Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP...

34
Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008 Microsoft, Microsoft Project and Microsoft Word are either trademarks or registered trademarks of Microsoft Corporation in the United States and other countries. Other terms may be trademarks or registered trademarks of their respective owners. © 2008. Agilitek Corporation. All Rights

Transcript of Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP...

Page 1: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

Maximizing the Power ofMicrosoft® Project and Microsoft® Word

Dr. John A. Estrella, CMC, PMP

Presented to MPA Greater Toronto Area

20 February 2008

Microsoft, Microsoft Project and Microsoft Word are either trademarks or registered trademarks of Microsoft Corporation in the United States and other countries. Other terms may be trademarks or registered trademarks of their respective owners.

© 2008. Agilitek Corporation. All Rights Reserved.

Page 2: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

2 of 34

Learning Objectives

1. Extend the power of Microsoft Project and Microsoft Word

2. Create work breakdown structures and mind maps Organize and transform brainstorming notes into schedules Convert mind maps into sophisticated documents instantly

3. Display summary and detail project information graphically

4. Incorporate time bands when defining task dependencies

Page 3: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

3 of 34

Learning Objective (1 of 4)

Extend the power of Microsoft Project and Microsoft Word

Page 4: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

4 of 34

Useful Third-Party Software Tools

Mindjet® MindManager®

Encourages creative thinking in a project Captures and manages information visually

Critical ToolsTM: WBS Chart ProTM

Facilitates graphical creation of work breakdown structures Displays summary and detail project information

Critical ToolsTM: PERT Chart EXPERTTM

Creates and displays project PERT network charts Incorporates vertical time bands on task dependencies

PERT = Program Evaluation and Review Technique

Page 5: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

5 of 34

Mindjet® MindManager®

Speeds up brainstorming sessions Defining the project scope Documenting project information Creating work breakdown structures

Converts mind maps automatically Into Microsoft Project schedules Into Microsoft Word documents

Facilitates graphical monitoring and controlling of projects Weekly progress reports

Source: Mindjet

Page 6: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

6 of 34

Source: Mindjet

Page 7: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

7 of 34

Critical ToolsTM: WBS Chart ProTM

Captures the overall project scope graphically Highlights and summarizes key project information Serves as a powerful communication and collaboration tool

Allows the project team to create work breakdown structures Decompose the project into manageable smaller tasks Facilitates team building during project initiation

Supports bidirectional link into Microsoft Project Converts WBS into Microsoft Project schedules Reflects Microsoft Project changes dynamically

Page 8: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

8 of 34

Source: Critical Tools

Page 9: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

9 of 34

Source: Critical Tools

Page 10: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

10 of 34

Critical ToolsTM: PERT Chart EXPERTTM

Enables the creation and definition of task dependencies Calculates critical and non-critical tasks Displays the sequence of tasks graphically

Makes it easier to view task predecessors and successors Incorporates vertical time bands in the PERT chart Shows dependency information (FS, SS, FF & FS, and lag)

Supports bidirectional link with Microsoft Project Converts WBS into Microsoft Project schedules Reflects Microsoft Project changes dynamically

FS = Finish-to-Start, SS = Start-to-Start, FF = Finish-to-Finish and FS = Finish-to-Start

Page 11: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

11 of 34

Page 12: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

12 of 34

Source: Critical Tools

Page 13: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

13 of 34

Learning Objective (2 of 4)

Create work breakdown structures and mind maps Organize and transform brainstorming notes into schedules Convert mind maps into sophisticated documents instantly

Page 14: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

14 of 34

Work Breakdown Structure (WBS)

What is WBS? “A deliverable-oriented hierarchical decomposition of the work to

be executed by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project.”

How do you create a WBS? Get the team to identify the upper levels of the WBS

• Major deliverable work areas of the project

• Major phases in the project’s life cycle Provide details on the lower WBS elements

• Scope, schedule, cost, resource, notes, etc.

Sources: PMI 2004, 379; PMI 2001, 5

Page 15: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

15 of 34

WBS (continued)

Is WBS supported in Microsoft Project? Yes, but only in an indented outline format

Are there other alternatives? Yes, use MindManager or WBS Chart Pro Import the WBS into Microsoft Project

Source: PMI 2001, 9

Page 16: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

16 of 34

Source: PMI 2001, 9

Page 17: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

17 of 34

WBS in WBS Chart Pro

Page 18: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

18 of 34

WBS in Microsoft Project

Page 19: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

19 of 34

Mind Mapping

What is a mind map? “A mind map is a diagram used to represent words, ideas, tasks

or other items linked to and arranged radially around a central key word or idea. It is used to generate, visualize, structure and classify ideas, and as an aid in study, organization, problem solving, decision making, and writing.”

How do you create a mind map? Start with a central key word or idea List 4 to 7 key items around the central key word or idea Add graphics, relationships, words, etc. as needed

Export the mind map into Microsoft Project or Microsoft Word

Source: Wikipedia

Page 20: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

20 of 34

Page 21: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

21 of 34

Page 22: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

22 of 34

Learning Objective (3 of 4)

Display summary and detail project information graphically

Page 23: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

23 of 34

Displaying Project Information

Graphical representation addresses the need of visual learners Makes presentations easier and more appealing

Microsoft Project Stores most of the information But, it cannot easily display the data in graphical format

MindManager Project dashboard, requirements documentation, etc.

WBS Chart Pro / PERT Chart EXPERT Summary, by resource, by phase, etc.

Page 24: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

24 of 34

Source: Mindjet

Page 25: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

25 of 34

Source: Mindjet

Page 26: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

26 of 34

Page 27: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

27 of 34

Page 28: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

28 of 34

Source: Critical Tools

Page 29: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

29 of 34

Source: Critical Tools

Page 30: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

30 of 34

Source: Critical Tools

Page 31: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

31 of 34

Learning Objective (4 of 4)

Incorporate time bands when defining task dependencies

Page 32: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

32 of 34

Source: Critical Tools

Page 33: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

33 of 34

References

Critical Tools. Project planning and graphing software. http://criticaltools.com/.

Mindjet. The Mindjet map gallery. http://www.mindjet.com/us/download/map_library/map_library_browse.php?pid=0&cid=1&page=3&index=10.

Project Management Institute, Inc. 2001. Project Management Institute practice standard for work breakdown structures. Newtown Square, PA: Project Management Institute, Inc.

Project Management Institute, Inc. 2004. A guide to the project management body of knowledge. 3rd ed. Newtown Square, PA: Project Management Institute, Inc.

Wikipedia. Mind map. http://en.wikipedia.org/wiki/Mind_map.

Page 34: Maximizing the Power of Microsoft ® Project and Microsoft ® Word Dr. John A. Estrella, CMC, PMP Presented to MPA Greater Toronto Area 20 February 2008.

34 of 34

Contact Information

Dr. John A. Estrella, CMC, PMP Management Consultant

• Project management, business analysis, and software testing International Author

• Courses, books, and products (http://agilitek.com/products.html) Professional Speaker

• Keynote, training, and webinar

Web sites: http://JohnEstrella.com • http://SampleExamQuestions.com