MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
Click here to load reader
Transcript of MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 1/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 1 of 11
A B
A : Approved B : Comment
A7 HH 21/12/2013
A6 HH 21/12/2013
A5 VM HH 19/12/2013
A4 VM HH 17/12/2013
A3 VM HH 16/12.2013
A2 YK HH 13/12/2013
A1 YK HH 12/12/2013
Rev. PREP'D CHK'D DATE
COMMERCIAL PROPOSAL
DOC NO: MG-1061T-CC-BOQ-0002
1ha the concrete laydown area at the
Schlumberger base.
Quotation.
CLIENT APPROVAL
STATUS
NAME
TITLE
DATE
SIGNATURE
Issued for review and comments
Single discipline check
Subject
TITLE:
Issued for review and comments
Single discipline check
Description APPR'D
Issued for review and comments
Issued for review and comments
Single discipline check
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 2/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 2 of 11
Job No: MCG-1061T
Client: Schlumberger Logelco Inc. - Baku Office
Subject:
Title:
Civil works
I Earth Works
1 Area leveling with bulldozer m2 10800 1.02 11016
2 Removed soil m3 13747
2.1 Removal rocky soil (45%) m3 6278 14.0 87892
2.2 Removal of loose soil (55%) m3 7469 7.77 58034
Total 156942
II Laydown Area General
3
Cleaning of the area and preparation for
construction m2 10034 1.02 10234
4
Crushed stone infill with compaction of each layer,
compacting factor -0.85, depth of 150 mm (labour
cost) m2 9075 1.75 1588
4,1 Crushed stone М1200-1000, fraction 40-70mm m3 1361.25 23.40 31853
5 Concrete, grade B 10 (material price) m3 453.75 97.50 44240
5,1 Concrete blinding depth of 50 mm (labour cost) m2 9075 3.11 28223
6 Hydro insulation Polyethylene layer setting m2 9075 0.78 7078
6,1 Polyethylene 200 micron m2 9075 1.04 9438
7 Monolithic RC concrete slab width 200 mm m2 9075 10.50 95287
7.1 Concrete, grade В 25 m3 1815 117.00 212355
7.2 Rebar Ø10 mm А-400, 35ГС t 117.58 1043.90 12274
7.3 Rebar Ø20 mm А-400, 35ГС t 1.74 1043.90 1816
7.4
PE pipe Ø32 for connection of rebar Ø20 mm А-400, L=500mm ea 740 0.65 48
Total 579631
1ha the concrete laydown area at the Sсhlumberger base.
Total
(AZN)
Quotation.
Description Qnty. UnitItem
No.Unit Price in AzN
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 3/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 3 of 11Job No: MCG-1061T
Client: Schlumberger Logelco Inc. - Baku Office
Subject:
Title:
1ha the concrete laydown area at the Sсhlumberger base.
Total
(AZN)
Quotation.
Description Qnty. Unit
Item
No. Unit Price in AzN
III Drain pit installation
8 Drain pit installation ea 7 581.49 4070
9 Crushed stone infill 100mm m2 20.23 1.40 28
9.1 Crushed stone М1200-1000, fraction 40-70mm m3 2.02 23.40 47
9.2 Concrete blinding, grade B 10 m3 1.01 143.00 144
9.3
Concrete grade B25, aggregate fraction 5-20, F150,
W6 m3 10.43 117.00 1220
9.4 Rebar Ø10 mm A400, 35GS kg 0.63 1.04 0
9.5 Pit cover GOST 3634-89 ea 7 280.00 1960
Total 7471
IV Rainwater drainage system
10 Arrangement of the inlet well for drainage channel l.m 530 38.85 20590
11 Crushed stone infill m2 371 1.40 519
11.1 Crushed stone М1200-1000, fraction 40-70mm m3 31.8 23.40 744
12 Arrangement of concrete blinding width of 50 mm m2 371 2.89 1072
12.1 Concrete blinding, 50 mm m3 10.6 97.50 1033
13 Hydro insulation Polyethylene layer setting m2 477 0.72 343
13.1 Polyethylene 200 micron m2 477 1.04 496
14 Monolithic RC concrete slab width 200 mm m2 95.4 10.50 100
14.1 Concrete, grade B25, fraction 5-20, F150, W6 m3 95.4 117.00 1116
14.2 Rebar Ø10 mm A400, 35GS Ton 8.162 1043.90 8520
14.3 Angle 30x30x5 steel, GOST 8509-86 kg 2310.8 1.04 2403
15
Steel grating drain cover, grid size 750x400x30,
Art.28 343 ea 706.67 84.50 59713
Total 107599
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 4/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 4 of 11Job No: MCG-1061T
Client: Schlumberger Logelco Inc. - Baku Office
Subject:
Title:
1ha the concrete laydown area at the Sсhlumberger base.
Total
(AZN)
Quotation.
Description Qnty. Unit
Item
No. Unit Price in AzN
V Reinforced concrete ramp
16 Crushed stone infill – 200 mm m2 48 2.45 117
16.1
Crushed stone M800-600, fraction 40-70mm, GOST
8267-93* m3 7.2 23.40 168
17 Concrete blinding, 50 mm m2 48 2.80 134
17.1 Concrete, grade B 10 m3 2.4 97.50 234
18
Concrete cover production and installation - 200
mm m2 48 8.40 403
18.1 Concrete grade B25, fraction 5-20, F150, W6 m3 9.6 117.00 1123
18.2 Rebar Ø10 mm А-400, 35ГС ton 0.62 1043.90 647
Total 2828
VI Foundation for lighting
19 Foundation excavation ea 8 98.00 784
20 Crushed stone filling m3 0.29 11.73 3
20.1
Crushed stone M800-600, fr. 40-70mm, GOST 8267-
93 * m3 0.29 23.40 6
21 Concrete grade B25, fraction 5-20, F150, W6 m3 6.4 117.00 748
21.1 Rebar Ø8 mm А-240, 35ГС ton 0.12 1043.90 125
21.2 Rebar Ø14 mm А-400, 35ГС ton 0.61 1043.90 636
21.3 Plastic conduit Ø100 L=3m ea 16 2.60 4
21.4 Anchor bolts Ø24 GOST 24379.1-80 ea 64 15.60 998
Total 3345
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 5/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 5 of 11Job No: MCG-1061T
Client: Schlumberger Logelco Inc. - Baku Office
Subject:
Title:
1ha the concrete laydown area at the Sсhlumberger base.
Total
(AZN)
Quotation.
Description Qnty. Unit
Item
No. Unit Price in AzN
VII Manholes 1.5m x 1.5m
22 Foundation excavation ea 2 154.00 308
23 Crushed stone filling m2 8.82 1.75 15
23.1
Crushed stone M800-600, fr. 40-70mm, GOST 8267-
93 * m3 0.88 23.40 20
24 Concrete blinding width of 50 mm m2 8 2.80 22
24.1 Concrete , grade B 10 m3 0.4 97.50 39
24.2Manhole preparation, concrete grade B25, fraction5-20, F150, W6 m3 6.88 126.00 86
24.3 Rebar А-400, 35ГС t 0.41 1141.25 467
Total 1740
VIII Manholes 1.5m x 1.0m
25 Foundation excavation ea 12 154.00 1848
26 Crushed stone filling m2 40.32 1.75 70
26.1
Crushed stone M800-600, fr. 40-70mm, GOST 8267-
93 * m3 4.03 23.40 94
27 Concrete blinding width of 50 mm m2 36 2.80 100
27.1 Concrete, grade B 10 m3 1.44 97.50 140
27.2
Manhole preparation, concrete grade B25, fraction
5-20, F150, W6 m3 34.24 182.00 623
27.3 Rebar А-400, 35ГС t 1.64 1155.00 1894
Total 10379
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 6/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 6 of 11Job No: MCG-1061T
Client: Schlumberger Logelco Inc. - Baku Office
Subject:
Title:
1ha the concrete laydown area at the Sсhlumberger base.
Total
(AZN)
Quotation.
Description Qnty. Unit
Item
No. Unit Price in AzN
IX Manholes 1.0m x 1.0m
28 Foundation excavation ea 2 98.00 196
29 Crushed stone filling m2 3.92 1.75 6
29.1
Crushed stone M800-600, fr. 40-70mm, GOST 8267-
93 * m3 0.39 25.20 9
30 Concrete blinding width of 50 mm m2 3.38 2.80 9
30.1 Concrete, grade B 10 m3 0.17 105.00 1
30.2
Manhole preparation, concrete grade B25, fraction
5-20, F150, W6 m3 4.62 182.00 840
30.3 Rebar А-400, 35ГС t 0.28 1155.00 323
Total 1404
X Electrical pipes Ø150
31 Installation of the inlet well for electrical pipes m 422.5 114.80 48503
31.1 Plastic pipe Ø150 m 2414.5 11.70 28249
Total 76752
XI Gates
32
Electrical driven gates 10mx2m. Gate shall be
similar to those already installed in Schlumberger
facility. Contractor shall visit the site to inspect gate
during tender period. ea 1 9750.00 9750
Total 9750
Total for Civil works 957844
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 7/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 7 of 11Job No: MCG-1061T
Client: Schlumberger Logelco Inc. - Baku Office
Subject:
Title:
1ha the concrete laydown area at the Sсhlumberger base.
Total
(AZN)
Quotation.
Description Qnty. Unit
Item
No. Unit Price in AzN
Electrical works
I
L g t ng an Power supp y system.
Equipment
1 650kVA Diesel Generator ea 1 123900.00 123900
2 Distribution board with following items: ea 1 2030.00 2030
2.1 - Three phase isolator 100A ea 1 338.00 338
2.2
- Single phase residual current circuit breaker, 16A,
30mA ea 2 132.60 265
2.3
- Single phase residual current circuit breaker, 20A,
30mA ea 2 149.50 299
2.4
- Single phase residual current circuit breaker, 25A,
30mA ea 1 149.50 149
2.5
- Single phase residual current circuit breaker, 40A,
30mA ea 1 156.00 156
2.6
- Single phase residual current circuit breaker, 63A,
30mA ea 3 195.00 585
2.7
- Three phase residual current circuit breaker, 16A,
30mA ea 1 253.50 253
2.8
- Three phase residual current circuit breaker, 32A,
30mA ea 5 273.00 1365
2.9 - Single-phase circuit breaker, 6A ea 2 20.80 4
2.10 - Single-phase circuit breaker, 20A ea 6 19.50 117
3 Photocell ea 2 312.00 624
4 20A Single Pole Contactor ea 5 58.50 292
5 25A Single Pole Contactor ea 1 58.50 58
6
High mast for 1x400W Floodlight lighting fixture
(h=16m) ea 8 3640.00 29120
7 1x400W Floodlight lighting fixture, IP65 ea 44 293.80 12927
8 Junction box, IP 65 ea 33 10.92 360
9 Start / Stop Push Button, IP 65 ea 2 39.52 79
10 16A,220V Industrial type socket outlet, IP 66 ea 8
11 16A,380V Industrial type socket outlet, IP 66 ea 8
Total 177381
552.50 4420
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 8/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 8 of 11Job No: MCG-1061T
Client: Schlumberger Logelco Inc. - Baku Office
Subject:
Title:
1ha the concrete laydown area at the Sсhlumberger base.
Total
(AZN)
Quotation.
Description Qnty. Unit
Item
No. Unit Price in AzN
II Cable Tray System and Accessories
12 50mm Wide Cable Tray with Cover (length -3m) ea 17 30.91 525
13 Stand-off bracket for 50mm Wide Cable Tray ea 35 3.22 112
14 M8 Bolt, nut, washers (100 e.a in the pack) pack 1 35.00 35
Total 673
III Earthing & Lightning Protection Systems
15 Copper Earthing Rod ∅17.2mm, L=3000mm ea 19 84.56 1606
16 Air Rod ∅15mm, L=1000mm ea 8 331.66 2653
17 Concrete Inspection Earthing Pit ea 4 47.46 189
18 Execution of Exotermic Welding ea 42 86.94 365
19
Ring Type Cable Lugs for 1cx6mm² Ø6mm (100e.a in the pack) pack 2 39.00 78
20
Ring Type Cable Lugs for 1cx6mm² Ø8mm (100e.a in the pack) pack 2 41.60 83
21 Ring Type Cable Lugs for 1cx70mm² Ø10mm ea 19 3.25 6
22 1cx70mm2 CU/XLPE Cable Green-Yellow ea 340 10.14 3447
23 1cx150mm2 CU/XLPE Cable Green-Yellow ea 715 25.09 1793924 1cx6mm2 CU/XLPE Cable Green-Yellow ea 150 2.60 390
Total 30101
IV Cable & Cable Gland.
25 of 3cx 2.5mm² Cu/XLPE/SWA/PVC m 690 3.64 251
26 3cx 4mm² Cu/XLPE/SWA/PVC m 100 4.34 434
27 3cx 6mm² Cu/XLPE/SWA/PVC m 215 4.76 1023
28 3cx 10mm² Cu/XLPE/SWA/PVC m 300 9.10 2730
29 3cx 16mm² Cu/XLPE/SWA/PVC m 515 13.16 6777
303cx 25mm² Cu/XLPE/SWA/PVC
m 83014.70 1220
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 9/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 9 of 11Job No: MCG-1061T
Client: Schlumberger Logelco Inc. - Baku Office
Subject:
Title:
1ha the concrete laydown area at the Sсhlumberger base.
Total
(AZN)
Quotation.
Description Qnty. Unit
Item
No. Unit Price in AzN
31 3cx 50mm² Cu/XLPE/SWA/PVC m 400 21.84 8736
33 5cx 2.5mm² Cu/XLPE/SWA/PVC m 160 14.00 2240
34 5cx 4mm² Cu/XLPE/SWA/PVC m 55 16.80 924
35 5cx 6mm² Cu/XLPE/SWA/PVC m 50 20.30 1015
36 5cx 10mm² Cu/XLPE/SWA/PVC m 300 22.96 6888
37 5cx 16mm² Cu/XLPE/SWA/PVC m 600 26.60 15960
38 5cx 150mm² Cu/XLPE/SWA/PVC m 480 106.12 50937
39 Cable gland M20 ea 5 44.80 224
40 Cable gland M25 ea 2 44.80 89
41 Cable gland M32 ea 12 49.00 588
42 Cable gland M40 ea 4 49.00 196
43 Cable gland M50 ea 1 63.00 63
Total 113538
V Accessories.
44 Plastic tie-wrap, L=150mm (100 ea. in the pack) pack 7 4.90 34
45 Cable labels set 1 2590.00 2590
Total 2624
VI Installation cost for electrical works 9942
Total for Electrical works 334261
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 10/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 10 of 11Job No: MCG-1061T
Client: Schlumberger Logelco Inc. - Baku Office
Subject:
Title:
1ha the concrete laydown area at the Sсhlumberger base.
Total
(AZN)
Quotation.
Description Qnty. Unit
Item
No. Unit Price in AzN
Mechanical works
I Water System For Laydown Area
1 Pipe PPR Ø25 (Turkey) M 420 4.62 1940
2 Elbow 90° PPR Ø25 (Turkey) ea 16 1.68 26
3 Elbow 45° PPR Ø25 (Turkey) ea 5 0.00 0
4 T-Branch-90˚ PPR Ø25 (Turkey) ea 7 1.68 1
5 Ball valve PPR Ø25 (Turkey) ea 10 25.20 252
6 Pump (Wilo Velo Norm 50/200) ea 14200.00 4200
Total6431
II Firefighting System For Laydown Area
7Pipe CS ASTM A 106 GR B SMLS SCH 40 BE. ASME
B36.10B (Turkey)m 600
43.40 26040
8Elbow-90° SCH 40 LR, BE CS ASTM A234 GR WPB.
ASME B16.9 (Turkey)
ea 10
42.00 420
9T-Branch-90° SCH 40 LR, BE CS ASTM A234 GRWPB. ASME B16.9 (Turkey)
ea 537.80 189
10Ball Valve CS CL150 ASTM A216-WCB. ASME
B16.10 (Turkey)ea 3
28.00 84
11Flange WN CL150 RF CS ASTM A105. ASME B16.5
(Turkey)ea 4
238.00 952
12Blind Flange WN CL150 RF CS ASTM A105. ASME
B16.5 (Turkey)ea 3
476.00 1428
13 Gasket FLAT RNG CL150 UNGRAPHITED BOTHSIDES. ASME B16.21 (Turkey)
ea 632.20 193
14Stud Bolts W/2 HVY HEX NUT ALLY. ASTM A193
B7/A194 2H GLV & CTRFGD. ASME 18.2 (Turkey)ea 48
8.40 403
15 Aboveground Hydrant (Turkey) ea 32660.00 7980
Total 37689
8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area
http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 11/11
Doc No: MG-1061T-CC-BOQ-0002
Rev: A7
Date: December 21,2013
Page: 11 of 11Job No: MCG-1061T
Client: Schlumberger Logelco Inc. - Baku Office
Subject:
Title:
1ha the concrete laydown area at the Sсhlumberger base.
Total
(AZN)
Quotation.
Description Qnty. Unit
Item
No. Unit Price in AzN
III Installation cost
1 Firefighting System 11205
2 Water System For Laydown Area 1466
Total 12672
Total for Water and Firefighting Systems 56792
Total by BOQ 1348898
Note:
These prices are exclusive of VAT and valid till of the end 2013
This Quotation is calculated according to BOQ provided by client. In case if discrepances between mention
above BOQ and the design drawings the prices will be revised accordingly