MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

11

Click here to load reader

Transcript of MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

Page 1: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 1/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 1 of 11

 A B

 A : Approved B : Comment

 A7 HH 21/12/2013

 A6 HH 21/12/2013

 A5 VM HH 19/12/2013

 A4 VM HH 17/12/2013

 A3 VM HH 16/12.2013

 A2 YK HH 13/12/2013

 A1 YK HH 12/12/2013

Rev. PREP'D CHK'D DATE

COMMERCIAL PROPOSAL

DOC NO: MG-1061T-CC-BOQ-0002

1ha the concrete laydown area at the

Schlumberger base.

Quotation.

CLIENT APPROVAL

STATUS

NAME

TITLE

DATE

SIGNATURE

Issued for review and comments

Single discipline check 

Subject

TITLE:

Issued for review and comments

Single discipline check 

Description APPR'D

Issued for review and comments

Issued for review and comments

Single discipline check 

Page 2: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 2/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 2 of 11

Job No: MCG-1061T

Client: Schlumberger Logelco Inc. - Baku Office

Subject:

Title:

Civil works

I Earth Works

1 Area leveling with bulldozer m2 10800 1.02 11016

2 Removed soil m3 13747

2.1 Removal rocky soil (45%) m3 6278 14.0 87892

2.2 Removal of loose soil (55%) m3 7469 7.77 58034

Total 156942

II Laydown Area General

3

Cleaning of the area and preparation for

construction m2 10034 1.02 10234

4

Crushed stone infill with compaction of each layer,

compacting factor -0.85, depth of 150 mm (labour

cost) m2 9075 1.75 1588

4,1 Crushed stone М1200-1000, fraction 40-70mm m3 1361.25 23.40 31853

5 Concrete, grade B 10 (material price) m3 453.75 97.50 44240

5,1 Concrete blinding depth of 50 mm (labour cost) m2 9075 3.11 28223

6 Hydro insulation Polyethylene layer setting m2 9075 0.78 7078

6,1 Polyethylene 200 micron m2 9075 1.04 9438

7 Monolithic RC concrete slab width 200 mm m2 9075 10.50 95287

7.1 Concrete, grade В 25 m3 1815 117.00 212355

7.2 Rebar Ø10 mm А-400, 35ГС t 117.58 1043.90 12274

7.3 Rebar Ø20 mm А-400, 35ГС t 1.74 1043.90 1816

7.4

PE pipe Ø32 for connection of rebar Ø20 mm А-400, L=500mm ea 740 0.65 48

Total 579631

1ha the concrete laydown area at the Sсhlumberger base.

Total

(AZN)

Quotation.

Description Qnty. UnitItem

No.Unit Price in AzN

Page 3: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 3/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 3 of 11Job No: MCG-1061T

Client: Schlumberger Logelco Inc. - Baku Office

Subject:

Title:

1ha the concrete laydown area at the Sсhlumberger base.

Total

(AZN)

Quotation.

Description Qnty. Unit

Item

No. Unit Price in AzN

III Drain pit installation

8 Drain pit installation ea 7 581.49 4070

9 Crushed stone infill 100mm m2 20.23 1.40 28

9.1 Crushed stone М1200-1000, fraction 40-70mm m3 2.02 23.40 47

9.2 Concrete blinding, grade B 10 m3 1.01 143.00 144

9.3

Concrete grade B25, aggregate fraction 5-20, F150,

W6 m3 10.43 117.00 1220

9.4 Rebar Ø10 mm A400, 35GS kg 0.63 1.04 0

9.5 Pit cover GOST 3634-89 ea 7 280.00 1960

Total 7471

IV Rainwater drainage system

10 Arrangement of the inlet well for drainage channel l.m 530 38.85 20590

11 Crushed stone infill m2 371 1.40 519

11.1 Crushed stone М1200-1000, fraction 40-70mm m3 31.8 23.40 744

12 Arrangement of concrete blinding width of 50 mm m2 371 2.89 1072

12.1 Concrete blinding, 50 mm m3 10.6 97.50 1033

13 Hydro insulation Polyethylene layer setting m2 477 0.72 343

13.1 Polyethylene 200 micron m2 477 1.04 496

14 Monolithic RC concrete slab width 200 mm m2 95.4 10.50 100

14.1 Concrete, grade B25, fraction 5-20, F150, W6 m3 95.4 117.00 1116

14.2 Rebar Ø10 mm A400, 35GS Ton 8.162 1043.90 8520

14.3 Angle 30x30x5 steel, GOST 8509-86 kg 2310.8 1.04 2403

15

Steel grating drain cover, grid size 750x400x30,

 Art.28 343 ea 706.67 84.50 59713

Total 107599

Page 4: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 4/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 4 of 11Job No: MCG-1061T

Client: Schlumberger Logelco Inc. - Baku Office

Subject:

Title:

1ha the concrete laydown area at the Sсhlumberger base.

Total

(AZN)

Quotation.

Description Qnty. Unit

Item

No. Unit Price in AzN

 V Reinforced concrete ramp

16 Crushed stone infill – 200 mm m2 48 2.45 117

16.1

Crushed stone M800-600, fraction 40-70mm, GOST

8267-93* m3 7.2 23.40 168

17 Concrete blinding, 50 mm m2 48 2.80 134

17.1 Concrete, grade B 10 m3 2.4 97.50 234

18

Concrete cover production and installation - 200

mm m2 48 8.40 403

18.1 Concrete grade B25, fraction 5-20, F150, W6 m3 9.6 117.00 1123

18.2 Rebar Ø10 mm А-400, 35ГС ton 0.62 1043.90 647

Total 2828

 VI Foundation for lighting

19 Foundation excavation ea 8 98.00 784

20 Crushed stone filling m3 0.29 11.73 3

20.1

Crushed stone M800-600, fr. 40-70mm, GOST 8267-

93 * m3 0.29 23.40 6

21 Concrete grade B25, fraction 5-20, F150, W6 m3 6.4 117.00 748

21.1 Rebar Ø8 mm А-240, 35ГС ton 0.12 1043.90 125

21.2 Rebar Ø14 mm А-400, 35ГС ton 0.61 1043.90 636

21.3 Plastic conduit Ø100 L=3m ea 16 2.60 4

21.4  Anchor bolts Ø24 GOST 24379.1-80 ea 64 15.60 998

Total 3345

Page 5: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 5/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 5 of 11Job No: MCG-1061T

Client: Schlumberger Logelco Inc. - Baku Office

Subject:

Title:

1ha the concrete laydown area at the Sсhlumberger base.

Total

(AZN)

Quotation.

Description Qnty. Unit

Item

No. Unit Price in AzN

 VII Manholes 1.5m x 1.5m

22 Foundation excavation ea 2 154.00 308

23 Crushed stone filling m2 8.82 1.75 15

23.1

Crushed stone M800-600, fr. 40-70mm, GOST 8267-

93 * m3 0.88 23.40 20

24 Concrete blinding width of 50 mm m2 8 2.80 22

24.1 Concrete , grade B 10 m3 0.4 97.50 39

24.2Manhole preparation, concrete grade B25, fraction5-20, F150, W6 m3 6.88 126.00 86

24.3 Rebar А-400, 35ГС t 0.41 1141.25 467

Total 1740

 VIII Manholes 1.5m x 1.0m

25 Foundation excavation ea 12 154.00 1848

26 Crushed stone filling m2 40.32 1.75 70

26.1

Crushed stone M800-600, fr. 40-70mm, GOST 8267-

93 * m3 4.03 23.40 94

27 Concrete blinding width of 50 mm m2 36 2.80 100

27.1 Concrete, grade B 10 m3 1.44 97.50 140

27.2

Manhole preparation, concrete grade B25, fraction

5-20, F150, W6 m3 34.24 182.00 623

27.3 Rebar А-400, 35ГС t 1.64 1155.00 1894

Total 10379

Page 6: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 6/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 6 of 11Job No: MCG-1061T

Client: Schlumberger Logelco Inc. - Baku Office

Subject:

Title:

1ha the concrete laydown area at the Sсhlumberger base.

Total

(AZN)

Quotation.

Description Qnty. Unit

Item

No. Unit Price in AzN

IX Manholes 1.0m x 1.0m

28 Foundation excavation ea 2 98.00 196

29 Crushed stone filling m2 3.92 1.75 6

29.1

Crushed stone M800-600, fr. 40-70mm, GOST 8267-

93 * m3 0.39 25.20 9

30 Concrete blinding width of 50 mm m2 3.38 2.80 9

30.1 Concrete, grade B 10 m3 0.17 105.00 1

30.2

Manhole preparation, concrete grade B25, fraction

5-20, F150, W6 m3 4.62 182.00 840

30.3 Rebar А-400, 35ГС t 0.28 1155.00 323

Total 1404

 X  Electrical pipes Ø150

31 Installation of the inlet well for electrical pipes m 422.5 114.80 48503

31.1 Plastic pipe Ø150 m 2414.5 11.70 28249

Total 76752

 XI Gates

32

Electrical driven gates 10mx2m. Gate shall be

similar to those already installed in Schlumberger

facility. Contractor shall visit the site to inspect gate

during tender period. ea 1 9750.00 9750

Total 9750

Total for Civil works 957844

Page 7: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 7/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 7 of 11Job No: MCG-1061T

Client: Schlumberger Logelco Inc. - Baku Office

Subject:

Title:

1ha the concrete laydown area at the Sсhlumberger base.

Total

(AZN)

Quotation.

Description Qnty. Unit

Item

No. Unit Price in AzN

Electrical works

I

L g t ng an Power supp y system.

Equipment

1 650kVA Diesel Generator ea 1 123900.00 123900

2 Distribution board with following items: ea 1 2030.00 2030

2.1 - Three phase isolator 100A ea 1 338.00 338

2.2

 - Single phase residual current circuit breaker, 16A,

30mA ea 2 132.60 265

2.3

 - Single phase residual current circuit breaker, 20A,

30mA ea 2 149.50 299

2.4

 - Single phase residual current circuit breaker, 25A,

30mA ea 1 149.50 149

2.5

 - Single phase residual current circuit breaker, 40A,

30mA ea 1 156.00 156

2.6

 - Single phase residual current circuit breaker, 63A,

30mA ea 3 195.00 585

2.7

 - Three phase residual current circuit breaker, 16A,

30mA ea 1 253.50 253

2.8

 - Three phase residual current circuit breaker, 32A,

30mA ea 5 273.00 1365

2.9 - Single-phase circuit breaker, 6A ea 2 20.80 4

2.10 - Single-phase circuit breaker, 20A ea 6 19.50 117

3 Photocell ea 2 312.00 624

4 20A Single Pole Contactor ea 5 58.50 292

5 25A Single Pole Contactor ea 1 58.50 58

6

High mast for 1x400W Floodlight lighting fixture

(h=16m) ea 8 3640.00 29120

7 1x400W Floodlight lighting fixture, IP65 ea 44 293.80 12927

8 Junction box, IP 65 ea 33 10.92 360

9 Start / Stop Push Button, IP 65 ea 2 39.52 79

10 16A,220V Industrial type socket outlet, IP 66 ea 8

11 16A,380V Industrial type socket outlet, IP 66 ea 8

Total 177381

552.50 4420

Page 8: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 8/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 8 of 11Job No: MCG-1061T

Client: Schlumberger Logelco Inc. - Baku Office

Subject:

Title:

1ha the concrete laydown area at the Sсhlumberger base.

Total

(AZN)

Quotation.

Description Qnty. Unit

Item

No. Unit Price in AzN

II Cable Tray System and Accessories

12 50mm Wide Cable Tray with Cover (length -3m) ea 17 30.91 525

13 Stand-off bracket for 50mm Wide Cable Tray ea 35 3.22 112

14 M8 Bolt, nut, washers (100 e.a in the pack) pack 1 35.00 35

Total 673

III Earthing & Lightning Protection Systems

15 Copper Earthing Rod ∅17.2mm, L=3000mm ea 19 84.56 1606

16 Air Rod ∅15mm, L=1000mm ea 8 331.66 2653

17 Concrete Inspection Earthing Pit ea 4 47.46 189

18 Execution of Exotermic Welding ea 42 86.94 365

19

Ring Type Cable Lugs for 1cx6mm² Ø6mm (100e.a in the pack) pack 2 39.00 78

20

Ring Type Cable Lugs for 1cx6mm² Ø8mm (100e.a in the pack) pack 2 41.60 83

21 Ring Type Cable Lugs for 1cx70mm² Ø10mm ea 19 3.25 6

22 1cx70mm2 CU/XLPE Cable Green-Yellow ea 340 10.14 3447

23 1cx150mm2 CU/XLPE Cable Green-Yellow ea 715 25.09 1793924 1cx6mm2 CU/XLPE Cable Green-Yellow ea 150 2.60 390

Total 30101

IV  Cable & Cable Gland.

25 of 3cx 2.5mm² Cu/XLPE/SWA/PVC m 690 3.64 251

26 3cx 4mm² Cu/XLPE/SWA/PVC m 100 4.34 434

27 3cx 6mm² Cu/XLPE/SWA/PVC m 215 4.76 1023

28 3cx 10mm² Cu/XLPE/SWA/PVC m 300 9.10 2730

29 3cx 16mm² Cu/XLPE/SWA/PVC m 515 13.16 6777

303cx 25mm² Cu/XLPE/SWA/PVC

m 83014.70 1220

Page 9: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 9/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 9 of 11Job No: MCG-1061T

Client: Schlumberger Logelco Inc. - Baku Office

Subject:

Title:

1ha the concrete laydown area at the Sсhlumberger base.

Total

(AZN)

Quotation.

Description Qnty. Unit

Item

No. Unit Price in AzN

31 3cx 50mm² Cu/XLPE/SWA/PVC m 400 21.84 8736

33 5cx 2.5mm² Cu/XLPE/SWA/PVC m 160 14.00 2240

34 5cx 4mm² Cu/XLPE/SWA/PVC m 55 16.80 924

35 5cx 6mm² Cu/XLPE/SWA/PVC m 50 20.30 1015

36 5cx 10mm² Cu/XLPE/SWA/PVC m 300 22.96 6888

37 5cx 16mm² Cu/XLPE/SWA/PVC m 600 26.60 15960

38 5cx 150mm² Cu/XLPE/SWA/PVC m 480 106.12 50937

39 Cable gland M20 ea 5 44.80 224

40 Cable gland M25 ea 2 44.80 89

41 Cable gland M32 ea 12 49.00 588

42 Cable gland M40 ea 4 49.00 196

43 Cable gland M50 ea 1 63.00 63

Total 113538

 V   Accessories.

44 Plastic tie-wrap, L=150mm (100 ea. in the pack) pack 7 4.90 34

45 Cable labels set 1 2590.00 2590

Total 2624

 VI Installation cost for electrical works 9942

Total for Electrical works 334261

Page 10: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 10/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 10 of 11Job No: MCG-1061T

Client: Schlumberger Logelco Inc. - Baku Office

Subject:

Title:

1ha the concrete laydown area at the Sсhlumberger base.

Total

(AZN)

Quotation.

Description Qnty. Unit

Item

No. Unit Price in AzN

Mechanical works

I Water System For Laydown Area

1 Pipe PPR Ø25 (Turkey) M 420 4.62 1940

2 Elbow 90° PPR Ø25 (Turkey) ea 16 1.68 26

3 Elbow 45° PPR Ø25 (Turkey) ea 5 0.00 0

4 T-Branch-90˚ PPR Ø25 (Turkey) ea 7 1.68 1

5 Ball valve PPR Ø25 (Turkey) ea 10 25.20 252

6 Pump (Wilo Velo Norm 50/200) ea 14200.00 4200

Total6431

 II Firefighting System For Laydown Area

7Pipe CS ASTM A 106 GR B SMLS SCH 40 BE. ASME

B36.10B (Turkey)m 600

43.40 26040

8Elbow-90° SCH 40 LR, BE CS ASTM A234 GR WPB.

 ASME B16.9 (Turkey)

ea 10

42.00 420

9T-Branch-90° SCH 40 LR, BE CS ASTM A234 GRWPB. ASME B16.9 (Turkey)

ea 537.80 189

10Ball Valve CS CL150 ASTM A216-WCB. ASME

B16.10 (Turkey)ea 3

28.00 84

11Flange WN CL150 RF CS ASTM A105. ASME B16.5

(Turkey)ea 4

238.00 952

12Blind Flange WN CL150 RF CS ASTM A105. ASME

B16.5 (Turkey)ea 3

476.00 1428

13 Gasket FLAT RNG CL150 UNGRAPHITED BOTHSIDES. ASME B16.21 (Turkey)

ea 632.20 193

14Stud Bolts W/2 HVY HEX NUT ALLY. ASTM A193

B7/A194 2H GLV & CTRFGD. ASME 18.2 (Turkey)ea 48

8.40 403

15 Aboveground Hydrant (Turkey) ea 32660.00 7980

Total 37689

Page 11: MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

8/13/2019 MCG 1061T CC BOQ 0002_A7_Develop of 1ha Laydown Area

http://slidepdf.com/reader/full/mcg-1061t-cc-boq-0002a7develop-of-1ha-laydown-area 11/11

Doc No: MG-1061T-CC-BOQ-0002

Rev: A7

Date: December 21,2013

Page: 11 of 11Job No: MCG-1061T

Client: Schlumberger Logelco Inc. - Baku Office

Subject:

Title:

1ha the concrete laydown area at the Sсhlumberger base.

Total

(AZN)

Quotation.

Description Qnty. Unit

Item

No. Unit Price in AzN

III Installation cost

1 Firefighting System 11205

2 Water System For Laydown Area 1466

Total 12672

Total for Water and Firefighting Systems 56792

Total by BOQ 1348898

Note:

These prices are exclusive of VAT and valid till of the end 2013

This Quotation is calculated according to BOQ provided by client. In case if discrepances between mention

above BOQ and the design drawings the prices will be revised accordingly