MARIN ENERGY AUTHORITY REQUEST FOR … ENERGY AUTHORITY REQUEST FOR ... energy resources to the...

30
MARIN ENERGY AUTHORITY REQUEST FOR PROPOSALS FOR LOCAL RENEWABLE ENERGY PROJECTS RFP RELEASE DATE: DECEMBER 3, 2010 RESPONSE DEADLINE: FEBRUARY 4, 2011 BY 2:00 P.M.

Transcript of MARIN ENERGY AUTHORITY REQUEST FOR … ENERGY AUTHORITY REQUEST FOR ... energy resources to the...

  

MARIN ENERGY AUTHORITY  

REQUEST FOR PROPOSALS    

   

FOR  

LOCAL RENEWABLE ENERGY PROJECTS                    

RFP RELEASE DATE: DECEMBER 3, 2010 RESPONSE DEADLINE: FEBRUARY 4, 2011 BY 2:00 P.M.   

2 of 30 

TABLE OF CONTENTS  

Overview ................................................................................................................................................ 3 Background ............................................................................................................................................ 5 RFP Schedule ......................................................................................................................................... 7 Requested Products and Services ....................................................................................................... 7 Project Location ..................................................................................................................................... 8 Other Considerations ........................................................................................................................... 9 Offer Requirements .............................................................................................................................. 9 Instructions for Submittal .................................................................................................................. 12 Evaluation ............................................................................................................................................ 14 Other Notices ....................................................................................................................................... 17    

3 of 30 

Overview  The  Marin  Energy  Authority  (“MEA”)  is  seeking  proposals  from  local  renewable  energy projects  and/or  project  developers  for  the  purpose  of  evaluating  clean,  sustainable  energy alternatives, which may  be  used  to meet  the  energy  requirements  of Marin Clean  Energy (“MCE”) program customers and MEA’s Renewable Portfolio Standard (RPS) goals.    MEA, a joint powers authority and a public entity organized under the laws of the State of California, was created pursuant to the Government Code of California and a Joint Powers Agreement  (December  2008)  to  study,  promote,  develop,  conduct,  operate,  and  manage energy  and  energy‑related  climate  change programs on behalf  of  its membership.   MEA’s current  membership  is  comprised  of  eight  municipalities,  which  are  located  within  the geographic  boundaries  of  Marin  County,  including  the  cities  of  Belvedere,  Fairfax,  Mill Valley,  San  Anselmo,  San  Rafael,  Sausalito  and  Tiburon  and  the  County  of  Marin (collectively,  the  “Members”  or  “Member  Agencies”).    Additional  information  about  the Marin Energy Authority can be found at www.marinenergyauthority.org.  Consistent with its stated objectives, MEA has implemented a community choice aggregation (“CCA”)  program,  MCE,  in  consideration  of  California  Assembly  Bill  117  and  related regulations.    The MCE  program,  which  began  serving  customers  on May  7,  2010,  targets significant  greenhouse  gas  emissions  (“GHG”)  reductions  through  increased  use  of renewable  energy  resources.   MCE  is  a voluntary program, which provides  customers  the opportunity  to  procure  electricity  from  competitive  energy  suppliers with  such  electricity being  delivered  over  Pacific  Gas  &  Electric  Company’s  (“PG&E”)  transmission  and distribution system.  At present, MCE serves approximately 9,000 customers, the majority of whom  receive  residential  electric  service.    The  annual  energy  requirements  of  MCE customers  total  nearly  160  gigawatt  hours  (“GWh”) with  peak  demand  approximating  33 megawatts  (“MW”).   Additional  details  related  to  the MCE  program  are  described  in  the MCE  Implementation  Plan,  which  was  certified  by  the  California  Public  Utilities Commission (“CPUC”) on February 2, 2010.    This  Request  for  Proposals  (“RFP”)  is  open  to  Eligible Renewable  Energy  Resources,  as described in the California Energy Commission’s Renewables Portfolio Standard Guidebook: http://www.energy.ca.gov/2007publications/CEC‑300‑2007‑006/CEC‑300‑2007‑006‑ED3‑CMF.PDF.    This  RFP  does  not  establish  a  purchase  commitment  from  MEA  for  electric capacity,  energy,  or  any  other  product  that  is  offered  as  a  result  of  this  process.   MEA reserves  the  right  to  execute  agreements with one or more of  the qualified  respondents  to this  RFP  as  determined  by  MEA  in  its  sole  discretion.    At  this  time,  MEA  is  soliciting proposals from qualified respondents for:  

4 of 30 

1. Up  to  forty  (40) megawatts  (MW)  of  Eligible  Renewable  Resources, which may  be supplied  from  one  or  more  unique  generation  projects  located  at  one  or  more locations.    MEA  seeks  resources  meeting  the  minimum  characteristics  described below:  Each proposal in response to this RFP should include one (1) project of at least five 

(5) megawatts  of  installed  generating  capacity,  if  located  outside  the  County  of Marin; 

Offers  for  renewable  energy projects  located within  the County of Marin  should include one (1) project of a size larger than one (1) megawatt installed generating capacity;   

MEA seeks the right to schedule electric capacity and energy from the agreed upon delivery  point  associated  with  the  selected  proposal(s)  with  the  Initial  Date  of Delivery as soon as January 1, 2012 but not later than December 31, 2014; 

The  proposed  resource  must  be  CEC‑certified  as  an  Eligible  Renewable  Energy Resource  (or must  receive  CEC  certification  prior  to  the  commencement  of  any energy deliveries proposed in response to this RFP);  

Appropriately sized photovoltaic solar resources  located either within or outside of  Marin County are not precluded from proposing under this section of the RFP, despite the specific request for similar resources in the following section; and 

All Environmental Attributes/Renewable Energy Certificates must be tendered to MEA  without  any  additional  costs  or  conditions  as  part  of  the  contract  for renewable power. 

 2. Up  to one  (1) megawatt  (MW) of  local, photovoltaic  solar  resources, which may be 

supplied  from  one  or  more  unique  generation  projects  located  at  one  or  more locations.    MEA  seeks  resources  meeting  the  minimum  characteristics  described below:  Each proposed project must be located entirely within the geographic boundaries 

of the County of Marin;  Offers from unique renewable energy projects located within the County of Marin 

should be at least 250 kW in size;    MEA seeks the right to schedule electric capacity and energy from the agreed upon 

delivery  point  associated  with  the  selected  proposal(s)  with  the  Initial  Date  of Delivery as soon as January 1, 2012 but not later than June 30, 2013; 

The  proposed  resource  must  be  CEC‑certified  as  an  Eligible  Renewable  Energy Resource  (or must  receive  CEC  certification  prior  to  the  commencement  of  any energy deliveries proposed in response to this RFP); and 

  All Environmental Attributes/Renewable Energy Certificates must be  tendered to 

MEA  without  any  additional  costs  or  conditions  as  part  of  the  contract  for renewable power. 

5 of 30 

  MEA will consider the following types of offers: 

Power Purchase Agreement (PPA) MEA  will  evaluate  PPAs  for  capacity  and/or  energy  with  minimum  contract durations  of  10  years  from Eligible Renewable Energy Resources.   Other,  longer contract durations will also be considered.  The resources can be located (options presented  in  order  of  evaluative preference):  (i) within  the County  of Marin,  (ii) within  northern  California  (NP  15),  including  all  counties  within  this  region  as well as portions of Monterey, San Benito, Fresno, Tulare and Inyo counties, or (iii) outside of NP 15 but within the state of California with the capability to deliver the proposed energy to the prescribed Delivery Point.  The Seller will own and operate the  facilities  and  be  responsible  for  development,  land  acquisition,  fuel  supply source and transportation, permitting, financing and construction for the facilities. 

PPA with Option to Buy Sellers can also provide an option price for MEA to acquire the facility that is being offered  through  a  power  purchase  agreement  as  described  above.    Such  pricing will  include  MEA’s  acquisition  for  all  Environmental  Attributes/Renewable Energy Certificates, land rights, permits and other licenses, enabling MEA to own and operate the facility at the end of the PPA term. MEA will consider the option to  buy  only  on  those  facilities  that  are  located  within  the  County  of  Marin.  Respondents should clearly describe the terms under which the purchase option is being proposed.    In  the event  that MEA determines, at  its  sole discretion, not  to exercise  it purchase option,  the PPA shall continue until  the end of  its scheduled conclusion. Any land lease, subject to MEA’s approval, must be in adequate form and for an adequate term (at least the life of the asset).  The offer should include (1) the energy price throughout the proposed delivery term (PPA); (2) a firm price for the  buyout  option;  (3)  if  applicable,  the  energy  price  for  the  remaining  PPA delivery  term  if  MEA  does  not  exercise  the  buyout  option.    Proposals  with  a buyout option should include complete design and construction specifications. 

Background  

In  September,  2002,  SB  1078 was  signed  into  California  law  (followed  by  SB  107  in  2006, which  accelerated  the  requirements  of  SB  1078),  establishing  California’s  Renewables Portfolio  Standard.    Pursuant  to  SB  107,  the  RPS  required  Investor  Owned  Utilities  and CCAs to increase their retail sales from Eligible Renewable Resources by a minimum of 1 percent  annually  and  to  procure  a  minimum  of  20  percent  of  retail  electricity  sales  from Eligible  Renewable  Energy  Resources  by  2010.   MEA  is  currently  exceeding  California’s minimum  RPS  requirements,  supplying  its  customers  with  more  than  25%  CEC‑eligible 

6 of 30 

renewable  energy  deliveries,  as  indicated  in  its  August  2010  RPS  Compliance  Report, submitted  to the CPUC on August 2, 2010.  MEA’s  long‑term goal  is  to supply  the entirety of  its  customers’  energy requirements with clean, renewable energy, subject to economic and operational constraints.  MEA also desires to promote the use of local energy resources to the greatest practical extent, improve energy efficiency in the region and promote local economic development.  In an effort to diversify its electric  resource  portfolio  and  meet  its  long‑term  RPS  goals,  MEA  invites  the  Sellers  of Eligible  Renewable  Energy  Resources  to  submit  supply  offers  for  the  aforementioned resource types, which include:  

1. Up  to  forty  (40) megawatts  (MW)  of  Eligible  Renewable  Resources, which may  be supplied  from  one  or  more  unique  generation  projects  located  at  one  or  more locations.    MEA  seeks  resources  meeting  the  minimum  characteristics  described below:  Each proposal in response to this RFP should include one (1) project of at least five 

(5) megawatts  of  installed  generating  capacity,  if  located  outside  the  County  of Marin; 

Offers  for  renewable  energy projects  located within  the County of Marin  should include one (1) project of a size larger than one (1) megawatt installed generating capacity;   

MEA seeks the right to schedule electric capacity and energy from the agreed upon delivery  point  associated  with  the  selected  proposal(s)  with  the  Initial  Date  of Delivery as soon as January 1, 2012 but not later than December 31, 2014; 

The  proposed  resource  must  be  CEC‑certified  as  an  Eligible  Renewable  Energy Resource  (or must  receive  CEC  certification  prior  to  the  commencement  of  any energy deliveries proposed in response to this RFP);  

Appropriately sized photovoltaic solar resources  located either within or outside of  Marin County are not precluded from proposing under this section of the RFP, despite the specific request for similar resources in the following section; and 

All Environmental Attributes/Renewable Energy Certificates must be tendered to MEA  without  any  additional  costs  or  conditions  as  part  of  the  contract  for renewable power. 

 2. Up  to one  (1) megawatt  (MW) of  local, photovoltaic  solar  resources, which may be 

supplied  from  one  or  more  unique  generation  projects  located  at  one  or  more locations.    MEA  seeks  resources  meeting  the  minimum  characteristics  described below:  Each proposed project must be located entirely within the geographic boundaries 

of the County of Marin; 

7 of 30 

Offers from unique renewable energy projects located within the County of Marin should be at least 250 kW in size;   

MEA seeks the right to schedule electric capacity and energy from the agreed upon delivery  point  associated  with  the  selected  proposal(s)  with  the  Initial  Date  of Delivery as soon as January 1, 2012 but not later than June 30, 2013; 

The  proposed  resource  must  be  CEC‑certified  as  an  Eligible  Renewable  Energy Resource  (or must  receive  CEC  certification  prior  to  the  commencement  of  any energy deliveries proposed in response to this RFP); and 

All Environmental Attributes/Renewable Energy Certificates must be tendered to MEA  without  any  additional  costs  or  conditions  as  part  of  the  contract  for renewable power. 

RFP Schedule  The proposed project schedule for this RFP is as follows:  Release RFP            December 3, 2010 Pre‑Bid Meeting          January 10, 2011 at 11:00 A.M. Deadline for Question Submittal      January 14, 2011 Responses Due          February 4, 2011 Short‑List Notifications        March 1, 2011 Short‑List Interviews        March 7‑11, 2011 Contract Negotiation        March 14 – May 31, 2011 Contract Approval and Execution     May‑June, 2011  Please note that the above schedule is subject to change.    

Requested Products and Services  Each offer submitted in response to this RFP must be for only one of the proposed Eligible Renewable Resource technology areas.  Sellers can, however, submit more than one offer in any  of  the Eligible Renewable Resource  technology  areas.    Projects  can  include more  than one generator of  like kind.   The  renewable  resources  requested  in  this  solicitation are described below.  Products from the offered technology can be structured in the following manner:  

8 of 30 

(1)   Unit Contingent Firm Basis (UC) The Seller will deliver  capacity  and energy  contracted  to MEA whenever  the plant  is operating and must meet certain negotiated availability requirements bundled with an equal amount of Environmental Attributes/Renewable Energy Certificates (REC’s). 

 (2) Firm/Shaped Capacity/Energy (FSE) 

The Seller will deliver capacity and energy at the times and amounts specified in  the  PPA  from  renewable  resources  only  regardless  of  the  availability  of  a particular  unit  bundled  with  an  equal  amount  of  Environmental Attributes/Renewable Energy Certificates.  

 (3) As‑Available Energy (AAE) or Intermittent Energy  

The  Seller  will  deliver  energy,  bundled  with  Environmental Attributes/Renewable Energy Certificates, whenever it can be produced by the facility.   

Project Location For  purposes  of  this  solicitation,  MEA  is  seeking  Eligible  Renewable  Energy  Resources located within one of the following broadly defined geographic areas: 1) “Local Renewable Resources,” which will  include  any  resources  located within Marin  County;  2)  “Northern California Resources,” which will  include any resources  located within northern California (NP 15), including all counties within this region as well as portions of Monterey, San Benito, Fresno, Tulare and Inyo counties; and 3) “Other In‑State Resources,” which shall include all other resources located outside of NP 15 but within the state of California with the capability to deliver the proposed energy to the prescribed Delivery Point.  While MEA has developed the aforementioned broad‑based geographic guideline  for Local Renewable Resources, any renewable  generating  resource(s)  located  within  the  jurisdictional  boundaries  of  MEA’s Member Agencies will be given additional preference during proposal evaluation.  However, MEA  will  not  preclude  renewable  resources  located  outside  of  the  Local  Renewable Resources area or the Northern California Resources area from bidding into this solicitation, so long as the respondent is capable of delivering to the prescribed Delivery Point. 

 Seller(s)  shall  be  financially  and  operationally  responsible  to  transmit  the  product  to  the specified Delivery Point, which shall be the PG&E Load Aggregation Point (LAP), as defined by the CAISO.   

Seller(s) will  also  serve as  their own scheduling  coordinator or make arrangements for a third party scheduling coordinator at the Seller’s cost.  

9 of 30 

Seller  or  its  third  party  scheduling  coordinator  will  be  responsible  for  all  CAISO imbalance costs, fee, and penalties associated with the delivery of the output from the project to the delivery point. 

Other Considerations  As previously  noted, MEA will  consider  offers  that  include  facility  acquisition  options  for contracted  generation  assets  within  the  County  of  Marin.    Seller(s)  should  indicate  the specific  terms  and  conditions,  including  pricing  and  other  pertinent  details,  which  will facilitate MEA’s evaluative process for such options.  In addition, the Seller(s) should specify whether or not the offer is for (i) the full project output, or (ii) partial output (with residual to other entity other than MEA).  

Offer Requirements 

A. Resultant PPA Due to the fact  that  the terms and conditions  in a PPA will  fluctuate widely depending on the type of resource being proposed, MEA has not included a sample PPA in this solicitation.  However,  each  Seller  should  provide  its  standard  terms  and  conditions  for  the  proposed project, which could serve as an initial basis to effectuate the establishment of a transaction governed by a PPA. 

B.  Equipment Availability Some agreements may  include a  requirement  to meet a minimum availability  level.   MEA will be entitled to damages (to be negotiated as part of the PPA, including but not limited to the right to terminate the PPA) in the event that the Seller fails to meet such requirements.   

C.  Re‑Power Projects Offers to re‑power an existing facility will be evaluated by MEA, and in  its sole discretion, MEA may choose to accept a proposed offer if it meets the following criteria: 

a. The proposed re‑power of a facility is anticipated to provide a remaining design life of thirty  (30)  years  after  the  Initial  Date  of  Delivery,  as  attested  by  a  Licensed Professional Engineer in the State of California. 

b. The re‑power provides increased capacity, increased efficiency, or an improvement in reliability to the offered project. 

c. The proposed project has obtained or has submitted an application for the necessary permits to operate which authorize the re‑power and also the operation of re‑powered units from the applicable Air Pollution Control District. 

10 of 30 

D.  Intermittent Energy Management   It  is  MEA’s  intent  to  schedule  energy  deliveries  from  contracted  resources  according  to industry practices applied in the WECC region.  Seller(s) shall be responsible for scheduling, forecasting and managing the exposure to and cost of any imbalance penalty that they may be  charged  for  their  operations.    Resources with  uncontrolled  fuel  sources  (such  as wind) shall negotiate project‑specific  terms and conditions with MEA on these  issues.   Seller also has  the  option  of  participation  in  a  CAISO  sponsored  program  such  as  the  Participating Intermittent Resources Program; however, such participation will be at the Seller’s expense. 

E.  Environmental  Attributes/Renewable  Energy  Certificates  and  WREGIS Registration In  addition  to  the  energy,  Environmental  Attributes/Renewable  Energy  Certificates  are required  to  be provided monthly  for  all  energy  produced  and purchased  by MEA  from a selected  and  contracted  product  offer,  evidencing  that  MEA  has  exclusive  rights  to  the Environmental  Attributes/Renewable  Energy  Certificates.    Environmental Attributes/Renewable  Energy  Certificates  shall  be  tracked  and  managed  by  MEA  for purposes of satisfying MEA’s renewable energy goals, objectives and reporting obligations associated with the California Renewables Portfolio Standard program, as may be amended or  supplemented by  the CPUC or CEC  from  time  to  time.   Any  Seller will  be  required  to register  with  the  Western  Renewable  Energy  Generation  Information  System  (WREGIS).  Prior to the Initial Date of Delivery, Seller shall register the Facility in WREGIS and take all other actions necessary  to ensure  that  the energy produced from the Facility  is  tracked  for purposes of satisfying the California Renewables Portfolio Standard requirements, as may be amended or supplemented by the CPUC or CEC from time to time. 

F.  Project  Certification  and  Environmental  Attribute/Renewable  Energy Certificate Tracking 

The  Seller  will  certify  the  proposed  project  as  a  renewable  energy  resource  through  the certification  process  administered  by  the  California  Energy  Resources  Conservation  and Development Commission (California Energy Commission or successor referred to as CEC) and  provide  information  requested  by  the  California  Energy  Commission  pursuant  to Sections 399.13 (a) and 399.13(b) of the California Public Utilities Code, respectively.  As part of this process, Seller should be prepared to complete and submit one of the following forms, CEC‑RPS‑1A  or  CEC‑RPS‑1B,  as  well  as  any  supplemental  registration/certification  forms required  by  the  CEC  to  certify  RPS  eligibility  of  proposed  projects.    These  forms  can  be reviewed and downloaded from the CEC’s website:  

 http://www.energy.ca.gov/renewables/documents/index.html.   

As  previously  noted,  participation  in  a  renewable  energy  certificate  tracking  system administered by the California Energy Commission (i.e. WREGIS or  its successor) will also 

11 of 30 

be required.  The Seller(s) will be responsible for abiding by all rules and regulations of the tracking system including paying all necessary costs, reporting all applicable sales to MEA and transferring all Environmental Attributes/Renewable Energy Certificates to MEA. 

G.  Avoided Greenhouse Gas Emissions (GHG) Environmental improvement, specifically GHG emissions reductions, is a charter objective of the  Marin  Energy  Authority.    State  legislation,  such  as  Assembly  Bill  32  (AB  32),  the California  Global  Warming  Solutions  Act  of  2006,  and  implementing  regulations,  also attempt  to  promote  environmental  improvement  through  the  reduction  of  GHG.    In consideration  of  this  legislation  and  MEA’s  interest  in  promoting  environmental improvement, the Seller will project for a typical contract year the avoided GHG emissions that  may  be  achieved  through  energy  deliveries  from  the  proposed  project.    It  is  MEA’s position  that  the  delivery  of  renewable  energy  likely  displaces  energy  generated  by marginally priced resources, which are  typically  fueled by natural gas.   With  this  in mind, MEA  requires  the  Seller  to  estimate  avoided GHG  emissions  in  the  following manner  for each year in which energy is proposed to be delivered: 

 Projected  Annual  Energy Production  (MWh  typical year) 

x  Marginal Emission Rate 

x  Estimated Annual Avoided Emissions (Tons) 

 Where: Marginal Emission Rate = 0.56 Tons/MWh  

The  Seller  will  also  transfer  all  rights  associated  with  estimated  avoided  GHG  emissions (using the aforementioned calculation) based on actual energy deliveries from the proposed project.  Following any contract execution, Seller transfers to MEA all rights to avoided GHG emissions created by delivered energy from the project.  Such avoided GHG emissions may be  referenced  by  MEA  in  demonstrating  compliance  with  any  implementing  regulations emanating from AB 32 or any other future legislation or regulations focused on the climate, environment or ecology.   

H.  CAISO Charges Seller shall be responsible for all CAISO charges and penalties associated with operation of the generating unit and transmission of energy to the Delivery Point.  I.  Collateral Requirements Seller(s)  may  be  required  to  post  collateral  as  an  assurance  of  performance  upon  the negotiation  of  a  contract  acceptable  to  the  Seller  and  MEA.    Specific  terms  related  to collateral posting will be negotiated with prospective Seller(s).  

12 of 30 

J.  Approvals Any agreement resulting from this process is expressly subject to: 

1. Negotiation of a mutually satisfactory PPA, or other contract, and 2. Obtaining related approval(s) of the MEA Board of Directors. 

K.  Submittal Requirements All Sellers that respond to this RFP shall provide a Renewable Project Application (attached hereto as Appendix A)  and shall  include a narrative  summary of  the offering,  technology, and state  the period under which the terms and conditions of the response to the RFP will remain valid, and must be signed by an authorized representative.  Sellers may also include any additional  information related  to  the proposed project  that may assist MEA during  its evaluative  process.    Sellers  of  multiple  projects  for  different  technologies  must  submit  a separate application for each of the proposed technology offers. 

 

Instructions for Submittal 

A.  RFP Solicitation and Offer Submittal Instructions for Sellers The schedule below is an anticipated schedule for the solicitation process to this RFP. 

 

Activity  Date Release of Request For Proposals  December 3, 2010 Pre‑Bid Meeting  January 10, 2011 at 11:00 A.M. Deadline for Question Submittal  January 14, 2011 Responses Due  February 4, 2011 Short‑list Notification  March 1, 2011 Short‑List Interviews  March 7‑11, 2011 Contract Negotiation  March 14‑May 31, 2011 Contract Approval and Execution  May‑June 2011 

B.  Timelines for Submission The Pre‑Bid Meeting, which is scheduled to occur on January 10, 2011, at 11:00 A.M. Pacific Prevailing  Time will  take  place  at  the  San Rafael Corporate Center,  Tamalpais Room,  750 Lindaro Street, San Rafael, CA 94901. 

 Participation  in  the  Pre‑Bid  Meeting  may  occur  via  teleconference  in  the  event  that registrants  are  unable  to  attend  in  person.    The  call‑in  number  will  be  posted  on MEA’s website (http://marinenergyauthority.org) within one week of the scheduled teleconference. 

 Submission of Renewable Project Applications and other materials must be received by MEA by 2:00 PM Pacific Prevailing Time on the Response Deadline (February 4, 2011). 

13 of 30 

C.  General Contact Information  General process and project questions related to this RFP shall be directed to the attention of Ms.  Jordis  Weaver.    All  questions  shall  be  submitted  in  writing  or  via  email.    Contact information:   

Marin Energy Authority Renewable Project Request for Proposals 781 Lincoln Avenue, Suite 320 San Rafael, CA 94901 Phone: 415.464.6021 Email: [email protected]   

 

D.  Clarifications and Amendments 

Clarifications shall be requested in writing to the individuals listed above.  Questions will be answered up until one week before the Response Deadline.  Clarifications and amendments to  the  RFP  Renewable  Project  Application  will  be  posted  on  MEA’s  website  located  at: http://marinenergyauthority.org.  Prospective Sellers will be responsible for accessing posted documents. 

E.  Submittals Proposals must be received by 2:00 PM Pacific Time on February 4, 2011.  Each respondent should provide five (5) double‑sided copies of its proposal at the time of submittal.  Receipt by MEA of an electronic copy by the due date will satisfy this requirement, provided that MEA receives five (5) double‑sided hardcopies by the close of business two business days following the proposal due date.  Copies of the proposal should be sent to the following addresses:  

Marin Energy Authority Renewable Project Request for Proposals 781 Lincoln Avenue, Suite 320 San Rafael, CA 94901 Phone: 415.464.6021 Email: [email protected]   

 Inquiries regarding this RFP may be directed to Ms. Jordis Weaver at  451.464.6021.  Specific  questions  about  the  RFP  should  be  sent  via  e‑mail  to [email protected]  no  later  than  January  14,  2011.    A  summary  of  all written questions  received and  responses will  be posted on MEA’s website  approximately one week following the Deadline for Question Submittal. 

14 of 30 

Evaluation 

A.  Evaluation Process and Criteria MEA may request, from any Seller at any time, additional  information on any offer for  the purpose  of  clarification.  MEA  shall  have  the  right,  at  its  sole  discretion,  to  request  this information without notifying other potential Sellers.   MEA will pre‑screen all responses prior to a detailed evaluation of the completed Renewable Project  Application  package.    The  minimum  qualifications  for  pre‑screening  purposes include the following:  

Is the proposed renewable resource listed as an Eligible Renewable Energy Resource according to CEC’s prescribed criteria? 

  Does the offer include Environmental Attributes/Renewable Energy Certificates? 

  Is  there  a  cover  letter  signed  by  an  officer  of  the  company  authorized  to  enter  the 

company  into  negotiations  for  a  PPA  included  with  the  Renewable  Project Application? 

  Are  there  five  originals  and  one  electronic  copy  of  the  submittal  included  in  the 

response package?  

If  the  project  is  a  proposed  re‑power  project,  does  it  include  an  attestation  from  a Licensed Professional Engineer from the State of California to indicate the remaining design life of the project? 

  Does the Renewable Project Application package include only one proposed project? 

  Is the proposal complete enough to allow MEA to conduct a detailed evaluation of the 

project  to  determine  its  benefits  so  actual  contract  negotiations  could  begin  in  a reasonable timeframe (i.e., has the applicant specifically identified the project location, fuel  source  availability,  point  of  planned  interconnection  and  delivery,  cost assumptions, etc.)? 

 A “No” response to any of the above questions will automatically establish grounds for the Response to be disqualified.  After prescreening, the Renewable Project Application will be evaluated against a common set  of  criteria  that  will  include  various  factors.    A  partial  list  of  factors  to  be  considered 

15 of 30 

during MEA’s evaluative process is included below.  This list may be revised at MEA’s sole discretion.  

  

Cost  Availability  Initial Date of Delivery 

Available Renewable Energy Certificates 

Project Location & Point of Delivery 

Resource Type and Diversity 

Environmental Impacts and Local Benefits 

Qualification of Project Team Financial Stability of Project 

Owner    MEA reserves the right  to consider other  factors  than  those specified above and to request additional information from respondents as needed to assist in selecting the proposal(s) for further  consideration.    Through  issuance  of  this  RFP, MEA makes  no  commitment  to  any bidder that it will be awarded a contract to provide the solicited services.  MEA reserves the right to discontinue this RFP process at any time for any reason. 

 Based on the outcome of the evaluation, MEA will establish a shortlist of selected offers and will enter into PPA negotiations.   

 

B.  Shortlist & Shortlist Deposit In  order  to  engage MEA  in  negotiations,  the  prospective  Seller(s)  on  the  shortlist  will  be required to pay a $2.00/kW deposit (“Shortlist Deposit”).  The purpose of the Shortlist Deposit is to secure the obligation of each respondent during the negotiation  and  approval  process,  and  to  ensure  that  each  offer  has  been  carefully considered and represents a binding offer to MEA.  MEA will notify the respondents if they have been selected as part of the shortlist to make the Shortlist Deposit.  Such deposit will be required within ten (10) business days after such notification.   If a Seller fails to submit the Shortlist Deposit, the offer will be rejected and removed from the Shortlist.    The form of the Shortlist Deposit can be in cash or as a Letter of Credit.  MEA will pay interest on each cash deposit, calculated on a monthly basis and compounded at the end of each calendar month from the date the Shortlist Deposit is fully deposited until the earlier of:    (i)  the return of the cash Shortlist Deposit  to the respondent, or (ii)  the date when the Shortlist Deposit is used as part of Project Development Security as negotiated in an agreement resulting from this RFP.   The applicable  interest rate will be determined at a later  date,  subject  to  MEA’s  approval,  and  agreed  upon  by  the  respondent  should  the respondent wish to participate further in the RFP process.    

16 of 30 

In  lieu  of  a  cash  deposit,  the  respondent  may  provide  a  Shortlist  Deposit  using  an irrevocable,  standby  letter  of  credit,  in  a  form  acceptable  to  MEA,  issued  by  a  U.S. commercial bank or foreign bank with a U.S. branch with such bank having total assets of at least USD$10 billion and a senior unsecured debt rating of no lower than A2 from Moody’s Investor  Services,  Inc.,  or  its  successor  (“Moody’s”)  or  A  from  Standard  &  Poor’s  Rating Group,  or  its  successor  (“S&P”).    Costs  of  the  letter  of  credit  shall  be  borne  by  the respondent.  

The Shortlist Deposit shall be returned by MEA under one of the following situations:  Upon  execution  and  approval  of  a  negotiated  agreement  and  the  Seller’s 

submission  of  the  collateral  required  under  the  agreement  where  funds will  be used as Project Development Security; 

MEA’s rejection of the offer subsequent to shortlist selection;  If in the course of negotiations, the respondent and MEA cannot agree to the terms 

of  the  offer  and  MEA  rejects  the  offer  and  any  agreement  submitted  by  a respondent; 

If  at  any  time  the  respondent  submits  a  letter  of  notification  indicating  the withdrawal of an offer within  ten  (10) days of being notified of  the respondent’s selection to be a part of the shortlist. 

 A respondent will forfeit the Shortlist Deposit if:  The respondent submits a notice to withdraw out of time as specified above;  If  there  is  any  material  misrepresentation  of  pricing  or  non‑price  information 

submitted by the respondent;  If the respondent files for bankruptcy, or is  involved in other similar proceeding; 

or   There is a merger or buyout without the assumption of the obligations proposed. 

 In the event that forfeiture of the Shortlist Deposit takes place, MEA will be entitled to draw  upon  the  shortlist  Deposit  in  its  entirety  as  payment  to  MEA  for  direct  and indirect damages incurred in connection with the respondent’s withdrawal of the offer or any misrepresentation.  

 Upon  selection  to  become  part  of  the  shortlist,  respondents  that  are  offering  the  same capacity and/or energy from one resource to multiple solicitations are advised that  if MEA notifies a respondent that their offer is being shortlisted, the respondent MUST immediately withdraw  their  offer  from  all  other  solicitations  or  risk  being  removed  from  the  MEA shortlist.    MEA  may  also  require  the  prospective  Seller(s)  to  enter  into  an  exclusivity agreement, which would preclude the Seller from engaging in discussions with other buyers during the negotiation process. 

17 of 30 

Other Notices 

A.  Proprietary & Confidential Information Submitted  offers  may  include  proprietary  and/or  confidential  information.   Sellers  are advised that Section 6253 of the California Public Records Act provides that any person may receive  a  copy  of  any  identifiable  public  record  that  is  not  exempt  from disclosure  under other provisions of the Act.  MEA will disclose such documents unless (1) the data submitted in response to this RFP is stamped ʺProprietary/Confidential Materials;ʺ and (2) the stamped data  qualifies  as  proprietary  and  confidential  information  under  the  Public  Records  Act.  MEA reserves the right to release such information to its advisers for purposes of evaluating the Seller’s offer.  In the event that such release to advisers is made, advisers will be bound to the same standard of care with respect to disclosure as MEA.  Neither MEA nor its advisers will  be  liable  for  any  damages  resulting  from  any  accidental  disclosure  before,  during  or after  this  RFP  solicitation  process,  even  if  the  documents  are  marked  as Proprietary/Confidential Materials. 

B.  Preparation Cost and Ownership of Offers MEA shall not be responsible for any of the Seller’s costs incurred to prepare, submit, negotiate, or to enter into a PPA, or for any other activity related thereto to meet the Requirements  for  offers  established  in  this  RFP.    All  submittals  shall  become  the property of MEA and will not be returned. 

C. Release of MEA for Delays The  Seller  acknowledges  that  it  bears  sole  responsibility  for  submitting  all applications and obtaining all necessary permits, leases or mortgages, interconnection, financing and other  agreements necessary  for  the Seller  to perform under proposed operation  as  submitted  in  the  Renewable  Project  Application  and  supporting documentation.  Seller further acknowledges that it will hold MEA harmless and not liable for: 

i. Any  time  and  costs  required  to  complete  studies  to  obtain  required permits for project operation, or enter into necessary agreements for the construction  of  a  new  project  or  re‑power  project  as  contemplated  by this  RFP  (including  without  limitation  any  interconnection arrangements  that  must  be  made  with  other  parties,  certification requirements, leases, mortgages, financing, or permits). 

ii. Any  time  and  costs  required  to  perform  any  transmission  facility upgrades necessary  to meet  the  Initial Date of Delivery as  set  forth by this RFP. 

iii. Any time and costs to construct the project. 

18 of 30 

iv. Costs  to construct any upgrades  to  transmission  facilities,  to  the extent that  the  actual  costs  differ  from  any  original  cost  estimates  used  to establish the offered price in the Renewable Project Application. 

v. Time required to obtain environmental permits to construct or operate, including acquisition of any emission reduction credits required by law or regulation. 

D. Revisions and Supplements Any revisions made  to  this RFP will be posted on MEA’s website as an addendum.  Potential  Sellers will  be  responsible  for  accessing posted documents  for  this RFP  at MEA’s  website  located  at  http://marinenergyauthority.org  and  for  reflecting  any amended or updated requirements, informational requests or other changes in Seller’s response(s).  

E.  CEC Renewable Certification  

Prior to delivery of any energy to MEA, Seller must complete all applicable renewable certifications required by the CEC to establish the proposed facility(ies) as an eligible renewable  resource  project.    The  CEC  provides  more  information  regarding  these certifications on its website:  http://www.energy.ca.gov/renewables/documents/index.html 

F.  Early Power Delivery In the event that a selected project offer is capable of delivering electric capacity and energy  prior  to  the  Initial  Date  of  Delivery,  both  MEA  and  Seller  may  negotiate pricing terms for the delivery of electric capacity and energy.   On the Initial Date of Delivery,  the  payment  to  Seller  shall  automatically  adjust  to  the  payment  structure negotiated in the PPA between MEA and Seller.  Notwithstanding the possibility for such arrangements, MEA shall  be under no obligation  to enter  into negotiations  for early delivery of electric capacity and energy.  

G.  Termination of RFP Process MEA  reserves  the  right  to  at  any  time,  in  its  sole discretion,  terminate  this  bidding process,  to  change dates  specified  in  this RFP,  to  change  the basis  for  evaluation of offers, to accept any offer and to enter into a PPA, and to evaluate the qualifications and proposals of any Seller upon notice of termination of this RFP process. 

H.  Definition of Terms Please refer to Appendix B. 

   

APPENDIX A                                

   

MARIN ENERGY AUTHORITY 

REQUEST FOR PROPOSALS 

RENEWABLE PROJECT APPLICATION 

 

Each Seller is required to complete this Renewable Project Application completely, using separate copies of  the Renewable Project Application  to describe each proposed project.  If a project involves multiple generators of like kind, using the same renewable resource (e.g.,  multiple  wind  generators  or  small  hydro  generators),  please  list  the  number  of generators.    Use  separate  sheets  as  necessary  to  provide  the  required  information, referencing  the  numbered  sections  on  this  application.    The  offering  description  and information presented in this application shall be no longer than 15 single‑spaced typed pages.    Additional  pages  may  be  used  as  appendices  to  show  resumes  of  key  people, company  literature,  published  reports  of  past  performance,  and  other  pertinent information.  To  facilitate  MEA’s  review  process,  each  response  must:  1)  contain  all  of  the  applicable information requested within this application; and 2) be organized in similar sequence to the order  in which  these  items  appear  below.    If  an  item  is  not  applicable,  please  indicate  by specifying “N/A” for “Not Applicable” and provide a brief explanation of why  the  item is not applicable.   In each response, the burden of proof is on the Seller to support the information provided in this Application.  MEA will not perform additional research and will not be responsible for potential  future  costs,  if  such  costs  are  incurred  by  the  Seller  in  order  to  meet  the requirements as stated in this RFP.  If there is a conflict between the terms used in this application and any other documents that constitute this RFP, the conflict shall be resolved by taking the following document priority:  i) RFP Process & Specifications, and ii) the Renewable Project Application.  In the event that a PPA is executed by MEA with any of the Sellers, the PPA shall take precedence over any other documentation in this RFP package.    

  

REQUEST FOR PROPOSALS MEA RENEWABLE PROJECT APPLICATION 

 Renewable Resource Type:                    Is this a re‑power project?  □ Yes              □ No  

Seller’s Name:                        

If the project has more than one owner, please list each owner and ownership share: Owner:              Ownership Share:       Owner:              Ownership Share:       Owner:              Ownership Share:       Owner:              Ownership Share:       Website(s), if available:                     Please include Resumes of key people.  

Seller’s Representative Contact Information Company (if applicable):                     Authorized Contact Name:                    Title:                           Street Address:                       City:                    State:         Zip      Office Telephone Number:                    Fax Number:                        E‑mail Address:                       Website, if available:                       

Offered Project/Facility Location Street Address:                       City:                    State:         Zip      Estimated plant service life?      Yrs.  1)  Does the project meet the CEC’s Renewable Resource eligibility criteria?            □ Yes              □ No   

If “Yes,” has the project already received CEC certification as an Eligible Renewable Energy Resource? 

  

2)  Please check the options that best describes your offer:   □ Unit Contingent Firm Capacity and Energy 

□ Firm/Shaped Capacity/Energy □ As‑Available Energy or Intermittent Energy 

 

Please indicate the number of generators (only of like kind and same technology) being included in this offer as a single facility: No. Generators:             

 

3)  Delivery Point: PG&E Load Aggregation Point (LAP), as defined by the CAISO.    Also, please specify if the project is in the CAISO’s interconnection queue): 

 4)  Please describe interconnection and transmission arrangements to deliver project 

output to the Delivery Point.  

5)   General Project Information a. Contract Capacity:          MW b. Annual Capacity Factor:        % c. Net Annual Energy Production:      GWh d. Manufacturers of Major Components of the project 

i. Component         Manufacturer       ii. Component         Manufacturer       iii. Component         Manufacturer       iv. Component         Manufacturer       

(Please attach another sheet if necessary).  

6)   Term (note: minimum term required is 10 yrs) a. Maximum Term Requested:      Yrs. 

 

7)  Price: For all Products: 

a. Melded Price for Capacity and Energy:      $/MWh b. If shaping is being provided for Intermittent Products please specify: 

i. Shaping Price included in Melded Price above:    $/MWh  

Escalation Factor (if applicable) for Melded Price above: a. List Index Used (if applicable):       b. Fixed Rate:          % 

 

8)  Does this price include all transmission charges associated with transporting the power to the point of delivery? □ Yes             □ No 

 

9)   Please provide an RPS Certified Supplier Number (if project is already certified as an Eligible Renewable Resource through the CEC): RPS Certified Supplier No.:          

 10)  If applicable, please provide the following air emissions information lbs/kWh: 

CO2  lbs/kWh  CO    lbs/kWh  NOx    lbs/kWh 

 

SO2      lbs/kWh  PM10      lbs/kWh   

 

Total Particulates    lbs/kWh  Hazardous Materials    lbs/kWh  11)  Please estimate annual avoided GHG emissions for a typical contract year using the 

following formula:  

Projected  Annual  Energy Production  (MWh  typical year) 

x  Marginal Emission Rate 

x  Estimated Annual Avoided Emissions (Tons) 

 

Where: Marginal Emission Rate = 0.56 Tons/MWh  

Estimated Annual Energy Production (MWh)     

Total avoided GHG emissions (tons)             

12)   If applicable, will emission reduction credits have to be obtained for your facility? □ Yes             □ No 

 

13) Please list the environmental benefits of the proposed offer to Marin County.  

14) Please provide a brief description of the Seller’s corporate structure.  If applicable, provide descriptions for each member of a consortium or partnership. 

 

15) How many years has the Seller’s organization been in business as a developer of power projects (under the present name)? 

  No. of Years:         

16) Please list the renewable energy projects that the Seller has developed or participated in within the last 5 years? No. of Projects:       1.            4.           2.            5.           3.            6.           (If more space is needed, please attach a separate sheet).       

 

17) Please list all other power supply projects or independent power supply ventures that the Seller has participated in or pursued within the last 5 years. No. of Projects:       1.            5.           2.            6.           3.            7.           4.            8.           (If more space is needed, please attach a separate sheet).   

 

18) Please provide a list of at least 3 former clients for which the Seller has provided similar power supply services (include names of client representatives, and phone numbers). 

  

Client Name  Representative Name  Telephone No.                 

19)  Is the Seller currently a debtor in a bankruptcy case?   □ Yes             □ No 

 

20)  Has the Seller’s organization been in bankruptcy at any time within the last five years (besides case listed above)? 

    □ Yes             □ No  

21)  Has the Seller, or any of the offered project’s owners, officers, or partners ever been found liable in a civil suit, or found guilty in a criminal action, for making any false claim or material representation to any public agency or entity?   □ Yes             □ No 

 

22)  Has the Seller, or any of the offered project’s owners, officers, or partners ever been convicted of a federal or state crime of fraud, theft or any other act of dishonesty? □ Yes             □ No  

23) Has the Seller been involved in contract disputes involving similar projects during the last five years? □ Yes             □ No If Yes, how many?       

 

24) Please provide a brief summary of the Seller’s financial stability and credit rating, and provide financial statements (or links to applicable filings that can be accessed via internet) for the last 2 years (if partnerships are contemplated, or guaranty, please provide statements for all involved). 

 

25) Please provide a brief explanation of the assumptions underlying any financing activities that will be required to complete the proposed project, if it is not yet built.  Include specific sources of financing, if known. 

 

26) Please provide a brief explanation of state and federal incentives (i.e. tax credits, state subsidies, and other awards or programs) that were considered in the economic assumptions and the impact of those assumptions on pricing structure, as presented in Question 7, or other proposed terms for the offer.  Also, provide proposed product pricing if such incentives cannot be retained. 

 

27)  Please provide a brief description of fuel source for the proposed offer, and a brief description of how proposed fuel supply will be maintained for the proposed term of a PPA (i.e. biomass supply, etc.).  If fuel supply comes from a specific location/contractor, please provide such information (i.e. geothermal steam well) as well as any agreements providing for necessary fuel supplies over the proposed contract term. 

  

28) Please indicate the Initial Date of Delivery for the proposed project:   Also, include a proposed project development timeline with your application, which identifies the Initial Date of Delivery as well as other pertinent development milestones.  If this is a new project that will be constructed, include times when appropriate permits from the appropriate environmental agencies and regulatory agencies, and other required certifications will be obtained in order to effectuate the operation of the facility under the terms established by this RFP. 

 

29) Please list any anticipated economic benefits to the member agencies of MEA.  

30)  Is your offer the subject of negotiations with any other party? □ Yes             □ No  If “Yes,” please list to the extent allowed by any confidentiality agreements, the party(ies) to which this offer has been extended, the current status of the offer,  and any other relevant disclosures. 

 

31)  Please provide any additional information not requested by MEA‑ in particular, information that may explain further the benefits of selecting your offer. 

  

32)  If your offer is for firm capacity, please fill in the following table:   

 

 

 

 

 

 

 

 Note: This table depicts the guaranteed firm energy, expressed in MWh, and the guaranteed capacity, expressed in MW, by month.  

   

   

Generation Month 

On‑Peak (MWh) 

Off‑Peak (MWh) 

Capacity (MW) 

January       February       March       April       May       June       July       August       September       October       November       December       

If your offer is for As‑Available Energy, please fill in the following table:       

              

Note: Please estimate the energy profile expected, expressed in MWh, for each month.      

33)  Is the Seller proposing a purchase option for the contracted generation assets (either a buyout option or turnkey acquisition agreement)? 

  □ Yes             □ No  If “Yes,” please elaborate on any pricing considerations associated with this option, including impacts to energy pricing schedules, contract term and any other relevant details that will assist MEA in evaluating the purchase option.    

34)  Please provide the standard terms and conditions of your proposed power purchase agreement. 

 35)  Please provide detail related to site control for the proposed project.  If site control has been achieved, please indicate the method that will be used to demonstrate the sufficiency of this arrangement (e.g. ownership, lease, option, development right or other contractual mechanism/agreement).  If site control has not yet been achieved, please describe your plans for satisfying this requirements as well as a proposed schedule. 

Generation Month 

On‑Peak (MWh) 

Off‑Peak (MWh) 

January     February     March     April     May     June     July     August     September     October     November     December     

        

   

 

 

APPENDIX B  

DEFINITION OF TERMS   As‑Available  Energy  –  Energy  delivered whenever  it  can  be  produced  by  the facility.  In  this  case,  no  minimum  plant  availability  factor  is  enforced.  Curtailments  are  only  due  to  the  cause  of  plant  unavailability,  not  because  of economic or other reasons.  CEC – The California Energy Commission, or its successor.  CAISO – The California Independent System Operator, or its successor.  Delivery Point  – For  the  purposes  of  this  RFP,  the Delivery  Point  shall  be  the PG&E Load Aggregation Point (LAP), as defined by the CAISO.  Environmental  Attributes/Renewable  Energy  Certificates  –  means  any  and  all credits,  benefits,  emissions  reductions,  environmental  air  quality  credits,  and emissions  reductions  credits,  offsets,  and  allowances,  howsoever  entitled, resulting  from  the  avoidance  of  the  emission  of  any  gas,  chemical,  or  other substance attributable to an offered product, or the generation, purchase, sale or use of energy from or by the offered project and which Seller has acquired from the owner of a proposed project upon such attributes coming into existence, and including,  without  limitation,  any  of  the  same  arising  out  of  legislation  or regulation concerned with oxides of nitrogen, sulfur, or carbon, with particulate matter,  soot,  or  mercury,  or  implementing  the  United  Nations  Framework Convention  on  Climate  Change  or  the  Kyoto  Protocol  to  the  UNFCCC  or crediting “early action” emissions reduction, or laws or regulations involving or administered by the CAMD, and all Environmental Attribute Reporting Rights.  One (1) MWh of electrical energy from the proposed project offer, as metered at the  propose  point  of  delivery,  corresponds  to  one  (1)  MWh  Environmental Attribute and one Renewable Energy Credit.  GWh – Gigawatthours, each GWh is equal to 1,000 megawatthours.  Initial Date of Delivery – The date of delivery whereby the Seller guarantees the commencement of delivery of the selected offered project electrical output, and the  seller  ensures  that  they  have  i)  obtained  the  necessary  operating  permits issued by the appropriate authorities for the operation of the facility, ii) certified 

the project as a renewable resource through the California Energy Commission, iii) secured appropriate interconnection arrangements for the offered project.  Melded Energy Price – A pricing structure developed by the Seller that combines the recovery of all project costs into an energy rate expressed in $/MWh and paid on all delivered MWh only.  MW – Megawatt or megawatts.  MWh‑ Mega‑watt‑hour or mega‑watt‑hours. A measure of energy expected to be generated in one hour by one MW of capacity.  Off‑Peak – Those hours which the WECC defines as off peak, consisting of hours ending 22  through 24 and 01through 06 on all weekdays and Saturday, and all hours Sundays and Holidays  On‑Peak – All hours defined by WECC as on peak, consisting of all hours that are not defined as off peak.  Participating  Intermittent  Resources  Program‑  A  CAISO  sponsored  program that  allows  intermittent  resources  (i.e.,  currently  only  available  to  wind)  to schedule  energy  in  the  forward  market  without  incurring  imbalance  charges when  the  delivered  energy  differs  from  the  scheduled  amount,  entails  the forecasting of wind available for generation that enables generators to accurately schedule generation in accordance with CAISO timelines.  Power Purchase Agreement  ‑ A contract executed between MEA and the Seller, wherein  the  Seller  delivers  to  MEA  energy,  capacity  and  associated Environmental Attributes/Renewable Energy Credits and MEA accepts and pays for the delivery of the energy, capacity and Environmental Attributes/Renewable Energy Credits.  Project – The proposed facility, or generating resource, which will produce  the renewable energy and REC’s being offered in response to this RFP.  Rate of Delivery – The rate at which energy is delivered in MWh/h.  Seller(s) – The respondent or group of entities responding to this RFP.  

Submittal  Letter  –  This  document  must  accompany  the  Renewable  Project Application and  shall  include a narrative  summary of  the offering,  technology, and state the period under which the terms and conditions of the response to the RFP will remain valid, and must be signed by an authorized representative.  WECC – The Western Electricity Coordinating Council, or its successor.  WREGIS  –  The  Western  Renewable  Energy  Generation  Information  System, currently  being  developed  by  the  California  Energy  Commission  and  various stakeholders.