MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on...

33
AUGUST 2017 Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status www.ska.ac.za

Transcript of MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on...

Page 1: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

AUGUST 2017

Francois Kapp (on behalf the entire SKA South Africa team)

MeerKAT Status

www.ska.ac.za

Page 2: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

MeerKAT

Page 3: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

MeerKAT construction - Dishes 64 x 13.5m highly efficient offset Gregorian dishes spread over 8 km (~75% within ~1km diameter)

Page 4: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

MeerKAT construction – Feeds and Digitisers

Page 5: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

MeerKAT construction – Time and Frequency Reference

Page 6: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

MeerKAT construction – Correlator Beamformer

Page 7: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

MeerKAT construction – Array Releases

• Array releases: planned engineering milestones to enable early integration, test, verification and observations to support this

• AR1 – June 2016 • AR1.5 – March 2017 • AR2 – late 2017 • AR3 – Q2 2018

• Followed by commissioning and

then science use

Page 8: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

MeerKAT construction

Receivers: L-band receivers (0.9–1.67 GHz) UHF (0.58–1.0 GHz) S-band (1.75–3.5 GHz) X-band (8 – 14.5 GHz) planning stage

Page 9: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

Extremely good L-band performance - Tsys

Note: the resonant peak at 1420MHz is a measurement artifact that could not be calibrated out with sufficient accuracy

Page 10: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

Extremely good L-band performance – Ae/Tsys

Page 11: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

KAT-7 (engineering testbed) image in 2012

Page 12: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

4-dish MeerKAT in May 2016 (commissioning)

Page 13: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

16-dish MeerKAT in June 2016 (Array Release 1)

1% of First Light image

Page 14: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

Page 15: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

Page 16: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

Page 17: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

Page 18: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

Page 19: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

Technical challenges

Page 20: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

MeerKAT Data Rates

Page 21: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

MeerKAT SDP Hardware Landscape

1.6 PFLOPs (GPU)

23 PBytes (Disk - CEPH)

40 PBytes (Tape)

Page 22: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

● 32 dishes available (square surrounding core is 1.2 km on the side)

● SKA SA commissioning team making a variety of observations to test telescope

● Closer commissioning interaction with LSP teams starting in May 2017

Array configuration in April 2017

Page 23: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

Commissioning in April 2017, up to 32 antennas

Page 24: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

● 4K channels

● 16 antennas dual-polarisation

● 12 hour track observed on 2017-04-04

● Imaged with 2 x phase + 1 x amplitude self-calibration on 16 s timescale

● With Briggs -0.5 weighting image has 9 μJy/beam (vs 10 μJy/beam in June 2016 image)

● Thermal is ~8.5 μJy/beam

● 1800 sources in central degree of field (vs 1400 in first light image)

“DEEP2 “

Early 8 km-baseline observations

Page 25: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

Array layout

Page 26: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

(Tom Mauch)

FRII type galaxy – offset vs centred

Page 27: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

● 32K channels (140 imaged)

● 16 core antennas, dual polarisation

● 9 hour track, 2017-04-05

● Mosaic: 7 pointings

● ~50 minutes per pointing

● Min baseline (projected): 16 m

● Max baseline: 711 m

● Beam 90x70 arcsec

● Measured rms 2.8 mJy (emission-free chan) vs 2.3 theoretical

(Spiral galaxy at 5 Mpc discovered in Cape Town in 1752 by Louis de La Caille)

HI emission in M83

Page 28: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

M83 (Sean Passmoor)

Page 29: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

● 8 channel binning

● No self-cal or primary beam corrections

● Imaged using wsclean:

● Multifrequency synthesis (7 channels)

● Multiscale (largest scale ~70 arcmin)

● Briggs robust 0

● Beamsize 58x64 arcsec

G330.89-0.36 star forming region (continuum, 32k mode)

● ATCA SGPS: 5 configs, 30 m – 3 km baselines

● Smoothed resolution 100 arcsec, sensitivity up to ~30 arcmin

ATCA (Sharmila Goedhart)

Page 30: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

● Hint of extended source in SUMSS

● 7-point MeerKAT mosaic in 4K mode

● Radio source (blue) angular size = 0.8 deg; elliptical galaxy (red/IR) at z = 0.02; linear size = 1.2 Mpc: GRG

(Nadeem Oozeer)

A newly identified Giant Radio Galaxy

Page 31: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

An extra (cool) detection in the new DEEP2 pointing (Spiral galaxy in continuum [and optical] at 70 Mpc)

Page 32: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

www.ska.ac.za

● AR2 within weeks

● AR3 within months (Q2 2018)

● Many hours of Commissioning

● Formal operations

● Eventually: Integration with SKA1…

MeerKAT: What is next?

Page 33: MeerKAT Status AUGUST 2017 Francois Kapp (on behalf the ... · AUGUST 2017 . Francois Kapp (on behalf the entire SKA South Africa team) MeerKAT Status . . MeerKAT . MeerKAT construction

Thanks

SKA South Africa, a Business Unit of the National Research Foundation, is supervising South Africa’s involvement in the SKA on behalf of the Department of Science & Technology.