Method Statement Report - Cape EAPrac Witsand... · A Method Statement describes the scope of the...
Transcript of Method Statement Report - Cape EAPrac Witsand... · A Method Statement describes the scope of the...
Method Statement Report OSMOSUN 100TM Desalination Plant
Witsand, South Africa
Prepared for
Turnkey Water Solutions
Prepared by
WML Coast (Pty) Ltd
and
Alternative Services Technology (Pty) Ltd
20 July 2018
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd i
Quality Management
Project number: 180423
Issue FINALV0
Date 2018/07/20
Preparedby Checkedby Authorisedby
EnriqueJulyan
andDudleyJanekeSpecialists
LaurieBarwell
ManfredKloos
Revision
Date
Preparedby Checkedby Authorisedby
Revision
Date
Preparedby Checkedby Authorisedby
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd ii
Table of Contents 1 IntroductionandBackground.........................................................................................................3
2 SiteDescription...............................................................................................................................5
3 Somerelevantsitecharacteristics..................................................................................................7
3.1 TidelevelsintheoceanatWitsand.........................................................................................7
3.2 RiverFlooding..........................................................................................................................8
3.3 Geohydrology...........................................................................................................................8
4 ShortsummaryoftheOSMOSUN100process...............................................................................9
5 Sitelayoutoverview......................................................................................................................11
6 MethodStatements......................................................................................................................12
6.1 Methodstatement1.1:IntakeWorks–Option1..................................................................14
6.2 Methodstatement1.2:IntakeWorks–Option2..................................................................18
6.3 Methodstatement1.3:IntakeWorks–Option3..................................................................22
6.4 Methodstatement2:Steelintakepipelineacrosssteepslope.............................................26
6.5 Methodstatement3:BuriedHDPEsupplyandeffluentpipelines........................................28
6.6 Methodstatement4:BuildingsandinfrastructurefortheROplant.....................................30
6.7 Methodstatement5:SolarFarmInfrastructure....................................................................32
6.8 Methodstatement6:Steeleffluentpipelineacrosssteepslope..........................................34
6.9 Methodstatement7:Brineoutfallworksalongestuarybank..............................................36
6.10 Methodstatement8:Botanicalaspects..............................................................................38
7 Closure..........................................................................................................................................39
List of Figures Figure1:Typicalappearanceofcurrentnaturalrockshelf (Bokkeveldshale)attheestuary/river’sedge.......................................................................................................................................................6Figure2.Viewofexistingpumpingstationinfrastructure–lookingnorth...........................................6Figure3:Typicalvegetationatlowersectionofsteepriverbank..........................................................7Figure4:Predictedfuture50-yearand100-yearreturnintervalfloodlevels(BreedeRiverFloodlineStudy).....................................................................................................................................................8Figure 5: Vertical sectional sketch of aquifer and groundwater relationship – looking upstream(Steenekamp,2018)..............................................................................................................................9Figure6:Proposedsitelayout.............................................................................................................11
List of Tables Table1:CharacteristictidallevelsatWitsand(SANHO)........................................................................7
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 3
1 Introduction and Background
The Hessequa Municipality has created the Hessequa Innovation Helix in collaboration with the
Stellenbosch Good Governance Forum (University of Stellenbosch) to implement innovative
solutions addressing the prevailingwater crisis/shortages in theWestern Cape. Given its pressing
need for water, the Hessequa Municipality has expressed its interest in implementing a pilot
OSMOSUN®plant on the critical coastal area ofWitsand. TheOSMOSUN is a desalination system
whichispoweredbysolarenergy.TheOSMOSUNisaproductofMascaraRenewableWater1.
Mascara RenewableWater have applied for a grant from the French treasury (FASEP innovation
verte).Thegrantwouldfundupto50%ofthepilotproject.Thishasbeendonewiththesupportof
the French Embassy in Pretoria. Approval in principle of the grantwas given on September 15th.
Hessequa Municipality has subsequently applied for the financing of the balance against the
WesternCapeDroughtRelieffundingwhichwassubsequentlyapproved.
TheprojectstakeholdersareshownintheTablebelow:
Name RoleHessequaMunicipality ClientTurnkeyWaterSolutions SolutionProviderAlternativeServicesTechnologies CoordinationoftechnicalspecialistsMascara OSMOSUNdesignersWMLCoast CivilEngineeringConsultantCapeEA-Practitioners EnvironmentalConsultantAnchorEnvironmental EffluentDispersionModelling
WMLCoast (Pty)Ltdwasappointedtodesignthecivil infrastructurecomponents required for the
project.AlternativeServicesTechnologies(Pty)LtdwasappointedtoassistTurnkeyWaterSolutions
withthecoordinationofinputfromthevarioustechnicalspecislists.
This report provides the detail of themethodology for the implemetation of the project. The so-
called Method Statement Report provides more detail on the individual tasks, roles and
responsibilities of the various roleplayers and lists key risks and the associated mitigatory /
managementactionsrequiredtoreducetherisks.
1http://mascara-nt.fr/en/about/#company
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 4
Thereportshouldbereadtogetherwiththedesignreport2butcanbeseenasastandalonereport.
It also forms part of the main Environmental Management Programme (EMPr) and the Method
StatementswillbeadoptedaspartoftheapprovaloftheEMPr.
NormallythecontractorshallprovideMethodStatementsforapprovalbytheEnvironmentalControl
Officer (ECO)and theResidentEngineer (RE)prior towork commencingonaspectsof theproject
deemedoridentifiedtobeofgreaterrisktotheenvironmentand/orwhichmaynotbecoveredin
sufficientdetail intheEnvironmentalManagementProgramme(EMPr),whencalledupontodoso
by the RE or ECO. In this instance the project applicant provided sufficient detail in theMethod
Statementstoensurethattheenvironmentalregulatoryauthoritycanmakeaninformeddecisionto
adoptitaspartoftheEMPr.
ItiscrucialthatcarefulthoughtneedstobegiventothedraftingoftheseMethodStatementsinthe
absence of an Environmental Impact Assessment study, which will under normal circumstances
assess all the potential negative environmental impacts during the construction phase of the
proposed development and provide mitigatory measures to minimise the impacts on the
surroundingenvironment.
Onceappointed,thecontractorwillbeheldaccountabletoundertaketheconstructionactivitiesin
accordancewith the pre-approvedmethod statements to ensure duty of care and accountability
duringthemostsensitivephaseoftheproject.
A Method Statement is a “live document” in that modifications are negotiated between the
Contractor and the ECO or project management team, as circumstances unfold. All Method
Statementswill formpartof theEMPrdocumentationandaresubject toall termsandconditions
containedwithintheEMPr.
Note that aMethod Statement is a ‘starting point’ for understanding the nature of the intended
actions to be carried out and allows all parties to review and understand the procedures to be
followedinordertominimiseriskofharmtotheenvironment.
Changesto,andadaptationsof,MethodStatementscanbeimplementedwiththepriorconsentof
allparties.
2DesignReport:OSMOSUN100DesalinationPlant,Witsand,SouthAfrica.WMLCoast(Pty)Ltd.July2018.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 5
AMethodStatementdescribesthescopeoftheintendedworkinastep-by-stepdescriptioninorder
fortheECOandtheREtounderstandtheContractor’sintentions.Thiswillenablethemtoassistin
devisinganymitigationmeasures,whichwouldminimiseenvironmentalimpactduringthesetasks.
For each instance where it is requested that aMethod Statement is to be provided, the format
shouldclearlyindicatethefollowing:
o What-abriefdescriptionoftheworktobeundertaken;
o How-adetaileddescriptionoftheprocessofwork,methodsandmaterials;
o Where-adescription/sketchmapofthelocalityofwork(ifapplicable);
o When - the sequencing of actions with due commencement dates and completion date
estimates;and,
o Who – The person responsible for undertaking the works described in the Method
Statement.
TheabovementionedformatwasusedtopreparethedifferentMethodStatementsincludedinthisreport.
2 Site Description
Thedesalinationplantwill be constructedon a site located to thenorthof the townofWitsand,
Western Cape South Africa. Existing infrastructure at the designated site includes a borehole
pumpingstation(34°24'4.35"S,20°47'16.34"E)whichsupplieswatertothetownreservoiradistance
ofabout2.3kmaway.ThisreservoiristhemainwatersupplyreservoirforWitsand/PortBeaufort.
Theexistinginfrastructureconsistsofthefollowing:
• Aboreholewithboreholepump,approximatedepth200m.Historicyield in theorderof8
l/s,currentyieldintheorderof2l/swithhighManganesecontent
• Generatorandvalveroomfortheboreholepump.
• Associatedpiping (visiblepipingmaterial is steel)–pipediameter in theorderof110mm
outsidediameterOD.
• Theboreholepumpstationandpipelinehaveexistingservitudes.Theboreholeissurrounded
by2farmportionswithdifferentownersascanbeseenonthelocalityplans.
TheexistingboreholesiteissituatedonahillnexttotheBreedeRiverEstuaryatameanheightof+
35mMSL.Thehillslopessteeplytotheriver/estuary.Theriverbankisovergrownwith indigenous
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 6
vegetation.Thesitewascomprehensivelysurveyedandthecontourlevels(tomMSL)areshownon
drawingsinthedesignreport.
Portionsofthenaturalterrainareshowninthefollowingimages:
Figure1:Typicalappearanceofcurrentnaturalrockshelf(Bokkeveldshale)attheestuary/river’sedge.
Figure2.Viewofexistingpumpingstationinfrastructure–lookingnorth.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 7
Figure3:Typicalvegetationatlowersectionofsteepriverbank.
3 Some relevant site characteristics
3.1 Tide levels in the ocean at Witsand
Table1:CharacteristictidallevelsatWitsand(SANHO)
Witsand(mCD) Witsand(+mMSL)Levellingdatumcorrection -0.8605 0LAT(LowestAstronomicalTide) 0 -0.8605MLWS(MeanLowWaterSpring) 0.265 -0.5955MLWN(MeanLowWaterNeaps) 0.815 -0.0455ML(MeanLevel) 1.095 0.2345MHWN(MeanHighWaterNeaps) 1.375 0.5145MHWS(MeanHighWaterSprings) 1.94 1.0795HAT(HighestAstronomicalTide) 2.255 1.3945HATIncludingpotentialsealevelrise(+0.5mby2050) 2.755 1.8945HATIncludingpotentialsealevelrise(+1.0mby2100) 3.255 2.39451:100yearrverfloodlevel 6.14 7.0
Notethattheinformationonthesealevelrise(SLR)valuesaretakenfrom(2018)reportsby
the Eden DistrictMunicipality on coastalmanagement lines. The site is located along an
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 8
estuary with a normally wide open mouth, thus the tidal levels (and future SLR) are
relevant.Sincethesiteis locatedwithintheestuary,adefaulthazardlevelof+5mMSLis
relevant.However,sincethe1:50yrand1:100yrfloodlineshavebeendetermined,these
areincluded.
3.2 River Flooding
TheBreedeRiverexperiencesperiodical flooding.The intakeandoutfall infrastructureare
designedtowithstandfloodingevents.The50-yearand100-yearfloodlinesoftheriverin
theinterestareaareshownontheFigure4below:
Figure4:Predictedfuture50-yearand100-yearreturnintervalfloodlevels(BreedeRiverFloodlineStudy).
3.3 Geohydrology
The northern riverbank at the location of the proposed river intake consists of exposed
“BokkeveldShale”rock(seeFigure5).
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 9
Figure5:Verticalsectionalsketchofaquiferandgroundwaterrelationship–lookingupstream(Steenekamp,2018).
4 Short summary of the OSMOSUN 100 process
The OSMOSUN 100 is powered by solar energy, however, the power supply to the
desalination plant can be augmented by the main power grid and/or an existing diesel
generator on site. The potablewater permeate output of theOSMOSUN100 plant using
solar power only is in the order of 100 m3/day during sunlight times. If it is operated
continuously (day andnight) with the addition of grid power the plant can produce 300
m3/day.
Rawwaterfromtheestuaryisabstractedatamaximumrateof40m3/h.Theintakerateis
scaleable and is a function of the energy available. The intake water is pumped either
directlythroughasandfilterandintotheOSMOSUN100(1pump,nostorage)orpumped
from the river into a reservoir located adjacent to theOSMOSUN 100 and then pumped
throughthesandfilterfromthereservoir(2pumps).
The generated brine (effluent) will be dispersed into the river via an environmentally
compliantdiffuseroutlet.Ifpre-treatmentofthebrineisrequiredabrinestoragetankwill
beerectedadjacenttotheOSMOSUN100plant.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 10
The design of the intake works, the supply pipline, the infrastructure for the Reverse
Osmosis (RO) Plant and solar farm, the permeate delivery component as well as the
effluent management system and discharge pipeline and outfalll works are described in
design report: Preliminary Design Report: OSMOSUN 100 Desalination Plant, Witsand,
SouthAfrica.WMLCoast(Pty)Ltd.July2018.
Thedispersalof thebrine fromtheplantatWitsand isdescribed in thespecialist report:.
LairdMC,WrightAGandClarkBM.2018.NearfieldModellingandAssessmentofImpacts
for the Proposed Reverse Osmosis Plant at the Breede River Estuary, South Africa.
SpecialistReportno.1799/3preparedbyAnchorEnvironmentalConsultants(Pty)Ltdfor
TurnkeyWaterSolutions.Pp71.
Permeatefromtheplantwillbestoredinareservoironsiteandandthenpumpedtothe
municipalreservoir.
The process diagrammes and technical specifications of the OSMOSUN 100 plant are
providedinthedesignreport.
5 Site layout overview
Shown below in figure 6 are the key components for which method statements are
prepared.
Figure6:Proposedsitelayout
Followingthelogicalprocessflow(fromtherawwaterintakeworks,throughtheROplant
to the effluent outfall works), the key to Figure 6 and theMethod Statement tables are
providedinthetablebelow.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 12
Refnumber
Key(Fgure6)
Shortdescription MethodStatementtablenumber
RelevantTechnicalDrawings3
1 IW IntakeWorksonestuarybank.Threeoptionsarepresented
MS1.1;MS1.2;MS1.3 180423-31to-33180423-34180423-35to-38
2 IP Supplypipeline(steelatthesteepslope)
MS2
3 P BuriedHDPEpiplines MS3 4 RO Buildingsand
infrastrustuctureforROplant
MS4 180423-21Ato180423-27A
5 SF SolarFarmandFence MS5 180423-41to--42180423-51A
6 OP Effluentpipeline(Steeldownsteepslope)
MS6
7 OW Outletworksalongestuarybank
MS7
8 BOT Botanicalaspects MS8 -
6 Method Statements
Rawwaterintakeworks:functionalrequirements
Thegeneralrequirementsoftheintakesystemarelistedbelow.
• Provideintakeflowofriverwateratamaximumrateof40m3/h;
• Environmentaldesigncriteriafortheintake,EPAguidelines.Intakevelocity<=
0.15m/s;Smallgridspacingmaynecessitateregularcleaning/maintenance;
• Waterintakeat–1.5mMSLtoallowforrequiredsubmergenceatalltidalwater
levels;
• Intakeassemblymadeofgalvanisedsteeland/orstainlesssteel;
• Pipelinefromintakeassemblyacrosstherock-shelfontheriverbankencasedin
concreteasprotectionduringriverfloods;
• Intakepipelinewillhavenovalvestoreducepossiblemaintenanceimplications;
• Intakeshouldallowforpipelinecleaningusinga‘pigging’technique;
3PreliminaryDesignReport:OSMOSUN100DesalinationPlant,Witsand,SouthAfrica.WMLCoast(Pty)Ltd.July2018.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 13
• Intakeassemblymodularallowingforreplacingandmaintenanceofdiscrete
elementsasrequired;
• Intaketooperateinvaryingriverwaterlevels–notedesalinationplantwilllikelynot
beoperatedinextremefloodsashighsiltcontentofintakewaterwillclogfilter
systemsexcessively.Usagetobedeterminedbyplantoperators.
Threeintakeconfigurationshavebeendeveloped.Eachoneisconsideredtobefeasibleand
achievable.Thechosenoptionwillbefinalisedbasedoncostsandpercievedrobustnessand
easeofmaintenance:
Option1:RiverbankPumphousewithSelf-PrimingPump
Option2:FloatingPontoonIntake
Option3:RiverbankPumpstationwithSubmersiblePump
Method Statements (MS 1.1 toMS 1.3) are provided for each of the three intakeworks
options.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 14
6.1 Method statement 1.1: Intake Works – Option 1
TABLEMS1.1INTAKEWORKSONESTUARYBANK:
OPTION1:PUMPHOUSEANDSELF-PRIMINGPUMP
1. SPECIFIC LOCATION: Refer to the layout on Figure 6, specifically component IW, theIntakeWorks.2.DESCRIPTION:
Thesealedconcretepumphouse (chamber) isbuiltonaconcrete footingboltedonto thenaturalrock.Aself-primingelectricalpumpisinstalledinsidethechamber.Thestructureissealedfromoutside.Accesstostructureisviaasteelhatchwith2doors.Largedoorforthepumpinstallationandmaintenanceandregularhatchforpersonnelaccess.Thekeycharecteristicsofthedesignareshownintheabovefigure.Thepipealongtherock-shelfontheriverbankwillbeencasedinconcreteasshowninthefigurebelow.Theconcreteencasingisanchoredtotherockshelf.Theconcreteencasingisforprotectionagainstfloodevents.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 15
At the end of the intake pipelinewill be a fabricatedwedge-wire intake screenwhich isbolted to the intake pipeline. The intake screen is sized to ensure compliance withenvironmentalguidelines.Theintakeisshownschematicallybelow.
Forthedrypumpinstallationinthechamber,aself-primingpumpisproposed.Self-primingpumpsprimethesuctionlineeachtimetheyarestarted.Self-primingpumpsaregenerallymore reliable thanother (generallyaftermarket) self-primingsystems.Self-primingpumpsaregenerally lessefficient than theequivalentnon-primingpump.A self-primingpump ispreferred for a dry pump installation as there is no requirement for check valves whichcould pose issues in a saline river intake environment with intermittent intake flowrequirementanddailydown-time.Thepumpwillbeconstructedfromcast-ironwithananodeattachedtoalleviatecorrosion.The anodewill be replaced as required. The dry installation of the pump allows for easymaintenanceofthepumpwhenrequired.Theintakesystemisdesignedtofacilitatepipelinepigging(cleaning).Thepumpisinstalledofflineofthemainpipelinealignment,therebyallowingofabypassofthepumphouseviaappropriatevalveactuation.Theendoftheintakeassemblyhasablankflangewhichcanberemovedwhenpiggingthepipeline.Thepigwillbeinstalledintothepipelinejustupstreamoftheintakewaterstoragetank.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 16
The intake assembly is modular and segments can be unbolted to be cleaned and/orreplaced.Moredetailofthedesignisshowninthedesignreport.3.SPECIFICACTIONS:Toconstructthepumphouseasmallsegmentoftheclifffacewillbeexcavatedtoprovidea“cove” inwhich to build the pumphouse, thereby providing additional protection againstflood damage. The intake assembly will be transported to the site via personnel or anexcavator.Anexcavatorwill hold theassembly in-placeduringboltingof theassembly tothepipesegmentprotrudingfromtheconcretepipelineencasing.Developmentfootprint:
Pipelineandintake:14mx0.5m=7m2
Pumpstation:2.9mx3.5m=10.15m2
Requiredexcavationvolume:
Pumpstationcove≈1.5mx3mx3.5mx0.5m=7.8m3
4.TIMING:Aspertheconstructionschedule.
5.SUPERVISORYPARTY:
• Applicant:HessequaLocalAuthority–MunicipalTechnicalDirector
• ManagingAgent/ResidentEngineer–TBC
• ProjectManager–TBC• EnvironmentalControlOfficer–TBC• Marineecologist–Anchor
Environmental• Commercialdivingsupervisor(ifdivers
areused)• SafetyOfficer
6.STAFF,PLANTANDEQUIPMENTTOBEUSED:All staffmustbeappropriatelyqualifiedandworkunder therelevant levelof supervision.EnsuringthisistheECOandcontract’smanager’sresponsibility.Allcontractingstaffshouldhavebeeninductedpriortocommencingwithanyworksonsite.AcopyoftheEMPrshouldbeavailableintheSiteOffice.Equipment typically associatedwith the placing of equipment and structures underwater
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 17
will be used (if divers are needed).Methods and standards according to the appropriateSABSstandardstobeadheredto.Equipmenttypicallyassociatedwithexcavationandsitepreparationwillbeused.MethodsandstandardsaccordingtotheappropriateSABSstandardstobeadheredto.Access forconstructionvehicles tothesitewillbealongademarcatedpathwayalongtherockshelfillustratedinFigure1.Deepgulleysorholescanbebridgedbytemporarymeans.NarrowconcretestrippathwayscanbecastinselectedareasinconsultationwiththeECO.Thesewillremaininplacetoassistaccessduringmaintenanceoremergencies.7.RISKS:Working underwater is a specialised job(whenneeded).Drillingintotherockfaceandepoxygroutingthe required pipe brackets i.t.o the anchorholes will disperse rock fragments into thewater column. This is a limited and localimpact.
The excavation of the ‘cove’ for thepumphouse will result in an excess ofmaterialbeingproduced.Theriskisthatthismaterialwill landup in theestuary therebysmotheringthemarineorganismsorcausinganartificialunderwaterhazard.Softer material that may wash off theconstruction site should be prevented fromdispersingwithin thewater column beyondtheimmediateconstructionfootprint.
8.PREVENTATIVEMITIGATORYACTION:Only qualified commercial divers and asupervisorshouldbeused(ifrequired).Construction materials should be non-toxicasfaraspossible.Concreteisacceptable.No blasting is foreseen. An excavator,possibly with a ‘hydraulic pecker’configuration will be used (see example inTableMS1.3below).Material excavated from the ‘cove’ shouldbe re-used for backfilling between thechamber and the excavation if possible. AllexcessmaterialshouldberemovedfromthesiteanddisposedofatanappropriatesiteasspecifiedintheEMPr.To minimise any possible negativeenvironmentalimpact,thecontractorhastoensure that concrete is not mixed in theintertidal area and that cement bags areimmediately placed in refuse bins whichneedtobeavailableonsite.A floating geofabric curtain fixed to thebottom with sandbags to be installed inradius of 5 m in the estuary around theconstructionsiteso-astolimitthedespersalof any fine material beyond the site andthusnotpollutingthewaterbody.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 18
6.2 Method statement 1.2: Intake Works – Option 2
TABLEMS1.2INTAKEWORKSONESTUARYBANK:
OPTION2:SUBMERSIBLEPUMPONHINGEDPONTOON
1. SPECIFIC LOCATION: Refer to the layout on Figure 6, specifically component IW, theIntakeWorks.2.DESCRIPTION:
The concept makes use of a submersible (borehole-type) pump installed on a floatingpontoonthatishingedofftherock-shelf.Somekeycharacteristicsare:
• Apipepontoon(diameterintheorderof914mmOD)withpipesleeve(diameterintheorderof610mmOD)formountingofsubmersible(borehole-type)pump;
• Pontoonishingedtoallowmovementwithvaryingwaterlevels;• Flexiblepipingisusedatthehingelocation;• Hingesarecastintoconcreteanchorsontherockshelf;• PipingtoOSMOSUN100plantaswithOption1–steelpipecastintoconcretewhich
isanchoredtorockshelf;• Entirepontoonunitisprefabricatedandassembledonsite,placedintoposition
usinganexcavatororsimilarliftingequipment;• Structurewillbedesignedtohandlefloodevents–possiblyalsoincorporate
anchoringsystemtostrapthepontoonifalargefloodisexpected;
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 19
Thekeycharacteristicsofthedesignareshowninthefigureabove.AsinOption1,thepipealongtherock-shelfontheriverbankwillbeencasedinconcrete.Thepipesleeveintowhichthepumpisdroppedwillhaveanintakescreen(notshownondrawing)tolimitingressofmarinelifeordebrisandtocomplywithenvironmentalguidelines.Allowanceformechanismstoassistinremovingthepumpandcleaningtheintakescreen.Atthebaseoftheabstractionpontoonwillbeafabricatedwedge-wireintakescreenwhichis bolted to the pontoon. The intake screen is sized to ensure compliance withenvironmentalguidelines.AsubmersibleboreholepumpwillbehousedinsidetheabstractionpontoonasindicatedintheFigures.Thepumpwillbeconstructedfromcorrosionresistantmaterial.Thepumpwillweighintheorderof80kg.Thepumpiscompletelysubmergedinwaterduringoperation.For maintenance the intake screen will be removed. After removal the screen can bereplacedwith a spare clean intake screen. Thepump canbe liftedout of the abstractionpontoonformaintenance.Moredetailofthedesignisshowninthedesignreport.3.SPECIFICACTIONS:AsinOption1,thepipealongtherock-shelfontheriverbankwillbeencasedinconcreteasshown in the figure below. The concrete encasing is anchored to the rock shelf. Theconcreteencasingisforprotectionagainstfloodevents.
Prior to installationof the floatingpontoon intake, twoconcreteanchors for thepontoonhingepointswillbeconstructedontherockshelf.ThedetailisshownonDrawing180423-34.Theconcreteanchorswillbecastdirectlyinpositionandfixedtotherockbymeansofnon-toxicchemicalanchors.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 20
The entire pontoon assembly is pre-fabricated in aworkshop. Themodular elements arethentruckedtosite.Thepontoonelementswillberemovedfromthetruckandplaced inthewaterbymeansofanexcavatoranda lifting slingarrangementora small crane.Theassembledfloatingpontoonwillbemovedtotheinstallationlocation.Thepontoonwillbecontrolledwithpersonnelandropesfromtheriverbank.Developmentfootprint:
Pipeline:12mx0.5m=6m2
Pontoonanchors:2m2
Floatingpontoon:4mx3m=12m2
Requiredexcavationvolume:zero4.TIMING:Aspertheconstructionschedule.
5.SUPERVISORYPARTY:
• Applicant:HessequaLocalAuthority–MunicipalTechnicalDirector
• ManagingAgent/ResidentEngineer–TBC
• ProjectManager–TBC• EnvironmentalControlOfficer–TBC• SafetyOfficer
6.STAFF,PLANTANDEQUIPMENTTOBEUSED:All staffmust be appropriately qualified. All contracting staff should have been inductedpriortocommencingwithanyworksonsite.AcopyoftheEMPrshouldbeavailableintheSiteOffice.Equipmenttypicallyassociatedwiththeliftingandplacingofequipmentandstructureswillbeused.Forexampleatrackedexcavatorcanbeusedtoliftandholdthepontoonstructureinpositiontoenable thehingepins tobesecured.Once floating thepipesandelectricitysupply can be connected. Methods and standards according to the appropriate SABSstandardstobeadheredto.Equipment typically associated with drilling the rock anchors and casting the concreteencasement over the steel pipe will be used. Methods and standards according to theappropriateSABSstandardstobeadheredto.Access forconstructionvehicles tothesitewillbealongademarcatedpathwayalongtherockshelfillustratedinFigure1.Deepgulleysorholescanbebridgedbytemporarymeans.NarrowconcretestrippathwayscanbecastinselectedareasinconsultationwiththeECO.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 21
Thesewillremaininplacetoassistaccessduringmaintenanceoremergencies.7.RISKS:Drillingintotherockfaceandepoxygroutingthe concrete encasement units into theanchor holes could disperse rock fragmentsintothewatercolumn.Theimpactislimitedandlocal.Softer material, such as cement water thatmaywashofftheconstructionsiteshouldbeprevented fromdispersingwithin thewatercolumnbeyond the immediate constructionfootprint.Lifting and placing the pontoon structureclose to water is a potential health andsafetyhazard.
8.PREVENTATIVEMITIGATORYACTION:Ageofabric(e.gBidimTM)wrappedaroundatemporarysandbag‘berm’ontherock-shelfenclosing the construction site will preventcementwaterandsuspendedmaterial fromwashingintotheestuary.A floating geofabric curtain (e.g BidimTM)fixedtofloatsatthewatersurfaceandfixedtothebottomwithsandbagstobeinstalledin radius of 5m in the estuary around theconstructionsiteso-astolimitthedespersalofanyfinematerialbeyondthesite.To minimise any possible negativeenvironmentalimpact,thecontractorhastoensure that concrete is not mixed in theintertidal area and that cement bags areimmediately placed in refuse bins whichneedtobeavailableonsite.All labourers involved with the pontoonliftingandinstallationprocessshouldbeableto swim and should wear life jackets at alltimes. All appropriate Personal ProtectiveEquipment (PPE) and Personal ProtectiveClothing(PPC)shouldbeusedatalltimes.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 22
6.3 Method statement 1.3: Intake Works – Option 3
TABLEMS1.3INTAKEWORKSONESTUARYBANK:OPTION3:RIVERBANKPUMPSTATION
WITHSUBMERSIBLEPUMPONRAILTRACK1. SPECIFIC LOCATION: Refer to the layout on Figure 6, specifically component IW, theIntakeworks.2.DESCRIPTION:
Somekeycharacteristicsofthisoptionareshowninthefigureaboveandinclude:
• Boreholepumpismountedtotrolleytypearrangementtoallowforremoval–incorporatedliftingpointstowhichablockandtackleormanualwinchcanbeattached;
• Thetrolleysliderhasloosetolerancestofacilitateremoval;• PipingtotheOSMOSUN100plantissimilartoOptions1&2–steelpipecastinto
concretewhichisanchoredtotherockshelf;• Steelchannelswillbeusedastherailsystemfortheremovalofthepumpandits
screen(so-calledtrolleyassembly);• Flexiblepipingwillbeusedatthebendtoallowforeasierremovalofthesystemfor
maintenance.The trolley has wheels to allow for extraction of the trolley and pump assembly. Formaintenanceor in caseof an imminent large flood, theassembly canbe removedat lowtidewithawinchingarrangement(liftinghooksareprovided).Theintakescreencanthenbecleaned manually. The material removed from the screen should be discarded in anenvironmentally appropriatemanner. For pumpmaintenance the pump can be detachedfromthetrolleyviaaboltingarrangement.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 23
Moredetailofthedesignisshowninthedesignreport.3.SPECIFICACTIONS:AsinOption1,thepipealongtherock-shelfontheriverbankwillbeencasedinconcreteasshown in the figure below. The concrete encasing is anchored to the rock shelf. Theconcreteencasingisforprotectionagainstfloodevents.
Anexcavatorwithhydraulicpeckerwillbeusedtocreateatrenchintherockfaceatlowspringtideoveranumberofdays;Theintakeassemblywillbeplacedintothetrench.Anexampleofthetrenchingequipmentrequiredcanbeseeninthefigurebelow.
Hydraulicpeckerforrockexcavation(example).
Theprefabricatedgalvanisedsteelrailassembly(Drawing180423-37inthedesignreport)willbebroughttositeonatruckandplacedintopositionusinganexcavatoradaptedforlifting(seeexamplebelow).Labourerswilluseropestoguidetheassemblyintopositionin
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 24
theexcavatedtrenchandontherockshelf.Theassemblywillbeboltedintotherocksurfacemakinguseofnon-toxicchemicalanchors.Thisworkwillbedonebycommercialdivers.
Exampleofaliftingarrangementonanexcavator.
Developmentfootprint:
Pipeline:8mx0.75m=6m2
Trolleyassembly:13mx1.1m=14.3m2Requiredexcavationvolume:
Rocktrenchexcavation:13mx1.1mx0.6m=7.9m3A3mwideblanket/netsecuredbysandbagsandplacedontherockslopeandestuarybottomforadistanceof3mpasttheendoftheexcavatedtrenchpriortocommencingtheuseof thehydraulicpecker. This is tocollectandremovethedebris.A floatinggeofabriccurtainfixedtothebottomwithsandbagstobeinstalledinaradiusof5mintheestuaryaround theconstruction site so-as to limit thedespersalofany finematerial beyond thesite.4.TIMING:Aspertheconstructionschedule.
5.SUPERVISORYPARTY:
• Applicant:HessequaLocalAuthority–MunicipalTechnicalDirector
• ManagingAgent/ResidentEngineer–TBC
• ProjectManager–TBC• EnvironmentalControlOfficer–TBC• Marineecologist–Anchor
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 25
Environmental• SafetyOfficer
6.STAFF,PLANTANDEQUIPMENTTOBEUSED:All staff must be appropriately qualified and work under the supervision of a qualifiedcommercial diver. Ensuring this is the ECO and contract’s manager’s responsibility. Allcontractingstaffshouldhavebeeninductedpriortocommencingwithanyworksonsite.AcopyoftheEMPrshouldbeavailableintheSiteOffice.Equipmenttypicallyassociatedwiththeliftingandplacingofequipmentandstructuresneartoandunderwaterwillbeused.Forexampleatrackedexcavatorcanbeusedtoliftandholdtherailassemblystructureinpositiontoenabletheboltstobesecured.MethodsandstandardsaccordingtotheappropriateSABSstandardstobeadheredto.Access forconstructionvehicles tothesitewillbealongademarcatedpathwayalongtherockshelfillustratedinFigure1.Deepgulleysorholescanbebridgedbytemporarymeans.NarrowconcretestrippathwayscanbecastinselectedareasinconsultationwiththeECO.Thesewillremaininplacetoassistaccessduringmaintenanceoremergencies.7.RISKS:Drillingintotherockfaceandepoxygroutingthe concrete encasement units into theanchor holes could disperse rock fragmentsintothewatercolumn.Theimpactislimitedandlocal.Softer material, such as cement water thatmaywashofftheconstructionsiteshouldbeprevented fromdispersingwithin thewatercolumnbeyond the immediate constructionfootprint.Lifting and placing the steel rail structureinto the underwater trench will requirelabourers to be positioned close to water.Thisisapotentialhazard.
8.PREVENTATIVEMITIGATORYACTION:Ageofabric(e.gBidimTM)wrappedaroundatemporarysandbag‘berm’ontherock-shelfenclosing the construction site will preventcementwaterandsuspendedmaterial fromwashingintotheestuary.A floating geofabric curtain (e.g BidimTM)fixedtofloatsatthewatersurfaceandfixedtothebottomwithsandbagstobeinstalledin radius of 5m in the estuary around theconstructionsiteso-astolimitthedespersalofanyfinematerialbeyondthesite.To minimise any possible negativeenvironmentalimpact,thecontractorhastoensure that concrete is not mixed in theintertidal area and that cement bags areimmediately placed in refuse bins whichneedtobeavailableonsite.All labourers involved with the close-to-wateractivitiesneedtobeabletoswimandshouldbeissuedwithlife jacketsandsafetyharnesses during the lifting and installation
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 26
process.AllPPEandPPCshouldbeadheredto.
6.4 Method statement 2: Steel intake pipeline across steep slope
TABLEMS2 INSTALLATIONOFTHESTEELINTAKESUPPLYPIPELINEATTHESTEEPSLOPE
1.SPECIFICLOCATION:RefertothelayoutonFigure6,specificallycomponentIP,theIntakePipeline.2.DESCRIPTION:Theidentifiedpipelineroutegoesalongasteepslopeintheareafromtheintakeworksattheestuaryup to the relatively flat slopedirectly to thewestof theROplant site. In thisareathegalvanisedsteelpipe(114mmOD)willbeplacedalongaseriesofraisedbracketsfixed to the natural ground or rock. The pipeline alignments can be seen on the layoutdrawing(IndicatedasIPonFigure6).3.SPECIFICACTIONS:Thesteelintakepipelinethatcrossesthesteepriverbankismountedtoaholdingbracketona raised pedestalwhich is driven into the natural ground / rock along the pipeline routefromtheintakeworksatthewater’sedgeuptotheflatterslopeatthetopofthehillwherethepipematerialchangestoHigh-densitypolyethylene(HDPE)andisburiedasdescribedinTableMS3.
Thepipelinealignmentwillbeclearedofvegetationtoallowtheinstallationofthepipeline.Asthepipelinerunsonthesurfacetheamountofvegetationdisturbancewillbeminimal.The pipeline pedestals will be driven into the existing ground as required. Where thesubstrateishardrock,arockdrillwillbeusedandthemetalsupportsgroutedinusinganappropriate adhesive suchas a cement/sandmixor epoxy.Alternatively a small concreteplinthwillbeconstructedtosupportthepipeline.Thesteelpipelinewillbesecuredtothepedestalbyabracket.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 27
Developmentfootprint:80mx0.3m=24m2Requiredexcavationvolume: zero.Material removedby the rockdrill,wherenecessary, isminimal.4.TIMING:AspertheconstructionscheduleandpostActivityAintheBotanicalMethodStatement.
5.SUPERVISORYPARTY:
• Applicant: Hessequa Local Authority –MunicipalTechnicalDirector
• Managing Agent / Resident Engineer –TBC
• ProjectManager–TBC• EnvironmentalControlOfficer–TBC• Botanist–TBC
6.STAFF,PLANTANDEQUIPMENTTOBEUSED:All staffmust be appropriately qualified andwork under the supervision of the ECO andcontract’smanager.All contracting staff shouldhavebeen inductedprior to commencingwithanyworksonsite.AcopyoftheEMPrshouldbeavailableintheSiteOffice.Equipmenttypicallyassociatedwiththeclearingofanareaalongthepipelinerouteandtheinstallation of the pipelines will be used. Methods and standards according to theappropriateSABSstandardstobeadheredto.7.RISKS:Destructionordamageofimportantand/orendangered vegatation beyond the directfootprintoftheconstructionactivities.
8.PREVENTATIVEMITIGATORYACTION:Contruction footprint area, eg the pipelineroute and labour access, to be physicallydemarcated and activities strictly restrictedtowithinthearearequiredforconstruction.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 28
6.5 Method statement 3: Buried HDPE supply and effluent pipelines
TABLEMS3 INSTALLATIONOFTHEBURIEDHDPESUPPLYANDEFFLUENTPIPELINES
1.SPECIFICLOCATION:RefertothelayoutonFigure6,specificallycomponentP,theburiedpipelines.2.DESCRIPTION:Theidentifiedpipelineroutegoesalongarelativelyflatslopeintheareaimmediatelytothewestof theROPlantprecint. In thisareaboththeHDPE intakeandeffluentpipelinesareburied in the same trench. The pipeline alignments can be seen on the layout drawing(IndicatedasPonFigure6).TheintakepipelinehasanODof110mm,andthatofthebrineeffluenthasa100mmOD3.SPECIFICACTIONS:Atrenchwillbeexcavatedusingamechanicalexcavatorandthepipelinesburiedalongsidewithinthetrench.Typicaltrenchdetailsareshownonthefigurebelow.Thespecificdesigndetailsareprovidedinthedesignreport.
Developmentfootprint:Buriedpipelinesegment:120mx0.3m=36m2forasinglepipeand60m2fortheareawherethetwopipelinesareplacedsidebysideinasingletrench.Avolumeofbeddingsand(approximately5m3)willbebroughtinforthepipelines.Requiredexcavationvolume:Thetotalvolumeofsoiltobeexcavatedforthetrenchisintheorderof18m3to30m3.Nettexcavationvolumeiszeroasexcavatedsoilwillbeplacedbackintothetrench.Storm water management and rehabilitation of the cleared area will be done to thespecificationsprovidedbytheBotanist.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 29
4.TIMING:AspertheconstructionscheduleandpostActivityAintheBotanicalMethodStatement.
5.SUPERVISORYPARTY:
• Applicant: Hessequa Local Authority –MunicipalTechnicalDirector
• Managing Agent / Resident Engineer –TBC
• ProjectManager–TBC• EnvironmentalControlOfficer–TBC• Botanist–TBC
6.STAFF,PLANTANDEQUIPMENTTOBEUSED:All staffmust be appropriately qualified andwork under the supervision of the ECO andcontract’smanager.All contracting staff shouldhavebeen inductedprior to commencingwithanyworksonsite.AcopyoftheEMPrshouldbeavailableintheSiteOffice.Equipment typically associated with the digging of a trench and the installation of thepipelineswillbeused.MethodsandstandardsaccordingtotheappropriateSABSstandardstobeadheredto.7.RISKS:Destructionordamageof importantand/or endangered vegatation beyond thedirect footprint of the constructionactivities.Soil erosion due to stormwater and / orwind within or adjacent to the areas ofconstruction.
8.PREVENTATIVEMITIGATORYACTION:Contruction footprint area, eg the pipelineroutesand labourand/orvehicleaccess, tobe physically demarcated and activitiesstrictlyrestrictedtowithinthearearequiredforconstruction.Storm water and wind erosion controlmanagement, eg contouring and speedyrehabilitationofdisturbedareas.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 30
6.6 Method statement 4: Buildings and infrastructure for the RO plant
TABLEMS4 BUILDINGSANDINFRASTRUCTUREFORROPLANT
1. SPECIFIC LOCATION: Refer to the layout on Figure 6, specifically component RO, thereverseosmosisplant.2.DESCRIPTION:A.DesalinationbuildingThe construction of a building in which the desalination technologies is required. Thecharacteristicsofthebuildingareasfollows:
• BrickbuildingwithNUTECtyperoof• Overalldimension6mx14m(84m2)• Accesstobuildingvialargerollerdoorandsecondarypersonaldoor(fireexit)
Thebuildingaccommodatesthefollowing:
• Intakewaterpre-treatment(sandfilter)• OSMOSUN100desalinationsystem• Watertreatment(remineralisation)• Storagearea• Electricalcontrolsystems
Thespecificdesigndetailsandtherelevantdrawingsareprovidedinthedesignreport.B.StoragetanksUp to three storage tankswill be installedon concretebases adjacent to theOSMOSUN.PlastictankssuchastheRototankorJoJotankareproposed.
• Intake seawater storage, 40m3 is required if Option 1 for the raw waterintakeworksisconstructed.
• Permeatestoragetank,10m3Thespecificationsofthetanksareprovidedinthedesignreport.C:ACCESSROADAccesstothenewROplantandSolarFarmwillbeviatheexistingroadinfrastructure.3.SPECIFICACTIONS:A: Sitewill be cleared and grubbed. Thereafter building foundations dug. Building to be
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 31
constructedwithbricksandmortar.Aftercompletionofwallsrooftrusseswillbeerectedonthesupportwallsandtherooftilesplaced.Thetechnicaldesignspecificationareprovidedinthe design report. All activities associated with the installation of the building andinfrastructureshouldadheretoSABSspecifiedconstructionmethodsandstandards.Developmentfootprint:Overalldimension6mx14m(84m2)Excavationvolume:Foundationexcavationvolume:10m3B: The plastic tanks are pre-fabricated andwill be delivered to site by truck. The plastictankswillbeplacedonconcreteplinthstructures(bases).Theplinthsizewillvarydependingonthetankdiameterandisspecifiedinthedesignreport.Theerectionsitewillbecleanedand levelledprior tocastingofconcreteadhering toSABSspecifiedconstructionmethodsandstandards.Developmentfootprint:
Permeatetank:2.5mx2.5m=6.25m2Intakestoragetank(optional):5mx5m=25m2
Requiredexcavationvolume:zeroC:Theuseofnoheavyorspecialconstructionvehiclesandequipment(whencomparedtotypicalfarmingrelatedvehicles–lorries,tractors,etc.)areforeseen.4.TIMING:A&B:AspertheconstructionscheduleandpostActivityAintheBotanicalMethodStatement.
5.SUPERVISORYPARTY:A&B:• Applicant: Hessequa Local Authority –
MunicipalTechnicalDirector• Managing Agent / Resident Engineer –
TBC• ProjectManager–TBC• EnvironmentalControlOfficer–TBC• Botanist–TBC
6.STAFF,PLANTANDEQUIPMENTTOBEUSED:All staffmust be appropriately qualified andwork under the supervision of the ECO andcontract’smanager.All contracting staff shouldhavebeen inductedprior to commencingwithanyworksonsite.AcopyoftheEMPrshouldbeavailableintheSiteOffice.Equipmenttypicallyassociatedwiththeconstructionofabrickbuildingandconcreteworkwillbeused.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 32
7.RISKS:Environmental sensitivities relate merely tothe access to, the cleaning of the site andthe construction of buildings and concreteplinths.Careshouldbetakennottospillanycementonconcreteonthebaresoil.Wind-blowndust fromthesiteand/or theaccess road could impact on adjacentfarmland during and post constructionactivities. Uncontrolled rubbish and litterfrom the construction site could impact onadjacentpropertiesandtheestuary.
8.PREVENTATIVEMITIGATORYACTION:To minimise any possible negativeenvironmentalimpact,thecontractorhastoensure that concrete is not mixed on baresoil and that cement bags are immediatelyplaced in refuse bins which need to beavailableonsite.Housekeeping rules contained in the EMPrshouldbeadheredto.Specificnoticeshouldbe taken of limited rubbish and litter beingblownaround.
6.7 Method statement 5: Solar Farm Infrastructure
TABLEMS5 INSTALLATIONOFTHESOLARFARMINFRASTRUCTURE
1.SPECIFICLOCATION:RefertothelayoutonFigure6,specificallycomponentSF,theSolarFarm.2.DESCRIPTION:A solar farmwith power generation of 72.3 kWpwill be constructed on a new servitudeadjacent to the existing servitude. This solar farm will be connected to the electricalinfrastructureasisrequired.Thelayoutofthesolarfarmisindicatedonthelayoutdrawings(Figure6).Theareawhichisrequiredforthesolarpanelsis51mx25m=1250m2.Thesolarpanelswillbemountedtoasteelframestructure.Theframewillhavepostswhichare anchored into pre-augered holes my means of mass concrete. The inclination andspacingofthepanelsistobeconfirmedbysolarsupplieranddesigners.Anapproriatesecurityfencewillbeinstalledfollowingthefencespecification.Thetechncialspecificationsandlayoutdetailsareprovidedinthedesignreport.3.SPECIFICACTIONS:Thesolarpanels,supportinginfrastructureandelectricalcomponentswillbeprefabricatedandbroughttositeviatransportvehicles.Thevariouscomponentswillbedeliveredaspertherequiredinstallationschedule.Theexistingvegetationatthesolarfarmsitewillbeleftundisturbedtolimitdustgeneration
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 33
which isdetrimentaltosolarpanelperformanceand increasesmaintenance.Holeswillbecreatedwithanaugermachine.ThesupportcolumnswillthenbeplacedinsidetheholeandthencastintoplacewithmassconcreteaspertherequireddesignspecificationandtoSABSmethodsandstandards.Developmentfootprint:153m2
Excavationvolume(holes):30m34.TIMING:AspertheconstructionscheduleandpostActivityAintheBotanicalMethodStatement.
5.SUPERVISORYPARTY:
• Applicant: Hessequa Local Authority –MunicipalTechnicalDirector
• Managing Agent / Resident Engineer –TBC
• ProjectManager–TBC• EnvironmentalControlOfficer–TBC• Botanist–TBC
6.STAFF,PLANTANDEQUIPMENTTOBEUSED:All staffmust be appropriately qualified andwork under the supervision of the ECO andcontract’smanager.All contracting staff shouldhavebeen inductedprior to commencingwithanyworksonsite.AcopyoftheEMPrshouldbeavailableintheSiteOffice.Theinstallationofthesolarpanelsandassociatedelectricalequipmentwillbeundertakenbythespecialistconstractor.Equipment typically associated with the installation of the specialist structures, raisedfootingsandinstallationofelectricalcablingandrelatedinfrastructure.7.RISKS:Environmental sensitivities relate merely tothe access to, the cleaning of the site andinstallationof the supporting columns.Careshould be taken not to spill any cement orconcreteonthebaresoil.Wind-blowndust fromthesiteand/or theaccess road could impact on adjacentfarmland during and post constructionactivities. Rehabilitation of disturbed areasshouldcommenceasapundersupervisionoftheECOandBotanist.
8.PREVENTATIVEMITIGATORYACTION:To minimise any possible negativeenvironmentalimpact,thecontractorhastoensure that concrete is not mixed on baresoil and that cement bags are immediatelyplaced in clearly marked refuse bins whichneedtobeavailableonsite.Housekeeping rules contained in the EMPrshouldbeadheredto.Specificnoticeshouldbe taken of limited rubbish and litter beingblownaround.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 34
Uncontrolled rubbish and litter from theconstruction site could impact on adjacentpropertiesandtheestuary.Insufficientablutionfacilities
Make sure that sufficient ablution facilitiesare available to construction staff, normallyonetoiletper15people.
6.8 Method statement 6: Steel effluent pipeline across steep slope
TABLEMS6 INSTALLATIONOFTHESTEELEFFLUENTPIPELINEACROSSTHESTEEPSLOPE
1. SPECIFIC LOCATION: Refer to the layout on Figure 6, specifically component OP, theOutfallPipeline.2.DESCRIPTION:The identifiedpipeline route goesdowna steep slope in the area from the relatively flatslopedirectlytothewestoftheROPlantsiteuptotheoutletworksintheestuary.Inthisareathegalvanisedsteelpipe(OD90mm)willbeplacedalongaseriesofraisedbracketsfixed to the natural ground or rock. The pipeline alignments can be seen on the layoutdrawing(IndicatedasOPonFigure6).3.SPECIFICACTIONS:Thesteeleffluentpipelinethatcrossesthesteepriverbankismountedtoaholdingbracketonaraisedpedestalwhichisdrivenintothenaturalground/rockalongthepipelineroutefromtheflatterslopeatthetopofthehillwherethepipematerialchangesfromHDPEinatrenchburiedasdescribedinTableMS3totheoutletworksatthewater’sedge(MS7).Thepipelinealignmentwillbeclearedofvegetationtoallowtheinstallationofthepipeline.Asthepipelinerunsonthesurfacetheamountofvegetationdisturbancewillbeminimal.The pipeline pedestals will be driven into the existing ground as required. Where thesubstrateishardrock,arockdrillwillbeusedandthemetalsupportsgroutedinusinganappropriate adhesive such as a cement/sand mix or epoxy. Alternatively small concreteplinthwillbeusedtosupportthepipeline.Thesteelpipelinewillbesecuredtothepedestalbyabracket.Developmentfootprint:80mx0.3m=24m2Required excavation volume: zero.Material removedby the rockdrill wherenecessary isminimal.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 35
4.TIMING:AspertheconstructionscheduleandpostActivityAintheBotanicalMethodStatement.
5.SUPERVISORYPARTY:
• Applicant: Hessequa Local Authority –MunicipalTechnicalDirector
• Managing Agent / Resident Engineer –TBC
• ProjectManager–TBC• EnvironmentalControlOfficer–TBC• Botanist–TBC
6.STAFF,PLANTANDEQUIPMENTTOBEUSED:All staffmust be appropriately qualified andwork under the supervision of the ECO andcontract’smanager.All contracting staff shouldhavebeen inductedprior to commencingwithanyworksonsite.AcopyoftheEMPrshouldbeavailableintheSiteOffice.Equipmenttypicallyassociatedwiththeclearingofanareaalongthepipelinerouteandtheinstallation of the pipelines will be used. Methods and standards according to theappropriateSABSstandardstobeadheredto.7.RISKS:Destructionordamageofimportantand/orendangered vegatation beyond the directfootprintoftheconstructionactivities.
8.PREVENTATIVEMITIGATORYACTION:Contruction footprint area, eg the pipelineroute and labour access, to be physicallydemarcated and activities strictly restrictedtowithinthearearequiredforconstruction.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 36
6.9 Method statement 7: Brine outfall works along estuary bank
TABLEMS7 CONSTRUCTIONOFTHEBRINEOUTFALLWORKSALONGESTUARYBANK
1. SPECIFIC LOCATION: Refer to the layout on Figure 6, specifically component OW, theOutfallWorks.2.DESCRIPTION:Thebrinecreatedbythedesalinationprocesswillbedischargedbackintotheriver/estuary.Toensureminimalnegativeenvironmentalimpactthedischargeisjettedthroughadiffuserport(jetnozzle)withinternaldiameterof100mmtoenablerapiddilution.Theso-calledBankDischargelocationontherockshelfupstreamoftheintakestructurewasshowntobethepreferedlocationbytheEffuentModellingstudy(Laird et al. 2018).Thesitecharacteristicsinclude:
• Accessviaaroutealongtheestuarybanksharedwiththatoftheintakeworks;• solidanchoringoftheoutfallinfrastructuretothenaturalrockfacethereby
mitigatingtheflooddamagerisk;• theabilityforeasyinspectionandmaintenanceoftheoutfallstructure;and• asufficient water depth to enable sufficient jet mixing and subsequent
dispersion.
TheoutfallpointisshowninFigure6(OW)andisbasedoneaseofconstructionandtominimisedamagetothelocalenvironment.3.SPECIFICACTIONS:Ifthetheoutfallpipelineisboltedtotherockshelfattheestuarywaterside,commercialdiverswillbe needed. The diffuserwill be a structural elementwhich is connected to the concrete pipelineencasingviaaboltedinterface.Thepipealongtherock-shelfontheriverbankwillbeencased inconcreteasshown inthe figurebelow.Theconcreteencasingisanchoredtotherockshelf.Theconcreteencasingisforprotectionagainstfloodevents.
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 37
Thedesigndetailisprovidedinthedesignreport.Developmentfootprint:
Pipelineandoutletassembly:14mx0.5m=7m2
Requiredexcavationvolume:none4.TIMING:Aspertheconstructionschedule.
5.SUPERVISORYPARTY:
• Applicant: Hessequa Local Authority –MunicipalTechnicalDirector
• Managing Agent / Resident Engineer –TBC
• ProjectManager–TBC• EnvironmentalControlOfficer–TBC• Commercial Diver and Supervisor if
divingisrequired.• SafetyOfficer
6.STAFF,PLANTANDEQUIPMENTTOBEUSED:All staff must be appropriately qualified and work under the supervision of a qualifiedcommercial diver. Ensuring this is the ECO and contract’s manager’s responsibility. Allcontractingstaffshouldhavebeeninductedpriortocommencingwithanyworksonsite.AcopyoftheEMPrshouldbeavailableintheSiteOffice.Equipment typically associatedwith the placing of equipment and structures underwaterwill be used.Methods and standards according to the appropriate SABS standards to beadheredto.Access forconstructionvehicles tothesitewillbealongademarcatedpathwayalongtherockshelfillustratedinFigure1.Deepgulleysorholescanbebridgedbytemporarymeans.NarrowconcretestrippathwayscanbecastinselectedareasinconsultationwiththeECO.Thesewillremaininplacetoassistaccessduringmaintenanceoremergencies.7.RISKS:Drillingintotherockfaceandepoxygroutingthe required pipe brackets ito the anchorholes will disperse rock fragments into thewater column. This is a limited and localimpacthowever.Lifting and placing the outfall structure in
8.PREVENTATIVEMITIGATORYACTION:Only qualified commercial divers and asupervisor should be used if under waterworkisrequired.All labourers involved with the lifting andinstallation process of the outfall structureshouldbeabletoswimandshouldwearlife
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 38
andclosetowaterisapotentialhazard
jacketsatalltimes.AppropriatePPEandPPCneedtobeadheredto.
6.10 Method statement 8: Botanical aspects
TABLEMS8 BOTANICALASPECTS:SEARCHANDRESCUEANDREHABILITATION
1.SPECIFICLOCATION:RefertocomponentsIP,P,RO,SFandOPshownonFigure62.DISCRIPTION:TheestablishmentofthenewROplantinfrastructurewillrequirethedisturbanceofareasasindicatedintheotherMStables.Thisactivitywilltakeplaceonallthesitesidentifiedforworks on the development precinct. These are (1) the pipeline routes – both intake andoutfalllines,andwheretheyaretogether;(2)thepositionofthebuildingsandtanksonsite;and(3)theareawherethesolarfarmistobeestablished.3.SPECIFICACTIONS:
A: Search andRescueof indigenous, vulnerable or critically endangered specieswithin
thedesignatedworkareas.(Figure6).Rescuedplantstobeplacedinsuitablenurseryarea.
B: The removal and storage in bulk of topsoil identified as containing seedbank orindividualplantsforlateruseintherehabilitationandlandscapingofidentifiedzones.
C:Thepreventionoferosionon someof theseareas thatwouldbeclearedwithin thedesignatedworkingareas.
D:Rehabilitationofsomeoftheworkareas,postconstruction.E:Maintenanceofstabilisedareas,postconstruction,duringtheoperationalphaseofthe
project.4.TIMING:
A:Priortothecommencementofany
works;B:Duringtheinitialexcavationsandor
otherworks;C:Duringongoingconstructionworks;D:Postconstruction;E:Postconstructionandduring
operationalphase.
5.SUPERVISORYPARTY:A: Applicant: Hessequa Local Authority –
MunicipalTechnicalDirectorB:Managing Agent / Resident Engineer –
TBCC:ProjectManager–TBCD:EnvironmentalControlOfficer–TBCE:Botanist–TBC
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 39
6.STAFF,PLANTANDEQUIPMENTTOBEUSED:All staffmust be appropriately qualified andwork under the supervision of the ECO andcontract’smanager.All contracting staff shouldhavebeen inductedprior to commencingwithanyworksonsite.AcopyoftheEMPrshouldbeavailableintheSiteOffice.Equipmenttypicallyassociatedwiththesearchandrescueofplantsandtherehabilitationofaconstructionsitewillbeused.7.RISKS:1. Destruction or damage of important
and/orendangeredvegatationbeyondthedirect footprint of the constructionactivities.
2.Soilerosionduetostormwaterand/orwindwithinoradjacenttotheareasofconstruction.
8.PREVENTATIVEMITIGATORYACTION:1. Contruction footprint area, eg the
pipeline routes and labour and/orvehicle access, to be physicallydemarcated and activities strictlyrestricted to within the area requiredforconstruction.
2. Stormwater andwind erosion controlmanagement, eg contouring andspeedy rehabilitation of disturbedareas.
7 Closure
Thisreportcontainsthedifferentmethodstatementswhichwillbeapprovedaspartofthe
maindocumentationoftheEnvironmentalManagementProgramme(EMPr).Itprovidesan
opportunity to properly understand each of the tasks to be undertaken to properly
implement the Witsand OSMOSUN 100 Desalination Project, planning for any potential
negativeimpactsonthenaturalenvironmentandmitigatingagainstit.Thisreportaimsto:
ü summarisetheinfrastructurecomponentsofthedesign;
ü providesadescriptionofthevarioustaskstobeundertaken;
ü providesanunderstandingoftheprocessesandmaterialtobeused;
ü providesabreakdownofthemethodofconstructionoftheseelements;
ü providesalocationoftheworkstobeundertakenviaasketchplanormap
ü providesanunderstandingofthesequencingoftasks,andfinallyit
180423OSMOSUN100TMDesalinationPlant July2018METHODSTATEMENTREPORT Rev:FINALV0
WMLCoast(Pty)LtdandAlternativeServicesTechnologies(Pty)Ltd 40
ü providesanunderstandingofthepeoplethatwouldmanageeachcomponentofthe
taskstoensureresponsibilityandaccountability.
The construction methodology, development footprint and excavation volume of each
componentarebrieflydescribedintheconstructionmethodologysectionofeachrelevant
component.
Insummary,webelievethattheMethodStatementsprovidedinthisreportshouldsatisfy
therequirementsoftheenvironmentalregulatoryauthority,DepartmentofEnvironmental
AffairsandDevelopmentPlanning.