METHODS
AT THE WORLD CONSTRUCTION CHAMPIONSHIP (WCC)
within the team nomination
Building Information Modeling and design
2021
![Page 2: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/2.jpg)
2
Contents
1. Purpose and scope 3
2. Terms and definitions 3
3. Regulations 5
4. Qualification criteria 6
5. Procedure of the nomination 6
6. “Homework” Stage 6
6.1 Description 6
6.2. Task 7
6.3. Recommendations on forming team composition 8
6.4. List of recommended software packages 8
7. Final stage 10
7.1. Description 10
7.2. Task 11
7.3. Requirements to the composition of teams 12
7.4. Recommendations on forming team composition 12
7.5. Hardware and software conditions of the site 14
7.6. List of software packages 15
8. Expert Jury and assessment strategy 16
8.2. Description of work of the Expert Jury at the "Homework" stage. 16
8.3. Description of work of the Expert Jury at the Final Stage 18
8.4. Technical Experts 18
8.4.1. The Developer Organization shall send Technical experts in the number, multiple of teams
to organize and conduct the nomination. 18
9. The procedure for determining the winners 18
10. Appeals 19
11. Rights, powers, and obligations 19
12. Replacements 19
13. Awards 19
Annex No. 1 Form of the final assessment protocol 21
Annex No. 2 Form of providing the Organizer with a list of Participants / Finalists 22
Annex No. 3 General assessment criteria for the Tasks 23
Annex No. 4 Timing schedule of the nomination 29
![Page 3: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/3.jpg)
3
1. Purpose and scope
These methodological recommendations of the International Construction Championship (hereinafter
referred to as the Methodology) determine the procedure and conditions of conducting World
Construction Championship (hereinafter referred to as the Championship) within the team nomination
“Building Information Modeling and design”.
The Methodology of team nomination " Building Information Modeling and design" is developed for
revealing the level of competence and complex evaluation of knowledge, skills and abilities of
specialists, carrying out activities in the field of designing with application of BIM-technologies at
industrial construction facilities.
2. Terms and definitions
Abbreviation Spelled out in form
Jury/Expert jury A group of experts evaluating the results of the tasks performed by the
Participants across categories
Task/Task of the
Championship
The Task to be performed, and according to whose results the Participants
demonstrate their knowledge level, abilities, and skills in the nomination
Quotas Number of places for specialists of Participant Organizations established
by the Organizing Committee for each nomination in the final stage of the
Championship
Nomination Name of the activity (profession) for which the Championship
competitions are held
Organizer A team of diverse specialists supervised by the Russian Federation
Ministry of Construction, and the Rosatom State Corporation, that is
responsible for organizing and holding the Championship
Participant
Organization
An Organization whose specialists take part in Championship
competitions/General Partner-Participant
Organizing
committee
Federal Organizing Committee of the Championship
Official site Website for the Championship that contains complete, reliable, and
updated information about the Championship
Site The site of the nomination, the place where the Participant/team of
Participants complete the Tasks for the final stage of the Championship
Participant / Team of
Participants
Specialist / Team of specialists taking part in the Championship
competitions
Organization-
developer
An Organization not participating in the competitions but providing
methodological support for nominations
Technical expert
A representative from the Developer Organization that works on the site
where the final stage in the Championship is held, and provides support for
holding nomination competitions and the work performed by the Jury
Finalist Specialist participating in the final competitions of the Championship
Championship The World Construction Championship (WCC) shall mean the
international championship in industrial facility construction
![Page 4: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/4.jpg)
4
Project Pilot project "Expansion and Reconstruction of the National Medical
Research Centre the Federal State Budgetary Institution "Dmitry Rogachev
NMIC DGOI" of the Russian Ministry of Health".
![Page 5: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/5.jpg)
5
Official Nomination
resource
Website that provides interaction between the Organizer, the Jury Experts,
the Participants in all stages of the Championship on the nomination.
Resource address: https://bim-wcc.ru
Resource and process
model, RPM
Interconnected data used to manage and optimize the processes of
construction work in the composition, including but not limited to:
− resource estimates;
− the schedule of work performance taking into account the
decomposition for work zones and power of links;
− process charts of work performance and working processes;
− resource sheets.
3. Regulations
The task was developed on the basis of the project documentation of the pilot project "Expansion and
Reconstruction of the National Medical Research Centre the Federal State Budgetary Institution
"Dmitry Rogachev NMIC DGOI" of the Russian Ministry of Health". The facility of the Task was
chosen due to the relevance and importance of the introduction of information technology in the
construction, including in the current environment of epidemiological situation associated with the
spread of coronavirus infection COVID-19.
List of regulations and documents used in the development of the task:
1. ISO 19650-1:2018 Organization and digitization of information about buildings and civil
engineering works, including building information modelling (BIM) — Information
management using building information modelling — Part 1: Concepts and principle;
2. ISO 19650-2:2018 Organization and digitization of information about buildings and civil
engineering works, including building information modelling (BIM) — Information
management using building information modelling — Part 2: Delivery phase of the assets;
3. ISO 16739-1:2018 Industry Foundation Classes (IFC) for data sharing in the construction
and facility management industries — Part 1: Data schema;
4. ISO 29481-1:2016 Building information models — Information delivery manual — Part 1:
Methodology and format;
5. ISO/TS 12911:2012 Framework for building information modelling (BIM) guidance;
6. ISO 22263:2008 Organization of information about construction works — Framework for
management of project information.
7. Resolution* of the Government of the Russian Federation No.87 dated February 16, 2008
"On the composition of sections of project documentation and requirements for their
content" (as amended on September 17, 2018);
8. GOST* (Russian state standard) 21.110-2013 System of design documentation for
construction (SDDC). Specification of equipment, products and materials”;
9. Set of Rules* 333.1325800.2017 "Information Modeling in Construction Industry. Rules of
generating information model of facilities at different stages of life cycle";
10. Set of Rules* 331.1325800.2017 "Information Modeling in Construction Industry. Rules of
exchange between information models of facilities and models used in software packages".
![Page 6: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/6.jpg)
6
11. Set of Rules* 404.1325800.2018 "Information Modeling in Construction Industry. Rules
for developing project plans implemented with the use of information modeling
technology".
* The documents were used for reference.
4. Qualification criteria
A team consisting of specialists involved in different parts of the Task at two stages of its execution
that meet the qualification criteria may take part in the nomination:
Item
No.
Requirement Content of requirement
1 Requirements to
qualification characteristics
and profession
Compliance of functional responsibilities with the following
positions:
- chief project architect,
- chief project engineer,
- PTD (Production and Technical Department) engineer,
- cost consultant engineer
- lead engineer.
5. Procedure of the nomination
5.1. The Participant Organizations shall, within the period specified in the nomination timing schedule
(Annex No. 4), select specialists on the qualification criteria for Participants in accordance with
Section 4 of the Methodology.
5.2. The Participant Organizations, within the period specified in the nomination timing schedule,
shall send to the Organizer information about the selected Participants according to the Form for
providing the Organizer with a list of Finalists (Annex No. 2) and ensure their registration on the
Official resource of the Nomination and the Championship's Official website https://pro-wcc.ru in the
section "For Participants".
5.3. Within the framework of the "Homework" stage, the Participant Organizations shall be offered to
perform the Task, which is the basis for further generation and execution of the Tasks of the
Championship Final Stage on the basis of the object information and resource and process models
created by the team.
5.4. The Participants shall be entitled to contact the Organizer and (if applicable) the Expert Jury for
additional information and explanations in the course of performing their Homework.
6. “Homework” Stage
6.1 Description
6.1.1. Within the period specified in the nomination timing schedule (Annex No. 4), the Participant
Organization team shall independently execute the Task and place the work result on the Official
Nomination resource. The result of the Task shall be checked for
![Page 7: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/7.jpg)
7
compliance with the criteria and rules of the work results assessment (Annex No. 3). Form of
participation - on-the-job in the Participant Organizations.
6.1.2. Results received later than the time specified in the timing schedule will not be reviewed by the
Expert Jury.
6.1.3. Participant Organizations independently ensure the availability of recommended software
packages at the work places of the Participants to execute the Task of the "Homework" stage.
6.1.4. As part of the stage Task execution for the Participant Organizations, the Organizer shall:
- register the Participants and provides access to the Nomination Official resource on the Internet;
- place the Task on the Nomination Official resource for the stage with instructions;
- provide consultations to the Participant Organizations during the period of the stage Task execution.
6.2. Task
Based on the object digital information models of the facility, the team of the Participants is required
to develop a consolidated object digital information and resource and process model of construction.
Item
No.
Name Contents
1 Initial data 1) digital object information models of sections
AR, KR, OV, TH of the Project in IFC format;
2) design documentation on the Project in PDF
format, in the scope sufficient to develop the object
and resource models.
2 Task 1) to develop object digital information models
for ES and VK sections;
2) to develop a consolidated object digital
information model;
3) to optimize design solutions;
4) to develop BEP (BIM Execution Plan) as a
part of:
a) Rules of information interaction;
b) Rules of naming and preparation of
elements;
c) Rules of preparation of the final
package of material for the
competition;
5) to develop a resource and process model of
construction (RPM) in the form of estimate
documentation.
The Organizer shall publish the composition of
initial data on the Project in the form of object digital
![Page 8: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/8.jpg)
8
information models and requirements to them at the
time of issue of the task.
6.3. Recommendations on forming team composition
At this stage of the Participant Organization is recommended to form a team of specialists:
1. BIM-manager;
2. Specialist in resource and process modeling;
3. Specialist in production planning;
4. Specialist in architectural and structural design;
5. Specialist in the design of engineering systems and networks;
6. Specialist in power supply section design;
7. Specialist in the design of the water supply and sewerage section.
In accordance with paragraph 7.3 of this Methodology, the Participant Organization shall send a team
of five Participants from the above mentioned specialists to the final stage of the Championship.
6.4. List of recommended software packages
Software Manufacturer Software name
Software for modeling capital construction object
Bentley Systems OpenBuildings Designer
Graphisoft Archicad
Autodesk Architecture, Engineering & Construction Collection
MagiCAD Group MagiCAD
Renga Software Renga
Nanosoft NanoCAD
Intergraph SmartPlan Foundation
Intergraph SmartPlant 3D
Neolant Polynome
Visual planning systems
EC "ASE" Multi-D Project
Bentley Systems SyncroPro
![Page 9: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/9.jpg)
9
Autodesk Navisworks Simulate
![Page 10: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/10.jpg)
10
Transport planning systems
Transoft solution Autoturn
Autodesk Vehicle Tracking
Modeling systems for construction layout plan
Credo-dialogue CREDO GENERAL PLAN
Consistent Software GeoniCS GENERAL PLAN
7. Final stage
7.1. Description
7.1.1 The final stage shall be held within the period specified in the timing schedule of the nomination
(Annex No. 4) in Sochi. The form of participation in the Championship is full-time, with a day release.
7.1.2 Participants shall arrive at the place of the final stage within the period specified in the timing
schedule of the nomination.
7.1.3 No later than 1 (one) day before the start of the Championship competition, Participants will
receive uniforms with the symbols of the Championship.
7.1.4 Prior to the start of the Championship competitions, the Participants shall undergo a General
labor protection and safety briefing, and participate in a General organizational meeting in the
Championship region. The time and place shall be determined by the Organizer and announced
additionally.
7.1.5 At the venue of the final stage, the Participants shall receive registration badges, participate in
the official opening ceremony of the Championship final stage and start to perform their Tasks. The
Organizer has the right to make changes in the schedule of the final stage of the Championship upon
notice of the Participants.
7.1.6 The time allowed to complete the Task is no more than 20 hours, including the lunch break. The
schedule may be changed by the Organizer upon notice of the Finalists at least one day before the
beginning of the Championship specified in the nomination timing schedule (Annex No. 4).
7.1.7 Becoming familiar with the workplace and Task:
- Participants are allowed to perform the Task only after passing the briefing on labor protection and
safety at the workplace;
- immediately before the beginning of the Task, the Jury Experts conduct an introductory briefing of
the Participants regarding the work regulations at workplaces, and acquaint the Participants with the
content of the Task and the evaluation criteria;
- no more than 30 minutes are allotted to conduct an introductory briefing and provide explanations
on the work regulations, which are not included in the total time for completing the Task.
7.1.8 Beginning and completion of work
The Participant Organization team must wait for instructions from the Technical Expert to begin and
complete the Task. In case for reasons beyond the control of the Participant Organization team, they
![Page 11: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/11.jpg)
11
had to interrupt the Task, they shall immediately report the forced stop to the Technical expert. In this
case, the cause and start and end time of the stop shall be officially recorded.
- after confirmation by the Jury expert, the Participant Organization team shall have the right to receive
additional time equal to the time of forced stop. The amount of extra time shall be determined by a
panel decision of the Expert Jury and shall be recorded in the Protocol of an emergency situation.
7.1.9 Abnormal situations
Any deviations from this Methodology and the provisions IN the General Procedure for the
Championship regarding the competitions during the final stage shall be considered as an abnormal
situation. The decision on an abnormal situation is made by Jury experts by a simple vote taken by
experts, while preparing the corresponding report sheet.
7.1.10 Communication and contacts by Participants and Jury experts
Any communication by Participants while executing the Tasks shall be regulated by the General
procedure of the Championship and by this Methodology.
7.1.11 Illness or accidents
In case of accident or sudden illness, the Participant shall first of all inform the Jury experts on the
site.
The Expert jury shall make a collective decision on whether it is possible to compensate for the time
lost by the Participant Organization team. If the Participant Organization team has to withdraw from
further participation in the Championship, it receives points for the amount of work performed at the
moment of the event.
7.2. Task
The Participant team is required to perform modeling of the Digital Construction Organization Project
(DCOP) in the selected system of software environments containing interconnected data for
construction process management.
Item
No.
Name Contents
1 Initial data All team developments performed as part of the Homework stage.
2 Tasks 1) to execute the construction organization project on the basis
of the object digital information model, interconnected with
the resource model, and also including the interconnected
data for the analysis and optimization of construction
processes;
2) to determine the need for building structures, materials and
equipment, labor, machinery and mechanisms with the
distribution by the structure construction periods;
3) to form RPM on the basis of analysis of construction
production methods according to the presented criteria (see
Annex No. 3);
4) to compare sequential, parallel and line production
construction methods with respect to the facility;
![Page 12: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/12.jpg)
12
5) to create presentation materials on the basis of RPM and
DCOP;
6) to visualize the facility construction process.
7.3. Requirements to the composition of teams
At this stage, the Participant Organization shall be required to form a team of five specialists selected
from the seven specialists specified in paragraph 6.3 of this Methodology.
The composition of the team of Finalists shall be strict in number, but not in functionality, and may
be agreed with the Organizer additionally at the request of the Participant Organization.
7.4. Recommendations on forming team composition
Item
No.
Recommendation Contents of the recommendation
1. Education
Higher industry-specific education on the basis of specialist
degree programs, bachelor's programs,
master's degree programs, work experience in the position
held at least 1 year.
Specializations:
- organization of construction production;
- design of buildings and housing;
- design of engineering systems for industrial and civil
buildings.
as well as:
Higher education (non-industry-specific) - bachelor’s
programme, specialist's programme, master’s programme
and complementary professional education or professional
retraining programs in the field of organization of
construction production and/or design of civil buildings and
housing and work experience in the position held not less
than 1 year.
Complementary professional education - professional
development programs in the field of information modeling
technologies.
2. Abilities and skills - to use national and international regulatory and
technical documentation in the field of design;
- to calculate technical and functional systems of the
design facility;
- to plan the construction works;
- to analyze analogs of equipment and materials to
implement technical solutions;
- to develop an information model of the capital
construction object in various CADs;
![Page 13: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/13.jpg)
13
- to have experience in creating object information
models in any of the systems specified in Section 7
of the Methodology.
![Page 14: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/14.jpg)
14
3. Competence - the national and international legislative and
regulatory acts in the area of design work in
construction;
- the national and international technical regulation
documentation in the field of design work in
construction;
- methods of designing engineering systems and
structures of buildings and housing;
- the features inherent in the software to develop object
digital information models for capital construction
projects.
4. Experience - obtaining and analysis of initial data;
- setting up software tools for working with
information models;
- development of an object digital information model
section in accordance with the information modeling
project implementation plan.
- creation of the consolidated object digital
information model of the capital construction project
- quality control of the consolidated object digital
information model of the capital construction project.
7.5. Hardware and software conditions of the site
7.5.1. The hardware conditions are the same for each Participant including but not limited to the
requirements specified in Table 7.3.
Operating System Microsoft® Windows® 10 (64-bit version)
Windows 10 Enterprise
Windows 10 Professional
CPU type Intel Xeon or i-Series multi-core processor or equivalent AMD processor
with SSE2 technology support.
Memory 64 GB RAM
![Page 15: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/15.jpg)
15
Screen and resolution 1920 x 1200
with support for full color True Color mode
Video adapter Video card with DirectX 11 and Shader Model 5 support
Location and type of
media
100 GB of free disk space
SSD
Pointing device Device compatible with MS-Mouse or 3Dconnexion
Browser Google Chrome latest version
7.5.1. Hardware conditions may be changed by the Organizer unilaterally for the conditions with
similar characteristics or to increase the total capacity of devices.
7.6. List of software packages
7.6.1. List of software packages used in the final stage:
Software Manufacturer Software name
Visual planning systems
EC "ASE" Multi-D Project
Bentley Systems SyncroPro
Autodesk Navisworks Simulate
Systems for valuation and creation of estimate documentation
Nomitech CostOS
StroySoft Atomsmeta
STC (Scientific and technical
center) "Hector" Hector 5D
RPE (Research and Production
Enterprise) "AVS-N" BIM-estimate
Transport planning systems
Transoft solution Autoturn
![Page 16: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/16.jpg)
16
Autodesk Vehicle Tracking
Modeling systems for construction layout plan
Credo-dialogue CREDO GENERAL PLAN
Consistent Software GeoniCS GENERAL PLAN
Quality control systems for object digital information models
Nemetschek Solibri
7.6.2. The list of software may be supplemented upon the requests of Participant Organizations sent
to the Organizer by February 15, 2021 at 18.00 (MSC). The final list of software shall be announced
not later than 5 days before the start of the Championship final stage.
8. Expert Jury and assessment strategy
8.1. Composition of the Expert Jury
8.1.1. Composition of the Expert Jury at the Homework stage:
- Representatives of Participant Organizations - 1 expert from each organization;
- Technical experts - 2 experts;
- Supervisory Group (hereinafter referred to as the Supervisory Group), consisting of:
- Representative of the Federal State Budgetary Institution "Dmitry Rogachev NMIC DGOI" of
the Russian Ministry of Health - 1 expert*.
(* - "Dmitry Rogachev NMIC DGOI" requirement, is responsible for the evaluation of the
technical and organizational solutions proposed by the Participants of the Championship in terms of
the object specificity)
- representative of BuildingSMART International - 1 expert**
(** - participates in the work of the Expert Jury due to a special award from buildingSMART
Russia);
- Representative of FAO FCS (Federal Autonomous Organization Federal Centre for
Standardization) - 1 expert***
(*** - participates in the work of the Expert Jury as the Chief Methodologist on IM from the
Ministry of Construction, Housing and Utilities of the Russian Federation);
- Representative of SC (sub-committee) 5 of TС (technical committee) 465 - 1 expert****.
(**** - participates in the work of the Expert Jury as a representative of the professional
community. Shall be selected in advance).
8.1.2. Composition of the Expert Jury at the Final stage:
- representatives of Participant Organizations - 1 expert from each Participant Organization;
8.2. Description of work of the Expert Jury at the "Homework" stage.
8.2.1. The qualification criteria for the experts are set forth in the Regulations on the work of Expert
Juries.
![Page 17: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/17.jpg)
17
8.2.2. Technical experts shall form the composition of the Supervisory group before the beginning of
the "Homework" stage.
8.2.3. The technical experts shall develop and submit checklists to the Expert Jury to assess the
completion of the Homework.
8.2.4. The Homework is assessed by a full Expert Jury as part of the Expert Jury meeting. Format of
participation: remote.
8.2.5. During the meeting the Chairman of the Expert Jury, his Deputy are elected and the composition
of the Expert Jury is approved.
![Page 18: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/18.jpg)
18
8.2.6. The results of the meeting shall be recorded in minutes and signed by the members of the Expert
Jury.
8.2.7. Upon recommendation of the Chairman, the composition of the Expert Jury may be completed
within the period up to the day of the beginning of the Championship (in case if the Participant
Organization submits an application for participation in the Championship after the Jury composition
is approved).
8.2.8. The winner Organization "For the best object digital information model" - a special award from
BuildingSMART Russia - shall be determined during the meeting.
8.3. Description of work of the Expert Jury at the Final Stage
8.3.1. The personal composition of the Jury at the final stage shall be formed by the procedure of
drawing, which shall be carried out in accordance with the Regulations on the work of the Expert Jury
from among the experts of the Participant Organizations. If, in the course of the drawing, an expert
from the Participant Organization gets the team from his/her Organization, the drawing shall be
repeated.
8.3.2. Representatives of the Surveillance Group, who are members of the Expert Jury at the
"Homework" stage, may be present at the Championship venue, observe the processes of performance
of tasks by the Participants, attend the Participants' presentations of their results and ask questions
during the presentations. Representatives of the Surveillance Group are not bound to specific teams
of the Participants.
8.3.3. The Expert Jury (representatives of the Participant Organizations) shall discuss and assess the
teams of Participants and determine the winners.
8.3.4. Representatives of the Surveillance Group may be present at the presentation of the summative
assessments by the Expert Jury. Representatives of the Surveillance Group shall not have the right to
assess the result of the Task performance by the teams of Participants, but the Expert Jury may take
into account the opinion of the Representatives of the Surveillance Group when assessing, if such
opinion is justified and does not contradict the requirements for the Task performance.
8.3.5. The Representatives of the Surveillance Group shall be a part of the Review Board as its full
members and shall perform the functions specified in the Regulations on the Nomination Review
Boards.
8.4. Technical Experts
8.4.1. The Developer Organization shall send Technical experts in the number, multiple of teams to
organize and conduct the nomination.
8.4.2. The work of the Technical Experts shall be regulated by the General Championship Procedure.
9. The procedure for determining the winners
9.1. The winners (first place) and prizewinners (second and third places) shall be determined by the
Expert Jury based on the assessment of the results of the teams of the Participant Organizations. The
winner shall be the team with the highest number of points according to the criteria and rules for
assessment of the Task results (Annex No. 3).
![Page 19: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/19.jpg)
19
9.2. In case two or more teams have scored the same number of points, the Organizer shall ensure that
an additional stage of assessment is conducted on the basis of a predetermined set of additional criteria
that do not correlate with the main ones.
9.3. The Expert Jury shall execute the final protocol in accordance with Annex No. 1 to this
Methodology and submit it to the Organizer.
10. Appeals
10.1 Within the framework of the final stage of the Championship, the Participants may lodge an
appeal against the quality of the evaluation done on the results, and the work done by the Jury for the
evaluation and tallying procedure.
10.2 The appeal is filed on the terms and conditions established by the Regulation on the appeal
commissions for nominations.
10.3 Appeals are reviewed by the Appeals Commission.
11. Rights, powers, and obligations
The rights, powers, and obligations borne by the Participants, Expert Juries, Technical Experts, and
the Organizer are established in the General Procedure for the Championship.
12. Replacements
12.1. Participant Organizations shall ensure that there is a reserve team of Participants for the
nomination to replace Finalists if unforeseen circumstances arise, and there is a forced cancellation of
participation for the Participants from the first team in the final stage of the Championship.
12.2. The number of reserve Participants shall be equal to the number of main Participants.
12.3. Participants from the reserve team shall meet the qualification criteria specified in the
Methodology.
12.4. Reserve team participants shall register on the official website of the Championship, and fill out
a Participant questionnaire in the “For Participants” section.
12.5. Participants can be replaced no later than 2 (two) weeks before the start of the final stage of the
Championship. The time the replacement is made is considered to be the date the Organizer sends a
response to the Participant Organization that acknowledges the replacement.
12.6. The Organization participating in the Championship shall replace the Participant drawing from
the reserve team of Participants by sending an official notification to the Organizer indicating the
reason for the replacement, and that gives data about the Participants from the main and reserve teams,
and then receives a response from the Organizer that confirms the replacement.
13. Awards
13.1 The winners and prizewinners are provided with monetary awards in accordance with the General
Procedure for holding the Championship.
![Page 20: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/20.jpg)
20
13.2 A special prize from BuildingSMART Russia for the best object digital information model made
at the Homework stage is provided.
![Page 21: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/21.jpg)
21
Annex No. 1
Form of the final assessment protocol
PROTOCOL
of the Expert Jury final assessment in the team nomination " Building Information Modeling and
design"
"___" ______________20___
Item
No.
Name
of the Participant Organization of the Championship
Point count Place taken
2
3
4
5
…
Jury Experts:
___________________ / _____________ /
![Page 22: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/22.jpg)
22
Annex No. 2
Form of providing the Organizer with a list of Participants / Finalists
Main composition of Participants/Finalists:
Item
No.
Full
Name
Position Organizati
on
E-mail Contact
phone
Specialty
within the
nomination
(if
applicable)
Registration
mark on the
Official
website (yes
/ no)
Team nomination “Information modeling and design”
Reserve team of Finalists:
Item
No.
Full
Name
Position Organizati
on
E-mail Contact
phone
Specialty
within the
nomination
(if
applicable)
Registration
mark on the
Official
website (yes
/ no)
Team nomination “Information modeling and design”
…
Head of a Participant Organization
___________________ /____________/
![Page 23: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/23.jpg)
23
Annex No. 3
General assessment criteria for the Tasks
Item
No.
Criteria Points*
1 Assessment of completeness and quality of the object digital information model of
the facilities of the "Homework" stage
1.1. Availability of object digital models and compliance of technical solutions with the
project documentation issued as initial data
1.1.1 Digital object models of ES and VK sections in the volume allowing to form
RPM are presented
5
1.1.2 Digital models of ES and/or VK section are not presented 0
1.2. Availability of a consolidated object digital information model
1.2.1 The consolidated object digital information model is presented 10
1.2.2 The consolidated object digital information model is not presented 0
1.3. Presence of BIM Execution Plan
1.3.1 The BIM Execution Plan is presented in full, including rules of information
interaction, rules of naming and preparation of elements and rules of
preparation of the final package of material for the competition.
30
1.3.2 The BIM Execution Plan is presented in the scope of rules of information
interaction, rules of naming and preparation of elements.
20
1.3.3 The BIM Execution Plan is presented in the scope of rules of information
interaction
10
1.3.4 BEP is not presented 0
1.4. Correct binding of the summary model to geographical and elevation coordinates
1.4.1 The object digital model is precisely bound to the base geographic coordinates
of intersection of at least two points of axes and two elevation marks
5
![Page 24: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/24.jpg)
24
1.4.2 Correct binding of the summary model to geographical and elevation
coordinates is not implemented
0
1.5. Availability of RPM in the form of local estimate calculations associated** with the
object digital information model in the current prices
1.5.1 Local estimate calculations associated with the object digital information
model in the current prices are presented
30
1.5.2 Local estimate calculations associated with the object digital information
model are presented, but not in the current prices
20
1.5.3 Local estimate calculations are presented in the current prices, but not
associated with the object digital information model
10
1.5.4 Local estimate calculations are not presented 0
1.6 Audit of the object digital information model of the building, detection of physical
and intellectual collisions (performed on the basis of the summary IFC2x3 model
file using Solibri Office v9.10.8)
1.6.1 The relative** total number of errors to the total number of elements of the
object digital information model (critical, medium level, non-critical) for a
standard set of checks in Solibri system is less than 15%
20
1.6.2 The relative** total number of errors to the total number of elements of the
object digital information model (critical, medium level, non-critical) for a
standard set of checks in Solibri system is 15 to 50%
10
1.6.3 The relative** total number of errors to the total number of elements of the
object digital information model (critical, medium level, non-critical) for a
standard set of checks in Solibri system is greater than or equal to 50%
5
Maximum number of points per stage 100
2. Assessment of RPM and digital construction organization project of the Final stage
![Page 25: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/25.jpg)
25
2.1. Availability of a construction organization project based on the object digital
information model, which includes interconnected*** data to manage construction
processes
2.1.1 The construction organization project connected with resource and object
digital information model is presented
5
2.1.2 The construction organization project connected with resource information
model is presented
3
2.1.3 The construction organization project connected with object digital
information model is presented
2
2.1.4 The construction organization project is presented 1
2.1.5 The construction organization project is not presented 0
2.2. Determination of the need for building structures, materials and equipment, labor,
machinery and mechanisms with the distribution by the structure construction
periods
2.2.1 The need for building structures, materials and equipment, labor, machinery
and mechanisms with the distribution by the facility construction periods is
determined
5
2.2.2 The need for building structures, materials and equipment, labor, machinery
and mechanisms is determined without the distribution by the construction
period of the facility.
3
2.2.3 The need is not defined 0
2.3. Generation of RPM based on the analysis of construction production methods by
several criteria****
2.3.1 The substantiation is presented that RPM is optimal in relation to four or more
criteria of efficiency of construction production processes
40
2.3.2 The substantiation is presented that RPM is optimal in relation to three criteria
of efficiency of construction production processes
30
2.3.3 The substantiation is presented that RPM is optimal in relation to two criteria
of efficiency of construction production processes
20
![Page 26: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/26.jpg)
26
2.3.4 The substantiation is presented that RPM is optimal in relation to one criterion
of efficiency of construction production processes
10
2.3.5 No substantiation is presented that the criteria of efficiency of the construction
production processes are taken into account in the generation of the RPM
0
2.4 Comparison of sequential, parallel and line production methods of the
facility construction
2.4.1 The substantiation report of the team's analysis of three methods of
construction production is presented, the most effective one in terms of the
previously selected criteria is justified
30
2.4.2 The substantiation report of the team's analysis of two methods of construction
production is presented, the most effective one in terms of the previously
selected criteria is justified
20
2.4.3 The substantiation report on the team's analysis of one of the methods of
construction production is presented
10
2.4.4 The substantiation report on the team's analysis of construction production
methods is not presented
0
2.5. Creation of presentation materials: visualization of the facility and construction
process Presentation of RPM and DCOP
2.5.1 The RPM and Digital CPD (construction planning design) are demonstrated
with an oral presentation of the main parameters and results
10
2.5.2 The RPM was demonstrated with an oral presentation of the main parameters
and results
5
2.5.3 The RPM and Digital CPD have not been demonstrated 0
2.6. Visualization of DCOP by building construction period
2.6.1 The visualization of the DCOP by building construction period is
demonstrated
5
2.6.2 No visualization 0
2.7. Answers to the questions of the Expert Jury
2.7.1 The team answered 5 of 5 questions satisfactorily 5
![Page 27: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/27.jpg)
27
2.7.2 The team answered 4 of 5 questions satisfactorily 4
2.7.3 The team answered 3 of 5 questions satisfactorily 3
2.7.4 The team answered 2 of 5 questions satisfactorily 2
2.7.5 The team answered 1 of 5 questions satisfactorily 1
2.7.6 The team answered 0 of 5 questions satisfactorily 0
Maximum possible point total 100
* Within each criterion, a point is assigned by the Expert Jury to determine whether the Participating
Organization team work result meets the requirements. The points are not summed up.
** Principle of points calculation on the basis of automated quality assessment of summary digital
object information models of Solibri system:
1. The total number of elements of the consolidated object digital information model for all
sections of the consolidated model is calculated.
2. All non-conformance assessments (critical, average, not critical errors) detected by Solibri
Office v9.10.8 system are summed up by rule blocks:
● BIM Validation Architectural
● BIM Validation Structural
● BIM Validation HVAC
● Intersection Between Architectural Components
● Intersection Between Structural Components
● Model Revision comparison
● Structural Versus Architectural Models
● Reinforcing Bar
● Intersection Between HVAC Elements
● Architectural Components versus HVAC
● Structural Components versus HVAC
3. The ratio of the number of errors to the total number of elements of the consolidated model in
percent is calculated. On the basis of this ratio, a final score is made;
4. The result of an automated quality check of the consolidated object digital information model:
a. up to 15% of the total number of errors detected - 10 points;
b. from 15 to 50% - 5 points;
c. more than 50% - 0 points.
![Page 28: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/28.jpg)
28
*** In accordance with Section 2 of this Methodology, the Interconnection or associativity of data
between models is checked by the Expert Jury by the method of introducing changes in one model
and controlling the result of these changes in another.
**** Criteria for evaluation of resource and technology model efficiency of the construction facility
are published by the Expert Jury for the Finalists on the day of issue of the task for the Final Stage of
the Championship.
![Page 29: METHODS AT THE WORLD CONSTRUCTION CHAMPIONSHIP …](https://reader033.fdocuments.net/reader033/viewer/2022043020/626c10623734e5260661c47d/html5/thumbnails/29.jpg)
29
Annex No. 4
Timing schedule of the nomination
Item
No.
Event Date, 2020
1 The beginning of the Championship.
“Homework” Stage
December 11, 2020
2 Registration of Participant Organizations and
Participants that meet the qualification criteria*
till December 11, 2020
3 The Organizer publishes the task for the
“Homework” Stage for the Participant
Organizations
December 14, 2020
4 The Participant Organization sends the work result
by means of the Official Nomination resource**
within 60 calendar days from the
date of publication of the Task
(clause 3), but no later than
February 15, 2021
5 The Expert Jury checks the results*** within 30 calendar days from the
date of receipt of the result of
work from the Participating
Organization, but no later than
March 15, 2021
6 The Expert Jury will forward the results of the
assessment of works on the "Homework" stage to
the Organizer
March 19, 2021
7 The final stage of the Championship - competition
days
April 2021
* The deadline for accepting applications can be increased by the Organizer.
** The deadline for completing homework is no more than 60 (sixty) calendar days from the date of
registration, but no later than April 02, 2021.
*** The assessment of the work performed at the "Homework" stage is carried out by the Expert Jury
no later than April 16, 2021.