MEP BIMNumber of objects
TJJ / 10.9.2013
Meilahti Tower Hospital, renovation, 36.000m2
Provision for Voids Heating and Cooling Water/Sewer Hospitalgas
Ventilation Structural Architectural Electrical
Fixed Hospital Equipments Vapour Sprinkler Pneumatic mail
Object count of model Architectural• 30.971
Structural• 85.120
MEP (All systems)• 469.305
Electrical• 70.394
Ventilation• 86.511
Water/Sewer• 147.148
Heating/Cooling• 74.948
Hospitalgas•32.823
Sprinkler• 41.743
Fixed Hospital Equipments• 2.071
Vapour•5.842
Pneumatic mail• 178
Provision for Voids•7.647
Number of objects in models
050000
100000150000200000250000300000350000400000450000500000
Number of objects in m2
02468
101214
Objects / m2
Meilahti Tower Hospital