Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to...
-
Upload
meagan-carroll -
Category
Documents
-
view
225 -
download
2
Transcript of Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to...
• Construction Progress Payments– Contractor gives a bill for progress to RPR
• Outlines what bill is for• Give details as needed (quantities)
– RPR reviews• Approves (sends to owner) or disapproves (calls
contractor)
– Contractor gets paid
• Approval of Payment Requests– RPR responsible for checking quantities and
costs• Quantity take off• Inventory of equipment and materials on site but
not used• Field measure work completed or claimed• Construction Cost Estimate of all completed work• Audit of Invoices and costs• Review of claims for extra work and completed
change orders• Check of retention amount• Check method used for profit and overhead,
material costs for estra work or change orders
• Basis for Payment Amounts– Accuracy of field measurements determined
by contract type– Lump sum contracts do not need accurate
field measurements– Cost plus or Unit price contracts need very
accurate field measurements• Pg 432
Schedule of Values v. Cost loaded CPM Schedule
• Unit Price Contracts– Do not call for Cost Loaded CPM Schedule
• Conflicts with line items on unit price sheet
– Do not call for schedule of Values– A breakdown of all line items is submitted w/
contractor’s bid and is binding throughout job
• Lump Sum Contracts with Cost Loaded CPM– Do not ask for Schedule of Values – cost loaded CPM
is equal– Request Cost loaded CPM be submitted before first
pay period ends
• Lump Sum Contracts w/o Cost loaded CPM– Do not ask for a cost loaded CPM schedule– Do not ask for a bid breakdown– Request a schedule of values before starting work on
project
Evaluation of Contractor’s Payment Requests
• Contractor submits request for payment at a prearranged date each month for previous month’s work– Lump sum contract – payment based on a fair
estimate of work completed plus overhead and profit– Unit Price Contracts – contractor gets paid based on
quantity used – RPR must have accurate field measurements
• +/- 25 % is okay more or less allows for renegotiations by either party
• Equipment And Materials delivered but not used– Contractor brings stuff on site early
• May try to bill owner since stuff is on site• Contractor only paid when stuff is used• Includes materials used but not completed – pipe
not paid for until covered and tested• Unit price contracts are usually for installed in
place materials – on site is not in place• Can make exceptions for long lead items which
arrive on site early
• Force Account– Daywork or for any type of cost plus payment– In US associated with extra work and change
orders– May be used to pay contractor when it is
difficult to provide adequate measurements or estimate cost of certain items of work
– Should be last choice when setting up items for payment
Force Account
– Change order is a must – Force account payments not authorized for
supers. Allowances for supers is in contractors O&P. Foremen working full time on item would be covered by account
– PM has authority to direct every aspect of force account work
• PM and Contractor must agree on • Labor
– Classification and approximate N of workers, wage rates, travel allowance, subsistence, are foremen included
• Equipment– Types to be used including size, rating, capacity,
which indicate that item can do work required, owned or leased, cost per hour for use
• Materials– Cost and freight charges, purchased for project or
from contractor’s stock
• PM prepares lists of equipment and labor classifications actually used and corresponding rates– Equipment list includes complete
nomenclature of the equipment to establish rental rate from a Rental Rate Book
– Labor list includes labor classification and composite hourly rate (basic wage + added costs listed in DOT standard specs)
• Payments for Extra Work and Change Orders– Usually laid out in Contract– Common is cost plus with a reasonable
allowance for O&P– State agencies may allow 15, 20, 24,33 % on
labor and then 15% on equipment, 15% on materials 5% on primary subs (not subs subs)
– RPR must evaluate all change orders and requests for payment of extra work
– RPR should consult PM or owner to determine the exact terms of the agreement that cover extra work
– RPR keeps daily record of extra work performed and materials used
• Mobilization Costs– Initial expenditures contractor makes before
any work towards progress payment– Permits, insurance, bonds– Equipment – Tools and supplies to do work– Field Office
• Make it a fixed cost that is on every bid– Contractor cannot inflate
• Make sure that all items allowed in the mobilization cost are listed– Can then either– Prorate mobilization based on % complete– Or Lump sum when all complete
• Other items to include– RPR Field Office & Utilities &
Communications– Pg 448
Mobilization
• Lump Sum Projects– Mobilization terms must be in a separate
technical section– Lump sum for mobilization
• Unit Price Projects– Part of Measurement and Payment section
with a separate line item and an A/E determined cost
Partial Payment to Contractor
• Waiver of Lien Procedure– After each progress payment GC, subs,
suppliers all sign waivers of liens for that payment
– Owner knows subs and suppliers are paid– Limits the amount of the lien to only what has
not been paid
• Total Cost Pricing of Change Orders– Compares total cost to do work with bid cost
to do work, owner pays difference– Allowed when
• Nature of claim makes it v. difficult to establish an accurate price
• Contractor’s bid was realistic• Contractor’s costs were realistic• Contractor’s actual costs were realistic• Contractor was not responsible for any of the
increased cost
• Forward pricing of Change ordersGC and Owner establish a mutually agreed
lump sum payment for work
Contractor cannot be forced to forward price work
Contractor needs to make sure price is right – they are stuck with it
• Retainage– 5 – 10% of contract price– Gives owner $ to satisfy lien claims if GC
does not pay– Also is the profit– Can do either a lump sum or it can be
computed based on each months progress payments
– Retainage given to GC 35 days after completion of work if
– all lien releases turned in– All employees paid– Approval of the performance insurance CO.– GC gets all but the amount representing the
value of uncompleted or substandard work or materials.
• Liquidated Damages during construction– Can have liquidated damages for missed
milestones• Throws other contractors behind• Deduct from next progress payment
Interpreting the Contractor’s Bid
• Bidding Errors– Mathematical errors (unit price x quantity)
• Adding up bid items
– Ask for values in words and numbers• Words rule
– GC may or may not get released from bid
• Unbalanced Bids– Contractor raises prices on some items and
lowers prices on others w/o changing total project cost
– Should be rejected if found
• Why do unbalanced bids– To discourage certain types of construction
and encourage others that the Contractor is good at
– Contractor thinks A/E estimate is low can make unit price high and make extra profit
– Increase unit prices on first items of work to be completed => receive excessive early payments then default on the job
• Leaves Surety with too little $ to do job
• Can build up working capital – eliminates squeeze due to 10% retention
• Detecting an Unbalanced Bid– Usually an unbalanced bid indicates and A/E
error in estimate– Use a spreadsheet to compare bids to find
wide swings in bid prices• All contractor’s should be in the same price range
if normal bid