MBA PM Summers 2006

download MBA PM Summers 2006

of 30

Transcript of MBA PM Summers 2006

  • 8/8/2019 MBA PM Summers 2006

    1/30

    estimated cost of generation as per CERC norms at 80% PLF

    installed capacity (Kw)

    PLF

    project cost including IDC and financing charges (Rs millions)

    project cost/kW Including IDC and financing charges (Rs millions)

    annual generation ( in million Kwh)

    auxillary consumption ( in million Kwh)

    net energy sent out ( in million Kwh)

    plant gross heat rate on LCV basis ( kCal/kWh)

    annual fuel charges at (US $/MBTU)

    O&M charges at Rs 8.44 lakhs/MW (Rs millions)

    O &M expenses escalation

    Debt

    Equity

    Interest rate on term loan IDC

    During Operation

    Depreciaton including AAD( as % of total project cost)ROE

    spares( on cost without IDC and financing charges) (historical cost basis)

    spares escalation

    Working capital loan

    Interest on working capital

    receivables (months)

    Repayment period (years)

    Depreciation as per company act

    Discounting factor

    Corporate tax

    MAT

  • 8/8/2019 MBA PM Summers 2006

    2/30

    1040000

    80%

    30925.57

    29.74

    7288.32

    218.65 3% OF ANNUAL GENERATION

    7069.67

    1850

    3.5

    877.76 0.84 Millions/MW

    4%

    80%

    20%

    7.25%

    7%

    6%14%

    1% 287.73 millions

    6%

    75%

    10.25%

    2

    12

    5.58%

    12%

    33.50%

    7.85%

  • 8/8/2019 MBA PM Summers 2006

    3/30

    Detailed project cost estimate as on oct 2004 as given in

    all figures are in

    LSTK Non LSTK

    preliminary investigation and site development 12.00

    Land 400.00gas turbine island 25,811.17

    civil works 30.00

    contingency(@3% of total direct and direct costs) 774.34

    external water supply system 379.35

    initial spares 825.96

    taxes and duties 103.25

    preoperative expenses 50.00

    engineering and legal expenses(@1.5%) 387.17

    project cost excluding IDC and financingcosts

    IDC

    Financing [email protected]%

    Total Project Cost including IDC and financing cost

    debt 80%

    equity 20%

    $3,206.73

  • 8/8/2019 MBA PM Summers 2006

    4/30

    DPR CALCULATED

    illions Rs.

    TOTAL

    12.00 0.04%

    400.00 1.29%25,811.17 83.46%

    30.00 0.10%

    774.34 2.50%

    379.35 1.23%

    825.96 2.67%

    103.25 0.33%

    50.00 0.16%

    387.17 1.25%

    28,773.23 93.04% 2877323%

    2,008.47 6.49% 292048%

    143.87 0.47% 14387%

    6.96%30,925.57 100.00% 3183758%

    24,740.45 2547006%

    6,185.11 636752%

    diference 912.01

  • 8/8/2019 MBA PM Summers 2006

    5/30

    LNG PRICE CALCULATION

    YEAR 2010-11 2011-12 2012-13 2013-14 2014-15

    1 2 3 4 5

    Capacity (MW) 1040 1040 1040 1040 1040

    Heat Rate(in kJ/kWh) 6000 6000 6000 6000 6000

    Heat Rate in kCal/kWh 1435 1435 1435 1435 1435

    Gross Station Heat Rate kCal/kJ 1850 1850 1850 1850 1850

    Total unit Generated /year (MU) 7288.3 7288.3 7288.3 7288.3 7288.3

    Units in one MMBTU 123.5 123.5 123.5 123.5 123.5

    Total MMBTU (in million) 59.0 59.0 59.0 59.0 59.0

    Million dollors 206.6 210.7 215.0 219.3 223.6

    Exchange Rate -Rs/US$ 46.00 46.23 46.46 46.69 46.93

    LNG Cost (in million Rs) 9504.10 9742.66 9987.20 10237.88 10494.85

    Annual Levellised price OF LNG (in million Rs) 11373.03

    Assumption: Rupee Depreciation against US dollar 0.50%

    one MMBTU is equal to 1.055 Gigajoules

    Exchange rate of 1US $ 46 Rs.

    LNG cost considered is US $3.5/MBTU

    HCV/LCV is equal to 1.105

    Annual Escalation of LNG price 2.00%

  • 8/8/2019 MBA PM Summers 2006

    6/30

    2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

    6 7 8 9 10 11 12 13 14

    1040 1040 1040 1040 1040 1040 1040 1040 1040

    6000 6000 6000 6000 6000 6000 6000 6000 6000

    1435 1435 1435 1435 1435 1435 1435 1435 1435

    1850 1850 1850 1850 1850 1850 1850 1850 1850

    7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3

    123.5 123.5 123.5 123.5 123.5 123.5 123.5 123.5 123.5

    59.0 59.0 59.0 59.0 59.0 59.0 59.0 59.0 59.0

    228.1 232.7 237.3 242.1 246.9 251.9 256.9 262.0 267.3

    47.16 47.40 47.63 47.87 48.11 48.35 48.59 48.84 49.08

    10758.27 11028.30 11305.11 11588.87 11879.75 12177.93 12483.60 12796.93 13118.14

  • 8/8/2019 MBA PM Summers 2006

    7/30

    2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33

    15 16 17 18 19 20 21 22 23

    1040 1040 1040 1040 1040 1040 1040 1040 1040

    6000 6000 6000 6000 6000 6000 6000 6000 6000

    1435 1435 1435 1435 1435 1435 1435 1435 1435

    1850 1850 1850 1850 1850 1850 1850 1850 1850

    7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3

    123.5 123.5 123.5 123.5 123.5 123.5 123.5 123.5 123.5

    59.0 59.0 59.0 59.0 59.0 59.0 59.0 59.0 59.0

    272.6 278.1 283.6 289.3 295.1 301.0 307.0 313.2 319.4

    49.33 49.57 49.82 50.07 50.32 50.57 50.83 51.08 51.33

    13447.40 13784.93 14130.93 14485.62 14849.21 15221.92 15604.00 15995.66 16397.15

  • 8/8/2019 MBA PM Summers 2006

    8/30

    2033-34 2034-35

    24 25

    1040 1040

    6000 6000

    1435 1435

    1850 1850

    7288.3 7288.3

    123.5 123.5

    59.0 59.0

    325.8 332.3

    51.59 51.85

    16808.71 17230.61

  • 8/8/2019 MBA PM Summers 2006

    9/30

    PHASING OF EXPENDITURE

    project cost 28773.23 millions All cost are in million Rs.

    IDC 7.25%

    2007-08 2008-09 2009-10

    1 half 2 half 1 half 2 half 1 half

    Phasing of Expenditure (%) 15% 20% 40% 15% 10.00%

    Phasing amount 4315.98 5754.65 11509.29 4315.98 2877.32

    Debt 3452.79 4603.72 9207.43 3452.79 2301.86

    Cumulative Debt 3452.79 8056.5 17263.94 20716.72 23018.58

    IDC 62.58 375.49 792.7 813.56 876.14

    Phasing amount including IDC 4378.57 6130.14 12301.99 5129.55 3753.47

    amount available for depreciation

    YEAR 2010-11 2011-12 2012-13 2013-14 2014-15

    1 2 3 4 5

    Loan repaymentcalculations

    Loan O/s at beginning of the year ### ### ### ### ###

    Repayment 2122.51 2122.51 2122.51 2122.51 2122.51

    Loan O/s at end of the year ### ### ### ### ###

    Interest 1708.62 1560.04 1411.47 1262.89 1114.32

    Depreciation(SLM) 1910.25 1910.25 1910.25 1910.25 1910.25

    AAD 2122.51 2122.51 2122.51 2122.51 2122.51

    Applicable Depreciation 2122.51 2122.51 2122.51 2122.51 2122.51

    Cumulative Depreciation 2122.51 4245.01 6367.52 8490.02 10612.53

    Working capital

    Fuel Cost for One month 792.01 811.89 832.27 853.16 874.57

    O&M Expenses for one month 73.15 76.07 79.12 82.28 85.57

    Spares 287.73 305 323.3 342.69 363.26

    (iteration) Receivables-2 Months #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Total Working Capital #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Working Capital for Loan #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Interest on working Capital#VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Computation of tax

    PBT #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Add: depr. 2122.51 2122.51 2122.51 2122.51 2122.51

    PBDT #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Depreciation(as per IT) 1776.54 1776.54 1776.54 1776.54 1776.54

    PBT #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Tax(@33.50%) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    MAT(@7.85%) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Tax payable(higher of two) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    10/30

    2 half TOTAL

    100%

    28773.23

    23018.58

    2920.48

    54712.29

    28653.82

    2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

    6 7 8 9 10 11 12 13 14

    ### ### ### 849002.09% 636751.57% 424501.05% 212250.52%

    2122.51 2122.51 2122.51 2122.51 2122.51 2122.51 2122.51

    ### ### 849002.09% 636751.57% 424501.05% 212250.52% 0

    965.74 817.16 668.59 520.01 371.44 222.86 74.29

    1910.25 1910.25 1910.25 1910.25 1910.25 1910.25 1910.25 1910.25 1910.25

    2122.51 2122.51 2122.51 2122.51 2122.51 2122.51 2122.51 0 0

    2122.51 2122.51 2122.51 2122.51 2122.51 2122.51 2122.51 1714.33 1714.33

    12735.03 14857.54 16980.04 19102.55 21225.05 23347.56 25470.06 27184.39 28898.73

    896.52 919.02 942.09 965.74 989.98 1014.83 1040.3 1066.41 1093.18

    88.99 92.55 96.26 100.11 104.11 108.27 112.61 117.11 121.79

    385.05 408.15 432.64 458.6 486.12 515.28 546.2 578.97 613.71

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    2122.51 2122.51 2122.51 2122.51 2122.51 2122.51 2122.51 1714.33 1714.33

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    1776.54 1776.54 1776.54 1776.54 1776.54 1776.54 1776.54 1776.54 1776.54

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    11/30

    2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33

    15 16 17 18 19 20 21 22 23

    1910.25 1910.3 1910.3 1910.3 1910.3 1910.3 1910.3 1910.3 1910.3

    0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

    1714.33 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3

    30613.06 32327.4 34041.7 35756.0 37470.4 39184.7 40899.0 42613.4 44327.7

    1120.62 1148.7 1177.6 1207.1 1237.4 1268.5 1300.3 1333.0 1366.4

    126.67 131.7 137.0 142.5 148.2 154.1 160.3 166.7 173.4

    650.54 689.6 730.9 774.8 821.3 870.6 922.8 978.2 1036.9

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    1714.33 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    1776.54 1776.5 1776.5 1776.5 1776.5 1776.5 1776.5 1776.5 1776.5

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    12/30

    2033-34 2034-35

    24 25

    TOTAL1910.3 1910.3 47756.4

    0.0 0.0 25470.1

    1714.3 1714.3 47756.4

    46042.0 47756.4

    1400.7 1435.9

    180.3 187.5

    1099.1 1165.0

    #VALUE! #VALUE!

    #VALUE! #VALUE!

    #VALUE! #VALUE!

    #VALUE! #VALUE!

    #VALUE! #VALUE!

    1714.3 1714.3

    #VALUE! #VALUE!

    1776.5 1776.5

    #VALUE! #VALUE!

    #VALUE! #VALUE!

    #VALUE! #VALUE!

    #VALUE! #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    13/30

    2010-11 2011-12 2012-13 2013-14 2014-15 2015-16

    1 2 3 4 5 6

    Income

    Units sold(MU) 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7

    Total Tariff (Rs.per Unit) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Total sales Rs millions #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Expenses

    Raw materials(Fuel) Rs miliions 9504.1 9742.7 9987.2 10237.9 10494.8 10758.3

    O&M charges Rs miliions 877.8 912.9 949.4 987.4 1026.9 1067.9

    Total expenditure Rs miliions 10381.9 10655.5 10936.6 11225.2 11521.7 11826.2

    PBDIT #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Depreciation Rs miliions 2122.5 2122.5 2122.5 2122.5 2122.5 2122.5

    Interest-

    Term loan Rs miliions 1708.6 1560.0 1411.5 1262.9 1114.3 965.7

    Working capital Rs miliions #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    PBT Rs miliions #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Tax Rs miliions #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    PAT Rs miliions #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Gross cash accruals Rs miliions #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    14/30

    2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25

    7 8 9 10 11 12 13 14 15

    7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    11028.3 11305.1 11588.9 11879.7 12177.9 12483.6 12796.9 13118.1 13447.4

    1110.6 1155.1 1201.3 1249.3 1299.3 1351.3 1405.3 1461.5 1520.0

    12138.9 12460.2 12790.1 13129.1 13477.2 13834.9 14202.3 14579.7 14967.4

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    2122.5 2122.5 2122.5 2122.5 2122.5 2122.5 1714.3 1714.3 1714.3

    817.2 668.6 520.0 371.4 222.9 74.3 0.0 0.0 0.0

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    15/30

    2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33 2033-34

    16 17 18 19 20 21 22 23 24

    7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    13784.9 14130.9 14485.6 14849.2 15221.9 15604.0 15995.7 16397.1 16808.7

    1580.8 1644.0 1709.8 1778.2 1849.3 1923.3 2000.2 2080.2 2163.4

    15365.7 15775.0 16195.4 16627.4 17071.2 17527.3 17995.9 18477.4 18972.1

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    1714.3 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3

    0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    16/30

    2034-35

    25

    7069.7

    #VALUE!

    #VALUE!

    17230.6

    2250.0

    19480.6

    #VALUE!

    1714.3

    0.0

    #VALUE!

    #VALUE!

    #VALUE!

    #VALUE!

    #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    17/30

    Fixed tariff for generation

    YEAR 2010-11 2011-12 2012-13 2013-14 2014-15

    1 2 3 4 5

    Installed Capacity(MW) 1040 1040 1040 1040 1040

    Months of operation(effective) 12 12 12 12 12

    Plant load factor(%) 80% 80% 80% 80% 80%8760 Units generated (MU) 7288.3 7288.3 7288.3 7288.3 7288.3

    Less:auxilliary consumption 218.6 218.6 218.6 218.6 218.6

    Units sold(MU) 7069.7 7069.7 7069.7 7069.7 7069.7

    Fixed tariff calculation

    Interest 1708.6 1560.0 1411.5 1262.9 1114.3

    Depreciation 2122.5 2122.5 2122.5 2122.5 2122.5

    Notional RoE 891.5 891.5 891.5 891.5 891.5

    O&M expenses with 4% escalation 877.8 912.9 949.4 987.4 1026.9

    Interest on WC #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Tax on Income #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Total fixed tariff in million Rs. #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Fixed tariff p.u of energy sold #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Levellised fixed #VALUE!

    Variable tariff calculation

    LNG cost 9504.1 9742.66 9987.2 10237.88 10494.85

    Total variable tariff in million Rs 9504.1 9742.66 9987.2 10237.88 10494.85

    Variable tariff p.u. of energy sold 1.34 1.38 1.41 1.45 1.48

    Levellised variable 1.61

    Total Tariff (Rs.per Unit) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Levellised Total Tariff (Rs per unit) #VALUE!

    Max. tariff #VALUE!

    Min. tariff #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    18/30

    up to 80%PLF

    2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

    6 7 8 9 10 11 12 13 14

    1040 1040 1040 1040 1040 1040 1040 1040 1040

    12 12 12 12 12 12 12 12 12

    80% 80% 80% 80% 80% 80% 80% 80% 80%7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3

    218.6 218.6 218.6 218.6 218.6 218.6 218.6 218.6 218.6

    7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7

    965.7 817.2 668.6 520.0 371.4 222.9 74.3 0.0 0.0

    2122.5 2122.5 2122.5 2122.5 2122.5 2122.5 2122.5 1714.3 1714.3

    891.5 891.5 891.5 891.5 891.5 891.5 891.5 891.5 891.5

    1067.9 1110.6 1155.1 1201.3 1249.3 1299.3 1351.3 1405.3 1461.5

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    10758.27 11028.3 11305.11 11588.87 11879.75 12177.93 12483.6 12796.93 13118.14

    10758.27 11028.3 11305.11 11588.87 11879.75 12177.93 12483.6 12796.93 13118.14

    1.52 1.56 1.60 1.64 1.68 1.72 1.77 1.81 1.86

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    19/30

    2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33

    15 16 17 18 19 20 21 22 23

    1040 1040 1040 1040 1040 1040 1040 1040 1040

    12 12 12 12 12 12 12 12 12

    80% 80% 80% 80% 80% 80% 80% 80% 80%7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3 7288.3

    218.6 218.6 218.6 218.6 218.6 218.6 218.6 218.6 218.6

    7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7 7069.7

    0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

    1714.3 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3 1714.3

    891.5 891.5 891.5 891.5 891.5 891.5 891.5 891.5 891.5

    1520.0 1580.8 1644.0 1709.8 1778.2 1849.3 1923.3 2000.2 2080.2

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    13447.4 13784.93 14130.93 14485.62 14849.21 15221.92 15604 15995.66 16397.15

    13447.4 13784.93 14130.93 14485.62 14849.21 15221.92 15604 15995.66 16397.15

    1.90 1.95 2.00 2.05 2.10 2.15 2.21 2.26 2.32

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    20/30

    2033-34 2034-35

    24 25

    1040 1040

    12 12

    80% 80%7288.3 7288.3

    218.6 218.6

    7069.7 7069.7

    0.0 0.0

    1714.3 1714.3

    891.5 891.5

    2163.4 2250.0

    #VALUE! #VALUE!

    #VALUE! #VALUE!

    #VALUE! #VALUE!

    #VALUE! #VALUE!

    16808.71 17230.61

    16808.71 17230.61

    2.38 2.44

    #VALUE! #VALUE!

  • 8/8/2019 MBA PM Summers 2006

    21/30

    URAN CCGT FIRR CALCULATIONS

    1040 MW

    Year Incr gen Incr sales Capex O&M cost

    Mus Mus Mus Rs. Millions Rs. Millions Rs. Millions

    2007-08 0.00 0.00 0.00 10070.63 0.00 0.00

    2008-09 0.00 0.00 0.00 15825.27 0.00 0.00

    2009-10 7288.32 218.65 7069.67 2877.32 9504.10 877.76

    2 7288.32 218.65 7069.67 9742.66 912.87

    3 7288.32 218.65 7069.67 9987.20 949.39

    4 7288.32 218.65 7069.67 10237.88 987.36

    5 7288.32 218.65 7069.67 10494.85 1026.86

    6 7288.32 218.65 7069.67 10758.27 1067.93

    7 7288.32 218.65 7069.67 11028.30 1110.65

    8 7288.32 218.65 7069.67 11305.11 1155.07

    9 7288.32 218.65 7069.67 11588.87 1201.28

    10 7288.32 218.65 7069.67 11879.75 1249.33

    11 7288.32 218.65 7069.67 12177.93 1299.3012 7288.32 218.65 7069.67 12483.60 1351.27

    13 7288.32 218.65 7069.67 12796.93 1405.32

    14 7288.32 218.65 7069.67 13118.14 1461.53

    15 7288.32 218.65 7069.67 13447.40 1520.00

    16 7288.32 218.65 7069.67 13784.93 1580.80

    17 7288.32 218.65 7069.67 14130.93 1644.03

    18 7288.32 218.65 7069.67 14485.62 1709.79

    19 7288.32 218.65 7069.67 14849.21 1778.18

    20 7288.32 218.65 7069.67 15221.92 1849.31

    21 7288.32 218.65 7069.67 15604.00 1923.28

    22 7288.32 218.65 7069.67 15995.66 2000.21

    23 7288.32 218.65 7069.67 16397.15 2080.22

    24 7288.32 218.65 7069.67 16808.71 2163.43

    25 7288.32 218.65 7069.67 17230.61 2249.97

    Aux.consumptio

    nTotal variable

    cost

  • 8/8/2019 MBA PM Summers 2006

    22/30

    FIRR #VALUE!

    Tariff Sales revenue

    Rs. Millions Rs. Per unit Rs.millions Rs. Millions

    10070.63 0.00 0.00 -10070.63

    15825.27 0.00 0.00 -15825.27

    13259.19 #VALUE! #VALUE! #VALUE!

    10655.53 #VALUE! #VALUE! #VALUE!

    10936.58 #VALUE! #VALUE! #VALUE!

    11225.24 #VALUE! #VALUE! #VALUE!

    11521.70 #VALUE! #VALUE! #VALUE!

    11826.20 #VALUE! #VALUE! #VALUE!

    12138.95 #VALUE! #VALUE! #VALUE!

    12460.18 #VALUE! #VALUE! #VALUE!

    12790.14 #VALUE! #VALUE! #VALUE!

    13129.07 #VALUE! #VALUE! #VALUE!

    13477.23 #VALUE! #VALUE! #VALUE!13834.87 #VALUE! #VALUE! #VALUE!

    14202.26 #VALUE! #VALUE! #VALUE!

    14579.67 #VALUE! #VALUE! #VALUE!

    14967.40 #VALUE! #VALUE! #VALUE!

    15365.73 #VALUE! #VALUE! #VALUE!

    15774.96 #VALUE! #VALUE! #VALUE!

    16195.41 #VALUE! #VALUE! #VALUE!

    16627.39 #VALUE! #VALUE! #VALUE!

    17071.23 #VALUE! #VALUE! #VALUE!

    17527.28 #VALUE! #VALUE! #VALUE!

    17995.87 #VALUE! #VALUE! #VALUE!

    18477.37 #VALUE! #VALUE! #VALUE!

    18972.14 #VALUE! #VALUE! #VALUE!

    19480.58 #VALUE! #VALUE! #VALUE!

    FIRR #VALUE!

    Total operatingcost

    Net financialbenefit

  • 8/8/2019 MBA PM Summers 2006

    23/30

    URAN CCGT EIRR CALCULATIONS

    1040 MW

    Year Incr gen Incr sales Capex O&M cost

    Mus Mus Mus Rs. Millions Rs. Millions Rs. Millions

    0.8 0.8 0.82007-08 0.00 0.00 8056.50 0.00 0.00

    2008-09 0.00 0.00 12660.22 0.00 0.00

    2009-10 7288.32 218.65 7069.67 2301.86 7603.28 702.21

    2 7288.32 218.65 7069.67 0.00 7794.12 730.30

    3 7288.32 218.65 7069.67 0.00 7989.76 759.51

    4 7288.32 218.65 7069.67 0.00 8190.30 789.89

    5 7288.32 218.65 7069.67 0.00 8395.88 821.48

    6 7288.32 218.65 7069.67 0.00 8606.61 854.34

    7 7288.32 218.65 7069.67 0.00 8822.64 888.52

    8 7288.32 218.65 7069.67 0.00 9044.09 924.06

    9 7288.32 218.65 7069.67 0.00 9271.09 961.02

    10 7288.32 218.65 7069.67 0.00 9503.80 999.46

    11 7288.32 218.65 7069.67 0.00 9742.34 1039.44

    12 7288.32 218.65 7069.67 0.00 9986.88 1081.02

    13 7288.32 218.65 7069.67 0.00 10237.55 1124.26

    14 7288.32 218.65 7069.67 0.00 10494.51 1169.23

    15 7288.32 218.65 7069.67 0.00 10757.92 1216.00

    16 7288.32 218.65 7069.67 0.00 11027.95 1264.64

    17 7288.32 218.65 7069.67 0.00 11304.75 1644.03

    18 7288.32 218.65 7069.67 0.00 11588.50 1709.79

    19 7288.32 218.65 7069.67 0.00 11879.37 2163.43

    20 7288.32 218.65 7069.67 0.00 12177.54 2249.97

    21 7288.32 218.65 7069.67 0.00 12483.20 1923.28

    22 7288.32 218.65 7069.67 0.00 12796.52 2000.21

    23 7288.32 218.65 7069.67 0.00 13117.72 2080.22

    24 7288.32 218.65 7069.67 0.00 13446.97 2163.43

    25 7288.32 218.65 7069.67 0.00 13784.49 2249.97

    Aux.consumptio

    nTotal variable

    cost

  • 8/8/2019 MBA PM Summers 2006

    24/30

    EIRR #VALUE!

    Tariff Sales revenue Consumer surplus

    Rs. Millions Rs. Per unit Rs.millions Rs. Millions Rs. Millions Rs. Millions

    1.258056.50 0.00 0.00 0.00 0.00 -8056.50

    12660.22 0.00 0.00 0.00 0.00 -12660.22

    10607.35 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    8524.42 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    8749.27 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    8980.19 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    9217.36 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    9460.96 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    9711.16 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    9968.15 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    10232.11 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    10503.26 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    10781.78 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    11067.89 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    11361.81 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    11663.74 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    11973.92 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    12292.58 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    12948.78 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    13298.29 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    14042.80 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    14427.51 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    14406.48 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    14796.74 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    15197.94 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    15610.40 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    16034.46 #VALUE! #VALUE! 8837.09 #VALUE! #VALUE!

    EIRR #VALUE!

    Total operatingcost

    Totaleconomic

    benefitNET economic

    benefit

  • 8/8/2019 MBA PM Summers 2006

    25/30

    DSCR calculation 2010-11 2011-12 2012-13 2013-14 2014-15

    1 2 3 4 5

    Numerator-Gross cash accrual #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    -Interest on term loan 1708.62 1560.04 1411.47 1262.89 1114.32

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    Denominator

    -Interest on term loan 1708.62 1560.04 1411.47 1262.89 1114.32

    -Repayment 2122.51 2122.51 2122.51 2122.51 2122.51

    3831.12 3682.55 3533.97 3385.40 3236.82

    DSCR

    Max. DSCR 0.00

    Min. DSCR 0.00

  • 8/8/2019 MBA PM Summers 2006

    26/30

    2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24

    6 7 8 9 10 11 12 13 14

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    965.74 817.16 668.59 520.01 371.44 222.86 74.29 0.00 0.00

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    965.74 817.16 668.59 520.01 371.44 222.86 74.29 0.00 0.00

    2122.51 2122.51 2122.51 2122.51 2122.51 2122.51 2122.51 0.00 0.00

    3088.25 2939.67 2791.09 2642.52 2493.94 2345.37 2196.79 0.00 0.00

  • 8/8/2019 MBA PM Summers 2006

    27/30

    2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32 2032-33

    15 16 17 18 19 20 21 22 23

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!

    0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

  • 8/8/2019 MBA PM Summers 2006

    28/30

    2033-34 2034-35

    24 25

    #VALUE! #VALUE!

    0.00 0.00

    #VALUE! #VALUE!

    0.00 0.00

    0.00 0.00

    0.00 0.00

  • 8/8/2019 MBA PM Summers 2006

    29/30

    Sensitivity : 1

    S No. PLF %age change in PLF

    1 75% -5% 2.49 -2.0209%

    2 80% 0 2.44 0

    3 85% 5% 2.39 1.7478%

    Sensitivity : 2

    S No. %age change

    1 3.33 -5% 2.35 3.4806%

    2 3.50 0 2.44 0

    3 3.68 5% 2.52 -3.5181%

    Sensitivity : 3

    S No. %age change

    1 30398.92 -5% 2.41 1.0238%

    2 31837.58 0 2.44 0

    3 33276.24 5% 2.46 -1.0613%

    Impact of variation in PLF on tariff(levelised)--keeping all other factors constant

    Corresponding levelisedtariff (Rs/Kwh)

    %age change in levelisedtariff

    Impact of variation in fuel price on tariff (Levelised)--keeping all other factors constant

    Fuel price($/MBTU)

    Corresponding levelisedtariff (Rs/Kwh)

    %age change in levelisedtariff

    Impact of variation in project cost on tariff (levelised)--keeping all other factors constant

    Project cost(Rs million)

    Corresponding levelisedtariff (Rs/Kwh)

    %age change in levelisedtariff

  • 8/8/2019 MBA PM Summers 2006

    30/30

    #VALUE!