MASTER Schedule2
-
Upload
ravi-singh -
Category
Documents
-
view
220 -
download
0
Transcript of MASTER Schedule2
-
8/13/2019 MASTER Schedule2
1/17
-
8/13/2019 MASTER Schedule2
2/17
Aggregate Production Planning
Aggregate production planning is defined as theprocess of development, analytics and maintenance ofa schedule for the business' overall operations.
It is usually medium range in nature, lasting anywherefrom three to 18 months.
The planned output levels, targeted sales andintended inventory levels are taken into account while
preparing an aggregate plan. An efficient aggregate plan should do away with day-
to-day scheduling
-
8/13/2019 MASTER Schedule2
3/17
Definition:Master Production scheduling (MPS)
Translating a business plan into a comprehensiveproduct manufacturing schedule that covers what is to
be assembled or made, when, with what materialsacquired when, and the cash required.
MPS is a key component of material requirementsplanning
It represents the critical linkage between planningand execution of operations. It is the next stage in theproduction planning process in any organisation afteraggregate production planning is done.
-
8/13/2019 MASTER Schedule2
4/17
HOW MPS WORKS
Information needed for MPS logic
Lot size
Lead time Product demand
Starting inventory
-
8/13/2019 MASTER Schedule2
5/17
Relationship between MPS &APP Aggregate production planning is a rough cut capacity
planning exercise on the basis of forecast quantities ofproducts.
MPS makes use of actual customer orders for thepurposes of capacity planning and resource allocation
to specific customer orders.
-
8/13/2019 MASTER Schedule2
6/17
Master Production Scheduling
TechniquesAvailable = inventory position at end of week
= starting inventory + MPS forecast
Plan to have positive inventory level
Buffer in case production below plan
Or demand higher than anticipated
-
8/13/2019 MASTER Schedule2
7/17
Utility of MPS MPS is the process by which disaggregation of varieties
is done
using this information additional planning is carriedout to assign the required capacity to each variety.
planning for the material required for productionduring each period is also done
-
8/13/2019 MASTER Schedule2
8/17
Why MPS is required ? . The most important reason is that at the stage of
aggregate production planning, normally forecast
demand is taken for the purpose of estimating thecapacity required
when actual orders are received this informationprovides a better input
MPS uses actual and the most recent information
-
8/13/2019 MASTER Schedule2
9/17
It ensures specific material and capacity availability ina particular time period.
As customer orders get amended and/or cancelled,the information has a bearing on capacity availability.
The MPS module serves the important purpose ofcomputing capacity available to promise.
-
8/13/2019 MASTER Schedule2
10/17
FORECASTING
AGGREGATEPRODUCTION
PLANNING
CAPACITYPLAN
MATERIALPLAN
ACTUALPRODUCTION
MASTERPRODUCTIONSCHEDULING
MARKET
LABOUR
VENDOR
-
8/13/2019 MASTER Schedule2
11/17
Link b/w MPS & other planning
processesAs shown the figure MPS takes inputs from the order
in flow system and APP to perform the disaggregationexercise.
Based on the disaggregation, capacity planning andmaterials planning are performed to ensure theiradequate availability
.If there is some infeasibility in either capacity or
material availability, the plans are altered to arrive atpossible production plans. Therefore, MPS determineswhat needs to be ultimately produced and what isdemanded.
-
8/13/2019 MASTER Schedule2
12/17
The stages involved in MPS There are two stages involve in MPS
1.To update the projected demand based on earlier
forecast and current market information. 2. It involves the Disaggregation of product
information and relating to specific material, andcapacity requirements.
-
8/13/2019 MASTER Schedule2
13/17
STEPS FOR ACTUAL PRODUCTION
Step 1. Incorporating current market information into
the production plan
Step 2.Disaggregation of product information
-
8/13/2019 MASTER Schedule2
14/17
-
8/13/2019 MASTER Schedule2
15/17
. if the forecast quantities are higher than the firmorders it is a normal practice to work on the basis offorecast quantities.
On the other hand if the firm orders are more thanthe forecast quantity then it is desirable to incorporatethis information for the purpose of planning .
-
8/13/2019 MASTER Schedule2
16/17
STEP 2.Disaggregation of product
informationAt the time of APP an aggregate unit was chosen and
different varieties of a product or services wereconverted to equivalent product/services .
-
8/13/2019 MASTER Schedule2
17/17
SUMMARY MPS breaks the Sales & Operations plan into product
families. Maintains Desired Level of Customer Service
Allows proactive control of inventory