 ]_\T_NZ S\_ NYY
structural elements required to be accepted ON`RQ \[ h=NO_VPNaV\[ @[`]RPaV\[i ]R_ C;EJj` CG7F(
1.22 Welding Procedure Specification (WPS) Is a formal written document describing welding procedures, which provides direction to the welder
or welding operators for making sound and quality production welds as per the code requirements.
5
STRUCTURAL FABRICATION UNIT
V092517
QA GUIDANCE DOCUMENT
PAGE 4 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
The purpose of the document is to guide welders to the accepted procedures so that repeatable
and trusted welding techniques are used.
2. Contact InformationThe Structural Fabrication Unit can be contacted by phone or email. G7@j` N_R _R^bV_RQ a\ O_V[T b_TR[a
matters to the appropriate contact person by phone and then immediately follow up by email for record
and attach all applicable supporting documentation to the email. All other matters are required to be
submitted via email and then a call, if needed, can be setup. JUR Ia_bPab_NY =NO_VPNaV\[ K[Vaj` RZNVY
resource is shown below:
3. Responsibilities
3.1 Team Effort
3.1.1 The Contractor, Fabricator, and MDOT will approach quality control and quality assurance
as a team effort to facilitate accurate and timely construction.
3.1.2 All parties will cooperate and maintain open lines of communication so that problems can
be quickly addressed and resolved.
3.1.3 JUR G7@j` cR_VSVPNaV\[ Q\es not relieve the Fabricator from the responsibility to perform the
required testing and inspection and produce a product satisfying the contract.
3.2 Fabricator
3.2.1 Provide quality control to ensure that the finished product meets or exceeds contract
requirements.
3.2.2 Develop and implement a QCP that reflects a commitment to quality and describes the
quality control activities that will be employed on each project.
3.2.3 Provide MDOT with a copy of the QCP.
3.2.4 Submit shop drawings to MDOT for review with weld procedure specification (WPS) and
supporting procedure qualification record (PQR), as applicable.
3.2.5 Provide structural precast concrete Material Source List (MSL) prior to the prefabrication
meeting.
3.2.6 Provide qualified QCIs who report to personnel responsible for quality control as defined by
the QCP.
3.2.7 Provide MDOT with an accurate notification before beginning work in the shop and all
production scheduling as required by the contract requirements.
3.2.8 F_R`R[a NYY ZNaR_VNY S\_ aUR G7@j` NPPR]aN[PR V[ N ZN[[R_ aUNa dVYY NYY\d N thorough
inspection of components and assemblies.
3.2.9 Provide the QAI full access to shop facilities where the work is being stored, fabricated, or
assembled.
6
STRUCTURAL FABRICATION UNIT
V092517
QA GUIDANCE DOCUMENT
PAGE 5 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
3.2.10 Provide the QAI with all approved shop drawings, NCRs, RFIs, MDOT Welder Qualification
test reports, WPSs, QC reports, material certifications/test reports, NDE reports,
personnel/plant certifications, equipment calibration reports, and all other applicable
documents in a timely manner as required by the contract requirements.
3.2.11 Keep the QAI informed prior to performing in-process repairs, NCRs (if applicable), QC
inspection activities, and pending nondestructive examination (if applicable).
3.3 MDOT
3.3.1 M\[Va\_ aUR =NO_VPNa\_j` P\[a_\Y \S aUR \]R_NaV\[` N[Q cR_VSf P\[S\_ZVaf \S aUR d\_X with the
contract requirements.
3.3.2 KRR] aUR =NO_VPNa\_js QCP confidential.
3.3.3 Observe fabrication (either on a schedule or at random) and perform testing of materials
N[Q SNO_VPNaRQ RYRZR[a` N` [RPR``N_f a\ P\[SV_Z aUR RSSRPaVcR[R`` \S aUR =NO_VPNa\_j` G9F(
3.3.4 MDOT has the right to observe all phases of the work, from initial receipt and preparation of
raw materials through prestressing, tying steel, fresh concrete testing, placing concrete,
testing cylinders, repairs, burning and cutting, welding, nondestructive testing, cleaning,
coating, shipping, and any other activities deemed appropriate by MDOT.
3.3.5 The frequency and nature of QA inspection will vary with the type of structure, experience
\S aUR =NO_VPNa\_& `a_R[TaU \S aUR =NO_VPNa\_j` G9 \_TN[VgNaV\[& N[Q \aUR_ `VZVYN_ SNPa\_`
that affect the quality of work.
3.3.6 Verify that production quality and fabrication processes generally satisfy contract
requirements, including the QCP.
3.3.7 Accept materials and fabricated elements that satisfy the contract requirements.
3.3.8 Notify MDOT when fabricator ships elements for projects, and specify if the shipment is the
final shipment for the project.
3.3.9 Submit project file to MDOT within one week of final shipment of elements.
3.3.10 MDOT will not waive items that are contractual obligations of the Fabricator and will not
accept material that does not conform to the contract requirements. However, based on
experience and knowledge of the specific situation, the Engineer may accept materials
and elements that are not in conformance with the contract and may allow material
substitutions. See the following two documents for more information:
' MDOT Structural Fabrication RFI Process
' MDOT Structural Fabrication Nonconformance Policy
3.3.11 MDOT dVYY [\a QV_RPa aUR =NO_VPNa\_j` d\_X( ?\dRcR_& MDOT should advise the Fabricator to
discontinue any operation that would result in noncompliance with the contract.
3.3.12 MDOT dVYY QV_RPa NYY \SSVPVNY P\ZZb[VPNaV\[` a\ aUR =NO_VPNa\_j` ^bNYVaf P\[a_\Y \_
management as determined in the prefabrication meeting.
3.3.13 MDOT will not convey directives or personal judgements about overall shop quality or
concerns about employee competence to production personnel.
7
STRUCTURAL FABRICATION UNIT
V092517
QA GUIDANCE DOCUMENT
PAGE 6 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
3.3.14 MDOT will not publish, copy, or distribute any proprietary information, documents, or forms
received from the Fabricator for any purpose other than the contractual needs of MDOT.
3.4 Prefabrication Meetings Prefabrication meetings facilitate effective quality control and quality assurance and are conducted
Of C;EJj` Ia_bPab_NY =NO_VPNaV\[ K[Va ]_ior to the start of fabrication and preferably after shop
drawings have been approved. The Structural Fabrication Unit, QAI, Fabricator, and QCI must be
present, whereas the Engineer and Contractor should be present to ensure a team effort to facilitate
accurate and timely construction. Quality assurance and quality control contact information will be
shared during this meeting to ensure effective and timely communication.
4. QAI Roles and Responsibilities
4.1 Qualifications of the QAIQualification requirements of the QAI is covered in the MDOT MQAP Manual for the type of inspection
required.
4.2 Equipment Requirements of the QAIEquipment requirements of the QAI is covered in the MDOT MQAP Manual for the type of inspection
required.
4.3 SchedulingThe scheduling of inspection and other QA functions can have a significant impact on the project.
The QAI must follow these guidelines:
4.3.1 Coordinate with the QCI for anticipated production scheduling to anticipate timing and
staffing needs. Discuss the progress of the work with appropriate fabrication personnel
designated during the prefabrication meeting.
4.3.2 Schedule inspections in a timely manner to facilitate fabrication progress, especially if
multiple shifts are used.
4.3.3 Discuss with the Structural Fabrication Unit whether additional presence in the shop is
required.
4.3.4 Document problems with scheduling inspection, including inaccurate information from
fabrication personnel and production delays.
4.4 Role of the QAI
4.4.1 Perform verification tests, measurements, inspection, or observations to ensure that
fabricated elements conform to the contract requirements. Although the QAI does not
perform the QC work, some QA activities may duplicate a portion of the QC activity for
verification purposes.
4.4.2 If there are questions about a requirement or level of quality, contact the Structural
Fabrication Unit and, if appropriate, alert the Fabricator.
4.4.3 Conduct consistent inspections based on the contract requirements and obtain assistance
from the Structural Fabrication Unit as needed.
8
STRUCTURAL FABRICATION UNIT
V092517
QA GUIDANCE DOCUMENT
PAGE 7 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
4.4.4 Be familiar with the QCP to better understand the QC operations of the shop.
4.5 Responsibilities of the QAI See subsection 3.3 above for a list of QAI responsibilities.
4.6 Interaction with the Fabricator QCI
4.6.1 LR_VSf aUR RSSRPaVcR[R`` \S aUR G9@j` RcNYbNaV\[ \S aUR d\_X(
4.6.2 Perform verification inspection after the QCI has completed their inspection and testing in
accordance with the =NO_VPNa\_j` QCP. However, serious problems noted at any time or
stage of fabrication must be immediately pointed out to the QCI.
4.6.3 Though QA inspection may include all aspects of fabrication, the QAI must not supersede
QC, which is the responsibility of the Fabricator. If QC is not accomplishing its role then the
Structural Fabrication Unit, Engineer, Contractor, and Fabricator must determine the
necessary corrections.
4.7 Interaction with Fabricator @S aUR =NO_VPNa\_j` V[^bV_VR` V[c\YcR QR`VT[ ^bR`aV\[`& ZNaR_VNY `bO`aVabaV\[`& NYaR_[NaR SNO_VPNaV\[
methods, or items that are beyond the authority of the QAI, refer them to (%*/EA .B@C3BC@19
Fabrication Request for Information Process. If thR =NO_VPNa\_j` V[^bV_VR` V[c\YcR SNO_VPNaV\[ \_ ZNaR_VNY
nonconformance questions, refer them to (%*/EA .B@C3BC@19 &12@831B8=< )=<3=<6=@;1<35 -5>=@B8<7
Process. Do not direct the fabricator.
4.8 Interpretation of the Contract Review contract requirements and seek guidance from the Structural Fabrication Unit if the QAI has
questions. Do not direct the Fabricator.
4.9 Fabrication Observation
4.9.1 Establish a pattern of regular and frequent observations during the progress of work to
verify satisfactory workmanship without delaying production or missing critical operations.
4.9.2 Coordinate verifications with the QCI and accomplish them with minimal additional
material handling by the Fabricator and with as little interference with the work in process
as possible.
4.9.3 Though there are not designated points during fabrication when the suitability of materials
must be checked, problems should be discovered and addressed as early as possible.
4.9.4 Provide narrative record keeping in accordance with applicable sections of the MQAP
manual.
4.10 Nonconforming Materials and Workmanship See (%*/EA .B@C3BC@19 &12@831B8=< )=<3=<6=@;1<35 +=983D and (%*/EA .B@C3BC@19 &12@831B8=<
Nonconformance Reporting Process for more information.
4.11 Final Acceptance of the Work Acceptance of structural elements must be in accordance with (%*/EA (,$+ (1<C19.
9
STRUCTURAL FABRICATION UNIT
V092517
QA GUIDANCE DOCUMENT
PAGE 8 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
5. QAI Frequent Questions and Answers The purpose of this section is to provide answers to frequently asked questions to ensure consistency and
alignment.
5.1 Fabricating without Approved Shop Drawings The QAI must notify the Structural Fabrication Unit immediately if the Fabricator is working without
MDOT approved shop drawings. Approved shop drawings are required prior to stamping elements
approved for shipping.
5.2 Inspecting Approved Repair Plans QAI must have the approved repair plan in hand prior to performing QA verification inspection of the
repair. Verification inspection also includes confirming that production and QCI have the approved
repair plan. If production and QCI do not have the approved plan then the QAI must notify them
that they are required to have the approved plan in hand during all aspects of the repair. If the
Fabricator begins working on the repair without the approved plan then the QAI must notify the
Fabricator of their observation in writing immediately and carbon copy the Structural Fabrication. The
Structural Fabrication Unit will notify the Engineer and Fabricator that the repair is recommend to be
rejected.
5.3 Stamping Elements Approved for Use QAI must have approved shop drawings prior to stamping any element approved for use. Elements
proposed to be shipped by the Fabricator that are not in general conformance with the approved
shop drawings must not be stamped. The only exception is if a nonconformance report (NCR) has
been approved by MDOT. Approved NCRs are to be used in conjunction with approved shop
drawings for acceptance. If elements are not in conformance with the approved shop drawings
then they are not to be stamped approved for use by the QAI. If requests for information (RFI) have
been approved by MDOT for the project then they must be incorporated into the shop drawings, if
applicable, prior to shipping.
5.4 Welder Qualification Testing See (%*/EA 05945@ ,C1986831B8=< +@=7@1; for all welding information.
5.5 As-Built Shop Drawings The Fabricator is required to submit as-built shop drawings to MDOT for historical purposes. All
approved RFIs that are incorporated into the project must be added to the shop drawings and
submitted to MDOT for review and approval. Very minor changes toward the end of fabrication must
be documented and submitted as as-built shop drawings to the QAI prior to shipping. The Structural
Fabrication Unit can provide more guidance on a project by project basis as to what constitutes a
shop drawing revision and what is considered an as-built.
10
(This page intentionally left blank)
(This page intentionally left blank)
@3G7E<3?F DH3?<GK 3FFHE3A57 CEB576HE7F @3AH3?
#$,-'$( "+%.)&*-
BN]YMP[ *()0 7OT]TYX <X LNNY[OLXNP `T]S ]SP *()*
F]LXOL[O FZPNTQTNL]TYX\ QY[ 5YX\][^N]TYX
5BAFGEH5G<BA 8<7?6 F7EI<57F 6<I<F<BA
11
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
,'(, CE7FGE7FF76 FGEH5GHE3? CE753FG 5BA5E7G7 834E<53G<BA
1+-1+-.+ NYef[
<+ O^_i fh[ijh[ii[Z ijhkYjkhWb fh[YWij YedYh[j[ \WXh_YWj_ed _dif[Yj_ed fheY[Zkh[ i^ekbZ X[ ki[Z je W_Z j^[ gkWb_jo WiikhWdY[ _dif[Yjeh &L<D' _d _dj[hfh[j_d] WdZ [d\ehY_d] j^[ YedjhWYj \eh fh[ijh[ii[Z YedYh[j[ [b[c[dji+ AWXh_YWj_ed _dif[Yj_ed _dYbkZ[i j^[ j_c[ \hec l[h_\o_d] cWj[h_Wbi ki[Z \eh \WXh_YWj_ed j^hek]^ beWZ_d] \eh i^_ff_d] je j^[ YedijhkYj_ed i_j[+
1+-1+-/+ M[\[h[dY[ ?eYkc[dji
<+ L<D ckij ^Wl[ W j^ehek]^ ademb[Z][ e\ j^[ \ebbem_d] h[\[h[dY[i7
.+ O^[ \ebbem_d] i[Yj_edi e\ j^[ H?JO NjWdZWhZ Nf[Y_\_YWj_edi \eh >edijhkYj_ed &H?JONN>' Wi ceZ_\_[Z Xo ikffb[c[djWb if[Y_\_YWj_ed ./NN*--.< s @hhWjW) Wi Wffb_YWXb[7
N[Yj_ed .-1 >edjheb e\ j^[ Reha N[Yj_ed .-2 >edjheb e\ j^[ HWj[h_Wbi N[Yj_ed 4-5 Kh[ijh[ii[Z >edYh[j[
/+ O^[ \ebbem_d] if[Y_Wb fhel_i_edi) Wi Wffb_YWXb[7
./NK*.-2< NekhY[ e\ Nj[[b WdZ Dhed &=ko <c[h_YW'
./NK*3-1> L> WdZ <YY[fjWdY[ e\ K>> \eh NjhkYjkhWb Kh[YWij >edYh[j[
./NK*4-5< Nf[Y_Wb Khel_i_ed \eh NjhWdZ ?[XedZ_d]
./NK*4-5= Kh[ijh[ii[Z >edYh[j[ =kbX*O[[ =[Wc
0+ H?JO NjhkYjkhWb Kh[YWij >edYh[j[ L<D HWdkWb
1+ >edijhkYj_ed A_[bZ N[hl_Y[i ?_l_i_ed &>AN' HWj[h_Wbi NekhY[ Bk_Z[ &HNB'
2+ H?JO NjhkYjkhWb AWXh_YWj_ed LkWb_jo <iikhWdY[ Bk_ZWdY[ ?eYkc[dj
3+ H?JO NjhkYjkhWb AWXh_YWj_ed Pd_j @*>edijhkYj_ed KheY[ii
4+ Kh[\WXh_YWj_ed c[[j_d] c_dkj[i &_\ WlW_bWXb['
=+ L<D ckij X[ \Wc_b_Wh m_j^ j^[ \ebbem_d] h[\[h[dY[i7
.+ H?JO NjhkYjkhWb AWXh_YWj_ed M[gk[ij \eh Dd\ehcWj_ed KheY[ii
/+ H?JO N^ef ?hWm_d] M[l_[m KheY[ii
0+ H?JO NjhkYjkhWb AWXh_YWj_ed IedYed\ehcWdY[ KheY[ii
1+ H_Y^_]Wd O[ij H[j^eZi
HOH .-/ H_Y^_]Wd O[ij H[j^eZ \eh <XhWi_ed M[i_ijWdY[ e\ <]]h[]Wj[ Xo j^[ Gei <d][b[i HWY^_d[
HOH .-5 H_Y^_]Wd O[ij H[j^eZ \eh HWj[h_Wbi A_d[h j^Wd Ie+ 42 N_[l[ _d H_d[hWb <]]h[]Wj[i Xo RWi^_d]
HOH .-6 H_Y^_]Wd O[ij H[j^eZ \eh N_[l[ <dWboi_i e\ A_d[) ?[di[ BhWZ[Z) Jf[d BhWZ[Z) WdZ >eWhi[ <]]h[]Wj[i _d j^[ A_[bZ
HOH ..1 H_Y^_]Wd O[ij H[j^eZ \eh HWa_d] >edYh[j[ Nf[Y_c[di \eh Ah[[p[*O^Wm O[ij_d] e\ >edYh[j[ >eWhi[ <]]h[]Wj[
HOH ..2 H_Y^_]Wd O[ij H[j^eZ \eh O[ij_d] >edYh[j[ \eh ?khWX_b_jo Xo MWf_Z
12
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
Ah[[p_d] _d <_h WdZ O^Wm_d] _d RWj[h
HOH /-3 H_Y^_]Wd O[ij H[j^eZ \eh Pi[ e\ PdXedZ[Z >Wfi _d ?[j[hc_dWj_ed e\ >ecfh[ii_l[ Njh[d]j^ e\ CWhZ[d[Z >edYh[j[ >ob_dZ[hi
2+ <<NCOJ NjWdZWhZi
O // >ecfh[ii_l[ Njh[d]j^ e\ >ob_dZh_YWb >edYh[j[ Nf[Y_c[di
O /0 HWa_d] WdZ >kh_d] >edYh[j[ O[ij Nf[Y_c[di _d j^[ A_[bZ
O /0. >Wff_d] >ob_dZh_YWb >edYh[j[ Nf[Y_c[di
3+ <NOH NjWdZWhZi
< .52 NjWdZWhZ Nf[Y_\_YWj_ed \eh Nj[[b R[bZ[Z R_h[ AWXh_Y) KbW_d) \eh >edYh[j[ M[_d\ehY[c[dj
< 1.3 NjWdZWhZ Nf[Y_\_YWj_ed \eh Gem*M[bWnWj_ed) N[l[d*R_h[ Nj[[b NjhWdZ \eh Kh[ijh[ii[Z >edYh[j[
< 164 NjWdZWhZ Nf[Y_\_YWj_ed \eh Nj[[b R[bZ[Z R_h[ AWXh_Y) ?[\ehc[Z) \eh >edYh[j[ M[_d\ehY[c[dj
> 0. NjWdZWhZ KhWYj_Y[ \eh HWa_d] WdZ >kh_d] >edYh[j[ O[ij Nf[Y_c[di _d j^[ A_[bZ
> 06 NjWdZWhZ O[ij H[j^eZ \eh >ecfh[ii_l[ Njh[d]j^ e\ >ob_dZh_YWb >edYh[j[ Nf[Y_c[di
> 61 NjWdZWhZ Nf[Y_\_YWj_ed \eh M[WZo*H_n[Z >edYh[j[
> .03 NjWdZWhZ O[ij H[j^eZ \eh N_[l[ <dWboi_i e\ A_d[ WdZ >eWhi[ <]]h[]Wj[i
> .05 O[ij H[j^eZ \eh ?[di_jo &Pd_j R[_]^j') T_[bZ WdZ <_h >edj[dj &BhWl_c[jh_Y' e\ >edYh[j[
> .10 NjWdZWhZ O[ij H[j^eZ \eh Nbkcf e\ CoZhWkb_Y >[c[dj >edYh[j[
> .4/ NjWdZWhZ KhWYj_Y[ \eh NWcfb_d] Ah[i^bo H_n[Z >edYh[j[
> .40 NjWdZWhZ O[ij H[j^eZ \eh <_h >edj[dj e\ Ah[i^bo H_n[Z >edYh[j[ Xo j^[ Qebkc[jh_Y H[j^eZ
> /0. NjWdZWhZ O[ij H[j^eZ \eh <_h >edj[dj e\ Ah[i^bo H_n[Z >edYh[j[ Xo j^[ Kh[iikh[ H[j^eZ
> 262 NjWdZWhZ Nf[Y_\_YWj_ed \eh =b[dZ[Z CoZhWkb_Y >[c[dji
> 3.4 NjWdZWhZ KhWYj_Y[ \eh >Wff_d] >ob_dZh_YWb >edYh[j[ Nf[Y_c[di
> ./0. NjWdZWhZ KhWYj_Y[ \eh Pi[ e\ PdXedZ[Z >Wfi _d Z[j[hc_dWj_ed e\ >ecfh[ii_l[ Njh[d]j^ e\ CWhZ[d[Z >edYh[j[ >ob_dZ[hi
> ./3- NjWdZWhZ O[ij H[j^eZ \eh Kej[dj_Wb <baWb_ M[WYj_l_jo e\ <]]h[]Wj[i &HehjWh =Wh H[j^eZ'
> .234 NjWdZWhZ O[ij H[j^eZ \eh ?[j[hc_d_d] j^[ Kej[dj_Wb <baWb_*N_b_YW M[WYj_l_jo e\ >ecX_dWj_edi e\ >[c[dj_j_eki HWj[h_Wbi WdZ <]]h[]Wj[ &<YY[b[hWj[Z HehjWh =Wh H[j^eZ'
4+ K>D NW\[jo WdZ Geii Kh[l[dj_ed HWdkWb NGK*.--
5+ H?JO <YY_Z[dj Kh[l[dj_ed KbWd
13
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
1+-1+-0+ LkWb_\_YWj_edi) M[ifedi_X_b_j_[i) ?kj_[i) WdZ @gk_fc[dj
<+ LkWb_\_YWj_edi e\ j^[ L<D s L<D f[h\ehc_d] j^[ \WXh_YWj_ed _dif[Yj_ed ckij feii[ii j^[ \ebbem_d] gkWb_\_YWj_edi7
.+ H_Y^_]Wd Khe\[ii_edWb @d]_d[[h &K@' b_Y[di[ eh Kh[YWij,Kh[ijh[ii[Z >edYh[j[Ddij_jkj[ &K>D' O[Y^d_Y_Wd G[l[b DD8
/+ H_Y^_]Wd >edYh[j[ <iieY_Wj_ed &H><' G[l[b D A_[bZ O[ij_d] O[Y^d_Y_Wd Y[hj_\_YWj_edeh <c[h_YWd >edYh[j[ Ddij_jkj[ &<>D' >edYh[j[ A_[bZ O[ij_d] O[Y^d_Y_Wd s BhWZ[ D&[nY[fj f[h_eZ e\ [\\[Yj_l[d[ii m_bb X[ h[ZkY[Z \hec 2 o[Whi je 0 o[Whi je cWjY^ H><'8WdZ
0+ H_Y^_]Wd >[hj_\_[Z <]]h[]Wj[ O[Y^d_Y_Wd &H><O' G[l[b D &edbo h[gk_h[Z \eh W]]h[]Wj[iWcfb_d]'+
=+ M[ifedi_X_b_j_[i e\ j^[ L<D s L<D f[h\ehc_d] j^[ \WXh_YWj_ed _dif[Yj_ed _i dej f[hc_jj[Z je cWa[ Y^Wd][i je j^[ YedjhWYj WdZ ^Wi j^[ \ebbem_d] h[ifedi_X_b_j_[i7
O^[ >edjhWYjeh) AWXh_YWjeh) WdZ H?JO m_bb WffheWY^ gkWb_jo Yedjheb WdZ gkWb_jo WiikhWdY[ Wi W j[Wc [\\ehj je \WY_b_jWj[ WYYkhWj[ WdZ j_c[bo YedijhkYj_ed+ L<Dvi l[h_\_YWj_ed Ze[i dej h[b_[l[ j^[ AWXh_YWjeh \hec j^[ h[ifedi_X_b_jo je f[h\ehc j^[ h[gk_h[Z j[ij_d] WdZ _dif[Yj_ed je fheZkY[ W fheZkYj iWj_i\o_d] j^[ YedjhWYj+ O^ek]^ L< _dif[Yj_ed cWo _dYbkZ[ Wbb Wif[Yji e\ \WXh_YWj_ed) j^[ L<D ckij dej ikf[hi[Z[ L>) m^_Y^ _i j^[ h[ifedi_X_b_jo e\ j^[ AWXh_YWjeh+ D\ L> _i dej WYYecfb_i^_d] _ji heb[ j^[d j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j) @d]_d[[h) >edjhWYjeh) WdZ AWXh_YWjeh ckij Z[j[hc_d[ j^[ d[Y[iiWho Yehh[Yj_edi+
L<D _i j^[ h[ifedi_Xb[ fWhjo) h[fh[i[dj_d] j^[ @d]_d[[h) m^e f[h\ehci gkWb_jo WiikhWdY[ l[h_\_YWj_ed _dif[Yj_ed ed j^[ [b[c[dj W\j[h gkWb_jo Yedjheb &L>' _dif[Yji WdZ Wffhel[i j^[ _j[c e\ meha+ O^[ L<D ckij X[ Wj j^[ \WXh_YWj_ed \WY_b_jo Wj Wbb j_c[i Zkh_d] \WXh_YWj_ed Wi h[gk_h[Z Xo j^[ _dif[Yj_ed fheY[Zkh[ ijWj[Z X[bem+ D\ _iik[i Wh_i[) _j m_bb X[ Wj j^[ @d]_d[[hvi Z_iYh[j_ed m^[j^[h je _dYh[Wi[ j^[ b[l[b e\ L< _dif[Yj_ed+
Dj _i j^[ @d]_d[[hvi h[ifedi_X_b_jo je [d]W][ j^[ @d]_d[[h e\ M[YehZ &@JM' m^[d cWa_d] ijhkYjkhWb Z[Y_i_edi+ O^[ @d]_d[[h _i Wbie h[ifedi_Xb[ \eh \ebbem_d] _dj[hdWb H?JO fheY[Zkh[i \eh h[l_[m WdZ WffhelWb e\ i^ef ZhWm_d]i) \WXh_YWj_ed fheY[Zkh[i) h[gk[ij \eh _d\ehcWj_ed &MAD') dedYed\ehcWdY[ h[fehji &I>M') WdZ \eh fhe\[ii_edWb Z[Y_i_ed cWa_d] ed \WXh_YWj_ed fheXb[ci j^Wj Wh_i[+ O^[ @d]_d[[h h[b_[i ed j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j je cWdW][ WdZ Wii_ij m^[d Wffhefh_Wj[+ O^[ @d]_d[[h ^Wi j^[ fh[he]Wj_l[ \eh ^ebZ_d] W fh[\WXh_YWj_ed c[[j_d] m_j^ j^[ AWXh_YWjeh je Z_iYkii WdZ YbWh_\o j^[ YedjhWYj fbWdi WdZ if[Y_\_YWj_edi+ O^[ @d]_d[[h _i j^[ h[ifedi_Xb[ fWhjo m^e [dikh[i H?JOvi \WXh_YWj_ed L< fhe]hWc _i \ebbem[Z \eh _dif[Yj_ed WdZ WYY[fjWdY[ e\ j^[ [b[c[dj+
AWXh_YWj_ed i^ekbZ fheY[[Z edbo m_j^ Wffhel[Z i^ef ZhWm_d]i+ Cem[l[h) _\ j^[ AWXh_YWjeh ckij fheY[[Z fh_eh je h[Y[_fj e\ Wffhel[Z i^ef ZhWm_d]i &f[h\ehc_d] meha Wj j^[_h emd h_ia') [dikh[ j^Wj j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j _i WmWh[ e\ j^_i WYj_l_jo WdZ WmW_j _dijhkYj_ed ed ^em je fheY[[Z+ D\ j^[ @d]_d[[h f[hc_ji j^[ meha je fheY[[Z m_j^ekj Wffhel[Z i^ef ZhWm_d]i) fheY[[Z m_j^ XWi_Y L< \kdYj_edi ki_d] j^[ ded*Wffhel[Z i^ef ZhWm_d]i+ GWj[h) l[h_\o dej[i W]W_dij Wffhel[Z ZhWm_d]i+ Iej_\o j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j _cc[Z_Wj[bo _\ \WXh_YWj_ed _i dej _d Yed\ehcWdY[ m_j^ j^[ Wffhel[Z i^ef ZhWm_d]i+
>+ ?kj_[i e\ j^[ L<D s L<D f[h\ehc_d] j^[ \WXh_YWj_ed _dif[Yj_ed ^Wi j^[ \ebbem_d] Zkj_[i7
.+ L<D ckij j^ehek]^bo kdZ[hijWdZ j^[ YedjhWYj+
14
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
/+ L<D ckij l[h_\o ij[[b cWj[h_Wb Y[hj_\_YWj_edi i^em Yecfb_WdY[ m_j^ =ko <c[h_YWYedjhWYj h[gk_h[c[dji+
0+ L<D ckij X[ fhe\_Y_[dj _d f[h\ehc_d] \h[i^ YedYh[j[ j[iji) iWcfb_d] W]]h[]Wj[ WdZej^[h cWj[h_Wbi) l[h_\o_d] cWj[h_Wb jhWY[WX_b_jo) WdZ _dif[Yj_d] YedYh[j[ fekhi+
1+ L<D ckij X[ fhe\_Y_[dj _d mh_j_d] h[fehji WdZ ki_d] Yecfkj[hi+
2+ L<D ckij dej_\o j^[ @d]_d[[h _\ fheZkYj_ed X[]_di X[\eh[ Wffhel[Z i^ef ZhWm_d]i Wh[ed j^[ i^ef \beeh WdZ fhel_Z[Z je j^[ L<D+
3+ L<D ckij Yecckd_YWj[ Wbb YedY[hdi j^hek]^ L>D eh m^ec[l[h j^[ AWXh_YWjeh Z_h[YjiZkh_d] j^[ fh[\WXh_YWj_ed c[[j_d]+
4+ L<D ckij Yecckd_YWj[ m_j^ L>D je eXjW_d j^[ meha iY^[Zkb[+
5+ L<D ckij \ebbem MDOT’s Structural Fabrication E-Construction Process \eh Ybei_d]ekj \WXh_YWj_ed _dif[Yj_ed \_b[+
?+ ?[\_Y_[dY_[i ed GeYWb <][dYo Khe`[Yji s H?JOvi L<D ckij dej_\o j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j _\ j^[o eXi[hl[ \WXh_YWj_ed eh _dif[Yj_ed Z[\_Y_[dY_[i ed beYWb W][dYo fhe]hWc &G<K' fhe`[Yji+ O^[ NjhkYjkhWb AWXh_YWj_ed @d]_d[[h m_bb h[fehj j^[ Z[\_Y_[dY_[i l_W [cW_b je j^[ @d]_d[[h j^Wj _i h[ifedi_Xb[ \eh YedijhkYj_ed el[hi_]^j e\ j^[ beYWb W][dYo fhe`[Yj WdZ YWhXed Yefo j^[ Wffb_YWXb[ >AN WdZ ?[i_]d ?_l_i_ed G<K @d]_d[[hi+
@+ Ddif[Yj_ed AWY_b_j_[i WdZ <YY[ii s AWY_b_j_[i \eh j^[ L<D ckij X[ fhel_Z[Z Xo j^[ AWXh_YWjeh f[h YedjhWYj+ L<D ckij ^Wl[ WYY[ii je Wbb fWhji e\ j^[ meha Wj Wbb j_c[i+ O^[ Wkj^eh_jo WdZ ][d[hWb Zkj_[i e\ j^[ L<D Wh[ if[Y_\_[Z _d N[Yj_ed .-1+-.+? WdZ @ e\ j^[ H?JO NN>+
A+ Ddif[Yj_ed @gk_fc[dj s L<D m_bb X[ \khd_i^[Z m_j^ j^[ \ebbem_d] _j[ci Xo j^[ @d]_d[[h7
.+ >edjhWYj &H?JO NN>) if[Y_Wb fhel_i_edi) ijWdZWhZ fbWdi) if[Y_Wb Z[jW_bi) fbWdi^[[ji) [jY+'
/+ <ffhel[Z i^ef ZhWm_d]i &fhel_Z[Z Xo AWXh_YWjeh'
0+ <YY[ii je H?JOvi AWXh_YWj_ed Ddif[Yj_ed $ >edijhkYj_ed Noij[c &AD>N'
1+ H?JO i^ef WffhelWb ijWcf
L<D ckij fhel_Z[ j^[ \ebbem_d] _dif[Yj_ed [gk_fc[dj7
.+ >ecfkj[h m_j^ ^_]^ if[[Z _dj[hd[j WYY[ii
/+ >[bb f^ed[ m_j^ YWc[hW
0+ AbWi^b_]^j
1+ O[cf[hWjkh[ c[Wikh_d] Z[l_Y[i YWfWXb[ e\ Yel[h_d] j^[ hWd][ \hec -qA je /--qA
2+ Ah[i^ YedYh[j[ j[ij_d] [gk_fc[dj &j^[hcec[j[h) ibkcf Yed[ a_j) WdZ W_h*c[j[h'
3+ H[Wikh_d] Z[l_Y[i &/-- \eej WdZ /- \eej ij[[b jWf[ WdZ YWb_f[hi'
4+ NjhW_]^j[Z][ WdZ b[l[bi
5+ NW\[jo [gk_fc[dj
6+ Jj^[h Wi d[[Z[Z \eh j^[ fhe`[Yj
15
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
1+-1+-1+ Ddif[Yj_ed KheY[Zkh[
<+ Kh[\WXh_YWj_ed H[[j_d] s Kh[\WXh_YWj_ed c[[j_d]i \WY_b_jWj[ [\\[Yj_l[ gkWb_jo Yedjheb WdZ gkWb_jo WiikhWdY[ ed j^[ fhe`[Yj WdZ Wh[ YedZkYj[Z Xo H?JOvi NjhkYjkhWb AWXh_YWj_ed Pd_j fh_eh je j^[ ijWhj e\ \WXh_YWj_ed WdZ fh[\[hWXbo W\j[h i^ef ZhWm_d]i ^Wl[ X[[d Wffhel[Z+ O^[ NjhkYjkhWb AWXh_YWj_ed Pd_j) L<D) AWXh_YWjeh) WdZ L>D ckij X[ fh[i[dj) m^[h[Wi j^[ @d]_d[[h WdZ >edjhWYjeh i^ekbZ X[ fh[i[dj je [dikh[ W j[Wc [\\ehj je \WY_b_jWj[ WYYkhWj[ WdZ j_c[bo YedijhkYj_ed+ LkWb_jo WiikhWdY[ WdZ gkWb_jo Yedjheb YedjWYj _d\ehcWj_ed m_bb X[ i^Wh[Z Zkh_d] j^_i c[[j_d] je [dikh[ [\\[Yj_l[ Yecckd_YWj_ed+
=+ AWXh_YWj_ed Ddif[Yj_ed s Kh[ijh[ii[Z YedYh[j[ ckij X[ \WXh_YWj[Z _d WYYehZWdY[ m_j^ j^[ H?JO NN> WdZ YedjhWYj+ L<D WdZ L>D ckij fWii WddkWb H?JO _dZ[f[dZ[dj WiikhWdY[ j[ij_d] &D<O' fh_eh je f[h\ehc_d] \h[i^ YedYh[j[ j[ij_d]+ AWXh_YWj_ed _dif[Yj_ed ckij X[ f[h\ehc[Z Wi i^emd X[bem7
.+ Kh[ijh[ii[Z YedYh[j[ \WXh_YWj_ed _dif[Yj_ed Yedi_iji e\ l[h_\o_d] Yecfb_WdY[ m_j^ j^[Wffhel[Z i^ef ZhWm_d]i) YedjhWYj) WdZ Wffhel[Z I>Mi+ MADi ckij X[ _dYehfehWj[Z_dje j^[ Wffhel[Z i^ef ZhWm_d]i \eh j^[ L<D je _dif[Yj je+
/+ <d Wffhel[Z HWj[h_Wbi NekhY[ G_ij &HNG' _i fhel_Z[Z je j^[ L<D Xo j^[ @d]_d[[h iej^Wj j^[ L<D ademi m^Wj cWj[h_Wbi Wh[ X[_d] _dYehfehWj[Z _dje j^[ fhe`[Yj WdZ m^Wjj^[ XWi_i e\ WYY[fjWdY[ _i+ O^[ HNG _i ki[Z je jhWYa cWj[h_Wb iWcfb_d] Xo j^[ L<DWdZ je \eij[h Yecckd_YWj_ed m_j^ L>D je [dikh[ Wbb h[gk_h[Z iWcfb_d] WdZ j[ij_d]eYYkhi _d W j_c[bo cWdd[h je fh[l[dj _cfWYji je j^[ fhe`[Yj iY^[Zkb[+ Dj _i j^[AWXh_YWjehvi h[ifedi_X_b_jo je dej_\o j^[ L<D m^[d cWj[h_Wbi Wh[ WlW_bWXb[ \eh iWcfb_d]+
0+ L<D X[]_di Xo _dif[Yj_d] cWj[h_Wbi j^Wj m_bb X[ ki[Z _d j^[ \WXh_YWj_ed fheY[ii WdZ[dikh[i j^[o Wh[ X[_d] ijeh[Z Yehh[Yjbo) jW]][Z \eh jhWY[WX_b_jo fkhfei[i) WdZ Wh[ _dYed\ehcWdY[ m_j^ j^[ YedjhWYj+ I[nj) j^[ L<D _dif[Yji j^[ AWXh_YWjehvi ef[hWj_edi je[dikh[ j^[ YedZ_j_ed e\ j^[ [gk_fc[dj WdZ meha Wh[W \eh Yed\ehcWdY[ je j^[ YedjhWYj+
1+ H?JOvi <YY_Z[dj Kh[l[dj_ed KbWd ijWj[i) tH?JO [cfbeo[[i i^Wbb dej [d]W][ _d WdoWYj m^_Y^ mekbZ [dZWd][h Wdej^[h [cfbeo[[ eh j^[ci[bl[iu+ L<D ckij dej_\o j^[@d]_d[[h _cc[Z_Wj[bo _\ meha YedZ_j_edi [n_ij j^Wj Wh[ dej iW\[+ D\ j^[ b[l[b e\_dif[Yj_ed Z_c_d_i^[i X[bem m^Wj _i if[Y_\_[Z _d j^_i L< fheY[Zkh[) Zk[ je iW\[joYedY[hdi) j^[d j^[ [b[c[dj m_bb dej X[ Wffhel[Z \eh ki[+
>+ NjhWdZ O[di_ed_d]
.+ General Information s R^_b[ j^[ ijhWdZ _i ij_bb l_i_Xb[) j^[ L<D ckij _dif[Yj j^[ ijhWdZije Wiikh[ j^Wj j^[o Wh[ \h[[ e\ e_b eh ej^[h \eh[_]d cWj[h_Wb+ NjhWdZi dej \h[[ e\ e_b eh\eh[_]d cWj[h_Wb) eh j^Wj YedjW_d a_dai) X[dZi) d_Yai) eh ej^[h Z[\[Yji &_dYbkZ_d] iYWb[eh [nY[ii_l[ hkij' m_bb X[ Xhek]^j je L>i Wjj[dj_ed j^Wj _dYehfehWj_ed e\ j^[i[dedYed\ehc_d] ijhWdZi m_bb h[dZ[h j^[ [b[c[dj kdWYY[fjWXb[ WdZ j^[ [b[c[dj m_bb dejX[ Wffhel[Z \eh ki[+
W+ NjhWdZi Wh[ fei_j_ed[Z je Zkfb_YWj[ j^[ ijhWdZ fWjj[hd i^emd ed j^[ Wffhel[Zi^ef ZhWm_d]i+ >^Wd]_d] j^[ l[hj_YWb fei_j_ed e\ j^[ ijhWdZi ckij ^Wl[ j^[WffhelWb e\ j^[ @d]_d[[h+ >^Wd]_d] j^[ ^eh_pedjWb fei_j_ed e\ j^[ ijhWdZi jei_cfb_\o \WXh_YWj_ed eh je WYYecceZWj[ jme ijhWdZ fWjj[hdi ed W X[Z _if[hc_jj[Z fhel_Z[Z j^[ \ebbem_d] _i ij_bb WY^_[l[Z7
_+ Nf[Y_\_[Z YedYh[j[ Yel[h8
__+ >[dj[h je Y[dj[h Z_ijWdY[ e\ ijhWdZi _i Wj b[Wij / _dY^[i8
___+ IkcX[h e\ ijhWdZi f[h hem _i cW_djW_d[Z8 WdZ
16
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
_l+ M[ikbj_d] ijhWdZ fWjj[hd _i iocc[jh_YWb WXekj j^[ l[hj_YWbY[dj[hb_d[ e\ j^[ [b[c[dj+
X+ Ome ijhWdZ fWjj[hdi _i f[hc_jj[Z je X[ YecX_d[Z ed W YWij_d] X[Z fhel_Z[Zj^[ \ebbem_d] YedZ_j_edi Wh[ c[j WdZ Wffhel[Z Xo j^[ @d]_d[[h7
_+ =edZ Xh[Wa[h ckij X[ fbWY[Z ed [WY^ e\ j^[ kdh[gk_h[Z ijhWdZi\eh j^[ \kbb b[d]j^ e\ [WY^ [b[c[dj+ =edZ Xh[Wa[h &h_]_Z) el[hi_p[Z)WdZ cedeb_j^_Y' cWj[h_Wb h[gk_h[i j^[ WffhelWb e\ j^[ @d]_d[[h+
__+ HWn_ckc e\ jme \kbb b[d]j^ Z[XedZ[Z ijhWdZi f[h [b[c[dj+
Y+ <bb ikffehji ki[Z je fei_j_ed j^[ ijhWdZ hemi ckij X[ e\ WZ[gkWj[ j^_Yad[iije ^ebZ j^[ jhk[ fei_j_ed e\ j^[ ijhWdZi+
Z+ Ddif[Yj_ed e\ j^[ j[di_ed_d] ef[hWj_ed Yedi_iji e\ l[h_\o_d] j^[ `WYa _iYWb_XhWj[Z WdZ eXi[hl_d] j^[ WYYkhWj[ _djheZkYj_ed e\ j^[ _d_j_Wb beWZ _d [WY^ e\j^[ ijhWdZi+ A_dWb ijh[ii_d] e\ j^[ ijhWdZi _i f[h\ehc[Z Xo Wffb_YWj_ed e\ beWZ_dje [WY^ ijhWdZ eh Wbb j^[ ijhWdZi Wj edY[ je fheZkY[ Wd [bed]Wj_ed [gkWb_d]W net elongation &]heii [bed]Wj_ed c_dki b_l[ [dZ i[Wj_d]'+ O^[ L<D ckijl[h_\o j^[ WbbemWXb[ ijh[ii _d [WY^ ijhWdZ Xo c[Wikh_d] j^[ net elongation e\j^[ _dZ_l_ZkWb ijhWdZi W\j[h j^[ \_dWb ijh[ii_d]+ O^[ cWn_ckc beWZ Wffb_[Z je[WY^ ijhWdZ) Wi _dZ_YWj[Z Xo j^[ fh[iikh[ ]Wk][ e\ j^[ j[di_ed_d] Z[l_Y[) _iWbie h[YehZ[Z \eh XWYa Y^[Ya_d]+
[+ L<D ckij Yecfb[j[ _dZ[f[dZ[dj ijhWdZ j[di_ed_d] YWbYkbWj_edi \eh l[h_\_YWj_edfkhfei[i m_j^ L>+
/+ O^[ L<D ckij l[h_\o j^[ beWZ &c[Wikh[Z _d fekdZi' WdZ [bed]Wj_ed &c[Wikh[Z _d_dY^[i' Wffb_[Z je [WY^ ijhWdZ ki_d] j^[ \ebbem_d] fheY[Zkh[i7
W+ Initial Load * <\j[h Wbb ijhWdZi Wh[ fei_j_ed[Z ed j^[ YWij_d] X[Z [WY^ ijhWdZ _ii[Ykh[Z Xo W ijhWdZ*l_i[ Wj j^[ Z[WZ [dZ WdY^eh_d] Xkba^[WZ e\ j^[ YWij_d]X[Z+ @WY^ ijhWdZ _i _dZ_l_ZkWbbo \_jj[Z Wj j^[ b_l[ [dZ WdY^eh_d] Xkba^[WZ&j[di_ed_d] [dZ' e\ j^[ YWij_d] X[Z WdZ Wd initial load _i Wffb_[Z [_j^[h ed[ijhWdZ Wj W j_c[ eh Wbb Wj edY[+ O^[ initial load ckij X[ Z[i_]dWj[Z Xo j^[AWXh_YWjeh WdZ ckij dej [nY[[Z 2--- fekdZi+
R^[d j^[ initial load _i h[WY^[Z) W h[\[h[dY[ cWha _i cWZ[ ed j^[ ijhWdZ edj^[ ekji_Z[ e\ j^[ b_l[ [dZ WdY^eh_d] Xkba^[WZ ikY^ j^Wj c[Wikh[c[dj e\Yedj_dk[Z [bed]Wj_ed YWd X[ eXi[hl[Z+ O^[ fkhfei[ e\ Wffbo_d] Wd initialload je [WY^ ijhWdZ _i je [ijWXb_i^ W YedijWdj ijWhj_d] fe_dj \eh c[Wikh_d] j^[net elongation c[Wikh[c[dji Xo [b_c_dWj_d] ibWYa _d j^[ ioij[c+ <j j^_i j_c[)j^[ ijhWdZ fWjj[hd _i Y^[Ya[Z Wj [WY^ Xkba^[WZ je cWa[ Y[hjW_d Wbb ijhWdZi Wh[_d j^[_h Yehh[Yj fei_j_ed WdZ ded[ e\ j^[ ijhWdZi Wh[ Yheii[Z+
Final Load s Di j^[ \ehY[ h[gk_h[Z X[oedZ initial load.
X+ Net Elongation s Pi_d] j^[ ijhWdZ cWha \hec j^[ fh[l_eki ij[f &W\j[h _d_j_WbbeWZ' j^[ \_dWb beWZ _i Wffb_[Z je j^[ ijhWdZ+ O^[ Z_ijWdY[ X[jm[[d j^[ ijhWdZcWha WdZ j^[ h[\[h[dY[ fe_dj ckij X[ c[Wikh[Z je j^[ d[Wh[ij -+-3/2 _dY^[ije Z[j[hc_d[ m^[d j^[ net elongation is reached+ D\ j^[ c[Wikh[Z [bed]Wj_ed_i [gkWb je eh ib_]^jbo ]h[Wj[h j^Wd &2 f[hY[dj eh b[ii' j^[ Yecfkj[Z [bed]Wj_ed)j^[ j[di_ed_d] ef[hWj_ed _i Yecfb[j[+ H_deh WZ`kijc[dji _d j^[ `WYa_d]ef[hWj_ed Wh[ cWZ[ je Xh_d] j^[ h[\[h[dY[ cWha je j^[ Z[i_h[Z c[Wikh[c[dj+R^[d j^[ j[di_ed_d] ef[hWj_ed \eh [WY^ ijhWdZ _i Yecfb[j[ WdZ X[\eh[ j^[j[di_ed _i h[b[Wi[Z \hec j^[ `WYa) W i[YedZ h[\[h[dY[ cWha ckij X[ cWZ[ ed
17
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
j^[ ijhWdZ Wj j^[ _di_Z[ e\ j^[ WdY^eh_d] fbWj[ WdZ j^[ ijhWdZ*l_i[ ckij j^[d X[ jWff[Z _dje fei_j_ed W]W_dij j^[ ekji_Z[ \WY[ e\ j^[ WdY^eh_d] fbWj[+ R^[d j^[ j[di_ed ^Wi X[[d h[b[Wi[Z \hec j^[ ̀ WYa j^[ L<D ckij Y^[Ya j^[ h[\[h[dY[ cWhai ed j^[ ijhWdZ Wj j^[ _di_Z[ e\ j^[ WdY^eh_d] fbWj[ je Z[j[hc_d[ j^Wj de ib_ffW][ e\ j^[ ijhWdZ*l_i[ &b_l[ [dZ i[Wj_d] beii' ̂ Wi eYYkhh[Z+ D\ ib_ffW][ ̂ Wi eYYkhh[Z j^[d _j ckij X[ YecfWh[Z je j^[ Wiikc[Z b_l[ [dZ i[Wj_d] beii ki[Z _d j^[ ijhWdZ j[di_ed_d] YWbYkbWj_edi+ <do Z_\\[h[dY[i ckij X[ dej[Z WdZ Yecckd_YWj[Z je L>+
Y+ Strand Elongation * O^[ j[di_ed_d] ef[hWj_ed ckij X[ ijeff[Z _cc[Z_Wj[bom^[d[l[h j^[ ijhWdZ _i [bed]Wj_d] m_j^ekj W Yehh[ifedZ_d] _dYh[Wi[ _d j^[beWZ) eh j^[ beWZ _dYh[Wi[i m_j^ekj W Yedj_dk_d] _dYh[Wi[ _d ijhWdZ [bed]Wj_ed+Dd j^[i[ eYYkhh[dY[i) j^[ \ebbem_d] ij[fi ckij X[ jWa[d7
_+ NjhWdZ [bed]Wj_ed YecfkjWj_ed _i Y^[Ya[Z8
__+ >Wij_d] X[Z b[d]j^ _i l[h_\_[Z8
___+ HeZkbki e\ [bWij_Y_jo e\ j^[ ijhWdZ _i l[h_\_[Z8 WdZ
_l+ AWYjehi h[ijh_Yj_d] j^[ \h[[ cel[c[dj e\ j^[ ijhWdZ Wh[ h[l_[m[Z+
O[cf[hWjkh[ Y^Wd][i cWo W\\[Yj j^[ ^oZhWkb_Y ioij[c e\ j^[ j[di_ed_d] WffWhWjki h[ikbj_d] _d lWh_Wj_edi _d beWZ h[WZ_d]i+
Z+ Tensioning Draped Strands * L<D ckij X[ Wb[hj je j^[ ijhWdZ [bed]Wj_ed WdZj[di_ed_d] ef[hWj_ed Z_iYkii[Z WXel[+ Dd iec[ YWi[i) j^[ dkcX[h WdZ[\\_Y_[dYo e\ ^ebZ*Zemd,^ebZ*kf ^WhZmWh[ cWo h[ijh_Yj j^[ \h[[ cel[c[dj e\ WijhWdZ el[h j^[ [dj_h[ X[Z b[d]j^ h[ikbj_d] _d W Yedj_dk_d] [bed]Wj_ed e\ ijhWdZm_j^ekj W Yehh[ifedZ_d] _dYh[Wi[ _d j^[ beWZ+ R^[d j^_i i_jkWj_ed eYYkhi) j^[j[di_ed_d] ef[hWj_ed _i ijeff[Z WdZ j^[ h[cW_d_d] [bed]Wj_ed Z[l[bef[Z _dj^[ ijhWdZ jWa[d Xo j[di_ed_d] j^[ ijhWdZ \hec j^[ effei_j[ [dZ e\ j^[ YWij_d]X[Z+
[+ Confirming Uniform Elongation of Draped Strands * O^_i YWd X[ WYYecfb_i^[ZXo cWha_d]*e\\ W .- \eej &eh ceh[ _\ WlW_bWXb[' b[d]j^ e\ ZhWf[Z ijhWdZ Wj j^[effei_j[ [dZ e\ j^[ X[Z W\j[h j^[ _d_j_Wb beWZ ef[hWj_ed ^Wi X[[d Yecfb[j[Z+ <jj^[ Yecfb[j_ed e\ j^[ \_dWb c[Wikh[Z [bed]Wj_ed ef[hWj_ed) j^[ c[Wikh[ZZ_ijWdY[ X[jm[[d j^[ cWhai i^ekbZ ^Wl[ _dYh[Wi[Z je j^[ net elongationYecfkjWj_ed \eh W .- \eej ijhWdZ b[d]j^ &eh m^Wj[l[h mWi _d_j_Wbbo cWha[Z e\\'+
\+ Wire Failure in Strand * N[[ K>D HIG ..3 \eh WYY[fjWdY[ e\ \W_bkh[ e\_dZ_l_ZkWb m_h[i _d W fh[j[di_ed_d] ijhWdZ+
?+ Forming and Casting
.+ General Information * L<D ckij Yed\_hc j^[ Z_c[di_edWb h[gk_h[c[dji e\ j^[Xkba^[WZi) i_Z[ \ehci) X[Wh_d] fbWj[i) ij[[b h[_d\ehY[c[dj) le_Z Xen[i) _di[hji) WdZWdo ej^[h Z[l_Y[i f[h j^[ Wffhel[Z i^ef ZhWm_d]i Wi fWhj e\ j^[_h feij*fekh_dif[Yj_ed+ O^[ edbo [nY[fj_ed _i j^Wj Wdoj^_d] j^Wj YWddej X[ _dif[Yj[Z feij*fekh)ckij X[ _dif[Yj[Z Zkh_d] fh[*fekh+ Dj _i _cfehjWdj je [cf^Wi_p[ j^Wj L< ckij dejikf[hi[Z[ L> ie j^[ L<Dvi _dif[Yj_ed ckij Yec[ W\j[h L> ^Wi Yecfb[j[Z j^[_h_dif[Yj_ed WdZ Wffhel[i j^[ [b[c[dj+ L<D j^[d ki[i j^[ L> _dif[Yj_ed h[fehji &_\WlW_bWXb[' Zkh_d] j^[_h l[h_\_YWj_ed _dif[Yj_ed+
/+ Concrete Forms * >edYh[j[ \ehci ckij X[ cW_djW_d[Z WdZ h[cW_d jhk[ je j^[ i^Wf[iWdZ Z_c[di_edi Wi i^emd ed j^[ Wffhel[Z ZhWm_d]i+
18
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
W+ H[jWb \ehci ckij X[ ki[Z i_dY[ j^[o Wh[ Z[i_]d[Z WdZ Wb_]d[Z je dej h[ijh_Yjj^[ bed]_jkZ_dWb cel[c[dj e\ j^[ YWij_d] m^[d j^[ fh[ijh[ii_d] \ehY[ _ijhWdi\[hh[Z+ Aehci ckij X[ m[bb XhWY[Z WdZ ij_\\[d[Z W]W_dij kdZ[i_hWXb[Z[\ehcWj_edi kdZ[h fh[iikh[ e\ \h[i^ YedYh[j[ WdZ ckij ^Wl[ iceej^ `e_djiWdZ _di_Z[ ikh\WY[i WYY[ii_Xb[ \eh WZ[gkWj[ Yb[Wd_d] W\j[h [WY^ ki[+
X+ Ee_dji X[jm[[d fWd[b \ehci ckij X[ cWZ[ WdZ cW_djW_d[Z iceej^ WdZj_]^j+ Pdb[ii ej^[hm_i[ i^emd ed Wffhel[Z i^ef ZhWm_d]i) Wbb Yehd[hi eh_dj[hi[Yj_edi e\ ikh\WY[i [nfei[Z _d j^[ Yecfb[j[Z ijhkYjkh[ ckij X[Y^Wc\[h[Z m_j^ W c_d_ckc Z_c[di_ed e\ -+2- _dY^[i WdZ Wbb h[*[djhWdj Wd]b[ickij X[ hekdZ[Z m_j^ W c_d_ckc hWZ_ki e\ -+42 _dY^[i+
Y+ Aehci j^Wj Wh[ mWhf[Z) Z_ijehj[Z) ZWcW][Z) eh _cfhef[hbo Yb[Wd[Z ckij dejX[ ki[Z+ ReeZ \ehci cWo X[ ki[Z \eh Xkba^[WZi+ O^[ _di_Z[ \WY[i e\ Wbb\ehci ckij X[ YeWj[Z m_j^ Wd Wffhel[Z Y^[c_YWb h[b[Wi[ W][dj+
0+ Reinforcing Steel s L<D ckij Yed\_hc j^Wj j^[ h[_d\ehY_d] ij[[b _i e\ j^[ Yehh[Yj i_p[)\h[[ \hec Z[\[Yji) WdZ fhef[hbo fei_j_ed[Z+ O^[ h[_d\ehY_d] ij[[b ckij X[ \h[[ e\ e_b)bkXh_YWdji) \eh[_]d cWj[h_Wb) WdZ [nY[ii_l[ hkij+ D\ [feno YeWj[Z XWhi Wh[ je X[ ki[Zj^[d d_Yai _d j^[ YeWj_d] Wh[ dej f[hc_jj[Z+
L<D ckij ifej Y^[Ya j^Wj j^[ h[_d\ehY_d] ij[[b ^Wi X[[d fhef[hbo fei_j_ed[Z WdZi[Ykh[Z _d WYYehZWdY[ m_j^ j^[ Wffhel[Z i^ef ZhWm_d]i WdZ cWa[ Y[hjW_d j^Wj _di[hji^Wl[ X[[d fbWY[Z m^[h[ h[gk_h[Z+
1+ Qe_Z =en[i * Qe_Z Xen[i ckij X[ e\ j^[ Z_c[di_edi WdZ fei_j_ed[Z _d j^[ \ehc _dWYYehZWdY[ m_j^ j^[ Wffhel[Z i^ef ZhWm_d]i+
<\j[h j^[ XWh h[_d\ehY[c[dj Wii[cXbo ^Wi X[[d fei_j_ed[Z _d j^[ \ehcmeha) j^[ L<Dckij Yed\_hc j^Wj j^[ le_Z Xen[i Wh[ i[Ykh[bo YbWcf[Z je j^[ \ehcmeha ie j^[o YWddejcel[ ekj e\ fei_j_ed Zkh_d] Yedieb_ZWj_ed WYj_l_j_[i+ <\j[h j^[ kd_j ^Wi X[[d YWij) WdZ_cc[Z_Wj[bo W\j[h j^[ jef ^Wi X[[d ijhkYa*e\\) j^[ jef ibWX j^_Yad[ii ckij X[Yed\_hc[Z Xo j^[ L<D je Wiikh[ j^Wj j^[h[ ^Wi X[[d de kfmWhZ cel[c[dj e\ j^[ le_ZXen WdZ j^Wj j^[ jef ibWX j^_Yad[ii _i m_j^_d j^[ WYY[fjWXb[ if[Y_\_YWj_ed b_c_ji+ O^[Z[fj^ e\ YedYh[j[ el[h j^[ le_Z Xen[i m_bb X[ ifej Y^[Ya[Z WdZ Wdo YedY[hdi dej[ZWdZ _cc[Z_Wj[bo i^Wh[Z m_j^ L>+
2+ Tests on Fresh Concrete s L<D ckij f[h\ehc j[ij_d] Wi h[gk_h[Z _d j^[ YedjhWYj WdZZeYkc[dj j^[ h[ikbji _d H?JO Aehc -26-+ O^[ AWXh_YWjeh ckij Yebb[Yj WZZ_j_edWb\h[i^ YedYh[j[ \eh L<D je f[h\ehc j^[_h j[iji Wi d[[Z[Z+
3+ Placing of Concrete s O^[ YedYh[j[ ckij X[ fhecfjbo fbWY[Z m_j^ c_d_ckc ^WdZb_d]je Wle_Z i[]h[]Wj_ed e\ j^[ cWj[h_Wbi WdZ j^[ Z_ifbWY[c[dj e\ j^[ h[_d*\ehY[c[dj+ @WY^ [b[c[dj ckij X[ YWij _d W Yedj_dkeki ef[hWj_ed m_j^ c_d_cWb_dj[hhkfj_ed X[jm[[d j^[ fbWY_d] e\ WZ`WY[dj fehj_edi e\ YedYh[j[ WdZ [WY^ bWo[h ckijX[ fbWY[Z WdZ Yedieb_ZWj[Z X[\eh[ j^[ fh[Y[Z_d] bWo[h ^Wi jWa[d _d_j_Wb i[j+
4+ Consolidation of Concrete s < c_d_ckc Wcekdj e\ l_XhWj_ed d[Y[iiWho je j^ehek]^boYedieb_ZWj[ j^[ YedYh[j[ ckij X[ ki[Z+ L<D ckij l[h_\o W hkXX[h YeWj[Z l_XhWjeh^[WZ _i ki[Z m^[d [feno*YeWj[Z eh ej^[h YeWj[Z h[_d\ehY[c[dj _i ki[Z+
@+ Transfer of Prestress s O^[ j[di_ed _d j^[ ijhWdZi ckij dej X[ jhWdi\[hh[Z je j^[ YedYh[j[ _d j^[ [b[c[dj kdj_b j^[ YedYh[j[ ^Wi WjjW_d[Z j^[ h[gk_h[Z Yecfh[ii_l[ ijh[d]j^ Wi
19
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
_dZ_YWj[Z Xo j[ij h[ikbji e\ L> Yecfh[ii_l[ ijh[d]j^ j[ij Yob_dZ[hi m^_Y^ ^Wl[ X[[d YWij WdZ cWjY^ Ykh[Z f[h j^[ YedjhWYj+ L<D ckij m_jd[ii j^_i j[ij_d]+
.+ Aehci Wh[ h[cel[Z WdZ j^[ ijhWdZi Wh[ h[b[Wi[Z Xo i_ckbjWd[ekibo Ykjj_d] Xej^ [dZie\ j^[ iWc[ ijhWdZ ki_d] W jehY^ eh ej^[h c[j^eZ Wffhel[Z Xo j^[ @d]_d[[h+ O^[AWXh_YWjeh ckij h[b[Wi[ ijhWdZi _d W iocc[jh_YWb fWjj[hd WXekj j^[ l[hj_YWb Y[dj[hb_d[+@njh[c[ YWh[ ckij X[ [n[hY_i[Z Xo j^[ AWXh_YWjeh je Wle_Z ZWcW]_d] j^[ YedYh[j[ Xoikf[h^[Wj_d] _j m_j^ j^[ jehY^+
/+ @b[c[dji Wh[ cel[Z \hec j^[ YWij_d] X[Z je j^[ oWhZ kfed Yecfb[j_ed e\ j^[ jhWdi\[he\ fh[ijh[ii+ <\j[h h[celWb \hec j^[ X[Z) j^[ L<D ckij _cc[Z_Wj[bo _dif[Yj j^[[b[c[dj \eh Wdo Z[\[Yji Yh[Wj[Z Zkh_d] YWij_d] WdZ f[h\ehc feij*fekh _dif[Yj_ediW\j[h L> ^Wi Yecfb[j[Z j^[_h _dif[Yj_ed WdZ Wffhel[i j^[ [b[c[dj+ L<D ckij dej[Wdo Z[\_Y_[dY_[i ed Aehc -26- WdZ _cc[Z_Wj[bo dej_\o j^[ AWXh_YWjeh WdZ @d]_d[[h+O^[ @d]_d[[h cWo h[gk[ij j^[ L<D je Yecfb[j[ W L< I>M WdZ WhhWd][ W c[[j_d]m_j^ L> je Z_iYkii m^o j^[ Z[\_Y_[dYo mWidvj YWk]^j Xo L>+
A+ Curing Requirements * >kh_d] h[gk_h[c[dji \eh fh[ijh[ii[Z YedYh[j[ ckij X[ Wi if[Y_\_[Z _d ikXi[Yj_ed 4-5+-0 e\ j^[ H?JO NN> Wi ceZ_\_[Z Xo j^[ YedjhWYj+ R^[d ij[Wc eh hWZ_Wdj ^[Wj Ykh_d] _i ki[Z) h[YehZ_d] j^[hcec[j[hi ckij X[ fhel_Z[Z Xo j^[ AWXh_YWjeh j^Wj ced_jehi j^[ j_c[,j[cf[hWjkh[ h[bWj_edi^_f j^hek]^ j^[ Ykh_d] f[h_eZ m^_b[ Whj_\_Y_Wb ^[Wj _i ki[Z+ O^[ L<D ckij l[h_\o j^Wj j^[ h[YehZ_d] j^[hcec[j[hi Wh[ fbWY[Z _d Yh_j_YWb beYWj_edi \eh ced_jeh_d] j^[ j_c[,j[cf[hWjkh[ h[bWj_edi^_f Zkh_d] j^[ Ykh_d] f[h_eZ+ Q[h_\o L> ^Wi j^[ h[gk_h[Z dkcX[h e\ h[YehZ_d] j^[hcec[j[hi f[h j^[ YedjhWYj WdZ j^[o Wh[ fbWY[Z Wj beYWj_edi m^[h[ j^[ Wdj_Y_fWj[Z ̂ [Wj ][d[hWj[Z Xo j^[ YedYh[j[ _i j^[ bem[ij WdZ ^_]^[ij `kij W\j[h _d_j_Wb YedYh[j[ i[j+ ?eYkc[djWj_ed \hec j^[ AWXh_YWjeh%i h[YehZ_d] j^[hcec[j[h ckij X[ ]_l[d je j^[ L<D \eh j^[_h h[l_[m+ O[cf[hWjkh[ h[gk_h[c[dji Zkh_d] j^[ Ykh_d] ef[hWj_ed ckij X[ _d WYYehZWdY[ m_j^ j^[ YedjhWYj if[Y_\_YWj_edi+
B+ Material Requirements s HWj[h_Wbi ckij c[[j j^[ h[gk_h[c[dji e\ j^[ YedjhWYj kdb[ii W MAD h[gk[ij_d] Wbj[hdWj[ cWj[h_Wbi ^Wi X[[d Wffhel[Z Xo j^[ @d]_d[[h+
C+ Shipping Requirements s @b[c[dji ckij WjjW_d j^[ h[gk_h[Z Yecfh[ii_l[ ijh[d]j^ Wi _dZ_YWj[Z Xo j[ij h[ikbji e\ L> Yecfh[ii_l[ ijh[d]j^ j[ij Yob_dZ[hi) m^_Y^ ^Wl[ X[[d YWij WdZ cWjY^ Ykh[Z \eh j^_i fkhfei[ Wi Z[iYh_X[Z f[h j^[ YedjhWYj+ O^[i[ Yob_dZ[hi ckij X[ YWij m_j^ c[jWb H?JO jW]i WdZ j^[ Yecfh[ii_ed j[ij_d] ckij X[ m_jd[ii[Z Xo j^[ L<D+
1+-1+-2+ M[fehji
<+ O^[ @d]_d[[h cWo h[gk_h[ W f[h_eZ_Y ijWjki h[fehj \hec j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j8 j^[h[\eh[) Wbb h[fehji Wh[ h[gk_h[Z je X[ Yecfb[j[Z _d W j_c[bo WdZ ehZ[hbo cWdd[h ki_d] j^[ Wffb_YWXb[ \_bbWXb[ fehjWXb[ ZeYkc[dj \ehcWj &K?A' \ehci b_ij[Z X[bem j^Wj YWd X[ \ekdZ ed H?JOvi m[Xi_j[+ HWa[ [djh_[i Wi ieed Wi feii_Xb[ W\j[h Wd [l[dj eh Yedl[hiWj_ed je [dikh[ WYYkhWYo+ IkcX[h j^[ h[fehji Yedi[Ykj_l[bo kdj_b Yecfb[j_ed e\ j^[ meha+
=+ L<D ckij Yecfb[j[ Wd WYYkhWj[ WdZ Z[jW_b[Z WYYekdj e\ \WXh_YWj_ed \eh j^[ fhe`[Yj+ O^[ h[fehj ckij _dYbkZ[ W Z_iYkii_ed e\ \WXh_YWj_ed fhe]h[ii \eh Wbb Wif[Yji e\ j^[ meha+ Dj _i _dj[dZ[Z je X[ W Z[jW_b[Z h[YehZ e\ j^[ ijWjki e\ \WXh_YWj_ed WdZ i^ekbZ _dYbkZ[ dkcX[h e\ [b[c[dji \WXh_YWj[Z) ZeYkc[djWj_ed e\ if[Y_\_YWj_ed WdZ fheY[Zkh[ Yecfb_WdY[ Wi m[bb Wi ZeYkc[djWj_ed e\ Yed\b_Yji) h[fW_hi) WdZ ej^[h fheXb[ci eh Z_iYkii_ed m^_Y^ YekbZ W\\[Yj j^[ fhe`[Yj _d WdomWo+ D\ \ehY[ WYYekdj meha _i jWa_d] fbWY[) ZeYkc[dj [WY^ ZWo j^Wj j^[ meha eYYkhi _d j^[ i^ef WdZ m^_Y^ [b[c[dji Wh[ X[_d] meha[Z+
20
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
>+ ?eYkc[djWj_ed _i dej W ikXij_jkj[ \eh Wffhefh_Wj[ Z_Wbe]k[ m_j^ j^[ AWXh_YWjeh) Xkj i^ekbZ fhel_Z[ W h[YehZ e\ _cfehjWdj Z_iYkii_edi+ Dd iec[ YWi[i) j^[ L<D _i ceh[ \Wc_b_Wh m_j^ j^[ [l[dji eh _iik[i WdZ j^[h[\eh[ i^ekbZ h[l_[m WdZ Yecc[dj ed ZhW\j Yef_[i e\ j^[ NjhkYjkhWb AWXh_YWj_ed Pd_jvi Yehh[ifedZ[dY[+
?+ M[fehji ckij X[ Wii[cXb[Z _dje ed[ \WXh_YWj_ed _dif[Yj_ed fehjWXb[ ZeYkc[dj \ehcWj &K?A' \_b[ WdZ ijeh[Z _d H?JOvi Khe`[YjR_i[ ZeYkc[dj ijehW][ fhe]hWc f[h MDOT’s Structural Fabrication Unit’s E-Construction Process+ O^[ @d]_d[[h m_bb h[Y[_l[ W \WXh_YWj_ed _dif[Yj_ed c[cehWdZkc \hec j^[ NjhkYjkhWb AWXh_YWj_ed @d]_d[[h W\j[h \WXh_YWj_ed _dif[Yj_ed _i Yecfb[j[+ O^[ c[cehWdZkc _i \eh _d\ehcWj_edWb fkhfei[i WdZ _i dej ki[Z \eh WYY[fjWdY[+
@+ =[bem _i W b_ij e\ lWh_eki H?JO h[fehji,\ehci WdZ W Xh_[\ Z[iYh_fj_ed e\ j^[_h fkhfei[ WdZ ki[ h[gk_h[c[dj+ N_c_bWh \ehci YWd X[ ki[Z _d fbWY[ e\ j^[ ijWdZWhZ H?JO \ehc _\ dej[Z X[bem+
.+ Project Folder Checklist (Form 2001) s O^_i \ehc ckij X[ Yecfb[j[Z Xo L<D \eh [WY^fhe`[Yj+ O^[ Y^[Yab_ij _i fbWY[Z ed jef e\ j^[ \WXh_YWj_ed _dif[Yj_ed \ebZ[h m^[d j^[fhe`[Yj _i Yecfb[j[+
/+ Shop Inspection Report (Form 5617) – O^_i \ehc ckij X[ Yecfb[j[Z Xo L<D ed Wm[[abo XWi_i \eh [WY^ fhe`[Yj WdZ i^ekbZ YedjW_d W Xh_[\ dWhhWj_l[ e\ j^[ mehaf[h\ehc[Z el[h j^[ h[fehj_d] f[h_eZ+ O^[ h[fehj ckij YedjW_d j^[ \ebbem_d]_d\ehcWj_ed7 R[Wj^[h YedZ_j_edi) [b[c[dji meha[Z ed) cWj[h_Wbi _dYehfehWj[Z _dje[b[c[dji &ckij ZeYkc[dj l_ikWbbo _dif[Yj[Z WdZ WYY[fj[Z') meha WYj_l_jo)dedYed\ehcWdY[i) i^_ff_d]) \ehY[ WYYekdj meha &hWh[') WdZ Wdoj^_d] [bi[ Z[[c[Z_cfehjWdj Xo j^[ L<D+
0+ Sample Identification (Form 1923) s O^_i \ehc ckij X[ ikXc_jj[Z m^[d cWj[h_WbiWcfb_d] _i h[gk_h[Z ed W fhe`[Yj+ L<D ckij Yecfb[j[bo \_bb ekj j^[ \ehc WdZ a[[f WYefo _d j^[ \WXh_YWj_ed _dif[Yj_ed \ebZ[h+
1+ Strand Tensioning Report (Form 0513) s O^_i \ehc ckij X[ Yecfb[j[Z Xo L<D \eh[WY^ X[Z) m^_Y^ cWo YedjW_d i[l[hWb [b[c[dji+
2+ Bar Reinforcement Report (Form 1985) s O^_i \ehc _i edbo ki[Z _\ L<D f[h\ehci L<l[h_\_YWj_ed _dif[Yj_ed ed XWh h[_d\ehY[c[dj \eh fh[\WXh_YWj[Z Xh_Z][ [b[c[dj ioij[ci&K=@N' eh ej^[h [b[c[dji j^Wj YedjW_d Yecfb[n h[_d\ehY[c[dj Wi Z_h[Yj[Z Xo j^[@d]_d[[h+
6. Pre and Post Pour Inspection Checklist (Form 5616) s O^_i Y^[Yab_ij ckij X[Yecfb[j[Z Xo L<D \eh W c_d_ckc e\ ed[ [b[c[dj f[h fhe`[Yj+ O^[ Y^[Yab_ij _i fbWY[Z_d j^[ \WXh_YWj_ed _dif[Yj_ed \ebZ[h m^[d j^[ fhe`[Yj _i Yecfb[j[+
4+ Field and Lab Test Report (Form 0590) s O^_i \ehc ckij X[ Yecfb[j[Z Xo L<D \eh[WY^ fekh m^_Y^ cWo YedjW_d i[l[hWb [b[c[dji+
5+ Repair Observation Report (Form 1981) s O^_i \ehc _i edbo ki[Z _\ L<D f[h\ehci L<l[h_\_YWj_ed _dif[Yj_ed ed h[fW_hi j^Wj ^Wl[ X[[d Wffhel[Z Xo j^[ @d]_d[[h+
6+ Material Source List (Form 0501) s O^_i \ehc _i i[dj _d Xo j^[ \WXh_YWjeh) j^[ L<D m_bbl[h_\o j^Wj j^[ \WXh_YWjeh \_bb[Z ekj j^[ \ehc Yecfb[j[bo) WdZ ZeYkc[dj j^[ XWi_i e\WYY[fjWdY[ \eh Wbb cWj[h_Wbi+ D\ j^[h[ Wh[ Wdo cWj[h_Wbi j^Wj h[gk_h[ j[ij_d] j^[d j^[NjhkYjkhWb AWXh_YWj_ed Pd_j ckij X[ Yef_[Z ed j^[ Yecfb[j[Z HNG je YeehZ_dWj[ j^[WYY[fjWdY[ j[ij_d]+
1+-1+-3+ NjeYaf_b[ KWoc[dj
21
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
<+ O^_i ijeYaf_b[ fWoc[dj i[Yj_ed Z_h[Yji j^[ L<D ed j^[ h[gk_h[c[dji m^[d ijeYaf_b[ fWoc[dj _dif[Yj_ed _i h[gk[ij[Z Xo j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j+ O^[ L<D ckij f[h\ehc j^[ \ebbem_d] ij[fi7
.+ Q[h_\o \WXh_YWj[Z cWj[h_Wb c[[ji Wffhel[Z i^ef ZhWm_d]i &_\ Wffb_YWXb['8
/+ Q[h_\o ijeYaf_b[ gkWdj_jo WdZ _dYbkZ[ gkWdj_jo _d h[fehj8
0+ Q[h_\o cWj[h_Wb _i bWX[b[Z \eh H?JO ki[ edbo8
1+ Q[h_\o cWj[h_Wb _i Yehh[Yjbo ijeh[Z WdZ fhej[Yj[Z \hec j^[ [b[c[dji8 WdZ
2+ Khel_Z[ W h[fehj ikccWh_p_d] j^[ _dif[Yj_ed WdZ fhel_Z[ WZ[gkWj[ f^ejei j^Wjh[fh[i[dj j^[ ][d[hWb YedZ_j_ed e\ j^[ [b[c[dji) ^em j^[ovh[ X[_d] ijeh[Z) WdZ f_[Y[cWhai+
1+-1+-4+ <YY[fjWdY[
<+ O^[ AWXh_YWjeh _i h[gk_h[Z je fhel_Z[ j^[ L<D m_j^ W c_d_ckc e\ \_l[ &2' Yef_[i e\ j^[ =_bb e\ GWZ_d] \eh [WY^ i^_fc[dj+ L<D m_bb ijWcf [WY^ Yefo e\ j^[ =_bb e\ GWZ_d] m_j^ j^[ H?JO t<ffhel[Z \eh Pi[u ijWcf+ Dj _i j^[ AWXh_YWjehvi h[ifedi_X_b_jo je Z_ijh_Xkj[ j^[ ijWcf[Z Yef_[i e\ =_bb e\ GWZ_d] je j^[ \ebbem_d] _dZ_l_ZkWbi7
.+ L<D
/+ @d]_d[[h
0+ AWXh_YWjeh
1+ >edjhWYjeh
2+ OhkYa_d] YecfWdo
O^[ =_bb e\ GWZ_d] _i h[gk_h[Z je YedjW_d) Wj W c_d_ckc) j^[ \ebbem_d] _d\ehcWj_ed7
.+ N^_ff_d] ZWj[
/+ ?[iYh_fj_ed e\ YWh]e &gkWdj_jo) [b[c[dj i_p[) m[_]^j) [jY+'
0+ @b[c[dj kd_gk[ f_[Y[ cWha
1+ H?JO fhe`[Yj beYWj_ed &hekj[) Yheii heWZ,h_l[h) WdZ Y_jo'
2+ H?JO fhe`[Yj _d\ehcWj_ed &ijhkYjkh[ dkcX[h) Yedjheb i[Yj_ed) WdZ `eX dkcX[h'
3+ HWdk\WYjkh[hvi dWc[ WdZ WZZh[ii
=+ <YY[fjWdY[ Yedi_iji e\ j^[ \ebbem_d] jme*fWhj fheY[ii7
.+ AWXh_YWj_ed Ddif[Yj_ed <YY[fjWdY[7 NjhkYjkhWb [b[c[dji ckij X[ _dif[Yj[Z Xo j^[ L<DW\j[h j^[o Wh[ beWZ[Z \eh i^_ff_d]+ D\ j^[ ijhkYjkhWb [b[c[dji c[[j j^[ YedjhWYjh[gk_h[c[dji) j^[ L<D m_bb ijWcf j^[c t<ffhel[Z \eh Pi[u+ O^[ [b[c[dji ckij X[ijWcf[Z t<ffhel[Z \eh Pi[u fh_eh je i^_ff_d]+ <ZZ_j_edWbbo) j^[ L<D ckij ijWcf Wjb[Wij \_l[ Yef_[i e\ j^[ =_bb e\ GWZ_d] j^Wj _i fh[fWh[Z Xo j^[ AWXh_YWjeh+ O^[ WffhelWbijWcf _i \eh ki[ Xo j^[ ?[fWhjc[dj WdZ Ze[i dej h[b_[l[ j^[ >edjhWYjeh e\ j^[_hh[ifedi_X_b_jo je c[[j YedjhWYj h[gk_h[c[dji+
/+ Q_ikWb Ddif[Yj_ed &QD' <YY[fjWdY[7 O^[ @d]_d[[h ckij Yebb[Yj ed[ Yefo e\ j^[ijWcf[Z =_bb e\ GWZ_d] WdZ ki[ _j je l[h_\o j^[ Z[b_l[h[Z ijhkYjkhWb [b[c[dji+<ZZ_j_edWbbo) j^[ @d]_d[[h ckij l[h_\o j^Wj j^[ [b[c[dji Wh[ ijWcf[Z WdZ l_ikWbbo_dif[Yj j^[c \eh i_]di e\ ZWcW][ j^Wj cWo ^Wl[ eYYkhh[Z Wi W h[ikbj e\ i^_ff_d] WdZ
22
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+-1
^WdZb_d]+ O^_i l_ikWb _dif[Yj_ed i^ekbZ X[ ZeYkc[dj[Z _d j^[ \_[bZ _dif[Yjehvi ZW_bo h[fehj+
23
(This page intentionally left blank)
(This page intentionally left blank)
(This page intentionally left blank)
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+..
,')) ABA&CE7FGE7FF76 FGEH5GHE3? CE753FG 5BA5E7G7 834E<53G<BA
1+..+-.+ NYef[
<+ O^_i ded*fh[ijh[ii[Z ijhkYjkhWb fh[YWij YedYh[j[ \WXh_YWj_ed _dif[Yj_ed fheY[Zkh[ i^ekbZ X[ ki[Z je W_Z j^[ gkWb_jo WiikhWdY[ _dif[Yjeh &L<D' _d _dj[hfh[j_d] WdZ [d\ehY_d] j^[ YedjhWYj \eh ded*fh[ijh[ii[Z YedYh[j[ [b[c[dji+ AWXh_YWj_ed _dif[Yj_ed _dYbkZ[i j^[ j_c[ \hec l[h_\o_d] cWj[h_Wbi ki[Z \eh \WXh_YWj_ed j^hek]^ beWZ_d] \eh i^_ff_d] je j^[ YedijhkYj_ed i_j[+ O^[ \ebbem_d] ded*fh[ijh[ii[Z ijhkYjkhWb fh[YWij YedYh[j[ [b[c[dji Wh[ _dYbkZ[Z _d j^_i _dif[Yj_ed fheY[Zkh[7
.+ >kbl[hji &_\ h[gk_h[Z Xo j^[ YedjhWYj eh Wi Z_h[Yj[Z Xo j^[ @d]_d[[h'
/+ Kh[\WXh_YWj[Z Xh_Z][ [b[c[dj ioij[ci
0+ H[Y^Wd_YWbbo ijWX_b_p[Z [Whj^ fWd[bi &_\ h[gk_h[Z Xo j^[ YedjhWYj eh Wi Z_h[Yj[Z Xo j^[ @d]_d[[h'
1+ NekdZ mWbb feiji WdZ fWd[bi &_\ h[gk_h[Z Xo j^[ YedjhWYj eh Wi Z_h[Yj[Z Xo j^[ @d]_d[[h'
1+..+-/+ M[\[h[dY[ ?eYkc[dji
<+ L<D ckij ^Wl[ W j^ehek]^ ademb[Z][ e\ j^[ \ebbem_d] h[\[h[dY[i7
.+ O^[ \ebbem_d] i[Yj_edi e\ j^[ H?JO NjWdZWhZ Nf[Y_\_YWj_edi \eh >edijhkYj_ed &H?JO NN>' Wi ceZ_\_[Z Xo ikffb[c[djWb if[Y_\_YWj_ed ./NN*--.< s @hhWjW) Wi Wffb_YWXb[7
N[Yj_ed .-1 >edjheb e\ j^[ Reha N[Yj_ed .-2 >edjheb e\ j^[ HWj[h_Wbi N[Yj_ed 1-3 Kh[YWij O^h[[*N_Z[Z) <hY^) WdZ =en >kbl[hji
/+ O^[ \ebbem_d] if[Y_Wb fhel_i_edi) Wi Wffb_YWXb[7
./NK*.-2< NekhY[ e\ Nj[[b WdZ Dhed &=ko <c[h_YW'
./NK*3-1> L> WdZ <YY[fjWdY[ e\ K>> \eh NjhkYjkhWb Kh[YWij >edYh[j[ ./NK*4-3? H[Y^Wd_YWbbo NjWX_b_p[Z @Whj^ M[jW_d_d] RWbb Noij[c
0+ H?JO NjhkYjkhWb Kh[YWij >edYh[j[ L<D HWdkWb
1+ >edijhkYj_ed A_[bZ N[hl_Y[i ?_l_i_ed &>AN' HWj[h_Wbi NekhY[ Bk_Z[ &HNB'
2+ H?JO NjhkYjkhWb AWXh_YWj_ed Pd_j @*>edijhkYj_ed KheY[ii
3+ H?JO NjhkYjkhWb AWXh_YWj_ed LkWb_jo <iikhWdY[ Bk_ZWdY[ ?eYkc[dj
4+ Kh[\WXh_YWj_ed c[[j_d] c_dkj[i &_\ WlW_bWXb['
=+ L<D ckij X[ \Wc_b_Wh m_j^ j^[ \ebbem_d] h[\[h[dY[i7
.+ H?JO NjhkYjkhWb AWXh_YWj_ed M[gk[ij \eh Dd\ehcWj_ed KheY[ii
/+ H?JO N^ef ?hWm_d] M[l_[m KheY[ii
0+ H?JO NjhkYjkhWb AWXh_YWj_ed IedYed\ehcWdY[ KheY[ii
1+ H_Y^_]Wd O[ij H[j^eZi
HOH .-/ H_Y^_]Wd O[ij H[j^eZ \eh <XhWi_ed M[i_ijWdY[ e\ <]]h[]Wj[ Xo j^[ Gei <d][b[i HWY^_d[
HOH .-5 H_Y^_]Wd O[ij H[j^eZ \eh HWj[h_Wbi A_d[h j^Wd Ie+ 42 N_[l[ _d H_d[hWb
24
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+..
<]]h[]Wj[i Xo RWi^_d]
HOH .-6 H_Y^_]Wd O[ij H[j^eZ \eh N_[l[ <dWboi_i e\ A_d[) ?[di[ BhWZ[Z) Jf[d BhWZ[Z) WdZ >eWhi[ <]]h[]Wj[i _d j^[ A_[bZ
HOH ..1 H_Y^_]Wd O[ij H[j^eZ \eh HWa_d] >edYh[j[ Nf[Y_c[di \eh Ah[[p[*O^Wm O[ij_d] e\ >edYh[j[ >eWhi[ <]]h[]Wj[
HOH ..2 H_Y^_]Wd O[ij H[j^eZ \eh O[ij_d] >edYh[j[ \eh ?khWX_b_jo Xo MWf_Z Ah[[p_d] _d <_h WdZ O^Wm_d] _d RWj[h
HOH /-3 H_Y^_]Wd O[ij H[j^eZ \eh Pi[ e\ PdXedZ[Z >Wfi _d ?[j[hc_dWj_ed e\ >ecfh[ii_l[ Njh[d]j^ e\ CWhZ[d[Z >edYh[j[ >ob_dZ[hi
2+ <<NCOJ NjWdZWhZi
O // >ecfh[ii_l[ Njh[d]j^ e\ >ob_dZh_YWb >edYh[j[ Nf[Y_c[di
O /0 HWa_d] WdZ >kh_d] >edYh[j[ O[ij Nf[Y_c[di _d j^[ A_[bZ
O /0. >Wff_d] >ob_dZh_YWb >edYh[j[ Nf[Y_c[di
3+ <NOH NjWdZWhZi
< .52 NjWdZWhZ Nf[Y_\_YWj_ed \eh Nj[[b R[bZ[Z R_h[ AWXh_Y) KbW_d) \eh >edYh[j[ M[_d\ehY[c[dj
< 1.3 NjWdZWhZ Nf[Y_\_YWj_ed \eh Gem*M[bWnWj_ed) N[l[d*R_h[ Nj[[b NjhWdZ \eh Kh[ijh[ii[Z >edYh[j[
< 164 NjWdZWhZ Nf[Y_\_YWj_ed \eh Nj[[b R[bZ[Z R_h[ AWXh_Y) ?[\ehc[Z) \eh >edYh[j[ M[_d\ehY[c[dj
> 0. NjWdZWhZ KhWYj_Y[ \eh HWa_d] WdZ >kh_d] >edYh[j[ O[ij Nf[Y_c[di _d j^[ A_[bZ
> 06 NjWdZWhZ O[ij H[j^eZ \eh >ecfh[ii_l[ Njh[d]j^ e\ >ob_dZh_YWb >edYh[j[ Nf[Y_c[di
> 61 NjWdZWhZ Nf[Y_\_YWj_ed \eh M[WZo*H_n[Z >edYh[j[ > .03 NjWdZWhZ O[ij H[j^eZ \eh N_[l[ <dWboi_i e\ A_d[ WdZ >eWhi[
<]]h[]Wj[i > .05 O[ij H[j^eZ \eh ?[di_jo &Pd_j R[_]^j') T_[bZ WdZ <_h >edj[dj
&BhWl_c[jh_Y' e\ >edYh[j[ > .10 NjWdZWhZ O[ij H[j^eZ \eh Nbkcf e\ CoZhWkb_Y >[c[dj >edYh[j[ > .4/ NjWdZWhZ KhWYj_Y[ \eh NWcfb_d] Ah[i^bo H_n[Z >edYh[j[ > .40 NjWdZWhZ O[ij H[j^eZ \eh <_h >edj[dj e\ Ah[i^bo H_n[Z >edYh[j[ Xo
j^[ Qebkc[jh_Y H[j^eZ > /0. NjWdZWhZ O[ij H[j^eZ \eh <_h >edj[dj e\ Ah[i^bo H_n[Z >edYh[j[ Xo
j^[ Kh[iikh[ H[j^eZ > 262 NjWdZWhZ Nf[Y_\_YWj_ed \eh =b[dZ[Z CoZhWkb_Y >[c[dji
> 3.4 NjWdZWhZ KhWYj_Y[ \eh >Wff_d] >ob_dZh_YWb >edYh[j[ Nf[Y_c[di > ./0. NjWdZWhZ KhWYj_Y[ \eh Pi[ e\ PdXedZ[Z >Wfi _d Z[j[hc_dWj_ed e\
>ecfh[ii_l[ Njh[d]j^ e\ CWhZ[d[Z >edYh[j[ >ob_dZ[hi > ./3- NjWdZWhZ O[ij H[j^eZ \eh Kej[dj_Wb <baWb_ M[WYj_l_jo e\ <]]h[]Wj[i
&HehjWh XWh H[j^eZ' > .234 NjWdZWhZ O[ij H[j^eZ \eh ?[j[hc_d_d] j^[ Kej[dj_Wb <baWb_*N_b_YW
M[WYj_l_jo e\ >ecX_dWj_edi e\ >[c[dj_j_eki HWj[h_Wbi WdZ <]]h[]Wj[ &<YY[b[hWj[Z HehjWh XWh H[j^eZ'
>+ H?JO <YY_Z[dj Kh[l[dj_ed KbWd
25
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+..
1+..+-0+ LkWb_\_YWj_edi) M[ifedi_X_b_j_[i) ?kj_[i) WdZ @gk_fc[dj
<+ LkWb_\_YWj_edi e\ j^[ L<D s L<D f[h\ehc_d] j^[ \WXh_YWj_ed _dif[Yj_ed ckij feii[ii j^[ \ebbem_d] gkWb_\_YWj_edi7
.+ H_Y^_]Wd >edYh[j[ <iieY_Wj_ed &H><' G[l[b D A_[bZ O[ij_d] O[Y^d_Y_Wd Y[hj_\_YWj_ed eh <c[h_YWd >edYh[j[ Ddij_jkj[ &<>D' >edYh[j[ A_[bZ O[ij_d] O[Y^d_Y_Wd s BhWZ[ D &[nY[fj f[h_eZ e\ [\\[Yj_l[d[ii m_bb X[ h[ZkY[Z \hec 2 o[Whi je 0 o[Whi je cWjY^ H><'8 WdZ
/+ H_Y^_]Wd >[hj_\_[Z <]]h[]Wj[ O[Y^d_Y_Wd &H><O' G[l[b D &edbo h[gk_h[Z \eh W]]h[]Wj[ iWcfb_d]'+
=+ M[ifedi_X_b_j_[i e\ j^[ L<D s L<D f[h\ehc_d] j^[ \WXh_YWj_ed _dif[Yj_ed _i dej f[hc_jj[Z je cWa[ Y^Wd][i je j^[ YedjhWYj WdZ ^Wi j^[ \ebbem_d] h[ifedi_X_b_j_[i7
O^[ >edjhWYjeh) AWXh_YWjeh) WdZ H?JO m_bb WffheWY^ gkWb_jo Yedjheb WdZ gkWb_jo WiikhWdY[ Wi W j[Wc [\\ehj je \WY_b_jWj[ WYYkhWj[ WdZ j_c[bo YedijhkYj_ed+ L<Dvi l[h_\_YWj_ed Ze[i dej h[b_[l[ j^[ AWXh_YWjeh \hec j^[ h[ifedi_X_b_jo je f[h\ehc j^[ h[gk_h[Z j[ij_d] WdZ _dif[Yj_ed je fheZkY[ W fheZkYj iWj_i\o_d] j^[ YedjhWYj+ O^ek]^ L< _dif[Yj_ed cWo _dYbkZ[ Wbb Wif[Yji e\ \WXh_YWj_ed) j^[ L<D ckij dej ikf[hi[Z[ L>) m^_Y^ _i j^[ h[ifedi_X_b_jo e\ j^[ AWXh_YWjeh+ D\ L> _i dej WYYecfb_i^_d] _ji heb[ j^[d j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j) @d]_d[[h) >edjhWYjeh) WdZ AWXh_YWjeh ckij Z[j[hc_d[ j^[ d[Y[iiWho Yehh[Yj_edi+
L<D _i j^[ h[ifedi_Xb[ fWhjo) h[fh[i[dj_d] j^[ @d]_d[[h) m^e f[h\ehci gkWb_jo WiikhWdY[ l[h_\_YWj_ed _dif[Yj_ed ed j^[ [b[c[dj W\j[h gkWb_jo Yedjheb &L>' _dif[Yji WdZ Wffhel[i j^[ _j[c e\ meha+ O^[ L<D ckij X[ Wj j^[ \WXh_YWj_ed \WY_b_jo Wj Wbb j_c[i Zkh_d] \WXh_YWj_ed Wi h[gk_h[Z Xo j^[ _dif[Yj_ed fheY[Zkh[ ijWj[Z X[bem+ D\ _iik[i Wh_i[) _j m_bb X[ Wj j^[ @d]_d[[hvi Z_iYh[j_ed m^[j^[h je _dYh[Wi[ j^[ b[l[b e\ L< _dif[Yj_ed+
Dj _i j^[ @d]_d[[hvi h[ifedi_X_b_jo je [d]W][ j^[ @d]_d[[h e\ M[YehZ &@JM' m^[d cWa_d] ijhkYjkhWb Z[Y_i_edi+ O^[ @d]_d[[h _i Wbie h[ifedi_Xb[ \eh \ebbem_d] _dj[hdWb H?JO fheY[Zkh[i \eh h[l_[m WdZ WffhelWb e\ i^ef ZhWm_d]i) \WXh_YWj_ed fheY[Zkh[i) h[gk[ij \eh _d\ehcWj_ed &MAD') dedYed\ehcWdY[ h[fehji &I>M') WdZ \eh fhe\[ii_edWb Z[Y_i_ed cWa_d] ed \WXh_YWj_ed fheXb[ci j^Wj Wh_i[+ O^[ @d]_d[[h h[b_[i ed j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j je cWdW][ WdZ Wii_ij m^[d Wffhefh_Wj[+ O^[ @d]_d[[h ^Wi j^[ fh[he]Wj_l[ \eh ^ebZ_d] W fh[\WXh_YWj_ed c[[j_d] m_j^ j^[ AWXh_YWjeh je Z_iYkii WdZ YbWh_\o j^[ YedjhWYj fbWdi WdZ if[Y_\_YWj_edi+ O^[ @d]_d[[h _i j^[ h[ifedi_Xb[ fWhjo m^e [dikh[i H?JOvi \WXh_YWj_ed L< fhe]hWc _i \ebbem[Z \eh _dif[Yj_ed WdZ WYY[fjWdY[ e\ j^[ [b[c[dj+
AWXh_YWj_ed i^ekbZ fheY[[Z edbo m_j^ Wffhel[Z i^ef ZhWm_d]i+ Cem[l[h) _\ j^[ AWXh_YWjeh ckij fheY[[Z fh_eh je h[Y[_fj e\ Wffhel[Z i^ef ZhWm_d]i &f[h\ehc_d] meha Wj j^[_h emd h_ia') [dikh[ j^Wj j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j _i WmWh[ e\ j^_i WYj_l_jo WdZ WmW_j _dijhkYj_ed ed ^em je fheY[[Z+ D\ j^[ @d]_d[[h f[hc_ji j^[ meha je fheY[[Z m_j^ekj Wffhel[Z i^ef ZhWm_d]i) fheY[[Z m_j^ XWi_Y L< \kdYj_edi ki_d] j^[ ded*Wffhel[Z i^ef ZhWm_d]i+ GWj[h) l[h_\o dej[i W]W_dij Wffhel[Z ZhWm_d]i+ Iej_\o j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j _cc[Z_Wj[bo _\ \WXh_YWj_ed _i dej _d Yed\ehcWdY[ m_j^ j^[ Wffhel[Z i^ef ZhWm_d]i+
>+ ?kj_[i e\ j^[ L<D s L<D f[h\ehc_d] j^[ \WXh_YWj_ed _dif[Yj_ed ^Wi j^[ \ebbem_d] Zkj_[i7
.+ L<D ckij j^ehek]^bo kdZ[hijWdZ j^[ YedjhWYj+
/+ L<D ckij l[h_\o ij[[b cWj[h_Wb Y[hj_\_YWj_edi i^em Yecfb_WdY[ m_j^ =ko <c[h_YW YedjhWYj h[gk_h[c[dji+
26
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+..
0+ L<D ckij X[ fhe\_Y_[dj _d f[h\ehc_d] \h[i^ YedYh[j[ j[iji) iWcfb_d] W]]h[]Wj[ WdZ ej^[h cWj[h_Wbi) l[h_\o_d] cWj[h_Wb jhWY[WX_b_jo) WdZ _dif[Yj_d] YedYh[j[ fekhi+
1+ L<D ckij X[ fhe\_Y_[dj _d mh_j_d] h[fehji WdZ ki_d] Yecfkj[hi+
2+ L<D ckij dej_\o j^[ @d]_d[[h _\ fheZkYj_ed X[]_di X[\eh[ Wffhel[Z i^ef ZhWm_d]i Wh[ ed j^[ i^ef \beeh WdZ fhel_Z[Z je j^[ L<D+
3+ L<D ckij Yecckd_YWj[ Wbb YedY[hdi j^hek]^ L>D eh m^ec[l[h j^[ AWXh_YWjeh Z_h[Yji Zkh_d] j^[ fh[\WXh_YWj_ed c[[j_d]+
4+ L<D ckij Yecckd_YWj[ m_j^ L>D je eXjW_d j^[ meha iY^[Zkb[+
5+ L<D ckij \ebbem MDOT’s Structural Fabrication E-Construction Process \eh Ybei_d] ekj \WXh_YWj_ed _dif[Yj_ed \_b[+
?+ ?[\_Y_[dY_[i ed GeYWb <][dYo Khe`[Yji s H?JOvi L<D ckij dej_\o j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j _\ j^[o eXi[hl[ \WXh_YWj_ed eh _dif[Yj_ed Z[\_Y_[dY_[i ed beYWb W][dYo fhe]hWc &G<K' fhe`[Yji+ O^[ NjhkYjkhWb AWXh_YWj_ed @d]_d[[h m_bb h[fehj j^[ Z[\_Y_[dY_[i l_W [cW_b je j^[ @d]_d[[h j^Wj _i h[ifedi_Xb[ \eh YedijhkYj_ed el[hi_]^j e\ j^[ beYWb W][dYo fhe`[Yj WdZ YWhXed Yefo j^[ Wffb_YWXb[ >AN WdZ ?[i_]d ?_l_i_ed G<K @d]_d[[hi+
@+ Ddif[Yj_ed AWY_b_j_[i WdZ <YY[ii s AWY_b_j_[i \eh j^[ L<D ckij X[ fhel_Z[Z Xo j^[ AWXh_YWjeh f[h YedjhWYj+ L<D ckij ^Wl[ WYY[ii je Wbb fWhji e\ j^[ meha Wj Wbb j_c[i+ O^[ Wkj^eh_jo WdZ ][d[hWb Zkj_[i e\ j^[ L<D Wh[ if[Y_\_[Z _d N[Yj_ed .-1+-.+? WdZ @ e\ j^[ H?JO NjWdZWhZ Nf[Y_\_YWj_edi \eh >edijhkYj_ed+
A+ Ddif[Yj_ed @gk_fc[dj s L<D m_bb X[ \khd_i^[Z m_j^ j^[ \ebbem_d] _j[ci Xo j^[ @d]_d[[h7
.+ >edjhWYj &H?JO NN>) if[Y_Wb fhel_i_edi) ijWdZWhZ fbWdi) if[Y_Wb Z[jW_bi) fbWd i^[[ji) [jY+'
/+ <ffhel[Z i^ef ZhWm_d]i &fhel_Z[Z Xo AWXh_YWjeh'
0+ <YY[ii je H?JOvi AWXh_YWj_ed Ddif[Yj_ed $ >edijhkYj_ed Noij[c &AD>N'
1+ H?JO i^ef WffhelWb ijWcf
L<D ckij fhel_Z[ j^[ \ebbem_d] _dif[Yj_ed [gk_fc[dj7
.+ >ecfkj[h m_j^ ^_]^ if[[Z _dj[hd[j WYY[ii
/+ >[bb f^ed[ m_j^ YWc[hW
0+ AbWi^b_]^j
1+ O[cf[hWjkh[ c[Wikh_d] Z[l_Y[i YWfWXb[ e\ Yel[h_d] j^[ hWd][ \hec -qA je /--qA
2+ Ah[i^ YedYh[j[ j[ij_d] [gk_fc[dj &j^[hcec[j[h) ibkcf Yed[ a_j) WdZ W_h*c[j[h'
3+ H[Wikh_d] Z[l_Y[i &/-- \eej WdZ /- \eej ij[[b jWf[ WdZ YWb_f[hi'
4+ NjhW_]^j[Z][ WdZ b[l[bi
5+ NW\[jo [gk_fc[dj
6+ Jj^[h Wi d[[Z[Z \eh j^[ fhe`[Yj
1+..+-1+ Ddif[Yj_ed KheY[Zkh[
<+ Kh[\WXh_YWj_ed H[[j_d] s Kh[\WXh_YWj_ed c[[j_d]i \WY_b_jWj[ [\\[Yj_l[ gkWb_jo Yedjheb WdZ gkWb_jo WiikhWdY[ ed j^[ fhe`[Yj WdZ Wh[ YedZkYj[Z Xo H?JOvi NjhkYjkhWb AWXh_YWj_ed Pd_j fh_eh je j^[ ijWhj e\ \WXh_YWj_ed WdZ fh[\[hWXbo W\j[h i^ef ZhWm_d]i ^Wl[ X[[d
27
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+..
Wffhel[Z+ O^[ NjhkYjkhWb AWXh_YWj_ed Pd_j) L<D) AWXh_YWjeh) WdZ L>D ckij X[ fh[i[dj) m^[h[Wi j^[ @d]_d[[h WdZ >edjhWYjeh i^ekbZ X[ fh[i[dj je [dikh[ W j[Wc [\\ehj je \WY_b_jWj[ WYYkhWj[ WdZ j_c[bo YedijhkYj_ed+ LkWb_jo WiikhWdY[ WdZ gkWb_jo Yedjheb YedjWYj _d\ehcWj_ed m_bb X[ i^Wh[Z Zkh_d] j^_i c[[j_d] je [dikh[ [\\[Yj_l[ Yecckd_YWj_ed+
=+ AWXh_YWj_ed Ddif[Yj_ed s Ied*fh[ijh[ii[Z YedYh[j[ ckij X[ \WXh_YWj[Z _d WYYehZWdY[ m_j^ j^[ H?JO NN> WdZ YedjhWYj+ L<D WdZ L>D ckij fWii H?JO _dZ[f[dZ[dj WiikhWdY[ j[ij_d] &D<O' fh_eh je f[h\ehc_d] \h[i^ YedYh[j[ j[ij_d] ed Wd WddkWb XWi_i+ AWXh_YWj_ed _dif[Yj_ed ckij X[ f[h\ehc[Z Wi i^emd X[bem7
.+ Ied*fh[ijh[ii[Z YedYh[j[ \WXh_YWj_ed _dif[Yj_ed Yedi_iji e\ l[h_\o_d] Yecfb_WdY[ m_j^j^[ Wffhel[Z i^ef ZhWm_d]i) YedjhWYj) WdZ Wffhel[Z I>Mi+ MADi ckij X[_dYehfehWj[Z _dje j^[ Wffhel[Z i^ef ZhWm_d]i \eh j^[ L<D je _dif[Yj je+
/+ <d Wffhel[Z HWj[h_Wbi NekhY[ G_ij &HNG' _i fhel_Z[Z je j^[ L<D Xo j^[ @d]_d[[h iej^Wj j^[ L<D ademi m^Wj cWj[h_Wbi Wh[ X[_d] _dYehfehWj[Z _dje j^[ fhe`[Yj WdZ m^Wjj^[ XWi_i e\ WYY[fjWdY[ _i+ O^[ HNG _i ki[Z je jhWYa cWj[h_Wb iWcfb_d] Xo j^[ L<DWdZ je \eij[h Yecckd_YWj_ed m_j^ L> je [dikh[ Wbb h[gk_h[Z iWcfb_d] WdZ j[ij_d]eYYkhi _d W j_c[bo cWdd[h je fh[l[dj _cfWYji je j^[ fhe`[Yj iY^[Zkb[+ Dj _i j^[AWXh_YWjehvi h[ifedi_X_b_jo je dej_\o j^[ L<D m^[d cWj[h_Wbi Wh[ WlW_bWXb[ \eh iWcfb_d]+
0+ L<D X[]_di Xo _dif[Yj_d] cWj[h_Wbi j^Wj m_bb X[ ki[Z _d j^[ \WXh_YWj_ed fheY[ii WdZ[dikh[i j^[o Wh[ X[_d] ijeh[Z Yehh[Yjbo) jW]][Z \eh jhWY[WX_b_jo fkhfei[i) WdZ Wh[ _dYed\ehcWdY[ m_j^ j^[ YedjhWYj+ I[nj) j^[ L<D _dif[Yji j^[ AWXh_YWjehvi ef[hWj_edi je[dikh[ j^[ YedZ_j_ed e\ j^[ [gk_fc[dj WdZ meha Wh[W \eh Yed\ehcWdY[ je j^[ YedjhWYj+
1+ H?JOvi <YY_Z[dj Kh[l[dj_ed KbWd ijWj[i) tH?JO [cfbeo[[i i^Wbb dej [d]W][ _d WdoWYj m^_Y^ mekbZ [dZWd][h Wdej^[h [cfbeo[[ eh j^[ci[bl[iu+ L<D ckij dej_\o j^[@d]_d[[h _cc[Z_Wj[bo _\ meha YedZ_j_edi [n_ij j^Wj Wh[ dej iW\[+ D\ j^[ b[l[b e\_dif[Yj_ed Z_c_d_i^[i X[bem m^Wj _i if[Y_\_[Z _d j^_i L< fheY[Zkh[) Zk[ je iW\[joYedY[hdi) j^[d j^[ [b[c[dj m_bb dej X[ Wffhel[Z \eh ki[+
>+ Aehc_d] WdZ >Wij_d]
.+ General Information * L<D ckij Yed\_hc j^[ Z_c[di_edWb h[gk_h[c[dji e\ j^[Xkba^[WZi) i_Z[ \ehci) X[Wh_d] fbWj[i) ij[[b h[_d\ehY[c[dj) le_Z Xen[i) _di[hji) WdZWdo ej^[h Z[l_Y[i f[h j^[ Wffhel[Z i^ef ZhWm_d]i Wi fWhj e\ j^[_h feij*fekh_dif[Yj_ed+ O^[ edbo [nY[fj_ed _i j^Wj Wdoj^_d] j^Wj YWddej X[ _dif[Yj[Zfeij*fekh) ckij X[ _dif[Yj[Z Zkh_d] fh[*fekh+ Dj _i _cfehjWdj je [cf^Wi_p[ j^Wj L<ckij dej ikf[hi[Z[ L> ie j^[ L<Dvi _dif[Yj_ed ckij Yec[ W\j[h L> ^Wi Yecfb[j[Zj^[_h _dif[Yj_ed WdZ Wffhel[i j^[ [b[c[dj+ L<D j^[d ki[i j^[ L> _dif[Yj_ed h[fehji&_\ WlW_bWXb[' Zkh_d] j^[_h l[h_\_YWj_ed _dif[Yj_ed+
/+ Concrete Forms * >edYh[j[ \ehci ckij X[ cW_djW_d[Z WdZ h[cW_d jhk[ je j^[ i^Wf[iWdZ Z_c[di_edi Wi i^emd ed j^[ Wffhel[Z ZhWm_d]i+
W+ H[jWb \ehci ckij X[ ki[Z i_dY[ j^[o Wh[ Z[i_]d[Z je X[ h_]_Z \eh h[f[j_j_l[YWij_d]i m_j^ekj Z[\ehc_d] eh m[Wa[d_d] Zk[ je j^[ ^[Wj \hec j^[ ^oZhWj_edfheY[ii+ Aehci ckij X[ m[bb XhWY[Z WdZ ij_\\[d[Z W]W_dij kdZ[i_hWXb[Z[\ehcWj_edi kdZ[h fh[iikh[ e\ \h[i^ YedYh[j[ WdZ ckij ^Wl[ iceej^ `e_djiWdZ _di_Z[ ikh\WY[i WYY[ii_Xb[ \eh WZ[gkWj[ Yb[Wd_d] W\j[h [WY^ ki[+
X+ Ee_dji X[jm[[d fWd[b \ehci ckij X[ cWZ[ WdZ cW_djW_d[Z iceej^ WdZj_]^j+ Pdb[ii ej^[hm_i[ i^emd ed Wffhel[Z i^ef ZhWm_d]i) Wbb Yehd[hi eh_dj[hi[Yj_edi e\ ikh\WY[i [nfei[Z _d j^[ Yecfb[j[Z ijhkYjkh[ ckij X[Y^Wc\[h[Z m_j^ W c_d_ckc Z_c[di_ed e\ -+2- _dY^[i WdZ Wbb h[*[djhWdj Wd]b[ickij X[ hekdZ[Z m_j^ W c_d_ckc hWZ_ki e\ -+42 _dY^[i+
28
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+..
Y+ Aehci j^Wj Wh[ mWhf[Z) Z_ijehj[Z) ZWcW][Z) eh _cfhef[hbo Yb[Wd[Z ckij dej X[ ki[Z+ ReeZ \ehci cWo X[ ki[Z \eh Xkba^[WZi+ O^[ _di_Z[ \WY[i e\ Wbb \ehci ckij X[ YeWj[Z m_j^ Wd Wffhel[Z Y^[c_YWb h[b[Wi[ W][dj+
0+ Reinforcing Steel s L<D ckij Yed\_hc j^Wj j^[ h[_d\ehY_d] ij[[b _i e\ j^[ Yehh[Yj i_p[) \h[[ \hec Z[\[Yji) WdZ fhef[hbo fei_j_ed[Z+ O^[ h[_d\ehY_d] ij[[b ckij X[ \h[[ e\ e_b) bkXh_YWdji) \eh[_]d cWj[h_Wb) WdZ [nY[ii_l[ hkij+ D\ [feno YeWj[Z XWhi Wh[ je X[ ki[Z j^[d d_Yai _d j^[ YeWj_d] Wh[ dej f[hc_jj[Z+
L<D ckij ifej Y^[Ya j^Wj j^[ h[_d\ehY_d] ij[[b ^Wi X[[d fhef[hbo fei_j_ed[Z WdZ i[Ykh[Z _d WYYehZWdY[ m_j^ j^[ Wffhel[Z i^ef ZhWm_d]i WdZ cWa[ Y[hjW_d j^Wj _di[hji ^Wl[ X[[d fbWY[Z m^[h[ h[gk_h[Z+
1+ Tests on Fresh Concrete s L<D ckij f[h\ehc j[ij_d] Wi h[gk_h[Z _d j^[ YedjhWYj WdZ ZeYkc[dj j^[ h[ikbji _d H?JO Aehc -26-+ O^[ AWXh_YWjeh ckij Yebb[Yj WZZ_j_edWb \h[i^ YedYh[j[ \eh L<D je f[h\ehc j^[_h j[iji Wi d[[Z[Z+
2+ Placing of Concrete s O^[ YedYh[j[ ckij X[ fhecfjbo fbWY[Z m_j^ c_d_ckc ^WdZb_d] je Wle_Z i[]h[]Wj_ed e\ j^[ cWj[h_Wbi WdZ j^[ Z_ifbWY[c[dj e\ j^[ h[_d\ehY[c[dj+ @WY^ [b[c[dj ckij X[ YWij _d W Yedj_dkeki ef[hWj_ed m_j^ c_d_cWb _dj[hhkfj_ed X[jm[[d j^[ fbWY_d] e\ WZ`WY[dj fehj_edi e\ YedYh[j[ WdZ [WY^ bWo[h ckij X[ fbWY[Z WdZ Yedieb_ZWj[Z X[\eh[ j^[ fh[Y[Z_d] bWo[h ^Wi jWa[d _d_j_Wb i[j+
3+ Consolidation of Concrete s < c_d_ckc Wcekdj e\ l_XhWj_ed d[Y[iiWho je j^ehek]^bo Yedieb_ZWj[ j^[ YedYh[j[ ckij X[ ki[Z+ L<D ckij l[h_\o W hkXX[h YeWj[Z l_XhWjeh ^[WZ _i ki[Z m^[d [feno*YeWj[Z eh ej^[h YeWj[Z h[_d\ehY[c[dj _i ki[Z+
?+ Curing Requirements * >kh_d] h[gk_h[c[dji \eh ded*fh[ijh[ii[Z YedYh[j[ ckij X[ Wi if[Y_\_[Z _d j^[ YedjhWYj+ R^[d ij[Wc eh hWZ_Wdj ^[Wj Ykh_d] _i ki[Z) h[YehZ_d] j^[hcec[j[hi ckij X[ fhel_Z[Z Xo j^[ AWXh_YWjeh j^Wj ced_jehi j^[ j_c[,j[cf[hWjkh[ h[bWj_edi^_f j^hek]^ j^[ Ykh_d] f[h_eZ m^_b[ Whj_\_Y_Wb ^[Wj _i ki[Z+ O^[ L<D ckij l[h_\o j^Wj j^[ h[YehZ_d] j^[hcec[j[hi Wh[ fbWY[Z _d Yh_j_YWb beYWj_edi \eh ced_jeh_d] j^[ j_c[,j[cf[hWjkh[ h[bWj_edi^_f Zkh_d] j^[ Ykh_d] f[h_eZ+ <j b[Wij j^h[[ h[YehZ_d] j^[hcec[j[hi ckij X[ fbWY[Z Wj beYWj_edi m^[h[ j^[ Wdj_Y_fWj[Z ^[Wj ][d[hWj[Z Xo j^[ YedYh[j[ _i j^[ bem[ij WdZ ^_]^[ij `kij W\j[h _d_j_Wb YedYh[j[ i[j+ ?eYkc[djWj_ed \hec j^[ AWXh_YWjeh%i h[YehZ_d] j^[hcec[j[h ckij X[ ]_l[d je j^[ L<D \eh j^[_h h[l_[m+ O[cf[hWjkh[ h[gk_h[c[dji Zkh_d] j^[ Ykh_d] ef[hWj_ed ckij X[ _d WYYehZWdY[ m_j^ j^[ YedjhWYj if[Y_\_YWj_edi+
@+ Material Requirements s HWj[h_Wbi ckij c[[j j^[ h[gk_h[c[dji e\ j^[ YedjhWYj kdb[ii W MAD h[gk[ij_d] Wbj[hdWj[ cWj[h_Wbi ^Wi X[[d Wffhel[Z Xo j^[ @d]_d[[h+
A+ Shipping Requirements s @b[c[dji ckij WjjW_d j^[ h[gk_h[Z Yecfh[ii_l[ ijh[d]j^ Wi _dZ_YWj[Z Xo j[ij h[ikbji e\ L> Yecfh[ii_l[ ijh[d]j^ j[ij Yob_dZ[hi) m^_Y^ ^Wl[ X[[d YWij WdZ cWjY^ Ykh[Z \eh j^_i fkhfei[ Wi Z[iYh_X[Z f[h j^[ YedjhWYj+ O^[i[ Yob_dZ[hi ckij X[ YWij m_j^ c[jWb H?JO jW]i WdZ j^[ Yecfh[ii_ed j[ij_d] ckij X[ m_jd[ii[Z Xo j^[ L<D+
1+..+-2+ M[fehji
<+ O^[ @d]_d[[h cWo h[gk_h[ W f[h_eZ_Y ijWjki h[fehj \hec j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j8 j^[h[\eh[) Wbb h[fehji Wh[ h[gk_h[Z je X[ Yecfb[j[Z _d W j_c[bo WdZ ehZ[hbo cWdd[h ki_d] j^[ Wffb_YWXb[ \_bbWXb[ fehjWXb[ ZeYkc[dj \ehcWj &K?A' \ehci b_ij[Z X[bem j^Wj YWd X[
29
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+..
\ekdZ ed H?JOvi m[Xi_j[+ HWa[ [djh_[i Wi ieed Wi feii_Xb[ W\j[h Wd [l[dj eh Yedl[hiWj_ed je [dikh[ WYYkhWYo+ IkcX[h j^[ h[fehji Yedi[Ykj_l[bo kdj_b Yecfb[j_ed e\ j^[ meha+
=+ L<D ckij Yecfb[j[ Wd WYYkhWj[ WdZ Z[jW_b[Z WYYekdj e\ \WXh_YWj_ed \eh j^[ fhe`[Yj+ O^[ h[fehj ckij _dYbkZ[ W Z_iYkii_ed e\ \WXh_YWj_ed fhe]h[ii \eh Wbb Wif[Yji e\ j^[ meha+ Dj _i _dj[dZ[Z je X[ W Z[jW_b[Z h[YehZ e\ j^[ ijWjki e\ \WXh_YWj_ed WdZ i^ekbZ _dYbkZ[ dkcX[h e\ [b[c[dji \WXh_YWj[Z) ZeYkc[djWj_ed e\ if[Y_\_YWj_ed WdZ fheY[Zkh[ Yecfb_WdY[ Wi m[bb Wi ZeYkc[djWj_ed e\ Yed\b_Yji) h[fW_hi) WdZ ej^[h fheXb[ci eh Z_iYkii_ed m^_Y^ YekbZ W\\[Yj j^[ fhe`[Yj _d WdomWo+ D\ \ehY[ WYYekdj meha _i jWa_d] fbWY[) ZeYkc[dj [WY^ ZWo j^Wj j^[ meha eYYkhi _d j^[ i^ef WdZ m^_Y^ [b[c[dji Wh[ X[_d] meha[Z+
>+ ?eYkc[djWj_ed _i dej W ikXij_jkj[ \eh Wffhefh_Wj[ Z_Wbe]k[ m_j^ j^[ AWXh_YWjeh) Xkj i^ekbZ fhel_Z[ W h[YehZ e\ _cfehjWdj Z_iYkii_edi+ Dd iec[ YWi[i) j^[ L<D _i ceh[ \Wc_b_Wh m_j^ j^[ [l[dji eh _iik[i WdZ j^[h[\eh[ i^ekbZ h[l_[m WdZ Yecc[dj ed ZhW\j Yef_[i e\ j^[ NjhkYjkhWb AWXh_YWj_ed Pd_jvi Yehh[ifedZ[dY[+
?+ M[fehji ckij X[ Wii[cXb[Z _dje ed[ \WXh_YWj_ed _dif[Yj_ed fehjWXb[ ZeYkc[dj \ehcWj &K?A' \_b[ WdZ ijeh[Z _d H?JOvi Khe`[YjR_i[ ZeYkc[dj ijehW][ fhe]hWc f[h MDOT’s Structural Fabrication Unit’s E-Construction Process+ O^[ @d]_d[[h m_bb h[Y[_l[ W \WXh_YWj_ed _dif[Yj_ed c[cehWdZkc \hec j^[ NjhkYjkhWb AWXh_YWj_ed @d]_d[[h W\j[h \WXh_YWj_ed _dif[Yj_ed _i Yecfb[j[+ O^[ c[cehWdZkc _i \eh _d\ehcWj_edWb fkhfei[i WdZ _i dej ki[Z \eh WYY[fjWdY[+
@+ =[bem _i W b_ij e\ lWh_eki H?JO h[fehji,\ehci WdZ W Xh_[\ Z[iYh_fj_ed e\ j^[_h fkhfei[ WdZ ki[ h[gk_h[c[dj+ N_c_bWh \ehci YWd X[ ki[Z _d fbWY[ e\ j^[ ijWdZWhZ H?JO \ehc _\ dej[Z X[bem+
.+ Project Folder Checklist (Form 2001) s O^_i \ehc ckij X[ Yecfb[j[Z Xo L<D \eh [WY^ fhe`[Yj+ O^[ Y^[Yab_ij _i fbWY[Z ed jef e\ j^[ \WXh_YWj_ed _dif[Yj_ed \ebZ[h m^[d j^[ fhe`[Yj _i Yecfb[j[+
/+ Shop Inspection Report (Form 5617) – O^_i \ehc ckij X[ Yecfb[j[Z Xo L<D ed W m[[abo XWi_i \eh [WY^ fhe`[Yj WdZ i^ekbZ YedjW_d W Xh_[\ dWhhWj_l[ e\ j^[ meha f[h\ehc[Z el[h j^[ h[fehj_d] f[h_eZ+ O^[ h[fehj ckij YedjW_d j^[ \ebbem_d] _d\ehcWj_ed7 R[Wj^[h YedZ_j_edi) [b[c[dji meha[Z ed) cWj[h_Wbi _dYehfehWj[Z _dje [b[c[dji &ckij ZeYkc[dj l_ikWbbo _dif[Yj[Z WdZ WYY[fj[Z') meha WYj_l_jo) dedYed\ehcWdY[i) i^_ff_d]) \ehY[ WYYekdj meha &hWh[') WdZ Wdoj^_d] [bi[ Z[[c[Z _cfehjWdj Xo j^[ L<D+
0+ Sample Identification (Form 1923) s O^_i \ehc ckij X[ ikXc_jj[Z m^[d cWj[h_Wb iWcfb_d] _i h[gk_h[Z ed W fhe`[Yj+ L<D ckij Yecfb[j[bo \_bb ekj j^[ \ehc WdZ a[[f W Yefo _d j^[ \WXh_YWj_ed _dif[Yj_ed \ebZ[h+
1+ Bar Reinforcement Report (Form 1985) s O^_i \ehc _i edbo ki[Z _\ L<D f[h\ehci L< l[h_\_YWj_ed _dif[Yj_ed ed XWh h[_d\ehY[c[dj \eh fh[\WXh_YWj[Z Xh_Z][ [b[c[dj ioij[ci &K=@N' eh ej^[h [b[c[dji j^Wj YedjW_d Yecfb[n h[_d\ehY[c[dj Wi Z_h[Yj[Z Xo j^[ @d]_d[[h+
5. Pre and Post Pour Inspection Checklist (Form 5616) s O^_i Y^[Yab_ij ckij X[ Yecfb[j[Z Xo L<D \eh W c_d_ckc e\ ed[ [b[c[dj f[h fhe`[Yj+ O^[ Y^[Yab_ij _i fbWY[Z _d j^[ \WXh_YWj_ed _dif[Yj_ed \ebZ[h m^[d j^[ fhe`[Yj _i Yecfb[j[+
3+ Field and Lab Test Report (Form 0590) s O^_i \ehc ckij X[ Yecfb[j[Z Xo L<D \eh [WY^ fekh m^_Y^ cWo YedjW_d i[l[hWb [b[c[dji+
30
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+..
4+ Repair Observation Report (Form 1981) s O^_i \ehc _i edbo ki[Z _\ L<D f[h\ehci L< l[h_\_YWj_ed _dif[Yj_ed ed h[fW_hi j^Wj ^Wl[ X[[d Wffhel[Z Xo j^[ @d]_d[[h+
5+ Material Source List (Form 0501) s O^_i \ehc _i i[dj _d Xo j^[ \WXh_YWjeh) j^[ L<D m_bb l[h_\o j^Wj j^[ \WXh_YWjeh \_bb[Z ekj j^[ \ehc Yecfb[j[bo) WdZ ZeYkc[dj j^[ XWi_i e\ WYY[fjWdY[ \eh Wbb cWj[h_Wbi+ D\ j^[h[ Wh[ Wdo cWj[h_Wbi j^Wj h[gk_h[ j[ij_d] j^[d j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j ckij X[ Yef_[Z ed j^[ Yecfb[j[Z HNG je YeehZ_dWj[ j^[ WYY[fjWdY[ j[ij_d]+
1+..+-3+ NjeYaf_b[ KWoc[dj
<+ O^_i ijeYaf_b[ fWoc[dj i[Yj_ed Z_h[Yji j^[ L<D ed j^[ h[gk_h[c[dji m^[d ijeYaf_b[ fWoc[dj _dif[Yj_ed _i h[gk[ij[Z Xo j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j+ O^[ L<D ckij f[h\ehc j^[ \ebbem_d] ij[fi7
.+ Q[h_\o \WXh_YWj[Z cWj[h_Wb c[[ji Wffhel[Z i^ef ZhWm_d]i &_\ Wffb_YWXb['8
/+ Q[h_\o ijeYaf_b[ gkWdj_jo WdZ _dYbkZ[ gkWdj_jo _d h[fehj8
0+ Q[h_\o cWj[h_Wb _i bWX[b[Z \eh H?JO ki[ edbo8
1+ Q[h_\o cWj[h_Wb _i Yehh[Yjbo ijeh[Z WdZ fhej[Yj[Z \hec j^[ [b[c[dji8 WdZ
2+ Khel_Z[ W h[fehj ikccWh_p_d] j^[ _dif[Yj_ed WdZ fhel_Z[ WZ[gkWj[ f^ejei j^Wj h[fh[i[dj j^[ ][d[hWb YedZ_j_ed e\ j^[ [b[c[dji) ^em j^[ovh[ X[_d] ijeh[Z) WdZ f_[Y[ cWhai+
1+..+-4+ <YY[fjWdY[
<+ O^[ AWXh_YWjeh _i h[gk_h[Z je fhel_Z[ j^[ L<D m_j^ W c_d_ckc e\ \_l[ &2' Yef_[i e\ j^[ =_bb e\ GWZ_d] \eh [WY^ i^_fc[dj+ L<D m_bb ijWcf [WY^ Yefo e\ j^[ =_bb e\ GWZ_d] m_j^ j^[ H?JO t<ffhel[Z \eh Pi[u ijWcf WdZ m_bb h[jW_d ed[ Yefo \eh j^[_h h[YehZi+ Dj _i j^[ AWXh_YWjehvi h[ifedi_X_b_jo je Z_ijh_Xkj[ j^[ h[cW_d_d] Yef_[i e\ =_bb e\ GWZ_d] je j^[ \ebbem_d] _dZ_l_ZkWbi7
.+ L<D
/+ >edjhWYjeh
0+ AWXh_YWjeh
1+ >edjhWYjeh
2+ OhkYa_d] YecfWdo
O^[ =_bb e\ GWZ_d] _i h[gk_h[Z je YedjW_d) Wj W c_d_ckc) j^[ \ebbem_d] _d\ehcWj_ed7
.+ N^_ff_d] ZWj[
/+ ?[iYh_fj_ed e\ YWh]e &gkWdj_jo) [b[c[dj i_p[) m[_]^j) [jY+'
0+ @b[c[dj kd_gk[ f_[Y[ cWha
1+ H?JO fhe`[Yj beYWj_ed &hekj[) Yheii heWZ,h_l[h) WdZ Y_jo'
2+ H?JO fhe`[Yj _d\ehcWj_ed &ijhkYjkh[ dkcX[h) Yedjheb i[Yj_ed) WdZ `eX dkcX[h'
3+ HWdk\WYjkh[hvi dWc[ WdZ WZZh[ii
=+ <YY[fjWdY[ Yedi_iji e\ j^[ \ebbem_d] jme*fWhj fheY[ii7
.+ AWXh_YWj_ed Ddif[Yj_ed <YY[fjWdY[7 NjhkYjkhWb [b[c[dji ckij X[ _dif[Yj[Z Xo j^[ L<D W\j[h j^[o Wh[ beWZ[Z \eh i^_ff_d]+ D\ j^[ ijhkYjkhWb [b[c[dji c[[j j^[ YedjhWYj
31
HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb /-./
1+..
h[gk_h[c[dji) j^[ L<D m_bb ijWcf j^[c t<ffhel[Z \eh Pi[u+ O^[ [b[c[dji ckij X[ ijWcf[Z t<ffhel[Z \eh Pi[u fh_eh je i^_ff_d]+ <ZZ_j_edWbbo) j^[ L<D ckij ijWcf Wj b[Wij \_l[ Yef_[i e\ j^[ =_bb e\ GWZ_d] j^Wj _i fh[fWh[Z Xo j^[ AWXh_YWjeh+ O^[ WffhelWb ijWcf _i \eh ki[ Xo j^[ ?[fWhjc[dj WdZ Ze[i dej h[b_[l[ j^[ >edjhWYjeh e\ j^[_h h[ifedi_X_b_jo je c[[j YedjhWYj h[gk_h[c[dji+
/+ Q_ikWb Ddif[Yj_ed &QD' <YY[fjWdY[7 O^[ @d]_d[[h ckij Yebb[Yj ed[ Yefo e\ j^[ijWcf[Z =_bb e\ GWZ_d] WdZ ki[ _j je l[h_\o j^[ Z[b_l[h[Z ijhkYjkhWb [b[c[dji+<ZZ_j_edWbbo) j^[ @d]_d[[h ckij l[h_\o j^Wj j^[ [b[c[dji Wh[ ijWcf[Z WdZ l_ikWbbo_dif[Yj j^[c \eh i_]di e\ ZWcW][ j^Wj cWo ^Wl[ eYYkhh[Z Wi W h[ikbj e\ i^_ff_d] WdZ^WdZb_d]+ O^_i l_ikWb _dif[Yj_ed i^ekbZ X[ ZeYkc[dj[Z _d j^[ \_[bZ _dif[Yjehvi ZW_boh[fehj+
32
(This page intentionally left blank)
*
STRUCTURAL FABRICATION UNIT
V011717
REQUEST FOR INFORMATION PROCESS
PAGE 1 of 3
MICHIGAN DEPARTMENT OF TRANSPORTATION
Structural Fabrication Request for Information Process
Description The purpose of this document is to provide the Michigan Department of Transportation (MDOT) with
statewide consistency managing and responding to a structural fabrication request for information (RFI).
MDOT’s Structural Fabrication Unit is responsible for implementing the Department’s quality assurance
program for structural elements that are required to be accepted based on “Fabrication Inspection” per
MDOT’s Materials Quality Assurance Procedures (MQAP) manual. MDOT utilizes vendor inspectors to
provide shop inspection for these structural elements. When information is requested, it is important for
MDOT to quickly respond to a RFI submittal in order to keep the project moving forward. This document is
broken down into the following sections:
1. Request for Information
2. RFI Report
3. RFI Submittal Process
4. Innovative Contracting
1. Request for Information Request for information is defined to be a request by the Fabricator seeking additional information or
proposing an alternate design, material, fabrication method, or inspection method for the structural
element. The Fabricator typically generates RFI submittals before shop drawings are produced, but they
are sometimes submitted after fabrication has begun. A RFI submittal is not to be confused with a
nonconformance report (NCR) that is defined to be an alteration in the work or a fabrication error that
results in the element not meeting project specifications. Each unique request should be submitted on a
separate RFI for housekeeping purposes.
The Structural Fabrication Unit is responsible for coordinating the RFI review process and should provide a
timely response or acknowledgement (explanation, decision, request for additional information, or
estimate of time needed to evaluate) within three business days after receiving the RFI submittal. The
Structural Fabrication Unit will distribute all RFIs that are design related to the Design PM for their
disposition and then the Design PM is responsible for engaging other MDOT areas, as applicable
(Roadside Development, Geometrics, etc.). MDOT will consider alternate fabrication methods or
configurations, materials, or inspection procedures proposed by the Fabricator provided the alternative
will result in improving or equaling the expected performance, maintenance, and longevity of the
structure; however, approval of a RFI may be contingent on a reduction in the contract unit price.
Contract modification due to approval of a RFI by the Fabricator requesting alternate material,
fabrication method, inspection method, or anything else that is not determined by the Engineer to be an
extra will be at no additional cost or time extension to MDOT. RFIs are resolved by providing an
appropriated response on the RFI form.
33
STRUCTURAL FABRICATION UNIT
V011717
REQUEST FOR INFORMATION PROCESS
PAGE 2 of 3
MICHIGAN DEPARTMENT OF TRANSPORTATION
2. RFI Report A RFI is generated by the Fabricator. The Fabricator is required to submit the RFI to MDOT as discussed in
Section 3 of this document.
MDOT has developed a standard Request for Information (Form 0558) form that should be used by the
Fabricator. Use of the form is recommended to facilitate a faster review process. RFIs submitted for
review are required to include, at a minimum, the following information:
" Follow MDOT’s file naming convention as shown on the RFI form;
" MDOT project information (structure number, control section, job number, project location, and
element mark);
" RFI number in ascending order for each project (resubmittals use a different RFI number);
" Clearly state what information is being requested or what is being proposed;
" Clearly state the required specifications if an alternate is being proposed;
" Include drawings (contract plan, sketches, etc.), numerous high resolution photos, product data
sheets, etc.;
" Indicate the urgency of a reply.
Approval of a RFI does not waive the contractual requirement to provide shop drawings prior to the start
of fabrication, nor is it sufficient information to allow MDOT’s quality assurance inspector (QAI) to stamp
elements approved for use. If the Fabricator elects to use an approved RFI then they need to
incorporate the RFI into the shop drawings for MDOT’s review and approval prior to the start of
fabrication. MDOT’s QAI is instructed to inspect using approved shop drawings and approved NCRs only.
The Fabricator is also required to obtain the Contractor’s acceptance of any contract modifications that
alter the finished product.
3. RFI Submittal Process Listed below is MDOT’s structural fabrication RFI submittal process:
1. Fabricator names RFI file per MDOT’s file naming convention shown on Form 0558.
2. Fabricator must send RFI to Structural Fabrication Unit and carbon copy the Engineer and Contractor. All correspondence to the Structural Fabrication Unit must be sent using the following email resource:
3. Structural Fabrication Unit distributes RFI to QAI and Design PM (if applicable) and begins reviewing.
4. Design PM distributes RFI to other areas (e.g. Geometrics, Load Rating, Roadside Development), as applicable, and provides all comments to Structural Fabrication Unit.
5. Structural Fabrication Unit provides response on RFI form via email to Fabricator and carbon copies the Engineer, Contractor, Design PM, and QAI.
34
STRUCTURAL FABRICATION UNIT
V011717
REQUEST FOR INFORMATION PROCESS
PAGE 3 of 3
MICHIGAN DEPARTMENT OF TRANSPORTATION
6. QAI places final RFI form and correspondence in the fabrication inspection file that will be stored in ProjectWise.
4. Innovative Contracting The request for information process described above applies to Design-Bid-Build projects. This section will
discuss subtle changes required to successfully submit RFIs for innovative contracting such as Design-Build
projects. Design-Build is an innovative construction method that pairs the Engineer of Record (EOR) with
the Contractor. The main difference between a Design-Build and a Design-Bid-Build project is that the
EOR on the Design-Build team is required to completely review and approve the RFI submittal prior to
MDOT’s review. Once the Design-Build team is satisfied with the submittal, the MDOT Design-Build Project
Manager (Design Build PM) acts as the MDOT RFI coordinator and distributes the submittal to the
Structural Fabrication Unit for review. The Structural Fabrication Unit returns any comments to the Design
Build PM. Once satisfied, the Structural Fabrication Unit stamps “Approved” on the RFI form. The Design
Build PM must be included on all correspondence related to a RFI, therefore Section 3 (RFI Submittal
Process) must be revised to reflect this for Design-Build projects.
35
H_Y^_]Wd ?[fWhjc[dj e\ OhWdifehjWj_ed
-225 &-.,.5' E7DH7FG 8BE <A8BE@3G<BAMAD "
Oe X[ Yecfb[j[Z Xo j^[ \WXh_YWjeh WdZ ikXc_jj[Z je j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j+ IWc_d] >edl[dj_ed7 -225 NI*>N*EI AWXh_YWjeh MAD"+fZ\
97A7E3? <A8BE@3G<BA
A<=MD><OJM , GJ><ODJI >JIOMJG N@>ODJI
EJ= ?@N>MDKODJI EJ= IPH=@M
MAD NP=E@>O NOMP>OPM@ "
?<O@
<A8BE@3G<BA E7DH7FG
@6BG E7FCBAF7
<ffhel[Z MAD) _\ _cfb[c[dj[Z Xo j^[ AWXh_YWjeh) ckij X[ _dYehfehWj[Z _dje j^[ i^ef ZhWm_d]i WdZ Wffhel[Z Xo j^[ @d]_d[[h fh_eh je j^[ ijWhj e\ \WXh_YWj_ed+
==N <ffhelWb =beYa
" NkXc_j je j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j WdZ YY j^[ >edjhWYjeh WdZ @d]_d[[h+
Clear Form
36
+
STRUCTURAL FABRICATION UNIT
V101915
NONCONFORMANCE POLICY
PAGE 1 of 5
MICHIGAN DEPARTMENT OF TRANSPORTATION
Structural Fabrication Nonconformance Policy
Description The purpose of this document is to provide the Michigan Department of Transportation (MDOT) with
statewide consistency in addressing material and fabrication nonconformance issues with structural steel
O\R ab`cQbc`OZ ^`SQOab Q]\Q`SbS SZS[S\ba+ C<EJja Ib`cQbc`OZ >OP`WQObW]\ K\Wb Wa `Sa^]\aWPZS T]`
W[^ZS[S\bW\U bVS <S^O`b[S\bja _cOZWbg Oaac`O\QS ^`]U`O[ T]` TOP`WQObW]\ W\a^SQbion and utilizes vendor
inspectors for inspection of structural steel and structural precast concrete elements at nationwide
fabrication facilities. When nonconforming material or fabrication issues are discovered the Structural
Fabrication Unit immediately notifies the Project Engineer (hereafter referred to as Engineer) overseeing
bVS Q]\ab`cQbW]\ ^`]XSQb ]T bVS RSTWQWS\QWSa+ Ab Wa bVS =\UW\SS`ja `Sa^]\aWPWZWbg b] `SXSQb ]` OQQS^b
nonconforming elements with consideration of imposing a negative price adjustment in accordance with
subsection 104.04 of the MDOT Standard Specifications for Construction. Bridge Field Services is available
to provide technical support to the Engineer when additional guidance is needed. Guidelines are
provided in this document for the Engineer and Structural Fabrication Unit to use when determining if a
price reduction is warranted. When a price reduction is warranted, the Structural Fabrication Unit
provides the recommended amount to ensure statewide consistency and alignment. Below is a list of the
structural elements inspected for acceptance by the Structural Fabrication Unit for which this document
applies (see contract documents for project specific information):
' Structural steel for bridges (plate, rolled, hollow structural shape, bridge tube railing, steel deck
grating, modular expansion joints, castings, forgings, etc.);
' Highway structures (sign structures, tower lighting units, mast arm traffic signals, DMS, etc.);
' Structural precast concrete (prestressed concrete beams, spun concrete poles, sound wall
panels/posts, MSE wall panels/posts, etc.);
' Precast concrete three-sided, arch, and box culverts (span lengths 20 feet and greater measured
parallel to the roadway centerline).
This document does not address fabricated elements cast by the contractor on the project site or non-
structural precast concrete (concrete pipe, manhole, etc.).
1. Control of Materials The service life of a highway is dependent upon the quality of the materials used in its construction as well
as the method of construction. Therefore, it is critical to ensure the materials incorporated into the work
meet the project specifications. Control of materials is discussed in subsection 105 of the MDOT 2012
Standard Specifications for Construction (hereafter referred to as Standard Specifications) with
information on approval of materials in subsection 105.05 and nonconforming materials in subsection
105.08. The Engineer may inspect materials that the contractor will incorporate into the work at any time
37
STRUCTURAL FABRICATION UNIT
V101915
NONCONFORMANCE POLICY
PAGE 2 of 5
MICHIGAN DEPARTMENT OF TRANSPORTATION
and at any place during the preparation, storage, and use of the materials. The Engineer will perform
inspections of the materials, including sampling and testing, in accordance with the methods required by
the contract to determine if the material is approved for use. Approval of materials is discussed in the
<S^O`b[S\bja CObS`WOZa GcOZWbg 8aac`O\QS F`]QSRc`Sa CO\cOZ &CG8F'+
2. Nonconforming Materials i Acceptable and Unacceptable UseAb Wa bVS <S^O`b[S\bja W\bS\b b] RWaQ]c`OUS bVS caS ]T \]\Q]\T]`[W\U [ObS`Wals from being incorporated
into the work even if they are found acceptable for use. Subsection 105.08 of the Standard
Specifications gives the Engineer the authority to either reject nonconforming materials or to allow the
nonconforming materials to remain in place. If materials are found to be unacceptable before or after
placement into the work, the Engineer may reject the materials, and the contractor must remove the
materials from the site at no cost to the Department. Materials that have been tested and approved at
their source or otherwise previously approved, but have become damaged or contaminated before use
in the project, are also subject to rejection by the Engineer.
Materials that are nonconforming, but determined by the Engineer to be acceptable for use may be
subject to a negative price adjustment. To ensure consistency in the decisions made for acceptance of
nonconforming material or workmanship, it is recommended the Engineer involve Bridge Field Services
before finalizing any decision. This communication will help keep the applicable technical sections of the
Bureau of Field Services informed about contractor or material problems that may require specification
changes, a Bridge Field Services Advisory, or discipline of a contractor. Additionally, this communication
will aid in the consistent treatment of nonconforming materials statewide. The Bureau of Field Services is
available to provide technical support if the Engineer has any questions regarding the acceptance or
rejection of nonc]\T]`[W\U [ObS`WOZa+ Ab Wa bVS =\UW\SS`ja `Sa^]\aWPWZWbg b] RSbS`[W\S eVSbVS` O
nonconforming material is acceptable for use; however, Bridge Field Services can assist with
recommendations.
2.1 Determining if Nonconforming Material can be Incorporated into the Work Good engineering judgment is required when making decisions on nonconforming materials. The
Engineer may choose to approve nonconforming materials, allow them to be incorporated into
the work, and impose a negative price adjustment. When making the decision to direct the
contractor to remove and replace the materials versus leave the materials in place, it is important
to consider the following:
' Safety;
' Long-term consequences on quality and durability;
' A[^ZWQObW]\a ]\ bVS ab`cQbc`OZ SZS[S\bjs life cycle costs, service life, serviceability, and
maintenance;
' Environmental and aesthetic considerations;
' A[^OQba ]\ bVS ^`]XSQbja b`OTTWQ) abOUW\U) O\R Q]\ab`cQbW]\ bW[ST`O[Sa6
' Future costs associated with maintenance.
38
STRUCTURAL FABRICATION UNIT
V101915
NONCONFORMANCE POLICY
PAGE 3 of 5
MICHIGAN DEPARTMENT OF TRANSPORTATION
2.2 Determination of Price Reductions After the Engineer has decided to allow nonconforming materials to remain in place, the
Structural Fabrication Unit will carefully evaluate each situation in deciding whether to
recommend a price reduction. The goal is to achieve statewide consistency in administering
price reductions for nonconforming materials that are allowed to remain place. The purpose of
the price reduction is to facilitate an environment that encourages the contractor to incorporate
materials meeting contract specifications and to make it fair for all contractors.
Results of retests and related quality tests should be considered. The following list includes some
examples of the types of factors the Structural Fabrication Unit will consider when deciding if a
price reduction is warranted:
' Has the contractor been conscientious to provide quality by carefully controlling materials
and construction operations?
' Has the contractor been proactive and made good use of quality control (QC) data to
maintain and improve quality?
' Did the contractor notify the Engineer of materials that needed to be tested in a timely
manner to ensure the test results would be reported prior to the materials being
incorporated?
' Did the Engineer process the test results within the industry accepted timeframe so the
contractor could make process or materials corrections?
' Upon becoming aware of a materials quality problem, has the contractor responded
quickly to correct it?
' Is the nonconforming test an isolated incident or a recurring situation?
' How does the nonconforming test compare to the rest of the project data:
o Have material test results been well within specification requirements or
consistently at the very limit of what is acceptable?
o How many tests are nonconforming versus how many tests have passed?
o How far out of specifications is the nonconforming test?
2.3 Nonconforming Structural Precast Concrete If the Engineer has decided to accept nonconforming material and it is determined that a
negative price adjustment is warranted then the final step is for the Structural Fabrication Unit to
determine a recommended price reduction. The following guidelines provide a list of common
nonconformance issues related to the structural precast concrete industry and are intended to
aid the Structural Fabrication Unit in determining the recommended price reduction. The goal of
these guidelines is to provide consistent price reductions independent of the type of project or
project office location.
The Engineer must justify and document the incorporation of any nonconforming materials into
the work. The Structural Fabrication Unit will provide the Engineer with the quantity and type of
\]\Q]\T]`[W\U [ObS`WOZ T]` bVS ^`]XSQb ]TTWQSja `SQ]`Ra+ E\Zg ]\S ^`WQS ORXcab[S\b aV]cZR PS
applied to a given quantity of material; however, if multiple nonconformance issues occur then
39
STRUCTURAL FABRICATION UNIT
V101915
NONCONFORMANCE POLICY
PAGE 4 of 5
MICHIGAN DEPARTMENT OF TRANSPORTATION
the price reduction may be increased on a case by case basis. In general, if the quantity in
question is subject to more than one of the following price reductions then the greater price
reduction would apply.
Any structural precast concrete element judged to be structurally or otherwise unacceptable by
MDOT due to low strength, cracking, breakage, honeycombing, or other deficiency will be
rejected and replaced. Note that honeycombing with exposed prestressing strand automatically
falls into this category.
Any structural precast concrete element judged to be acceptable, but deficient by MDOT due to
any of the following issues will be subject to the pay deductions listed below. These guidelines for
standard deductions are intended to be applied to typical problem severity in the majority of
cases. In occasional cases where problem severity is lower or higher than typical, the pay
deduction may be decreased or increased, respectively. Standard deductions shown represent
a percentage of bid item price for the structural precast concrete element.
2.3.1 Nonconforming Compressive Strength Compressive strength below specified level at required test age for strand release,
stripping forms, shipping, etc. is subject to the greater of $500 or 20% deduction on the bid
item price if the elements are approved for use. This price reduction would apply for all
elements represented by the tested cylinders.
2.3.2 Nonconforming Fabrication Defects Price reduction for the following fabrication defects and nonconformance issues will be
recommended by the Structural Fabrication Unit and should be implemented by the
Engineer. The following table of deductions will be applied to infrequent occurrences of
the stated defects. In the event of repeated occurrences of the same defect, these
deductions will be doubled. Note that negative pay adjustments may be waived for
minor fabrication and nonconformance defects judged to be inconsequential. The
following price reduction percentages are deducted from the bid item price and are only
applicable to nonconforming structural precast elements determined by the Engineer to
be acceptable:
' Misalignment of form and soffit joints (1/8 inch or greater on flat surface) i 10%
deduction;
' Inadequately sealed joints with significant mortar washout i 10% deduction;
' Cracking/spalling caused by fabrication and curing i 10% deduction;
' Dimensional tolerance deviations outside contract documents i 10% deduction;
' Honeycombing i 10% deduction;
' * Curing temperature i 10% deduction;
' Broken/cracked components i 10% deduction.
* Structural precast concrete elements cured at elevated temperatures are suspect in
terms of durability. The Structural Fabrication Unit will make a recommendation to the
Engineer to either reject the element or accept it with a price reduction.
40
STRUCTURAL FABRICATION UNIT
V101915
NONCONFORMANCE POLICY
PAGE 5 of 5
MICHIGAN DEPARTMENT OF TRANSPORTATION
2.3.3 Nonconforming Miscellaneous Items The Engineer must determine the quantity of nonconforming material. Only one price
adjustment will be applied to a given quantity of material. If the quantity in question is
subject to more than one of the following conditions, apply the adjustment with the
greater price reduction.
2.3.4 Minor Nonconformance If the structural element does not conform to the requirements of the contract, but is
accepted, apply one of the following two price reductions (if not already covered in part
2.3.1 or 2.3.2):
1. 20% price reduction on the bid item price;
2. 50% price reduction on all material (invoice) costs utilized to fabricate the structural
precast concrete element.
2.3.5 Major Nonconformance The Engineer should not pay for elements determined by the Department to be in major
nonconformance with the contract requirements.
2.4 Nonconforming Structural Steel Due to the specialized nature and track record of structural steel fabrication, acceptable
nonconformance rarely lends itself to recommended price reductions. In general, deficient
structural welds can be easily replaced and the homogenous nature of steel typically means if
the material does not meet specification then it is rarely accepted even with a price reduction.
However, the Structural Fabrication Unit would review and provide a recommended price
reduction to the Engineer on a case by case basis depending on the nature of the deficiency,
recurrence, etc. Dimensional tolerance deviations outside the contract documents is an example
of a workmanship nonconformance subject to a 10% price deduction from the bid item price if
the structural steel element is determined by the Engineer to be acceptable.
2.5 Special Cases For other nonconforming issues not covered above, consult personnel in the appropriate area of
the Bureau of Field Services for guidance. Some examples of items in which it may be
unacceptable to leave the nonconforming item in place, even at reduced cost, include the
following:
' Bar reinforcement;
' Anchor bolts;
' High strength bolts+
41
(This page intentionally left blank)
(This page intentionally left blank)
(This page intentionally left blank)
STRUCTURAL FABRICATION UNIT
V092517
NONCONFORMANCE PROCESS
PAGE 1 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
Structural Fabrication Nonconformance Reporting Process
Description The purpose of this document is to provide the Michigan Department of Transportation (MDOT) with
statewide consistency managing and responding to a structural fabrication nonconformance report
(NCR). B;DIi_ H`^aO`a^MX =MN^UOM`U[Z JZU` U_ ^Q_\[Z_UNXQ R[^ UY\XQYQZ`UZS `TQ ;Q\M^`YQZ`i_ ]aMXU`e
assurance program for structural elements that are required to be accepted based on g=MN^UOM`U[Z
@Z_\QO`U[Zh \Q^ B;DIi_ BM`Q^UMX_ FaMXU`e 7__a^MZOQ E^[OQPa^Q_ %BF7E& YMZaMX. MDOT utilizes vendor
inspectors to provide shop inspection for these structural elements. When nonconformance occurs, it is
important for MDOT to quickly respond to a NCR submittal to keep the project moving forward. This
document is broken down into the following sections:
1. Nonconformance
2. QC Nonconformance Report
3. QA Nonconformance Report
4. NCR Submittal Process
5. MDOT Standard Repair Procedures
6. Innovative Contracting
1. Nonconformance Nonconformance is defined to be an alteration in the work or a fabrication error that results in the
element not meeting project specifications. A NCR is not to be confused with a request for information
(RFI) that is defined to be a request by the Fabricator seeking additional information or proposing an
alternate material, fabrication method, or inspection method. A RFI is typically submitted before
fabrication work begins, whereas a NCR is submitted after a nonconformance is observed by quality
control (QC). Nonconformance renders the affected element unacceptable until such time as the issue
is referred to MDOT for disposition. Nonconformance that results in the Fabricator rejecting an element
does not require a NCR to be submitted for review; however, MDOT does request the Fabricator to send
our quality assurance inspector (QAI) written correspondence that clearly documents who rejected the
element, why it was rejected, when it was rejected, and proposed changes to the piece mark naming
convention for the fabrication inspection records.
Nonconformance is generally defined to be material or workmanship in nature and is further classified by
MDOT to be minor or major. Minor nonconformance can be repaired by the Fabricator using a
preapproved MDOT standard repair procedure that can be found in the MDOT Structural Precast
Concrete Standard Repair Program and does not need to be approved by MDOT on a case by case
basis throughout the project. Major nonconformance can typically be repaired by the Fabricator using a
MDOT standard repair procedure that can be found in the MDOT Structural Precast Concrete Standard
Repair Program and does need to be approved by MDOT on a case by case basis throughout the
42
STRUCTURAL FABRICATION UNIT
V092517
NONCONFORMANCE PROCESS
PAGE 2 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
project. Below are common minor nonconformances that can be repaired using a preapproved MDOT
standard repair procedure:
' Cosmetic and in-process weld defects;
' Concrete air hole;
' Epoxy coated reinforcing steel damage;
' Coating damage;
' Hot-dip galvanizing damage.
Examples of major nonconformances include, but are not limited to the following:
' Buy America;
' Material specifications;
' Element dimensions;
' Unauthorized repairs;
' NCR corrective action without adequate notification;
' Coating system requirements;
' Unauthorized welds;
' Defective structural welds;
' Unqualified welder or welding operator;
' Welding without approved weld procedure specifications (WPS);
' Overheating steel and not maintaining preheat;
' Fresh concrete properties;
' Strength requirements;
' Concrete curing requirements;
' Honeycombing, voids, and concrete damage (except air holes).
The QAI should obtain clarification from the Structural Fabrication Unit if the QAI has questions regarding
the proper disposition method for nonconformances. All nonconformance issues observed by the QAI
must be brought to the attention of the Fabricator immediately upon discovery; however, the QAI must
not direct corrective action. The QAI must notify the Structural Fabrication Unit immediately if the
Fabricator fails to take corrective action or continues to fabricate nonconforming elements. Verbally
notifying the Fabricator of nonconformance is sometimes sufficient; however major nonconformance
issues should always be followed up in writing to the Fabricator via email with a carbon copy to the
Structural Fabrication Unit. The Structural Fabrication Unit will decide if the Fabricatori_ [\Q^M`U[Z_
warrant notifying the MDOT Construction Engineer (Engineer) and MDOT Design Project Manager (Design
PM) to prevent schedule delays or potential claims. An internal conference call amongst the Structural
Fabrication Unit, Engineer, Design PM, and QAI may be needed to better understand the issue and to
discuss /,16KG 5HFI9HIF7A -78F?97H?DC 0DC9DC=DFB7C9< 2DA?9J to ensure statewide consistency with
acceptance of nonconforming materials and potential price reductions if nonconforming elements are
permitted to be incorporated into the project.
43
STRUCTURAL FABRICATION UNIT
V092517
NONCONFORMANCE PROCESS
PAGE 3 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
The Structural Fabrication Unit is responsible for coordinating MDOTs NCR review process and should
provide a timely response or acknowledgement (explanation, decision, request for additional
information, or estimate of time needed to evaluate) within three business days after receiving the NCR
submittal. The Structural Fabrication Unit will distribute all NCRs that are design related to the Design PM
for their disposition and then the Design PM is responsible for engaging other MDOT areas (Roadside
Development, Geometrics, etc.), as applicable. All NCRs M^Q ^Q]aU^QP `[ NQ _`MY\QP g7\\^[bQPh by the
Structural Fabrication Unit on the coversheet if they are found to be acceptable to MDOT.
Unacceptable NCRs are returned to the Contractor with an appropriate response MZP _`MY\QP gC[`
7\\^[bQPh. Corrective action that requires use of a weld procedure specification (WPS) will require the
Structural Fabrication Unit to stamp the WPS in addition to the NCR.
2. QC Nonconformance Report QC NCRs are generated by the Fabricator after their QCI observes a nonconformance during their
inspection. The Fabricator is required to submit the NCR to MDOT as discussed in Section 4 of this
document if they intend to have the element considered by MDOT to be incorporated into the project.
Although not required, it is highly recommended that the QCI discuss the NCR submittal with the QAI to
ensure it is in general conformance with MDOT requirements. The QAI should not review the actual NCR
at this point in time since they will be asked to verify that the NCR is accurate by the Structural Fabrication
Unit after the Contractor submits it to MDOT.
MDOT has developed a standard Nonconformance Report (Form 0559) that should be used by the
Fabricator. Use of the form is recommended to facilitate a faster review process. NCRs submitted for
review are required to include, at a minimum, the following information:
' =[XX[c B;DIi_ RUXQ ZMYUZS O[ZbQZ`U[Z as shown on the NCR form;
' MDOT project information (structure number, control section, job number, project location, and element mark);
' NCR number in ascending order for each project (resubmittals use the same NCR number, but would have a different revision number);
' Clearly state the nonconformance;
' State the reason for nonconformance;
' State measures to prevent nonconformance from occurring again;
' Include supporting documentation (marked up shop drawings, QC reports, WPS, PQR, numerous high resolution photos showing all locations proposed to be repaired, etc.);
' State proposed corrective action (repair procedure, NDE, MDOT standard repair procedure, etc.);
' Indicate the urgency of a reply.
The Fabricator must notify the QAI, prior to performing repairs to the nonconforming element, so MDOT
has the opportunity to witness the repair. Elements containing repairs performed without adequate
notification for QA inspection may not be approved for use. All nonconformances must be properly
resolved before the element can be considered for acceptance.
44
STRUCTURAL FABRICATION UNIT
V092517
NONCONFORMANCE PROCESS
PAGE 4 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
3. QA Nonconformance Report It is not common for MDOT to write a NCR; however, a QA NCR could be issued due to the following
reasons:
1. Fabricator does not acknowledge a material or workmanship nonconformance.
2. QAI verification inspection results in major nonconformance missed by QCI during their inspection.
The Structural Fabrication Unit uses the standard Quality Assurance Nonconformance Report (Form 0560)
for a QA NCR and submits the completed form to the Engineer and Design PM for their review and
subsequent discussion. It is important for QA to document when QC is ineffective so the appropriate
quality management system organization (AISC, NPCA, and PCI) specified by MDOT in the contract
documents can follow up with the complaint. The Fabricator is required to respond to the QA NCR by
either submitting their own NCR acknowledging they are in agreement with the QA NCR or in writing that
they are in disagreement. The Fabricatori_ C9G U_ ^Q]aU^QP `[ UZOXaPQ MXl of the information stated in
Section 2 of this document. A conference call may be requested by the Structural Fabrication Unit
between the Engineer, QAI, Contractor, Fabricator, and QCI to discuss the NCR.
Once all elements have been re-inspected by the QCI, they must notify the QAI via email or by submittal
of the QC report that the QC inspection is complete for the elements under consideration. The QAI will
start the QA verification inspection again and if major nonconformances are found then the process will
repeat itself. It is important to note that the QAI must not perform their QA verification inspection until
after QCI notifies them via email or by submittal of the QC report that their QC inspection is complete for
the elements under consideration. This prevents QA from inspecting prior to QC.
4. NCR Submittal Process AU_`QP NQX[c U_ B;DIi_ structural fabrication NCR submittal process:
1. Fabricator ZMYQ_ C9G RUXQ \Q^ B;DIi_ RUXQ ZMYUZS O[ZbQZ`U[Z shown on Form 0559.
2. Fabricator must send NCR to the Structural Fabrication Unit and carbon copy the Engineer and Contractor. All correspondence to the Structural Fabrication Unit must be sent using the following email resource:
3. Structural Fabrication Unit distributes NCR to QAI and Design PM (if applicable) and begins reviewing.
4. Design PM distributes NCR to other areas (e.g. Geometrics, Load Rating, Geotechnical, Roadside Development), as applicable, and provides all comments to the Structural Fabrication Unit.
5. Structural Fabrication Unit provides response on NCR via email to Fabricator and carbon copies the Engineer, Contractor, Design PM, and QAI.
6. QAI places final NCR and correspondence in the fabrication inspection file that will be stored in ProjectWise.
45
STRUCTURAL FABRICATION UNIT
V092517
NONCONFORMANCE PROCESS
PAGE 5 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
5. MDOT Standard Repair Procedures The Structural Fabrication Unit has developed standard repair procedures to expedite the review process
for common repairs to structural elements. These repair procedures have been reviewed by industry and
should be used by Fabricators when applicable to speed up the review process. Standard repair
procedures for structural steel have not been developed at the time of this document, but will be added
in subsequent revisions.
Listed below are the MDOT standard structural precast concrete repair procedures, which can be found
in /,16KG 5HFI9HIF7A 2F<97GH +DC9F<H< 4<E7?F .I?;7C9< ,D9IB<CH on B;DIi_ H`^aO`a^MX =MN^UOM`U[Z
JZU`i_ cQN_U`Q:
1. * Procedure #1: Air Hole
2. Procedure #2: Minor Surface Defect
3. Procedure #3: Major Surface Defect
4. * Procedure #4: Hot-Dip Galvanize
5. Procedure #5: Fiber Reinforced Polymer
6. * Procedure #6: Epoxy Bar
7. Procedure #7: Epoxy Injection
* Indicates MDOT standard repair procedure for minor nonconformance. These procedures can be
preapproved by the Structural Fabrication Unit before the project begins and do not need to be
approved on a case by case basis throughout the project. Fabricator is required to notify the QAI when
the repairs will be performed so they can have the opportunity to witness. Fabricator must have copies
of the standard repair plan with them at all times while performing the repair.
Listed below is the MDOT standard structural steel repair procedure:
1. Procedure #1: Shop Coating Repairs
6. Innovative Contracting The nonconformance reporting process described above applies to Design-Bid-Build projects. This
section will discuss subtle changes required to successfully submit NCRs for innovative contracting such as
Design-Build projects. Fabrication nonconformance should already be addressed in the Design-Build
Design Quality Manual (DQM)5 T[cQbQ^( B;DIi_ H`^aO`a^MX =MN^UOM`U[Z C[nconformance Policy provides
MDOT with statewide consistency in addressing material and fabrication nonconformance issues.
Design-Build is an innovative construction method that pairs the Engineer of Record (EOR) with the
Contractor. The main difference between a Design-Build and a Design-Bid-Build project is that the EOR
on the Design-Build team is required to completely review and approve the NCR submittal prior to
B;DIi_ ^QbUQc* DZOQ `TQ ;Q_USZ-Build team is satisfied with the submittal, the MDOT Design-Build Project
Manager (Design Build PM) acts as the MDOT NCR coordinator and distributes the submittal to the
Structural Fabrication Unit for review. The Structural Fabrication Unit returns any comments to the Design
46
STRUCTURAL FABRICATION UNIT
V092517
NONCONFORMANCE PROCESS
PAGE 6 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
Build PM. If satisfied, the Structural Fabrication Unit stamps gApprovedh _`MY\ [Z `TQ C9G* The Design
Build PM must be included on all correspondence related to a NCR, therefore Section 4 (NCR Submittal
Process) must be revised to reflect this.
47
H_Y^_]Wd ?[fWhjc[dj e\ OhWdifehjWj_ed
-226 &-.,.5' ABA5BA8BE@3A57 E7CBEG I>M "
Oe X[ Yecfb[j[Z Xo j^[ \WXh_YWjeh WdZ ikXc_jj[Z je j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j+ IWc_d] >edl[dj_ed7 -226 NI*>N*EI AWXh_YWjeh I>M" M@Q"+fZ\
97A7E3? <A8BE@3G<BA
A<=MD><OJM , GJ><ODJI >JIOMJG N@>ODJI
EJ= ?@N>MDKODJI EJ= IPH=@M
I>M NP=E@>O NOMP>OPM@ "
?<O@
ABA5BA8BE@3A57 67F5E<CG<BA
E73FBA 8BE ABA5BA8BE@3A57
E75HEE7A57 CE7I7AG<BA 35G<BA
5BEE75G<I7 35G<BA
IedYed\ehcWdY[i h[dZ[h j^[ [b[c[dj kdWYY[fjWXb[ \eh ki[ kdb[ii j^[ @d]_d[[h Wffhel[i j^[ dedYed\ehcWdY[+ 44F 3ZZ[Y_LV 4VYNU
" >ecX_d[ j^_i ZeYkc[dj m_j^ Wbb h[b[lWdj L> h[fehji) f^ejei) h[fW_h fbWdi) RKN) [jY+ _dje ed[ K?A ZeYkc[dj fh_eh je
ikXc_jj_d] je j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j \eh WffhelWb+ YY j^[ >edjhWYjeh WdZ @d]_d[[h+
Clear Form
48
H_Y^_]Wd ?[fWhjc[dj e\ OhWdifehjWj_ed
-23- &-.,.5' DH3?<GK 3FFHE3A57 ABA5BA8BE@3A57 E7CBEG
L< I>M "
Oe X[ Yecfb[j[Z Xo j^[ H?JO L< _dif[Yjeh WdZ ikXc_jj[Z je j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j+ IWc_d] >edl[dj_ed7 -23- NI*>N*EI AWXh_YWjeh L< I>M" M@Q"+fZ\
97A7E3? <A8BE@3G<BA
KM@K<M@? =T * >JHK<IT >JIOMJG N@>ODJI
A<=MD><OJM , GJ><ODJI EJ= IPH=@M
EJ= ?@N>MDKODJI NOMP>OPM@ "
I>M NP=E@>O ?<O@
ABA5BA8BE@3A57#67F5E<CG<BA
" >ecX_d[ j^_i ZeYkc[dj m_j^ Wbb h[b[lWdj L> h[fehji) f^ejei) h[fW_h fbWdi) RKN) [jY+ _dje ed[ K?A ZeYkc[dj fh_eh je
ikXc_jj_d] je j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j+
Clear Form
49
STRUCTURAL FABRICATION UNIT
V103015
STD REPAIR GUIDANCE DOCUMENT
PAGE 1 of 9
MICHIGAN DEPARTMENT OF TRANSPORTATION
Structural Precast Concrete Repair Guidance Document
Description The purpose of this guidance document is to provide the Michigan Department of Transportation (MDOT)
with statewide consistency reviewing and approving structural precast (prestressed and non-prestressed)
concrete repair submittals. It provides internal guidance for the minimum acceptable procedures to
ensure a durable repair that will preserve the integrity of the fabricated structural element. MDOT uses a
minimum 75-year bridge design life and any proposed repairs to the element should be consistent with the
original design. MDOT’s Structural Fabrication Unit is responsible for implementing the Department’s quality
assurance program for structural elements required to be accepted based on “Fabrication Inspection” per
MDOT’s Materials Quality Assurance Procedures (MQAP) manual and utilizes vendor inspectors to provide
the shop inspection. The fabricator is required to notify MDOT’s quality assurance inspector (QAI) prior to
performing any approved repairs for the opportunity to perform verification inspection.
Structural precast concrete elements may contain defects from the fabrication process or are often
damaged during formwork removal or shipping and handling. The fabricator’s quality control inspector
(QCI) is required to notify the MDOT QAI of all defects/damages that occur to the elements. The
fabricator is responsible for submitting a NCR with proposed corrective action (repair plan) to bring the
element into conformance if it is to be considered for incorporation into the project. MDOT will consider
the corrective action and provide a response to the contractor in accordance with MDOT’s Structural
Fabrication Nonconformance Reporting Process. Submittal of a NCR does not guarantee approval since
the defect/damage may have resulted in structural, durability, or aesthetic concerns that is not
addressed by the repair plan. Repairs are not permitted to be performed until after the NCR has been
approved and the QAI has been notified in a timely manner when the repair will take place. See MDOT’s
Structural Fabrication Nonconformance Policy for more information on when nonconformances can be
incorporated into the project and associated price reductions. See MDOT’s Structural Fabrication
Nonconformance Reporting Process for more information on what NCR’s are and how to submit them.
Both of these documents can be found on the MDOT Structural Fabrication Unit website located inside
the Structural Precast Concrete Fabrication Inspection Portfolio document.
MDOT Standard Repair Procedures 41 -Wxerhevh#Wxvygxyvep#Tvigewx#Gsrgvixi#Vitemv#Tvsgihyvi#&4>#Emv#Lspi#
51 Wxerhevh#Wxvygxyvep#Tvigewx#Gsrgvixi#Vitemv#Tvsgihyvi#&5>#Qmrsv#Wyvjegi#Hijigx#
61 Wxerhevh#Wxvygxyvep#Tvigewx#Gsrgvixi#Vitemv#Tvsgihyvi#&6>#Qensv#Wyvjegi#Hijigx#
50
STRUCTURAL FABRICATION UNIT
V103015
STD REPAIR GUIDANCE DOCUMENT
PAGE 2 of 9
MICHIGAN DEPARTMENT OF TRANSPORTATION
71 -Wxerhevh#Wxvygxyvep#Tvigewx#Gsrgvixi#Vitemv#Tvsgihyvi#&7>#Lsx0Hmt#Kepzerm~i#
81 Wxerhevh#Wxvygxyvep#Tvigewx#Gsrgvixi#Vitemv#Tvsgihyvi#&8>#Jmfiv#Vimrjsvgih#Tsp}qiv#W}wxiq#
91 -Wxerhevh#Wxvygxyvep#Tvigewx#Gsrgvixi#Vitemv#Tvsgihyvi#&9>#Its|}#Vitemv#
;1 Wxerhevh#Wxvygxyvep#Tvigewx#Gsrgvixi#Vitemv#Tvsgihyvi#&;>#Its|}#Mrnigxmsr#
-Mrhmgexiw#wxerhevh#wxvygxyvep#tvigewx#gsrgvixi#vitemv#tvsgihyvi#xlex#hsiw#rsx#viuymvi#wyfqmxxep#sj#e#RGV#jsv#
QHSX#ettvszep?#ls{iziv/#xli#jefvmgexsv#mw#viuymvih#xs#jspps{#xliwi#tvsgihyviw#erh#rsxmj}#xli#UEM#{lir#xli#
vitemvw#{mpp#fi#tivjsvqih#ws#xli}#lezi#xli#sttsvxyrmx}#xs#{mxriww1##Jefvmgexsv#qywx#lezi#gstmiw#sj#xli#wxerhevh#
vitemvw#tperw#{mxl#xliq#ex#epp#xmqiw1#
#
QHSX�w#Wxvygxyvep#Tvigewx#Gsrgvixi#Wtigmepmwx#{mpp#gsrwypx#{mxl#xli#Wxvygxyvep#Jefvmgexmsr#Irkmriiv#erh#sxliv#
xiglrmgep#viwsyvgi#eview#{lir#vitemv#tperw#jepp#syxwmhi#xli#wgsti#sj#xli#efszi#wxexih#wxerhevh#vitemv#tvsgihyviw1##
Xli#jspps{mrk#rsr0wxerhevh#qexivmepw2tvsgihyviw#lezi#fiir#ywih#mr#pmqmxih#ettpmgexmsrw#sr#tewx#tvsnigxw#{mxl#
wyggiww>#
41 FEWJ#LF5#+jsvqivp}#Xlsvsg,#jsv#szivlieh#wxvygxyvep#vitemvw#erh#{lir#pexi|#vitemv#qm|xyviw#ger�x#fi#fmvh0
qsyxlih#mrxs#xli#jsvq{svo1#
51 FEWJ#Iqegs#+&4,#erh#Wmoe#456#Tpywx#+&5,#jsv#rsr0wxvygxyvep#ettpmgexmsrw#{lir#pexi|#vitemv#qm|xyviw#ger�x#
fi#fmvh0qsyxlih#mrxs#xli#jsvq{svo1##Rsxi#mx#mw#vevi#xs#lezi#e#rsr0wxvygxyvep#vitemv#ettpmgexmsr1##
61 Rsr0wxvygxyvep#gvego#vitemv>#Liepiv#wiepiv#mw#e#kssh#rsr0wxvygxyvep#gvego#vitemv#xs#ijjigxmzip}#mqtihi#
qsmwxyvi#mrxvywmsr#erh#glpsvmhi#tirixvexmsr1#
71 Wiepmrk#i|tswih#ekkvikexi#we{#gyxw>#Liepiv#wiepiv#mw#e#kssh#tvshygx#jsv#wiepmrk#e#we{#gyx#ihki1##[exiv#
vitippirx#xviexqirx#{syph#fi#xli#wigsrh#fiwx#stxmsr1##Fsxl#tvshygxw#{mpp#fi#hmjjmgypx#xs#ettp}#sr#e#zivxmgep#
wyvjegi1##
81 Gsexmrk#i|tswih#wxiip#vimrjsvgiqirx>#Epyqmryq#qewxmg#its|}#mw#e#kssh#gsexmrk#w}wxiq#xs#gsex#i|tswih#
wxiip#vimrjsvgiqirx1#Xli#its|}#qywx#fi#jvsq#e#qeryjegxyviv#xlex#mw#pmwxih#mr#QHSX�w#QWK#UTP#+Wigxmsr#
=48>#Gsexmrk#W}wxiqw#jsv#Wxiip#Wxvygxyviw,1##Xli#wxiip#qywx#fi#gpierih#xs#WWTG#WT#9#sv#fixxiv1##Xli#
qeryjegxyviv�w#vigsqqirhexmsrw#qywx#fi#jspps{ih1##E#qmrmqyq#sj#x{s#gsexw#sj#xli#epyqmryq#qewxmg#
its|}#+wii#qeryjegxyviv#jsv#vigsqqirhih#qmr2qe|#HJX,#wlsyph#fi#ettpmih#{mxl#xli#tvstiv#gyvi#xmqi#
fix{iir#gsexw1##Er#eggitxefpi#gsrgvixi#vitemv#qexivmep#ger#xlir#fi#tpegih#sziv#xli#gsexih#wxiip#
vimrjsvgiqirx1#
#
51
STRUCTURAL FABRICATION UNIT
V103015
STD REPAIR GUIDANCE DOCUMENT
PAGE 3 of 9
MICHIGAN DEPARTMENT OF TRANSPORTATION
Appendix A – Air Hole
#
Figure 1. Air holes greater than 3/4” in any direction and greater than 3/8” deep.
52
STRUCTURAL FABRICATION UNIT
V103015
STD REPAIR GUIDANCE DOCUMENT
PAGE 4 of 9
MICHIGAN DEPARTMENT OF TRANSPORTATION
Appendix B – Minor Surface Defect
#
Figure 2. Rubber gasket crease
53
STRUCTURAL FABRICATION UNIT
V103015
STD REPAIR GUIDANCE DOCUMENT
PAGE 5 of 9
MICHIGAN DEPARTMENT OF TRANSPORTATION
Figure 3. Moderate honeycombing along MI 1800 girder.
54
STRUCTURAL FABRICATION UNIT
V103015
STD REPAIR GUIDANCE DOCUMENT
PAGE 6 of 9
MICHIGAN DEPARTMENT OF TRANSPORTATION
Figure 4. Moderate honeycombing at end of PCI beam.
55
STRUCTURAL FABRICATION UNIT
V103015
STD REPAIR GUIDANCE DOCUMENT
PAGE 7 of 9
MICHIGAN DEPARTMENT OF TRANSPORTATION
Appendix C – Major Surface Defect
Figure 5. Broken corner at end of PCI beam.
56
STRUCTURAL FABRICATION UNIT
V103015
STD REPAIR GUIDANCE DOCUMENT
PAGE 8 of 9
MICHIGAN DEPARTMENT OF TRANSPORTATION
# #
Figure 6. Spalled bottom corner at end of box beam.
#
#
57
STRUCTURAL FABRICATION UNIT
V103015
STD REPAIR GUIDANCE DOCUMENT
PAGE 9 of 9
MICHIGAN DEPARTMENT OF TRANSPORTATION
# #
Figure 7. Spalled bottom corner at end of box beam. #
58
STRUCTURAL FABRICATION UNIT
V101117
REPAIR PROCEDURE #1
PAGE 1 of 1
MICHIGAN DEPARTMENT OF TRANSPORTATION
Standard Structural Precast Concrete Repair Procedure #1: Air Hole
Description This structural precast concrete repair procedure is for patching air holes that exceed acceptable
dimensional tolerances. The repair plan is in accordance with subsections 406 and 708 of the 2012
Michigan Department of Transportation Standard Specifications for Construction (MDOT SSC) as
applicable.
The Type R-2 mortar used for patching air holes must be selected from the following locations:
" Cement: Approved Manufacturer or Test
" White Cement: Visual inspection
" Fine aggregate (2NS or 2MS): Prequalified Aggregate Source or Test
" Air entrainment: Qualified Products List
Procedure Below is the standard repair procedure for air holes:
1. Immediately patch all air holes larger than 3/4 inch in any direction and greater than 3/8 inch deep
with Type R-2 mortar after removing forms.
2. Perform the following steps prior to patching air holes if they are not filled immediately after forms are
removed:
o Flush the area with minimum 2500 psi pressurized clean water.
o Remove excess water from patch area by blasting with minimum 90 psi oil-free compressed air to
produce a saturated surface dry condition immediately prior to application of mortar.
3. Place mortar when substrate is at least 40 degrees, and maintain a temperature of at least 40 degrees
Fahrenheit during the placement and curing period.
59
STRUCTURAL FABRICATION UNIT
V103015
REPAIR PROCEDURE #2
PAGE 1 of 2
MICHIGAN DEPARTMENT OF TRANSPORTATION
Standard Structural Precast Concrete Repair Procedure #2: Minor Surface Defect
Description This structural precast concrete repair plan is for minor surface defects defined to have a patch depth of
less than 1.5 inches. This repair plan is in accordance with the following subsections of the 2012 Michigan
Department of Transportation Standard Specifications for Construction (MDOT SCC):
" 712.03.F.2 - Hand Chipping Concrete Other Than Deck Concrete;
" 712.03.O - Mixing, Placing, Finishing, and Curing Concrete Patches;
" 712.03.R - Cold Weather Limitations for Placing SFMC or LMC Overlay Mixtures; and
" 712.03.S - Hot Weather Limitations for Placing Overlay Mixtures.
The latex bonding agent and cement used for patching mixtures must be selected from an Approved
Manufacturer in the MDOT Materials Source Guide (MSG). The aggregate must be from a MDOT
prequalified source or tested for acceptance.
Procedure Below is the standard repair procedure for minor surface defect:
1. Remove unsound or loose concrete with air hammers (15 pound class or smaller) or grinding. Saw-
cut areas requiring patching to an edge depth of at least ½ inch. Patch area must have vertical
edges (normal to the surface) and re-entrant corners rounded with a minimum 1 inch radius. Ensure
there are no voids or delaminated concrete by sounding. Clean exposed areas by sandblasting
to provide an anchor profile.
2. Remove loose material from patch area by blasting with minimum 90 psi oil-free compressed air.
Flush the area with minimum 3000 psi pressurized clean water. Remove excess water from patch
area by blasting with oil-free compressed air immediately prior to application of patching material.
3. Drill galvanized or epoxy coated anchors into the repair area spaced 2-3 inches apart and use
coated tie wire to create a floating mesh with spaces large enough for latex repair mixture to flow
through. Provide at least 1 inch concrete clear cover over the anchors and tie wire. Use extreme
care not to damage mild reinforcing steel or prestressing strand.
4. Patch the area with a F-L patching mixture in accordance to Table 703-1 (Structures Patching
Mixtures) of the 2012 MDOT Standard Specifications for Construction. Maintain a SSD (saturated
surface dry) condition prior to placing patching mixture. Vibrate forms or use a tamping rod to
consolidate the concrete patch.
60
STRUCTURAL FABRICATION UNIT
V103015
REPAIR PROCEDURE #2
PAGE 2 of 2
MICHIGAN DEPARTMENT OF TRANSPORTATION
5. Place a layer of wet burlap immediately over the finished concrete patch. Burlap must be soaked
in water for at least 12 hours prior to placing patching mixture. Place a 4-mil thick layer of
polyethylene film immediately over the burlap to protect the top surfaces from evaporation.
6. Wet cure patches using burlap and polyethylene for 48 hours and allow concrete to air cure for an
additional 48 hours.
7. Air and concrete substrate temperatures must be at least 40o F and rising, but below 85oF. The
forecast air temperature during the curing period must be 35o F or higher. Use insulating blankets if
the curing period forecasted (or actual) air temperature is below 45o F.
61
STRUCTURAL FABRICATION UNIT
V103015
REPAIR PROCEDURE #3
PAGE 1 of 2
MICHIGAN DEPARTMENT OF TRANSPORTATION
Standard Structural Precast Concrete Repair Procedure #3: Major Surface Defect
Description This structural precast concrete repair plan is for major surface defects defined to have a minimum patch
depth of 1.5 inches. This repair plan is in accordance with the following subsections of the 2012 Michigan
Department of Transportation Standard Specifications for Construction (MDOT SSC):
# 712.03.F.2 - Hand Chipping Concrete Other Than Deck Concrete;
# 712.03.O - Mixing, Placing, Finishing, and Curing Concrete Patches;
# 712.03.R - Cold Weather Limitations for Placing SFMC or LMC Overlay Mixtures; and
# 712.03.S - Hot Weather Limitations for Placing Overlay Mixtures.
The latex bonding agent and cement used for patching mixtures must be selected from an Approved
Manufacturer in the MDOT Materials Source Guide (MSG). The aggregate must be from a MDOT
prequalified source or tested for acceptance.
Procedure Below is the standard repair procedure for major surface defect:
1. Remove unsound or loose concrete with air hammers (15 pound class or smaller) or grinding. Saw-
cut areas requiring patching to an edge depth of at least ½ inch. Patch area must have vertical
edges (normal to the surface) and re-entrant corners rounded with a minimum 1 inch radius. Ensure
there are no voids or delaminated concrete by sounding. Clean exposed areas by sandblasting
to provide an anchor profile.
2. Do not damage any prestressing strand or mild steel reinforcement. If mild steel reinforcement is
exposed, remove concrete to provide ¾ to 1 inch of clearance around the steel for anchoring.
3. Remove loose material from patch area by blasting with minimum 90 psi oil-free compressed air.
Flush the area with minimum 3000 psi pressurized clean water. Remove excess water from patch
area by blasting with oil-free compressed air immediately prior to application of patching material.
4. Drill galvanized or epoxy coated anchors into the repair area spaced 2-3 inches apart and use
coated tie wire to create a floating mesh with spaces large enough for latex repair mixture to flow
through. Provide at least 3/4 inch concrete clear cover over the anchors and tie wire. Use extreme
care not to damage mild reinforcing steel or prestressing strand.
5. Repair damaged epoxy coating in accordance with subsection 706.03.E.8 of the MDOT SSC.
6. Patch the area with a C-L patching mixture in accordance to Table 703-1 (Structures Patching
Mixtures) of the 2012 MDOT Standard Specifications for Construction. Maintain a SSD (saturated
62
STRUCTURAL FABRICATION UNIT
V103015
REPAIR PROCEDURE #3
PAGE 2 of 2
MICHIGAN DEPARTMENT OF TRANSPORTATION
surface dry) condition prior to placing patching mixture. Vibrate forms or use a tamping rod to
consolidate the concrete patch.
7. Place a layer of wet burlap immediately over the finished concrete patch. Burlap must be soaked
in water for at least 12 hours prior to placing patching mixture. Place a 4-mil thick layer of
polyethylene film immediately over the burlap to protect the top surfaces from evaporation.
8. Wet cure patches using burlap and polyethylene for 48 hours and allow concrete to air cure for an
additional 48 hours.
9. Air and concrete substrate temperatures must be at least 40o F and rising, but below 85oF. The
forecast air temperature during the curing period must be 35oF or higher. Use insulating blankets if
the curing period forecasted (or actual) air temperature is below 45oF.
63
STRUCTURAL FABRICATION UNIT
V092717
REPAIR PROCEDURE #4
PAGE 1 of 1
MICHIGAN DEPARTMENT OF TRANSPORTATION
Standard Structural Precast Concrete Repair Procedure #4: Hot-Dip Galvanize
Description The following plan is for the repair of hot-dip galvanized components and is in accordance with
subsection 716.03.E of the 2012 Michigan Department of Transportation Standard Specifications for
Construction (MDOT SSC) and ASTM A780-09.
Procedure Below is the standard repair procedure for hot-dip galvanizing. The fabricator must select a zinc-rich paint
that meets ASTM A780 requirements and the following procedures:
1. Prepare the damaged galvanized area in accordance with paint manufacturer’s instructions or as
stated herein, whichever is stricter. Surface preparation must extend into the undamaged
galvanized coating to ensure a smooth reconditioned coating can be effected.
2. Surfaces to be reconditioned with paints containing zinc dust shall be clean, dry, and free of oil,
grease, preexisting paint, and corrosion by-products in accordance to SSPC-SP1 (Solvent Cleaning).
3. Clean the surface to bare metal, in accordance with SSPC-SP10 (Near-White Blast Cleaning) or
SSPC-SP11 (Power Tool Cleaning to Bare Metal). Use a grinder and wire wheel to grind burrs, fins,
tears, slivers, irregularities, or sharp edges. Sharp corners must be “broken” to ensure adequate
edge dry film thickness.
4. Use a clean cloth to remove any contaminant from the area being repaired. Oil free pressurized air
(90 psi minimum) must be used to remove any dust or any other particles.
5. If the area to be repaired includes welds, first remove all weld flux residue and weld spatter (of a
size that cannot be removed by wire brushing or blast cleaning) by mechanical means such as
chipping, grinding, or power scaling.
6. Hand coat the area according to the paint manufacturer’s instructions or as stated herein,
whichever is stricter.
7. Allow adequate cure time before recoating or placing the repaired component into service in
accordance with paint manufacturer’s product data sheet.
8. Use a magnetic, electromagnetic, or eddy-current gage to measure dry film thickness in
accordance with SSPC-PA2 (Measurement of Dry Paint Thickness with Magnetic Gages). QC must
calibrate the gage prior to each use. The repaired area must have a coating thickness of 1.5 times
the thickness or thickness equivalent specified or 5 mils, whichever is greater. Spot or area
measurements, as applicable, must be taken in accordance with the SSPC– PA 2 (Required Number
of Measurements for Conformance to a Thickness Specification). Record thickness measurements
for the job file on QC reports and provide to MDOT’s QAI.
64
STRUCTURAL FABRICATION UNIT
V103015
REPAIR PROCEDURE #5
PAGE 1 of 2
MICHIGAN DEPARTMENT OF TRANSPORTATION
Standard Structural Precast Concrete Repair Procedure #5: Fiber Reinforced Polymer System
Description The following repair plan is for elements required to be reinforced with a fiber reinforced polymer (FRP)
sheet and adhesive composite system due to surface defect, honeycombing, damage, etc. and would
be used in conjunction with another MDOT standard structural precast concrete repair procedure or
approved unique repair procedure. This FRP repair plan is in accordance with the latest Michigan
Department of Transportation Special Provision for Fiber Reinforced Polymer System for Prestressed
Concrete Beam Repair (hereafter referred as FRP SP). A MDOT approved FRP system from Table 1 of the
FRP SP must be selected.
Submit the following items for MDOT’s review and approval:
1. FRP manufacturer’s product data sheet for the following: sheet, resin, and protective top coat;
2. Concrete surface coating manufacturer’s product data sheet, federal color number, and swatch
of the color proposed for coating. The coating color must match the color of the beam unless the
beam will be concrete surface coated, which would require the coating color to match the
concrete surface coating.
3. Manufacturer’s recommended installation procedures;
4. Details of any construction device that may be attached to the structure during construction;
5. Quality control inspector (QCI) information (at a minimum the full name, FRP training, and FRP work
history) for individual responsible for inspection and fabricator acceptance of FRP sheet and
adhesive composite system; and
6. FRP manufacturer’s on-site technical representative trained in the application of FRP sheet and
adhesive composite system installation on concrete substrate. Representative must be physically
on-site during startup of the FRP installation process to assist the fabricator and answer questions
from the Department’s representative.
Procedure Below is the standard repair procedure for the FRP sheet and adhesive composite system. In general, the
manufacturer’s recommended installation procedures must be followed. In the event of a conflict, the
more strict procedures must be adhered to:
1. Verify latex repair patches have been wet cured for 48 hours and air cured for 48 hours prior to
installation of FRP sheet and adhesive composite system.
2. Grind all rough edges on latex repair patches smooth after they have completely cured.
3. Remove concrete dust from surface by blasting with minimum 90 psi oil-free compressed air.
65
STRUCTURAL FABRICATION UNIT
V103015
REPAIR PROCEDURE #5
PAGE 2 of 2
MICHIGAN DEPARTMENT OF TRANSPORTATION
4. Verify environmental conditions (dew point, humidity, concrete moisture content, and concrete
substrate temperature) are within the FRP SP prior to placing primer and FRP sheet. Fabricator’s QCI
must possess one of the following endorsements:
a. National Association of Corrosion Engineers (NACE) – National Coating Inspector Training
and certification Program Session I: Coating Inspection Training;
b. SSPC-C1 Fundamentals of Protective Coatings for Industry for Industrial Structures; or
c. National Highway Institute (NHI) – Bridge Coating Inspection Course.
5. Apply the FRP primer and FRP sheet in accordance with the FRP SP.
6. FRP sheet must extend past the patch area by at least 3 inches in all directions, but extend across
the entire bottom flange and up both sides of the web to the bottom of the top flange.
7. FRP sheet must be placed with fiber orientation perpendicular (90 degrees) to the beam’s
longitudinal axis.
8. Allow at least 24 hours for initial resin to cure prior to performing direct adhesion testing in
accordance with ASTM D7522.
9. Completely cure the FRP sheet and adhesive composite system per the manufacturer’s
recommendations before applying the protective top coat per the manufacturer’s
recommendations.
10. After curing, check entire FRP wrap for any delamination by acoustic tap inspection per the FRP SP.
11. Use the project’s Special Provision for Concrete Surface Coating, if available, to coat the FRP system
in accordance with the manufacturer’s product data sheet except as modified by subsection 716
of the MDOT SSC. If the project does not have concrete surface coating then a special provision
will be provided.
66
STRUCTURAL FABRICATION UNIT
V062917
REPAIR PROCEDURE #6
PAGE 1 of 1
MICHIGAN DEPARTMENT OF TRANSPORTATION
Standard Structural Precast Concrete Repair Procedure #6: Epoxy Repair
Description The following plan is for the repair of epoxy coated reinforcing steel and is in accordance with subsection
706.03.E.8 of the 2012 Michigan Department of Transportation Standard Specifications for Construction
(MDOT SSC) and ASTM A775.
Procedure Below is the standard repair procedure for epoxy coating. The fabricator must select a patching or repair
material selected from the MDOT Qualified Products List (QPL) and follow the following procedures:
1. Prepare the damaged areas by cleaning to remove surface contaminants in accordance withmanufacturer’s instructions or as stated herein, whichever is stricter.
2. Roughen the area requiring patching before applying patching material.
3. Remove rust by dry blast cleaning or power tool cleaning immediately before applying patchingmaterial.
4. Immediately treat bars in accordance with the manufacturer’s recommendations and beforeoxidation occurs.
5. Overlap patching material onto the original coating by 2 inches, or as recommended by themanufacturer.
6. Provide at least 8 mils of dry film thickness on the patched areas.
7. Bars with 5 percent or more damaged in a 12 inch bar length is considered to be severely damagedand will be rejected.
67
STRUCTURAL FABRICATION UNIT
V103015
REPAIR PROCEDURE #7
PAGE 1 of 1
MICHIGAN DEPARTMENT OF TRANSPORTATION
Standard Structural Precast Concrete Repair Procedure #7: Epoxy Injection
Description The following plan is for the repair of concrete cracks using epoxy injection in accordance with subsection
712.03.U of the 2012 Michigan Department of Transportation Standard Specifications for Construction
(MDOT SSC).
The epoxy resin used for injecting into the cracks must be selected from the Qualified Products List (QPL) in
the MDOT Materials Source Guide (MSG).
Procedure Below is the standard repair procedure for epoxy crack injection. The fabricator must follow the following
procedures or the manufacturer’s recommendations, whichever are more strict:
1. Remove leaching deposits from cracks by abrasive blasting or wire brushing.
2. Apply a temporary seal, with entry ports for adhesive, along the clean, dry crack without defacingthe concrete surface. Ensure the seal will contain the pumped adhesive.
3. Space ports farther apart than the estimated crack depth and close enough to allow adhesivematerial to travel between ports.
4. Flush the cracks with water by pressure washing through injection ports. Wash out concrete laitanceor contaminants in the crack. Remove free water by blowing oil-free air (90 psi minimum) throughthe crack after flushing.
5. Perform injection when the concrete and ambient air temperatures are above 50 degreesFahrenheit.
6. Begin injection at the lower entry port and continue until adhesive is visible at the port directlyabove, or next to the pumping port. Stop injection and seal the port. Transfer the injector fromboth sides of a cracked member to complete crack repair. Prevent leakage of the adhesive fromthe crack after injection is complete.
7. Cure adhesive at temperatures of at least 50 degrees Fahrenheit for the minimum cure timerecommended by the manufacturer. Remove the seal or grind flush with the concrete surface.
8. Clean areas repaired by injection of surface contamination caused by injections.
79
(This page intentionally left blank)
,
#
STRUCTURAL FABRICATION UNIT
V022818
BUY AMERICA
PAGE 1 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
Structural Fabrication Buy America Guidance Document
Description The purpose of this document is to provide the Michigan Department of Transportation’s (MDOT)
Structural Fabrication Unit with guidance to supplement MDOT’s 12SP-105A Special Provision for Source of
Steel and Iron (Buy America). The Structural Fabrication Unit is responsible for implementing the
Department’s quality assurance program for material required to be accepted based on “Fabrication
Inspection” per MDOT’s Materials Quality Assurance Procedures (MQAP) manual. It is important to note
that this document is not contractual and all project related decisions should be based on the contract.
This guidance document will be used to ensure statewide consistency in performing quality assurance
(QA) verification inspection at fabrication facilities for Buy America compliance. It provides a brief
background on FHWA’s Buy America policy, what step certification is, where more Buy America
information can be found, how foreign steel or iron could be incorporated into the project, and tables
that provide common steel and iron components used in the fabrication process of structural precast
concrete and structural steel elements. This document is broken down into the following sections:
1. Background
2. Step Certification
3. Foreign Steel or Iron
4. Documentation Requirements
5. Buy America Tables
1. Background The FHWA’s Buy America policy is based upon the statutory provisions in the Surface Transportation
Assistance Act of 1982, as implemented with a November 25, 1983 final rule. FHWA has since issued
clarifications and interpretations on the Buy America policy and standing waiver of 1983 with memo’s
issued on December 22, 1997, June 13, 2011 and December 21, 2012; however, the December 21, 2012
memo was rescinded on December 22, 2015. In general, FHWA’s Buy America policy requires a domestic
manufacturing process for all steel (including stainless steel; however, brass, bronze and copper are not
subject to Buy America) or iron manufactured products (including the application of protective coatings,
but not the coating itself) that are permanently incorporated into a Federal-aid highway construction
project.
Title 23 Section 313 and FHWA's regulations in 23 CFR 635.410 provide that the Administrator may issue a
waiver. Procedures for any waivers are in the FHWA guidance for Buy America on the FHWA website.
Waivers are very rare and typically take about 9 months to be issued, which would require them to be
submitted during the design stage. Additionally, the FHWA's regulations permit a minimal use of foreign
steel and iron in the amount of $2,500 or one-tenth of one percent (0.1%), whichever is greater, to be
used in a Federal-aid project. Note that application of Buy America is triggered by the obligation of
Federal funds. If any amount of federal funding is used in the project, then Buy America requirements
$% 2019 Interim
STRUCTURAL FABRICATION UNIT
V022818
BUY AMERICA
PAGE 2 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
apply. Map 21 requires all parts of a project to comply with Buy America if any previous parts of the
larger project used Federal funds. This includes environmental EIS, planning, design, small subparts, etc.
FHWA may issue a standing national or regional waiver if it is warranted, although it is extremely rare (only
4 ever issued). The waiver would be granted by the Secretary of Transportation if the product is not
manufactured in the United States and the public rulemaking process demonstrates that non-domestic
availability of the product would adversely impact the Federal-aid program in multiple states, specific
region, and/or nationwide.
2. Step Certification Step certification is the process under which each company (supplier, fabricator, manufacturer,
processor, etc.) of the steel and iron products certifies that their step in the manufacturing process was
domestically performed. Contractors must provide manufacturers’ step certifications to the Engineer
showing the steel and iron products are of domestic origin prior to permanent incorporation into the
Federal-aid highway project. MDOT requires step certification for all steel and iron related pay items,
materials, products, and components as specified on the Department website. The Department will
maintain a list of these pay items, materials, products, and/or components on the following website:
http://www.michigan.gov/documents/mdot/MDOT_BuyAmericaRequirements_387704_7.pdf
Raw materials are not required to meet Buy America; however, every step from melting through coating
application and anything else is subject to meet Buy America. If a steel or iron component has any step
performed by a non-domestic company then the total cost for the entire component would need to be
less than the allowable foreign limit in order to be incorporated into the project.
3. Foreign Steel or Iron It is the Contractor’s responsibility to seek approval from the Engineer to use foreign steel or iron prior to
incorporation into the project. Additionally, it is the Contractor’s responsibility to keep track of the
amount of foreign steel or iron used on the project.
For additional information on Buy America requirements, please refer to any project specific Special
Provision for Source of Steel and Iron (Buy America), MDOT Construction Manual, MDOT MQAP Manual,
and the FHWA website.
4. Documentation Requirements The Contractor is required to provide Buy America certification for the project and Buy America step
certification for all products and materials not designated as full compliant with the Buy America
requirements on the Qualified Products List (QPL), Approved Manufacturer’s, and Tested Stock Suppliers
List maintained by MDOT’s Construction Field Services Division.
Buy America certification letter or Bill of Lading must include the following language:
" Company name;
" Signature of company representative; and
" Following statement:
70 2019 Interim
STRUCTURAL FABRICATION UNIT
V022818
BUY AMERICA
PAGE 3 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
I, (company representative), certify that the material shipped/provided to the project are in full
compliance with the Federal Highway Administration (FHWA) Buy America requirements as
specified in Title 23 of the Federal Code of Regulations (CFR) Section 635.410.
Buy America step certification letter must include the following language:
" Company name;
" Signature of company representative; and
" Following statement:
I, (company representative), certify that the (cutting, bending, punching, drilling, shearing,
machining, welding, galvanizing, coating) process/es, as specified in the purchase order, for
manufacturing or fabricating the material shipped/provided to the project are in full compliance
with the Federal Highway Administration (FHWA) Buy America requirements as specified in Title 23
of the Federal Code of Regulations (CFR) Section 635.410.
Mills and manufacturing plants that produce hot-rolled shapes, hollow structural sections (HSS), plate,
ingot, slab, billet, bloom, high-strength bolts, anchor bolts, prestressing strand, bar reinforcement, and
welded wire reinforcement are not required to provide the above stated Buy America step certification
letter. Instead, language located in the material test report (MTR) stating the material was melted and
manufactured in the United States is sufficient to meet Buy America step certification requirements.
Contractors are not permitted to write Buy America step certification letters for their subcontractors since
they do not have control over the work. This was determined based on discussions between MDOT
management and FHWA.
5. Buy America Tables Below are several tables displaying common steel and iron components used in the fabrication of
structural precast concrete and structural steel elements. This information has been prepared exclusively
for MDOT’s Structural Fabrication Unit to assist with the Buy America requirements. These tables are not
complete and do not relieve the contractor of their contractual obligations to meet Buy America
requirements for MDOT projects.
71 2019 Interim
STRUCTURAL FABRICATION UNIT
V022818
BUY AMERICA
PAGE 4 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
Table 1. Steel components used in fabricating structural precast (prestressed and non-prestressed)
concrete elements.
STRUCTURAL PRECAST CONCRETE FABRICATION
Component Description Buy
America Cert
Buy America Step Cert
Comment
Prestressing Strand
High strength strand for prestressing
concrete Yes *Yes
Project BA cert from fabricator and language in MTR (e.g. melted
and manufactured in the USA)
Bar Reinforcement
Mild bar reinforcement for
strengthening concrete
Yes *Yes Project BA cert from fabricator
and language in MTR (e.g. melted and manufactured in the USA)
Welded Wire Fabric
Mild fabric reinforcement for
strengthening concrete
Yes *Yes Project BA cert from fabricator
and language in MTR (e.g. melted and manufactured in the USA)
Sole Plates
Steel plate cast over support and
bears on the elastomeric pad
Yes Yes Project BA cert from fabricator and BA step certs from each
company that performs a process
Position Dowels
Dowels used to provide translation restraint for beams
Yes Yes Project BA cert from fabricator and BA step certs from each
company that performs a process
MSE Connection
Lug
Connects wall panel to
reinforcement Yes No Project BA cert from fabricator
Laminated Elastomeric
Pad
Steel shims used to reinforce
elastomeric pads Yes Yes
Project BA cert from fabricator and BA step certs from each
company that performs a process
PCI Beam Lifting Strand
Device for moving beams
Yes No Project BA cert from fabricator
Culvert Lifting Device
Device for moving culverts
Yes No Project BA cert from fabricator
MSEW Lifting Device
Device for moving MSEW panels, posts,
and copings Yes No Project BA cert from fabricator
Sound Wall Lifting Device
Device for moving sound wall panels
and posts Yes No Project BA cert from fabricator
72 2019 Interim
STRUCTURAL FABRICATION UNIT
V022818
BUY AMERICA
PAGE 5 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
Table 1 (continued). Steel components used in fabricating structural precast (prestressed and non-
prestressed) concrete elements.
STRUCTURAL PRECAST CONCRETE FABRICATION
Component Description Buy
America Cert
Buy America Step Cert
Comment
Tie Wire Secures bar
reinforcement Yes No Project BA cert from fabricator
Bar Chair Supports bar
reinforcement Yes No Project BA cert from fabricator
Screed Supporting
Frame (pipe)
Supports screed machine
Yes No Project BA cert from fabricator
SIP Deck Clip Support location for
attaching SIP decking
Yes No Project BA cert from fabricator
Half Hanger Anchor
Supports false work Yes No Project BA cert from fabricator
False Work Insert
Supports false work Yes No Project BA cert from fabricator
Safety Line Embed
Provides tie off Yes No Project BA cert from fabricator
Spun Pole Structural Steel
Mounts cameras, etc. to pole
Yes No Project BA cert from fabricator
Spun Pole Hardware
Mounts cameras, etc. to pole
Yes No Project BA cert from fabricator
Concrete Insert
Attach threaded bar reinforcement
or bolt Yes No Project BA cert from fabricator
* Denotes alternate Buy America step certification.
73 2019 Interim
STRUCTURAL FABRICATION UNIT
V022818
BUY AMERICA
PAGE 6 of 6
MICHIGAN DEPARTMENT OF TRANSPORTATION
Table 2. Steel components used in fabricating structural steel elements.
STRUCTURAL STEEL FABRICATION
Component Description Buy
America Cert
Buy America Step Cert
Comment
Hot Rolled Shape and
Plate
Structural steel used for fabrication of
bridge or highway elements
Yes Yes Project BA cert from fabricator and BA step certs from each company
that performs a process
HSS
Structural steel used for fabrication of
bridge or highway elements
Yes Yes Project BA cert from fabricator and BA step certs from each company
that performs a process
High Strength Bolts
Bolts for structural steel connections
Yes *Yes Project BA cert from fabricator and language in MTR (e.g. melted and
manufactured in the USA)
Anchor Bolts Bolts for anchoring structural elements
Yes *Yes Project BA cert from fabricator and language in MTR (e.g. melted and
manufactured in the USA)
Laminated Elastomeric
Pad
Steel shims used to reinforce
elastomeric pads Yes Yes
Project BA cert from fabricator and BA step certs from each company
that performs a process
Welding Rod Weld metal used in
SMAW process Yes No Project BA cert from fabricator
Welding Wire Weld metal used in
GMAW, SAW, or FCAW processes
Yes No Project BA cert from fabricator
* Denotes alternate Buy America step certification.
73a 2019 Interim
(This page intentionally left blank)
(This page intentionally left blank)
MICHIGAN DEPARTMENT OF TRANSPORTATION
STRUCTURAL FABRICATION UNIT
V020118
METALS LABORATORY SAMPLING GUIDANCE
PAGE 1 of 6
Metals Laboratory Sampling Guide
DescriptionThe following procedures provide step by step instruction on sampling all materials required to be tested
by the Michigan Department of Transportation Metals Laboratory.
Sampling Instructions
1. Samples must be selected randomly without bias, must be representative of the material
sampled, and can only represent the population of material available at the time of sampling
(e.g. makeup material must be resampled since the original sample cannot statistically
represent material not available at the time of sampling). Specific sample size and frequency
can be found in the Materials Acceptance Requirements table located in the MDOT Materials
Source Guide.
2. All samples must be securely tagged with a numbered zip tie. Zip ties are provided by MDOT
and are uniquely numbered for sample identification purposes. High strength bolt samples
must be placed in plastic bags and closed with zip ties. All other samples must have zip ties
placed directly on the sample.
3. Population of material sampled must be tagged or marked in accordance with subsection
1.08 of the MDOT Materials Quality Assurance Procedures (MQAP) Manual.
4. Sample Identification (Form 1923) must be electronically prepared and filled out in detail for
each sample, placing the zip tie number in the remarks section. All available information for
proper identification of the sample must be provided, including the heat number, lot number,
tag number, batch number, serial number, and any other unique identification marks.
5. All material documentation for the sample must be electronically combined with Form 1923
as the first page into one Adobe portable document format (PDF) file (naming convention in
#6 below) and submitted to the testing lab via email to [email protected]. If
the MDOT Standard Specifications for Construction do not apply to the sample, applicable
plan sheets, special provisions or shop drawings must be included in the PDF submittal. The
email must have the zip tie number in the subject line. The Contractor is responsible for
providing all material certification and test data reports to the MDOT inspector in PDF
format.
6. Materials Submittal File Naming Conventions:
" Acceptance Sample: Control Section_Job Number_Material_Size_Date
Example: 63172 123143 Anchor Bolt 2in 07-09-2018
" Tested Stock Sample: TS_Material_Size_Date
Example: TS Extruded 12in 07-09-2018
" Certification Verification Sample: CV_CV Number_Material_Size_Date
Example: CV 2015-31 Rebar #5 07-09-2018
" A glossary of standard material names is included on page 3 of this document.
" A Lab Number will be assigned by the Metals Lab and incorporated into file name. Example: 18M123 63172 123143 Anchor Bolt 2in 07-09-18
2019 Interim 77
MICHIGAN DEPARTMENT OF TRANSPORTATION
STRUCTURAL FABRICATION UNIT
V020118
METALS LABORATORY SAMPLING GUIDANCE
PAGE 2 of 6
7. Form 1923 must be securely attached to the sample using a method which would ensure the
form remains with the sample and is readable when it arrives at the testing lab.
8. The method of transportation of the samples to the testing lab is at the discretion of the
Contractor. The Contractor is responsible for all associated shipping costs and must determine
shipment method in a manner deemed most appropriate. Non-MDOT employees dropping
off samples must check in with security at the loading dock gate or south entrance of the C&T
building prior to dropping samples off to the Metals Laboratory (room 122).
9. All samples must be consigned to:
MDOT Metals Lab
C/o MDOT – Operations Field Services
C&T Building – Mail Code E-020
8885 Ricks Road
P.O. Box 30049
Lansing, MI 48909
10. Test results can typically be expected within 2 weeks after the sample arrives in the testing lab.
Inquiries regarding test results may be directed to [email protected].
11. Metals Lab will place test reports into the ProjectWise MDOT In Box folder at the location
shown below. The Engineer will then place the report in the appropriate project folder.
$ Region
o TSC
" Project Specific JN
" Construction
o MDOT In Box
2019 Interim 78
MICHIGAN DEPARTMENT OF TRANSPORTATION
STRUCTURAL FABRICATION UNIT
V020118
METALS LABORATORY SAMPLING GUIDANCE
PAGE 3 of 6
Glossary of Materials Tested by the MDOT Metals Laboratory
Spec Reference Material Name *File Name
712.03.L Mechanical Splicing Splice
713.02.A Temporary Support Hanger Rod Hanger Rod
905.03 Rebar Rebar
905.06 Welded Wire Fabric Welded Wire
905.07 Prestressing Strand Prestressing Strand
906.07 High Strength Bolts HS Bolt
907.05 High Tensile Wire Tensile Wire
908.09.A Bridge Rail Post Rail Post
908.09.A Bridge Rail Plate Rail Plate
908.09.B Bridge Tube Railing Bridge Tube
908.09.C Railing Anchor Studs Anchor Stud
908.11.A Guardrail Beam Guardrail
908.12 Guardrail Post Guardrail Post
908.14 Anchor Base Plate Base Plate
908.14.B Sign Support and Light Standard Anchor Bolts Anchor Bolt
908.14.C Traffic Signal Strain Poles Strain Poles
908.14.D Anchor Bolts for Other Purposes Anchor Other
909.05.A.1 Corrugated Steel Pipe Corrugated
914.07 Dowel Bars Dowel
918.11.A Guy Wire Guy Wire
919.02.A Extruded Aluminum Sign Planks Extruded Aluminum
919.02.A.3 Aluminum Sheet Aluminum Sheet
919.07.A Cantilever Pipe Wall Tubing
* This is to be used as the naming convention to save the file.
2019 Interim 79
MICHIGAN DEPARTMENT OF TRANSPORTATION
STRUCTURAL FABRICATION UNIT
V020118
METALS LABORATORY SAMPLING GUIDANCE
PAGE 4 of 6
SampleManager login instructions (you must have a login name and password):
1. Open up Sample ID and certification paperwork.
2. In SampleManager, click on “MDOT/Sample Submission” and then pick sample type.
3. Click on “Contract” button to pull up list of job numbers to pick one.
4. Click on “Metals” radio button.
5. Click on pulldown labeled “Material” to pick type of material.
6. Click on “Spec Level” in order to pick size of sample.
7. If remarks are needed, enter them in the “Remarks” box.
8. If needed, under “Send Results To” you can pick a person and reason for sending results.
9. Click “OK” to go to the next page for sample details.
10. Click on “Date Sampled” to pick the dates sampled. You can type it in or pick from the calendar.
11. Pick the “Supplier” from the dropdown list.
12. Pick a location from the “Sampled From” list.
13. Put in a number for “Quantity Represented”, this usually comes from the Materials Source List.
14. If needed, pick “Quantity Units” from the list.
15. Pick the “Sampled By” person from the dropdown list.
16. Pick the “Submitted By” person from the dropdown list.
17. Fill in the zip tie tag number or deer tag number.
18. If applicable, pick the “Manufacturer” of the bolt, nut and washer.
19. Also fill out the lot and heat numbers of the bolt nut and washer. If one component is not present,
pick “Not Supplied” as the manufacturer name from the dropdown list. Use the certifications to
find lot and heat numbers.
20. If applicable, also attempt to identify the products markings and enter these. Common
manufacturer’s markings are listed following this page.
Note: You can view logged samples by expanding the “Metals Lab” icon at the left of SampleManager.
From there you will see different folders showing the state of testing for the samples. Also, if a company or
employee needs to be added to SampleManager or you have login questions, please email:
You can find SampleManager training videos on the MDOT YouTube page or they are available by request.
2019 Interim 80
MICHIGAN DEPARTMENT OF TRANSPORTATION
STRUCTURAL FABRICATION UNIT
V020118
METALS LABORATORY SAMPLING GUIDANCE
PAGE 5 of 6
Metals Product Markings
Product, spec book section and ASTM
Required markings Commonly seen markings (and manufacturer)
Temporary Support Hanger Rod
712.02A, ASTM A193
15.1 See Specification A962/A962M. Thegrade symbol shall be as shown in Table 4.From Table 4: B7
Rebar
905.03, A706, A615
16.2 Each manufacturer shall identify thesymbols of his marking system. For Grade60 [420] bars, the marking shall be either thenumber 60 [4] or a single continuouslongitudinal line through at least five spacesoffset from the center of the bar. For Grade80 [550] bars, the marking shall be either thenumber 80 [6] or three continuouslongitudinal lines through at least fivespaces.
See rebar markings list below (Appendix A).
*If rebar is coated, then coating company is the manufacturer (ABC Coating Co.)
High Strength Bolts
906.07, ASTM F3125 grade A325
From Table 1: A325 5.1 At a minimum, all bolts shall be markedas required in Table 1. Marking shall be onthe bolt head and may be raised or depressedat the manufacturer’s option. The markingshall be visible after coating.5.2 Grade and Type marking, and themanufacturer’s mark shall be in separate anddistinct locations on the head. Othermarkings, if used, such as private labeldistributor’s mark shall also be separate anddistinct.
nA325 (Nucor)
SLA325 (St. Louis Screw & Bolt)
SLA325USA (St. Louis Screw & Bolt)
GA325 (Gaffney Bolt Co.)
Nuts
906.07, 908.14, ASTM A563 gr. DH or ASTM A194 gr. 2H
14.5 Nuts made to the requirements of GradeDH shall be marked with the grade symbol,DH (or 2H) (Note 4) on one face.14.7 In addition, nuts shall be marked with asymbol to identify the manufacturer orprivate label distributor, as appropriate.
DHU (Unytite)Dhn (Nucor)2HU (Unytite)DHn (Nucor)TDC2H (Dyson) 2HDHD/N (Dyson)DMCDH (Dyson) FSADH/2H (Foundation Systems)
Washers
906.07, 908.14 ASTM F436
15.1 Washers shall be marked with a symbol,or other distinguishing marks, to identify themanufacturer or private label distributor, asappropriate.
TSIF436 (Technical Stamping) PF436 (Prestige Stamping) Ws (Wrought Washer)
2019 Interim 81
MICHIGAN DEPARTMENT OF TRANSPORTATION
STRUCTURAL FABRICATION UNIT
V020118
METALS LABORATORY SAMPLING GUIDANCE
PAGE 6 of 6
Product, spec book section and ASTM
Required markings Commonly seen markings (and manufacturer)
Anchor Bolts
908.14 ASTM F1554, grade 55 and 105
19.1 Unless otherwise specified (see Note 4),the end of each anchor bolt intended toproject from the concrete shall be colorcoded to identify the grade as follows:Grade 36 Blue, grade 55 Yellow, grade105 Red.S2. (not required by spec butinformational)S2.1 The end of the anchor bolt intended toproject from the concrete shall be steel diestamped with the manufacturer’sidentification.
AVA 55 (AA Anchor Bolt) ASI 55 (Alton Steel) 27 (“XX”) (Gerdau Ameristeel) S41 (“XXX”) (Cardinal Fabricating) FSA105 (Foundation Systems)
Bridge Tube Railing
908.09B, ASTM A500 grade B
908.09B The manufacturer of the structuralshape must identify the product as follows: 1. Place identification before galvanizing; 2. Include heat number or other codetraceable to the heat number; 3. Include manufacturer’s uniqueidentification code; 4. Place identification on only one sectionface; 5. Repeat identification a no more than 4-foot intervals; 6. Do not extend identification into thecurved surface at corners of section; and 7. Do not place identification on side facingtraffic or side opposite traffic.
BMT U65 (Bull Moose Tubing)
Railing Anchor Studs
908.09C, ASTM A449
16.1 Manufacturers Identification—All hexcap screws and bolts and one end of studs 3"8
in. and larger, and whenever feasible studssmaller than 3"8 in., shall be marked by themanufacturer with a unique identifier toidentify the manufacturer or private labeldistributor, as appropriate.16.2.1 Type 1 hex cap screws and bolts andone end of Type 1 studs 3"8 in. and larger, andwhenever feasible studs smaller than 3"8 in.,shall be marked “A449.”
BFA449 (Birmingham Fastener)
SLA449 (St. Louis Screw & Bolt)
JHBA449 (J.H. Botts)
Guardrail Beam
908.11A, AASHTO M180
11.1 Each beam element shall be identifiedby the following: Name or brand ofmanufacturer, identification symbols or codefor heat, number and coating lot, AASHTOspecification number, and class and type.
2019 Interim 82
CXRWXVP] 9T_Pac\T]c EU JaP]b_^acPcX^]
,3-. $+0*,.%
F3@C?7 <67AG<8<53G<BA
IT]S bP\_[T c^ C9EJ 8^]bcadRcX^] <XT[S ITaeXRTb 2220 HXRZb HS)' BP]bX]V' CXRWXVP] /23+3
F77 <AFGEH5G<BAF 47?BJ
8EDJHEB I;8J?ED
@E7 DKC7;H*FE DKC7;H 96J; I6CFB;9
B67 DKC7;H 96J; H;8;?L;9
B674 6VVaTVPcT 6M? 8^]RaTcT >C6 CTcP[b I^X[b* =T^cTgcX[Tb
D6C; E< C6J;H?6B
IEKH8; * IKFFB?;H * F?J D6C; 699H;II * F?J DKC7;H
C6DK<68JKH;H * FHE9K8;H 699H;II
I6CFB;9 <HEC
GK6DJ?JN E< C6J;H?6B H;FH;I;DJ;9 7N I6CFB;
8EDI?=D;9 JE 699H;II
I6CFB;9 7N F>ED;*;C6?B J?JB;
IK7C?JJ;9 7N F>ED;*;C6?B J?JB;
?DJ;D9;9 KI;
IF;8?<?86J?ED I;D9;HjI I6CFB; ?)9)
JNF; E< I6CFB; 6RRT_cP]RT JTbcTS Ic^RZ 8TacXUXRPcX^] LTaXUXRPcX^] " OOOOOO DTf I^daRT ?]U^a\PcX^] G)6)
H;C6HAI
I;D9 H;IKBJI JE4
<AFGEH5G<BAF
ABG72 GST\ <6 T\ ]SP \YVP ML\T\ QY[ TOPX]TQTNL]TYX LXO OT\][TM^]TYX YQ ]SP [PZY[]' C?73F7 47 355HE3G7
5BAGEB? F75G<BA =B4 AB' i 6b VXeT] ^a FKH8>6I; EH9;H DE) i ?U P__[XRPQ[T A3@7 B8 @3G7E<3? i 6b bW^f] X] IcP]SPaS I_TRXUXRPcX^]b i X]R[dST SX\T]bX^]b U^a Q^[cb' bRWTSd[T " U^a R^]SdXc' RT\T]c ch_T' TcR) FBHE57 i 8^]caPRc^a' bd__[XTa' _a^SdRTa' _Xc ] \T' ^a [^RPcX^] U^a ]PcdaP[[h ^RRdaaX]V \PcTaXP[b 366E7FF i 6SSaTbb ^U b^daRT $RXch # bcPcT ^a R^d]ch% F3@C?76 8EB@ i ?ST]cXUXPQ[T [^c ^a QPcRW ]d\QTa' P]S*^a b_TRXUXR [^RPcX^]' _a^YTRc bXcT' b^daRT' TcR) DH3AG<GK E7CE7F7AG76 i Dd\QTa ^U _XTRTb' UTTc' b`dPaT UTTc' _^d]Sb' VP[[^]b' TcR) 5BAF<9A76 GB i ?U bP\_[TS Pc b^daRT ^cWTa cWP] _a^YTRc' bcPcT c^ fW^\ P]S fWTaT cWT \PcTaXP[ Xb c^ QT bWX__TS F3@C?76 4K i DP\T P]S JXc[T XU SXUUTaT]c Ua^\ bdQ\XccTa <AG7A676 HF7 i IcPcT \PcTaXP[jb dbT X] VT]TaP[ cTa\b $T)V)' II(,W' 8HI(-C' 8II(,W' TcR) U^a Q^[cb5 VT^bh]cWTcXRb U^a bT[TRc QPRZUX[[' T\QP]Z\T]c' .Uc) VaP]d[Pa Q[P]ZTc' TcR)% FC75<8<53G<BA i 6]RW^a 7^[c' 6IJC <,00/' VaPST 00' -+,- IcS) I_TR) 3+2),/7
6[d\X]d\' 6IJC 7--,' -+,- IcS) I_TR) 3,3)+-6 F7A67EF F3@C?7 <6 i B^c' WTPc' a^[[' TcR) ]d\QTa5 bP\_[T SX\T]bX^]b5 P]S P]h ^cWTa STcPX[b b_TRXUXR c^ cWT bP\T $]^c
bT]STajb ]P\T% E7@3E>F i IcPcT b_TRXP[ cTbcb c^ QT ad]' XU bP\_[T Xb adbW ^a aTbP\_[T' P]S XU aTbd[cb PaT c^ QT _W^]TS ^a T\PX[TS' bcPcT c^
fW^\ $_W^]T ]d\QTa ^a T\PX[%
<X[T .+-
Clear Form83
CXRWXVP] 9T_Pac\T]c EU JaP]b_^acPcX^]
,3-. $+0*,.%
F3@C?7 <67AG<8<53G<BA
IT]S bP\_[T c^ C9EJ 8^]bcadRcX^] <XT[S ITaeXRTb 2220 HXRZb HS)' BP]bX]V' CXRWXVP] /23+3
F77 <AFGEH5G<BAF 47?BJ
8EDJHEB I;8J?ED
@E7 DKC7;H*FE DKC7;H 96J; I6CFB;9
B67 DKC7;H 96J; H;8;?L;9
B674 6VVaTVPcT 6M? 8^]RaTcT >C6 CTcP[b I^X[b* =T^cTgcX[Tb
D6C; E< C6J;H?6B
IEKH8; * IKFFB?;H * F?J D6C; 699H;II * F?J DKC7;H
C6DK<68JKH;H * FHE9K8;H 699H;II
I6CFB;9 <HEC
GK6DJ?JN E< C6J;H?6B H;FH;I;DJ;9 7N I6CFB;
8EDI?=D;9 JE 699H;II
I6CFB;9 7N F>ED;*;C6?B J?JB;
IK7C?JJ;9 7N F>ED;*;C6?B J?JB;
?DJ;D9;9 KI;
IF;8?<?86J?ED I;D9;HjI I6CFB; ?)9)
JNF; E< I6CFB; 6RRT_cP]RT JTbcTS Ic^RZ 8TacXUXRPcX^] LTaXUXRPcX^] " OOOOOO DTf I^daRT ?]U^a\PcX^] G)6)
H;C6HAI
I;D9 H;IKBJI JE4
<AFGEH5G<BAF
ABG72 GST\ <6 T\ ]SP \YVP ML\T\ QY[ TOPX]TQTNL]TYX LXO OT\][TM^]TYX YQ ]SP [PZY[]' C?73F7 47 355HE3G7
5BAGEB? F75G<BA =B4 AB' i 6b VXeT] ^a FKH8>6I; EH9;H DE) i ?U P__[XRPQ[T A3@7 B8 @3G7E<3? i 6b bW^f] X] IcP]SPaS I_TRXUXRPcX^]b i X]R[dST SX\T]bX^]b U^a Q^[cb' bRWTSd[T " U^a R^]SdXc' RT\T]c ch_T' TcR) FBHE57 i 8^]caPRc^a' bd__[XTa' _a^SdRTa' _Xc ] \T' ^a [^RPcX^] U^a ]PcdaP[[h ^RRdaaX]V \PcTaXP[b 366E7FF i 6SSaTbb ^U b^daRT $RXch # bcPcT ^a R^d]ch% F3@C?76 8EB@ i ?ST]cXUXPQ[T [^c ^a QPcRW ]d\QTa' P]S*^a b_TRXUXR [^RPcX^]' _a^YTRc bXcT' b^daRT' TcR) DH3AG<GK E7CE7F7AG76 i Dd\QTa ^U _XTRTb' UTTc' b`dPaT UTTc' _^d]Sb' VP[[^]b' TcR) 5BAF<9A76 GB i ?U bP\_[TS Pc b^daRT ^cWTa cWP] _a^YTRc' bcPcT c^ fW^\ P]S fWTaT cWT \PcTaXP[ Xb c^ QT bWX__TS F3@C?76 4K i DP\T P]S JXc[T XU SXUUTaT]c Ua^\ bdQ\XccTa <AG7A676 HF7 i IcPcT \PcTaXP[jb dbT X] VT]TaP[ cTa\b $T)V)' II(,W' 8HI(-C' 8II(,W' TcR) U^a Q^[cb5 VT^bh]cWTcXRb U^a bT[TRc QPRZUX[[' T\QP]Z\T]c' .Uc) VaP]d[Pa Q[P]ZTc' TcR)% FC75<8<53G<BA i 6]RW^a 7^[c' 6IJC <,00/' VaPST 00' -+,- IcS) I_TR) 3+2),/7
6[d\X]d\' 6IJC 7--,' -+,- IcS) I_TR) 3,3)+-6 F7A67EF F3@C?7 <6 i B^c' WTPc' a^[[' TcR) ]d\QTa5 bP\_[T SX\T]bX^]b5 P]S P]h ^cWTa STcPX[b b_TRXUXR c^ cWT bP\T $]^c
bT]STajb ]P\T% E7@3E>F i IcPcT b_TRXP[ cTbcb c^ QT ad]' XU bP\_[T Xb adbW ^a aTbP\_[T' P]S XU aTbd[cb PaT c^ QT _W^]TS ^a T\PX[TS' bcPcT c^
fW^\ $_W^]T ]d\QTa ^a T\PX[%
12345
123456 Oct 18, 2017
17A
Edward C. Levy Co. Aggregates/Ray Road 275 Ray Rd. Oxford, MI. 48371, 63-115
Structural Precast Concrete Fabrication Plant
Structural Precast Concrete Fabrication Plant
1000tons
person qualified to pull sample
person dropping off sample to lab
Coarse Aggregate used in fabrication of prestressed concrete beams
MTM 109, MTM 108, *MTM 110
natural aggregate must meet the physical properties of 6AA
Clear Form
%)$'(&%
84
.
#
STRUCTURAL FABRICATION UNIT
V110515
E-CONSTRUCTION PROCESS
PAGE 1 of 2
MICHIGAN DEPARTMENT OF TRANSPORTATION
Structural Fabrication E-Construction Process
Description The purpose of this document is to provide the Michigan Department of Transportation’s Structural
Fabrication Unit with a process for implementing e-construction for structural fabrication inspection
record retention. E-construction requires all fabrication inspection records to be provided by the
contractor to MDOT in Adobe portable document format (PDF) files and for MDOT to store the records in
ProjectWise.
1. Receiving Fabricator DocumentsThe fabricator must provide MDOT with electronic files in Adobe PDF. Documents are provided to
MDOT’s quality assurance inspector (QAI) in a timely manner (within 24 hours after the date
covered by the report for structural concrete) for their review prior to stamping structural elements
approved for use.
2. Creating Quality Assurance DocumentsThe QAI must convert all QA documents into PDF files. If fillable forms are used then the files must
be “flattened” to embed all form fields, comments, and any other type of annotation into the
page content prior to combining the PDF files to prevent the fields in similar forms from merging.
The stamped Bill of Lading must be scanned by the QAI for inclusion in the final documentation
package. The paper copy can be discarded after scanning.
3. Assembling and Bookmarking Fabrication Inspection FilesThe QAI combines, arranges, and bookmarks all project QA and QC documents in one PDF
fabrication inspection file using Adobe Acrobat. See MDOT document titled Structural Fabrication
Bookmarking Template for instructions on bookmarking.
4. Sending Fabrication Inspection File to MDOTQAI sends the fabrication inspection file to the MDOT Structural Fabrication Unit using a file transfer
protocol (FTP) program. The MDOT Structural Fabrication Unit randomly audits fabrication
inspection files and follows up with QAI to address any deficiencies.
5. Placing Fabrication Inspection Files into ProjectWiseThe MDOT Structural Fabrication Unit places the fabrication inspection file into ProjectWise at the
following location (in red) and assigns project attributes to the file:
$ Xxxxx Region
o Xxxxx TSC or Region Projects
" JN XXXXXX
" Construction
o Field Services
" Structural Fabrication
85
STRUCTURAL FABRICATION UNIT
V110515
E-CONSTRUCTION PROCESS
PAGE 2 of 2
MICHIGAN DEPARTMENT OF TRANSPORTATION
6. MDOT Fabrication Inspection MemorandumThe MDOT Structural Fabrication Unit works with the MDOT Structure Technical Section
Administrative Assistant to prepare the memorandum (memo) for the MDOT Structural Fabrication
Engineer’s digital signature. The assistant places a copy of the signed memo into ProjectWise at
the following location (in red below) and assigns project attributes to the files for the project
office’s records:
$ Xxxxx Region
o Xxxxx TSC or Region Projects
" JN XXXXXX
" Construction
o Field Services
" Structural Fabrication
A copy of the signed memo is also placed into the Structural Fabrication Unit’s ProjectWise
storage folder for historical record.
7. Notification of Fabrication Inspection CompletionThe MDOT Structure Technical Section Administrative Assistant emails the ProjectWise link to the
structural fabrication folder (in red below) to the individuals listed on the fabrication inspection
memo:
$ Xxxxx Region
o Xxxxx TSC or Region Projects
" JN XXXXXX
" Construction
o Field Services
" Structural Fabrication
86
(This page intentionally left blank)
(This page intentionally left blank)
STRUCTURAL FABRICATION UNIT
V&&%,&+
BOOKMARKING TEMPLATE
PAGE 1 of 1
MICHIGAN DEPARTMENT OF TRANSPORTATION
Structural Fabrication Bookmarking Template
Description Use this table of contents template for bookmarking final e-construction project documentation files. This
document is both the instructions for assembling a fabrication inspection file and the template for
bookmarking the file. It contains the bookmarks for structural concrete (prestressed and non-prestressed)
and structural steel so the bookmarks not needed must be removed.
Inspection File Assembly Instructions
1. Assemble the inspection file by inserting QC and QA files in PDF format into this document.
2. Using this document as the first page in the inspection file, arrange the files using the
bookmarks shown in this document.
3. Click on the Bookmarks Tab to display the default bookmarks. Scroll through your document
and locate the page (or first page of a section with multiple pages) that corresponds to the
bookmark. Highlight the corresponding bookmark in the list, single right click, and select Set
Destination. Repeat for each applicable bookmark until every section of the inspection file is
bookmarked.
4. Delete any bookmarks that are not needed for your particular project.
5. Delete this document after the file is complete as it is no longer needed in the file.
6. Once document is complete, electronically sign the Inspector’s Project Folder Checklist.
File Naming Convention: “SN-CS-JN Element Inspected Date”
" SN: Structure Number
" CS: MDOT Control Section
" JN: MDOT Job Number
" Element Inspected: Bearing-type, high mast tower, modular expansion joint, sign structure-
type, structural steel-type, culvert-type, prestressed beam-type, precast bridge element-
type, sound wall, spun concrete pole, etc.
" Date: Date file is completed
Examples of this naming convention are shown below:
" B03-82117-112703 Structural Steel-Pin & Hanger 093013
" W01-73022-156776 Sound Wall 111716
" S17-09031-121776 Bearing-Disc 021514
" C07-11015-126765 Culvert-Three Sided 070416
87
(This page intentionally left blank)
(This page intentionally left blank)
(This page intentionally left blank)
JA;C KFQ<=J ?GN=JFGJ
STATE OF MICHIGAN
67C3EG@7AG B8 GE3AFCBEG3G<BALANSING
CAJC L) KL=M<D= <AJ=;LGJ
9MJ=8M G> >A=D< K=JNA;=K m ;GFKLJM;LAGF $ L=;@FGDG?Q 9MAD<AF? m H)G) 9GP .++/4 m D8FKAF?' EA;@A?8F /34,2 iii)_[UZ[YS`)Yah m %0,2&(.--(,+32
BS`gSdk ,.' -+,/
La OZa_ Af ESk ;a`UWd`5
9SeWV a` fZW dWeg^fe aX S dWUW`f \a[`f dWeWSdUZ bda\WUf TWfiWW` fZW E[UZ[YS` <WbSdf_W`f aX
LdS`ebadfSf[a` S`V E[UZ[YS` KfSfW M`[hWde[fk f[f^WV' Effects of Debonded Strands on the
Production and Performance of Prestressed Concrete Beams Tk J[YaTWdfa 9gdYWgW`a S`V Q[
Kg` %Zffb5**_[UZ[YS`)Yah*VaUg_W`fe*_Vaf*E<GLRJWeWSdUZRJWbadfRJ;(,0/1R.0//,3R2)bVX&
S`V fZW dWeg^fe aX S egUUWeeXg^ b[^af bda\WUf ^Sef eg__Wd' E<GL ZSe UZS`YWV fZW efdS`V
VWTa`V[`Y _SfWd[S^ ebWU[X[USf[a`e Xad geW a` E<GL bda\WUfe) KfdS`V VWTa`V[`Y [e dWcg[dWV
iZW` ebWU[X[WV a` fZW Ua`fdSUf b^S`e ad [` fZW WhW`f fZW KfdgUfgdS^ >STd[USf[a` =`Y[`WWd S^^aie
_g^f[b^W efdS`V bSffWd`e fa TW geWV a` fZW eS_W TWV) =XXWUf[hW ESdUZ ,' -+,/' S^^ E<GL
bda\WUfe i[^^ Ua`fS[` fZW SffSUZWV KbWU[S^ Hdah[e[a` Xad KfdS`V <WTa`V[`Y n ,-KH2+3%</2+&'
iZ[UZ dWcg[dWe d[Y[V _a`a^[fZ[U ahWde[lWV VWTa`V[`Y _SfWd[S^) >^Wj[T^W ba^k_Wd b^Sef[U eb^[f(
eZWSfZ[`Y `TVV XY] TW bWd_[ffWV a` E<GL bda\WUfe)
J[Y[V _a`a^[fZ[U ahWde[lWV VWTa`V[`Y _SfWd[S^ _S`gXSUfgdWde fZSf ZShW bdWh[age^k _Wf E<GLqe
ebWU[X[USf[a`e SdW ^[efWV TW^ai Xad [`Xad_Sf[a`S^ bgdbaeWe a`^k5
" @a_W S`V ?SdVW` A`Vgefd[We' A`U) 02++ F) O) .-`V 8hW`gW E[S_[' >D ..,/- HZa`W5 %.+0& 1./(+13,
" LZW Kb[dSfWj ;a_bS`k 1... ;aYeiW^^ JaSV Ja_g^ge' EA /3,2/ HZa`W5 %2./& 2--(+,++
88
To Whom It May Concern Page 2 of 2 January 14, 2014
H^WSeW Ua`fSUf _W Tk bZa`W Sf %0,2& .--(02+4 ad W_S[^ Sf X[^UW]_7_[UZ[YS`)Yah i[fZ
cgWef[a`e ad Ua`UWd`e) LZS`] kag Xad kagd bSf[W`UW S`V g`VWdefS`V[`Y Vgd[`Y fZ[e fdS`e[f[a`)
K[`UWdW^k'
ESffZWi B) >[^UW]' H)=) KfdgUfgdS^ >STd[USf[a` =`Y[`WWd 9d[VYW >[W^V KWdh[UWe n KfdgUfgdW LWUZ`[US^ KWUf[a`
EB>5\f
=`U^aegdW
;U5 E) ;Zk`aiWfZ B) ?gff[`Y H) BS`eea` B) OW[^Wd <) HSbS`W] KfdgUfgdS^ HdWUSef ;a`UdWfW >STd[USfade EAL8
5;LLB?O!4%!3CE=?D1CACL;EEP!KCAG?>!<P!5;LLB?O!4%!3CE=?D!
16.!=G/5;LLB?O!4%!3CE=?D#!H/5C=BCA;G!1?I;JLF?GL!
H@!8J;GKIHJL;LCHG#!HM/7LJM=LMJ;E!3;<JC=;LCHG!
2GACG??J#!?F;CE/@CE=?DF0FC=BCA;G%AHN#!=/97!
1;L?.!(&'*%&'%'+!&-.*-.*,!$&+"&&"
89
,-KH2+3%</2+&
EA;@A?8F <=H8JLE=FL G> LJ8FKHGJL8LAGF
KH=;A8D HJGNAKAGF >GJ
FGE3A6 674BA6<A9
9>K5EB> , aX , 8HHJ5;=J5HGB5+-(--(,.
L' 6P\N[TZ]TYX' LZ[e iad] Ua`e[efe aX Xgd`[eZ[`Y S`V [`efS^^[`Y d[Y[V ba^k_Wd VWTa`V[`Y _SfWd[S^ Sdag`V bdWefdWee[`Y efdS`Ve [` bdWUSef Ua`UdWfW W^W_W`fe Sf ^aUSf[a`e S`V ^ W`YfZe [`V[USfWV a` fZW b^S`e) >^Wj[T^W ba^k_Wd b^Sef[U eb^[f(eZWSfZ[`Y [e `af bWd_[ffWV)
M' @L]P[TLV\' Hdah[VW d[Y[V _a`a^[fZ[U ba^k_Wd VWTa`V[`Y _SfWd[S^ i[fZ S` agfe[VW V[S_WfWd aX +)2-0 [`UZWe S`V S iS^^ fZ[U]`Wee aX +)+/ [`UZWe) LZW efdS`V VWTa`V[`Y _SfWd[S^ _gef TW U^aeWV fgT[`Y %^a`Y[fgV[`S^ e^[fe SdW `af bWd_[ffWV& S`V _gef `af hSdk [` V[S_WfWd ad iS^^ fZ[U]`Wee Se ebWU[X[WV STahW) LZW ba^k_Wd _gef TW ba^kbdabk^W`W' Z[YZ(VW`e[fk ba^kWfZk^W`W' ad afZWd ba^k_Wd b^Sef[Ue iZ[UZ SdW `af dWSUf[hW i[fZ fZW Ua`UdWfW ad efWW^ Se SbbdahWV Tk fZW =`Y[`WWd) LZW _SfWd[S^ _gef ZShW egXX[U[W`f efdW`YfZ S`V Vg dST[^[fk fa dWe[ef VS_SYW S`V VWfWd[adSf[a` Vgd[`Y XSTd[USf[a`' fdS`ebadf' efadSYW' [`efS^^Sf[a`' Ua`UdWfW b^SUW_W`f' S`V fW`e[a`[`Y) LZW VWTa`V[`Y _SfWd[S^ _gef ZShW S UaWXX[U[W`f aX Xd[Uf[a` i[fZ fZW efdS`V aX ^Wee fZS` +)+0)
N' 5YX\][^N]TYX' H^SUW fZW d[Y[V ba^k_Wd VWTa`V[`Y _SfWd[S^ Sf fZW ^aUSf[a`e ebWU[X[WV S`V fa fZW ^W`YfZe eZai` a` fZW b^S`e) ;a_b^WfW^k eWS^ fZW W`Ve aX fZW d[Y[V VWTa`V[`Y _SfWd[S^ i[fZ VgUf fSbW ad afZWd _SfWd[S^e Se SbbdahWV Tk fZW =`Y[`WWd fa bdWhW`f fZW [`fdge[a` aX UW_W`f bSefW ad iSfWd i[fZ[` fZW VWTa`VWV dWY[a`e aX fZW efdS`V)
O' @PL\^[PWPX] LXO CLaWPX]' 8^^ Uaefe SeeaU[SfWV i[fZ Xgd`[eZ[`Y S`V [`efS^^[`Y fZW d[Y[V ba^k_Wd VWTa`V[`Y _SfWd[S^ Se ebWU[X[WV i[^^ TW [`U^gVWV [` fZW Sbb^[UST^W g`[f bd[UWe Xad fZW Ua`UdWfW [fW_e) Fa SVV[f[a`S^ bSk_W`f i[^^ TW bWd_[ffWV)
90
JA;C KFQ<=J ?GN=JFGJ
STATE OF MICHIGAN
67C3EG@7AG B8 GE3AFCBEG3G<BALANSING
CAJC L) KL=M<D= <AJ=;LGJ
9MJ=8M G> >A=D< K=JNA;=K m ;GFKLJM;LAGF $ L=;@FGDG?Q 9MAD<AF? m H)G) 9GP .++/4 m D8FKAF?' EA;@A?8F /34,2 iii)_[UZ[YS`)Yah m %0,2&(.--(,+32
BS`gSdk ,/' -+,/
La OZa_ Af ESk ;a`UWd`5
LZW E[UZ[YS` <WbSdf_W`f aX LdS`ebadfSf[a` %E<GL& ZSe dWUW`f^k UZS`YWV [fe SUUWbfS`UW bdaUWee Xad efdgUfgdS^ bdWUSef Ua`UdWfW W^W_W`fe fZSf SdW eZ[bbWV fa fZW bda\WUf e[fW) LZW `Wi bdaUWee TWUS_W WXXWUf[hW [` fZW FahW_TWd ,3' -+,. dW^WSeW aX fZW -+,- E<GL ESfWd[S^e IgS^[fk 8eegdS`UW HdaUWVgdWe ES`gS^ %EI8H& S`V eZag^V TW [`U^gVWV [` S^^ bda\WUf ^Wff[`Ye TWY[``[`Y <WUW_TWd -+,.) LZW E<GL EI8H [e S Ua`fdSUf VaUg_W`f bWd egTeWUf[a` ,+1)+, aX fZW -+,- E<GL KfS`VSdV KbWU[X[USf[a`e Xad ;a`efdgUf[a` S`V US` TW Xag`V a` E<GLqe iWTe[fW ge[`Y fZW Xa^^ai[`Y ^[`]5
Zffb5**iii)_[UZ[YS`)Yah*_Vaf*+'/1,1'2(,0,(41--R,,+//R,,.12(-+243+(('++)Zf_^
KfdgUfgdS^ bdWUSef Ua`UdWfW XSTd[USf[a` SUUWbfS`UW UZS`YWe US` TW Xag`V [` fZW Xa^^ai[`Y eWUf[a`e aX fZW EI8H5
" KWUf[a` .),+ n ;a`UdWfW H[bW' ;g^hWdf' S`V JW^SfWV AfW_e S`V6
" KWUf[a` /)+/ n HdWefdWeeWV ;a`UdWfW >STd[USf[a`)
LZW EI8H `ai U^WSd^k eZaie S fia bSdf SUUWbfS`UW bdaUWee S`V dWcg[dWe fZW XSTd[USfad fa bdWbSdW S`V bdah[VW E<GLqe eZab [`ebWUfad i[fZ Sf ^WSef X[hW %0& Uab[We aX fZW 9[^^ aX DSV[`Y Xad WSUZ eZ[b_W`f) LZW eZab [`ebWUfad i[^^ efS_b S^^ efdgUfgdS^ Ua`UdWfW W^W_W`fe S`V WSUZ Uabk aX fZW 9[^^ aX DSV[`Y i[fZ fZW E<GL o8bbdahWV Xad MeWp efS_b S`V i[^^ dWfS[` a`W Uabk Xad fZW[d dWUadVe) Af [e fZW XSTd[USfadqe dWeba`e[T[^[fk fa V[efd[TgfW fZW dW_S[`[`Y Uab[We aX 9[^^ aX DSV[`Y fa fZW Xa^^ai[`Y [`V[h[VgS^e5
" E<GL Ua`efdgUf[a` [`ebWUfad6
" >STd[USfad6
" Hd[_W Ua`fdSUfad6
" LdgU][`Y Ua_bS`k)
LZW UZS`YWe fa E<GLqe SUUWbfS`UW bdaUWee Xad efdgUfgdS^ bdWUSef Ua`UdWfW XSTd[USf[a` S^[Y` [f i[fZ fZW efdgUfgdS^ efWW^ XSTd[USf[a` bdaUWee fZSf E<GL ZSe ZSV [` b^SUW Xad _S`k kWSde S`V ZSe bdahW` fa TW WXXWUf[hW S`V WXX[U[W`f) LZ[e UZS`YW ZSe _SVW fZW SUUWbfS`UW bdaUWee fZW eS_W Xad S^^ efdgUfgdS^^k XSTd[USfWV W^W_W`fe' dWYSdV^Wee aX _SfWd[S^ fkbW S`V i[^^ ZW^b XaefWd Ua`e[efW`Uk S`V S^[Y`_W`f SUdaee S^^ aX E<GLqe bda\WUf aXX[UWe) 8VV[f[a`S^^k' fZ[e eZag^V ZW^b WjbWV[fW fZW bSk_W`f bdaUWee) LZW 8bbdahWV Xad KZ[bb[`Y EW_adS`Vg_ fZSf fZW KfdgUfgdS^ >STd[USf[a` M`[f ZSe TWW` [eeg[`Y [` fZW bSef fa fZW bda\WUf aXX[UWe TWXadW fZWk _S]W bSk_W`f i[^^ `a ^a`YWd TW `WWVWV) 8e eaa` Se fZW fia bSdf SUUWbfS`UW bdaUWee [e Ua_b^WfW bSk_W`f Uag^V TW _SVW)
91
La OZa_ Af ESk ;a`UWd` HSYW - aX - BS`gSdk ,/' -+,/
E<GL W`UagdSYWe S^^ XSTd[USfade fa bdah[VW fZW KfdgUfgdS^ >STd[USf[a` M`[f i[fZ S eS_b^W aX kagd 9[^^ aX DSV[`Y Xad ge fa dWh[Wi bd[ad fa eZ[bb[`Y) LZ[e i[^^ S^^ai ge fa bdah[VW Ua__W`fe iW^^ [` SVhS`UW aX iZW` [f i[^^ TW `WWVWV) 8f S _[`[_g_' fZW Xa^^ai[`Y [`Xad_Sf[a` eZag^V TW eZai` a` fZW 9[^^ aX DSV[`Y5
" KZ[bb[`Y VSfW6
" <WeUd[bf[a` aX USdYa %cgS`f[fk' TWS_ e[lW' ^W`YfZ' WfU)&6
" E<GL bda\WUf ^aUSf[a` %dagfW' Udaee daSV*d[hWd' S`V U[fk&6
" E<GL bda\WUf efdgUfgdW `g_TWd' Ua`fda^ eWUf[a`' S`V \aT `g_TWd)
H^WSeW Ua`fSUf _W Tk bZa`W Sf %0,2& .--(02+4 ad W_S[^ Sf X[^UW]_7_[UZ[YS`)Yah i[fZ cgWef[a`e ad Ua`UWd`e) LZS`] kag Xad kagd bSf[W`UW S`V g`VWdefS`V[`Y Vgd[`Y fZ[e fdS`e[f[a`)
K[`UWdW^k'
ESffZWi B) >[^UW]' H)=) KfdgUfgdS^ >STd[USf[a` =`Y[`WWd 9d[VYW >[W^V KWdh[UWe n KfdgUfgdW LWUZ`[US^ KWUf[a`
EB>5\f
;U5 E) ;Zk`aiWfZ B) ?gff[`Y H) BS`eea` B) OW[^Wd <) HSbS`W] KfdgUfgdS^ HdWUSef ;a`UdWfW >STd[USfade EAL8
5;LLB?O!4%!3CE=?D1CACL;EEP!KCAG?>!<P!5;LLB?O!4%!3CE=?D!
16.!=G/5;LLB?O!4%!3CE=?D#!H/5C=BCA;G!1?I;JLF?GL!H@!
8J;GKIHJL;LCHG#!HM/7LJM=LMJ;E!3;<JC=;LCHG!2GACG??J#!
?F;CE/@CE=?DF0FC=BCA;G%AHN#!=/97!
1;L?.!(&'*%&'%'+!&-.*).)*!$&+"&&"
92
MD>F NIT?@MBJQ@MIJM
STATE OF MICHIGAN
67C3EG@7AG B8 GE3AFCBEG3G<BALANSING
FDMF O+ NO@P?G@?DM@>OJM
=PM@<P JA AD@G? N@MQD>@N r >JINOMP>ODJI $ O@>CIJGJBT =PDG?DIB r K+J+ =JS 0--16 r G<INDIB) HD>CDB<I 156.4mmm+c_Y^_]Wd+]el r &2.4'*0//*.-54
HWhY^ .0) /-.1
Oe R^ec Dj HWo >edY[hd7
O^[ H_Y^_]Wd ?[fWhjc[dj e\ OhWdifehjWj_ed &H?JO' _i h[gk_h_d] W HWj[h_Wb NekhY[ G_ij &HNG' je X[ ikXc_jj[Z \eh Wbb H?JO WdZ GeYWb <][dYo fhe`[Yji m_j^ ijhkYjkhWb fh[YWij YedYh[j[ [b[c[dji+ O^_i h[gk_h[c[dj _i [\\[Yj_l[ \eh fhe`[Yji G[j W\j[h <fh_b .) /-.1 WdZ Wffb_[i je Wbb [b[c[dji j^Wj h[gk_h[ \WXh_YWj_ed _dif[Yj_ed Wi j^[ XWi_i e\ WYY[fjWdY[ f[h j^[ H?JO HWj[h_Wbi NekhY[ Bk_Z[&HNB' eh Wi Z[j[hc_d[Z Xo j^[ Khe`[Yj @d]_d[[h+ O^[ Khe`[Yj @d]_d[[h m_bb dej_\o j^[ YedjhWYjeh _\ \WXh_YWj_ed _dif[Yj_ed m_bb X[ f[h\ehc[Z ed [b[c[dji dej [nfb_Y_jbo ijWj[Z _d j^[ HNB ie W HNG YWd X[ ikXc_jj[Z+
O^[ YedjhWYjeh ckij fhel_Z[ W Yecfb[j[Z WdZ i_]d[Z HNG &H?JO Aehc -2-.' je j^[ Khe`[Yj@d]_d[[h _d WYYehZWdY[ m_j^ ikXi[Yj_ed .-2+-. e\ j^[ NjWdZWhZ Nf[Y_\_YWj_edi \eh >edijhkYj_ed L] Y[ Z[TY[ ]Y ]SP Z[P&NYX\][^N]TYX WPP]TXR' O^[ Khe`[Yj @d]_d[[h m_bb \ehmWhZ j^[ HNG \eh H?JO fhe`[Yji je j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j je h[l_[m WdZ ki[ Zkh_d] _dif[Yj_ed+ Dd\ehcWj_ed ed Yecfb[j_d] j^[ HNG YWd X[ \ekdZ _d j^[ H?JO HWj[h_Wbi LkWb_jo <iikhWdY[ KheY[Zkh[i HWdkWb &HL<K' Y^Wfj[h .+-1+ O^[ HL<K _i W YedjhWYj ZeYkc[dj f[h ikXi[Yj_ed .-3+-. e\ j^[ /-./ H?JO NjWdZWhZ Nf[Y_\_YWj_edi \eh >edijhkYj_ed WdZ YWd X[ \ekdZ ed H?JOvi m[Xi_j[ ki_d] j^[ \ebbem_d] b_da7
^jjf7,,mmm+c_Y^_]Wd+]el,cZej,-)13.3)4*.2.*63//V..-11V..034*/-465-**)--+^jcb
C_ijeh_YWbbo) H?JO ^Wi dej h[gk_h[Z \WXh_YWjehi je Yecfb[j[ j^[ HNG \eh cWj[h_Wbi _dYehfehWj[Z_dje ijhkYjkhWb fh[YWij YedYh[j[ [b[c[dji8 ^em[l[h) j^[ ?[fWhjc[djvi ]eWb _i je h[ZkY[ cWj[h_Wb dedYed\ehcWdY[ _iik[i+ H?JO [dYekhW][i Wbb \WXh_YWjehi je YedjWYj j^[ NjhkYjkhWb AWXh_YWj_ed Pd_j _\ j^[o ^Wl[ Wdo gk[ij_edi ed Yecfb[j_d] j^[ HNG eh cWj[h_Wb WYY[fjWdY[+
Kb[Wi[ YedjWYj c[ Xo f^ed[ Wj &2.4' 0//*24-6 eh [cW_b Wj \_bY[ac;c_Y^_]Wd+]el m_j^gk[ij_edi eh YedY[hdi+ O^Wda oek \eh oekh fWj_[dY[ WdZ kdZ[hijWdZ_d] ed j^_i cWjj[h+
N_dY[h[bo)
HWjj^[m E+ A_bY[a) K+@+NjhkYjkhWb AWXh_YWj_ed @d]_d[[h=h_Z][ A_[bZ N[hl_Y[i s NjhkYjkh[ O[Y^d_YWb N[Yj_ed
@dYbeikh[
HEA7`j
YY7 H+ >^odem[j^ E+ Bkjj_d] K+ EWdiied ?+ KWfWd[aE+ R[_b[h >M<H HDO< HHGNjhkYjkhWb Kh[YWij >edYh[j[ AWXh_YWjehi?+ AhWda) K>D s ?_h[Yjeh e\ LkWb_jo >edjheb
6>OOEBR!4%!2FH@BG1FDFO>HHS!NFDJBA!?S!6>OOEBR!4%!2FH@BG!
17,!@J-6>OOEBR!4%!2FH@BG#!K-6F@EFD>J!1BL>MOIBJO!KC!<M>JNLKMOFKJ#!KP-/MFADB!2FBHA!
;BMQF@BN!$!;OMP@OPMB!<B@EJF@>H!;B@OFKJ#!BI>[email protected]@EFD>J%DKQ#!@-=;!9B>NKJ,!3!E>QB!MBQFBRBA!OEFN!AK@PIBJO!
5K@>OFKJ,!618<!02;!/PFHAFJD!1>OB,!(&'*%&)%')!'+,&+,'(!$&*"&&"
93
1(
7,
5/(
06
63
85
*,
0/6
7
F
PVT O
OOO ^
U OOOO
38>
?=
@-
?39
8>
* K
bT cWT Q
7EOH
MIEJN
>L
PMF
H 1
PIG
HR U^a
\PcT
aXP[ ]P\
T P
]S b
_TRXUXR
PcX^
] ]
d\
QTa)
=`fW
d "K
H"
Xad
E<
GL
KH
=;
# Xad
_SfW
d[S
^eebWU[X[W
V T
k e
bWU[S
^ bda
h[e
[a`) L
^ P
e^XS
VW^S
ke' egT_
[fSe e
aa` S
e b
aee[T
^W) F
a fWef[`Y a
X _
SfW
d[S^e
i[^^
TW
Ua`VgUfW
V g
`f[^ Xa
d_e S
dW d
WUW[h
WV)
KgT_
[f fa 8
^]bca
dRcX^]*F
a^YT
Rc ;
]VX]
TTa)
;
a`efd
gUf[a`*H
da\W
Uf =
`Y
[`WWd
fa Xadi
SdV
fa J
WY[a
` E
SfW
d[S^e
KgbWdh
[ead)
$F
[TPbT F
aX]c ^
a J
h_T P
[[ <
XT[S
b%
-9
8?
=9
6>
/-
?39
8
*3
26
75
8*
7/3
2';
=9
4/
-?
/8
138
//
=
-9
8?
=+
-?
9=
49
, 8
@7
,/
=
;=
94/
-?
69
-+
?39
8
<E
H E
<<
?8;
KI
; E
DB
N $
Ef
]Ta
6VT]Rh%
,+
>3>
90
+-
-/
;?
+8
-/
7
.9
?
>;
/-
"
1+
37
7+
?/
=3+
6'4
53
+8
*7
8+
7/
?
C;
/'>
3D/
LM
-6
+>
>
+;
;B
&
<?
C&
>9
@=
-/
90
7+
?/
=3+
6
#8+
7/
%+
..
=/
>>
%6
9-
+?
398
% 4
@D "
$ ?
/>
?
?&>
& A
&3&
<;
6
-/
=?
=/
7+
=5
>'9
?2
/=
-9
8?
=+
-?
9=
S> >
318
+?
@=
/
;=
38?
8+
7/
?
/6
/;
29
8/
8@
7,
/=
.
+?
/ 6
8)
1/7
7,
+
CXR
WXV
P] 9
T_Pac
\T]c
EU J
aP]b_^ac
PcX^]
+0+, $
+2*,
.%
3;
2,
5 (
-,
2*
< #
5>B
& 6
@?A
=DE
C>$
4
5/2
7 2
(1
,
7
,0
,4
.3
2,
28
1)
,5
+
(7
, 5
,*
,/9
,+
SdW
Ad
dit
ion
al P
ag
e
File
300
CL
EA
R F
OR
M
94
MD>F NIT?@MBJQ@MIJM
STATE OF MICHIGAN
67C3EG@7AG B8 GE3AFCBEG3G<BALANSING
FDMF O+ NO@P?G@?DM@>OJM
BUREAU OF FIELD SERVICES • >JINOMP>ODJI $ O@>CIJGJBT =PDG?DIB • K+J+ =JS 0--16 • LANSING, MICHIGAN 48917www.michigan.gov • &2.4'*0//*.-54
January 0, 2015
To Whom It May Concern:
It has recently come to the attention of the Michigan Department of Transportation (MDOT) that structural precast concrete fabricators have been providing sole plates for prestressed concrete beams shorter than what is detailed and required in the contract plans. In some cases, the shorter sole plates were approved via a Request for Information (RFI), email correspondence, or a note in the shop drawings. MDOT has discussed this issue with several structural fabricators that perform work for MDOT and their reasoning for providing the shorter sole plates is to avoid additional machining required to get the sole plates to properly fit-up in the forms. Most forms are fabricated with a radius in the bottom soffit corners and the sole plate edge would need to bechamfered to accommodate this radius (see attached MDOT Bridge Design Guides 8.43.01 and 8.43.01A). After thoroughly reviewing the design intent and contract details, MDOT’s position is that full-width sole plates are required when detailed in the contract plans.
MDOT currently designs and details sole plates for prestressed concrete beams when the geometry warrants their use. Over the years, MDOT has noted excessive spalling at the bottom ends of prestressed concrete beams without sole plates. Spalling typically occurs after the side forms have been removed and the strands are detensioned. The large eccentric compressive force from the de-tensioning operation creates large horizontal and vertical shearing forces at the beam ends from the friction between the beam and formwork and a rotation about the beam ends from the ensuring positive deflection (camber). Spalling is more severe on skewed beam ends since the rotation occurs at the tip of the skewed beam end resulting in a point load versus evenly along the entire beam end for beams with no skew. Beams detailed with sole plates do not typically experience beam end spalling since they are armored by the sole plate to resist the shear forces and point loads. To reduce the number of occurrences where the beam ends spall and the ensuing beam repairs, MDOT is requiring all prestressed concrete beams to be designed, detailed, and fabricated with sole plates. This should be effective starting with the March 2015 Letting. Fabricators are welcome to propose the addition of sole plates on current projects at no additional cost to MDOT.
95
TO WHOM IT MAY CONCERN Page 2 of 2 January 0, 2015
Please contact me by phone at (517) 322-5709 or email at [email protected] with questions or concerns. Thank you for your patience and understanding during this transition.
Sincerely,
Matthew J. Filcek, P.E. Operations Field Services Structural Fabrication Engineer
MJF: jt
Enclosure
cc: M. Chynoweth J. Gutting D. Juntunen P. Jansson D. Papanek J. WeilerACEC CRAM MITA MML Structural Precast Concrete Fabricators
HWjj^[m E+
A_bY[a
?_]_jWbbo i_]d[Z Xo HWjj^[m E+ A_bY[a
?I7 Yd9HWjj^[m E+ A_bY[a) e9H_Y^_]Wd ?[fWhjc[dj e\
OhWdifehj_ed) ek9=h_Z][ A_[bZ N[hl_Y[i * NjhkYjkh[
O[Y^d_YWb N[Yj_ed) [cW_b9\_bY[ac;c_Y^_]Wd+]el) Y9PN
M[Wied7 D ^Wl[ h[l_[m[Z j^_i ZeYkc[dj
GeYWj_ed7 H?JO >AN =k_bZ_d]
?Wj[7 /-.2+-.+0- .27-17.4 *-2%--%
96
Iej[ ieb[ fbWj[
[nj[dZi je i_Z[ e\
X[Wc &jof_YWb'+
97
Iej[ ieb[ fbWj[
[nj[dZi je i_Z[ e\
X[Wc &jof_YWb'+
98
MD>F NIT?@MBJQ@MIJM
STATE OF MICHIGAN
67C3EG@7AG B8 GE3AFCBEG3G<BALANSING
FDMF O+ NO@P?G@?DM@>OJM
=PM@<P JA AD@G? N@MQD>@N r >JINOMP>ODJI $ O@>CIJGJBT =PDG?DIB r K+J+ =JS 0--16 r G<INDIB) HD>CDB<I 156.4mmm+c_Y^_]Wd+]el r &2.4'*0//*.-54
?[Y[cX[h .3) /-.2
Oe R^ec Dj HWo >edY[hd7
Dj ^Wi h[Y[djbo Yec[ je j^[ Wjj[dj_ed e\ j^[ H_Y^_]Wd ?[fWhjc[dj e\ OhWdifehjWj_ed &H?JO' j^Wj iec[ ijhkYjkhWb fh[YWij YedYh[j[ \WXh_YWjehi meha_d] ed H?JO fhe`[Yji cWo dej X[ fhef[hbo ^WdZb_d] WdZ ijeh_d] [feno YeWj[Z h[_d\ehY_d] ij[[b+ NkXi[Yj_ed 6-2+-0+> e\ j^[ H?JO NjWdZWhZ Nf[Y_\_YWj_edi \eh >edijhkYj_ed &Wi ceZ_\_[Z Xo ikffb[c[djWb if[Y_\_YWj_ed ./NN*--.<*.-) @hhWjW je j^[ /-./ NjWdZWhZ Nf[Y_\_YWj_edi' h[gk_h[i [feno YeWj[Z h[_d\ehY[c[dj je c[[j j^[ h[gk_h[c[dji e\ <NOH < 442+ =[bem _i Wd [nY[hfj e\ YbWki[ .2 e\ <NOH <442*-4X&/-.1'7
15 | Handling and Identification
15.1 All systems for handling coated steel reinforcing bars shall have padded contact areas. All bundling bands shall be padded or suitable banding shall be used to prevent damage to the coating. All bundles of coated steel reinforcing bars shall be lifted with a strong back, spreader bar, multiple supports, or a platform bridge to prevent bar-to-bar abrasion from sags in the bundles of coated steel reinforcing bars. The bars or bundles shall not be dropped or dragged.
15.2 If circumstances require storing coated steel reinforcing bars outdoors for more than two months, protective storage measures shall be implemented to protect the material from sunlight, salt spray and weather exposure. If the manufacturer stores coated steel reinforcing bars outdoors without protective covering, the date on which the coated bars are placed outdoors shall be recorded on the identification tag on the bundled steel. Coated steel reinforcing bars, whether individual bars or bundles of bars, or both, shall be covered with opaque polyethylene sheeting or other suitable opaque protective material. For stacked bundles, the protective covering shall be draped around the perimeter of the stack. The covering shall be secured adequately, and allow for air circulation around the bars to minimize condensation under the covering.
15.3 Coated steel reinforcing bars, whether individual bars or bundles of bars, or both, shall be stored off the ground on protective cribbing.
15.4 The identification of all steel reinforcing bars shall be maintained throughout the coating and fabrication processes to the point of shipment.
O^[ fhel_i_ed \eh jme*cedj^i e\ [nfeikh[ ijWj[Z _d <NOH <442 mWi Z[l[bef[Z \hec j[ij_d] YedZkYj[Z Xo >*NCMK m^[h[ XWhi m[h[ b[\j [nfei[Z WdZ j^[d j[ij[Z+ O^[ @feno Ddj[h[ij Bhekf e\ j^[ >edYh[j[ M[_d\ehY_d] Nj[[b Ddij_jkj[ &>MND' h[Yecc[dZi [feno*YeWj[Z h[_d\ehY_d]
99
OJ RCJH DO H<T >JI>@MIKW][ / e\ /?[Y[cX[h .3) /-.2
XWhi X[ Yel[h[Z _\ ekjZeeh ijehW][ _i je [nY[[Z 0- ZWoi+ Aki_ed*XedZ[Z [feno YeWj_d]i cWokdZ[h]e ikh\WY[ Z_iYebehWj_ed WdZ Y^Wba_d] \hec [nfeikh[) m^_Y^ cWo h[gk_h[ h[fW_h YeWj_d] ZWcW][ eh beYWb_p[Z Yehhei_ed+ @feno YeWj_d]i j^Wj [nY[[Z j^[ cWn_ckc jme*cedj^ [nfeikh[ b_c_j f[h <NOH <442 Wh[ ikX`[Yj je YWh[\kb _dif[Yj_ed Xo j^[ >edjhWYjeh fh_eh je _dYehfehWj_ed_dje j^[ fhe`[Yj) h[fW_h e\ YeWj_d] ZWcW][ WdZ beYWb_p[Z Yehhei_ed) WdZ ikX`[Yj je fh_Y[h[ZkYj_edi f[h H?JOvi NjhkYjkhWb AWXh_YWj_ed IedYed\ehcWdY[ Keb_Yo+
Kb[Wi[ YedjWYj c[ Xo f^ed[ Wj &2.4' 0//*24-6 eh [cW_b Wj \_bY[ac;c_Y^_]Wd+]el m_j^ gk[ij_edi eh YedY[hdi+
N_dY[h[bo)
HWjj^[m E+ A_bY[a) K+@+Jf[hWj_edi A_[bZ N[hl_Y[iNjhkYjkhWb AWXh_YWj_ed @d]_d[[h
HEA7c`\
YY7 >+ Me][hiE+ Bkjj_d]K+ EWdiied?+ KWfWd[aE+ R[_b[h<>@>>M<HHDO<HHGNjhkYjkhWb Kh[YWij >edYh[j[ AWXh_YWjehi
100
MD>F NIT?@MBJQ@MIJM
STATE OF MICHIGAN
67C3EG@7AG B8 GE3AFCBEG3G<BALANSING
FDMF O+ NO@P?G@?DM@>OJM
=PM@<P JA AD@G? N@MQD>@N r >JINOMP>ODJI $ O@>CIJGJBT =PDG?DIB r K+J+ =JS 0--16 r G<INDIB) HD>CDB<I 156.4mmm+c_Y^_]Wd+]el r &2.4'*0//*.-54
?[Y[cX[h .4) /-.2
Oe R^ec Dj HWo >edY[hd7
Ekij W h[c_dZ[h j^Wj meha fhe]h[ii j[ij if[Y_c[di Wh[ h[gk_h[Z je X[ cWjY^ Ykh[Z _d j^[ iWc[ cWdd[h Wi j^[ fheZkYj _d WYYehZWdY[ m_j^ ikXi[Yj_ed Y+2+A e\ j^[ MDOT Special Provision for Quality Control and Acceptance of Portland Cement Concrete &./NK3-1B*-2'+ O^[ fkhfei[ e\ j^[ cWjY^ Ykh_d] h[gk_h[c[dj _i je [dikh[ j^[ meha fhe]h[ii j[ij if[Y_c[di WYYkhWj[bo h[fh[i[dj j^[ ijh[d]j^ e\ j^[ fheZkYj Wj j^[ j_c[ e\ j[ij_d]+ G_ij[Z X[bem Wh[ Yecced ijhkYjkhWb fh[YWij YedYh[j[ meha fhe]h[ii ijh[d]j^ h[gk_h[c[dji7
" Aehc h[celWb8
" M[b[Wi[ e\ fh[ijh[ii_d]8
" CWdZb_d] WdZ i^_ff_d]8 WdZ
" <YY[fjWdY[ j[ij_d]
H?JO YWd meha m_j^ Wdo \WXh_YWjeh j^Wj ^Wi gk[ij_edi ed m^Wj _i h[gk_h[Z je fhef[hbo cWjY^ Ykh[ meha fhe]h[ii j[ij if[Y_c[di je j^[ fheZkYj+ Kb[Wi[ YedjWYj c[ Xo f^ed[ Wj &2.4' 0//*24-6 eh [cW_b Wj \_bY[ac;c_Y^_]Wd+]el m_j^ gk[ij_edi eh YedY[hdi+
N_dY[h[bo)
HWjj^[m E+ A_bY[a) K+@+Jf[hWj_edi A_[bZ N[hl_Y[iNjhkYjkhWb AWXh_YWj_ed @d]_d[[h
HEA7c`\
YY7 >+ Me][hi <>@>E+ Bkjj_d] >M<HK+ EWdiied HDO<?+ KWfWd[a HHGE+ R[_b[h NjhkYjkhWb Kh[YWij >edYh[j[ AWXh_YWjehi
101
MD>F NIT?@MBJQ@MIJM
STATE OF MICHIGAN
67C3EG@7AG B8 GE3AFCBEG3G<BALANSING
FDMF O+ NO@P?G@?DM@>OJM
>JINOMP>ODJI $ O@>CIJGJBT =PDG?DIB r K+J+ =JS 0--16 r G<INDIB) HD>CDB<I 156.4mmm+c_Y^_]Wd+]el r &2.4'*0//*.-54
September 12, 2017
To Whom It May Concern:
It has recently come to the attention of the Michigan Department of Transportation (MDOT) that some welded sole plates for prestressed concrete beams are not meeting project requirements. MDOT requires structural precast concrete plants to be certified by either the Precast/Prestressed Concrete Institute (PCI) or National Precast Concrete Association (NPCA) depending on the type of work being performed. The American Concrete Pipe Association (ACPA) is considered an approved equal to NPCA for concrete culverts. PCI and NPCA state structural steel component welding requirements that must be followed by the Contractor. Below are excerpts from PCI and NPCA on structural steel welding:
" The first paragraph of subsection 2.3.1 of PCI MNL-116, 1999, 4th Ed. states, “Welding of steel plates, angles, and other shapes shall be in accordance with AWS D1.1. Welders qualified in accordance with AWS D1.1 and D1.4 shall perform all welds. Qualified engineers or quality control personnel shall write welding procedure specifications (WPS) for structural steel”. See PCI MNL-116 the additional information.
" Subsection 4.2.3 of NPCA, 2016, 12th Ed. States, “Welding of steel assemblies which are cast into or attached to precast concrete products shall be performed in accordance with American Welding Society D1.1, Structural Welding Code – Structural Steel”.
Please review your welding procedures and ensure structural steel welding required for structural precast concrete pay items meets the project requirements. Additionally, it is important to note that MDOT does not permit welding of reinforcing steel unless approved by the engineer due to the difficulty with obtaining sound welds. A detailed welding plan would be required to be submitted for MDOT’s Structural Fabrication Unit’s review prior to approval.
Please contact me by phone at 517-322-5709 or email at [email protected] with questions or concerns.
Sincerely,
Matthew J. Filcek, P.E.Bureau of Bridges and StructuresStructural Fabrication Engineer
cc: M. ChynowethM. BellgowanP. JanssonD. Papanek
J. WeilerACECCRAMMITA
MMLStructural Precast Concrete Fabricators
102
(This page intentionally left blank)
(This page intentionally left blank)
(This page intentionally left blank)
STRUCTURAL FABRICATION UNIT
V111417
COMMENTARY FOR PROJECT FOLDER CHECKLIST
PAGE 1 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
Commentary for Project Folder Checklist
Description
The Inspector’s Project Folder Checklist is used to aid in the gathering and combining of fabrication
documents for submittal to the Structural Fabrication Unit upon completion of fabrication. This document
is intended to provide the inspector with additional information regarding different materials involved in
precast concrete fabrication.
Fabrication work should not begin until all certifications, calibrations, materials (including coatings) and
test reports are verified and visually inspected, stamped approved shop drawings are in hand and all
required steel meets "Buy America" requirements. Notify MDOT-Structural Fabrication Unit (structural
precast concrete specialist), via email, if there are any deficiencies at the time of the first concrete pour
(when materials are incorporated into the fabricated elements). Be sure to allow enough time at the
fabrication facility prior to fabrication to go through the entire checklist. The checklist is not all inclusive:
there may be specifications of materials on the shop drawing or items in a special provision that may not
be covered on the checklist. Be sure to get all required documentation and check what is given to you.
It is the responsibility of the inspector to know the basis of acceptance for all materials incorporated into
the project. The information in this document may have changed after this document was written. If you
have any questions the Structural Precast Concrete Fabrication Specialist is one resource you can get
answers.
I. Forms/Certifications/Calibrations and other Non-Material Items Materials that have Approved Manufacturer listed as the “Basis of Acceptance” in the Materials
Acceptance Requirements Table in chapter 7 of the Material Quality Assurance Procedures (MQAP)
manual and in the Materials Source Guide (MSG) must have a General Certification accompany the
material per the requirements of section 3.01.03 of the MQAP Manual (Suppliers and Contractors can
write the General Certification). In addition, the quantity shipped is required on the certification. This is
listed in section 3.02.04 of the MQAP manual. Some examples are steel reinforcement, cement, precast
concrete box sections, precast concrete 3 sided or arch.
I have attached a link to our forms page for each form. Always be sure to use the most current forms.
See the appropriate section of the MQAP for a thorough explanation of the forms.
A. Project Folder Checklist Form 2001
B. Shop Inspection Report Form 5617
C. Sample Identification Form 1923
D. Strand Tensioning Report (0513) Form 0513
E. Bar Reinforcement Report Form 1985
103
STRUCTURAL FABRICATION UNIT
V111417
COMMENTARY FOR PROJECT FOLDER CHECKLIST
PAGE 2 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
F. Pre and Post Pour Inspection Checklist Form 5616
G. Field and Lab Test Report (forms 0590 and 0551 have been merged) Form 0590
H. Repair Observation Report Form 1981
I. Material Source List Form 0501 This form is required to be filled out by the fabricator. The
fabricator submits the form to MDOT, MDOT/QAI then fills out the basis of acceptance
requirements for the materials, and then distributes the completed form to the fabricator (the
construction office must be copied if materials will need to be tested by the construction office –
example: mechanical reinforcement splices). QAI should notify MDOT-Structural Fabrication Unit
if there is any required acceptance testing needed.
J. Certifications
1. Plant Certification
a. Prestressed Concrete Institute (PCI)
b. National Precast Concrete Association (NPCA)
2. Approved Manufacturers General Certification
a. See 3.01 in the MDOT MQAP Manual for General Certification requirements
b. Precast Concrete Box Sections (909.04D)
c. Precast Concrete Tree-Sided Arch Culverts (909.04G)
3. QC Certifications
a.
b. MCA Level II certification for anyone making concrete mix adjustments
c. PCI Level II certification, temporary cards are not acceptable certifications
d. PCI Level III certification, temporary cards are not acceptable certifications
e. ACI, Concrete Strength Testing Technician
4. QA Certifications
a. ACI or
b. PCI Level II Certification ), required for any prestressing QA inspection
c.
K. Calibrations
1. Compression Testing Machine
a.
2. Stressing Jacks
a.
3. Air Meter
a. Calibration
b. QA & QC air meter calibration sheet
4. Scales used for Aggregate and Cement
a.
104
STRUCTURAL FABRICATION UNIT
V111417
COMMENTARY FOR PROJECT FOLDER CHECKLIST
PAGE 3 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
b. Cement & Aggregates, measured on separate scales, follow 601.03.B.1.
c. Cement, cement and aggregates measured cumulatively, follow 601.03.A.2.
5. Volumetric Admixture Dispensers, Water Batching Devices (incl. water meters)
a.
b. Accuracy follow 601.03.B.5.
c.
6. Mixers, ensure have an attached metal plate showing the following information:
a. Serial number
b. Maximum mixing capacity in volume of mixed concrete
c. Mixing speed of the drum
d. Maximum agitating capacity in volume of mixed concrete, or on truck mixers and
agitators, the agitating speed of the drum or blades.
Note: frequency of scales checks can be less than the above if it is published in documents
from the plant certification organization (NPCA and PCI).
L. QC DocumentationDocumentation is required to be given to the Engineer within 24 hours of the date covered by the
record in a format acceptable to the Engineer. The list below may not be all inclusive.
1. Fresh Concrete Test Reports
2. Tensioning Report
3. Cylinder Test Reports
4. Curing Charts/Graph
5. Pre and Post Pour Checklists
M. Shop Drawings
1. The shop drawings must have an approval stamp on all sheets.
2. All revised sheets must have an approval stamp.
3. The stamp must have a name and date. It can either be an MDOT stamp or a stamp
that reads “Approved for MDOT”.
4. Design Build Projects will have a company name on the approval stamp on the shop
drawing sheets and a stamp from MDOT “Released for Construction”
N. Stamped Bill of Ladings Stamped bill of ladings are required for all projects with full-time inspection. Before stamping the
BOL’s the QA inspector should verify that the element mark listed on the BOL is unique to a
specific piece; there should not be any elements listed using the same element mark. If there are
any unstamped BOL’s, put them in the project folder and note why they are not stamped
“Approved for Use”, then sign and date.
II. Concrete
A. Fabricator Batched Concrete
1. Fabricator Mix Design
105
STRUCTURAL FABRICATION UNIT
V111417
COMMENTARY FOR PROJECT FOLDER CHECKLIST
PAGE 4 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
a. Cement (Approved Manufacturer)
b. Air entraining admixtures (QPL)(Gen Cert)
c. Water reducing and water reducing retarding admixtures (QPL)(Gen Cert)
d. Concrete accelerators (QPL & General Certification)
e. Fly ash and other pozzolanic admixtures (Approved Manufacturer)
f. Ground granulated blast furnace slag (Approved Manufacturer)
g. Verify batch to discharge times do not exceed allowable times. The time allowed
between charging mixer and placing concrete is in table 601-1 of the 2012 Standard
Specifications for Construction
B. RediMix Plant Concrete
1.
2. Concrete Tickets
a. All tickets must contain batch weights.
b. QAI Collects and signs all tickets when the trucks arrive.
c. Verify batch discharge times do not exceed allowable times (table 601-1 of the SSC)
3. Weekly Summary of Cert. Concrete from Central Mix and Transit Mix Plants Form 1155
The 1155 is filled out and signed by a representative from the redimix plant. It is needed for all
concrete pours for the project. The plant needs to know MDOT control section, job number
and construction engineer name. The fabricator should be getting the information to the
redimix plant, and if they don’t have the information then they can get it from the bridge
contractor or they can look it up themselves. Construction Contract Inquiry (select General
Contract Level Information and enter the project number). There is no need to check all
materials for the concrete. Verify that the materials not listed on the 1155 meet the basis of
acceptance. They are listed in the mix design that is required to be given by the fabricator.
III. Fine Aggregates Aggregates should be stockpiled at the fabrication facility so the stockpile is easily identifiable.
Multiple piles with different aggregates not identified are not acceptable.
A. Prequalified Aggregate Source
1. Aggregate Tickets
a. Collect signed ticket with a certified statement from the prequalified source.
b. Requirements of aggregate ticket can be found in Chapter 3 (MDOT Aggregate
Supplier Program) on page 32 of the Procedures for Aggregate Inspection
MDOT Procedures for Aggregate Inspection
2. Testing
Verify that a quality assurance (QA) test or an acceptance test has been completed by
MDOT on the material (Form 1900 or 1901).
a. The sampling schedule for MDOT Acceptance tests set up at the fabrication plant by
the Structural Fabrication Unit are 1 test per year on every aggregate being used at
every fabrication location. This will be pulled at the beginning of the construction year
to avoid any project delays.
106
STRUCTURAL FABRICATION UNIT
V111417
COMMENTARY FOR PROJECT FOLDER CHECKLIST
PAGE 5 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
b. If the inspector notices a stockpile management problem (segregated aggregates,
contaminated aggregates) at the fabricator location, notify MDOT so additional
testing (acceptance testing) can be set-up.
3. Alkali Silica Reactivity Test
Alkali Silica Reactivity test, In addition to collecting the ASR information, you need to check
that documentation submitted is acceptable (not required for fine aggregate used in R-2
mortar). ASR test results are valid for 2 years from completion of testing. If the ASR test expires
after fabrication starts then the fabricator must stop incorporating the material until new
acceptable test data is provided.
" The QAI must verify that an applicable ASTM has been submitted and results are
current. Check the special provision “QC & Acceptance of…”
B. Non-prequalified Aggregate Source
1. Acceptance Test
a. Required (1 test represents 1,000 tons). This needs to be done before the material is
incorporated into the work.
2. If the inspector notices a stockpile management problem (segregated aggregates,
contaminated aggregates) at the fabricator location then notify MDOT so additional
testing (acceptance testing) can be set up.
3. Alkali Silica Reactivity Test
In addition to collecting the ASR information, you need to check that what is submitted is
acceptable. ASR test results are valid for 2 years from completion of testing.
" The QAI must verify that an applicable ASTM has been submitted and results are
current. Check the special provision “QC & Acceptance of…”
IV.Coarse Aggregates Aggregates should be stockpiled at the fabrication facility so the stockpile is easily identifiable.
Multiple piles with different aggregates not identified are not acceptable.
A. Prequalified Aggregate Source
1. Aggregate Tickets
a. Collect signed ticket with a certified statement from the prequalified source.
b. Requirements of aggregate ticket can be found in Chapter 3 (MDOT Aggregate Supplier
Program) on page 32 of the Procedures for Aggregate Inspection
MDOT Procedures for Aggregate Inspection
2. Testing
Verify that a quality assurance (QA) test or acceptance test has been completed by MDOT
on the material (Form 1900 or 1901).
a. The sampling schedule for MDOT Acceptance tests set up at the fabrication plant by the
Structural Fabrication Unit are 1 test per year on every aggregate being used at every
107
STRUCTURAL FABRICATION UNIT
V111417
COMMENTARY FOR PROJECT FOLDER CHECKLIST
PAGE 6 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
fabrication location. This will be pulled at the beginning of the construction year to avoid
any project delays.
b. If the inspector notices a stockpile management problem (segregated aggregates,
contaminated aggregates) at the fabricator location, notify MDOT so additional testing
(acceptance testing) can be set-up.
3. Alkali Silica Reactivity Test
In addition to collecting the ASR information, you need to check that what is submitted is
acceptable. ASR test results are valid for 2 years from completion of testing. If the ASR test
expires after fabrication starts then the fabricator must stop incorporating the material until
new acceptable test data is provided. This is not needed for any coarse aggregates sources
from within the state of Michigan.
" The QAI must verify that an applicable ASTM has been submitted and results are
current. Check the special provision “QC & Acceptance of…”
4.
a. Prestressed Elements: 0.010 percent per 100 cycles
b. Concrete Spun Poles: 0.030 percent per 100 cycles
c. Non-Prestressed Elements
" 0.030 percent per 100 cycles or less for box culverts and 3-sided culverts
" 0.067 percent per 100 cycles or less for all others
" A special provision may change the F.T. requirement (MSE walls requires 0.010 percent
per 100 cycles or less
B. Non-Prequalified Aggregate Source
1. Acceptance Test
a. Required (1 test represents 1,000 tons). This needs to be done before the material is
incorporated into the work.
2. Alkali Silica Reactivity Test
In addition to collecting the ASR information, you need to check that what is submitted is
acceptable. ASR test results are valid for 2 years from completion of testing. If the ASR test
expires after fabrication starts then the fabricator must stop incorporating the material until
new acceptable test data is provided. This is not needed for any coarse aggregates sources
from within the state of Michigan.
" The QAI must verify that an applicable ASTM has been submitted and results are
current. Check the special provision “QC & Acceptance of…”
3. .)
a. Prestressed Beams: 0.010 percent per 100 cycles
b. Concrete Spun Poles: 0.030 percent per 100 cycles
c. Non-Prestressed Elements
" 0.030 percent per 100 cycles or less for box culverts and 3-sided culverts
" 0.067 percent per 100 cycles or less for all others
" A special provision may change the F.T. requirement (MSE walls requires 0.010 percent
per 100 cycles or less.
108
STRUCTURAL FABRICATION UNIT
V111417
COMMENTARY FOR PROJECT FOLDER CHECKLIST
PAGE 7 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
4. Stockpile Management
a. If the inspector notices a stockpile management problem (segregated aggregates,
contaminated aggregates) at the fabricator location then notify MDOT so additional
testing (QA sample) can be set up.
V. Stockpiled Aggregates (Aggregate ticket is over 1 year old). In addition to Coarse and Fine Aggregate requirements stated above, an acceptance test needs to
be run to verify that the material is still acceptable every year.
VI. All Steel (basis of acceptance)
A. Buy America The Buy America requirements for Structural Precast Concrete materials is summarized in the
document “Structural Fabrication Buy America Guidance Document” located in the Structural
Precast Concrete QAI Manual and the Structural Precast Concrete Fabrication Portfolio found in
the Structure Technical Section website.
Structure Technical Section
Buy America Compliance Listing for Approved Manufacturers, Qualified Products
List and Tested Stock Suppliers
Buy America-Compliance Listing
The inspector is required to verify that all processes for steel that is required to meet “Buy America”
requirements are checked. If you identify a QPL, Approved Manufacturer or Tested Stock
Supplier listed on the “Buy America Compliance Listing document” list the material name, its
source and the rating given on the site, then list it on the Shop Inspection of Precast Concrete
(Form 5617). If the rating given is a BA- we require the fabricator to compile the invoice cost of
the “non-USA made steel” to be submitted for acceptance by the Construction Engineer. No Buy
America Step Certs are required of a BA+ manufacturer. Steel Materials 1-6 are required to be
step certified if not from a BA+ manufacturer.
1. Strand for Prestressed Concrete
a. Approved MFR, General Cert, and Test Data Certification: 0.6" Dia. ASTM A416 Grade 270
low relaxation with load elongation curve.
2. Steel Reinforcement
a. Epoxy coating, QPL and General Cert.
b. Steel reinforcement, Approved MFR and General Cert.
c. Coating Company, Approved MFR and General Cert. The coating company needs to
provide a written certification that the coated reinforcing bars were cleaned, coated,
and tested in accordance with ASTM A775 (see SSC 905.03C.3.).
3. Welded Steel Wire Reinforcement
a. Approved MFR and General Cert.
109
STRUCTURAL FABRICATION UNIT
V111417
COMMENTARY FOR PROJECT FOLDER CHECKLIST
PAGE 8 of 8
MICHIGAN DEPARTMENT OF TRANSPORTATION
4. Steel Sole Plates
a. Step Certification for Buy America: See Shop Drawings for requirements
b. Shear Developers or Studs: QPL and General Certification
5. Position Dowels
a. Step Certification for Buy America: See Shop Drawings for requirement
6. MSE Connection Lugs
a. Test Data Certification: See Special Provision for requirements
7. Anchor Bolts
a. Test or General Cert for Anchor Bolts for Other Purposes (see special instructions in MSG)
8. High Strength Bolts
a. Test
9. Mechanical Reinforcement Splices (QPL with General Cert and Test)
a. The contractor must make test splices, witnessed by the Engineer, on the largest bar sizes
that are to be spliced. See Bridge Field Services Advisory (BFSA) 2012-03. BFS Advisory-
Mechanical Reinforcement Splicing Test splice consists of 2 pieces of reinforcing bar joined
by the coupler with 12 inches of bar exposed on each end of the coupler. This is witnessed
by the construction field office staff.
10. Concrete Design Inserts:
a. Verify that the design inserts meet electro-galvanizing to ASTM B633 Service Condition 4
11. Contractor Add-Ons
a. Visual Inspection of coating (be sure to VI and Accept the coating on form 5617)
VII. Elastomeric Bearing Pads The entire section of 914.12 of the SSC is replaced entirely with the frequently used special provision
“Elastomeric Bearings”. Must have a Certification and Test Data Certificate.
VIII. Curing Compound Test Data Certification & verification by the inspector
date of manufacture (be sure to VI and Accept the curing compound [list the date of
manufacturer] on form 5617)
110
/
#
PROJECT FOLDER CHECKLIST
1. Forms, Certifications, Calibrations and Non-Material Items
2. Concrete
3. Fine Aggregates
111 2019 Interim
4. Coarse Aggregates
5. Stockpiled Aggregates
6. Steel
7. Rigid Debonding
8. Curing Compound
9. Carbon Fiber Composite Cable (CFCC)
1122019 Interim
113 2019 Interim
KW][ . e\ .
H_Y^_]Wd ?[fWhjc[dj e\ OhWdifehjWj_ed
23.4 &-.,.5'834E<53G<BA <AFC75G<BA E7CBEG
Oe X[ Yecfb[j[Z Xo j^[ L< _dif[Yjeh) YecX_d[Z m_j^ Wbb ej^[h \WXh_YWj_ed
ZeYkc[djWj_ed) WdZ [b[Yjhed_YWbbo ikXc_jj[Z je j^[ H?JO NjhkYjkhWb AWXh_YWj_ed Pd_j+ M@KJMO "
B@I@M<G DIAJMH<ODJI DINK@>ODJI <B@I>T DINK@>OJM ?<O@
A<=MD><OJM , GJ><ODJI >JIOMJG N@>ODJI
EJ= ?@N>MDKODJI NDU@ <I? @G@H@IO OTK@ EJ= IPH=@M
NO<OPN JA A<=MD><ODJI AJM K@MDJ? @I?DIB M@LP@NO@? ?@GDQ@MT ?<O@ A<=MD><O@? #
>JHH@ION7
114
STRAND TENSIONING REPORT
SEQUENCE LOCATION MEASURED
ELONGATION ACTUAL GAUGE
READING
TENSIONING CALCULATIONS
INPUTS
OUTPUTS
NOTES
*
**
115 2019 Interim
SEQUENCE LOCATION MEASURED
ELONGATION ACTUAL GAUGE
READING COMMENTS
1162019 Interim
STRAND TYPE SYMBOL QUANTITY DESCRIPTION
TOTAL STRANDS
117 2019 Interim
0
Page 1 of 2
Michigan Department of Transportation
5616 (0 /18)
PRE AND POST POUR INSPECTION CHECKLIST
To be completed by the QA inspector, combined with all other fabrication documentation, and electronically submitted to the MDOT Structural
Fabrication Unit. REPORT #
GENERAL INFORMATION
INSPECTION AGENCY INSPECTOR DATE
FABRICATOR / LOCATION CONTROL SECTION
JOB DESCRIPTION SIZE AND ELEMENT TYPE JOB NUMBER
INSPECTION ITEM PRE POST
FO
RM
/DIM
EN
SIO
NS
Cleanliness
Form Oil
Bulkhead Plan End Square/Skew
Bulkhead Vertical Deviation
Side Plum Vertical Deviation
Sweep (Stringline)
Length Final
Width
Depth
Camber/Haunch
CO
VE
R Reinforcing Steel
Box Beam Top Slab Thickness
Size
Location
Number
Lap Length
Epoxy Coating
Slab Tie (count and spacing)
Slab Tie Projection
Size
Location
Number
Pattern
Debonding Location
Debonding Length
Debonding Material
Mid-Span Top Cable Pocket
Mid-Span Top Cable Debond
Draped Strands
EN
DS
Bearing Assembly Orientation
Pavement Seat Size & Orientation
Dowel Pin & Slot Location
Blockout Provided
119 2019 Interim
Page 2 of 2
INSPECTION ITEM PRE POST
CO
NC
RE
TE
Mix Design
Fresh Concrete Tests
Consolidation
Tining
Maximum Cure Temperature
Cylinder Tests
EM
BE
DD
ED
IT
EM
S
Lift Loop Location/Projection
PT Duct Size/Location
PT Duct Recess/Blockout
Keyway Size/Location
Styrofoam Void Size/Location
Drain Tube Installation
Drain Tubes Open After Casting
Insert Locations
Insert Size/Coating
Insert Threading (Coil/NC)
Deck Clip Spacing/Location
Forming Hanger Spacing/Location
Screed Pipe Spacing/Projection
Safety Line Bolt Spacing/Projection
INSPECTION ITEM AFTER LOADING
SH
IPP
ING
AP
PR
OV
AL
Face Finish
Back Finish
Cracks
Strands Cut Flush/Treated
Marked End
Top Finish Provided
Chamfers
Forms Seams Clean/Smooth
Surface Voids/Cracks
Keyways
Sealer Application
Stamped Approval For MDOT Use
COMMENTS:
120 2019 Interim
FIELD TEST REPORT
121 2019 Interim
REPAIR OBSERVATION REPORT
122 2019 Interim
#
#