October 30, 2014
B/C Connector
Old Concourse C
New Concourse C
Major Projects
Old Concourse C Security Checkpoint
Major Projects
New Concourse B/C Security Checkpoint
Major Projects
New B/C Connector
Major Projects
New B/C Connector
Major Projects
New B/C Connector
11
DE Connector Exterior
12
Final Upper Level
New 8 lane Security Checkpoint
Secure side Connector
Widened Circulation Corridor
New Holdrooms
Sterile Corridor for International Arrivals
Concession Core
13
Final Arrival Level
Mechanical Support Spaces
Future Outbound Baggage Expansion Future International
Baggage Claim Expansion
14
DE Checkpoint – Early Massing Diagram
15
DE Checkpoint - Final Design
5- Gate Concourse E Extension – Planning Concept
17
Overall Program 2011-2015
Runway Safety Areas – 2015 Deadline
18
Overall Program 2011-2015
19
Overall Program 2011-2015
• Meet all FAA Runway Safety Area Standards• Long Term Runway Pavement Rehabilitation (20+ Years)• Connecting Taxiways in Concrete at Runway Ends• Concrete Runway Ends• New Hold Aprons (Runway 15R/33L)• NAVAID Replacement• Resolution of FAA Modifications of Standards (MOS)• Taxiways meet Engineering Brief 75 Standards and -13A• Removal of Historic Identified “Hot Spots”• Complete Dual Parallel Taxiway System • Obstruction Removal for Runways 10-28 and 15R-33L
20
Overall Program 2011-2015
• 52 Design Tasks Completed/Underway
• 7 Property Negotiations Completed/Underway
• 10 Inter-Governmental/
Agency Agreements Executed
• 24 Construction Projects Substantially Complete
• 2 Construction Projects Underway
21
Runway 15R Deicing Pad Rehabilitation & Runway 15R-33L RSA, PMP & Standards Project
Upcoming Procurements
Construction Management & Inspection Services – Ad 12/14
Est. Value $40MSBP Roadway and Sidewalk at CRCF – Ad 12/14
Est. Value $500kComprehensive Interior/Exterior Improvements – Ad 1/15
Est. Value $40M Est. Task Range $200k-$5MSBR Comprehensive Interior/Exterior Improvements – Ad 2/15
Est. Value $5M Est. Range $25 – 250kComprehensive Pavement Marking – Ad 2/15
Est. Value $3MComprehensive Paving – Ad Fall 2015
Est. Value $20 million Est. Task Range $50k - $5M