Method Statement for PLATE BEARING TESTS - i · PDF fileMethod Statement for PLATE BEARING...
Transcript of Method Statement for PLATE BEARING TESTS - i · PDF fileMethod Statement for PLATE BEARING...
Method Statement for
PLATE BEARING TESTS
Chulalongkorn University Saraburi Campus
Contractor: EMC Public company limited
NOVEMBER 2009
BY
Infratech ASTM CO., LTD.
TABLE OF CONTENTS
Chapter Title Page
Table of Contents.................................................................................................................................. 1
List of Appendix.......................................................................................Error! Bookmark not defined.List of Figures..........................................................................................Error! Bookmark not defined.
1.0 PROJECT INFORMATION........................................................................................................ 3
2.0 PLATE LOAD TEST INFORMATIN .......................................................................................... 3
3.0 TEST APPARATUS .................................................................................................................. 3
4.0 TEST PROCEDURE ................................................................................................................. 3
5.0 RESULTS OF TEST ................................................................................................................. 4
Appendix
1
Infratech ASTM CO., LTD.
List of Appendix
Appendix A Data Recording FormAppendix B Sample of Graph of Load-Time-Settlement
Appendix C Sample of Test Data Appendix D Calibration of Hydraulic Jack
2
Infratech ASTM CO., LTD.
1.0 PROJECT INFORMATION
� Project Name : Chulalongkorn University Saraburi Campus
� Contractor : EMC Public Company Limited
� Location : Saraburi,Thailand
2.0 PLATE LOAD TEST INFORMATION
� Number of Tests : 11
� Plate Size : Dia . 12”x 25 mm
� Design Load : 20 Tons/sq.m.
� Proposed Test : 50 Tons/sq.m. (2.5 * design load)
� Testing Standard : AASHO T235-74 (1986) / ASTM D1195
3.0 TESTING APPARATUS
The test apparatus consists of the following:
1. A 10-ton hydraulic jack was used as loading device.
2. A dia.12”x 25 mm thick steel plate was used to distribute the load from the jack to the plate and to the ground.
3. Three dial gauges with accuracy of 0.01 mm were used to measure the deflections during loading and unloading.
4 .Back hoe axial was used as reaction load during loading .
4.0 TEST PROCEDURE
The test ground was loaded as per AASHO T 235-74 (1986) as per the loading and unloading steps. These steps were for all the tests conducted.
Loading: 0- 25% - 50% - 75% - 100% - 125% - 150% - 175% - 200% - 225% - 250% of the design load.
Unloading: 150% - 100% - 50% and 0% of the design load
3
Infratech ASTM CO., LTD.
Each loading and unloading stage was maintained for 15 minutes with readings made at 1, 2, 4, 8 and 15 minutes after the application or removal of load. During the test, records including plots of load vs. time and load vs. settlement were maintained progressively.
5.0 RESULTS OF TEST
Results of test will be presented in graph form show relationship among load-time-settlement and prediction of subgrade modulus.
4
Appendix-A
Data recording form
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……….... Area : ………Pit 1Certification No. : Date : …26/10/2010
Soil Description : Silty SandPlate Size : Dia.12" x 25 mm.Area / Line No. : …………………………………………….
Def. Rate(mm/min)
10.30
Result : Accepted Rejected Re-Compact
Test by : Check by : ( Rungruang D. ) ( Poosit Sunlakaviset ) Soil Technician Soil EngineerDate ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\05-PlateBearing-EMC\[PlateLoadTestEMC.xls]Basic Info
14 1.09 15.0
14 0.73 10.013 0.73 10.012 0.73 10.010 0.73 10.0
13 0.36 5.012 0.36 5.010 0.36 5.08 0.36 5.0
0 (bars)
31 (bars)
50.00
50.00
15.0
15.015.015.015.0
15.015.0
15.0
10.0
10.0
15.0
10.010.010.010.0
0.36
0.00 0.0
5.05.0
0.360.36 5.0
5.0
5.05.0
1.09
1.09
1.09
1.091.09
1.091.091.091.09
0.730.73
0.73
0.730.730.73
0.36
0.360.36
2
1248
1415
48
15
15
01
10
1312
0
0
124
0
DATE TIME(tons)TIME
26-Oct-10
REMARKS
51 (bars)
ELAPSED
ASTM Testing Co.,ltd. Kenber
72 (bars)
Rangsan Gamsantia Poosit S.
SUBMITTED BY RECEIVED BY
t/m^2G1 G3
(mm)G2
LOAD APPLIED Avg. Set.
50.00
50.00
Owner : CU
Main Conractor:EMC
Contractor :Footing
Appendix-A
Data recording form
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……….... Area : ………Pit 1Certification No. : Date : …26/10/2010
Soil Description : Silty SandPlate Size : Dia.12" x 25 mm.Area / Line No. : …………………………………………….
Def. Rate(mm/min)
10.30
Result : Accepted Rejected Re-Compact
Test by : Check by : ( Rungruang D. ) ( Poosit Sunlakaviset ) Soil Technician Soil EngineerDate ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\05-PlateBearing-EMC\[PlateLoadTestEMC.xls]Basic Info
14 1.09 15.0
14 0.73 10.013 0.73 10.012 0.73 10.010 0.73 10.0
13 0.36 5.012 0.36 5.010 0.36 5.08 0.36 5.0
0 (bars)
31 (bars)
50.00
50.00
15.0
15.015.015.015.0
15.015.0
15.0
10.0
10.0
15.0
10.010.010.010.0
0.36
0.00 0.0
5.05.0
0.360.36 5.0
5.0
5.05.0
1.09
1.09
1.09
1.091.09
1.091.091.091.09
0.730.73
0.73
0.730.730.73
0.36
0.360.36
2
1248
1415
48
15
15
01
10
1312
0
0
124
0
DATE TIME(tons)TIME
26-Oct-10
REMARKS
51 (bars)
ELAPSED
ASTM Testing Co.,ltd. Kenber
72 (bars)
Rangsan Gamsantia Poosit S.
SUBMITTED BY RECEIVED BY
t/m^2G1 G3
(mm)G2
LOAD APPLIED Avg. Set.
50.00
50.00
Owner : CU
Main Conractor:EMC
Contractor :Footing
Appendix-B
Sample of Graph for Load-Time-Settlement
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……. Area : …………………
Certification No. : Date : ………………..……
Soil Description : Silty Clay
Plate Size : Dia. 304 mm. x 25 mm.
Area / Line No. : ………………………………………………………..
k = Subgrade modulus( t/sq.m./mm.) =9.3E = Soil Modulus(Mpa.) = k x Dx(1-u^2)/100 = 0.91xKx450/100 ,in which u = Poison ratio,D=Plate Diameter (Ref. Foundation analysis and design By Joseph E. Bowles 4th Edition page407 Eq.9.6a) For Silt,Sand&Dry clay, E = 26 MPA For wet clay, E = 22 MPA
Result : Accepted Rejected Re-Compact
Test by : Check by :
( Rungruang D. ) ( Poosit Sunlakaviset )
Soil Technician Soil Engineer
Date ..…../……./……. Date ..…../……./…….
COMPANY
SIGNATURE
NAME
DATE
(ITP-C-116/LRS) Rev.0 E:\99-07-PlateBearingTest\[PlateBearingTestReport.xls]Report (1)
SUBMITTED BY RECEIVED BY
Infratech ASTM Co.,ltd.
Rangsan Gamsantia
Owner : CU
Main Contractor: EMC
Contractor :
LOAD-SETTLEMENT CURVE
-7.0
-6.0
-5.0
-4.0
-3.0
-2.0
-1.0
0.00 10 20 30 40 50 60
PRESSURE, (t/m2)
SETT
LEM
ENT,
(mm
)
Actual loading
Unloading
Linear loading
TIME - LOAD CURVE
0102030405060
0.0 1.0 2.0 3.0 4.0TIME, (hrs)
PRES
SUR
E,(t/
m2 )
TIME-SETTLEMENT CURVE
-7.0-6.0-5.0-4.0-3.0-2.0-1.00.0
0.0 1.0 2.0 3.0 4.0
TIME, (hrs)
SETT
LEM
ENT,
(mm
)
Footing
P234 ������������� 1 Line No. 4/J-K
Appendix-C
Sample of Test Data
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……….... Area : …………………Certification No. : Date : …26/10/2010
Soil Description : �������������Plate Size : Dia. 304 mm. x 25 mm.Area / Line No. : P 234 ������������� 1 [Line 4/J-K]
Def. Rate(mm/min)
15:05
15:0515:0615:0715:0915:1315:20
15:2015:2115:2215:2415:2815:35
15:3515:3615:3715:3915:4315:50
15:5015:5115:5215:5415:5816:05
16:0516:0616:0716:0916:1316:20
Result : Accepted Rejected Re-Compact
Test by : Check by : ( Rungruang D. ) ( Poosit Sunlakaviset ) Soil Technician Soil EngineerDate ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\99-07-PlateBearingTest\[PlateBearingTestReport.xls]Report (1)
15 1.46 20.043.72 2.89
40.48 42.11 2.90
43.74 2.868 1.46 20.0 40.49 42.12
1.46 20.0 40.52 42.152 1.46 20.0 40.61 42.21 43.77 2.80
20.0 40.63 42.22 43.780 1.46 20.0 40.73 42.30 43.82 2.72 92 (bar)
44.02 2.39
15.0
15 1.09 15.044.02 2.398 1.09 15.0 41.23 42.58
15.0
1.09 15.0 41.33
41.271.09
43.04
41.71
41.80
42.6542.63
42.5842.60
42.58
45.00
42.825.0
42.81
0.0
5.05.0
43.53
43.5242.80
43.5342.82
42.80
45.00
43.5243.52
43.52
43.13
43.0743.0543.04
Rangsan Gamsantia
SUBMITTED BY RECEIVED BY Infratech ASTM Co.,ltd.
113 (bar)41.7641.7541.7341.72
72 (bar)
G3(mm)
G2LOAD APPLIED Avg. Set.
(t/m^2)G1
24
1
Jack Pressure
51 (bar)
26-Oct-10
0
1
DATE TIME(tons)TIME
ELAPSED
0.00
0.36
0
1.82
1.091.09
1 1.46
4
15
15
01
1
248
15
0
24
0
248
1.821.821.82
10.010.0
1.821.82
0.73
15.0
0.730.730.73
0.36
0.36
0.73
0.36
0.36
0.73
5.0
5.0
25.0
10.010.010.010.0
25.0
25.025.025.025.0
39.9039.88
41.23
42.80
42.0641.9941.8741.86
42.1043.11
39.87
41.86
39.9739.93
41.30
41.24
39.91
43.44
45.00
44.6444.6344.63
44.64
44.63
44.04
44.34
43.43
44.3444.35
43.49
44.0744.06
43.4643.46
43.47 3.28
2.3644.02 2.39
43.71
44.0444.3944.36
1.341.351.35
1.34
3.29
1.811.861.911.92
2.79
1.35
3.25
0 (bar)
31 (bar)
0.00
44.63 1.35
3.303.323.33
1.91
2.322.34
8 0.36 5.0
1.92
Owner : CU
Main Contractor: EMC
Contractor :FootingFooting
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……….... Area : …………………Certification No. : Date : …26/10/2010
Soil Description : �������������Plate Size : Dia. 304 mm. x 25 mm.Area / Line No. : P 234 ������������� 1 [Line 4/J-K]
Def. Rate(mm/min)
16:2016:2116:2216:2416:2816:35
16:3516:3616:3716:3916:4316:50
16:5016:5116:5216:5416:5817:05
17:0517:0617:0717:0917:1317:20
17:2017:2117:2217:2417:2817:35
Result : Accepted Rejected Re-Compact
Test by : Check by : ( Rungruang D. ) ( Poosit Sunlakaviset ) Soil Technician Soil EngineerDate ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\99-07-PlateBearingTest\[PlateBearingTestReport.xls]Report (1)
3.28 45.037.17 39.69 41.41 5.5837.14 39.64 41.37 5.62
8 3.28 45.037.23 39.76 41.50 5.504 3.28 45.0
3.28 45.0 37.32 39.85 41.59 5.4137.40 39.92 41.65 5.341 3.28 45.0
40.04 41.75 5.22 195 (bar)
2.92 40.0
3.28 45.0
5.0615 2.92 40.0 5.09
40.25
37.70 40.14 41.8837.73 40.18 41.92
2 2.92 40.0
8
40.311 2.92 40.0
4 2.92 40.0
5.77
4.79 175 (bar)
4.90
216 (bar)
4.85
4.97
6.1740.7940.91
5.905.97
42.1240.41 42.18
37.96 40.362.92 40.0
38.4838.44
2.55 35.0
2.552.55
2.55
Avg. Set.
6.06
42.95 3.95
3.75133 (bar)
4.61
8 2.19 30.0
42.44
42.7142.5642.53
2.19 3.98
4.40
40.73
42.3942.35
41.2141.0841.00
42.0842.01
39.04
43.1243.0643.00
43.18
39.07
36.59
38.26
36.9736.8536.78
38.03
37.8337.90
37.55
38.70
36.54
35.035.035.0 38.35
38.30
50.0
36.7150.050.050.050.0
2.19
2.552.55
30.030.0
2.192.19 30.0
2.1930.0
35.0
35.0
30.0
3.653.65
3.653.653.653.65
50.0
15
15
01
48
0
0
2
15
0
2
1248
15
24
0
DATE TIME(tons)TIMELOAD APPLIED
(t/m^2)
1
Jack Pressure
154 (bar)
ELAPSED
41.32
G3(mm)
G2
Infratech ASTM Co.,ltd.
6.23
41.19
Rangsan Gamsantia
SUBMITTED BY RECEIVED BY
40.9140.75
4.434.524.57
41.40
41.14
4.23
3.833.89
3.67
42.9241.11
39.30
G1
39.3039.2139.14
39.40
41.25
39.04
39.2139.10
40.7340.6440.6040.57
39.5039.38
Owner : CU
Main Contractor: EMC
Contractor :Footing
(ITP-C-116/LRS)
Chulalongkorn Saraburi Campus
LOAD SETTLEMENT - TIME RELATION SHIPS
System : ………..……….... Area : …………………Certification No. : Date : …26/10/2010
Soil Description : �������������Plate Size : Dia. 304 mm. x 25 mm.Area / Line No. : P 234 ������������� 1 [Line 4/J-K]
Def. Rate(mm/min)
17:3517:3617:3717:3917:4317:50
17:5017:5117:5217:5417:5818:05
18:0518:0618:0718:0918:1318:20
18:2018:2118:2218:2418:2818:35
18:3518:3618:3718:3918:4318:50
Result : Accepted Rejected Re-Compact
Test by : Check by : ( Rungruang D. ) ( Poosit Sunlakaviset ) Soil Technician Soil EngineerDate ..…../……./……. Date ..…../……./…….
COMPANY SIGNATURE NAME DATE
(ITP-C-116/LRS) Rev.0 E:\99-07-PlateBearingTest\[PlateBearingTestReport.xls]Report (1)
39.76
39.5639.6039.6239.6639.71
39.0339.0339.0339.03
39.04
G1
36.5436.5436.54
36.54 39.04
39.04
G3(mm)
0 (bar)
G2
39.0439.04
Infratech ASTM Co.,ltd.
Rangsan Gamsantia
SUBMITTED BY RECEIVED BY
5.50
Jack Pressure
151 (bar)
ELAPSED
39.04
DATE TIME(tons)TIMELOAD APPLIED
(t/m^2)
124
0
4815
15
012
4
0.00
0124815
1.461.46
1.46
15
01248
2.19
1.461.46
30.0
0.0
40.0
40.0
30.0
20.020.0
20.020.0
10.0
2.92
2.92
30.0
30.030.030.0
2.192.19
0.000.00
2.192.192.19
0.00
0.00
0.73
0.00
2.9240.040.0
2.922.92 40.0
0.00.00.00.00.0 36.90
36.8536.87
36.54
36.8036.81
36.5436.54
36.54
36.54
36.83
36.5436.5436.5436.54
39.0339.03
5.66
40.73
40.74
36.54
36.54
39.03 40.71
36.54 39.04
40.7240.7240.72
40.72
6.24
6.246.24
41.83
40.7140.71
41.5541.60
40.73
6.236.236.23
6.23 197 (bar)
8 2.92 40.0
5.60
6.23
40.7140.7140.71
5.6441.6441.70
6.24
39.046.23
40.72
Avg. Set.
6.24
40.71 6.24
6.23
5.55
6.23
6.18
41.76
6.24
5.70
6.23 104 (bar)
6.236.23
20.0 36.54 39.04 40.7340.73
39.04 40.731.46 20.0 36.54 39.04
0 0.73 10.0 36.56 39.08 6.19 58 (bar)40.801 0.73 10.0 36.56 39.08 40.80 6.192 0.73 10.0 36.56 39.08
39.09 40.8136.56 39.09
40.80 6.1936.56 6.18
8 0.73 10.0 40.81 6.1815 0.73 10.0 36.56 39.09 40.81
Owner : CU
Main Contractor: EMC
Contractor :Footing
Appendix-D
Jack Calibration
Pr
ojec
t :C
hula
long
korn
Sar
abur
i Cam
pus
Con
trac
tor
EMC
PC
L
Pla
te S
ize
0.30
48m
.(D
ia.)
Pla
te a
rea
0.07
30Sq
.m.
Jack
Rea
ding
and
Pla
te lo
ad T
able
PLA
TEJa
ckLo
adJa
ckPr
essu
re
App
lied
Load
(Y)
Cal
cula
te(X
)
(tons
/sq.
m.)
(kg)
bar
00
0LO
AD
ING
536
531
Y
= A
X+B
X=(
Y-B
)/A
1073
051
A=
17.7
758
1510
9472
2014
5992
UN
LOD
ING
2518
2411
3A
=15
.683
3
3021
8913
3B
=-1
76.3
889
3525
5415
4
4029
1917
5
4532
8319
5
5036
4821
6
4029
1919
7
3021
8915
1
2014
5910
4
1073
058
00
0
Appendix-E
Photograph from previous test