Building the Future
Current Activities this Week:
Foundations:
Area 4 Field Level – Backfill of foundations for “infill”
area between Column Lines 39-1 is complete.
Concrete Flatwork:
Area 3 Field Level – Concrete for base slab at Cauldron
Club is complete.
Masonry:
Area 3 – Masonry pilaster installation at Truck Dock is
ongoing. Area 1, 2, 3 – Masonry installation is ongoing
at Concession Buildings.
Steel:
Area 1, 2, 3 – Canopy decking installation is ongoing.
Area 2 – Concession Building steel truss and decking
installation is nearly complete. Area 1 – Elevator
support steel installation is ongoing for F1.
Roofing and Sheetmetal:
Area 1, 3 – Canopy gutter installation is complete.
Area 1 – Subgirt installation for metal panels is ongoing
at West Building.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Drywall installation is
is ongoing at Field and Mezzanine Levels
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 10.20.2010
Re: Wizards Stadium Project
Update – Week of
10.18.2010
Field Level Area 3 – Cauldron Club base slab
has been placed.
Field Level Area 3 – Masonry pilaster
installation at East Elevation (Truck Dock).
Area 1 – Masonry and Densglas installation
at Northwest corner of West Building.
Building the Future
Glass:
Area 1 - Curtainwall framing and glass installation is
ongoing at West Building on west, south and east
elevations. South “wing” framing is complete.
MEP Rough-in:
Area 4 – Underground MEP rough-in is ongoing.
West Building - Ductwork installation on
Concourse, Suite and Press Levels are ongoing.
Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Concourse, Suite and Press Levels. Electrical rough-in is
ongoing on Concourse, Suite and Press Levels.
Projected Activities occurring next Week:
Concrete Flatwork:
Area 3 Field Level – Prep for Slab-on-Grade at Stair 1
will continue. Area 4 Field Level – Installation of on-grade
seating risers and intermediate stairs will continue.
Area 1 Concourse Level – Placement of topping slabs inside
Concession Buildings will begin.
Masonry:
Area 3 – Field level masonry installation will continue in
Area C and D. Area 1, 2, 3 – Concourse building
masonry installation will continue.
Steel:
Field Level Area 3 – Misc steel installation that supports
Burnished CMU will begin. Field Level Area 2 - Subroof
installation will continue.
Roofing and Sheetmetal:
Area 1 – Permanent roofing installation at West
Building will continue. Area 1 – Subgirt installation at
West Building will continue.
Metal Stud Framing:
Area 1 – Metal stud framing on Field Level will continue.
Area 1 - Drywall installation will continue at Field Level
Concourse Level Area 1 – Soffit construction
on SW Concourse Concession Buildings.
Mezzanine Level Area 4 – Slab prep is
ongoing for Mezzanine walkway.
Field Level Area 4 – Structural steel at infill
area is set and foundations are backfilled.
Building the Future
and Mezzanine Level. Drywall installation will begin on
Suite Level.
Glass:
Area 1 – Curtain Framing and Glass installation around West
Building will continue. Curtainwall framing on Suite and
Press Level balconies will continue. Solar Innovations
recessed track will deliver.
MEP Rough-in:
MEP Rough-in at Concourse, Suite and Press Levels will
continue. Ductwork installation on Concourse, Suite, and
Press Level will continue. Fire Sprinkler installation will
continue on Concourse, Suite and Press Levels. MEP
rough-in will continue in Main Concourse Buildings.
Area 1 – Shot of the Field Side of the West
Building looking Northwest.
Area 1 – Shot of the west building showing
the progress of the exterior envelope.
Building the Future
Additional Photos:
Concourse Level Area 2 – Plumbing carriers
set in Restrooms 03.19.01.
Field Level Area 2– Swithgear is set in
Electrical Service Room 01.20.01.
Field Level Area 3 – Emergency Generator is
set.
Concourse Level Area 1 – Stair 4 installation
is ongoing.
Concourse Level Area 4 – Installation of
metal decking is nearly complete at “infill”
area.
Field Level Area 1 – Metal stud framing is
ongoing in Wizards Locker room.