Masonry: Cavity Wall Insulation: Partial Fill Isometric cut-away view ...
Transcript of Masonry: Cavity Wall Insulation: Partial Fill Isometric cut-away view ...
Masonry: Cavity Wall Insulation: Partial FillIsometric cut-away view
Service void / protectionzone for air tightnessmembrane (optional)
Air tightness barrier
Insulation supportedwithin secondary timberstud frame
Wall ties
Cavity
Outer leaf (renderon block shown)
Inner leaf (block shown)
Insulation
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Plasterboard
LegendInsulation zone
Air tightness barrier(note: this can alsoact as a vapourcontrol layer)
Guidance on thermalcontinuity
Blue text
Guidance on airtightness
Red text
General guidance notes
Alternative constructions1. The thermal resistance of cavity
insulation needs to be greater than thatused in the inner leaf insulation, toreduce the risk of interstitialcondensation.
2. Different constructions can be used toprovide an outer leaf but check thatthere is sufficient ventilation provisionto prevent moisture from being trappedwithin the wall.
Sealing membrane junctions3. All membranes should be taped,
stapled or bedded in adhesive asidentified by manufacturer. Repair alltears in membranes beforecommencing next stage of work.
Psi-value calculations4. For details of all thermal conductivity
values of materials used in the psi-valuecalculations, see also Appendix B of theIntroduction.
Material λ-values usedin calculations(W/mK)
Plasterboard 0.21Insulation (generic) 0.04Plywood sheathing 0.13Brick outer leaf 0.77Mineral wool insulation 0.044Concrete block(dense) protected
1.13
Concrete block(lightweight, high strength)
0.19
Timber frame 0.13Concrete floor beam 2.3Concrete screed 1.15Render (cement/sand) 1.0Gypsum plaster(1000kg/m3)
0.4
Concrete roof tiles 1.5EPDM membrane 0.25Timber battens 0.13Timber flooring 0.13Chipboard 0.13Floor joists 0.13Aluminium 160Steel 50Stainless steel 17Glass 1Sarking felt 0.23Insulation board 0.022
Values used in psi calculations
Detail 2.00
Masonry: Cavity Wall Insulation - Partial fillPitched Roof: Ventilated Roofspace - EavesPsi value = 0.0392W/mK
Thermal continuity checklist
1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions
2. Check that roof insulation butts against thecavity wall insulation, with minimum of50mm overlap at narrowest point
3. Install cavity barrier at the top of the wall.
Air tightness checklist
1. Check that any air tightness barrierused in the ceiling overlaps with thelayer in the wall
Detail 2.01
Proprietary cross flowventilator to maintainminimum 25mm air gap
Ventilation gap equivalent to10mm minimum continuousopening is required whereroof pitch is above 15°orventilation gap equivalent to25mm minimum continuousopening is required wherethe roof pitch is below 15°
Vapour control layer in wall and ceiling
Ventilation gap equivalent to 5mmminimum continuous opening at ridgeis required where the roof pitch isgreater than 35° or the roof span ismore than 10m
Cavity barrier giving 30minute fire resistance -ensure cavity barrier is notbreeched by inappropriaterigid sheathing insulationmaterial
Timber batten to provide fixingfor plasterboard sheet
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check ventilation paths are clear before
installing insulation above the ceiling
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WRoof - 9.500(m²K)/W
Note: See detail numbers 2.02 and 2.21 forother junctions using this roof construction
Insulation between the studsin addition to the cavity insulation.
This insulation to be tightly fittedagainst the wall, leaving no gaps
Masonry: Cavity Wall Insulation - Partial fillPitched Roof: Ventilated Roofspace - GablePsi value = 0.0918W/mK Detail 2.02
Air tightness checklist
1. Check that any air tightness barrierused in the ceiling overlaps with thelayer in the wall
Cavity insulation continuedfull height of gable or to thetop of the loft insulation
Insulation betweenthe last truss andthe gable wall
Vapour control layer in wall and ceiling
Timber batten to provide fixingfor plasterboard sheet
Insulation between the studsin addition to the cavity insulation.
This insulation to be tightly fittedagainst the wall, leaving no gaps
Thermal continuity checklist
1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions
2. Ensure that roof insulation butts againstthe gable wall
3. Install cavity barrier at the top of the wall.
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check ventilation paths are clear before
installing insulation above the ceiling
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WRoof - 9.500(m²K)/W
Note: See detail numbers 2.01 and 2.21 forother junctions using this roof construction
Cavity barrier giving30 minute fireresistance - ensurecavity barrier is notbreeched byinappropriate rigidsheathing insulationmaterial
Masonry: Cavity Wall Insulation - Partial fillPitched Roof: Ventilated Rafter Void - GablePsi value = 0.0206W/mK Detail 2.03
Insulationbetween joistsand coveringcavity insulation
Cavity barriergiving 30 minutefire resistance -thin calcium silicateboard or similaracross top of wall
Vapour control layer in wall and ceiling
Timber runner to provide fixingfor plasterboard sheet
Insulation between the studs inaddition to the cavity insulation.
This insulation must be tightlyfitted, leaving no gaps
Minimum 50mm ventilation path over insulation
Where two insulation types areused together see
supplementary guidance
Air tightness checklist
1. Check that any air tightness barrierused in the ceiling overlaps with thelayer in the wall
Thermal continuity checklist
1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions
2. Ensure that roof insulation butts againstthe gable wall
3. Install cavity barrier at the top of the wall.
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check ventilation paths are clear before
installing insulation above the ceiling
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WRoof - 9.500(m²K)/W
Note: See detail numbers 2.04, 2.05 and 2.22for other junctions using this roof construction
Note: thisconstruction istypically usedwhere there arehabitable roomswithin the roofconstruction
Masonry: Cavity Wall Insulation - Partial fillPitched Roof: Ventilated Batten Void (warm roof) - EavesPsi value = 0.034W/mK Detail 2.04
Rigid insulation used as sarkingInsulation to be vapour permeable
Proprietary overfascia ventilator
Vapour control layer in wall and ceiling
Insulation between thestuds in addition to thecavity insulation. This
insulation must be tightlyfitted, leaving no gaps
Timber batten toprovide fixing for
plasterboard sheetVentilation tobatten void
Vapour permeable membrane(with a vapour resistance ofnot more than 0.25MN.s/g)
Lap roof and wall insulationminimum 150mm thickness atnarrowest point
Ventilation gap equivalent to5mm minimum continuousopening is required at ridgeto batten space
Thermal continuity checklist
1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions
2. Ensure that roof insulation butts againstthe cavity wall insulation, with minimum of50mm overlap at narrowest point
3. Install cavity barrier at the top of the wall
Air tightness checklist
1. Check that any air tightness barrierused in the ceiling overlaps with thelayer in the wall
Cavity barrier giving 30 minutefire resistance - ensure cavitybarrier is not breeched byinappropriate rigid sheathinginsulation material
Alternative air barrier- parge coat of plaster
finish on blockwork
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check ventilation paths are clear before
installing insulation above the ceiling
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WRoof - 9.500(m²K)/W
Note: See detail numbers 2.03, 2.05 and 2.22for other junctions using this roof constructionNote: this construction is
typically used where thereare habitable rooms withinthe roof construction
Masonry: Cavity Wall Insulation - Partial fillPitched Roof: Ventilated Batten Void (warm roof) - GablePsi value = 0.0552W/mK Detail 2.05
Insulation betweenjoists and inner faceof the wall
Cavity barrier giving30 minute fireresistance - ensurecavity barrier is notbreeched byinappropriate rigidsheathing insulationmaterial
Vapour control layer in wall and ceiling
Timber runner to provide fixingfor plasterboard sheet
Insulation between the studs inaddition to the cavity insulation.
This insulation must be tightlyfitted, leaving no gaps
50mm ventilation path over insulation
Where two insulation types areused together see
supplementary guidance
Vapourpermeablemembrane(with a vapourresistance ofnot more than0.25 MN.s/g)
Air tightness checklist
1. Check that any air tightness barrierused in the ceiling overlaps with thelayer in the wall
Thermal continuity checklist
1. Ensure that insulation layers are fittedperpendicularly, to cover junctions
2. Ensure that roof insulation butts againstthe gable wall
3. Install cavity barrier at the top of the wall.
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check ventilation paths are clear before
installing insulation above the ceiling
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WRoof - 9.500(m²K)/W
Note: See detail numbers 2.03, 2.04 and 2.22for other junctions using this roof construction
Note: this constructionis typically used wherethere are habitablerooms within the roofconstruction
Masonry: Cavity Wall Insulation - Partial fillTimber Flat RoofPsi value = 0.0695W/mK Detail 2.06
Verge option - tightly fitinsulation into void overwall and under deck tomaintain thermalcontinuity
Cavity barrier giving 30minute fire resistance -ensure cavity barrier is notbreeched by inappropriaterigid sheathing insulationmaterial
Vapour control layer
Timber runner to provide fixingfor plasterboard sheet
Insulation between the studs inaddition to the cavity insulation.
This insulation must be tightlyfitted, leaving no gaps
Eaves - fix full height blockingpiece and tightly fit insulation intovoid and under deck
Vapour control layer turned up edgeof roof insulation, lapped with roofwaterproofing layer and sealed
Vapour controllayer in ceiling
Air tightness checklist
1. Check that any air tightness barrierused in the ceiling overlaps with thelayer in the wall
Thermal continuity checklist
1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions
2. Ensure that roof insulation butts against the gable wall
3. Install cavity barrier at the top of the wall.
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Membrane roof construction
Design advice
Minimising condensation risk1. Check ventilation paths are clear before
installing insulation above the ceiling2. A vapour control layer is required at
ceiling level, to prevent moisture fromentering into the roof construction
3. The option shown here includes a vapourcontrol layer and insulation as part of amembrane roof construction. Similardetails could be used for a profiled metaldecking roof but consult withmanufacturer regarding ventilationrequirements.
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WRoof - 9.500(m²K)/W
Masonry: Cavity Wall Insulation - Partial fillTimber Flat Roof with ParapetPsi value = 0.0811W/mK Detail 2.07
Insulation between the studs in additionto the cavity insulation. This insulation must
be tightly fitted, leaving no gaps
Compressible filler
Roofing membrane to be taken minimum150mm above finished roof level
Vapour control layer turned up edgeof parapet, lapped over top of
blockwork and sealed
Vapour control layer inwall and roof
Membrane roof construction
Air tightness checklist
1. Check that any air tightness barrierused in the ceiling overlaps with thelayer in the wall
Thermal continuity checklist
1. Ensure that insulation layers in roof arefitted perpendicularly, to cover junctions
3. Ensure that roof insulation butts against the gable wall
4. Install cavity barrier at the top of the wall
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check ventilation paths are clear before
installing insulation above the ceiling2. A vapour barrier is required at ceiling
level, to prevent moisture from enteringinto the roof construction
3. The option shown here includes a vapourcontrol layer and insulation as part of amembrane roof construction. Similardetails could be used for a profiled metaldecking roof but consult withmanufacturer regarding ventilationrequirements.
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WRoof - 9.500(m²K)/W
Masonry: Cavity Wall Insulation - Partial fillLintel at Window HeadPsi value = 0.1302W/mK
Thermal continuity checklist
1. Check that there is no debris in the cavity2. Install cavity barrier around opening3. Install insulation in the window reveal
Air tightness checklist
1. Install window to overlap with outer leaf ofwall finish.
Alternative:If window lines through with the bottom ofthe opening in the external finish, somemeans of preventing a direct line of airinfiltration will be required
2. Install air tightness seal between theinside face of the window and thestructural finish of the window opening.
Insulation tobe tightly fixed
back to innerleaf of wall30 minute fire
resistingproprietaryinsulating cavitybarrier withintegral DPC -ensure cavitybarrier is notbreeched byinappropriaterigid sheathinginsulationmaterial
Detail 2.08
Insulate the window reveal
Sealant to back of frame
Sealant at window frame
Air tightness tape
Compressiblefill
Lintol -any type
Vapour controllayer
Cavity tray withminimumupstand of140mm andstop ends
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Alternative internal finish at window
reveal - use insulation backedplasterboard
General notes2. The window head and jamb details
shown have used a plywood box liningaround the window opening in the internalleaf of the wall, to allow for windowfixings. Alternative details are possiblebut the continuity of insulation and airtightness should be considered.
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WInsulated plasterboard - 1.591(m²K)/W
If position of window head islower than or level with theunderside of the lintol, a largercompressible filler will berequired to stop up a potentialair infiltration route
Detail shows window fixed to plywoodframe set into window opening
Note: the timber batten in window reveal is shown smallerthan actual size, to allow the membrane corner strip to be seen
Masonry: Cavity Wall Insulation - Partial fillWindows and Doors - Jambs and Cills
Psi value (jamb) =0.2224W/mK Psi value (cill) =-0.02W/mK
Thermal continuity checklist
1. Check that there is no debris in the cavity2. Install cavity barrier around opening3. Install insulation in the window reveal
Air tightness checklist
1. Install window to overlap with outer leaf ofwall finish.
Alternative:If window lines through with the externaljamb, some means of preventing a directline of air infiltration will be required
2. Install air tightness seal between theinside face of the window and thestructural finish of the window opening.
Detail 2.09
Insulate the window reveal
Air tightness tape andsealant to back of frame
Sealant at window frame
30 minute fire resistingproprietary insulating cavitybarrier with integral DPC
Vapour control layer in wall
Insulation between the studs inaddition to the cavity insulation.
This insulation must be tightlyfitted, leaving no gaps
DPC lappedbehind cill andbelow window
Solid cill acts as cavitycloser. If pressed cill isused, a 30 minute firerated thermally insulatedcavity closer will berequired
Insulate the window reveal
Air tightness tape andsealant to back of frame
Compressible fillerbetween window and cill
Air tightness barrier in wall
30 minute firerated thermallyinsulatedcavity barrier
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Alternative internal finish at window
reveal - use insulation backedplasterboard
General notes2. The window head and jamb details
shown have used a plywood box liningaround the window opening in the internalleaf of the wall, to allow for windowfixings. Alternative details are possiblebut the continuity of insulation and airtightness should be considered.
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WInsulated plasterboard - 1.591(m²K)/W
Cill detail
Jamb detail
Detail shows window fixedto plywood frame set intowindow opening
Note: the timber battens inthe window reveal and cill are
shown smaller than actualsize, to allow the membrane
corner strip to be seen
Masonry: Cavity Wall Insulation - Partial fillGround Bearing Floor: Insulation Above SlabPsi value = 0.0744W/mK
20mm strip of perimeterinsulation with thermal
conductivity (λ value) notexceeding 0.025 W/mK around
slab and any screed
Detail 2.10
Thermal continuity checklist
1. Use a perimeter strip of insulation wherethe concrete slab abuts the concreteblockwork wall
2. Ensure that insulation level in externalwall overlaps with the insulation at thefloor slab
Air tightness checklist
1. Check that any air tightness barrier usedin the wall overlaps with the layer in thefloor
The wall insulation installedbelow the wall dpc must befit for purpose with regardsto water absorption
External ground level
Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board
and floor using a flexible sealant
Vapour control layer
Damp proof membraneabove or below slab
Vapour control layer belowtimber floor finish
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check that concrete slab is level and
clear of debris before fitting the insulationat floor level
2. If a screed finish is used instead of atimber floor, use a strip of perimeterinsulation with a minimum R value of0.75 m²/KW for the depth of the screed
Alternative detail3. Using lightweight blockwork (e.g. with λ
value of 0.19W/mK) to improve thethermal performance at the junction wherethe external wall and ground floorconstructions meet will change the psivalue
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WInsulated perimeter strip - 0.455 (m²K)/WFloor - 3.864 (m²K)/W
Masonry: Cavity Wall Insulation - Partial fillGround Bearing Floor: Insulation Below SlabPsi value = 0.175W/mK Detail 2.11
Thermal continuity checklist
1. Use a perimeter strip of insulation wherethe concrete slab abuts the concreteblockwork wall
2. Ensure that insulation level in externalwall overlaps with the insulation at thefloor slab
20mm strip of perimeterinsulation with thermal
conductivity (λ value) notexceeding 0.025 W/mK around
slab and any screed
The wall insulation installedbelow the wall dpc must befit for purpose with regardsto water absorption
External ground level
Seal between the wall andfloor membrane with a flexible
sealant or seal the gap betweenskirting board and floor using a
flexible sealant
Vapour control layer
Damp proof membrane
Air tightness checklist
1. Check that any air tightness barrier usedin the wall overlaps with the layer in thefloor
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. If a screed finish is used instead of a
timber floor, use a strip of perimeter insulation with a minimum R value of 0.75 m²/KW for the depth of the screed
Alternative detail2. Using lightweight blockwork (e.g. with λ
value of 0.19W/mK) to improve thethermal performance at the junctionwhere the external wall and ground floorconstructions meet will change the psivalue
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WInsulated perimeter strip - 1.136 (m²K)/WFloor - 3.864 (m²K)/W
Masonry: Cavity Wall Insulation - Partial fillTimber Suspended Ground FloorPsi value = 0.0978W/mK Detail 2.12
Sub floor ventilation should beprovided, minimum 1500mm²
per run of external wall or500mm² per m² of floor area
External ground level
Use air tightness tape at junction of airbarrier in wall and floor. Seal between the
wall and floor membrane with a flexiblesealant or seal the gap between skirtingboard and floor using a flexible sealant
Vapour control layer
Air tightness barrierbelow timber floor finish
Solum
Damp proof membrane
Insulation directly under flooring -supported on netting draped over joists
and stapled at the required depths
Minimum 50mm strip ofinsulation with thermalconductivity (λ value) notexceeding 0.025 W/mKshould be installed betweenwall and the last joist
Floor joist ends supported on joisthangers or using scarcement wall
Thermal continuity checklist
1. Use a perimeter strip of insulationbetween the floor joists and blockworkwall
2. Ensure that insulation level in externalwall overlaps with the insulation at thefloor construction
Air tightness checklist
1. Check that any air tightness barrier usedin the wall overlaps with the layer in thefloor
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check that all ventilation paths are clear
before installing the floor insulationAlternative detail2. Using lightweight blockwork (e.g.
with λ value of 0.19W/mK) to improvethermal performance at the junctionwhere the external wall and ground floorconstructions meet will change the psivalue
3. If there are concerns about damaging theair tightness membrane in the floor finishduring construction, an additional servicesvoid can be created using timber battenson top of the floor joists
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WInsulated perimeter strip - 1.136 (m²K)/WFloor - 5.455 (m²K)/W
Masonry: Cavity Wall Insulation - Partial fillSeparating WallPsi value = 0.0508W/mK
Thermal continuity checklist
Design stage1. Install thermally insulated cavity barrier in
line with separating wall2. Check that there is no debris in the cavity
Detail 2.13
Air tightness checklist
1. Check that any air tightness barrier usedin the internal wall overlaps with the layerin the external wall
Cavity barrier giving 30 minutefire resistance - ensure cavitybarriers are not breeched by
inappropriate insulation material
For more informationon acoustic details see
guidance in Section 5 ofthe Technical Standards
Vapour control layer
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check that insulation is fitted tightly to
concrete block wall at corner junctions
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/W
Air tightness layer,13mm plaster shown
Minimum specification of8kg/m2 gypsum based
plasterboard required if13mm plaster not used, to
comply with acousticrequirements
Masonry: Cavity Wall Insulation - Partial fillConcrete Separating FloorPsi value = 0.0541W/mK
Thermal continuity checklist
1. Check that there is no debris in the cavity
Detail 2.14
Air tightness checklist
Design stage1. Check that any air tightness barrier used
in the external wall is secured onto thefloor slab
2. If plaster is use as an air tightness barrierseal over junction at floor with barrier tape
Vapour control layer
Insulation between the studs in additionto the cavity insulation. This insulationmust be tightly fitted, leaving no gaps
Vapour control layer
Vapour control layerbelow timber floor finish
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check that insulation is tightly fixed into
the studs adjacent to the floor junction,leaving no gaps
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/W
Vapour control layer lappedover corner junction and taped to
underside of floor construction
Separating floors requireto comply with Section 2:Fire and Section 5: Noise
Vapour barrier lapped overcorner junction and taped tosurface of floor construction
Alternative air barrier - parge coatof plaster finish on blockwork
Masonry: Cavity Wall Insulation - Partial fillTimber Intermediate FloorPsi value = 0.0109W/mK Detail 2.15
Vapour control layer in wall
Insulation between the studs in additionto the cavity insulation. This insulationmust be tightly fitted, leaving no gaps
Air tightness barrier to becontinuous behind joists
Thermal continuity checklist
1. Check that there is no debris in the cavity
Minimum 50mmstrip of rigidinsulation withthermal conductivity(λ value) notexceeding 0.025W/mK should beinstalled betweenjoists
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check that insulation is tightly fixed into
the studs adjacent to the floor junction,leaving no gaps
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/WInsulated infill strip - 1.136(m²K)/W
Air tightness checklist
1. Check that any air tightness barrier usedin the internal wall overlaps with the layerin the floor or ceiling
Alternative:If the air tightness barrier is installed ontothe face of the blockwork wall and runscontinuously through the floorconstruction, infill any gaps where floorfixing is made to external wall
Air tightness barrier cornerstrip lapped over top ofjoists and joist hangers
Vapour control layer lappedover corner junction and taped
to air tightness barrier
Joists shown supportedon joist hangers
Alternative air barrier - parge coatof plaster finish on blockwork
Masonry: Cavity Wall Insulation - Partial fillGround Floor / Separating Wall junction - Timber susp. floorPsi value = 0.2365W/mK Detail 2.16
Sub floor ventilation should beprovided, minimum 1500mm²
per run of external wall or500mm² per m² of floor area
Use air tightness tape at junction of air barrier in walland floor. Seal between the wall and floor membrane
with a flexible sealant or seal the gap between skirtingboard and floor using a flexible sealant
Air tightness barrier in wall (plaster option shown)
Damp proof membrane
Air tightness layer belowtimber floor finish
Solum
Insulation directly under flooring -supported on netting draped over joists
and stapled at the required depths
Air tightness checklist
1. Check that any air tightness barrier usedin the wall overlaps with the layer in thefloor
2. Consider gluing joints between floorboards
Thermal continuity checklist
1. Ensure that insulation is tightly fitted to theback of the masonry wall
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check that all ventilation paths are clear
before installing the floor insulationAlternative Detail2. Lightweight thermal blockwork can be
used in the separating wall to improve thethermal performance but this will alsoreduce the acoustic performance of thewall. If this alternative is used thenadditional elements will be required tomeet Section 5 of the TechnicalStandards.
Thermal Resistance of insulation used indetails:
Internal Wall - 1.136 (m²K)/WFloor - 5.455 (m²K)/W
Masonry: Cavity Wall Insulation - Partial fillConcrete Ground Floor/ Separating Wall: Insulation Below SlabPsi value = 0.2736W/mK Detail 2.17
Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board
and floor using a flexible sealant
Air tightness barrier in wall (plaster shown)
Damp proof membrane
Thermal continuity checklist
1. Ensure that insulation is tightly fittedagainst the separating wall
Air tightness checklist
1. Check that there are no gaps between thewall and floor constructions
2. Check that any air tightness barrier usedin the wall overlaps with the layer in thefloor
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Minimum 50mm strip of insulationwith thermal conductivity (λ value)
not exceeding 0.025 W/mK should beinstalled between wall and the slab
Design advice
Minimising condensation risk1. If a screed finish is used instead of a
timber floor, use a strip of perimeterinsulation with a minimum R value of0.75 m²/KW for the depth of the screed
Alternative Detail2. Lightweight thermal blockwork can be
used in the separating wall to improve thethermal performance but this will alsoreduce the acoustic performance of thewall. If this alternative is used thenadditional elements will be required tomeet Section 5 of the TechnicalStandards.
Thermal Resistance of insulation used indetails:
Insulated infill strip - 1.136 (m²K)/WFloor - 3.864 (m²K)/W
Tape corner strip of airtightness membraneover wall / floor junction Vapour control layer in floor
Masonry: Cavity Wall Insulation - Partial fillConcrete Ground Floor/ Separating Wall: Insulation Above SlabPsi value = 0.2822W/mK Detail 2.18
Air tightness checklist
1. Check that there are no gaps between thewall and floor constructions
2. Check that any air tightness barrier usedin the wall overlaps with the layer in thefloor
Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board
and floor using a flexible sealant
Air tightness barrier in wall (plaster option shown)
Damp proof membrane
Thermal continuity checklist
1. Ensure that insulation is tightly fittedagainst the separating wall
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Minimum 20mm strip of insulationwith thermal conductivity (λ value)
not exceeding 0.025 W/mK should beinstalled between wall and the slab
Design advice
Minimising condensation risk1. Check that concrete slab is level and
clear of debris before fitting the insulationat floor level
2. If a screed finish is used instead of atimber floor, use a strip of perimeterinsulation with a minimum R value of0.75 m²/KW for the depth of the screed
Alternative Detail3. Lightweight thermal blockwork can be
used in the separating wall to improve thethermal performance but this will alsoreduce the acoustic performance of thewall. If this alternative is used thenadditional elements will be required tomeet Section 5 of the TechnicalStandards.
Thermal Resistance of insulation used indetails:
Internal Wall - 1.136 (m²K)/WInsulated infill strip - 0.455 (m²K)/WFloor - 3.864 (m²K)/W
Tape corner strip of airtightness membraneover wall / floor junction
Vapour control layer in floor
Masonry: Cavity Wall Insulation - Partial fillConcrete Separating Floor / Separating Wall junctionPsi value = 0.0133W/mK Detail 2.19
Air tightness barrier inwall (plaster shown)
Air tightness barrier lappedover corner junction
5mm minimum resilient flankingstrip to be used at floor junction. See
Technical Standards GuidanceNotes for Section 5 for details
Air tightness barrier in wall(plaster option shown)
Separating floors requireadditional layers and components
to comply with Section 2: Fireand Section 5: Noise
Air tightness checklist
1. Check that any air tightness barrier usedin the internal wall overlaps with the layerin the floor or ceiling
Thermal continuity checklist
1. Ensure that there are no gaps betweenfloor slabs or between the top of the walland the underside of the floor slab.
2. Ensure that the insulation is tightly fitted tothe top of the floor slab.
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check that concrete slab is level and
clear of debris before fitting the insulationat floor level
If membrane used, seal onto top ofscreed. If render or plaster used as
airtightness layer, add a corner stripof membrane to cover junction
before applying finish
Cavity barrier isused in toprevent thermalbypass.Usedense insulationor proprietarycavity barrier insleeve
Masonry: Cavity Wall Insulation - Partial fillTimber Intermediate Floor / Separating Wall junctionPsi value = 0.1053W/mK Detail 2.20
Air tightness barrier in to becontinuous behind joists
Seal between the wall and floormembrane with a flexible sealant orseal the gap between skirting board
and floor using a flexible sealant
Air tightness barrier inwall (plaster shown)
Thermal continuity checklist
1. Check that there are no gaps between thefloors and the separating wall.
Air tightness checklist
1. Check that any air tightness barrier usedin the internal wall overlaps with the layerin the floor or ceiling
Alternative:If the air tightness barrier is installed ontothe face of the blockwork wall and runscontinuously through the floorconstruction, infill any gaps where floorfixing is made to the wall
Air tightness barrier inwall (plaster shown)
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk
See general guidance notes
Masonry: Cavity Wall Insulation - Partial fillPitched Roof: Cold Roof / Separating Wall junctionPsi value = 0.2008W/mK Detail 2.21
Thermal continuity checklist
1. Install a cavity barrier at the top of the wall2. Ensure that insulation layers in roof are
fitted perpendicularly, to cover junctions
Air tightness checklist
1. Check that there are no gaps betweenthe top of the masonry wall and theunderside of the roof
2. Check that the air tightness barrierused in the ceiling overlaps with thelayer in the wall
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Vapour control layer inwall and ceilingMinimum 50mm strip of
rigid insulation withthermal conductivity (λvalue) not exceeding0.025 W/mK should beinstalled between walland the last joist
Design advice
Minimising condensation risk1. Check ventilation paths are clear before
installing insulation above the ceiling
Thermal Resistance of insulation used indetails:
Roof - 9.500(m²K)/W
Note: See detail numbers 2.01 and 2.02 forother junctions using this roof construction
For more informationon acoustic details see
guidance in Section 5 ofthe Technical Standards
Cavity barrier is used in toprevent thermal bypass.Uselow or soft density insulationwrapped in plastic ormembrane
Masonry: Cavity Wall Insulation - Partial fillPitched Roof: Ventilated Batten Void/ Separating Wall junctionPsi value = 0.2247W/mK Detail 2.22
Cavity barrier giving 30minute fire resistance -ensure cavity barrier is notbreeched by inappropriaterigid sheathing insulationmaterial
Air tightness barrier inwall and ceiling (plaster
shown on wall)
Minimum 50mm ventilation path over insulation
Where two insulation types areused together see
supplementary guidance
Thermal continuity checklist
1. Install a cavity barrier at the top of the wall2. Ensure that insulation layers are fitted
perpendicularly, to cover junctions
Air tightness checklist
1. Check that there are no gaps betweenthe top of the masonry wall and theunderside of the roof
2. Check that the air tightness barrierused in the ceiling overlaps with thelayer in the wall
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check ventilation paths are clear before
installing insulation above the ceiling
Thermal Resistance of insulation used indetails:
Internal Wall - 2.045 (m²K)/WRoof - 9.500(m²K)/W
Note: See detail numbers 2.03, 2.04 and 2.05for other junctions using this roof construction
Separating walls requireadditional layers and componentsto comply with Section 2: Fireand Section 5: Noise
Note: this construction istypically used where thereare habitable rooms within
the roof construction
Cavity barrier is used in toprevent thermal bypass.Use lowor soft density insulationwrapped in plastic or membrane
Masonry: Cavity Wall Insulation - Partial fillWall JunctionPsi value = 0.0607W/mK Detail 2.23
Plan view
Vapour control layer
Insulation between thestuds in addition to thecavity insulation. Thisinsulation must betightly fitted, leaving nogaps
Thermal continuity checklist
1. Check that there is no debris in the cavity.2. Check that there are no gaps in insulation
fitted at the corner junction in the cavity
Air tightness checklist
1. Check that any air tightness barrier usedin the external walls overlaps at thecorner
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check that insulation is tightly fixed into
the studs at the corner junction, leavingno gaps
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/W
Masonry: Cavity Wall Insulation - Partial fillWall Junction - Inward Corner Psi value = -0.0826W/mK Detail 2.24
Plan view
Vapour control layer
Insulation betweenthe studs in addition to
the cavity insulation.This insulation must be
tightly fitted, leavingno gaps
Thermal continuity checklist
1. Check that there is no debris in the cavity
Air tightness checklist
1. Check that any air tightness barrier usedin the external walls overlaps at thecorner
HEAT 2.7 software image of isothermsthrough junction detail.
For illustrative purposes only.
This example should be read in conjunction with the guidance in the introduction to this document. It illustrates the reductionof unwanted infiltration in buildings and provides a Psi value for this junction situation which can be used in calculationprovided the principles outlined and any identified component specification are followed.
Design advice
Minimising condensation risk1. Check that insulation is tightly fixed into
the studs at the corner junction, leavingno gaps
Thermal Resistance of insulation used indetails:
Wall (cavity) - 2.500 (m²K)/WWall (inner leaf) - 2.272 (m²K)/W