MARS Update, Presented by Dale Nash
-
Upload
wallopsislandregionalalliance -
Category
Government & Nonprofit
-
view
269 -
download
1
Transcript of MARS Update, Presented by Dale Nash
MARS Update Jan 11, 2016
2
Sep 30 - Pad 0A Rebuild CompleteNov 6 - Performance Testing Complete
3
MARS Launch Pad-0AOn Track to Support the Hot-Fire, and Cargo Resupply missions with the Upgraded Antares
Unmanned Aircraft Systems Runway
4
Funding $5.8M for the UAS Runway
appropriated to Virginia Space in the FY15 Budget
Funding released with the execution of the NASA Space Act Agreement
Runway Construction 3000’ x 75’ (with 35’ cleared on
the sides), includes staging pad and electrical power
VDOT is managing the project to obtain savings through their efficiencies/expertise in contract management, construction, engineering services, enviromental
UAS Runway Update
Space Act Agreement fully executed with NASA Construction
Agreed upon approach between Virginia Space and VDOT leadership VDOT will manage the runway construction from bid to completion VDOT has reviewed the entire runway package provided by NASA VDOT has reviewed the UAS agreement to prep construction plans
Tentative Schedule Mandatory site inspection by potential contractors Dec/2015 Award construction contract - winter 2016 Begin construction - spring 2016 Begin flight operations - fall 2016
Potential Customers NASA Wallops, NASA Langley, Navy Dahlgren, Navy Patuxent River, Other
DoD, DARPA, VA Cyber Security Comm, Several Commercial companies
5
UAS Runway Update
Tree Clearing is in Progress