MAS ERRÁZURIZ LTDA. – AVENG GRINAKER LTA.
CONSORTIUM
SINKING VENTILATION SHAFTS CONSTRUCTION
CHUQUICAMATA SUBTERRÁNEA PROJECT
Sr. Iván Pérez P.
Business Manager
Mas Errázuriz Ltda.
Sr. Louis Germishuys
International Business Manager
Aveng Grinaker LTA
Expositors
Isometric View of the Project
Consortium Organization
MAS ERRAZURIZ LTDA. – AVENG GRINAKER LTA.
TECHNICAL ADMINISTRATIVE COMMITTE
MAS ERRAZURIZ LTDA. – AVENG GRINAKER LTA.
SITE MANAGER
TECHNICAL LEADERSHIP
AVENG GRINAKER LTA
ADMINISTRATIVE LEADERSHIP
MAS ERRÁZURIZ
DOCUMENTATION o Analysis and legal adjustment and Grinaker experience
o Communication, participation and consultation
Dissemination
Incident Indicator Report
Behavior Improvement Program
Risk Assessment
o Documentation and control (Quality Manual)
o Preparation and response in emergency cases
Preparation of procedures
Formation of Committees
VERIFICATION AND CONTROL o Measurement and monitoring of the SSOMA program performance.
Monthly review through the Administrative Technical Committees on site
Monthly reports to the senior management (Directory)
o Evaluation of legal compliance
o Accident Investigation
o Non compliances and corrective actions
Findings Management System
o Internal Audit Program
o Leadership Review: evaluate program SSOMA effectiveness
Risk Control, Environmental and Occupational Health Program
Human Resource Management Plan
The Human Resource Management Model is
based on a mixed organization of Chilean and
southafrican personnel. Aveng Grinaker’s
Technical Leadership involves training and
transferring knowledge to Mas Errázuriz staff, by
training carried out in current Aveng Grinaker
works in South Africa or Zambia and on-site
instruction for six months periods in previously
defined positions. The organization follows similar
criteria.
CHILEAN/SOUTHAFRICAN MIXED ORGANIZATION
• RECRUITING AND SELECTION
• TRAINING IN CHILE AND SOUTHAFRICA
• TRAINING AND DEVELOPMENT PLAN WITH COMPETENCE
CERTIFICATION
• PERFORMANCE MANAGEMENT
• QUALITY OF LIFE AND SOCIAL RESPONSIBILITY
• INTERNAL AND EXTERNAL COMMUNICATIONS
Direct Personnel
DIRECT PERSONNEL AND STRUCTURAL
MECHANICAL ASSEMBLIES
Capataz de Montajes
Maestro Primera de Montajes
Maestro Segunda de Montajes
Soldadores Plancha
Ayudantes de Montajes
Maestro Primera Mecánico
Maestro Primera Eléctrico
Ayudante Mecánico
Ayudante Eléctrico
DIRECT PERSONNEL AT THE FACE
Jefe de Turno Pique
Operadores de Perforadoras
Ayudantes Mineros
DIRECT PERSONNEL AT THE PLATFORM
Jefe de Turno Plataforma
Campanero de Plataforma
Ayudantes de Minería (Plataforma)
DIRECT PERSONNEL ON BENCH OR SURFACE
Minería: Ayudante Minería (Banco)
Operador de Grúa Torre
SUPPORT SERVICES
Jefe de Turno Minería
Mecánicos
Ayudantes
Eléctrico Servicios
Mecánico Servicios
Soldadores
PERSONAL TRAINING FOR 6 MONTHS
Jefe de Turno Minería General
Jefe de Turno Plataforma
Jefe de Turno Pique
Operador Compuerta de Superficie
Operador de Clam Shell
Operador de guinche
Mecánico de Jumbo
1. Avoid Falling Objects at all Cost
2. Follow procedures for Working at Heights
3. Safety Slings on All Tools
4. Follow Proper Barring Technique & Procedure
5. Support Installed to Standard
6. Follow Correct Explosive Handling & Blasting Procedures
7. Ensure Right Equipment for the Job
8. Follow procedures – No Short Cuts
9. Personal Protective Clothing
10. Behavioural Based Safety (BBS) – Your and your colleague’s safety
Critical Shaft Sinking Safety Rules
1. Mobilisation
2. Design & Planning
3. Site Establishment
4. Collar Construction
5. Pre-Sink
6. Change over to Main Sink
7. Main Sink
8. Remove Sinking Services & Clear Site
Shaft Sinking Phases
1. Mobilisation of Equipment
2. Forwarding & Clearing of Equipment
3. Recruitment of Workforce
4. Sinking Training
5. Approvals and Permits (legal requirements)
1. Mobilisation
Type of Drawing Number of Drawings Hours Required
General Arrangement 5 110
Infrastructure & Reticulations 30 1150
Collar & Pre-Sink 20 720
Main Sink 35 1100
Sinking Headgear 25 1100
Sinking Equipment 15 600
Winders 15 550
Management & Administration 400
2. Design & Planning
1. Winder Foundations
2. Batch Plant
3. Workshops
4. Stores
5. Offices
6. Services Reticulations
7. Manufacture in Chile
3. Site Establishment
1. Survey – setting out
2. Back Actor
3. Support
4. Shutter
5. Concrete
4. Collar Construction
1. Drilling
2. Support
3. Mucking
4. Hoisting
5. Pre-Sink Stage
5. Pre-Sink
1. Remove pre-sink stage
2. Lower main sink stage
3. Collar Steel
4. Headgear
5. Winders
6. Fans
6. Change Over to Main Sink
1. Drilling
2. Mucking
3. Support
4. Concrete Lining
5. Services
7. Main Sink
1. Remove all sinking infrastructure
2. Hand over of site to client
3. Permanent Fan Construction to commence
8. Remove Sinking Services & Clear Site
Alternativa
Duración m3
Excavados Consumo Explosivos
m3 Totales de Hormigón**
Consumo Eléctrico Estimado
Dotación Total Promedio
Mes m3 Kg m3 KWh Trabajadores/Mes
Pique 1
Alt 1 Concurrent 24.0 117,078 316,112 27,478 71,215,200 219
Alt 1 in line 30.0 idem idem idem 89,019,000 213
Pique 1 + Pique 2
Alt 2 Concurrent 41.0 234,022 631,859 55,041 121,659,300 230
Alt 2 in line 52.0 idem idem idem 154,299,600 225
Pique 1 + Collar 2
Alt 3 Concurrent 24.0 123,891 334,505 31,064 71,215,200 230
Alt 3 in line 30.0 idem idem idem 89,019,000 223
Resumen
Site Preparation and Civil Works
Site Preparation and Civil Works
Site Preparation and Civil Works
Pre-Sinking
Pre-Sinking
Main Excavation
Main Excavation
Blast Diagram
Phase : Jumbo Perforation
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : Blast
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : Ventilation
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : Dump
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : Fortification
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : removal of perforation equipment
Caso :
Ciclo trabajo en Línea:
Prohibido Trabajo Paralelo
Phase : Box Lining