MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) Naval Station Newport, Rhode Island Wednesday, January 20, 2016, 6:30 pm Courtyard by Marriott – Newport Middletown 9 Commerce Drive, Middletown, RI 02842 CALL TO ORDER APPROVAL OF PREVIOUS MINUTES – November 18, 2015 SITE PROGRESS HANDOUTS o Site Progress Milestone Chart o Site Summary Status Table TECHNICAL PRESENTATION o Naval Station Response to an Emerging Contaminant: Perfluorocarbon Compounds (PFCs) COMMUNITY UPDATE o RAB Co-Chair Update from Margaret Kirschner REGULATORY UPDATE o EPA and RIDEM Updates NEXT MEETING o March 16, 2016 o Upcoming Topics and Presentations ADJOURN

Transcript of MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd...

Page 1: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

MEETING AGENDA RESTORATION ADVISORY BOARD (RAB)

Naval Station Newport, Rhode Island

Wednesday, January 20, 2016, 6:30 pm Courtyard by Marriott – Newport Middletown 9 Commerce Drive, Middletown, RI 02842

• CALL TO ORDER

• APPROVAL OF PREVIOUS MINUTES – November 18, 2015

• SITE PROGRESS HANDOUTS

o Site Progress Milestone Chart

o Site Summary Status Table

• TECHNICAL PRESENTATION

o Naval Station Response to an Emerging Contaminant: Perfluorocarbon Compounds (PFCs)

• COMMUNITY UPDATE

o RAB Co-Chair Update from Margaret Kirschner

• REGULATORY UPDATE

o EPA and RIDEM Updates

• NEXT MEETING

o March 16, 2016

o Upcoming Topics and Presentations

• ADJOURN

Page 2: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17
Page 3: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

SITE PROGRESS MILESTONESEnvironmental Restoration ProgramNaval Station Newport, Rhode Island Updated: 01/11/16

Site

US

EP

A O

pera

ble

Uni

t (O

U)

Des

igna

tion

Nav

y R

PM

Nav

y N

ewpo

rt Fa

cilit

y C

onta

ct

EP

A R

PM

RID

EM

RP

M

Fina

l PA

Rep

ort

Fina

l SI o

r SA

SE

Rep

ort

Dra

ft S

AP

or W

P

Fina

l SA

P o

r WP

Com

plet

ion

of F

ield

Pro

gram

Dra

ft R

I Rep

ort o

r SIR

Fina

l RI R

epor

t or S

IR

Dra

ft FS

Rep

ort

Fina

l FS

Rep

ort

Dra

ft P

P

Fina

l PP

Dra

ft R

OD

or C

AP

Fina

l RO

D o

r CA

P

Com

plet

ion

of D

esig

n

Com

plet

ion

of C

onst

ruct

ion

O&

M a

nd L

TM

Onshore OU 1 x x x x x x x x x x x x x x x OngoingOffshore OU 4 x x x x x x x x x x x x x x x Ongoing

Site 2 NA JG DM -- PC x xSite 4 NA NC DM KK PC x TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBDSite 8 OU 7 NC DM KW PC x x x x x x x x x x x x x TBD 01/30/17 TBDSite 9 OU 3 JG DM KK PC x x x x x x x x x x x x x x x Ongoing

Cat 1 TBD x x x x x x x x x x 04/18/16 05/27/16 10/24/16 TBD TBD TBDCat 2 NA x x TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBDCat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17 TBD TBD TBD TBD TBD TBD TBD TBD TBDCat 1 TBD x x x x x x x x 07/04/16 06/29/16 01/10/17 03/26/17 10/07/17 TBD TBD TBDCat 2 NA x x TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBDCat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17 TBD TBD TBD TBD TBD TBD TBD TBD TBDCat 1 TBD x x x x x x x x 06/25/16 07/14/16 01/25/17 04/10/17 10/22/17 TBD TBD TBDCat 2 NA x x TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBDCat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17 TBD TBD TBD TBD TBD TBD TBD TBD TBDCat 1 OU 11 x x x x x x x x x x x x x x 03/09/16 TBDCat 2 NA x x TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBDCat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17 TBD TBD TBD TBD TBD TBD TBD TBD TBDCat 1 T53, 56 x x x x x x x x x x TBD TBD TBDCat 1 Other x x x x x x x x x x x x x x 07/19/16 TBDCat 2 T50 NA x TBD TBDCat 2 Other NA x x TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBD TBDCat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17 TBD TBD TBD TBD TBD TBD TBD TBD TBD

Site 17 OU 6 JG DM KK PC x x x x x x x x x x x x x 04/11/16 04/29/17 TBDOnshore OU 12 x x x x x x x x x x x x x x 05/01/17 TBDOffshore OU 5 x x x x x x x x x x x x x x 12/27/16 TBD

Site 22 OU 10 NC DM JD NN x x x x x x x 03/31/16 10/12/16 01/10/17 07/24/17 07/06/17 01/17/18 TBD TBD TBDMRP Site 1 OU 9 NC DM JD NN x x x x x x x 03/10/16 09/21/16 11/20/16 06/03/17 01/31/17 07/30/17 TBD TBD TBDSite 23 TBD NC TS KK PC x x x x x x 02/22/16 02/26/16 09/08/16 11/07/16 05/21/17 07/26/17 02/06/18 TBD TBD TBD

x = Completed Notes:12/15/14 = Ongoing; expected date Category 1 - Includes non-petroleum impacts; managed under CERCLA; lead regulatory agency is USEPA PA = Preliminary Assessment RI = Remedial Investigation

TBD = To be determined; if needed Category 2 - Includes only petroleum impacts; managed under RIDEM regulations; lead regulatory agency is RIDEM SI = Site Inspection SIR = Site Investigation Report (RIDEM) = Not applicable; not required Category 3 - Nature of site impacts is not yet defined; will be placed in either Category 1 or 2 SASE = Study Area Screening Evaluation RACR = Remedial Action Completion Report

Site investigation for Tank Farm 5 consisted of pilot study report for Cat 2 TF50, and characterization report for Cat 3 SAP = Sampling and Analysis Plan FS = Feasibility StudyX = Completed, NA = Not applicable WP = Work Plan PP = Proposed PlanDM = Deb, KK = Kymberlee, PC = Pam, KW = Kim CAP = Corrective Action Plan (RIDEM) ROD = Record of DecisionTS = Tom, JG = Jim, JD = Jane, NN = Nick, NC = Nicole OU = Operable Unit T = Tank

O&M = Operation and Maintenance LTM = Long-term Monitoring

Full Investigation Site Response DecisionTechnology EvaluationWork PlanPreliminary Investigation Remediation

Site Name

PC

Old Fire Fighting Training Area (OFFTA)

Site 7 Tank Farm 1 JG DM

Melville North LandfillCoddington Cove Rubble Fill Area (CCRF)NUSC Disposal Area

NN

JD PC

Site 1 McAllister Point Landfill NC DM KW

Carr Point Shooting RangeCoddington Point Buried Debris Sites (5)

Site 13

Site 19

Carr Point Storage Area

PC

Gould Island

KK

Tank Farm 5

OU 2

JG DM JD

Derecktor Shipyard JG DM PC

PC

Site 11 Tank Farm 3 JG PC

Site 12 Tank Farm 4 JG DM JD

DM JD

Site 10 Tank Farm 2 JG DM JD

Page 4: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

SITE STATUS SUMMARY AND PATH FORWARDEnvironmental Restoration ProgramNaval Station Newport, Rhode Island

Updated: 01/11/16

Site Operable Unit ROD Regulatory Phase Status and Path Forward NAVSTA Navy RPM EPA RPM RIDEM RPM

Source OU 1 9/27/1993

Migration OU 4 3/1/2000

Site 4 NA NAPre-CERCLA Study Area Screening Evaluation (SASE) Groundwater Addendum

• Conduct additional supplemental groundwater sampling in 2015• Finalize Supplemental Groundwater Evaluation Report in 2016• Complete SASE phase in 2016• Document team decision for NFA or begin RI/FS process in 2016

D. Moore N. Cowand K. Keckler P. Crump

Site 8 OU 7 9/30/2012 CERCLA Remedial Design and Remedial Action

• Complete soil removal and soil capping RA in 2016• Finalize groundwater and sediment RD in 2016• Initiate groundwater and sediment RA in 2016/2017• Implement O&M and LTM programs in 2017• Conduct annual LUC inspections • Include in five-year review in 2018

D. Moore N. Cowand K. Keckler P. Crump

Site 9 OU 3 9/28/2010 CERCLA Long-term Monitoring (LTM)

• Complete desktop review of potential PFCs per 2014 Five-Year Review• Continue to implement groundwater LTM program• Conduct annual LUC inspections • Include in five-year review in 2018

D. Moore J. Gravette K. Keckler P. Crump

Cat 1 OU 13 CERCLA Remedial Investigation and Feasibility Study (RI/FS)

• Finalize soil FS and soil Proposed Plan in 2016• Complete soil ROD in 2016• Conduct soil Pre-Design Investigation in 2016• Complete soil RD in 2016/2017• Implement and complete soil RA in 2018• Initiate approach for groundwater assessment (as-needed) in 2017• Include in five-year review in 2018

Cat 2 NA NA RIDEM Investigations and Response Actions

• Continue coordinating with DESC on system dismantling• Anticipate system dismantling by 2019• Continue investigations and response actions as-needed

Cat 3 NA NA NA • No Cat 3 AOCs at Tank Farm 1

Cat 1 OU 14 CERCLA Remedial Investigation and Feasibility Study (RI/FS)

• Complete RI Report in 2015• Prepare FS and Proposed Plan in 2016• Scope and implement soil PDI in 2016• Prepare ROD in 2017• Conduct RD/RA in 2017/2018• Include in five-year review in 2018

Cat 2 NA NA RIDEM Investigations and Response Actions

• Continue coordinating with DESC on system dismantling• Anticipate system dismantling by 2019• Continue investigations and response actions as-needed

Cat 3 NA NA RIDEM Site Investigation (SI) and/or Closure

• Complete Work Plan in 2016• Initiate and complete field investigation in 2016• Recommend paths forward for each AOC in 2016/2017

Cat 1 OU 15 CERCLA Remedial Investigation and Feasibility Study (RI/FS)

• Complete RI Report in 2015• Prepare FS and Proposed Plan in 2016• Scope and implement soil PDI in 2016• Prepare ROD in 2017• Conduct RD/RA in 2017/2018• Include in five-year review in 2018

N. Noons

P. Crump

P. Crump

K. Keckler

J. Dolan

J. Dolan

N. Cowand

J. Gravette

J. Gravette

Site Name

Site 1 McAllister Point Landfill D. Moore

D. Moore

Site 10 Tank Farm 2

Coddington Cove Rubble Fill Area (CCRF)

NUSC Disposal Area

Old Fire Fighting Training Area (OFFTA)

Site 7 Tank Farm 1

• Complete Annual LTM Report for 2014 • Continue LTM program for 2015• Update post-closure monitoring and maintenance (PCMM) plan in 2016• Continue onshore and offshore LTM program• Conduct annual LUC inspections • Include in five-year review in 2018

CERCLA Long-term Monitoring (LTM) Implementation

D. Moore

Page 5: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

SITE STATUS SUMMARY AND PATH FORWARDEnvironmental Restoration ProgramNaval Station Newport, Rhode Island

Updated: 01/11/16

Site Operable Unit ROD Regulatory Phase Status and Path Forward NAVSTA Navy RPM EPA RPM RIDEM RPMSite Name

Cat 2 NA NA RIDEM Investigations and Response Actions

• Continue coordinating with DESC on system dismantling• Anticipate system dismantling by 2019• Continue investigations and response actions as-needed

Cat 3 NA NA RIDEM Site Investigation (SI) and/or Closure

• Complete Work Plan in 2016• Initiate and complete field investigation in 2016• Recommend paths forward for each AOC in 2016/2017

Cat 1 OU 11 9/30/2013 CERCLA Remedial Action (RA) and Long-term Monitoring (LTM)

• Implement soil excavation RA in 2016• Complete groundwater LTM Plan in 2016• Initiate groundwater LTM program in 2016/2017• Conduct annual LUC inspections • Include in five-year review in 2018

Cat 2 NA NA RIDEM Site Investigation and Response Actions • Continue investigations and response actions as-needed

Cat 2 Tanks 38, 42, 45, 48 NA NA RIDEM Site Investigation and

Response Actions • Continue investigations and response actions as-needed

Cat 3 NA NA RIDEM Site Investigation (SI) and/or Closure

• Complete Work Plan in 2016• Initiate and complete field investigation in 2016• Recommend paths forward for each AOC in 2016/2017

Cat 1 OU 2 1/9/2014 CERCLA Remedial Action (RA) and Long-term Monitoring (LTM)

• Implement soil cover RA in 2016• Initiate and complete groundwater LTM Plan in 2016• Initiate groundwater LTM program in 2016/2017• Conduct annual LUC inspections • Include in five-year review in 2018

Cat 1 Tanks 53, 56 OU 2 Interim ROD Closure

• Groundwater treatment was conducted for two years; LTM was conducted accordingly; LTM was discontinued in 2006; the treatment plant and wells were decomissioned in 2008; final NFA documentation is planned either separately or part of a tank farm wide decision, to document no further action for these areas

Cat 2 NA NA RIDEM Investigations and Response Actions • Continue investigations and response actions as-needed

Cat 2 Tank 50 NA NA RIDEM Investigations and Response Actions

• A pilot study was conducted in 1997, during which it was determined that there is light non-aqueous phase liquid (LNAPL) that was not possible to recover; no Corrective Action Plan (CAP) was drafted

Cat 2 Tanks 51, 52, 54, 57 NA NA RIDEM Investigations and

Response Actions • Continue investigations and response actions as-needed

Cat 3 NA NA RIDEM Site Investigation (SI) and/or Closure

• Complete Work Plan in 2016• Initiate and complete field investigation in 2016• Recommend paths forward for each AOC in 2016/2017

Site 17 OU 6 6/30/2014 CERCLA Remedial Design and Remedial Action (RD/RA)

• Complete soil excavation and debris removal RD in 2015• Implement soil excavation and debris removal RA in 2015/2016• Conduct groundwater monitoring well inventory in 2016• Prepare and initiate groundwater LTM program in 2016• Complete sediment RD in 2016• Implement sediment RA in 2017• Conduct annual LUC inspections • Include in five-year review in 2018

D. Moore J. Gravette K. Keckler P. Crump

P. Crump

P. Crump

P. Crump

J. Gravette

J. Dolan

J. Dolan

J. Dolan

J. Gravette

J. GravetteTank Farm 4

Gould Island

Tank Farm 5Site 13

D. MooreSite 12

D. Moore

Site 11 Tank Farm 3 D. Moore

Page 6: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

SITE STATUS SUMMARY AND PATH FORWARDEnvironmental Restoration ProgramNaval Station Newport, Rhode Island

Updated: 01/11/16

Site Operable Unit ROD Regulatory Phase Status and Path Forward NAVSTA Navy RPM EPA RPM RIDEM RPMSite Name

Onshore OU 12 9/16/2014 CERCLA Remedial Design and Remedial Action (RD/RA)

• Complete soil cover RA in 2017• Install additional near-shore LUCs in 2016• Complete soil and groundwater LUC in 2016• Prepare and initiate groundwater LTM program in 2016/2017• Conduct annual LUC inspections • Include in five-year review in 2018

Offshore OU 5 9/16/2014 CERCLA Remedial Design and Remedial Action (RD/RA)

• Complete sediment PDI in 2016• Finalize sediment RD in 2016• Implement and complete sediment RA in 2015/2016• Install additional near-shore LUCs• Conduct annual LUC inspections • Include in five-year review in 2018

Site 22 OU 10 CERCLA Remedial Investigation and Feasibility Study (RI/FS)

• Finalize RI Report in 2015• Conduct FS and prepare Proposed Plan in 2016• Scope and implement soil and groundwater PDI in 2016• Prepare ROD in 2017• Prepare RD in 2017• Implement RA in 2018• Include in five-year review in 2018

D. Moore N. Cowand K. Keckler N. Noons

MRP Site 1 OU 9 CERCLA Remedial Investigation and Feasibility Study (RI/FS)

• Finalize RI Report in 2015• Conduct FS and prepare Proposed Plan in 2016• Scope and implement soil and groundwater PDI in 2016• Prepare ROD in 2017• Prepare RD in 2017• Implement RA in 2018• Include in five-year review in 2018

D. Moore N. Cowand J. Dolan N. Noons

Site 23 TBDCERCLA Focused Remedial Investigation and Feasibility Study (RI/FS)

• Finalize RI Report in 2015• Conduct FS and prepare Proposed Plan in 2016• Prepare ROD in 2017• Prepare RD in 2017• Implement RA in 2018• Include in five-year review in 2018

T. Smith N. Cowand K. Keckler P. Crump

P. CrumpJ. Gravette K. Keckler

Carr Point Storage Area

Carr Point Shooting Range

Coddington Point Buried Debris Sites (5)

Site 19 Derecktor Shipyard D. Moore

Page 7: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

1

NAVSTA Newport

Emerging Contaminants: Perfluorinated Compounds (PFCs)

NAVSTA Newport, Rhode Island

Restoration Advisory Board (RAB) January 20, 2016

Page 8: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

2

2

Road Map

Emerging Contaminants

Perfluorinated Compounds (PFCs)

The Navy and PFCs

NAVFAC PFC Guidance

PFCs at Naval Station Newport

Next Steps

Questions

Page 9: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

3

3

What are Emerging Contaminants (ECs)?

The US Department of Defense defines Emerging Contaminants as: “A contaminant that:

• Has a reasonable possible pathway to enter the environment; • Presents a potential unacceptable human health or environmental risk; and

• Does not have regulatory standards based on peer-reviewed science, or the regulatory standards are evolving due to new science, detection capabilities, or pathways.”

In addition, the US Environmental Protection Agency further defines Emerging Contaminants as:

“A chemical or material that is characterized by a perceived, potential or real threat to human health or the environment or by a lack of published health standards.”

Page 10: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

4

4

What are Perfluorinated Compounds (PFCs)? Perfluorocarbons (PFCs) fall into the Emerging Contaminant (EC) category from both

the US DOD and US EPA perspectives, with both agencies working collaboratively to identify potential sources, locations, and paths forward. PFCs represent a large family of synthetic chemicals that are used in a diverse

selection of manufacturing processes: PFCs were commonly used in surface treatments

–Non-stick cookware (Teflon®) –Breathable, all weather clothing (Gore-tex®) –Scotchgard™ –Fluoro-elastomers (gaskets, O-rings, Hoses) –Paper and packaging protectors

PFCs were also commonly used in performance chemicals –Mining and oil surfactants –Insecticides –Lubricant manufacturing –Metal plating baths, including Chromium Plating –Aqueous film forming foams (AFFF) for fire fighting

Page 11: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

5

5

Are there specific types of PFCs? AFFF is an effective firefighting agent, applied by blanketing the fuel, which cools

the fuel surface and prevents re-ignition and release of flammable vapors

Two types of fire suppression foams were in used at NAVSTA Newport: Class A (AFFF) and Class B (non-PFC, protein-based foams).

For Class A (AFFF) foams, only some of them contain PFCs

Example of Foam Application (not at NAVSTA Newport)

In general, PFCs are considered generally resistant to environmental decomposition, meaning they may persist in soil and groundwater

Because of their stability, PFCs can be associated with potential risks to higher trophic level receptors (birds, mammals) and human organs that function in adsorption (liver, kidney)

Page 12: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

6

6

The Navy and PFCs

1960s 1970s Late 1980s-Early 1990s 2000s

United States Navy developed

AFFF for extinguishing liquid hydrocarbon fires.

Fire-fighting training exercises occur 3 to 4 times per year

at NAVSTA Newport.

NAVSTA Newport switches from using

Class B (protein-based foam) to

Class A (AFFF) on an installation-wide

scale.

Chemical industry begins to phase out

the use of AFFF containing PFCs. NAVSTA Newport

also phases out use of AFFF containing

PFCs.

Page 13: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

7

7

NAVFAC PFC Guidance The Naval Facilities Engineering Command (NAVFAC) has prepared Interim Perfluorinated Compounds Guidance/Frequently Asked Questions (Jan 2015) to assist Project Managers with programmatic and technical issues related to PFCs at Naval Environmental Restoration sites, including NAVSTA Newport NAVFAC PFC Guidance Highlights Investigation of PFCs Sampling and Analysis of PFCs Human Health Risk Assessment for PFCs Response to PFC Detections Remedial Actions for PFCs

NAVFAC PFC FAQs General/Definitions Investigation and Sampling Risk Assessment Remedial Response Considerations

Page 14: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

8

8

Does the Navy expect to find PFCs at NAVSTA Newport?

Yes. The first step in the Navy’s guidance is consider whether PFCs were potentially stored or used, and to develop a site-specific conceptual site model (CSM) for the locations where further assessment may be warranted

The Navy has identified approximately

50 areas that are being evaluated and considered for assessment relative to the potential for former use of PFCs

The most likely areas with PFCs at NAVSTA Newport are associated with former fire suppression systems and former firefighting training areas

Other potential areas within the Naval Station include the former landfill (McAllister Point), historic storage areas and buildings, and former plating shops

Building S42 in the Melville Area with former storage of AFFF

Page 15: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

9

9

What has the Navy accomplished relative to potential PFCs at NAVSTA Newport?

Developed an Initial PFC Assessment (Jun 2015)

Initiated an expanded “PFC Preliminary Assessment” (PA) after the identification of prior PFC storage and use with in the Melville area (Jun 2015)

Continued to review the historic potential storage and use of PFCs across the Naval Station, prioritizing assessment of the Melville area and portions of Tank Farms 4 and 5 (Sep 2015)

Developed Sampling and Analysis Plans and completed groundwater sampling for PFCs within the Melville Area and Tank Farms 4 and 5 (Oct/Nov 2015)

Continuing to review the inventory of potential PFC areas across the Naval Station with a prioritization schedule for continued sampling (Jan 2016)

Continuing to refine the PFC PA Report for regulatory review (Jan/Feb 2016)

Portable Fire Suppression Delivery Unit in the Melville Area

Page 16: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

10

10

What are the next steps planned relative to PFCs at NAVSTA Newport?

Continue to prepare and implement groundwater sampling plans that include the analysis of PFCs at all locations where the potential exists for PFCs (FY16, FY17)

Continue to work closely with EPA and Rhode Island Department of Environmental Management (RIDEM) on whether additional events are warranted based on the team’s findings and PFC results.

Page 17: MEETING AGENDA RESTORATION ADVISORY BOARD (RAB) …cat 2 other na x x tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd tbd Cat 3 NA 03/18/16 09/29/16 01/27/17 04/09/17 10/21/17

11

11

Questions or Comments?

Jim Gravette MIDLANT, North IPT

NAVFAC 757-341-2014

[email protected]

Deb Moore NAVSTA Newport

NAVFAC 401-841-1790

[email protected]

Nicole Cowand MIDLANT, North IPT

NAVFAC 757-341-2009

[email protected]